EUROCONTROL Study of Barcelona Airport Operations and Related Airspace
EUROCONTROL Study of Barcelona Airport Operations and Related Airspace
ANEXO 689/301
DOCUMENT CHARACTERISTICS
TITLE
Copyright Notice: No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means,
electronic, mechanical, photocopying, recording or otherwise.
@2019 The European Organisation for the Safety of Air Navigation (EUROCONTROL) – All rights reserved
CONTENTS
EXECUTIVE REPORT ...................................................................................................... i
1. INTRODUCTION ..................................................................................................... 1
1.1 Context of the Study ........................................................................................... 1
1.2 Scope .................................................................................................................. 1
1.3 Methodology ....................................................................................................... 1
1.4 Report Structure ................................................................................................. 2
EXECUTIVE REPORT
INTRODUCTION
In summer 2018, there was a significant deterioration in the regularity and continuity of
air traffic operations at Barcelona-El Prat airport, which led to a significant delays and a
reduction in the quality of service.
From a European perspective, traffic in 2018 increased more than 3% compared to 2017,
following year-on-year growth of more than 2% over the previous 5 years. 2018
registered a historic traffic peak of 37000 flights (with 30,000 flights per day on average)
which represents 4,000 more flights per month than in 2012.
The performance deterioration was not exclusive to Barcelona -El Prat as the total
European Network delay increased 61.2% on 2017. The impact of this performance
deterioration was constant flight delays (double those of 2017) and cancellations.
The main issues leading to poor performance included adverse weather conditions, lack
of ATC capacity, ATC staffing, and ATC industrial action, mainly in France.
With the aim of preparing an independent and comprehensive diagnosis of the causes
that led to the poor performance at Barcelona-El Prat airport and identifying measures
to improve operations in the short term (summer 2019) and the medium-long term, the
General Directorate of Civil Aviation (DGCA) commissioned a study from
EUROCONTROL in the autumn of 2018.
Among other issues, this study looks at the operations at the airport and its surrounding
airspace, the procedures used by airlines, the capacity of air traffic control and airport
infrastructure, the weather and human resources (ATCO rostering scheme).
The main stakeholders at Barcelona-El Prat were consulted, including: ENAIRE, AENA,
the major airlines (Vueling and EasyJet), the airline association ALA as well as the
National Supervisory Agency, AESA.
EUROCONTROL’s study methodology began with an analysis of available
EUROCONTROL information, including the Central Office for Delay Analysis (CODA)
and the Performance Review Unit (PRU).
Following this analysis, interviews were prepared and conducted with the main
stakeholders. The working meetings took place in the months of November 2018 and
January 2019.
Section 1: Introduction provides an overview of the analysis, the scope and the
methodology used in its preparation are detailed.
Section 2: Barcelona-El Prat Operational Context details the environmental factors
that determine operations at the airport.
Section 3: What Happened in the Summer of 2018? provides a diagnosis of the
causes that had an impact on airport operations during the summer of 2018.
Section 4: Benchmarking provides a comparison of the airport’s operational key
performance indicators to other European airports in the summer of 2018, such as
London Gatwick, Munich etc. that operate with comparable runway configurations.
Section 5: Detailed Analysis examines in-depth the various causes that motivated
this situation and provides recommendations for each of the problems d etected.
Section 6: Recommendations are summarised by actor and prioritised, highlighting
those to be implemented in the short term, i.e. for the upcoming 2019 summer season,
and in the medium-long term.
Barcelona-El Prat airport does not operate in its optimal runway configuration for
environmental reasons
Barcelona-El Prat was originally designed to operate with a configuration of independent
parallel runways in mixed mode, which would permit a maximum of 90 movements per
hour, pursuant to the provisions of its Master Plan. The construction project has a formal
Positive Environmental Assessment.
After the inauguration of the third runway in 2004, the special geographic location of the
airport and proximity to urban centres led to environmental concerns raised by
neighbouring populations. This made it necessary to establish a new runway-operating
configuration, applicable as long as demand is satisfied by the capacity offered under
this new configuration.
The new configuration was significantly different from the one laid-out in the airport
Master Plan’s original design.
For noise reduction, this new configuration requires the use of the short runway for
departures and the long runway for arrivals only, which is the oppo site of normal practice.
Such a configuration complicates the management of aircraft movements on the airport’s
surface area (for example numerous crossing points, opposite direction flows, lack of
holding areas at runway ends) with a negative impact on airport capacity, currently
declared at 78 movements per hour in the daytime period.
Furthermore, due to their performance, wide body departing aircraft are unable to use
the departure runway, and have to use the longer runway (used for landings). This
interferes in the arrival runway’s operation and with an increasing trend in these types of
(long-haul) operations, they will continue to have an adverse effect on capacity.
As well as the daytime environmental restrictions, night-time restrictions are imposed
from 11 p.m. to 7 a.m., longer than most other European airports (almost 1.5 hours
more). This is another negative factor. Importantly, the night-time runway configuration
reduces airport capacity from 78 to 48 movements per hour.
Barcelona Area Centre manages a complex airspace, which is highly influenced
by traffic operations in nearby airports and by close proximity to France
The airspace surrounding the airport is highly complex, with traffic flows at nearby
airports (Reus, Lleida, Sabadell, Girona), and the Balearic Islands, included together with
the Barcelona-El Prat operations. This complexity has an impact on the workload of air
traffic controllers and negatively influences the capacity of the system.
Furthermore, the proximity of the French airspace boundary increases complexity.
Controllers have to sequence a large amount of traffic to and from France (approximately
70% of the airport’s traffic) in the airspace near Barcelona-El Prat airport, which requires
a smooth coordination and sharing of information with the control centres in Marseille
and Bordeaux.
The sectors in the Barcelona Control Centre (airspace is divided into volumes, called
sectors, to which air traffic controllers are assigned) are not optimised for current day
traffic evolution.
Sector openings are planned well before the day of operation so are often not adapted
to manage actual traffic flows at certain moments, resulting in a lack of flexibility to absorb
peak traffic demand.
In the en-route airspace managed by Barcelona Control Centre, there is a need to
improve coordination with adjacent French airspace. Currently, there is a single point of
exchange of traffic between France and Barcelona airspace, causing significant
bottlenecks.
A need to make progress in improving the use of flexible use of airspace, equitable and
collaborative sharing of airspace between civil and military users, was also identified.
In summer 2018, the problems experienced in the European network had a significant
influence on the performance at Barcelona-El Prat airport. As well as capacity difficulties
in Central Europe and ATC industrial action in France (Marseille), an overall increase of
network regulations (capacity limitations) due to adverse weather, ATC capacity and
staffing shortages, all had a negative influence on the airport’s operations.
At Barcelona-El Prat airport and in its surrounding airspace, the main local causes of
delay were significant adverse weather, delays resulting from the additional time needed
to implement the BRAIN project, the lack of ATC capacity (unavailability of ATCOs, staff
rostering scheme, etc.) and certain environmental restrictions.
All of these issues, together with tight schedules operated by the main Barcelona -El Prat
based airlines, and the low level of resilience to disruptions of their daily schedules,
resulted in delay that accumulated throughout the day (reactionary delay) and that, on
occasion, reached up to 80 minutes on the last flights of the day.
In this situation, the remaining aircraft operations of the day arrived very late, which in
turn affected the next day’s early morning operations, mainly due to difficulties in
completing night time maintenance and the allocation of appropriate airport facilities.
With the first wave of the day and environmental restrictions overlapping, any operational
issues from late night arrival, maintenance and airport facilities contributed to a disrupted
‘first wave’ with a negative impact on operations throughout the rest of the day.
Poor European Network performance due to lack of capacity and staff, industrial
action, and adverse weather
In 2018, the operation across the European air transport network, with traffic growth
above 3.5% and a traffic record in September 2018 that amounted to 37,100 flights, was
the worst in recent years. This particularly affected Barcelona-El Prat airport because of
its geographical location and connections with other northern Europe airports. Delays in
the network due to regulations1 increased by 64% compared to the same period in 2017.
With more than 50% of departures at Barcelona-El Prat airport bound for northern
Europe, the ATC industrial action that took place in the summer (mainly in Marseille) and
ATC capacity and staffing problems in Marseilles and Karlsruhe (Germany) had a
negative impact on the operations of the main airlines at the airport (Vueling and
EasyJet).
As can be seen in the figure I, below, the impact on delays caused by the European
network at Barcelona-El Prat airport was 57%.
1
An air traffic regulation is applied in order to avoid exceeding airport or air traffic control capacity in handling traffic .
Between June and September 2018, the impact of adverse weather alone, increased by
70% in Europe compared to the same period of the previous year.
Adverse weather at Barcelona-El Prat had a major impact on delays during the
summer of 2018. Bad weather at the airport was the single biggest delay generator last
summer, accounting for 47% of delays due to daily regulations 2 at Barcelona-El Prat.
This resulted in numerous weather regulations set by ENAIRE, which contribu ted to the
delays at the airport. Such regulations are conservative in nature, designed to protect
airspace from overloading and the lack of precise meteorological forecasting and
predictive tools contributed to the cautious approach.
Delayed implementation of the BRAIN project. The BRAIN project, whose main aim
was to increase throughput and reduce the workload of controllers in the guidance of
aircraft on their final approach, had a longer period of adaptation than expected
(extended to end July 2018). Its initial timeframe was optimistic. This led to a reduction
in capacity, causing 14% of airport delays (again due to regulation).
The lack of ATC capacity and related regulation. The complexity of the airspace,
traffic flows in nearby airports (Reus, Lleida, Sabadell, Girona) and the Balearic Islands
managed by Barcelona Centre, the interaction with the adjacent French control centres,
and conservative regulation measures, to protect ATC against traffic overloads due to
lack of ATC capacity, resulted in additional delay to Barcelona-El Prat operations.
Environmental Restrictions constrain the effective capacity of the airport. Several
environmental restrictions are in place at Barcelona-El Prat that impede efficient runway
operations and have an effect on the capacity of the system. The original design of the
runways would provide greater capacity than that currently declared.
Although the declared capacity is sufficient for night-time operations at the airport in
normal conditions and without the summer disruption, it caused additional delay for those
aircraft that accumulated delays throughout the day, which arrive when capacity is
reduced to night-time levels.
This situation posed additional complications to accommodate such aircraft that arrived
after 11:00 pm (some with up to 80 minutes in additional delays).
2
Adverse weather regulations consist of retaining aircraft at the airport of origin long enough to prevent them from having
to hold (wait) in the air before landing as a result of severe weather conditions when they approach the destination airport.
The schedules of the main Barcelona-El Prat based airlines need greater
“resilience”, which, due to the nature of their “low cost model” (turnaround times are
35-40 minutes, although the main Barcelona carrier’s turnaround times for the entire
2018 season were 58 minutes) have serious difficulty to recover from external disruption.
Even considering the backup aircraft positioned in Barcelona (the main carrier alone had
seven aircraft on stand-by, a significant investment) the significant disruption
experienced in summer 2018 contributed to delays that accumulated throughout the day,
making it difficult, if not impossible, for the companies to recover.
The poor execution of the first wave of the day had an impact on the performance
of the airport throughout the rest of the day. Despite having implemented mitigation
measures, the main carrier, with 39% of the total movements at the airport and a majority
share of the first wave operation, suffered challenges throughout the summer. This
included handling problems resulting from a number of issues including late arrival of its
delayed aircraft on the previous day resulting from reactionary delays, aircraft
maintenance and airport facilities issues.
The main Barcelona carrier had difficulty tracking its aircraft maintenance
processes and being aware of allocated gates. Changes in the airline’s maintenance
schedule, and apparent problems with internal communication, resulted in difficulties in
complying with AENA’s assignment of resources (gates), which led to inefficient
operation of the first departure flights the following day. The airline worked with AENA to
improve this situation to mitigate the issue of delayed departures which was linked to
reactionary delay driving aircraft changes and subsequent gate changes.
There was a lack systematic communication between the different actors (AENA,
ENAIRE, airlines, handling agents), which negatively affected planning and the ability to
anticipate and act on potential disruptions during the day.
Better communication with airlines through regular daily briefings as in other European
airports (such as London) to inform and update on disruption to operations, how
regulation may be applied, their duration and severity, would have greatly helped
companies and their ground handling agents to adapt their operations more efficiently.
RECOMMENDATIONS
The recommendations are assigned to the main parties involved in the operation of the
airport (AENA, ENAIRE and Airlines) and to the DGCA. The DGCA, through an
appropriate governance structure, will be the body in charge of establishing the plan to
implement and monitor compliance of the short-term measures.
There are two main areas of recommendations: structural measures aimed at reducing
delays in order to optimise the airport’s capacity, and improvements, aimed at enhancing
the different actors responses in the event of unforeseen events.
Develop processes and tools (SMART – Specific, Measurable, Attainable, Realistic and Timely) that improve the methodology
ENAIRE for the establishment of regulations due to adverse weather and implement short and medium-term weather prediction High Short
tools, making use of new technologies. Reduced and SMART Regulation is a goal of the Network Manager.
Develop processes (SMART) that improve the establishment and reduce the number of ATC capacity regulations. The
ENAIRE recommendation proposes an exhaustive analysis of ATC regulations established last summer, with the aim of avoiding the High Short
application of over-conservative regulations during the following season.
Implement enhanced BRAIN procedures, ensuring full coordination with and in-depth understanding of all actors. The
recommendation proposes measure to ensure greater efficiency, increased systemisation and improved adherence to BRAIN
ENAIRE High Short
procedures (includes waypoints, reduced flight levels bands, guidance on distance to touch down, standard phraseology
etc.) This recommendation is complementary to that on “runway occupancy time” management.
Reduce runway occupancy times (ROT) for aircraft landing at the airport. The measure requires a monitored and
performance driven process to be agreed with airlines to reduce runway occupancy. Normalised runway occupancy times
and preferential runway exit points should be published; currently they are variable and have a negative effect on arrival
capacity (implemented at airports such as Gatwick and Vienna).
ENAIRE High Short
Runway occupancy can be further reduced by defining separation minima for aircraft grouped by categories based on
runway occupancy, taking account of wake vortex minima. The separation applied would be larger of radar minima, wake
turbulence or runway occupancy time. This recommendation is complementary to that on BRAIN procedures and minimum
radar separation.
Reduce the minimum radar separation distance between arrivals in the approach sequence from the current value of 3 miles
to 2.5 miles, thus increasing the number of arriving aircraft per hour, which will diminish the disruption caused by wide-body
ENAIRE High Long
departing aircraft operating non-preferential departures from the arrival runway (implemented at airports such as Gatwick,
and Vienna). This recommendation is complementary to that on BRAIN procedures and runway occupancy.
Implement the planned modifications to the current airspace sectors (both en-route, and in the terminal airspace around
ENAIRE the airport) to improve the management of air traffic flows that cross the airspace, with greater flexibility than the current High Short/long
rigid historical structure.
Improve coordination processes with the adjacent Bordeaux En-route Control Centre by increasing the number of transfer
ENAIRE points between the control centres, which will improve air traffic flows between France and Spain, reducing airspace High Short
complexity and providing a positive impact on controller work load and airspace related delays.
