Method Statement

Uploaded by

naresh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
92 views16 pages

Method Statement

Uploaded by

naresh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

9. Applicator's Method Statement.

Khalifa Bin Zayed Street


Development, Al Ain
Project Client Consultant Contractor

Project: Khalifa Bin Zayed Street Development, Al Ain

Method Statement
for
Installation of Electrical Cabinet

Ref. BAS-OTK-KBZ-MS-0034-00

Revision Date Prepared by Reviewed by Endorsed by Approved by Status


04-12-
00 Consultant
2024

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 1 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

Contents
1. PURPOSE ........................................................................................................................... 4

2. SCOPE ................................................................................................................................ 4

3. LEGISLATION AND CODE OF PRACTICE ............................................................................... 4

4. REFERENCES ...................................................................................................................... 5

5. DEFINITIONS ...................................................................................................................... 5

6. RESOURCE ......................................................................................................................... 5
6.1 MATERIAL AND THEIR APPROVAL .......................................................................................................................... 5
6.2 TOOLS, EQUIPMENT AND MACHINERIES: ............................................................................................................... 6
6.3 SUBCONTRACTOR APPROVAL ............................................................................................................................... 6
6.4 SHOP DRAWING APPROVAL.................................................................................................................................. 6

7. RESPONSIBILITIES .............................................................................................................. 6
7.1 SR. PROJECT MANAGER...................................................................................................................................... 6
7.2 CONSTRUCTION MANAGERS AND PROJECT ENGINEERS ............................................................................................. 7
7.3 TECHNICAL ENGINEER ........................................................................................................................................ 7
7.4 QA/QC ENGINEER ............................................................................................................................................ 7
7.5 SITE ENGINEER.................................................................................................................................................. 7
7.6 QUANTITY SURVEYOR......................................................................................................................................... 8
7.7 HSE MANAGER ................................................................................................................................................ 8
7.8 HEALTH SAFETY & ENVIRONMENTAL ENGINEER (HSEE) ........................................................................................... 8
7.9 HSE OFFICER ................................................................................................................................................... 9
7.10 NURSE/FIRST AID STAFF ................................................................................................................................. 10
7.11 SURVEYOR ................................................................................................................................................... 10
7.12 SITE SUPERVISORS ......................................................................................................................................... 10
7.13 FOREMAN .................................................................................................................................................... 10
7.14 DOCUMENT CONTROLLER ............................................................................................................................... 10

8. DETAILED METHODOLOGY ............................................................................................... 11


8.1 PREPARATION OF WORK: .................................................................................................................................. 11
8.2 DELIVERY, HANDLING, AND STORAGE OF MATERIALS ............................................................................................. 11

9. INSPECTION AND TEST PROCEDURE ................................................................................. 12


9.1 INSPECTION PROCEDURE:.................................................................................................................................. 12
9.2 TEST PROCEDURES:.......................................................................................................................................... 12

10. HSEW REQUIREMENTS:.................................................................................................... 13


10.1 HEALTH SAFETY REQUIREMENTS: ..................................................................................................................... 13
10.2 EMERGENCY PROCEDURE ................................................................................................................................ 14

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 2 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

10.3 ENVIRONMENTAL REQUIREMENTS: ................................................................................................................... 14


10.4 HOUSEKEEPING ............................................................................................................................................. 14

11. INSPECTION AND TESTING PLAN (ITP) .............................................................................. 14

12. RECORDS: ........................................................................................................................ 15

13. DISTRIBUTION: - .............................................................................................................. 15

14. ATTACHMENT .................................................................................................................. 15


14.1 INSPECTION AND TESTING PLAN (ITP) ............................................................................................................... 15
14.2 INSPECTION CHECK LIST (ICL) .......................................................................................................................... 15
14.3 RISK ASSESSMENT (RA) .................................................................................................................................. 15

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 3 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

1. PURPOSE
This method statement is applicable for defining the sequential procedures, ensuring the safe
execution of Installation of Electrical Cabinet as needed in the project. It adheres to contract
requirements, incorporates hazard and safety precautions, and systematically conducts Quality
Assurance/Quality Control activities, with thorough inspection and documentation of the work.

