Module5 Design Mix Job Mix
Module5 Design Mix Job Mix
MIX DESIGN
Concrete:
Sand
Gravel
33%
38%
CONCRETE VOLUME
Sand
7%
Portland
Cement
68%
CONCRETE COST
Note:
Cement accounts for most of the concrete raw material cost.
Source: Conference on CONCRETE Art, Science and Technology (BICOL CAST ’98)
Concrete Design MIX:
END
Initial Estimate of Mix Proportions
Selection of
Estimation of water-cement Trial Batch
mixing water and ratio [w/c] or Adjustments
air content
[w/(c+p)]
Steps in Concrete Mix Design (ACI 211.1)
Choice of If slump is not specified, a value can be selected from the given table:
Slump
Table A1.5.3.1. Recommended slumps for various types of construction
Types of Construction Slump
Maximum Minimum
Reinforced foundation walls and footings 75 25
Plain footings, caissons and substructure 75 25
walls
Beams and reinforced walls 100 25
Building columns 100 25
Pavements and slabs 75 25
Mass concrete 75 25
Steps in Concrete Mix Design (ACI 211.1)
Choice of In general, the nominal maximum size should be the largest that
max. size of is economically available and consistent with the dimensions of
aggregate the structure.
Trial batch
Scale the mass or volume down to one mold of
adjustment
s concrete.
Sample Problem for ACI Method:
October 7, 2021
Expectations?
2
ASPHALT MIX DESIGN METHOD
Introduction
PROCESSION STREET
The first recorded use of asphalt as a road
building material was in Babylon around 615
B.C., in the reign of King Naboppolassar.
© www.asphaltpavement.org 5
BRUCE G. MARSHALL
Bituminous Engineer of Mississippi
Department of Highways
6
MARSHALL METHOD OF MIX DESIGN
Overview
8
MARSHALL METHOD OF MIX DESIGN
Overview
VMA
Total Asphalt
Effective
Air Voids Asphalt
Absorbed
VMA Asphalt
Asphalt
Aggregate
Aggregate Aggregate
14
MARSHALL METHOD OF MIX DESIGN
Mix Design Procedure:
AC Select the right materials (asphalt cement and aggregates)
Select design aggregate gradation (blending of aggregates)
G sG b Determine the specific gravity (combined aggregates and AC)
Prepare test specimens (loose and compacted specimen)
GmmGmb Determine specimen height and specific gravity
Density and voids analysis (AV, VMA, VFA)
Marshall Stability and Flow tests
Plot the Test Property Curves
OAC Compute the Optimum / Design Asphalt Content
Evaluate using the Marshall Method Design Criteria
15
© Asphalt Handbook
16
Select the right materials (asphalt cement and aggregates)
17
GRADING RANGES – HOT PLANT MIX BITUMINOUS PAVEMENTS Asphalt - Wearing Course
( Mass Percent Passing Square Sieves, AASHTO T11 and T27 ) Grading D
20
Select design aggregate gradation (blending of aggregates)
CUMULATIVE PERCENT PASSING GRADING D
Sieve Designation
Aggregate “A” Aggregate “B” Aggregate “C” Fillers Total, General
mm (inch)
34 % 41 % 3% % Specifications, %
22 %
19.0 (3/4”) 100 34 - 22 - 41 - 3 100 100
12.5 (1/2”) 91 30.94 100 22 - 41 - 3 97 95 – 100
9.5 (3/8”) 68 23.12 86 18.92 100 41 - 3 86 74 – 92
4.75 (No. 4) 28 9.52 46 10.12 91 37.31 - 3 60 48 – 70
2.36 (No. 8) 9 3.06 32 7.04 73 29.93 - 3 43 33 – 53
1.18 (No. 16) 7 2.38 27 5.94 48 19.68 - 3 31 22 – 40
0.60 (No. 30) 5 1.7 18 3.96 35 14.35 - 3 23 15 – 30
0.30 (No. 50) 3 1.02 8 1.76 20 8.2 - 3 14 10 – 20
0.075 ( No. 200) 1 0.34 3 0.66 5 2.05 100 3 6 4–9
A + B + C + F
21
No. 200 No. 50 No. 30 No. 16 No. 8 No. 4 3/8 " 1/2 " 3/4 "
23
25
26
Specific Gravities of an Aggregate Particle
Vs Apparent Specific Gravity,
Vap
Vpp WS
Vpp - Vap Gsa =
VS 𝜸w
When the total aggregate consists of separate fractions of coarse aggregate, fine aggregate, and
mineral filler, all having different specific gravities, the bulk specific gravity for the aggregate
combination is calculated as follows:
P1 + P2 + . . . + Pn where:
Gsb = Pn = percentage by weight of aggregate ‘n’
P1 P2 Pn
+ +...+
G1 G2 Gn Gn = bulk specific gravity of aggregate ‘n’
28
Preparation of Asphalt Mixture Specimens (ASTM D6926)
Produce a compacted specimen 63.5 ± 1.3 mm in height.
