Construction Contract Administration (CON3372) NEC
Chapter 6 An Introduction to New Engineering Contract (NEC)
Background
The Construction Industry Review Committee (CIRC) in its report in 2000, highlighted
the fundamental problems that exist in the construction industry such as
Adversarial culture and fragmentation chain with different parties in the
procurement of a project
Lack of collaboration and lack of efficiency
In response to the recommendations in the CIRC report, the SAR Government have
examined suitable form of contract embracing partnering approach into a contractual
relationship and have decided to try out the NEC form of contract. NEC promotes co-
operation, mutual trust and collaborative risk management between contracting parties.
It is composed of a family of contracts which is as listed below :-
The NEC (New Engineering Contract) - Family of Contracts
Engineering & Construction Contract (ECC) - between an Employer and a
Contractor. The ECC is for the appointment of a Contractor for construction
works using a wide range of procurement routes and including any level of
design responsibility. It is suitable for capital works contracts.
Engineering & Construction Subcontract (ECS) - between a Contractor and
a Subcontractor. It is for the appointment of a Sub-contractor where the
Contractor has been appointed under the ECC. It may also be used to appoint a
Sub-contractor under other forms of main contract.
Professional Services Contract (PSC) - between an Employer or a Contractor
and a Consultant. The PSC is for the appointment of a consultant to provide
professional services, such as project management, quantity surveying,
architectural and engineering services.
©VTC2024 Page 1 of 7
Construction Contract Administration (CON3372) NEC
Adjudicator’s Contract (AC) - between two contracting parties and an
Adjudicator.
The AC is for the appointment of an adjudicator under an NEC3 contract’s
dispute resolution provision. It may also be used to appoint an adjudicator under
other forms of contract.
Engineering & Construction Short Contract (ECSC) for “simple” work (not
necessarily low value). ECSC as an alternative to ECC and is for use with
contracts which do not require sophisticated management techniques, comprise
straightforward work and impose only low risks on both the employer and the
contractor.
Engineering & Construction Short Subcontract (ECSS) for use with the
ECC or ECSC.
As a subcontract to ECC or ECSC and is for use with contracts which do not
require sophisticated management techniques, comprise straightforward work
and impose only low risks on both the contractor and the subcontractor.
Term Services Contract (TSC) where the contract is for a period of time rather
than a single project.
Framework Contract (FC) for the appointment of one or more
Suppliers/Contractors/ Consultants to carry out construction works or to provide
professional services on an "as instructed" basis over a set term.
©VTC2024 Page 2 of 7
Construction Contract Administration (CON3372) NEC
What are the characteristics of the NEC Contracts in general?
1) Flexibility
The NEC contracts are flexible modular of forms of contract for e.g. ECC
(Engineering Construction Contract) contains core clauses and a choice of main
Options regarding pricing, risk allocation and payment mechanism (e.g. Lump
Sum, target cost etc.).
The form can be coupled with other option to tailor the contract to suit project
specific requirements.
2) Clarity and Simplicity
The NEC suites of contracts are written in non- legal language, using concise
sentences and a limited use of legal terminology.
Less clauses/words and the use of simple language (avoid legal jargon)
Clear definition of responsibilities
Guidance notes and flow charts are used to help to explain the intent of clauses.
3) Stimulus to Good Management
Good project management requires all parties to work collaboratively, and the
NEC achieves this by clear division of responsibilities and function to promote
accountability and transparency.
Includes detailed set of PM procedures
Early risk identification
Collaboration amongst parties via mutual trust
©VTC2024 Page 3 of 7
Construction Contract Administration (CON3372) NEC
Who are the Main Parties to the ECC contract?
Parties Named in ECC (Engineering & Construction Contract)
The Employer
The Contractor
The Project Manager – appointed by the Employer and administers the contract
on behalf of Employer.
Role of the PM
Review and acceptance of programmes
Issue instructions
Certify payments
Assess compensation events and their impact on time and cost
The Supervisor – administers testing, inspection, quality of work and defects
(similar to Clerk of Works or Resident Engineer)
The Adjudicator (appointed jointly by the Employer and the Contractor)
Others - people or organisations (e.g. design team and cost manager) who are
not the above, or any employee, Subcontractor or Supplier of the Contractor
©VTC2024 Page 4 of 7
Construction Contract Administration (CON3372) NEC
Overview of ECC – Core Clauses
Core Clauses (common to all contracts)
1. General
2. The Contractor’s main responsibilities
3. Time
4. Testing and Defects
5. Payment
6. Compensation events (19 CEs: EOT + Direct Loss and Expenses)
7. Title
8. Risks and insurance
9. Termination
And a list of Secondary Optional Clauses such as
X1. Price adjustment for inflation (used only with Options A, B, C & D)
(sim. “Fluctuation Clause”);
X2. Changes in the law;
X3. Multiple currencies (used only with Options A & B);
X4. Parent Company Guarantee;
X5. Sectional Completion;
X6. Bonus for Early Completion;
X7. Delay Damages (sim. Liquidated and Ascertained Damages);
X12. Partnering;
X13. Performance bond;
X14.Advanced payment to the Contractor etc.
X15. Limitation of Contractor’s Liability for design to reasonable skill & care
Etc
©VTC2024 Page 5 of 7
Construction Contract Administration (CON3372) NEC
What are the Key Differences between an NEC contract and a Traditional
contract used in Hong Kong?
The key differences can be summarized in the following terms:-
i) In the Drafting philosophy, unlike the traditional contracts which are
commonly used in Hong Kong, NEC embodies partnering concepts (e.g.
mutual trust and co-operation (clause 10.1) and multi-party partnering
(Option X12)) and collaborative management working towards common
goals.
ii) Management Approach - The contract form requires not only timely
decision making by the parties but also promotes transparency in such
decision-making process. For example, it requires the Project Manager to
state reasons for his decisions which is not common in other traditional form
of contracts.
Through the innovation of the early warning notification system, the risk
register and the risk reduction meetings, NEC encourages proactive risk
identification and problem solving in an open and collaborative manner.
iii) Risk Management Approach – NEC incorporates innovation of early
warning notification system, the risk register, risk reduction meetings and
encourages proactive risk identification and problem solving in an open
manner.
©VTC2024 Page 6 of 7
Construction Contract Administration (CON3372) NEC
iv) Contractual Practices - There are a number of key differences between NEC
and other traditional form of contracts. Terms such as provisional sum,
prime cost sums, and contingency sums are not used in NEC3. Procedures
for claiming additional payment and extension of time which are usually
separate have been replaced by a consolidated compensation event
procedure.
Generally, the NEC contracts focus more on project management than other forms
traditionally used in Hong Kong. Compared to the traditional forms of contract, the
NEC is more procedural and management intensive. Parties should be aware that
training will ideally be required before the contracts can be used effectively.
©VTC2024 Page 7 of 7