2. SCOPE
This method statement pertains to the Installation of Electrical Cabinet outlined in the project,
encompassing the following:

1. Delivery and Handling


2. Electrical Cabinet

3. LEGISLATION AND CODE OF PRACTICE


1. Al Ain City Municipality (AACM) Regulations and Guidelines.
2. Standard Specification- ADM Landscape and Public Realm by Department of Municipalities and
Transport (DMT), Abu Dhabi City Municipality.
3. ADQCC: Abu Dhabi Quality and Conformity Council
4. All applicable Local Regulatory Authority requirements and regulations.
5. UAE Labor Code of Practices.
5.1. OSHAD SF - CoP - 02.0 - Personal Protective Equipment
5.2. OSHAD SF - CoP - 03.0 - Occupational Noise
5.3. OSHAD SF - CoP - 03.1 - Vibration
5.4. OSHAD SF - CoP - 04.0 - First Aid and Medical Treatment
5.5. OSHAD SF - CoP - 08.0 - General Workplace Amenities
5.6. OSHAD SF - CoP - 09.0 - Workplace Wellness
5.7. OSHAD SF - CoP - 11.0 - Safety in the Heat
5.8. OSHAD SF - CoP - 14.0 - Manual Handling and Ergonomics
5.9. OSHAD SF - CoP - 17.0 - Safety Signage and Signals
5.10. OSHAD SF - CoP - 21.0 - Permit to Work
5.11. OSHAD SF - CoP - 22.0 - Barricading of Hazards
5.12. OSHAD SF - CoP - 25.0 – Driver Fatigue Prevention
5.13. OSHAD SF - CoP - 29.0 –Excavation
5.14. OSHAD SF - CoP - 36.0 - Plant and Equipment
5.15. OSHAD SF - CoP - 51.0 - Powered Lift Trucks
5.16. OSHAD SF - CoP - 53.0 - OSH Management During Construction Work
5.17. OSHAD SF - CoP - 54.0 - Waste Management

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 4 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

4. REFERENCES
1. Project Specifications
2. IFC Drawing and Shop Drawings.
3. Material Approvals / Manufacturer Recommendation
4. BOQ
5. Approved Project Quality Plan
6. Approved HSE Plan
7. No Objection Certificate
8. Permit to work.

5. DEFINITIONS
Definitions used within this document is detailed within the text shall have the meanings indicated
below unless otherwise clearly indicated by context of the use.

1. Project : Khalifa Bin Zayed Street Development, Al Ain


2. Employer : Department of Municipalities and Transport (DMT)
3. Engineer : Otak International
4. Contractor : Basatin Landscaping LLC
5. PQP : Project Quality Plan.
6. MS : Method Statement.
7. ITP : Inspection & Test Plan.
8. RA : Risk Assessment
9. ITL : Independent Testing Laboratory.
10. WIR : Work Inspection Request.
11. MIR : Material Inspection Request.
12. HSEW : Health, Safety, Environment and Welfare.
13. IFC : Issued for Construction.
14. SD : Shop Drawing.

6. RESOURCE
6.1 Material and their approval
All materials used on site have to be approved prior to starting any work. The following list is a
summary of key materials to be used for the activities.

List of Materials:
1. Aluminium Tube Frames
2. Aluminium CNC Cut Screen
3. Screws and Fastener
Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.
MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 5 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

4. Accessories

6.2 Tools, Equipment and Machineries:


1. Site Survey Equipment
2. General Hand Tools
3. Hand gloves
4. Drilling Machine
5. Spirit Level
6. PPE

6.3 Subcontractor approval


External organization, executing part works on behalf of contractor, based on a specified (sub)
contract with approved prequalification.

6.4 Shop drawing approval.


The shop drawings will be prepared based on the issued contract drawings, which will include all
necessary additional information and details to enable proper execution of the works. Shop
drawings submittals are to be complete with respect to dimensions, design criteria, materials,
connections, bases, foundations, anchors, etc. and will be accompanied by technical and
performance data (as necessary) to fully illustrate the information in the drawings.

7. RESPONSIBILITIES
7.1 Sr. Project Manager
§ Direct all construction operations, responsible for skilled person and staff members, while
responsible for direction, leadership, and control.
§ Responsible for strategic planning.
§ Responsible for cost control and budget to avoid overruns.
§ Create and manage the master construction schedule for more than one project.
§ All operational issues, involving, people, skills, plant, financial.
§ Responsible for effectiveness, and efficiency of staff, plant, materials, logistics, Procurement,
subcontractor, management.
§ Client relationship & Staff relationships, grading, training, recruitment, and terminators.
§ Coordinates all facets of construction to ensure overall performance, with regards to budget,
planning, technical, and value engineering.
§ Manage staff development and ensure performance standards.
§ Ensure efficient use of human resources, and grading of staff, to increase or decrease current
positions.
§ Mange subcontractor performance.
§ Responsible for site cost implementation records and monitoring of set budget.
§ Ensure QA-QC Standards are set to be implemented and met.
§ Ensure HSE Standards are set, implemented, and met.
Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.
MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 6 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

§ Overall responsibility or site safety.