Implement the planned departure clearance data link, which will improve clearance delivery access for pil ots and reduce
radio frequency congestion. In the event the data clearance cannot be deployed in 2019, implement a second departure
ENAIRE clearance delivery position and frequency to reduce frequency congestion and ensure timely access to departure clearances. High Short
Airlines must make maximum use of this facility once implemented.
Systematically identify and reallocate adequate numbers of air traffic control staff to peak traffic periods by identifying when
ENAIRE a fewer controllers can be allocated to l ess busy periods of the day, rescheduling the staff accordingly. This is an important High Short
quick win step to ensure the optimum number of resources are allocated to manage peak demand in summer 2019.
Modify the staff rostering scheme in the Control Centre by implementing a flexible demand based rostering scheme in order
ENAIRE High Long
to obtain a greater availability of resources during peak demand hours (implemented at control centres such as Maastricht).
Modify the standard instrument departure routes (SID) to enable reduced separation between successive take-offs by
ENAIRE implementing Performance Based Navigation SIDs, improving capacity whilst respecting noise abatement requirements Normal Short
(implemented at airports such as Edinburgh and Brussels).
Improve the update of estimated arrival times of flights that cross the France-Spain border inbound to Barcelona-El Prat, to
ENAIRE ensure that the established arrival sequence to the airport (established by the Arrival Management system) is stable, correct Normal Short
and does not have to be manually by the controller due to incorrect times thus reducing unnecessary controller workload.
ENAIRE Enhance coordination between ENAIRE and the Ministry of Defence, to review agreements on the flexible use of airspace. Normal Long
Work closely with local authorities and interest groups to adjust the environmental restrictions currently in place, with the
AENA / particular aim of modifying the current daytime noise configuration restrictions to the enable design capacity of 90
High Medium
DGCA movements per hour through full independent parallel operations, as well as revising night-time hours to align with the
European average.
Modify the airport infrastructure by extending the length of runway 25L at the departure threshold (currently used for
AENA departing flight) to allow wide-body departures, mixed-mode operations and improving noise abatement by enabling an Normal Long
earlier turn over the sea on the standard instrument departures.
Establish an effective communication process with the other actors involved in the airport operation, through the
AENA implementation of daily meetings to anticipate possible problems, coordinating the necessary mitigation measures High Short
(implemented at airports such as London Heathrow and Amsterdam).
Establish a robust communication process to collaboratively manage airport key performance indicators, with regular
AENA reviews of post operation analysis with all the agents involved, establishing a coordinated approach to optimised Normal Long
airport performance.
Improve the allocation of airport resources and management processes, in particular, appropriate gate allocations
considering the needs of on time and late flights and passenger boarding (firstly with the main carrier), especially for
AENA / Airlines High Short
flights which land late during night-time hours, in order to improve the operation of the first departure wave next
day.
Following a deep analyse of 2018 issues, prepare appropriate airline human and technical resource in times for
summer 2019, with the aim of improving response times and schedule resilience to un foreseen circumstances,
Airlines High Short
operational disruption and reduced performance, due, for example, to poor weather, ATC industrial action, and lack
of ATC staff within the European network.
Collaborate with AENA and ENAIRE to properly implement the technical parameters and operational procedures
Airlines necessary to ensure the correct functioning of the Airport-Collaborative Decision Making process. EUROCONTROL Normal Short
proposes to support this work, bring its expertise of A-CDM and experience from other European CDM airports.
Promote, not only at Corporate level, but also amongst operational staff, a cultural change that is outcome oriented,
ENAIRE High Long
sharing with all staff members the performance objectives, observed results and continuous improvement measures.
Communicate post-operation analysis results from Corporate to Control staff levels, with the objective of
ENAIRE encouraging operational staff involvement in the effective application of corrective measures to improve the Normal Short
performance of air traffic services.
1. INTRODUCTION
1.1 Context of the Study
In autumn 2018, the DGCA Spain requested EUROCONTROL to undertake a high level assessment
of Air Traffic Management (ATM), Air traffic Control (ATC), Airport and Airline performance at
Barcelona airport and the surrounding airspace.
This followed a challenging summer of delay and poor weather experienced in Barcelona,
exacerbated by staffing availability and industrial action in the European ATM Network.
The goals of the assessment set by the DGCA were to identify the key issues, understand the main
causes and effects, and define performance mitigations that can be implemented by summer 2019.
EUROCONTROL proposed a study that involved key airport stakeholders through questionnaires
and interviews, complemented by a network level performance analysis, to identify the key issues,
their cause and effect. A set of mitigation options were collected from stakeholders through the
questionnaires and during discussions. These were further elaborated by EUROCONTROL.
This report collates the findings of the high level assessment undertaken by EUROCONTROL and
sets out recommendations defined together with the key airport stakeholders to be considered for
implementation in early 2019.
The report is destined to be used by DGCA in consultation with stakeholders and government entities
to support a common stakeholder plan for operations in summer 2019. The stakeholder plan should
identify actions for each stakeholder, to be developed into individual action plans. The common plan
would be jointly monitored by stakeholders through a high level steering body chaired by DGCA.
1.2 Scope
As agreed with DGCA, the study scope includes operational performance, agreements, plans and
events, including weather, staffing and industrial action covering:
Barcelona airport airside (stands, aprons, taxiways and runways), staffing, operational
procedures and working methods, of the key stakeholders namely ENAIRE, AENA and
selected Airlines.
Related airspace in the Spanish FIR/UIR, neighbouring airspace and associated boundary
agreements, and
The European Network.
Common Air Traffic Flow Management performance indicators were used as the basis for
assessment and in general these are expressed in minutes of delay. From a cost perspective, the
consensus reference rate for one minute of delay is 100 Euro.
For this study, the “summer period” is considered to be June 2018 through to end September 2018.
A number of activities and related measures that occurred in the period leading up to summer 2018
have been included to provide context.
Where possible, a comparison with 2017 performance is also provided.
1.3 Methodology
Considering the critical time path, EUROCONTROL undertook an initial assessment based on
readily available data and information from the EUROCONTROL Network Manager, Central Office
of Delay Analysis (CODA) and the Performance review Unit (PRU).
This information was used to identify key themes for stakeholder questionnaires, to prepare
interviews and obtain analytics from stakeholders.
Barcelona stakeholders included ENAIRE (Air Navigation Service Provider - ANSP), AENA (airport
operator) and two main Airlines, Vueling and EasyJet, the Airlines Association who participated in
discussions over a two week period. The discussions were open and well prepared by stakeholders.
Two further discussions were held, one with ENAIRE Corporate and another with AESA, both in
Madrid.
Specific discussions on staffing and rostering were organised with ENAIRE management
representatives from Barcelona Tower, Area Control Centre and ENAIRE Corporate.
A second phase of the performance assessment is planned in 2019 and each task will report
independently. These complementary activities cover airspace changes, runway and airside
capacity, staffing and rostering, separation minima and an A-CDM health check. In general, they
will provide recommendations which are beyond implementation in summer 2019.
The mix of aircraft types is important as it influences the separation minima used by Air Traffic Control
to separate arriving and departing flights. Larger aircraft require increased separation to ensure
safety for following aircraft types, typically to avoid wake turbulence generated by the larger leading
aircraft or to have sufficient time to clear the runway before the next aircraft lands.
The aircraft mix operating at Barcelona is primarily medium size ICAO category Percentage (%)
aircraft, typically Airbus A320 or Boeing B737 types. However, Heavy 7.73%
there is a trend to increasing numbers of wide body aircraft or B757 0.06%
heavy types.
Medium Jet 91.69%
This trend is expected to continue due to additional demand from Medium Turboprop 0.00%
Asia for access to Barcelona. Indeed, there is a third terminal
Light 0.53%
planned, dedicated to wide body aircraft.
This will naturally lead to an impact on runway throughput due to Figure 3: Barcelona Traffic Mix
increased separation requirements and greater taxiway complexity due to the larger wing span of
wide body aircraft.
Surface Movement Limitations
There are other limitations that impact Barcelona parking and surface movement operations from
complexity, controller workload and runway throughput perspectives. These include:
Taxiway and stand limits, due either to wing tip clearance between taxiway and stands or
aircraft pushing back blocking the taxiway;
Aircraft taxiing from terminal 2 to 25L/07R for departure, use a “by-pass” located at the
threshold of runway 07L, which interferes with departing aircraft on 25R;
Aircraft taxiing from terminal 1 to 25R/07L for departure taxi against the natural flow of aircraft
that have landed on 25R/07L proceeding to terminal 1 requiring holding and longer taxing;
Holding points for runway 25L/07R have insufficient space to be used for sequencing aircraft
on to the runway, in some cases aircraft cannot pass each other;
Runway 25R/07L high speed exits (RETs) are not fully optimised to support the needed
runway occupancy time of less than 50 seconds, constraining runway throughput;
Lack of suitable runway exits on runway 02, which means aircraft roll almost full length of the
runway before being able to exit, increasing runway occupancy and reducing throughput.
Noise Abatement
Night time noise procedures are driven by the local environmental agreements based on a capacity-
demand relationship which were feasible when agreed but today are particularly stringent.
Procedures have been prescribed for a night time preferential runway configuration which is enforced
from 2300 to 0700 local time.
Many European airports operate night time restrictions starting at 2300 but ending around 06:00.
The Barcelona restriction is particularly stringent, ending at 0700.
The change over from day to night and night to day capacity creates a complex operational challenge
for ATC as they need to implement a runway configuration change. Two configuration changes are:
Day to night capacity (a reduction from 78 to 48 movements per hour) when arrivals use
runway 02, flying over the sea to avoid population areas. This involves a reduction of
available capacity at 2240 local time so ATC can manage the runway change transition,
creating environment delay, and
Night to day capacity, increasing the number of movements but having to change the runway
configuration when the first morning departure wave is building.
The increase in wide body aircraft types over the coming years should also be assessed on the
probable impact on runway throughput. The taxiway and holding bay infrastructure changes will
help ease the impact of additional wide body aircraft using Barcelona, potentially moderating their
impact on runway performance.
o T1W (TMA sector T1 preferential westerly configuration) and T1N (preferential night
configuration) also provide approach services to Girona whilst T4W and T4N provide
approach services to Lleida airport;
o Standard Instrument Departures (SIDs) and Standard Arrival Routes (STARS) are
complex and some of these instrument routes interact with each other (cross).
70 % of traffic to Barcelona comes/goes from/through Marseille and Bordeaux Flight Information
Regions (FIRs) / Upper Information regions (UIRs). One issue is related to the French airspace
boundary which is only 80NM from Barcelona airfield. This short distance to Barcelona equalling
less than 15 minutes flying time means that the electronic flight update messages provided by France
to Spain arrive late and disrupt the already planned Barcelona AMAN (Arrival Manager) sequence.
An AMAN is dependent on accurate flight update information to calculate an initial arrival sequence
into an airport. A flight update message, sent by the Area Control Centre in the adjacent UIR/FIR
transferring the flight, is often used to update the AMAN. Since the UIR/FIR boundary is so close to
Barcelona, the AMAN has already defined the inbound sequence before the update message is sent
from France.
This disrupted AMAN requires a controller intervention to reset the arrival sequence, an unnecessary
and workload intensive problem. This should be easily resolved through an improvement to the
SACTA System (ENAIRE ATC Technical System)
Introduction of New Arrival Procedures (BRAIN Barcelona RNAV Approach Innovation)
During spring 2018, the BRAIN project deployed new arrival routes based on the use of predefined
area navigation procedures (RNAV) that require aircraft to follow defined routes levels and speeds
on arrival until the arrival controller clear the aircraft to turn onto final approach.
Before the introduction of BRAIN, feeder
sectors managed the sequence by vectoring
and providing speed control to traffic from
the Initial Approach Fix (IAF). The Final
sector controller received that traffic and
adjusted the sequence giving final vector
onto the ILS and speed control until 4 DME.
In radar vectoring, when a controller is
managing 8 to 10 aircraft in the sequence,
holding prior to IAF is needed for subsequent
aircraft to manage increasing controller
workload, resulting in loss of efficiency at
Feeder sectors. Radar vectoring is highly
dependent on ATCO skills and ensuring a
safe balance between quality of service and
overloading the air traffic controller.
With the BRAIN procedure (figure 7), each
transition to the ILS consists of an initial
section from the IAF, an outbound section
(downwind) and an approach section aligned
with the runway.
A transition chart is published, showing the Figure 7: New Arrival Procedures Example - 25R - BRAIN
procedure for each runway and used by the
pilot to manage the procedure.
In BRAIN, the feeder sector Controllers manage the sequence using transition waypoints and speed
control, however traditional vectoring is used in periods of low demand and in the presence of
thunderstorm activity.
The Final sector controller receives traffic in transition on the procedure and combines aircraft
arriving from north and south procedures into one final approach sequence using a turn instruction
to vector aircraft onto the Localiser and then speed control to manage separation until 4 DME.
The number of aircraft flying the procedure, based on AMAN, is normally 10 with number 11 having
to enter the hold.
BRAIN was a one-off implementation. It is expected that with increased controller exper ience and
full awareness, training and briefing of flight crews in use of the new procedures, performance will
improve with no need to regulate arrival sectors due BRAIN in 2019.
However, there is opportunity to optimise BRAIN based on pilot feedback and a EUROCONTROL
top level assessment, with focus on speed control, level management and distance to touchdown
advice to pilots during the approach.
For departures during peak hours there are several consecutive flights via the same waypoint that
increases sector complexity. Only 2 flight levels (FL300 and FL320) are available for use without
coordination between Bordeaux and Barcelona Controllers.
In Barcelona en-route centre, the three GO sectors managing traffic through GIROM and OKABI
share the same vertical volume, each sector defined by a flight level split.
These sectors climb departures from Balearic Islands (Ibiza, Palma and Mahon) to their Requested
Flight Planned Level (RFL) and sequence them towards France via reporting points GIROM or
OKABI.
ATC merges the departing flights into traffic flows from Alicante, Valencia, Castellon and Murcia
(Levante flow). This is a complex operational procedure with the majority of merging traffic managed
by Barcelona.
The capacity of the sectors involved is limited and
introducing additional transfer points would significantly
facilitate an increase in en-route capacity.
During recent discussions involving EUROCONTROL
Network Manager, Spain and France, an agreement to
add a third point, NATPI, positioned between GIROM
and OKABI, was made.
This new point is planned in summer 2019 and will
facilitate departures from Spain towards France
There will also be an improved traffic distribution
between the new interface points and other existing
points at the interface. Barcelona will also climb
departing traffic to FL320, further helping to reduce
complex interaction with descending arrival traffic.
NATPI will provide a parallel route structure which will
significantly reduce the traffic loading at GIROM and
OKABI as seen in figure 9, reducing ATC workload and
delay. In addition, Spain agreed additional flight level
allocations for traffic departing into France, further
reducing complexity.
The military also use this airspace for training. Whilst
this is manageable and route structures are designed to
avoid existing military areas affecting en-route airspace,
there are opportunities to apply Flexible Use of Airspace Figure 9 Boundary Bottleneck between French
and Barcelona Airspace
concepts to the benefit of civil and military ATC, and
airspace users.
