Handbook of Precast Segmental Tunnel Lining Systems (2024, CRC Press)
Handbook of Precast Segmental Tunnel Lining Systems (2024, CRC Press)
Lining Systems
This comprehensive handbook covers all aspects of design, production and construction of
precast concrete tunnel segmental lining, with the best practices in the field included in one
book for the first time.
New and current design methods and quantitative analyses are considered in line with
ACI and ASTM codes, as well as a full selection of global standards for the reliable design
of the product and all components. Also incorporated are new applications of science and
technology, such as new admixtures, and the latest manufacturing processes and precisions,
such as tight dimensional controls and high repeatability cycles.
With detailed guidance from world- leading practitioners, this is the definitive inter-
national technical and practical manual on these linings, forming a one-stop reference for
tunnel engineers and an invaluable resource for advanced students in civil, mechanical and
mining engineering.
Handbook of Precast Segmental
Tunnel Lining Systems
Preface vii
List of contributors ix
About the editors xiii
Index 825
Preface
After several decades of continuous progress, mechanized tunneling has now become the
main method applied in almost all types of geology, all sizes, and in increasingly shorter
lengths. The predominant excavation support system for TBM tunnels consists of a one-pass
precast concrete segmental liner, which in addition to typical use in soft ground contexts, is
also increasingly applied in competent rock settings to better manage the geotechnical and
hydrogeological risks.
The design, production and construction of the tunnel precast concrete segmental liners
is now one of the most complex and advanced fields in civil engineering. However, there is
currently no publication available that covers all these aspects, and this was the main reason
I decided to write this book. During more than three decades work on major tunneling
projects around the world, I gained a wide range of experience on various methods of seg-
mental liner design, production and construction. The difference in practice in various parts
of the world and the lack of one document covering all basic aspects and best practices were
among the main reasons I felt the need for writing this book.
I started first by suggesting and authoring the guidelines for the American Concrete
Institute (ACI) and for the International Tunneling Association (ITA). Then I started think-
ing about authoring a textbook for university students at undergraduate and graduate levels
and young engineers to allow them to learn all necessary details from a single document
instead of spending multiple years in the tunneling industry to become familiar with the
basic principles of segmental tunnel linings. Such a book could obviously provide young
engineers with a significant advantage when they start working in the tunneling industry
and in addition, allows the standardization and the use of best practices in various parts of
the world.
To achieve this goal, I asked David Klug, a leading figure in the tunneling industry with
four decades of experience with all aspects of tunnel segmental liners in North America and
Europe to join me in this effort. Then David and I asked Brian Fulcher and James Morrison
to join our team in writing and editing the book chapters, making full use of their decades-
long experience in this field. Brian and Jim are very well known in the tunneling industry in
North America and have worked on many large and challenging TBM projects with differ-
ent types of segmental liners on both design and construction sides. Finally, to author the
state-of-the-art and the most comprehensive document on this topic, we decided to involve
the very best international experts in various aspects of design, production and construc-
tion of tunnel segmental liner from consulting, manufacturing and contracting industries to
write the chapters and sections of this book.
The book is structured in 13 chapters describing practically all details related to pre-
cast concrete segmental tunnel linings. Chapter 1 discusses the history and evolution of
viii Preface
segmental tunnel liners and explains different steps and breakthroughs in their technical
and commercial developments, which provides a complete background context for all read-
ers. In Chapter 2, fundamental geotechnical aspects relevant to the design of tunnel seg
mental linings are briefly explained, which allows understanding of basic design concepts.
Chapter 3 covers all necessary details for analysis and design and provides in-depth infor
mation allowing a young engineer to start designing tunnel segmental linings. All required
elements of concrete technology are presented in Chapter 4 by one of the best specialists
in this field. Chapter 5 describes the use of fiber for reinforcing segmental linings, which
has become the preferred solution for most cases. Highly engineered connections play an
important role for this type of precast structure and that is why their state-of-the-practice
data is presented in Chapter 6. The latest developments for segment waterproofing gaskets
are described in Chapter 7. The gasket is a critical element in success of a tunnel project.
Chapter 8 details all aspects of segment formwork manufacturing while Chapter 9 discusses
all practical details of segment production by the very top specialists in the field. All essen-
tial information related to segment transportation in different production and construction
phases are described in Chapter 10. Chapter 11 provides the required practical details for
backfill grouting, which is a critical part of the tunnel lining performance. Durability of
the permanent tunnel lining, which is increasingly becoming an important element of the
tunnel design is discussed in Chapter 12. Additionally, this chapter describes the practical
methods needed to design a segmental tunnel lining based on the project required design
life. Finally, Chapter 13 presents the latest developments and innovations in various aspects
of segmental tunnel linings, which results in further expanding its use in global tunneling
industry.
I believe the authors and contributors to this book have achieved their goal of covering
for the first time, all aspects of design, production and construction of precast concrete tun-
nel segmental lining and the best practices in this field in one consolidated document. I am
confident this book will become a significant educational resource for tunnel engineering
students and practitioners all over the world.
Verya Nasri is Senior Vice President and Chief Tunnel Engineer at AECOM. He was for-
merly Tunnel Practice Leader for URS Corporation, and research scientist at MIT. He has
published more than 200 journal and conference papers mainly in tunneling.
David Klug is President of David R. Klug and Associates, Inc. and Klug Construction
Systems, LLC. He is the Past Chairman of the Underground Construction Association
of SME.
Brian Fulcher is Principal and Tunnel Practice Leader at Delve Underground. He is the
Past Animator of the International Tunnelling Association’s Mechanized Tunnelling
Working Group.
1.1 INTRODUCTION
Precast concrete segmental tunnel linings have been in existence for in excess of 100 years
but have only gained popular acceptance and use in the past 40 years or so. During these
most recent years, precast segmental tunnel liners have undergone considerable changes
and improvements in design and materials to the point that they are presently a highly engi-
neered, precision manufactured concrete product with very reliable physical and structural
properties. Additionally, the design and fabrication of precast concrete segmental tunnel lin-
ings are intimately linked to tunnel boring machine (TBM) design and operations. As will be
discussed in greater detail in the following chapters, modern day precast concrete segmental
tunnel linings have substantially benefited from high-quality manufacturing processes and
equipment in conjunction with highly refined materials that did not exist decades ago.
The following describes the history and technical developments for precast concrete seg-
mental tunnel linings from the earliest concepts including materials and manufacturing
methods, through its progressive preference over the use of cast iron and fabricated steel
segments. During this period, many innovations were achieved related to design, materials
and manufacturing processes.
DOI: 10.1201/9781032675541-1
2 Handbook of Precast Segmental Tunnel Lining Systems
Figure 1.1 A .F. Mattson patent for precast tunnel lining segments.
Note: This patent describes one of the earliest precast concrete segmental lining designs devel-
oped in the United States for shield-d riven tunnels in soft soils. (US Patent No.830,345 drawing
dated 1906).
and some transit tunnels in Russia), precast concrete segmental tunnel linings are univer-
sally accepted for both rock and soft ground tunneling conditions, for both initial and final
lining requirements.
Figure 1.2 illustrates the overall timeline for development of precast concrete segmental
tunnel liners. While not all activities and tunnels are listed, it provides a summary of the
key developments and application stages from the first patents, through to modern day
use on a wide variety of tunnels for municipal utility systems and transportation needs.
It should be noted that whereas precast concrete eventually overtook the use of cast iron
Precast segmental tunnel lining history 3
as the preferred material in soft ground tunneling applications, it has also gained popular
acceptance for ground support needs in rock tunnel applications and more recently for shaft
linings. Figure 1.3 illustrates one of the earliest precast segmental tunnel lining installations
in a small diameter hand shield-driven tunnel.
The following summary was excerpted from “Use of Precast Segmented Concrete Lining
for a Tunnel in Soft Clay”, by J. D. Morton, D. D. Dunbar and J. H. L. Palmer (1978).
Tunnel lining in the form of cast iron segments expanded and bolted together were
in use as early as 1869. By 1920, 50 years later, concrete segments had been intro-
duced (Donovan, 1974) but it was not until cast iron was in short supply about 1936
that concrete segments became more widely used (McBean and Harries, 1970). This
increased use of concrete was paralleled by an increase in the number of segment design
alternatives.
In Europe and in the United Kingdom, precast concrete segments have been widely used
by tunnels in so-called “soft ground” where, usually the ground was self-supporting for
sufficient time to erect each ring. Use of segments, particularly unbolted segments, in
ground that is not self-supporting without resorting to compressed air is a very recent
innovation.
In North America, the traditional tunnelling format even for ground that is self-supporting
for a limited period as comprised a two-stage lining system in which steel liner plates
4 Handbook of Precast Segmental Tunnel Lining Systems
or steel ribs and timber lagging are erected as the primary lining, followed by a cast-in-
place concrete secondary liner. Both the primary and the secondary linings are independ-
ently designed to be self-supporting to comply with commercial and safety legislation.
The responsibility for design of the primary lining rests with the contractor, whereas
the responsibility for design of the final liner rests with the Owner (and the Owner’s
Engineer). This procedure results in over-design and is an increasingly significant cost
escalator for the estimated overall project cost.
his day. Greathead’s achievements went further than any other engineers’ tunneling with
additional patented processes and materials. Greathead’s patent of 1874 (see Figure 1.4)
further improved the shield by using water pressure or compressed air to force debris back
from the shield face into the tunnel, using hydraulic rams to force the shield forwards, and
introducing the use of compressed air in the tunnel to further reduce the risk of collapse in
very soft soil conditions. Another patent by Greathead was the addition of the grouting pan
at ceiling height that allowed cement grout to be injected hydraulically behind the cast iron
segments to stabilize the tunnel wall outside the shield itself. (This appears to be the initial
application of annular grouting behind assembled segments.)
The shield was used for the construction of the corridor between the Waterloo and City
Line and the Central Line (Figures 1.5 and 1.6). The red structure is the remains of a
Greathead style shield used at the tunnel head when the Waterloo and City Line was origin-
ally built. It was left at this point when the railway was completed in 1898 and rediscovered
in 1987 during construction of the DLR extension to the Bank Station.
Greathead was accredited with the first shield construction for what is now known as
the Tower Gateway complex in 1869. According to William C. Copperthwaite, who once
worked under Greathead, both Greathead in England and Alfred Ely Beach in New York
invented and constructed their own versions of tunneling shields simultaneously and inde-
pendently of each other. Copperthwaite’s comprehensive publication, Tunnel Shields and
the Use of Compressed Air in Subaqueous Works (1912) recorded many of the innovative
works by Greathead.
6 Handbook of Precast Segmental Tunnel Lining Systems
Figure 1.7 Parmley system for precast tunnel construction – circular cross-s ection.
Note: Ten-foot diameter water tunnel in Cleveland, Ohio. Precast segment erector machine
was mounted in a separate track and was operated by compressed air and electric motors. Unit
weight of precast concrete block were approximately 485 kg (1,075 lbs).
Source: The Parmley System of Arch Construction; Catalogue E (1927).
Figure 1.8 Parmley system for precast tunnel construction – oval cross-s ection.
Note: 24” × 36” (60 cm × 90 cm) Standard English egg-s haped sewer sections. Parmley Reinforced
Concrete Segmental linings were available in all sizes from 24” × 36” (60 cm × 90 cm) and larger.
For a given wall thickness, they had greatly increased strength against collapse than other circular
sewer designs and materials.
Source: The Parmley System of Arch Construction; Catalogue E (1927).
patented designs for precast concrete segmental tunnel liners starting with his US Patent No.
1,043,348 in 1912. Additional patents included those listed in Table 1.2.
Over the course of several decades, John Francis O’Rourke patented many precast con-
crete products having special emphasis on sewer and tunnel construction. None of these,
however, were related to tunnel excavation using a shield or tunnel boring machines.
Figure 1.9 Parmley system factory mock-u p for precast concrete tunnel segment assembly.
Note: Segments for a 3.05 m (10-foot) diameter water tunnel in Cleveland, Ohio. Precast seg-
ment erector machine was mounted in a separate track and was operated by compressed air and
electric motors.
Source: The Parmley System of Arch Construction; Catalogue E (1927).
Figure 1.10 Isometric view of the fully assembled parmley precast tunnel system.
Note: “Parmley reinforced concrete segment plans, using solid concrete walls with all steel
embedded in individual segments as they are molded. All transvers joints are broken; longitudinal
joints being continuous”.
Source: The Parmley System of Arch Construction; Catalogue E (1927).
10 Handbook of Precast Segmental Tunnel Lining Systems
Figure 1.11 C ross-s ectional view of the fully assembled parmley precast tunnel system.
Note: “Cup Block” plan of the Parmley System reinforced concrete segmental construction for
conduit sizes 0.760m (30”) to 1.676m (66”) diameter”
Source: The Parmley System of Arch Construction; Catalogue E (1927).
Table 1.2 O ’Rourke’s patents for precast concrete products for tunnels.
Summary of O’Rourke’s United States patents for precast concrete products used for
tunnel construction projects. Many of these were considered as precast segmental
tunnel linings used in both shallow and deep tunneling applications
Figure 1.12 M ount Royal Tunnel – mixed-f ace tunneling using precast segmental tunnel lining.
Note: 1912 isometric view of excavation and lining operations in the Mount Royal Tunnel in
Montreal, Quebec. O’Rourke Interlocking Tunnel Blocks were erected for both parallel tunnel
arches only.
Source: “Tunnelling–S hort and Long Tunnels of Small and Large Sections Driven Through Hard
and Soft Materials”, by Lauchli, 1915.
mixed-face tunnel was located near the inter-city terminus of the tunnel and proved to be
very challenging. The O’Rourke Interlocking Tunnel Block system was successfully used
in conjunction with a tunnel shield and segment erector device, Figure 1.12 below (from
Lauchli, 1915).
Precast segmental tunnel lining (arch only) were constructed using “Interlocking Concrete
Blocks”, patented by John F. O’Rourke, New York City. Reference US Patent No. 1,043,348
(1912); Interlocking Concrete Blocks”. Details of the precast concrete segmental tunnel
liner used in the mixed face tunnel section included the following:
Key details of the fixed-face portion of the Mount Royal Tunnel are shown below in
Figures 1.13 and 1.14.
Excerpts from The Journal for the Engineering Institute of Canada, April 1919, No.4
include the following.
Precast segmental tunnel lining history 13
Figure 1.13 M ont Royal Tunnel – cross-s ection showing precast segments in arch.
Note: Twin tunnel cross-s ection in soft ground requiring excavation by use of the shield and
“concrete block” lining.
Source: The Mount Royal Tunnel Report, by Mackenzie, Mann and Company,
1913.
Figure 1.14 M ont Royal Tunnel – tunnel lining demonstration in the precast shop.
Note: Full size shop demonstration of the O’Rourke Concrete Block Arch precast segmental
tunnel lining in Montreal, Quebec in 1912.
Source: The Mount Royal Tunnel Report, by Mackenzie, Mann and Company,
1913.
14 Handbook of Precast Segmental Tunnel Lining Systems
Tunnel
The concrete blocks [segments] were 610mm (2 feet) thick radially and 810mm (2 feet,
8 inches) long in the direction of the tunnel. The oval tenons 300 x 790mm x 180mm
(12 x 20 x 7 inches) deep were cast on one side of each block. While corresponding
depressions were cast on the opposite side to engage the tenons on the blocks in the adja-
cent ring of the arch. At the side of the tunnel the arch blocks rested on concrete walls
built into the solid rock.
Segment Precast Plant
A special plant was installed between Dorchester and Cathcart Streets for the casting of
the concrete blocks [segments]. The plant consisted of travelling cranes and hand hoists
for handling the forms and blocks, with an elevated runway for the concrete mixing
plant, from which the concrete was fed to the forms by gravity. The forms themselves
were built-up of flanged cast iron sections mounted on a steel plate. The tenons were
filled to overflowing and smoothed-off to correct level when the concrete was commen-
cing to set. A tapered steel mandrel through the center of the form held a special 50 mm
(2-inch) nut in such position that it was cast into the center of the block and could be
reached through the hole left by the mandrel. This nut was used for attaching the block
to the erector on the shield.
Segment Erector
At the rear of the shield [operation in the mixed face portion of the twin tunnels], two
mechanical erectors were provided for placing the arch blocks in position. Each erector
was pivoted under the working gallery and by means of hydraulic rams, racks and pin-
ions, was able to make four distinct motions, namely, rotation about the central pivot,
longitudinal motion along the axis of the pivot, radial motion, and rotation on its own
axis. By this means, the erector could pick up a block from a car in the heading, revolve
it, and swing it until it was opposite its position in the ring, then push it into the line so
that the tenons fitted into the depressions in the blocks already in place.
Segment Sealing
After erection of the blocks, the joints, the bolts holes and also the space over the blocks
left by the skin of the shield were all closed up with a cement gun and grouting machine.
Figure 1.15 H olland Tunnel concept proposal in 1918 using precast segmental tunnel lining.
Note: Proposed 3D concept rendering for a twin level tunnel Holland Tunnel by George Goethals
and John F. O’Rourke in 1919.
Source: The Illustrated London News, Sunday, 05 Apr 1919.
The larger diameter tunnel was supported with precast concrete segmental tunnel liners,
most probably using the patented O’Rourke Interlocking Tunnel Blocks. (Reference US
Patent No. 1,043,348 (1912). Ultimately, twin parallel tunnels were constructed using gray
cast iron segmental tunnel liners. While this proved successful, O’Rourke argued that the
precast concrete tunnel liners were less expensive and more durable.
Ultimately, the Holland Tunnel was constructed as a twin tunnel facility, completed
in 1927. It is still in service today. The twin tunnels were constructed 9.0-m (29.5-foot)
16 Handbook of Precast Segmental Tunnel Lining Systems
Figure 1.16 H olland Tunnel concept proposal in 1919 using precast segmental tunnel lining, cross
section.
Note: A 12.8-m (42-foot) outer diameter twin level tunnel was proposed by George Goethals
and John F. O’Rourke in 1919 for the Holland Tunnel. Three-foot thick precast “interlocking
tunnel blocks” were proposed as the initial tunnel lining, for ground support and groundwater
control.
Source: The Sun (newspaper), Sunday, 26 Jan 1919.
diameter using four separate soft ground compressed air shields that concurrently installed
a bolted and sealed cast iron segmental tunnel liner (comprised of 14 curved segments that
are each 1.83 m (6-feet) long as the excavation advanced.
The twin tunnel initial concept arrangement in comparison to the single-bore tunnel con-
cept is illustrated in Figure 1.17. The north tube is 2,608-m (8,558-feet) long and the south
tube 2,551-m (8,371-feet) long. The roadway is 6.1-m (20-feet) wide and reaches a max-
imum depth below mean high water of 28.5 m (93.4 feet).
Excerpts from The Sun (newspaper), Sunday, 26 Jan 1919:
“….The part of the tunnel extending under the river, on inshore as far as the subsurface
and street surface conditions permit, will be 42 feet in diameter at the outer rim and built
of concrete blocks three feet in thickness. Steel has been rejected, the tendency being
nowadays in such work to be back to concrete and stone. Construction will be by the
shield method….”
“….Interlocking Concrete Blocks–as the basis of construction will be thoroughly
waterproofed at the outer side of the joints by asphalt, while the face of the joints on the
inner side of the tunnel will be treated with tarred oakum and cement mortar. The whole
Precast segmental tunnel lining history 17
Figure 1.17 H olland Tunnel concept proposal – 1918 using precast segmental tunnel lining.
Note: A 12.8-m (42-foot) outer diameter twin level tunnel was proposed by George Goethals
and John F. O’Rourke in 1918 for the Holland Tunnel in comparison to a twin tube concept using
traditional cast iron segments. The single-b ore tunnel used three-f oot thick precast “interlocking
tunnel blocks” as the initial tunnel lining.
Source: The Sun (newspaper), Sunday, 26 Jan 1919.
interior filled with mortar introduced under compression and then coated with white
cement….”
composite solution (systems) involving highly mechanized tunneling and ground support
systems and innovative materials. A partial summary listing of reports prepared for the
United States Department of Transportation (DOT) and Federal Railway Administration
(FRA) included the following, for example.
Many of the above-noted reports were developed with the intent to advance the state of
the domestic and international tunnelling industry, materials and engineering. Many other
reports and technical publications are listed in the Bibliography and Additional Reading
Materials.
Table Legend:
• Primary condition or majority of the work
Secondary (infrequent) condition or occasional encounter to the work
CP/S ta Cross-p assage break-o ut location. Station-t o-t unnel lining transition due to seismic design criteria.
used fabricated steel plate tunnel liners. It was only in subsequent BART tunnels, that pre-
cast concrete segmental tunnel liners became the preferred material choice as well as the
most economical solution.
Figure 1.18 P refabricated steel segmental tunnel lining – BART system. Example 1.
Note: Transit tunnel construction using fabricated steel segmental tunnel liners.
Source: BART Archives.
By the mid-1980’s and continuing to the present, all WMATA tunnels were designed for
precast concrete segmental tunnel linings, with tunnel excavation equipment adjusted to
suit. Fabricated steel tunnel linings were not used. Precast concrete segmental tunnel liners
become the preferred material choice as well as the most economical solution. There were
many reasons for this choice, most notably cost and local preferences (and industrial cap-
acity) for fabrication of precast concrete.
Figure 1.19 P refabricated steel segmental tunnel lining – BART system. Example 2.
Note: Transit tunnel construction using fabricated steel segmental tunnel liners.
Source: BART Archives.
Kinnear, Moodie & Co., Ltd. Made the first precast reinforced concrete bolted segmental
lining for shafts and tunnels in 1936. At that time, the Company was asked
by the Consulting Engineers on the then London Passenger Transport Boars, Messrs.
Mott, Hay, & Anderson, to carry out experiments in the manufacture and use of precast
reinforced concrete bolted segments, with a view to meeting the need, which began to
develop at that time, for economizing on cast iron. Before this, various form for concrete
block lining had been devised but none with outstanding success. The underlying prin-
ciple of Messrs. Mott, Hay, & Anderson’s design was to retain the bolted segmental ring,
and to replace cast iron by reinforced concrete in the manufacture.
The distribution and type of loading likely to be applied to tunnel segments do not
lend themselves to laboratory tests, so that in order to settle the structural merits of these
segments, the Engineers carried-out full-scale tests on specially constructed experimental
lengths of tunnel. The results of these tests have been published and have established def-
initely that concrete segments compare favorably with cast iron in strength and stiffness,
whilst their cost is substantially lower.
The making of precast concrete segments at the Company’s works was controlled
at every stage, strict attention being paid to all details of the manufacturing processes
involved. Clean aggregates of proper mechanical analysis are used, and the mixing is
done by gravimetric methods, the material being tested regularly as a matter of routine
and any necessary alteration made forthwith. Strict attention is paid to the accuracy of the
22 Handbook of Precast Segmental Tunnel Lining Systems
Figure 1.20 P refabricated steel segmental tunnel lining – BART system tunnels.
Note: San Francisco Bay Area Rapid Transit (BART) system tunnels were constructed using fab-
ricated steel segment tunnel liners.
Source: BART Archives.
molds and all segments are properly consolidated on heavy vibrating table. The method
of manufacture ensures that there can be no difference of dimensions of practical import-
ance between different units of the same pattern, all segments being interchangeable.
Figure 1.21 P refabricated steel segmental tunnel lining – WMATA contract design.
Note: 1980-e ra Contract Drawing illustrating the Owner’s design of fabricated steel segmental
bolted and gasketed tunnel lining for a metro tunnel in Washington, DC, United States.
Source: WMATA Archives.
Figure 1.24 P recast concrete segmental tunnel lining – WMATA contract design.
Note: 1980-e ra Contract Drawing illustrating the Owner’s design of precast segmental bolted
and gasketed tunnel lining for a metro tunnel in Washington, DC, United States.
Source: WMATA Archives.
Precast segmental tunnel lining history 25
Tunnelling is an ancient art which, until recent times, has used a combination of manual
labor for excavation and readily available raw materials (usually timber) for support
as required. Although tunnelling is basically an art, scientific influence is becoming a
common place due to the combination of improved technology, increasingly difficult
ground conditions, an increased cost of labor, and other economic pressures. Such factors
have provided impetus to the development and use of Tunnel Boring Machines instead
of manual excavation, and a concomitant reassessment or development of compatible
tunnel lining systems. One such novel tunnelling procedure which has been developed
in Canada employs full-face Tunnel Boring Machine together with an unbolted precast
segmented concrete tunnel lining. The initial contract use of the system was in a soft to
firm clay deposit of lacustro-deltaic origin at Thunder Bay, Ontario; however, the system
Figure 1.25 S ection through a TBM adapted to handle and erect precast segmental tunnel linings.
Note: Excerpt from a 1978 US Patent drawing for a Lovat TBM adapted to transport and erect
precast segments as tunnel liners in the first ever application in Canada.
Source: US Patent No.4,067,201 dated January 1978.
26 Handbook of Precast Segmental Tunnel Lining Systems
Figure 1.26 T BM adapted to handle and erect precast segmental tunnel linings.
Note: Excerpt from a 1978 US Patent drawing for a Lovat TBM adapted to transport and erect
precast segments as tunnel liners in the first ever application in Canada.
Source: US Patent No.4,067,201 dated January 1978.
is highly adaptable to other ground conditions and has been specified as a design alterna-
tive for tunnels in more competent soils and sedimentary rock.
Tunnel Lining
Since the TBM would advance by thrusting on the completed tunnel lining, each thrust
had to be as long as possible, and the erection of each ring had to proceed rapidly within
Precast segmental tunnel lining history 27
the protection of the tail shield. To achieve this, unbolted segments were preferred. Each
assembly ring would come in contact with the ground only as is emerged from the rear
of the tail shield during the machine advance. As the lining was to serve both as a pri-
mary and secondary lining, it had to be designed to accommodate all anticipated ground
loads, as well as erection and handling stresses and the longitudinal stresses developed
as a consequence of the TBM thrust. The design would rely on the segmental ring hav-
ing sufficient flexibility to deform to the degree needed to reduce the bending stresses
to acceptable limits. Finally, all joints have to be adequately sealed to prevent inflow of
grout or remolded soil and water when the segmental lining was thrust out of the pro-
tection of the tail shield.
Figure 1.27 shows a representative image of “junk segments” installed in soft ground and
hard rock tunnels as the “primary lining”.
29
newgenrtpdf
Table 1.4 (Continued)
30
Handbook of Precast Segmental Tunnel Lining Systems
Dimensions Ground conditions Other issues
Item Project name Project location Outside diameter Overall length Rock Soil Water Gas Risks Costs
12 South Hartford Tnl e
USA 5.5 m 4,600 m
Hartford, CT 2021 (18’) (15,000 LF)
13 Three Rivers CSO 5 USA 5.5 m 7,475 m
Ft Wayne, IN 2021 (18’) (24,520 LF)
14 Kemano Power Tunnel CAN 5.72 m 7,606 m
Kitimat, BC 2021 (18’–9 ”) (24,954 LF)
Notes:
a
PSTL (ungasketed) selected to control excess groundwater infiltration and to support potentially variable ground conditions. Additional benefit was to provide
a predictable and beneficial hydraulic surface for effluent flows.
b
PSTL selected to satisfy Tunnel Health and Safety requirements, control excess groundwater and dissolved H 2S gas infiltration.
c
PSTL selected to satisfy construction permit requirements, control excess groundwater infiltration, stabilize highly variable ground conditions and potential
gas pockets.
d
Design life cycle (100 years) and estimated capital costs of the CIP concrete liner was more than the single-p ass precast segmental tunnel liner; with predict-
able waterproof performance and maintenance costs.
e
PSTL selected to cope with excess groundwater infiltration and planned water control measures
Table Legend:
• Primary condition or majority of the work
Secondary (infrequent) condition or occasional encounter to the work
Precast segmental tunnel lining history 31
Figure 1.28 B uckskin Mountains Tunnel – contractor’s precast segmental tunnel lining approach.
Note: Contractor’s drawings for the first ever precast segmental lining used in the bored hard
rock tunnel in the United States Groseclose and Schoeman).
Source: RETC 1976, Chapter 26, Society and Mining Engineers.
Figure 1.30 D eer Island Effluent Outfall Tunnel – under construction in 1995.
Note: Interior of the Deer Island Effluent Outfall Tunnel where 8.1m (26’-6 ”) diameter precast
segmental tunnel liner was used in an argillite formation.
Source: Brian Fulcher, personal photo collection.
rock tunnels) and use of mechanized excavation equipment. Research by the United States
Department of Transportation (US DOT) and acute steel shortage precipitated the evalu-
ation of alternate ground support materials and especially for the growing quantity of
transportation tunnels anticipated in urban areas. Whereas fabricated steel tunnel lining
segments had been developed and used in several transportation projects (i.e. BART transit
tunnels in San Francisco), precast concrete segments were initially used in the Baltimore
Metro tunnels in the mid-1980’s.
tunnel linings were used previously in North America and other parts of the world, but this
was their first application in the United States upper Midwest and would go on to become
a very integral part of the extensive Great Lakes Clean-Up Program. Sehulster brought
together with his own engineers, local engineering firms; i.e. Freeze and Nichols as well
as international experts from Charcon Tunnels Ltd. in the United Kingdom to develop a
precast segmental tunnel lining design that was submitted and approved by the MMSD
(Figures 1.31 and 1.32).
Note the segments resemble cast iron tubbings that were the international standard at
the time with pockets cast in the lining to facilitate weight savings and ease of bolting with
straight bolts as these segment types were typically erected manually in the tunnel in the
United Kingdom. After construction of the precast tunnel lining, a welded steel pipe was
installed and the annular space between the steel pipe and the precast lining was grouted.
A lining of this design was then manufactured and supplied to the Northeast Ohio Regional
34 Handbook of Precast Segmental Tunnel Lining Systems
Sewer District (NEORSD) in Cleveland, OH for 5,000 feet (1,524 m) of 10.3-foot (3.14-m)
internal diameter from 1985 to 1986.
As Sehulster Tunnels was gaining experience in precast segment manufacturing the team
were working on a new innovation in conjunction with the MMSD that is now known as
“one-pass precast tunnel linings”; meaning the internal face of the precast segments were
smooth that facilitated the removal of a secondary carrier pipe of steel or concrete thus
saving the MMSD time from the construction schedule and an overall lower project cost,
Figures 1.33 and 1.34.
To achieve this concept, Sehulster developed, tested and implemented proprietary innova-
tions in precast segment design that were later used on other tunnel projects throughout
the world by Charcon Tunnels Ltd. In order to facilitate a true “one-pass” segmental lining,
the internal face of the segments had to be completely smooth without pockets as the
Precast segmental tunnel lining history 35
cast-in pockets would create turbulence and decrease the hydraulic efficiency of the lining.
To obtain the “segmental lining without pockets”, a new innovation was created for con-
necting the circumferential joints of the segmental ring while at the same time allowing for
segment joint stagger that is important for ring stability. This new innovation was called the
“Fast Lock Dowel and Socket Assembly”, Figure 1.35. This connection device is covered
under US Patent 4,477,204 dated 16 Oct 1984.
The “Fast Lock Dowel System” aligned the adjoining segments and associated gaskets
while the special internal locking system prevented the rings from separating during ring
installation, with the steel center axis providing substantial shear resistance from external
forces acting on the lining. Past connection systems were dependent upon manual installa-
tion and tightening bolts, but the real innovation of this system was that it used the massive
power of the TBM thrust jacks to set the system into place thus minimizing human involve-
ment and effort, resulting in improved ring build quality and reduced installation time.
This, combined with the Charcon Tunnels “Camlock Radial Joint Connection System”,
dramatically changed how tunnels were built in the Milwaukee area and other parts of
North America.
36 Handbook of Precast Segmental Tunnel Lining Systems
Sehulster’s one-pass tunnel lining innovations were used on two sewer tunnel projects in
Milwaukee, Wisonsin and later incorporated into a large storm water diversion tunnel in
San Antonio, Texas where Sehulster Tunnels successfully built 6,706 m (22,000 feet) of
7.4-m (24.3-foot) internal diameter one-pass precast segmental tunnel lining. This precast
segment manufacturing technology was then used to manufacture the tunnel lining for three
world class underwater tunnel projects at the time.
• MWRA Boston Outfall Tunnel in Boston, MA, United States (1991 to 1994)
• 13,715-m (45,000-feet) long
• 7.4-m (24.3-foot) internal diameter tunnel lining
newgenrtpdf
Precast segmental tunnel lining history
Figure 1.35 P recast segmental tunnel lining – fast lock dowel and socket assembly drawing.
Note: Patent application drawing for the Sehulster “Fast Lock Dowel and Socket Assembly” to illustrate a section through the installation and
all component parts.
Source: Sehulster Tunnels, Inc.
37
38 Handbook of Precast Segmental Tunnel Lining Systems
• St. Clair River Railroad Tunnel in Sarnia, Ontario, Canada (1992 to 1994)
• 1,854-m (6,083-feet) long
• 8.4-m (27.5-foot) internal diameter tunnel lining
• San Diego Southbay Ocean Outfall in San Diego, CA, United States (1995 to 1998)
• 6,096 m (20,000 feet)
• 2.74-m (9.0-foot) internal diameter tunnel lining
Sehulster and his team of engineers were tunnel industry leaders and innovators who built
11 major tunnel projects from Boston to Seattle while always striving to improve the quality
of the product being delivered. Sehulster promoted the beneficial uses of one-pass precast
segmental tunnel linings to owners, design engineers and tunnel contractors. The work
Sehulster did to promote the use of one-pass precast segment tunnel linings was instru-
mental in one-pass precast segmental tunnel linings having the industry acceptance they
enjoy today.
Innovative reinforcing solutions have also included the use of polypropylene fibers, par-
ticularly for transportation tunnels where fire (and severely elevated temperatures) pose
threats to the structural integrity of the segmental tunnel lining.
A more thorough discussion on the application and use of both steel and plastic fibers
reinforcing is enclosed in Chapter 5 .
The tunnel sections consist of two separate tubes with a semi-circular top made of con-
crete arch voussoirs cast separately, set into position and supported on either side by
concrete walls ad in the middle by a dividing wall made up of 10.5 inch, 65 lbs/foot
Bethlehem H-columns space 2’-3” center to center and spanned by structural steel built-
up lintels, all encased in concrete. The [interlocking concrete] blocks are 2 feet thick
radially and 27 inches in the direction of the tunnel axis and were made in length of 5
newgenrtpdf
40
Handbook of Precast Segmental Tunnel Lining Systems
Table 1.5 M olds and production systems for segment casting operations
Summary of mold types (and materials used) and production casting systems for recently completed tunnels where precast
segmental tunnel lining was selected as the final lining. Note the mold materials changes
feet circumferentially. They have plane faces on the intrados and on the radial joints but
are provided on one vertical face with concrete keys or tenons 12 x 20 inches in section
and 7 inches high, while of the opposite face contains depressions of the same shape to
engage the projections of the blocks in the adjacent ring of the arch.
Figures 1.37 and 1.38 illustrate the steel and cast iron molds used to form Interlocking
Concrete Blocks for the Mount Royal Tunnel project (circa 1912).
Figure 1.39 below illustrates a patented 1930-era precast segment casting operation for
multiple (side-by-side) tunnel project.
Modern precast segmental tunnel liners are commonly fabricated from 0.10 to 0.05 mm
(0.004 to 0.002 inch) tolerance. This precision and repeatability greatly contribute to the
safe and reliable handling at the plant, site and in the tunnel. Individual segment unit weights
are also carefully controlled resulting in repetitive, predictable handling through all phases
of fabrication and tunnelling operations.
A more thorough discussion on modern segment molds and casting facilities is enclosed
in Chapter 8 and Chapter 9. Additional information on segment handling and installation
is enclosed in Chapter 10.
42 Handbook of Precast Segmental Tunnel Lining Systems
44
Generalized summary of the primary logistics, materials, facilities trade skills and transportation modes needed for fabrication of
segmental tunnel liners since first conceived in the 1870s and later refined and consolidated to precast concrete segmental tunnel
45
newgenrtpdf
Table 1.6 (Continued)
46
Handbook of Precast Segmental Tunnel Lining Systems
Fabrication operations Materials needed Transport’n
Item Description Method Labor Supplies Fuel/power Rail Ship Road
3 Precast concrete – Precast concrete Skilled labor Bulk supplies of Depending on 3
advanced operations: classes: the following: manufacturing
stage with full • Shop and plant • Precast plant • Steel fibers era, the
mechanization; facilities workers (all • Welding supplies following:
ready-mix concrete, • O verhead cranes with skill sets • Ready-mix • Natural gas
carousel production GPS controls; repetitive • Heavy concrete • High-voltage
line, machined and handling equipment • Segment electrical power
power-assisted • M echanize and operators accessories • Steam heat
molds, steel fiber automated steel fiber • Electrician • Anchored
reinforcing handling • E lectronic gaskets
• S egment molds with • P LC
machined surfaces, Programmers
power assist and • Millwrights
anchored gaskets (for machined
• C arousel production molds)
line system • Quality
• O n-site concrete batch Control
plant Technician
• Concrete placing &
finishing
• Handling & storage
yard
• QC lab facilities
Notes:
1
In the late 1800’s and early 1900’s, highway systems were very limited and primitive and definitely not suitable for heavy load transport. Rail and marine (ship)
modes were preferred. Fabrication facilities were, therefore, located at transportation hubs.
2
As fabricated steel segments were popular for a short period (mid-1990’s), the use of marine (ship) transport was very limited with the preference being rail
and road. Logistically, fabrication facilities were, therefore, located at transportation hubs.
3
As precast concrete segmental tunnel liners gained in popularity (in the 1970’s and to the present), and the location of suitable plant facilities were more
flexible, the use of rail and marine (ship) transport became very limited with the preference being road (highways). Logistically, precast segment fabrication
facilities were, therefore, located at highway transportation hubs.
Table Legend:
• Primary condition or majority of the work
Secondary (infrequent) condition or occasional encounter to the work
Precast segmental tunnel lining history 47
Table 1.7 H ealth and Safety considerations for precast segmental tunnel linings.
Summary of the primary Health and Safety considerations for the manufacturing,
handling, storage, transport and installation of the precast segmental tunnel liners
Figure 1.41 A rrowhead Tunnels Project, San Bernardino, California, United States.
Note: A very robust precast segmental tunnel lining system was designed and installed on this
project. In this case there were two different concrete design strengths needed to suit subsur-
face conditions and a single gasket sealing system designed for 27 bar groundwater pressure.
Source: Brian Fulcher, personal photo collection.
Precast segmental tunnel linings also benefited from changes (enhanced) in material
properties focused on concrete, reinforcement and sealing systems that occurred in recent
decades. These changes increased durability and the estimated service lives of the installa-
tions. Sealing systems and corresponding connection devices have advanced to the point
where 30 bar groundwater pressures are readily achievable. The use of a very robust precast
segmental tunnel lining for the Arrowhead Tunnels Project located in San Bernardino,
California was instrumental to the success of the project. The use of state-of-the-art TBMs
to penetrate very egregious ground and groundwater conditions could not have been safely
and successfully accomplished without the concurrent installation of a precast segmental
tunnel lining specifically designed for highly variable ground conditions including squeezing
ground occurrences and very high groundwater pressures, Figure 1.41.
At the manufacturing stage, efficiency, accuracy and reliable repeatability have greatly
improved. High precision and low tolerance molds and carousel casting and curing pro-
cesses for increasing daily segment production rates are also the State-of-the-Art resulting in
considerable fabrication economies over alternate materials. Manufacturing improvements
currently underway include increased automation and extensive use of robotics. It should
be noted that the “build tolerance” and watertightness of segmental tunnel linings is a direct
reflection on design and fabrication of segment molds as well as strict protocols on segment
casting, curing, storage and handling. Whereas, the original precast segmental tunnel lining
molds were built from cast iron, steel, concrete and wood, they are now universally fabri-
cated from very high precision machined and polished rigid steel frames.
50 Handbook of Precast Segmental Tunnel Lining Systems
Future developments for precast segmental tunnel linings will include additional auto-
mation in their manufacture, handling and installation as well as improved durability and
service lives. They will also be further adapted for non-circular tunnels and rehabilitation
projects to extend (or repurpose) the service lives of existing underground facilities.
2.1 INTRODUCTION
A tunnel system is designed and built based on a series of assumptions and simplifications
developed by the engineer to model the natural geologic environment. The actual conditions
of the geologic realm are far too complex to capture completely and accurately, and the
ability to sample the environment is only possible at discrete points of space and time. For
example, if 50 mm (2 inches) diameter specimens from borings are collected at 165 m (540
feet) intervals along a tunnel alignment, the engineer has only physically examined about
1.0 ppm of the soil that will impact the tunnel. The tools available to the engineer to create
the best possible model of the environment as a basis of design include accurate and reli-
able sampling and testing methods, and a thorough understanding of the natural science of
geology to connect the dots. Technology such as remote sensing, LiDAR, and drone surveil-
lance is also available to help the engineer in understanding the bigger picture and regional
perspective necessary to interpret geologic conditions.
The contractor, on the other hand, is generally responsible to determine the appropriate
equipment and installation methods necessary to build the tunnel and assure that the
DOI: 10.1201/9781032675541-2
54 Handbook of Precast Segmental Tunnel Lining Systems
specifications of the designer are met. To meet this objective, the contractor will be focused
on developing a geotechnical model that defines the following:
While there is overlap, the use of the geotechnical model is quite different between designer
and contractor. The geotechnical investigation, data and reporting prepared during the
design phase of the project ultimately needs to address both objectives. The art of preparing
and reporting geotechnical data that covers each objective is discussed briefly in Section 2.7
but warrants further discussion and integration with the overall contracting approach in
other reference documents.
The purpose of this section is to present the reader with a general overview and guidance
to the principles of geotechnical engineering that are typical in segmental tunnel design and
construction. It is not intended to be a comprehensive document to define geotechnology,
or to facilitate other types of subsurface design. Many detailed references have been devel-
oped as outlined in Sections 2.8 through 2.10, and the reader is directed to these references
for the detailed development and evaluation of specific parameters to be incorporated into
a design.
2.3.1 Soft ground
The materials described as soft ground are the weathering products of decomposed rock and
consist of an accumulation of individual particles of varying size and chemical composition.
Classification and behavior of soft ground is influenced by its deposition, chemical compos-
ition, grain size and shape, and stress and loading history. From an engineering perspective
soft ground materials are broadly grouped into two categories, cohesive and non-cohesive,
based on their behavior and their properties of interaction between individual soil particles.
Cohesive soils are defined as a material that retains its strength, electrostatic forces and/or
capillary forces between soil particles. From a tunneling perspective, cohesive soils exhibit
some degree of stand-up time during excavation but will deform in a plastic manner while
retaining individual particle connections. Cohesive soils also generally exhibit low perme-
ability and act as a barrier to water flow and drainage and may exhibit sticky behavior
during excavation.
Non- cohesive soils represent an aggregate of particles that exhibit strength through
gravity and frictional forces between particles. The relative strength of a non-cohesive soil
is related to the particle size gradation, layering, and shape or roughness of individual par-
ticles. The relative strength generally increases with increased confining stress. From a tun-
neling perspective, non-cohesive soils will lose strength and displace by flowing or raveling
with the loss of confinement and/or loss of capillary forces due to drainage.
Naturally deposited soils are often a mixture or layering of different soil types and par-
ticle sizes and will exhibit a complex overall behavior profile during mining. Further dis-
tinction is given to materials that behave somewhere between soil and rock, and these are
referred to as intermediate geotechnical materials or IGM discussed further below. Soil
types by deposition include the following:
• Alluvium
Includes soils deposited by flowing water. Alluvial soils tend to be stratified in depos-
ition, with particle size bands being related to the water velocity at the time of depos-
ition. Ancient alluvial deposits may appear to be highly variable in vertical and lateral
extent when exposed during an excavation. From a tunneling perspective, complica-
tions arise due to the variability of porosity and the concentration of water flow in the
open-graded coarse deposits, and the water trapping potential of fine grained and clay
strata.
• Lacustrine
Includes soils deposited in still water or lake environments. Like alluvium, lacustrine
deposits will be stratified in composition, but are generally fine grained. Depositional
56 Handbook of Precast Segmental Tunnel Lining Systems
strata generally reflect seasonal variations in water flow. Silt and fine sand strata tend to
accumulate where a water body is active with precipitation or stream flow, such as spring
melt and run-off or periods of wet weather. During periods of still water, the finer grained
silt and clay soil minerals fall out of suspension, forming clay strata. From a tunneling
perspective, lacustrine soils can manifest with stand-up time and stability issues, where
water transports through the coarser grained strata resulting in slip planes. Instability can
also result if excess pore pressure develops in the finer grained silts and clays. Effectively
dewatering or depressurizing lacustrine deposits can prove problematic, due to the typ-
ical overall fine-grained nature and thin horizontal bedding of the soils.
• Glacial
Glacial soils have been formed by the action of flowing ice and from distinctive pat-
terns of deposition. Kames and eskers are concentrated regions of generally coarse
material deposited by water flowing through or beneath a glacier. After the glacier has
retreated, these deposits form stratified ridges and long linear features in the topog-
raphy. Glacial till is the ground-up residue typically formed as the ice sheet advances
across native ground or exposed rock.
Till is generally comprised of a wide range of particle sizes, from clay fraction to
cobbles and boulders. From a tunneling perspective, till deposits are typically dense
and have substantial strength, offering excellent stand-up time during excavation.
However, cobbles and boulders result in obstructions to mining, and impact the effi-
ciency and design of mining equipment. Predicting the presence and concentration of
boulders is problematic, as the occurrence and frequency is difficult to capture with
conventional soil sampling methods.
• Wind-blown
Wind-blown soils deposits are typically referred to as loess and exist in large expanses
of the great plains of North America, and the Eurasian steppes. Loess is characterized
by fine, angular particles that lock together into soil deposits that have both strength
and low density. Stand-up time for mining can be very advantageous, as well as the
natural ability to drain rapidly due to the relatively high void ratio. Problems with
loess deposits include the tendency to collapse and lose strength when disturbed by
excavation or vibration.
• Residual
Residual soils are the product of parent rock decomposing in place into a soil con-
sistency. Residual soils are extensive in the southeast United States in an area known
as the Piedmont region. Within the Piedmont, residual soils are extremely variable
over short distances due to weathering along ancient rock fractures and can result in
extreme variation from soft ground to rock within the space of a single excavation.
The formation and strata of residual soils mirrors the minerology and fracturing of the
parent rock. Subsequently, slip planes and water flow channels will appear random
and variable in an excavation.
multiple parties can understand the terminology used in describing a soil or rock. From
this common language, a common understanding of expected behavior is communicated.
For tunneling, the Designer needs to understand the material type, its weight, density, and
strength characteristics. The Contractor will be interpreting the ground for its resistance to
excavation, ability to transmit water, and other physical characteristics necessary to define
his means and methods of construction.
2.3.3 Organic soils
Encountered extensively in northern latitudes as fibrous peat or muskeg, and range to black
silt and clay where decomposition can occur over time. Properties of organic soils need to
be determined reflecting as close as possible to their natural state. Peat is fibrous, and sponge
like, which allows for very high-water content values in the range of 50% to 2,000%.
Organic soils often have comparatively high strength per unit weight due to fibrous inter-
locking. Other general properties include high acidity, which can prove detrimental to cor-
rosion in concrete and steel, and often interferes with slurry additives used in drilling and
slurry shield TBM construction.
newgenrtpdf
Table 2.1 ASTM 2487 – Unified Soil Classification System.
58
Summary of soil classification nomenclature and criteria as defined by ASTM
C U = D 60 / D 10 greater than 4
gravels
mixtures, little or no fines
Clean
between 1 and 3
(more than 50% retained on No.200 ASTM sieve)
Gravels
SW
little or no fines C c between 1 and 3
Clean
sands
6 Poorly graded sands and gravely sands, Not meeting both criteria
SP
little or no fines for SW
passes No.4
ASTM sieve
less)
CL plasticity, gravelly clays, sandy clays,
ASTM sieve)
11 Organic silts and organic silty clays of
OL
low plasticity Check plasticity chart
11 Inorganic silts micaceous or
or less)
silts
59
newgenrtpdf
60
Table 2.2 Tunnelman’s ground classification of soils.
Summary data from Terzaghi (1950) and Heuer (1974) for tunneling in soft soils and their anticipated behaviors under various
The following issues should be considered during tunnel design if organic soils are
identified:
Several references are available to further define the properties of organic soils such as
(McFarlane, 1969).
• Common definition of IGM: N=>50 bpf, 480 kPa to 1,380 kPa (69 psi to 200 psi)
• Range of geologic materials:
• Cemented sand and gravel (glacial soils, ancient sand dunes)
• Salt cement
• Calcium cement
• Residual decomposed rock
• Mudstone
• Decomposed granite
• Cemented loess
2.3.5 Rock
Rock is typically defined as a geologic material with a material matrix stronger than 1.3
MPa (200 psi) and encompasses a very broad range of both material composition, and
mass structural properties. From a tunnel design perspective, the equipment and meth-
ods of construction are distinctly different than those used for soft ground tunneling. In
addition, the analytical methods used to evaluate and design the tunnel are distinctly
different. For a tunnel in rock, the comprehensive mass properties and fracturing geom-
etry of the geological formation play a more significant role in defining the behavior of
the material, and in determining the loads that affect a tunnel. In contrast to the overall
loading and design properties, cutting tool selection and durability is affected by specific
material composition, and specific material strength. Both the micro-behavior (discreet
samples) and the macro-behavior (overall formation) of materials must be understood in
detail to design and build a tunnel. Further details on design properties of rock are pre-
sented in Section 2.6.1
62 Handbook of Precast Segmental Tunnel Lining Systems
These parameters are evaluated using geologic maps, rock cores, borehole logging data
and hydraulic conductivity testing or observations of water inflow. Ratings are assigned
based upon the criteria shown in Tables 2.4a to 2.4d. The RMR ranges from 0 to 100, rep
resenting “very poor” to “very good” rock, respectively. For large projects it may be neces-
sary to divide the tunnel alignment into segments based on structural features or changes
in spacing and character of discontinuities, which permits separate ranges of RMR for
each segment to be defined. Published correlations relate RMR to Q (quality index from
Q-system of rock classification) such that only one rock mass classification system may be
needed under certain circumstances.
2.3.5.3 Q-system
The Q-system of rock classification was developed at the Norwegian Geotechnical Institute
(NGI) (Barton, et al. 1974) in the early 1970’s and updated several times to incorporate
advances in tunneling and rock support technology. The quality index Q is computed as the
product of three quotients as shown below. The first quotient is related to block size, the
second is related to joint friction, and the last is related to active stress around an opening.
newgenrtpdf
Table 2.4a Rock mass rating system – classification parameters and ratings.
64
Summary of rock mass classification parameters for the rock mass rating system (RMR)
Ground pressure
water Major principal
stress
General Completely dry Damp Wet Dripping Flowing
conditions
Rating 15 10 7 4 0
Geotechnical investigations for segmental tunnel lining design 65
Table 2.4b Rock mass rating system – rating adjustments for joint orientations.
Summary of joint orientation for the rock mass rating system (RMR)
Very
Item Parameter favorable Favorable Fair Unfavorable Very unfavorable
B Strike and dip orientations of joints
Tunnels 0 -2 -5 -1 0 -1 2
1 Ratings Foundations 0 -2 -7 -1 5 -2 5
Slopes 0 -5 -2 5 -5 0 -6 0
Table 2.4c Rock mass rating system – rock classes determined from total ratings.
Summary of rock mass determination for the rock mass rating system (RMR)
The value of Q can range from 0.001 (exceptionally poor) to 1,000 (exceptionally good).
The Q index is computed using the following equation:
RQD Jr J
Q= * * w (2.1)
Jn J a SRF
where
RQD Rock quality designation, ranging between 0 and 100
Jn Joint set number
Jr Joint roughness number
66 Handbook of Precast Segmental Tunnel Lining Systems
While the RQD and joint set number can be determined from drill cores, the remainder
of the parameters are best determined by direct observation in the excavation. In deter-
mining Q, it is advisable to prepare a range of values for individual parameters from many
measurements, and from those compute the minimum, maximum, and mean Q value. More
information and tables of values to be used when selecting parameters to compute Q can be
found in Barton et al. (1974) and NGI (2015).
The Q-system is commonly used to delineate tunnel alignments into separate support cat-
egories based on rock quality. Correlations have been developed to relate Q to other useful
parameters such as seismic P-wave velocity and rock mass static modulus of deformation
(Barton, 2002).
• The presence of aquitards within the stratigraphic profile, and the water pressures
associated with each stratigraphic sequence
• Variability of water pressures over time due to seasonal fluctuations, or tidal
fluctuations
• The impact of constructing a tunnel through different geologic strata, and the poten-
tial for the tunnel itself to connect different hydrogeologic strata. (The design may
need to incorporate barriers to flow in this case.)
• The presence of artesian pressure due to regional topographic features
• Predictions for change over time due to influences such as global warming and sea
level rise
• The chemistry of groundwater, and the corrosion potential for various construction
materials
Groundwater within or moving through naturally acidic or alkaline soils, organic soils and
soils contaminated from industrial processes can be corrosive to the reinforcing in concrete
liners. Groundwater rich in sulfates, chlorides, and/or with high pH can result in degrad-
ation of the concrete of the tunnel liner. As a general practice, chloride and/or sulfate con-
centrations greater than 500 ppm are corrosive (FHWA, 2017).
For the tunnel construction process, the engineer is faced with all the above concerns, but
limited in time to variability within the period of construction. In addition, the short-term
Geotechnical investigations for segmental tunnel lining design 67
manifestation of water flow and ground stability during the excavation process should be
considered. Several texts have been developed (see Bibliography) that address the evaluation
of hydrogeologic properties, estimating groundwater inflow rates, and other specific ana-
lyses that are required for design, and are beyond the scope of this book.
2.3.7 Seismic considerations
Historically, the tunnel industry has considered tunnels to be naturally resistant to seismic
movements, as they did not experience the same high levels of shaking as surface structures.
This perception was supported by the relatively good historic performance of tunnels and
underground structures, especially of tunnels in rock during large earthquakes. Dowding
and Rozen (1978) presented one of the first compilations of damage to rock tunnels due to
earthquake shaking. They collected information on 71 tunnels and compared their response
to ground shaking to estimated peak ground accelerations (PGAs) and peak ground veloci-
ties (PGVs).
Hashash, Hook, Berger, and Yao (Hashash et al. 2001) summarized the state-of-the-
art for seismic analysis and design for underground structures, as part of the activities of
the International Tunneling Association (ITA) Working Group 2. This research placed par-
ticular emphasis on practice within the United States. The report provides a summary of the
historical performance of underground structures under seismic loading and an introduc-
tion to the types and magnitude of movements and shaking that tunnels can be subjected
to under seismic events (see Figure 2.1). Additionally, the report describes approaches to
quantify those effects, aspects of seismic design criteria and traditional (primarily linear
elastic) closed form methods and approaches for analysis.
The following provides general observations regarding the performance of under-
ground structures when subjected to shaking during seismic events [from Hashash
(2001)]:
Other considerations for areas with potentially liquefiable soils to include buoyancy ana-
lyses and the effects of shear strength loss (and increases in lateral earth pressures) on the
lining systems.
Geotechnical investigations for segmental tunnel lining design 69
• To gather available site history and subsurface information at the conceptual stage to
guide later investigations and gain a general understanding of the geology and general
subsurface conditions to be encountered.
• To provide guidance in interpreting between boreholes or other investigative meas-
ures. The general understanding gained from the desktop study guides the geotech-
nical engineer in developing the appropriate ground investigation program required
to establish an engineering design.
A select list of typical reference sources that can often be found online include the
following:
For tunnels and construction projects in urban areas, the Sanborn map collection in the
United States is a useful tool to identify where old buildings and potential buried obstruc-
tion are located. The map series dates from approximately 1867 into the 1970’s and has
been updated at approximately 10-year intervals for the purpose of assisting fire insur-
ance agents in assessing the fire hazard of structures for underwriting. Sanborn maps can
typically be found in public libraries or from on-line sources. To the engineer, the Sanborn
map series presents a chronology of structures, streets, and utilities over time, and can
guide geotechnical investigation and planners on where old or buried structures may be
located.
2.5.1 Planning stages
The questions to be answered during the early planning stages of a project typically involve
an overall understanding of the geotechnical environment. Regional features and general
geologic history are typically developed from the desk-top study described above. However,
the planning phase of a project warrants the following investigations:
• Topographic information
• Such as LiDAR models and topographic survey to define the geometry of a project
area and establish a reference grid for design development
• Borings and test pits
• Performed in a grid pattern to establish the three-dimensional conceptual model
of major earth strata and material types including rock, if within the tunnel
horizon.
• While many Codes provide guidance or prescribe minimum boring frequency, the
Engineer must adjust these values based on the complexity and unique nature of the
geology for each project site.
• Water wells
• To identify and monitor the hydrogeologic regime over time.
• Index testing
• To properly classify materials and establish the basic approach to design.
Geotechnical investigations for segmental tunnel lining design 71
2.5.3 Construction stages
The contractor’s precast segmental tunnel lining design often requires a refinement and
expansion of the geotechnical information and laboratory data that was collected for the
project design. At this stage of a project, the contractor is focused on answering the specific
details of quantifying materials and establishing construction performance predictions for
use in both project planning, execution, and final price development. While specific to each
project, the information required for construction planning often includes the following.
upon the degree of uncertainty, borings made during the preliminary phase are typically
widely spaced and extended to depths two to three diameters below the planned tunnel.
Where surface features preclude the drilling of vertical boreholes along the alignments,
inclined borings can be used to intersect the planned tunnel location at depth. After the
tunnel profile is established, the boring spacing for most projects is reduced, and borings
advanced 1.5 to 2 diameters below the tunnel invert. AASHTO provides guidelines for
boring spacing for bridges and highway structures based on ground conditions as shown
in Table 2.5.
Table 2.6 presents boring spacing recommendation by the U.S. Army Corps of Engineers
for rock tunnels.
Geotechnical borings are performed as part of most subsurface investigations, as they
allow for the direct sampling of subsurface materials. Borings or, more specifically, open
boreholes are needed to enable direct measurement of groundwater levels, sampling of
groundwater for environmental analyses, permeability testing at prescribed depth intervals,
and certain in situ testing methods.
Sampling methods must be selected based on the character of the subsurface mate-
rials and the intended laboratory testing regimen. For granular soil or cohesive soil
where undisturbed samples are not needed, a common sampling method is the Standard
Penetration Test (SPT), for driving a split-barrel sampler into the soil with repeated
blows of a 63.5 kg (140 lb) hammer free-falling 760 mm (30 inches) (ASTM D1586).
The SPT N-value is determined from the number of hammer blows needed to drive the
sampler 300 mm (1 foot) into the soil. The N-value can be used to estimate the friction
angle and relative density of granular soil, and shear strength of cohesive soil based on
published correlations as described in Section 2.6. Soil captured within the sampler is in
a disturbed state and is typically used for visual classification and certain index tests in
the laboratory.
Where undisturbed samples of cohesive soil are needed for consolidation or triaxial
strength testing, thin-walled tube samples are obtained by direct push methods using spe-
cially designed tooling (ASTM D1587). Like the SPT method, the thin-walled sampling
Geotechnical investigations for segmental tunnel lining design 73
Table 2.6
G uidelines for Assessing Exploration Needs for Tunnel in Rock (USACE, 1997).
Summary of guidelines for assessing geotechnical exploration needs in rock
conditions as published by U.S. Army Corps of Engineers in 1997
device is typically 600 mm (2 feet) in length, thus requiring that the sampling interval be
prescribed in advance based on available subsurface information or determined in the field
based on observation of recovered soil.
In cases where continuous recovery of soil strata is needed, the SPT or thin-walled sam-
pling methods may prove too cumbersome or time consuming. Sonic drilling may be a
cost-effective alternative, as this method enables the retrieval of continuous soil or sedi-
ment cores up to 6.0 m (20 feet) or more with each trip out of the borehole. As the method
involves high-frequency vibration during advance of the sampling barrel, the in situ soil
structure is likely to be disturbed.
• When vertical fracture features are present that cannot be intercepted by vertical bor-
ings, or
• Where the cost of drilling through deep overburden soils above rock can be avoided.
The horizontal boring is made by drilling a horizontal or inclined hole through over-
burden soils using a directional drill to reach the tunnel profile and then drilled horizon-
tally. Advantages of directional drilling is that several vertical boreholes can be replaced by
drilling horizontally, and a continuous record of ground conditions is provided along the
tunnel profile.
74 Handbook of Precast Segmental Tunnel Lining Systems
service vessels for work over water. Some tunnel alignments, however, may pass beneath
areas that are inaccessible due to land use or local geology, or where access agreements or
temporary easements cannot be obtained. Although direct sampling of subsurface materials
may not be possible under such circumstances, valuable insight into local geomorphology
and surficial hydrology may be gained from high resolution aerial photography and LiDAR
survey from manned or unmanned aircraft, or satellite imagery.
Geophysical methods for identifying variations in subsurface strata or the soil/bed-
rock interface include seismic refraction surveys, electrical resistivity, ground penetrating
radar (GPR), or the horizontal to vertical spectral ratio (H/V) method. While these meth-
ods require site access for personnel, each can be performed without the need for large
machinery or vehicles. GPR and H/V surveys can generally be performed by a single
operator with hand-portable, battery powered equipment. Careful consideration must
be given to the site constraints and limitations of each method when planning the site
investigation.
rock cores roughly 50 mm (2 inch) diameter from a borehole up to about 100 mm (4 inch)
diameter. Larger diameter tools are available if needed for certain down-hole testing that
may require larger core holes. Cores are typically retrieved in lengths of 1.5 m or 3 m (4.9
to 9.8 feet).
Core barrels are referred to as “double-tube” if the core sample is captured in a steel
sleeve that does not rotate with the barrel and bit. Specialty “triple-tube” core barrels,
containing an inner split barrel may be needed in weaker formations to protect the core
from damage when being extracted from the barrel. Water is pumped down through the
core barrel and circulated up the annular space along the drill string to cool the coring bit
and flush out pulverized rock. In deep boreholes, clay suspension or polymer drilling fluids
may be needed to efficiently evacuate drill cuttings. Proper selection of tooling and a skilled
driller are critical for obtaining high-quality cores and allowing for accurate measurements
of core recovery and RQD.
Oriented core drilling was developed to enable the measurement of fracture angle and
orientation, which are essential data for evaluation of block or wedge stability in tunnels
and excavations. The process involves etching a line of known orientation along the axis
of the rock core during drilling. Advances in optical (OTV) and acoustic televiewer (ATV)
technology have all but replaced oriented coring in practice, as the automated process and
data acquisition available today eliminate the cumbersome process of manually measuring
the angle and orientation of every fracture in an oriented core. Typical output from OTV/
ATV borehole logging are shown in Figure 2.5.
• The flat jack method involves measuring displacement caused by stress relief as a slot
is cut into a rock surface, then inserting and pressurizing a flat jack until the displace-
ment is recovered.
• The over-coring method involves measuring deformation at the base of a borehole as
stress is relieved by coring a larger diameter hole around a specialized deformation
gauge.
• The hydraulic fracturing method involves isolating a segment of borehole between
inflatable packers, then increasing fluid pressure in the test interval until a fracture
occurs in the borehole wall.
• The fluid pressure can stabilize, and several cycles of pressurization are conducted.
• Magnitude of the principal stresses are calculated from the recorded pressure
readings.
Table 2.7 In situ testing methods used in soil.
78
Summary of in situ testing methods used in soil as guidelines published by FHWA (2002)
79
various clay deposits.
newgenrtpdf
Table 2.7 (Continued)
80
Table and Symbol Legend
σ ho’ In-s ite horizontal effective stress E max Small strain Young’s modulus
Descriptions of the suggested use and limitations of each method are provided in the
references.
from local experience. Consultation and review from local qualified practitioners are
recommended.
Table 2.9 Guide for consistency of fine-g rained soils (DM 7.01, 1986).
Nomenclature for describing consistency of fine-g rained soils based on correlation to
the standard penetration test (SPT)________________
Estimated consistency
Estimated range of
Standard unconfined compressive
penetration strength
test (SPT) Estimated consistency based on standard
Item (blows/f oot) penetration testing (SPT) Metric Imperial
1 <2 Very soft <0.024 <0.25
(Extruded between fingers when squeezed) MPa tons/f t 2
2 2 to 4 Soft 0.024 to 0.25 to 0.50
(Molded by light finger pressure) 0.048 MPa tons/f t 2
3 4 to 8 Medium 0.048 to 0.50 to 1.00
(Molded by strong finger pressure) 0.096 MPa tons/f t 2
4 8 to 15 Stiff 0.096 to 1.0 to 2.00
(Readily indented by thumb but penetrated 0.192 MPa tons/f t 2
with great effort)
5 15 to 30 Very stiff 0.192 to 2.00 to 4.00
(Readily indented by thumbnail) 0.383 MPa tons/f t 2
6 >30 Hard >0.383 >4.00
(Indented with difficulty by thumbnail) MPa tons/f t 2
Triaxial compression tests are performed to develop undrained and drained strength
parameters and stress–strain relationships. The unconsolidated undrained (UU) triaxial
compression test (ASTM D2850) is performed with a confining pressure with no drainage
of the sample permitted. This test measures the undrained shear strength, cu, of the soil
sample. The friction angle, ø, is assumed as zero since there is no drainage during the test.
For the consolidated undrained (CU) triaxial compression test (ASTM D4767), the sam-
ples are first consolidated and stabilized at a defined confining pressure and then sheared
in compression without drainage. One of the reasons that the soil sample is consolidated is
to compensate for the sample disturbance that occurs after removal of in situ overburden
pressure during sampling. Measurements during testing of axial load, axial deformation,
and pore water pressure permit determination of both total and effective stress paths in the
sample, as well as total and effective shear strength parameters, cohesion, friction angle and
modulus of elasticity, E.
The consolidated drained (CD) triaxial compression test (ASTM D7181) is consolidated
and sheared at a specific strain rate to permit drainage without an increase in pore pressure
during shearing. Effective stresses and drained soil parameters, c’ and ø’, and modulus of
elasticity, E’ are determined from this test.
estimated based on local experience or empirical correlation with SPT blow counts and/or
cone penetration resistance.
Presence of larger particles such as cobbles and boulders in a non-cohesive soil typically
increase the shearing capacity of a soil and therefore the design friction angle. Quantifying
the proportion of the subsurface strata comprising cobbles and boulders may not be pos-
sible, and sampling cobbles or boulders in the subsurface is difficult and time-consuming.
Additionally, cobbles and boulders may result in refusal of CPT tooling or lead to erro-
neously high SPT N-values and can lead to an over-estimate of design values, as well as
resulting in complications during construction. Sonic drilling using 20 mm to 25 mm (0.75
to 1.0 inches) diameter casing has been used successfully to penetrate and sample soils with
appreciable cobbles and boulders.
Unconfined compressives
Strength (q u)
Item Intact rock material Metric Imperial Ratio q u/q t
1 Berea sandstone 73.8 MPa 10,700 psi 63.0
2 Navajo sandstone 213.9 MPa 31,030 psi 26.3
3 Tensleep sandstone 72.4 MPa 10,500 psi
4 Hackensack siltstone 122.7 MPa 17,800 psi 41.5
5 Monticello Dam sandstone (greywacke) 79.3 MPa 11,500 psi
6 Solenhofen limestone 244.8 MPa 35,500 psi 61.3
8 Bedford limestone 51.0 MPa 7,400 psi 32.3
9 Tavernalle limestone 97.9 1MPa 14,200 psi 25.0
10 Oneota dolomite 90.3 MPa 13,100 psi 29.8
11 Flaming Gorge shale 35.2 MPa 5,100 psi 167.6
12 Micaceous shale 75.2 MPa 10,900 psi 36.3
13 Dworshak Dam gneiss (45° foliation) 162.0 MPa 23,500 psi 23.5
14 Quartz mica schist (ꓕ schistocity) 55.2 MPa 8,000 psi 100.4
15 Baraboo quartzite 319.9MPa 46,400 psi 29.1
16 Taconic marble 61.4 MPa 8,900 psi 53.0
17 Cherokee marble 66.9 MPa 9,700 psi 37.4
Geotechnical investigations for segmental tunnel lining design 85
Unconfined compressives
Strength (q u)
Item Intact rock material Metric Imperial Ratio q u/q t
18 Nevada Test Site granite 141.3 MPa 20,500 psi 12.1
19 Pikes Peak granite 216.2 MPa 32,800 psi 19.0
20 Cedar City tonalite 101.4 MPa 14,700 psi 15.9
21 Palisades diabase 241.0 MPa 34,950 psi 21.1
22 Nevada Test Site basalt 148.2 MPa 21,500 psi 11.2
23 John Day basalt 355.1 MPa 51,500 psi 24.5
24 Nevada Test tuff 11.4 MPa 1,650 psi 10.0
Table Legend and Notes:
q
u Strength or unconfined compressive strength of the rock
q
t Tensile strength of the rock
strength to tensile strength for a variety of rock types. While these generalizations are useful
to gain an understanding of the range of strength one can expect based on geology, it is not
recommended to use such generalizations as a basis of design. Site-specific laboratory test-
ing of rock is recommended, combined with an evaluation of local and regional fracturing
of the rock mass.
Intact rock strength is typically determined by laboratory uniaxial or triaxial testing of
core specimens recovered during subsurface investigations. Due to the variability of rock
strength and the presence or absence of core imperfections, a series of tests should be per-
formed to determine the typical range of strength for each rock type encountered.
Intact rock strength can be highly anisotropic in metamorphic rock with well-developed
foliation or cleavage, and in sedimentary rock exhibiting prominent bedding. Point load
strength index (PLSI) testing (ASTM D5731) is a simple and inexpensive way to test sam-
ples in the field to estimate compressive strength and the anisotropy index, or ratio of
strength perpendicular to or parallel to natural planes of weakness. It should be noted,
however that the Point Load Strength index should be used with caution as results for rock
with compressive strength below about 25 MPa (3,625 psi) may be unreliable.
Hoek and Brown developed a method to estimate the strength and deformation character-
istics of jointed rock masses based upon the geological strength index (GSI), a rock mass
rating system developed by Hoek (1994), which considers the lithology, structure and sur-
face conditions of the discontinuities within the rock mass as shown in Figure 2.6. The GSI
is used to reduce the laboratory determined values of uniaxial compressive strength σci, and
material constant mi, related to the frictional properties of the rock, to appropriate values
for the in situ rock mass. The Hoek–Brown failure criterion is one of the most common
models for estimating the shear strength of rock with closely spaced discontinuities. A more
in-depth discussion of the Hoek–Brown failure criterion and GSI, and its utilization, is
found in (Hoek–Brown, 2018)
86 Handbook of Precast Segmental Tunnel Lining Systems
The use of GSI assumes an isotropic rock mass and should only be applied where discon-
tinuities are closely spaced compared to tunnel diameter. The rock can then be considered
as a homogeneous and isotropic mass of interlocking blocks and wedges.
Where the rock mass consists of strong, blocky rock with large block size relative to the
tunnel diameter, the rock mass behavior will be controlled by the displacement of blocks
or wedges along discontinuities that may be an order of magnitude weaker than the parent
Geotechnical investigations for segmental tunnel lining design 87
material. Under such conditions, the blocks and wedges should be treated individually.
Computer programs such as “UnWedge” utilize block theory to enable 3D analyses of
blocky rock stability. Careful consideration must be given to the selection of discontinuity
strength parameters in such analyses. Barton (2013) has contributed a great deal of research
into shear strength of rock fractures, the non-linear shear behavior of rock joints, and
displacement-dependent joint roughness. The Barton–Bandis joint model can be applied in
“UnWedge” and other jointed rock modeling software where appropriate.
from the modulus of subgrade reaction of the surrounding ground multiplied by the tribu-
tary length of lining on each side of the node (FHWA, 2009).
The modulus of subgrade reaction is an empirical parameter that is dependent on the type
of soil or rock, the model selected for the analysis, as well as the tunnel diameter. While
there are many publications that document limitations of the use of the modulus of sub-
grade reaction in tunnel liner design, it remains common in many engineering offices and
agencies, and has been used in many successful projects. It is crucial that the modulus of
subgrade reaction (k) is selected by a qualified geotechnical engineer.
m
σ′
E = Eref (2.2)
pref
where
E =stress dependent modulus
Eref =reference soil modulus corresponding to the reference confining pressure pref
m =power for stress-level dependency of stiffness
σ’ =effective stress
For sands, development of soil hardening model parameters typically relies on correla-
tions from field data, particularly CPT and DMT, full scale testing, and local experience.
Laboratory results, including triaxial and consolidation tests, are typically used to derive
90 Handbook of Precast Segmental Tunnel Lining Systems
parameters for clays based on calibration. Typical reference modulus for sand typically
ranges between 10 MPa and 50 MPa (1,450 to 7,250 psi) at reference pressure of 100 kPa
(14.5 psi), depending on the relative density. For soft clays, the reference modulus can be in
the 1 MPa to 5 MPa (145 to 725 psi) range (at pref of 100 kPa) (14.5 psi). The value “m”
can be about 0.5 to 0.6 for sand and silt, and about 1.0 for soft clay.
Many available soil hardening models also consider the high soil stiffness at the small
strain level (typically defined as lower than 10-5). Research has shown that constitutive
models considering the small strain stiffness can provide a more realistic ground settle-
ment trough (e.g. Brinkgreve et al. 2006). The input parameters for small strain stiffness
are typically developed based on measuring the shear wave velocity in the laboratory or
in the field.
be used in design. The parameters are typically custom tailored for the analytical methods
employed by the designer.
The specific use and limitations of these reports should be clearly stated. The DMs should
be used for its intended purpose and the recommendations and data in it not extrapolated
for other uses or used by other parties without consultation with the geotechnical engineer.
Typical examples would include a memorandum describing the geotechnical design param-
eters for a structural analysis, or a pre-bid interpretation of geotechnical factors affecting a
construction bid.
a common interpretation of the materials and geotechnical behavior for the specific purpose
and use of a contractor developing his bid price, and in defining the criteria for additional
contractor compensation and/or schedule extension should conditions be encountered that
are different than presented in the GBR at the time of the contractor’s bid.
The use of GBR’s on tunnel and underground construction was conceived and developed
during the implementation of the Washington DC Metro system in the 1970’s and has
since been refined and expanded into common use on underground projects. Guidelines
for the development and use of GBR’s has been summarized in an ASCE publication
titled: “Geotechnical Baseline Reports for Underground Construction– Guidelines and
Practices” [18].
BIBLIOGRAPHY
For preparation of this chapter, the following references were used, which are categorized into two
categories of authority published documents and authored documents.
REFERENCE PAPERS
Atkinson, J.H., Sallfors, G. (1991). Experimental Determination of Soil Properties. Proceedings of the
10th ECSMFE, Florence, Volume 3, pp. 915–956.
Barton, N. (1988). Rock Mass Classification and Tunnel Reinforcement Selection Using the Q-System,
Rock Classification Systems for Engineering Purposes, ASTM STP 984, Louis Kirkaldie (Ed.),
American Society for Testing and Materials, Philadelphia, PA, pp. 59–88.
Barton N. (1991), Geotechnical Design, World Tunneling, November 1991, pp. 410–416.
Barton, N. (2002). Some New Q-Value Correlations to Assist in Site Characterization and Tunnel
Design. International Journal of Rock Mechanics & Mining Sciences Volume 39, pp.
185–216.
Barton, N. (2013). Shear Strength Criteria for Rock, Rock Joints, Rockfill, and Rock Masses: Problems
and Some Solutions. Journal of Rock Mechanics and Geotechnical Engineering Volume 5,
pp. 249–261.
Barton, N., Lien, R. and Lunde, J. (1974). Engineering Classification of Rock Masses for the Design
of Tunnel Support. Rock Mechanics, Volume 9, No. 4, pp. 189–236.
Bieniawski, Z. T. (1979). The Geomechanics Classification in Rock Engineering Applications,
Proceedings, 4th International Society of Rock Mechanics (ISRM) Congress, Montreux. A.
A. Balkema, Rotterdam, Volume 2, pp. 41–48.
Bieniawski, Z. T. (1984). Rock Mechanics Design in Mining and Tunneling. A.A. Balkema, Rotterdam,
272 pages.
Bieniawski, Z. T. (1989). Engineering Rock Mass Classifications: A Complete Manual for Engineers
and Geologists in Mining, Civil and Petroleum Engineering. Wiley, New York, 251 pages.
Bieniawski, Z. T. (1992). Design Methodology in Rock Engineering. A.A. Balkema, Rotterdam,
198 pages.
Bieniawski, Z.T. (1973). Engineering Classification of Jointed Rock Masses. Transactions of the South
African Institution of Civil Engineers, Volume 15, No. 12, Dec. 1973, pp. 335–344.
Bieniawski, Z.T. (1974). Geomechanics Classification of Rock Masses and Its Application in
Tunneling. In Advances in Rock Mechanics, Proceedings of 3rd International Congress,
Society of Rock Mechanics, Denver, 1974, Part A, pp. 27–32. National Academy of Science,
Washington, DC.
Bieniawski, Z.T. (1978). Determining Rock Mass Deformability–Experiences from Case Histories.
International Journal of Rock Mechanics and Mining Science & Geomechanics Abstracts,
Volume 15, pp. 237–247.
Brinkgreve, R.B.J., Bakker, K.J. and Bonnier, P.G. (2006). The Relevance of Small-Strain Stiffness in
Excavation and Tunnelling Projects. Proceedings of 6th European Conference on Numerical
Methods in Geotechnical Engineering, Graz-Austria, September 6–8, pp. 133–139.
Canadian Geotechnical Society (1992). Canadian Foundation Engineering Manual. Canadian
Geotechnical Society, Richmond, BC.
Casagrande, A. (1948). Classification and Identification of Soils. Transactions ASCE, Volume 113,
pp. 901–932.
Deere, D.U. and Deere, D.W. and United States Army Corps of Engineers (1989). Rock Quality
Designation (RQD) After Twenty Years; Issue 89, Part 1 of Contract Report, US Army Engineer
Waterways Experiment Station, Mississippi.
Duncan, J.M. and Chang, C.Y. (1970). Nonlinear Analysis of Stress and Strain in Soil. ASCE Journal
of the Soil Mechanics and Foundation Division, Volume 96, pp. 1629–1653.
Edgerton, W. (2008). Recommended Contract Practices for Underground Construction. Society for
Mining, Metallurgy, and Exploration, Littleton, CO.
Geotechnical investigations for segmental tunnel lining design 95
Essex, R. (2007). Geotechnical Baseline Reports for Construction, Suggested Guidelines. American
Society of Civil Engineers, Reston, VA.
Federal Highway Administration (2009). Technical Manual for Design and Construction of Road
Tunnels –Civil Elements, FHWA-NHI-10-034. U S Department Of Transportation; Federal
Highway Administration; National Highway Institute, Washington, DC.
Goodman, R.E. (1993), Engineering Geology– Rock in Engineering Construction, John Wiley,
New York.
Goodman, R.E. and Shi, G.H. (1985). Block Theory and Its Application to Rock Engineering, Prentice
Hall, New Jersey.
Hashash et al. (2001). Seismic Design and Analysis of Underground Structures, Tunnelling and
Underground Space Technology, Volume 16, Issue 4, 2001, pp. 247–293, ISSN 0886-7798,
https://doi.org/10.1016/S0886-7798(01)00051-
Hatem, D. (1997). Geotechnical Baselines–Professional Liability Implications. The Central Artery/
Tunnel (CA/T), Professional Liability Reporter, Volume 3, No. 1.
Heuer, R.E. (1974). Important Ground Parameters in Soft Ground Tunneling. Proceedings of Specialty
Conference on Subsurface Exploration for Underground Excavation and Heavy Construction,
ASCE, New York.
Hoek, E. (1982) Geotechnical Considerations in Tunnel Design and Contract Preparation. Journal of
Mines, Metals and Fuels, Volume 30, No. 1, pp. 573–584.
Hoek, E. and Brown, E.T. (1980). Underground Excavations in Rock. Institution of Mining and
Metallurgy, London, 527 pages.
Hoek, E. and Brown, E.T. (2018). The Hoek–Brown Failure Criterion and GSI–2018 Edition. Journal
of Rock Mechanics and Geotechnical Engineering, Volume 11, pp. 445–463.
Hoek, E. and Diederichs, M.S. (2006) Empirical Estimation of Rock Mass Modulus. International
Journal of Rock Mechanics and Mining Sciences, Volume 43, pp. 203–215. http://dx.doi.org/
10.1016/j.ijrmms.2005.06.005
Hoek, E. and Marinos, P. (2000) GSI: A Geologically Friendly Tool for Rock Mass Strength Estimation.
ISRM International Symposium, Melbourne, Australia. ISRM-IS-2000-35.
International Tunneling Association (ITA) (1988). Guidelines for the Design of Tunnels. Tunneling
and Underground Space Technology, Volume 3, No. 3, pp. 237–249 (April).
International Tunneling Association (ITA) (1997). Immersed and Floating Tunnels State of the Art
Report, Working Group No.11, Tunneling and Underground Space Technology, Volume 12,
No. 2 (April).
Janbu, N. (1963). Soil Compressibility as Determined by Oedometer and Triaxial Tests. Proceedings
of ECSMFE, Volume 1, pp. 19–25.
Law, T.C.M. and Moore, I.D. (2007). Numerical Modeling of Tight-Fitting Flexible Liner in Damaged
Sewer Under Earth Loads. Tunnelling and Underground Space Technology: Special Issue on
Trenchless Technology, Volume 22, Issues 5 and 6, pp. 655–665.
Liu, T.K. (1967). A Review of Engineering Soil Classification Systems. Highway Research Board
Record, Volume 156, pp. 1–22.
Meguid, M.A., Rowe, R.K., and Lo, K.L. (2002). 3-D Effects of Surface Construction Over Existing
Subway Tunnels. International Journal of Geomechanics, Volume 2, No. 4, pp. 447–469.
NAVFAC DM 7 (2011). Soil Mechanics, Foundations and Earth Structures, vulcanhammer.net, ISBN-
10: 1257064231.
NAVFAC DM 7 (2011). Soil Mechanics, Foundations and Earth Structures, vulcanhammer.net, ISBN-
10: 1257064231.
Norwegian Geotechnical Institute (2015). Handbook: Rock mass classification and support design
using the Q-System, NGI, Oslo.
Owen, G.N. and Scholl, R.E. (1981). Earthquake Engineering of Large Underground Structures.
Report no. FHWARD- 80195. Federal Highway Administration and National Science
Foundation, Washington, DC.
Peck, R. B. (1969). Deep Excavation and Tunneling in Soft Ground. Proceedings of the 7th International
Conference of Soil Mechanics, Mexico, State-of-Art Volume, pp. 225–290.
96 Handbook of Precast Segmental Tunnel Lining Systems
Proctor, Robert V, and White, Thomas L. (1977) Earth Tunneling with Steel Supports, Commercial
Shearing.
Robinson, C.S. (1972). Prediction of Geology for Tunnel Design and Construction. Proceedings of
Rapid Excavation and Tunnelling Conference, Chicago, 1972 (editors K.S. Lane and L.A.
Garfield), pp. 105–114. American Institute of Mining Engineers (AIME), New York.
Schmidt, B. (1969). Settlements and Ground Movements Associated with Tunneling in Soil. Ph.D.
Thesis, University of Illinois, Urbana and Champaign, IL, 448 pages.
Chapter 3
3.1 INTRODUCTION
The tunnel bore behind the tunnel-boring machine (TBM) during the excavation in the soft
ground and the fractured and weak rock formations are supported almost immediately by
the installation of precast concrete segmental rings. The thrust needed for TBM driving is
provided by jacks that push against the circumferential joints of the newly installed fully
erected segmental ring. In the last approximately 40 years, precast concrete segmental rings
have showed progressively increased use, not only functioning as the initial ground support
but also acting as the final lining, avoiding the installation of a final cast-in-place lining,
therefore termed a “one-pass lining” system. Precast segments must be designed to resist
the temporary loads from production, transportation and construction as well as permanent
loads from the ground and groundwater in the service stage.