7.2 Construction Managers and Project Engineers


§ Implement and maintain a successful completion of the work.
§ Communicate this Method Statement to his subordinates.
§ Provide his subordinates with the information they need to carry out their responsibilities.
§ Enforce the application of this document once it is approved.
§ Stop all unsafe work activities.
§ Ensure the Health and Safety of the personnel on the site.
§ Ensure that the requirements of the Project Specifications and relevant ITP are followed and
implemented during construction.
§ He shall coordinate with Engineer / Employer authorities and arrange the necessary arrangements
and to ensure that proper control measures are enforced for performing the activities as per
Engineer / Employer expectations.

7.3 Technical Engineer


§ Check tolerance, dimensions, and fabrication feasibility of designs and works with Engineers to
resolve problem.
§ Adjust current drawings and recommend changes based on their understanding and knowledge of
the project.
§ Follow project schedules and meet project due dates.
§ Meet all project specifications and formatting within the company principles.
§ Work closely to Project managers and project engineers to make sure that the design is precise,
also to ensure and that contract responsibilities are met.
§ Review and interpret Client specifications.

7.4 QA/QC Engineer


§ Maintain all quality records properly documented.
§ Conduct inspections and monitor the required tests.
§ Determining and reporting any non-conformance to the QC Manager.
§ Checking compatibility between production processes, test procedures and the applicable
documentation through review and circulation of the technical and administration document
related to the various activities.
§ Ensuring all personnel are fully aware of all the quality requirements and application for all quality
documents as relevant to their discipline.
§ Ensuring appropriate supervision for all work activities enabling quality related operations to be
effectively covered.
§ Coordinate with the Independent Testing laboratory representative so that all test is carried out as
required by specification and records as per the Quality Control Plan.
§ Stop all unsafe and substandard work activities.

7.5 Site Engineer


§ The Engineers are responsible for the implementation and execution of day-to-day activities in a
safe manner.

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 7 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

§ He shall arrange the manpower, equipment and materials required for the implementation of
activities to meet the target schedule in quality and safe manner, coordination with HSE officers,
QC Engineers and progress the involved tasks in accordance with specifications, method statement
and approved Risk Assessment.
§ He shall maintain project schedule by monitoring project progress, coordinating activities, resolving
problems.
§ He shall raise WIRs as per approved ITPs.

7.6 Quantity Surveyor


§ Price/forecast the cost of the varied materials needed for the project.
§ Prepare tender documents, contracts, budget, bill of quantities and other documentation.
§ Track changes to the design and/or construction work and adjusting budget projection accordingly.
§ Measure and value the work done on site.

7.7 HSE Manager


§ Responsible for the Company's OSH implementation
§ Liaise with Department Managers in implementation of OSH Management System and issues safety
directives accordingly.
§ Monitors, reviews, and advises the Project Manager on OSH policies implementation and results of
the OSH audits.
§ Makes sure OSH roles, responsibilities, policies, plans, and objectives are communicated to all
relevant personnel.
§ Monitors OSH training requirements of personnel and coordinates in arranging internal and
external training.
§ Receives client's latest OSH standards and procedures and advises the Project Manager to revise
Company procedures accordingly, if necessary.
§ Preventing injury to personnel and damage to plant and equipment.
§ Determine the cause of any accident or dangerous occurrence and recommend means of
preventing recurrence.
§ Promote awareness of injury prevention and damage control to all levels of employees.
§ Supervise the recording and analysis of information on injuries, damage, and loss, assess accident
trends and review overall safety performances.
§ Keep up-to-date with recommended codes of practices and new safety literature; circulate
information applicable to each level of employee.

7.8 Health Safety & Environmental Engineer (HSEE)


§ HSE Engineer coordinate with the Project Manager and Report to HSE Manager
§ Prepare all site safety documents / reports and submit to Client / Consultant HSE Management.
§ Investigate and advise on any legal requirements affecting safety, health, and welfare.
§ Coordinates with the concerned project engineer for performing the task risk.
§ assessment for the project activities as identified.
§ Identify potential hazards on new contracts before and during the course of the works, notifying
the site safety organization of these and any additional fire precautions that may be required.
§ Participate in the weekly/monthly HSE meeting.
§ Assist accident /incident investigation.