One particular area, D21A, provides a
significant challenge to ATC, requiring
routes to deviate causing additional route
miles, affecting at least three additional
sectors.
It is understood that D21A is only used for 70
hours per year and is not available for civil
use outside this. Close coordination with
military organisations should be undertaken
to see what alternative operations can be
agreed to reduce the complexity of this
already challenging airspace.
Figure 10: D21A and Routing / Sector Issue
Traffic
delay increased 64% on 2017. This was attributed 15.000.000 10.400.000
to bad weather, ATC capacity, ATC staffing and a 10.000.000 10.200.000
doubling of delay caused by Industrial Action. 10.000.000
5.000.000 9.800.000
The number of regulations that accompanied these 0 9.600.000
delays increased compared to 2017 leading to 2016 2017 2018
Network instability and concern on the excessive
use of regulation. Airport Delay ER Delay Traffic
An important issue was the lack of systematic communication with airlines on weather (and other
performance issues). Airlines were unable to plan their schedule in an optimum manner as they
were not fully aware of the extent and duration of the weather regulations applied. Bad weather
resulted in Airlines cancelling or re-planning flights with related passenger management issues.
From the network perspective, the combined ATC Capacity, Staffing and Industrial Action from
Marseille Airspace alone, accounted for 39% (150,013 min) ATFM Delay directly impacting
Barcelona arriving and departing flights (figure 16).
As with weather, ATC Capacity regulation is based on future traffic predictions and on occasion the
predicted issues evolve, for many reasons. Barcelona has recognised this issue in some sectors
and will try to reduce the use of regulation.
In many cases, the sector complexity is such that regulation is essential to be able to safely manage
traffic loads. This occurs both in en-route airspace, particularly where traffic arrives from French
airspace and requires sequencing into separate flows for Barcelona and Balearic Island arrivals.
Some of the Barcelona arrival sectors also need protection and regulation is applied to avoid
Controller overload during periods of peak demand.
Environment Delay – and Reactionary Delay?
Whilst the Environment delay trend is
reducing, Environment issues still resulted in
10% of the overall delay.
This is probably an understatement as
environmental issues, primarily noise, are
the main reason behind the non-optimal
operation of the airport.
As aircraft accumulated delay after each
rotation, many of the aircraft returning late to
Barcelona at the end of the day’s schedule
suffered from a colossal amount of
Reactionary Delay; some aircraft
accumulated more than 80 minutes of this
Figure 17: Night Time Runway Configuration
delay type on return to base!
As well as Reactionary Delay, ATC systematically reduces capacity each night when preparing the
change from day to night capacity, which involves a complex ATC procedure to change the runway
configuration (figure 17). Since there is no buffer between day and night capacity, which changes
at 23.00 local time, ATC regulates the flow to ensure arrivals rates are in place at 23.00.
Reactionary delay including aircraft returning late to base, the regulation to prepare for night
capacity, and the change in runway configuration together contribute to the Environment delay.
First Departure Wave In The Morning Is Critical To Daily Performance!
The most common refrain during summer 2018 discussions was “if the first wave does not work,
performance is impacted all day.” In many respects, this statement and the reasons behind it, sum
up many of the issues affecting performance in summer 2018.
The main carrier in Barcelona, with 39% of total movements, has a majority share of wave 1. The
airline operates primarily out of Terminal 1, close to the preferential departure runway. If the airline
has a poor first wave, wave 1 is compromised.
Despite implementing a number of mitigations to manage any disruption in summer 2018, The main
carrier suffered from reactionary delay which posed recovery issues for ground handling and
impacted night time maintenance windows which should normally be allocated 7 hours.
An additional issue at night was the airline’s apparent difficulty to trac k maintenance progress and
lack of awareness as to where aircraft were parked. This apparent “lack of awareness” impeded the
departure planning process of matching aircraft-to-destination and ensuring a good gate distribution
so that similar time departures did not pose issues of boarding and pushback.
It was also noted that the main carrier had 50% of the
aircraft returns to parking during the summer period.
This can be for a number of reason but if it happens
during Wave 1 it can create issues with taxing aircraft
and parking, increasing complexity.
During summer 2018, AENA, responsible for gate
allocation and operation, worked with the main carrier’s
operations to to alleviate these issues and is focusing
additional effort on Wave 1 for 2019.
The outcome of these different challenges could lead to
late departures, critical to Wave 1 and the performance
of subsequent waves. Taking into consideration the
numerous Network and local disruptions that occurred
during summer 2018, it is easy to see how the difficulties
confronting airlines lead to Reactionary Delay (estimated
to be 44% of the total 2018 delay in Europe). Figure 18: Main carrier’s returning Aircraft & De-
code
70% of Barcelona Traffic is Low Cost Carrier: Tight
Schedules and Short Turnaround!
Whilst tight block times and short turnarounds are core to the LCC business model, they are also
susceptible to disruption. This was clearly the case in summer 2018 with the large number of
disruptions impacting flights, the lack of resilience in the LCC schedules with no “demand troughs”
for recovery contributed further to Reactionary Delay.
The summer schedules leave little room for recovery from disruption and each rotation of an airframe
can lead to further delay. Reactionary delay in Barcelona at 20.00 local time was approaching 30
minutes per flight with later flights recording in excess of 80 minutes delay (figure 43).
With expectations of challenging performance in summer 2019, airlines would be advised to consider
including firebreaks in their schedules to build resilience against disruption.
Communication Builds Trust!
ENAIRE, AENA and the local Airlines all hold important information concerning current and future
operational issues. Sharing such information to build common awareness could help all
stakeholders anticipate and plan mitigation to expected disruption, or even planned events.
Unfortunately, there was no systematic communication of this nature in Barcelona. Communication
appeared to be ad hoc, subject to time or staff availability and frequently “a concern” in case any
information would be used inappropriately.
An important example where communication has important business benefits is the impact of
weather regulation on airlines. A long weather regulation has significant consequences for airlines,
flights are delayed, rerouted and cancelled, with associated collateral damage to passengers’
journeys. Significant delay can quickly result in reparation costs to airlines under EU Regulation
261.
Systematic communication to airlines on the nature of regulations, their likelihood, duration and
severity would help airlines better plan changes to flights, rearrange their daily schedules, and
prepare for disrupted passenger journeys. It would also build trust, facilitating other difficult
conversations, for example, on demand reduction sharing to avoid major disruption.
Systematic communication of expected disruption in the network and at the airport, and the plans or
actions put in place to mitigate disruption was absent in Barcelona during summer 2018. It is urgently
required and is in place at other major European airports. Critical information is available and
processes should be put in place to systematically inform all stakeholders of issues that are likely to
disrupt their operations. This would have made a difference in 2018.
4. “BENCHMARK” COMPARISON
A comparison with other “similar” European airports is challenging considering Barcelona does not
operate the airport runways as designed and in general, no “two” airports operate the same way.
Nevertheless, the EUROCONTROL Performance Review Unit (PRU) 2018 data provides interesting
comparison points, which are discussed below.
As Gatwick is cited by a number of stakeholders as being best in class, we have included it here
although it is a single mixed mode runway operation. We look across a spectrum of airports with
parallel runways, operated in different configurations, to provide a level of co mparison.
The airports are: London Gatwick, London Heathrow, Madrid Barajas, Munich, Palma de Mallorca
and Rome Fiumicino.
Runway Layout and Usage
As previously discussed, Barcelona
operates two parallel segregated runways,
with the short runway for departures and the
longer runway for arrivals. Occasional wide-
body aircraft depart from the longer runway.
This supports a declared runway capacity of
78 movements per hour.
In comparison, Heathrow and Munich, both
operating parallel runways in different
configurations, achieve runway throughput
of 88 and 90 movements per hour, similar to
the design capacity of Barcelona (without the Figure 20: Comparison with European Airports (2017 Data)
same restrictive noise constraints).
Interesting, high performance is achieved at Heathrow, despite the aircraft mix which has a
significant percentage of heavy wide body aircraft types compared to Barcelona which is primarily
medium size jets, yet Heathrow declares 10 movements an hour more.
London Gatwick, best in class for single runway mixed-mode operation, had a declared throughput
of 55 movements per hour. This is achieved through a strict performance based runway
management in collaboration between the ANSP and airlines.
In comparison, Barcelona throughput is 40 per hour departures and 38 per hour arrivals on dedicated
runways, suggesting room for performance growth.
Taxiway Complexity
Barcelona has a complex taxiway system,
which is due to the complex surface issues
such as runway crossing, wing tip clearance
on certain taxiway / gate areas and the lack
of appropriate holding bays close to the
preferential departure runway, 25L.
Non-constrained average taxi time is 15
minutes.
The additional taxi-out time KPI is a proxy for
the average departure runway queuing time
on the outbound traffic flow, during
congestion periods at airports. Figure 21: Additional Taxi-Out Time 2018 Comparison
Barcelona performance in terms of additional taxi-out times is the 5th highest in Europe, but average
compared with our chosen airports, as can be seen in figure 21, although it underlines airport surface
complexity and lack of runway holding.
Off-Block and Reactionary Delay
Pre-departure delay is the delay in “Off
Block” with respect to the Schedule Time for
Departure. The reasons for off block delay
are provided by the airlines / handling agents
to the airport.
Average delay in the off block time (AOBT-
STD) in Barcelona is almost 23 minutes per
departure, which is the 6th highest in
Europe. The main reason for the off block
delay is attributed to reactionary delays by Figure 22: Average Pre-Departure Delay 2018 Comparison
airlines (standard IATA codes 91 to 96).
Average pre-departure delay in Barcelona reflects the challenges of the low cost carriers to manage
tight turnaround times when there is additional disruption in the system or insufficient resilience in
airlines daily schedule to make up lost time. Reactionary delay is discussed in section 5.3.3.
Arrival Delay and Airspace Holding
The PRU Airport Arrival ATFM Delay KPI
provides an indication of ATFM delays on
the ground due to destination constraints.
This indicator shows in the period January-
September 2018, Barcelona had the second
highest arrival ATFM delay per arrival in
ECAC Top 49 airports (after Lisbon).
Much of this delay can be attributed to
weather, ATC Capacity in Terminal Airspace
and BRAIN deployment. Apart from Palma Figure 23: Arrival ATFM Delay 2018 Comparison
de Mallorca, other airports have a different
mix of delay reasons making a meaningful comparison difficult.
The indicator used as a proxy for arrival holding or TMA LEBL EGKK EGLL LEPA LFPO
delay is Additional time (Arrival Sequencing and 12,0 14,7 15,1 11,4 11,5
Metering Area). This is the difference between the
Table 1: ASMA Time
actual ASMA transit time (actual time on arrival in
terminal airspace) and the unimpeded ASMA time calculated for non -congested conditions.
ASMA shows that Barcelona performance is not Punctuality
LEBL EGKK EGLL LEPA LFPO LIRF
indicators
dramatically worse than other airports in Europe. At Arrival
Punctuality 59.9% 61.7% 77.8% 67.1% 77.6% 75.6%
capacity challenged airports, holding is often used (% flights)
as a means to ensure there is always demand Average
Arrival 27.0 23.6 11.8 20.3 12.8 13.8
pressure on a runway, to maximise throughput. Delay (Min)
London Heathrow is a typical example. Departure
Punctuality 60.2% 65.1% 75.7% 62.6% 73.1% 68.3%
(% flights)
In 2019, BRAIN airspace procedures should improve Average
terminal airspace resilience, containing ASMA delay. Departure
Delay (Min)
23.9 20.4 12.7 21.7 14.8 16.6
Arrival
Punctuality Comparison Traffic
Ahead of
5.6% 8.2% 17.1% 7.2% 8.8% 8.7%
EUROCONTROL compiles airport and air carrier Schedule
>15 min (%
data on arrival and punctuality delay. Table 2 shows flights)
that in all classes, Barcelona has lower performance. June to October 2018 Air Carrier-Airport Data
For arrival punctuality, Barcelona is similar to London Gatwick although average arrival delay,
minutes per flight, are higher than Gatwick at 27 minutes.
For departure punctuality, Barcelona
and Palma are similar, but average
departure delay, minutes per flight,
are worse than others at 23.9
minutes.
During summer 2018, Barcelona
arrival and departure punctuality was
worse than the selected comparison
airports.
Top Level View on ATFM Delay
EUROCONTROL analysis shows that
Barcelona airport is second out of the
top ten European airports in total
ATFM delay (figure 26).
Amsterdam is first although the
number of movements in Amsterdam
in 2018 was 511,272 compared to
Barcelona with 335,594.
The Barcelona Area Control Centre Figure 24: Barcelona Area Control
Figure 25: Barcelona Airport ATFM
was ranked seventh out of the top ten Delay Compared Centre ATFM Delay Compared
European Area Control Centres in
Total En-route ATFM delay (Figure 24).
In comparison with other Centres, Barcelona issues were weather, ATC Capacity and Staffing whilst
the headline Centres were hit by Staffing, ATC Capacity and industrial action (Marseilles).
The Environment: Noise
A number of large European airports have night curfews in place, e.g. London Heathrow, Frankfurt
and Munich, severely impacting flights. Where there are curfews in place, the curfew start time varies
from 22:00 (local) to 23:30 (local) and generally ends at 06:00 (local).
Some other European airports, whilst not having a complete curfew in place, operate with restrictions
for night operations. These can be:
Specifying certain runways only for use, as is the case in Barcelona and Milan Malpensa for
example, and
A combination of measures as is the case in Brussels (Weekend / Weekday time differences
and night time hourly quotas).
As an example, in Brussels, between 22:00 and 04:59 (local):
Monday – Thursday inclusive, 2 runways are specified for departure, depend ing on the
SID/route flown after departure
Friday – Sun inclusive, only 1 runway is available for departure but a different one for each
night; 25R on Friday night, 25L on Saturday night and 19 on Sunday night
Friday – Sunday inclusive between 00:00 and 05:00 aircraft operators cannot schedule
departures as no departure airport slots will be issued. Landings are still permitted and some
delayed departures may still be allowed
Changeover times from night-time to day-time operations may have a level of flexibility in order to
ensure transition in safe conditions. ATC will operate the changeover as close as possible from the
indicated time, taking into account the actual traffic conditions.
It should be emphasised however, that whenever there is a night-time restriction or curfew, they are
generally lifted no later than 06:00 and the day-time configuration is then used.
Summary
The comparison of both parallel and single runway configurations show that Barcelona has scope
for future runway performance improvements. This will require development of different techniques
and support tools and investment appropriate runway exit availability runway holding areas.
There is an opportunity to undertake quick improvements by borrowing techniques such as the
collaborative runway performance management procedures used in London Gatwick and Heathrow
to reduce runway occupancy time. These offer a short term option to achieve quick benefits whilst
preparing future change such as reduced radar separation on final approach , that should be
addressed (as discussed later in section 5.1.1).
Punctuality in Barcelona is generally poor compared to other European Airports, however the Airport
and ATC En-route Centre are in the top ten locations for overall ATFM dela y.