DOI: 10.1201/9781032675541-3
98 Handbook of Precast Segmental Tunnel Lining Systems
The first four load cases in this table, i.e. segment stripping (demolding), segment storage
(stacking), segment transportation and segment handling are categorized as “production
and transient stages” loads. These load cases are analyzed and designed using similar meth-
ods and occur in early stages of production compared to others. The next four load cases in
Table 3.1, i.e. accidental TBM thrust jack removal, TBM thrust jack forces, tail skin back
grouting pressure and localized back grouting (secondary grouting) pressure are catego-
rized as “construction stages” loads. Finally, the last three load cases in Table 3.1 are the
governing load cases are categorized as “final service stages” loads, which all occur after
completion of construction of segmental rings where the lining is completely embedded in
the surrounding ground.
All other loads that may apply to segmental linings but are dependent on the intended
use, the specific configuration/arrangement or the specific location of the tunnel are referred
to as “other loads” in this chapter. Earthquake or seismic loads; loads of fire, blast and
explosion; loads specific to stacked arrangement of tunnel geometry; aerodynamic loads in
railway, subway or high-speed rail tunnels; mechanical, electrical, plumbing and overhead
catenary support (OCS) loads; train wheel weights, longitudinal forces of braking and train
derailment loads; loads due to internal pressure in tunnels subjected to high internal water
pressure; are fit into this category and the loading considerations are superimposed on the
final service stage load case.
Table 3.1, in addition to the most critical load cases, presents the required strength (U)
and the required resistance in service (Rs) for each critical load case expressed in terms of
load combinations of all possible action loads and load factors. The required strength (U)
is used for the ultimate limit state (ULS) design and the required resistance in service (Rs)
Load case 9 Earth pressure and groundwater U = 1.25(w ± WAp) ± 1.35(EH + EV) ±1.5 P 0;
load Rs = 1.0(w ± WAp) ± 1.0(EH + EV) ±1.0 P 0;
Load case 10 Longitudinal joint bursting U = 1.25(w ± WAp) ± 1.35(EH + EV) ±1.5 P 0;
Rs = 1.0(w ± WAp) ± 1.0(EH + EV) ±1.0 P 0
is used for the service limit state (SLS) design, which are the two most commonly specified
LRFD limit states by codes and regulations.
The load combinations and load factors in Table 3.1 are based on American Concrete
Institute (ACI) design codes of ACI 533.5R-20 and ACI 544.7R-16. Elsewhere in the world,
whenever local codes provide a different load combination and different load factor than the
ones shown in this table, those should be followed in lieu of the information in this table.
These load cases and their required strengths (U), together with analysis methods specific to
each load case are further explained in Sections 3.3 to 3.5 of this chapter. Performing ana-
lysis for each critical load case, the resulting internal forces of axial force, bending moment
and shear force are used for design of concrete and reinforcement, after applying reduction
factors on the strength of materials.
tunnels from the early stages of design through the final stages to ensure minimum required
size of tunnels for their specific intended use and service has been provided.
In single-track railroad and subway tunnels, as shown in Figure 3.1, the space proofing
at the early stages of design is done initially based on train’s static and dynamic clearance
envelopes considering the maximum super elevation in the tightest curve on the alignment,
track design and structure, size and elevation of safety walkways and emergency evacuation
corridor (egress space), and structure and envelop of the overhead catenary system (OCS)
contact line stays. The internal tunnel diameter is then determined by the smallest circle that
includes all these items and conditions and needs to be verified for providing sufficient ven-
tilation space. In addition, construction tolerances usually in the range of radial tolerance
of R =±4 inches (100 mm) recommended by ACI 533.5R-20 and DAUB:2013 should be
provided, which results in an additional 8 inches (200 mm) in diameter to be added to the
required internal structural boundary. This usually will determine the internal diameter of
the segmental ring during the tender design or early design stages. In later stages of design,
the sufficiency of the initially considered space is verified for inclusion of drainage trough,
and the electrical equipment and conduits, standpipe water pipes and other equipment such
as fire-telephone-cabinet (FTC), WIFI enclosures, blue light, blue light stations, handrails,
train antenna, train antenna power cable and lighting. Fire life safety requirements of NFPA
130 (2017) are recommended to be followed during the railroad or subway tunnel space
proofing exercise. In a double track or twin tunnel case, tunnel inner dimensions are add-
itionally governed by distance between the centers of tracks or the cross-passageways.
Analysis and design of precast segmental linings 101
In the road tunnels, the space proofing at the early stages of design is done based on
horizontal and vertical traffic clearances, shoulders, barriers, fans and spaces for ventila-
tion, size and elevation of emergency egress corridor, and size and elevation of FTC cabi-
nets (cabinets for hose reels, fire extinguishers and emergency telephones). One important
parameter that may have a significant impact on the shape and size of traffic clearances is
the maximum super elevation on the tightest curve on the alignment. The smallest circle
encircling all these clearances and elements in addition to 8 inches (200 mm) diametrical
construction tolerance defines the internal tunnel diameter during the tender design or
early design stages. In later stages of design, as shown in Figure 3.2, space proofing is veri
fied for the tunnel drainage, lighting, traffic control system, water supply pipes for fire-
fighting, passive fire protection, fiber optic cable and electric conduits, signals and signs
above roadway lanes, CCTV surveillance cameras, communication antenna and equip-
ment, and monitoring equipment of noxious emissions and visibility. Note that all new
road tunnels must conform to NFPA 502 (2017) standard requirements for fire life safety
which need to be strictly followed in the space proofing exercise. Also, when the area
under the roadway is designed for low-point pump station (LPPS), as shown in Figure 3.3,
space proofing should be done with respect to providing sufficient space for access stairs,
dry well, wet well, discharge pipe, drainage pipe, LPPS pump and sump pump in the lower
level of tunnel section.
102 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.3 Tunnel space proofing for TBM bored road tunnels at pump station.
Note: Typical space proofing for TBM-b ored road tunnels: section at low-p oint pump station.
Source: ITA WG 2, 2019.
For the wastewater or combined sewer overflow tunnels, the size of tunnel is defined by
the storage volume and occasionally based on volumetric flow rate of design storm, for
example a 100-year storm, set forth by local authorities and updated collection system mod-
eling. This is similar to sizing the water conveyance tunnels, which are often defined by the
design flow rate.
diameter. General observation from Figure 3.5 is that the ID-to-thickness ratio increases
with the tunnel diameter; however, this trend stops around tunnel diameters in the range
of 23 feet (7 m). Breaking the figure into different size categories, Figure 3.5 shows that
for the tunnel diameter under 13 feet (4 m), disregarding the higher and lower outliers, the
internal diameter-to-thickness ratio is in the range of 11 to 20. When the tunnel dimeter was
between 13 feet (4 m) and 18 feet (5.5 m), the internal diameter-to-thickness ratio is in the
range of 14 to 26 disregarding one high outlier datum.
104 Handbook of Precast Segmental Tunnel Lining Systems
Finally, when the tunnel dimeter was more than 18 feet (5.5 m), the internal diameter-to-
thickness ratio is in the range of 17 to 31. In addition, JSCE (2007) recommends that the
ring thickness should be less than 4% of the tunnel outer diameter, a statement that leads
to an internal diameter-to-thickness ratio of 23 or less. Considering all the information and
analysis, as the best practice, it is recommended to take initial ring thickness as 1/23rd to
1/20th of the internal dimeter (ID) for tunnels larger than 13 feet (4 m) in diameter, and 1/
15th of the internal dimeter (ID) for tunnels smaller than 13 feet (4 m) in diameter.
Segmental ring thickness in addition to providing sufficient structural capacity must sat-
isfy the conditions imposed by the contact joints. This means providing sufficient bearing
surface area at the circumferential joints compatible with TBM thrust jacks, sufficient bear-
ing surface at the longitudinal joints for transferring hoop forces without causing exces-
sive spalling stresses, and sufficient clear space for segment recesses, i.e. gasket recess and
stress relief recess. Also, from the durability perspective, the lining thickness, for example
in wastewater or combined sewer overflow tunnels, must account for an additional sacrifi-
cial lining thickness that will be sacrificed during the service life of tunnel due to microbial
induced concrete corrosion (Chapter 12). Due to durability considerations, DAUB:2013
recommends a minimum thickness of 12 inches (300 mm) for one-pass tunnel linings.
Tunnel lining outer diameter is determined simply by adding the thickness of segmental
ring to its internal diameter. The TBM shield outer diameter is obtained by adding tunnel
lining outer diameter to a so-called parameter “overcut,” a gap space between the segment
outer side (extrados) and the ground profile, which is filled by backfill annulus grout. This
gap space, which ranges from 4.5 inches (115 mm) to 10.8 inches (275 mm) (depending
upon the TBM diameter, ground condition and alignment curvature) is also equal to sum-
mation of the tail clearance inside the shield, shield skin plate thickness and an additional
TBM clearance with the ground at the tail due to the conical shape of the shield.
There is a clear relationship between the shield outer diameter and the minimum radius
of the tightest curve of the alignment as one can limit the other or vice versa. Historical data
from JSCE 2007 on the minimum curve radius versus shield outer diameter of more than
100 tunnel projects is presented in Figure 3.6. The best way to analyze this data is to cat
egorize them into three categories of shield outer diameter: less than 20 feet (6 m), between
20 and 32 feet (6 and 10 m) and more than 40 feet (12 m). As one can see, the upper bound
limit for minimum curve radius for all size categories is 1,650 feet (500 m), but the lower
bound limit for the minimum curve radius is a function of shield outer diameter category.
For shield outer diameter in 20 feet (6 m) or less, the minimum curve radius is limited to
about 260 feet (80 m), and for shield outer diameter in the range of 20 to 32 feet (6 to 10
m), the minimum curve radius is limited to about 520 feet (160 m). This is 990 fee (300 m)
for the largest shield outer diameter category of more than 40 feet (12 m). These numbers
can be used as a guide to provide a relationship between shield outer diameters and lower
bound limits for the radius of tightest curve in the alignment. Note that the minimum curve
radius is not only related to the shield outer diameter or vice versa, but also to the ring
geometry (taper and ring width), overcut, shield design (articulated or not), and radial gap
between segment and tail skin.
3.2.3 Ring length
Length of segmental rings or the width of segments historically ranges 2.5 to 8.0 feet (0.75
to 2.5 m) with tunnels with smaller diameters often times toward the lower side of this
range and the ones with larger diameters toward the upper side. The data collected from
Analysis and design of precast segmental linings 105
Figure 3.6 Tunnel minimum curve radius and TBM shield outer diameter.
Note: Relationship between minimum curve radius and TBM shield outer diameter.
Source: JSCE 2007.
more than 60 projects in Japan before 2006 (JSCE, 2007) presented in Figure 3.7 indicate
that while the ring length increases by the size of tunnel, the relationship is not very strong.
This can be justified as the ring length or segment depends also on the tightest curve radius
in the tunnel alignment. In addition, narrower rings are favorable for transportation and
erection simplicity, construction of curved alignments and reducing the length of shield tail.
Wider rings are favorable for reducing the production cost, numbers of joints, the total per-
imeter of gasket length in project, the number of bolt pockets where leakage may occur and
increasing the construction speed (JSCE, 2007).
Among other parameters, the ring length depends on the available space for segment sup-
ply and handling inside the shield, the segment production easement, the segment weight
and the weight limitations during transportation to the site on public roads as often the main
limiting condition. The length of the ring is taken as an optimized value considering all these
conditions and parameters and the efficiency of tunnel works. The best practice is to use a
ring length of 5 to 5.5 feet (1.5 to 1.7 m) for tunnel diameters of 19 to 23 feet (6 to 7 m), a
ring length of 6 to 6.5 feet (1.8 to 2 m) for tunnels of 23 to 30 feet (7 to 9 m) in diameter,
and a ring length of 6.5 to 7.5 feet (2 to 2.3 m) for tunnels larger than 30 feet (9 m). Most
advanced ring length optimization methods by BIM modeling is presented in section 3.2.8.
Figure 3.8 shows parallel rings, rings with parallel circumferential faces, which are per
pendicular to the tunnel axis. These rings are not inherently suitable for curved alignments
and since most tunnels have curves, negotiating alignment curves is only possible through
the use of packers placed partially in circumferential joints. This ring system cannot be
Analysis and design of precast segmental linings 107
properly sealed because packers reduce the compression in the gasket. Even in straight
alignment, rings can never be built perfectly straight and adopting methods to restore line
and grade require use of packers, which leads to sealing issues.
In parallel rings with corrective ring systems, corrective rings (up, down, left or right ring)
replace packers for negotiating curves. Up rings are the rings that do not have two parallel
circumferential faces and at least one face of the ring is tapered in a way that a sequence of
these rings turn in upward direction when key segment is located at or in the proximity of
the crown. By keeping the key segment in that place, in similar fashion but with a different
taper, the down rings turn in the downward direction, the left rings turn in the left and the
right rings turn in the right direction. The main disadvantage of this system is the require-
ment for different types of formwork sets, which are cost prohibitive.
The right/left ring is a type of ring that tapered in a way that when the key segment is
above the springline, the ring turns in the right or left direction. Figure 3.9 shows most
common right/left ring system with one circumferential face (often the front face) perpen-
dicular to the tunnel axis and the other face (often the rear face) inclined to the tunnel axis
with a slightly longer length on the right or left side when looking at the elevation view of
the ring. The difference between maximum and minimum ring length is called ring taper.
The entire tunnel lining can be built with different sequences of these right and left rings.
The sequence of right-tapered (right) and left-tapered (left) rings produces a straight align-
ment or a tangent alignment whereas a sequence of right-right ring, as shown in Figure 3.9,
results in a curve to the right, and left-left ring produces a curve to the left with a minimum
system radius.
Upward and downward turns/curves are achieved through rotation of the right or left
rings by 90 degrees. Instead of using right/left rings and following same concept but with
a taper in a different axis, the entire tunnel can be built with up/down rings. On up/down
rings, when looking at the plan view of the ring, the most common taper is when the ring
has one face (often the front face) perpendicular to the tunnel axis and on the other face
(often the rear) is tapered in a way that it has a slightly longer length on the upward or
downward side. Right/left rings and up/down rings have been also made of rings with
double taper, i.e. tapers on both faces of the rings with half of the required taper on each
end face of the ring to turn in the rings in the desired directions. Using the right/left or up/
down ring system, it is possible to always have the key segment on the top and, therefore,
108 Handbook of Precast Segmental Tunnel Lining Systems
to be able to build the ring from the bottom upward, which is preferable to some contrac-
tors. The right/left or up/down ring system provides a proper sealing performance for an
impermeable tunnel, with the only disadvantage being requiring different types of form-
work set.
In the universal ring system, the key segment can be located anywhere in the tunnel
including below the springline and at or near the invert. With this system, the ring can
turn in any desired direction of up, down, left, right and their combinations. As shown
in Figure 3.10, universal rings are often built with both circumferential faces of the ring
inclined to the tunnel axis. Nonetheless, universal rings with only one tapered side –prefer-
ably the rear face –are occasionally used. Depending on having both circumferential faces
of the ring tapered or only one, the required ring taper is divided in one or both ends of the
universal rings. Equation (3.1) can be used to calculate the required ring taper (k) based on
the size of the ring and tightest curve in the alignment.
k = ∅ A .bm /R (3.1)
where
∅ A is outer diameter of the segmental ring
bm is the average ring length at the tunnel springline
R is the minimum curve radius
It is necessary to consider the effect of correction curve drives, which are required in the
potential events of deviations from the theoretical alignment in order to return the tunnel/
TBM back into the designed alignment. The minimum curve radius should be taken at least
20% less than the smallest curve radius in the horizontal or the vertical alignment (ACI
533.5R-20, DAUB:2013). Figure 3.10 shows how straight drives or tangent alignments and
different curves and directional turns can be negotiated through the rotation of the universal
segmental ring.
Analysis and design of precast segmental linings 109
In order to develop a straight drive or tangent alignment with universal rings, every
other ring must be turned by 180° in reference to the previous one. This means that if we
start with a ring that have a taper on the upward and downward sides with a key segment
located on the top at or near the tunnel crown (similar to up ring), by rotating the next ring
by 180°, the key segment will be located in the bottom at or near the tunnel invert. For
minimum right or left curve radius, such a universal ring must be rotated by 90o resulting
in the key segment placement at or near the tunnel springline. Such a design is preferred by
some designers and contractors who prefer to place the key segment where the ring length
is the narrowest.
Universal rings can be tapered alternatively on the right and left sides of the rings with the
key segment being located at or near the tunnel crown. While placement of the key segment
above the springline for the entire alignment is not an inherent characteristic of this ring
system, in recent years and using advanced software for guiding TBM, universal rings can
negotiate the curves and straight drives with keys always above springline through adjusting
the drive error of less than fractions of an inch (a few millimeters) in two or three rings. The
main advantage of the universal ring system is the requirement for only one type of form-
work set (ÖVBB 2011).
3.2.5 Ring segmentation
The number of segments that comprise a ring is one of the main parameters for the design
of segmental tunnel linings. From transportation, handling and erection process perspec-
tive, shorter segments or higher number of segments that comprise a ring is preferred.
Nonetheless, longer segments or a smaller number of segments that make up a ring results
in a stiffer segmental ring, reduced production cost, less hardware for segment connection,
shorter gasket length for entire project, fewer number of bolt pockets where cracking and
leakage can occur, and increased construction speed.
In tunnels smaller than 20 feet (6 m) in diameter, maximum segment lengths are nor-
mally limited by the space available to turn the segments inside the TBM shield and in the
backup gantries behind the shield. In larger tunnels, the weight of segment and its structural
capacity are usually the main factors for deciding maximum length of segments. For this
purpose, a parameter called segment slenderness (λ) is presented, which is defined as the
ratio between the breadth or curved length of segment along its centroid and the segment
thickness. Review of previous tunneling projects indicate that segment slenderness is usually
between 8 to 13. Up until a few years ago, slenderness ratio for fiber-reinforced concrete
(FRC) segments were limited to 10. Nonetheless, in recent years and with the introduction
of high-strength steel and advanced and innovative anchorage technologies for fibers, FRC
segment with slenderness of more than 10 and up to 13 have been used (ACI 544.7R-16;
Bakhshi and Nasri, 2017a; Beňo and Hilar, 2013; Harding and Francis, 2013; ITA Working
Group 2, 2016). General criteria for ring segmentation of tunnels larger than 20 feet (6 m)
in diameter can be expressed as dividing the ring into as many segments that result in a
single segment’s slenderness ratio of 10 or higher.
In order to provide a guideline on the ring segmentation based on the tunnel size,
numerous authors have done an extensive review of previous TBM tunnel projects
(Bakhshi and Nasri, 2018). Results of this review indicate that TBM tunnels can be
divided into five different size categories shown in Table 3.2 according to the number of
segments in a ring. While Table 3.2 presents most common cases in practice, there will
110 Handbook of Precast Segmental Tunnel Lining Systems
be segmental ring segmentations for different sizes that are not shown in this table. In
general, the most common configurations comprise of an even number of segments with
an odd number of ordinary segments and one key segment, usually one-third the size of
ordinary segments, or with an even number of ordinary segments and two key segments.
Such a design is most compatible with an even number of TBM thrust pads as often three
pads push against each ordinary segment and one pad pushes against the small key seg-
ment. On occasions, key segments are smaller than one-third or as large as half or full size
of ordinary segments.
For tunnels 20 feet (6 m) in diameter or less, a ring division into six segments is typical.
The most common configuration is five ordinary segments and one small key segment, also
known as 5+1 configuration (Figure 3.11). Also, a ring segmentation into four ordinary
segments and two smaller key segments (one at or near invert and one at or near crown)
also known as 4+2, is common. For this size of tunnel, sometimes a ring segmentation with
three ordinary segments (e.g. each covering 72o on tunnel perimeter), two counter key seg-
ments (e.g. each covering 56.5o on tunnel perimeter), and one key segment (e.g. covering
31o on tunnel perimeter) also known as 3+2+1, or sometimes a ring segmentation with six
segments of the same length including the key segment (each covering 60o on the tunnel per-
imeter) have also been used. The same configuration concept consisting of an even number
of segments with an odd number of ordinary segments and one or key segment, or with an
even number of ordinary segments and two key segments is utilized and is the most common
also for tunnels 26 to 36 feet (8 to 11 m) in diameter as well as for tunnels larger than 46
feet (14 m) in diameter.
As shown in Table 3.2, 7+1 and 6+2 are the most common ring segmentations for the
former category, and 9+1 with either small or large key and 11+11 are the most common
ring configurations for the latter group. However, when the tunnel is 20 to 26 feet (6 to 8
m) in diameter or when the tunnel dimeter ranges 36 to 46 feet (11 to 14 m), for example,
a 5+1 ring configuration with a small key for the former category and a 7+1 with a small
key for the latter may result in very long segments with potential weight issues and insufficient
structural capacity. Solutions adopted for tunnels in the range of 20 to 26 feet (6 to
8 m) in diameter, is either to use a 5+1 ring configuration with a large key (6 segment ring
Analysis and design of precast segmental linings 111
configuration) to reduce the length of ordinary segments, or adopting a 6+1 ring segmentation
with a small key, which is not ideal but can solve the issues related to the length of
segments. Similarly, for tunnels between 36 and 46 feet (11 and 14 m) a 7+1 ring configur-
ation but with a large key (eight segment ring configuration with each segment covering
45o on tunnel perimeter) or a 7+1+1 ring configuration with basically same segmentation as
eight segment ring but this time with dividing one full segment in one-third and two-third to
create key (covering 15o on perimeter) and counter key segment (covering 30o on perimeter).
3.2.6 Segment shape
Individual segment geometry can be categorized into four main categories of hexagonal,
rectangular, trapezoidal and rhomboidal segment systems.
The oldest segment geometry system is the hexagonal system shown in Figure 3.12. In
this system, TBM does not need to stop for the ring build as TBM jacks can thrust against
counter key segments (half of the ring) while erecting and installing the other half of the ring
112 Handbook of Precast Segmental Tunnel Lining Systems
in shape of key segments. Then for the next ring, TBM jacks push against newly installed
half of the ring while the other half of the ring can be erected in an open teeth condition.
Disadvantages of this system include discontinuous ring build with this system, suscepti-
bility of gap opening between segments over successive rings, and inefficiency of gaskets in
this system for sealing the tunnel. Because the hexagonal segment system compromises the
watertightness of the tunnel, it is now only being used in long straight (tangent alignment)
tunnels where water infiltration is not a concern, or in part of two-pass lining system as
the first lining system. When this system is adopted and especially in conjunction with the
double-shield TBM it can result in very rapid advance rates.
In a rectangular system, all segments comprising a ring are in rectangular shape except
only the key and counter key segments that have a slightly tapered joint angle. With this
system, the ring is built continuously starting with erecting first the reverse key segment
(segment located opposite to key segment) and then erecting other segments, for example,
with a sequence shown in Figure 3.13 toward the key segment, which is installed last. The
main advantages of this system are the continuous ring build, efficiency of gaskets in sealing
the segment joints, and the simplicity of longitudinal joint geometry. However, there are
three major issues with this segment system.
First issue is the likelihood of star or crucifix joints as staggered joints are not inherently
guaranteed with these segments and sealing performance can be compromised.
Second issue is the difficulty of installing rectangular segments without impacting the gasket
on the adjacent segment because of the right angle at the joints.
Third issue is the difficulty of using fast-connecting dowels with this system because dowels
can withstand only limited construction tolerances compared to time-consuming bolting
systems. While bolts are fastened after complete segment insertion into the ring, dow-
els are preinserted into segments, which limits the segment approach path into a very
narrow path and may cause more friction between gaskets of adjacent segments (ACI
533.5R-20).
This system is still being used in large-diameter tunnels where there is a high demand for
shear capacity of connection system at the circumferential joints and the dowels unlike bolts
may not provide sufficient capacity.
Analysis and design of precast segmental linings 113
In trapezoidal segment system, all segments comprising a ring (usually an even number
of segments) are in trapezoidal shape and have the same length along the segment center-
line. As shown in Figure 3.14, half of the ring’s segments are reverse key type or counter
key type segments (wider on rear side of the ring) and the other half are key type segments
(narrower on the rear side of the ring). From the ring build perspective, as shown
in Figure 3.14, this system is similar to a hexagonal system assembled by erecting first
the reverse key type segments (e.g. segments 1, 2 and 3) like an in open-teeth configuration
and then erecting the key type segments in the gaps between them (e.g. segments
4, 5 and 6). The main advantage of this system is the creation of staggered longitudinal
joints from otherwise star or crucifix joints (in case of rectangular segments) for negoti-
ating most important drives in the alignment such as the tightest right/left or upward/
downward curves. See Section 3.2.8.2 for more details on this subject. Another advantage
of this system is that every other segment is a key type segment and therefore with this
configuration, there is a freedom to close the ring at almost any given location. The main
disadvantage is the discontinuous ring build process.
In the rhomboidal or parallelogrammical-trapezoidal segment system ordinary segments
are in the shape of parallelogram and only key and reverse key segments are in the shape
of a trapezoid. From the ring build perspective, for example as shown in Figure 3.15,
process starts with erecting trapezoid reverse key segment, which is No. 1, followed by
continuous placement of ordinary parallelogrammical segments Nos. 2 and 3 on each side
of reverse key segment, and then placing next ordinary segments Nos. 4, 5, 6 alternating
left and right, and finally closing the ring with the installation of key segment or segment
No. 7. Therefore, the ring is built continuously, from bottom to top, or right to left, or
vice versa.
Rhomboidal segment system is the most common segment shape system nowadays because
of eliminating all inherent disadvantages of previously discussed systems. First, this segment
system is compatible with efficient use of gaskets. This, together with replacing important
crucifix joints (present in rectangular segments) by the staggered joints provide the best
sealing performance among all systems. Continuous ring build process as explained above
is another major advantage of this system, especially when compared with trapezoidal seg-
ment system. Compatibility with use of fast-connecting dowels instead of time-consuming
114 Handbook of Precast Segmental Tunnel Lining Systems
and labor-intensive bolting procedure is another major advantage of this system. This is
due to angled/tapered longitudinal joints, which prevent early friction of the gasket of the
segment being installed with the gaskets of adjacent installed segment during the ring build
phase, resulting in reduced construction tolerance for connection devices and facilitating use
of dowels in circumferential joints.
where
‘R’ =radius
‘k’ represents the taper
‘D’ represents the tunnel outside diameter
‘bm’ is the ring length, which is aimed to be optimized
The local maximum deviation ‘Δmax’ is determined by the face angle ‘θ’ and length of the
ring ‘bm’. Since taper k =(Lmax – Lmin) is linearly proportional to the diameter, ‘D’, the same
Figure 3.16 Cone shape envelope of centerline locations for two adjacent rings.
Note: Possible ring centerline set-o ut resulting from all relative rotations of the ring.
116 Handbook of Precast Segmental Tunnel Lining Systems
face angle, ‘θ’, can be achieved for a fixed minimum path radius, ‘R’. Therefore, for a given
alignment, the diameter of the ring, ‘D’, has no direct impact on the resulting deviation.
In addition to the minimum curve radius ‘R’, the number of circumferential connections
in a ring ‘n’ –and its evenness/oddness –is the only other parameter that affects the max-
imum local deviation of segmental rings in the curved drives. Although this parameter has
not been formulated in Figure 3.17, its impact on the resulting deviation is due to limiting
the maximum possible relative rotations of the ring. Parameter ‘n’ itself is a function of
a number of segments per ring, and number of circumferential connections per each seg-
ment. With the dowel system as the most common connection device for the circumferential
joints, often three dowels are designed for each ordinary segment and one dowel for the key
segment (often sized as 1/3rd of the ordinary segments).
The most common ring segmentations and ring lengths categorized based on the tunnel
diameter (Section 3.2.5) are used in these examples to determine most common values for
parameter ‘n’. As a result of the primary analysis, as shown in the upper half of Table 3.3,
maximum deviation of the segmental ring is presented as function of minimum curve radius,
and total number of circumferential connections per ring ‘n’. As for the maximum allowable
deviation of the ring centerline from its theoretical location, 0.24 inches (6 mm) is often set as
the criteria. This roughly corresponds to 1.2 (30 mm) deviation of the TBM shield from the
TBM theoretical location since in general, length of the shield is about 5 times the length of a
single ring that is being installed inside it. Respecting maximum allowable ring deviation [e.g.
0.25 inches (6 mm)] and using the upper half of Table 3.3 when there is no other restriction
(see Table 3.4), one can determine the maximum length of the ring as a function of minimum
curve radius of the project and the number of circumferential connections per ring.
Analysis and design of precast segmental linings 117
(Continued)
120 Handbook of Precast Segmental Tunnel Lining Systems
3.3.1 Segment stripping
Figure 3.24 shows the stripping (demolding) phase that is modeled by two cantilever beams
loaded under their own self-weights (w). The design is performed with regard to the specified
Analysis and design of precast segmental linings 123
strengths when segments are stripped or demolded (that is, about 6 hours after casting). As
shown in Figure 3.25, the self-weight (w) is the only force acting on the segment and the
applied load factor in ultimate limit state (ULS) is 1.4 as recommended by ACI 544.7R-16
and ACI 533.5R-20.
3.3.2 Segment storage
Segment stripping (demolding) is followed by the segment storage phase in the storage yard
at the precast plant where segments are stored to gain specified strength before transporta-
tion to the construction site. As shown in Figure 3.26, in the most common scheme, all seg
ments comprising a full ring are piled up within one stack. Designers, in coordination with
the segment manufacturers, provide the distance between the stack supports considering an
124 Handbook of Precast Segmental Tunnel Lining Systems
eccentricity of ‘e’ =4 inches (100 mm) between the locations of the stack support for the
bottom segment and the supports of above segments. This load case can be represented by
a simply supported beam loaded under its self-weight as shown in Figure 3.27. The dead
weight of segments positioned above (F) acts on the designed segment as a concentrated
load in addition to its self-weight (w). Therefore, corresponding load combination can be
considered as 1.4w +1.4F (ACI 544.7R-16, ACI 533.5R-20).
Analysis and design of precast segmental linings 125
Figure 3.21 All possible relative ring rotations for a rhomboidal segmental ring system.
Note: Resulting in crucifix joints (more transparent layouts) between adjacent rings.
126 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.23 Developed plan view between two adjacent rings after adjustments.
Note: Developed plan between two adjacent rings where a crucifix joint has been eliminated by
slight adjustment of segment geometry.
3.3.3 Segment transportation
During the segment transportation phase, stored precast segments in the storage yard
are transported to the construction site and TBM trailing gear. Segments may encounter
dynamic shock loads during this phase and as shown in Figure 3.28, half or all of the seg
ments of each ring are transported on one dolly. Wood blocks provide supports for the
segments. An eccentricity of 4 inches (100 mm) is recommended for design. Note that the
wood blocks should be installed nearly parallel to the segment axis. Similar to segment stor-
age phase (Figure 3.27), simply supported beams represent the load case of transportation
with dead weight of segments positioned above (F) and self-weight (w) as the acting loads
on designed segment. In addition to load combination of 1.4w +1.4F per (ACI 544.7R-16,
ACI 533.5R-20), a dynamic impact factor of 2.0 is recommended to be applied to the F
force for the transportation phase.
128 Handbook of Precast Segmental Tunnel Lining Systems
3.3.4 Segment handling
Segment handling inside the precast plant and from storage yard to trucks or rail cars are
carried-out by specially designed lifting devices such as vacuum lifters, forklifts or mechan-
ical clamping or a combination of them (Figures 3.29–3.31). For handling by vacuum lift-
ers and mechanical clamping the same analysis and design procedure utilized for segment
stripping (demolding) should be followed. However, when segments are handled by
forklifts as schematically shown in Figure 3.32, a loading scheme similar to segment stack
ing for storage and transportation (Figure 3.27) should be adopted. In this case, the total
Analysis and design of precast segmental linings 129
eccentricity is equal to sum of spacing of forklift contact point from the wood blocks axis
and the minimum design eccentricity of e =4 inches (100 mm). A dead load factor of 1.4
in ultimate limit state (ULS) and a dynamic impact factor of 2.0 are recommended for this
load case (ACI 544.7R-16, ACI 533.5R-20). In addition, when lifting inserts are used for
segment handling, the pullout capacity of lifting inserts and concrete should be checked to
130 Handbook of Precast Segmental Tunnel Lining Systems
be greater than the self-weight of the segment under dynamic loading conditions. Pullout
capacity of concrete in this case can be calculated following the pullout failure diagrams and
equations of Figure 3.33.
Table 3.5 Internal forces developed in segments for first four load cases in Table 3.1.
Required design checks and factors for production and transient stages
transportation and handling stages. Precast concrete segments should be sufficiently rein-
forced to withstand developed bending moments and shear forces due to these actions at
an early age. Designers should follow structural codes and guides such as ACI 318-19, ACI
544.7R-16 and ACI 533.5R-20 for calculating the bending strength (Mn) and check the
design strength vs. developed bending moments and shear forces.
spalling tensile stresses that develop along the circumferential joints due to the advancing of
the TBM. The segments should also be able to resist the axial forces and bending moments
that develop when the annular space between the segments and the ground is pressure-filled
with grout. Included is the primary backfilling of the tail skin void and the secondary grout-
ing that is needed in case a complete contact of the lining with the ground has not been
achieved through the primary grouting.
where
γd is the load factor segment self-weight
γg is the load factor for gasket reaction force
Wkey is the segment self-weight
Pg,ULS is unfactored reaction force of gasket on segment at ultimate limit state of dowel
b is the width of segment
h is the thickness of segment
dg is the distance of gasket centerline from the segment extrados.
Vu = γd W (3.4)
Analysis and design of precast segmental linings 133
Figure 3.34 Acting and resisting forces on segment at the time of accidental TBM thrust removal.
Note: Schematics of acting forces (red) and resisting forces (green) for the load case of acci-
dental removal of TBM thrust jack forces.
Pu should be compared with the reduced nominal pullout strength of dowel or ϕPNt,ULS
and Vu should be compared with the reduced nominal shear strength of dowel or
ϕPNv,ULS.
For this load case the mechanical properties of dowels must be obtained from the dowel
supplier on a case-by-case basis. For example, as shown in Figures 3.35 and 3.36, nominal
ultimate limit state (ULS) pull-out capacity of the dowel (PNt,ULS), displacement of dowel at
ULS under pull-out (dc,ULS), and nominal ULS shear capacity of the dowel (PNv,ULS) are 22.5
kips (100 Kn), 0.375 inches inches (9 mm) and 40.5 (180 Kn), respectively. Estimated
gap between gasket profiles (dg,ULS) corresponding to ULS displacement of dowel (in this
example dc,ULS =0.375 (9 mm), as shown in Figure 3.37, can be determined as 0.60 inches
(15.4 mm) considering a linear approximation of displacement at the circumferential
joint. Under such large gap between gasket profiles, effect of the gasket reaction force, as
shown for example in Figure 3.38 for a typical gasket load-gap diagram, is completely
dissipated.
Results of this design check should prove that the ultimate pull-out force of dowel (Pu) is
less than the reduced ultimate pull-out resistance of dowel (ϕPNt,ULS), and the ultimate shear
force developed in dowels (Vu) is less than the reduced ultimate shear resistance of dowel
(ϕPNv,ULS). Otherwise, a higher dowel capacity should be adopted.
134 Handbook of Precast Segmental Tunnel Lining Systems
Whenever the TBM’s total thrust is available, maximum thrust jack forces are known
and therefore cannot be exceeded. This important input is given by the TBM manufacturer
often by two values of nominal machine thrust and maximum exceptional machines thrust.
Nominal machines thrust is the maximum operational thrust forces applied on all jacks
required for boring and advancing the machine for the worst-case ground condition while
maximum exceptional machines thrust are only used in exceptional cases when TBM is
stuck and cannot advance with normal thrust conditions and all exceptional machine thrust
needs to be mobilized for further TBM advancement.
Forces required for ultimate failure of precast segments in this load case are much higher
than maximum TBM thrust jack forces that are normally exerted on segments. Accordingly,
precast segments in this load case should be designed for a serviceability limit state (SLS)
of cracking. In addition to high thrust jack forces, eccentricity of jack forces with respect
Analysis and design of precast segmental linings 137
to segment thickness centerline and asymmetric positioning of jacking pads with respect to
segment ends in the circumference of the ring (thrust jacks are irregularly spaced or segment
sizes are unequal) are considered as other major causes of cracking during the thrust phase
(SIG WG N. 2, Report N. 1 –Damages of Segmental Lining (2019). Limiting magnitude of
jack forces, reducing the eccentricity of jack forces along the ring thickness and uniform dis-
tribution of jack pads with respect to segment ends can be considered as mitigation methods.
138 Handbook of Precast Segmental Tunnel Lining Systems
Nonetheless, in practice almost none of these methods can be guaranteed. Therefore, such
extreme conditions should be considered during the design procedure of segments.
One very important detail for this load case is the detail of circumferential joints with
gasket recess on the exterior side (extrados), and stress relief recess on the interior side
(intrados) of tunnel. For example, as shown Figures 3.41 and 3.42, while the total thick
ness of segment in this example is 11.8 inches (300 mm), maximum thickness of segment in
contact with TBM thrust pads can be only 7.9 inches (200 mm). Consequently, high eccen-
tricities of jack pads in radial direction toward extrados may result in reduced contact area
with segments and increased pressure on the contact zone. Nominal and maximum excep-
tional eccentricities of jack pad in the radial direction are recommended as en =±1.20 inches
(30mm) and emax =± 1.6 inches (40 mm), respectively.
The design procedure must consider all possible combinations of nominal and max-
imum exceptional thrust jack forces with nominal and maximum exceptional thrust
pad eccentricities. This results in a total number of 10 jack force scenarios. Each jack
force scenario is defined by an appropriate load factor of 1.00, 1.05 or 1.20 in order to
Analysis and design of precast segmental linings 139
Table 3.6 Eccentricities and load factors for TBM thrust force scenarios.
TBM thrust force scenarios, eccentricities, load factors, and factored pressures for
load case 6
Factored pressure
Load Unfactored jack force Eccentricity Load factor Contact area on contact area,
case on each pad, F p (kN) e (mm) γ A contact (mm 2) P contact (MPa)
consider the variability in the prediction of loads and eccentricities. For example, the
likelihood of exceeding maximum exceptional eccentricity and maximum exceptional
machine thrust at the same time is zero, and therefore, a load factor of 1.0 is applied
on this thrust force scenario. Because eccentricities have an impact on the contact area
of thrust pads and segments, for all scenarios, contact areas and resulting pressure on
contact zone should be compiled in a table such as Table 3.6 as the first step toward the
design for this load case.
140 Handbook of Precast Segmental Tunnel Lining Systems
The eccentricity toward the extrados (upward in Figure 3.42) is shown with a positive
sign in this table and the eccentricity toward intrados (downward in Figure 3.42) is shown
with a negative sign. One quick conclusion from this table is that the maximum contact
pressure applied on circumferential faces by TBM thrust jacks which provides a basis for
unfactored specified compressive strength of the concrete mixture.
Different analysis and design methods available for this load case, including ACI 318-19
equations for bursting forces, DAUB:2013 formulas, Iyengar Diagram (1962), and two and
three-dimensional finite element simulations are presented in the following.
h
ACI 318 − 18: Tburst = 0.25Ppu 1 − anc ; dburst = 0.5(h − 2eanc (3.5)
h
hanc
DAUB: 2013 Tburst = 0.25Ppu 1 − ; dburst = 0.4 ( h − 2eanc ) (3.6)
h − 2eanc
This load case and corresponding parameter are schematically shown in Figure 3.43.
Equations (3.5) and (3.6) represent the radial bursting stresses in the circumferential joints.
These equations are also applicable to tangential bursting stresses developed in the circum-
ferential joints.
Reinforcing bar or fiber reinforcement is designed to resist the bursting stresses developed
by jacking forces. Equations (3.7) and (3.8) have been adopted to determine the required
area (As) of reinforcing bars with a yield stress of fy for a reinforced concrete segment.
High compressive stresses can be developed under the jacking pads due to the TBM thrust
jacking forces. These compressive stresses, σc,j, can be estimated using Equation (3.9).
Ppu Ppu
σc, j = = (3.9)
Aj al hanc
Because only part of the circumferential segment face is in contact with the pads, the allow-
able compressive stresses (f′c) can be factored to account for the strength of a partially pres-
surized surface. ACI 318-19 specifies the formula used for designing the bearing strength of
concrete [Equation (3.10)] with a partially loaded segment face. DAUB:2013 recommends
a similar formula for designing tunnel segment faces.
Ad at ( h − 2eanc )
fco′ = 0.85fc′ = 0.85fc′ (3.10)
Aj al hanc
As shown in Figure 3.46, this load case can be simulated by modeling typical segments
of one ring or two adjoining rings. The jacking forces are applied along the contact area
between the jacking pads and the segment face. Recesses due to the gasket and stress relief
grooves are modeled between two segments to simulate the transfer of force through a
reduced cross-section. With this approach, the translational degrees of freedom are fixed in
all directions behind the previously installed segment. Figures 3.47 and 3.48 show typical
Analysis and design of precast segmental linings 143
results consist of the transverse and radial bursting stresses under the jack pad and the
spalling stresses in the areas between the jacking pads as a result of an elastic finite element
analysis. Examples of typical compressive stresses distribution due to this load case are
shown in Figure 3.49 (Bakhshi and Nasri, 2013b, 2014d).
Results from the three-dimensional FEM simulation indicate that spalling tensile stresses
between the jack pads, and the jack pads and end faces, can be more significant than the trans-
verse bursting tensile stresses under the jacking pads (Bakhshi and Nasri, 2013b). Precast
tunnel segments should be designed to withstand these high tensile stresses. Reinforcement
bars or fibers are designed for the tensile forces determined by the integration of stresses
through the tensile zone, similar to Iyengar diagram (1962) method.
Figure 3.50 Fine mesh used for 3D NFEA simulation of TBM thrust jack forces.
Note: Example of a 3D non-linear FEM simulation for the load case of TBM thrust jack forces
applied on fiber-reinforced concrete segment: fine mesh used for simulation.
shown in Figure 3.53. These parameters are used in conjunction with the total strain
crack constitutive model to introduce and assign a nonlinear concrete material model to
the segments.
As for geometry, the exact shape of segments in rectangular, rhomboidal or parallelogram
shape with potential longitudinal joint taper angle (8.5o in presented example) and
exact positioning of thrust pads in actual asymmetric pattern with respect to segment cen-
terline and segment ends are imported to 3D NFEA (non-linear finite element analysis)
program. Recesses along the segment thickness due to the gasket and stress relief grooves
(similar to shown in Figure 3.50) should be accurately modeled. Boundary condition for
146 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.51 Transverse tensile stresses as results of 3D NFEA simulation of TBM thrust jack
forces.
Note: Example of a 3D non-linear FEM simulation for the load case of TBM thrust jack forces
applied on fiber-reinforced concrete segment: transverse tensile stresses.
Figure 3.52 Crack width dimensions as results of 3D NFEA simulation of TBM thrust jack forces.
Note: Example of a 3D non-linear FEM simulation for the load case of TBM thrust jack forces
applied on fiber-reinforced concrete segment: crack width dimension. Size of contact area of
jacking pad is 6.8 inches (0.17 m) by 24 inches (0.6 m) and segment thickness is 12 inches (0.3 m).
three non-loaded end faces of segments are set by a compression-only constraint (blocking
movement of joints) normal to the joint faces.
Segment is modeled by solid linear hexahedron (dominant) elements and meshed with
element grading size varying from 0.31 inches (8 mm) near the thrust pads to 8.9 inches
(200 mm) towards the opposite boundary parallel to the thrust pads. The fine meshed model
(1.8 million hexahedron dominant elements in presented example) with higher density near
the jacking forces ensures that the model covers the crack initiation and propagation in
Analysis and design of precast segmental linings 147
various dimensions of the segment including the thickness. Uniform surface pressure with
the intensity shown in Table 3.6 should be used to impose the effect of jacking forces acting
on the pads. In order to perform a nonlinear analysis, an incremental loading method
was introduced to capture the evolution of the plasticity in the model. The accuracy of the
results must be ensured with simultaneous convergence criteria based on the quasi-Newton
iterative method.
In the presented example (Bakhshi and Nasri, 2020), as shown in Figure 3.53, tensile
cracking strength of fiber-reinforced segments is 403 psi (2.77 MPa) and its post-cracking
tensile strength is 233 psi (1.6 MPa). Figure 3.50 shows the transverse tensile stresses, and
Figure 3.51 shows the crack width dimension due to jacking force. As expected, cracks are
observed at the regions with highest spalling stresses in the linear analysis, i.e. between jack-
ing pads, and jacking pad and edge of segment. In this example the size of contact area of
jacking pad is 6.8 inches (0.17 m) by 24 inches (0.6 m).
the optimal grout pressure by considering the combined effects of groundwater level, plas-
ticity of grout, rate of advancement of the TBM, and the filling rate of the tail void. Using
Equation (3.11), the equivalent specific weight of the grout is determined by taking the
equilibrium condition between the upward component of the total grout pressure, tunnel
self-weight, and tangential component of the grout shear stresses (Groeneweg, 2007). These
forces are schematically shown in Figure 3.55.
π 2
De bρeq = πDe hbρconcrete + 2De bτ yield (3.11)
4
The vertical gradient of the radial grout pressure between the crown and the invert of the
tunnel is determined by Equation (3.12).
Note that AASHTO DCRT-1-2010 specifies that 10 psi (69 kPa) above the groundwater
pressure is the maximum permissible grouting pressure applied to the segmental ring.
However, a maximum permissible grouting pressure of up to 22 psi (150 kPa) above the
maximum groundwater pressure has been also considered (Ninić and Meschke, 2017). For
this load case, the lining is evaluated in a cross-sectional plane perpendicular to the longitu-
dinal direction of the tunnel and modeled as a solid ring with a reduced flexural rigidity to
account for the segment joints. Because the lining is surrounded completely by semi-liquid
and fresh grout materials at this point, no interaction is taken into account between the ring
and ground.
As shown in Figure 3.53, the back-grouting load condition is modeled by applying radial
pressure varying linearly from the minimum grout pressure at the crown to the maximum
Analysis and design of precast segmental linings 149
Figure 3.56 Analysis and design checks for tail skin grouting – model.
Note: Example of analysis and design checks for the load case of tail skin grouting: geometry of
segmental ring model and imposed grouting pressure.
grout pressure located at the invert of the tunnel. The self-weight of the lining and the grout-
ing pressure are the only loads applied to the tunnel lining at this stage of the analysis. For
a load combination of self-weight and grout pressure, a load factor of 1.25 is suggested
to both loads (ACI 544.7R-16, ACI 533.5R-20). Analysis can be performed using general
structural analysis packages or 2D/3D FEM model of the segmental ring with the exact
geometry of segments and joints, and with joints modeled by the Janssen (1983) model
(Figure 3.74). Because the lining is surrounded completely by a semi-liquid fresh grout with
negligible interaction with the ground, an interface element with a very low (practically
zero) spring stiffness should be used for simulation of this interaction.
150 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.57 Analysis and design checks for tail skin grouting – results.
Note: Example of analysis and design checks for the load case of tail skin grouting: bending
moments in the ring as a result of FEM analysis.
As a result of analysis for this load case, significant axial forces and limited bending
moments (Figure 3.57) are usually developed in the lining. Precast segments are designed
for combined maximum bending moments and axial forces. As shown in Figure 3.58, for
the design checks, these results are compared with the axial force-bending moment (M-N)
interaction diagram.
Figure 3.58 Analysis and design checks for tail skin grouting – design check.
Note: Example of analysis and design checks for the load case of tail skin grouting: comparison
with M-N diagram.
segments and joints, and with joints modeled by the Janssen model, similar to Figure 3.56.
Because secondary grouting occurs long after the primary grouting materials have cured, it
can be assumed that tunnel lining is in full contact with the surrounding ground except in
the local area where the secondary grouting is to be performed. To simulate the boundary
condition for this case, the interaction between lining and surrounding ground or primary
hardened grout can be modeled using radial springs with the segments supported radially.
Linear translational springs have been used to represent this type of interaction.
The method described by USACE EM 1110-2-2901 (1997) can be used, as an example,
to determine the spring stiffness per unit of exterior tunnel surface. For example, consider-
ing a primary grout with f’c of 450 psi (3 MPa) and a modulus of elasticity of 43.5 ksi (300
MPa), radial spring stiffness of 368 lb/in3 (100,000 kN/m3) is a reasonable assumption for
a 20 ft (6 m) diameter tunnel. Using the same grout pressure on the crown as for the pre-
vious load case and with the radial spring stiffness, the bending moments and axial forces
developed within the lining can be determined from the localized grouting operation. This
loading case often results in small incremental axial forces with large bending moments
(Figures 3.61 and 3.62). Precast segments are designed for this load case using axial force-
bending moment interaction diagrams.
ring installation and before installation of precast buoyancy unit. TBM drawings, such
as Figure 3.64, show that this back-up load is applied on specific locations in cross section
on contact areas with tunnel lining intrados. In addition, longitudinal TBM drawings
(Figure 3.65) reveal that the back-up load is applied longitudinally (with respect to the tun
nel direction) on two wheels on each ring. For this load case, two-dimensional finite element
method (FEM) analysis is often sufficient, with the assumption that backup load is applied
uniformly on this area.
Typical analysis results including deformations, axial forces, bending moments and shear
forces are shown in Figures 3.66–3.69. Resulting factored bending moments and axial forces
for all critical cases (for example, shallow cover and deep tunnel) are compared with axial
force-bending moment interaction diagram of segmental lining. Results should confirm that
precast concrete tunnel segments can withstand axial forces and bending moments induced
Analysis and design of precast segmental linings 153
Figure 3.61 Analysis results and design checks for secondary grouting – results.
Note: Example of analysis results and design checks for the load case of secondary grout-
ing: bending moments as result of FEM simulation.
154 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.62 Analysis results and design checks for secondary grouting – design check.
Note: Example of analysis results and design checks for the load case of secondary grout-
ing: comparison with M-N diagram.
Figure 3.63 Groene Hart Tunnel – schematics of TBM, back-u p train and tunnel lining.
Note: Schematics of TBM, backup train (gantries), and tunnel lining at the Groene Hart Tunnel
as segmental lining is being erected inside the TBM.
Source: Adopted from Talmon and Bezuijen, 2013.
by TBM back-up load or otherwise design should be modified. Punching shear strength of
the segmental lining should be also assessed following concrete design codes such as ACI
318-19 and EN 1992-1-1:2004.
For the TBM back-up load consideration, the early stage strength (setting time) of the tail
void grout and the TBM advance rate are also critical. The advance rate can be limited to
the tail void grout strength needed for support of the first and second gantries.
Analysis and design of precast segmental linings 155
beam-spring models, finite element methods (FEM) and discrete element methods (DEM).
Other acceptable methods of analysis include Muir Wood’s (1975) continuum model with
discussion from Curtis et al. (1976), Duddeck and Erdmann’s (1982) model, and an empir-
ical method based on tunnel distortion ratios (Sinha, 1989; Deere et al. 1969) that was
originally developed by Peck (1969). The results of these analyses are used to specify the
concrete strength and reinforcement. Reduction in bored tunnel segmental lining moment
of inertia also known as reduced flexural rigidity, where relevant, will be in accordance with
Muir Wood’s (1975) proposed method as presented in Equation (3.13).
Ir = Ij + (4/n)² × I (3.13)
where
Ij is moment of inertia at joint (taken as zero in the design)
I is the moment of inertia for nominal lining thickness
n is the number of segments per ring excluding key segment (n ≥ 4).
Figure 3.66 Finite element analysis for TBM back-u p load case – deformations.
Note: Typical results of FEM analysis for TBM back-u p load case: deformations. Units are inches,
kips and kips-feet.
Source: ACI 533.5R-2 0.
Figure 3.67 Finite element analysis for TBM back-u p load case – axial forces.
Note: Typical results of finite element analysis for TBM back-u p load case: axial forces. Units are
inches, kips and kips-feet.
Source: ACI 533.5R-2 0.
158 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.68 Finite element analysis for TBM back-u p load case – bending moments.
Note: Typical results of finite element analysis for TBM back-u p load case: bending moment.
Units are inches, kips and kips-feet.
Source: ACI 533.5R-2 0.
Figure 3.69 Finite element analysis for TBM back-u p load case – shear forces.
Note: Typical results of finite element analysis for TBM back-u p load case: shear forces. Units
are inches, kips and kips-feet.
Source: ACI 533.5R-2 0.
Analysis and design of precast segmental linings 159
model consists of applying uniform vertical ground and groundwater pressures, a linearly
varying lateral earth pressure, self-weight of the lining and a triangularly distributed hori-
zontal ground reaction between 45° and 135° from the crown. Member forces are calcu-
lated using the elastic equations contained in Table 3.8 (JSCE, 2007; ITA WG2, 2000).
π / 4 ≤ θ ≤ π /2 π / 4 ≤ θ ≤ π /2 π / 4 ≤ θ ≤ π /2
( − π / 8 + ( π − θ) ( − πS + θS + πS2 ( − (π − θ) C + θS +
S − 5/ 6C − 1/ 2 πS 2
) −1/ 6C ) Rc 2 g πSC − 1/ 6S ) Rc g
Rc 2 g
6 Horizontal
δh =
( 2 P − Q − Q ′ + π g ) Rc 4
deformation at 24 (EI + 0.045kRc 4 )
springline (δ h )
For this method, the segmental tunnel lining is modeled using a uniform reduced bending
rigidity (Muir Wood, 1975) that takes into account the effect of longitudinal joints between
the segments. Subgrade reaction modulus (spring stiffness) formulations recommended by
different guidelines are given in Table 3.7.
Here Es or oedometer stiffness has the following relationship [Equation (3.14)] with sur-
rounding ground Young’s modulus (Duddeck and Erdmann, 1982).
Es =
(1 − ν) Er (3.14)
(1 − 2ν) (1 + ν)
joints, and ring models with rotational springs. However, two-dimensional models can-
not be used to represent circumferential joints or staggered arrangement of segments
between rings.
As shown in Figures 3.72 and 3.73, a two-and-a-half-dimensional multiple-hinged seg
mented double-ring beam spring has been used to model the reduction of bending rigidity
and the effects from a staggered geometry. This manipulation is achieved by modeling the
segments as curved beams, flat longitudinal joints as rotational springs or Janssen joints
(Janssen, 1983), and circumferential joints as shear springs. Under final service loads, the
longitudinal joints may be open or closed.
2N
Closed joint: θ≤
Eblt
Analysis and design of precast segmental linings 163
2N
Open jo int : θ>
Eblt
The Janssen rotational spring stiffness (kjr) is derived accordingly by the following equations:
blt2 E
Closed joint: kjr = (3.15)
12
2
2M
9blt EM − 1
Nlt
Open joint: kjr = (3.16)
8N
where
b is the width of segment (contact area in longitudinal joint)
E is Young’s modulus
lt is the length of contact area between segments in longitudinal joints
N is the axial hoop force in segments
θ is the rotation
Refer to Figure 3.74 for presentation of parameters used in the Janssen model.
Two rings are used to evaluate the coupling effects; however, this method uses symmetry
conditions to remove complex support conditions and only half of the segment width is con-
sidered from each adjacent ring for the longitudinal and circumferential joint zone of influ-
ence. Considering the self-weight of the lining, and distributing the ground, groundwater
and surcharge loads along the beam, member forces can be calculated using a conventional
structural analysis package.
Figure 3.75 Discrete element method model and developed internal forces (axial forces).
Note: Discrete element method (DEM) model and developed internal forces along the lining per-
imeter as a result of DEM analysis on large diameter tunnel excavation in fractured rock: axial
forces.
Analysis and design of precast segmental linings 165
Figure 3.76 Discrete element method model and developed internal forces (bending moments).
Note: Discrete element method (DEM) model and developed internal forces along the lining per-
imeter as a result of DEM analysis on large diameter tunnel excavation in fractured rock: bending
moments.
Figure 3.77 2D finite element method (FEM) simulation for tunnel excavation in soft ground.
Note: Example of a 2D FEM model for a TBM tunnel in soft ground developed in Plaxis.
As shown in Figure 3.77, FEM is used to model the ground surrounding the liner, where
a continuum medium is discretized into smaller elements, which are connected along adjoin-
ing nodal points (Bakhshi and Nasri, 2013c). The advantage of this method is to be able
to model the ground deformations and the post yielding behavior of the liner materials to
166 Handbook of Precast Segmental Tunnel Lining Systems
include any redistribution of stress that results from deformation of the lining and excava-
tion of the tunnel (ÖVBB 2011). FEM analysis techniques can also be used to represent
non-uniform and anisotropic stresses such as when non-symmetrical features are present
in the ground. This can be the case when several different geologic formations or external
loads are present within close proximity of an existing structure (AFTES-WG7:1993). Using
FEM techniques, complex underground conditions, and tunnel characteristics can be ana-
lyzed with a degree of accuracy, and the large axial forces and bending moments developed
in the segments can be reliably determined. Precast segments are designed using an axial
force-bending moment diagram.
The most accurate results for this load case when tunneling in soft ground are obtained
from 3D staged NFEA modeling of shield-driven tunnel excavation (Figure 3.78). In this
type of simulation, segmental ring configuration with exact geometry of each segments
(rhomboidal, trapezoidal or rectangular) and staggered joint are directly imported to the
model. Segments are modeled as shell elements and a multi-linear tension softening and
compression functions (for example, Figure 3.53) is used for material modeling.
The Janssen non-linear line interfaces simulate the segment joints, and surface inter-
faces are used between the lining and the surrounding ground. Excavation advances are
modeled in intervals equal to the length of segmental rings. A variable balancing face
pressure is applied along the tunnel cross section equal to the horizontal in situ stress.
Compression-only gap elements are used to model the conical shield and the variable
gap between the ground and the shield. The length of shield is assumed to be 5 to 10
times the ring length and the grout pressure is only applied on the most recently acti-
vated segmental ring and one ring immediately behind, considering anticipated advance
rate and hardening time of grouts (two-component grout here). A step-by-step simu-
lation is adopted to simulate the tunneling procedure. Figure 3.79 presents a typical
result of this 3D NFEA simulations in the format of internal bending moments in the
segmental rings.
Analysis and design of precast segmental linings 167
Figure 3.79 Segmental lining bending moments in a 3D staged non-linear finite element model.
Note: Example of segmental lining bending moments as a result of 3D staged non-linear finite
element modeling of shield-d riven tunnel excavation.
Here
Ppu is the maximum normal force from the permanent ground, groundwater, and sur-
charge loads
eanc is the maximum total eccentricity, consisting of the normal force eccentricity (M/N)
and the eccentricity of the load transfer area.
h
ACI 318 − 19: Tburst = 0.25Ppu 1 − anc ; dburst = 0.5 ( h − 2eanc ) (3.17)
h
168 Handbook of Precast Segmental Tunnel Lining Systems
Similar to ACI 318-19, simplified equations by DAUB:2013 [Equation (3.14)] are used
for evaluating bursting stresses in the longitudinal (planar or flat) joints. Nonetheless,
DAUB:2013 presents more details about this specific load case using an approach that
transfers force by means of a stress block, as shown in Figure 3.80. Additional reinforce
ment for spalling and secondary tensile stresses are placed when there are high eccentric
normal forces (e > d/6) (DAUB:2013). Bursting, spalling and secondary tensile stresses are
calculated using the following equations:
e 1
Fsd , r = N Ed ⋅ − ; Fsd , 2 = 0.3Fsd ,r (3.19)
d 6
where
The total eccentricity, e, consists of eccentricity from normal force, el, and the eccentri-
city of hinge joint, ek.
Therefore, e = el + ek = M/N + ek, d1 = dk –2e, and ds =2e′= d − 2el.
Figure 3.81 Finite element method analysis for longitudinal joint bursting (model).
Note: Example of finite element method (FEM) analysis for the load case of longitudinal joint
bursting: FEM model representing governing cases.
0.1ds and 2/3d from the face of the segment, respectively (DAUB:2013). Simplified equa-
tions, which include Equations (3.18) and (3.19), can be used for this load case to determine
the compressive stress and the strength of the partially loaded surface.
Iyengar diagram methods (Figure 3.44) and FEM simulations can also be used as an alter
native approach to determine the stresses within the longitudinal joints. For this load case,
two-dimensional FEM models are developed to represent the recess of the gasket and the
stress relief grooves (curvature of elements is neglected). Bursting stresses at the vicinity of
the longitudinal joints are analyzed for cases of maximum hoop force and maximum posi-
tive and negative load eccentricities (el = M/N) transferred between longitudinal joints. For
example, Figures 3.81 and 3.82 show the most governing cases considering partially open,
and closed joints due to extreme eccentricities, and the maximum uniform load transfer for
a typical mid-size tunnel lining project. Reinforcement is designed to take these bursting and
compressive stresses, similar to the case for TBM thrust jacking loads.
In addition to the eccentricity of forces (M/N) and of the load transfer area (because of
recesses), design for an additional eccentricity due to ovalization (or squatting) and mis-
alignment during the ring erection are sometimes asked for in project’s technical require-
ments. Such a load case is referred to as ring ovalization due to out of round ring build or
birds-mouthing. The design procedure includes an assumption that the ring is initially built
in the shape of an ellipse, and that the chord length of the displaced segment, as shown in
Figure 3.83 does not change. Note that in this figure the x-axis and y-axis represent the
dimension of the quarter of the segmental ring in the Cartesian coordinate system. Solid
arc and dashed arc represent the shape of quarter of ring before and after ovalization,
respectively.
Specific out-of-round build allowance over diameter is considered [for example, 0.6 inches
(15mm)]. Joint rotation and joint opening distance are calculated with total joint rotation
causing birds-mouthing (τ as in Figure 3.83) and opening distance due to poor ring build (δ
as in Figure 3.83) as the main parameters. Joint closure under minimum/maximum embed
ment loads on segment intrados and extrados are assessed by determining the load required
to close the gap and comparison with the hoop force due to embedment loads.
170 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.82 Finite element method analysis for longitudinal joint bursting (bursting stresses).
Note: Example of finite element method (FEM) analysis for the load case of longitudinal joint
bursting: resulting bursting stresses.
Depending on whether the joint remains open or closed, one of the two diagrams shown
in Figure 3.84 is used for calculation of birds-mouthing eccentricity. Although provided
details are for flat joints as the most conventional joint shape, convex joint details are
similar in terms of design approach with consideration of a line load instead of a distributed
load at the joint locations.
Figure 3.84 Bursting tensile stresses around longitudinal joints under hoop (normal) forces.
Note: Developed bursting tensile stresses around longitudinal joints under hoop (normal) forces
due to service loading condition and gasket pressure: (b) eccentric contact stresses.
Source: Adopted from Francis and Mangione, 2012.
172 Handbook of Precast Segmental Tunnel Lining Systems
of an adjacent tunnel. This additional distortion is the difference between the movement of
the tunnel at the left and right springline or the crown and invert of the tunnel. Some local
authorities such as LACMTA 2013 and LTA 2010 require the design to accommodate this
additional distortion. The former specifies a minimum additional diametrical distortion of
0.5% of diameter due to imperfect lining erection and the latter specifies an additional
distortion of ±5/8 inches (15 mm) on the diameter to allow for future development in the
vicinity of the tunnel. The following formula introduced by Morgan (1961) is commonly
used to calculate the additional distortional bending moment. Please refer to Equation
(3.20).
3EI δ d
Mdistortional = (3.20)
2r02
Using other approaches, the maximum distortion can be calculated based on the theory of
elasticity or finite element methods (FEM). Note that during excavation in certain ground
conditions such as clay materials, consolidation of underlying clay layers can result in add-
itional distortion to be a function of time. In such cases, additional distortion should be
considered and analyzed as a time-dependent phenomenon.
3.5.4 Seismic loads
Bored tunnels are usually designed for two earthquake levels: maximum design earth-
quake (MDE), and operating design earthquake (ODE). The MDE has a low probability of
exceedance, approximately 4% in 100-year service life, and the tunnel shall be designed to
maintain public safety during and after this design event. The ODE has a higher probability
of occurrence, approximately 50% in 100-year service life, and the tunnel performance
objective for this event is to remain operational with minimal damage.
During a seismic event, a bored tunnel primarily undergoes three types of deforma-
tions: ovaling, axial, and curvature (Owen and Scholl, 1981), as shown in Figure 3.85.
Ovaling is mainly caused by shear waves propagating vertically perpendicular to the tunnel
axis (Wang, 1993). Axial and curvature deformations are generated when the seismic waves
propagate either parallel or oblique to the tunnel axis. In the following sections, some of
the most widely accepted approaches for estimating each of these three deformation types
will be reviewed.
In general, the closed-form solutions are more suitable for early stages of design since
majority of tunnels are excavated in layered strata and there are different ground formations
near the tunnel, which result in some level of non-linearity during MDE ground motion.
Analysis and design of precast segmental linings 173
Therefore, more rigorous analyses, such as using numerical modeling, which is explained in
the next section, is recommended for detailed design of tunnels.
Estimating the seismic-induced ovalization of tunnels using closed-form solution consists
of the following steps:
AF*Vs
γ max = (3.21)
Cs
174 Handbook of Precast Segmental Tunnel Lining Systems
where
Vs is peak ground velocity (PGA)
AF is attenuation factor obtained from Table 3.9
Cs is effective shear wave velocity obtained from in situ (e.g. geophysical investigations)
or lab testing
Em (1 − vl2 ) R
C= (3.22)
El t (1 + vm ) (1 − 2vm )
Em (1 − vl2 ) R3
F= (3.23)
6El I (1 + vm )
where
Em is modulus elasticity of the medium
I is moment of inertia of the tunnel lining (per unit width)
Cs is effective shear wave velocity obtained from in-situ (e.g. geophysical investigations)
or lab testing
R and t are nominal radius and thickness of the tunnel lining, respectively
vl and vm are Poisson’s ratios of the tunnel lining and medium, respectively.
To account for presence of longitudinal joints between precast segments, the moment of
inertia can be adjusted using Equation (3.13).
1 Em
Tmax = ± K1 Rγ max (3.24)
6 (1 + vm )
1 Em
Mmax = ± K1 R2 γ max (3.25)
6 (1 + vm )
where
12 (1 − vm )
K1 = .
2 F + 5 − 6v m
This solution assumes both the tunnel and medium behave linearly during an earthquake.
For tunnels excavated in rock or hard soil, however, the interface condition is between full-
slip and no-slip. Therefore, it is recommended to conservatively assume no-slip condition
when estimating the maximum thrust (Höeg, 1968; Schwartz et al., 1980).
Em
Tmax = ± K2 Rγ max (3.26)
2 (1 + vm )
where
1
F (1 − 2vm ) − (1 − 2vm )C −
(1 − 2vm )2 + 2
K2 = 1 + 2
5
F (3 − 2vm ) + (1 − 2vm )C + C − 8vm + 6vm2 + 6 − 8vm
2
Figure 3.86 Typical finite element model of TBM tunnel for seismic analysis.
Note: Example model built using PLAXIS 2D for seismic analysis with appropriate boundary
conditions and geometry.
to the boundaries. In this case, because the underlying rock layers are significantly stiffer
than the overburden, the free-field deformation is only applied over the surficial soil column
with an overall height of H.
3 – Dynamic time- h istory analysis This is the most rigorous method among the three
approaches and involves applying different earthquake time histories at the base of the tunnel
cross section model. In addition to stiffness, the strain-dependent damping of all ground lay-
ers shall be input into the software. For cases when the tunnel behaves dynamically different
than the surrounding ground, e.g. tunnels in liquifiable soils or with significant inertial effect,
adoption of this approach is necessary. The amount of data generated in this analysis is usually
large and engineering judgment might be needed to interpret and use them for design purposes.
It should be noted that some authorities may limit the designers to using more refined
analysis approaches. For instance, the Los Angeles County Metropolitan Transportation
Authority only recognizes the time-history methods (pseudo-static or dynamic) for ana-
lyzing the tunnels within its jurisdiction (LACMTA 2013).
For P waves:
VP A
ε= cos2 ∅ + R P2 sin∅ cos2 ∅ (3.27)
CP CP
For S waves:
VS A
ε= sin∅ cos∅ + R 2S cos3∅ (3.28)
CS CS
VR A
ε= cos2 ∅ + R R2 sin∅ cos2 ∅ (3.29)
CR CR
where
VP , Vs , VR are the peak ground velocities of P, S and Rayleigh waves at tunnel elevation,
respectively;
CP , Cs , CR are the effective propagation velocities of P, S and Rayleigh waves, respectively;
AP , As , AR are the peak ground acceleration of P, S and Rayleigh waves, respectively;
∅ = angle of seismic wave propagation with respect to the tunnel axis.
Among these three seismic wave types, generally, the S waves generate the largest axial
strains, and the seismic wave propagation angle should be set to generate the maximum
effect when checking the lining seismic response.
178 Handbook of Precast Segmental Tunnel Lining Systems
The above equations are overly conservative when the tunnel is significantly stiffer than
the surrounding ground. For such cases, the equations need to be adjusted using reduction
factors to account for tunnel-ground interaction:
For axial strains:
2
El Al 2π
Ra = 1 + cos ∅ (3.30)
2
Ka L
4
El Il 2π
Rb = 1 + cos ∅ (3.31)
4
Kh L
where
El is Young’s modulus of tunnel lining,
Al is cross sectional area of the lining (per unit width),
Il is moment inertia of the tunnel lining (per unit width),
Kh is transverse ground spring constant,
Ka is longitudinal ground spring constant,
L is wavelength of the P, S or Rayleigh waves.
Ra and Rb are multiplied into the first and second terms of Equations (3.27) to (3.29),
respectively. The maximum calculated axial strain should not exceed the tunnel-ground
interface shear strength, Qmax , as defined by the following equation:
fL
Qmax = (3.32)
4
where
fL is tunnel-ground interface shear strength per unit lining width.
For the cases where the tunnel traverses highly variable strata or undergoes abrupt stiff-
ness change, e.g. at tunnel interface with a station or a shaft, adopting a 3D modeling
approach might be crucial to properly capture the tunnel axial and curvature behavior. The
joints at the tunnel interface with other structures should be designed carefully to be able to
accommodate the anticipated seismic deformations while maintaining the water tightness
of both the tunnel and the adjoining structure. Figure 3.89 shows an example bored tunnel-
station joint detail implemented in Crenshaw/LAX Transit Corridor Project in Los Angeles,
CA, using Omega seals (Piek et al., 2017). Three-dimensional time-history analyses in 3D
LS-DYNA were conducted to estimate the differential movements at the joints.
flexible lining to minimize the potential damage. Fault crossing assessment usually carried
out in three steps: 1 –estimating the average free-field fault displacement, 2 –imposing
the anticipated displacement to the tunnel using a numerical model capable of capturing
ground-tunnel interaction, and 3 –checking the tunnel lining demand versus its capacity.
The average free-field fault displacement can be evaluated by either observing the mag-
nitude of fault displacement during past earthquakes or using empirical method that relate
the displacement to earthquake magnitude (LACMTA, 2013). As an example, Wells and
Coppersmith (1994) developed a graph, as shown in Figure 3.89, that correlates the max
imum fault displacement with earthquake magnitude. It should be noted that the maximum
displacement occurs only along a very limited section of the fault. Therefore, the average
displacement, which is in the range of 20 to 80% of the maximum displacement, is recom-
mended to be used for design purposes (Wells and Coppersmith, 1994).
The estimated free-field displacement is applied to the tunnel lining through the use of
non-linear ground springs or, in the case of implementation of a continuum finite element
of finite difference modeling approach, via definition of appropriate boundary conditions,
as shown in Figure 3.90.
180 Handbook of Precast Segmental Tunnel Lining Systems
(ITA WG6, 2004). The ISO 834 curve is recommended up to an expected fire heat release
rate of 50 MW, above which the hydrocarbon curve (up to 100 MW) and thereafter the
RWS curve (up to the stoichiometric limit) should be applied. When cooling phase is con-
sidered, RABT curves can be used.
Once one of the standard design fire curves is selected (temperature versus time), it is
applied on the tunnel intrados. The increase in lining temperature vs. lining thickness is cal-
culated and the resulting reduction in concrete and reinforcement properties (modulus and
strength) is determined based on available data. This will determine the lining thickness loss
during the fire. If using basic structural analysis programs, applying non-linear temperature
gradients are not allowed for, an equivalent temperature load can be established that has
the same impact on the equivalent section as the original temperature gradient has on the
original section (Neun, 2012). This can be followed by adopting a layered section analysis
where the normal force (N) and bending moment (M) can be determined by integration/
summation of the stresses in the individual layers.
The most accurate results for the fire action are often obtained as a results two-dimensional
finite element analysis using a coupled thermo-mechanical model. For example, for fire acci-
dents in railway/subway tunnels, RWS fire loading, which is typical for these types of tun-
nels is applied on either the entire tunnel lining intrados (Figure 3.92) or along the tunnel
lining intrados except those areas, which will be filled by track slab or ballast (Figure 3.93).
Alternatively, a fire curve specific to project can be obtained through the computational
fluid dynamics (CFD) simulation of actual train fire.
Initial temperature is typically considered as 68oF (20oC). Heat flow is simulated fol-
lowing recommendations of Eurocode 2 standard (EN 1992-1-2:2004) for structural fire
design. As shown in Figures 3.94 and 3.95, the concrete conductivity and the volumetric
specific heat (heat capacity) as a function of temperature are used as inputs to the model
following recommendation of EN 1992-1-2:2004 Section 3.3.2 and 3.3.3.
For the RWS fire curve example, the numerical results of the thermal analyses as nodal
temperature contours along a 21 feet (6.5 m) diameter tunnel lining are presented in
Figure 3.93 L ocations of fire loading in FEM model excluding areas that will be filled by track
slab or ballast.
Note: Example of locations of fire loading along the tunnel lining intrados excluding areas that
will be filled by track slab or ballast.
Figures 3.96 to 3.100 at 30 minute intervals. These results are also presented by means of
the temperature history at different points over the segment thickness in Figures 3.101 and
3.102, and by means of the temperature distribution along the segment thickness at differ
ent fire exposure times in Figure 3.103. Note that for the fire analysis, it is recommended to
reduce the tunnel lining thickness by 0.8 in (20 mm) from the intrados to consider the effect
of potential spalling zone.
184 Handbook of Precast Segmental Tunnel Lining Systems
uniaxially stressed concrete at elevated temperatures are introduced to the FEM model as
stress–strain relationships as a function of temperature. The main parameters of the stress–
strain relationships of normal weight concrete at elevated temperatures are the compressive
strength (f’c or fck), the strain corresponding to peak compressive strength (εc1), and ultimate
compressive strain capacity (εcu). These parameters are available in EN 1992-1-2:2004
Table 3.1 and can be directly introduced to the model as shown in Figures 3.104 to 3.106.
In precast concrete segments reinforced with rebar, the tensile strength of concrete under
tension can be neglected, and recommendation of EN 1992-1-2:2004 Table 3.2a for the
strength and deformation properties of reinforcing steel at elevated temperatures should
186 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.100 Nodal temperatures at 120 min. for RWS fire curve analysis.
Note: Nodal temperature as a result of thermal analysis along the lining perimeter.
be followed. In case segments are only reinforced with steel fibers, the mechanical decay
of the post-crack residual flexural and tensile stresses of FRC should be used for analysis.
Experimental results of Caverzan et al. (2015) are recommended for this purpose and are
shown in Figures 3.107 and 3.108. In their study, feq1 is the nominal strength in crack mouth
opening dimension (CMOD) ranging between 0.012 and 0.02 inches (0.3 to 0.5 mm), which
is considered as a reference for serviceability limit state (SLS) residual strength and feq2 is
the average strength in CMOD for ultimate crack width which is regarded as ultimate limit
state (ULS) residual strength.
Analysis and design of precast segmental linings 187
Figure 3.101 Temperature history along the lining thickness for RWS fire curve analysis (node
locations).
Note: Example of temperature history at different nodal points along the lining cross-s ection
(segment thickness of 12 in or 300 mm) as a result of 2D FEM fire analysis: location of nodes.
Figure 3.102 Temperature history along the lining thickness for RWS fire curve analysis (analysis
results).
Note: Example of temperature history at different nodal points along the lining cross-s ection
(segment thickness of 12 in or 300 mm) as a result of 2D FEM fire analysis: analysis results.
188 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.103 Temperature profile at different fire exposure times for RWS fire curve analysis.
Note: Example of temperature profile at different fire exposed times along the lining thickness.
An average stress decay factor applicable to post-crack flexural and tensile strength can
be introduced to the model as shown in Figure 3.109. Also, according to Caverzan et al.
(2015), the ultimate crack width is reduced from 0.155 inches (3.94 mm) at 68oF (20oC) to
0.119 inches (3.02 mm) at 392oF (200oC), 0.083 inches (2.12 mm) at 752oF (400oC), and
0.046 inches (1.17 mm) at 1112oF (600oC). The fib Model Code 2010 defines the structural
characteristic length (lcs) for sections without traditional reinforcement as the entire section
thickness. In the referenced study (Caverzan et al. 2015) the section thickness of the samples
Analysis and design of precast segmental linings 189
was 30 mm. Considering this characteristic length, the ultimate tensile strain (εtu) at 68oF
(20oC), 392oF (200oC), 752oF (400oC) and 1112oF (600oC) are 0.13, 0.1, 0.07 and 0.039,
respectively. As for the first peak tensile strength decay of concrete materials under elevated
temperature, section 3.2.2 of EN 1992-1-2:2004 provides a relationship, which is shown in
190 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.107 Decay of post-c rack residual flexural strength of fiber reinforced concrete.
Note: Serviceability limit state (SLS) strength as a function of temperature.
Source: Data from Caverzan et al. 2015.
Figure 3.108 Decay of post-c rack residual flexural strength of fiber reinforced concrete.
Note: Ultimate limit state (ULS) strength as a function of temperature.
Source: Data from Caverzan et al. 2015.
Figure 3.110. All aforementioned tensile material properties are introduced to FEM models
as input tensile material models for a coupled thermo-mechanical analysis.
The tunnel lining is commonly modeled as a non-jointed solid ring due to difficulties in
simulation of the longitudinal joints in two-dimensional (2D) plane strain FEM models –
which are often used for the load case of fire. The interaction with the ground is simulated
using an interface with radial spring stiffnesses presented in Table 3.7. As a result of coupled
Analysis and design of precast segmental linings 191
thermo-mechanical analysis, the hoop stresses developed along the lining thickness can be
obtained. Example of hoop stresses in the lining at exposure time of two (2) hours due to
a project-specific fire curve are presented in Figures 3.111, 3.112 and 3.113. Note that fol
lowing the methodology of EN 1992-1-2:2004, in the compressive zone and near intrados
192 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.113 Tabular and graphical presentation of variations of hoop stress versus distance from
the lining extrados.
Note: Example of hoop stresses developed along the lining thickness due to fire as a result of
coupled thermo-m echanical FEM analysis.
where very high temperatures are anticipated, isotherm 500oC (932oF) zone method should
be adopted by ignoring both strength and developed stresses in a zone with temperatures
higher than 932oF (500oC). This methodology basically implies that this part of section
contributes neither to capacity nor demand for structural calculations. The hoop stresses
in the segment thickness such as those presented in Figure 3.111 to 3.113 –excluding the
isotherm 500oC (932oF) zone –are integrated to obtain resulting axial forces and bending
moments in the tunnel lining.
In addition, existence of the longitudinal joints in the segmental ring results in reduction
of the bending moment. Note that according to Muir Wood’s (1975) formula [Equation
(3.13)], the effective moment of inertia of the lining also known as reduced flexural rigidity
considering the number of longitudinal joints in the ring is much lower than its full flex-
ural rigidity or moment of inertia. For example, for a ring with six longitudinal joints, the
effective moment of inertia of the lining is only 0.44 times its full flexural rigidity (Ir = Ij +
(4/6)2 × I =0.44 I). Such bending stiffness reduction due to the effect of joints usually results
in reduction of non-jointed solid rings’ bending moments by 30–40%. Therefore, when for
example a 2D plane strain FEM model is adopted for a six-segment ring, considering a 30%
reduction in the bending moment for effect of joints seems to be reasonable. Axial forces
and reduced bending moments obtained from presented fire analysis must be superimposed
by the internal forces resulting from the embedment loads in final service stage analysis
presented in Sections 3.5.1 through 3.5.4. The resulting internal forces are considered as
structural demands for the load case of fire.
In a simplified approach, the compressive and tensile capacity of the lining at specific
exposure time to fire such as two hours can be determined using average decay factors for
compression and tension. A table that presents variation of temperature and corresponding
compressive strength decay factor as a function of distance from intrados can be helpful for
194 Handbook of Precast Segmental Tunnel Lining Systems
this purpose. After excluding the isotherm 500oC (932oF) zone, an average decay factor for
the compression zone and an average decay factor for tensile zone are determined accord-
ingly. Compressive and tensile material properties related to each average decay factor are
used for the calculation of decayed lining capacity due to fire. Decayed bending moment-
axial force (M-N) interaction diagram can be constructed using closed-form solutions of
Section 3.6.8 (Yao et al., 2018) and compared with the internal forces due to the fire and
embedment loads for design checks.
Explosions, on the other hand, are simulated by increasing the internal radial pressure on
the tunnel lining at the service condition by a representative value such as one atmosphere
or 14.5 psi (1 bar) (Caan et al., 1998). This internal radial pressure in the direction opposite
to ground and groundwater pressure results in reduced axial forces in the lining without
significant change in the bending moments. Recently an advanced and detailed design pro-
cedure for tunnels subjected to internal explosion and possibly preceded by fire accidents
was developed for FRC tunnel lining (Colombo et al., 2015). Simplified finite element model
and dynamic analyses were carried out to study the tunnel’s response under internal blast
loads in the form of pressure-impulse (p-i) diagrams and an ultimate limit state criterion
based on eccentric flexural capacity (M-N interaction diagram) was generated. Also, a limit
state criterion considering the fire-blast interaction was introduced through the modifica-
tion of the M-N diagram. This procedure is suggested for an advanced blast-fire analysis.
Figure 3.114 Temporary steel lintel and sill beams in segmentally lined tunnels.
Note: Temporary steel lintel and sill beams as steel bracing structures (support frames) in seg-
mentally lined tunnels to mitigate ring ovalization resulting from opening and cross-p assage
excavation.
Source: Lee and Choi, 2017.
geometry, developed meshes and shear stresses around a penetration zone. Total shear force
of a ring around the penetration area is calculated and compared to the shear strength of the
bicones to determine the minimum number of bicones required for this action.
the ring. Other important design considerations include ring systems, ring configurations in
terms of number of segments that form a complete ring, geometries of individual segments,
and geometry and tapering of key segments (Bakhshi and Nasri, 2018).
Manufactured rolled and cut welded wire meshes can be custom made as an alternate avoid-
ing the labors of tying. Radial bars have been designed in longitudinal joints as No. 3 or No.
4 (10 or 13 mm diameter). Longitudinal reinforcing bars in longitudinal joints are often of
the same size as the general longitudinal reinforcement inside the segment.
reinforced concrete (FRC) precast segments, first-crack and residual flexural strength, as
the basis of design, are specified in accordance with recommendations of ACI 544.7R-16,
Chapter 4.
3.6.3 Concrete cover
DAUB:2013 recommends a minimum concrete cover of 1.6 inches (40 mm) on the sur-
faces of the tunnel segments. On the end faces of segments and in areas close to bolt pock-
ets, the minimum concrete cover recommended by DAUB:2013 is 0.8 inches (20 mm).
However, ACI 318-19 specifies a minimum concrete cover of 1.5 inches (38 mm) for pre-
cast concrete elements exposed to earth. ITA Working Group on General Approaches to
the Design of Tunnels (1988) specifies a minimum 2.0 inches (50 mm) cover only for the
cast-in-place concrete lining at its outer surface in contact with ground and groundwater.
This specification does not apply to segmental lining especially when a one-pass lining
system is adopted.