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 8 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

§ Conducts periodical inspection of facilities, machinery, vehicles, equipment, tools, tackle and
firefighting facilities at the project site to ensure that validity of them and to ensure the compliance
with the regulations.
§ Collaborate and advise on any changes in legislation or client procedure to be conducted /
communicated by managing engineer and or supervisor.
§ Monitor the action points at the site project and provides necessary advice to Engineers, Foreman,
and workers during the site inspection.
§ Participates in the appropriate implementation and installation of the safety devices and
equipment at all locations, in coordination with the Project Engineer
§ Prepare all site safety documents / reports and submit to Client / Consultant HSE Management.
§ Conducts HSE induction training for all new project staff onsite as needed.
§ Prepare Monthly HSE statistics.

7.9 HSE Officer


§ Ensure the pre-task meeting shall be conducted by engineer and or supervisor before starting the
day-to-day activities.
§ Ensure that HSE related documents, procedures, forms, and checklist are in place to ready to use,
including risk assessment.
§ Advise on the prevention of injury to personnel and on the prevention of damage to property, plant
& equipment, and other resources.
§ Identify potential hazards on new contracts before and during the course of the works, notifying
the site safety organization of these and any additional fire precautions that may be required.
§ Conduct safety meetings with site personnel and subcontractors.
§ Foster safety awareness in all tradesmen and supervisors
§ Investigate further improvement in existing safe working methods.
§ Investigate and advise on any legal requirements affecting safety, health, and welfare.
§ Ensure provision and use of protective clothing and equipment and its use.
§ Ensure suitability from a safety viewpoint, of new and hired plant and equipment, and validity of
all appropriate test certificates.
§ Determine the causes of any accidents or dangerous occurrences and recommend means of
preventing recurrence.
§ Supervise the recording and analysis of information on injuries, damage, and production loss,
assess accident trends and review overall safety performances.
§ Supervise the recording of all employees’ safety training records.
§ Have absolute power to stop work on site if they consider a dangerous situation exists or could
exist and cannot be remedied immediately.
§ Identify the training need and the competency factor of the site personnel.
§ Conduct training as per program and maintain attendance records.
§ Fully coordinate with internal and external auditors to carry out the audits.
§ Initiate follow-up audit activities in order to verify audits and record the implementation and
effectiveness of corrective and preventive action taken.
§ Report the result of internal site inspections, corrective and preventive actions and the overall
effectiveness of the system to the HSE Manager, with a copy to the concerned head of the section.
§ To conduct site safety induction.
§ Set a personal example.
§ Implement the “No Smoking” rule at workplace.
Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.
MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 9 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

7.10 Nurse/First Aid Staff


§ Giving assistance in case of accidents.
§ Instituting, filling-in and updating a sanitary file for each employee.
§ Co-operating with site project manager and HSE Engineer for the implementation procedures for
worker’s safety and health.
§ Inspecting first aid facilities
§ Verifying the food hygiene and cleanliness in construction site
§ Informing timely site HSE Engineer concerning cases of epidemic infection or poisoning
§ Frequent site visits to brief workers at site on current weather conditions and its health hazards

7.11 Surveyor
§ The Surveyor will be responsible for all survey activities, control points, recording of survey data as
well as control and calibration of survey instruments.

7.12 Site supervisors


§ Incorporate HSE instructions in routine orders and see that they are obeyed always.
§ Ensure that all machinery and plant, including power and hand tools, are maintained in good order.
§ Ensure the quality and safety of the work being performed and proper housekeeping.
§ Make the necessary preventive action to minimize the noise production during working hours.
§ Monitor that new employees are adequately trained and supervised always and comply with safety
precautions.
§ Organize the site activities safely and systematically so that work can be carried out as per the
required standard without any impact to workforce, equipment, materials and to the environment.
§ Monitor that the Personal Protective Equipment of the workforce are enough for current work at
hand.
§ Conduct daily "Toolbox Talks” and in advance of any critical work and enforce proper PPEs as per
task.

7.13 Foreman
§ Preparation and execution the works at site as per the approved drawings.
§ Mange the required team at site.
§ Ensure the quality and safety of the work being performed and proper housekeeping.
§ Make the necessary preventive action to minimize the noise production during working hours.
§ Monitor that new employees are adequately trained and supervised always and comply with safety
precautions.
§ Organize the site activities safely and systematically so that work can be carried out as per the
required standard without any impact to workforce, equipment, materials and to the environment.
§ Monitor that the Personal Protective Equipment of the workforce is enough for current work at
hand.
§ Conduct daily "Toolbox Talks” and in advance of any critical work and enforce proper PPEs as per
task.