Noise is a significant challenge in Barcelona and it is prevalent in all areas of operation . However,
there is no common model in Europe to reference, although the application of the night -time
operations start and end times are similar in most European airports reviewed.
The “benchmark has identified that Barcelona, in comparison to other parallel runway airports, with
its potential for mixed-mode runway operations, has significant growth potential to transition towards
the original design throughput of 90 movements per hour. This is feasible with the necessary
operational and technical investment.
The analysis undertaken in this report is focused on the summer issues in 2018 . A strategic and
systemic assessment of all the operational, technical, infrastructure and environmental issues,
involving all stakeholders would provide a better understanding and help stakeholders develop and
align long term strategic plans.
5. DETAILED ANALYSIS
5.1 AIRPORT AND AIRSPACE OPERATIONS
5.1.1 Airport
In 2018, Barcelona enjoyed an average of
3.74% traffic growth (comparable with the Traffic Barcelona Airport Evolution
network growth of 3.82%) with traffic 35000
increase in the summer period of 2%
30000
compared to 2017, which is within
25000
Movements
EUROCONTROL forecasts.
20000
Unfortunately in 2018, average arrival delay
15000
per flight (year to date including September)
increased from 2 minutes per flight in 2017 to 10000
3.1 minutes in 2018. 5000
0
Barcelona Airport capacity delays were
September
March
February
April
May
August
July
January
November
December
June
October
experienced mostly on weekends. The busy
Barcelona traffic days are Monday, Friday
and Sunday. One peak day to note was the
15th of June, when 1123 flights were 2016 2017 2018
recorded.
Figure 26: Barcelona Average Daily Evolution of Departure
Traffic per Month
Traffic Waves: Summer Demand, Actual
Traffic and Issues of Resilience
Theoretically, Barcelona scheduled capacity and demand balance shows periods of respite between
departure and arrival waves. This would facilitate schedule recovery time, critical for the low cost
carriers, who normally operate short block times with highly efficient turnaround processes typically
lasting around 35 to 45 minutes in Barcelona (the main carrier’s average turnaround time for the
entire season in Barcelona was 58 minutes).
90 90
80 80
70 70
60 60
50 50
40 40
30 30
20 20
10 10
0 0
1 3 5 7 9 11 13 15 17 19 21 23 0 2 4 6 8 10 12 14 16 18 20 22
Figure 27: Scheduled Traffic Summer 2018 Figure 28: Actual Traffic Summer 2018
The Barcelona turnaround times (35 to 45 minutes) and are agreed by the slot coordinator. However,
delay in the first wave of departures, can have severe performance repercussions throughout the
day. There is further discussion on this in section 5.3.3
Compared to 2017, summer 2018 saw an increase in throughput throughout the day, with a second
departure wave overlapping with the second arrival wave, significantly reducing the recovery troughs
in the schedule, as seen in figure 28 above.
The reasons for this are complex and would include: ATC procedures and challenges to deliver
runway capacity, airline schedules and significant demand at peak periods, for example the first
departure wave.
With current ATC operational techniques, additional demand can only be accommodated during the
less busy hours of the day as increases in capacity during peaks will likely be marginal, further
reducing recovery buffers and resilience when there is a performance down fall.
In the ATENEA strategic plan, a process of Custom Slot Coordination by hours is proposed to start
in 2019. Capacity benefits are expected in 2020 with 40 arrival and 42 departure movements
predicted.
Part of the hourly Custom Slot Coordination strategy is to ensure that capacity offered is tailored to
peak demand. It also means that there will be periods of recovery built-in when ”valley” periods are
created between peak demand to ensure that resilience and recovery time is available in the event
of actual over-demand occurring during operations.
Wide Body Conundrum – Operational Complexity and Delay Allocation
Barcelona airport is served primarily by medium type aircraft such as Boeing 737 and Airbus 320.
As such, wide body aircraft types will impact separation minima and as a consequence, runway
throughput performance.
Wide-body aircraft movements represent around 10 to 15 flights per day and the airport foresees an
increase in wide-body movements, particularly on routes to and from Asia. A dedicated wide body
terminal is planned in the AENA 8 year strategy to cater for increased wide body access.
Wide-body movements pose particular challenges due to the Barcelona preferred noise related
runway use. If they are an older generation aircraft type they require to undertake a non -preferential
runway operation, departing from runway 25R.
This increases surface flow complexity as these aircraft must taxy against the predominant traffic
flow to reach runway 25R holding point from their gate.
A second issue is the need to create a departure gap in the arrival sequence to accommodate the
wide-body departure from runway 25R, resulting in a temporary capacity reduction.
Previously, the associated delay was attributed to aerodrome capacity, however, a new delay
allocation formula agreed between AENA and ENAIRE, came into effect on 01 August with the wide-
body non-preferential delay is now allocated to Aerodrome ATC Capacity delay. 2018 summer data
show a change in balance between aerodrome and ATC capacity delay, reducing aerodrome
capacity delay.
As demand from Asia increases, additional wide-body movements will further impact operational
complexity and runway throughput so options should be explored to see how this increase can be
accommodated to avoid reductions in capacity.
Apart from operating the airport during the day as originally planned, one serio us option to be
considered would be to extend runway 25L/07R by approximately 500 metres to the east. This
brings operational and noise reduction benefits. An increase in take-off length of runway 25L
removes the need for wide body aircraft to depart from runway 25R, providing an improvement in
noise. Furthermore, it removes the need to increase separations for wide -body departures on 25R,
reducing the associated loss of throughput.
Such an extension is a challenge due to the existence of the nature rese rve to the east of the runway,
close to the beach. However, the overall benefit to the airport, municipalities and neighbouring
communities’ is positive and merits further study and discussion.
Summary
Barcelona airport is operating with a significant disadvantage due to the local noise procedures which
constrain the original design use of the parallel runways, as explained above.
Despite the maximum design for throughput of 90 aircraft per hour (possible through independent
runway operations) Barcelona was operating at 76 movements per hour in 2018.
Without significant change in runway use, together with investments in ATC procedures, systems
and airport infrastructure, achieving a throughput of 90 aircraft per hour is a major challenge.
A EUROCONTROL assessment suggests runway throughput capacity increase is possible through
tight runway occupancy management and reduced radar separation minima, reduced runway
occupancy time and new wake vortex separation (RECAT EU).
Runway throughput can be further enhanced through the implementation of performance based
standard instrument departures, providing a greater number of diverging tracks for aircraft to
establish shortly after departure.
Airport performance is relatively dependent on the performance of it s main airline and particularly
it’s performance on the first departure wave in the morning. The demand during the first wave is
greater than capacity and therefore there is little resilience in the event of disruption either from
external factors such as weather, industrial action, ATC Staffing and Capacity regulation or the main
carrier’s specific issues related to aircraft readiness and off-block performance.
A continued increase in the number of wide-body aircraft in the Barcelona traffic mix will impact the
predominantly medium traffic mix and therefore related capacity (bigger aircraft generate wake
turbulence leading to larger separation minima reducing runway capacity . This can be mitigated by
implementing RECAT EU Wake Turbulence separations when appropriate and Time Based
separation later.
Related to arrival airspace procedures and runway throughput, is the radar separation applied. The
normal radar separation on final approach is 3NM, however, when there is a wide -body departure
from runway 25R, Tower Controllers require a spacing of 8NM. This results in the loss of 3 arrivals
for every 2 wide-body departures.
The impact of noise procedures was discussed in section 2.1, however, the opportunity to move
towards the target 90 hourly movements runway throughput could also be facilitated if the current
runways operating as designed during day time hours when, normally, as in most European airports,
noise restrictions negotiated with local populations, are less onerous.
Comparison of both parallel and single runway configurations operated at different airports shows
that transition towards 90 movements per hour, should be feasible even within current constraints.
ENAIRE should continue to benchmark with other airports to identify the specific operation al and
technical improvements necessary to achieve the target, updating its ATENEA plan accordingly.
AENA should also benchmark infrastructure deployed that enables high throughput rates at other
airports, to ensure that future infrastructure investments on priority items such as runway exit points,
displaced thresholds, parallel taxiways and runway extended holding bays are adequate and
included in its 8 year strategic plan.
Recommendations
Short Term
[M01] Performance Based Runway Occupancy Time (ROT) Management
The full potential of Barcelona runways can be better served if airlines exit the runways after landing
in a consistent, expeditious and predictable manner. Today ROT is variable and there are no
processes in place to develop a performance culture in Pilots and Controllers to optimise ROT.
It is recommended that ENAIRE develop a performance based runway occupancy time management
process together with airline stakeholders, to safely minimise ROT, agreeing, monitoring and
reporting on ROT and use of preferential runway exit points, per aircraft type.
This recommendation will result in additional runway throughput and will be an enabler for further
performance enhancements such as reduced minimum radar separation and the application of
ROCAT, Runway Occupancy Categorisation, developed by EUROCONTROL and being deployed
in Vienna (similar traffic mix to Barcelona) and Paris Charles de Gaulle.
The process will require close cooperation between airlines and ENAIRE, strict monitoring and
reporting process, with regular (weekly) feedback on individual aircraft and airline performance.
Runway occupancy times and exit point by aircraft type should be published in the AIP.
Barcelona should consider benchmarking against both Heathrow (independent parallel runway
operations) and Gatwick (intense single runway operations) where ROT procedures are deployed,
bringing reduced occupancy time supporting reduced radar separation and an increase in
throughput.
Long Term
[M02] Implement Day-Time (Mixed Mode) Independent Parallel Runway Operations
Due to environmental issues, Barcelona runways are not used as designed, leading to operational
complexity and capacity issues during day and night time operations.
It is recommended that DGCA and AENA revisit current local noise constraints together with local
population and municipal stakeholder groups to implement independent parallel and mixed mode
runway operations between 0700 and 2300 local time.
An equitable and balanced position should be sought using EUROCONTROL Collaborative
Environment Management (CEM) and expertise to develop and implement noise efficient standard
instrument departure and standard arrival routes, and continuous climb / continuous descent
procedures, exploiting aircraft performance and Performance Based Navigation ( PBN).
This recommendation is expected to reduce operational complexity and safely increase runway
capacity, with a view to achieving the full airport performance design capacity of 90 movements per
hour, bringing associated economic benefits to airlines and local communities alike whilst mitigating
noise. Comparison with other European parallel runway airports with noise constraints, shows this
to be feasible, Heathrow operates 88 movements per hour and Gatwick 55 on a single runway..
[M03] Hourly Based Custom Slot Capacity
Barcelona suffers from lack of resilience during summer peak traffic, when there is little respite
between departure and arrival waves and subsequent aircraft rotations. The nature of low cost
carriers business operations such as short block times and quick turnaround leaves little margin to
recover from reactionary delay.
With flights already departing Barcelona late, the knock on effect results in aircraft returning during
busy arrival traffic, further exacerbating and compressing the daily schedule, resulting in no respite.
Airlines need to review what actions to take to avoid the virtuous reactionary delay cycle. Airline
options are discussed in section 5.3.3.
It is recommended that ENAIRE deploy their proposed hourly “custom slot capacity scheme” in time
for 2020, that maximises the availability of ATC Capacity and Staffing resources during periods of
peak demand and creates troughs of reduced capacity, that responds to airlines needs whilst
recognising that a respite period is required to recover from reactionary delay.
This hourly based custom slot capacity system must be agreed with the slot coordinator and
coordinated with AENA and the airlines operating in Barcelona.
Hourly based custom slot capacity system is expected to bring increased runway throughput and
airspace capacity during periods of peak traffic demand, additional resilience during the day to
address lack of respite for delayed aircraft (due to reactionary delay) by focusing ATC capacity and
staffing to address the airlines main operational peaks.
[M04] Performance Based Standard Instrument Departures (SIDs)
Barcelona departures on the preferential runway configuration (departures from runway 25L) are
required to turn left after 500ft in the climb and track out over the sea , due to noise abatement.
This procedures constrains ATC ability to fully optimise departure separation minima resulting in
poor runway performance.
It is recommended that ENAIRE implement SIDs based on RNAV with diverging splits of 21° that
aircraft establish on when turning left after climbing through 500ft, and which will permit ATC to fully
optimise runway 25L departure separations.
This recommendation is expected to increase the number of diverging tracks that can be used for
departure separations, by “mirroring” the “left, right, straight ahead procedures traditionally used to
expedite departures through RNAV routes.
[M05] Runway 25L Extension
The Take Off Run Available (TORA) for runway 25L departures is too short for many of the larger
wide-body aircraft, and as a consequence these aircraft are required to undertake a non-preferential
departure from runway 25R which reduces throughput on that runway.
It is recommended that AENA extend runway 25L by at least 500m to the east of the current
threshold, thus providing additional TORA, suitable for wide-body departures.
This recommendation will obviously require support from Department/DGCA in negotiating the
proposed extension with the local population, nature lobby, Autonomous Government of Cataluña
and municipal authorities.
This runway extension is expected to be a “win-win” opportunity as it will safely increase runway
throughput on 25L, providing sufficient TORA for wide –body departures, removing such movements
from runway 25R and reducing noise on the 25R departure path close to population areas.
Furthermore, it will remove the wide-body constraint to operations on 25R, and will facilitate eventual
possibility of mixed-mode high performance operations on 25L, including medium aircraft turning
earlier than today.
In the event that this proposal is agreed, AENA should take the opportunity to prioritise the
construction of parallel taxiways and extended holding bays as well as additional entry points to
access runway 25L and facilitate aircraft passing further enhancing ATC ability to optimise each
departure separation. An infrastructure benchmark at similar high performing airports and in-depth
discussions with Enaire will refine and inform such investment.
[M06] Implement ROCAT, Runway Occupancy Categorisation
With peak demand requiring an increase in capacity there is an opportunity to use the different ROT
of the aircraft operating in Barcelona. Specifically, there is a natural split of ROT between Boeing
B737 and Airbus A320 aircraft types and smaller aircraft, result ing in two categories. These
categories also match the RECAT-EU wake turbulence split in the medium aircraft category.
EUROCONTROL has defined a new separation procedure to exploit these two categories and to
increase runway throughput. This is ROCAT – Runway Occupancy Categorisation.
It is recommended that ENAIRE implement ROCAT at Barcelona following the deployment of
performance based runway occupancy time (ROT) management and the agreement to reduce
minimum radar separation to 2.5 nm, both of which are pre-cursors to ROCAT.
This recommendation is expected to bring additional runway throughput due to the reduced
separation minima which can be used either to enhance capacity during peak demand or to improve
resilience. It is currently being deployed in Vienna and Paris Charles de Gaulle.
EUROCONTROL is ready to support ENAIRE by transferring knowledge on ROCAT and providing
technical and safety expertise to support the development and implementation preparation of the
procedure.
In the longer term, when wide-body aircraft movements increase above 15%, EUROCONTROL
recommends and is ready to support ENAIRE to develop and implement RECAT EU six category
wake separation minima (already implemented in Paris Charles de Gaulle and London Heathrow),
which will mitigate the impact of additional wide-boded operations on runway throughput.