Among other codes, guidelines, and recommendations, AASHTO DCRT-1-2010 does
not specify a minimum concrete cover; JSCE 2007 specifies a minimum 1 inches (25 mm)
concrete cover over reinforcement and a minimum 1.4 inches (35 mm) concrete cover in
a corrosive environment for a one-pass segmental lining system; ÖVBB 2011 refers to
EN 1992-1-1:2004, which specifies a minimum concrete cover of 1.0 to 1.8 inches (25 to
45 mm) depending on exposure conditions; AFTES:2005 specifies 1.2 inches (30 mm) as the
minimum cover on the intrados and extrados faces and 0.8 inches (20 mm) concrete cover
on other zones; and NEN 6720:1995 specifies 1.4 inches (35 mm) as the minimum concrete
cover for precast elements. A summary of recommendations for minimum concrete cover
over reinforcement are presented in Table 3.11.
3.6.4 Curing
Steam curing should be used as the primary curing method for the first six hours after con-
crete is placed into the forms. Immediately after segments have been cast, forms are placed
in a sealed, vapor-tight enclosure to prevent escape of moisture and heat, but large enough
to allow complete circulation of steam. Segments should not be removed from the forms
until specified stripping (demolding) compressive strength is attained, determined by com-
pressive cylinder test results.
Analysis and design of precast segmental linings 201
3.6.5 Reinforcement spacing
There is no specific recommendation available in ACI 318-19 for reinforcement spacing in
the precast tunnel segments. However, general spacing limits for reinforcement include min-
imum and maximum clear bar spacing of 1 inch (25 mm) and 18 inches (457 mm), respect-
ively. DAUB:2013, provides a typical reinforcing spacing range of 4 to 6 inches (100 to
150 mm) for segmental tunnel linings, and specifies a minimum clear spacing of 3.5 inches
(90 mm).
202 Handbook of Precast Segmental Tunnel Lining Systems
3.6.6 Fiber reinforcement
Fiber reinforcement has emerged as an alternative to traditional reinforcing bars and
welded wire mesh reinforcement for precast concrete tunnel segments. Due to significantly
improved post-cracking behavior and crack control characteristics, fiber reinforced concrete
(FRC) segments offer advantages over traditionally reinforced concrete segments such as
saving (especially labor) cost and reducing production time while developing a more robust
product with improved handling and long-term durability (ACI 544.7R-16; fib Working
Party 1.4.1 2017; ITA Working Group 2 2016).
FRC technology has developed in recent years with the introduction of high-strength con-
crete, allowing the use of fibers as the sole reinforcement system for more challenging condi-
tions on larger diameter tunnel project. In other cases, fiber and reinforcing bars have been
used in conjunction to reinforce the tunnel segments (Yao et al., 2018a, 2018b). Ladder bars
at the longitudinal joint as well as bursting links at the circumferential joint may be signifi-
cantly reduced by adding steel fibers. Tunnels with different sizes with internal diameters
ranging between 7.2 and 39 feet (2.2 m and 11.9 m) have been built using fiber reinforce-
ment. Minimum and maximum thickness of the FRC precast segments in existing tunnels
Analysis and design of precast segmental linings 203
are 5.9 inches (0.15 m) and 18 inches (0.46 m), respectively. These projects include water
supply, wastewater, gas pipeline, power cable, subway, railway, and road tunnels.
For fiber reinforced concrete (FRC) elements, following ACI 544.7R-16 and fib Working
Party 1.4.1 2017, appropriate strength reduction factors or material safety factors should
be considered for flexure, compression, shear and bearing actions of concrete segments.
Such factors account for the uncertainty of post-crack tensile strength when calculating the
design strength of FRC elements.
reinforcement is necessary for the required flexural capacity against ground and ground-
water loads at final service stage (de la Fuente et al., 2012).
In addition, TBM thrust forces in large diameter tunnels can be very high, especially
in soft ground tunneling. In some extreme cases, segments resisting these extraordinarily
localized bursting and spalling stresses due to the TBM jacking process needs to be rein-
forced by rebar in addition to fibers. Also, in large-diameter tunnels with an increased ratio
between the tunnel diameter and lining thickness, segments are more likely to withstand the
high flexural stresses due to imperfections and irregular construction (Tiberti, 2009). As an
example, gaps between rings or outward eccentricity of thrust jack forces necessitate the
use of rebar for in-plane deep beam behavior (Burgers et al., 2007). Collectively speaking
from the design point of view, if FRC is not adequate for design because of any of reasons
mentioned above, a hybrid solution of fibers and reinforcing bars may provide the required
strength at ultimate limit state (ULS) and serviceability limit state (SLS).
During the application of load cases occurring from the demolding stage all the way to
the final service stage, segments are most of the time subjected to combined axial force and
bending moment. Axial force-bending moment interaction (P–M) diagram is, therefore, an
important tool that tunnel engineers use for the structural design. Despite the popularity
and abundance of numerical methods for deriving P–M diagrams, closed-form solutions
offer important advantages for engineering problems.
First, algorithms expressed with closed-form solutions are more computational efficient
and easier to implement into computer programs or simple hand calculations in com-
parison to finite element methods (FEMs) or complex equations that need non-linear
numerical solvers (Vasdravelliset et al., 2012; Rodriguez and Aristizabal-Ochoa, 1999;
Dinsmore, 1982).
Second, closed-form solutions that are presented as symbolic math expressions offer a clear
view into how different variables interact with one another in affecting the results under
various modes of failure. Optimization algorithms and parametric studies can be conducted
readily using symbolic differentiation and integration to investigate the role of critical design
parameters such as reinforcement ratio, sample dimensions, concrete strength and tensile
residual strength.
Third, parameterized equations can be used for selection of variables using a design auto-
mation procedure; hence gradient-based optimization algorithms can be conducted much
faster.
Finally, analytical model with closed-form solutions can be implanted into a simple and
user-friendly spreadsheet program that allows user to define the problem with a limited
number of parameters. This is much more difficult with numerical or FEM analysis as com-
plicated models have to be created each single time and the computation time will be much
longer.
Due to these advantages, Yao et al. (2018) presented material models (Figure 3.125), sec
tional stress and strain diagrams at all failure modes (Figures 3.126 to 3.130), derivations
and for the first time closed-form solutions (Table 3.12 and Table 3.13) to construct a full
range P–M interaction diagram of hybrid reinforced segments (Figures 3.131 to 3.134)
considering the contributions of fibers in the post-cracking strength in addition to reinfor-
cing bars.
206 Handbook of Precast Segmental Tunnel Lining Systems
Parametric studies have been conducted by Yao et al. (2018) on the effects of fiber addi-
tions represented by residual strength, the confined compressive strength, the longitudinal
reinforcement ratio and the steel strength. Results show an improvement in moment cap-
acity after tensile cracking with addition of fibers, because of the fiber contribution to tensile
resistance in cracked zones. The increased compressive strength due to lateral confinement
mainly contributed to the load and moment capacities in compression-controlled mode of
Analysis and design of precast segmental linings 207
Table 3.12 Normalized height of compression/t ension zones, stresses/forces for each mode.
Normalized height of compression/t ension zones, stresses/forces at vertices for
all modes
hc1 - ω−λ ωk ωk
h λ cu − λ λ cu λ cu
ht1 - - 1− k k −1 k −1
h β β
Normalized fc2 γω γω γω
stress
E ε cr
γω γλ γω γω
f c1
E ε cr
nκ nκ nκ nχ
f s′
E ε cr
- - β 1 1
f t1
E ε cr
- - - µ µ
f t2
E ε cr
nκ nχ nχ nκ
fs
E ε cr
Normalized - - -
force Fc 2 λ cu − ω γ kω( λ cu − ω )
γω
bhE ε cr λ cu − λ λ cu
γω γω γω
Fc1 ω2 − λ 2 γ kω 2
γω
bhE ε cr λ cu − λ 2 λ cu
(Continued)
208 Handbook of Precast Segmental Tunnel Lining Systems
ρg nκ ρg nκ ρg nκ ρ g nχ
Fs′
bhE ε cr
- -
Ft1 β(1 − k ) (1 − k ) (1 − k )
bhE ε cr 2 2β 2β
- - -
Ft 2 ( k − 1)(1 + β ) ( k − 1)(1 + β )
µ µ
bhE ε cr β β
ρ g nχ ρ g nχ ρg nκ
Fs
bhE ε cr
2.1
( ω 2 γ − 2ωγλ cu + βλ cu )k β
P21′ = − + nρg ( χ + κ ) +
2 λ cu 2
2.2
ω2 γ 2βµ + 2µ − 1
P22′ = − + ωγ k + ( k − 1) + nρg ( χ + κ )
2 λ cu 2β
3.1
ω2 γ 2βµ + 2µ − 1
P31′ = − + ωγ k + ( k − 1)
2 λ cu 2β
3.2
ω2 γ 2βµ + 2µ − 1 nρg ( α − 1)
P32′ = − + ωγ k + ( k − 1) − nρg ( λ cu − κ ) + λ cu
2 λ cu 2β k
C12
3.2 ′ = C7 k 2 + C8 k + C11 +
M32
k
where
λ cu
k= , C1 = 6nρg (2α − 1)( χ − κ ) , C2 = 12β2 nρg (2α + 1)(κ − χ ) − 3βγω( ω − 2 λ cu ) ,
β + λ cu
ω3 γ 3ω 2 γ 1 3ω 2 γ
C3 = β2 C1 − γω 2 (2ω − 3λ cu ) , C 4 = − + − 3ωγ + β , C 5 = − − 6ωγ + β
λ cu 2
λ cu 2 λ
cu
,
β, ω − 3λ cu 2 6µ − 3 3µ − 2
C 6 = 3nρg (2α − 1)( χ − κ ) − C7 = − γω − 3( γω + µ ) − + ,
2 λ cu 2 β β2
3γω 2 18µ − 9 6µ − 4 6µ − 3 3µ − 2
C8 = − + 3( γω + µ ) + + , C9 = −3nρg (2α − 1) , C10 = − −
2 λ cu 2β β2 2β β2 ,
(Figures 3.139 and 3.140) and cast-in place concrete tunnel linings (Figure 3.141). These
results further verified the accuracy of the model and its suitability for design engineers.
A spreadsheet-based program has also been developed and is available for general users
to readily construct the interaction diagram with the present method at https://doi.org/
10.13140/RG.2.2.14437.09440/1
Analysis and design of precast segmental linings 211
most structural codes. This is especially true for repetitive units, where large numbers are
required to meet a particular purpose such as with the manufacturing of segments. Full-
scale tests are often conducted to evaluate the design and performance of fiber reinforced
concrete (FRC) segments with slenderness ratio of more than 12 to 13. Non-structural tests
on precast concrete tunnel segments include full-scale fire test, which helps to ensure 2-to-3-
hour fire resistance using standard fire load curves shown in Figure 3.91.
Analysis and design of precast segmental linings 213
Figure 3.137 Comparison of proposed axial force-b ending moment interaction diagram (HPFRC
columns).
Note: Comparison of proposed P-M diagram and experimental results for HPFRC columns tested
by Foster and Attard (2001).
Figure 3.138 Comparison of proposed axial force-b ending moment interaction diagram (UHPFRC
columns).
Note: Comparison of proposed P-M diagram and experimental results for UHPFRC columns
tested by Steven and Empelmann (2014).
Analysis and design of precast segmental linings 215
Figure 3.139 Axial force-b ending moment interaction diagram for the tunnel lining segment.
Note: Axial force-b ending moment interaction diagram for the tunnel lining segment in Reference
(de la Fuente et al., 2012) with a cross-s ection of 4.92 feet (1,500 mm) by 1.0 foot (300mm), 8
φ10 rebar (4 in top layer and 4 in lower layer) and varying amount of fibers.
Figure 3.140 Locally magnified axial force-b ending moment interaction diagram for tunnel lining
segments.
Note: Closer look at the range indicated in Figure 3.133 representing axial force- b ending
moment interaction diagram for the tunnel lining segment in de la Fuente et al. (2012) with a
cross-s ection of 4.92 feet (1,500 mm) by 1.0 foot (300 mm), 8 φ10 rebar (4 in top layer and 4 in
lower layer) and varying amount of fibers.
216 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.141 Comparison between applied actions for a cast-in-p lace concrete lining.
Note: Comparison between applied actions for a 1,000 mm by 500 mm cross section cast-in-
place concrete lining in Chiaia et al. (2007) and the model-p redicted interaction diagrams by
different methods.
3.7.1 Materials tests
Tests used to determine the required design parameters include compressive, flexural
and splitting tensile strength tests. Standard ASTM C39 tests with 6 × 12 inch (150 ×
300 mm) cylinders are recommended for determining the specified compressive strength,
f’c. This test is conducted on cylindrical concrete specimens. Peak flexural strength and
residual flexural strengths are obtained from ASTM C1609 standard tests, using 6 ×
6 × 20 inch (150 × 150 × 500 mm) fiber-reinforced concrete (FRC) beams in three-
point loading. EN 14651 (2005) test is used as an alternative for obtaining the residual
strength of FRC.
The ASTM C1609 or EN 14651 (2005) standard beam test is the most common test used
for the design of FRC segments on tunnel projects; however, the residual standard flex-
ural parameters cannot be used directly for design purposes because of the overestimation
that develops from using elastic methods of analysis (Bakhshi et al., 2014; Mobasher
et al., 2014). A stress–strain diagram is required for designing the load cases mentioned in
Chapters 4 through 6 using methods recommended in ACI 544.7R-16.
Alternative methods to obtain FRC tensile stress–strain diagram include the cracked hinge
formulations by de Oliveira e Sousa and Gettu (2006) and Olesen (2001), and the fictitious
crack models by Zhang and Stang (1998) and Kitsutaka (1997). A simplified approach for
obtaining the post-crack residual tensile strength consists of using the post-crack tensile
plastic constitutive law with a scale factor of 0.33 to 0.37 (Bakhshi et al., 2014; Mobasher
et al., 2014; Vandewalle, 2000; Barros et al., 2005; fib Model Code 2010) applied to the
standard residual parameters. This simplified approach has been successfully used on several
Analysis and design of precast segmental linings 217
tunneling projects (Vodička et al., 2012; Caratelli et al., 2012; Barwart et al., 2013; Tiberti
et al., 2008).
Although the specified residual tensile strength is used to check bursting and spalling
tensile stresses, ASTM C496 splitting tensile strength test is also recommended for verifica-
tion to make sure measured splitting strength is greater than the designed residual strength.
Also, results of a modified closed-loop splitting test method equipped with crack opening
displacement (COD) gauges, including splitting tensile strength, can be used directly for
design against bursting and spalling stresses replacing σp parameter when a hardening-type
behavior is exhibited. Statistical scattering of test results, which is usual for FRC materials,
requires at least three test data for averaging all of the aforementioned design parameters.
The aforementioned parameters are used for the construction of a stress block model such
as the CS TR63 (2007) model, which is typically used for calculation of the nominal resist-
ance bending moment of FRC members subjected to combined axial and bending actions.
3.7.2 Full-scale tests
Bending and point load tests at full scale are conducted up to load levels much higher than
the TBM nominal service load, and strength results are compared with the actions presented
in Sections 3.3 through 3.5. Bending tests, as shown in Figures 3.142 to 3.144, are per-
formed to verify the design and performance of segments during the production stages
of stripping (demolding), storage, transportation and handling, as well as for asymmetrical
earth pressure at the service stage. Full-scale point load tests, as shown in Figures 3.145 and
3.146, simulate the TBM thrust jack forces on the segment cross section during the excava
tion process (Caratelli et al., 2012), as well as the force transfer through a reduced cross
section in longitudinal joints.
The cantilever load test, as shown in Figures 3.147 and 3.148, is another full-scale test
that is used to investigate the circumferential joint strength under misaligned jacking loads
(Poh et al., 2009). Concrete tunnel lining strength has also been evaluated by full-scale tests,
such as those shown in Figure 3.149 to 3.151 to simulate dominant effects of axial forces,
bending moments, and combined action of axial loads and bending moment (Mashimo
et al., 2002). In this study, half of the circular tunnel lining was simulated for a tunnel with
an outer diameter of 31.8 feet (9.70 m), a thickness of 12 inches (300 mm), and a height of
3.2 feet (1.0 m). Loads were applied on 17 locations every 10 degrees from the bottom with
two jacks per each location, each 1 foot (300 mm) and 2.3 feet (700 mm) from the bottom
of specimen. As shown in Figures 3.149 to 3.151, three types of loading were adopted.
Type (a) loading represents a case that a load of loose rock/soil acts on the lining in the tun-
nel crown while rest of the lining is supported by the surrounding ground. To simulate
this load case, loading was applied in all 17 locations to the lining with 34 jacks up to
4.5 kip/jack (20 kN/jack). Except for jacks applying loads on three locations in the crown
that continued loading increase up to the failure, the remaining jacks maintained 4.5
kip/jack (20 kN/jack) axial force, simulating forces of springs as ground-structure inter-
action. As a result of load type (a), axial force was the dominant internal force compared
to the bending moment.
220 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.149 Full-s cale tests on half of the circular segmental lining – case 1.
Note: Full-s cale loading cases on half of the circular lining simulating: (a) load of loose rock and
soil acts on the lining in the tunnel crown while rest of the lining is supported by the surround-
ing ground.
Source: Adopted from Mashimo et al., 2002.
222 Handbook of Precast Segmental Tunnel Lining Systems
Figure 3.150 Full-s cale tests on half of the circular segmental lining – case 2.
Note: Full-s cale loading cases on half of the circular lining simulating: beyond/b ehind a cavern,
load of loose rock/s oil acts on the lining in the crown with ground providing no support on large
part of tunnel shoulder.
Source: Adopted from Mashimo et al., 2002.
Figure 3.151 Full-s cale tests on half of the circular segmental lining – case 3.
Note: Full-s cale loading cases on half of the circular lining simulating: ground is unfavorable and
only acting against the lining in all direction without providing any support.
Source: Adopted from Mashimo et al., 2002.
Type (b) loading on the other hand is for a case that beyond/behind a cavern, the load
of loose rock/soil acts on the tunnel lining in the crown but ground does not provide
support on a large part of the tunnel shoulder, and only a limited part of the lining is
supported by the surrounding ground. Type (b) simulation was done by applying loads
in nine locations, with four locations from the left as well as right bottom, and from
one location at the crown. Loading was increased in the crown location after the axial
force in all other 16 jacks (two per location) reached and maintained 2.25 kip/jack (10
kN/jack) simulating loads of ground-structure interaction springs. As a result, bending
moment in the tunnel shoulder was the dominant internal force in type (b) loading com-
pared to the axial force dominant effect in load type (a).
Type (c) loading represents a case that ground is unfavorable and only acts as loading
against the lining in all directions without providing any type of support. For this simu-
lation, loads in all 17 locations and 34 jacks (two per location) increase to failure. This
load case combined the action of axial loads and bending moments. Experimental results
include load-displacement curves at the crown measured by the load cell and linear vari-
able differential transformer (LVDT) connected to the jack located at the crown.
Analysis and design of precast segmental linings 223
3.8.2 Stress verification
Critical stresses in the segments at SLS are calculated for a combination of maximum bend-
ing moments and corresponding axial forces. Compressive stresses are limited in the struc-
tural codes to avoid microcracking that may lead to a reduction of durability. Maximum
compressive stresses in both reinforced and fiber reinforced concrete (FRC) at service limit
state are limited to a restricted value of 0.4f′c according to JSCE 2007, and 0.6f′c accord-
ing to EN 1992-1-1:2004, AFTES-WG7:1993, and fib Model Code 2010. On the other
hand, tensile stresses in the reinforcing bar are limited to fy according to JSCE 2007 and to
0.8fy according to EN 1992-1-1:2004 and fib Model Code 2010. AFTES-WG7:1993 limits
reinforcement tensile stresses to 34.8 ksi (240 MPa) for detrimental cracking and 29 ksi
(200 MPa) for highly detrimental cracking.
Flexural stresses in the joints are calculated using maximum bending moments and cor-
responding axial forces at joints as results of analysis such as beam-spring modeling or FEM
simulations. Developed stresses in the concrete at segment joints are limited to allowable
compressive stress of concrete. Developed stresses and forces in the bolts are limited to
allowable stress of connecting bolts reported by the manufacturer.
3.8.3 Deformation verification
Segment deformations are obtained directly as results of different models presented in
Sections 3.5.2 through 3.5.4 for the load case of earth pressure; groundwater; and surcharge
loads including elastic equation, beam-spring, finite element method and distinct element
method. However, joint gap and joint offset are only obtained from models that simulate
joints between segments and rings. For serviceability limit state (SLS) verification, these
Analysis and design of precast segmental linings 225
3.8.4 Cracking verification
Cracking in segments is a major cause for reduction in serviceability due to reduction
of watertightness and reinforcement corrosion. In particular, cracking has a significant
effect on the durability of the tunnel in an environment with frequent freeze–thaw cycles.
Examination using appropriate methods should be carried out to ensure that cracking in
segments does not impair the serviceability, durability, or intended purposes of the tunnel
lining (Bakhshi and Nasri, 2015a, 2015b). Among possible cracks induced in segments
under service loads are mainly the cracks due to bending moment and axial force. Cracking
should be examined by ensuring that the flexural crack width is not greater than the allow-
able crack width. The flexural crack width calculation for reinforced concrete (RC) and
fiber reinforced concrete (FRC) segments is presented in the following.
Equation (3.33)
2
fs s
w = 0.076βfs 3 dc A × 10−3 and w = 2 β dc 2 + (in.-lb)
Es 2
226 Handbook of Precast Segmental Tunnel Lining Systems
2
fs s
w = 0.011βfs 3 dc A × 10−3 and w = 2 β dc 2 + (SI)
Es 2
Equation (3.34)
f 15 5 (n + 2)
w = s s + ε csd
′ ; s > 13.97 + 0 .7 ⋅ ⋅
Es 0.006895fc + 20
’
7n + 8
(101.6dc + 17.78( s − ϕ)) (in.-lb)
f 15 5 (n + 2)
w = s s + ε csd
′ ; s > 0.55 ’ + 0 .7 ⋅ ⋅ ( 4 ⋅ dc + 0.7 ⋅ ( s − ϕ )) (SI)
Es fc + 20 7n + 8
Equation (3.35)
fct ,eff E A
fs − kt As
1+ s ⋅ s
E A
A fs
w = sr, max ≥s
r , max 0.6
Es Es
fib Model Code 2010, CNR DT 204/ 2006, RILEM TC 162- TDF, and DAfStB
Stahlfaserbeton:2012-11 can be used to calculate the crack width in concrete sections rein-
forced by fibers with and without conventional reinforcement. The flexural crack width of
FRC segments has been well presented in fib Working Party 1.4.1 2017 by considering ana-
lytical sectional approaches as well as finite element methods.
Requirement Allowable
Item class Designation Application Requirement crack width
1 AT-1 Largely dry • One-p ass lining with Impermeable 0.008”
very tight waterproofing (0.20 mm)
requirements
• Portal areas
2 AT-2 Slightly • One-p ass lining for road Moist, no 0.010”
moist and railway tunnels with running water (0.25 mm)
normal waterproofing in tunnel
requirements (excluding
portals)
3 AT-3 Moist • One-p ass lining Water 0.012”
without waterproofing dripping (0.30 mm)
requirements from
• Two-p ass lining systems individual
spots
4 AT-4 Wet • One-p ass lining Water 0.012”
without waterproofing running (0.30 mm)
requirements in some
• Two-p ass lining as a places
drained system
Source: Per ÖVBB 2011.
On the other hand, results of parametric studies and application to a case of a mid-
size tunnel show a significant impact of fiber reinforcement in controlling the initial water
inflow. The proposed methodology indicates that in addition to the superior effect of fiber
reinforcement in controlling the cracks under service load, compared to conventional
reinforcement, fiber reinforcement also significantly improves the watertightness of cracked
concrete lining most likely due to change in morphology of cracks. The proposed approach
can be used to provide project-based allowable crack width for concrete tunnel lining based
on parameters that are specific to the project including the type of reinforcement.
where the CO2-eq factor is the amount of equivalent CO2 per pound or kg of material that
comes from environmental product declarations (EPDs).
In the following, different ways of reducing CO2 emissions are presented.
total cementitious materials or slag is greater than 40% and fly ash is greater than 20%
of total cementitious materials). High levels of cement replacement by SCMs will result in
lowering the early strength of concrete. High early-strength concrete is required for demold-
ing segments within 5–6 hours after casting (for example, 15 MPa after 5–6 hrs). This is
the focal point of today’s industry research and so far, the only solution has been using an
alkali-activated binder (AAB) based on sodium carbonate. The concern with the use of AAB
is the risk of the alkali–silica reaction (ASR) and long-term durability issues.
these emissions are presented. These equations will be applied for all diesels driven and elec-
trical equipment that will be studied later.
DCi = Mi × 2 × d × C g (3.37)
C g ≈ 7 ( fR ± i ) (3.38)
A typical value for the friction coefficient in a civil work road is fR =3.5%. The sign of the
slope will be negative when the equipment goes downwards and will be positive upwards.
The consumption in grams can be translated into liters, using the diesel density (833 g/l).
The CO2 emissions ( DEj ) can be calculated multiplying the consumption of this equipment
by its conversion factor ( rD ):
rD can vary depending on the region and data uses. A typical value of 3.25 kgCO2 per liter
of fuel for mining equipment can be assumed (Shillaber et al., 2016).
For equipment speed higher than 25 km/h (for example, for transportation from the pro-
duction factories to the construction site), the consumption, in grams, will be given using
the following formula taking into consideration two different roads, the outside and the
inside of the tunnel:
V
(inside) Cg Mati ( )
= di × ( mT + mL ) × 15 − C gi + di × mT × 15 − i
20
(3.41)
where d0 is the distance travelled outside in km, v0 is the speed of the truck outside of the
tunnel (we can consider here the average speed of 60 km/h), di is the distance travelled inside
in km, vi is the speed of the truck inside of the tunnel (10 km/h), mT and mL are the weight
of the truck and the load respectively. Cgi is the amount of diesel consumed (grams) per ton
transported and km driven and can be calculated using the following formula:
vi
C gi ≈ 15 − (3.42)
20
Analysis and design of precast segmental linings 231
To have an idea, the accumulated quantity of CO2 emission due to the articulated trucks
used to remove the rock from a tunnel is presented in Figure 3.154 (Rodriguez, 2020). The
tunnel taken as a reference is a double tube tunnel in Northwest of Spain with a slope of
about 1% upwards. The depth was 125 m in average.
ECi = NP × LF × t (3.43)
where NP is the nominal power in kW, LF is the load factor (%), and t is the working time
in hours.
The emissions ( EEJ ) can be calculated multiplying the consumption of the electricity by
its conversion factor ( rE ):
A typical value for rE is 0.267 kg CO2 per kWh according to the Spanish institute IDAE
(2011). When using electric generator, it can be assumed as 0.66 kgCO2/kWh. These
values depend on the specific regional characteristics, other authors suggest different
emissions rate: i.e., Shillaber et al. (2016) suggest a conversion factor 0.981 kgCO2/kWh
for electric generators. To have an idea, the accumulated quantity of CO2 emission by
the mobile electric generators used in the reference tunnel is presented in Figure 3.155
(Rodriguez, 2021).
232 Handbook of Precast Segmental Tunnel Lining Systems
The conversion factor rex is about 0.258 kgCO2 per kg of explosive used (manufacturers
Maxam 2015). If emissions due to manufacturing should be included, this rate should be
2.0 kgCO2 per kg of explosive. In the case of tunnels with a cross sectional area bigger
than 60 m2, the amount of explosive needed according to different researchers (Cardu and
Seccatore, 2016) varies from 0.5 to 1.5 kg/m3. To have an idea, the accumulated quan-
tity of CO2 emission by explosive detonation used in the reference tunnel is presented in
Figure 3.156 (Rodriguez, 2021)
The jumbo has two sources of emissions. The first is the diesel fuel consumed to move in
and out this equipment of the tunnel in every cycle. Equation (3.39) can be used for esti-
mating this emission ( DEj ) . The second source of emissions is the electricity consumed
Analysis and design of precast segmental linings 233
by the jumbo. It uses an electrical motor to drill the blasting hole. Equation (3.44) can
be used for this emission ( EEj ). The total emissions of the jumbo during its work will be
TEJ = DEJ + EEJ .
The platform to load the explosives uses diesel to move in and out of the tunnel and
to load the explosives into the blasting holes in every cycle. Its consumption ( DEPL ) will
be the same as Equation (3.39), and its emissions ( EEPL ) will be calculated as shown in
Equation (3.44). The total emissions of the platform during its work will be TEPL = DEPL +
EEPL .
The CO2 produced during the blasting of the explosives will be calculated using
Equation 3.41.
For the working time, it will also depend on the quality of the rock as we mentioned above.
For each specific case, the working time needs to be measured and the emissions will be
evaluated.
Rodríguez et al. (2020) calculated the carbon emission of seven different tunnels exca-
vated in Northwest Spain. The summary of the ratio emissions for these tunnels (kg/m) can
be seen in Table 3.17.
grCO2 hr CO2
3200 kW × (106 − 750) × 20 = 6, 780 − 48, 000 kg.
kWh 100ft 100ft
= 222 − 1575 kg CO2 /m
where NP is the net equipment power in kW, and t is the number of hours working.
Regarding the truck or dumper waiting on low motion to be loaded, can be negligible,
only 2.64 l/h are used. Then, the consumption of the truck (in liters) in waiting mode
will be
The CO2 emissions of this task DEL can be calculated using the conversion factor rD (a
typical value for rD is suggested in 3.9.2.1.
We will consider the speed of 10 and 30 km/h inside and outside the tunnel respectively. Cg
can be calculated based on equations presented in Section 3.9.2.1
The emission will be calculated multiplying the consumption by the CO2 conversion
factor rD :
and invert. Using the presented method in Section 3.9.1, the CO2 emission per m3 of these
mixtures and the total CO2 can be calculated (Tables 3.20 and 3.21).
Portland cement was replaced with limestone Portland cement and 27% of the cementous
material was replaced with slag and silica fume (22% slag and 5% silica fume). Table 3.25
presents these concrete mixture designs.
The baseline backfill/infill concrete consists of ordinary Portland cement (OPC) with no
slag and silica fume. In the carbon-reduced case, 50% of the Portland cement was replaced
with slag. Table 3.26 presents the backfill/infill concrete mixtures for these two cases.
The tail-void backfill grout design is presented in Table 3.27. The same design is used both
for the baseline case and the carbon-reduced case.
Table 3.28 and Table 3.29 summarize the detail of the total embodied carbon footprint
of the tunnel based on the geometry of the tunnel and unit CO2 emission presented in the
previous tables for baseline mixture design and SCM mixture design.
Based on Table 3.29, the total carbon footprint of the two cases, baseline design, and
carbon reduced design is calculated as below:
Total CO2 eq /1m tunnelbaseline design = 6.7 + 2.2 + 1.4 = 10.3 ton
Total CO2 eq /1m tunnelcarbon reduced design = 3.6 + 1.4 + 1.4 = 6.4 ton
As is seen, by using the carbon-reduced concrete mixture for segments and backfill/infill
concrete, the total carbon footprint per 1 m length of the tunnel is reduced by 38%.
BIBLIOGRAPHY
AUTHORITY DOCUMENTS
American Association of State Highway and Transportation Officials (AASHTO)
AASHTO DCRT-1-2010 Technical Manual for Design and Construction of Road Tunnels–Civil
Elements
AASHTO LRFD-1-2017 LRFD Road Tunnel Design and Construction Guide Specifications
American Concrete Institute
ACI 207.1-21 Mass Concrete –Guide
ACI 224.1R-07 Causes, Evaluation, and Repair of Cracks in Concrete Structures
ACI 318-14 Building Code Requirements for Structural Concrete and Commentary
ACI 533.5R-20 Guide for Precast Concrete Tunnel Segments
ACI 544.7R-16 Report on Design and Construction of Fiber-Reinforced Precast Concrete Tunnel
Segments
newgenrtpdf
Table 3.22 Shotcrete mixture design – low carbon case.
SCM shotcrete mixture design for CIP section – low carbon case
239
240 Handbook of Precast Segmental Tunnel Lining Systems
Portland Fiber-
Cementitious Portland limestone Silica Dramix 4D
241
242 Handbook of Precast Segmental Tunnel Lining Systems
Cement +
bentonite+ Portland Rebar
stabilizer cement Bentonite Stabilizer Water/ (kg/ Admixtures Total
(kg/m 3) (kg/m 3) (kg/m 3) (kg/m 3) cement m 3) (kg/m 3) (kg/m 3)
Baseline- 325 325 42.5 5 2.55 0 3.0875 1205.59
grout
Table 3.29 Total embodied carbon footprint of the backfill/infill and tail void backfill grout –
TBM tunnel.
Total embodied carbon footprint of the OPC backfill/infill, OPC backfill/infill with
50% slag and tail void backfill grout – TBM tunnel
BIBLIOGRAPHY
Codes, Standards and Guidelines
ASTM International
ASTM A615/A615M Standard Specification for Deformed and Plain Carbon-Steel Bars for
Concrete Reinforcement
ASTM A706/A706M Standard Specification for Deformed and Plain Low-Alloy Steel Bars for
Concrete Reinforcement
ASTM A1064/A1064M
Standard Specification for Carbon- Steel Wire and Welded Wire
Reinforcement, Plain and Deformed, for Concrete
ASTM A820/A820M Standard Specification for Steel Fibers for Fiber-Reinforced Concrete
ASTM C39/C39M Standard Test Method for Compressive Strength of Cylindrical Concrete
Specimens
ASTM C496 Standard Test Method for Splitting Tensile Strength of Cylindrical
Concrete Specimens
ASTM C618 Standard Specification for Coal Fly Ash and Raw or Calcined Natural
Pozzolan for Use in Concrete
ASTM C989 Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM C1609/C1609M
Standard Test Method for Flexural Performance of Fiber- Reinforced
Concrete (Using beam with Third-Point Loading)
Concrete Society
CS TR63 2007 Guidance for the Design of Steel-Fibre-Reinforced Concrete
French Ministry for the Economy and Finance–Béton armé états limites
BAEL 91 Révisé 99:2007 Considerations on the Usual Methods of Tunnel Lining Design Working
Group No.7―Temporary Supports and Permanent Lining
German Committee for Structural Concrete within German Institute for Standardization
DAfStB Stahlfaserbeton:2012-11 Richtlinie Stahlfaserbeton/Technical Guidelines for Steel Fiber
Reinforced Concrete, Part 1-3
AUTHORED DOCUMENTS
Angerer, W., and Chappell, M., 2008, “Design of Steel Fibre Reinforced Segmental Lining for the Gold
Coast Desalination Tunnels,” Proceedings of 13th Australian Tunneling Conference, pp. 4–7.
Bakhshi, M., and Nasri, V., 2013a., “Latest Developments in Design of Segmental Tunnel Linings,”
Proceedings of the Canadian Society for Civil Engineering General Conference (CSCE 2013),
Montréal, QB, Canada.
Bakhshi, M., and Nasri, V., 2013b, “Practical Aspects of Segmental Tunnel Lining Design,”
Underground –The Way to the Future” Proceedings of the World Tunnel Congress, 2013., G.
Anagnostou and H. Ehrbar, editors, Geneva, Switzerland.
Bakhshi, M., and Nasri, V., 2013c, “Structural Design of Segmental Tunnel Linings,” Proceedings
of 3rd International Conference on Computational Methods in Tunneling and Subsurface
Engineering: EURO: TUN 2013, Ruhr University, Bochum, Germany, pp. 131–138.
Bakhshi, M., and Nasri, V., 2014a, “Review of International Practice on Critical Aspects of Segmental
Tunnel Lining Design,” Proceedings of the 2014 North American Tunneling (NAT) Conference,
Los Angeles, CA, pp. 274–282.
Bakhshi, M., and Nasri, V., 2014b, “Guidelines and Methods on Segmental Tunnel Lining Analysis
and Design –Review and Best Practice Recommendation,” Proceedings of the World Tunnel
Congress, Iguassu Falls, Brazil.
Bakhshi, M., and Nasri, V., 2014c, “Developments in Design for Fiber Reinforced Concrete Segmental
Tunnel Lining,” 2nd FRC International Workshop (1st ACI–fib Joint Workshop) on Fibre
Reinforced Concrete, Montreal, QB, Canada, pp. 441–452.
Bakhshi, M., and Nasri, V., 2014d, “Design Considerations for Precast Tunnel Segments According
to International Recommendations, Guidelines and Standards,” TAC 2014, Vancouver, BC,
Canada.
Bakhshi, M., and Nasri, V., 2015a “Design of Segmental Tunnel Linings for Serviceability Limit
State,” ITA World Tunnel Congress (WTC) 2015, Dubrovnik, Croatia, May 22 to 28, 2015.
Bakhshi, M., and Nasri, V., 2015b, “Cracking Serviceability Limit State for Precast Concrete Tunnel
Segments,” Canadian Society of Civil Engineers (CSCE) 2015 General Conference, Regina,
Canada.
Bakhshi, M., and Nasri, V., 2017a, “Design of Steel Fiber-Reinforced Concrete Segmental Lining for
the South Hartford CSO Tunnel,” Rapid Excavation Tunneling Conference (RETC) 2017, San
Diego, CA, June 4–7, 2017, pp. 706–717.
Bakhshi, M., and Nasri, V., 2017b, “Reduction of Water Inflow by Controlling Cracks in Tunnel
Segmental Linings Using Fiber Reinforcement,” SP-319, Reduction of Crack Width with Fiber,
American Concrete Institute, Farmington Hills, MI (CD-ROM).
246 Handbook of Precast Segmental Tunnel Lining Systems
Bakhshi, M., and Nasri, V., 2018, “Guide for Optimized Design of Tunnel Segmental Ring Geometry,”
Proceedings of the 2018 North American Tunneling (NAT) Conference, Los Angeles, CA,
pp. 274–282.
Bakhshi, M., and Nasri, V., 2020, “Crack Width Simulation and Non-Linear Finite Element Analysis
of Bursting and Spalling Stresses in Precast FRC Tunnel Segments Under TBM Thrust Jack
Forces,” RILEM-fib International Symposium on Fibre Reinforced Concrete. Springer, Cham,
Switzerland, 2020.
Bakhshi, M., Barsby, C., and Mobasher, B., 2014, “Comparative Evaluation of Early Age Toughness
Parameters in Fiber Reinforced Concrete,” Materials and Structures, V. 47, No.5, pp. 853–872.
Barros, J. A. O., Cunha, V. M. C. F., Ribeiro, A. F., and Antunes, J. A. B., 2005, “Post-Cracking
Behaviour of Steel Fibre Reinforced Concrete,” Materials and Structures, V. 38, No. 1,
pp. 47–56.
Barwart, C., Romualdi, P., and Barioffi, A., 2013, “Headrace Tunnel of the El Alto Hydropower
Project in Panama,” Geomechanics and Tunnelling, V. 6, No.4, pp. 301–311. https://doi.org/
10.1002/geot.201300019
Beňo, J., and Hilar, M., 2013, “Steel Fibre Reinforced Concrete for Tunnel Lining –Verification by
Extensive Laboratory Testing and Numerical Modelling,” Acta Polytechnica, V. 53, No. 4,
pp. 329–337.
Blom, C. B. M., 2002, “Design Philosophy of Concrete Linings for Tunnels in Soft Soil,” Ph.D. disser-
tation, Delft University Press, December.
Burgers, R., Walraven, J., Plizzari, G.A., and Tiberti, G., 2007, “Structural Behavior of SFRC
Tunnel Segments During TBM Operations,” World Tunneling Congress (WTC) 2007,
pp. 1461–1467.
Caan, C.P., Jansen, J. A. G., Heijmans, R. W. M. G., and van der Put, J. L., 1998, “High Speed Line–
South: The Groene Hart Tunnel –Lining Design,” Reference Design, Report No. 9G4 0001
981028, 52 pages.
Caratelli, A., Meda, A., and Rinaldi, Z., 2012, “Design According to MC2010 of a Fibre-Reinforced
Concrete Tunnel in Monte Lirio, Panama,” Structural Concrete, V. 13, No. 3, pp.166–173.
Cardu, M., and Seccatore, J., 2016, “Quantifying the Difficulty of Tunnelling by Drilling and Blasting,”
Tunnelling and Underground Space Technology V. 60, No. 2016, pp. 178–182.
Caverzan, A., Colombo, M., Di Prisco, M., and Rivolta, B., 2015, “High Performance Steel Fibre
Reinforced Concrete: Residual Behaviour at High Temperature,” Materials and Structures,
V. 48, No.10, pp. 3317–3329.
Chaallal, O., and Shahawy, M., 2000, “Performance of Fiber-Reinforced Polymer-Wrapped Reinforced
Concrete Column Under Combined Axial-Flexural Loading,” ACI Structural Journal, V. 97,
pp. 659–668. https://doi.org/10.14359/7433
Chiaia, B, Fantilli, A.P., Vallini, P., 2007, “Evaluation of Minimum Reinforcement Ratio in FRC
Members and Application to Tunnel Linings,” Materials and Structures, V. 40, pp. 593–604.
https://doi.org/10.1617/s11527-006-9166-0
Çimentepe, A. G., 2010, “Evaluation of Structural Analysis Methods Used for the Design of TBM
Segmental Linings,” MSc Thesis, Middle East Technical University, Ankara, Turkey.
Colombo, M., Martinelli, P., and di Prisco, M., 2015, “A Design Approach for Tunnels Exposed to
Blast and Fire,” Structural Concrete, V. 16, No. 2, pp. 262–272.
Curtis, D. J., Hay, M., and Croydon, A., 1976, “Discussion on ‘The Circular Tunnel in Elastic
Ground,’ ” Géotechnique, V. 26, No. 1, pp. 231–237.
de la Fuente, A., Pujadas, P., Blanco, A., and Aguado, A., 2012, “Experiences in Barcelona with
the Use of Fibres in Segmental Linings,” Tunnel and Underground Space Technology, V. 27,
pp. 60–71. https://doi.org/10.1016/j.tust.2011.07.001
de Oliveira e Sousa, J. L. A., Gettu, R., and de Oliveira e Sousa, 2006, “Determining the Tensile Stress-
Crack Opening Curve of Concrete by Inverse Analysis,” Journal of Engineering Mechanics,
V. 132, No. 2, pp. 141–148. https://doi.org/10.1061/(ASCE)0733-9399(2006)132:2(141)
Deere, D. U., Peck, R. B., Monsees, J. E., and Schmidt, B., 1969, “Design of Tunnel Liners and Support
Systems,” Highway Research Record 889, Final Report to Urban Mass Transit Administration,
U.S. Department of Transportation, Washington, DC.
Analysis and design of precast segmental linings 247
Miliutenko, S., Akerman, J., and Bjorklund, A., 2012, “Energy Use and Greenhouse Gas Emissions
during the Life Cycle Stages of a Road Tunnel –The Swedish Case Norra Lanken,” European
Journal of Transport and Infrastructure Research, V. 12, No. 1, pp. 39–62.
Mobasher, B., Bakhshi, M., and Barsby, C., 2014, “Back Calculation of Residual Tensile Strength of
Regular and High Performance Fiber Reinforced,” Construction & Building Materials, V. 70,
pp. 243–253.
Moccichino, M., Romualdi, P., Perruzza, P., Meda, A., and Rinaldi, Z., 2010, “Experimental Tests
on Tunnel Precast Segmental Lining with Fiber Reinforced Concrete,” ITA 2010 World Tunnel
Congress, Vancouver, Canada.
Morgan, H. D., 1961, “A Contribution to the Analysis of Stress in A Circular Tunnel,” Geotechnique,
V. 11, pp. 37–46.
Muir Wood, A. M., 1975, “The Circular Tunnel in Elastic Ground,” Géotechnique, V. 25, No. 1,
pp. 115–127.
Neun, E., 2012, “Structural Fire Safety Engineering. Eurocode Approach and Practical Application,”
Proceedings of the World Tunnelling Congress 2012. Bangkok, Thailand.
Newmark, N. M., 1965, “Effects of Earthquakes on Dams and Embankments,” Geotechnique, V. 15,
pp. 139–159.
Ninić, J., and Meschke, G., 2017, “Simulation Based Evaluation of Time-Variant Loadings Acting
on Tunnel Linings During Mechanized Tunnel Construction,” Engineering Structures, V. 135,
pp. 21–40.
Olesen, J. F., 2001, “Fictitious Crack Propagation in Fiber Reinforced Concrete Beams,”
Journal of Engineering Mechanics, V. 127, No. 3, pp. 272– 280. https://doi.org/10.1061/
(asce)0733-9399(2001)127:3(272).
Owen, G. N., and Scholl, R. E., 1981, “Earthquake Engineering of Large Underground Structures,”
Final Report, Report No. FHWA/ RD-80/
195, Federal Highway Administration, U.S.
Department of Transportation, Washington, DC.
Peck, R. B., 1969, “Deep Excavation and Tunnelling in Soft Ground, State of the Art Report,”
7th International Conference on Soil Mechanics and Foundation Engineering, Mexico City,
Mexico, pp. 225–290.
Piek, L., Ramsey, M., Oginski, S., and Hariharan, M., 2017, “Tunnel Station Joint Solution on the
Crenshaw LAX Corridor,” North American Tunneling Journal, Dec. 2017–Jan 2018, pp. 12–18.
Plizzari, G., 2009, Construction Methodologies and Structural Performance of Tunnel
Linings: Optimisation of the Structural, Technological and Functional Performance, of
Construction Methodologies and Materials, in Tunnel Linings, Starrylink Editrice, Brescia,
Italy.
Poh, J., Tan, K. H., Peterson, G. L., and Wen, D., 2009, “Structural Testing of Steel Fibre Reinforced
Concrete (SFRC) Tunnel Lining Segments in Singapore,” Proceedings of the World Tunnelling
Congress, Budapest, Hungary.
Rodriguez, J.A., and Aristizabal-Ochoa, J.D., 1999, “Biaxial Interaction Diagrams for Short RC
Columns of Any Cross-Section,” Journal of Structural Engineering, V. 125, pp. 672–683.
https://doi.org/10.1061/(ASCE)0733-9445(1999)125:6(672)
Rodríguez, R., and Pérez, F., 2020, “Carbon Foot Print Evaluation in Tunneling Construction using
Conventional Methods,” Tunnelling and Underground Space Technology, 108, p. 103704.
10.1016/j.tust.2020.103704.
Rodríguez, R., Tosal, A., P´erez, F., Díaz- Aguado, M.B., 2017. “Advancing Rate and Carbon
Footprint Related to Different Excavation Methods in Conventional Tunnelling” (Fabares tun-
nel, Asturias, Spain). International Conference on NexGen Technoclogies for Mining and Fuel
Industries 2017 (NxGnMiFu 2017). February 15–17, 2017, New Delhi, India.
Rostami, J., 2008, “Hard Rock TBM Cutterhead Modeling for Design and Performance Prediction,”
Geomechanics and Tunneling, V. 1, No. 1, pp. 18–28.
Salam, A., Greberg, B., Skawina, B., Gustafson, A., 2015, “Analysing Energy Consumption and Gas
Emissions of Loading Equipment in Underground Mining,” Canadian Institute of Mining,
Metallurgy and Petroleum (CIM), V. 6, No. 4, pp. 179–188.
Analysis and design of precast segmental linings 249
Schwartz, C. W., Azzouz, A. S., and Einstein, H. H., 1980, “Improved Design of Tunnel Supports,”
UMTA-MA-06-0100-8 0-5. U.S. Department of Transportation, Washington, DC.
Shillaber, C., Mitchell, J., and Dove, J., 2016, “Energy and Carbon Assessment of Ground Improvement
Works. 2016 II: Working Model and Example,” Journal of Geotechnical and Geoenvironmental
Engineering, V. 142, No. 3, pp. 04015083-1–04015083-9.
Sinha, R. S., 1989, Underground Structures: Design and Instrumentation, Elsevier Science, New York,
500 pages.
Soranakom, C., and Mobasher, B., 2007, “Closed-Form Solutions for Flexural Response of Fiber
Reinforced Concrete Beams,” Journal of Engineering Mechanics, V. 133, No. 8, pp. 933–941.
St. John, C. M., and Zahrah, T. F., 1987, “Aseismic Design of Underground Structures,” Tunnelling
and Underground Space Technology, V. 2, No. 2, pp. 165–197.
Steven, G., and Empelmann, M., 2014, “UHPFRC- Columns with High- Strength Longitudinal
Reinforcement,” Beton–und Stahlbetonbau 109, 344–354. https://doi.org/10.1002/best.201300090
Talmon, A. M., and Bezuijen, A., 2013, “Analytical Model for the Beam Action of a Tunnel Lining
During Construction,” International Journal for Numerical and Analytical Methods in
Geomechanics, V. 37, No. 2, pp. 181–200.
Tiberti, G., 2009, “Concrete Tunnel Segments with Combined Traditional and Fiber Reinforcement:
Optimization of the Structural Behaviour and Design Aspects,” Ph.D. Dissertation, University
of Brescia.
Tiberti, G., 2014, “Concrete Tunnel Segments with Combined Traditional and Fiber Reinforcement:
Optimization of the Structural Behavior and Design Aspects,” Ph.D. Thesis, Department of
Civil, Environmental, Architectural Engineering and Mathematics, University of Brescia, June
2014, Aracne editrice s.r.l., Rome, Italy, ISBN: 978-88-548-7005-5, 396 p.
Tiberti, G., Plizzari, G. A., Walraven, J. C., and Blom, C. B. M., 2008, “Concrete Tunnel Segments with
Combined Traditional and Fiber Reinforcement,” Proceedings of the fib 2008 Symposium: Tailor
Made Concrete Structures, Amsterdam, the Netherlands, pp. 199–205.
Tiberti, G., Conforti, A., and Plizzari, G.A., 2015, “Precast Segments Under TBM Hydraulic
Jacks: Experimental Investigation on the Local Splitting Behavior,” Tunnelling and Underground
Space Technology, V. 50, pp. 438–450. https://doi.org/10.1016/j.tust.2015.08.013
Vandewalle, L., 2000, “Cracking Behaviour of Concrete Beams Reinforced with a Combination of
Ordinary Reinforcement and Steel Fibers,” Materials and Structures, V. 33, No. 3, pp. 164–170.
Vasdravellis G, Uy B, Tan EL, and Kirkland B., 2012, “Behaviour and Design of Composite Beams
Subjected to Negative Bending and Compression,” Journal of Constructional Steel Research,
V. 79, pp. 34–47. https://doi.org/10.1016/j.jcsr.2012.07.012
Vodička, J., Krátký, J., Hilar, M., and Ráček, V., 2012, “Structural SFRC for Precast Segments of
the Tunnel Lining,” 8th Central European Congress on Concrete Engineering, Durability of
Concrete Structures, Plitvice Lakes, Croatia.
Wang, J.- N., 1993, Seismic Design of Tunnels – A Simple State- of-
the-Art Design Approach,
Monograph No. 7, Parsons Brinckerhoff, New York.
Wells, D., and Coppersmith, K., 1994, “Updated Empirical Relationships among Magnitude, Rupture
Length, Rupture Area, and Surface Displacement,” Bulletin of the Seismological Society of
America, V. 84, pp. 974–1002.
Yao, Y., Bakhshi, M., Nasri, V., and Mobasher, B., 2018a, “Interaction Diagrams for Design of Hybrid
Fiber-Reinforced Tunnel Segments,” Materials and Structures, V. 51, No. 1, 17 pages.
Yao, Y., Bakhshi, M., Nasri, V., and Mobasher, B., 2018b, “Closed-Form Solutions for Interaction
Diagrams of Hybrid Fiber-Reinforced Tunnel Segments,” Proceedings of FRC2018–3rd ACI-
fib-
RILEM on Fibre Reinforced Concrete: From Design to Structural Applications, Lake
Garda, Italy.
Zhang, J., and Stang, H., 1998, “Applications of Stress Crack Width Relationship in Predicting the
Flexural Behavior of Fibre Reinforced Concrete,” Cement and Concrete Research, V. 28, No. 3,
pp. 439–452. https://doi.org/10.1016/S0008-8846(97)00275-5.
Zhong, X.-C., Liu, Q.-W., and Zhao, H., 2011, “Study on the Grouting Pressure of Shield Tunnel,”
ASCE Geotechnical Special Publication, V. 215, pp. 183–190.
250 Handbook of Precast Segmental Tunnel Lining Systems
NOTATION
A = effective tension area of concrete around rebar divided by number of steel bars,
in.2 (mm2)
Ad = load distribution area inside segment under thrust jack forces, in.2 (mm2)
Ag = gross area of concrete section, in.2 (mm2)
Aj = area of contact zone between jack shoes and the segment face, in.2 (mm2)
As = area of reinforcing bars, in.2 (mm2)
a = distance from edge of vacuum lift pad to edge of segment in the load case of
stripping (demolding), or dimension of final spreading surface under thrust jack
forces, in. (mm)
al = transverse length of contact zone between jack shoes and the segment face,
in. (mm)
at = transverse length of stress distribution zone at the centerline of segment under
thrust jack forces, in. (mm)
b = width of tunnel segment, or width of tested specimen, ft (m)
Cc = compression force in the concrete section, lbf (N)
Ct = tensile force in the section due to fiber reinforcement, lbf (N)
De = external diameters of the tunnel segmental lining, ft (m)
Di = internal diameter of the tunnel segmental lining, ft (m)
d = thickness of tested specimen, or total width of the segment cross section, in. (mm)
d1 = length of load transfer zone for the case of longitudinal joint bursting load,
in. (mm)
dburst = centroidal distance of bursting force from the face of section, in. (mm)
dk = width of the hinge joint or thickness of contact surface between segment joints
for the case of longitudinal joint bursting load, in. (mm)
dc = concrete cover over rebar, in. (mm)
ds = distributed width of stress block inside the segment for the case of longitudinal
joint bursting, in. (mm)
E = modulus of elasticity of concrete, psi (MPa)
Er = modulus of elasticity of surrounding ground, psi (MPa)
Es = stiffness modulus of the surrounding ground determined by oedometer test, psi
(MPa); or modulus of elasticity of rebar, psi (MPa)
EH = horizontal earth pressure, psi (MPa)
EV = vertical earth pressure, psi (MPa)
e = eccentricity, in. (mm)
eanc = eccentricity of jack pads with respect to the centroid of cross section, or max-
imum total eccentricity in longitudinal joints consisting of force eccentricity and
eccentricity of load transfer area, in. (mm)
F = forces acting on bottom segment due to self-weight of segments positioned above
when segments are piled up within one stack during storage or transportation
phases, lbf (N)
Fsd = bursting tensile forces developed close to longitudinal joints, lbf (N)
Fsd,r = spalling tensile forces developed close to longitudinal joints, lbf (N)
Fsd,2 = secondary tensile forces developed close to longitudinal joints, lbf (N)
fy = yield stress of required reinforcing bars, psi (MPa)
f1 = first peak flexural strength, psi (MPa)
fbot = stress at the extreme bottom fiber of concrete section, psi (MPa)
f′c = specified compressive strength of concrete segment, psi (MPa)
Analysis and design of precast segmental linings 251
Pe2 = vertical earth pressure at invert of lining applied to the elastic equation
method, psi (MPa)
Pg = segment dead load, psi (MPa)
Pgr = Radial grouting pressure, psi (MPa)
Pw1 = vertical water pressure at crown of lining applied to the elastic equation
method, psi (MPa)
Pw2 = vertical water pressure at invert of lining applied to the elastic equation
method, psi (MPa)
Ppu = factored jacking force applied on each jack pad in circumferential joints, or
maximum factored normal force from the final service loads transferred in
longitudinal joints, psi (MPa)
qe1 = horizontal earth pressure at crown of lining applied to the elastic equation
method, psi (MPa)
qe2 = horizontal earth pressure at invert of lining applied to the elastic equation
method, psi (MPa)
qw1 = horizontal water pressure at crown of lining applied to the elastic equation
method, psi (MPa)
qw2 = horizontal water pressure at invert of lining applied to the elastic equation
method, psi (MPa)
R = radius from centerline of lining, ft (m)
ro = radius of excavated tunnel, ft (m)
s = maximum rebar spacing, in. (mm)
S = distance between stack supports and free edge of segments in the load case of
segment storage, ft (m)
ss = sample standard deviations of test results
sr,max = maximum crack spacing, mm
Tburst = bursting force, lbf (N)
WAp = groundwater pressure, psi (MPa)
w = segment self-weight, plf (kg/m); or maximum crack width, in. (mm)
yc = distance from extreme compression fiber to centroid of equivalent compres-
sion force in the section, in. (mm)
y = distance from extreme tension fiber to the neutral axis, in. (mm)
β = dimension of the loaded surface under thrust jack forces according to Iyengar
diagram, in. (mm); or in crack width analysis ratio of the distance between
neutral axis and tension face to the distance between neutral axis and cen-
troid of rebar
ΔPg, invert = vertical gradient of radial grout pressure between the crown and invert of
tunnel, psi (MPa)
δ = displacement of lining applied to the elastic equation method, in. (mm)
δd = diametrical distortion, in. (mm)
εtu = ultimate compressive strain
εcu = ultimate tensile strain
ε’csd = compressive strain due to shrinkage and creep equal to 150×10-6
ϕ = strength reduction factor; or reinforcing bar diameter, in. (mm)
γ = material safety factor
λ = slenderness defined as the ratio between the developed segment lengths and
its thickness
Analysis and design of precast segmental linings 253
θ = angle from crown in the elastic equation method, or rotation in the longitu-
dinal Janssen joint, radians
ρconcrete = specific weight of concrete, lb/ft3 (kg/m3)
ρeq = equivalent specific weight of grout, lb/ft3 (kg/m3)
σc,j = compressive stresses developed under jack pads because of axial effects of
thrust jack forces, psi (MPa)
σcm = fully spread compressive stress in method of the Iyengar diagram, psi (MPa)
σcx = bursting tensile stresses using the Iyengar diagram, psi (MPa)
σp = specified post-crack residual tensile strength of FRC segment, psi (MPa)
τyield = shear yield strength of grout, psi (MPa)
Chapter 4
4.1 INTRODUCTION
Portland cement industry is among the primary producers of greenhouse gases generating
between 5 to 8% of worldwide man-made point-source CO2 emissions. The nature of the
release of greenhouse gases from cement plants has led to pervasive discussions on the
carbon footprint of concrete materials [1]. Substitution with alternative construction mate
rials is however a daunting task since cement and concrete contain the lowest embodied
energy of all man-made industrial and construction materials [2].
The statistics are staggering. Every year an estimated weight of 25 billion tons of con-
crete is manufactured globally, represented by about 3.8 tons per person. Concrete is used
around the world more than the total of all other building materials, including wood,
steel and plastics. According to United States Environmental Protection Agency (US EPA)
estimates, at the end-of-use stage, the Construction and Demolition (C & D) debris con-
stituted 600 million tons in the United States in 2018, twice the amount of generated
MSW [3].
The United States cement industry developed a voluntary goal of reducing CO2 emissions
by 10% (based on 1990 levels) per ton of cementitious products by implementing quality
monitoring and control to make cement production more sustainable. We still face a multi-
faceted set of challenges that include better design of structural materials by taking into
account the climate change, cement carbon footprint, the volume of materials used, envir-
onmental risk factors, durability and the need to incorporate serviceability, performance-
based specifications, economy and hybrid design approaches. It is expected that we focus
on developing methods to better utilize, design and construct concrete structures while pur-
suing sustainable guidelines that include new materials and design approaches.
In recent years, a significant number of tunneling projects worth more than $100 bil-
lion are planned by municipalities in every state in the nation with more than $40 billion
in active bidding [4]. Given such infrastructure investments, the precast concrete industry
needs a more robust and systemic approach for design, analysis, testing, quality control,
tolerance control and qualifications of the tunnel lining segments that are among the most
highly engineered components of the civil works projects. Furthermore, with extremely high
tolerances and substantial costs of repair due to failure or deterioration, we must address
new construction or maintenance of aging infrastructure using innovative approaches devel-
oped recently in the concrete industry.
The use of precast segments by tunnel boring machines (TBMs) in underground con-
struction is becoming the dominant and cost-effective approach for traffic, rail, metro,
water and wastewater tunnels systems [5]. The justifications for the use of precast concrete
DOI: 10.1201/9781032675541-4
Precast concrete technologies 255
segments are based on the speed of construction, elimination of temporary support, serv-
ing as the reaction frame for boring, the combination of initial and final support, choice
support for TBM bored tunnels in soft ground and weak fractured rock [6]. This chapter
addresses the criteria and fundamental importance of the parameters that affect the
strength, ductility and durability of the precast concrete materials used in tunnel segments
using the TBM-type machines. Fundamental contributions of the mix components, design
parameters, early age and long-term properties, as well as the durability of the material,
are addressed.
resistant to corrosion, hence the stringent requirements of these structures require con-
crete quality and control of crack widths. The main design requirements of wastewater
treatment facilities are water tightness and durability. Tunnel facilities must be designed
to minimize fluids leakage. Accordingly, the design process should address the probability
distribution of maximum crack width under service loads while preventing the emergence
of wide cracks and other potential sources of leakage, such as joints. Shrinkage and thermal
dimensional changes must also be considered in the definition of joints. Criteria need to
be defined for the movement along slip lines and permission zones including barriers to
avoid the passage of fluids. Design analysis must be as accurate as possible, allowing the
perception of the structure’s true stress distribution and preventing cracking at the max-
imum stress zones.
In environmental applications, such as tunnel lining, one can anticipate advantages from
the use of FRC that include drastic reductions in reinforcement and a mix formulation
that permits self-consolidation and improved segregation resistance. By increasing the cost-
effectiveness and labor efficiency in construction, improved durability and minimized need
for maintenance and repair operations are expected.
The designer starts from the applied forces due to loading conditions, obtains the solu-
tion of equilibrium of forces using structural analysis or finite element models, and proceeds
to compute the limit states, failure mechanisms and deformations to obtain the structural
demand. After the choices of material properties are made, these will be interfaced with
optimization tools of analysis and design for a large subset of design parameters. Model
validation can be carried out through material testing, parameter estimation, experimental
full-scale tests, failure mode analysis and load-displacement experiments on full sections
that include TBM precast sections and other structural concerns, such as the durability that
apply to environmental structures.
The stages of loading can be determined in terms of production, handling, transporta-
tion and installation before the service life or ultimate state is considered. In these stages,
ductility and crack tolerance are important aspects of serviceability requirements. Due to
the many advantages offered to the tunnel sections, fiber reinforced concrete has received
much attention compared to conventional reinforced concrete (RC). In addition to the
economy and speed of construction, these include their ductility, durability, crack control,
as well as higher impact, fatigue, blast and fire resistance. In addition, fiber reinforcement
provides overall materials toughness and protections for localized cracking in the edges
and corners, which could easily occur during handling or installation. Special loading
cases are also considered in terms of dynamic loading, blast, impact and fire [10].
The primary mode of serviceability level loading of the circular tunnel linings is the com-
bined loading of normal forces and relatively low bending moments. Due to the low bend-
ing capacity required, oftentimes, the use of SFRC to satisfy the minimum reinforcement is
sufficient. SFRC segment applications have thus flourished as an integral part of the design
domain. SFRC also helps in areas with no continuous reinforcement to protect the edges
and corners of the elements. The benefits of FRC in areas such as fire and blast events in
the lining design have received limited attention. The energy density released in a confined
volume of a tunnel due to an explosion is much higher compared to a blast in open space.
Explosions are therefore the extreme consequence of fire accidents [11]. Design aspects such
as stiffness of the section after cracking, its ductility, and residual tensile capacity are dom-
inant design parameters. This indicates that the flexural strength or compressive strength
cannot be used as the primary acceptance metric and the full response of the sections under
flexural or tensile loading should be characterized.
Precast concrete technologies 257
Key concerns in terms of design for serviceability in terms of permeability, crack width
and stiffness can be addressed by the use of fibers. Therefore, this has further promoted the
application of FRC due to its cost competitiveness at the structural level compared with
other traditional solutions which require a higher reinforcement ratio.
4.3.1 Portland cement
Portland cement is the main binding agent in concrete that sets and hardens by the chemical
reactions of its constituents with water, hence categorized as hydraulic cement. Portland
cement clinker is made by calcination of raw natural minerals containing oxides of cal-
cium, silica, aluminum and iron elements. These are expressed in terms of the oxides (CaO,
SiO2, Al2O3, Fe2O3) and partial amounts of impurities. These oxides are intermixed and go
through the process of calcination in a kiln to produce the Portland cement clinker. At this
stage, the clinker is a hydraulic material with two primary components of tri-calcium and
di-calcium silicates (3CaO ⋅ SiO2 and 2CaO ⋅ SiO2), as that contributes to the hydration pro-
cess. The remaining compounds of calcium, aluminum and iron-containing phases as well
as other compounds can be viewed as impurities.
Portland cement is produced by grinding the clinker to a powder with a high surface area
and then blending it with gypsum (calcium sulfate) to help control the reaction of the alu-
minate phases. Cement types are classified differently throughout the world. In the United
States, most Portland cements for commercial construction meet the requirements of ASTM
C150 [16]. ASTM C150 is a prescriptive specification with limits on both chemical and
physical characteristics. According to ASTM C150, cement types are classified based on the
relative proportions of the oxides present and labeled as type I through type V with those
meeting multiple categories such as types I/II, and those including secondary components
258 Handbook of Precast Segmental Tunnel Lining Systems
as blended such as air-entraining component with an A, such as type IIA. Blended cements
with pozzolans or slag are available and referred to with a suffix such as type IIP, IIS.
Portland-cements in Canada are specified under a performance specification of CSA
A3001 [17]. Cement types are labeled as type GU, type MS, type MH, type HE, type LH, or
type HS, with an L added after the two-letter code, such as GUL, designating that a higher
amount of limestone has been added.
In Europe, types of cement are classified in EN 197 by the composition of oxides into
many categories of different common types of cement, sulfate- resisting-
cements, blast
furnace cement, and their constituents. Portland types of cement are labeled CEM I and
blended types of cement labeled CEM II, through CEM V [18]. Sulfate-resisting Portland
types of cement are labeled with an SR designation. In addition, the cement is labeled with
a strength class of 32.5, 42.5, or 52.5, which is the minimum 28-day strength of mortar, in
MPa, from standard testing. An example of a blended sulfate-resisting cement from EN 197
is CEM III/B-SR 32.5. Desired concrete performance and local availability of specific classes
of cement will guide the selection of Portland cement for a project. New Belite cements are
also gaining popularity [19].
(a) Rheology and workability by reducing the bleeding and segregation tendency
(b) Durability enhancements by reducing the permeability, and pore size, while increasing
the matrix and the interfacial transition zone packing and hydration products
Precast concrete technologies 259
(c) Resistance to ionic mobility including chlorides, sulfates, and alkalis responsible for
alkali-aggregate expansion. Reduction of heat generation, shrinkage potential, plastic
shrinkage cracking, as well as resistance to thermal cracking,
(d) Increase early age and ultimate strength
The history of using blended cements to improve the strength and durability of concrete
goes back decades. The primary feature is the pozzolanic reactivity, which is generally iden-
tified with the reaction of SCM with portlandite to create additional calcium silicate hydrate
(C-S-H) [22]. Primarily the initial applications revolved around the effectiveness of blended
cements in reducing the potential sulfate attack damage [23]. Despite the wealth of studies
conducted, the role of the chemical composition of pozzolanic materials is affected by the
source due to the large degree of variation among the origin, type and manufacturing pro-
cess of pozzolans. The demand for blended cements and applications of pozzolanic materials
for ASR and sulfate attack mitigation has enhanced the scientific nature of characterization
tests. While the supplies are diminishing in certain categories, new sources of SCMs will
need to be identified and optimized for use in concrete construction [24].
The SCM materials used are typically specified in terms of their specific ASTM designa-
tions that include type I/II ordinary Portland cement (OPC) conforming to ASTM C150,
class F, and C fly ash and metakaolin, or natural pozzolans conforming to ASTM C618, slag
conforming to ASTM C989, limestone powder conforming to ASTM C568, and microsilica
(silica fume) conforming to ASTM C1240. While these materials are significantly different
260 Handbook of Precast Segmental Tunnel Lining Systems
in terms of their chemical and physical properties, their particle size can be used as a basis
for comparison. The particle size distribution (PSD) curves of some of these materials are
shown in Figure 4.2. The chemical compositions and physical characteristics of these mate
rials are available in the report [25].
The following sections describe some of the more common SCMs with the primary cat-
egories that include fly ash, silica fume, slag and metakaolin, which provide significant eco-
nomic and environmental benefits.
Due to its fine particle size and challenges in handling and mixing, silica fume is used
under different forms of microsilica powder, condensed silica fume or slurry form. Research
has shown that silica fume particles tend to agglomerate resulting in extremely low work-
ability and therefore it is important to develop mixing methods to reduce the agglomera-
tions for a workable concrete mixture. The condensed silica fume is used quite commonly
due to ease of handling, and airborne particle safety.
Silica fume is pozzolanic and enhances the mechanical properties of the matrix due to
pore size and interface transition zone refinement as a result of the formation of secondary
hydration products. The reactivity of silica fume is attributed to the nature of highly reactive
silica and its small particle size, which results in faster property development compared to
other SCMs. The high reactivity is best shown by comparing the strength activity indices of
silica fume with fly ash in cementitious systems [27]. While the small particle size directly
increases the rate of reaction, a thorough and uniform dispersion of such fine particles is
challenging, thus a high dosage of superplasticizer is needed. The particle agglomeration
may reduce the expected benefits of mechanical properties or cause ASR-type reactions due
to the agglomeration of condensed grains.
4.3.4 Fly ash
Fly ash is the finely divided residue that is airborne and collected in a bag-house as a coal-
burning by-product of a steam-generating power plant. Pulverized fuel ash is a less common
term for fly ash. Fly ash is primarily glassy (amorphous) spherical particles that react via the
pozzolanic reaction only, or have both pozzolanic and cementitious properties. Its chem-
ical nature is directly affected by the properties of the coal burned at the power plant. The
spherical shape of the particles improves the rheology, workability and packing density of
the mixture, thus improving the permeability [Figures 4.3(a) and (b)].
As the burning of pulverized coal generates heat, inorganic molten mineral residues
harden into bottom ash. Cooling of the flue gas causes the airborne particles to harden
as fly ash. Emission control equipment use a combination of electrostatic separators and/
or filter fabric bag-houses that remove the fly ash [28]. The economic and environmental
benefits of fly ash in concrete is enhanced by improving mechanical properties. Fly ash use
reduces greenhouse gases, decreases life cycle costs, and increases the concrete’s durability.
Production of fly ash during the 1990s was about 100 million tons per year at a utilization
rate of 20% in applications such as blended cements, and road base stabilization. The avail-
ability however is reduced due to the switching of the power plants from coal to natural gas.
Depending on the source of coal, fly ash may be siliceous or calcareous, and while both
types have pozzolanic properties, higher calcium levels indicate potentials for hydraulic
properties. Siliceous fly ash consists of reactive silicon dioxide (SiO2) and aluminum oxide
(Al2O3) in the form of a spherical fine powder. The remainder contains iron oxide (Fe2O3)
with a low proportion of reactive calcium oxide (CaO) that is less than 10% by mass and
other compounds. In the United States, fly ash is classified primarily by the calcium content
into high-calcium (class C) or low-calcium (class F). Its chemical composition is per ASTM
C618. Due to the relatively high calcium content of up to about 20%, class C fly ashes typ-
ically have some cementitious nature. In Canada, class C fly ashes are further divided into
class CI, for intermediate calcium content, and class CH, for high calcium content [29]. Fly
ash is often used at a level of 15 to 30% of the total cementitious content of a concrete mix.
Class C ashes from sub-bituminous coals contain calcium alumino-sulfate glass, such as
quartz (Si O2), free lime (CaO), and high-calcium content that is a key factor in mitigating
sulfate attack and ASR.
The reaction of calcium silicate phases (C3S and C2S) in the Portland cement generates
calcium silicate hydrate CSH gel and the extra calcium is released in the form of the calcium
hydroxide. As a pozzolanic material, fly ash reacts with the released calcium hydroxide to
form its CSH hydration product [30]. Due to the need for high pH necessary and sufficient
calcium ions present, this sequential reaction takes longer to accomplish than the hydration
of Portland cement. The additional CSH production ultimately improves concrete proper-
ties. Due to the extended time required for the hydration of fly ash, the rate of the heat of
hydration reduces. The net increase of the hydration products (C-S-H gel), improves the
mechanical properties and durability of concrete. The synergy of the use of fly ash with
other SCMs such as silica fume and metakaolin accelerates property development at early
ages [31]. The disadvantages include the slower rate of reaction of fly ash (in general, class
F), which may affect the setting times, as well as lower early-age strength. The variability
of fly ash sources introduces uncertainty in the setting time, which affects the operation
schedule.
Class F fly ash replacement levels range from 10 to 30% by mass of cement, while class C
fly ash can be used in higher proportions. Early promotion of the use of fly ash can be
attributed to the significant research conducted during the 1980s and 1990s to address
concrete durability Aïtcin [32]. The utilization of mineral by-products was correlated to
the worldwide growth of infrastructure development. Neville and Aitcin [33] reported on
high-performance concrete containing fly ash, ground granulated blast furnace slag, and
silica fume where the dosage of fly ash in high volume of fly ash (HVFA) concrete can
exceed 50% [34]. Many studies addressed the physical, chemical (including trace elements),
mineralogical, and LOI (loss on ignition test) properties of fly ashes. The LOI tests deter-
mine the unburnt carbon content of fly ash as it affects the influence of carbon content on
air-entraining admixture demand. The durability of concrete under various chemical and
physical environments has been studied in detail and with satisfactory resistance. Sulfate
resistance may be improved depending on the replacement level.
The chemistry of class C ashes is quite variable and less efficient at mitigating ASR com-
pared to class F. ASTM C1567 testing is required for comparison of different grades of
class C fly ash from class F so that a minimum dosage level is determined. The design for
Precast concrete technologies 263
ASR resistance requires a reduction in the Portland cement to limit the alkali loading to
≤ 2.1 kg/m3 (3.5 lb/CY). ASTM C1567 testing is used to determine if reduced dosages,
other local class C ashes, or tertiary blends are acceptable. Figure 4.3(a) shows a scanning
electron microscope’s (SEM) micrograph of the small and characteristically round fly ash
particles. The X-ray diffraction pattern of class F fly ash shows the general amorphous
nature of fly ash containing quartz and mullite as the few crystalline phases are shown in
Figure 4.3(b) showing present.
To address the risks from improper disposal and discharge of coal ash, new environmental
guidelines for coal ash disposal and additional controls on power plant water regulations
discharges were placed. Coal utilization in the energy sector has significantly reduced, lead-
ing to the decline in coal combustion products, therefore new fly ash sources are becoming
scarce. With the conversion of power generation plants to natural gas in recent years, the
supplies of conventional SCMs such as produced coal combustion fly ash or blast furnace
slags are diminishing [36]. Beneficiation of reclaimed and low-quality fly ashes may also
provide large volumes of SCMs.
4.3.5 Slag cement
Slag cement, also called ground granulated blast furnace slag (GGBFS), is a hydraulic and
pozzolanic material that is produced by rapid quenching, granulating, and grinding of the
molten slag that is a by-product of steel production in a blast furnace. Although some use
the terms slag and slag cement interchangeably, it should be noted that slag is the material
that is the by-product of steel production, and it is only by rapid quenching that it becomes
reactive in cementitious systems.
Air-cooled slag is non-reactive and may be used as aggregate. Slag cement fume is usually
added in a concrete mix at a level of 30 to 50% of the total cementitious content of a con-
crete mix, but higher levels can be used. Slag cement may be used in concrete to improve
compressive strength, reduce permeability, improve sulfate resistance, improve resistance to
alkali-silica reaction (ASR), and reduce thermal stress in mass concrete [37]. ASTM C989
specification addresses different grades of ground granulated blast-furnace slag [38] that is
used for blending with Portland cement per specification of ASTM C595 or as a separate
ingredient in concrete, grout and mortars.
4.3.6 Metakaolin
Metakaolin is a calcined clay that is produced by low-temperature calcination of kaolin clay
of high purity. It is a white powder that is often used as a substitute for silica fume when
light-colored concrete is required. It is added in a concrete mix at a rate of 5 to 20% by
mass of cement to improve the durability of the concrete by reducing the permeability and
increasing the compressive strength. Concrete with metakaolin will almost always require
the use of a high-range water-reducing admixture to improve its workability and ensure the
dispersion of the powder.
Metakaolin (Al2Si2O7) has been commercially available since the mid-1990s as a high-
reactivity pozzolan for HPC applications. It is a thermally activated alumino-silicate material
manufactured by calcination of kaolin clay in a temperature range of 1,300 to 1,560°F (700
to 850°C), which contains 50 to 55% SiO2 and 40 to 45% Al2O3 [39].
Metakaolin improves workability and constructability while improving the mechanical
properties. Brooks and co-workers [40] reported a 30% reduction of slump when using
264 Handbook of Precast Segmental Tunnel Lining Systems
15% metakaolin in concrete followed by a 20% retardation of setting times. The mech-
anical and durability properties show as much as 20% increase in compressive strength,
a decrease of water penetration by 50%, gas permeability of 40% for 15% replacement
of the Portland cement by metakaolin. Both the water absorption potential decreased by
30%; while the ASR expansion decreased by 80% [41]. The use of metakaolin significantly
improved the durability performance and sulfate resistance of concrete.
Metakaolin is highly reactive with calcium hydroxide, resulting in a rapid strength gain
and accelerated cement hydration. Both silica and alumina in metakaolin increase the C/S
ratio of the produced C-S-H gel compared to the C-S-H generated due to the hydration of
silica fume and fly ash. The CH consumption in the mixture was dependent on the level of
metakaolin replacement according to Wild and Khatib [42]. CH content after a year of cur
ing reduced by 50% in pastes with 15% metakaolin indicating an increased C-S-H gel pro-
duction. The pore diameter of the paste after 28 days decreased by 66% (0.0122 microns)
for 20% metakaolin mixtures.
4.3.7 Limestone
The use of limestone powder is becoming an attractive cement replacement material based
on its ability to reduce the carbon footprint of the blended cement system through bypassing
the flow of limestone through the kiln and either co-grinding it with the clinker or blending
it with the Portland cement after separate grinding. Portland limestone cements are rou-
tinely used in the United States. According to ASTM C595, a type IL cement may include
up to 15% limestone powder as an SCM [43].
Once fine limestone particles are specified and used in the micron range, the particle
packing, as well as enhancements in packing density are obtained. The small size of parti-
cles also serves as nucleation sites for the initiation of hydration reactions with aluminate-
bearing materials. The chemical reaction of limestone powder with the aluminate phases
results in cement forming a carboaluminate phase. Research has shown that fine limestone,
in the presence of metakaolin or fly ash, enhances the amount of C-S-H gel formed as
early as 28 days, and has a beneficial impact on strength development. This has provided
the rationale for using fine limestone in ultra high performance concrete (UHPC) mixtures
in combination with other SCMs, [35, 44], which in turn improves the sustainability of
concrete.
4.4 AGGREGATES
The aggregate type and its source have a considerable influence on the compressive strength
of concrete since they occupy 60 to 75% of the concrete volume. As a general rule, an
uncrushed coarse aggregate (generally smooth and rounded) makes a concrete with a lower
strength than one with crushed coarse aggregate. Tunnel segment concretes are generally
very low in slump and designed to be produced in short production cycles considering
high early strength requirements, fine details on the surface for gaskets and other handling
details, and complex geometry of the segments.
Aggregates must conform to certain standards for project or owner-specific properties
as well as national standards such as American Society for Testing Materials (ASTM) or
Canadian Standards Association (CSA). In general, clean and strong aggregates are expected
to be durable, free from adsorbed chemicals, and fine materials such as clay that may inter-
fere with cementitious materials hydration and bonding to aggregate surfaces. Geometrical
Precast concrete technologies 265
Table 4.1 Range of proportions for normal weight steel fiber reinforced concrete
Size aggregate
Item Concrete ix parameter 3/8 ” maximum 3/4 ” maximum 1.5” maximum
1 Cement (lbs/yd 3) 600 to 1,000 500 to 900 470 to 700
2 Water cement ratio (w/c) 0.35 to 0.45 0.35 to 0.50 0.35 to 0.55
3 Percent of fine or coarse 45 to 60 45 to 55 40 to 55
aggregate
4 Entrained air content (%) 4 to 8 4 to 6 4 to 5
5 Fiber content (volume %)
5a Deformed fiber 0.4 to 1.0 0.4 to 0.8 0.2 to 0.7
5b Smooth fiber 0.8 to 2.0 0.6 to 1.6 0.4 to 1.4
Source: [46].
factors fine aggregates such as the fineness, maximum size, grading distribution, and particle
shape and surface texture, affect the compressive strength as well. Aggregate characteristics
indirectly influence the compressive strength through the water demand. Table 4.1 presents
the range of proportions for normal weight steel fiber reinforced concrete depending on
maximum aggregate size.
4.4.1 Coarse aggregates
A wide range of aggregate sources are used in the production of tunnel sections and opti-
mization of aggregate characteristics improves fresh and long-term concrete properties
through optimal packing and reduced need for water, and chemical admixtures. Key char-
acteristics include but are not limited to shape, angularity and texture; gradation (including
maximum aggregate size), and fine particles. These characteristics may be considered based
on empirical, rheology-based models and or amount of vibration to be used in production
to predict fresh concrete behavior and properties. The coarse aggregates are generally a
combination of gravels, or crushed stone particles larger than 5 mm (0.20 inch) or No. 4
sieve to the optimal size of 9 to 25 mm (0.375 to 1.0 inch) depending on cage openings,
cover, and 13 mm (0.50 inch) of the fiber length. Generally, tunnel segment concretes have
some combination of higher total aggregate content, the greater amount of fine aggregate
relative to coarse aggregate, and smaller maximum aggregate size ACI 533.5R) [45]
As a rule, aggregates including sand need to be washed and graded at the pit or plant.
Use of recycled aggregate is not recommended considering the complexity of the sourcing
and related durability concerns unless otherwise tested and proved to be applicable for the
project.
4.4.2 Fine aggregate
Fine aggregates are natural sand or produced from crushing aggregates smaller than 5 mm
(0.20 inches) or No. 4 sieve. Fine aggregates produced in crushing aggregates may not
need to be washed if the process is built to minimize the impurities in crushed sand. The
266 Handbook of Precast Segmental Tunnel Lining Systems
size and shape of fine aggregate particles affect the workability such that very fine sand
increases water demand for similar workability than using coarser sand. The interlocking
of angular fine aggregates affects the rheology and mobility of the aggregates during mixing
and consolidation.
The compaction of real aggregates is challenging due to their irregular shape and the
random number of different sizes present. The compressible packing model (CPM) is widely
used for the prediction of the different size aggregate packing densities. The rheology of
fresh cementitious mixtures is affected by the solid packing fraction.
4.5 WATER
Water used in the production of tunnel segment concretes is expected to meet ASTM C1602
requirements. The use of recycled water is not recommended since impurities in batch water
268 Handbook of Precast Segmental Tunnel Lining Systems
may influence the set time, speed of hydration and impact the initiation and total duration
of curing time, and production cycles.
4.6 CHEMICAL ADMIXTURES
Admixtures are chemicals that are introduced into the fresh concrete or at the time of
mixing to modify in the fresh state or post-hardening properties. These areas include
affecting the water demand through plasticizing or water-reducing, changing the rate of
setting through accelerating/retarding action, changing the yield strength and plastic vis-
cosity to control segregation, cohesion or the bleeding of the mix. These admixtures can
be a single or a blend of several chemicals mostly in aqueous solutions so that they can be
easy to measure, dispense and disperse accurately through the fresh concrete. The active
chemical in liquid admixtures is typically 35 to 40% but can reach as high as 100% in the
case of shrinkage-reducing admixtures and as low as 2% for the synthetic air-entraining
admixtures. Since the majority of admixtures are in the typical range of 0.3 to 1.5%,
a correction in water, cement or total weight is not required. The dosage is normally
expressed as liters or kg per 100 kg (220 lbs) of total supplementary cementitious prod-
ucts. The nature of chemical admixtures is through the various mechanisms that include
the following:
Admixtures are essential components of fresh concrete and benefit rheology, compac-
tion and finishing characteristics. The benefits to the hardened properties are in terms
of strength, stiffness, bond to the substrate, and permeability, which ultimately lead to
enhanced durability.