7.14 Document Controller


§ Leads the Contractor’s Document Controller on proper document numbering as per procedure.
§ Generates transmittal of project technical documents and maintains track of document revisions.
Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.
MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 10 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

§ Monitors and maintains Document Register for all technical documents.


§ Maintain Common access server for easy access of project documents.
§ Monitor and track correspondence of Client and Contractors.
§ Support Consultant Engineers for formatting of documents and subsequent submission to the
client.
§ Responsible for preparing Monthly Progress Report to be submitted to Client.
§ Attending weekly progress meeting and responsible for preparing Minutes of Meeting.

8. DETAILED METHODOLOGY
Following are the step-by-step procedures to be followed for the installation of Storm water Network.

Step-1: Preparation of Work


Step-2: Delivery and handling of materials
Step-3: Installation of Electrical Cabinet

8.1 Preparation of Work:


§ Prior to installation, the supervisor and foreman will verify and ensure that the work area is clean
and safe for carrying out the activities and proper clearance is available from the civil side before
the commencement of works.
§ Related clearance shall be obtained prior to start the installation.
§ Verify that all relevant approved latest revisions of shop drawings, technical submittals,
inspection, and test plans for installation reference. This also includes installation procedures.
Ensure that all drawings are current and marked “APPROVED”.
§ The supervisor and foreman will inspect all the materials delivered to the workplace and ensure
that these are approved materials and for damage or defect. Materials found not to be as per
requirement or with damage or defect will be set aside. These will be properly labeled and
returned to the warehouse. These will also be reported in a Non- Conformance Report.
§ The supervisor and foreman will orient and familiarize all the technicians and labors involved in
the installations regarding the relevant approved shop drawings, technical submittals,
installation procedures and details, acceptance criteria and safety requirements.
§ The designs and execution to be followed as per the approved code of practice.

8.2 Delivery, Handling, and Storage of Materials


§ Before delivery, Fabricated components should be fully protected to ensure the components remain in
good condition until they are ready for installation.
§ All materials for delivery should be verified against the quantity and batch number stated in the delivery
order.
§ Upon delivery on site, the materials should be checked for damages during transportation and that the
delivered materials are in compliance with the specifications. Any damaged or incorrect materials should
be returned to the factory.
§ Delivery of materials should be carefully planned according to the installation schedule so that only the
required quantity of materials is stored on site, where the possibility of damages is higher. Just-in-time
Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.
MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 11 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

(JIT) inventory management system is effective in minimizing unnecessary handling, storage, and
damages to the materials.
§ Proper site storage is important in preventing damages to the components. A suitable storage location
should be Sheltered from weathering and fallen objects and located for ease of material handling and
distribution.
§ Components should be placed on timber bases to avoid direct contact with the floor.
§ In addition, the various components should be arranged according to the installation sequence to
facilitate ease of retrieval, i.e. to minimize searching and unnecessary shifting of material which may lead
to damages.

8.2.1 Installation of Steel Railing

§ The Electrical Cabinet shall be fabricated at the factory as per the approved Shop Drawing.
§ The Electrical Cabinet shall be delivered to the site fully fabricated complete with Framework,
Aluminum CNC Screen and Accessories
§ Mark the locations of the Anchor bolts on the approved location as per the predrilled holes on the
framework.
§ Drill the holes as per embedment length.
§ Position the Electrical Cabinet. Ensure proper alignment, levelness, and plumbness.
§ Secure the Electrical Cabinet with the Approved Anchorage and screws.
§ Once fixed, check the rigidity of the application. Ensure it’s not moving.
§ Clean the installed Cabinet.

9. INSPECTION AND TEST PROCEDURE


9.1 Inspection Procedure:
§ The material received on site shall be inspected by the consultant prior to commencement of
work and the same should be recorded in MIR.
§ Once the Electrical Cabinet are installed, it shall be ensured that they are in compliance with the
approved material, approved Method Statement and it complies with all the reference section
stated in the ITP.
§ It shall be verified that the Gas Cabinet are installed at exact location coordinates as shown in
approved shop drawing or As-built drawing.

9.2 Test Procedures:

9.2.1 Visual Inspection:


§ Begin with a visual inspection of the installed gas cabinet to identify any visible defects,
misalignments, or damage.

9.2.2 Plumb and Alignment Check:


§ Ensure that the grates are plumb and aligned correctly.