This knowledge transfer and implementation support will also be available from EUROCONTROL in
the future, if ENAIRE decides to deploy Time Based Separation, TBS, to bring further runway
capacity enhancements. NATS is also in a position to provide support on RECAT -EU and TBS
implementation.
ATC has identified periods when regulation was applied to reduce sector overload , for example in
the DDI sector. In hindsight, ATC perceived that in many cases the regulation was not needed as
the predicted traffic load did not arrive as expected. This provides an opportunity to avoid regulation
although some system or procedure support will be necessary to he lp Controllers safely judge on
which occasions a regulation can be avoided.
The non-optimal use of Barcelona runways, discussed in section 2.1. With arrival aircraft landing on
the longest runway, 25R, throughput is affected each day by non-preferential departures of wide
body aircraft that need the long runway for take-off.
The proposal to reduce minimum radar separation on final approach will resolve issues related to
protecting a missed approach and the associated loss of throughput due to increase sepa ration
resulting in a loss in throughput is 2 movements for every three wide body departures. ATC
specialists believe that reducing the minimum radar separation to 2.5nm will reduce this gap to 6nm.
The challenge is that landing traffic need to consistently exit the runway in under 50 seconds to
ensure the reduced separation is safe.
Current runway occupancy time (ROT) varies around 50 or more seconds . This should be
addressed as discussed in the section 5.1.1, through implementation of a performance based
runway management.
Impact of BRAIN
In general, this mode of operation is easier for Controllers, as trajectories are more predictable and
the operation is standardised (it does not depend so much on the expertise of the controller).
Nevertheless, it requires training and on-the-job practical experience and this takes time.
During the implementation it was necessary to apply a reduction in capacity and therefore regulation,
resulting in delays. These are recorded as special event delay. Throughout the transition, capacity
gradually increased from 32 arrivals per hour at the start of the implementation up to the current 38
per hour.
The implementation of BRAIN was planned to take 24 days but in reality it took three months, lasting
until the end of July.
The reasons for this are:
Controllers becoming accustomed to the procedure
Some strip failures in SATCA (the ENAIRE ATC System)
Pilot non-compliance with the procedure
The main consequence was extended regulation, longer than anticipated, with the accompanying
increase in delay.
By the end of the extended transition, the full runway throughput capability was achieved and no
further regulation was required.
On a positive note, BRAIN has reduced the need for airborne holding by 70% and brought a capacity
increment of one movement per hour. With more operational practice and experience for Controllers
and Pilots during winter 2018/2019, it can be expected that BRAIN will bring further performance
benefit to Barcelona.
With regard to procedures, additional systemisation could be achieved through strict use of BRAIN
to ensure pilot familiarity, providing distance to touchdown information to pilots, publishing and
systematically applying speed control reductions along the approach, and possibly reducing the size
of the pre-defined level bands.
This, combined with the reduced radar separation referred to earlier in this report, will have a
significant positive impact in delay reduction.
However, some caution is necessary since bad weather in the vicinity of the BRAIN arrival procedure
may require Controllers to revert to vectoring to avoid bad weather. This is not unique to Barcelona
and is normal practice.
Summary
The complexity of Barcelona Terminal Airspace sectors and the additional factors of VFR traffic, pilot
training, parachute operations and control of arrivals and departures to Girona, Reus and Lleida
airports adds significant workload for Controllers to manage as well as frequency congestion. These
issues are likely to increase with demand.
The Barcelona Arrival Management Sequencing tool, AMAN, is disturbed by late delivery of flight
update estimates from France due to the closeness of the boundary between Bordeaux, Marseilles
and Barcelona. This results in unnecessary Controller workload to reset the optimal sequence and
a suitable system fix should be identified and implemented.
Future TMA infrastructure should ensure segregation of IFR and VFR traffic through a dedicated
Flight Information Service (FIS) working position with a dedicated frequency. The design should
also consider segregating arrival and departure traffic through specialised sectors and redesigned
SIDs and STARs.
The recognition that using regulation to “protect” some arrival sectors from traffic overload has not
been necessary as the predicted traffic complexity did not happen should be taken as an opportunity
to trial periods of predicted Traffic complexity when regulation is not applied. This wil l require
significant analytical evidence and guidelines to support ATC regulation decision making .
The ENAIRE deployment strategy, ATENEA, has already identified key actions to reduce complexity
and increase capacity through Terminal Airspace re-design.
The BRAIN project was one of the first of the ATENEA initiatives and BRAIN will further enhance
operations in 2019.
Whilst BRAIN implementation resulted in delay during summer 2018, it has brought efficiency to ATC
arrival operations by helping Controllers systematically build structured arrival sequences and better
manage the sequence gaps that are required to enable non-preferential wide body departures from
runway 25R.
However, a number of operational shortcomings were identified by airlines and ENAIRE during the
initial operation of BRAIN and these should be resolved in time for summer 2019.
Recommendations
Short Term
[M07] Enhanced BRAIN procedures
During the implementation of BRAIN, pilots complained of lack of distance to touchdown information
which is used to understand the descent profile and manage aircraft speed. This is critical to ensuring
an optimum continuous descent approach and to preparing the aircraft’s final approach to land
configuration.
There was confusion for some pilots not local to Barcelona operations resulting in some operational
errors.
It is recommended that ENAIRE further systemise BRAIN approach procedures by refining, testing
and if acceptable, publishing, the amended approach procedures, incorporating:
1. Predefined and systematically applied speed profiles, typically 210KTS downwind, 180KTS
base leg and 160KTS on final to 4NM;
2. Reduced level bands from 4000ft to 2000ft where level banding is applied;
3. Consistent use of “distance to touchdown” guidance from Controllers to support pilots in
managing the flight profile and aircraft energy, thereby avoiding unstable approaches
4. Continuous use of the procedure with no “ad-hoc” direct clearances in low traffic, to reinforce
and ensure pilot and controller proficiency in the procedures;
5. A rigid approach to use of standard phraseology to avoid non-local Pilot confusion, and
6. Incorporate BRAIN into the published STAR procedures, so there is only one reference for
approach.
The recommended changes should be communicated to and refined with airlines and Pilots, to
ensure the operability and full awareness of any procedure changes. The decision to implement the
change should be well informed by consultation with airlines in the event that the changes might be
too late to be fully integrated before summer 2019.
This recommendation is expected to systemise the application of BRAIN procedures making it easier
for Controllers and Pilots alike to manage the approach to land with improved aircraft profiles and
better adherence to the procedures. This systemised approach is ingrained in Heathrow and
Gatwick approach control resulting in consistent and predictable Controller and Pi lot performance
whilst the “trombone” technique (BRAIN)is used in Frankfurt and Munich.
There is need for additional study and validation of steps 1, 2 and 6 to confirm the applicability and
benefit before considering implementation of these parts of the recommendations by 2021.
These single transfer points result in excessive traffic merging at a single point for traffic transiting
between France and Spain, creating a bottleneck (Figure 9).
In Barcelona the GO sectors manage traffic
on the GIROM / OKABI axis. These sectors
have continued to absorb increasing traffic
demand during summer 2018 as can be
seen in figure 31.
The decision to add an additional point,
NATPI, agreed in January 2019 (described
in section 2.3) should be formalised and
procedures designed and implemented for
summer 2019. This will relieve GO sector
workload and should result in capacity
increase.
A technical issue identified is the inability to
retrieve flight plans from Madrid Centre for
aircraft that have deviated from Madrid
airspace into Barcelona airspace due to
weather avoidance, leading to flight plan
deviation. This capability does not exist in
the SACTA ATC System.
Taking into account the considerable
weather issues it 2018, it is highly advisable
that this capability is implemented in SACTA Figure 32: Additional Transfer point (NATPI) and Airspace
to avoid Controllers having to manually volume allocation
prepare flight plans when flights divert from one Centre to another. This is likely to be a National
issue so a common solution will have wider benefit.
The issue of D21A, only used for 70 hours per year, was identified in 2.3 (figure 10) and should be
addressed to avoid additional routing to deviate around the area. The traffic on the impact ed route
is around 200 flights per day which are unnecessarily rerouted through three additional sectors. A
dialogue with the appropriate military organisations should be initiated to achieve an equitable
solution to reduce complexity of this already challenging airspace.
Recommendations
This recommendation is expected to significantly reduce the complexity at the airspace boundary,
facilitating the traffic management and control tasks necessary to prepare the traffic sequences
either towards France or arrivals towards Barcelona and the Balearic islands.
Long Term
[M13] Implement SACTA Flight Plan Retrieval for Weather Deviating Flights
During severe weather, aircraft deviate significantly from their flight plan and may cross from Madrid
Centre airspace into Barcelona Centre airspace, or vice versa. When this occurs, the Controller has
to coordinate to obtain flight details from the transferring Centre and manually create a flight plan.
Given the severity and amount of severe weather in summer 2018 and the increasing trend of severe
weather, it is advisable that ENAIRE updates the SACTA system to support easy flight plan retrieval
by the sector controller receiving the diverting flight. This is likely to bring National benefit.
It is recommended that ENAIRE develop a flight plan retrieval application in SACTA for summer
2019 that allows a Controller receiving an aircraft diverting from one Centre’s airspace to another’s,
to quickly retrieve and create a flight plan for that flight, thus enabling the flight monitoring, sector
profiles and transfer functions in SACTA.
This recommendation is expected to resolve the lack of system support for flight plan retrieval,
facilitating the Controllers work during periods of high workload during poor weather conditions that
result in flights deviating across Centre boundaries.
ENAIRE has commented that this recommendation requires significant system modifications and
would not be available until 2021.
[M14] Dynamic Sector Volume Allocation
During peak summer traffic, the sector CCC family can be overloaded by traffic inbound flows to
Bordeaux or to the Balearic Islands from Marseilles. When this happens one of the sectors in the
CCC sector family may become overloaded. It is proposed to define a “dynamic airspace volume”
that can be allocated to the sector that is overload, to provide additional airspace in an attempt to
facilitate the Controller’s work in vectoring to create the initial arrival sequence.
A “dynamic airspace volume” is a new concept in Spain and although it is used elsewhere, i n Italy
for example, it will require a full justification and safety assessment to obtain approval from the
Spanish Regulators, AESA.
It is recommended that the ENAIRE develop the “dynamic airspace volume” concept, validate the
procedures and complete a detailed safety proposal to justify its use to the regulator, in time for
implementation by summer 2019.
This recommendation is expected to bring additional capacity to the sectors involved although it is
not expected to fully resolve the delay generated by these sectors.
[M15] Negotiate a Flexible Use of Airspace Solution to Reduce Impact of D21A
The military area D21A is lightly used and impacts a busy airway in Barcelona Airspace. The impact
of D21A is an increase in track miles flown to deviate around the area and an increase in the number
of sectors through which the deviation route crosses.
It is recommended that ENAIRE and the Spanish Military Authorities work together to identify a
Flexible Use of Airspace solution that equitably resolves the issue of re -routing and additional sector
crossing to the satisfaction of both organisations.
This recommendation is expected to provide a solution that reduces the additional track miles flown
and the associated cost to airspace users.
Table 4 Summary of summer 2018 Weather Regulations in Barcelona Table 5: Weather regulation Compared
Airport 2018-2017
In the period June to September, there was a 52% increase in Barcelona airport
weather delay with respect to 2017 and 300% increase on 2016. The airport
weather was accompanied by 37 days of one or more weather regulation s (in
total there were 44 weather regulations). In 2017 for the same period there were
42 weather regulations (table 4).
Two factors that may further explain “why” there is significantly more delay in
2018 compared to 2017, despite the minimal increase in regulations are
increased total duration and more flights impacted (Table 5).
Analysis of the two years also shows a difference in the time period when the
regulations were applied: in 2017 delays were mostly in the morning, whilst in
2018 they were mostly in the afternoon / evening. Of course, weather delay in
the network was also significantly worse in 2018 exacerbating the overall
weather delay impacting Barcelona traffic.
Weather regulations amounted to 5,529 flights being regulated, accumulating Figure 34: Weather
123,466 minutes of Barcelona arrival delay, excluding any additional Terminal Types (AENA)
Airspace (TMA) delay, which was 51,322 minutes.
The peak Barcelona weather delays range from 8,000 to 11,00 0 minutes of delay, for example,
impacting between 220 and 356 arrival flights in peak delay. Fortunately only one of the peak delays
corresponded to a busy weekend.
With flights impacted by both Network and Barcelona weather regulations, flight rotations suffered
further from reactionary delay. Additional performance deterioration would have been experienced
from ATC using control techniques to manage air traffic acute complexity created by aircraft deviating
to avoid severe weather, to reduce traffic loading on controllers so they can manage non-standard
and safety critical situations.
As can be seen in figure 34, the main types of weather causing delay were Cumulus Nimbus (CB)
and Thunder Storms (TS) both of which require aircraft to deviate around or h old before departure.
These techniques include:
“Miles-in-trail” which is a form of en-route holding achieved by increasing separation between
aircraft, to provide additional space to manoeuvre aircraft around storms as well as reducing
the simultaneous number of aircraft in a sector to increase safety and reduce workload.
“Traffic stop” simply stopping departures for example, to create “respite” and a reduction in
the number of aircraft in a given volume of airspace.
Additional “track miles” (vectoring aircraft around storm areas), and
“Ad hoc airspace holding” (holding patterns created by ATC when there are too many aircraft
in a given airspace) used by ATC to manage severe traffic disruption and controller workload
due to weather avoidance.
Whilst the weather impact on arrival flights is primarily Barcelona regulation, departure flights were
primarily impacted by ATFM Network delay.
From an airline perspective, weather regulation resulted in flight delays, diversion and cancellation,
reactionary delay, disrupting their daily schedule.
An initial analysis of the 44 weather regulations at Barcelona that were applicable from June to
September 2018 compared the actual duration of each regulation and its activation time with the
TAFs and METARs registered at the same date (figure 35 example). The average daily wind based
on METAR information was also considered.
Whilst this analysis provides an initial overview, a deeper investigation is needed to clarify the impact
of other factors impacting the application of weather regulations (i.e. upper winds, pilot reports, etc.),
based on the available evidence.
The analysis permits the following high level observations:
There is inconsistency in the application of the 44 weather related regulations applied
during the summer with the forecast and actual meteorological reports, observed by
comparing TAF / METAR data and the 44 weather regulations (Figure 35 is an example
of the 3rd June).
ATC was similarly affected with operations disrupted and regulations needed to reduce ATC
complexity and ensure safety.
It is likely that poor weather will continue to be an issue in future years, considering current evolution
of weather patterns. ATC, as in other countries, uses forecast information to decide on future t raffic
flows and understandably is conservative when applying regulation.
Understanding a weather forecast, being able to better predict evolution of weather and an accurate
outcome, and to have direct and immediate access to meteorological forecasting expertise to support
analysis is now critical for Barcelona Flow Managers (FMP) and Tower Supervisor staff.
A SMART approach (Specific, Measurable, Attainable, Realistic and Timely) to accurately address
regulation is essential to avoid unnecessary and overly cautious regulations. This requires new
techniques and expertise.