With the use of admixtures, there is usually a primary property for which the admixture
is being used that is also associated with secondary effects that are associated with the use.
For example, a water-reducing admixture may be used to address durability concerns but
if the concrete mix lacks cohesion and bleeds, the use of a water-reducing admixture that
increases cohesion would be more appropriate. The primary and secondary functions are
therefore a water reducer that improves cohesion. The secondary effects are often the prime
reason why an admixture works well with a specific source of cement and aggregates and is
completely ineffective for another cement type and aggregate source [12].
Precast concrete technologies 269
Air entrainment is usually specified by the total volume of air voids, their size, specific
surface area or spacing. Typical dosage is relatively a small amount of the order of 0.2%
by cement weight and will result in significant changes, therefore, accurate and calibrated
dosing equipment is needed to obtain a consistent level of air. Since the strength of concrete
is affected by entrained air by as much as 5 to 6% reduction for each 1% of additional air,
air content should be limited to the lowest level necessary to achieve the required proper-
ties. However, in low cement content and harsh mixes, air entrainment may improve the
rheology and workability, allowing water reduction that may compensate for the strength
loss. The sensitivity of air entrainment to the mix design components, mixing, temperature,
transport and pumping from batch to batch diminishes the opportunity to specify a pre-
scriptive dosage for all situations.
4.6.2 Water-reducing admixtures
Water-reducing admixtures (WRA) in the concrete mix serve multiple advantages when
producing a precast segmental tunnel liner. They assist in increasing the workability of the
concrete mix, finish surface characteristics, increased strength (compressive, tensile, flex-
ural), allow for the reduction in water-cementitious ratio, increased concrete durability,
and allows lesser quality cements to be used, thus promoting a lower carbon footprint and
subsequently can reduce overall costs.
Water reducing agents are a low viscosity liquid that mainly reduces the water content in
the mix design. The water reducers’ primary function is to disperse as many of the cemen-
titious particles as possible allowing more particles to be coated and hydrated by water
thus resulting in increased concrete strength [55]. There are two types of watering reducing
liquids presently in use in the industry, type A and type F.
Type A water reducing agent is considered mid-range water-reducing admixture (MRWR)
superplasticizers allowing water content reductions up to 20% dependent on superplasti-
cizer dosage rates applied. Dosage rates vary between 60 to 180 ml/45 kg (2 to 6 fl oz per
100 lbs) of cementitious powder. Whereas, type F is high-range water reducing admixture
(HRWR) from normal-range to high-range superplasticizers allowing water content reduc-
tions up to 35% to 45% dependent on the dosage rates applied. Dosage rates vary between
150 to 240 ml/45 kg (5 to 8 fl oz per 100 lbs) of cementitious powder. The dosage rates for
the water-reducing admixtures are dependent on the manufacturer’s dosage recommenda-
tion and testing during the trial mix design period as compared with the available products.
A low water cementitious ratio is most advantageous in defining concrete durability and
water-reducing admixtures play a role in determining its success.
4.6.3 Retarding admixtures
A retarding admixture’s main function is to reduce/delay the process of cement hydration
within the concrete mix, thus increasing the setting time of concrete. The primary concern
is to avoid rapid hardening, which can cause shrinkage cracks and reduce the concrete’s
overall durability. This is often subject to the manufacturing plant’s location or time when
hot-weather concreting occurs. Other considerations are the manufacturing plant’s opera-
tions requiring sufficient time to access aggregates/materials, batch, transport and cast con-
crete into precast segmental tunnel liners molds.
High compressive strength requirements with high cementitious powder may also require
retarding admixtures to ensure good-quality products. When a retarding admixture is
Precast concrete technologies 271
utilized, the proper dosage would be affected by the water-cementitious ratio and the tri-
calcium silicate (C3A) content.
4.6.4 Accelerating admixtures
There are primarily two reasons to consider the use of a set-accelerating admixture in a
concrete mix design, the primary reason is to reduce the concrete setting time to allow the
beginning of accelerated curing and subsequently obtaining a higher early strength for the
product to be removed from its mold. The second consideration would be due to a predom-
inately cold-weather environment that requires an accelerator in the concrete mix.
4.6.5 Specialty admixtures
As a minimum, the coarse and fine aggregates are required to be tested in conjunction with
the cementitious material for alkali-silica reactivity according to ASTM C1567 standard. If
the results are not acceptable based on the standards, inhibiting admixtures can be included
in the concrete mix design. Other specialty admixtures include corrosion-inhibiting and
shrinkage-reducing admixtures.
4.6.6 Mixtures proportioning
Concrete mix proportions are made in consideration of workability, strength and durability.
The selection of mixture proportions requires an optimization of the initial, service level and
ultimate state design requirements for handling, transportation, installation and service life.
These topics are addressed under the criteria that include workability, appearance, finish-
ability, strength, durability and final surface features based on the economy. Other fresh
properties include pumpability, bleeding, density and heat generation.
The mix design procedures range from the local experience of the precast pro-
ducers mix plant operators using empirical guidelines and arbitrary proportions of
cement:sand:gravel:water up to much more sophisticated methods. The general approach
for selecting proportions for concrete made with hydraulic cement meeting ASTM C150/
C150M, C595/C595M, or C1157/C1157M, SCM, normal or high-density aggregates, and
chemical admixtures, with workability suitable for normal cast-in-place construction. The
next-level mix designs are based on meeting minimum criteria for accomplishing the stated
minimum requirements of the project. Most commercially produced concrete today con-
tains a combination of chemical admixtures, and SCM, incorporated in proportioning the
mixture. A broad range of characteristics ranging from high strength to self-consolidation
and flowable, from low permeability characteristics and applications are made possible with
the use of mineral and chemical admixtures and SCMs. The next level is extended to the first
principles such as packing model [56].
There are a wealth of resources available to troubleshoot the problems encountered in
the production cycle. These resources fall back on the fundamental aspects of the mecha-
nisms discussed in the previous sections. Variations in the strength for a given w/cm may
be due to changes in placement or curing conditions, gradation, maximum size, texture,
shape, strength and stiffness of aggregates. Differences in cement types or sources; air con-
tent; and the use of chemical admixtures that affect the cement hydration process or that
develop cementitious properties themselves are also contributing factors. Water-reducing
admixtures are used to reduce the mixing water requirements by (ACI 212.3R). Slump char-
acteristics for developing special concretes such as self-consolidating concrete (ACI 237R),
272 Handbook of Precast Segmental Tunnel Lining Systems
or other applications are needed for close control of workability (ACI 29 238.1R). In add-
ition, admixtures such as set-retarders, accelerators, and shrinkage-reducers are used based
on various performance targets. (ACI 212.3R).
A low w/cm will improve the transport properties by reducing the penetration of aggres-
sive ionic species as discussed. Resistance to freezing and thawing damage and deicing salts
are greatly improved by the incorporation of entrained air system (ACI 201.2R). The dur-
ability of concrete may be affected by exposure to seawater or sulfate-containing soils,
which can be addressed by using sulfate-resisting or slag cement, as well as other SCMs. The
aggregate-alkali reaction (AAR) potential is mitigated by ASTM C1778.
[62]. There are many field experiences with tunnels constructed with TBM in which FRC
is used as the main reinforcing component of the section. Several studies in the published
literature address the experiments, production methods, quality control testing, materials
property evaluation, and numerical modeling of precast concrete tunnel lining segments
[63, 64, 65, 66, 67].
544-8R model which include the ratio of compressive to tensile strength, the post crack
tensile stiffness and strain capacity in the post-peak range, the post-crack tensile residual
strength, and the ultimate allowable compressive strain as defined in Figures 4.6(a) and
(b) for tension and compression response. Using these parameters, the location of the neu-
tral axis, moment capacity and curvature of the section can be obtained at any imposed
Precast concrete technologies 275
strain. In the following curves, the results obtained from the back-calculation process are
represented. In this procedure, the material properties of the samples are extracted from the
four point-bending test results. These parameters enable one to predict the stress-strain dia-
gram for the FRC materials for use in the design. A simulation of the average test results is
shown in Figures 4.7(a) and (b).
quantify the parameters that affect the cohesion and flow. For example, adding water to a
mix reduces yield stress by increasing the slump but also reduces plastic viscosity (cohesion)
increasing the risk of bleeding and segregation [77]. The rheology tests are quite varied and
range from basic to empirical measurements of properties. They measure the amount of
shear stress to achieve the twisting torque required to impose a shearing strain rate on the
fresh concrete sample. As a measure of the flowing capability and adhesion of particles, the
shear stress is plotted vs. the rate of shear strain [78].
Various rheological tests are available in the testing of fiber reinforced concrete in terms
of flow characteristics as discussed in (ACI544-PRC 2R). High cement contents and low
water content as well as the extra small SCM particles often result in the high plastic vis-
cosity and cohesiveness of high-strength concrete. In areas such as underwater and pumped
concrete the added cohesiveness is valuable since they increase concrete’s resistance to seg-
regation. In self-compacting concrete, the yield stress is required to be low while the plastic
viscosity is maintained to a level to meet the flow requirements. These requirements allow
for the selection of admixtures to achieve the required values of yield strength and plastic
viscosity.
The workability of the segment concrete and duration of vibration should be studied
during the mix design development phase. Tunnel segments can be produced in a carousel
system or in stationary production. The workability of a precast section can be low in
carousel systems and very high, even self-consolidating in stationary systems. When there
is a sign of segregation present the potential for excessive vibration during consolidation
should be examined. [79]
When the concrete slump is 50 mm (2 inches) and below, it is placed with heavy vibra-
tion. The flow of concrete and its stability during vibration, as well as the surface finishing
properties, are important parameters to control. Some tunnel projects have very low water
Precast concrete technologies 279
tightness and surface cracking requirements that may require none or minimal cracking and
no bug holes, especially around tunnel sealers.
When low slump concrete is used for the production of tunnel segments, its rheology is
very critical. Vibration is necessary to make the concrete fluid. Although the accuracy of its
measurements is not found to be accurate slump, Ve-be (ASTM C1170) or DIN flow table
(EN 12350-5) are the most common workability testing methods. Other rheology and test
methods that include vibration as a part of the testing procedure may be used.
The crack width and the water-tightness are important factors in the design of tunnel sec-
tions. The use of fibers has been significantly helped with the reduction of the water perme-
ability to the effect of fibers in reducing the crack width as well as the increased tortuosity
of the crack path.
Frost damage results from the freezing and expansion of water within the capillary
system. The tensile forces may cause surface scaling or crack the concrete. Capillaries pores
are formed due to excess water present in capillary pores which were added for concrete
for workability enhancement. Most frost damage occurs in concrete due to the saturated
aggregates [77, 80].
Several mechanisms that include hydraulic and osmotic pressures, contribute to the dam-
age evolution due to freeze–thaw damage in hydrated cement paste. Hydraulic pressure is
the source of damage in the aggregates due to water expansion due to freezing. Aggregates
with low or very high porosity are generally prone to failure by hydraulic pressure because
the amount of freezable water is so low, or the pore sizes are significantly large to withstand
the expansion volume. Aggregates with intermediate porosity are the least durable.
Many of the current structural design approaches lack objectivity in defining the important
parameters needed to characterize and define the durability failure criteria of concrete struc-
tures. At the same time, metrics and test methods for the determination of the acceptability
criteria are still under development and various approaches are not uniformly reached a
consensus approach. As we move towards serviceability-based designs and performance-
based specifications, we need to acknowledge that many durability measures are still defined
and related primarily to water to cement ratio and compressive strength of concrete [81].
Analysis of the existing durability assessment methods shows that these two metrics are not
proper indicators of the success of concrete structures. As long as the compressive strength
is used as the main governing parameter for the prescription of durability and service life,
the challenge of introducing indicators for better specifications remains a difficult goal to
accomplish.
280 Handbook of Precast Segmental Tunnel Lining Systems
Currently, there is little true durability-based design applied to reinforced concrete struc-
tures. While many engineers are aware of the deterioration mechanisms, rational prescrip-
tion of economic solutions and decision support tools in terms of modeling of deterioration
rates are absent. These deficiencies significantly affect the confidence and reliability of the
prediction of service life.
An in-depth discussion of serviceability-based design and design for durability are avail-
able through RILEM Committee publications [82]. For example, European standard EN
206-1 [83], addresses the specification, performance, production, and conformity for con
crete construction via a prescriptive set of specifications. Lack of agreement on test methods
has resulted in the inability to move forward with the existing test methods. This accen-
tuates the need for a better definition of parameters that affect the rates of deterioration
and can be quantified under the production schedule. There are many test methods under
various stages of development that address appropriate test methods reviewed by RILEM
TC-NEC [84]. These tests include chloride penetration, carbon dioxide using an accelerated
carbonation chamber, electrical resistivity, gas permeability, gas permeability, oxygen per-
meability and several others.
Several studies [85,86] indicate that implementation of performance-based specifications
by proper prediction of service life design requires several key features and parameters
addressing the following.
Bentur and Mindess [57] define the steps in the design process into four steps, including the
following:
Transport properties play the dominant role in understanding the service life and durability
modeling of concrete. Research in this area has made tremendous strides, improvements
and contributions to a better understanding of the behavior of concrete materials [82].
The durability modeling challenges are not trivial. For example, the general governing phe-
nomena for mass transfer of harmful ions such as sulfates or chlorides through concrete is
modeled using conservation of mass type of partial differential equations that include diffu-
sion, and convection, in addition to chemical reactions, reactivation, binding, and sorption.
Precast concrete technologies 281
Similar approaches also are operative for moisture diffusion into and out of concrete in the
case of free or restrained shrinkage.
4.14.1 Transport properties
The major indicators of transport characteristics that affect the design life are the ionic
diffusion parameters. The diffusivity parameter, D, is the constant of proportionality. The
diffusion process is often modeled using Fick’s first and second laws, which use the concen-
tration gradient of the specific ions as the forcing function and the driving force to main-
tain the equilibrium. Fick’s first law states that the diffusive flux is linearly proportional to
the concentration gradient, however, it is only applicable under steady-state conditions. To
describe the kinetics of diffusion, Fick’s second law is used, which is represented in terms of
space and time and predicts the diffusive flux to be only a function of concentration gradient
at the point and a function of time.
Fick’s second law can be converted to a diffusion-reaction equation and accompanied by
a second term that is due to the reaction of the external ions with the cement constituents
or hydration products. A solution strategy for this class of problems was proposed [87].
The secondary reactions may also result in a reduction of the ions in the reaction front flux
and thus a delaying effect. Therefore, as the diffusion proceeds inward, a reaction front is
characterized by an effective ionic concentration that is conducive to the expansive reactions
that result in the decomposition of cement paste constituents, or the corrosion of rebars
due to their loss of passivation by chlorides. This leads to a positive feedback loop, where
the net consequence of the expansive product formation leads to microcracking of the bulk
paste, formation of new microcrack paths available for diffusion, and thus increasing the
diffusion constants for a higher ionic flux, often by an order of magnitude [88].
The coefficients of diffusion for various ionic species in concrete depend on the mixture
parameters such as aggregate size, type, volume, pozzolan type and dosage, degree of hydra-
tion, w/cm, additives, etc.), as well as curing conditions (time, moisture, temperature, etc.).
The mathematical basis for the diffusion-reaction equations can be used for various sources
of ions by changing the ionic species, and the coefficients of diffusion that are relevant to
the durability problem. Ionis species such as chlorides (Cl−) and sulfates (SO4-2) have similar
diffusion rates in normal concrete [89].
The diffusivity parameter is affected by the internal capillary porosity as well as the inter-
facial transition zone (ITZ). The transport properties at the ITZ directly correlate with their
higher porosity, larger pore sizes and higher density of calcium hydroxide crystals in com-
parison to the bulk CSH. The diffusion coefficient of ITZ is reported to be 6 to 12 times
more than the bulk cement paste [88, 90]. The correlation between the transport properties
of cement paste with and without the SCM is a clear indication of durability improvements
due to the use of SCM materials.
282 Handbook of Precast Segmental Tunnel Lining Systems
diffusion-reaction equations predicts the expansion of mortar bars in the 1-D case [94] as
shown in Figure 4.10.
To simulate 1-D diffusion, ASTM C1556 is used to measure the apparent coefficients
of diffusion for ions by wet chemical methods (e.g. NaCl for chlorides and Na2SO4 for
sulfates) from a singly exposed side [97]. The effective ionic diffusivity ‘D’ of cement paste
normalized to the diffusivity of ion in unconfined water, ‘D0’, can be related to the porosity
as described by Garboczi and Bentz [98]. Parameter D0 for sulfate ions was reported by
Hilsdorf in the order of 10−9 m2/s [90]. This approach was used in the formulation devel
oped by Bonakdar et al. [96]. The diffusion coefficients of sulfate ions (D) for various con
crete mixtures are in the range of 10−14 to 10−11 m2/s.
Figure 4.10 shows a semi-infinite medium subjected to chemical ingress from one side as a
1st order reaction. The condition simulates a slab or a wall exposed to the initial condition
of C(x,0) = Ci and boundary condition of C(0,t) = C0 where D is the apparent coefficient
of diffusion and k is the chemical reaction coefficient. The solution by error function solu-
tion for a simplified case of Ci =0. Typical concentration profiles considering the presence
or absence of the reaction term and assuming D =10−12 m2/s and k =10−8 s−1 are shown
in Figure 4.10 and represent the fact the reaction term has a damping effect on the rate of
penetration assuming that the products of the reaction are stable.
4.14.4 Alkali-silica reactions
Alkali-silica reactivity is of major concern in the final precast concrete segmental tun-
nel liner product. Alkali-silica reactivity is a two-step process. First, there is a chemical
284 Handbook of Precast Segmental Tunnel Lining Systems
reaction between the alkali phases in the cement that are primarily considered as impur-
ities and reactive silica present in aggregates thus resulting in an alkali-silica gel. Once
moisture encounters the gel, the results are internal pressures causing cracks within the
concrete product, which ultimately decreases the product’s strength, durability and imper-
meability [99].
Damage induced due to ASR reactions has been known for more than 60 years in the
field of concrete technology. Various methods are available based on the determination
of deleterious aggregates, alkali concentration in cement as well as the use of SCMs. The
damage mechanisms have been effectively addressed using specifications on the cement and
aggregates as well as the use of pozzolanic materials partly to reduce the calcium hydroxide
in the microstructure and change the diffusivity of the matrix.
The effect of blended cement on the morphology and chemical composition of reaction
products has addressed the change in the morphology of ASR gel that forms and its expan-
sion potential. Experimental data from ASTM C1567 [100] test method and microstruc
tural studies including ESEM and quantitative EDS were used to develop a physio-chemical
model of the different silicate glass structures [101]. Several fly ashes with various properties
were used to study the number of bridging and non-bridging oxygens in the gel network
providing insight into ASR products.
Many chemical and mechanical models developed based on numerical and analytical
approaches address the diffusion of alkali ions (usually Na+, K+) into the cementitious
system, their reaction with amorphous silica from aggregates, and the formation of an
alkali-silica gel [102]. These models have been compared and summarized through review
papers [103] and [104] to mention a few are based on gel permeation into the pores, swell
ing due to uptake of water, and generation of hydrostatic pressures. Micromechanics is
used to estimate the expansive stresses of spherical particles due to internal pressure. The
behavior of the silica gel is either elastic (solid-state) or elasto-plastic (liquid-solid state) and
is considered as silicate glass whose structure depends on the alkali composition of sodium
and calcium phases.
ACI 544-5R discusses the fire resistance tunnel lining precast panels and means to remedy
the situation (ACI 544-5R-2010). The fire resistance of assemblies and systems are normally
determined using the ASTM E119 fire test standards which create a temperature rise of
1,093°C (2,000°F) over three hours. Hydrocarbon-fueled fires may result in catastrophic
spalling failure and have a much faster heating rate. Polymeric fibers are quite effective in
the prevention of explosive spalling due to their low melting point [about 160°C (220°F)].
The effectiveness depends on the size, distribution, and volume content of the polypropylene
(PP) fibers.
These test results are taken into account in determining the concrete mix design’s durability
and the extent of the structure’s life serviceability. In summary, the concrete mix design’s
material proportions have to be taken into account when developing its final acceptable state.
REFERENCES
[1] J. S. Damtoft, J. Lukasik, D. Herfort, D. Sorrentino, and E. M. Gartner, “Sustainable devel-
opment and climate change initiatives,” Cement and Concrete Research, vol. 38, no. 2, pp.
115–127, Feb. 2008. doi: 10.1016/j.cemconres.2007.09.008
[2] G. P. Hammond, and C. I. Jones, “Embodied energy and carbon in construction materials,”
Proceedings of the Institution of Civil Engineers–Energy, vol. 161, no. 2, pp. 87–98, May
2008. doi: 10.1680/ener.2008.161.2.87
[3] A. D. L. Feeney, C. S., S. Thayer, M. Bonomo, and K. Martel, “White Paper on Condition
Assessment of Wastewater Collection Systems,” Washington, D.C., 2009. doi: https://cfpub.
epa.gov/si/si_public_record_Report.cfm?Lab=NRMRL&dirEntryId=209530
[4] Tunnel Business Magazine, “https://tunnelingonline.com/upcoming-tunneling-projects/.”
https://tunnelingonline.com/upcoming-tunneling-projects/
[5] “Water tunnel business ‘exploding’ as technology reduces risk and cost.” www.enr.com/artic
les/44133-cities-dig-water-tunnels-to-meet-long-term-demands (accessed Nov. 30, 2018)
[6] Bakhshi, M., and Nasri, V. “Cracking serviceability limit state for precast concrete tunnel
segments,” Canadian Society of Civil Engineers (CSCE) 2015 General Conference, Regina,
SK, Canada, 2016.
[7] U.S. Environmental Protection Agency (USEPA), Clean Water and Drinking Water
Infrastructure Gap Analysis. Washington, District of Columbia, 2002.
[8] A. D. L. Feeney, C. S., S. Thayer, M. Bonomo, and K. Martel, “White paper on condition
assessment of wastewater collection systems,” Washington, D.C., 2009. doi: https://cfpub.
epa.gov/si/si_public_record_Report.cfm?Lab=NRMRL&dirEntryId=209530
[9] ACI Committee 350, Environmental Engineering Concrete Structures. American Concrete
Institute, 2003.
[10] M. di Prisco, G. Plizzari, and L. Vandewalle, “Fibre reinforced concrete: New design perspec-
tives,” Materials and Structures, vol. 42, no. 9, pp. 1261–1281, Nov. 2009. doi: 10.1617/
s11527-009-9529-4
[11] M. Colombo, P. Martinelli, and M. di Prisco, “A design approach for tunnels exposed to
blast and fire,” Structural Concrete, vol. 16, no. 2, pp. 262–272, Jun. 2015. doi: 10.1002/
suco.201400052
[12] P. Hewlett, Lea’s Chemistry of Cement and Concrete. Elsevier, 2003. doi: 10.1016/
B978-0-7506-6256-7.X5007-3
[13] P. J. Jackson, “Portland cement: Classification and manufacture,” in P. Hewlett (ed.),
Lea’s Chemistry of Cement and Concrete, Elsevier, 1998, pp. 25–94. doi: 10.1016/B978-
075066256-7/50014-X
[14] W. C. P. Kosmatka, H. Steven, and B. Kerkhoff, Design and Control of Concrete Mixtures,
14th ed. Portland Cement Association, 2002.
[15] P. Hewlett, Lea’s Chemistry of Cement and Concrete. Elsevier, 2003.
[16] ASTM-C150-18, “Standard specification for portland cement,” 2018.
[17] “CSA A3000-2018 cementitious materials compendium,” 2018.
[18] EN 197-1, “EN 197-1-2011 Cement–Part 1: Composition, specifications and conformity
criteria for common cements,” 2011.
[19] K. Scrivener, V. John, and E. Gartner, Eco-Efficient Cements: Potential Economically Viable
Solutions for a Low-CO2 Cement-Based Materials Industry. 2016.
[20] D. K. Panesar, “Supplementary cementing materials,” in Developments in the Formulation
and Reinforcement of Concrete, Elsevier, 2019, pp. 55– 85. doi: 10.1016/B978-0-08-
102616-8.00003-4
288 Handbook of Precast Segmental Tunnel Lining Systems
[40] J. J. Brooks, M. A. Megat Johari, and M. Mazloom, “Effect of admixtures on the setting
times of high-strength concrete,” Cement and Concrete Composites, vol. 22, no. 4, pp. 293–
301, Jan. 2000. doi: 10.1016/S0958-9465(00)00025-1
[41] M. Shekarchi, A. Bonakdar, M. Bakhshi, A. Mirdamadi, and B. Mobasher, “Transport
properties in metakaolin blended concrete,” Construction and Building Materials, vol. 24,
no. 11, pp. 2217–2223, Nov. 2010. doi: 10.1016/j.conbuildmat.2010.04.035
[42] J. M. Khatib, and S. Wild, “Pore size distribution of metakaolin paste,” Cement and Concrete
Research, vol. 26, no. 10, pp. 1545–1553, Oct. 1996. doi: 10.1016/0008-8846(96)00147-0
[43] W. J. Tennis, P., Thomas, M.D.A, and Weiss, “State-of-the-art report on use of limestone in
cements at levels of up to 15%,” Skokie, Illinois, USA, 2011.
[44] K. Vance, A. Arora, G. Sant, and N. Neithalath, “Rheological evaluations of interground
and blended cement–limestone suspensions,” Construction and Building Materials, vol. 79,
pp. 65–72, Mar. 2015. doi: 10.1016/j.conbuildmat.2014.12.054
[45] A. C. 533, “Guide for precast concrete tunnel segments,” 2020.
[46] ACI 544.7R-16, “ACI PRC-544.7-16 report on design and construction of fiber-reinforced
precast concrete tunnel segments,” 2016.
[47] M. Glavind and E. J. Pedersen, “Packing calculations applied for concrete mix design,” 1999.
[48] M. R. Jones, L. Zheng, and M. D. Newlands, “Comparison of particle packing models for
proportioning concrete constituents for minimum voids ratio,” Materials and Structures /
Mat6riaux et Constructions, vol. 35, pp. 301–309, 2002. doi: 10.1007/BF02482136
[49] R. Yu, P. Spiesz, and H. J. H. Brouwers, “Mix design and properties assessment of Ultra-
High Performance Fibre Reinforced Concrete (UHPFRC),” Cement and Concrete Research,
2014. doi: 10.1016/j.cemconres.2013.11.002
[50] T. Stovall, F. de Larrard, and M. Buil, “Linear packing density model of grain mixtures,”
Powder Technology, vol. 48, no. 1, pp. 1–12, Sep. 1986. doi: 10.1016/0032-5910(86)80058-4
[51] G. Fu, and W. Dekelbab, “3-D random packing of polydisperse particles and concrete aggre-
gate grading,” Powder Technology, vol. 133, no. 1–3, pp. 147–155, Jul. 2003. doi: 10.1016/
S0032-5910(03)00082-2
[52] F. De Larrard, Concrete Mixture Proportioning: A Scientific Approach (Modern Concrete
Technology). Taylor & Francis Ltd, 1999.
[53] B. Mobasher, A. Arora, M. Aguayo, F. Kianmofrad, Y. Yao, and N. Neithalath, “Developing
ultra high- performance concrete mix designs for Arizona bridge element connections,”
Arizona State University. School of Sustainable Engineering and the Built Environment,
FHWA-AZ-19-745, 2019. https://rosap.ntl.bts.gov/view/dot/55498
[54] P. J. F. Wright, “Entrained air in concrete,” Proceedings of the Institution of Civil Engineers,
vol. 2, no. 3, pp. 337–358, May 1953. doi: 10.1680/iicep.1953.11041
[55] D. Sniderman, “Material matters: Water- reducing admixtures,” Precast Inc. Magazine,
vol. May/June, pp. 14–17, 2015.
[56] F. De Larrard, Concrete Mixture Proportioning: A Scientific Approach (Modern Concrete
Technology). Taylor & Francis, 1999.
[57] A. Bentur, and S. Mindess, “Mechanics of fibre reinforced cementitious composites,” in
Fibre Reinforced Cementitious Composites, 2nd ed., CRC Press, 2006, pp. 125– 192.
doi: 10.1201/9781482267747-12
[58] B. Mobasher, Mechanics of Fiber and Textile Reinforced Cement Composites. CRC Press,
2011. doi: 10.1201/b11181
[59] B. Mobasher, “Single yarns in woven textiles: Characterization of geometry and length
effects,” in Mechanics of Fiber and Textile Reinforced Cement Composites, CRC Press,
2011, pp. 83–96. doi: 10.1201/b11181-8
[60] ACI Committee 544, “ACI PRC-544.7R-16 Report on design and construction of fiber-
reinforced precast concrete tunnel segments,” 2016.
[61] ACI Committee 544, “ACI 544. 8R-16 Report on indirect method to obtain stress-strain
response of Fiber-Reinforced Concrete (FRC),” 2016.
290 Handbook of Precast Segmental Tunnel Lining Systems
[62] fib, fib Model Code for Concrete Structures 2010. Weinheim, Germany: Wiley-VCH Verlag,
2013. doi: 10.1002/9783433604090
[63] P. Nanakorn, and H. Horii, “Fracture mechanics-based design method for SFRC tunnel
linings,” Proceedings of the Materials Engineering Conference, vol. 1, no. 1, pp. 819–828,
1996. doi: 10.2208/jscej.1996.532_221
[64] L. Liao, A. de la Fuente, S. Cavalaro, and A. Aguado, “Design of FRC tunnel segments con-
sidering the ductility requirements of the Model Code 2010,” Tunnelling and Underground
Space Technology, vol. 47, pp. 200–210, 2015. doi: 10.1016/j.tust.2015.01.006
[65] L. Liao, A. de la Fuente, S. Cavalaro, and A. Aguado, “Design procedure and experimental
study on fibre reinforced concrete segmental rings for vertical shafts,” Materials and Design,
vol. 92, pp. 590–601, 2016. doi: 10.1016/j.matdes.2015.12.061
[66] G. A. Plizzari, and G. Tiberti, “Steel fibers as reinforcement for precast tunnel segments,”
Tunnelling and Underground Space Technology, vol. 21, no. 3–4, pp. 438–439, May 2006.
doi: 10.1016/j.tust.2005.12.079
[67] M. L. Nehdi, S. Abbas, and A. M. Soliman, “Exploratory study of ultra-high performance
fiber reinforced concrete tunnel lining segments with varying steel fiber lengths and dosages,”
Engineering Structures, vol. 101, pp. 733–742, 2015. doi: 10.1016/j.engstruct.2015.07.012
[68] CNR-DT204, “Guidelines for the design, construction and production control of fibre rein-
forced concrete structures,” National Research Council of Italy, 2006.
[69] ASTM C1609 /C1609M–12, Standard Test Method for Flexural Performance of Fiber-
Reinforced Concrete (Using Beam With Third-Point Loading). 2012.
[70] B. Mobasher, Mechanical Testing and Characteristic Responses. CRC Press, 2011.
doi: 10.1201/b11181-8.
[71] Y. Yao, M. Bakhshi, V. Nasri, and B. Mobasher, “Interaction diagrams for design of hybrid
fiber-reinforced tunnel segments,” Materials and Structures/ Materiaux et Constructions,
vol. 51, no. 1, 2018. doi: 10.1617/s11527-018-1159-2
[72] DIN EN 14651, “Test method for metallic fibre concrete–Measuring the flexural tensile
strength (limit of proportionality (LOP), residual),” 2007.
[73] M. Briffaut, F. Benboudjema, and L. D’Aloia, “Effect of fibres on early age cracking of con-
crete tunnel lining. Part II: Numerical simulations,” Tunnelling and Underground Space
Technology, vol. 59, pp. 221–229, Oct. 2016. doi: 10.1016/j.tust.2016.08.001
[74] D. Patel, C. Pleesudjai, Y. Yao, S. Schaef, and B. Mobasher, “Validation testing of precast
segments using polymeric fibers,” no. September, 2020.
[75] C. Pleesudjai, D. Patel, M. Bakhshi, V. Nasri, and B. Mobasher, “Applications of statistical
process control in the evaluation of QC test data for residual strength of FRC samples of
tunnel lining segments,” 2021, pp. 815–826. doi: 10.1007/978-3-030-58482-5_72.
[76] C. Pleesudjai, D. Patel, M. Bakhshi, V. Nasri, and B. Mobasher, “Applications of statistical
process control in the evaluation of QC test data for residual strength of FRC samples of tun-
nel lining segments,” in RILEM-fib International Symposium on Fibre Reinforced Concrete,
pp. 815–826, 2020.
[77] J. Dransfield, “Admixtures for concrete, mortar and grout,” in Advanced Concrete
Technology, Elsevier, 2003, pp. 3–36. doi: 10.1016/B978-075065686-3/50280-9
[78] C. F. Ferraris, “Measurement of the rheological properties of high performance con-
crete: State of the art report,” Journal of Research of the National Institute of Standards and
Technology, vol. 104, no. 5, pp. 461, Sep. 1999. doi: 10.6028/jres.104.028
[79] Walker, H. N., Lane, D. S., and Stutzman, P. E., “Petrographic methods of examining hard-
ened concrete: A petrographic manual,” 2004.
[80] M. Richardson, “Degradation of concrete in cold weather conditions,” Durability
of Concrete and Cement Composites, Elsevier, 2007, pp. 282– 315. doi: 10.1533/
9781845693398.282
[81] M. Alexander, A. Bentur, and S. Mindess, Durability of Concrete. Boca Raton: CRC
Press, [2017] | Series: Modern concrete technology series: CRC Press, 2017. doi: 10.1201/
9781315118413
Precast concrete technologies 291
[82] M. Alexander, and H. Beushausen, “Durability, service life prediction, and modelling
for reinforced concrete structures–review and critique,” Cement and Concrete Research,
vol. 122, pp. 17–29, Aug. 2019. doi: 10.1016/j.cemconres.2019.04.018
[83] E. 206-1, Concrete-Specification, Performance, Production and Conformity. 2013.
[84] H. Beushausen, and L. Fernandez Luco, Eds., Performance-Based Specifications and Control
of Concrete Durability, vol. 18. Dordrecht: Springer Netherlands, 2016. doi: 10.1007/
978-94-017-7309-6
[85] J. C. Walraven, “Design for service life: How should it be implemented in future codes,” in
Concrete Repair, Rehabilitation and Retrofitting II, II., P. M. Mark G. Alexander, Hans-Dieter
Beushausen, Frank Dehn, Ed. CRC Press, 2008, pp. 21–28. doi: 10.1201/9781439828403-5
[86] M. Alexander, A. Bentur, and S. Mindess, Durability of Concrete. Boca Raton : CRC
Press, [2017] | Series: Modern concrete technology series: CRC Press, 2017. doi: 10.1201/
9781315118413
[87] R. Tixier, and B. Mobasher, “Modeling of damage in cement-based materials subjected to
external sulfate attack. I: Formulation,” Journal of Materials in Civil Engineering, vol. 15,
no. 4, pp. 305–313, Aug. 2003. doi: 10.1061/(ASCE)0899-1561(2003)15:4(305)
[88] A. Bonakdar, and B. Mobasher, “Multi-parameter study of external sulfate attack in blended
cement materials,” Construction and Building Materials, vol. 24, no. 1, pp. 61–70, Jan.
2010. doi: 10.1016/j.conbuildmat.2009.08.009
[89] H. Hilsdorf, and J. Kropp, Eds., Performance Criteria for Concrete Durability. CRC Press,
1995. doi: 10.1201/9781482271522
[90] H. Hilsdorf, and J. Kropp, Eds., Performance Criteria for Concrete Durability. CRC Press,
1995. doi: 10.1201/9781482271522
[91] U. M. Angst, “Predicting the time to corrosion initiation in reinforced concrete structures
exposed to chlorides,” Cement and Concrete Research, vol. 115, pp. 559–567, Jan. 2019.
doi: 10.1016/j.cemconres.2018.08.007
[92] D. Krajcinovic, “Damage mechanics,” Mechanics of Materials, vol. 8, no. 2–3, pp. 117–
197, 1989.
[93] D. Krajcinovic, M. Basista, K. Mallick, and D. Sumarac, “Chemo-micromechanics of brittle
solids,” Journal of the Mechanics and Physics of Solids, vol. 40, no. 5, pp. 965–990, Jul.
1992. doi: 10.1016/0022-5096(92)90058-A
[94] R. Tixier, and B. Mobasher, “Modeling of damage in cement- based materials sub-
jected to external sulfate attack. II: Comparison with experiments,” Journal of Materials
in Civil Engineering, vol. 15, no. 4, pp. 314– 322, 2003. doi: 10.1061/(ASCE)0899-
1561(2003)15:4(314)
[95] J. Bentz, D. Ehlen, M. Ferraris, and C. Winpigler, “Service life prediction based on sorptivity
for highway concrete exposed to sulfate attack and freeze-thaw conditions,” 2002.
[96] A. Bonakdar, B. Mobasher, and N. Chawla, “Diffusivity and micro-hardness of blended
cement materials exposed to external sulfate attack,” Cement and Concrete Composites, vol.
34, no. 1, pp. 76–85, 2012. doi: 10.1016/j.cemconcomp.2011.08.016
[97] ASTM C 1556, ASTM C 1556. Standard test method for determining the apparent chloride
diffusion coefficient of cementitious mixtures by bulk diffusion. 2004.
[98] E. J. Garboczi, and D. P. Bentz, “Computer simulation of the diffusivity of cement-based
materials,” Journal of Materials Science, vol. 27, no. 8, pp. 2083–2092, 1992. doi: 10.1007/
BF01117921
[99] H. H. Powers, and T. C. Steinour, “An interpretation of some published researches on the
alkali-aggregate reaction Part 1-The chemical reactions and mechanism of expansion,” ACI
Journal Proceedings, vol. 51, no. 2, pp. 497–516, 1955.
[100] A. C1567-21, ASTM C1567-21,Standard Test Method for Determining the Potential Alkali-
Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated
Mortar-Bar Method). USA, 2021.
292 Handbook of Precast Segmental Tunnel Lining Systems
[101] A. Bonakdar, B. Mobasher, S. K. Dey, and R. Della M, “Correlation of reaction products and
expansion potential in alkali-silica reaction for blended cement materials,” ACI Materials
Journal, vol. 107, no. 4, pp. 380–386, 2010.
[102] S. Poyet et al., “Chemical modelling of Alkali Silica reaction: Influence of the reactive aggre-
gate size distribution,” Materials and Structures, vol. 40, no. 2, pp. 229–239, Jan. 2007.
doi: 10.1617/s11527-006-9139-3
[103] A. Nielsen, F. Gottfredsen, and F. Thøgersen, “Development of stresses in concrete structures
with alkali-silica reactions,” Materials and Structures, vol. 26, no. 3, pp. 152–158, Apr.
1993. doi: 10.1007/BF02472932
[104] R. Esposito, and M. A. N. Hendriks, “Literature review of modelling approaches for ASR
in concrete: A new perspective,” European Journal of Environmental and Civil Engineering,
vol. 23, no. 11, pp. 1311–1331, Nov. 2019. doi: 10.1080/19648189.2017.1347068
[105] P. Gambarova, B. Chiaia, A. P. Fantilli, C. Oggieri, C. Ronco, F. Minelli, G. Plizzari, G.
Tiberti, M. Aiello, and E. Vasanelli, Construction Methodologies and Structural Performance
of Tunnel Linings. 2009.
Chapter 5
DOI: 10.1201/9781032675541-5
294 Handbook of Precast Segmental Tunnel Lining Systems
Over the last 20 years, the increased use around the world of SFRC in precast concrete seg-
ments was driven by many research studies and testing programs performed by industry,
owners, contractors and designers to gain its acceptance for use in specific projects. Testing
standards and protocols developed primarily in Europe and the USA over time were refined
to provide accurate and relevant fiber performance characterization to provide confidence
in the product’s use. These studies and test programs, as well as the many successful inter-
national project experiences, provided a continual better understanding of the performance
behavior of SFRC. This led to the development of valid constitutive laws for design with
SFRC, again primarily in Europe and the USA. The achieved body of knowledge resulted in
development of international codes, guidelines and standards, which have been published
on the design of fibers for use in structural reinforced concrete, such as the fib Model Code
2010. More recently design guide documents have been published on the specific use of
SRRC in precast tunnel segment, such as American Concrete Institute, ACI 544.7R-16; fib
(fib =Fédération Internationale du Béton) Bulletin 83; and in 2020, ACI 533.5R-20. SFRC
used as “fiber only” or in a “combined solution” is now the standard of practice of the con-
crete in precast segments around the globe. Today, fib Bulletin 83, based on the 2010 Model
Code and ACI 544.7R-16 are the most widely referenced documents for the design of SFRC
used in precast tunnel segments in the world.
However, for use in precast concrete segments, choosing appropriate fibers is relatively
straight forward. The three types of fibers that have been used in segments boil down to the
following:
Controlling crack widths in tunnel linings by limiting the crack widths during design
and construction is critical. Wide crack widths can adversely impact the serviceability and
long-term durability of the tunnel. Cracks in the lining are a major cause of leaks in a tun-
nel, both infiltration and exfiltration. Because steel fibers are distributed throughout the
entire cross-section, steel fibers provide for reduced crack widths compared to convention-
ally reinforced concrete. The ability to control and reduce the width of cracks in a precast
segmental lining is a fundamental difference between a steel and synthetic fiber; steel fibers
are the preferred choice, including over conventional reinforcement. Section 5.5.3 of this
chapter will discuss durability of SFRC and the overall superior performance of it compared
to conventional reinforced concrete.
Comparing the melting and creep temperatures of a steel vs. a synthetic fiber explains the
fundamental differences in how the composite behaves under exposure to heat and fire and
under sustained loading. Section 5.4 of this chapter will discuss the use of micro-synthetic
fibers for passive fire protection in the event of a fire in the tunnel. In this application the
fibers melt creating pathways to alleviate the pressure build-up from the pore water in the
concrete turning to steam. However, because of the low melting temperature and creep
temperature of synthetic fibers it is not appropriate to use macro-synthetics as a structural
reinforcement in any application subject to elevated temperatures or fire or where creep is
a concern. Table 5.2 provides a summary of the appropriate fiber types for the different
applications.
The differences in fiber types and properties will have a significant impact on the behavior
observed in different FRC characterization tests and in real-life ground support systems. In
fact, in hyperstatic systems such as those found in ground support, an effective control of
the crack widths will promote a more efficient multi-cracking process and, therefore, a more
ductile behavior of the structure, most probably due to the higher degree of hyper-staticity
that is maintained.
in concrete is dependent on three primary attributes of the fiber: aspect ratio (L/D), wire
tensile strength and anchorage mechanism as shown in Figure 5.3.
The following are the recommendations for steel fibers used in precast segments:
• Fibers out of drawn wire, with a tensile strength of steel wire >1,800 MPa (260 ksi)
minimum
• Precast segments typically have compressive strengths well in excess of the min-
imum that is required for their structural design: 35 to 40 MPa (5,000 to 6,000
psi)
• Because of high early strength requirements for production efficiency in the seg-
ment manufacturing plant, higher compressive strengths in the 65 to 70 MPa
(9,000 to 10,000 psi) are common
• To maintain ductility of the SFRC, higher tensile strength wire is recommended
• Hooked ends that have been optimized to ensure proper anchorage in the concrete
matrix
• Fiber length: in the range of 50 mm (2”) to 60 mm (2.4”)
• Aspect ratio (length/diameter): a minimum of 65; 80 is recommended
• Minimum fiber length: 2.5 times the maximum coarse aggregate size
• Fibers glued in clips to promote homogenous distribution and eliminate balling of
fibers
• Introduction of fibers into mix using a fully integrated automatic dosing system
over conventionally reinforced concrete as shown in Figure 5.4. “Fiber only” SFRC is suit
able for most tunnel linings but it has some performance limitations. Conventional reinfor-
cing steel can be added to provide a “combined solution” in areas with large, concentrated
bending moments or large isolated tensile forces in the concrete, to absorb these higher or
isolated stresses.
The SFRC mix design is determined by the same principles which apply to concrete mix
design. The prime factors controlling strength and quality are the water/cementitious mate-
rials ratio, the grading of the aggregates and the degree of consolidation achieved. However,
there are a number of design considerations in which SFRC differs from conventional
structurally reinforced concrete. The major differences lie in the aggregate grading and the
cementitious content of the concrete design. The concrete composition must be engineered
in order to obtain homogeneous distribution of the steel fibers and good finishing ability.
The performance of SFRC is determined primarily by the following characteristics of the
material:
• Performance of the specific fiber in the specific concrete mix are related to the
following:
• Fiber tensile strength
• Aspect ratio (L/D)
• Anchorage mechanism
• Fiber distribution
• Concrete composition (both freshly mixed and the hardened matrix properties)
• Concrete compressive strength
• Quantity of fibers (dosage)
300 Handbook of Precast Segmental Tunnel Lining Systems
Figure 5.4 Benefits of steel fiber reinforced concrete precast segmental tunnel linings.
Note: Benefits diagram of the advantages of the use of steel fiber in precast tunnel segments.
To ensure a sufficient distribution network of fibers is achieved, Table 5.4 provides a “sug
gested” minimum dosages of fibers to meet spacing requirements based on fiber aspect ratio
and application. This minimum is applicable if dosage to meet the structural performance
requirements demonstrated by beam testing is less than these values. The minimum fiber
aspect ratio for segments is 65, and 80 is considered optimal. Any fibers over a 65 aspect
ratio must be provided glued in clips to prevent fiber balling and, therefore, restricting
proper distribution in the concrete.
SFRC was first used in precast segments for the modest level of post first crack flex-
ural capacity that it provides and the savings in costs due to efficiency and cost savings in
material and labor in the factory. As experience and SFRC technology has grown, other
very significant benefits that SFRC can provide in segments require further assessment of
the materials performance to assure realizing these added benefits. Therefore, when deter-
mining the appropriate dosage for a particular fiber, meeting a prescribed minimum flexural
performance is only one consideration.
SFRC with the appropriate performance characteristics, i.e. flexural hardening, provides
an exceptionally tough and durable segment to withstand high impact loading and provide
crack widths a fraction of that of conventional only reinforced segment. Eliminating dam-
age during handling and installation and providing a maximum crack width well within
or below allowable values specified by the codes, guidelines and recommendations in a
range of 0.15 to 0.3 mm (0.006” to 0.012”) are essential considerations. By increasing the
performance of SFRC to a level providing hardening characteristics the added benefits of
superior resistance are realized.
When characterizing SFRC performance in flexure, there are three basic material behav-
iors. Elastic and deflection softening, and deformation hardening plastic behaviors in bend-
ing. By definition, bending softening behavior in flexure is where the load capacity after first
crack is less than the load at first crack, and hardening is characterized as the load carrying
Fiber reinforcement in precast concrete segments 301
Table 5.4 Recommended minimum dosages of steel fibers for “fibers only” or “combined
solution” design.
Minimum dosages in kg/m 3 of steel fibers based on different aspect ratios and overlap
factors to achieve a sufficient network based on the McKee spacing theory
Notes:
1
The steel fibers dosages recommended above are not fixed.
2
The design engineer may at any time choose to use a different steel fiber spacing which ensures a different
degree of network.
3
For precast segment linings, recommendation is to use an overlap factor = 1.66 for combined solutions with
conventional rebar and an overlap factor = 1.8 to 2.0 for applications 100% steel fiber reinforcement (structural
applications). The consideration of steel fiber spacing requirements ensures that there will be improvements in
concrete crack widths and impact resistance compared to wire mesh reinforce concrete.
4
Final decision on which dosage to use will be determined by residual strength minimum.
capacity of the SFRC segment in flexure after some deflections is greater than the first crack
in the post-crack zone. As we will discuss in the following sections, fiber performance in the
small scale is typically characterized by performing flexural testing on beams and measuring
the load deflection response of the material. Figure 5.5 shows graphically the load deflection
response of SFRC exhibiting hardening vs. softening behavior.
Most SFRC in the past that contained approximately 0.5% by volume of the steel fibers,
typically provided flexural softening behavior. Today, with the advancements in fiber and
concrete technology, obtaining deflection hardening response in flexure is achieved using
the same volume of the appropriate fibers in an optimized concrete mixture. Higher per-
formance levels of SFRC provide more applications for “fiber only” reinforcement solutions
in segments. The SFRC for segments, “fiber only” or “combined solution”, to optimize
the performance requires more considerations than just structural capacity of the segment.
Tunnels being built today typically require 100 to 120 plus year design service life to be
demonstrated. Properly designed higher performance SFRC in segments is a powerful tool
in achieving a robust, durable and watertight tunnel lining with a long service life as illus-
trated in Figure 5.6.
5.2 PRECONSTRUCTION TESTING
Prior to any production of segments on a project testing is performed to determine the
appropriate fiber dosage and optimization of the concrete mix design to assure that
the SFRC to be used meets all of the requirements of the design. In general, most of the
302 Handbook of Precast Segmental Tunnel Lining Systems
Figure 5.6 High-p erformance SFRC hardening behavior for segments (red circles).
Note: Characterization of softening vs. hardening performance of fiber reinforced concrete.
engineering properties of SFRC are primarily related to its concrete matrix properties and
thus test methods developed for plain concrete in both fresh and hardened state can be used
in the case of SFRC. These include the conventional concrete tests at early-age to char-
acterize workability, plastic shrinkage and, at later ages once it is hardened, tests such as
compression, direct tensile (splitting) and modulus of elasticity. The significant difference in
the performance of SFRC vs. plain concrete is its post-crack tensile performance of SFRC
Fiber reinforcement in precast concrete segments 303
that marks the significant difference of FRC’s behavior in relation to that of plain concrete.
The parameters that impact the post-cracking tensile strength performance of SFRC were
discussed in Section 5.1.2. In the design of the segmental SFRC tunnel linings, the relevant
performance characteristic to be quantified is the tensile stress–strain behavior in its hard-
ened state.
The post-crack tensile properties of SFRC can be determined by the following types
of tests:
Figure 5.7 Overview steel fiber reinforced concrete design with beam testing.
Note: Design flowchart of the key design stages for fiber reinforced concrete.
material characterization. The two main standardized flexural (beam) test methods being
used around the globe are either the ASTM C1609 or the EN 14651 (same as RILEM beam)
methods. Primary differences between the two test methods are how the load is applied to
the beam [notched beam is single-center point loaded and un-notched is loaded at the third
points (two points) of the beam] and the EN beam is notched vs. ASTM is unnotched.
A notch in the bottom of the beam at mid-span controls the location of the crack when
loaded.
The ASTM standard has been referenced predominately in areas where the ACI standards
and guides are referenced and the EN standard is used predominately where the fib 2010
Model Code is the reference design document. There are perceived advantages and disad-
vantages of both types of tests. The European fib Model Code 2010 prescribes the use of the
notched beam whereas the ACI 544.7R design guide prescribes the ASTM C1609. Because
the results of the two types of tests are markedly different, it is essential that the design
method and test method are consistent. The beam type specified by the designer cannot be
changed without the designer’s confirmation.
As discussed earlier in this chapter, historically SFRC typically exhibits strain softening
characteristics in flexure. Now, thanks to advancements in steel fiber and concrete tech-
nology, SFRC that exhibits post-crack deflection hardening is readily achievable at reason-
able dosages (0.5% by volume). The benefits in tunnel linings for reduced crack widths,
durability and increased toughness means that SFRC that exhibits hardening in flexure is
the state of the art. In the past, the engineer typically only specified the “average” residual
strength that the FRC provides from the beam test. Today with high performance SFRC,
the engineer should specify minimum fiber performance requirements at first crack, SLS and
ULS load deflection levels. Now engineers are looking at design for serviceability as well as
ultimate strength levels due to this higher level of SFRC performance.
Serviceability in SFRC is a performance characterized by the residual strength at lower
levels in the deflection or crack opening response in the beam (L/600 deflection in ASTM
Fiber reinforcement in precast concrete segments 305
Table 5.5 Comparing EN 14651 to ASTM C1609 beam test results in a deflection hardening
SFRC.
Test results in hardening steel fiber reinforced concrete (SFRC) show that the
ASTM beam test results are underestimated at higher load/d eflection values due to
structural effects (multiple cracks forming) in the beam
correlating the results of an ASTM C1609 beam to EN 14651 beam test, the ASTM L/600
corresponds to EN fR1 (SLS), and the L/150 corresponds to the fR3 (ULS) value.
The execution of preconstruction testing using beams should be in a laboratory con-
trolled environment. Regardless of the testing standard used, the casting of the SFRC and
test beams are of critical importance to obtain accuracy and the lowest variation in the
results. The following are the leading steel fiber manufacturers’ recommendations for mak-
ing the preconstruction test beams.
Preferably, the specimens are made under laboratory conditions. In this case, a pan
mixer shall be used to mix the concrete, and all the ingredients must be weighed accur-
ately. Aggregates, sand and cement are added to the mixer (in this order) and mixed for 60
seconds. Then the water is added, and the concrete is mixed for another 60 seconds. After
this step, the fibers are added, and mixed for 270 seconds to make sure that all fibers are
separated and homogeneously distributed. The mixer can be stopped now, and a visual
inspection of the distribution of the fibers needs to be performed. Filling the molds is done
in one lift, up to a height of 110% of the mold. The concrete is then vibrated on a vibrating
table (unless it is self-compacting concrete) and levelled off during vibration.
Full compaction is achieved when there is no further appearance of large air bubbles on
the concrete surface, and the surface is becoming relatively smooth with a glazed appear-
ance, without excessive segregation. Internal vibration is not recommended, in order not to
disturb the three-dimensional homogeneous distribution of the fibers. If a vibration needle
is used, the zone around the vibration needle will contain less fibers than the rest of the
beam. The specimens should be left in the molds for at least 16 hours, but no longer than
three days, protected against shocks, vibration and dehydration. The specimens are cured
at a temperature of 20±5°C (68±9°F) for a minimum of 3 days, either in water at a tem-
perature of 20±2°C (68±4°F), or in a chamber at 20±2°C (68±4°F) and a relative humidity
of minimum 95%. Regular checks should be made that the surfaces of the specimens in the
chamber are continuously wet. Loss of moisture and deviations from the required tempera-
ture should be avoided.
Bending tests must be performed on a minimum number of specimens and the variation of
the results in terms of residual strength at SLS value, must not exceed the following values:
The values derived from the suggested 12 minimum beam characterization tests are not
“mean” values but need to be expressed as “characteristic” values (denoted as a subscript
“k”–in the EN 14651 beam testing values; fR1k, fR2k, fR3k, etc.). Figure 5.8 below listed the
information from the fib Model Code 2010 to calculate characteristic values.
Figure 5.9 ASTM C1609 four-p oint beam bending test – general arrangements.
Note: Typical arrangement and calculations for residual strengths of FRC.
span as shown in Figure 5.9. The design method in ACI 544.7R, “Design and Construction
of Fiber-Reinforced Precast Concrete Tunnel Segments” guide is based on the results from
this testing method. This method provides reliable and accurate results for SFRC exhibiting
flexural softening or elastic characteristics.
For SFRC that exhibits flexural hardening, the residual strength results at higher deflec-
tions have been found to have wide variations and to significantly understate the residual
strength values in the beam. ASTM currently has a work item in process (ASTM-WK68392)
which states in its rationale, “As more designers are using crack width as a design param-
eter for FRC, it is essential and useful to include a notched beam version as an alterna-
tive in ASTM C1609”. Until a notched alternative is available in ASTM, the EN 14651
beam protocol should be used, requiring the engineer’s approval and needing to provide the
applicable performance requirements for using this alternative method.
308 Handbook of Precast Segmental Tunnel Lining Systems
5.2.1.2 EN 14651 –test method for metallic fiber concrete–measuring the flexural
tensile strength
EN 14651 is the reference standard for the European Union CE label for steel and polymer
fibers and has been adopted by a number of fiber manufacturers and designers especially
in Europe and the Middle East regions. The tensile behavior of SFRC is evaluated in terms
Fiber reinforcement in precast concrete segments 309
of residual flexural tensile strength values, determined from the load-crack mouth opening
displacement curve, or load-deflection curve, obtained by applying a center-point load
on a simply supported notched beam. Notch dimension is 25 mm long × 5 mm wide (1”
long × 0.25” wide); and beam dimension is 550 × 150 × 150 mm (22” long × 6” thick ×
6” wide). The test results are expressed in terms of the limit of proportionality (LOP) and
the residual flexural strength. Testing of the specimens is done in a three-point bending test
configuration but can be performed in two ways. In the first method, the crack mouth open-
ing displacement (CMOD) placed at the notch is measured, and a displacement transducer
is mounted along the longitudinal axis at the mid-width of the test specimen. The distance
between the bottom of the specimen and the line of measurement shall be less than 5 mm
(0.25”) as shown in Figure 5.12.
A second possibility is to measure the deflection instead of the CMOD. In that case, a
displacement transducer shall be mounted on a rigid frame that is fixed to the test spe-
cimen at mid-height over the supports. One end of the frame should be fixed to the spe-
cimen with a sliding fixture, and the other end with a rotating fixture. A thin plate fixed at
one end can be placed at mid-width across the notch mouth at the point of measurement.
The tests are preferably deflection controlled. To control the test with a CMOD, knives
need to be glued next to the notch. It is possible that they come loose during the test due
to a bad interlayer between the knives and the concrete. It is easier to mechanically fix the
deflection transducer to the concrete specimens. Less test specimens and test results will
be lost in this way.
The testing machine should be capable of operating in a controlled manner, producing a
constant rate of displacement (CMOD or deflection), and have a sufficient stiffness to avoid
unstable zones in the load–CMOD curve or the load deflection curve. A total stiffness of
the system of 200 kN/mm (1,132 lbf/in) (including frame, load cell, loading device and sup-
ports) is advised. All rollers should be made of steel and have a circular cross-section with
310 Handbook of Precast Segmental Tunnel Lining Systems
a diameter of 30 mm ±1 mm (1.18” ±0.04”). Two of the rollers, including the upper one,
shall be capable of rotating freely around their axis and of being inclined in a plain perpen-
dicular to the longitudinal axis of the test specimen. The distance between the centers of the
supporting rollers shall be equal to 500 ±2 mm (19.7” ±0.08”). The load measuring device
needs an accuracy of 0.1 kN (0.011 ton) and the linear displacement transducer needs an
accuracy of 0.01 mm (0.0004”). The data recording system should be able to record load
and displacement at a rate not less than 5 Hz.
In the case of a testing machine controlling the rate of CMOD increase, the machine
should operate from the start of the test with a CMOD increase of 0.05 mm/min (0.002”/
min) and a data logging minimum of 5 Hz. When CMOD is 0.1 mm (0.004”), the machine
should operate at a CMOD increase of 0.2 mm/min (0.008”/min) and a data logging min-
imum of 1 Hz. The test should not be terminated before a CMOD value of 4 mm (0.157”).
In the case of controlling the deflection increase, the machine should start the test with a
deflection increase of 0.08 mm/min (0.003”/min) with a data logging minimum of 5 Hz.
When the deflection reaches 0.125 mm (0.005”), the deflection increase should change to
0.21 mm/min (0.008”/min) until a final deflection of 3.5 mm (0.139”), and a data logging
minimum of 1 Hz. If the crack starts outside the notch, the test result should be rejected.
Before starting any segment production, compressive and bending tests in accordance
with EN 14651 have to be performed in order to control the fulfilment of the character-
istic values defined in the design. Note that the “k” subscript fLk, fR1k, fR3k denote the use of
“characteristic”, not mean values as discussed in Section 5.2.1.
The test results, which need to be expressed, are the limit of proportionality (LOP) and
the residual flexural strengths as shown in Figure 5.12.
The limit of proportionality f fct,L is calculated as
3 l
fctf ,L = .FL . 2 (5.1)
2 bh
where FL is the maximum load between CMOD of 0.00 and 0.05 mm (0.0020”) or deflec-
tion of 0.00 and 0.08 mm (0.00315”). The residual flexural strength fR,x needs to be evalu-
ated at four different displacements.
Fiber reinforcement in precast concrete segments 311
3 l
f R, i = .FR,i . 2 (5.2)
2 bh
and
l =the span between the supports; nominal distance 500 mm (19.6”)
b =the width of the concrete sample; nominal value 150 mm (6”)
h =the residual height of the concrete sample; nominal value 125 mm (5”)
Value fR1 (CMOD =0.5 mm) (0.020”) is used for the service limit state (SLS). Value fR3
(CMOD =2.5 mm) (0.098”) is used for the ultimate limit state (ULS). FRC toughness can
be classified by using a couple of parameters: the first one is a number representing the
SFRC compressive strength while the second one is a letter representing the ratio fR3k/fR1k.
The strength interval for fR1k is defined by two subsequent numbers in the series: 1.0; 1.5;
2.0; 2.5; 3.0; 4.0; 5.0; 6.0; 7.0; 8.0 MPa (145, 217, 290, 362, 435, 580, 725, 870, 1,015,
1,160 psi) and,
The fR3k / fR1k ratio can be represented with letters a, b, c, d, e, corresponding to the ranges:
The designer should specify the residual strength class and the fR3k / fR1k ratio as well as the
type of fiber and its material properties such as fiber strength. Materials with fR1k ranging
from 4.0 MPa to 5.0 MPa (580 to 725 psi) are commonly used for precast tunnel segments
without any bar reinforcement, combined with a fR3k / fR1k ratio in the ranges 0.9 < fR3k /
fR1k < 1.1 or 1.1 < fR3k / fR1k < 1.3 (class C or class D, respectively, according to the Model
Code 2010 definition). Note that flexural hardening is indicated by a fR3k / fR1k ratio > 1.0.
5.2.2 Full-scale testing
Proof testing (aka, proof-of-design) of precast concrete elements is routinely done, espe-
cially true for repetitive units, where large numbers are required to meet a particular pur-
pose such as with the manufacturing of segments. Load testing can be used to determine the
ability of a structural element to validate performance, to gain knowledge on the behavior
of a structure, and to supplement, validate or refine analytical work models. Both ACI
544.7R and Bulletin 83 recommend full-scale testing during preconstruction to “prove” the
performance of the segment is adequate.
SFRC precast segments are subjected to various loads; from manufacturing, to installa-
tion, and then in situ conditions. Two different types of full-scale tests have been performed
on segments in specific projects in Europe to successfully assist in the design process to val-
idate the EN 14651 beam test in characterizing the SFRC material performance in conform-
ance with fib Model Code 2010 methodology and constitutive laws in design.
Testing performed included the following:
• Full-scale bending tests aiming to evaluate the bearing capacity under flexure, that
can occur during transitional stages; i.e. demolding, storage and moving phase, and
in field due to the asymmetrical ground pressure)
• Thrust tests able to reproduce the TBM action on the segment during the excavation
process.
• The load F, measured by means of a 1,000 kN (112 tons) load cell with a precision
of 0.2%
• The midspan displacement measured by means of multiple potentiometer wire trans-
ducers placed along the transverse line
• The crack opening at midspan, measured by means of two linear variable differential
transformers (LVDTs)
Furthermore, the crack pattern should be recorded at each different step, with the help of a
grid plotted on the intrados surface 100 mm × 100mm (4” × 4”). See Figure 5.16.
applied by adopting the same steel plates used by the TBM machine as shown in Figures 5.17
and 5.18. A uniform support is considered, as the segment is placed on a stiff beam suitably
designed. Two 2,000 kN (225 ton) hydraulic jacks were used for every steel plate.
The load was continuously measured by pressure transducers. Four wire transducers (two
located at the intrados and two at the extrados) measure the shoes displacement, while
314 Handbook of Precast Segmental Tunnel Lining Systems
one linear variable differential transformer (LVDT) transducers is applied between the load
shoes, to measure the crack openings.
testing done in a typical precast concrete manufacturing plant are applicable to the produc-
tion of a precast concrete segment that incorporate fibers into the concrete mix. There
are two quality control reference documents commonly used by structural precast concrete
manufacturers in North America that are applicable to the manufacturing of precast seg-
ments utilizing structural fibers. The documents are as follows:
• The Precast Concrete Institutes (PCI) MNL-116, Manual for Quality Control: Structural
Precast Concrete Products
• National Precast Concrete Association’s NPCA Quality Control Manual for Precast
Concrete Plants.
When fibers are used as structural reinforcement there are areas where additional test-
ing and controls need to be in-place in the precast plant to assure the conformance with
the design and specifications for the segments are being met. These areas include the
following.
317
318 Handbook of Precast Segmental Tunnel Lining Systems
This equipment helps to assure that the correct dosage of the applicable fiber is added into
the mixer. The fibers are introduced into the mix at the appropriate stage of loading the
materials into the mixer. Fibers are not to be the first item loaded in the mixer. Loading
the prescribed quantity of the right fibers into the mixer is step number one in obtaining a
quality segment. Followed by sufficient mixing, then placing and vibration of the mix into
the formwork will result in a homogenous fiber distribution network throughout the seg-
ment with performance that meets or exceeds the specifications.
cylinders for doing concrete compressive strength testing, specific test specimens such as
beams and cylinders also need to be made to determine the structural design performance
requirements of the hardened SFRC. (residual flexural strength)
and St. Pancras Station in central London. Because of the extensive damage from the fire in
the Channel Tunnel in 1996, CTRL decided to do an extensive fire testing at the University
of Delft in the Netherlands to evaluate different concrete mixes including monofilament
and fibrillated polypropylene fibers. This testing found that by inclusion of 1.0 kg/m3 (1.7
lbs/CY) of monofilament polypropylene fibers in the high strength, low permeability mixes
significantly the risk of explosive spalling when exposed to a severe hydrocarbon fire was
reduced. The CTRL project was the first project to use the recommended 1.0 kg/m3 (1.7
lbs/CY) of micro-PP fibers for controlling explosive spalling. In this project 30 kg/m3 (51
lbs/CY) of steel fiber was used as the only reinforcement along with the micro PP fibers as
passive fire protection (PFP).
Figure 5.22 Basic concepts of using micro-s ynthetic polypropylene (PP) fibers for PFP.
Note: General arrangement mechanism illustrating the failure of tunnel lining in compression.
Fiber reinforcement in precast concrete segments 323
The dosing of micro-PP fibers into the mix is a relatively simple process. For smaller pro-
jects, micro-PP fibers are typically supplied in fully degradable paper packaging that enables
the desired dosage per unit volume to be simply added directly into the concrete truck or
mixer. The packaging is designed to rapidly break down allowing uniform distribution of
the fibers into the concrete. In smaller projects this is often the most cost-effective method
to adopt, with packaging available in 1.0 kg (1.7 lbs/CY) or 2.0 kg (3.4 lbs/CY) bags. On
larger precast segment project applications that involve significant quantities of micro-PP
fibers the use of a separate automatic dosing equipment can be employed. See Figure 5.20
for example.
5.5 SUSTAINABILITY
Today green is not just a color! The modern environmental movement or “green revolu-
tion” as it is sometimes called had its roots in the 1960’s in the USA. On 22 June 69, the
324 Handbook of Precast Segmental Tunnel Lining Systems
Cuyahoga River in Cleveland, Ohio, burst into flames five stories high as a result from long
time dumping of oil and chemical pollution into the river. This event became what is now
considered a defining moment in the modern environmental movement. In 1969, the US fed-
eral government enacted legislation called The National Environmental Policy Act (NEPA).
This act established the US Environmental Protection Agency (EPA) in 1970 that continues
to exist today. For the last 50 years the United States has been committed to a national
policy “to create and maintain conditions under which humans and nature can exist in
productive harmony, that permit fulfilling the social, economic and other requirements of
present and future generations”.
Today the terms sustainability and sustainable development are embraced globally. The
concept of sustainability is one that has been around for as long as humans have: a concern
for the future of our resources. The word itself, however, has more recent origins. A term first
used in Germany, Nachhaltigkeit, meaning “sustained yield”, appeared in a forestry hand-
book published in 1713. The term was used to say that to be “sustainable” in forestry you
should never harvest more trees than the forest can regenerate. An example of sustainable
use today in the context of fisheries is that fishing limits of a particular species are established
to assure that species population does not decline over time because of over-fishing practices.
In the 1980s, the term sustainability began to be used in terms of how humans live on the
planet. Today, the concept of sustainability when used in terms of a construction project
being sustainable, has roots in the 1980’s. The United Nations convened a group in 1987,
known as the World Commission on Environment and Development (WCED), also called
as The Brundtland Commission, that was first to use the term “sustainable development”.
The commission’s report defined sustainable development as “development that meets the
needs of the present generation without compromising the ability of future generations to
meet their own needs”.
The designer of a reinforced concrete precast tunnel segment tasked with providing a
sustainable TBM bored tunnel lining must consider not only environmental impacts of the
design, but structural requirements must also be met as well as meeting minimum service life
requirements through providing increased durability. When the geology requires the tunnel
to be lined, the use of SFRC in a precast tunnel segment, either in combination with bar
reinforcement or alone, has been found to provide a more sustainable solution over other
options.
The consequences of changing the natural atmospheric greenhouse are difficult to pre-
dict, but some effects seem likely: On average, Earth will become warmer. Some regions
Fiber reinforcement in precast concrete segments 325
may welcome warmer temperatures, but others may not. Warmer conditions will prob-
ably lead to more evaporation and precipitation overall, but individual regions will vary,
some becoming wetter and others dryer.
A stronger greenhouse effect will warm the ocean and partially melt glaciers and
ice sheets, increasing sea level. Ocean water also will expand if it warms, contrib-
uting further to sea level rise. Outside of a greenhouse, higher atmospheric carbon
dioxide (CO2) levels can have both positive and negative effects on crop yields. Some
laboratory experiments suggest that elevated CO2 levels can increase plant growth.
However, other factors, such as changing temperatures, ozone, and water and nutrient
constraints, may more than counteract any potential increase in yield. If optimal tem-
perature ranges for some crops are exceeded, earlier possible gains in yield may be
reduced or reversed altogether. Climate extremes, such as droughts, floods and extreme
temperatures, can lead to crop losses and threaten the livelihoods of agricultural pro-
ducers and the food security of communities worldwide. Depending on the crop and
ecosystem, weeds, pests, and fungi can also thrive under warmer temperatures, wet-
ter climates, and increased CO2 levels, and climate change will likely increase weeds
and pests.
Finally, although rising CO2 can stimulate plant growth, research has shown that it
can also reduce the nutritional value of most food crops by reducing the concentrations
of protein and essential minerals in most plant species. Climate change can cause new
patterns of pests and diseases to emerge, affecting plants, animals and humans, and pos-
ing new risks for food security, food safety and human health.
Although the consequences of climate change is difficult to predict, the rapid increase in
Earth’s temperature will bring about detrimental impacts to future generations. It is increas-
ingly evident that we must act to reduce manmade levels of CO2 emissions into our atmos-
phere. To be considered a sustainable project today, design engineers are required to make
conscious efforts to reduce the carbon footprint as well as provide for a minimum service
life of structures they are designing. Considerations on selection of design and construction
process are no longer based on the lowest first cost. This section of the chapter will look at
how the use of fibers to replace all or a portion of the conventional reinforcement in a pre-
cast tunnel segment provides for a significant reduction of the carbon footprint of the tunnel
and high-performance steel fibers provide smaller crack widths and improved durability and
increased service life.
5.5.2 Sustainability assessments
Determining the environmental impacts of one construction process or alternative to
another needs to be objectively assessed. The engineer must also consider that reducing
the environmental impact of a structure is only one consideration. The structural design
of a tunnel lining segment is primarily dependent upon the load conditions applied to it
(ground and groundwater loads, handling, transportation, and erection, as well as live
loads). The benefits of reduced embodied CO2 can only be realized when the selected
reinforcement alternative also meets all the design requirements (structural, safety and
durability).
fib Bulletin 83, “Precast Tunnel Segments in Fibre-Reinforced Concrete”, contains a
chapter entitled, “10.1 Sustainability Index”. The chapter proposes a method to compare
precast concrete segment alternatives taking into account the economic, environmental
326 Handbook of Precast Segmental Tunnel Lining Systems
and social requirements involved in the production of the precast segments. The com-
parison is carried-out on three different precast segment alternatives by means of the
sustainability and mechanical indexes assessed for each alternative. The chapter provides
a detailed assessment on an example precast concrete tunnel segment using three differ-
ent alternative reinforcing solutions. This chapter is a good reference for an engineer that
needs to perform a sustainability assessment on precast concrete segmental tunnel lining
alternatives.
rebar and steel fibers is assumed the same. This is a generalization assuming the wire rod
that the fiber is produced from, and the rebar have similar percentage recycled material
content and similar steel production methods. In a precast concrete segment design the per-
centage of reduction of steel is dependent on the structural and serviceability requirements
of the segment, the fiber’s attributes, and performance in the specific concrete mix. Based on
information from a leading steel fiber producer, a typical reduction percentage in steel when
using steel fibers in a precast concrete segment is typically 60 to 65%. The actual reduction
in embodied CO2 of the lining will depend on the contribution of the reinforcement plus
the concrete.
From the descriptions of the reference projects listed above, it is noted that advances with
regard to durability are carried on from either previous projects from the region. Moreover,
as will be presented in the following, the advances in terms of durability are associated with
a gain in terms of sustainability, but it is stressed that the advances in terms of sustain-
ability, e.g. reduction of CO₂ emission, have been made without sacrificing the durability
of the concrete structures. The key to the innovations and the corresponding gains regard-
ing durability and sustainability lies in a construction material and the overarching design.
Some examples presenting selected trends regarding concrete durability design of bored,
segmental linings in the Middle East are presented along with the benefits from a sustain-
ability perspective are given in the list below.
The cost savings in the installation of SFRC segments is due to significant reduction of dam-
age to the segment caused by the high, concentrated jacking forces on the segment that drive
the excavation. The thrust loads applied by the jacking rams acting in the cross section of
the tunnel induce spalling and bursting stresses in the circumferential joints of the tunnel
segments. Conventional reinforcing steel requires cover whereas steel fibers can reinforce
all the way to the edges. When spalling occurs, the segment requires costly repairs or even
replacement, which can then delay the excavation. The damaged edges also compromise the
durability of the concrete and performance of the gasket in the damaged area. Experience
has shown that the use of SFRC in segments substantially reduces this type of damage dur-
ing installation. See Figure 5.24.
A study undertaken in the United Kingdom in 2004, by the Client Manager for the High
Speed 1, Channel Tunnel Rail Link (CTRL) Project. The CTRL is the high-speed Euro-
Star train line running for 108 km (68 miles) between the Channel Tunnel and St. Pancras
Station in central London. This project was a real break-through, with more than 260,000
segments with SFRC only, using 30 kg/m3 (50.5 lbs/CY) of steel fibers along with 1 kg/m3
(1.70 lbs/CY) of micro-PP fibers for passive fire protection. The study concluded that using
SFRC significantly improved the handling capacity and surface finish of the segments.
Segment damage requiring repair or replacement during manufacturing and installation
was minimized compared to rebar reinforced segments. The study concluded that the use of
steel fibers to replace the conventional rebar in the segments ended up providing more than
a 10% savings on the estimated installation costs of the tunnel lining. This level of savings
by replacing conventional reinforcement with steel fibers has become a consistent outcome
throughout the tunneling industry.
Fibers, like conventional rebar, is passivated by the high alkalinity of the concrete, which
protects against corrosion. Rebar requires the bars to be embedded within the concrete,
whereas steel fibers require little to no cover to become passivated. Fibers that are located
within the 2 to 5 mm (0.08 to 0.20”) of the surface are susceptible to corrode with time.
Corrosion initiation is due to ingress of chlorides or other deleterious substances as well as
higher levels of oxygen availability. Fibers will remain passivated in good-quality uncracked
concrete, but if there is carbonation of the concrete, which lowers the pH in an area fiber
corrosion can take place. Regardless of this, because of the discrete nature and very small
diameter [in a segment typically less than 1mm (0.04”)] of the fiber any corrosion initiation
is isolated (no electrical continuity of the network) and corrosion by product volume is so
little, even when occurring at or near the surface no cracking, spalling or structural degrad-
ation that happens with conventional bar will result.
Durability of a tunnel liner is controlled by limiting the crack width to specific levels to
prevent increased permeability, excessive water leaks, and reinforcement corrosion. Poor
durability of conventional only reinforced segments by the bar corroding is a consequence
of wide crack widths inherent with the bar requiring cover. Steel fibers, on the other hand,
have a very positive effect on cracking and crack propagation. The distance between steel
fibers is much smaller than typical spacing for reinforcing bars.
Unlike reinforced concrete, fibers are homogenously distributed throughout the entire
segment cross-section providing reinforcement all the way to the concrete surface and edges.
Performance of SFRC in cracked concrete is based on the width of the cracks and if a
fiber near the surface crosses a crack or not. The use of deflection hardening SFRC promotes
multiple-crack development, thereby significantly reducing the permeability of concrete in
service. Unlike reinforced concrete, fibers are distributed throughout the whole
330 Handbook of Precast Segmental Tunnel Lining Systems
section. Hence, there is no area throughout the entire cross-section without reinforcement.
Furthermore, stresses in the root of a crack can be picked-up quicker. This is why crack
propagation and crack patterns change when compared to plain or even reinforced con-
crete. Please refer to Figure 5.25.
Steel fibers typically bridge cracks at a non-perpendicular angle so they will already be
deforming and picking-up load at small crack widths. Local friction is increased and thus
compressive stresses parallel to the crack surface are induced. As a consequence, the associ-
ated tensile stresses perpendicular to the crack can lead to secondary cracking. Those cracks
may be compared to cracks in conventional reinforced concrete, which can be found in the
zone directly around rebar. With steel fiber concrete, secondary cracking can be observed
over the whole cracked section. Subsequently cracks become more curved. Fragmentation,
translation and multiplication can be identified. Resistance to intruding substances, espe-
cially liquids, is substantially increased with aggregate interlock and friction also enhanced.
With high performance steel fibers, engineers can design the SFRC for a maximum allow-
able crack width. Small crack widths will assure little risk of corrosion of the fibers near
the surface as well as a very low permeability to reduce the ingress of potentially dele-
terious substances into the segment and control leaks. Control of micro-cracking is also an
important parameter. Steel fibers have been used successfully in tunnel projects to reduce
cracking widths to 0.20 mm (0.80”). When a crack in SFRC does not exceed 0.20mm
(0.80”) width, it presents a very tortuous and discontinuous path. This makes the diffusion
of aggressive agents or water far more difficult. Further research has shown that when a
crack in SFRC does not exceed 0.30 mm (1.20”), self-healing mechanisms occur, and the
corrosion products fill in the interior of the cracks. These two physical mechanisms conse-
quently obstruct the cracks and, therefore, prevent further deterioration.
In cases where the design requires a combined solution of steel fibers and conventional
rebar, the steel fibers enhance the durability compared to a rebar only reinforced segment.
If there are extremely severe exposure conditions that are present or no surface corrosion
of fibers is desired for aesthetics, galvanized or solid stainless steel fibers are available with
some limitations. If the project requires a combined solution, any of these types of steel fib-
ers can be combined with corrosion resistant rebar (CRR) with no concern of any dissimilar
metal issues in the concrete. For a very durable combined solution the use of SFRC with
glass fiber reinforced polymer (GFRP) bar is a consideration.
The use of electric powered trains in railways is increasing being considered to move to
lower carbon footprints and increase the sustainability of the transportation system. A dur-
ability issue that sometimes calls to be addressed are concerns of durability due to stray cur-
rent induced corrosion in reinforced concrete. Stray currents may be DC or AC depending
Fiber reinforcement in precast concrete segments 331
upon the source. Typically, electrified railways utilize DC power to drive the trains. In the
case of DC current, a cathodic reaction; e.g. oxygen reduction or hydrogen evolution takes
place, where the current enters the structure (or, reinforcement), while an anodic reaction
takes place; e.g. metal dissolution, where the current returns to the original path, through
the soil (or, concrete). The precast segment tunnels that serve DC electrified railway applica-
tions require careful consideration of the potential for stray current-induced corrosion of
the reinforcement in the lining.
The initiation of stray-current induced corrosion in a reinforced concrete segment is the
transmission of current by the steel reinforcement though the lining. Kangkang Tang, a
Senior Lecturer at Brunel University London, published a study entitled Corrosion of Steel
Fiber Subjected to Stray Current Interference in the March 2020 ACI Materials Journal that
showed steel fibers are much less prone to picking-up and transferring direct current com-
pared to traditional bar reinforcement. Initiation of stray current induced corrosion requires
the steel to pick up and then transport of current throughout the structure. In conventional
rebar reinforced concrete this this is an issue. However, in SFRC it was found that due to
the short length of the fibers it is difficult to have an anode and a cathode form on the same
fiber. Without this formation the transfer of current from fiber to another and then through
the structure cannot occur. Tang’s study concluded that since the fibers likely do not transfer
stray-current there is in practice no risk of stray-current induced fiber corrosion in SFRC
used in DC electrified railway applications.
mix. These special concretes replace the OPC with replacement materials such as GGBS, fly
ash, metakaolin and calcined clay; they are activated with the addition of alkali additives
such as hydroxides and silicates. There are new products that are becoming available that
completely replace the OPC in the concrete and have shown to provide improved proper-
ties for use in precast segments. Alkali-aggregate reaction (AAR) and alkali-silica reaction
(ASR) and their associated deleterious expansion of concrete or mortar can cause major
long term durability problems in concrete structures. It is important that testing is done to
address this concern.
In a recent paper, Charles Allen (OTB Consulting) refers to the case for using one such
product in segmental linings called “Earth Friendly Concrete” (EFC®) geopolymer con-
crete. EFC has been developed over the past ten years by Wagner Concrete in Queensland,
Australia. The structural performance of EFC has been tested and shown to be equal to that
of OPC-based concretes while its durability often exceeds that of OPC-based concretes.
The results from the beam tests show that the SFR EFC has similar magnitude limit of
proportionality (LOP) and residual flexural tensile strengths to those of a typical C50/60
Portland cement-based concrete containing high performance steel fibers. See Figure 5.26.
Steel and polypropylene fiber reinforced EFC has been tested for fire resistance to the RABT-
ZTV (Eureka) fire curve in Australia and shows equivalent performance to similar concretes
based on OPC cements. In the paper Charles states,
in tunnel linings could be quantified by conducting full-scale production trials with the
segment manufacturer.
A combination of appropriate low-carbon concrete mix design combined with the efficient
use of steel fibers in the design of the segment can give dramatic reductions in the embodied
carbon of tunnel lining segments when compared with traditional segments used in major
projects.
5.5.6 Project examples
5.5.6.1 Project example –Paris Metro Line 16-1
The Grand Paris Express project is an investment of $38.2 (€35.6) billion in 2012 num-
bers and will add more than 68 stations and 200 km (125 miles) of trackway to double
the existing mass transit rail network for Paris. The 100 km (62 miles) currently in con-
struction includes Line 16, which is scheduled to be in operation for the Paris Summer
Olympic Games in 2024. The $1.98 (€1.84) billion Grand Paris Express Line 16-1 is a
19.3 km (12 mile) long tunnel contract that was awarded in February 2018 to a con-
sortium led by Eiffage Génie Civil. The project employs the use of six tunnel boring
machines of three different diameters; 9.0, 7.7 and 9.5 m (29.2, 25.3, and 31.2 feet)
outer diameter, that will install approximately (200,000 m3 (261,600 CY) of precast
concrete segments in the lining.
It was soon after award of initial contracts for the Grand Paris Express that Société
du Grand Paris, the owner of the mega-project, began to explore the use of steel fiber
reinforcement for the segmental linings to replace the rebar reinforcement. One of their
primary objectives was to enhance the sustainability credentials of the project, to pro-
mote respect for the environment and reduce as much as possible the carbon footprint.
The specifications for the 16-1 work package provide for conventional rebar only –no
fibers. Three months after awarding of the contract for Line 16-1 in 2018, Eiffage Génie
Civil proposed to Société du Grand Paris to implement a 100% SFRC segments. The
objectives by using steel fiber as an alternative to rebar reinforcement was to reduce the
amount of steel required per cubic meter of precast lining and capture the benefits that
steel fiber creates less carbon pollution in its manufacture and transportation. The use of
SFRC plus formulating a low carbon concrete mix would optimize the carbon footprint
of the project.