This volume of aggregate will normally weigh about 1,200 g.
1 Pa · s = 1,000 cP
Mixing Temperature 0.17 ± 0.02 Pa · s
Viscosity Test using
Compacting Temperature 0.28 ± 0.03 Pa · s Brookfield Viscometer
31
Temperature, Viscosity,
°C Pa · s
114 0.58
155 0.12
Mixing Temperature,
146 °C
0.28 Pa · s
Min Max Compaction Temperature Range
136 °C 156 °C
0.17 Pa · s
Compaction Temperature, Mixing Temperature Range
133 °C
133 °C 146 °C
Min Max
123 °C 143 °C
Weighing
Aggregates for
Batch Mixes
Prepare
at least three (3),
preferably five (5)
specimens for
each increment of
Weighing aggregates for Heating of alt cement inside the
asphalt content.
batch mixes thermostatic controlled oven
Place the pans in the oven or on the hot plate and heat to a temperature approximately
28 °C above the mixing temperature specified.
Heat the mold assembly and the face of compaction hammer in a water bath or hot
plate at 93 °C to 149 °C.
33
2.384
After compaction, remove the base plate and the paper disks
and allow the specimen to cool at room temperature.
When more rapid cooling is desired table fans may be used,
but not water unless the specimen is in a plastic bag.
37
38
Thickness Determination
68 mm
cm
0.02 mm
65 mm
39
Thickness Determination
0.02 mm
T = 68 mm + 0.58 mm
0.5 mm 0.58 mm
Thickness of S-2 (4.5%)
T1 = 68.58 mm
40
Thickness Determination
Bulk sp gr = A / (B – C)
Bulk volume, cc = (B – C) / 𝝆 Unit weight, pcf = BSG (𝜸water )
𝝆water = 1 g / cc 𝜸water = 62.4 pcf
43
Asphalt
BSG
Content, %
4.5 2.399
5.0 2.453
5.5 2.493
6.0 2.509
6.5 2.508
44
Test Property Curves – Bulk Specific Gravity
45
Note that as the binder content 4.5 7,691.5 1,508.2 8,625.1 2.625
increases, Gmm always
decreases. This is because the 5.0 7,691.5 1,520.4 8,629.6 2.611
percentage of aggregate, which 5.5 7,691.5 1,501.3 8,611.8 2.584
has a higher specific gravity,
necessarily decreases for a unit 6.0 7,691.5 1,518.8 8,619.0 2.569
volume with an increase in the
percentage of binder, which has a 6.5 7,691.5 1,515.1 8,613.2 2.553
lower specific gravity.
A
Bowl in Air Determination: Gmm (actual) =
A+D–E
47
Note: High asphalt absorption maybe due to the Additive ‘Z’ (0.05% dosage)
Saturation of micro pores on aggregate surfaces
49
% Absorbed % Effective
% Asphalt % Aggregate by
Asphalt by weight Asphalt Content
Content by weight weight of mix,
of aggregate, by weight of mix,
of mix, Pb Ps
Pba Pbe
% AC
The air voids, AV, in a compacted (BSG) Air Voids,
by weight Gmm
paving mixture consist of the small of mix
Gmb %
air spaces between the coated
aggregate particles. 4.5 2.625 2.399 8.61
51
4.5 8.61
5.0 6.05
5.5 3.52
6.0 2.34
6.5 1.76
52
Test Property Curves – Air Voids
5.42
53
% PS = 100 – % AC
Bulk S.G. Aggregate, Gsb = 2.762 (Given)
54
Test Property Curves – Voids in Mineral Aggregate (VMA)
Asphalt
VMA, %
Content, %
4.5 17.05
5.0 15.63
5.5 14.70
6.0 14.61
6.5 15.10
55
Pa = 4.0%
Nominal Maximum Particle Size
= 12.5 mm (1/2”) Pa = 3.0%
56
VFA in Compacted Paving Mixture
% AC
The voids filled with asphalt, VFA, is Air Voids, VMA, VFA,
by weight
the percentage of the intergranular of mix
% % %
void space between the aggregate
particles (VMA) that are filled with 4.5 8.61 17.05 49.50
asphalt.