ENAIRE has embraced this need and is planning to deploy advanced capabilities in 2019 to move
towards SMART regulation and reduce unnecessary regulation which is extremely costly to Airlines.
The measures include:
Contract with EARTH Networks to provide predictive tools to identify direction, duration
and evolution over time of storms in the vicinity of Barcelona. This will directly support a
SMART approach to weather regulation although there will be a learning period in
summer 2019, and
AEMET Forecaster staff being located in the Area Control Centre to directly support and
advise ATC
These are important and welcome changes.
Another issue was the lack of communication between Airlines, ENAIRE and AENA on bad weather,
the likely impact and the measures to be proposed. Lack of communication made it extremely
difficult for airlines to plan their actions often resulting in crisis situations. This is dealt with in section
5.3.2 where communication is discussed in more detail
Short Term
[M16] Weather Prediction Tools, Direct Meteorology Forecaster Support and SMART
Regulation
As described above, ATC is naturally cautious when implementing weather regulations due to the
lack of supporting information and decision support tools on likelihood of occurrence, weather
severity, evolution and duration. This can lead to overcautious regulations and occasional
unnecessary regulation with an associated high cost to airlines.
It is recommended that ENAIRE deploy the weather prediction tools and AEMET meteorology
forecaster support as planned. ENAIRE should ensure that their weather regulation process is
updated, ensure staff are fully trained in the new tools, have clear procedures for AEMET and
ENAIRE staff to work together and have clear SMART regulation decision making criteria covering
how weather regulation will be deployed, justified and reviewed.
For this to be successful, AEMET should fully support ENAIRE.
This recommendation is expected to improve the understanding of forecast weather phenomenon
and help to support SMART regulation, optimising the use of weather regulation and leading to
reduced weather delay.
ENAIRE should consult and explain the changes, with AENA and the main Barcelona airlines to
ensure full visibility, understanding and build confidence of stakeholders.
Airlines have indicated that they are willing to take a limited amount of risk on diversion and delay to
avoid regulation. ENAIRE should fully understand their position and consider how this might be
incorporated into their SMART weather regulation proceses, whilst making it clear to stakeholders,
that in all cases, safe operations remain the top priority for ATC.
Communication
Communicating weather disruption to airlines, AENA ground handling and other stakeholders is
fundamental!
This should be a normal and continuous communication, including the need for regulation, its
likelihood, applicability, duration etc. and must be a systematic process in Barcelona.
Whilst communication is strongly linked to the above recommendation, it has a wider application
than weather regulation so is discussed in section 5.3.2.
Long Term
Understanding SMART regulation will require an in-depth analysis of weather and regulation data.
The use of big data and machine learning techniques could be applied to support weather regulation
decision making based on historical data and real time data.
EUROCONTROL would welcome the opportunity to work with ENAIRE using Barcelona weather
Regulation as a study Use Case with a view to developing Weather Regulation decision support
capability for FMP and ATC Tower Supervisors, based on historic weather, regulations and results.
This study would cover a wider analysis of the applied procedures, the regulations applied and why,
and the impact of the actions taken leading to lessons learned and possible guidance. It should
include an in-depth analytics “big data” study to assess the benefits of applying machine learning
techniques to provide decision support to weather regulation.
This study would provide guidance for a similar approach to SMART regulation in general.
Summary
It is clear that Barcelona was significantly impacted by industrial action in the network and particularly
in Marseilles Area Control Centre (6 days in June 2016). Impact of Marseilles Industrial Action (14%
of overall delays in Barcelona), ATC Staffing and Capacity delays in June alone, affected 70% of
arrivals to Barcelona.
In effect, Barcelona is “captive” to Marseilles issues. Of the total of Industrial Action, ATC Staffing
and Capacity ATFM delays generated during the reference summer period, 40% of the related
Marseilles delay directly impacted Barcelona.
The “losers” in this unfortunate situation are European citizens and the airlines that serve them.
Airlines were required to re-route around the affected airspace when possible, re-plan and cancel
flights to a significant cost, including costs attributable to EU Regulation 261 on Passenger Rights.
As an example, Vueling alone quoted its approximate additional costs in Q2 and Q3 2018 to cover
the performance issues in Barcelona (including operational costs) were in excess of 50 million euro.
Unfortunately, there are few remedies that can be applied by ENAIRE and AENA and Barcelona is
a hostage to circumstances. However, airlines need to be aware of the potential and have scenario
based plans ready to activate in the event industrial action impacting their operations are announced
in summer 2019.
European organisations, including EUROCONTROL Network Manager and the States involved
should consider the possibility of defining preferential routings that airlines can flight plan to avoid
areas generating major delay due to Industrial Action, with clearly ide ntified levels of service, to
reduce the impact on International traffic.
This could be a pre-emptive and coordinated action in preparation for possible Industrial Action in
summer 2019
Recommendations
Short Term
The industrial action was outside of Spanish jurisdiction, nevertheless, it is important that the cost of
delay due to such action is clearly identified and communicated to at the political level to ensure full
awareness to all European actors and organisations.
[M17] Airline Pre-Defined Scenarios to Mitigate Industrial Action
Industrial action in Marseilles severely impacts airlines operating out of Barcelona (and Spain in
general) leading to costly re-routing, when feasible, and cancelations. During such actions, the only
options available to airlines are flight planning around the affected area or cancelling flights and re-
scheduling passengers where possible.
Airlines need to be aware of the potential and have scenario based plans ready to activate in the
event industrial action impacting their operations are announced in summer 2019.
It is recommended Barcelona based airlines develop operational scenarios to avoid the impact of
industrial action in 2019, including the possibility of reducing flights through and defining preferred
re-routing options around, the affected airspace. These scenarios should be discussed with ENAIRE
and the Network Manager so they can be coordinated with the Air Navigation Services likely to be
involved, and preferential routings agreed in anticipation.
This recommendation is expected to ensure that airlines, authorities, the Network Manager and
ANSPs are fully aware of the actions to take and services to put in place in the event of further
Industrial Action in Summer 2019. It will support an optimisation of fleet use and facilitate greater
predictability of daily schedules.
Awareness should be part of the communications processes in Barcelona airport so that any
declared industrial action identified by the Network Manager is quickly and clearly communicated to
all stakeholders. Where necessary, common planning can be defined and actions to mitigate the
impact raised by ENAIRE to the Network Manager to facilitate their successful implementation.
The actual roster planning for Barcelona Area Control Centre and Tower is performed by the local
Head of Human Resources Planning Department in Barcelona.
As a result of the above methodology for capacity planning, the roster planning for operational staff
suffers the same buffers and related inefficiencies. Furthermore, the labour agreement currently in
place is considered obsolete, inflexible and therefore does not meet the need of Barcelona Area
Control Centre (which will be the same for other operational Centres in Spain) . This obviously further
aggravates the effects of the inefficiencies mentioned above.
The resulting rigidity of the allocation of shifts within the strict 5/3 roster framework is another main
contributing factor. The operational shifts themselves are fixed and cannot easily be changed despite
the fact that they are not adapted to the current traffic patterns in Barcelona.
Some tactical rostering is done manually to mitigate the effects but without the benefit of effective
resource support tools.
As a consequence, staff are regularly required to work overtime shifts, whereby the planned 5/3
rotation is changed into a 6/2 rotation. The effects of this with regard to the upcoming Fatigue Risk
Management regulations have not been assessed in detail.
The rigidity of the current 5/3 roster limits the ability to accurately match staffing to demand, and
constrains the greater flexibility in rostering which is required and desired. To achieve such changes
will, however, require national coordination and negotiation with the social partners.
Lack of staff availability and rostering flexibility in Barcelona has resulted in:
The need to collapse sectors, despite increasing demand;
Staffing gaps between evening and night shifts;
An impact on the ability to train new staff, and
Lack of operational expertise to support operational improvement projects.
ENAIRE is committed to add 420 new
Controllers to its staff up to 2025 (taking into
account retirements, leave and active
reserve). This will entail a net increase of
employees by 21.3% when compared to
2017, that is, from 1,974 Controllers to
2,394.
For Barcelona this represents a net increase
of 96 additional Controllers planned up to
2023, an increase on 2017 of 32.2%.
This takes account of retirements and
provides an opportunity to review staff
training and ATC qualification policy, looking Figure 38: Planned Annual Staff Increase
towards optimisation through specialisation of Controllers according to business needs, as
discussed below.
Summary
There is a perceived staff shortage especially in the Barcelona Area Control Centre.
EUROCONTROL considers that there are obvious opportunities for optimising the resource
management processes both short and long term, and that, critically, there might be an issue of lack
of staff availability rather than just a problem of the actual number of staff.
This has been exacerbated by a lack of recruitment, staffing allocation rules as well as an unbalanced
age pyramid of operational staff. There is a challenge to have sufficient staff allocated during peak
traffic period, when office staff with current validations are required to provide back-up and
operational experts are not released to support performance improvement projects.
However, this shortage of staff availability could, for a large part, be mitigated through application of
up-to-date, efficient demand based processes deployed through a new and flexible rostering
scheme.
These demand based processes would be rooted in an in-depth post operational analysis of all data
relevant to the staff planning, thereby ensuring that staffing is accurately targeted towa rds the
predicted demand, rather than being a result of an outdated and inefficient roster framework such
as the current 5/3 system.
An additional prospect is the effect of the current ENAIRE training and rating strategy where staff
are trained to obtain all 3 licenses (tower, approach and en-route). This is a time consuming and
costly process which should be assessed in detail with regard to cost, benefit and opportunity for
staff to specialise. Many European ANSPs have evolved their training and rating strategy to
specialised qualification to fit with business needs.
The effort required for these mitigations to be realised should, however, not be underestimated.
EUROCONTROL’s experience is that the required dialogue with social partners needs careful
preparation as the changes have significant social impact.
Recommendations
Short Term
In the short term, even minor changes to the current shifts may offer opportunities for significant
improvements in sector opening (e.g. between evening and night shifts).
Nevertheless, it is recognised that such minor changes to the shifts may be seen as a change to the
existing labour agreement, and that it may not be possible to negotiate such changes locally in
Barcelona, as labour agreements are nationwide with the social partners.
An assessment should be made as to whether the current system of training staff for all 3 licenses
(tower, approach and en-route) is the best and most cost-efficient solution, or whether a higher
degree of specialisation would offer increased staff availability.
[M18] Post-Operational Staffing Analysis
The challenge of recruitment, staffing levels and the 5/3 rostering scheme are a national process
and linked to historical agreements. With increased demand, an aging works force and the need for
greater and more agile business practices, current proceses are considered to be inefficient and
outdated by staff, social partners and ENAIRE management.
A future agreement should be well informed with the impact of current practices and should be
monitored with enhanced post operations analysis. Such analysis is used today in Maastricht Upper
Area Centre.
In alignment with [M21] Enhance, Focus and Deepen ATC Post Operational Analysis, it is
recommended that ENAIRE widens the current post-operational analysis to include an in-depth
review, specifically aimed at analysing the data and factors important for the staff planning processes
(e.g. optimum sector opening, hourly sector allocation, actual working time on position versus
available working time, and actual sector loads versus declared loads).
This recommendation is expected to define the most accurate Sector Opening Table (SOT) for the
future. This SOT should be accurately staffed according to the current set of rules until new
agreements are reached through negotiation for an enhanced and demand based staffing and
rostering system.
Long Term
[M19] Implementation of a Flexible Rostering Scheme
The current 5/3 rostering scheme is costly, inefficient, lacks flexibility and is no longer able to adapt
to increasing traffic demand.
It is recommended that ENAIRE implement a flexible demand based rostering scheme that at the
same time satisfies the upcoming regulation for Fatigue Risk Management Scheme (FRMS).
This will entail the definition, negotiation and implementation of a new basic shift roster whereby the
planning would not be constrained by a fixed 5/3 basic rotation, but rather subject to more flexible
allocation of shifts, targeting an adequate opening of sectors to meet the predicted traffic demand.
This recommendation is expected to offer increased staff efficiency, freeing up resources in order to
address the current staffing shortfall during peak traffic periods and in the late evening.
The increased staff availability would also offer opportunities in terms of freeing up operational
resources for participation in project related activities.
It is EUROCONTROLs experience that changes to working conditions in general, but especially
changes to shift rosters, has a significant impact on staff and as a result attracts widespread attention
from the social partners. It is therefore recommended that ENAIRE revisits its social dialogue
platform to ensure it is prepared to host such discussions/negotiations between ENAIRE corporate,
the regional/local units and the staff represented by the social partners.
EUROCONTROL welcomes the opportunity to support ENAIRE, with its experience of implementing
a similar scheme in the Maastricht Upper Area Centre (MUAC).
This would include support in the advance preparatory work of ensuring the existence of a suitable
social dialogue platform, as well as the actual establishment, negotiation and subsequent
implementation of the best fit flexible demand based rostering scheme .
Whilst the average number of sectors opened was equal to 2017, the Network Operations Plan
(NOP) declared sector openings for Barcelona Area Control Centre were not always delivered.
It was identified that during peak traffic, en-route and Terminal Airspace sectors were regulated to
manage excessive demand.
The result of the Barcelona Terminal Manoeuvring Area being regulated impacts both Barcelona
arrival and departing flights.
Barcelona En-route and Terminal Airspace are complex airspace structures, especially considering
the proximity of Bordeaux and Marseilles FIR and Balearic Island airports.
Controllers face challenges to integrate Barcelona arrival traffic flows, ensuring initial sequence
development and descent profiles in preparation for arrival procedures.
Departures from Barcelona to France airspace are integrated into traffic flows by Barcelona
Controllers before transfer at single exit points for Bordeaux and Marseilles before transfer of control.
The proximity of the French FIR boundary results in updated boundary estimates for Barcelona
arrivals being sent too late resulting in a negative impact on the Arrival Manager, requiring manual
interaction. A possible solution could be to use the Flight Update Message (FUM) from A-CDM is a
potential “stop-gap” solution.
Another possible solution could be to carry out an evaluation to ascertain if EUROCONTROL’s B2B
web service flight data output are sufficiently accurate to be used in the AMAN.
In Terminal Airspace complexity is further increased due to the interaction of Barcelona and Girona
arrival and departure traffic, with Girona traffic managed by the same sectors controlling Barcelona
traffic. Furthermore, a number of sectors operate at capacity when the airport is operating in
“easterly” configuration.
During the implementation of the “BRAIN” airspace change, airspace complexity increased, and
capacity was reduced to facilitate the transition. This is further discussed below. On a positive note,
BRAIN related delays will not be present in 2019 and the resulting implementation will reduce the
complexity of Terminal Airspace operations, smoothing traffic sequencing and increasing
predictability.
Summary
Barcelona Terminal Airspace and Airport were impacted by both Network and local delay regulations
during periods of excessive demand. This delayed both arrival and departure flights when regulation
was used to manage the excessive demand.
Challenges in airspace design and staffing also mean that the NOP proposed sectors were not
always delivered as planned, with an adverse impact of ATC Capacity.
As discussed earlier, the proximity of the French airspace boundary and a single transfer point
creates problems for Barcelona to integrate Barcelona and Balearic island departures into Spanish
traffic flows towards France and to create separate sequences for Barcelona arrivals and Balearic
island destination traffic.