In France, prior to when Line 16-1 was launched, steel fiber reinforced concrete (SFRC)
segments had only been used in temporary (sacrificial) or experimental lining segments
(in siding areas, for example). In the rest of Europe, excluding Spain (due to the use of
hybrid segments; i.e. fiber-reinforced concrete segments combined with a perimeter cage
of reinforcing bar) and the United Kingdom (where smaller diameters are the norm, with
numerous segments per ring; typically 9+1, to distribute loads as for CTRL), there are no
references for all-SFRC segments being used in large diameter metro tunnels in Europe
such as Line 16-1. At a global level, particularly since the publication of the fib Model
Code 2010, the Anglo-American nations have pioneered the use of 100% SFR segments.
Although the United States, Canada and Australia provided the momentum, the Doha
metro project in Qatar marked a milestone in 2014, by proving that, in a particularly
aggressive environment, an all-SFRC solution combined with innovative low-carbon
334 Handbook of Precast Segmental Tunnel Lining Systems
concrete formulations met the specified durability requirements and provided a much
superior sustainable solution.
When the contract for Line 16-1 was awarded, Eiffage Génie Civil immediately nego-
tiated a subcontract with segment producer Bonna Sabla. Then in the summer of 2018,
Eiffage initiated a $1.3 (€1.2) million research program to validate the performance of the
SFRC segments. This 18-month campaign included:
Following this most extensive study in December 2019, the new SFRC segments were
approved for installation for the 2 km × 9.5 m (7.5 mile × 31.2 foot) outside diameter
drives for Lines 16 and 15. Manufacturing was at the same Bonna Sabla factory casting
the rebar reinforced segments. The low carbon mix design contains 40 kg/m3 (67 lbs/
CY) of high-performance steel fibers glued in clips for homogenous distribution in the
mix. This quantity of fibers completely replaces the original 85 kg/m3 (143 lbs/CY) of
steel rebar cages for the same 2m (6.6 foot) wide × 9.5m (31.2 foot) outside diameter
segments.
The use of SFRC in a portion of the segments in the Paris Metro Line 16-1 has pro-
vided substantial environmental benefits and lowered carbon footprint derived from the
following:
The production of structural precast concrete segments 100% reinforced with SFRC for
the permanent lining of Paris Metro Line 16-1 large diameter tunnel is the first of such pas-
senger rail structure in France and Europe. Using SFRC for this type of structure is emerging
as the obvious choice from a technical, economic, and more so now sustainability perspec-
tive in conjunction with low-carbon concretes. This groundbreaking project opens the door
to more SFRC segment projects in France and Europe and confirms that the use of SFRC
Fiber reinforcement in precast concrete segments 335
Equivalent CO 2
Material quantities quantities
Carbon
Item Operation Metric Imperial Metric Imperial footprint
A Data comparisons
1 Steel fiber production 1 kg 2.2 lb 0.88 kg 1.94 lb Carbon dioxide
(CO 2)
2 Rebar production 1 kg 2.2 lb 1.85 kg 4.08 lb Carbon dioxide
(CO 2)
B Comparison summary
1 SFRC segments have 50% less steel than rebar reinforced segments saving more than
5,000 tonnes (5,512 tons) of steel production carbon for 10 km (6.2 miles) of tunnel.
2 One truck can transport 24.2 tonnes (26.7 tons) of fiber per load compared with
17.85 tonnes (19.7 tons) per truck load of rebar.
3 The concrete chosen for the Paris Metro Line 16, Lot 1, fiber reinforced segments had
a low carbon footprint of 170 kg (375 lbs) CO 2 equivalent/m 3 and reduces the carbon
weight of the steel in the segments by 90 kg (198 lbs) CO 2 equivalent/m 3 or nearly
11,000 tonnes (12,125 tons) equivalent CO 2.
for precast segments is the sustainable state of the art solution in France and around the
world. See Figure 5.27.
Table 5.8 Comparison of total embodied carbon of the tunnel – segmental lining alternatives.
Embodied CO 2 comparison of segments between rebar with OPC mix and SFRC with
SCM mix
Volume, m 3 / CO 2 eq 1m
Thickness 1 m tunnel CO 2 eq/m 3 length
Item Description mm m3 Kg tons
1 Temporary shotcrete 325 5.90 470.3 2.8
2 CIP arc concrete 400 7.03 513.9 3.6
3 Invert concrete 320 2.85 539.7 1.5
Total 7.9
shotcrete lining, and 320 mm (12.6 inch) thick invert. The shotcrete and invert concrete are
reinforced with the same hooked end, collated, high-performance steel fibers. The concrete
mix design was modified to reduce the carbon emission while having the same strength
properties. Portland cement was replaced with limestone Portland cement and 27% of
the cementitious material was replaced with slag and silica fume [22% slag and 5% silica
fume which is considered moderate supplementary cementitious materials (SCM)]. This
mixture was proposed for both shotcrete and invert concrete. The total embodied carbon
footprint per 1 m (3.3 foot) length of the tunnel alternate design was calculated and shown
in Table 5.10.
In comparing the low-carbon PSCL design utilizing low-carbon concrete mix with the
CIP Baseline design the total CO2 emission saving is over 79%!
Volume, CO 2 eq 1 m
Thickness m 3 /1 m tunnel CO 2 eq/m 3 length
Item Description mm m3 Kg tons
1 Temporary shotcrete + 160 1.80 361 0.7
Shotcrete final lining
2 Invert concrete 320 2.85 361 1.0
Total 1.7
design, construction and procurement decisions using material data provided through the
product’s environmental product declaration (EPD).
An environmental product declaration (EPD) is essentially an externally verified and
standardized description of the environmental profile of any product or material over its
lifetime. If you are a construction engineer or an architect, you can easily compare the
EPD data of the materials you are about to use and choose the most sustainable option.
The manufacturer through an EPD certifies their product on the issues of climate change,
carbon impact and environmental footprint. Having an EPD for a product does not neces-
sarily mean that the product is environmentally better than others, but it is a way to obtain
transparent information on the environmental impact of the product during its whole life-
time. Table 5.11 is an excerpt from an EPD for steel fibers manufactured by a leading global
producer.
The reduction in CO2 emissions on a precast segmental lining tunnel project is made
possible by modification of the concrete and further reduction by being able to replace the
rebar with steel fibers in a dosage that satisfied all the design requirements. On a per kilo-
gram (or pound) basis the embodied CO2 of conventional rebar and steel fibers previously
had been assumed the same. This example EPD shows that this is not a valid assumption
as the steel fibers as fiber production contributes less CO2 than rebar. Using the One Click
LCA and EPD data provided by the producer gives the owner/engineer tools to optimize the
sustainability of a project.
5.6 COMBINED SOLUTIONS
Precast segments in service are typically mainly in compression and experience low bending
moments. The use of fibers only is the preferred solution, however sometimes there are
loads that are too high for the fibers alone to resist. Fibers are efficient for resisting tensile
stresses that are uniformly distributed. Bar reinforcement is efficient for resisting localized
higher tensile stresses. A combined solution is one where bar reinforcement is added to
provide additional localized capacity where fibers alone are not sufficient. The bars are
considered secondary reinforcement and the fibers are primary. The fibers provide superior
340 Handbook of Precast Segmental Tunnel Lining Systems
A Project application
1 Producers of steel fibers are used for concrete reinforcement and are an alternative
to steel mesh and bars. They are discontinuous, three-d imensional and isotropic
reinforcement. The steel fibers bridge cracks at their small widths, distribute stresses
and increase the strength of concrete in a cracked state. Adding the adequate number
of fibers to the concrete plasticizes it, increasing its tensile and shear strength, impact
strength and fatigue resistance. Steel fibers for structural use are used for concrete
and mortar reinforcement for below applications: over ground applications (flooring,
building, civil engineering, etc.), underground applications (segmental linings for
tunneling etc.) and precast.
B Results interpretation
1 The environmental impact of the producers’ fibers [cradle to gate (grave) with options]
is largely dependent on the energy-intensive production of steel (half product) on which
the manufacturer has a limited influence only. The carbon impact of steel production
(wire rods) in the product stage A1 is as high as 85%. The impact of the production line
A3 largely depends on the amount of electricity consumed by the manufacturing plant
(0.34 kWh/k g of product). There are no significant emissions or environmental impacts
in the A3 production processes alone (partly gas combustion). The production process
itself does not have significant environmental impacts in the life cycle.
2 Interrogation of the LCA results show that the cradle-t o-g ate carbon (global warming
potential) impact of 1 kg of fiber production is 0.88 kg CO 2 equivalent. In comparison,
a ton of steel produced worldwide in 2019 emitted on average 1.85 tons of carbon
dioxide. The LCA results show that the cradle-t o gate (grave) primary energy demand
of fossil fuel is equal to 9.4 MJ. This is due to the production of nuclear energy in
the factory’s region. The transport of raw materials from considerable distances is
optimized and not significant (0.007 kg CO 2/k g).
3 Due to the high potential for recycling and reuse (95%), the products have noticeable D
module potential (beneficial to other product systems).
benefits of increased toughness, durability and efficient crack control compared to rebar
alone. The rebar is added to provide localized strength to resist a specific load case(s) where
the fiber only design either cannot meet the requirement, or it is determined a combined
solution is more efficient. Typically, combined solutions are applicable for larger-diameter
tunnels, which have higher in service internal forces, soft ground conditions, high unbal-
anced loads or special loading cases such as at the start and end of tunnels, at locations of
cross passages, seismic fault zones, etc.
5.6.1 Hybrid solutions with reinforcing steel bar and welded wire mesh
The most common type of bar reinforcement utilized with the fiber is conventional reinfor-
cing steel bar or welded wire mesh. In a rebar +mesh only segment design, the reinforcing
consists of three general groups of bars that provide specific functions:
• Transverse bars
• Top and bottom curved bars considered the main flexural reinforcement placed
perpendicular to the tunnel axis.
Fiber reinforcement in precast concrete segments 341
• Longitudinal bars
• Top and bottom straight bars welded or tied to transverse bars and typically
designed as minimum amount of steel required for temperature and shrinkage.
• Joint bars
• Additional bars at both circumferential and radial joints to provide reinforcement
to resist bursting/spalling forces at the joints.
• Circumferential joints typically consist of transverse curved bars with radial stir-
rups or ties (resembling a curved beam cage).
• In the radial direction not as robust typically consisting of a top and bottom bar
the same size as the other radial steel bars provided transverse resembling a ladder.
In a combined solution, the bars that are added to the fibers are typically the circumferential
joint type reinforcement and all other bars are replaced with SFRC as shown in Figures 5.29
and 5.30.
order to evaluate the structural performance, both in terms of strength and crack width,
bending and point load tests were carried-out on typical metro tunnel size segments. The
testing consisted of performing the tests on segments reinforced with high performance
SFRC only and on segments with the same SFRC plus a light GFRP cage (SFRC +GFRP) as
shown in Figures 5.31 and 5.32.
Results of load deflection full scale tests showed that after an initial almost identical
elastic-type response, the SFRC +GFRP segment presented a peak load about 63% higher
Fiber reinforcement in precast concrete segments 343
than the SFRC, 367 kN (41 tons) against 225 kN (25 tons) of the SFRC segment. Maximum
crack widths were measured at different load steps, and the results showed the SFRC +
GFRP provided further reduction compared to the SFRC solution, of about 60%.
Point load testing was performed by applying three-point loads on the segment, using the
same steel plates used by the TBM machine. Two loading cycles were performed, first with a
load level equal to 1,580 kN (178 tons) for each pad which corresponds to the service load-
ing thrust of the TBM rams. The second loading cycle to 2,670 kN (300 tons) for each pad,
which corresponds to the maximum thrust of the TBM. The addition of the GPRP cages at
the circumferential edges led to halve the crack width under the service load, and to reduce
it of about 37.5%, under the maximum thrust force. Furthermore, a reduction of the crack
width of about 33% was measured after the complete unloading.
The results of bending tests clearly show the synergic effects of the two materials (SFRC +
GFRP reinforcement) by increasing the peak load and reducing the crack width. The results
of the point load test further confirm the effectiveness of the addition of a GFRP cage at
the circumferential edges to provide superior performance in regard to counteracting TBM
thrust forces.
Since tunnels can have different geotechnical conditions along their length, in general it
is best to define a SFRC solution that can cover the greatest part of the tunnel and adopt a
hybrid solution only in the remainder. Therefore, if a base SFRC only solution is viable for
the vast majority of the tunnel, the use of a GFRP or steel bar hybrid solution can be con-
venient, e.g. in cross-passages, in shallower sections of tunnels and in areas where increased
performance is required.
fibers are being considered. Furthermore, current design guidelines such as ACI 544-7R
or the fib Model Code 2010 are valid for steel fiber only. Synthetic fibers are susceptible
to other types of degradation, as is mentioned in the EN 14889 standard. Also, the long-
term effects of exposure to ultraviolet light, chemicals, microbes, is not well documented.
The example application mentioned earlier in this chapter is a small-diameter combined
sewer overflow (CSO) tunnel where the fibers were able to meet the structural performance
requirements with the benefit that the segments were free of any metallic reinforcement
eliminating any risk of corrosion.
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
1982 Naples Metro–M etrosud Subway Italy 5.8 Steel Yes
1989 Fanaco, Sicily Water Italy 3.0 Steel Yes
1990 Munich Water Tunnels Sewage Germany 3.4 Steel Yes
1992 Metro Subway Tunnel Napoli Metro Italy 7.3 Steel Yes
1992 Water Tunnel Hydro South Africa 4.6 Steel No
1993 Heathrow Airport Baggage Tunnel Utility UK 4.5 Steel Yes
1994 Heathrow Express Rail UK 5.7 Steel Yes
1995 Naples Metro Metro Italy 5.8 Steel Yes
1995 Lesotho Highlands Water South Africa 4.5 Steel Yes
1996 Essen Metro Metro Germany 7.3 Steel Yes
1996 Kandertal Exploratory Tunnel, Faido Rail Switzerland 5.0 Steel Yes
1996 Portsmouth Wastewater Transfer Hydro UK 3.0 Steel Yes
1996 Wanley Island Wastewater Tunnel Hydro UK 2.9 Steel Yes
1996 Jubilee Line Extension (cont103) Metro UK 4.5 Steel Yes
1997 High Wycombe Water Transfer Hydro UK 3.4 Steel Yes
1998 Cigar Lake Uranium Mine Mining Canada 4.2 Steel Yes
1998 Hachinger, Munich Water Germany 2.2 Steel Yes
1998 Bromborough Wastewater Tunnel Utility UK 2.9 Steel Yes
1999 Dunfermline Duplicate Sewer Sewage UK 2.9 Steel Yes
1999 2nd Heinenoord, Rotterdam Road Netherlands 7.6 Steel Yes
Fiber reinforcement in precast concrete segments 345
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
1999 Torbay Wastewater Tunnel Utility UK 3.0 Steel Yes
2000 Esperanza (Trasvases Manabi) Hydro Ecuador 3.5 Steel Yes
2000 Oenzberg Rail Tunnel Rail Switzerland 12.0 Steel Yes
2000 Sörenberg Gas Tunnel Utility Switzerland 4.3 Steel Yes
2000 CTRL Rail Tunnels–L ots 220 and 240 Rail UK 6.0 Steel Yes
2001 Manapouri Second Tailrace Tunnel Hydro New Zealand 10.1 Steel Yes
2002 Marina Line C825 Metro Singapore 6.4 Steel Yes
2002 Dartford Cable Tunnels Utility UK 2.8 Steel Yes
2003 Genova Metro–P rincipe/C ari/G razie Metro Italy 4.9 Steel No
2003 Bankside Cable Tunnel Utility UK 4.0 Steel Yes
2003 CTRL Rail Tunnel, Contract Lot 103 Rail UK 7.2 Steel Yes
2003 Margate Sewer Tunnel; Sewage UK 3.0 Steel Yes
2003 Transco Gas Pipeline Utility UK 2.4 Steel Yes
2004 Hofoldinger Stollen Hydro Germany 3.1 Steel Yes
2004 Croydon Cable Tunnel Utility UK 3.0 Steel Yes
2005 Metro Barcelona Line 9 Metro Spain 12.0 Steel No
2005 Metro Madrid, Linea 3 Extension Metro Spain 8.6 Steel No
2005 Metro Madrid, Linea 5 Extension Metro Spain 8.6 Steel No
2005 Metro Norte Madrid Metro Spain 9.4 Steel No
2005 Dockland Light Rail Extension Rail UK 5.3 Steel Yes
2005 Big Walnut Sewer, Columbus, OH Sewage USA 3.7 Steel No
2005 Metro Expressway Shinjuku Route Road Japan 10.9 Steel No
2005 Piccadilly Line and Heathrow Express Metro UK 5.7 Steel Yes
Ext’n
2006 Circle Line C856 Metro Singapore 6.4 Steel Yes
2006 Heathrow Piccadilly Extension Metro UK 4.5 Steel Yes
2006 Thames Water Ring Main Brixton Utility UK 3.0 Steel Yes
2006 Thames Water Ring Main River Utility UK 3.0 Steel Yes
2006 Heathrow–S WOT Water UK 2.9 Steel Yes
2006 Brightwater Sewer Tunnel–C entral, Sewage USA 4.7 Steel Yes
Seattle
2006 Brightwater Sewer Tunnel–E ast, Sewage USA 5.1 Steel Yes
Seattle
(Continued)
346 Handbook of Precast Segmental Tunnel Lining Systems
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
2006 Brightwater Sewer Tunnel–West, Sewage USA 4.0 Steel Yes
Seattle
2006 San Vicente Water Tunnel Hydro USA 4.0 Steel Yes
2007 North Sewerage Project Melbourne Hydro Australia 2.5 Steel No
2007 Lötschberg Base Tunnel Temp Switzerland 4.5 Steel Yes
2007 Belfast Sewer Tunnels Hydro N. Ireland 2.9 Steel Yes
2007 Metro Napoli, Linea 1 Metro Italy 6.8 Steel No
2008 Gold Coast Desalination Plant Hydro Australia 2.8 Steel Yes
Tunnels
2008 North-S outh Bypass Brisbane Road Australia 12.4 Steel Yes
2008 Hobson Bay Sewer Hydro New Zealand 3.7 Steel Yes
2008 AVE Frontera Espanola-F rancia Rail Spain 9.5 Steel No
2008 Metro Madrid, Linea 11 Metro Spain 6.6 Steel No
2008 Tunel Oliola Irrigation Hydro Spain 3.0 Steel Yes
2008 Heathrow Airport Baggage Tunnel 2 Utility UK 5.3 Steel Yes
2009 Adelaide Desalination Hydro Australia 2.8 Steel Yes
2009 Melbourne Desalination Hydro Australia 4.5 Steel Yes
2009 Melbourne Sewer Replacement Hydro Australia 1.8 Steel No
2009 Sydney City West Cable Tunnel Utility Australia 3.2 Steel Yes
2009 Sydney Desalination Plant Tunnels Hydro Australia 3.2 Steel Yes
2009 Yellow Line, Sao Paolo Metro Brazil 8.4 Steel No
2009 Genoa Subway Metro Italy 5.4 Steel No
2009 Metropolitana di Roma, Linea C Metro Italy 7.0 Steel No
2009 Rosedale Wastewater Sewer Hydro New Zealand 3.2 Steel Yes
2009 AVE Frontera Malaga-Valencia Rail Spain 8.4 Steel No
2009 Cercanias Madrid–N avalcarnero Rail Spain 6.5 Steel No
2009 West Ham Sewer Tunnel, London Hydro UK 2.8 Steel Yes
2009 Docklands Light Railway Extension, Rail UK 5.3 Steel Yes
London
2009 Brightwater Sewer, Phase 1, Seattle Sewage USA 4.0 Steel No
2009 Copenhagen Heating Tunnel Water Denmark 4.2 Steel Yes
2009 Harefield Gas Tunnel Gas UK 2.6 Macro- Yes
PP
2010 Airport Link / North Busway, Road Australia 12.4 Steel Yes
Brisbane
Fiber reinforcement in precast concrete segments 347
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
2010 South East Collector Sewer Tunnel Sewage Canada 3.8 Steel Yes
2010 Naples Metro, Linea 6 Metro Italy 6.8 Steel No
2010 Monte Lirio–Pando–E l Aldo Tunnel Hydro Panama 3.2 Steel Yes
2010 Sabadell Road Tunnel Road Spain 6.6 Steel No
2010 East Kent Tunnel, Phase 2 Road UK 3.1 Steel No
2010 South Brighton and Hove Water Hydro UK 2.9 Steel Yes
Tunnel
2010 Brightwater Sewer, Phase 2, Seattle Sewage USA 4.0 Steel No
2010 San Francisco Bay Utility Tunnel Hydro USA 3.7 Steel Yes
2010 Fortanta–Trinitat Interconnection Water Spain 5.2 Steel No
2010 Keio Line Rail Japan 6.7 Steel No
2010 FGC Terrassa Rail Spain 6.0 Steel No
2010 Clem Jones–C lem 7 Road Australia 11.2 Steel No
2011 Legacy Way (Northern Link) Road Australia 11.3 Steel No
2011 Mill Woods Tunnel, Edmonton Sewage Canada 4.0 Steel Yes
2011 ADIF AVE Serrano, Madrid Rail Spain 11.5 Steel No
2011 Crossrail C300 West Running Rail UK 6.0 Steel Yes
Tunnels
2011 National Grid Cable Tunnels 1 Utility UK 4.4 Steel No
2011 National Grid Cable Tunnels 2 Utility UK 3.6 Steel Yes
2011 National Grid Cable Tunnels 3 Utility UK 3.6 Steel Yes
2011 Preston Storm Water Tunnel Hydro UK 2.9 Steel Yes
2011 Portland Eastside CSO Sewage USA 6.7 Steel Yes
2011 Izumi–O tsu Water Japan 1.8 Steel No
2011 Metropolitan Expressway Road Japan 13.4 Steel No
2012 Sydney City East Cable Tunnel Utility Australia 3.5 Steel Yes
2012 Metro Linea 3, Tramo 3 Metro Brazil 8.8 Steel + Yes
MPP
2012 Metro Linea 3, Tramo 7 Metro Brazil 8.8 Steel + Yes
MPP
2012 York–S padina Subway Extension, Metro Canada 6.1 Steel Yes
Toronto
2012 El Torito Hydro Hydro Costa Rica 7.4 Steel Yes
2012 Pando Hydro Project, Chiriquí Water Panama 3.0 Steel Yes
(Continued)
348 Handbook of Precast Segmental Tunnel Lining Systems
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
2012 Downtown Line 3, Contract C933 Metro Singapore 6.4 Steel Yes
2012 Metro Barcelona, Line 9 Metro Spain 12.0 Steel No
2012 Well Point Close Cable Tunnel, Utility UK 1.8 Steel Yes
2012 Blue Plains Tunnel, Washington, DC Sewage USA 7.7 Steel Yes
2012 Euclid Creek Sewer, Cleveland, OH Sewage USA 7.9 Steel Yes
2012 Midosuji Utility Utility Japan 5.1 Steel No
2012 Sagami Line Road Japan 11.8 Steel No
2013 Grosvenor Coal Mine Mining Australia 7.7 Steel Yes
2013 Santos GLNG Gas Transfer Tunnel Utility Australia 3.4 Steel Yes
2013 Bibiheybet Sewage Azerbaijan 3.3 Steel Yes
2013 Güneşli-D ernegül Sewage Azerbaijan 2.9 Steel Yes
2013 Xirdalan Sewage Azerbaijan 2.8 Steel Yes
2013 Xocahesen Sewage Azerbaijan 3.2 Steel Yes
2013 Klang Valley MRT–S BK Line Metro Malaysia 6.4 Steel + Yes
MPP
2013 Klang Valley MRT–S BK Line Metro Malaysia 6.4 Steel + Yes
MPP
2013 Waterview Connection, Auckland Road New Zealand 13.0 Steel No
2013 STEP Strategic Tunnel Program, T01 Sewage UAE 2.8 Steel No
2013 STEP Strategic Tunnel Program, T02 Sewage UAE 5.5 Steel No
2013 STEP Strategic Tunnel Program. T03 Sewage UAE 6.0 Steel No
2013 Bridlington Outfall Tunnel Sewage UK 3.6 Steel Yes
2013 Central Subway, San Francisco CA Metro USA 5.4 Steel No
2013 El Alto Water Panama 5.8 Steel Yes
2013 Asada Trunk Line Sewage Japan 4.6 Steel No
2013 Koishikawa Kasen Rail Japan 6.7 Steel No
2013 Oi-A riake Cable Tunnel Power Japan 4.0 Steel No
2014 Sydney North West Rail Link Rail Australia 6.5 Steel + No
MPP
2014 Sao Paulo Metro, Linea 6 Metro Brazil 8.4 Steel + Yes
MPP
2014 Evergreen LRT Line, Vancouver, BC Metro Canada 5.4 Steel + Yes
MPP
2014 Abu Hamour, Doha Sewage Qatar 3.7 Steel + Yes
MPP
Fiber reinforcement in precast concrete segments 349
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
2014 Green Line, Doha Metro Metro Qatar 6.2 Steel + Yes
MPP
2014 Thomson Line T206 Metro Singapore 6.4 Steel + Yes
MPP
2014 Safety Tunnel Giessbach Road Switzerland 5.1 Steel Yes
2014 Anacostia River CSO, Washington, Sewage USA 7.0 Steel Yes
DC
2014 Lee Tunnel (Tideway) Segments Sewage UK 7.2 Steel Yes
2014 Wehrhahn Tunnel Metro Germany 8.3 Steel Yes
2015 Thomson Line, Contract T206 Metro Singapore 6.4 Steel + Yes
MPP
2015 Thomson Line, Contract T207 Metro Singapore 6.4 Steel + Yes
MPP
2015 Klang Valley MRT, SBK Line Metro Malaysia 6.0 Steel + No
MPP
2015 Sao Paulo Metro, Linea 6 Metro Brazil 10.6 Steel + Yes
MPP
2015 Liantang Tunnel Road Hong Kong 14.1 Steel No
2015 Doha Metro, Red Line South Metro Qatar 6.2 Steel Yes
2015 Sanierungstunnel Belchen Road Switzerland 13.5 Steel No
2015 Farnworth Rail Tunnel Rail UK 8.0 Steel No
2015 Dugway Storage Tunnel, NEORSD, Sewage USA 7.9 Steel Yes
Cleveland
2015 First Street CSO, Washington, DC Sewage USA 6.1 Steel Yes
2015 LADWP, RSC 5 and 6 Water USA 3.1 Steel Yes
2016 Doha Metro, Red Line North Metro Qatar 6.2 Steel Yes
2016 Doha Metro Gold Line Metro Qatar 6.2 Steel Yes
2016 Hanlan Water Tunnel, Peel, Ontario Sewage Canada 3.6 Steel Yes
2016 Ohio Canal Interceptor, Akron, OH Sewage USA 9.1 Steel Yes
2016 Blacklick Creek Sanitary Sewer, Sewage USA 3.1 Steel Yes
Columbus, OH
2016 Centennial Parkway Sewer–S hafts Sewage Canada 3 to Steel Yes
8.0
2016 Quito Metro Metro Ecuador 9.1 Steel No
2016 Nice Tramway, Line 2 Metro France 9.3 Steel No
2016 Paris Metro, Line 14 (prolongation) Metro France 9.3 Steel No
(Continued)
350 Handbook of Precast Segmental Tunnel Lining Systems
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
2016 Follo Line, Oslo Rail Norway 8.8 Steel No
2016 Northern Line Extension Metro UK 5.3 Steel Yes
2016 Shieldhall Sewer Tunnel Sewage UK 5.2 Steel No
2017 Klang Valley MRT, SSP Line Metro Malaysia 5.8 Steel + No
MPP
2017 Kasai Bashi TEPCO Cable Tunnel Metro Japan 6.0 Steel + No
MPP
2017 Thames Tideway West Tunnel Sewage UK 6.6 Steel Yes
2017 Ottawa CSST, Ottawa, Ontario Sewage Canada 3.7 Steel Yes
2017 South Hartford CSO, Hartford Sewage USA 6.1 Steel Yes
2017 Expolink 2020, Dubai, UAE Metro Dubai 8.5 Steel Yes
2017 CMC Catania Tunnel Metro Italy 9.6 Steel No
2017 Forrestfield Airport Link Rail Australia 7.0 Steel No
2018 Kemano T2 Tunnel, Kitmat, British Hydro Canada 6.5 Steel Yes
Columbia
2018 3R Port, Fort Wayne, IN Sewage USA 5.8 Steel Yes
2018 CBBT–Parallel Thimble Shoals Tunnel Road USA 12.8 Steel Yes
2018 Mumbai Metro, Line 3–H CC Metro India 6.7 Steel No
2018 Thames Tideway East Sewage UK 7.8 Steel + Yes
MPP
2018 Circle Line 6, Lot C882 Metro Singapore 6.7 Steel + Yes
MPP
2018 Circle Line 6, Lot C885 Metro Singapore 6.7 Steel + Yes
MPP
2018 North East Line Extension, Lot C715 Metro Singapore 8.3 Steel + Yes
MPP
2018 Deep Tunnel Sewer System 2, Lot Sewage Singapore 6.0 Steel Yes
T07
2019 Roma Metro, Linea C Metro Italy 6.7 Steel Yes
2019 Sydney Metro Tunnel Metro Australia 6.5 Steel No
2019 Doan Valley NEORSD CSO, Sewage USA 7.9 Steel Yes
Cleveland
2019 Tideway West / Frogmore Street Sewage UK 4.0 Steel Yes
Tunnel
2019 Blacksnake CSO, St. Joseph, Missouri Sewage USA 2.7 Macro Yes
PP
2019 Silicon Valley Clean Water, Palo Alto, Sewage USA 4.8 Steel Yes
CA
Fiber reinforcement in precast concrete segments 351
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
2019 Westerly Storage Tunnel Sewage USA 7.6 Steel Yes
2020 Cowell Bypass Tunnel Sewage Canada 6.3 Steel Yes
2020 Ashbridges Bay Outfall Tunnel, Sewage Canada 7.0 Steel Yes
Toronto
2022 Réseau Express Métro (REM), Metro Canada 7.4 Steel + Yes
Montréal MPP
2020 I-7 5 Modernization Tunnel Sewage USA 4.4 Steel Yes
2020 Bergen Point Outfall Replacement Sewage USA 3.8 Steel Yes
Tunnel
2020 Second Narrows Tunnel, Vancouver Hydro Canada 6.5 Steel Yes
2020 Grande Paris Metro–L ine 16-1 Metro France 8.7 Steel Yes
2021 Hampton Roads Tunnel, Norfolk, VA Road USA 14.0 Steel No
2021 JWPCP LA Outfall Tunnel, Los Sewage USA 6.5 Steel + No
Angeles, CA PT
2021 Annacis Island Phase 1 Tunnel, Water USA 4.2 Steel Yes
Vancouver, BC
2022 Scarborough Subway Tunnel, Metro Canada 11.9 Steel + Yes
Toronto, Ontario MPP
2022 Eglinton Subway Tunnel, Toronto, Metro Canada 6.6 Steel + Yes
Ontario MPP
2022 Fairbanks Silverthorn Tunnel, Sewage Canada 4.5 Steel Yes
Toronto, Ontario
2022 Broadway Subway Tunnel, Vancouver Metro Canada 6.0 Steel + Yes
BC MPP
2022 Pawtucket CSO, Pawtucket, RI Sewage USA 9.1 Steel Yes
2022 Ship Canal Tunnel, Seattle, WA Sewage USA 5.7 Steel Yes
2022 AlexRenew Tunnel, Alexandria, VA Sewage USA 4.5 Steel Yes
2022 Lower Olentangy Tunnel, Columbus, Sewage USA 3.7 Steel Yes
OH
2022 Shoreline Storage Tunnel, Cleveland, Sewage USA 7.9 Steel Yes
OH
2022 Snowy Hydro, Cooma, NSW Hydro Australia 10.6 Steel No
2022 Metro New Airport Link, Sydney Metro Australia 6.6 Steel Yes
2022 West Gate Tunnel, Melbourne, Road Australia 16.6 Steel Yes
Victoria
2022 Cross River Rail Twin Tunnels, Metro Australia 6.6 Steel Yes
Brisbane
(Continued)
352 Handbook of Precast Segmental Tunnel Lining Systems
Fibers
Dia.
Year Tunnel or project name Type Country (m) Type(s) Only
2022 Thomson East Coast Line T-3 16, Metro Singapore 5.8 Steel + Yes
Singapore MPP
2022 Cross Island Phase 1, Contract Metro Singapore 6.3 Steel + Yes
CR109 MPP
2022 Cross Island Phase 1, Contracts Metro Singapore 6.3 Steel + Yes
CR115 & CR116 MPP
2022 Tuas Water Reclamation Plant to Water Singapore 6.0 Steel Yes
Jurong Island
2023 Metro Western Package, Sydney Metro Australia 6.6 Steel Yes
2023 Metro Central Package, Sydney Metro Australia 6.6 Steel Yes
2023 Metro Eastern Package, Sydney Metro Australia 6.6 Steel Yes
2023 North-E ast Link, Melbourne Road Australia 16.6 Steel Yes
2023 Integrated Pipeline Tunnel Section Sewage USA 3.5 Steel Yes
19, Dallas, TX
tunnel was built, name of the tunnel, type or function of the tunnel and the country where
the tunnel is located. Further, the fiber type(s) used in the segments are shown as fol-
lows: “Steel”, indicating steel fibers were used as primary reinforcement; “Steel +MPP”,
indicating steel fibers were used as the primary reinforcement and micro-polypropylene
fibers were added for passive fire protection; and “macro-PP”, indicating a higher per-
formance macro-synthetic polypropylene fiber was used as primary reinforcement. The
last column indicates if the segment was reinforced with fibers only (fibers only? =Yes), or
used with conventional reinforcing steel bars or welded wire mesh as a combined solution
(fibers only? =No).
BIBLIOGRAPHY
For preparation of this chapter, the following references were used, which are grouped into three cat-
egories of published codes, industry guidelines and technical publications.
PUBLISHED CODES
ACI Committee 533. (2020). ACI 533.5R- 20: Guide for Precast Concrete Tunnel Segments.
Farmington Hills, MI: American Concrete Institute.
ACI Committee 544. (2016). ACI 544.7R-16: Report on Design and Construction of Fiber-Reinforced
Precast Concrete Tunnel Segments. Farmington Hills, MI: American Concrete Institute.
ACI Committee 544. (2017). ACI 544.2R-17: Report on the Measurement of Fresh State Properties
and Fiber Dispersion of Fiber-Reinforced Concrete. Farmington Hills, MI: American Concrete
Institute.
ACI Committee 544. (2017). ACI 544.9R-17: Report on Measuring Mechanical Properties of Hardened
Fiber-Reinforced Concrete. Farmington Hills, MI 48331: American Concrete Institute.
Fiber reinforcement in precast concrete segments 353
ACI Committee 544. (2018). ACI 544.4R-18: Guide to Design with Fiber-Reinforced Concrete.
Farmington Hills, MI.: American Concrete Institute.
ASTM C09.42 Subcomittee on Fiber-Reinforced Concrete. (2020). ASTM C1609 /C1609M–19a–
Standard Test Method for Flexural Performance of Fiber-Reinforced Concrete (Using Beam
With Third-Point Loading). West Conshohocken, PA,: ASTM International.
ASTM A820 /A820M–16–Standard Specification for Steel Fibers for Fiber-Reinforced Concrete.
ASTM International.
ASTM C1609 /C1609M–19a–Standard Test Method for Flexural Performance of Fiber-Reinforced
Concrete (Using Beam With Third-Point Loading). ASTM International.
British Standards Institute. (2008). BS EN 14651:2005–Test Method for Metallic Fibre Concrete–
Measuring the Flexural Tensile Strength (Limit of Proportionality (LOP), residual) (+A1:2007).
London: British Standards Institution.
British Standards Institute. (2006). BS EN 14889-1:2006–Fibres for Concrete. Steel fibres. Definitions,
Specifications and Conformity. London: British Standards Institution.
ISO/TC 17/SC 17 Steel Wire Rod and Wire Products. (2013). ISO 13270:2013–Steel Fibres for
Concrete –Definitions and Specifications. Geneva, Switzerland: ISO, the International
Organization for Standardization.
INDUSTRY GUIDELINES
National Precast Concrete Association (NPCA). (20 Jan 20). NPCA Quality Control Manual For
Precast Concrete Plantsm, 14th Edition. Carmel, IN USA 46032: National Precast Concrete
Association (NPCA).
Precast/Prestressed Concrete Institute. (1999). MNL-116-99: Manual for Quality Control for Plants
and Production of Structural Precast Concrete Products, 4th Edition. Chicago, IL, USA: Precast/
Prestressed Concrete Institute.
TECHNICAL PUBLICATIONS
Allen, C. (October 2009). Fibre Decider; Tunnels and Tunnelling International. pp. 35–37.
Allen, C.. (November 2021). Low Carbon Concrete for Shafts and Tunnel Linings–Rule of Thumb.
Tunnels & Tunnelling–The Official Magazine of the British Tunnelling Society, pp. 28–33.
Bakhshi, M. (2015). Design of Segmental Tunnel Lining for Serviceability Limit State, AASHTO
SCOBS T- 20: Technical Committee for Tunnels April 2015 Meeting. Saratoga Springs,
New York.
Bakhshi, M., and Nasri, V. (2017). Water Infiltration and Crack Control for Tunnel Concrete Lining.
Proceedings of the World Tunnel Congress 2017–Surface Challenges–Underground Solutions
(pp. 1–10). Bergen, Norway: ITA–AITES.
Bekaert-Maccaferri Underground Solutions. (2018). Info Sheet: What About Stray Currents With
Steel-Fibre Reinforced Concrete. Ghent, Belgium: Bekaert-Maccaferri Underground Solutions.
Bischoff, Jean Luc, Benoit de Rivaz, Dieter Hansel, and Roland Herr. (February 2022). Steel-Fibre-
Reinforced Segments Improve Carbon Footprint. Tunnel–Official Journal of STUVA, No. 02/
2022.
de Rivaz, Benoit. (2016). Design Approach Assisted by Test. Ghent, Belgium: Bekaert-Maccaferri
Undergound Solutions.
de Rivaz, Benoit. (2019). Characteristics of Steel and Polymer Based Fibre Concrete. Zwevegem,
Belgium: NV Bekaert SA.
de Rivaz, Benoit. (2020). Tunneling Applications: Concrete Segment Reinforcement. Zwevegem: NV
Bekaert SA.
de Rivaz, Benoit. (2022). Low Carbon Tunnel and Shaft Linings–White Paper. Zvergem, Belgium:
Bekaert.
354 Handbook of Precast Segmental Tunnel Lining Systems
de Rivaz, Benoit. (March 2022). Moving to Low-Carbon Linings. Tunnels & Tunnelling International,
the official magazine of the British Tunnelling Society, pp. 40–44.
di Prisco, M., Colombo, M., and Dozio, D. (2014). Fibre-Reinforced Concrete in fib Model Code 2010;
Principles, Models and Test Validation. Structural Concrete 14 (2013), No. 4, pp. 342–361.
Edvardsen, C. (October 2010). The Consultant's View on Service Life Design. 2nd International
Symposium on Service Life Design for Infrastructure (pp. 249– 264). Delft, The
Netherlands: RILEM– International Union of Laboratories and Experts in Construction
Materials, Systems and Structures.
fib Special Activity Group 5. (2010). Bulletin 55- 56: Model Code 2010–First Complete Draft.
Lausanne: International Federation for Structural Concrete (fib).
fib Working Party 1.4.1 Tunnels in Fibre-Reinforced Concrete. (2017). fib Bulletin 83 Precast Tunnel
Segments in Fibre-Reinforced Concrete State-of-the-Art Report. (A. Meda, Editor) Lausanne,
Switzerland: Fédération International du Béton (fib).
Gerhard Vitt. (2011). Understanding Steel Fibre Reinforced Concrete: Dramix (Version 1.0 ed.).
Zwevegem, Belgium: NV Bekaert SA.
ITA Working Group 2– Research; Bakhshi, M., Nasri, V., Main Authors. (April 2019). ITA
Report No.22–Guidelines for the Design of Segmental Tunnel Linings. Longrine, Avignon,
France: AITES/ITA.
ITA Working Group 2–Research; Tiberti, G., Chiniottri, E., Pizzari, G., Main Authors. (April 2016).
ITA Report No 16– Twenty Years of FRC Tunnel Segments Practice: Lessons Learnt and
Proposed Design Principals, Avignon, France: AITES/ITA.
ITAtech Activity Group Support. (2016). ITAtech Report No.7; ITAtech Guidance for Precast Fibre
Reinforced Concrete Segments–Volume 1: Design Aspects. Longrine: International Tunnelling
and Underground Space Association.
ITAtech Activity Group Support. (2018). ITAtech Report No.9: Guideline for Good Practice of
Fibre Reinforced Precast Segment–Volume 2: Production Aspects. Longrine: The International
Tunnelling and Underground Space Association.
Jarast, P., Bakhshi, M., and Nasri, V. (2023), Carbon Footprint Reduction in Montreal Blue Line
Extension: RETC Proceedings (pp. 580–588). SME.
Latson, J. (22 June 15). The Burning River That Sparked a Revolution. Retrieved from Time.
Com: https://time.com/3921976/cuyahoga-fire/
Meda, A., and Rinaldi, Z. (2015). Tests on Precast Tunnel Segment in Concrete Newly High
Tensile Strength Steel Fibers Dramix 4D 80/60BG. University of Rome "Tor Vergata", Civil
Engineering. Rome: TERC–Tunnelling Engineering Research Center.
Meda, A., and Rinaldi, Z. (July 2017). Beam Tests on Fiber Reinforced Concrete According to EN
14651 and ASTM C1609. Rome, Italy: University of Rome–Tor Vergata.
Meda, A., Rinaldi, Z., Spagnuolo, de Rivaz, B., and Giamundo, N. (January 2019). Hybrid Precast
Tunnel Segments in Fiber-Reinforced Concrete with Glass Fiber Reinforced Bars. Tunnelling
and Underground space Technology 86, pp. 100–112.
Meson, V. M. (2019). Durability of Steel Fibre Reinforced Concrete in Corrosive Environments–Ph.D.
Thesis. Kongens Lyngby, Denmark: Department of Civil Engineering, Technical University of
Denmark.
NV Bekaert SA. (June 2021). Environmental Product Declaration Type III ITB No. 215/2021.
Zwevegem, Belgium: Bekaert.
Pascal Guedon (Arcadis) Working Group Leader. (Juillet/Août 2013). Recommendation of AFTES
No.GT38R1A1–Design, Dimensioning and Execution of Precast Steel Fibre Reinforced
Concrete Arch Segments. Tunnels et Espace Souterrain–No. 238, pp. 312–324.
Rack, J. (20 August 14). A Brief History of Sustainability. Retrieved from The World Energy
Foundation: https://theworldenergyfoundation.org/a-brief-history-of-sustainability/
Rossi, P. C.-P. (18 April 16). SFRC Durability in a Chlorinated Environment. Tunnel Talk (Direct by
Design), pp. 2.
Fiber reinforcement in precast concrete segments 355
Scaffidi, S.C., Salini Impregilo S.p.A., Milano, Italy, Anders, A., Porto, S., and Torres, E., SI-NRW JV,
Redcliffe, Perth, Western Australia, Forrestfield Airport Link Project, Perth, Western Australia;
Precast Concrete Segmental Lining, 2019. ITA-AITES World Tunnel Congress, Naples, Italy.
Tang, K. (March 2020). Corrosion of Steel Fiber Subjected to Stray Current Interference. ACI
Materials Journal, pp. 99–112.
Tunnel Talk Reporting. (25 April 19). TunnelTech: First Use of Macro-Synthetic Fiber Reinforced
Concrete in Segments in the USA. TunnelTalk.
TunnelTalk Reporting. (March 2015). TunnelTech: Lab Comparison of Steel vs. Synthetic FRC
SegmentsTests and Results; by University of Rome Tor Vergaata. TunnelTalk.
United States Environmental Protection Agency, U. S. (17 September 20). Learn about Sustainability.
Retrieved from EPA.Gov: www.epa.gov/sustainability/learn-about-sustainability
United States National Aeronautics and Space Administration (NASA). (30 September 20). Global
Warming. Retrieved from Earth Observatory NASA: https://earthobservatory.nasa.gov/featu
res/GlobalWarming/page1.php
Vandewalle, M. (2005). Tunnelling is an Art. Zwevegem, Belgium: NV Bekaert SA.
Wallis, Shani. (April 2022). A Leap Forward for SFRC Segmental Linings in France. Tunnel Talk,
pp. 1–8.
Chapter 6
6.1 INTRODUCTION
In the early stage of tunneling, there were no segmental linings but only masonry and the
lining was made of hand-placed bricks and mortar. The first segments used were not made
of concrete but cast iron. The ring was divided into several small segments in order that
these small pieces could be handled manually, as at this time, tunnels were not mechanically
excavated.
The first concrete segments were produced for tunnel projects in London, England
as described in Chapter 1. At this early stage of concrete segmental linings, their shape
was similar to the cast iron segments. Connections between rings and segments were
basic: standard straight bolts and nuts were used to connect these segments (similar to cast
iron segments). This type of segment was used up to the end of the 1960s.
The next evolution of the segment design started in the middle of the 1960s. At this time
several major developments occurred for the tunneling industry including the development
of tunnel boring machines (TBMs) in soft ground conditions. New mechanical erectors were
also developed, offering a high accuracy in the ring build. From a precasting point of view,
the first sealing gaskets were used in Hamburg on the third Rohrelbe Tunnel, which started
in 1969.
From this time, there have been two kinds of connections as shown below in Figure 6.1: the
connections in the circumferential joint, to connect one ring to the next. The other connec-
tion within a ring is in the radial joint (also known as longitudinal joint), from one segment
to another segment. Their purpose is not the same and the systems used in both joints can
be different one from each other.
6.2 CONNECTING BOLTS
Straight bolts with highly engineered plastic sockets, usually made of polyamide or acrylo-
nitrile butadiene styrene (ABS), are commonly used throughout the world today. It was not
always the case, and initially some basic systems such as curved bolts (also named “banana
bolts”) were used on projects designed by British engineers and were prevalent in Asia.
This curved bolt system was not highly engineered but accomplished its main purpose,
which was to keep the segments in-place and the gasket compressed. One of the main weak-
nesses of this system is that it requires more openings in the segment (one in each segment to
be linked) and that the installed bolt are subject to corrosion at two locations (on the head
and in the thread or nut). If this type of connection would be used for a water conveyance
system, it would also require many pockets to be filled as each pocket may create minute
turbulences for the water.
DOI: 10.1201/9781032675541-6
Connections and accessories for segmental tunnel linings 357
In the early 1980s, the first straight bolts with plastic sockets were used in Europe. These
sockets were not specifically designed for the tunnel industry, indeed in France or Germany,
steel bolts with plastic sockets from the railway industry, designed for the concrete sleepers,
were used. These sockets were usually produced out of high-density polyethylene (HDPE)
and the bolts used were spike screws with a sharp thread. Properties of the plastic were also
studied, and it was demonstrated that the HDPE is not the proper material for a tunnel bolt-
ing system. Indeed, the HDPE socket creeps under sustained load and is not capable to hold
the load and thus does not provide sufficient safety factor to keep the gasket compressed.
This creep leads to release or relaxation of the gasket pressure once the TBM rams are
removed and before the installation of the next segment.
In a later stage, at the beginning of the 90s, bolting systems were specifically designed
for the tunnel industry. The thread design was different and developed with roll-formed
threads (round shape). The sockets were produced out of newer material such as polyamide
or acrylonitrile butadiene styrene (ABS), providing higher resistance than HDPE, which are
also not subject to creep.
Now that the force can be held, the bolting system can also be better designed. The reac-
tion load from the compressed gasket results in tension within the bolting system and the
system should be able to withstand this load (Figure 6.2).
The tightening of the bolt can be controlled with sufficient applied torque. Indeed, the
force exerted by the bolting system can be well established thanks to the relation between the
torque and the tensile strength (according to the AFNOR Norme NF E25-030, Fasteners–
Threaded Connections with ISO Metric Thread–Part 1: Design Rules for Tensile Loaded
Bolted Joints–Simplified Procedure, Figure 6.3).
where
T =torques applied
F =tensile force exerted by the bolting system
P =pitch of the bolt thread
358 Handbook of Precast Segmental Tunnel Lining Systems
µ =mean friction coefficient under the bolt head and in the bolt thread
D2 =diameter on the flank thread
rm =mean radius of the bearing surface under the bolt head
Bolting systems now exist with various diameters and lengths so it can be used on any pro-
ject and with any requirements:
• With narrow segments, using bolting systems with a small diameter [19 mm (0.75”)]
and short socket [100mm (3.93”)]
• For standard transportation projects, with bolting systems the standard diameter is
25 mm (1.0”) and with sockets from 80 up to 160 mm (1.15 to 6.3”)
• For large diameter projects, with larger diameter bolting systems to provide higher
resistance [up to 400 kN (45 tons)].
Connections with straight bolts and plastic sockets require less effort in the construction of
the formwork than the curved bolts because it is necessary to create only one pocket and
groove into which the bolts are inserted. This type of connection is traditionally associated
with rectangular segments and is generally used both between rings and between segments
within a ring. Figure 6.4 shows the typical housing of a straight bolt. Attention should be
paid to the following geometrical details:
• Pockets should be large enough for head of the bolt and pneumatic wrench to be
easily inserted.
• The slot side of the pocket should have a conicity of at least 1° for ease of mold
release.
• The bolt slot in the segment that houses the plastic socket should also have a compat-
ible conicity.
• The bolt axis should pass through the center of the segment.
• The distance between the end part of the plastic socket and the extrados of the seg-
ment should be sufficient to prevent concrete cracking
The stainless steel is of course an option, but several zinc institutes have made studies of
the rate of corrosion depending on the environment to which the material is exposed.
See Figures 6.5(a) and (b) from Galvazinc (French Zinc Institute), which describes the
rate of corrosion zinc coating applied to steel by hot-dip galvanizing (HDG) depending
on the environment (according to ISO 14713-1:2017; “Zinc Coatings –Guidelines and
Recommendations for the Protection Against Corrosion of Iron and Steel in Structures –
Part 1: General Principles of Design and Corrosion Resistance”).
The sockets are usually made of plastic but in certain projects, and for specific applica-
tions; stainless steel sockets may be used. For example, temporary bolts are always removed
from projects of Deutsche Bahn but at the same time they always design their projects in
keeping the first and last rings being connected with stainless steel bolting systems (bolt and
socket). This solution ensures that the first (and last) rings remain under compression, mak-
ing like two stoppers and also preventing the other rings to decompress. Permanent bolting
system may also be required next to any niche or opening in the tunnel.
dowels only connect one ring to the next one. Dowels have been used in many tunnel
projects and now a large variety of dowel systems exists on the market. Historically,
the first dowels were used in Switzerland and at that period of time they were made of
wood. In that time, segments did not include any gaskets and for this reason, the main
purpose of these dowels was the centering (installation alignment) of the precast concrete
elements.
After this initial period, the first dowels were developed for the connection of the rings
with the approach of keeping the gasket under compression. These first dowels were usu-
ally made of steel, like the “Fast Lock Dowel” system developed by Sehulster Tunnels in
the United States as described in Chapter 1. In follow-up developments, the dowels were
made of plastic such as “Bucklock Sof-Clip” couplers and the Conex Dowel (developed by
Schulter and Wagner, D2 Consult, Linz, Austria) that was made of wood. The dowels could
either be a friction dowel, or a mechanical dowel.
The friction dowel is a dowel designed with a slightly smaller diameter than the receiving
concrete socket in the precast segment. The dowel is engaged by force in the concrete
element in using the TBM thrust jacks. The Conex Dowel and “Bucklock Sof-Clip” were
the type of dowel predominantly used with this concept.
The mechanical dowel is slightly different as it is composed of a male and two female
parts. The female parts, also named sockets are cast in the circumferential joint of the seg-
ments. This type of dowel allows having higher performance in pull-out resistance since
the sockets are designed to perfectly engage the dowel. Please refer to the illustrations in
Figures 6.6 and 6.7 for the friction and mechanical dowels.
The expansion of the usage of the dowels started at the end of the 1980s. Initially
the dowels were mainly used for sewer or water conveyance one-pass lining projects
under 4.0 m (13.0 feet) in diameter. This was for at least two reasons; the dowels were
not strong enough for larger diameter tunnels including transportation tunnels but also
because the usage of dowels eliminates the pockets in the segments. It has many advan-
tages for this type of project, in providing a better durability for the connection and
keeping a smooth intrados. Figure 6.8 below shows finished tunnel lining using only
dowels and guide rods.
362 Handbook of Precast Segmental Tunnel Lining Systems
• Mechanical dowels to connect one ring to another one to replace the bolting system,
they are used in every circumferential joint
• Shear dowels (or bicone), which are used to strengthen the ring at special locations
and for special application (cross-passages, for example)
6.3.1 Mechanical dowels
With this significant evolution, dowels are designed not only for alignment but also for their
mechanical properties in pull-out and shear resistance. The pull-out resistance should be
designed to meet the reaction load of the gasket and the shear resistance to withstand the
weight of the segment.
The main advantages of the dowel systems are the following:
• Shear resistance
Dowels are typically made of thermoplastic and can have a steel core center if required
by design. This steel core helps the dowels to have a high shear resistance. Compared
to the design of the bolting system, where bolts are engaged in a tapered channel with
a gap between bolt and concrete, the dowels have a significant advantage, as they
neatly fit 1-to-1 in the sockets. It means that the shear resistance is directly mobilized
to the dowel without significant displacement.
• Pull-out resistance
The dowels are designed to achieve high pull-out resistance with a minimum of dis-
placement and this to keep the gasket under compression. Their design has evolved
with the time. The first dowel systems had two similar sockets with the dowel pushed
in. Please refer to Figures 6.9 and 6.10 below. The last evolution is the usage of asym-
metrical dowel system, with one side screwed- in and the other side pushed- in.
The screwed-in side is usually placed on the trailing edge and the pushed-in side on
the leading edge of the segment. Some designers and contractors still prefer to have a
symmetrical dowel system with both sides being pushed in.
• Speed of installation and safety
Joints with dowels require less work for the construction of the formwork and less
manpower in the tunnel for the insertion into segments. Indeed, compared to bolting
system, as it is a self-locking system, it does not require any human intervention. It
also makes the dowel system a safer system, as it does not require any worker to be
under the segment (for the bolt insertion).
Figure 6.11 shows the typical housing of a dowel, which is placed along the cen
terline of the segment. This is a further advantage as the reaction load of the gasket
is parallel to the pull-out force of the dowel. In most cases, the dowel connections
are used with rhomboidal and trapezoidal segments (but it can also be used with
rectangular segments) to avoid early crawling of the gaskets during the segments-
approach phase of the ring assembly.
Figure 6.12 shows a segment formwork circumferential face with a socket for dowel
insertion. As there is no pocket, like for the bolting system, the reinforcement has con-
tinuity and is also easier to design.
6.3.2 Bicones
Bicones as illustrated in Figure 6.13 are also named shear dowels as their primary function
is to take high shear loads, but this type of dowel system can be used for two purposes:
366 Handbook of Precast Segmental Tunnel Lining Systems
Compared to the mechanical dowel system, this system, which is designed only to take shear
load, is a single dowel without sockets embedded in the concrete. The bicones are engaged
in a designated concrete socket and depending on the primary usage, they may be glued
or not.
The combination of an alignment dowel together with a bolting system has been mainly
used on challenging projects with high water pressure or large diameter tunnels. The
Hallandsås Tunnel in Sweden, for example is one of them. This rail tunnel was very challen-
ging due to the high pressure [up to 15 bar (218 psi)] and high amount of water present in
the ground. In order to build this tunnel, segments with a very wide gasket [44mm (1.75”)],
inducing a high reaction load, were used. Because of this gasket and the resulting reaction
Connections and accessories for segmental tunnel linings 367
load, it was decided to use bolting systems in the radial (longitudinal) joint and the circum-
ferential joint. In order to minimize the steps and lips, and consequently improve the per-
formance of the gasket, it was decided to use bicone as alignment dowels between each ring.
The performance of this type of shear dowel was satisfactory to the joint venture and
some contractors started to look at this type of dowel for a different application. As this
type of bicone can produce significant shear resistance (up to 500 kN or 56 tons), their
usage was developed not only for alignment but also for specific areas like cross-passages
(see Section 6.8).
6.4 GUIDE RODS
The guide rods can only be used in the radial (longitudinal) joint. The guide rods are made
of plastic; their diameter may vary from 30 mm for the thin segments up to 80 mm for the
very thick segments. Lengths can vary but typically covers approximately two thirds of the
ring width. They can be used as a single connection in the radial (longitudinal) joint or in
conjunction with one or two bolts. They are fixed in a groove on one side of the segment
and the other side of the segment should be designed with a continuous groove to engage
and receive this rod. An example is shown in Figure 6.14.
As stated by the name, the main function of the guide rod is to provide guidance to the
segment during segment installation, but they also have a locking functionality. Guide rods
absorb shear forces in the longitudinal joints (ÖVBB 2011). An advantage of using guiding
rods is that, in the longitudinal joints, inserted longitudinal guiding rods can prevent the
segments slipping away from each other during ring building [DAUB Recommendations for
the Design, Production and Installation of Segmental Rings (2013)]. Guiding rods can be
used in conjunction with any connection system in the circumferential joint but when they
are adopted in conjunction with dowel connection systems, they result in a smooth ring-to-
ring contact.
the gasket glue is not required anymore at the segment precast factory. The precasters were
looking for a solution to anchor the guiding rod without glue.
A new fixation system with studs has been developed as shown in Figures 6.15, 6.16 and
6.17. In order to use the studs, the guiding rods are drilled. The studs are anchored at the
precast factory. Once the segment produced, only two small portions of the studs remain
Connections and accessories for segmental tunnel linings 369
exposed outside of the concrete. The guide rods are easily engaged on the studs to hold it.
This fixation is mechanical, durable, and not sensitive to weather alteration and with health
and safety benefits for the workers (e.g. not exposed to solvent).
6.5.1 Mechanical erector
Historically, first segments used to be installed by a mechanical erector. A socket installed
in the center of the segment together with a screwed in-place lifting device were used for
this operation. The sockets were first made of steel and over the time the usage of plastic
grout-lift socket has been developed. The plastic material made these sockets more durable
but also lighter and easier to install in the formwork.
The connection between the erector arm and the segment is made by the means of a lift-
ing pin. This lifting pin is designed by the TBM and accessories manufacturers. Indeed, its
head should be made to suit the design of the erector, while its thread should perfectly match
the thread of the socket. There are different types of sockets used by the industry, including
single or triple thread style. The triple style thread has an advantage that the lifting pin can
be quickly engaged in the socket (one turn is three threads down). But on the other hand,
when you unscrew it by 1/3 of a turn, the lifting pin loses one full thread in the socket.
Because it is used for lifting purpose and is also a safety tool, some tunnel designers prefer
to use a single thread style.
Using the vacuum lifter, the central socket now has only one single use: grouting. The
style of the sockets also evolved with this evolution in making the sockets lighter, designed
only for this purpose and sometime shorter. Indeed, they could be shorter as they are from
time-to-time combined with designated vacuum erector concrete pockets. With this config-
uration, the grouting socket is placed on the vacuum erector pocket, making the installation
of the screw cap more difficult. But at the same time, this configuration reduces the number
of openings in the segment and facilitates the design of the reinforcement.
Another major change has been the development of backfill grouting through the tail
shield of the TBM. After this evolution, the grout socket (if any are used) is only needed for
secondary and/or proof grouting.
The packers can be self-adhesive or glued in-place with similar glue as used for gaskets.
They are always installed just after stripping and before storage of the segments. The com-
pressed thickness of the packers should always be considered at the design stage. Indeed,
if dowels are used in the circumferential joints, this additional thickness or space between
the rings may have an influence on how the dowels engage and will have negative impact
on gasket performance if not considered during the design. To ensure that the dowel system
always performs properly, the distance between the two dowel sockets should never vary
even if the distance between the concrete faces evolves. The position of the socket in the
formwork should take into consideration this parameter in reducing the installation depth
of the socket by half of the compressed thickness of the packers.
It is of note that on some projects, packers may also be used in the radial (longitu-
dinal) joint.
Please add sample test results for bolts and dowels. For example, for dowels show sample
pullout and shear test.
concrete with the proper reinforcement should be organized by the contractor, as each con-
crete is different and can lead to different results. Figures 6.22, 6.23 and 6.24 show a pull-
out test on grout-lifting socket embedded in a concrete segment.
If the socket is used for grouting purpose, the main concern is the watertightness of the
screw cap after its installation in the socket. Like the gasket, the screw cap will be exposed
to the water pressure during the lifetime of the tunnel. For this reason, a durable material
for the screw cap and its O-ring should be used: polyethylene or polypropylene for example
for the screw cap and an EPDM base material for the O-ring. In the same manner for the
gasket, and due to the aging of the material, it is suggested to test the screw cap for 20 hours
and with a factor of safety of 2.0 against the maximum water pressure as per, “STUVA
Praxis 54 Recommendations for Gasket Frames in Segmental Tunnel Linings”.
More recently, the usage of high-strength shear cones has been first introduced success-
fully to the A86 Duplex Project in Paris, tunnel built by Vinci Grands Projets; they have
been quickly adopted on other projects around the world. The concept is to develop and
use a shear cone having similar resistance than the concrete lining itself, if the bicone would
376 Handbook of Precast Segmental Tunnel Lining Systems
be too stiff, it may induce failure of the concrete at an early stage, and if the bicone is too
weak, it cannot provide the adequate stiffness to the lining. For this reason, several bicones
with various resistances, stiffness and designs have been developed to cover different project
requirements (see Figure 6.25).
Connections and accessories for segmental tunnel linings 377
The sequence for the ring installation would be the following (see Figure 6.29):
• Installation of the first segment with tie-rod engaged and tighten in the end bicone or
end cone (half bicone)
• After excavation of the next drift (one ring), retraction of the TBM thrust jacks
• Tightening of the bicone on the ring already installed with tie-rod
• Tie-rod of the segment to be erected should be engaged in the bicone manually and
then the segment installed
• The tie-rod is then tightened with the special tightening tool
Connections and accessories for segmental tunnel linings 379
made of new material such as composite plastic, providing high resistance and durability.
The aim of this new radial (longitudinal) system is to secure the two segments and prevent
them from their opening. Two Omegas are cast in the segments while a “dowel” is making
the connection between the segments. The shape of this pin can be adjusted to the gasket
to have a full gasket compression only when the system is fully closed. This kind of new
technology allows for the use of boltless segments for tunnel linings subject to high internal
pressure.
Segments are usually connected radially (longitudinally) with bolting systems, and guide
rods may also be used to ensure a good alignment of the segment. For the circumferential
joint, the rings are connected by means of tie rods that can apply a post-tensioning on the
ring to ensure the gasket compression. These tie-rods are usually combined with dowels that
ensure the alignment of the segments.
Depending on the type of shafts, the bolts to connect the segments in the radial (longitu-
dinal) joint can be tightened from the extrados (jacking or Herrenknecht VSM technology)
or from the intrados (underpinning technology).
tear-off the membrane from the concrete. The membrane had an opening for the grout lift
socket and this opening was patched over on-site, at the same time the circumferential and
radial (longitudinal) joints were welded with electric heat guns. Figure 6.36 shows a seg
ment with a cast-in PVC lining.
For the IDRIS Project (Inner Doha Resewage Implementation Strategy), Bouygues imple-
mented the same concept with an additional development. To prevent the patching of the
grout-lift socket openings on site, the grout-lift socket was fixed to the membrane by the
mean of an adaptor welded to the membrane. For this reason, the socket was made of two
elements:
• The adaptor with an inner thread, which was welded to the membrane
• The socket with an outer thread, which is screwed-on the adaptor after welding and
prior to concrete placing
In order to ensure a perfect repetitiveness and a sealing, a special welding machine was
developed to weld this adaptor to the membrane. This operation was performed at the pre-
cast fabrication plant.
The implementation of this solution was not only possible because the adaptor and mem-
brane are made of a similar material (for welding purposes), but also because the screw caps
are made of similar material as the membrane and provide the same chemical resistance to
hydrogen sulfide gas (H2S). Figures 6.37 to 6.39 show examples of the welding station, as
well as a segment with HDPE segment.
often used to support components of railway overhead catenary systems as well as both
temporary and permanent mechanical and electrical equipment of road and utility tunnels.
Additional applications of fastening systems include supporting intermediate slabs, corbels,
cross-passage doors and platform screen doors.
386 Handbook of Precast Segmental Tunnel Lining Systems
Figure 6.44 Embedded fastening systems including threaded inserts and cast-in channels.
Note: No dust creation conditions and, therefore, no dust control measures needed.
health hazards are related to noise and vibration. These hazardous effects can be reduced
with embedded fastening systems also.
(preferably I-anchors) that are placed in segment forms before casting concrete. Such sys-
tems provide efficient, flexible and safe methods of fastening without drilling while signifi-
cantly improves the installation quality. Some key advantages of this system are the increase
in connection adjustability, allowance for more flexibility in the construction schedule,
increased service life, can be used for temporary installations during construction, allow-
ance for accurate planning due to reliable assembly times and reduction of overall construc-
tion schedule due to reduced installation time. These installations can also be structurally
integrated with segment reinforcing elements.
Cast-in-place systems also have lower maintenance cost, lead to much easier quality con-
trol, both in precast plants and before ring assembly and provide more favorable point load
properties. Note that definitive preliminary planning efforts are needed for all cast-in chan-
nel systems, namely preparation of installation drawings for segmental lining (Figure 6.50),
as well as effects on ring construction logistics that need to be closely coordinated with the
tunnel contractor and TBM operation team.
One of the most suitable applications of cast-in channels is in railway tunnels and espe-
cially high-speed rail systems. This is due to requirements for anchoring electrical compo-
nents to the tunnel lining, such as catenary wire anchoring, wheel tensioners, anchor points
and line feeders (Figure 6.49).
In addition, in these tunnels, resistance to fatigue as a dynamic type of load is a key
requirement. Finnetunnel, 7.0 km (4.3 miles) long, twin tunnel tubes, 9.6 m (31.5 feet)
diameter high-speed railway line from Erfurt to Leipzig (Germany), is one such example.
Figures 6.50 through 6.55 show all stages of building a cast-in fastening system for this tun
nel from design to final service.
Loads can result both vertically and horizontally at the point of anchoring as Figures 6.48
illustrate. Serrated cast-in channels are a new development for applications with high longi-
tudinal loads, where the channel is cast-in vertically. The special toothed channels guarantee
a positive mechanical connection as illustrated in Figure 6.46. Furthermore, serrated chan
nels can safely absorb high fatigue-related stress ranges with a high number of cycles. They,
therefore, meet all requirements for secure anchoring of vertical loads with an increased
392 Handbook of Precast Segmental Tunnel Lining Systems
requirement on load cycles for example catenary systems, jet fans, passage doors and other
utilities in tunnels with train passages. Hot-rolled cast-in channels with serrations are also
suitable for applications in safety relevant areas of nuclear power plants and seismic areas.
To prevent concrete from filling the channel when pouring the concrete, a filling strip is
installed inside the channel that can be readily removed once the concrete has cured. This
allows T-bolts to be used for rapid installation of equipment in the tunnel. Such integrated
fastening systems can be employed for the temporary assembly of supply and transport
lines, walkways or working platforms while the tunnel is being driven.
Similar systems have been used for subway tunnels such as 25 km (15.5 mile) long, 5+
1 segmental ring configuration at Shenzhen Subway Line 9 in China. In this tunnel, due to
requirements for anchoring in eight different locations all around the tunnel perimeter, a
full-ring cast-in channel integrated system was adopted for power rail fixing, safety walkway
Connections and accessories for segmental tunnel linings 393
fixation and support of cables, mechanical and electrical equipment. Also, utility tunnels
such as the 8.5 km (5.3 mile) long 3.0 m (10 foot) diameter tunnel in Berlin, Germany with
5+1 ring configuration have taken advantage of the cast-in channel systems to house under-
ground high-voltage cable networks that is future-proof for anticipated upgrades.
modified assembly channels at segments utilizing segment connection bolts that do not
require drilling. Figure 6.56 shows this solution for 1.0 km (3,200 ft) long Diabolo railway
line twin tunnels with a 7.3 m (24 ft) internal diameter and 7+1 segmental ring configur-
ation. As shown in Figures 6.57 through 6.60, installation of curved assembly channels was
accomplished with mounting plates connected to the back of post-installed channels and
through the bolted connection system in the circumferential joints. This fastening system
has been utilized for installing numerous utilities as well as mechanical and electrical equip-
ment in this tunnel.
Segmental lining systems take advantage of dowel connections in circumferential joints
and, therefore, circumferential pockets designed in segments for fastening bolts are often
not always available. Solutions such as in Figure 6.59 cannot be always guaranteed with
Connections and accessories for segmental tunnel linings 395
Figure 6.55 Curved cast-in channel fastening system in a high-s peed railway tunnel.
Note: Finished segmentally lined high-
s peed railway tunnel after fit-
o ut and shortly before
trial run.
Figure 6.56 Curved post-installed channel fastening system in high-s peed railway tunnels.
Note: Finished segmentally lined high-
s peed railway tunnel after fit-
o ut and shortly before
trial run.
396 Handbook of Precast Segmental Tunnel Lining Systems
assembly channel systems and, despite all of its advantages, the anchorage issue and sec-
ondary drilling remain a primary drawback.
Cast-in fastening systems provide similar opportunities for road tunnels with fixing light-
ing, signal facilities, ventilation and exhaust air ducts. Figures 6.61 to 6.62 show another
398 Handbook of Precast Segmental Tunnel Lining Systems
major opportunity for modern fastening systems in road and rail tunnels for supporting
plenum slabs. Tension-rod systems are quick to install and reliable mounting systems as
favorable solutions when there is a high demand for load capacity in addition to high
demands for corrosion and fire protection.
• Two lines creating a large circular ring around Paris, connecting suburbs cities to each
other. Please refer to Figure 6.63.
• Two lines to connect Paris to Charles de Gaulle Airport, and Orly Airport to Versailles
The Société du Grand Paris is the owner and in charge of the development of this new net-
work. In total this new extension represents 200 km (122 miles) of metro lines and 68 new
stations. With this project, the network of the Paris Metro will almost be doubled. The first
lines should come in operation for the Paris Olympics in 2024.
Connections and accessories for segmental tunnel linings 399
For the new lines, like the most recent extensions built, it was decided that two metro
trains operate in the same tunnel, without any separation wall. For this reason, the internal
diameter for the lines 15, 16, 17 and 18 is about 8.70m (28.5 feet) with segments having
400 mm (16 inch) thickness.
On a design point of view, most of these projects have been built with a 7+0 ring config-
uration (key segment having the same size than a regular segment). Depending on the choice
of the contractors, the segments can be rectangular or “parallelogramic-trapezoidal” (i.e.
rhomboidal). A combined (EPDM +hydro-swelling cord in the center) anchored gasket has
been implemented on all the projects. For the first time, on Line 16, steel fiber reinforced
concrete has been used in Paris Metro.
On all the projects, segments in the circumferential joint are connected by the mean of
plastic dowels. Symmetrical dowels (Sof-Fix) were already used on previous Paris Metro
Project, but for the Line 15, some projects decided to use asymmetrical dowel (one side
screwed in, one side pushed in) testing the new features of this system (easier and more
ergonomic installation, for instance).
400 Handbook of Precast Segmental Tunnel Lining Systems
In the radial (longitudinal) joint, guiding rods fixed by the means of studs (and not
glue) are implemented on all projects. Indeed, as the gasket is anchored on all projects, the
usage of studs to fix the guide rods offered the precast fabricators the opportunity to work
“glue free”.
Additionally, the radial (longitudinal) joints were not necessarily bolted; the decision was
left to the contractors. Some decided to use one bolting system in each segment, one only in
the key or no bolting system at all. But it is to note that on all the projects, the bolts had to
be considered for temporary use only. The bolts must be removed to prevent them loosening
and falling on the train tracks due to vibrations.
The grouting is made essentially through the tail shield, most of the contractors did not
install any socket for secondary grouting through the segments. If a socket is used, this
socket is then installed on the top of the erector cone.
For the construction of openings, almost all the projects used shear bicones. They could
be standard shear bicone or bicones combined with tie-rods. On a specific area, where Lines
15 and 12 crossed themselves, it was decided to use shear bicone with tie rods in a very high
steel class (Grade 10.9) on a long section. Indeed, one portion of the tunnel was almost con-
sidered “a bridge” over the other line. The usage of the bicones helped to stiffen the tunnel
for this specific application (also subject to the vibration of the trains).
Several other innovations have been implemented on the Grand Paris Project. For
example, shafts have been built with segments and using the Herrenknecht VSM tech-
nology. This was one of the first times in France and it was done successfully; on the Line
15-T3C and L17-1.
At the time of this writing, the Lines 15 and 16 are under construction with some sec-
tions already completed and Lines 17 and 18 started the excavation phase at the very end
of 2021. The first lines should be opened for the Olympics of 2024, while the total project
completion should not occur before 2030. More information can be found on www.soci
etedugrandparis.fr/
After various studies and evaluations, the Florida Department of Transportation (FDOT)
selected the public-private-partnership (PPP) construction model for building the project.
FDOT contracted (through MAT Concessionaire) with the international contractor, Civil
& Building North America Inc. (formerly Bouygues Civil Works Florida). The project con-
sisted of twin-tube tunnels 1,260 m (4,134 feet) long each with a precast segmental tunnel
lining 11.27 m (37.0 foot) internal diameter × 12.47 m (41.0 foot) external diameter to be
constructed under Biscayne Bay in a soft, porous limestone/coral formation. There were
many geological challenges that had to be addressed before the tunnel could be constructed
with a Herrenknecht hybrid TBM. Refer to Figure 6.64. Many papers have been written
on the geotechnical challenges encountered and addressed by the tunnel contractor on this
project.
Civil & Building North America Inc. (CBNA) had considerable international experience
in building large diameter highway tunnels in challenging geological conditions and worked
closely with their design engineer of record in developing the optimum final tunnel lin-
ing design for the project. Since the tunnel is located in a subtropical climate with high
humidity, corrosion of any steel segment connecting componentry had to be addressed as
the tunnel has a design life of 100+years plus the owner complicated the segmental lining
design by adding a “security design requirement” since the lining is under water and had a
relatively shallow cover, the ring-to-ring connectors must support a defined force exerted if
an explosion occurred in the tunnel.
CBNA and their designer developed a very innovative segment connection system in con-
junction with the Tunnel Engineering Department of Anixter (now Optimas Solutions). In
lieu of corrosion resistant bolts being installed as permanent connectors in the circumferen-
tial joint faces, a special plastic over steel bicone was developed to connect segment ring to
segment ring. As shown in Figure 6.65 the bicones were designed with a hard plastic outer
cone that was injection molded over a high strength steel center steel axis. This innovative
design gave the bicone a high shear rating, 375 kN (42 tons) but flexibility in movement to
minimize concrete damage during load distribution.
For the radial (longitudinal) joint connections, the lining designers specified guide rods
only as this is a common practice in Europe where no permanent steel bolts are used to
connect segment to segment in the longitudinal joints of the lining. Guide rods are cir-
cular plastic rods that are glued into recesses cast into each radial (longitudinal) joint face.
Because of the large diameter of this tunnel, the diameter of the plastic guide rods was
60 mm (1.35”). Refer to Figure 6.66. The all-plastic guide rods provided shear resistance
against segment to segment movement and being 100% plastic eliminated any concerns
about long-term corrosion.
To facilitate assembly of the (8) eight-piece ring with a segment width of 1.67 m (5.5
feet) and with each segment weighing many tons, the segments needed to be temporarily
connected ring to ring in the TBM so that when the rams were retracted, the gaskets
remain compressed, and each segment remain in its installed position. A temporary con-
nection system was implemented from the leading segment ring using 28 mm (1.10 inch)
diameter steel bolts. Refer to Figures 6.67 and 6.68. After the segmental lining was back
fill grouted with a cementitious backfill grout and the grout hardened, the temporary
steel bolts were removed and “leap-frogged” down the tunnel for reuse. This is a very
common practice in other parts of the world, one reason the bolts are also removed is
that they can back out over time and fall to the roadway thus being a potential long-term
safety hazard.
newgenrtpdf
402
Handbook of Precast Segmental Tunnel Lining Systems
Figure 6.64 Port of Miami Highway Tunnel, Miami, Florida, United States.
Note: TBM breaking into the shaft of twin-t ube Port of Miami highway tunnels.
Connections and accessories for segmental tunnel linings 403
Norm NF E25-030: Fasteners–Threaded Connections with ISO Metric Thread–Part 1: Design Rules
for Tensile Loaded Bolted Joints–Simplified Procedure. Association Française de Normalisation
(AFNOR).
PATENT DOCUMENTS
United States Design Patent
COUPLING
• Patent No: US D930,464 S
• Inventer: Sandrine Ordener
• Date of Patent: Sep. 14, 2021
Chapter 7
7.1 HISTORICAL BACKGROUND
The history of gasketed tunnel linings goes back to the year 1874 when cast iron segments
were used to construct underground metro tunnels in London, England. Ordinary lead was
used as a sealing material, which was mortised into the joints between the segments. Cast
iron segments were commonly used in shield-driven tunnel construction until the 1970s.
The first rubber-made compression sealing gaskets were used on cast iron segments
designed for the construction of the New Elbe River Crossing Highway Tunnels in Hamburg,
Germany. See Figure 7.1 below. Construction of the ramp sections of these three shield-
driven tunnel tubes started in 1968 and were completed in 1974. Ready corner-vulcanized
chloroprene rubber gasket frames made of a comb-shaped sealing profile were used at that
time. This project is known as a milestone for the TBM-driven tunnel method using seg-
mental tunnel linings equipped with rubber sealing gaskets. It opened-up a new area in
modern mechanized tunnel construction.
In the late 1970s and early 1980s cast iron segments were increasingly replaced by rein-
forced concrete segments and comb-shaped profile geometries on the segment gaskets were
replaced by hollow chamber profile geometries that could cope with larger building toler-
ances regarding gaps and offsets in the segment joints. Chloroprene elastomer was replaced
by ethylene-propylene-diene-monomer (EPDM) elastomer, a material which offered a better
durability and long-time performance at lower cost. Refer to Figures 7.2 and 7.3.
DOI: 10.1201/9781032675541-7
408 Handbook of Precast Segmental Tunnel Lining Systems
Figure 7.1 Cast iron segments used on the new Elbe River Tunnel in Hamburg, 1968 to 1974.
Note: Construction of New Elbe River Crossing Tunnel using cast iron segments.
Figure 7.4 Typical concrete tunnel segment with gasket. Figure 7.5 Gasket groove with
gasket profile.
Note: Typical concrete tunnel segment with gasket groove
positioned near the extrados.
410 Handbook of Precast Segmental Tunnel Lining Systems
higher the utilization of the gasket groove volume by the compressed gasket rubber volume,
the higher is the restoring force and respectively the watertightness. Thus, the design of the
corresponding gasket groove geometry and joint configuration on the segments play a major
role in addition to the design of the gasket profile geometry.
The design and dimensions of both the gasket groove and gasket profile geometry are
mainly dependent on the waterproofing requirements of the tunnel project and must always
be considered together. The main criteria are the maximum allowable ring building toler-
ances in terms of gaps and offsets in the circumferential and longitudinal segment joints in
conjunction with the applicable water pressure.
In this regard, the tunnel designer’s desire for small gasket grooves often conflicts with
the required performance capabilities of the gasket. In general terms, the higher the water-
proofing requirements, the larger must be the dimensions of the gasket groove and profile.
In principle, wider gasket grooves and profile geometries can be found on larger tunnels as
the segment width is usually increasing together with the increasing tunnel diameter. More
space is available on the segment face to design a wider gasket groove without taking too
much risk that the distance between the gasket groove and the edge on the lining extrados
is becoming too small, which can result in potential concrete edge spalling.
On large diameter tunnels with an exceptionally large lining thickness, it can be possible
and feasible to place a second gasket near to the intrados lining face. Such double-gasket
designs have been used on a small number of outstanding traffic tunnel projects with special
waterproofing requirements.
Design criteria
Groove area
Profile area
groove design is mostly a compromise solution under consideration of all these factors in
which case the leading designer needs to consult with the gasket manufacturer of record.
7.6 GASKET MATERIALS
The elastomer material mainly used for gaskets is EPDM (ethylene- propylene-diene-
monomer). It is a synthetic rubber that has outstanding characteristics in terms of aging,
stress-relaxation and chemical durability.
Economically and technically, EPDM elastomer is the most suitable material and best
possible compromise to meet the demand for a design life of up to 125 years. EPDM has
excellent resistance to the key drivers provoking the aging process which are ozone, oxygen
Gasket systems for sealing segmental tunnel linings 415
and ultraviolet (UV) radiation. EPDM also has a good resistance to high temperatures [up
to 150°C (302°F) short-term and up to 50°C (122°F) long-term]. Therefore, EPDM gaskets
installed onto the segments can withstand atmospheric exposure during long periods of
unprotected outdoor storage in the segment stockyard without showing any deterioration
and change in physical properties.
416 Handbook of Precast Segmental Tunnel Lining Systems
EPDM elastomer also offers a low degree of stress-relaxation when constantly being
deformed and compressed in the gasket grooves alongside the joints of the segmental lining.
Further to that, EPDM elastomer has a very good permanent resistance to various aggres-
sive and highly concentrated chemical substances. It can resist substances with an acidity of
down to pH =3. Refer to Figure 7.14.
EPDM elastomer also has a low gas flow rate (permeability), which can be an important
aspect for tunnel construction in strata containing methane gas. The resistance of EPDM
elastomer to hydrocarbons and mineral oil is limited, especially when tested in high concen-
trations and under permanent contact, respectively, under conditions of accelerated aging.
However, regarding the application situation of tunnel segment gaskets, EPDM elastomer
was approved and used on several tunnel projects in which soil and ground water contam-
ination with hydrocarbons, mineral oils and also tar sands have been serious concerns. An
installed tunnel segment gasket is embedded within the gasket grooves located in the closed
joints between the tunnel segments and behind a 100 to 200 mm (4 to 8 inches) thick layer
of grouting mortar. In this specific installation-situation the gaskets normally do not come
in any direct contact with the contaminated soil.
Even in the case of a permanent infiltration and flow of groundwater seeping-out of the
surrounding soil, percolating through small cracks in the grouting mortar and reaching the
gasket in the segment joints, the chance of contact with highly concentrated residues of such
substances over a wide contact surface is low.
Further to that, the concentrations of hydrocarbons, mineral oils and tar sands found on
recent projects were proportionally low, causing no concern for the resistance of the EPDM
gaskets.
Gasket systems for sealing segmental tunnel linings 417
Physical property material tests on EPDM tunnel gaskets are recommended to ensure the
gasket was made of a high-quality EPDM compound and the extruded sealing profiles have
reached sufficient grade of vulcanization. Such tests can also serve to check and monitor the
gasket production processes.
As an example, the German STUVA (Studiengesellschaft für Tunnel und Verkehrsanlagen
e.V., Cologne) specified the following physical property requirements within their
Recommendation for Gasket Frames in Segmental Tunnel Linings (published in ‛Forschung
+Praxis, Volume 54, December 2019’) as summarized in Table 7.2.
7.7 WATERTIGHTNESS TESTING
The watertightness test is one of the elementary tests to check the suitability of the gasket
profile geometry and corner design. A project- specific approval test in the laboratory
should hereby simulate the segment design and installation conditions as closely as pos-
sible. Technically and economically, it makes sense to perform waterproofing tests using test
devices made of steel that simulate the T-joint section of a tunnel lining, which is the most
critical area. Such T-joint test devices have been used for tunnel gasket waterproofing tests
for more than 50 years. See Figures 7.15 and 7.16. They are common international industry
practice and are being recommended by authorities such as the following:
The T-joint test device comprises of a flat steel panel and two panels at an angle of 90°.
