Preface
Preface
This report has been prepared after getting different theoretical and
practical training in Construction of Bridge and Highway of Six Lane
Eastern Peripheral Expressway (NH No. NE-II) Package IV from 03-
06-2017 to 18-07-2017 Under ASHOKA BUILDICON PVT LTD. in
reference to my collage letter dated 30-05-2017 of Training &
Placement Officer for ALLENHOUSE INSTITUTE OF
TECHNOLOGY ROOMA, KANPUR (UP). The training was divided
in seven different sections of the Directorate.
• I- GIRDER
• VUP
• PUP
• BOX CULVERT
• ROB
• CONCRETEROAD
• DRAINAGE,
• INSPECTION UNIT
The process of training from my point of view was excellent for each
section was very useful for Civil Engineering Student with very
limited resources and time schedule. There are many things in the
Directorate on each subject which can be learnt from regular training
and proper guidance.
A little knowledge which I could get from this training, I am trying to
reproduce some of them in following pages. Any error in making
deliberations may please be ignored.
INDEX
S. No CONTENT PAGE
NO.
1 Introduction
2 Detail of the project and its route
3 Project Status and update Water Treatment
Process
4 Methodology and its component
5 Scope of the Project
6 Major construction activity
7 Machine used for road construction
8 Methodology of carrying out structural concrete
in bridges and culverts
9 Transporting and placing of concrete
10 Major Components
• I-girder
• VUP
• PUP
• BOX CULVERT
• ROB
• CONCRETE ROAD
• DRAINAGE
11 Inspection Unit
INTRODUCTION ABOUT EASTERN
PERIPHERAL EXPRESSWAY:-
See also: NH 24: Wider highway set to unlock real estate potential in
the NCR
Numbers of structure in this project:-
"There are a total of 390 structures in this project, out of which
• 2 major bridges are on river Yamuna & 1 major bridge on river
Hindon and Agra
Canal.
• There are eight interchanges,
• four flyovers,
71 vehicle underpasses,
• Six road-over-bridges, etc.
The project work has been divided into six packages -
SCOPE OF PROJECT
1. Topography Survey
2. Traffic Surveys, which included Classified Weekly Volume Counts,
Turning Movement Counts, Origin - Destination Survey, Plate
Registration Survey, Axle Load Survey, Speed & Delay Survey.
3. Road & Bridge Inventory Survey
4. Pavement Condition Survey
5. Bridge Condition Survey
Environmental Survey, which included Vegetation and Fauna Survey
i. Concrete dumpers
ii. Powered hoists
iii. Chutes
iv. Buckets handled by cranes
v. Transit truck mixer
vi. Concrete pump
vii. Concrete distributor booms
viii. Belt conveyor
ix. Cranes with skips
x. Tremies
TRANSPORTING, PLACING & COMPACTION OF
CONCRETE
Transportation of concrete is carried by pumps. Pipe lines from the
pump and to the placing area should be laid out with minimum bends.
Concrete at the time of pouring should have temperature in between 5
to 40 degree Celsius. It shall be compacted to its final position within
30 minutes of its discharge from the mixture. Concrete shall be
poured in horizontal layer of compacted thickness of 300 mm. Fresh
concrete shall not be placed against concrete which has been in
position for 30 minutes unless appropriate construction joints are
provided.
Placement of concrete shall not be carried out when the day
temperature exceeds 40 deg.
Celsius.
A. Formwork
Only steel formwork shall be used. All bolts shall be countersunk. The
use of approved internal ties or plastic spacer shall be used. Structural
steel tubes are used as support for forms and form shall have
minimum thickness of 4mm ply.
(B) Construction Joints
Construction joints shall be provided as minimum as possible and
shall be as per drawings. Laitance shall be removed before fresh
concrete is cast. The surface shall be roughed enough not to dislodge
the coarse aggregate. Concrete may be brushed with stiff brush in its
green stage at the location of construction joint. Fully hardened
concrete shall be treated with mechanical tools to remove the laitance.
(C) Curing
Water curing shall be done with water specified in section 1000 of
MORT&H exposed surface of concrete shall be kept continuously in a
damp or wet condition by pending or by covering with a layer of
sacks, canvas, Hessian or similar materials and shall be kept
constantly wet for a period of not less than 14 days from the date of
placing the concrete.
MAJOR COMPONENTS:-
• I-GIRDER:-
The I girder is a I shaped girder which is used where used in the place
where the u girder cannot be placed due to curve radius or the
unavailability to put the u girder in place. The I girder can be upto
30meters in length different height as desired. The height varies as 1
1.2 and 2 meters. Also the numbers of stands vary as per the height.
The number of strands vary from 14 in 1 meter,, 29 in 1.2 meter and
45 in 2 meter height girder. The casting procedure is given in the
below paragraphs: first of all the reinforcement caging is prepared the
reinforcement is of high strength steel (FeSOO) the casing is done in
three zones namely zone a,b,c. the different zones have different
spacing and different diameter of bars are used.
Second the reinforcements are tied together with the help of steel
wires. Each bar is tied to its proximity bars so that the bars are not
loose.
Third the sheathing pipe is introduced in the between the
reinforcement layers and the stands are passed in them. A stand is a
group of cables twisted together to provide greater strength.
Each strand consists of 6 cables twisted together. Concreting process
in which ready mix concrete is poured in the reinforced cage which is
fitted in the casing. The concrete is made available from the nearby
batching plant which has two plants of 60 and 30 cubic meter
capacity. The mixture is transferred from the transit mixture truck of 6
cubic meter capacity to the u girder casting area.
After concreting the mixture is left for setting so that the mixture can
attain its desired strength in the specified number of days. The mix is
of MS5 strength. Also some admixtures are used in the mix
proportional (2% of the total weight of mix). After the setting process
is completed and desired setting time is over the girders are
transferred to the desired place for placing.
Fig: - I-girder
Process of I- Girder
1. Label alignment
2. Cleaning of bed
3. Shuttering oil
4. Reinforcement cage & lowering
5. Sithing pipe fixing (cable duck profile fixing)
6. Outer (vertical shuttering fixing)
7. Plumb and alignment
This cost can typically be offset through the long life cycle of the
pavement. Concrete pavement can be maintained over time utilizing a
series of methods known as concrete pavement restoration which
include diamond grinding, dowel bar retrofits, joint and crack sealing,
cross-stitching, etc. Diamond grinding is also useful in reducing noise
and restoring skid resistance in older concrete pavement.
Fig: - Placing of concrete