Solutions to these issues have been developed and are detailed in recommendations [12] Implement
Bordeaux Barcelona Boundary Transfer Point NATPI Agreement, [14] Dynamic Sector Volume
Allocation
The proximity of the French boundary also has a negative impact on the arrival management system,
as discussed in sections 2.2 and 5.1.2 with a potential solution proposed in recommendation [M09]
Improved Boundary Update Message for AMAN.
The implementation of BRAIN airspace changes led to extended regulation a s the new procedures
“bedded in” resulting in contributing to 14% of the overall delay in Barcelona during summer 2018.
However, this was a “one off” issue and benefits from BRAIN are expected in 2019.
Recommendations
5.2.5 Environment
Top View
From June to end September 2018, Total Network ATFM delay due to Environment decreased from
91,459 minutes to 74,187 minutes, compared to 2017. This represents a decrease of almost 20%
for the reference period
There was a similar trend in Barcelona Airport and TMA with 36,452 minutes of delay in 2018, down
from 46,680 minutes in 2017. A 22% improvement.
Barcelona environmental issues are specifically related to noise, constraining runway operations.
The restrictions are based on agreements between the airport and local communities.
Noise restrictions apply 24 hours a day with more stringent procedures and reduced movement rates
(regulated to between 26 and 18 arrivals per hour, depending on the hour) applied through a night
time configuration which is operational between the hours of 23:00 and 07:00 (local time)
As presented in the chapter describing Barcelona Airport Context, parallel independent runway
operations are not used and the preferential runway configuration is westerly. All wide body
movements that are unable to use the departure runway (25L / 07R) operate a non -preferential
departure from runway 25R. Under certain conditions, these movements a re recorded as
environmental delay.
During the change from and to the runway night time configuration (arrival traffic on runway 02 and
departures on runway 07R) there are occasions when the change induces environmental delay. This
can be exacerbated when there is an accumulation of reactionary delay late in the evening that
overlaps with the reduced night time capacity. This is recorded as environmental delay.
Whilst there is sufficient capacity to cater for normal night schedule traffic with some buffer, this is
quickly absorbed by reactionary delay impact. There is a capacity buffer between slot allocation (24
arrivals per hour at night) and ATC capacity (up to 30 arrivals per hour on runway 02).
However, during summer 2018 there was a significant amount of reactionary delay (up to 80 minutes
per flight) that resulted in late arrival traffic being impacted by night time capacity reduction. This
can be seen in figure 44.
The impact of Environment on runway operations is discussed extensively in section 2.1 and 5.1.1.
Summary
Noise and ecological environmental issues constrain Barcelona airport, significantly reducing
flexibility and opportunity for growth.
Whilst the most constraining impact of noise is the required use of preferential runway configurati ons,
there is also a reduction in night time capacity, effective between 23:00 and 07:00.
The Environmental delay recorded is due to regulation to reduce traffic during the transition from day
capacity to night capacity and the associate change to the nigh t time runway configuration. This
change is an operational challenge with no buffer to accommodate the difficulty to achieve the
change by 23:00.
Recommendations
There are no additional recommendation in addition to those already proposed in section 5.1.1.
Nevertheless, EUROCONTROL suggests that AENA, supported by DGCA, revisit the current local
noise constraints together with local population stakeholder groups to adjust the night time
configuration to between 2300 and 0600 local time. This would enable t he day configuration, with
associated increased capacity, to be used for the first wave departures, without changing
configuration during the interaction of first departure and arrival waves.
Table above summarises and compares the number of regulations per type for the summer period
June to September in 2017 and 2018. Whilst the increase in the number of regulation s for the period
year on year is not dramatic, the delay increase is.
Also, the Network operates on the basis of the “worst” regulation applicable to a flight plan route
being the applicable regulation. With all ANSP operating to this rule, there is a significant level of
unexpected cause and effect or “Network effect.”
Perhaps more importantly, ATC will naturally be cautious when applying a regulation, in most cases
defining the regulation on the basis of worst case scenario to ensure safe and efficient ATC.
As previously discussed, ATC Capacity regulation was identified by ENAIRE as an opportunity to
reassess the need for systematic application of regulation and to ask the question, “what if no
regulation was applied”.
An in-depth study of the application and impact of regulations should be undertaken by ENAIRE to
understand regulation interactions and the actual processes used to identify opportunities to further
reduce or apply SMART regulation, for example, opportunities not to apply regulation, or to avoid
interacting regulations, or to identify inconsistent process.
A number of studies have been undertaken in the past by EUROCONTROL and there is work
ongoing in SESAR supported by ENAIRE which could bring longer term benefits.
Summary
There is an opportunity for ENAIRE to assess the use of regulation, in particular weather related
regulation, to define a SMART regulation approach that will reduce the impact of regulations.
Whilst the use of regulation is being addressed at Network level, it will still be an issue in 2019.
A-CDM should be assessed to identify improvements to reduce the number of updates.
One approach to improving the lack of respite may be through addressing scheduling at a lower level
of granularity. This is being tackled by ENAIRE with a proposal to move to hourly capacity
scheduling.
Recommendations
Long Term
[M20] SMART Regulation Study
The use of regulation is being question due to a significant increase in the use of regulation in the
network. The historic data available on application and result of regulation provides an important
opportunity to understand better the cause, effects and unknown Network influences of regulation.
It is recommended that ENAIRE undertake an assessment of the application and impact of
regulations to understand regulation interactions and the actual processes used to identify
opportunities to reduce or apply SMART regulation.
This recommendation is expected to provide insight, guidance and improved procedures used by
the FMP and Tower Supervisor when applying a regulation. The potential of big data and machine
learning assessments to inform guidelines on probability of occurrence, duration and severity of a
regulation based on historical data should be considered.
A number of previous studies and new work by Maastricht and EUROCONTROL Network Manager
can be made available to ENAIRE. Furthermore, work ongoing in SESAR is supported by ENAIRE
which could bring quick wins.
EUROCONTROL would welcome the opportunity to work with ENAIRE on this subject. The
proposed study on SMART Weather Regulation discussed in section 5.2.1 would be one concrete
opportunity.
One of the key processes is the ‘Plan-Do-Check-Act’ (PDCA) performance cycle. When applied
correctly the PDCA cycle enables an organisation to continuously monitor and improve the service
delivered through accurate performance reporting and assessment against the agreed targets.
Once the ‘Plan’ is established it is put into action through the ‘Do’-part of the cycle. In the ‘Check’-
part the post-operational analysis processes assess in detail to what extent the ‘Do’-part has
delivered the performance foreseen in the ‘Plan’-part.
In case of discrepancies between the planned and delivered result, the performance management
processes will identify the underlying causes for the inadequate performance and subsequently
establish corrective actions to be implemented as part of the updated ‘Plan’ for the following period.
A healthy performance management system produces periodic performance reports as well as
dashboard type of views that in a glance allow the user to ascertain the level of performance
achieved against the targets set (figure 40).
These reports are ideally used at multiple levels of the organisation in various forms, mainly to allow
the decision makers to take informed decisions, but also to promote the overall performance based
culture in general.
Recommendations
5.3.2 AENA
AENA undertakes a significant level of performance post analysis covering multiple aspects of the
airport operation. It was not clear to what degree AENA shares this analysis and uses it to influence
airport performance, including that of ENAIRE and the Airline stakeholders.
AENA recognise that the 1st departure wave is not efficient in terms of stand allocation. AENA is
responsible for gate allocation and has worked with the main carrier to better allocate contact stands
to alleviate the challenge of aircraft position. As aircraft-to-destination allocation was frequently last
minute, ensuring gate positions were known in advance is important to efficient boarding and
achieving Target Off Block Times (TOBT) used in A-CDM.
AENA recognises the need to improve the service provided to aircraft operators and a new contract
is under development to address gate staff (e.g. air bridge operators) availability during peak periods
There is a unique opportunity for AENA to establish a performance “governance” position to discuss,
federate and align airport Key Performance Indicators that can be understood and shared by all
stakeholders in driving a common Barcelona airport performance
Given that Barcelona is both a complex airport and ATC operational environment, it is essential to
manage strategic and tactical issues in a manner that ensures all stakeholders are informed and
motivated to play their role.
Considering the dramatic increase in delay experienced by the airpor t in summer 2018 when the
airport was frequently operating close to the limits of its current capabilities, systematic, clear and
immediate communication becomes an essential tool.
Best in class airports now operate regular daily briefings to ensure that a ll airport stakeholders are
aware of the strategic and tactical issues affecting the airport and the plans and opportunities to
mitigate and maintain efficient operations. It is a challenge yet an essential business need.
Communication Issue
A shared concern identified during discussions with stakeholders was the challenge to ensure that
meaningful communication was established, especially during periods of reduced performance.
Ad-hoc conversations do occur, when time permits, to clarify issues such as ATFM regulations or to
inform on “crisis” related matters. However, communication is not systematic and often subject to
staffing and time availability, and constrained by a lack of confidence in available information.
There is also a perception amongst stakeholders, that information disclosed may be used in a
negative manner. This is a trust issue, which can be addressed through communication.
There is a wealth of information available on Network and local issues, either of a strategic nature
(future work on the airfield such as tunnelling under a runway that will impact schedules) or weather
regulations (information on the severity, duration of the regulation, that can be used by airlines to
improve their planning and reduce the impact).
Top performing airports (Heathrow, Gatwick, Amsterdam ..) and other operational entities (Network
Manager) use open communication (such as daily early morning conference calls) as a performance
tool, bringing visibility on issues, agreeing actions to jointly manage airport performance whilst
building trust.
Barcelona is now at a point where trust and communication across operational pillars is critical to a
common approach to achieve performance improvement and growth, making best use of available
resources and infrastructure, to cater for growth.
In the most severe of situations, advance knowledge of a significant event can also be communicated
to stakeholders to agree a reduction in demand to reflect predicted available capacity, thus promoting
a level of stability in operations when disruption starts. This is currently done at Heathrow and
Amsterdam where percentage reductions are agreed in a collaborative and voluntary manner
between airlines.
Communication Opportunity
Barcelona should develop a communication process to ensure regular and timely briefings with its
stakeholders (ENAIRE, Airlines, Handling Agents, Maintenance, Slot Coordination and other
stakeholders impacting day to day operations).
Two areas should be considered:
1. Daily performance briefings -
To share a common view on the daily schedule and issues such as weather, network
regulations, strike action, work in progress etc. that is likely to require close cooperation and
a coordinated approach to mitigations to ensure acceptable performance is achieved.
Recommendations
Short Term
[M23] Airport Performance Communication Process
Today, there are strategic performance briefings undertaken in Barcelona on future issues and
developments, often on a bi-lateral basis but not always achieving full understanding or buy-in. This
should be a continuous conversation designed to ensure full awareness of all issues impacting the
future airport performance, extending to common KPI that can be jointly monitored.
However, there is no systemised tactical communications on daily airport performance, expected
downfall and planned mitigations. This leads to different stakeholders taking diverse actions when
a crisis occurs or are unable to plan sufficiently to manage the p erformance down fall.
There is a perception of lack of trust. Stakeholders are not confident in disseminating information,
concerned that divulging information may lead to it being used in a negative manner.
It is highly recommended that AENA implement a daily briefing through conference calls to inform
and discuss with all stakeholders, on critical performance events such as system outage,
infrastructure availability, work in progress, expected capacity challenges, Network issues, bad
weather and associated weather regulations.
The daily briefing should include any future calls to review, refine and update or take decisions based
on latest information, as different scenarios evolve. Typically, weather issues in the summer would
be discussed as well as any lack of resources impacting performance.
For some briefings, AENA should delegate responsibility to the appropriate organisation.
The ENAIRE SMART regulation process for weather events should be used in the daily briefing and
updates. This will provide all airport stakeholders with full understanding and visibility on regulation
such as weather, including probability, severity and duration thus helping airlines to efficiently plan
their daily schedule.
In periods of severe capacity reduction, this communication process could be extended to airlines
voluntarily agreeing to implement schedule reductions to ensure a minimum of predictable service.
This recommendation is expected to ensure greater awareness of how each day is expected to
unfold, helping all stakeholders’ better plan resources and take early action to manage expected
performance shortfalls, and to work together to maintain or revert to normal operations.
This process is deployed in Heathrow, Amsterdam and Brussels airports.
Long Term
[M24] Implement an Airport wide Performance Management Processes
It would appear from discussions with stakeholders during the study assessment interviews that a
“silo” mentality exists with stakeholders primarily focused on their own issues and actions with limited
consultation and buy in to a bigger goal.
Barcelona airport has operational, technical and infrastructure challenges impacting day to day
operations and certainly constraining future growth. This can be addressed by stakeholders working
more closely together to optimise existing scarce resources and agreeing on common goals and
actions to drive future performance.
It is recommended that AENA develop a common overarching airport performance management
process to proactively drive Barcelona Airport performance together with all key stakeholders.
The airport wide performance management system should be integrated through an airport
performance dashboard, using agreed KPIs and processes, to ensure systematic and regular
monitoring of performance and proactive strategic and tactical responses to performance shortfall.
The governance of this rests naturally with AENA, providing an opportunity to drive common Airport
performance KPI through a management lifecycle of ‘Plan, Do, Check, Act.’
This recommendation is expected to provide a vehicle for continuous improvement, where
stakeholders can openly discuss issues, assess past performance and agree common performance
based improvement actions to drive the overall performance of the airport.
This approach to Total Airport Management is currently being addressed in SESAR through a
common performance dashboard. Early examples are deployed in Heathrow, Zurich and Munich .
EGB*
OTHERS
EGPHARR
EGSSARR
LE
LFR
LFB
EGKKARR
EG*
EGKBARR
EGGWARR
EGTT
EGD*
EGPTLA
Europe. Figure 42 shows an example of
EGSHE
EGP*
EGK*
EGL*
arrival airport delay, being the greater delay,
contributing to reactionary.
A - Accident/Incident C - ATC Capacity
G - Aerodrome Capacity I - ATC Ind Action
Delay was exacerbated by an overlap of M - Airspace Management O - Other
inbound and outbound waves, with delayed P - Special Event
T - ATC Equipment
S - ATC Staffing
W - Weather
departures from wave 1 returning late,
increasing traffic demand in the second
Figure 42: Example of Regulations (leading to reactionary)
inbound wave.
This knock-on scenario continued through the day and ultimately led to delayed flights arriving late
in the evening when implementation of the night configuration results in a reduction in capacity,
leading to a worsening delay situation.
Figure 43 shows reactionary delay during the reference 90,0
period. By 11:00 local time 15 minutes of reactionary
delay affected each flight of the three main LCC 80,0
operators in Barcelona. By 20:00 this delay reaches 28
70,0
minutes per aircraft then reaches more than 80 minutes
per flight after 23:00 when capacity is reduced, for the 60,0
remaining delayed returning flights.
50,0
Wave 1 Criticality
40,0
With 39% of total movements, Vueling has a majority
share of wave 1 so a good performance at the beginning 30,0
of each day is critical.