5.0 6.05 15.63 61.29
*excluding the absorbed asphalt.
5.5 3.52 14.70 76.05
57
Asphalt
VFA, %
Content, %
4.5 49.50
5.0 61.29
5.5 76.05
6.0 83.98
6.5 88.34
58
Test Property Curves – Voids Filled with Asphalt (VFA)
59
Stability
dial
Flow
Meter
Immersing compacted Placing specimen in lower
specimens in the water bath. testing head and center
*Point of failure is the maximum load reading obtained. Marshall Procedure,
While stability test is in progress, hold the flow meter Compression Testing Device
(zeroed) firmly and remove as the load begins to decrease. (Loading rate = 51 mm / min)
60
Stability Correlation Rations
61
Marshall Stability
Asphalt Marshall
Content, % Stability, lbs
4.5 2,376
5.0 2,330
5.5 2,400
6.0 2,424
6.5 2,255
63
4.5 % AC 8.8
Asphalt Flow,
Content, % 0.25 mm
4.5 8.8
5.0 10.4
5.5 13.6
6.0 14.4
6.5 16.3
66
Test Property Curves – Marshall Flow
67
68
Selection of Design Binder Content
69
70
Marshall Mix Design Criteria
Light Traffic Surface Medium Traffic Heavy Traffic
Marshall Method Mix
& Base Surface & Base Surface & Base
Criteria Design ESAL < 104 104 < Design ESAL < 106 Design ESAL > 106
*20-year period
Min Max Min Max Min Max
Compaction, number of
35 50 75
blows each end of specimen
5,338 8,006
Stability, N (lb.) 3,336 (750) - - -
(1,200) (1,800)
Flow, 0.25 mm (0.01 in.) 8 18 8 16 8 14
Percent Air Voids 3 5 3 5 3 5
Percent Voids in Mineral
Refer to VMA table
Aggregates (VMA)
Percent Voids Filled with
70 80 65 78 65 75
Asphalt (VFA)
71
Important notes:
• All criteria, not just stability value alone, must be considered in
designing an asphalt paving mix.
• The flow value refers to the point where the load begins to decrease.
When an automatic recording device is used, the flow should be
corrected.
• The upper limit of the flow criteria should be waived when
polymer-modified or rubber-modified binders are used.
• Percent air voids should be targeted at 4 percent and this may be
slightly adjusted if needed to meet the other Marshall criteria.
72
Determining Marshall Flow
No correction is necessary
when using a proving ring
and flow meter, since the
flow meter has been
“zeroed out” on a calibrated
4.00-inch metal disk or
specimen.
73
Asphalt 2.499
ID BSG
Content
5.42 5.65
74
Air Voids – Test Properties of Mix based on…
Asphalt Air
ID
Content Voids
4.0
OAC 2 5.42 % 4.0 %
3.2
5.42 5.65
75
2,401
Asphalt Stability,
ID 2,393
Content lbs
5.42 5.65
Asphalt Flow,
ID
Content 0.25 mm
5.42 5.65
77
*The nominal maximum particle size is one size larger than the first sieve to retain more
than 10 percent.
**Interpolate minimum voids in the mineral aggregate (VMA) for design air void values
between those listed.