The T-joint test device comprises of a flat steel panel and two panels at an angle of 90°.
The respective gasket groove design is milled into all three panels. Specially manufactured
testing frames are used for testing, also including “flat corners”. These flat corners do not
occur in tunnel design and must be suitably prepared for testing, in order to rule-out pre-
mature failure in this irrelevant area. The relevant area of testing are the 90° shaped gasket
frame corners with the abutting profile sections. The T-joint test device is designed to simu-
late different joint gap and offset scenarios by enlarging the distance between the panels
(gap) and shifting one of two angle panels out of the building line (offset).
A series of minimum two single tests performed per combination of gap and offset is
usually required (one test +one repeat test). German STUVA recommends conducting an
additional third single test in the case of a large deviation in the achieved results to judge if
the lower result from the first two single tests has been an outlier.
The results of tightness testing are usually shown in a diagram such as that shown in
Figure 7.17 from which the groove bottom distance, the corresponding gap and offset of
each individual test set-up is shown. It is also mandatory to show the gasket groove geom-
etry of the test device taking account of the initial gap. The initial gap may vary on the air
side and on the pressure side, depending on the groove geometry and recesses next to the
gasket groove. For project-specific approval testing the gasket groove geometry and joint
configuration design on the T-joint test device must be precisely similar to the one used on
the segments of the tunnel for which the gasket is tested for.
newgenrtpdf
Table 7.2 Physical material properties of EPDM tunnel segment gaskets.
Requirements acc. to STUVA recommendation for gasket frames in segmental tunnel linings
419
420 Handbook of Precast Segmental Tunnel Lining Systems
For specific projects, this extrapolation can be extended to a longer design life as it is
becoming increasingly common for owners and designers to look at extended design life of
up to up to 125 years.
Depending on the gasket profile geometry and the material shore hardness, the decline
in the restoring force within these five minutes holding time can be 25 to 40% compared
to the initial force measured during gasket compression. Erecting the tunnel segments
and building one complete lining ring usually takes more than five minutes. That gives
the designer some confidence that the fastening system has some substantial reserves
with regard to the required holding forces that are needed when removing the TBM
thrust jacks.
• Limit the punctual loads in the T-joints developing from the increased restoring force
of the injection molded corner section to an extent that concrete spalling on the tunnel
segments will be avoided
The latter criterion contradicts the aforementioned and, therefore, requires a reasonable
compromise for the gasket corner design. See Figure 7.24 below. Hereby the interaction
with the adjoining gasket lengths as far as profile geometry and material composition are
concerned must be taken under consideration when designing the gasket corner detail.
In recent years, well-established and experienced tunnel gasket manufacturers have
developed various design concepts and production methods seeking to minimize the cross-
sectional volume of the injection-molded corner sections as much as possible. In this regard
it is also important to minimize and control the material flow into the hollow chambers
of the abutting extruded profile sections during the injection molding procedure. See
Figures 7.25 and 7.26.
Gasket frame corners are usually designed with angles of 90°. Due to the flexible gasket
material, such 90° corners can usually absorb deviations in the segment edge angles (</>
90°) to quite a large extent. However, depending on the profile size, the geometry and the
general gasket corner design, adjustments of the frame corner angles might become neces-
sary in the case of extreme degrees of acute and obtuse angles or/and extreme rotations on
the segment corner. Such adjustments require additional tooling equipment and effort for
the gasket manufacturer.
Gasket systems for sealing segmental tunnel linings 427
Adjustment of gasket frame corners to acute and obtuse angles on the concrete segment
corners are shown in Figures 7.27 to 7.29.
Installed on segment corners with angles </> 90°, elastomer sealing gaskets with standard
90° frame corners usually show slight deformations on the gasket corners in the form of a
contraction on an acute segment corner and a hump on the obtuse corner.
Within a tolerable range such deformations are usually just a visual phenomenon without
creating any technical problems, neither with regard to the segment installation procedure
nor to the sealing performance. Deviations within a range up to +/–5 mm (0.20 inches) out
of alignment are to be tolerated and will be fully compensated within the gasket grooves
after segment installation with the gaskets being compressed. On segment corners with
angles ranging between 80° and 100°, gasket frame corners designed with standard 90°
corner angles usually show deviations, which are much smaller. See Figure 7.30. For seg
ment corners with angles smaller than 70° and larger than 110°, the gasket corner angles
428 Handbook of Precast Segmental Tunnel Lining Systems
Figure 7.27 Developed plan view of segmental ring – rectangular segmental ring arrangement.
Note: Specific angles of radial (longitudinal) side flanks on the key segment in a rectangular seg-
mental ring system that result in acute and obtuse corners on the key and counter key segments.
Figure 7.28 Developed plan view of segmental ring – rhomboidal segmental ring arrangement.
Note: Angle of radial (longitudinal) side flanks on trapezoidal/p arallelogram shaped segments
in a universal rhomboidal segmental ring system that result in acute and obtuse corners on all
segments.
Gasket systems for sealing segmental tunnel linings 429
must definitely be adjusted accordingly since the degree of deformation would become
intolerable and a proper bond to the gasket groove could be compromised (especially for
glued-on gaskets).
Experience has shown that the shorter the molded gasket corner sections are, the less
deformation on the installed gasket will occur. In general, anchored (cast-in) gasket frames
show less deformations on the gasket frame corners as well.
Depending on the key segment design, torsion on the segment corners can appear on the
key and the counter key segments. This torsion result in a distorted angle (angle ß) in the
gasket groove. See Figure 7.31. As shown in Figure 7.32, the gasket frame corner should be
adjusted to such distorted angles in case of being larger than 10°.
7.11 FIRE RESISTANCE
According to the German Standard DIN 4102-1 B2 –Fire Behaviour of Building Materials
and Components, tunnel segment gaskets made of extruded and vulcanized EPDM elastomer
are usually classified as being “conditionally permanent” to fire. However, in the event of
direct and unprotected contact to fire with the intensity, temperature and duration as we
have experienced in some disastrous tunnel accidents, the EPDM gasket would start burn-
ing quickly. The fire resistance can be substantially improved by the addition of flame pro-
tection additives. But this in general could have a negative impact on the physical material
properties and the durability of gaskets.
Therefore, fire rating requirements for tunnel segment gaskets are very rarely seen in tun-
nel project specifications. The common approach that has been accepted by project owners
and their designers is to look at the specific installation situation of a tunnel segment gasket.
Since the gaskets are mostly installed at the lining extrados and embedded within the
gasket grooves alongside the closed segment joints the chance of direct contact with fire
occurring from inside the tunnel is very low. This installation situation has been repeatedly
Gasket systems for sealing segmental tunnel linings 431
investigated in simulation testing with different scenarios regarding lining thickness, dis-
tance of gasket groove and installed gaskets from lining intrados, fire temperature and dur-
ation. All these tests have shown that the temperatures developing at the area of the gasket
groove are absolutely non-critical for the gasket and that no negative impact and damage
must be expected, provided that the fire can be extinguished within a period of approxi-
mately 30 minutes.
An example of the temperatures that have been measured in the gasket groove area and
published on one of such fire simulation tests are listed below in Table 7.3.
Results are related to a test performed on a 250 mm (10 inches) thick lining with a distance
between the intrados lining edge to the gasket groove of 190 mm (7.50 inches). Measuring
point 1 was located directly at the installed gasket in the gasket groove and measuring point
2 was located inside the joint gap close to the gasket (temperature of trapped air).
432 Handbook of Precast Segmental Tunnel Lining Systems
In this test, a burner was directly located a few centimeters below the segment simulating
a fire source from the intrados side developing a measured heat of 800°C (1,470°F). The
temperatures at the measuring points were detected after 30 minutes burning time.
Under very similar test conditions several project-specific fire rating tests have been con-
ducted by specialized institutions such as the iBMB (Institut für Baustoffe, Massivbau und
Brandschutz) in Braunschweig, Germany. One of these tests has been performed in conjunc-
tion with the road tunnel project, “Herrentunnel Lübeck” in Germany in 2003 in which
450 mm (17.7 inch) thick segments and 44mm (1.72 inch) wide EPDM gaskets were used.
See Figure 7.33.
The main purpose of this test was to generally investigate the effect of plastic fibers to
improve the fire and heat protection as this was the time when companies such as Hochief
AG from Germany began to make very successful research and development implementing
this technology on concrete mixture used for tunnel lining segments.
For this test, the segment has been put directly over a burning chamber made of concrete
in which a fire with a temperature of 1,200°C (2,190°F) was produced. Within a burning
time of 60 minutes the highest temperatures reached around the gasket groove area were
below 100°C (212°F), which is absolutely uncritical for such a short-term exposure on an
EPDM gasket.
No damage was observed on the compressed EPDM gaskets after 60 minutes burning
time and no changes in the physical material properties were found in subsequent labora-
tory testing on these gasket test specimens. EPDM gaskets can temporarily withstand tem-
peratures of up to 200°C (392°F) without any problems. With the latest fire life safety
standards and technologies already implemented in most developed countries and regions
today, the 30 minutes period as the most frequent requirement is technically a sufficient
time to put out a fire in a traffic tunnel.
Enormous efforts and improvements have been made after the world has seen several
disastrous accidents followed by deadly fires, such as in the Mont Blanc Tunnel, France in
1999 or in the Gotthard Tunnel, Switzerland in 2001.
Gasket systems for sealing segmental tunnel linings 433
After the severe accident in the Eurotunnel in September 2008 in which a fire with tem-
peratures of up to 1,300°C (2,370°F) had occurred for a duration of several hours, massive
damage on the concrete segment linings was observed. On some of these damaged concrete
segments, some sections of gaskets were laid bare from the inside. Surprisingly, the gaskets
were still faultless and in good order and no leakage has occurred.
Whenever fire protection and safety are an absolute must inside a tunnel (which more
and more is the fact for nearly all traffic tunnels in the world), the market offers some very
effective and simple options to protect the tunnel structure against fire from the inside (fire
protection boards).
In 2005, the STUVAtec in Germany, for example, carried-out fire tests on concrete
segments equipped with EPDM gaskets and fire protection panels, whereby a fire with
1,200°C (2,190°F) was produced in accordance with German ZTV-ING-Teil 5 Tunnelbau
(Zusätzliche Technische Vertragsbedingungen und Richtlinien für Ingenieurbauten) pub-
lished by German Authority BAST (Bundesanstalt für Straßenbau). In this test, neither the
concrete segments nor the gaskets have been in any way affected or damaged by the fire or
by high temperatures caused. In this case, the distance between the fire and the groove in
which the gaskets were installed was only 100 mm (4 inches), which is much less than in any
real tunnel. The time period of this test was 200 minutes, which was 85 minutes longer than
what is required by German authority for railway construction EBA (Eisenbahn-Bundesamt)
and their published Guidelines for Fire Protection and Safety in Railway Tunnels.
7.12 GLUED-O N GASKETS
From early on, the installation of tunnel segment gaskets onto the tunnel lining segments
has been carried-out by different kinds of bonding procedures using adhesives with solvents
as well as special equipment. Both the “brush-on” and the “spray-on” adhesive methods are
still well-established and approved procedures among the industry. See Figure 7.34 below.
Rubber-based adhesives specifically developed for that purpose and offered by the leading
gasket manufacturers usually provide high and durable bonding strengths even in the event
of unprotected outdoor storage of the segments over a period of up to one year or longer.
However, these bonding procedures implicate the following risks and disadvantages:
• Cost involved with purchase and safe stocking of adhesives (potentially dan-
gerous goods)
• Cost involved with purchase and installation of spray guns and pressing frames
• Cost involved with protection measures for the workers and the environment
• Costs involved with recycling of empty adhesive tins (statutory in many countries)
• Segment groove repair measures required before gasket installation
• Process times for gasket installation and bonding of 15 to 20 minutes per segment
• High risk of leakage in the tunnel caused by insufficient gasket bonding due to
improper workmanship/failures during gasket installation
7.13 ANCHORED GASKETS
In the early 1990’s, the first so-called “anchored” tunnel segment gasket, which is directly
cast-in the reinforced concrete segment was developed in Germany. For that purpose, the
gaskets were designed to be installed into a special gasket groove on the side parts inside the
segment formwork before casting. See Figures 7.35 and 7.36.
434 Handbook of Precast Segmental Tunnel Lining Systems
Successful field trials with this new gasket technology were carried-out at that time in
Germany and Japan. In 2008, a 500 m (1,640 foot) long sewer tunnel section in Moscow,
Russia was successfully equipped with anchored gaskets. However, the first reference that
has received high recognition among the international tunnel industry and that is known as
Gasket systems for sealing segmental tunnel linings 435
the pilot project for this new gasket application technology has been the Lee Tunnel Project
completed in the year 2014 in London, Great Britain. This sewage and rainwater overflow
collector tunnel with an outer diameter of 8.5 m (27.6 feet) laid the foundation for anchored
tunnel segment gaskets becoming the new state-of-the-art technology. From that time on,
anchored gaskets have increasingly been used in projects all around the world, predomin-
antly in regions with high requirements for environment protection and high labor costs.
In comparison to the traditional “glued-on” gasket design and installation procedure the
anchored gasket technology provides the following advantages:
• Environment-friendly workplace
• Decisive reduction of gasket installation process time (i.e. in average from 15 to 3
minutes, depending on segment/gasket frame size)
Despite these advantages it must be emphasized that the involved formwork maker should
have sufficient experience and expertise on the special design required on the formwork’s
side parts. In this regard they must closely cooperate with the gasket manufacturer and tun-
nel designer and Engineer-of-Record. The best possible gasket insertion groove design on
the formwork is required to reduce the risk of damaging the segments during the formwork
stripping process and to prevent miscalculation of the effective gasket groove filling rate. In
this regard, the issue of concrete spalling during segmental ring assembly that might result
from gasket over-compression, insufficient groove to edge distance or disadvantageous
gasket corner design must be looked at even more critically. In comparison to the “glued-
on” gasket technology, the shape of anchored gasket profile defines the gasket groove on
the concrete side.
Further to that, a high degree of diligence and discipline is required to properly clean the
segment formwork after each casting cycle. Any smallest residue of concrete in the gasket
insertion grooves on the segment formwork will hinder a proper gasket installation and may
cause failures on the gasket’s embedment to the concrete during casting.
Limited repair procedures for such installation failures on anchored gaskets do exist, but
these methods require much more effort than repairing a defective mounting on a “glued-
on” gasket and possibly require special approval by the project owner.
This subject is of major importance and one of the most under-estimated issues in a seg-
mentally lined tunnel construction. Even after 50 years of using gasketed segment tunnel lin-
ing as a proven and well-established construction method, severe failures repeatedly occur,
simply because of improper or missing lubrication on the segment gaskets.
Insufficient or missing gasket lubrication can easily be identified by the phenomenon of
gasket corners coming loose and being squeezed-out of the radial joints or even stretched
around the segment edges when looking from behind the last built segment ring onto the
long circumferential side of the installed key segment. In worst cases, the gasket frame is
completely detached and pulled away from the segment groove and hanging loose from the
longer circumferential key segment side. Proper and reliable repair of such failures are not
possible. The only way to keep moving forward with TBM advance and segment ring build
is cutting the stretched and detached gasket section off, trying to bring both cut gasket ends
together again by a cold joint bonding. Leakage on such a repaired gasket section will occur
most likely. In this regard it should be mentioned that improper bonding of the gaskets onto
the segments caused by prior gasket installation failures in the segment factory can cause
a similar phenomenon as well or can increase the failures caused by insufficient or missing
lubrication on the gasket.
7.15 GASKET REPAIR
Repairs on gaskets installed onto the segments that have been damaged during transporta-
tion or in the segment stockpile yard are generally possible. Both, the “glued-on” and the
“anchored” type of gaskets can be repaired by cutting and removing the damaged gasket
profile section from the segment and by properly inserting a replacement profile section by
using adhesive on the gasket groove and on the abutting joint sections.
Recognized gasket manufactures usually provide specific repair instructions and assis-
tance in terms of demonstration training on site. Project-specific waterproofing tests on
such repaired gaskets have shown that the sealing performance can be proven as long as the
waterproofing requirements are in a moderate range. However, it must be emphasized that
a repaired gasket does not have the same properties as a virgin gasket frame being endlessly
vulcanized all around the segment. At the cold-welded joints of the repaired section, it has
a weaker resistance to mechanical stress that might be caused during segment installation
procedures, which may lead to premature damage resulting in a leakage. In this regard, the
gasket manufacturers usually do not take responsibility and the acceptance of repaired gas-
kets and the final approval allowing segments with repaired gaskets going into the tunnel
must be provided by the owner’s Engineer-of-Record. Particularly in the case of high water-
proofing requirements, such an approval must be based on project-specific waterproofing
tests on repaired gaskets.
Experience in the past has shown that a proper gasket repair is practically feasible and
has not evidently led to failures in the tunnel. However, it is absolutely mandatory to install
segments with repaired gaskets with utmost care and to use an approved lubricant that
prevents surface friction between the gaskets regardless of the segment type (key, counter
key or standard segment).
Gasket systems for sealing segmental tunnel linings 439
designer. In addition to that, it makes sense to also investigate the decline in restoring force
within the first 5 minutes after compressing the gaskets, which simulates the installation
situation within the first 5 minutes from erecting and installing the segments. German
STUVA recommends performing such load deflection tests minimum three times as project-
specific suitability test. See Figures 7.39 and 7.40.
• Permanent laser light control of the profile width and height during the complete
extrusion process
• Profile geometry dimensions checks on 10:1 scale overhead projector on samples fre-
quently being taken from the profile extrusion process (tolerances according to ISO
3302-1, Class E2)
• Dimensional checks during profile cutting process
• Dimensional checks on ready vulcanized gasket frames
• Final visual check of all vulcanized gasket corners
• Destructive tearing force and tensile strength testing of frame corners by spot checks
• Tensile strength checks per DIN 53504 on the profile
• Elongation at break checks per DIN 53504 on the profile
• Compression set testing per DIN 53517 on the profile
• Shore hardness checks per DIN 53505 on the profile
442 Handbook of Precast Segmental Tunnel Lining Systems
The material property checks listed here can also be found in a chart defined as “Works
Production Controls –Table 5” required within the STUVA “Recommendation for Gasket
Frames in Segmental Tunnel Linings”, published in December 2019 as shown in Figure 7.41.
a compression carrier gasket with a separate hydrophilic round cord, which is completely
embedded within the carrier profile, and which can be installed shortly before transporta-
tion of the segments down into the tunnel.
The hydrophilic cord would only be activated in the case of contact with water, for
example, in the case of a leakage through insufficiently compressed gaskets due to bad ring
build (in the event of extremely large gaps in the segment joints). In this case and under
certain advantageous circumstances, that leakage can be stopped within a period of two
to three days due to the additional restoring force developed by the expanding hydrophilic
cord. Such a “self-healing-effect” has been observed in laboratory testing. Fully embedded
into the groove on top of the compressed carrier profile, such a restoring force developed by
expanding and pushing against the surrounding barriers can provide an efficient additional
sealing performance over time.
This hybrid gasket design approach has partially become established in metro tunnel
construction in France where the authority AFTES (Association Française des Tunnels et de
Gasket systems for sealing segmental tunnel linings 445
Figure 7.45 High-s peed rail line between Stuttgart and Ulm, Germany.
Note: The new east-w est link of Europe’s high-s peed-r ailway network under development and
construction includes the Deutsche Bahn Albvorland Tunnel near Stuttgart, Germany.
The contractor applied even further safety margins to the specification stipulated by
Deutsche Bahn Netz AG for the watertightness test certificate. The manufacturer of the
sealing gaskets was required to perform additional tests for a simulated “worst-case” scen-
ario involving 8 mm (0.30 inches) joint gap and 20 mm (0.80 inch) joint offset.
Deutsche Bahn Netz AG specified a minimum contact width of 38 mm (1.5 inch) for
the sealing gasket profile geometry to be used, which closely approximated to a “classical
sealing” gasket profile for a groove-base width of 44 mm (1.75 inch) as previously used in
various large diameter rail-tunnel projects.
Based on experience and existing test reports in conjunction with project-related approval
testing with such “classical” 44 mm (1.75 inch) sealing profiles, it had to be assumed that
with the test parameters specified by DB Netz AG, i.e. with a joint expansion of only 6 mm
(0.25 inch), a critical limit range would already be reached, especially when tested at an
offset range from 0 to 20 mm (0 to 0.8 inch) as specifically required for the Albvorlandtunnel
project. See Figure 7.46.
This included CTS Cordes Tubes & Seals GmbH & Co. KG to enter into the development
of a new suitable sealing profile geometry specifically for the test requirements applying to
the Albvorlandtunnel. After intensive research and development work and product tests
performed across a period of several months mainly at the recognized testing institute MPA
in Hannover (Materialprüfanstalt für das Bauwesen und Produktionstechnik Hannover),
in full accordance with the STUVA Recommendations, a totally new profile design concept
was achieved.
The advantages of this newly developed geometric concept can be found, essentially, in
the form of a considerably greater sealing effect, which exhibits no significant, geometrically
influenced fluctuations whatsoever across all joint offset dimensions as illustrated below
in Figure 7.47. It was possible to demonstrate fulfilment of the minimum watertightness
448 Handbook of Precast Segmental Tunnel Lining Systems
requirements for “joint gap” of 6 mm (0.25 inch) in accordance with the project specifica-
tion across all offsets and with significant additional reserves.
The resultant overall concept for groove design and profile optimization permitted the
above-described improvement in sealing action with no significant increase in the maximum
restoring force with the smallest joint gap. It was possible to achieve a test pressure of 10
bar (147 psi) even in the “worst-case” tests performed additionally with a joint gap of 8 mm
(0.30 inch) [i.e. a groove-bottom-distance of 34 mm (1.33 inch)] and an offset of 20 mm
(0.80 inch).
In comparison with the former classic 44 mm (1.75 inch) profile shape CTS 44/20, used
on large diameter railway tunnels, the improvements made with this improved profile geom-
etry design, CTS 44/20 AVT (Albvorlandtunnel), can be summarized and concluded as listed
in Table 7.4.
This innovative development has proven that even after 50 years of designing segment
gasket profile geometries, accompanied with a large number of international patents granted
to the involved gasket manufacturers, there is still potential for improved and patentable
new concepts. Hereby, the improvements in the profile extrusion technology plays an
important role, which has made it possible for CTS Cordes to design and manufacture a
sophisticated profile geometry with an increased number of hollow chambers and a com-
plex arrangement of ligaments.
Another invention being used on this new geometry concept was the special archway-
shape arrangement, which has been a key to achieve a high waterproofing performance
without offset related weaknesses and moderate restoring forces at the same time. Stored
segment for the Albvorland Tunnel are shown in Figure 7.48.
Gasket systems for sealing segmental tunnel linings 449
developed for the project with a 5 mm (0.25 inch) Black Swell (hydrophilic) round cord
integral to the gasket. See Figure 7.52. The EPDM gaskets were glued to each segment at
the casting plant in Puyallup, WA, and the hydrophilic round cord was installed on each
segment at the project site prior to each segment being transported into the tunnel.
The 44mm (1.75 inch) gasket was chosen based on the “worst-case scenario” of 8 mm
(0.31 inch) gap and 20mm (0.80 inch) offset and tested with 15 bar (218 psi) pressure and
fulfilled this requirement and more. The actual gap open to water pressure during the test
was 11mm (0.43 inch); groove bottom distance of 32 mm (1.26 inches) with a shoulder
height of 10.5 mm (0.41 inches).
Gasket systems for sealing segmental tunnel linings 453
Excessive testing required for selecting the best gasket for this project. Besides the demand-
ing watertightness test mentioned above, there were requests for swelling tests of the hydro-
philic material in all different water types (distilled, tap and salt water), external spalling
tests, chemical resistance of the gasket and hydrophilic material. These tests were required
in addition to the standard mandatory tests described in the specifications and typical for
North American tunnel projects.
Due to unexpected project delays during tunnel construction, the segments with installed
EPDM gaskets had to be stored outside for more than two years. This required further tests
on the gaskets, confirming that the gasket performance was not affected. The additional
tests showed that the EPDM compound showed no impact from the outside storage. On
another recent project in United States., EPDM gaskets have been stored outside in the sun
for over four years without impacting gasket performance.
Since many factors go into the creation of a dry tunnel, the Washington State Department
of Transportation (WASDOT), the project design engineers and the tunnel contractor evalu-
ated the various project requirements, conducted the required tests and selected a gasket
sealing system that met the needs of a very complex tunnel project.
454 Handbook of Precast Segmental Tunnel Lining Systems
The tunnel opened on 04 Feb 19 creating a bypass for auto and truck traffic through
downtown Seattle thus improving the transit time for the people of Seattle and creating
a waterfront park when the old viaduct was removed. Tunnels improve the quality of life
wherever they are constructed.
Project fact summary
DIN EN 681-1Elastomeric Seals–Material Requirements for Pipe Joint Seals Used in Water and
Drainage Applications–Part 1: Vulcanized Rubber; German Version EN 681-1:1996 +A1:1998
+A2:2002 +AC:2002 +A3:2005.
(Elastomer-Dichtungen–Werkstoff-Anforderungen für Rohrleitungs-Dichtungen für Anwendungen in
der Wasserversorgung und Entwässerung–Teil 1).
DIN 4102 B2 Fire Behaviour of Building Materials and Elements; Part 1: Classification of Building
Materials Requirements and Testing.
(Brandverhalten von Baustoffen und Bauteilen– Teil 1: Baustoffe; Begriffe, Anforderungen und
Prüfungen).
DIN 53504 Testing of Rubber–Determination of Tensile Strength at Break, Tensile Stress at Yield,
Elongation at Break and Stress Values in a Tensile Test Standard.
(Prüfung von Kautschuk und Elastomeren– Bestimmung von Reißfestigkeit, Zugfestigkeit,
Reißdehnung und Spannungswerten im Zugversuch).
DIN 53505 Shore A and Shore D Hardness Testing of Rubber.
(Prüfung von Kautschuk und Elastomeren–Härteprüfung nach Shore A und Shore D).
DIN 53508 Accelerated Aging of Rubber.
(Prüfung von Kautschuk und Elastomeren–Künstliche Alterung).
DIN 53509 Determination of Resistance of Rubber to Ozone Cracking under Static Strain.
(Prüfung von Kautschuk und Elastomeren–Bestimmung der Beständigkeit gegen Rissbildung unter
Ozoneinwirkung–Teil 1: Statische Beanspruchung).
DIN 53517 Testing of Rubber and Elastomers; Determination of Compression Set after Constant
Strain.
(Prüfung von Kautschuk und Elastomeren; Bestimmung des Druckverformungsrestes nach konstanter
Verformung).
DAUB:2013 Lining Segment Design: Recommendations for the Design, Production, and Installation
of Segmental Rings.
456 Handbook of Precast Segmental Tunnel Lining Systems
BS PAS 8810:2016 Tunnel Design –Design of Concrete Segmental Tunnel Linings –Code of Practice.
BRITISH TUNNELLING SOCIETY (BTS) AND THE INSTITUTION OF CIVIL ENGINEERS (ICE)
8.1 INTRODUCTION
This chapter discusses segment mold design and manufacturing and all the aspects related to
segment production, including the equipment used in segment precasting plant and the typ-
ical configuration of the segment production process. It also explains the tolerances of the
mold and the advances measurement techniques for the mold and the segment. The segment
and mold quality control and documentation as well as innovation in segment production
and relevant case histories are also described in this chapter.
8.2.1 Ring designs
Once having defined the tunnel track, the geometrical dimensions as well as the tunneling
mode, the designer develops a concept for tunnel lining. The lining must meet or rather
guarantee the following requirements:
After the selection of the tunneling method and the tunnel boring machine (TBM) type, a
segmental lining concept must be defined, which includes the following:
DOI: 10.1201/9781032675541-8
458 Handbook of Precast Segmental Tunnel Lining Systems
Both rings with one-side taper as well as those with both-side taper can be designed with a
small or a large key segment, as shown in Figure 8.1.
The common designation for rings with a small key segment is X +1. Universal rings;
i.e. rings with a large key segment are usually described with X +0. Until a few years ago,
universal rings were used in most cases for smaller tunnel diameters, as the individual seg-
ment length was considerably shorter and, therefore, easier to handle in tight conditions.
However, this ring type is recently applied for almost any diameter and is getting more and
more important.
Principle sketch of ring types:
8.2.2 Mold design
The mold design is based on the ring or segment design, which must be defined by the
designer. However, the design focuses on the implementation of the static requirements,
i.e. bearing the bending moments and normal forces, the size of the contact faces as well
as initiation of point and line loads by bolting and EPDM gaskets. Therefore, the designer
considers all occurring loads and load cases as well as the states of construction.
After having approved the ring design for production of the lining segments, the mold
manufacturer checks the ring design with regard to geometrical feasibility and implementa-
tion for mold manufacture. For this purpose, the mold manufacturer prepares a 3D model
at the beginning of the project and compares it to the existing 2D/3D model of the approved
ring design. Further, the mold manufacturer checks all drawings regarding:
In addition, the mold manufacturer adds adequate radii and transition zones.
Another aim is to make sure that opening of the mold does not cause any restraints that
could possibly damage the early age concrete.
Further tasks of the mold manufacturer:
• Verification of the correct position of the gasket joint and the connections between
rings and segments
Formwork systems for precast segmental tunnel linings 459
• Matching of the segment angles and the positions of the thrust ram shoes with the
specifications of the TBM manufacturer
• Verification of the ring taper on the basis of the radii of the planned tunnel track
According to the current state of the art, mold design is developed in three-dimensional
space (3D design), thus, on the one hand, enabling the designer to correctly visualize the
complex geometrical features –particularly in non-radial and angled surfaces –and, on the
other hand, to simulate the movements of the side shutters and covers to detect possible
interfering edges.
In general, the mold manufacturer issues the following drawings:
• Drawings of the steel structure: they include all cutting measures and manufacturing
dimensions as well as positions and dimensions of the weld seams
• Drawings for mechanical processing: they include all information and measures for
milling as well as specifications regarding roughness of the machined surfaces
• Assembly drawings: these drawings include all information for assembly as well as
dimensions for inspection
460 Handbook of Precast Segmental Tunnel Lining Systems
In the first step, the tolerance requirements of the designer are decisive for the dimensions,
angles and measurement specifications implemented by the mold manufacturer. In the
next step, the mold manufacturer defines the tolerance necessary for manufacturing the
molds so that the produced concrete segments, i.e. the inside of the molds, show the correct
dimensions.
8.2.3 Implementation of molds
The molds are generally implemented with the following:
The side and front shutters can be moved by means of a tilting system or a horizontal dis-
placement. Depending on the mold manufacturer, there are different philosophies regarding
execution of the molds. Figure 8.2 shows different closing systems of the molds.
• The front shutters are closed first and then the side shutters are bolted
• This system offers the best adjustment and replicability in regard to the width of
the segment
• Or the side shutters are closed first and afterwards the short front shutters
• This system offers a better adjustment of the very important arc lengths and angles
in the longitudinal joints
• Further, shrinkage and creeping of the concrete in longitudinal direction can better
be controlled and probably re-adjusted
Production of the lining segments is subject to very strict requirements regarding precision.
For example, a tolerance of ±0.6 to 0.8 mm (0.024” to 0.032”) is usual for the arc length.
The width of the segments is in most cases tolerated with ±0.5 mm (0.02”). For this reason,
high-precision molds are required, which are able to permanently produce the required
dimensions and tolerances.
Re-adjustable mold systems that can permanently guarantee the required dimensions, are
the preferred solution.
In general, tilting and bolting systems for opening, closing and locking of the side shutters
and covers are implemented. Spring-supported lever-arms are necessary especially for the
covers and front shutters to enable a manual movement of the components.
Design of a mold for stationary production generally does not differ from design of a
mold for carousel production. In the case of carousel molds, the base frame is additionally
equipped with wheelhouses and high-quality wheels.
• Compressed air vibrators have been used for segment thickness up to 400 mm and
500 mm (15.75” to 19.60”)
• Electrical vibrators haven been used for segment thickness exceeding 400 mm to
500 mm (15.75” to 19.60”)
Control of compressed air vibrators is very restricted. Intensity can be varied via air supply
only. In contrast, electrical vibrators offer an exact adjustment of the frequency by means
of a converter.
However, experience has shown that the use of electrical vibrators quite often leads to
damage on the mold bottom. Possible causes include the following, for example,
Due to the low cost of acquisition and operation combined with satisfactory compacting
results, compressed air vibrators are used in most of the cases.
Independent of the type of compacting, the type and location of frequency in the mold
bottom should be provided as directly as possible. Movement of the vibrator on the mold
bottom in almost any case leads to cracks and subsequently deformations. Therefore,
rigidity of the mold bottom must be sufficient, however, at the same time it has to be flexible
enough to enable the vibrations to be transferred to the concrete. Suitable steel plates, gen-
erally with a thickness between 10 mm and 12 mm (0.39” to 0.47”), must be used.
• Serviceability
• Dimensional stability
Serviceability focuses on the permanent movability of the side and front shutters as well
as the covers. For this purpose, the mold manufacturer provides appropriate material and
greasing possibilities, respectively lubrication-free bearings.
Dimensional stability is a product of precision in manufacture and careful use of the
mold. On average, approximately 600 to 1,000 segments are produced with one mold.
During this period, the mold is not allowed to exceed the required tolerances. Should the
Formwork systems for precast segmental tunnel linings 463
tolerance be exceeded, the mold must be re-adjusted. Several projects with up to 2,500 pro-
duction cycles per mold have been realized. These are exceptions.
8.3.1 Steel fabrication
After cutting and rolling of the sheets, the mold bottom is composed in a special gauge and
welded. The following has to be considered:
After inspection of the weld seam, a ground coat has to be applied on the lower surface of
the mold bottom. Figure 8.5 shows an example of steel fabrication.
8.3.2 Mechanical processing
During steel works and welding, the side and front shutters are exposed to a high-
temperature impact. Due to thermal expansion this leads to increased tensions within the
material. Therefore, a thermal heat-treatment; i.e. stress relief heat treatment at 550 to
600°C (1,022° to 1,112°F) is necessary before milling of the side shutters. Subsequently,
the steel parts must be sandblasted or shot-blasted to be optimally prepared for mechanical
processing.
A common machine for mechanical processing is a five-axle CNC milling machine with
a sufficiently big space for processing. After processing, the contact surfaces and the gasket
joint have to show a surface finish of Roughness, Ra 2.3. The use of a portal milling machine
could possibly be necessary for large side shutters or complex geometries.
Milling of the complex geometries in principle requires a lot of experience and care. An
example of the milling of side shutters is shown on Figure 8.6.
Ra is the arithmetic average of surface heights measured across a surface, Ra surface fin-
ish. Simply average the height across the microscopic peaks and valleys. Surface roughness
can be measured by a profilometer, a surface profile measurement tool.
8.3.3 Assembly
The molds must be assembled on an appropriate, even surface. Attention must be paid to
avoiding any torsion of the mold bottom by attaching the side and front shutters. Already
during assembly of the side and front shutters, maximum precision is necessary in order to
enable a subsequent precise adjustment of the surfaces between each other. Figure 8.7 shows
a mold assembly setup.
Formwork systems for precast segmental tunnel linings 465
Further information cannot be gained. In the recent past, segment producers more and
more renounced the production of test rings and requested a virtual test ring instead.
To get a virtual test ring, the 3D measuring data of a mold are used to virtually build a
ring. Please also refer to Section 8.8 –Master ring erection and virtual ring build.
8.3.5 Inspection
Before a mold leaves the manufacturer’s factory, a mechanical verification should be made
in any case. Today, a 3D measuring by means of a laser tracker is standard (see Figure 8.10).
The measuring report confirms the correct dimensions before transport.
Formwork systems for precast segmental tunnel linings 467
8.3.6 Painting
Despite the relatively short service time of a mold, it is provided with a paint coat at the
manufacturer’s premises. It consists of adequate base coats and finishing coats. The painting
supports the necessary cleaning of the mold during operation. Besides the optical effect or
classification, the painting does not offer further functionality.
8.3.7 Transport
The mold manufacturer has to work out a concept for transport of the molds considering
the following aspects:
The molds have to be equipped with clearly marked positions for attachment, shackles or
forklift guides. If the molds are attached on other positions, torsions may cause a permanent
damage to the molds; an example of molds transport is shown in Figure 8.11.
If the molds are transported in stacks it must be made sure that the stack cannot move
within itself. For this, a static proof is necessary.
In sea containers the molds or stacks must be protected against slipping and tilting; i.e.
against any kind of movement.
With truck transport this is not possible in most of the cases. Here, fixing of the position
has to be made sure by means of lashing straps.
production curve is anything but easy and can never be considered as an absolute value.
Typical influencing parameters are as follows:
Having defined the production quantities and the required storage capacity, the necessary
components of the segment plant must be planned. In general, these are the following:
When starting a project, the responsible planners should carefully check whether a new
plant is required or if experienced precasters are available in the region who could produce
a sufficient quantity of high-quality segments.
8.4.1 Segment factory
The segment factory/field factory (Figure 8.13) is generally installed in a steel building with
a concrete foundation. Depending on the surrounding conditions (temperatures, noise
emission), the factory should be insulated. The following utilities must be installed in the
building:
• Electricity
• Water
• Compressed air
• Optional sprinkler system
• Ventilation
• Wi-Fi/VoIP (Voice over Internet Protocol)
The overhead cranes (gantry cranes) should be able to safely pick-up the loads (in most
cases, the total load of segment, handling device and lifting force must be considered), espe-
cially with regard to their minimum distance between crane rope and wall.
Besides the production area itself, the following additional areas must be provided:
Sufficient lighting has to be installed in the hall (light bands at the ceiling and on the walls,
ceiling lights) and access gates have to be planned.
A rescue concept defines the position of the emergency exits and helps to make all areas
accessible.
Fire loads have to be planned in advance and agreed with the responsible authorities.
The number and type of silos depends on the concrete concept. In most cases, the following
is necessary:
The aggregates (sand, fine and coarse gravel) must be stored separately in bunkers/boxes.
Depending on weather conditions it is recommended to provide a housing for the aggre-
gates. The size of the bunkers/boxes should be sufficient to bridge a failure of supply or a
series of holidays. The same applies to cement, fly ash, etc.
For the case that steel fibers or fire protection fibers are used, delivery of the fibers into
the mixer must be well planned in advance. The fibers can be dispensed into the mixer dir-
ectly or via the conveyor belt or the inclined concrete transport hopper. As in most cases
steel fibers are supplied in big packs, sufficient access and lifting space has to be planned.
Further, access areas for cement and aggregates must be considered when planning the
batching plant.
Finally, a concept for the treatment of concrete sewage and concrete residue should be
drawn up already in the beginning. Consumption of water and electricity should be agreed
with the local providers.
The rescue and fire protection concepts are similar to the segment factory. Correspondingly,
planning of gates, ventilation and lighting.
Special attention should be paid to power consumption, as a large number of welding
devices with a high input power are used.
The reinforcement cages have to be produced in specially manufactured gauges. Besides
the outer dimensions (length, width, thickness, radii, angles) the gauges must define the
areas without reinforcement and the recesses.
However, the graph cannot consider any kind of interruptions, which can lead to a consid-
erable increase of the required storage area.
Therefore, segment production experts often work with a yard, which is capable to store
an output of three to four months of regular production. This approach proved to be applic-
able for a regular production.
• The output of the first month of production may not be used due to an insufficient
compressive strength
• The output of the second and third month of production can be used
• The output of the fourth month of production serves as a buffer for any kind of
interruptions
Further attention should be paid to special segments and rings for the following
considerations:
• Cross-sections
• Rings with special inserts
• Rings with increased reinforcement
• At the beginning of the storage planning it is necessary to draw up a concept consider-
ing the complete way of the segments/rings from production until installation of the
tunnel. This is what finally influences the sequence and arrangement of the piles. The
following should be considered:
• Arrangement of the molds in the segment factory
• Arrangement of the segments in the pre-storage area
• Piling sequence for storage on the outside yard
• Piling sequence for release from stock
• Transport to the TBM
• Further intermediate storage facilities
• Segment crane on the TBM
• Segment feeder on the TBM
• Possible ring arrangements and the resulting sequence of ring building
Formwork systems for precast segmental tunnel linings 473
Particularly for transport of the segments, attention has to be paid to avoid a mirror-inverted
supply of the segments. For this purpose, strict guidelines have to be issued for segment
handling (truck, forklift, etc.) or must be provided in a structural manner.
It is usual to turn the segments in the segment factory already (INTRADOS side showing
towards the top). The following is required for piling:
The support on the floor in most of the cases consists of reinforced concrete elements with
a wooden, plastic or rubber support. It is important to have a space between the support
and the bottom side of the segment to enable the segment clamp to grab the segment or the
pile. When it comes to the points of support, experience showed that a division in thirds (in
vertical direction) turned-out to be adequate. Finally, this has to be defined by the designer.
The intermediate supports generally consist of wood. For heavy segments, hard wood is
used. When defining the vertical support points, it is necessary to check the inner radii of
the segments with regard to an application of the piling wood without slipping or tilting.
The height of the piling woods is calculated on the basis of
Further, position and quantity of the piling woods results from the compressive strength on
the one hand and the decision, whether a line load can be transmitted into the young seg-
ments, on the other hand. It often turns out that a three-point-support makes more sense as
the risk of restraints or torsion tends towards zero.
Another important aspect regarding piling is to avoid horizontal offsets. The pile could
possibly collapse as a consequence of unilateral load peaks when the load is transmitted in
the floor. Further, the structural clearance of the clamp is limited. This would quickly lead to
damages on the segment. Experience showed that an eccentricity of ±50 mm (2”) proved to
be an acceptable value for horizontal offset. However, this has to be calculated and defined
by the planner.
Certain minimum spaces between the piles are necessary for storage and release of the
segments from stock. On the one hand, as said before, the dimensions of the clamp as well
as its opening and closing have to be considered. On the other hand, storage yards are often
defined as accessible areas and are therefore subject to applicable health and safety regula-
tions. Local and national regulations have to be considered here.
The number of segments per pile results from the following:
Usually, at least one complete ring is piled per storage position. This makes identification
of the pile easier. Making use of a warehouse logistics system, higher piling is also possible
when the corresponding conditions are established and maintained. Meanwhile it is usual to
pile 1.5 or even two complete rings on one storage position, thus increasing storage capacity
considerably. Resulting from the overall concept and the crane capacity, in most cases pile
packages of three or four segments each are planned.
Special attention has to be paid to small key segments. They always have to be the top
segment on a pile or separate piles are made using key segments only.
For historical reasons, a storage per ring has been implemented for many projects. This
means that on each storage position one complete ring is piled, following a defined sequence.
However, this leads to a loss of storage capacity in many cases. Further, due to the many
handling activities on the way to the TBM, the sequence often cannot be kept. Therefore,
experience showed that a storage per type could offer advantages. This means that there are
only identical types of segments on one storage position. They are carried to the place of
installation (TBM) in this way and the piling sequence is configured directly there.
Due to the large number of piles it is recommended to use a data management system.
In this case, during production already, the segments are provided with an identification
number (segment internal diameter) and can thus be assigned to a special storage position.
The different options and possibilities for organization of the warehouse are described in
detail in Chapter 10.
On most of the outside storage yards, gantry cranes are used. When it comes to dimen-
sioning of the gantry cranes, it is necessary to consider the following:
The outside storage yard generally must provide a sufficient soil bearing capacity. The
relatively high loads from the piles must be transmitted safely to the ground. If necessary,
Formwork systems for precast segmental tunnel linings 475
the soil must be improved. In this regard, a possibility for drainage of the surface water
(rain, ice, snow, etc.) is also important. For this reason, watertight surfaces (asphalt, con-
crete, etc.) should be allowed to drain.
In the case of an outside storage yard with gantry crane, the foundations for the
crane runway have to be dimensioned and built in a way that dangerous settlements are
avoided.
For the case only forklifts are intended for storage and release from stock, sufficient sur-
faces should be provided around the piles.
Generally, all roads for loading and unloading as well as all access roads of the storage
yard must be prepared for heavy cargo.
• Water: mainly in the area of the batching plant and cleaning of the molds. In this con-
nection, the treatment of concrete sewage should also be considered.
• Sewage: besides concrete sewage mainly in the area of the sanitary installations
• Electricity: at the beginning of the planning, an electricity concept should be drawn
up, evaluating the main consumers (batching plant, gantry cranes, overhead cranes)
with regard to their power consumption and simultaneous operation. The use of a
transformer station could possibly be necessary.
• Gas/Oil: for operation of the heating system for the segments, the segment factory
and optionally for the concrete aggregates
• WiFi: for data management and production control in the factory, on the outside
storage yard up to installation in the tunnel
• Telephone: communication between batching plant and concreting operator, concrete
demand, etc.
8.4.7 Infrastructure
When planning the segment plant, an infrastructure concept has to be drawn up considering
any logistics and transport of goods, particularly, the following:
At the same time, an unlimited access to any utilities systems; e.g. ground wires/air ducts,
must be provided for from the beginning.
8.4.9 Redundancy
One of the most important topics when it comes to planning of a factory is redundancy. It
is necessary to check which components have an important influence on quality and safety
of production. In the case of failure of a compressed air generator, for example, production
can be continued with a mobile power pack in most of the cases. In contrast, however, when
the only overhead crane of a factory installation fails, the whole production must possibly
be stopped for days or weeks.
The following components are considered to be critical for the production:
• Batching plant
• Carousel system
• Cranes
• Energy supply
• Concrete supply systems
Often a second batching plant is not provided, stating that the plant provides a sufficiently
high output. When the plant is working smoothly this may be correct, however, based on
experience, the batching plant turned out to be the bottle neck. Considering a concrete
plant located far away to help out in case of a failure is not an option as the require-
ments to the fresh concrete are very high (temperature and consistency as well as plasticity
over time).
When it comes to the carousel plant, cleaning and maintenance are often underrated,
not considering that besides provision of critical spare-parts, cleaning and maintenance are
decisive for a high availability of the plant.
Generally, two cranes are required in the production factory. The cranes should be speci-
fied to have the same or at least similar capacities in order to be able to replace each other
in the case of a failure. Although in this case it is not possible to achieve the same output, a
production running at 50% is even better compared to a complete standstill.
Particularly in the case of field factories, a continuous and enough power supply must
be provided. Each failure of the power grid results in a standstill of the plant. Further, safe
operation may be endangered in the case of a power failure when vacuum lifters transport
segments weighing several tons. The time remaining until failure of the vacuum and crush-
ing of the segment is restricted. Experience has shown that an independent power system
(diesel generator) makes sense for at least several areas. Also, power fluctuations appear
(even when the local supplier provides electricity) that may cause damages and failures of
the frequency converters and control units.
The same as to the carousel also applies to the different concrete supply systems (concrete
hopper, conveyor, truck mixer, etc.) cleaning and maintenance contribute to a high avail-
ability. Here, redundancies can also be created, for example, by providing transport mixers
or switches for the bucket conveyor systems.
Figure 8.16 Stationary segment production with crane-b ased concrete distribution system.
A stationary production is said to be unable to achieve the same output as a carousel plant.
A worldwide comparison, however, has shown that the same; partly even higher, production
rates can be achieved with a stationary system. Therefore, this argument is not crucial.
Operation of a carousel plant is always subject to the cycle time of the plant/personnel
and the curing time of the concrete as, in addition, only a fixed number of molds is avail-
able. In the case of a stationary production, however, the number of mold sets can be
increased at any time. Further, the requirements to the fresh concrete are not as high as the
mold does not have to be moved directly after concreting and as demolding of the segment
after curing can be postponed if necessary.
Another unjustified argument is that the quality of the segments is better when using a
carousel plant. It can be confirmed that monitoring of the quality; e.g. cleaning or installa-
tion of the reinforcement cages, is easier, however, this does not mean that quality is higher
in any case.
Maintenance of carousel systems may not be underrated. Choosing this type of produc-
tion, operational safety must be guaranteed at any time. If the carousel cannot move, there
is no output at all. When working with a stationary production, however, production can
be continued with restrictions in the case of a failure of the plant.
The following numbers have become established during the last years as listed in Table 8.1.
Costs for heating and consumption costs are slightly lower with carousel production. The
curing tunnel, which is part of the carousel plant enables the curing temperature to be kept
on a constant level.
Besides the short time required for assembly, flexibility is a further advantage of a sta-
tionary production. The system can be flexibly adapted to existing buildings using available
surfaces optimally.
Yet safety and ergonomic aspects have to be considered when planning a stationary pro-
duction. Special attention should be paid to travel paths for concrete transport and crane
travel with heavy load.
The concrete is often transported using flying hoppers assembled to the hall pillars. These
hoppers are able to transfer the fresh concrete, generally between 2 and 3 m³ (2.6 to 3.9 CY)
Formwork systems for precast segmental tunnel linings 479
very quickly from the batching plant to the place of concreting (mold). The mold is then
filled with a bucket on a rope or a distribution system attached to a crane bridge.
Depending on the geometry of the building and local safety standards, the concrete can
also be filled into the mold directly from a mixer truck.
When implementing a carousel plant, concrete is supplied via a bucket conveyor system.
In this case, the batching plant is located close to the place of concreting.
Summarizing the above, it can be said that, having experience with segment production
and planning to realize future projects, a carousel can offer cost saving in a region with high
wages. The investment can be depreciated on several projects and a well-instructed team can
achieve a high output on a high quality level.
A look at the recent years shows that stationary systems are implemented for approx. 60
to 70% of all projects, whereas only 30 to 40% are realized using carousel systems.
• Demolding
• Transport in the hall
• Rotation/turning
• Equipment
• Evacuation from the hall
• Transport to the outside storage yard
• Storage and retrieval of segments
• Transport to the tunnel /launching shaft /intermediate storage
• Transport to the TBM
• Transport on the TBM
• Installation in the tunnel
The following customized handling devices have been implemented most during the last
years (Figure 8.18):
8.6.1 Demolding
After having achieved a minimum compressive strength of the early age concrete, in general
a minimum compressive strength of 12 to 15 N/mm² (1,740 to 2,175 psi) is required, the
segment can be demolded/stripped.
It is common to use vacuum lifters with suction plates for demolding, enabling the seg-
ment to be lifted safely without damages. However, for the use of a vacuum plate the surface
has to be as even as possible without offsets.
For a safe transport in the hall, safety clamps can be installed which fix the segment after
demolding, thus avoiding a crush of the segment in case of a vacuum failure.
480 Handbook of Precast Segmental Tunnel Lining Systems
Figure 8.18 (a) One-s egment clamp; (b) multi-s egment clamp; (c) gasket gluing frames; (d) turning
clamp; (e) tilting tables; (f ) transport trolley; (g) extrados vacuum lifter; (h) intrados
vacuum lifter; (i) turning table.
Formwork systems for precast segmental tunnel linings 481
8.6.3 Rotation/turning
Before or after intermediate storage, the segments are turned. The intrados side showing to
the bottom (the side that is later visible in the tunnel) must be turned up to the top. There
are two possibilities for turning:
Turning around the longitudinal axis is common when working with partly or fully auto-
mated segment transport and equipment lines. Applying this system, the segment is clamped
on the side, lifted from the transport trolley and turned by 180°.
Tilting tables more and more prevail in practice in the last years. Initially laying on an
“L-profile” intrados down, the segment is tilted with two movements of 90° each with this
method. This simple and fast system offers different ways of application.
8.6.4 Equipment
Unless using a cast-in gasket, the EPDM gasket is optimally applied to the segment after
turning. For this purpose, a gluing agent is applied first, on which the gasket is placed
after a defined open time. In the next step, a gasket gluing frame presses the gasket
to the segment for a period defined by the gasket manufacturer. When applying the
gasket frame, attention must be paid to maintaining the gasket correctly in its designated
position.
Generally, plywood sheets are not applied to the segments until only after turning.
Additionally, many producers use the gasket gluing agent also for application of the ply-
wood sheets.
All systems are essential and should be selected depending on segment dimensions and
weights as well as local conditions (position of the outside storage yard, crane of forklift,
etc). In many cases, a combined transport and equipment line is chosen, which offers fixed
working positions similar to a carousel system.
482 Handbook of Precast Segmental Tunnel Lining Systems
Outside the hall, the segments can be loaded on the transport vehicles by means of gantry
cranes, semi-gantry cranes and overhead cranes or similar. Here, a defined sequence of
stacking can be followed.
Fortified and clearly defined transport routes are necessary in this case for reasons of work-
ing safety, on the one hand, and in order to avoid damages and twisted storage of the seg-
ment, on the other hand.
When it comes to the transport of heavy segments or complete stacks, it is recommended
to use a system consisting of a tractor or container towing vehicle and trailers (heavy-duty
pallets). Multi-service vehicles (MSVs) can optionally be used.
In general, it is necessary to provide large and stable transport routes. Small turning radii
and too steep inclines must be avoided.
Mechanical clamps dispose of a mechanical system starting when the clamp becomes in
contact with the segment and closing automatically when the segment is lifted. The same
operation for disengaging the segments. This simple type of clamp is used very often.
If segment stacks with different numbers of segments need to be lifted, a clamp with
hydraulic or electric operation is recommended in most cases. The clamp can be opened
and closed via remote control. Further, the support system of the clamp can be selected
depending on the number of segments to be lifted; e.g. instead of a stack of three segments,
a stack of two segments or an individual segment can be transported.
Besides the stacking sequence, handling of the key segment should be an object of further
investigation, as its smaller size requires special solutions.
A static proof is necessary for segment clamps in any case. The supports (contact of the
clamp with the concrete) have to be executed in a way to avoid impact of the forces in
the marginal area of the concrete. Instead, forces have to be transferred as far as possible at
the center. The support surface should generally be executed as a polyamide support.
8.6.8 General
For any handling device and any state of construction, the designer has to carry-out static
investigations and calculations considering decisive loads working on the segment. In the
case of an unfavorable stacking or displaced stacking woods, for example, loads may occur
that are not considered in the standard static equilibrium of the segment or ring.
The most common and economical method to perform 3D checks in bigger scales is to
use a laser tracker or laser scanner instrumentation. While laser scanner technology still
fails to meet the accuracy required in most tunneling specifications, contact measurements
using laser trackers deliver acceptable results and are meanwhile an industry-wide standard
to proof the dimensional compliance of molds in mold manufacturing factories across the
globe. Figure 8.21 shows a semi-automatic 3D segment measurement.
Such a system typically comprises a laser tracker to carry out a measurement of all the
contact surfaces, the radii, both the outer and the inner diameters as well as any detail such
as gasket grooves and bolt-hole positions. These measurements are analyzed and processed
via a traceable 3D metrology software platform and comparison is then made between the
measured object and the nominal design. Any report that is made from the measurement of
the tolerances should be as succinct as possible but as comprehensive as necessary to impart
the necessary information.
8.7.2 Measurement regime
The total quality control should be clearly defined as the responsibility of the contractor
who should supervise the segments supplied by the precast company.
Key points to add according to International Tunnelling Association (ITA); ITAtech
Report No.9: Guideline for Good Practice of Fibre Reinforced Precast Segment–Volume
2: Production Aspects (2018) include the following:
1. The reference temperature that the segments should achieve the specified tolerances.
2. The time after de-molding when precision measurement of the segment is acceptable.
3. A clear measurement regime should be specified such as follows:
a. Dimensional measurement control of all molds at manufacturers’ factory including
segment detail such as bolt hole position, gasket grooves etc.
b. Check dimensional measurement control of all molds on the precast production line
(either static or carousel before mass production), this should include a check on any
torsion.
c. The measurement location; e.g. roofed hall with temperatures between 10° and 62°C
(50° and 80°F) should be specified in the construction contract.
Formwork systems for precast segmental tunnel linings 485
Particularly for large diameters, building trial rings is a challenging and risky task for
the workforce in the segment factory. In some cases, it can take up to a week to complete
a master ring and a truck-mounted crane is necessary (Figure 8.22). The concept of virtual
rings (Figure 8.23) may have the potential to replace this tradition by assembling master
rings digitally instead of physically based on a best-fit approach considering the 3D coordi-
nates from laser tracker measurements of segments or segment molds.
Building a virtual ring, a sub-millimeter accuracy can be achieved, the alignment of neigh-
boring circumferential and ring joints observed, and the fit of bolt holes checked. The mean-
ing of the traditional method, on the other hand, despite the significant amount of work and
risks, is considered controversial in the industry as the horizontal position of the ring and
absence of gaskets do not simulate the reality in the excavated tunnel.
To demonstrate the manufacturing capabilities of a segment supplier including concrete
quality and surface characteristics, a master ring erection is mandatory for both parties the
contractor as well as the owner. Subsequent checks against the master ring on the other
hand should be performed by building virtual rings based on the geometrical results of 3D
measurements of segments or segment molds.
Formwork systems for precast segmental tunnel linings 487
Most projects include a requirement in the tender documents that specifies compliance with
the tolerances indicated in one of the several international standards, most of which were
issued prior to the use of fiber reinforcement or the availability of the current measurement
technologies. Many of these international standards already call for sub-millimeter accuracy
on several key dimensions. Ring designers will frequently modify these values according to
project specific requirements.
All these standards are however incomplete with respect to the requirements of current
precision measurement techniques and fail to include full traceability of the segment, its
constituent components, manufacturing process, dimensional accuracy and installed loca-
tion as part of an ongoing quality assurance/quality control process. On some projects there
is only a passing reference to the tolerance and quality control requirements, which enable
the contractor or precast company to bypass the checking that is implied in the standards/
guidelines.
The simple addition of a few clarifying clauses in the tender documents are called for to
significantly improve this. The inclusion of all these requirements in a table or diagrammat-
ically on a single composite diagram will dramatically improve the understanding of the
requirements and assist in their implementation. Please refer to Table 8.3 below.
All tolerances mentioned in Table 8.3 should be subject to the following set of rules:
• It is not allowed that the maximum tolerances add to one another, hence tolerances of
the whole ring are smaller than the sum of the single tolerances.
• All given tolerances refer to a reference temperature of, e.g. 21°C (70°F).
In the case of inconsistencies of two dependent tolerances, the more stringent shall be rele-
vant. Furthermore, tolerances for gasket grooves (TG, WG) shall be in accordance with the
requirements of the gasket supplier.
Traditional quality control methods include pen and paper, or Microsoft Excel based
solutions to document the fabrication of segmental linings in the precast factory. With the
introduction of BIM models (building information modeling) and ongoing digitalization,
the need for reliable and complete data increased significantly to be able to trace from an
individual segment installed in the tunnel back to the raw materials used to produce it.
Traditional methods often fail to fulfil these demands.
Besides the documentation aspect, modern tracking systems support production man-
agers in increasing productivity of their precast factories and connect them to the tunnel
jobsite thus creating comprehensive reporting and dashboards about the logistic and instal-
lation procedures.
8.10.1 Segment labeling
There are various options to label (tag) precast segments and give them a unique identifier
(Figure 8.24). In addition to the limited information (e.g. mold set number and type) pro
vided by the marking plate typically mounted on the mold’s circumferential joint, the most
common way to tag a segment is using two barcode stickers; one at the leading edge and one
intrados face. For the purpose of long-term identification in the tunnel or automatization
steps, synthetic marking plates with or without RFID tags recently became more popular
in the industry.
Regardless of which tagging is applied, the unique serial number always links to a
database that saves the complete history of the segment. Using handheld devices such as
smartphones or barcode scanners, new information can be added to this database and the
segment’s vitae can be reviewed.
490 Handbook of Precast Segmental Tunnel Lining Systems
Figure 8.25(a) and 8.25(b) Dashboard of segment production performance and shift comparison.
To be able to produce high-quality segments with dimensional stability, the molds regularly
have to be checked. For this purpose, the mold manufacturer issues an operating manual
including recommendations regarding type and interval of the inspections. Please refer to
Table 8.4 for summary checklist of inspection and preparatory tasks for segment casting
operations.
492 Handbook of Precast Segmental Tunnel Lining Systems
Decommissioning
Prior to each ese
Commissioning
1 to 2× yearly
Item Activity description operations and verifications
1 Cleaning – with rag and spatula W W W
2 Mold release agent – application W W W
3 Bolt hole formers grease – check gasket (O-r ing) W W W
4 Bolt hole formers – grease threads (if applicable) W W W
5 Spindles – grease W W W
6 Adjusting screw – check for firm fitting W W W
7 Centering screws – cones and grease W W W
8 Sealing/g askets – clean, check, exchange if necessary W W M M
9 Vibrators – visual and auditory check W W W M
10 Bolts for vibrator mountings – checking fixations M M W
11 Bolts, hinges, joints. axles and pivots – M M M
grease visual check of welded seams
12 Limit stops, locking and safety pins –clean and check M M/E W
13 Rubber block supports – clean and check M M W
14 Tension springs – check for damage M M M
15 Welds and welded joints – check M M W
16 General check of conditions – check M/E M/E M/E
17 Vibrators – check direction of rotation M M
18 Compressed air feed – check M M
19 Compressed air distribution – check M M
20 Anti-r ust agent – apply M W
21 Wheels – check M M M
22 Bearings – check M M W
Table Legend:
W Worker operator
E Electrician
M Mechanic, Foreman
Special Notes:
1
During the first use of the molds after assembly has been completed, there is an acute danger that
threaded connections can work themselves loose.
2
After commissioning, all threaded connections must be maintained and are the responsibility of the cus-
tomer and/o r operator both in term of maintenance and costs.
3
Consider additionally, maintenance instructions in suppliers’ documentation package.
Formwork systems for precast segmental tunnel linings 493
In case these measures show deviations from the nominal measures given by the mold manu-
facturer, it is recommended to measure the mold in detail using a 3D laser tracker.
In the field of segment production, innovations and improvements were brought to market
maturity and count among the state of the art in the meantime:
Recent requirements particularly focus on the reduction of labor –due to the lack of getting
labor –the costs for plants, wages (labor costs) and operation as well as increasing safety
for the workers. The following innovations are currently investigated and implemented on
the market:
For this purpose, a bend-proof steel portal with an overhead traveling crane has been
installed on top of the working line (to be compared with an assembly line in the automotive
industry). On this crane, a six-axle industrial robot is installed headfirst. The robot and the
overhead traveling crane position themselves according to X-Y-Z coordinates and provide
a repetitive accuracy of less than half of a millimeter. The robot has been equipped with a
quick coupling system for the use of different tools. The tools travel together with the robot
and the crane. Figure 8.26 shows an example of a robot-supported working line.
Safety installations
The complete working zone of the robot is protected with a fence. The access doors are
integrated in the control system. Within the fenced area, separate cells are defined, which
are protected by means of light barriers; i.e. persons working within the fenced area cannot
enter the zone where the robot is working in that moment.
This two-shell construction method, on the one hand, requires a large tunnel cross section
and a long construction period, on the other hand, as the inner shell cannot be installed
before completion of the outer shell. Further, all joints of the sealing lining require a gas-
tight welding.
When implementing a one-pass lining system with so-called Combisegments®, the tun-
nel cross section (excavation) can be reduced, the time-consuming and risky welding is no
longer necessary, thus resulting in a significant reduction of the construction time.
The Combisegments® consist of well-proven products used in the tunneling industry
for years:
In the production factory, the HDPE panel and the EPDM gasket are put in a large alu-
minum injection mold and over-molded with pdcpd. The product, a strong panel, can easily
be inserted in the segment mold.
The panel is concreted with the segment and shows a very good compound with the
concrete and a high pull-out force after curing. The segments with Combisegments®
panels are stored, transported to the tunnel and installed in the same way as standard
segments.
By compressing the EPDM gasket, on one hand, water extrusion to the outside is avoided
and, on the other hand, it offers a protection of the joint sides towards the sulpurous gases.
The inner surface of the segment itself is protected against corrosion caused by the gases by
means of the HDPE.
Formwork systems for precast segmental tunnel linings 499
Figure 8.33(a) and 8.33(b) Tunnel lined with Combisegments® and mold with Combisegments®
inliner.
The interceptor sewers are built quite close to the surface in general. Therefore, the
outer water pressures caused by ground water can mostly be neglected (<1 bar) (14.5
psi). However, in case of higher water pressures from outside, the Combisegments® can be
drained with the help of special drain valves. This means that the external water pressing
from outside is led into the tunnel for relief.
An alternative possibility for application of the Combisegments® panels is protection
of the extrados side, i.e. the outer side of the segment. In the case of a high impact of
chloride, for example, a permanent concrete protection could be achieved. See Figure 8.33
for examples of CombiSegments usage)
presented before, some projects for recent segment production are shown in the following
with facts and figures.
• Concreting station with concrete hopper, gates, automatic mold cover and con-
trol system
• Reinforcement supply system with clamp, monorail with lifting hoist, reinforcement
cage feeder
• Curing tunnel with heating system
• Two vacuum lifters with (Figure 8.35) a capacity of 16 mt (18 tons)
• Evacuation line including deposit blocks, a tilting table 2 × 90° with a capacity of 16
mt (18 tons), a gasket gluing frame
• Two mechanical clamps with a capacity of 16 mt (18 tons)
The first carousel production line started operation in October 2009, running at full pro-
duction on the 20,000 m² (4.95 acre) site in March 2010. The efficient carousel production
kept the segments, some weighing up to eleven tons, in continuous motion 24/7 to ensure
just-in-time segment production for tunneling. The segment production plant in Sochi was
the world’s largest of its kind at that time.
• 20 sets of segment molds for stationary production (concreting with truck mixer)
• Segment handling equipment (Figure 8.40)
• Design of the complete segment production plant
• Factory set-up including site preparation, steel building (Figure 8.38)
• MEP works and building concrete works
• Overhead cranes, gantry cranes, rails and transport trolleys
• Compressed air station
• Segment dimensional system (SDS): modular segment production and logistics man-
agement system
Due to the careful planning, the segment factory could be erected in the desert sand in
10 months only.
8.13.3 Albvorlandtunnel, Germany
For lining of the of the approx. 8 km (4.9 mile) long railway tunnel in Germany, the pro-
duction company installed a stationary production plant with (Figure 8.41) 77 molds and
an elaborate concrete transport and supply system in an existing building close to the
tunnel portal. The concrete logistics system included a flying hopper running on a gantry
crane along the longitudinal axis of the hall and a concreting bucket movable on a crane
(Figure 8.42) along the transverse axis of the hall to fill the molds, which were equipped
with compressed-air vibrators.
For a perfect curing result, the mold supplier installed a combined heating system including
direct heating under the molds (finned pipes) with individual control to balance temperature
fluctuations as well as an overall heating system for the hall.
After demolding with a vacuum lifter (with safety clamp), the segments were placed in
the pre-storage area. After turning of the segments from intrados to extrados by means of a
special turning device the gasket was applied with the help of a special gasket gluing frame
(Figure 8.43). Following this, a mechanical segment clamp put the segments on a trailer
504 Handbook of Precast Segmental Tunnel Lining Systems
to be transferred to the close tunnel portal, where the segments where loaded on a multi-
service vehicle to enter the tunnel. See Figure 8.44 for transport of segments.
The segment factory for the Albvorlandtunnel had been built, planned and equipped in
close cooperation between the construction company and the manufacturer of the segment
production equipment. The plant was ready for production after six months of planning,
manufacture and installation only.
includes the segments of 8.2 mt (9.1 tons) as well as the invert segments of 13.4 mt (14.8
tons), which are produced on two carousel systems with 112 molds in total. Despite the
high occupancy of more than 1,300 production cycles, the molds kept to the tolerances of
up to 0.5 mm 0.012”). The tolerances were proven by means of 3D measurement of the
segments using a laser tracker.
The segment production with two carousel plants with 8 sets (48 pieces) of molds each
allowed consistently high production rates. Furthermore, the modular segment production
and logistics management system, Segment dimensional system (SDS), provided a reliable
basis for quality management on the jobsite. With this system, each segment can be moni-
tored from the pouring of the concrete to its installation in the tunnel.
After demolding with a vacuum lifter and pre-storage in the hall in intrados position, the
segments were turned, fitted with the gasket and transported to the outdoor storage area
by means of an automatic evacuation line with scissor lifts running on rails to transfer the
segments between the different positions. See Figures 8.46 and 8.47 for the carousel plant
and automated segment evacuation lines.
Formwork systems for precast segmental tunnel linings 507
ACI Committee 533. (2020). ACI 533.5R- 20: Guide for Precast Concrete Tunnel Segments.
Farmington Hills, MI: American Concrete Institute.
ACI Committee 544. (2016). ACI 544.7R-16: Report on Design and Construction of Fiber-Reinforced
Precast Concrete Tunnel Segments. Farmington Hills, MI: American Concrete Institute.
ACI Committee 544. (2017). ACI 544.2R-17: Report on the Measurement of Fresh State Properties
and Fiber Dispersion of Fiber-Reinforced Concrete. Farmington Hills, MI: American Concrete
Institute.
ACI Committee 544. (2017). ACI 544.9R-17: Report on Measuring Mechanical Properties of Hardened
Fiber-Reinforced Concrete. Farmington Hills, MI 48331: American Concrete Institute.
ACI Committee 544. (2018). ACI 544.4R-18: Guide to Design with Fiber-Reinforced Concrete.
Farmington Hills, MI.: American Concrete Institute.
American Society of Civil Engineers (ASCE), Guidelines for Tunnel Lining Design, Prepared by the
Technical Committee on Tunnel Lining Design of the Underground Technology Research
Council, Edited by T. D. O’Rourke. ISBN: 0-87262-402-1
AFTES Guide Specifications, The Design, Sizing and Construction of Precast Concrete Segments
Installed at the Rear of a Tunnel Boring Machine, No.GT32.R2A1, Association Francais des
Tunnels et de L’espace Souterrain (AFTES) (1999).
British Standards Institute. (2008). BS EN 14651:2005–Test Method for Metallic Fibre Concrete–
Measuring the Flexural Tensile Strength (limit of proportionality (LOP), residual) (+A1:2007).
London: British Standards Institution.
British Standards Institute. (2006). BS EN 14889-1:2006–Fibres for Concrete. Steel fibres. Definitions,
Specifications and Conformity. London: British Standards Institution.
British Tunnelling Society (BTS) (2004). Tunnel Lining Design Guide, Institution of Civil Engineers,
Thomas Telford, , London, England. ISBN-13: 978-07277-29-866, ISBN-10: 072-77298-61
British Standards Institute (BSI) (2016). Tunnel Design–Design of Concrete Tunnel Lining Code of
Practice, PAS 8810:2016, British Standards Institution (BSI). ISBN 978-0-580-88170-1
508 Handbook of Precast Segmental Tunnel Lining Systems
International Federation for Structural Concrete (fib), Precast Tunnel Segments in Fibre-Reinforced
Concrete–State of the Art Report, No. 83, ISBN 978-2-88394-123-6, October 2017), ISBN
978-2-88394-123-6, October 2017)–pdf format
fib Special Activity Group 5. (2010). Bulletin 55- 56: Model Code 2010– First Complete Draft.
Lausanne: International Federation for Structural Concrete (fib).
fib Working Party 1.4.1 Tunnels in Fibre-Reinforced Concrete. (2017). fib Bulletin 83 Precast Tunnel
Segments in Fibre-Reinforced Concrete State-of-the-Art Report. (A. Meda, Editor) Lausanne,
Switzerland: Fédération International du Béton (fib).
ISO/TC 17/SC 17 Steel Wire Rod and Wire Products. (2013). ISO 13270:2013–Steel Fibres for
Concrete –Definitions and Specifications. Geneva, Switzerland: ISO, the International
Organization for Standardization.
INDUSTRY GUIDELINES
National Precast Concrete Association (NPCA). (20 Jan 20). NPCA Quality Control Manual For
Precast Concrete Plants 14th Edition. Carmel, IN 46032: National Precast Concrete Association
(NPCA).
Precast/Prestressed Concrete Institute. (1999). MNL-116-99: Manual for Quality Control for Plants
and Production of Structural Precast Concrete Products, 4th Edition. Chicago: Precast/
Prestressed Concrete Institute.
TECHNICAL PUBLICATIONS
Allen, C. (October 2009). Fibre Decider; Tunnels and Tunnelling International. Tunnels and Tunnelling
International, vol. 2009, pp. 35–37.
Bakhshi, M. (2015). Design of Segmental Tunnel Lining for Serviceability Limit State, AASHTO
SCOBS T- 20: Technical Committee for Tunnels April 2015 Meeting. Saratoga Springs,
New York .
Bakhshi, M., and Nasri, V. (2017). Water Infiltration and Crack Control for Tunnel Concrete Lining.
Proceedings of the World Tunnel Congress 2017–Surface Challenges–Underground Solutions
(pp. 1–10). Bergen, Norway: ITA–AITES.
Bekaert-Maccaferri Underground Solutions. (2018). Info Sheet: What About Stray Currents
With Steel-Fibre Reinforced Concrete. Ghent, Belgium: Bekaert-Maccaferri Underground
Solutions.
Formwork systems for precast segmental tunnel linings 509
de Rivaz, Benoit. (2016). Design Approach Assisted by Test. Ghent, Belgium: Bekaert-Maccaferri
Undergound Solutions.
de Rivaz, Benoit. (2019). Characteristics of Steel and Polymer Based Fibre Concrete. Zwevegem,
Belgium: NV Bekaert SA.
de Rivaz, Benoit. (2020). Tunneling Applications: Concrete Segment Reinforcement. Zwevegem: NV
Bekaert SA.
di Prisco, M., Colombo, M., and Dozio, D. (2014). Fibre-Reinforced Concrete in fib Model Code 2010;
Principles, Models and Test Validation. Structural Concrete 14 (2013), No. 4, pp. 342–361.
Edvardsen, C. (October 2010). The Consultant's View on Service Life Design. In K. van Breugel, Guang
Ye, Yong Yuan (eds.), 2nd International Symposium on Service Life Design for Infrastructure
(pp. 249– 264). Delft, The Netherlands: RILEM– International Union of Laboratories and
Experts in Construction Materials, Systems and Structures.
Gerhard Vitt. (2011). Understanding Steel Fibre Reinforced Concrete: Dramix (Version 1.0 ed.).
Zwevegem, Belgium: NV Bekaert SA.
ITA Working Group 2– Research; Bakhshi, M; Nasri, V.; Main Authors. (April 2019). ITA
Report No.22–Guidelines for the Design of Segmental Tunnel Linings. Longrine, Avignon,
France: AITES/ITA.
ITA Working Group 2–Research; Tiberti G.; Chiniottri E.; Pizzari G., Main Authors. (April 2016). ITA
Report No 16–Twenty Years of FRC Tunnel Segments Practice: Lessons Learnt and Proposed
Design Principals. Avignon, France: AITES/ITA.
ITAtech Activity Group Support; (2016). ITAtech Report No.7; ITAtech Guidance for Precast Fibre
Reinforced Concrete Segments–Volume 1: Design Aspects. Longrine: International Tunnelling
and Underground Space Association.
ITAtech Activity Group Support; (2018). ITAtech Report No.9: Guideline for Good Practice of
Fibre Reinforced Precast Segment–Volume 2: Production Aspects. Longrine: The International
Tunnelling and Underground Space Association.
Latson, J. (22 June 15). The Burning River That Sparked a Revolution. Retrieved from Time.
Com: https://time.com/3921976/cuyahoga-fire/
Meda, A., and Rinaldi, Z. (July 2017). Beam Tests on Fiber Reinforced Concrete According to EN
14651 and ASTM C1609. Rome, Italy: University of Rome–Tor Vergata.
Meda, A., Rinaldi, Z., Spagnuolo, de Rivaz, B., and Giamundo, N. (January 2019). Hybrid Precast
Tunnel Segments in Fiber-Reinforced Concrete with Glass Fiber Reinforced Bars. Tunnelling
and Underground Space Technology 86, pp. 100–112.
Meson, V. M. (2019). Durability of Steel Fibre Reinforced Concrete in Corrosive Environments–Ph.D.
Thesis. Kongens Lyngby, Denmark: Department of Civil Engineering, Technical University of
Denmark.
Pascal Guedon (Arcadis) Working Group Leader. (Juillet/Août 2013). Recommendation of AFTES
No.GT38R1A1– Design, Dimensioning and Execution of Precast Steel Fibre Reinforced
Concrete Arch Segments. Tunnels et Espace Souterrain–No. 238, Association Française Des
Tunnels et de L’espace Souterrain, pp. 312–324.
Professor Meda, A., and Professor Rinaldi, Z. (2015). Tests on Precast Tunnel Segment in Concrete
Newly High Tensile Strength Steel Fibers Dramix 4D 80/60BG. University of Rome "Tor
Vergata", Civil Engineering. Rome: TERC–Tunnelling Engineering Research Center.
Rack, J. (20 August 14). A Brief History of Sustainability. Retrieved from The World Energy
Foundation: https://theworldenergyfoundation.org/a-brief-history-of-sustainability/
Rossi, P. C.-P. (18 April 16). SFRC Durability in a Chlorinated Environment. Tunnel Talk (Direct by
Design), pp. 2.
Tang, K. (March 2020). Corrosion of Steel Fiber Subjected to Stray Current Interference. ACI
Materials Journal, vol. 117, no. 2, pp. 99–112.
Tunnel Talk Reporting. (25 April 19). TunnelTech: First Use of Macro-Synthetic Fiber Reinforced
Concrete in Segments in the USA. TunnelTalk.
510 Handbook of Precast Segmental Tunnel Lining Systems
TunnelTalk Reporting. (March 2015). TunnelTech: Lab Comparison of Steel vs. Synthetic FRC
SegmentsTests and Results; by University of Rome Tor Vergaata. TunnelTalk.
United States Environmental Protection Agency, U. S. (17 September 20). Learn about Sustainability.
Retrieved from EPA.Gov: www.epa.gov/sustainability/learn-about-sustainability
Vandewalle, M. (2005). Tunnelling is an Art. Zwevegem, Belgium: NV Bekaert SA.
VMT–Segment Documentation System SDS. Modular Production and Logistics Management: VMT
GmbH GB | Segment Documentation System SDS (vmt-gmbh.de).
Chapter 9
9.1 INTRODUCTION
The goal of this chapter is to introduce and sensitize the reader to the key elements of the
precasting of tunnel liners –a series of complex multidisciplinary activities that require
planning, rigor, discipline –it is a lot more complex than meets the eye. Production of pre-
cast segmental tunnel liners is to TBM mining operations as tires are to Formula 1 racing
motors and automobiles; a less glamorous and spectacular element, as well as relatively
modest in price compared to the car and motor (the TBM), but everything rides on them
and the success or failure of the TBM operation is heavily dependent on them. Within this
chapter, we will try to briefly touch on select topics of interest to provide a background for
the reader’s information.
Note to the reader, that the following chapter regarding the process of fabricating seg-
ments, is written in an informal style, as the subject matter discussed is done so from a
production person’s point of view, skimming and touching many topics that could deserve
a chapter to themselves, and this producer’s point of view is one that the designers and
stakeholders in the industry must account for to guarantee successful future projects. There
is rich information contained in this chapter, segment manufacturing information that does
not exist in this holistic form in the current literature. This chapter is geared towards inform-
ing the young upcoming generation of tunnel industry workers, with the goal of transferring
knowledge about the precasting operations and knowledge leads to confidence and com-
petence benefiting the industry. Typical precast segments are shown below in Figures 9.1
and 9.2.
9.2 GENERAL SUMMARY
For an overview on estimating costs and schedule for precast tunnel operations and running
a precast tunnel liner operation, there are many systems involved that require many talented
people with skills and judgment and it is a tour-de-force to keep operations smooth. Bidding
a job and the consideration of the depth and complexity of the various systems required will
humble the most experienced senior estimator because on top of everything to study, most
of the purchases, system set-ups and operations must be predicted, with risks assessed over
the course of two to three years with volatile prices of equipment and raw materials.
DOI: 10.1201/9781032675541-9
512 Handbook of Precast Segmental Tunnel Lining Systems
A schedule delay, when factoring in the extra costs of overhead, indexed material costs
and incremented material costs, can add up to hundreds of thousands, and even millions
of dollars of extra costs. The precaster must ensure to measure risks, and account for them
or qualify them in the quoting process. This is an important element that contractors and
owners must understand when they run their own risk analysis.
In 2022, we cannot forget to mention the impact that Force Majeure events have on a
precast tunnel liner manufacturing supply chain. The effects of pandemics and wars (which
will continue to plague humankind) are touching most aspects of the production as tunnel
liner jobs are material heavy, they rely on international suppliers, who source their raw
materials worldwide (some sources of raw material are disappearing and the law of supply
and demand, with the scarcity, increases costs and limits opportunity), which in turn means
a dependence on sea-shipping, in which we have seen container costs doubling and tripling.
All major domestic products suppliers (cements, steels, aggregates) are feeling crunches and
breaking contractual agreements and increasing prices. Energy costs are increasing drastic-
ally, affecting transport costs and operation costs.
Many suppliers are breaking contracts, refusing to honor contracts, knowing that they
are guaranteed to lose money on a supply. The other important impact that the Force
Majeure events has is on the delivery time of equipment, materials, supplies and even com-
modities. Supply chain delays due to shortages of manpower, vital parts/components, com-
mon parts, get compounded during the delivery/transportation stage with the world logistic
systems, a once well-oiled machine now tilted.
The number of shipping vessels or sea containers have decreased, and the result is that
shipping confirmations are cancelled, and rescheduled several times last-minute. If that were
not enough, the situation in the major ports is affected with delays to unload and process
goods, and then finally, further delays await with trucking shortages backing up the ports.
Trucking and driver shortages have a tremendous impact on precast operations. This
includes everything that comes in or out of a precast plant, unless a rail line or barging is
available, is transported by truck. These Force Majeure events are a serious issue that the
owners need to address in the present moment and in future contracts upfront. The world
events happening at the writing of this chapter in 2022, and their effects on the precasters of
tunnel liners will most probably be the new normal in years to come with continued global
conflicts, probable global pandemics, prolonged climate change and coming demographic
changes. Understanding causes and effects helps to better plan major projects, to manage
them efficiently, to limit risks (and equitably allocate or share risks) and surprises, and to
avoid potential litigation.
Bidding precast tunnel liners is like bidding moving targets. And the challenge is always
to find a suitable place to set up operations. At times, one can copy and clone from existing
operations, at times one must set up from scratch. The costs of each set-up vary tremen-
dously and thus it makes some of us chuckle when some people brandy about costs per liner
foot for segmental ring. The answer is always; it depends.
9.2.2 Historical background
A good place to start would be to take a moment to peruse the book, History of Tunnelling
in the United States, by David Klug, Michael Roach, Colin Lawrence and Brian Fulcher. In
this book, one will come to realize that that as shown in a borrowed slide from this book
that what we think is a recent technology, actually was developed in the United States
more than 100 years ago. Note that in 1906, a US Patent No.830,345 by A.F Mattson was
recorded for what in effect are precast concrete tunnel liners. Please refer to Figure 9.3 for
the original patent document.
There are many other examples of early tunneling techniques in Europe and Asia. For
example, the Metrosud tunnel in Naples, Italy in 1982 was the first application of steel fiber
reinforced concrete (SFRC) segments used on a significant public works project.
The rebirth of modern use of precast concrete tunnel liners –installed with an erector
in a modern TBM was pushed forward in the 1980s by American tunnel contractors who
used them as first pass primary lining, commonly called “junk liners”. The contractors
were successful with the use of this multiple pass lining (as initial support), waterproofing,
cast-in-place final lining, method that was commonly used with geological conditions that
permitted this type of tunneling.
When owners and associated system programs required that the tunnel alignments be
driven in soft running soils or in mixed face conditions, the North American tunnel industry
looked to Europe and Asia, to where they were building tunnels in these challenging geo-
logical conditions using one-pass precast tunnel linings with bolted connections and water-
proofing seals in conjunction with tunnel boring machines (TBMs) that controlled the
geological conditions while provide safe working conditions.