20,0
Some issues that challenge a good Wave 1 performance
have been identified and these are discussed here. 10,0
Aircraft Parking: The first wave of the main carrier’s departures from terminal 1 was hindered by
aircraft availability after night maintenance compounded by previous day reactionary delay and also
by an apparent lack of understanding where aircraft were parked.
The main carrier provide their next day programme around 20:00 local time the evening prior to the
day of operation. AENA provides the carrier with the final stand allocation list at 23:00 local time.
However, maintenance issues resulted in many changes during the night with the perception that
the main carrier’s Operations Centre (AOC) were either unaware of the aircraft gate or they did not
take the gate allocation into account in their subsequent planning update.
Furthermore, reporting on progress and estimating aircraft availa bility following maintenance,
together with gate allocation, has negatively impacted timely planning of aircraft -to-destination.
Issues with knowing where aircraft are parked or when aircraft maintenance will be completed, timely
matching aircraft-to-destination and ensuring a good gate distribution so that similar time departures
do not pose boarding and pushback issues were important to ensuring a successful Wave 1
AENA also identified that the main carrier
suffered from return-to-stand occurrences
during the summer period, with some aircraft
returns occurring after take-off.
These returns in the summer period was 48
aircraft compared to 51 returns from all other
companies.
AENA proposed to support the carrier to
improve first wave departures by towing
aircraft likely to stay longer than planned to
remote stands to reduce complexity.
Further AENA improvement proposals are
focused on terminal facility management Figure 44:The main carrier’s aircraft Returns to Parking ©AENA
including passenger queuing and “air bridge”
management for the first morning arrivals, to reduce delay accumulation
AENA has also invited the carrier’s staff to observe and understand its gate allocation process to
help improve aircraft readiness and aircraft-to-destination matching processes. Extending this to
have these staff collocated in the AENA Airport Operations Centre during critical planning periods in
the summer could provide greater awareness to both AENA and the carrier and should be explored.
Furthermore, an in-depth discussion between AENA and the main carrier to fully understand the
issues and challenges of Wave 1 preparation could identify other actions that AENA could undertake
to support improvements in it’s morning Wave 1 operations. This would benefit all airlines.
Other issues impacting early morning performance included:
Repositioning aircraft from maintenance to the gate is difficult due to conflict with the first
departure wave;
Gate allocation for delayed aircraft is further impacted as the main carrier is reticent to accept
towing of aircraft at night to remote stands, proposed by AENA to facilitate better stand
planning/allocation, to ensure an optimal gate allocation for first wave departures;
There were also late crew changes happening after boarding has commenced resulting in
reduced punctuality;
The increasing number of Passengers with Reduced Mobility (PRM), whilst a positive factor,
also slows boarding processes. This merits further analysis to improve processes for PRM.
The main carrier is aware of the summer operational challenges and in 2018 had taken action to
increase the number of back-up aircraft in Barcelona to seven, the number of crews on stand-by,
especially on critical days, to ensure that flight cancellations due to crew rest times are limited and
increased Ground Handling resources, to cope better with operational turnaround issues.
In this example the flight programme of the aircraft involved builds up reactionary delay throughout
the morning rotations, made worse by an additional delay on the flight segment EBBR – LEBL
(Brussels to Barcelona) which was delayed an additional 30 minutes.
This delay moved A/C 1 into the Barcelona night time reduced capacity period (after 23.00 hours)
and resulted in the aircraft returning to base with an accumulated delay of 100 minutes!
Summer 2018 was very busy for the main carrier with aircraft being fully utilised. If aircraft are late
out of maintenance (discussed above) or suffer a technical issue at the beginning of the day, the
knock-on effect may be that the aircraft will suffer from delayed rotations throughout the day.
Some maintenance or technical issues can mean that an aircraft is not available for that day’s
operation. Consequently, the airline may choose to use “stand-by aircraft if available or aircraft that
were already fully utilised to operate the routes of the aircraft suffering from the above issues with
the consequence that initial delay to, or cancellation of, some flights is inevitable.
Considering typical tight block times operated by low cost carriers, the airlines should analyse their
summer schedules, taking account of the cost of reactionary delay and lack of resilience, to
understand the need for changes by, for example, building recovery periods into its daily schedule.
In response to expected issues in summer 2019, and as an example, Vueling proposes to increase
its Barcelona block times by 1.6%.
Turnaround times used by the airline were also assessed. In general, during the summer, the target
duration of turnaround were not an issue during significant delay so further reduction in these times
would be unlikely to be achieved or bring any benefit to the airline.
As an example, for summer 2019, Vueling plans:
No increase in overall number of aircraft based at Barcelona;
Increase in the number of back-up aircraft in Barcelona to 9 (possibly 11 if new aircraft
delivery is on time) and 12 Network-Wide;
Increase the number of crews on stand-by, especially on critical days, to ensure that flight
cancellations due to crew rest times are limited. This increase will be 10% in Barcelona, with
crews protected from redeployment by an overall increase of 30% in Vueling’s network. ;
Further increase in Ground Handling resources, to cope better with operational issues
(Vueling will triple the extra-manpower buffer agreement with its handling agent).
Increase Operational Control Centre (OCC) staff by 21%, to improve the management of
days suffering from high levels of disruptions and enhance service to meet crew and
passenger needs.
Airport Collaborative Decision Making
The Barcelona A-CDM process, whilst accepted as essential by airlines, was seen as less than
optimum and inflexible, especially during periods of significant network delay. Increases in Network
regulation resulted in many changes to TSATs (so called “dancing regulations”).
Airline schedules should be analysed to identify if periods for recovery should be added. Without
resilience in their schedules and the expectation that network delay is unlikely to dramatically
improve in summer 2019, there is a high probability of significant levels of reactionary delay.
It is perceived by airlines that A-CDM was inefficient in summer 2018. A-CDM should be assessed
to identify improvements that can be made in time for summer 2019.
The procedure for obtaining and on occasion, led to aircraft missing their TSAT. The proposed data-
link departure clearance needs to be available in 2019 to resolve this issue otherwise a back -up
frequency should be made available.
Recommendations
6. RECOMMENDATIONS CONSOLIDATED BY
STAKEHOLDER
6.1 Prioritised Recommendations
GREEN colour coding is used to highlight priority recommendations considering their impact on
delay reduction or management, the urgency to start preparation for implementation such as data
capture and analysis, and quick wins.
Short Term
[M01] Performance Based Runway Occupancy Time (ROT) Management
[M07] Enhanced BRAIN procedures
[M08] Trial of “Non-Application of Terminal Airspace Regulation (sector DDI)
[M12] Implement Bordeaux Barcelona Boundary Transfer Point NATPI Agreement
[M16] Weather Prediction Tools, Direct Meteorology Forecaster Support and SMART
Regulation
[M17] Airline Pre-Defined Scenarios to Mitigate Industrial Action
[M18] Post-Operational Staffing Analysis
[M21] Enhance, Focus and Deepen ATC Post Operational Analysis
[M23] Airport Performance Communication Process
[M25] The main Barcelona carrier and AENA Gate, Night Maintenance and Daily Schedule
Coordination
[M26] LCC Operators Summer Delay Preparations
[M27] Airline Summer Schedule Resilience Analysis
[M29] Departure Clearance DCL
Long Term
[M02] Implement Day-Time (Mixed Mode) Independent Parallel Runway Operations
[M03] Hourly Based Custom Slot Capacity
[M06] Implement ROCAT, Runway Occupancy Categorisation
[M19] Implementation of a Flexible Rostering Scheme
6.2.2 ENAIRE
Short Term
[M01] Performance Based Runway Occupancy Time (ROT) Management
It is recommended that ENAIRE develop a performance based runway occupancy time management
process together with airline stakeholders, to safely minimise ROT, agreeing, monitoring and
reporting on ROT and use of preferential runway exit points, per aircraft type.
[M07] Enhanced BRAIN procedures
It is recommended that ENAIRE further systemise BRAIN approach procedures by refini ng, testing
and if acceptable, publishing, the amended approach procedures, incorporating:
1. Predefined and systematically applied speed profiles, typically 210KTS downwind, 180KTS
base leg and 160KTS on final to 4NM;
2. Reduced level bands from 4000ft to 2000ft where level banding is applied;
3. Consistent use of “distance to touchdown” guidance from Controllers to support pilots in
managing the flight profile and aircraft energy thereby avoiding unstable approaches
4. Continuous use of the procedure with no “ad-hoc” direct clearances in low traffic, to reinforce
and ensure pilot and controller proficiency in the procedures;
5. A rigid approach to use of standard phraseology to avoid non-local Pilot confusion, and
6. Incorporate BRAIN into the published STAR procedures, so there is only one reference for
approach.
[M08] Trial of “Non-Application of Terminal Airspace Regulation” (sector DDI)
It is recommended that ENAIRE explore what happens if regulation is not systematically applied, in
particular to sector DDI, when traffic predictions suggest excessive demand, as part of an approach
to SMART regulation.
[M12] Implement Bordeaux Barcelona Boundary Transfer Point NATPI Agreement
It is recommended that Barcelona and Bordeaux complete the procedure design and implement the
agreed additional transfer point, NATPI, in time for summer 2019. The additional actions to improve
traffic distribution on the new transfer points and the existing points should be formalised in a new
Letter of Agreement between Barcelona and Bordeaux Area Control Centres.
[M16] Weather Prediction Tools, Direct Meteorology Forecaster Support and SMART
Regulation
It is recommended that ENAIRE deploy the weather prediction tools and AEMET meteorology
forecaster support as planned. ENAIRE should ensure tha t their weather regulation process is
updated, ensure staff are fully trained in the new tools, have clear procedures for AEMET and
ENAIRE staff to work together and have clear SMART regulation decision making criteria covering
how weather regulation will be deployed, justified and reviewed.
[M18] Post-Operational Staffing Analysis
In alignment with [M21] Enhance, Focus and Deepen ATC Post Operational Analysis, it is
recommended that ENAIRE widens the current post-operational analysis to also include an in-depth
review, specifically aimed at analysing the data and factors important for the staff planning processes
(e.g. optimum sector opening, hourly sector allocation, actual working time on position versus
available working time, and actual sector loads versus declared loads).
[M21] Enhance, Focus and Deepen ATC Post Operational Analysis
In alignment with [M18] Post-Operational Staffing Analysis, it is recommended that ENAIRE further
enhance, focus and deepen the post-operational analysis capability, both ENAIRE corporate and
locally in Barcelona, to fully understand the performance levels of the current capacity and resource
management processes.
[M29] Departure Clearance DCL
It is recommended that ENAIRE deploy the data-link based Departure Clearance solution, DCL, in
time for summer 2019 and if not possible, ensure a second frequency and associated ATC Departure
Clearance delivery procedure is deployed. Airlines must make maximum use of this facility once
implemented.
Long Term
[M03] Hourly Based Custom Slot Capacity
It is recommended that ENAIRE deploy their proposed hourly “custom slot capacity scheme” in time
for 2020, that maximises the availability of ATC Capacity and Staffing resources during periods of
peak demand and creates troughs of reduced capacity, that responds to airlines needs whilst
recognising that a respite period is required to recover from reactionary delay.
[M04] Performance Based Standard Instrument Departures (SIDs)
It is recommended that ENAIRE implement SIDs based on RNAV with diver ging splits of 21° that
aircraft establish on when turning left after climbing through 500ft, and which will permit ATC to fully
optimise runway 25L departure separations.
[M06] Implement ROCAT, Runway Occupancy Categorisation
It is recommended that ENAIRE implement ROCAT at Barcelona following the deployment of
performance based runway occupancy time (ROT) management and the agreement to reduce
minimum radar separation to 2.5 nm, both of which are pre-cursors to ROCAT.
[M09] Improved Boundary Update Message for AMAN
It is recommended that ENAIRE identify another data source to update the Barcelona arrival
manager with arrival estimates other than those sent following the Bordeaux advanced boundary
information. A more accurate estimate could be taken from one of the A-CDM milestone times such
as the Flight Update Message sent by the Network Manager, or an appropriate estimate from the
SACTA ATC system.
[M10] Reduced Minimum Radar Separation
It is recommended that ENAIRE implement a minimum radar separation of 2.5 NM in time for
summer 2019, to reduce the impact of non-preferential wide-body departures from runway 25R. This
will require a detailed local safety case to justify the improvement to the National safety regulator.
6.2.3 AENA
Short Term
[M23] Airport Performance Communication Process
It is highly recommended that AENA implement a daily briefing through conference calls to inform
and discuss with all stakeholders, on critical performance events such as system outage,
infrastructure availability, work in progress, expected capacity challenges, Network issues, bad
weather and associated weather regulations.
[M28] A-CDM Health Check and TOBT Updating by Airline / Ground Handler
[M28b]It is recommended that AENA with ENAIRE undertake an A-CDM “health check” supported
by EUROCONTROL, to identify the airline issues, explain why these occur if it is due to a non -optimal
airline / ground handler process, or take action to resolve the issues, if feasible in the A-CDM system,
benefiting from EUROCONTROL knowledge of other airport A-CDM operations.
Long Term
[M02] Implement Day-Time (Mixed Mode) Independent Parallel Runway Operations
It is recommended that DGCA and AENA revisit current local noise constraints together with local
population and municipal stakeholder groups to implement independent parallel and mixed -mode
runway operations between 0700 and 2300 local time.
[M05] Runway 25L Extension
It is recommended that AENA extend runway 25L by at least 500m to the east of the current
threshold, thus providing additional TORA, suitable for wide-body departures.
[M24] Implement an Airport wide Performance Management Processes
It is recommended that AENA develop a common overarching airport performance management
process to proactively drive Barcelona Airport performance together with all key stakeholders.
6.2.4 AIRLINES
Short Term
[M17] Airline Pre-Defined Scenarios to Mitigate Industrial Action
It is recommended Barcelona based airlines develop operational scenarios to avoid the impact of
industrial action in 2019, including the possibility of reducing flights through and defining preferred
re-routing options around, the affected airspace. These scenarios should be discussed with ENAIRE
and the Network Manager so they can be coordinated with the Air Navigation Services likely to be
involved, and preferential routings agreed in anticipation.
[M25] The main Barcelona carrier and AENA Gate, Night Maintenance and Daily Schedule
Coordination
It is recommended that the main carrier work more closely with AENA on Terminal 1 gate
management allocation, with Ground Handling and Aircraft Maintenance to be fully aware of night
aircraft maintenance tracking and progress reporting, a nd use non-contact stands when
maintenance is known to be late, to solve gate position and aircraft -to-destination allocation issues
to improve the probability of a successful first morning departure wave.
[M26] LCC Operators Summer Delay Preparations
It is recommended that Airlines implement their plans in time for summer 2019. Other airlines
operating in Barcelona should be equally prepared, using the example of Vueling’s actions,
measured to their operation.
Annex 1: ABBREVIATIONS
Abbreviations Definitions
ACC Area Control Centre
APT Airport
ASMA Arrival Sequencing and Metering Area
Abbreviations Definitions
PDCA Plan-Do-Check-Act
Abbreviations Definitions