78
Marshall Mix Design Criteria
Gradation of Aggregates
Sieve Designation Result Retained
mm in % %
19.0 3/4” 100 0 < 10 %
12.5 1/2” 97 3 < 10 %
9.5 3/8” 86 11 > 10 %
4.75 No. 4 60 26
2.36 No. 8 43 17
1.18 No. 16 31 12
0.600 No. 30 23 8
0.300 No. 50 14 9
0.075 No. 200 6 8
First sieve to retain more than 10 percent
Nominal Maximum Size (One sieve size larger)
Maximum Size (Two sieve sizes larger)
79
Asphalt
ID VMA
Content
Interpolate! 14.83
14.60
AV 3.0% 3.2% 4.0%
Pa = 4.0% 5.42
Pa = 3.2% 5.65
VMA 13% 13.2 % 14%
80
Voids Filled with Asphalt (VFA) – Test Properties of Mix based on…
Asphalt 77.80
ID VFA
Content
5.42 5.65
81
Adjustment is necessary.
Satisfactory complied with the Marshall Method Design Criteria
Use Design Asphalt Content (at 4.0% Air Voids) = 5.42 % by weight of mix
82
Dust to Binder Ratio
Reminders:
• It is necessary to make several trial mixes in order to satisfy the
design criteria.
• When the trial mixes fail to meet the design criteria, it is necessary to
modify or redesign the mix (adjust the gradation of aggregate
blend)
• The aggregate gradation and asphalt content in the final mix must
strike a favorable balance between stability and durability.
• The primary consideration in the design should always be for
adequate stability and maximum durability.
84
References (Primary)
• American Society for Testing and Materials (ASTM) Test Methods
• American Association of State Highway and Transportation
Officials (AASHTO) Test Methods
• Asphalt Institute (1989). The Asphalt Handbook: Manual Series
No. 04. Lexington, KY 40512-4052 USA
• Asphalt Institute (2014). Asphalt Mix Design Methods: Manual
Series No. 02 (7th ed). Lexington, KY 40512-4052 USA.
• Department of Public Works and Highways (2013). Standard
Specifications for Highways, Bridges and Airports.
• Transport Research Laboratory (2002). Overseas Road Note 19:
A guide to the design of hot mix asphalt in tropical and subtropical
countries. Crowthorne, Berkshire, RG45 6AU, United Kingdom.
85
COMPREHENSIVE TRAINING ON
MATERIALS TESTING TECHNOLOGY
Any
Questions?
END OF PRESENTATION
86
Accreditation – The procedure by which the
DPWH gives formal recognition, under duly
established rules and regulations, that a company is
competent to operate an asphalt/Portland cement
concrete batching plant and supply DPWH project
requirements, or a private testing laboratory,
laboratories of Provincial Engineering Offices, and
universities/colleges that can perform the testing of
materials for Government infrastructure projects.
Portland Cement Concrete Batching Plant - an
assembly of mechanical and electronic equipment
where a satisfactory mix proportion of water, cement,
aggregates and admixtures (if necessary) are
accurately measured and weighed to produce concrete
mix meeting specified requirements.
4. Mix Proportions
a. Approved mix design received
b. Size and batch determined
c. Mix design proportions adjusted
for desired air content
Portland Cement Concrete Batching Plant Inspector’s
Checklist
5. Batch Quantities
a. Dry weights per batch established for:
• Sacks or pounds of cement
• Pounds of fine aggregate
• Pounds of coarse aggregate
b. Total water required per batch
c. Total yield (including air) per batch
d. Quantity of air entraining agent required per batch
e. Quantity of other additives required per batch
Portland Cement Concrete Batching Plant Inspector’s
Checklist
6. Moisture Content
a. Percent total moisture for each aggregate
b. Gallons of effective moisture per batch
c. Gallons of water to be added at mixer
Portland Cement Concrete Batching Plant Inspector’s
Checklist
9. Routine Duties
The chamber in which the binder and aggregates are mixed is called a
pugmill. The pugmill consists of a lined mixing chamber with two
horizontal shafts on which several paddle shanks, each with two paddle
tips, are mounted. The paddle tips are adjustable and easily replaced.
In general, the paddles are required to be set so that there are no "dead
areas“ in the pugmill. A dead area is a place where material may
accumulate out of reach of the paddles and not be thoroughly mixed.
Dead areas may be avoided by being certain that clearance between the
paddle tips and the liner is less than one-half the maximum aggregate
size. Paddles that have worn considerably or are broken are required to
be readjusted or replaced prior to plant startup.
PUGMILL MIXING
Underfilled Pugmill