Within the one-pass tunnel liner systems, there are two subcategories:
• Transportation tunnels, which will see a high volume of human or vehicular traffic
• Utility and water/wastewater tunnels, which are part of infrastructure systems
Because transportation tunnels present a direct threat on human life, as opposed to the fluid
transport tunnels, transportation tunnels tend to have stricter design parameters, but in
reality, both types of systems merit the same attention and there is no reason to not ensure
that the specifications and fabrication of tunnel liners for either system be to the same
quality standards.
The forming systems used to make the segments have evolved over the years. Originally
the segments were formed on curved concrete bases that had movable sidewalls (made of
steel or wood as shown below in Figures 9.4 and 9.5). These are still used in certain applica
tions. The accuracy and precision of these systems, in the right hands, was good but even-
tually came the evolution to steel formwork systems. Steel forms are resilient, offer better
precision and accuracy, allow a larger variety of cast-in elements, and permit quicker set-
ups during plant operations. See Figures 9.6 and 9.7 and refer to Chapter 8, for additional
details on this subject.
Fabrication of precast segmental tunnel linings 515
Figure 9.3 A.F. Mattson 1906 Patent for precast tunnel lining segments.
Note: This patent describes one of the earliest precast concrete segmental lining designs devel-
oped in the United States for shield-d riven tunnels in soft soils.
516 Handbook of Precast Segmental Tunnel Lining Systems
Figure 9.4 Segment mold with concrete base and wood sidewalls (1980s).
Note: Example of an early, high precision precast mold used for bolted and gasketed segmental
tunnel liners.
Figure 9.5 Segment mold with concrete base and wood sidewalls with rebar cage.
Note: Example of an early segment design with rebar reinforcement placed in the mold.
• It is a major challenge to keep the housekeeping under control during the operations
and maintenance of systems
• Filtering systems have trouble keeping up. Layers and coating of dust and debris make
equipment and parts overheat or run hotter than design temperature. As a result,
system components often wear out prematurely with heavy use, and equipment that
often sits in idle mode is often the greater target of the corrosive environment
• These roughest of environmental conditions for equipment (mechanical and elec-
tronic) are rarely met with such variety in any industrial setting and at times military
grade components are the only way to go, and even with that, equipment break-
downs, failure and troubleshooting and fixing-on-the-fly are part of everyday life in
a precast plant.
Keep in mind that it takes quite a good level of competence and expertise to run a precast
tunnel liner operation including the following essential activities.
Precast plant operators get a little offended when someone criticizes an operation without
consideration of all the issues and potential causes.
With small diameter tunnel liners, it is easier to fit many mold sets on a floor layout and
they are relatively cheaper than large diameter tunnel molds that also gobble up two to three
times more floor space.
There is a calculation that needs to be made regarding working with fewer mold sets on
two shifts or more mold sets (which have a considerable capital cost) on one shift.
It should be noted that if producing on one shift is possible, the cost of the concrete can
be reduced in the sense that one would have 24 hours to reach the stripping strength. With
a normal fixed-mold operation or a carousel operation where one would turn the molds
twice (or more per day), the concrete design mix is driven by the early strength that must
be achieved in about 6 hours or so, hence a richer mix (more costly) is required. However,
a richer mix well designed, has better durability characteristics.
The stationary mold production arrangements as shown in Figures 9.11 and 9.12 have
smaller capital costs (no semi-automated carousel system expense) but there is one disad-
vantage; the output of the plant is limited to at best cycling the number of molds on the
plant floor twice a day. In certain circumstances, this system may not meet the TBM con-
tractor’s schedule or peak mining schedule. The segments are typically cured by covering
the stationary molds with tarps and then injecting steam under the tarps from steam pipes
located under the molds.
Please refer to Chapter 8, for in-depth details and photos of both systems of production.
depending on the cementitious materials used, there are maximum internal concrete tem-
peratures that must be respected by North American codes –between 70 and 77°C (158
and 170°F). A primary kiln will usually have two or more temperature zones, with zones
having higher set point temperatures as the molds travel through. Thus, when preset and
internal temperature restrictions are factored into the design, along with the fact that
the specifications in North America call for a slow acting type-II cements (now being
replaced by environmentally favorable type-1L cements) and steam curing, a carousel
will require more molds and a larger primary kiln so that the segments are metered out
at about a 6-hour interval.
The advantage of the carousel system is that it can be run continually, if need be 24 hours,
7 days per week, with segments spending about 6 hours in the primary curing and coming
out at a regular interval (say between 10 and 15 minutes). It must be understood that 24/7
is a theoretical principle because real life gets in the way, and there is equipment mainten-
ance, break-down downtime, manpower exhaustion and inefficiency, etc. to consider, but
the possibility of running in a quasi-continuous manner exists. Please refer to Figure 9.13
for an image of a modern carousel arrangement.
Another advantage of a carousel is that it is possible, with considerable effort, to integrate
two different productions on the same manufacturing line/operation. The logistics of run-
ning two jobs on the same line are demanding as different mix designs may be involved, but
the carousel system offers this flexibility.
The capital cost of carousels gets offset by the volume of segment-rings required for
the project and the possibility of running several projects out of the same plant. Also, the
additional capital cost of a carousel must be measured against the savings on labor that
524 Handbook of Precast Segmental Tunnel Lining Systems
Below we will provide a brief introduction to both main types of reinforcing materials.
Fabrication of precast segmental tunnel linings 525
Note the release agent sheen on the steel formwork elements. Mastering the choice and
specific/correct application of the release agent is crucial to achieve a good durable concrete
finish and aids in the maintenance of the molds. Several different release agent products
for specific areas and steel treatments are part of the precaster’s release agent arsenal. This
little-known subject could merit its own chapter because the esthetics are always an element
526 Handbook of Precast Segmental Tunnel Lining Systems
of visual concern for precasters, engineers and clients, and concrete finish may in some
instances be an aspect of the overall durability of the precast elements.
Cages assembled with tie wire must be well designed and tied with great care. If one
uses type-706 weldable rebar (in USA market), per ASTM A706 Standard Specification for
Deformed and Plain Low-Alloy Steel Bars for Concrete Reinforcement), one can tack-weld
the components in strategic locations that will provide good rigidity. One can assemble the
components solely with weld tacks or with a hybrid solution of tacks and tie-wire. At times,
standard ASTM A615, Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement,
rebar may be allowed to be tack welded for assembly purposes. In Europe and Asia and
other parts of the world, steel wire products are the norm, with high carbon drawn out steel
that is weldable, such as the ASTM A1064, Standard Specification for Carbon-Steel Wire
and Welded Wire Reinforcement, Plain and Deformed, for Concrete.
Generally, the cages that result may be a combination of components of different grades,
shapes, loose bars, welded components. The components are assembled in precision jigs by
tack welding (or they could also be tie-wire assembled). The great advantage using deformed
wire are the following:
• If using Grade 60 reinforcing steel (60 ksi) (415 MPa) steel; (European most used
equivalent is 500 MPa steel) and comes up with a desired number of required reinfor-
cing bars, one will be designing with a specific cross-sectional area of reinforcing
steel. But in the case where the reinforcing is available in Grade 80 reinforcing steel
(80 ksi) steel; (European equivalent 550 MPa steel) grade, the equivalent area will
be 60/80 =0.75, resulting in a 25% reduction in the amount of reinforcing steel
required.
• By using the deformed wire products, 25% of the steel weight required to reinforce
the segment rings is saved and on a typical project and it could mean saving thousands
of tons of steel and such savings go to the owner and taxpayer on public projects. And
it could be argued that it is an ecological advantage too because our natural resources
can be put to the better use. Many but not all reinforcing designs and configurations
lend themselves to these savings by reducing weight afforded by the increasing wire
strength.
528 Handbook of Precast Segmental Tunnel Lining Systems
Wire bar sizes are sized as per the final area of the wire that is drawn. The nomenclature
is designated as dXX. For example, a d25.4 bar would have an area of 0.254 in2
(163.87 mm2). The maximum size of bar that can be made is a d31, 0.31 in2 (200 mm2).
Please refer to Figures 9.15 and 9.16 below that illustrate deformed wire products in the
precast plant and placed in a segment mold. Additional welded wire products are shown in
Figure 9.17.
9.5.4 Reinforcing design
It is usually best for the Tunnel Liner Design Engineer to show the reinforcing as classic
reinforcing and let the precaster come up with the reinforcing equivalence scheme as there
are many ways to achieve the intended result. Each precaster may have preferences on which
type of assembly systems they prefer, based on a variety of factors, such as facility layouts,
expertise with the assembly methods, industry supply chain issues and opportunities, etc.
There are many embedded elements in a mold and these embedded elements are attached
to steel components that protrude into the mold sidewalls and bottom; there are tapered
hole formers for bolt holes and shear cone reservations to contend with and covers must
be respected at each of these pinch points and thus the design of a reinforcing cage is very
complicated. There is also the fact that the sidewalls and end walls are not at a perfect 90°
to the mold bottom surface and this also adds complexity to the design of the cages and
cage assembly jigs.
for water to get to the rebar, however, nowadays, there are many different chair geometries
and polymer type systems, with chemistries and behaviors that are available to control these
effects, in consideration of the relatively low concrete curing temperatures. The tunnel liner
design engineer decide on this issue, case by case. In some circumstances with extremely
high reinforcing ratios, the weight of the cages is such that there is little choice but to use
polymer chair systems. Other times, because of the geometry of the cages, the plastic chair
systems offer better stability of the cage during casting vibration. In general, there is a wider
range of choices of polymer chair systems, with a more limited range of choices for concrete
chair systems.
Additionally, the engineers and new technology suppliers must keep this in mind and
design systems that can easily be put into the molds so that the industrial flow of work is
not impacted by the punctual operations related to the discrete installation and monitoring
of the specialized embedded sensors. Moreover, many of these embedded sensors require an
activation procedure that requires a piece of electronic equipment to be rubbed against the
area over which the sensor is embedded. With the precaster’s production segment stacking
procedures and arrangements, this extra instrument activation process can easily impact the
regular production rates because of the following considerations.
Understandably, a lot of creative engineering and design are going into the addition
of these systems in the quest for Big Data Collection, but little thought is being given on
how to implement this technology in an industrial production setting. Without proper
planning, a precast segment production can be reduced as much as 80% due to the dis-
continuous additional operations: this is very costly, and the extra costs must get passed
onto the owner. Recent experience has shown that the client, owners and engineers are
often astounded at the actual additional costs for installation of embedded instruments at
the precast plant.
get it right and keep the cages secure. See Figures 9.20 and 9.21 for examples of how a steel
reinforcing cage is tied down.
floor layout will typically consist of a minimum of six to eight jigs with the accompanying
welding machines and storage racks.
The storage of steel reinforcing components alongside of the assembly jigs is critical and
there is always the complexity of the large number of components with certain jigs: for
instance, with a counter-key segment that has one square end and one skewed end where
one can have up to 25 to 30 bars of different lengths to deal with for just one cage. In these
circumstances, at times it is more efficient to order several bars of the same length and cut
them to size and field fit, but this is going to increase the tonnage on the job but may offset a
combination of labor, staging area needs, and operation costs. It may raise the overall price
a little but simplify the operation and may lower the overall cost of the operation and it
would be a choice that the precaster makes.
Special considerations in terms of classic steel reinforcing schemes
A word of caution to those who want to estimate the cost of steel classic reinforcing designs
simply by measuring theoretical lengths of bars on a design concept drawing: this can get
you close but you may also be far off in terms of the actual quantity, costs, and price for the
job. There are a few factors to give consideration to that affect the total final cost of reinfor-
cing steel, such as the following:
• Waste factors coming from the manufacturing process (i.e. cutting and bending and
steel cutouts to avoid interference with embedded items).
• Application of CRSI (Concrete Reinforcing Steel Institute) industry practices based on
its Manual of Standard Practice, as it relates to detailing and the calculation finished
product billing.
• Waste and costs associated with the Engineer of Record (EoR) special non-industry
standard tolerances.
• Waste and efforts required to build, test and modify assembly jigs in order to assemble
reinforcing cages to EoR special non-industry specifications.
• Waste and efforts to run full size test steel cages, and extra costs related to small pro-
duction runs of specialty steel products.
With certain designs and large volumes/tonnage, as is the case in the repetitive cage tight
tolerance design configurations of tunnel liners, the consideration of these factors can sig-
nificantly increase the overall cost relative to the cost number derived from actual manufac-
tured bar length calculations.
In every operation there is cut-off waste (drops) from cutting and bending of reinfor-
cing and some shaped reinforcing elements have more than others. There is no universal
“one-size-fits all” waste factor. As an example, if reinforcing is coming in 40-foot lengths
(≈12 meters), and stirrups are being made in an automated straightening/bending machine,
because of the lengths of the bar required for a particular stirrup, one could be left with
39 inches (≈1 meter) of a useless piece of reinforcing if the minimum bar length required for
the stirrup is 42 inches (≈1.066 meters).
One must consider that in certain markets, the supply of reinforcing steel may be in
lengths that are disadvantageous with respect to being left over with cut-off “drops” that
must be considered scrap steel. There may be bars that are only available in 20-foot (6.1
m), 40-foot (12.2m) or 60-foot (18.3 m) lengths and the lengths available may create more
waste than if there was a choice in the supply. At times, the drop or left-over short bar can
be re-used in certain instances (with further handling and work such as cutting and bend-
ing), at times, it cannot. If coils or bobbins of wire reinforcing are available, cut-off waste
534 Handbook of Precast Segmental Tunnel Lining Systems
is reduced because of fewer drops afforded by the greater overall lengths of bars that are
wound up around spools. These details matter when comparing the cost of reinforcing steel
designs. It is not a matter of just counting the theoretical lengths and applying a random
2% waste factor!
There is also a waste factor and premium to pay that can come with special geometries
where the design engineer insists on maintaining zero tolerances (combinations of plus X;
minus 0, or plus 0; minus X on covers for instance) with regard to concrete covers. There
are some shapes of bars that are difficult to maintain in the fabrication process because of
the mix of:
These factors combined may mean that the there is an inconsistent bend or bounce back
in the bar as it comes off the pin that the bar is bent around, and the final shape becomes
out-of-tolerance and the bar/reinforcing element is considered rejected or scrap. Certain
bar sizes, bar grades, and shape combinations may be prone to more geometry tolerance
errors and thus create more rejects and scrap. And certain bar and shape combinations may
require more set-up trials in order to find the correct machine settings and precise set-points.
Since these learning curve trials create scrap, these quantities must be addressed and paid
for. At the same time, everyone must understand that there are tolerances that accumulate
and compound along the process with different parts of the process needing the plus/minus
allowances, some requiring minus 0; plus X tolerances, some requiring plus 0; minus X
tolerances, etc.
The final achievable tolerances are a function of numerous factors including the following:
There is a reason why there are standard plus/minus specifications in governing standards
such as ACI, and when we get more restrictive, the costs go up with the unprecedented and
astounding levels of precision that are being demanded. The achievement of extreme dimen-
sional tolerances is often an iterative process with trials and readjustments to elements, the
process, and the reinforcing steel jigs used, and the costs of these must be accounted for and
compensated by the entities demanding great precision in the final product.
With regard to what is meant by the CRSI effect, it should be noted that bar lists in
almost all of the United States and Canada are developed in accordance with the Concrete
Fabrication of precast segmental tunnel linings 535
Reinforcing Steel Institute (CRSI) theoretical lengths. This is the practice of using the sum
of the individual out-to-out lengths of a bent bar to determine its overall length. This intro-
duces the phenomenon of “bend curve deduction”, which has an effect on the length of the
bent reinforcing steel that is listed and the invoiced weight on unit price projects.
For straight pieces there is no impact. For long single-end or double-end bent members,
however, “bend curve deduction” is relatively minor, but when a large percentage of the
project is short members such as stirrups with mid-size diameter bars such as No.5, 6, and
7, the listed and thus invoiced lengths of the stirrups can be significantly longer than the
length of bar sheared to fabricate the item.
The phenomenon of “bend curve deduction” is best illustrated by an example, such as
a simple L-shaped bent bar, a 24-inch (610 mm) by 24-inch (610 mm) that is bent at 90
degrees. For such a shape, one will be invoiced for 48 inches (1,220 mm) of bar, no matter
the diameter of bar used, but there is a difference to note. If a small bar diameter is used,
such as a No.4 bar (No.15 metric bar equivalent), the total length of the actual bent bar will
be shorter than 48 inches (1,220 mm) because of the rounded corner, it will be 46.5 inches
long (1,180 mm). If a large bar diameter is used, such as a No.8 bar (No.25 metric bar
equivalent), the total length of the actual bent bar will be shorter than 48 inches (1,220 mm)
because of the rounded corner, it will be 45.5 inches long (1,155 mm). But note that the
L-shaped bar made with a larger diameter bar has a shorter actual length than an L-shaped
bar made with a smaller diameter bar but in both cases, the invoiced L-shaped bars will
be based on 48-inches (1,220 mm). In both cases, one pays for the theoretical out-to-out
dimension of the L-shaped bar and not the actual length of bar used, and the “bend curve
deduction” factor is bigger with the larger bar.
One may ask, is this practice and reasonable for measurement and payment consider-
ation? In reality, it is standard industry practice for the manner in which materials are meas-
ured and paid for. It may be that one of the reasons for the practice of using the out-to-out
dimensions to define the length is to keep the process simple and consistent. All single-end
bent bars that span 2 feet × 2 feet are listed as 4 feet long on all of the documents on the
project. The design engineer’s drawings might show this. The detail drawings, shop bar list
and item tags certainly do. The only place that the reduced length is shown is for the cut
length listed on the shear cutting list. Everywhere else, the theoretical length and total of the
out-to-out rebar lengths are used.
So, estimating the cost of steel based on theoretical design concept lengths can be mislead-
ing and it is unjust and unreasonable to not consider the reality of what it takes to execute
each particular custom design, and the corresponding correct price must be paid. At times a
design that seems on the surface to be less expensive on the basis of a quick look based on
a rapid calculation of the concept drawings theoretical bar lengths may turn out to be more
expensive. And as a final note, certain classic reinforcing designs with special grades of steel
may look good on paper but it may not be possible to guarantee a supply of the steel grade
in certain markets or parts of the country.
Reinforcing steel mills in certain sectors of the country may not roll certain grades of
steel, or if they do, they may have limited rollings, which are off-timed with the precast
production schedules, or the mills may have large minimum rollings/order quantities that
remove the possibility of the supply. For example, large tunnel jobs have thousands of tons
of steel but this is a relatively small quantity that a mill can churn out in a matter of hours.
Moreover, a local mill may have the ability to roll the special grades of steel but the mill
would want to roll out the tonnage of the job in one rolling and ship it immediately, thus
creating potential cash flow and storage issues, making it a show stopper for the precaster
536 Handbook of Precast Segmental Tunnel Lining Systems
and the owner and contractor who may not be in position to pay the whole steel for the job
upfront.
Careful coordination is required with the engineers, contractors, owners and precasters in
regard to the materials specified. For reinforcing steel, and as well as for all other materials
specified, care must be taken when finalizing the design to make sure that all such materials
are readily available in the specific market and that they will continue to be for the entire
duration of the project, which may span several years, with added attention to safeguard
against the specification of materials from unique suppliers that can fail to have or maintain
the capacity to deliver the materials at the pace required for the precast production (result-
ing in costly segment production shutdowns).
standard with a CE marking system 1 (steel fiber for structural use) or the ISO 13270 (class
A) as a minimum. The fibers in the appropriate dosage are homogenously mixed into the
concrete and then provide a network of individual pieces that are oriented in multiple direc-
tions and reinforce the entire cross-section of the segment.
The following are the recommendations and considerations for steel fibers used in precast
segments:
• Fibers out of drawn wire, with a tensile strength of steel wire >1,800 MPa (261 ksi)
minimum
• Precast segments typically have compressive strengths well in excess of the min-
imum that is required for their structural design
• Typically, 35 to 40 MPa (5,000 to 6,000 psi)
• Because of high early strength requirements for production efficiency in the seg-
ment manufacturing plant, higher compressive strengths in the 65 to 70 MPa
(9,000 to 10,000 psi) are common
• To maintain ductility of the SFRC, higher tensile strength wire is recommended
• Hooked ends that have been optimized to ensure proper anchorage in the con-
crete matrix
• Fiber length: in the range of 50 mm (2”) to 60 mm (2.4”)
• Aspect ratio (length/diameter): a minimum of 65, 80 is recommended
• Minimum fiber length: 2.5 times the maximum coarse aggregate size
• Fibers glued in clips to promote homogenous distribution and eliminate balling of
fibers since it takes more of a mixing effort to integrate loose fibers.
• Introduction of fibers into mix using a fully integrated automatic dosing system
may struggle to find room to store the big bags of steel fiber if precast production is slowed
down or halted. In any precast plant arrangement, the management of steel fiber, pertaining
to logistics and plant storage, is very challenging.
The steel fiber bags must be stored under roof in a dry environment. The logistics of pro-
viding this floor area in a precast plant must not be ignored.
batched comes along quite well –balling is generally rare with glued fibers (but there could
be instances of it, with some adjustments required).
As an example, with certain plant feeding arrangements, the metering in of glued fibers
could be done by dumping all the glued fibers in at once. With a dosage rate of 35.6 kg/m3
(60 lbs/CY) of fiber, for a 1.5 m3 (2 CY) concrete batch, one could easily think of dumping
55 kg (120 lbs) of fiber almost instantaneously (in a skip hoist setting), or at a very fast rate
per second or minute. If one has a 4.2 m3 (5.5 CY) batch of concrete, getting 160 kg (350
lbs) of fiber in rapidly poses a different challenge.
One way to dump all the glued fibers in at once, at times the easiest way, would be to
introduce the fibers with the pre-weighed aggregates in the aggregate skip hoist. Introducing
540 Handbook of Precast Segmental Tunnel Lining Systems
the fibers into a skip hoist system is quite simple because one would do this almost at ground
level; and the fibers would travel up to the mixer with the sand and stone. The layout of the
plant would have to allow this, and this is not always the case!
Assuming the layout of the plant allows sending in the steel fiber in with the aggregates,
the solution would seem simple enough but perhaps too good to be true in certain instances
because of one thing –some high-tech concrete mixes and batching systems work with
moisture probes in the mixer and these moisture probes are microwave-based and when the
steel fiber gets introduced with the aggregates, the mixer moisture probe, whose job it to
542 Handbook of Precast Segmental Tunnel Lining Systems
measure what the water content of the combined constituents that are in the mixer drum
(so the batch software can subtract this amount of water free water from the water that it
intended to add to reach the design water content based on the water cement ratio) does not
read properly. The presence of steel fiber with the aggregate will falsify or affect the reading
of the moisture probe and create havoc. There are innovations in the sensitivity of moisture
meters to iron-based interference.
Fabrication of precast segmental tunnel linings 543
So, with certain batch plant arrangements it may not be possible or desirable to introduce
the steel fibers with the aggregates and this is a big challenge. What does this mean? It means
introducing the fibers, metering them in, after the aggregates are introduced. Metering the
fibers after the aggregates means that the fibers get introduced directly into the mixer that
is possibly 9.1 m (30 feet) off the ground with all sorts of equipment in the way. Conveyors
may be required.
The other disadvantage is that metering in fibers directly in the mixer drum, in a batch
system that uses a probe in the mixer, lengthens the batch mixing cycle, and whatever that
extra batch time number is, 30 seconds, 60 seconds, etc., in the grand scheme of things,
when one has a high volume job and the mixer needs to supply a certain number of batches
per hour, it matters! So, with glued fibers, the introduction of fibers is more a straight-
forward matter, but there is quite a bit of logical thinking and system design involved and
it is not that simple.
We have to remember that the batch plant controls the components that are added to
each batch cycle, and these components are added within set tolerances (example ±1% to
3%) and the batch cycle stops if the tolerances are off. So, if your batch plant is calibrated
following required industry specifications, each batch of concrete should have the proper
amount of fiber in it, within tolerances and if the mixer is kept in proper working order, the
fiber should be well distributed in each batch of concrete. You will have an indication of this
through the washout test statistics (and it is the statistics that one must pay attention to and
not the measured value of each test).
This test is typically performed on the volume of the concrete that is found in the air
testing pot, e.g. 0.25 ft3 of concrete (two air pots for 0.5 ft³). One can easily do the math
and figure out the pounds of fiber that should be present in the specific volume of the pot.
Hence the test consists of washing out the paste and aggregate from the fibers, baking the
fibers until all the moisture is gone and then weighing the fibers. Please refer to Figures 9.31
to 9.33.
One must understand that the dispersion of the fiber in the concrete shoveled into an air
pot will have some variance and typically the acceptable limits of fiber presence in air pot
samples can vary by; minus 20% and plus 20%, from batch to batch but it is the monitoring
of the running averages that is of value.
There are now new technology alternatives to the wash-out test, i.e. induction machines
that can calculate the amount of fiber that is in a wet or hard concrete sample.
Once filled, the lab technician must use judgment to vibrate them with the proper amount
of time to guarantee proper consolidation, and to avoid entering a state of segregation: if
the large aggregates drop, they can affect the orientation and position of some of the fibers
and the testing results will be skewed.
Special robust vibration tables with high-frequency are a must. Not just any vibrating
table will consolidate the concrete properly and keep the aggregates and fibers sus-
pended in their natural initial state. We do not want segregation; aggregates and fibers
to drop, or to have fibers change their orientation (which could possibly help or hinder
the results).
As with all concrete vibration activities, good judgment and good crews are required to
do it correctly. It is important to ensure consistency in the making of samples. The previ-
ously mentioned washout test is really more a measure of the consistency of the making of
the samples, and not a measure of how much fiber is in the concrete batch. There is a specific
protocol for the preparation of beam samples in the American (ASTM) and European (EN)
specifications, but there are some steps that are not detailed and there are efforts underway
to provide more guidance in the specifications.
• American test
• ASTM C1609, Standard Test Method for Flexural Performance of Fiber-Reinforced
Concrete (Using Beam with Third-Point Loading)
• European test
• EN 14651, Test Method for Metallic Fibre Concrete– Measuring the Flexural
Tensile Strength (Limit of Proportionality (LOP), Residual)
They are both equivalent tests within 34.5 to 41.3 MPa (5,000 to 6,000 psi) concrete range,
but when concrete strengths reach 58.6 to 82.7 MPa (8,500 to 12,000 psi), the European
test shows more consistent results. This matter is explored in detail in a previous chapter
of this book.
It is important to note that there are some new tests that are being introduced and proofed
that would replace or complement the classic beam tests such as the EN 14651 test and the
ASTM C1609 test. One such test, as an example, is the Barcelona test that is used to evaluate
FRC post-cracking behavior. The Barcelona test is a double-punch test that can be seen as
offering important advantages over other types of tests. It can be relatively easily carried-out
on regular compressive testing equipment, and it uses light and easy to handle specimens. It
is said that its use reduces the dispersion of results, which is welcome. One idea is to use it
to complement existing tests. There is also a notched beam test being developed by ASTM.
Figure 9.35 Example of beam breaking machine for ASTM C1609 test protocol.
(a) This machine is set-u p to perform the ASTM 1609 beam bending test.
(b) General arrangement and specific beam set-u p apparatus (yoke and transducer).
Fabrication of precast segmental tunnel linings 549
containing steel fiber. So, one can proof the mix during pre-production with the absence
of fibers, but during production, it will not be possible to test the fibered samples, for tests
measuring, for instance, chloride ion diffusion (one would have to use a sacrificial batch
that lacked fiber and there are costs related to this but there are significant costs to sacrificial
batches in terms of wasted concrete and the disposal of wasted concrete, and the fact
that the batching of sacrificial concrete may affect production time schedules). The other
solution is to develop a system to extract the fibers from the wet concrete (which comes at
a significant cost depending on the frequency) but if a few fibers are left behind, the tests
could be compromised.
In the end, a hybrid solution is more than the sum of the parts in terms of organization,
logistics, operations and testing –it is at times three or four times the work and effort; i.e.
higher costs to implement at the project level.
• Fiber metering equipment, vibratory feeders, conveyors have up front capital costs
and can have significant costs of installation.
• There are costs related to the electronic controls that are required to link the metering
systems to the batch plant software –so that one can control with assurance the true
amount of fiber that is fed in the mix.
• There are metering system calibration costs (that occur on an established frequency).
• Fiber metering systems must be fed throughout the shift by manpower, at times with
specialized equipment.
• Fiber must be unloaded from delivery trucks, at times with special handling equip-
ment, on a regular frequency.
• Fiber must be handled and stored protected from the elements. This means a roofed
area for storage and there are costs to this.
• Fiber metering systems are quite robust, but they still need to be constantly monitored
because they can be prone to mechanical issues, or jams if not properly designed.
• Fiber metering systems need to be maintained and repaired occasionally.
• If fiber metering systems go down, the production stops.
• One must be aware that batching time can be increased by fractions of a minute to
several minutes with these processes.
• There is a labor-intensive aspect to the testing of fiber concrete, there is expensive
testing equipment, and there are large expenses related to shipping and testing with
an independent lab, or even with in-house testing.
• Hence it is important to understand that fiber reinforced concrete is not a cakewalk
for the precaster –there are many considerations and costs to deal with, depending
on the numerous factors outlined above.
typically when the batching operation is close to the casting molds. It is standard industry
knowledge that the concrete mix designs used for making segments are typically high-strength
high-tech concretes that are “hot” meaning they are rich in cements and admixtures and can
react relatively rapidly –not necessarily exhibiting an abnormal early set but they may lose
workability rapidly (so timing in getting it to the molds quickly matters).
A modern dedicated batch plant will have several silos of cementitious materials such
as cement, slag, fly ash and silica fume and several tanks of admixtures. It will need to be
designed for the output required for continuous, high-volume production in varying wea-
ther conditions –hence attention to the aggregate storage (stone and sand bins/silos) and
aggregate handling systems (conveyors) is important. The plant will most probably require
hot water heaters, chillers, and possibly aggregate heating systems to meet certain climatic
conditions. The batch plant needs to be sized to the project, meaning that the mixer can
produce sufficient concrete to fill one mold completely in one or two cycles, otherwise
manufacturing efficiencies are challenged.
While modern batch plants rely on moisture meters for aggregates and possibly for the
mixer, there is a substantial amount of technology in a modern casting operation. Just the
same, there are three important factors that can impact plant performance:
• Setting-
out the allowance of ambient steam temperatures during the concrete
preset period
• The maximum internal temperature that is allowed in the concrete itself
Secondary curing period (the bid specifications should have clear directives regarding
this period)
Clarity is required to even the playing field. Confusion in the specification language is not
easy for the precaster bidding work, all of the competition must know what is going to be
required for the job and be held to the same standards. There is a world of financial, oper-
ational and durability performance differences between applying a curing product to seg-
ments versus curing segment-rings in steam in computer controlled vapor kiln enclosures
(there is the cost of the vapor generation systems, the gas costs, the kiln costs, the real estate
costs, the costs of handing, among many more, versus the cost of a Hudson garden sprayer
and relatively inexpensive curing compound liquids –the difference being multiple hundreds
of thousands of dollars).
9.8.5 Anchored gaskets
Anchored gaskets have “feet” that extend into the cast concrete of the segment, and these
feet anchor the gasket to the final segment without any secondary gluing operation, that was
the past practice. Anchored gaskets provide safer working conditions in the casting plant
as typical gasket adhesives contain ingredients that give off volatile gases during the curing
process, which require the work area to be properly ventilated for worker safety. Anchored
gaskets are attached with care to a groove machined into the steel mold’s circumferential
and radial walls, after oiling of the mold. See Figure 9.38 that illustrates the anchored
gasket installation work in progress. The sequence of installing the gasket must be followed
for consistent results.
9.8.6 Glued gaskets
Glued gaskets are installed using a contact-cement type adhesive system that connects the
EPDM rubber gasket to the gasket groove that is cast into the segment. This operation is
typically performed after the segment has been removed from the initial curing process as
shown below in Figure 9.39. The preferred industry system and more secure method is to
apply the gasket glue to the groove area only and then use a gasket press to apply pressure
for a few minutes. This process mimics the process of applying glue to two surfaces, the
gasket and the gasket groove, and then tapping the gasket into the gasket groove. There is
less human skill and judgment required when using the gasket press and the results are typ-
ically better quality than hand application methods.
Fabrication of precast segmental tunnel linings 555
Segment dimensional measurement comes with a cost and the owner/design engineer must
determine in advance of the bidding of the project if this level of quality control is required
and if the owner willing to pay this additional cost. This may be required for a 14 m (46-
foot) diameter transportation tunnel but not required for a 3.0 m (10-foot) diameter sewer
tunnel.
558 Handbook of Precast Segmental Tunnel Lining Systems
• The mold manufacturer builds the first set of a series of molds using their fabrication
jigs and templates.
• These are carefully checked against segment design dimensions and allowable
tolerances.
• The geometry of the first set of molds is checked with the 3D scanning technology to
certify that the tools used to build the molds (e.g. manufacturing fixtures and jigs) are
within tolerance with the theoretical geometry and in particular, to confirm that the
manufacturing fixtures and jigs meet the theoretical dimensions and geometry within
tolerance. Tolerances between the actual mold surfaces and the 3D generated surfaces
must be compared and respected. (See Figure 9.41.)
• Next, the first set of molds are cast at the mold fabricator’s shop.
• Each one of the segments cast are now measured by the 3D scanning technology to see
if the mold has produced a segment that is within the geometrical tolerances allowed.
If this is the case, you now are assured that the mold (the resultant of all its tolerances)
yields a segment that is in geometric tolerance (the aggregate of all its tolerances).
• At this point, the “baseline mold tolerance set” is established. See Figures 9.42 to 9.46
for examples of the mold-segment tolerance comparisons.
Only once the mold manufacturer is convinced by the previous 3D measurement testing
that the mold fabrication templates and jigs are of the sufficient precision and accuracy to
Fabrication of precast segmental tunnel linings 559
build molds that will in turn produce segments that are in tolerance, the mold manufacturer
continues the assembly of the other sets of molds in the production sequence. If discrepan-
cies were seen, adjustments are made to the first set of molds that was fabricated and these
adjustments are in turn applied to the following sets of molds being assembled. Each set of
molds gets checked with the 3D instruments to certify each mold.
By this process of interactive checking and logical deduction, we can, at this point, with
great confidence measure molds with either traditional methods or 3D methods with the
reassurance that the segments produced from these molds will be in tolerance. Hence, we
can confidently say, using this protocol, that the geometry checks of the molds equate the
geometry checks of the segments during production.
The documentation related to these methods of measurement comes in two forms:
• In digital raw data form and summary tables for the 3D laser scanning methods and
• In manual check sheet data that is converted to excel tables whereby statistics can be
followed and analyzed.
• Hence, once we have established a “baseline mold tolerance set”, one can use 3D
measurement systems for the validation of segment tolerances, or the traditional meas-
urement systems (calibrated vernier instruments), both types of systems to measure
only the critical measurements determining geometrical tolerances.
newgenrtpdf
560
Handbook of Precast Segmental Tunnel Lining Systems
Figure 9.42 Segment mold-s egment tolerance comparisons – widths.
Note: Examples of segment mold width tolerance comparison reports and corresponding graphic images listing the actual measurements and
apparent deviations.
newgenrtpdf
Fabrication of precast segmental tunnel linings
Figure 9.43 Segment mold-s egment tolerance comparisons – half diagonals.
Note: Examples of segment mold half diagonal tolerance comparison reports and corresponding graphic images listing the actual measurements
and apparent deviations.
561
newgenrtpdf
562
Handbook of Precast Segmental Tunnel Lining Systems
Figure 9.44 Segment mold-s egment tolerance comparisons – fatness.
Note: Examples of segment mold “flatness” tolerance comparison reports and corresponding graphic images listing the actual measurements
and apparent deviations.
newgenrtpdf
Fabrication of precast segmental tunnel linings
Figure 9.45 Segment mold-s egment tolerance comparisons – thickness.
Note: Examples of segment mold thickness tolerance comparison reports and corresponding graphic images listing the actual measurements
and apparent deviations.
563
newgenrtpdf
564
Handbook of Precast Segmental Tunnel Lining Systems
Figure 9.46 Segment mold-s egment tolerance comparisons – plane orientation.
Note: Examples of segment mold plane orientation tolerance comparison reports and corresponding graphic images listing the actual measure-
ments and apparent deviations.
Fabrication of precast segmental tunnel linings 565
• One that is built at the mold manufacturer’s plant as a control of the first ring set
of production molds, before launching into production of the complete set of molds
required for the project.
• This is the most useful type and is usually only one ring high.
• It may be measured with high precision with a FARO-type 3D surveying instru-
ment and provides useful comparative geometric data between the molds and the
final product, the segments.
• The other type of test ring is the one usually called for at the project’s precasting plant,
as the first production rings come out of production.
• This test ring (or rings if they are stacked on top of each other) are mostly cere-
monial in nature if the test ring at the mold manufacturing plant already conveyed
critical geometric tolerance information.
566 Handbook of Precast Segmental Tunnel Lining Systems
Please refer to Figures 9.47 and 9.48 for photos of a test ring set that is set-up at the pre
caster’s yard.
Test rings, being built vertically, especially multiple level rings, are extremely challenging
to build and are prone to move and creep with time because of the awkward forces that
can deform certain connectors, and because the circumferential joint connectors are ground
down to allow for dismantling (these ground-down connectors have slop in them). The ver-
tical installation arrangement requires forcing segments unnaturally into position, and this
may force the plastic inserts. There is also the “slop” (loose fitting) in the tapered bolt holes
to contend with which permits movement between the segments. Finally, the temperature
will have an effect on the ring geometry; e.g. if the sun is beating on one side of the ring and
the other side is cool, there will be differences in measurements depending on the time of
day they are taken. However, the roundness and fit of the segments can be witnessed and
this is the important aspect.
Historically it made sense to build a test ring at the precasting plant to verify if fit was
good and if the bolt pockets or inserts had been located improperly in the molds. Please
recall that 30 years ago, the mold shop drawings were created by draftspersons and engin-
eers using a pencil and paper and drawn in two dimensions. One can brazenly say that a
segment-ring is just a cylinder, but it is a challenging and frustrating exercise to study a ring
Fabrication of precast segmental tunnel linings 567
and its fine and subtle segment geometrical details and to manually draw it up because every
segment looks alike, it was easy to make a mistake. The test rings generally caught these
mistakes and subtle misalignments.
Today we have 3D computer-aided design software where the segment drawings are
made by the modeling of a ring and its segments directly with the 3D software and then the
molds and their detailed parts are designed off these digital 3D segment models The risk of
bolt pockets and elements being located and/or assembled in the wrong location is almost
non-existent. Hence, nowadays, the checking of a test ring is different than the original
intention of a test ring. Whereas originally and using the technology available at the time,
the test ring was used to verify general fit-up, today, a test ring is used to delve into the fine
details of dimensional tolerances that can be measured with theoretical surface models that
are generated with the available computing power.
The other issue that a test ring or set of two or three test rings does not address is the
different permutations of say the situation with a production using seven sets of molds with
seven segments per ring, and possibly three circumferential bolt/dowel locations per seg-
ment. It would be impractical to interchange the seven sets of segments from seven sets of
molds and clock them in each possible position that the rings could be mated in. This is why
the test ring at the mold manufacturer is so important.
• Very tight mold manufacturing tolerances (at the apex of manufacturing ability –to
provide a buffer)
• Tight mold production setting tolerances
• Segment production tolerances
• Two surface orientation measurements given in linear measurement offsets and angles
(which are incompatible with large mold dimensions). See Figure 9.50 below.
• True flatness –planarity of a surface measurements. See diagram in Figure 9.51 below.
The data listed in the table, shown in Figure 9.49, is an example of the tolerances that are
of importance to the mold manufacturer and precaster vs. the segment tolerances. The table
Fabrication of precast segmental tunnel linings 569
Figure 9.50 Orientations of mold circumferential joints and radial joints – measurable/a djustable
values.
Note: It is important to have a diagram related to the tolerance nomenclature to avoid
misunderstandings.
also gives an indication of how the measurements can be taken (method) at the three time
intervals
Diagrams in Figures 9.50 to 9.53 provide information for the elements of the tabular sum
mary illustrated in Figure 9.49.
• Pre-pour inspection
• Post-pour inspection and repair (if it occurs)
• Batch tickets for the concrete used
• Fresh concrete testing
• Hardened concrete testing data (cylinder breaks, beam breaks when steel fibers are
used), mold dimensional checks, and steel cage inspections
• Concrete constituents’ material testing data (mill tests, aggregate testing)
There is a considerable cost to using the latest technology in terms of traceability. For
example –software development (usually plant customized), hardware requirements
Fabrication of precast segmental tunnel linings 573
(scanning guns, etc.), plant Wi-Fi, repeaters and internet technology required, personnel
to manage the data and systems, system crashes affecting production schedules, etc. Often,
dealing with the large amount of data generated by these systems can turn into polemic ses-
sions of interpretation and argument which in turn, can lead to unnecessary further inves-
tigations on unimportant elements, unrelated to the product’s performance, which directly
or indirectly severely penalize the precaster (most frequently because of the burden of proof
applied by the tunnel contractor and owner). In the age of modern computerized systems
that generate tremendous amounts of data, it is important to maintain attention on the ori-
ginal intent and that more data may not mean more knowledge and intelligence if it is not
managed properly and if the persons involved do not act responsibly. The intelligent and
responsible use of technology is great and powerful, but its misuse is a waste of resources,
money and brings a false sense of assurance orsecurity.
paper method is based upon. People generally love the greater data capabilities but crave
the more tangible quick dashboard view that the pen-and-paper reports give with the ring-
based reports.
The digital quality control tracking systems are based on bar code and/or QR code scan-
ning using hand-held scanners. The molds each have a bar code and/or QR code and when
a mold undergoes a QC check, this bar code or QR code is scanned. When the mold is cast,
again, the mold codes are scanned, linking it to the batches that went into the specific mold.
When the mold is stripped, again the mold QR or bar code is scanned and linked to the
new tag that will be printed and glued onto the freshly stripped segment. At this point, the
segment is officially born and has its identity linked to the mold it came from and quality
controls that were done in the pre-pour inspection. Figures 9.54 and 9.55 shows an example
of a mold QR code tag. An embedded number and bar code for segments and a stick-on QR
code for segments as shown in Figures 9.56 and 9.57.
As the segment progresses through the rest of the operation, as it may possibly get
repaired, or ready for shipping, it gets scanned and quality control inspections get recorded
into the growing database. Please refer to Figure 9.58, which shows a detailed flow chart of
the segment production process.
One of the main advantages with the databases is that one can easily track defects by type
and one can more easily see how their frequency evolves with time, although the quality
control team usually sounds the alert when certain issues arise in repetition. There are many
reports that can get generated from the segment quality control database, but most are
standardized from the onset in conjunction with the software developer. One issue to note
is that not everyone has the same idea of what a “dashboard report” should show. What is
important to the precaster may not be what the owner’s engineer may want or expect to see.
There is evolution to come with these new systems for digital capture of data and all of the
parties involved; the contractor, the owner, the owner’s engineer and the precaster. Software
and hardware developers must work together to make sure everyone’s expectations are pos-
sible, reasonable, cost effective, and that they can be met.
It is also apparent that there is a cost in software development in order to produce custom
reports, special written report formats as well as specific dashboard formats, few of which
are embedded in advance in the contract specifications. And there is often the case, because
this is a new innovation, where one party desires to add or change parts of the data or report-
ing formats, these are not readily possible once the segment precasting has commenced. And
finally, if these systems get too intense, data acquisition and reporting becomes a significant
576 Handbook of Precast Segmental Tunnel Lining Systems
Figure 9.58 F low chart of the segment manufacturing process – overview and quality control
stop points.
Note: Technopref Industries, Inc, Cape Charles, Virginia; Hampton Roads Bridge and Tunnel
Project, Norfolk, Chesapeake, Virginia Beach, Hampton, VA.
Fabrication of precast segmental tunnel linings 577
task that requires an experienced management team as big as the production quality control
team. Few understand the energy that these data reporting systems demand for the limited
benefit that may result (i.e. tracking data with little value or follow-up). On the other hand,
there are significant benefits to come in regard to these new digital data systems but more
industry collaboration required to bring these systems on-line and make them more func-
tional and productive.
With the digital quality control tracking systems, there is an important learning curve
with the personnel. Learning to input the quality control checking data is not that easy in a
bustling plant environment where the learning is going on at the same time as a production
kicks-off with a learning curve for everyone (laborers, lead people, client inspectors, owner’s
inspectors), and often debugging systems and procedures. One of the main issues is not the
gathering of data, it is the registering of data once the checking is done. The inspector may
run all the checks and click the boxes but there is always a last step where a final approval
must be given and at times this is forgotten and going back to correct this step is compli-
cated and time consuming.
For example, the logistics of the precast plant encompasses the coordination of the
following:
• All the components of the plant mechanical systems (including, at times, the erection
of a batch plant and its ancillary systems), and of rented equipment.
• Consumables (for example, release agents).
• Cast-in components (example –sockets, grout/lifting inserts, guide rods).
• Arrival, staging and coordination of the accessories that need to be sent to jobsite for
ring erection in the TBM (i.e. steel bolts, washers, dowels).
• Concrete constituents: aggregates, cement, slag, fly ash, silica fume, admixtures, steel
fiber big bags, reinforcing steel.
• The staging and storage of the above-mentioned elements within the precast building
and yard is complex because poor timing results in literally nowhere to put things. If
there is lengthy downtime in production, scheduled deliveries that are in ocean vessels
or coming from continental suppliers do not stop their journeys and the plant gets
overwhelmed.
• Storing of the final product in the yard:
• If there are delays with tunneling, managing a precast yard to maximize storage is
very complex. These are large elements and every time you handle them comes the
risk of damaging them.
• If the precast storage yard gets filled-up, there may be a need to transport the
product to temporary remote yards which entails renting land, renting haul trucks
for the transfers, extra labor, and renting extra costly heavy equipment in the new
yard to unload and eventually load-out. These are costly energy-intensive situ-
ations. Please refer to Figures 9.61 to 9.67.
• Transporting segment-rings to jobsite with inconsistent mining schedules.
Fabrication of precast segmental tunnel linings 579
loads. In these situations, the number of deliveries for the job will go up and
the jobsite will also have to manage different types of deliveries, resulting in dis-
continuous reception routines, oddball jobsite storage and staging patterns, thus
potentially creating havoc and errors.
To be able to have a good handle on logistics, one needs to plan schedules properly, main-
tain excellent communication with your suppliers, subs, transporters, trucking companies
and client. A deep understanding of the lead times and developing plan B’s, C’s, and D’s for
each of the elements is required to adapt and adjust to changes. Please see Figures 9.62 to
9.65 for segments in transport tot eh site from the precasting plant.
Fabrication of precast segmental tunnel linings 581
of energy and resources that are required to recruit, train, sustain, keep safe, and support
a workforce with high turnover is significant. At the end of the day, it is the boots on the
ground that win wars, not all the fancy equipment.
The precaster will need to set-up a plant in record time and when the whistle blows,
a green crew will need to be trained and kept safe with seasoned leaders and procedures
that will be constantly adapting, and very quickly will have to produce product of the
highest quality (often with zero tolerances) while de-bugging systems, as all eyes from
the contractor, owner’s engineer and owner are scrutinizing work over the shoulder of the
precaster, even as some technical specifications are still being debated, argued or inter-
preted. In these environments, the seasoned owners, owner’s representatives, inspectors
and contractors understand the enormity of what is being achieved and leave the pre-
caster with the breathing room to take care of his most important assets; e.g. the labor
that is being trained and kept safe, while the precaster debugs, adapts and improves the
process and machinery. High quality becomes a natural by-product of the operations, for
every segment produced.
ASTM A1064/A1064M, Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement,
Plain and Deformed, for Concrete.
ASTM A307, Standard Specification for Carbon Steel Bolts, Studs, and Threated Rod 60,000 PSI
Tensile Strength.
ASTM A36/A36M, Standard Specification for Carbon Structural Steel.
ASTM A615, Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement.
Fabrication of precast segmental tunnel linings 585
ASTM A706/ A706M, Standard Specification for Deformed and Plain Low- Alloy Steel Bars for
Concrete Reinforcement.
ASTM A820, Standard Specification for Steel Fibers for Fiber-Reinforced Concrete.
ASTM C1012/C1012M, Standard Test Method for Length Change of Hydraulic-Cement Mortars
Exposed to a Sulfate Solution.
ASTM C1064/C1064M, Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement
Concrete.
ASTM C1116/C1116M, Standard Specification for Fiber-Reinforced Concrete.
ASTM C1157/C1157M, Standard Performance Specification for Hydraulic Cement.
ASTM C1202, Standard Test Method for Electrical Indication of Concrete’s Ability to Resist Chloride
Ion Penetration.
ASTM C1218/C1218M, Standard Test Method for Water-Soluble Chloride in Mortar and Concrete.
ASTM C1240, Standard Specification for Silica Fume Used in Cementitious Mixtures.
ASTM C138/C138M, Standard Test Method for Density (Unit Weight), Yield, and Air Content
(Gravimetric) of Concrete.
ASTM C143/C143M, Standard Test Method for Slump of Hydraulic-Cement Concrete.
ASTM C150/C150M-18, Standard Specification for Portland Cement.
ASTM C1556, Standard Test Method for Determining the Apparent Chloride Diffusion Coefficient of
Cementitious Mixtures by Bulk Diffusion.
ASTM C1567, Standard Test Method for Determining the Potential Alkali-Silica Reactivity of
Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method).
ASTM C1604, Standard Test Method for Obtaining and Testing Drilled Cores of Shotcrete.
ASTM C1607, Standard Test Method for Determination of “Microwave Safe for Reheating” for
Ceramicware.
ASTM C1609 /C1609M–19a, Standard Test Method for Flexural Performance of Fiber-Reinforced
Concrete (Using Beam With Third-Point. Loading)
ASTM C231/C231M, Standard Test Method for Air Content of Freshly Mixed Concrete by the
Pressure Method.
ASTM C260/C260M, Standard Specification for Air-Entraining Admixtures for Concrete.
ASTM C31/C31M, Standard Practice for Making and Curing Concrete Test Specimens in the Field.
ASTM C33/C33M, Standard Specification for Concrete Aggregates.
ASTM C39/ C39M, Standard Test Method for Compressive Strength of Cylindrical Concrete
Specimens.
ASTM C496/C496M, Standard Test Method for Splitting Tensile Strength of Cylindrical Concrete
Specimens.
ASTM C595/C595M, Standard Specification for Blended Hydraulic Cements.
ASTM C618, Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use
in Concrete.
ASTM C666/C666M, Standard Test Method for Resistance of Concrete to Rapid Freezing and
Thawing.
ASTM C920, Standard Specification for Elastomeric Joint Sealants.
ASTM C989/C989M, Standard Specification for Slag Cement for Use in Concrete and Mortars.
ASTM D1149, Standard Test Methods for Rubber Deterioration–Cracking in an Ozone Controlled
Environment.
ASTM D1171, Standard Method for Rubber Deterioration– Surface Ozone Cracking Outdoors
(Triangular Specimen).
ASTM D2240, Standard Test Method for Rubber Property–Durometer Hardness.
ASTM D395, Standard Test Method for Rubber Property–Compression Set.
ASTM D412, Standard Test Method for Vulcanized Rubber and Thermoplastic Elastomers–Tension.
ASTM D471, Standard Test Method for Rubber Property–Effect of Liquids.
ASTM D573, Standard Test Method for Rubber–Deterioration in an Air Oven.
ASTM D638, Standard Test Method for Tensile Properties of Plastics.
ASTM F436/F436M, Standard Specification for Hardened Steel Washers Inch and Metric Dimensions.
586 Handbook of Precast Segmental Tunnel Lining Systems
BS PAS 8810:2016, Tunnel Design –Design of Concrete Segmental Tunnel Linings –Code of Practice.
BRITISH TUNNELING SOCIETY (BTS) AND THE INSTITUTION OF CIVIL ENGINEERS (ICE)
AFTES:2005, Recommendations for the Design, Production, and Installation of Segmental Ring
Recommendation for the Design, Sizing and Construction of Precast Concrete Segments
Installed at the Rear of a Tunnel Boring Machine (TBM)s.
DAUB:2013, Lining Segment Design: Recommendations for the Design, Production, and Installation
of Segmental Rings.
ISO/TC 17/SC 17 Steel Wire Rod and Wire Products. (2013). ISO 13270:2013–Steel Fibres for
Concrete –Definitions and Specifications. Geneva, Switzerland: ISO, the International
Organization for Standardization.
Fabrication of precast segmental tunnel linings 587
10.1 INTRODUCTION
The logistical challenge to transport, handle, and install segmental tunnel liner rings has
existed ever since the invention of the prefabricated tunnel liner. In the first tunnel built
under the St. Clair River linking Sarnia, Ontario with Port Huron, Michigan (1889 to
1891) the tunnel was lined with cast iron segments forming rings 6.4m (21 feet) in outside
diameter and 460 mm (18 inches) wide. Each ring had 13 curved segments weighing about
460 kg (1,000 lbs). The tunneling shield had a crane with an arm (Figure 10.1) that pivoted
on the center of the shield with a counterweight on the other end to hoist the segments into
position. The arm could grab and maneuver a segment in three dimensions. The segment
was positioned and bolted in place by a 15-man crew that could assemble a complete ring
in 15 minutes.
In a modern tunnel, heavy precast concrete tunnel liner segments must be delivered on
time, in the correct order, and without damage to the segments. The assembled segmental
liner ring is the final product on most projects, so ring assembly must be done with pre-
cise placement of individual segments. Gasketed precast segments provide a watertight seal
at pressures up to 20 bar (290 psi) and keep the groundwater from entering the tunnel.
Efficiency of the segmental liner installation is important due to the work being on the pro-
ject schedule’s critical path schedule and the activities on a TBM are repeated thousands of
times like a production line at a factory.
DOI: 10.1201/9781032675541-10
Transportation, handling and installation 589
Figure 10.1 Erecting cast iron tunnel liner segments at the St. Clair Tunnel.
Note: Illustration courtesy of Lambton Heritage Museum, Grand Bend.
the cost of shipping segments to the jobsite. The handling of segments is reduced and thus
the chance of segment damage is also reduced. The reduced handling also provides a direct
safety benefit with the reductions in handling and inspection.
The erection sequence needs to be determined before the segment molds can be ordered.
The precast plant needs to organize the molds for a ring so that as the segments are removed
from the molds and stacked, the segments get stacked and stored in the order requested by
the contractor. If a delivery is split because of weight considerations, the stacks need to be
delivered with the bottom half of the stack first. Depending on the location of the precast
plant to the job site there are some creative ways to cut down on trucking costs. If the pre-
cast plant is hours away, consideration for adding an additional stone to the truck load if
room and weight permits may be a possibility. The stacking of the added segments would
be completed at the job site and would have to be managed logistically.
With a universal ring, all the rings are the same so the site yard only stages one type of
ring. Delivery from the precast plant to the job site needs to meet daily average production.
With a left-right-parallel type rings, segments sent to the tunnel need to be coordinated with
the heading to make sure the correct ring is sent to the heading. This also means that the
yard needs to store and have access to three different types of rings. The different type of
rings cannot block-off access by storing one type of ring in front of a different type, unless
rings are stored and retrieved by a crane. There may be more than one ring in the process of
being loaded or in transit to the heading, careful coordination is required to make sure the
correct sequence of rings is supplied to the heading.
and movement of tunnel segments. More handling generally leads to more damaged seg-
ments, less handling of segments is preferred. The edges on precast concrete liner segments
near the gaskets are very delicate. The segment edge below the gasket groove is easily
chipped or spalled resulting in an exposed gasket. Sometimes the spalling can extend below
the gasket seat. Damaged segments require costly labor-intensive repairs, and the space to
make the repairs.
The site yard layout needs to consider the flow of traffic, the size of the yard, the need
for access to different types of liner rings, and the number of rings to be stored on site
based on production numbers and location of the precast plant. There will be a constant
flow of trucks into the yard delivering segments and other supplies along with trucks
hauling away tunnel muck. If possible, the site should separate the traffic for segment
deliveries and muck hauling so that one does not hold up the other. If the yard is large
enough, there may be room to separate the muck pit from the segment storage area
and prevent muck trucks from stacking up while a load of segments is inspected and
unloaded.
On a small site, segments may be unloaded from trucks parked momentarily on an active
street with flaggers directing traffic around the unloading zone.
Segment handling and staging does not happen in isolation but is part of an overall
system that supports the TBM. There must be an overall site plan that addresses not only
the segments, but muck handling, support equipment, materials storage, plant and equip-
ment, and utilities. All these pieces have to be arranged until they fit together like a jigsaw
puzzle to provide the optimum solution for the site. This is not necessarily the ideal solution
but the best that can be achieved given the constraints of the site.
Ideally, the yard should be large enough to accommodate enough rings for a day of
peak production, which is usually about two times the average production. There should
also be enough storage to handle interruptions in supply due to weather and traffic.
When the contractor is in control of the segment plant and the plant is nearby, storing a
minimum number of rings at the tunnel site may be reasonable. If the segment plant is an
outside supplier far away, prudence requires the storage of more rings on site to guard
against shortages, which would shut down the entire tunneling operation. An additional
storage yard for segment storage may be a consideration by the contractor to control the
segment inventory at the job site. Keep in mind that double handling usually results in
more damage to segments.
The site segment storage yard needs to have a flat all-weather surface capable of handling
high bearing loads from a stack of segments. Truck unloading areas need to be flat so that
the lifting device picks-up the segment stack evenly. An uneven surface can damage the seg-
ment lifting device and the segments as the load is being picked-up by the device.
Small sites are the most difficult because all the support equipment, muck storage and
tunnel supplies compete for space. The smallest footprint will come from a 100% crane
set-up with a tower crane picking the segments directly from a truck and storing them in a
tightly packed configuration (Figure 10.4). The same crane will be used to lower the seg
ments down the shaft and load the transporter. The contractor should ensure that the seg-
ment stack spacing leaves enough room for workers to maneuver the segment picker over
the stack.
If there is room for more segment storage at the site, there may be room for a storage yard
beyond the reach of the shaft crane. This segment yard might be serviced by another crane
or by a forklift. If the segments are handled by forklift, then a paved surface is needed to
prevent rutting and out-of-level operation by the forklift.
594 Handbook of Precast Segmental Tunnel Lining Systems
Figure 10.4 Storing segments on-s ite using crane and segment picker.
Note: Maximizing segment storage in small yard on-s ite.
10.3.5.1 Forklifts
Forklifts are a popular way to unload and stack segments. They are a good solution if the
yard is large enough. Forklift operators must be trained and skilled, but they do not require
the certifications that are required for a crane operator. The forklift will be quite large to
handle a segment stack (Figure 10.5). A forklift can only access segment stacks on the out
side edge of the storage area, so a left-right-parallel ring scheme is going to require a layout
for access to all three types of rings. The forklift can free up the shaft crane to service the
shaft, making the positioning of the segment delivery trucks less critical. The forklift should
have HDPE lined sleeves over the forks to prevent damage to segments and match up with
596 Handbook of Precast Segmental Tunnel Lining Systems
the curvature of the segment (Figure 10.6). Alternative options for the forklift forks are to
have custom forks fabricated or to use wood dunnage to match segment curvature placed
on top of the forks. The dunnage scheme must consider the placement of the forks to pre-
vent overstressing of the bottom segment in the stack. This scheme must be reviewed and
approved by the segment designer to avoid overstressing the segments.
The system is simple and rugged but requires clearance at the segment ends for the place-
ment and removal of the picker. The operation of an A-frame picker is shown in Figure 10.7.
The side lifting picker lifts a stack of segments by sliding in lifting fingers from the sides.
This eliminates the need for end clearance but requires additional side clearance. The picker
is operated by the motion of the crane on picker to actuate the lifting fingers and move them
in and out of position. Figure 10.7 shows such a picker in operation.
A variation of the side lifting picker is the powered side picker where the crane oper-
ator can operate the grab mechanism remotely by an electric cable suspended from a crane
overhead reel. The electrically actuated picker has the disadvantage that the picker must
be disconnected electrically every time the crane is used for another purpose. The discon-
nection process is at a height that requires a ladder and requires care to avoid damaging
the connector. The electrical power also adds another complication to the picker. Both the
A-frame and the side lifting picker work equally well. Clearances at loading and unloading
points will decide which is best for the job.
Figure 10.10 Multi-s ervice vehicle from the low-p rofile operator’s cab end.
Note: Front end of MSV going into the tunnel, unloaded segments pass over the cab.
Photo courtesy of Techni-M étal Systèmes division of Herrenknecht Tunneling Systems.
10.5.1 Segment supply and unloading within the TBM trailing gear
For single shield TBMs, the tunnel is built by erecting a ring and then thrusting off the ring
to advance the TBM. Since the construction of the tunnel is usually on the project critical
path, any interruption of the ring erection delays the entire project. Every effort must be
made to have the segments immediately ready for ring assembly once the push is completed.
A double shield TBM does not have to wait on the ring to be assembled to continue mov-
ing but it consumes rings at a faster rate, so an efficient segment delivery system is just
as important. As previously discussed, the segments need to be unloaded and staged in a
defined order.
gear, the train or MSV is stationary relative to the trailing gear and unloading of segment
and supplies is simplified. Given a choice, most contractors prefer a closed floor system.
Once the segments arrive at the TBM trailing gear, the segments along with all the other
supplies need to be unloaded and delivered to the correct location. The quicker the trans-
port train or MSV can be unloaded, the sooner the train or MSV can go back to the service
shaft for another load of supplies. Eventually, if the tunnel is long enough, a second sup-
ply train or MSV, and perhaps even a third will need to be added to the supply chain. The
overall cycle time of the train to load at shaft-travel to TBM-unload at TBM-travel to shaft
will dictate when another transporter must be added to the system. For intermediate length
tunnels in the 3,500 to 4,500 m (12,000 to 15,000 feet) range, a quick unloading system
may eliminate the need to run a second transporter and install a passing place in the tunnel.
For that reason, many clever schemes have been developed to speed up segment handling.
around the perimeter and a port to pump out the air and produce a vacuum. The plate is
suspended from the monorail crane and is set down on top of the segment. A vacuum is
applied, and the segment is lifted with nothing more than atmospheric pressure exerted on
the segment. The lifting place is designed to hold a vacuum for 30 minutes in the event of a
power failure and the plate will not attempt to lift the segment until a specified vacuum is
reached. The physics are sound, but it is still amazing to see a segment weighing tons being
lifted by the application of a vacuum. Vacuum erectors have an excellent safety record.
Figure 10.15 shows a vacuum lifting plate arrangement under a monorail crane. The plate
has three vacuum zones. All three are used to lift a segment but only the center zone is used
to lift a key.
Segments made for vacuum lifting do not have a threaded insert for as a fixture, but they
do have to have holes cast in them for shear cones. Shear cones are not required for straight
vertical lifts but they are required for holding the segment in a subvertical or vertical plane.
The foam gasket on the plate seals off the segment for air evacuation but it is not capable
of transmitting shear. Holes cast in the segment line up with a matching plug. The plug is a
wear part with a steel core and a nylon outer shell. The shear cones also serve as an align-
ment tool to make sure the vacuum plate is correctly and consistently positioned over the
segment before the vacuum is applied.
The vacuum lifting plate is more complicated and expensive but has been proved to be
reliable. The plate does not require a worker to repeatedly handle a heavy fixture or retrieve
the fixture from an awkward position. There is no need to cast a threaded insert in the
segment unless a grout port is required. There is a need to cast shear cone pockets into the
segment, but the casting process is simpler compared to a threaded insert. One disadvan-
tage with a vacuum lifting plate occurs when handling a cracked segment. Occasionally a
cracked segment may have to be removed from the heading. The vacuum erector will not
work if the crack runs under a vacuum pickup zone. In those cases, the segment must be
lifted using chains or slings and the process is very slow. A whole shift can be lost moving a
damaged segment out of the heading.
In the past, precast concrete segments were reinforced exclusively with steel reinforcing
bar cages. The current trend is to use precast segments made with steel fibers. The steel
606 Handbook of Precast Segmental Tunnel Lining Systems
fiber segments are more susceptible to cracking if lifted from a single point. Vacuum lifting
distributes the load and is less likely to damage segments.
The segment feeder is essentially a heavy-duty conveyor. The segments are unloaded, rotated
90°, and placed on the segment feeder in the order required by the segment erector. The
feeder brings the segments to the ring erector for pick-up and placement. With a train, the
segment cars may be detached from the rest of the train so that the other supplies can be
unloaded simultaneously with segment unloading. Then the empty train is reassembled and
pulled back to the service shaft.
In this section we will discuss how and why a particular ring erection position is selected
and the process to erect a ring. We will also discuss problems to avoid.
position but the principles are the same for manual selection. The selection of the next ring
position to be erected in TBM tail shield needs to consider:
10.6.2 Importance of keeping the liner ring centered in the tail shield
For shielded TBMs, the ring is necessarily assembled inside the protection of the tailshield
and the ring outside diameter (extrados) is smaller than the tail shield inner diameter. If the
TBM maintains a pressurized face, the annular gap between the tail shield and the liner ring
must be sealed to maintain a pressurized zone around the TBM. The annular gap between
the two is sealed by up to four rows of wire brushes and a grease sealing system. There
are usually two or three rings of wire brushes (Figures 10.20 and 10.21) and the space in
between the rings is filled with a biodegradable grease that does the actual sealing. Part of
the brush system is the brush holder, which is a curved steel ring around the inside of the tail
shield to which the wire brushes are attached.
The sealing system can tolerate an eccentricity of about 50 mm (2 inches) between the
precast liner ring and the shield. The exact tolerance depends on the design of the TBM.
Once that is exceeded, a portion of the liner ring will come in hard contact with the brush
holder and damage to the segment is likely to occur as the liner ring is pushed-out of the tail
shield, often described as being “iron-bound”. Keeping the assembled ring in the center of
the tail shield reduces the possibility of segment damage.
As the liner ring is pushed out the back of the TBM, the gap between the ring extrados
and the tail shield is measured, usually at springline and at the top arch and invert. Each
tunnel liner ring has a known offset for the length of the ring to the tunnel longitudinal axis
and this is used to steer the ring back towards the shield center. The gap is usually meas-
ured manually but may be measured electronically if the guidance system has the necessary
equipment.
When the TBM is on a straight section (tangent) or in a circular curve, the selection of
rings soon becomes established and routine. Errors in TBM tunnel alignment and damage
to liner rings usually occur at the transitions between tangents and curves. If the tunnel is
designed with tangents and circular curves only, as most sewer tunnels are, the operator will
get in trouble if they blindly follow the guidance system. If they wait until the TBM is at the
end of a tangent before beginning a turn, they will start the turn too late and will usually
over-correct to get the TBM back on course. This often causes damage to the liner rings in
the tail shield, which cannot follow an abrupt change in TBM heading. That same problem
can happen at the end of a circular curve.
If the TBM operator waits for the end of a circular curve to make the transition to a tan-
gent, the operator will again be too late and will oversteer the TBM to get back on track.
An experienced TBM operator will start and end a curve early thus putting in a transition
in and out of the curve. Rather than let the TBM operator freehand the alignment, the
situation can be improved by introducing spiral curve transitions at the exit and entry to a
circular curve within the guidance system design tunnel alignment. The TBM is less likely to
go off alignment following railroad and highway tunnel design alignments because they are
designed with spiral curves for trains and cars.
16 mm (1/8 to 5/8 inches). Consistent gaps all the way around the ring is an indication of a
circular ring. The ring builder can see how he is performing and improve accordingly.
A sample report is shown in Figure 10.25. A report should be prepared for every ring
describing whether any damage occurred during installation or from the advance afterward.
Transportation, handling and installation 615
Often this is required by the specifications, but it is also good practice to record the installa-
tion of every ring. If there is a rash of cracking, the reports can be used to determine whether
there are any systemic failures, which can be eliminated. The gaskets may be required to
resist water pressures up to 20 bar (290 psi), therefore good alignment between the gaskets
is necessary. The gaskets are designed to tolerate a certain amount of offset, which depends
on the design of the gasket, but the ring builder should not rely on that tolerance.
The guidance system calculates the best ring position, cross-checks this selection against a
table of forbidden positions. If that position is forbidden, then the program selects the closest
allowed position. The TBM operator or field engineer relays this information to the ring
erector and the ring assembly starts for the designated position. Immediately upon com-
pleting a ring, the ring erector notifies the TBM operator. The position of the completed ring
618 Handbook of Precast Segmental Tunnel Lining Systems
is put into the guidance system and another cycle begins. The field engineer, TBM operator
and ring builder should always check that the guidance system selection is reasonable. They
have the option to install the ring in a different position if necessary and input the selection
into the guidance system.
On a large diameter TBM where the top arch segments could be 6 m (20 feet) or more
off the invert, the operator needs to climb a purpose-built platform to see up close how the
segment is being placed. The operator will have an assistant who can call out the position
of the segment on the far side of the operator. As the ring is erected, the assistant will install
the bolts (if bolts are used) and will tighten them with an air powered wrench. The ring
builder and his assistant are often not in clear sight of each other and must communicate
constantly to make sure the assistant is not pinched or crushed by the erector or segment
being installed.
provides a guide for the ring builder allowing him to quickly align the plate and shear cones
with the segment.
If the segments use an interlocking ring-to-ring dowel system, a certain amount of force
will be required to connect the dowels. Additionally, the segment must be forced against the
preceding segment to compress the gasket. The mechanical gripping system uses the same
fixture that was installed for unloading the segment from the transporter to transmit the
thrusting force of the erector arm into the segment. The vacuum plate requires the presence
of shear cones to transmit the thrust force because the foam gasket seal use to hold the
vacuum cannot handle the shear forces.
When the TBM is an open face shield, the problem is that a fluid grout will run towards
the front of the TBM. TBMs can be outfitted with spring steel plates at the tail shield to
prevent forward movement of the grout but these plates wear out and will not work if
rock in the arch or shoulder fall out at the face. In these cases, the solution has been to
inject pea gravel through the segments using shotcrete pots. The gravel provides immediate
support however lipping between rings and squatting does occur. The newer method is to
inject a two-part grout behind the tail shield that gels within seconds after injection and has
adequate bearing for the first liner ring loaded by the trailing gear.
discontinuous segments, the ring tends to squat upon exiting the tail shield. Every ring is
built and connected next to the previous ring so if the first ring squats, then the ring builder
will have to fight the tendency of every subsequent ring to squat.
Different contractors use different schemes at TBM launch to prevent ring squat from
building and external frame to post-tensioning cables around the rings to provide compres-
sion forces. Figure 10.36 shows a rigid frame with wedges to help round-up the temporary
liner rings inside the launch shaft. Figure 10.37 shows another TBM launch scheme using
post-tension cables. Once the TBM is inside the tunnel and grout pressure can be built
up, the rings tend to round up, but it can still take 20 rings to get the squat out. Another
consideration is that the gaskets between the rings are like powerful springs. Although the
ring-to-ring connectors should be able to resist the gaskets pushing apart, contractors often
bolt tie bars across the first five rings from the portal to make sure the rings do not move.
together as a team. Any substitute workers must be trained and watched until they know
the routine. Workers must not stand under overhead loads or in areas where a segment
erector failure could cause injury. Because the segment area has a wide range of motion and
the operator has poor visibility of many areas, visitors should not be allowed in the imme-
diate area during ring erection. The segment handling equipment must be inspected by a
mechanic following a checklist to ensure that all parts of the equipment have been checked.
Inspections should be done at the start of every shift. The segment erection area must have
work platforms that allow the ring builder and their assistant to reach any part of the seg-
ment needed to install bolts and check for alignment of the segment.
For the operations within the TBM and gantry area two trends are present:
The fully automated subsystems can include all operations for segment handling starting
with unloading from the transport vehicle up to the point where the erector picks up the
segment.
However, when introducing automated handling systems, the segments as well as the seg-
ment stack on the supply vehicle must be suitable for automation. Whereas the segments
are high-precision precast elements that may already incorporate means like bar codes or
similar for automatic identification, increased requirements on geometrical accuracy of the
segment stacks, including the dunnage placed between segments and the stack position on
the supply vehicle are necessary.
If the human operator is eliminated from segment handling within the gantry area, the
possibility for a final human visual check of the individual segments before being supplied
to the erector is no longer available. The visual check and subsequent correction measures
typically includes the detection of damages caused during transport in the tunnel, correct
position of the segment seals, and contamination of the segment surface by dirt, snow or ice
that could cause a malfunction of the vacuum lifter. Instead, an automated inspection done
by artificially intelligent cameras is required. Also, the integration of an automated cleaning
device for the segment intrados is advisable to eliminate the risk of vacuum plate malfunc-
tions caused by surface contamination.
Whenever automated systems are installed physical barriers with interlocked access doors
need to be installed to prevent personnel from entering the area where automated hand-
ling operations are in progress. Consequently, such areas within the gantry would only be
human accessible during manual operation mode or maintenance.
Even a fully automated system needs to provide the option for safe manual operation including
the possibility to reverse the transport direction and bring damaged segments back out from the
installed position in the tail shield to the transport vehicle and finally out of the tunnel.
Automated systems require a larger amount of sensor technology and more computer-
ized control systems. The harsh environment in a tunnel heading must be addressed for
component selection and design as well as appropriate qualification and training of on-site
maintenance personnel. Besides the possibility for fully automated systems, modern sen-
sor technologies provide the possibility to display additional information on the erector
operator’s control panel for the ring erection itself. Such information can include ring build
clearance, or the relative position of the segment currently being placed segment to its neigh-
boring segments.
Measuring and providing such geometrical information to the erector operator electron-
ically can eliminate the need for an assistant ring builder climbing up and down the erector
platforms and performing manual measurements. This combined with the use of boltless
rings would result in faster ring erection and the elimination of a person who is often out of
sight of the ring builder leading to a safer environment.
BIBLIOGRAPHY
For preparation of this chapter, the references were used and are grouped into four categories of
authority published documents, tunnel research and industry association documents, govern-
ment agency documents and authored documents as listed below.
Website: www.aftes.fr
• Tunnel Lining Design Guide, March 2004
AUTHORED DOCUMENTS
Duhme, R.; Rahm, T.; Thewes, M.; and Scheffer, M., 2015, “A Review of Planning Methods for
Logistics in TBM Tunneling”, Proceedings of ITA WTC 2015 Congress and 41st General
Assembly, Lacroma Valamar Congress Center, Dubrovnik, Croatia.
Scientific American, August 9, 1890, “The Great Railway Tunnel Under the St. Clair River, Between
the United States and Canada”, Scientific American Magazine Vol. 63 No. 6, pp. 87–88.
Chapter 11
11.1 INTRODUCTION
This chapter will discuss why annular grout is needed, what the desired characteristics are
for annular grout, and the different types of grouts. Some sample grout mixes are provided
for each type of grout as examples only. Placement methods and example projects are also
discussed.
Making sure the correct mix design is selected prior to tunneling and documenting/veri-
fying the grout quantities injected during tunneling operations is key for proper execution,
ground loss minimization, cost savings and eliminating rework. Low volume quantities that
are not addressed immediately in the field will result in having to do secondary grouting,
which entails more labor and additional cost. Knowing the job specifications and making
sure the grouting requirements are clear to all parties is extremely important prior to start-
ing any TBM operation.
DOI: 10.1201/9781032675541-11
630 Handbook of Precast Segmental Tunnel Lining Systems
Figure 11.1 Sources of annular gap surrounding the TBM and segmental lining.
Note: Gap starts with overcut at cutterhead and increases as the mid-s hield and tail shield typ-
ically have slightly smaller diameters. Largest source of annular gap is between the liner ring and
the tail shield extrados.
thrust loads on the erected lining and TBMs going around curves exert differential pressures
on the segmental lining.
• Ensure uniform continuous contact between the grout and the precast segments.
• Prevent or reduce the movement of the ground, which could result in surface settle-
ment above the tunnel.
• Serve as a sound foundation or bedding for the precast segmental line ring.
• Ensure that the annular gap is filled and that the grout stiffens in a timely manner to
provide ring stability, especially in non-cohesive soils.
• Avoid movement of the segments generated by the thrust force and shield steering.
• Prevent heave or flotation of the lining.
• Provide adequate support for loads from the advancing TBM trailing gear.
• Protect the precast segments from direct contact with chemically aggressive soil
or rock.
• Provide a barrier against water moving along the tunnel lining extrados.
• Provide a secondary barrier to water and fines moving through damaged or mis-
aligned segment gaskets.
• Distribute internal tunnel pressures that are greater than the ground water pressure in
operating water and sewer tunnels.
The grout must provide uniform continuous contact so that the liner ring can function as a
compression ring. If the void is not completely filled all around the ring, the native ground
Annular backfill grouting of precast segmental tunnel linings 631
will move towards the ring in soft ground tunnels or leave a void at the crown in hard rock
tunnels and will not load the ring uniformly causing deformation of the ring. Ground loos-
ening above the tunnel and moving into the annular gap will eventually result in surface
settlement. The settlement can be immediate if there are non-cohesive soils overhead but
will eventually show up even with cohesive soils.
The TBM makes an overcut with the cutterhead that is in the range of 10 to 20 mm (3/
8 to 3/4 inches) larger in radius than the front shield. This overcut is required to steer the
TBM and reduce skin friction. The distance from the cutterhead to the tail end of the shield
where the liner ring is pushed out of the tail shield is typically in the range of 8 to 11 m (26
to 33 feet). TBMs with a mid-shield articulation and a tail shield typically step down or
tapered about 10 mm (0.375 inch) in diameter with each section make the TBM easier to
move after a shutdown when the ground may squeeze in slightly towards the TBM along
the length of the TBM. The ground is held back by the slurry pressure in the case of a slurry
TBM and by the conditioned soil packed around the shield in the case of an earth pres-
sure balance (EPB) machine. Some specifications require the injection of bentonite slurry
around the EPB TBM shield to keep the annulus open. At the end of the TBM tail shield,
the annulus widens to around 130 to 180 mm (5 to 7 inch). This is the gap that needs to be
filled promptly and completely with grout. The potential for further tunnel induced surface
settlement once the TBM tail shield passes a given point is nil provided the annular gap is
filled and the grout is adequately stiff.
Fully embedding the precast liner ring in pressurized grout also keeps the ring circular.
The liner ring has a natural tendency to squat from its own weight if there is not uniform
support from the grout. Modern precast liner ring design allows for a small amount of squat
by relieving the interior and exterior edges so that the segment edges within a ring do not
spall and expose the gasket. Excessive squat will cause spalling at the edges of the opposing
segments and expose the gasket. Uniform loading of the ring will help keep the ring circular
and will assist with the construction of the next ring in the tail shield since the rings are con-
nected to each other via connector pins or bolts.
For hard rock tunnels the problem is the fall-out of rock blocks created by intersecting
joints or the failure in the quarter arch created by swelling rock. Rock tunnels can produce
water that can wash out the grout. When tunneling through water-bearing rock formations,
incomplete grouting can lead to the movement along the tunnel liner extrados that increases
as the tunnel progresses. Inadequate grout liner support will lead to ring squat and offsets
between liner rings that will result in damage as the TBM trailing gear advances.
The complete TBM advance cycle for a single shield to excavate and build one ring can
be one hour or less for the typical 6.0 m (20 feet) diameter machine. Ring widths typically
range from 1.2 to 1.8 m (4 to 6 feet) although some have been made 2.2 m (7.2 feet) wide.
As soon as the ring is built, the TBM resumes advancing, which means that the next to last
ring already embedded in the grout is experiencing thrust and steering forces about one
hour after the grout has been placed.
TBMs pull a long train of equipment behind them that is about 100 to 150 m (330 to 500
feet) long known as gantries, back-up or trailing gear. That train of equipment has substan-
tial weight and usually advances on some type of wheeled system. Often there is a bridge-
like structure that spans from the end of the TBM to the front of the first wheel supported
trailing gear. The idea is for the bridge to span around five to seven rings before the first
wheel loads are imposed on the liner. These wheel loads can be quite high for a large diam-
eter TBM. The grout needs to be stiff enough so that when the wheels roll over the invert
of the rings, the liner rings do not move up and down like piano keys. The first wheel loads
632 Handbook of Precast Segmental Tunnel Lining Systems
must be resisted by the liner ring and grout combination about 2 to 5 hours after grout
placement depending on the rate of TBM advance.
• Active –full hydration of a cement component that acts as a binder and provides the
stiffness and hardness properties of the final product
• Semi-inert –a lesser amount of cement and a slower strength gain and lower ultimate
strength
• Inert –grout without cement, but perhaps with lime or clay
The EFNARC division between active and semi-inert grout are defined by the amount of
cement in the grout but are somewhat arbitrary. For this chapter, we will use Thewes and
Budach’s classification that more than 200 kg/m3 (344 lbs/CY) of cement constitutes an
active grout while 200 to 50 kg/m3 (344 to 86 lbs/CY) of cement constitutes a semi-inert
grout. Semi-inert grouts are also called semi-active or reduced active grouts. Active mortar
grouts have the highest long-term strength because of the amount of cement used. Active
non-mortar grouts also have the possibility of being chemically accelerated at the point of
injection. Mortar in this context means that the grout contains a fine aggregate.
Semi-inert mortar grouts are mainly composed of the same elements, as found in the
inert type, but there is stronger reliance on the properties of the non-cement ingredients to
give the proper rheological properties. A smaller percentage of cement or other hydrating
material will cause a degree of hydration to occur. The grout may harden slowly although
stiffening will occur more quickly.
Inert mortar grouts contain no Portland cement but may contain other hydrating ingredi-
ents, such as hydraulic lime. Inert grout ingredients are a mixture of water, various grades of
natural and crushed sand, and supplementary fine materials such as fly ash, metakaolin, slag
cement, lime, silica fume, crushed stone filler and bentonite. The compressive strength is very
low, and the setting time will be delayed or sometimes will never set. Inert mortar grouts are
economical backfill grouts. Inert mortar grouts have been used in several projects, mainly
by French contractors and engineers. The fine aggregates must be carefully selected and pro-
portioned to get the right mix of flowability during placement and stiffness after injection.
The classification system is not perfect. For example, some projects use slag cement as the
only active ingredient. This could be classified as an inert grout since it contains no Portland
cement, but the grout does hydrate and gets hard so it could be considered active grout. Pea
gravel is an inert ingredient used in some grouts, but the gravel is later flooded with cemen-
titious grout, which is clearly active.
Annular backfill grouting of precast segmental tunnel linings 633
• Single component –all ingredients are mixed outside the tunnel and delivered to the
tunnel heading for injection into the annular space
• Two component –one component is the cementitious product, and the other is an
accelerator, which are only mixed at the last moment to provide a grout that becomes
a gel within seconds of injection.
• Pea gravel –blown into the annular gap and then later flooded with cementitious grout
Single component grout can be active, semi-inert, or inert. Cementitious grout is composed
of cement, bentonite, water, admixtures and a fine aggregate. Fly ash may also be substi-
tuted for part of the cement. One component grouts are batched outside the tunnel and
transported to the tunnel heading via rail or rubber-tired transport. Once at the heading,
the grout is transferred to a holding tank for injection into the annulus. The injection system
must maintain the backfill mortar pressure at or above the face pressure (as a rule of thumb
one to two bars above face pressure). Injecting the grout with too high a pressure can force
the grout to go into the cutter head chamber or into the wire brushes. Grout contaminated
brushes may require replacement. The stability of the ring occurs when there is adequate
cohesion of the mix and adequate friction at the grout/ring and grout/soil interfaces.
Chemical admixtures play an important role in active and semi-inert single component
grouts since the mix should have enough fluidity to be transported or pump from the
grout plant to the TBM; and the mix should be able to set within 4 to 5 hours of batching.
Admixtures could be hydration controllers, viscosity modifiers or a superplasticizer.
Advantages of the one component grout are that the ingredients are less expensive than a
two-component grout mix and visually checking grout volumes injected from holding tanks
is easy. Over the last 10 years, two-component grouts have become popular but one com-
ponent grouts are still favored by some contractors and engineers.