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 12 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

9.2.3 Recording and Documentation:


§ Maintain detailed records of the testing process and any issues identified. Proper documentation
is crucial for quality assurance and compliance reporting.

10. HSEW REQUIREMENTS:


10.1 Health Safety Requirements:
1. Activities covered in this method statement shall be carried out in strict compliance with the
requirements of the approved Project HSEW Plan.
2. Job briefing / Toolbox Talk shall be conducted by concerned Charge hand/ Foreman before
starting activity.
3. For safety purpose, provide a safety barrier along the perimeter of the excavated area to
prevent hazards.
4. The area of construction shall be cordoned off properly with all necessary safety measures like
signboards, warning tape, traffic cone, barriers & flashlight etc.
5. Access and egress to trench shall be done.
6. Attention will be given to ensure that the safety of all devices is being used for the job.
7. Experienced worker shall be deployed for operation of all type machine and tools.
8. All the required PPEs such as helmet, safety goggles, hand gloves, overall, safety shoes and ear
plugs shall be used by involved workers.
9. Proper supervision shall be ensured to monitor the work.
10. Appropriate Safety guidelines must be adhered to during all stages of construction activity.
11. Manual Handling training shall be conducted.
12. First aid facilities shall be provided with provision of First Aider/ Male Nurse
13. Accident / incidents will be reported immediately followed by a written report within 24 hours
of the occurrence as per site accident / incident reporting procedures.
14. Proper escape route in case of evacuation shall all be designated, marked, and notified to all
personnel.
15. Work area shall be barricaded as applicable and necessary.
16. Required safety sign boards shall be placed in the area.
17. AACM waste management system to be followed.
18. Access and egress to trench shall be done. Ensure proper coordination with other disciplines so
that all relevant personnel are aware of the requirements. Ensure that a relevant permit to
work is obtained from the appropriate civil contractor, if required.
19. Ensure that the work area is safe and that all constraints on operations have been identified
and necessary precautions have been taken.
20. Welfare Facilities such as drinking water, rest area/ toilets.
21. Safety requirements and precautions, please refer to the approved RA.

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 13 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

10.2 Emergency Procedure


To facilitate the reporting of emergency situations the safety in-charge/Engineer shall arrange for
the following emergency procedure and telephone numbers to be displayed on site and updated
regularly:

Step-1: If a person is injured/need medical assistance, remove the injured person from where
danger still exists and get first aid, do not leave the injured person until help arrives.
Step-2: For major injuries and incidents, call emergency service required and give location and
nature of emergency.
§ Ali Nazir (HSE Lead) - 056 995 7731
§ Ahmed (HSE Officer) - 050 752 7427
§ George (CM) - 056 995 7728
§ Darwin Armada Colete (HSEM) - 055 2991798
§ Aiham Tayar (PM) - 055-2216355
§ Police - 999
§ Ambulance - 998
§ Civil Defense (Fire) - 997
PPE requirement
The following PPEs shall be worn by workers involved:
• Helmet, safety goggles, hand gloves, overall, safety shoes and ear plugs.

10.3 Environmental Requirements:


1. All applicable government requirements and regulations pertaining to environmental
protection and pollution shall be identified and adhered to.
2. Good housekeeping should be followed at all times to prevent the occurrence of accidents and
consequent injuries.

10.4 Housekeeping
Housekeeping of fabrication and installation sites will be done in accordance with the OSHAD, DMT
and project safety manual.

11. INSPECTION AND TESTING PLAN (ITP)


Details particular testing requirements to be undertaken in relation to particular activities in relation
to construction works to ensure contractual quality requirements are achieved and to identify any
non-compliance. Inspections shall be carried out as per ITP approved by the Engineer.

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 14 of 15
Khalifa Bin Zayed Street
Development, Al Ain
Project Client Consultant Contractor

12. RECORDS:
1. Work inspection request approvals.
2. Material inspection request approvals
3. Test reports.

13. DISTRIBUTION: -
Copies of this Method Statement shall be circulated to the following for Information & action.
1. Project Manager. 4. HSE officer.
2. Project Engineer / Site Engineer. 5. Supervisors
3. QC Engineer / Inspector. 6. Foremen.

14. ATTACHMENT
14.1 Inspection and Testing Plan (ITP)

14.2 Inspection Check List (ICL)

14.3 Risk Assessment (RA)

*****************

Document No. BAS-OTK-KBZ-MS-0034 Rev.: Issue: Issued Date: Page No.


MS for Installation of Electrical Cabinet 00 1 04/12/2024 Page 15 of 15