Component quantities
Metric Imperial
Item Mix design components Quantity UoM Quantity UoM
A Primary materials for 1.0 m 3 for 1.0 CY
1 Cement 400 kg/m 3 689 lbs/C Y
2 Pre-h ydrated bentonite slurry at 5% 147 kg/m 3
253 lbs/C Y
3 Aggregates 0 to 6mm (0 to 0.25 inches) 757 kg/m 3
1,304 lbs/C Y
4 Aggregates fine 606 kg/m 3
1,044 lbs/C Y
5 Water 185 kg/m 3
38.24 gal/C Y
B Admixtures
1 Retarder/s uperplasticizer combination 2.28 l/m 3 60 oz/C Y
Annular backfill grouting of precast segmental tunnel linings 635
Component quantities
Metric Imperial
Item Mix design components Quantity UoM Quantity UoM
A Primary materials for 1.0 m 3 for 1.0 CY
1 Cement 40 kg/m 3 69 lbs/C Y
2 Bentonite 20 kg/m 3
34 lbs/C Y
3 Aggregates (crushed and powdered 1,150 kg/m 3
1,981 lbs/C Y
limestone)
4 Fly ash 200 kg/m 3 344 lbs/C Y
5 Water 350 kg/m 3
72.24 gal/C Y
B Admixtures
1 Micro air entrainment 0.75 l/m 3 20 oz/C Y
2 Long chain polymer superplasticizer 3.0 l/m 3
79 oz/C Y
diameter of 7 m (23 foot) and was driven in shale and limestone rock containing ground-
water with high amounts of sulphates and chlorides.
Component quantities
Metric Imperial
Item Mix design components Quantity UoM Quantity UoM
A Primary materials
1 Hydraulic lime 72 kg/m 3 124 lbs/C Y
2 Fly ash 251 kg/m 3
432 lbs/C Y
3 Limestone fillers 152 kg/m 3
262 lbs/C Y
4 Natural sand 0 to 1.4 mm 527 kg/m 3
908 lbs/C Y
(0 to 0.055 inch)
5 Natural sand 1.4 to 3.4 mm (0.055 to 263 kg/m 3 453 lbs/C Y
0.134 inches)
6 Natural sand 3.4 to 5.6 mm (0.134 to 198 kg/m 3 341 lbs/C Y
0.220 inches)
7 Natural sand 5.6 to 8 mm (0.220 to 329 kg/m 3 567 lbs/C Y
0.315 inches)
8 Water 295 kg/m 3 60.89 gal/C Y
Component quantities
Metric Imperial
Item Mix design components Quantity UoM Quantity UoM
A Primary materials for 1.0 m 3 for 1.0 CY
1 Cement 280 kg/m 3 482 lbs/C Y
2 Bentonite 30 kg/m 3
52 lbs/C Y
3 Water 838 kg/m 3
173 gal/C Y
B Admixtures
1 Hydration stabilizer–r etarder 4 l/m 3 106 oz/C Y
2 Sodium silicate based accelerator 75 l/m 3
15.5 gal/C Y
added at tail shield injection mixer
Annular backfill grouting of precast segmental tunnel linings 637
Component quantities
Metric Imperial
Mix design components
Item for 1.0 m 3 (and 1.0 CY) Quantity UoM Quantity UoM
A Primary materials for 1.0 m 3 for 1.0 CY
1 Pea gravel – clean with none passing ¼ placed in advance placed in advance
inch sieve and 100% passing ½ sieve
2 Cement 897 kg/m 3 1,545 lbs/C Y
3 Fly ash 98 kg/m 3
169.0 lbs/C Y
4 Water 427 kg/m 3
88.13 gal/C Y
5 Pre-h ydrated bentonite slurry 6% 232 kg/m 3
47.88 gal/C Y
solution
B Admixtures
1 Superplasticizer 12 l/m 3 317 oz/C Y
2 Hydration stabilizer (retarder) 0.5 to 1.0 l/m 3
13 to 26 oz/C Y
the tail shield in a soft ground tunnel where required ultimate strengths are low. More
details are in Section 11.10.
Grout injection quantity limits are usually preset at the theoretical quantity plus 15 to
20%. Grout pressure limits are usually set a 1 to 2 bar (15 to 30 psi) above the face pres-
sure. Grout injection should stop when one of these limits is exceeded. Slurry TBMs will
have the same grout pressure at the face, along the shield, and in the annulus because any
vacant space is filled with fluid. EPB TBMs tend to lose pressure along the shield and the
larger annulus behind the tail shield may be at a lower pressure. For TBMs operating at
atmospheric pressure, quantity is usually the controlling factor. Injecting too much grout
risks forcing the grout around the TBM shield and possibly grouting in the TBM. Grout
quantities and pressures should be tracked to look for worrying trends.
Grout injection pressure readings can often be a source of disagreement. Grout pres-
sures sensed at the pump are a combination of the pressure from the face +static pressure
of the grout head +the dynamic pumping pressure. If a two-component grout is used, the
viscosity changes quickly over time as the grout gels. The best indication of grout pressure
is the grout pressure reading from a top port sensor at the end of the TBM advance when
the annular gap is filled, and no more grout is being injected. A good practice is to pump
grout through the circuit before the TBM is launched at various flow rates to determine the
dynamic pumping pressures. This information will assist with interpreting pumping pres-
sures during normal operations.
A grout that is difficult to pump can result in grout over-pressures around the precast
segmental liner. For example, a one-component grout with poorly selected aggregates will
require more pump pressure to move the grout through the lines. If the injection pump
cut-off pressure is set to 5 bar (72.5 psi) above face pressure to overcome dynamic pres-
sures in the grout line, the entire liner ring can be over pressurized. When the TBM gets
to the end of the advance and the last bit of fluid grout is injected into the annular space
reaches the cut-off pressure, all the fluid annular grout in the space will be at the cut-off
pressure.
Both pressurized and non-pressurized face TBMs may have an excluder ring (Figure 11.3)
around the outer perimeter of the tailshield, typically overlapping thin spring steel plates, to
prevent grout from moving forward around the TBM shield. Once launched, the excluder
shield is not accessible for repair or inspection and can be easily damaged or worn away as
the TBM advances. The excluder shield is not a sophisticated device and will not seal off
areas where the ground has fallen out prior to grouting. Annular grout best practices should
not rely on the presence of the excluder ring but should rely on closely monitoring our grout
quantities and pressures. Excessive grouting pressures will force grout around the TBM or
past the tailshield wire brushes and grease seals.
The tail seal system and the grouting system must work together. Without a properly
operating tail seal system, there is no way for the annular grout to achieve the desired
pressure as the grout will leak past the tail seal brushes and contaminate the tail seal area
with grout. The tail seal grease must be injected between the wire brushes with a quantity
and pressure adequate to seal off the tail shield and protect the wire brushes. Operating
the annular grout system at excessive pressures will force grout past the tail seal brushes,
damage the tail seal system and create a clean-up problem inside the TBM tail shield. The
grout injection rate should be commensurate with TBM advance rate to maintain the pres-
sure in the annulus. Grout flow in the pipes leading to the injection port should maintain
a minimum flow rate to prevent clogging. About 0.67 m/sec (2.2 feet/sec) is a good rule of
thumb. The ring erector operator has the best view of the segment/tail shield interface and
must alert the grout operator when excessive grout leakage is observed. A slight increase in
Annular backfill grouting of precast segmental tunnel linings 639
tail seal grease pressure may be enough to stop the leak. Continuous leakage of grout will
require inspection of the tail seal system.
The decision for either method must be made early in the project as the tail shield method
requires the installation of grout pipes and discharge ports (Figure 11.4) in the tail shield.
Grouting through the segments requires the installation of grout ports in the segment. If
through-segment grouting is selected as the production method, provisions should be made
in the segments to perform remedial grouting, also known as proof grouting or secondary
grouting. The TBM trailing gear may carry the equipment to support the grouting operation
and must be compatible with the method used.
port and the grout is injected. The quantity and pressure of the grout are monitored,
and injection is stopped when preset limits are achieved. The grout hoses are moved
up as the next liner ring is pushed out of the tail shield. The grout can either be a
mortar or a two-component grout. Reinjection through a grout port is not possible if a
two-component grout is used. Mortar grouts are less susceptible to line plugging when
injected through the segments.
Typically, the contractor can select between mechanical lifting or vacuum lifting of
the segments. For mechanical lifting, a threaded plastic insert is cast into the center of
gravity of each segment. This threaded plastic insert can also be used for grouting, either
primary or secondary. A hollow adapter that screws into the insert (Figure 11.5) with a
grout hose fitting on the end projecting inside the tunnel is used to connect to the grout
pump hose.
The procedures below describe the steps for grouting through segments in various
conditions.
• Dry tunnel
• Drill with a 25 mm (1 inch) diameter roto-hammer bit through the back of the
segment
• Screw in adapter
• Attach grout hoses and pump to refusal
• Dry tunnel–digger shield
• Same procedure as above
• Drilling should be done 10 m (30 feet) back from the tail of the shield This is to
prevent grout traveling on top of the machine
• Wet or pressurized tunnel
• Install adapter with a 50 mm (2 inch) diameter NPT full port ball valve
Annular backfill grouting of precast segmental tunnel linings 641
• With the valve open, drill with a 25 mm (1 inch) diameter roto-hammer bit through
the back of the segment until contact with water
• Quickly remove the drill bit and close the 50 mm (2 inch) diameter valve
• Attach grout hoses and pump to refusal
One-component or two-component grouts can be used with through-the-segment injection.
A recent development has been to inject two-component grouts through the segments when
advancing in rock tunnels. The grout is injected farther back from the tail shield to prevent
grout going around the shield and being ingested by the cutterhead.
Tail shield grouting has the disadvantage that the pipes carrying the grout through the
shield are relatively small and can clog easily with one-part grouts if the grout is not prop-
erly designed. Even two-part grouts can set up and clog the lines if the lines are not kept
clean. Grout lines are usually installed in four quadrants of the tail shield. Spare grout lines
may be embedded in the tail shield for rapid change over when a line is plugged. These
are usually filled with tail seal grease to keep them from filling up with grout when not in
use. Cleaning the lines is usually done by rodding with a cable or by jetting with high pres-
sure water.
if it can provide the immediate support needed by the ring and fill the annulus before the
native ground collapses into the annular void. One-part grouts can be active, semi-active or
inert. One-part grouts are still used although they have been largely replaced by two com-
ponent grouts.
Two-component (i.e. bi-component) grouts are also called A+B grouts where A is the fluid
cementitious material and B is the accelerator. They were invented by the Japanese to pro-
vide more immediate support and started being used in western countries around 2000. The
grouts are made by combining a cementitious component (generally cement, bentonite, and
a retarder) with an accelerator (generally sodium silicate based). Fly ash and slag cement
may also be used.
The two components are mixed just before or just after injection into the annular space
and the grout forms a gel withing 5 to 15 seconds that continues to gain strength by the
hour. The grout is very fluid at first but stays in place once gelling starts and provides nearly
immediate support to the ground and liner ring. Because the cementitious component con-
tains no sand, it can be pumped from the surface to the TBM using 50 or 75 mm (2 or
3 inch) diameter steel pipes, eliminating the need for rail or rubber-tired transport to the
heading. The grout mixing plant on the surface is also simplified as the grout can be mixed
using colloidal mixers instead of a concrete-style batch plant. Two component grouts can
provide more consistent properties as the primary ingredients are made in factories with
high-quality control. Two-component grouts are classified as active grouts.
Shielded TBMs that advance through rock and assemble a finished precast liner in the tail
shield were first used in Europe. These shielded rock TBMs operated at atmospheric pressure
so there was not an immediate need to support the ground to prevent surface subsidence,
however the annular void needs to be filled to prevent the loosening of the rock and uneven
loading of the liner ring. There was also the need to support the assembled rings so that they
maintain a circular profile and carry the wheel loads of the trailing gear immediately behind
the TBM. Clean pea gravel with a maximum diameter of 10 mm (0.375-inch) was used to fill
the annular space around the liner ring. Because the TBM was not operating in a pressurized
face mode, there was nothing to prevent a fluid grout from moving towards the TBM cutter-
head once injected. Pea gravel was injected as the initial supporting medium. The pea gravel
was blown in through the segments to fill the annulus as much as possible and then later the
same injection points were used to inject a fluid cementitious grout to fill the interstitial spaces
in the pea gravel and prevent the migration of ground water. The pea gravel filler was inert,
but the flood grout was an active grout. Two-component accelerated grouts are beginning to
replace pea gravel/flood grout as contractors become more familiar with the technology.
If the tunnel alignment passes under buildings, bridges and critical utilities, such as old
water mains, there will be more concern with settlement than if the tunnel is passing under
open fields or under bodies of water. Soft ground is more susceptible to settlement than
rock. Some types of soft ground, clean pressurized sands, for example, may be more sensi-
tive than others, such as heavy consolidated clays. The owner and contractor may have a
liability to third parties if settlement is not controlled. Owners or contractors may have to
make settlement performance promises to obtain the necessary permits. For sensitive condi-
tions, grouting through the tail shield is the preferred method.
The type of grout to be used may depend on the owner’s past tunneling experience. If the
owner has had bad experiences with two-component accelerated grout, they may request
that a one-component grout be used. In a traditional design/bid/build project the owner and
designer may specify the grouting method and the type of grout to be used before the job
is bid. Most western contractors are moving towards grout injection through the tail shield
using two component accelerated grouts for soft ground and hard rock applications. The
ingredients themselves are more expensive than one-part mortar grouts but the system sim-
plifies the surface grout mixing plant, and the grout can be delivered via a pipeline to the
TBM. One-component style mortar grouts require a batch plant, like a concrete plant with
all the attendant material handling equipment.
If the contractor already has the equipment invested in the batch plant and rail delivery
cars, he may make the calculation that a one-part grout is still more economical. Familiarity
with the technology plays a big part in the selection process. One-part grouts do clog tail
shield grout pipes more easily than two-part accelerated grouts. The crews must be trained
to properly operate the grout system and clean it out at the first sign of clogging.
Availability of grout ingredients is always a consideration. In developed countries, the
prompt delivery of quality ingredients such as cement, fly ash, bentonite and accelerator
may be a given. In remote locations or under-developed countries, there may be limitations
on availability, timeliness of deliveries or reasonable pricing. In these cases, looking at one-
part semi-inert or inert grouts where local aggregates can make up most of the grout and
admixtures can be minimized may be appropriate.
Large quantities of grout are required for tunnels of any length. For example, a 10 km (6
miles) tunnel with an excavated diameter of 8 m (26 feet) and an annulus gap of 150 mm
(6 inches) requires 37,000 m3 (47,360 CY) of grout. If the sample one-component mix in
Table 11.1 is used, 14,800 tons of cement and 50,431 tons of aggregate are required. If the
same space were fill using the accelerated two-component grout in Table 11.4, no aggregate
would be required but 10,360 tons of cement would be required. The grout should never
limit the advance of the TBM. One needs to be sure that the requisite materials can be deliv-
ered consistently to allow maximum production.
Table 11.6 below summarizes the different grouts and grouting systems and where they
may be used.
process. Multiple trial batches are prepared and tested, using ingredients available to the
tunnel project, until the right combination of properties is achieved.
grouts do not have as background the body of specifications that have accumulated for cast-
in-place concrete.
There are some guidelines but there is still lots of room for experimentation.
EFNARC Specifications and Guidelines includes the following guidance for one-part
grouts (Table 11.8).
For two-component grouts, the requirements are slightly different. Bleeding is still an
important property as the A component needs to stay mobile for hours or days before being
mixed with the accelerator. As with one-part grouts, excessive bleeding indicates settlement
of the cementitious particles, whether in a pipeline or in a tank. Bleeding and settlement can
have bad consequences when the A part is being pumped through a pipeline that is many
kilometers long. The liquid consistency of the A component is an important characteristic if
it is to be pumped to the heading.
Gelling time is generally in the range of 5 to 15 seconds and depends on the application.
After gelling, the grout has the consistency of a plastic clay. After one hour, the compressive
strength can be between 0.05 and 0.5 MPa (7 and 70 psi). After 24 hours, the compressive
strength can be between 1.5 and 2 MPa (218 to 290 psi). The 28-day strength can vary
between 2 and 4 MPa (290 and 580 psi). The required 28-day strength is generally higher
650 Handbook of Precast Segmental Tunnel Lining Systems
for tunnels excavated in rock. The strength achieved depends on the ratios of cementitious
materials, water, bentonite and accelerator. Cement contents can vary a lot for this type
of grout.
Two- component grouts are less susceptible to wash- out once the grout has gelled.
Pressurized face TBMs have less problems with washout since the TBM is operated at a
pressure that prevents ground water movement. Rock TBMs that operate at atmospheric
pressure have more problems with washout because the water can be moving toward the
excavated face.
The desire time of set depends on the grout deliver method to the heading and the advance
rate of the TBM. If grout cars are used to transport grout from the batch plant to the TBM,
there will probably be a storage tank at the shaft, the transport in the railcar, and the stor-
age tank on the trailing gear before the grout is finally injected into the annulus. Delays may
occur during TBM advance and that may require dumping the grout because of the rela-
tively short set time commonly used in one-component grouts. If the grout is transported
along the tunnel by pipeline, the grout may rest in the pipe for extended periods without
agitation.
cements. The flow and the compressive strength results varied significantly from one cement
to the other. Always test the different available materials to optimize the mix design and
have an alternative mix design for cases where critical materials become unavailable or too
costly to use.
Fly ash is widely used in annular grout. Fly ash is a very fine powder product of coal com-
bustion in electric power generating plants. Class C is usually a reactive fly ash while F is a
pozzolanic fly ash. Type F fly ash tends to produce more consistent results in grout mixes.
The ASTM specifications for fly ash are not tight and the characteristics of the fly ash vary
from powerplant to powerplant depending on the coal used and how the power plant is
operated.
ASTM C476 and C270 permit the use of cement meeting ASTM C595, “Standard
Specification for Blended Hydraulic Cements”. ASTM C595 allows 15% to 40% fly ash
by weight of Portland cement as a cement replacement. Fly ash is used in two-component
annular grout mainly because it cost less than cement. Fly ash increases durability and
enhances pumpability
Table 11.10 provides an example of two different Class F fly ashes with different perform
ance. Using the same mix design as in Table 11.9 and same components Fly Ash 1 increased
the flow duration after 24 and 48 hours. This case is not typical but demonstrates the vari-
ability of two fly ashes that both meet the ASTM Type F classification.
11.7.3.3 Bentonite
Bentonite is an absorbent aluminum phyllosilicate clay used in two-component annular
grout as an economical way to control bleeding. Bentonite clays absorb several times its
mass in water enhancing the rheological properties of the grout mix. Bentonite performance
depends on the source of the bentonite and how it reacts with the other components in
652 Handbook of Precast Segmental Tunnel Lining Systems
Table 11.9 Flow and strength comparisons for the same mix with different cements.
Never assume that a grout mix from one project can be used on another without
testing
Cement 1 Cement 2
Metric Imperial Metric Imperial
ASTM
Item Description code Qty UoM Qty UoM Qty UoM Qty UoM
A Viscosity D6910
retention (no
accelerator)
1 Initial 42.0 sec 43.0 sec
2 24 hours 45.0 sec 65.0 sec
3 48 hours 46.0 sec min n/a
flow
4 72 hours 53.8 sec no flow n/a
Flyash 1 Flyash 2
Metric Imperial Metric Imperial
ASTM
Item Description code Qty UoM Qty UoM Qty UoM Qty UoM
A Viscosity retention D6910
(no accelerator)
1 Initial 38.1 sec 36.6 sec
2 24 hours 56.3 sec 36.4 sec
3 48 hours 73.0 sec 36.7 sec
Annular backfill grouting of precast segmental tunnel linings 653
Component quantities
Metric Imperial
Item Mix design components Quantity UoM Quantity UoM
A Primary materials for 1.0 m 3 for 1.0 CY
1 Cement 372 kg/m 3 641 lbs/C Y
2 Bentonite 35 kg/m 3
60 lbs/C Y
3 Water 867 kg/m 3
178.95 gal/C Y
B Admixtures
1 Hydration stabilizer–r etarder 5 L/m 3 132 oz/C Y
the grout mix. As an example, various bentonite sources and one bentonite from the same
source but different manufacturing plants were tested using the same grout design shown
in Table 11.11.
As shown in Figure 11.9, no two bentonites had the same effect on bleed and even ben
tonite sourced from the same quarry performed differently depending on the manufac-
turing plant.
654 Handbook of Precast Segmental Tunnel Lining Systems
11.7.3.5 Admixtures
Use admixtures meeting the requirements of ASTM C494, the Standard Specification for
Chemical Admixtures for Concrete, and ASTM C1017, the Standard Specification for
Chemical Admixtures for Use in Producing Flowing Concrete, as required to improve
pumpability, control time of set, to hold sand in suspension, and to reduce segregation and
bleeding. Do not use foam or admixtures that promote steel corrosion. Admixtures have
various chemistries that may not be compatible with other ingredients in the mix and must
be tested for compatibility and mix stability.
Accelerators used can vary depending on the type of grouting. The most common accel-
erator used in annulus grouting is sodium silicate. Sodium silicates vary by density (solids
content). As density increases, so does viscosity, and this will affect the pumping and dosing
of the additive. There are many sources of sodium silicate. Testing is required to determine
the performance of the grout mixture. The use of other types of accelerators is not typical.
Retarding additives can be grouped into two categories. These are set retarding and
hydration control additives. Set retarders typically are sugar-based products. The sugar
source is variable. These can be efficient in the grout mixture design. They are less efficient
in lower water to cement ratio grouts as dosages can cause issues in mixture performance.
In two-component grouting, they are effective and can extend the workability of the unac-
celerated grout mixture for many days.
Hydration control additives retard the setting by controlling the hydration of Portland
cement and other cementitious materials. They are more efficient and predictable at lower
water to cement ratios. Testing is required to determine the effect they have on the grout
design. A hydration controlling admixture will stop cement hydration for a defined time
interval by forming a protective barrier around cementitious particles. This barrier effect-
ively delays the hydration process and initial set and helps to maintain the flow time
of grout
Plasticizers can be various chemistries including lignosulfonates, gluconates, sulfonated
naphthalene formaldehyde condensates (BNS), sulfonated melamine formaldehyde conden-
sates and polycarboxylates.
Lignosulfonates are products of the wood pulp industry. In cementitious systems, they
act as a plasticizer and water reducer and can have a retarding effect on the system. Many
companies provide lignosulfonate-based additives that are formulated to provide various
performances. As an example, they can be designed to keep the retarding effect or to provide
a normal set time development. Sodium gluconate is a retarding additive that also provides
a plasticizing effect. Testing is required to determine the effect they have on the grout design.
Sulfonated naphthalene formaldehyde condensates (BNS) and sulfonated melamine for-
maldehyde condensates are commonly referred to as high-range water reducers (HRWR).
They can provide much lower water contents for the same consistency and/ or higher
slumps and flows at the same or slightly lower water contents. They do not greatly retard
Annular backfill grouting of precast segmental tunnel linings 655
cementitious mixtures like the lignosulfonate products. If overdosed in the grout, it can
create problems such as bleeding, segregation and retardation. HRWRs are also provided
by many companies and are formulated to provide variable performance. This can include
dose efficiency/flexibility, strength enhancement, workability retention and rapid disper-
sion. Testing is required to determine the effect they have on the grout design.
Polycarboxylate superplasticizers are highly efficient HRWR additives that typically
allow high water reduction at a low dosage. They can provide much lower water contents
for the same consistency and/or higher slumps and flows at the same or slightly lower water
contents. They do not greatly retard cementitious mixtures like the lignosulfonate products.
If overdosed in the grout, it can create problems such as bleeding, segregation and retard-
ation. These are also provided by many companies and are formulated to provide variable
performance. This can include dose efficiency/flexibility, strength enhancement, workability
retention and rapid dispersion. Testing is required to determine the effect they have on the
grout design.
Anti-washout admixture can be used for grout placed in wet conditions such as between
the precast segmental tunnel lining and the TBM excavated rock surface. However, the use
of anti-washout additives in two component systems can cause problems with reactivity.
The accelerator may not blend easily with the grout, effecting performance.
• Batching
• Transport through the tunnel
• Grout injection into the annulus
The equipment can vary greatly depending on whether the grout is a mortar type one-
component grout or a two-component grout made with only cement and bentonite. Mortar
grouts require concrete style batching equipment at the portal (or shaft) and must be trans-
ported to the heading in grout cars. Two-component grouts can use a simpler colloidal mix-
ing system and pump the grout to the heading. Regardless of grout type, the entire system
must be sized to provide grout at the maximum rate that the TBM can advance. This can
vary widely depending on whether the TBM is an EPB, slurry or hard rock machine and the
type of ground that the TBM is advancing through. The batch plant is part of the supply
chain feeding the TBM and every part of the chain must have enough capacity to keep the
TBM advancing at its maximum speed.
Different powdered products are delivered by trucks with the same size and type fittings.
The connection ports should be clearly marked. Ports for different ingredients should have
a physical separation to make connecting to the wrong silo less likely to occur.
Because the batch plant is a link in the supply chain that keeps the TBM going, consist-
ency and reliability are key. Modern batch plants still require an operator to monitor the
operation and maintain the plant, but the batching process should be computer controlled.
Except for the absence of coarse aggregate, the batch plant is no different than any other
concrete batch plant and should be set up and operated with the same standards. After ini-
tial set up the batch plant should be certified to National Ready Mix Concrete Association
(NRMCA) or equivalent standards.
A storage tank with mild agitation is required so that the supply train or transporter can
be instantly filled and sent back into the tunnel. Although a good mix design will resist
bleeding and segregation, a paddle or ribbon mixer will ensure that a consistent mix is
delivered to the TBM. The storage tank should be at least equal in volume to the trans-
porter tank.
ingredients are added, the shearing action of the pump on the water and powder creates a
uniform, well blended mix in just a few minutes. Colloidal grout mixers come in various
sizes and can produce from 2 to 100 m3/hr (3 to 130 CY/hr). The same pump mixing the
grout can discharge the grout to the holding tank very quickly. The powdered ingredients
should still be weighed to ensure a consistent grout, but the handling of fine aggregates is
eliminated along with the need to determine the moisture content.
As with the one-component batch plant, consistent output and reliability are key. The
batch plant can be operated by computer with one operator to monitor and maintain the
plant. Since the number of ingredients is reduced and the powdered products have good-
quality control, the opportunities for problems are reduced. Although the plant is not a
concrete-style batch plant, the critical items such as the powder scales, the water meter and
the admixture meters should be calibrated according to manufacturer's specifications and
checked regularly.
Occasionally, the two-component grout will be delivered to the heading via rail or rubber-
tired vehicle. In these cases, a holding tank with mild agitation is required to load up the
transport vehicle as soon as it shows up at the shaft or portal.
The agitator is normally ribbon mixer on a horizontal shaft powered by the locomotive’s
hydraulic circuit. Sometimes the mixer is powered by an electrical motor. Once a valve at
the tank car bottom is connected to a pump and the car is emptied with the ribbon mixer
assisting by pushing the grout towards the discharge point. Because the ribbon mixer shaft
is below the top of grout, the bearing seals are exposed to the grout and a failure of the
seal leads to a failure of the shaft bearings. Make sure the bearings have automatic greasing
systems.
size with a rotor speed of 40 to 50 rpm and outputs in the 15 to 25 m3/hr (20 to 33 CY/hr).
A foam ball or bullet type pig can be pumped through peristaltic pumps arranged in series.
Other advantages of peristaltic pumps are that there are no seals or valves to wear out
or replace. The pump can accurately measure grout flow within 1%. The pump can move
sanded grouts, but wear is accelerated. The hose must be checked daily for delamination or
bulging. Tests pumping 20% slaked lime show a hose life of 800 to 1,000 hours and a min-
imum life of 400 hours is anticipated. The peristaltic hose can be replaced in 15 minutes.
The pump does produce a pulsating flow, but this is not a problem when pumping into a
holding tank on the TBM.
Each seal only handles the pressure difference between the adjacent cavities and the pressure
difference is limited to somewhere between 1 and 6 bar (15 to 90 psi). When more abrasive
fluids are pumped, the pressures towards the lower end are used.
PCP have at least two stages (cavities) and the number of stages increases as the pressure
goes up. PCPs get longer and more expensive as pressures go up and stages are added. PCPs
run at low speeds to keep rotor/stator friction heat low and this leads to physically large
pumps for high-pressure, high-volume pumping.
Because the fluid being pumped provides the sliding lubrication between the rotor and the
stator, the pump cannot be allowed to run dry. If allowed to run dry, the stator will heat up,
expand and be damaged in just a few minutes. Running the pump dry is the biggest reason
for PCP failures. PCPs should be set up to stop if dry running is detected.
PCPs excel at handling viscous fluids, accurate metering and providing a smooth non-
pulsating flow. The stator rotor assembly naturally functions as a valve with a seal between
each progressing cavity, so no check valves are required. The pump will accurately meter
flows over a wide range of head pressures. The volume pumped is directly proportional to
the rotor rotational speed. PCPs have a short life when pumping sanded grouts. PCPs have
some good characteristics and they have been used to pump two-component grouts through
tunnel pipelines, but they are better suited to be used as metering pumps on the TBM. PCPs
are more expensive than peristaltic pumps with the same pumping capacity.
Typical grout piston pumps used for tunnel supply lines range from 37 to 45 kW (50 to
60 HP) although smaller pumps are available. These pumps are a good alternative to the
peristaltic pump if higher pressures are required and no pumps can be permitted in the tun-
nel. These pumps are reliable although the pistons and cylinders wear and need to be peri-
odically replaced. They are more expensive than a similar sized peristaltic pump.
There should be a ball valve in the grout line every 100 to 150 m (330 to 500 feet).
A ball valve should be used instead of a cheaper butterfly valve to allow passage of cleaning
pigs. Gate valves can be used but they are more expensive and have lower- pressure
ratings. A valve is required because the grout line must be disconnected every time a new
piece of pipe is added. When the line is broken all the grout in the line back to the last valve
will run out. A bathtub style catch pan may be part of the tunneling scheme to catch and
reuse the drained grout but this pan has a finite capacity. Often the grout is just dumped
on the ground for the discharge water system to clean up. The muck extracted from the
water treatment plant then has a high Ph, which can cause disposal problems. Collecting
large quantities of spilled grout during final tunnel cleanup may also cause disposal issues.
Developing and using methods to minimize grout spillage during pipe extensions and clean-
ing will save time and money.
The valve, coupling and pipe should all have pressure ratings that exceed the pressure that
can occur when the grout line pump is pushing against a closed valve or plug. Otherwise,
the first time the grout plant operator turns the grout pump on, and someone forgets to
open the ball valve, the line will fail explosively somewhere in the tunnel and the other
connections will have been overstressed. A pressure relief valve should be installed just
downstream of the pump outlet, but one should not count on that valve to save the system.
The entire grout line should be composed of quality components from reputable suppliers.
When the grout line is in use, a cleaning pig (Figure 11.16) should be pushed through
the pipeline as often as every shift to wipe the pipeline walls clean of sludge. If the interval
between pig runs is too long, the pig runs the risk of becoming stuck when there is too much
sludge in the line. Running the pig from the surface batch plant to the TBM requires plan-
ning to catch the grout in a grout car or holding tank. Otherwise, the spilled grout in the
heading makes a mess and pumping it back to the surface through the waste discharge line
causes issues to the water treatment plant increase plant operating costs. Use a non-brush
type pig if using a peristaltic booster pump.
664 Handbook of Precast Segmental Tunnel Lining Systems
Running a cleaning pig through a grout line requires a written plan and training of the
workers to prevent injuries. The sudden release of energy occurring when a pig pushing a
plug of material comes out of the pipeline can be unexpected and very forceful!
should be mounted vertically to make sure a full flow of grout is read by the meter. Pressure
is measure by an electronic transducer. The flow meter can be anywhere between the pump
and the injection point. For tail shield grouting, the pressure sensor should be at the point
where the grout pipe enters the tail shield. Even then, the pressure sensor will still be about
4 m (13 feet) from injection point.
cement storage and two for bentonite. The bentonite was mixed in a colloidal mixer and
pre-hydrated in a tank prior to combining the ingredients in an 8 m3 (10 CY) concrete
mixer truck.
The mixer truck moved to the shaft and discharged the grout into a hopper at the top
of the shaft (Figure 11.20). Grout then traveled down a 250 mm (10 inch) drop pipe. At
the bottom of the shaft, an energy absorbing chamber received the grout and discharged
through a pipe to a grout tank on the supply train. The 8 m3 (10 CY) delivered to the train
was enough to grout the annulus of two rings.
All the grout pumps were the piston style positive displacement similar to a concrete pump.
Initially there was no waiting time for supply trains since a fresh resupply train could reach the
TBM before the ring build was complete. Once the TBM began to wait on trains, a passing place
(rail switch) was installed in the tunnel to allow a resupply train to wait closer to the TBM.
The TBM had four pairs of grout ports set up for grouting through the tail shield. The
grout ports were located at about 10, 2, 4 and 8 o’clock positions. At each pair of grout
ports, one was in active use and the other was a spare. Each grout port was connected to a
grout pipe embedded in the tail shield that had a connection at the front of the tail shield.
The spare grout ports and pipe were normally filled with grease to keep them clean and
Annular backfill grouting of precast segmental tunnel linings 669
Figure 11.22 Grout injection control panel screen shot from a Herrenknecht TBM.
Note: The injection system in manual mode. Only top two ports are active.
empty of grout until needed. The pressure sensor for each grout port was located at the
front of the tail shield where the grout pipe enters the tail shield, so the pressure sensor
measured the dynamic head and static head during a pump stroke. The static grout pressure
in the annulus 3.5 m (11.5 feet) away from the injection point was measurable only when
the grout was not moving. The maximum injection pressure was initially set at 6 bar (90 psi)
based on the formula below and using 4 bar (60 psi) as the reference pressure.
The grout could be injected using either the manual or automatic mode. In the manual
mode, the injection pumps were activated individually from the control panel and the
pumping speed could be adjusted. Start-up and cut-off pressures were preset but could be
adjusted if required. The pump had to be restarted manually when the injection pressure
value fell below the preset limits. Figure 11.22 shows one page of the touch screen grout
control panel.
In the automatic mode, the grout injection pumps started and stopped by operation from
the control panel. The start-up and cut-off pressures were preset, and the injection process
stopped when the cutoff pressure was reached in any of the injection lines. Process would
restart when the pressure fell below the cut-off value.
The computer calculated the theoretical volume of mortar required based on the advance
rate of the TBM. Relationship between the actual volume injected and the theoretical was
constantly monitored and reviewed. Grout volume parameters were set as follows:
670 Handbook of Precast Segmental Tunnel Lining Systems
(a) The maximum injection pressure was reached and did not drop or
(b) The maximum injection volume was reached
If (a) or (b) occurred, the TBM advance automatically stopped. Then the field supervision
checked the excavation (tons measured by the scales) and grout injection (injected m3) data.
The individual ring was checked but previous three rings were also checked to determine the
cause of the alarm and look for trends in the data.
Table 11.12 Initial annular grout mix design for the Riachuelo Tunnel.
Mix was considered unpumpable by the field supervision
Component quantities
Metric Imperial
Item Mix design components Quantity UoM Quantity UoM
A Primary materials for 1.0 m 3 for 1.0 CY
1 Cement 80 kg/m 3 138 lbs/C Y
2 Fly ash 250 kg/m 3
431 lbs/C Y
3 Aggregates 0 to 6mm (0 to 0.25-inch) 918 kg/m 3
1,581 lbs/C Y
4 Aggregates fine 795 kg/m 3
1,369 lbs/C Y
5 Water 230 kg/m 3
47 gal/C Y
B Admixtures
1 Retarder/s uperplasticizer combination 1 l/m 3 26 oz/C Y
Annular backfill grouting of precast segmental tunnel linings 671
Component quantities
Metric Imperial
Item Mix design components Quantity UoM Quantity UoM
A Primary materials for 1.0 m 3 for 1.0 CY
1 Cement 130 kg/m 3 224 lbs/C Y
2 Fly ash 250 kg/m 3
431 lbs/C Y
3 Bentonite 5.75 kg/m 3
10 lbs/C Y
4 Aggregates 0 to 6mm (0 to 0.25 inch) 728 kg/m 3
1,254 lbs/C Y
5 Aggregates fine 826 kg/m 3
1,423 lbs/C Y
6 Water 235 kg/m 3
54.7 gal/C Y
B Admixtures
1 Retarder/s uperplasticizer combination 1.0 l/m 3 26 oz/C Y
in the proposed mix were crushed gravel and natural river sand in combination with cemen-
titious material to form a paste with a low initial compressive strength and high plasticity.
The mortar was intended to move from a fluid and thixotropic behavior to stiff mortar
almost as soon as it was injected into the annulus. Injecting the mortar under pressure was
expected to expel part of the free water to help stiffen the grout. The mix was intended to
have an unconfined compressive strength of 0.2 MPa (29 psi) at 24 hours and 1 MPa (145
psi) at 28 days.
Supervision modified the mix by adding 5.75 kg/m3 (10 lbs/CY) of powdered bentonite
[one 23 kg (50 lb) sack in a 4 m3 (5.2 CY) grout batch]. Because the manufactured gravel
was jagged and elongated and did not have the round shape of natural pea gravel. More
natural fine sand was substituted for the 0 to 6 mm (0 to 0.25 inch) manufactured gravel.
Also, more cement was added resulting in the mix shown in Table 11.13.
Using bentonite provided lubrication and prevented bleeding, but the mix was still diffi-
cult to pump and slow to set. High pump pressures were required to move the grout through
the lines. Natural pea stone to replace the 0 to 6 mm (0 to 0.25 inches) manufactured gravel
was not commercially available. Considering the unreliable fly ash supply and the use of
manufactured gravel, the final modified mix design was as listed below in Table 11.14.
Pre-hydrated bentonite slurry provided a grout with more consistent properties over
time. The 5% bentonite slurry resulted in a total water content of 323 kg/m3 (67 gal/CY).
Bentonite addition was 7.25 kg/m3 (12.2 lbs/CY). Fly ash was eliminated and the 400 kg/m3
(675 lbs/CY) of cement compensated for the rough shape of the 0 to 6 mm (0 to 0.25 inch)
gravel. This one-component active mix was successfully used for the rest of the tunnel drive.
Table 11.14 Final one-c omponent active grout mix design for the Riachuelo Tunnel.
This mix used more cement to work with locally available materials
Component quantities
Metric Imperial
Item Mix design components Quantity UoM Quantity UoM
A Primary materials for 1.0 m 3 for 1.0 CY
1 Cement 400 kg/m 3 689 lbs/C Y
2 Fly ash
3 Pre-h ydrated bentonite slurry at 5% 147 kg/m 3 253 lbs/C Y
4 Aggregates 0 to 6 mm (0 to 0.25 inch) 757 kg/m 3
1,304 lbs/C Y
5 Aggregates fine 606 kg/m 3
1,044 lbs/C Y
6 Water 185 kg/m 3
38.15 gal/C Y
B Admixtures
1 Retarder/s uperplasticizer combination 2.28 l/m 3 60 oz/C Y
Test results
Specifications Test results
Project specification for
Item fresh grout Metric Imperial Metric Imperial
A Fresh grout
1 Viscosity 48 sec 46 sec
2 Bleeding (1 hour) <5% 0
3 Gel Time 8-1 2 sec 10 sec
B Strengths
1 1 hour >0.1 MPa >14.5 psi 0.2 MPa 29 psi
2 1 day 0.95 MPa 138 psi
3 7 days 1.65 MPa 239 psi
4 28 days >1.72 MPa >250 psi 1.95 MPa 282 psi
for 3.75 km (2.25 miles) at a pressure of 3.5 bar (50 psi). Six-piece segmental liner ring was
1.8 m (6 feet) wide and had a 7.01 m (23 feet) inside finish diameter. The annular gap to be
filled with grout was 133 mm (5.25 inches) wide. Tunnel started in a shaft and passed under
a river for 460 m (1,500 feet). The grout was batched at the TBM starting shaft and was
delivered to the TBM via a 75mm (3 inch) pipeline.
Grout was a combination of cement, bentonite and water. There was enough retarder in
the mix to keep the grout fluid in the pipeline for 72 hours. The grout proportions are listed
in Table 11.4. Contract requirements and the test results of the laboratory trial batch are
given in Table 11.15.
Annular backfill grouting of precast segmental tunnel linings 673
Figure 11.23 General site layout with weatherized batch plant and silos.
Note: Because the grout can be pumped, the batch plant does not have to be next to the shaft
allowing flexibility in layout.
674 Handbook of Precast Segmental Tunnel Lining Systems
Accelerator was brought to heading by rail flatcar in 1 m3 (273 gal) containers filled from
the 20 m3 (5,300 gal) tank on the surface.
All the grout and accelerator pumps were the progressive cavity type.
Like the Riachuelo TBM, the TBM had four pairs of grout ports set-up for grouting
through the tailshield located at about 10, 2, 4 and 8 o’clock. At each pair of grout ports,
one was in active use and the other was a spare.
The grout control panel was a touchscreen separate from the TBM operator’s controls.
This allowed the grout operator to monitor the grouting and the ground conditioning.
Figure 11.26 shows a page from the touch screen control panel.
The TBM PLC calculated the required grout volume based on the TBM advance. After
the target volume was reached, the PLC continued to pump grout until the target pressure
was reached as indicated by the pressure transducer on the discharge side of the pump.
At the start of an excavation stroke, the TBM operator would signal the grout plant
operator to commence the grouting operation. The grout was pumped first, followed, after
a short delay, by the accelerator. Mixing of the grout and accelerator occurred before the
grout exited the ports at the end of the tail shield.
The grout injection flow rate was regulated by the grout plant operator during excavation
to maintain a pressure range. When the TBM excavation stroke neared completion, the
TBM operator informed the grout operator who stopped the accelerator pump followed by
the grout pump. The accelerator pump was turned-off about 100 mm (4 inches) before the
end of the excavation stroke to prevent plugging the tail shield line. Immediately after, the
676 Handbook of Precast Segmental Tunnel Lining Systems
Figure 11.26 Grout injection control panel screen shot from the Herrenknecht TBM.
Note: Another page allowed the operator to set the grouting parameters
grout operator backflushed the system with water to prevent the grout lines from getting
blocked.
Grout pressures were measured continuously by pressure sensors located near the pump
on the TBM trailing gear. They were connected to the PLC, automatically stopped the
grout pumps if the pressures reached the maximum limit. The grout pressures were regu-
larly reviewed based on the actual quantity of grout being placed, monitoring of ground
movement and segmental lining movement. The volume and pressure of the grout and
accelerator was recorded automatically during advance. For immediate feedback, the
grout operator kept manual records of grout and accelerator consumption for every ring.
Grout pressures and quantities were set with percentage limits similar to those set for the
Riachuelo system.
be shut down for extended periods. Ideally end of the last mining shift was planned so that
pig chased out the grout need to complete the TBM advance so that only small amounts
were wasted. This was an important consideration as every 1,000 m (3,300 feet) of 75 mm
(3 inch) line held 4.4 m3 (5.6 CY) of grout and the final length of the pipeline was 3,658 m
(12,000 feet).
also added to the mess. Spilled grout was washed-down the invert and pumped out through
the waste discharge line to the water treatment plant. The sludge in the water treatment
plant would reach a pH over 12 and required the use of sulfuric acid to adjust the pH.
The cement and bentonite sludge were difficult to handle and expensive to dispose. For the
follow-on tunnel contract which was 8.2 km (5.1 miles) long, the tunnel grout pipeline was
eliminated in favor of grout cars.
six to eight rings behind the tail shield at the 12 o’clock position to fill the crown with pea
gravel. An open face of pea gravel fill was kept at injection locations to avoid pea gravel
locking up in the hose. Because a void in the crown could develop at previously injected
rings as pea gravel settled, pea gravel was re-injected at previously injected ports to ensure
complete filling.
• Getting the gravel to flow from the injection port to fill the annulus required consist-
ency during injection.
• Water could be injected at adjacent ports to provide lubrication and carry the pea
gravel to the invert, preventing the material from bridging.
• Directional inserts were welded to the injection port adapters to direct the gravel.
• Hoses from the hard line to the connection ports were steel reinforced and the bends
limited.
• Hose couplings were lengthened to prevent the hose from pulling-out at the segmental
liner and hardline connections.
• Hose blow outs and line wear would occur. Weak points in the system were addressed
and the workers protected at these locations. Hardened piping was used to transport
the gravel as close as possible to the injection locations.
Segment grout injection ports not previously used for pea gravel injection had to be
drilled out through the last 50 mm (2 inches) of concrete. A plastic check valve was threaded
down into the embedded injection port leaving enough thread to connect to the grout hose
adapter fitting. The check valve allowed the 75 mm grout hose to be disconnected after
injection was completed.
relevant ATSM document should be followed. Some of the tests are not ASTM prescribed
but are helpful to define a grout mix characteristics.
All equipment should be properly calibrated prior to any annular grout testing.
11.12.3 Density
The grout density will be calculated when the trial batch sheet is prepared. Density is a good
quick check to see if the batched grout has the right amount of water. This is especially true
for one-component mortar grouts where the aggregate moisture content is determined sep-
arately. A mud balance is a good way to check density quickly (see Figure 11.36).
686 Handbook of Precast Segmental Tunnel Lining Systems
To use the balance, fill the balance cup with the sample to be tested. Tap the side of the
balance cup several times to break up any entrained air or gases. Put the lid onto the balance
cup by pushing it downward with a slow rotating motion until it is firmly seated.
Make sure that some of the test sample is forced out through the vent hole in the lid. Clean
any sample from the outside of the balance cup and lid. Fit the knife edge of the balance
arm into the fulcrum and balance the assembly by moving the rider along the arm. The
mud balance is horizontal when the level bubble fluctuates an equal distance to either side
of the center line. Take the reading from the side of the rider nearest the balance cup. The
Annular backfill grouting of precast segmental tunnel linings 687
measurement reading should be recorded to the nearest 0.01 g/cm3 (which is equivalent to
specific gravity).
a stopwatch and measure the time from when you release the seal at the bottom and the
grout begins to flow until the full quart has passed through the funnel.
Stabilization time is typically measured using the same methods as for flowability and
viscosity. The loss of these properties is measured over time.
• The weight of rod and cone should be 100 grams (0.22 lbs)
• Measure the amount of accelerator to be used and pour into a 2 liter graduated
beaker (plastic). In a separate beaker, measure 1 liter of the grout minus the amount
690 Handbook of Precast Segmental Tunnel Lining Systems
Figure 11.41 Penetrometer.
Note: Use for time of set test.
• Keep stopwatch running and position the metal pan under the penetrometer.
• Adjust the height so the tip of the weight sits just on top of the grout. When the stop-
watch reaches a time of 1 minute, 30 seconds, drop the weight into the grout and
measure the distance. Reposition to a clean portion of the grout.
• Repeat this each minute (stopwatch: 2:30, 3:30, 4:30, etc.…).
The test is complete when three tests have a reading of less than 14 mm (0.55 inches).
Record the time at the final reading as the “setting time”.
Time of set for one-component mortar grouts can be determined using methods such as
ASTM C403/C403M the Standard Test Method for Time of Setting of Concrete Mixtures
by Penetration Resistance or ASTM C953 the Standard Test Method for Time of Setting of
Grouts for Preplaced-Aggregate Concrete.
A modified Vicat needle test (ASTM C807) is used to measure the time of setting of
hydraulic cement mortar (Figure 11.42). The elapsed tie after initial mixing of water and
cement required for the mortar to reach a penetration resistance of 500 psi is defined as ini-
tial setting time and the elapsed time to read a penetration resistance of 27.6 MPa (4,000
psi) is defined as final setting time. Penetration resistance is not the same as compressive
strength. A penetration resistance of 27.6 MPa (4,000 psi) corresponds to approximately
0.70 MPa (100 psi). Time of set is not commonly requested for two-component grouts.
mixed by pouring the grout sample into the accelerator and then back and forth between
the containers until the sample will no longer pour out of the container. The time from the
start of this procedure until its end is measured as gel time.
To perform the test, measure the amount of accelerator to be used and pour it into a 2
liter (67.6 fluid ounces) graduated plastic beaker. In a separate beaker, measure 1 liter of
the grout minus the amount of accelerator being used [example, if there is 80 ml (2.7 fluid
ounces) of accelerator, then add 920 ml (31 fluid ounces) of grout]. Next, start a stopwatch
then quickly pour the accelerator into the grout then back and forth between the beakers.
Do this until the grout “gels” and no longer flows.
the excess grout to make a flat top. Cover with plastic wrap and a heavy flat object. Record
the time at pouring.
After the grout has been in the molds 60 minutes, carefully remove the test cubes and
submerge them in a bucket of water kept at 20°C (68°F). Select a cube and place on the
compressive strength testing device (Figure 11.45). Position it so the entire cube is within
the extents of the upper and lower crushing plates. Set the meter to measure the peak force
with the desired unit. Compress the cube and record the reading on the meter. Repeat this
for a second and a third cube. Being sure to have consistent units, convert the force into
pressure by dividing the reading by the area of one side of the cube. Average and record the
three pressure readings. After another 5 hours (6 hours since cubes poured), repeat this test
for a second set of three cubes. Retain the other three cubes in water to be tested 28 days
later by a certified lab.
694 Handbook of Precast Segmental Tunnel Lining Systems
• Density
• Slump
• Set time
• Bleed
• Temperature
• Grout cubes
• Air content
Density measurements made with a mud balance provide a quick way to check the amount
of water in the mix since all other ingredients are weighed and the moisture in the aggregate
is the only variable. Air content should be checked if the grout density is low.
For two-component grout, the batch plant uses a simple colloidal mixer and there is no
need for moisture adjustments as there are no aggregates. As with the one-component plant,
the scales and meters should be tested during commissioning and once every six months
thereafter. Tests that should be done at the batch plant include the following:
Annular backfill grouting of precast segmental tunnel linings 695
• Density
• Viscosity
• Bleed
• Temperature
A quick test with the mud balance will show if the water/cementitious ratio is cor-
rect. Air content need be checked only if the water and cement have been weighed but
the density is too low. No test samples for compressive strength are taken at the batch
plant because testing without the accelerator added would not be representative of the
injected grout.
On smaller TBMs without an upper trailing gear deck there is no room for drilling cores
at the crown position. For larger TBMs, the upper deck is filled with equipment although
there may be small areas that can accommodate core drilling operations. At the tail end of
the trailing gear begins the ventilation line which occupies the crown and prevents any fur-
ther grout investigation until the ventilation line is taken down at the end of the TBM drive.
If the designer wants to verify grout fill by coring, he should specify that a section of TBM
trailing gear be dedicated to that task so that equipment and labor can be included in the
contractor’s bid.
A typical coring program will include more coring and testing at the beginning of the
tunnel; on the order of two proof holes every 5th ring for the first 50 to 100 rings. If the
grouting program is shown to be effective, the proof holes can be eliminated. If the proof
holes show a problem, the proof hole testing can be extended.
Coring is required at the crown because that is the most likely spot for a void but some-
times core holes are required at 10 or 2 o’clock. Observations are made during coring
for penetration rate, water flow and depth to the native ground. Coring is done past the
grout into the ground to see if the grout completely filled the annulus. The core hole is
examined for voids. Core holes are usually 50 mm (2 inches) in diameter. Since the hole
is cored through the segment and is typically 330 to 430 mm (13 to 19 inches) deep, one
needs a fiber optic inspection tool or a hooked probe to determine if there are any voids.
If voids are discovered, proof grout can be injected to fill the void. Use a metered grout
pump to determine the size of the void. Injection pressure is usually groundwater pressure
plus one bar.
If high pressure groundwater is present, and if the ground can be mobilized by water
movement, drilling through a segment to check grout fill is not a good idea. If the grout is
not placed promptly behind the tail shield, the ground will have moved in to fill the void
before one can check for grout and this will be obvious from ground settlement measure-
ments. When a TBM is tunneling through sandy, gravely, or silty ground beneath an inex-
haustible source of water such as a river or estuary, coring through the lining has more risks
than benefits and other methods should be used such as impact-echo testing.
Placing annular grout in a rock tunnel can be quite different than in soft ground if over-
break is expected and the excavated face is at atmospheric pressure. A good example would
be a large diameter TBM excavating at atmospheric pressure through horizontally stressed
shale. The ground can be expected to break out at the shoulders and rock may be resting on
top of the TBM and the segmental liner. The annular grout is not going to fill large crown
voids. Instead placing additional grout will only push the grout towards the TBM. In this
situation, it makes sense to drill holes on a systematic basis, say one hole every ten rings to
check for voids. When a void is discovered, a grout line tied to the annular grout system
can be used to fill the void with grout. If using a two-component grout, accelerator may
be reduced to allow the grout to travel farther. In this manner, the contact grout can be
addressed as the TBM advances.
to educate the workers and reduce hazards. This section will look at these safety aspects of
the grouting operation:
• Personnel training
• Grout mix design
• Site layout
• Equipment selection
• Equipment installation and commissioning
• Start-up
• Operations and maintenance
A constant theme that runs through the above list is that pumping and injecting grout
involves high pressures with the possibility for sudden uncontrolled releases of energy. The
stored energy exists over long distances where people working on the same grout line are
not in sight or in verbal communication with each other. Stored energy in a pipe or hose will
not be evident but is present. Even when the grout is behind the segmental liner, there is a
chance of injury while the pressurized grout is still fluid.
New workers should never be put in the tunnel untrained. They should be trained by a
supervisor in the procedures and hazards to the same standard as the original crew members.
the location of the cement delivery truck (which has to park and unload for 1.5 hours)
be such that the delivery truck driver can make his connections to the silos without being
struck by passing equipment? Are the deliveries of chemicals by tanker or totes compatible
with the parade of trucks hauling muck away from the site? Are the turning radii of large
trucks accounted for? Is the batch plant clear of overhead swinging loads to the shaft? Are
all existing and temporary utilities considered? There are many different solutions to these
problems.
As we saw in the Riachuelo Project (Section 11.9), the interaction of the grout plant
operations with the rail crane servicing the main shaft was largely eliminated by batching
the grout away from the shaft and bringing the grout to shaft with a concrete mixer truck.
This was a good solution for the Riachuelo jobsite but a different jobsite, say in New York
City, would require a different solution.
The commissioning process is well defined when a multi-million dollar piece of equip-
ment like the TBM is assembled on site. Manufacturers have check lists which should be
followed for safety and to ensure the warranty is enforceable. Often, a gap exists between
various equipment systems which the site management must fill with experienced personnel.
For example, the surface grout plant and the TBM probably come from separate manufac-
turers. The site needs to identify the interface, which in this case would be the grout line
between the batch plant and the TBM, and make sure that the two work together smoothly.
11.14.6 Start-up
Start-up can be a dangerous process. While the individual pieces of equipment have been
tested in the commissioning process, some parts of the process cannot be tested until grout
is run through the lines and injected behind the segments. The equipment and personnel are
new to the site, the process of batching and delivering the grout is untested, and the pressure
exists for the jobsite to produce. There is an entire complex chain of processes that must
take place for the grout to be safely delivered and injected and the grouting process is only
one of many starting up. There most certainly will be pieces of equipment that do not func-
tion as intended and grout lines that get plugged. As the entire tunneling enterprise cannot
advance until the grout system is operating, the pressure to take shortcuts can be intense.
The risks of start-up are reduced when the previous steps of personnel training, devel-
oping a good grout mix, selecting the right equipment, and testing equipment are taken
seriously. Daily briefings with the workers to explain what is about to happen and what
hazards exist must be done. Communication from every critical point along the grout pro-
cess must exist whether that is by radio, mine telephone or at pre-shift meetings. Every
worker must be empowered to stop the process if something amiss is observed.
Personnel responsible for commissioning equipment should also be on hand for startup.
Site leadership needs to exhibit patience and set the example for the crews by following the
written procedures. The first time a grout line is clogged, site supervision needs to lead the
way in finding the plug, releasing the pressure and cleaning out the plug. A determination
must be made on why the plug happened in the first place. Start-up will include establishing
grout batching and pumping capacities. Fine tuning will be necessary. Procedures changed
in the field need to be immediately followed up with revised work plans that include any
new hazards created by the changes.
• Grout burns
• Eye injuries
• Foot injuries
The simplest measures of wearing standard personal protective equipment (hardhat, gloves,
safety glasses, and steel tied boots) will go a long way towards abating some of the hazards.
Other hazards described in more detail below are as follows
• High pressures
• Slips, trips and falls
• Cleaning out the equipment
• Changes in routine and procedure
Pipe couplings
Rigid pipe and flexible hoses (Figures 11.47 and 11.48) are assembled with quick connec
tion clamps to facilitate cleaning. These clamps have safety pins and clips which should
always be reinserted after taking a coupling apart. Keep plenty of spare pins and clips on
hand. Some couplings use two bolts to hold the coupling together. Bolted couplings must
use the correct bolts. The coupling and hose end must be cleaned off before making up the
connection to ensure that no foreign objects are trapped in the coupling. The couplings
must use the correct gasket. Never use damaged couplings. A good connection has a certain
look to it. Make sure that all connections are good.
Grout
Grout spills, especially of unaccelerated two-component grout, can be slippery, in the
curved invert of the smoothly finished precast tunneling. Even clean wet inverts are slip-
pery. Steel deck plates can also become slippery. When hoses and pipe are disassembled
for cleaning, the resultant wash water and grout ends up in the curved invert. Any grout
spills should be cleaned. Best practice is to clean up the grout spill immediately into a skip
box and not through the discharge pipe because the grout will eventually plug the dis-
charge line.
Lock-out/tag-out
Never allow workers to clean powered equipment without making sure the equipment
cannot be accidentally turned on. This applies to electrical equipment but can also apply
to pressurized water and hydraulic lines. Have a lock-out/tag-out station on the TBM
(Figure 11.49).
Confined space
A worker may occasionally be required to enter a space not set up for human occupation
defined as a confined space. Working in these areas requires special training of the entire
work crew. Make sure that proper ventilation is provided, a watch is kept on the worker,
method of extracting on unconscious worker exists are in place, and proper confined space
paperwork is filled out and kept for record purposes.
rated against pressure washer penetration add another layer of protection. Have eyewash
stations on the TBM where grout is handled, or equipment may be disassembled.
BIBLIOGRAPHY
For preparation of this chapter, the following references were used, which are categorized into two
categories of authority published documents and authored documents.
C39/C39M, Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens.
C109/C109M, Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using
2-inch or [50mm] Cube Specimens).
Annular backfill grouting of precast segmental tunnel linings 707
EFNARC:2005, Specification and Guidelines for the Use of Specialist Products for Mechanized
Tunneling (TBM) in Soft Ground and Hard Rock.
European Standards/European Norms (EN)
EN 480-4:1997, Determination of Concrete Bleeding.
EN 413: 1995, Masonry Cement–Part 2: Test Methods.
ITA Report No.4, Guidelines on Best Practices for Segment Backfilling, May 2014.
National Ready Mix Concrete Association (NRMCA)
Plant Certification Electronic Checklist Version 03.20.20.
Plant Inspector’s Guide.
AUTHORED DOCUMENTS
Ivantchev, A.; Del Rio, J.; 2015, “Two-Component Backfill Grouting for Double Shield TBMs”,
ITA-AITES World Tunnel Congress, Dubrobnik, Croatia, May 22–28, 2015.
Linger, L.; Cayrol, M.; Boutillon, L.; 2008, “TBM’s Backfill Mortars –Overview –Introduction to
Rheological Index”, Tailor Made Concrete Structures 2008, J.C. Walraven and D. Stoelhorst,
editors, Taylor & Francis, London, pp. 271–276.
Maidl, B.; Herrenknecht, M.; Maidl, U.; Wehrmeyer, G.; 2012, Mechanised Shield Tunneling, 2nd
Edition, February 2012, Ernst & Sohn, Berlin, Germany, 490 p.
Mok, P.; Norbert, M.; 2014, “Tunnel Boring Machine Excavation Stability–Double Shield Tunnel
Boring Machine Advance with Partially Grouted Annulus”, 15th Australasian Tunneling
Conference 2014, Sydney, NSW, Australia, September 17–19, 2014.
Novin, A.; Tarighazali, S.; Mohammad, F.; Fasihi, E; Mirmehrabi, S; 2015, “Comparison Between
Simultaneous Backfilling Methods with Two Components and Single Component Grouts
in EPB Shield Tunneling”, ITA-AITES World Tunnel Congress, Dubrobnik, Croatia, May
22–28, 2015.
Pellegrini, L.; Perruzza, P.; “Sao Paolo Metro Project– Control of Settlements in Variable Soil
Conditions Through EPB Pressure and Bicomponent Backfill Grout”, Proceeding of the Rapid
Excavation Tunnel Conference 2009, G. Almararis and B. Mariucci, editors, Society for Mining,
Metallurgy, and Exploration, Las Vegas, NV, June 14–17, 2009.
Pelizza, S.; Peila, D.; Borio, L.; Dal Negro, E.; Schulkins, R.; Boscaro, A.; 2010, “Analysis of the
Performance of Two Component Backfilling Grout in Tunnel Boring Machines Operating
Under Face Pressure”, ITA-AITES World Tunnel Congress 2010, Vancouver, Canada, May
14–20, 2010.
Salini Impregilo /Webuild S.p.A. Argentine Office, 2021, Riachuelo 3 the Tunnel and the Underground
Worlds in Culture, Webuild S.p.A., Buenos Aires, Argentina.
708 Handbook of Precast Segmental Tunnel Lining Systems
Shirlaw, J.; Richards, D.; Ramond, P.; Longchamp, P.; 2004. “Recent Experience in Automatic Tail
Void Grouting with Soft Ground Tunnel Boring Machines”, Proceedings of the 30th ITA-
AITES World Tunnel Congress, Singapore, May 22–27, 2004.
Thewes, M.; Budach, C.; 2009 “Grouting of the Annular Gap in Shield Tunneling–an Important
Factor for Minimization of Settlements and Production Performance”, Proceedings of the 35th
ITA World Tunnel Congress, Budapest, Hungary.
Vitale, M.; Carlson, J.; Garrod, B.; Gabriel, D.; 2013, “Innovation in Annular Grouting at the Euclid
Creek Tunnel, Cleveland, Ohio”, Proceedings of the Rapid Excavation Tunnel Conference
2013, M.A. DiPonio and C.J. Dixon, eds., SME Press, Engelwood, CO.
Youn, B.; Schulte-Schrepping, C.; Breitenbucher, R.; 2016, “Properties and Requirements of Two
Component Grouts in Mechanized Tunneling”, ITA World Tunneling Congress 2016, San
Francisco, April 22–28, 2016.
Chapter 12
12.1 INTRODUCTION
Tunnels are typically designed for a service life of more than 100 years. In segmentally
lined tunnels, the durability of a tunnel is directly related to the durability of the concrete
segments, acting as both the initial support and the final lining. In this chapter, the most-
frequent degradation mechanisms of concrete linings are briefly discussed. This includes
reinforcement corrosion by chloride attack and carbonation, and sulfate and acid attacks as
major deterioration processes caused by external agents. This discussion will also include
frost attack, freeze-and-thaw, and alkali-aggregate reactions caused by internal chemical
reactions. Stray current-induced corrosion is also introduced as another major durability
concern specific to the railway and the subway tunnels. Mitigation methods for stray cur-
rent corrosion, including the use of fiber reinforced concrete (FRC) segments are presented,
and durability of segments under the coupling effects of stray current and other conven-
tional degradation mechanisms are explained.
The conventional approach for durability design, based on European codes EN 1992-1-
1:2004 and EN 206-1:2013, American code ACI 318-19, and Canadian code CSA A23.1-19
are summarized. Using these standards, recommendations made on concrete strength class,
maximum water-to-cement ratio (w/c), minimum cementitious materials content, minimum
air content and other requirements to ensure tunnel durability are explained. Although the
durability recommendations of other guidelines such as BS PAS 8810 (2016), DAUB:2013,
AFTES (2005), ÖVBB (2011) and LTA (2010) are not covered in this chapter, their method-
ologies are very similar in nature to EN, ACI and CSA methods. Performance-based service
life design for concrete structures is explained and an example of using this methodology to
design service life of a segmentally lined tunnel is given.
DOI: 10.1201/9781032675541-12
710 Handbook of Precast Segmental Tunnel Lining Systems
Diameter
Tunnel Completion
Item Tunnel name Location type Metric Imp’l year
1 Basel/O lten Hauenstein Switzerland Railway 1916
2 Northern Line Old Street to United Metro 3.5m 11.5’ 1924
Moorgate Kingdom
3 Shimonoseki/M oji Kanmon Japan Railway 1944
4 Mikuni National Route 17 Japan Highway 7.6m 25.0’ 1959
5 Uebonmachi-N ipponbashi Japan Railway 10.0m 32.8’ 1970
6 Dubai Road Tunnel UAE Road 3.6m 11.8’ 1975
7 Tokyo Underground Japan Road 1976
8 Berlin Tunnel Airport Germany Road 1978
9 Second Dartford Tunnel United Road 9.6m 31.5’ 1980
Kingdom
10 Mass Transit Railway Hong Kong Metro 5.6m 18.4’ 1980
11 Ahmed Hamdi Egypt Road 10.4m 34.1’ 1980
12 Stockholm Underground Sweden Metro 1988
Source: Abbas, 2014.
Durability and service life of precast segmental linings 711
infiltration initiates from the lining extrados, whereas corrosion due to deicing salts sprayed
from vehicle tires starts from lining intrados.
When the chloride concentration in concrete exceeds the threshold level between 0.15
and 0.6% by mass of cement (ACI 318-19), iron atoms lose electrons in anode and electrons
flow in the rebar to cathode and react with water and oxygen in the concrete to
form hydroxide (OH-). The ferrous ions (Fe+2) then combine with hydroxide to form iron
hydroxides, Fe(OH)2, also known as rust. For more information about electrochemical cor-
rosion reactions in concrete reinforcement, refer to ACI 533.5R-20 and Wang et al., 2018.
Rust, as the reaction product, has a greater volume than steel, which then exerts pressure on
concrete solid skeleton. When concrete tensile stress exceeds its tensile strength, this results
in cracking, delamination, and spalling in the concrete (Figures 12.1 and 12.2).
conjunction with sufficient concrete cover over reinforcement, provide high-quality and dense
concrete that can delay the initiation time of corrosion, also known as propagation time,
beyond the service life of the structure. Further details regarding code recommendations to
reduce chloride attack are provided in Section 12.3. Two other effective mitigation methods,
which are not outlined in the codes are using cements with high amounts of tricalcium alumi-
nate (C3A or 3CaO Al2O3) and the addition of corrosion inhibitors to concrete mixture.
There is also another type of sulfate attack, known as internal sulfate attack, which is
caused by the sulfate present in cement, which is commonly referred to as delayed ettringite
formation (DEF). DEF, however, is observed in concrete only when the initial concrete curing
temperature is high [greater than 160°F (70°C)], or in the case of mass concrete due to
excessive heat of hydration. Project specifications usually prohibit such high curing tempera-
tures for precast concrete tunnel segments. Therefore, it is expected that damages in tunnel
linings due to sulfate attack start on segment extrados and at the interface between the lining
and the ground where sulfate from ground or groundwater can penetrate the concrete.
Sulfate attack can be mitigated in a number of ways:
Because sufficient moisture is needed to promote the destructive expansion, PCA IS536
reports the internal relative humidity of 80% as a threshold, below which the alkali-silica
reactivity can be virtually stopped.
Concrete tunnel linings are not different from general types of concrete elements as far as
AAR sources, which are internal reactive aggregates. Therefore, the degradation mechanism
of AAR does not depend on the specific use of each tunnel. Sub-sea tunnels may be more
susceptible due to exposure to warm seawater-containing dissolved alkalis that may aggra-
vate ASR. AAR can be mitigated using inert aggregate, controlling the amount of soluble
alkalis in concrete, and using blended cements with pozzolans.
All of these measures, with the exception of the latter, are effective in reducing the amount
of stray current and, therefore, are considered as general measures for stray current corro-
sion mitigation of all metals embedded in the ground or reinforcement in both cast-in-place
and precast segmental linings.
Brenna et al. (2010) used finite element method (FEM) simulations to study specific cases
of reinforcement corrosion in precast segments due to stray current. In their simulations,
stray current was due to the traction power of surface tramway lines in close proximity to the
tunnel, and not from the catenary system of the subway train inside the tunnel (Figure 12.8).
While this particular simulation pertains to a subway line in Milan, located under an oper-
ating surface tramway line, results of this study can be extended to general segmentally lined
tunnels. Figure 12.9 shows the conduction field in the ground and equipotential surfaces
around the segmental ring under a tramway track voltage of 8 volts, corresponding to rush
hour conditions. As shown in Figure 12.10, the area near the joints between two adjacent
segments has been studied as a critical aspect of the model. The current leaves the upper
segment (Segment #6 on Figures 12.9 and 12.10), flows into the ground, and then returns
to the adjacent segment (Segment #5 on Figures 12.9 and 12.10). Particular parts of the
reinforcement where current leaves the reinforcing bar, constitute the anode where corro-
sion can initiate, depending on the reinforcement-to-ground potential difference.
Simulation results in this research demonstrate that the potential difference between the
reinforcement and ground, for example for Segment #6 on Figures 12.10 and 12.11, is
greater than the maximum value allowed by EN 50122-2:2010, indicating the possibility
Durability and service life of precast segmental linings 719
of corrosion initiation. Therefore, a potential mitigation method for stray current corrosion
in precast reinforced concrete segments is providing an equipotential connection between
reinforcing bars of adjacent segments and of adjacent rings to prevent zones of high output
current density.
As shown in Figures 12.12 and 12.13, Dolara et al. (2012) modeled this solution by using
copper plates connecting reinforcement cages of adjacent segments together, for the same
tramway line studied by Brenna et al. (2010). In this figure, the traces of reinforcing bars
in adjacent segments were presented with red dashed lines connected together with a plate
connection. Using this solution, the equi-potential connections between reinforcing bars of
segments in a ring constitute a path with extremely low electrical resistance that allows the
current to flow from one segment to another without passing through the ground (Dolara
et al., 2012).
Electrically connected bars behave like a cylindrical metallic shield that allows the stray
current to distribute in a nearly uniform way, both when entering from the top (crown)
and when leaving from the invert of the tunnel. In this case, the anode is the ring outer sur-
face near the invert and the maximum potential difference between the reinforcement and
ground is reduced by more than 15 times. A conclusion can be drawn that an equipotential
connection between the reinforcement of adjacent segments reduces the reinforcement-to-
ground potential difference (voltage) to values well below the standard limits for corrosion
initiation (EN 50122-2:2010) and provides an effective method to prevent stray current
corrosion.
Steel fiber-reinforced concrete (SFRC) has been introduced as an effective mitigation
method for stray current-induced corrosion (Tang, 2017; Solgaard et al., 2013). Results of
studies on stray current corrosion indicate that reinforcing bars are more likely to pick up
the current than short steel fibers under the same conditions (Edvardsen et al., 2017). This
can be attributed to the chloride threshold for the corrosion of reinforcing bars in concrete,
which is between 0.15 and 0.6% by mass of cement (ACI 318-19). On the other hand,
steel fiber-reinforced concrete demonstrates a much higher corrosion resistance compared
to rebar with a chloride threshold level of 4% by mass of cement, which is one order of
magnitude higher than the reinforcing bars (Tang, 2017).
722 Handbook of Precast Segmental Tunnel Lining Systems
From a theoretical point of view, corrosion current can be picked up by the reinforcement
if the potential difference between the anodic and cathodic areas at least equals the sum
of the anodic and cathodic polarizations. This polarization of the reinforcement is con-
trolled by the level of the stray currentfield and the distance between the anode and cathode.
Stray current may flow through the rebar or steel fibers embedded in concrete only when a
threshold value of driving voltage in the concrete is reached between the opposite ends of
the reinforcement (Bertolini et al., 1993). Solgaard et al. (2013) performed a comparative
experimental study between a commercial steel fiber [hooked-end, 1.4 inches (35 mm) long
and 0.022 inch (0.55 mm) in diameter] and a short carbon steel bar 14 inches (350mm) long
and 0.4 inches (10mm) diameter. They evaluated the stray current flow versus the potential
gradient needed for the current pickup.
Views of specimens and schematics of experimental test set-up for stray current measure-
ments are shown in Figures 12.14 to 12.16. Results of their studies, as shown in Figures 12.17
and 12.18, indicate that the minimum potential gradient required for current circulation in
the steel fibers is about 3.05 to 3.96 V/ ft (10 to 13 V/ m) compared to
rebar specimens, with an observed potential gradient of 0.21 to 0.03 V/ft (0.7 to 0.1 V/m).
Confirming the theory, this indicates a linear relationship between the required potential
gradient and length of the reinforcement solution for stray current circulation. The rebar
used in these experiments is only 10 times longer than the fibers, whereas rebar used in
practice can be several orders of magnitude longer. Thus, in practice steel fibers are much
less susceptible to transferring current than rebar for concrete structures subjected to the
same level of stray current. Additionally, results of the study conducted by Solgaard et al.
Durability and service life of precast segmental linings 723
Figure 12.14 Experimental test set-u p for stray current measurements—s teel fibers.
Notes: (a) Top view of specimens with fibers; (b) side view of specimens with fibers.
Source: Adopted from Solgaard et al., 2013.
Figure 12.15 Experimental test set-u p for stray current measurements—s teel bars.
Notes: (a) Top view of specimens with short rebar; (b) side view of specimens with short rebar
(Solgaard et al., 2013).
Source: Adopted from Solgaard et al., 2013.
(2013) indicate that after stray current was picked up by the embedded steel, the stray cur-
rent potential gradients in steel fiber specimens (Figure 12.17) are much lower than those
for rebar specimens (Figure 12.18). This further highlights the significance of steel “length
effect” on the stray current corrosion.
For example, in order for stray current flow of 0.5mA to be circulated through the
embedded steel, the potential gradient required for steel fiber is more than 6.1 V/ft (20 V/
m) compared to 0.37 V/ft (1.2 V/m) for steel bar. Therefore, the potential gradient required
for the circulation of the current through a single fiber was of the order of several volts per
minute, which is not realistic in actual structures. This is because, in the case of rebar, the
724 Handbook of Precast Segmental Tunnel Lining Systems
Figure 12.16 Experimental test set-u p for stray current measurements—g eneral arrangement.
Note: Experimental set-u p for stray current measurements.
Source: Adopted from Solgaard et al., 2013.
Figure 12.18 Stray current potential gradients in tunnel segments—s hort steel bars.
Note: Current transferred by embedded steel as a function of the potential gradient between the
left and the right side of (after long-t erm exposure): short steel bar.
Source: Adopted from Solgaard et al., 2013.
polarization contributions of the anodic and cathodic sites are less intensified and diluted
along the length of the bar.
A conclusion can be drawn that in real structures where the rebar may be tens of meters
long compared to 14 inches (0.35 m) in this study, the potential gradient required for the
circulation of stray current may be negligible. In contrast, in the case of steel fibers, which
are not electrically interconnected, as shown in Figure 12.19, the stray current should con
tinuously enter and exit every single fiber, each time dissipating the driving voltage for
anodic and cathodic polarizations. This is presented schematically by a “red path” in
Figure 12.19 compared to the least resistance path presented by a “green path.” Therefore,
“length effect” makes a clear distinction between discrete steel fibers and continuous steel
bars, making the risk of stray current circulation extremely low in the case of concrete rein-
forced only by steel fibers.
726 Handbook of Precast Segmental Tunnel Lining Systems
The higher chloride threshold found for steel fibers was also explained by an effect of cold
drawing, which may increase the polarization resistance and decrease the surface roughness
and micro-structural defects (Solgaard et al., 2013). Therefore, steel fibers are less suscep-
tible to stray current-induced corrosion than ordinary rebar; not only because of their short
length but also because of higher intrinsic resistance to chloride-induced corrosion.
As far as the risk of circulation of stray current through steel fiber is concerned, the posi-
tive effect of short fiber length may be reduced when fibers come into direct electrical con-
tact. The conventional amount of steel fiber added to the concrete is usually around 0.5%
volumetric or 67 lbs/yd3 (40 kg/m3) by mass. Although some fibers are likely to touch each
other and thereby form a metallic path through the concrete, it is very unlikely that the steel
fibers generate a continuous metallic path, similar to reinforcing bars. Also, the accidental
presence of a few fibers electrically interconnected by surface contact, would not reduce the
order of magnitude of the threshold values of the potential gradients shown in Figure 12.17;
consequently, extremely low stray current would be expected even in this case.
In summary, the short, discontinuous and discrete nature of steel fibers or the length-
effect is the main reason for the high corrosion resistance of SFRC, as fibers rarely touch
each other and there is no continuous conductive path for stray currents through the con-
crete (ACI 544.1R). This in addition to higher intrinsic resistance to chloride-induced cor-
rosion because of the cold-drawing fabrication process suggests that there would be no risk
in relation to stray current corrosion of steel fibers in concrete. Even if steel fibers corrode,
it will not lead to structural damage in the form of cracking and/or spalling [Graeff et al.,
2009)].
(Continued)
727
newgenrtpdf
Table 12.2 (Continued)
728
Degradation Type of tunnels susceptible to Location of tunnel
Figure 12.20 Study on stray current with multiple concrete degradation mechanisms—g eneral.
Note: Size and layout of experimental segment samples and reinforcement.
Source: Li et al., 2014.
Figure 12.21 Study on stray current with multiple concrete degradation mechanisms—s ection.
Note: Schematics of test set-u p for combined effect of chloride and sulfate penetration and
stray-c urrent.
Source: Li et al., 2014.
Figure 12.22 Study on stray current with multiple concrete degradation mechanisms—t ests.
Note: Views of carbonation test set-u p.
Source: Li et al., 2014.
730 Handbook of Precast Segmental Tunnel Lining Systems
Figure 12.23 Study on stray current with multiple concrete degradation mechanisms—d evices.
Note: Views of carbonation test set-u p.
Source: Li et al., 2014.
Figure 12.24 Study on stray current with multiple concrete degradation mechanisms—rebar cage.
Note: Corrosion in main reinforcement and stirrups.
Source: Li et al., 2014.
Figure 12.25 Study on stray current with multiple concrete degradation mechanisms—s tirrup.
Note: Corrosion in main reinforcement and stirrups.
Source: Li et al., 2014.
Durability and service life of precast segmental linings 731
obstruction of the concrete pores through which chloride ions migrate. In addition, results
demonstrate that the carbonation depth in segment intrados is only 0.04 to 016 inches (1
to 4 mm), concluding that carbonation is not a controlling durability factor for concrete
segments when compared to the chloride and sulfate ion penetration and stray current
corrosion. Considering the results of this study, a conclusion may be drawn that coupling
factors of chloride ion penetration and stray current has the most detrimental effect on the
durability of precast concrete tunnel segments.
Depending on the severity of exposure class, ranges of XC1 to XC4, XD1 to XD3, XS1
to XS3, XF1 to XF4, and XA1 to XA3 are provided for different exposure conditions. For
clarity, as shown in Table 12.3, EN 1992-1-1:2004 describes the environmental condition
for each exposure class and provides informative examples where each exposure classmay
occur. Nonetheless, EN 1992-1-1:2004 does not directly provide informative examples for
underground construction. EN 206-1:2013 provides specific limiting values for exposure
classes in the case of chemical attack from natural soil and groundwater, which is presented
here on Table 12.4.
For the specific case of tunnel lining, suggested exposure classes for carbon dioxide-
induced carbonation are XC3 to XC4, for seawater chloride-induced corrosion are XS2
to XS3, for deicing salt chloride-induced corrosion are XD2 to XD3, for freezing and
thawing are XF3 to XF4, and for harmful ions other than chloride (such as Mg+2, SO42-
) are XA1 to XA3 (Helsing and Mueller, 2013). The concrete requirements specified by
732 Handbook of Precast Segmental Tunnel Lining Systems
Exposure class
Chemical Reference
Item characteristic test method XA1 XA2 XA3
A Groundwater
1 SO 42- mg/l EN 196-2 ≥200 and ≤600 >600 and >3,000 and
≤3,000 ≤6,000
2 pH ISO 4316 ≥5.5 and ≤6.5 <5.5 and ≥4.5 <4.5 and ≥40
3 CO 2 mg/l; aggressive EN 13577 ≥15 and ≤40 >40 and ≤100 > 100 up to
saturation
4 NH 4+ mg/l ISO 7150-1 ≥15 and ≤30 >30 and ≤60 > 60 and ≤100
5 Mg 2+ mg/l EN ISO ≥300 and ≤1,000 >1,000 and > 3,000 up to
7980 ≤3,000 saturation
B Soil
1 SO 42- mg/l [1]
total EN 196-2 [2] ≥2,000 and >3,000 [3] and >12,000 and
≤3,000 [3] ≤12,000 ≤24,000
2 Acidity according to EN 16502 >200 Not encountered in practice
Baumann Gully ml/k g
Source: EN 206-1 :2013, Table 2.
Notes:
[1]
Clay soils with a permecability below 10 -5 m/s may be moved into a lower class.
[2]
The test method prescribes the extraction of SO 42- by hydrochloric acid; alternatively, water extraction
may he used, if experience is available in the place of use of the concrete.
[3]
The 3,000 mg/k g limit shall be reduced to 2,000 mg/k g where there is a risk of accumulation of sulfate
ions in the concrete due to drying and wetting cycles or capillary suction.
Structural classification
Exposure class according to Table 4.1 on EN 1992-1 -1 :2004
(Table 12.3 here)
XD2/ XD3/
Item Criterion X0 XC1 XC2/XC3 XC4 XD1 XS1 XS2/X S3
1 Design Increase Increase Increase Increase Increase Increase Increase
working life of Class Class Class Class Class Class Class
100 years by 2 by 2 by 2 by 2 by 2 by 2 by 2
2 Strength ≥ C30/ ≥ C30/ ≥ C35/ ≥ C40/ ≥ C40/ ≥ C40/ ≥ C45/
class according 37 [1] 37 [1] 45 [2] 50 [3] 50 [3] 50 [3] 55 [4]
to EN 1992-1 -1 : reduce reduce reduce reduce reduce reduce reduce
2004 Class Class Class Class Class Class Class
by 1 by 1 by 1 by 1 by 1 by 1 by 1
3 Member with reduce reduce reduce reduce reduce reduce reduce
slab geometry Class Class Class Class Class Class class
(position of by 1 by 1 by 1 by 1 by 1 by 1 by 1
reinforcement
not affected by
construction
process)
4 Special quality reduce reduce reduce reduce reduce reduce reduce
control of Class Class Class Class Class Class Class
the concrete by 1 by 1 by 1 by 1 by 1 by 1 by 1
production
ensured
Special Notes:
[1]
The strength class C30/3 7 based on Eurocode is equivalent to concrete with f′ c = 4,350 psi (30 MPa)
The strength
[2]
class C35/4 5 based on Eurocode is equivalent to concrete with f′ c = 5,100 psi (35 MPa)
The strength
[3]
class C40/5 0 based on Eurocode is equivalent to concrete with f′ c = 5,800 psi (40 MPa)
The strength
[4]
class C45/5 5 based on Eurocode is equivalent to concrete with f′ c = 6,550 psi (45 MPa)
Table Notes:
1
The strength class and water/c ement (w/c) ratio are considered to be related values. A special composition
(type of cement, w/c value, fine fillers) with the intent to produce low permeability may be considered.
2
The limit may be reduced by one strength class if air entrainment of more than 4% is applied.
• First, ACI 318-19 has an additional exposure category W, for the durability of con-
crete in contact with water but not exposed to freezing and thawing, chlorides, or
sulfates.
• Second, exposure category C applies to concrete exposed to all conditions that require
protection against corrosion of reinforcement regardless of the corrosion source. In
general, exposure category C in ACI 318-19 can be compared to XC and XD/XS
exposure classes in EN 1992-1-1:2004, which provides more insight into how speci-
fications are set differently with respect to corrosion sources.
• Third, ACI 318-19 considers only sulfate attack requirements category S exposure,
whereas EN 206-1:2013 and EN 1992-1-1:2004 cover a wide range of chemical
attacks induced by different types of ions and acids, not limited to sulfate.
newgenrtpdf
736
Table 12.6 Recommended characteristics of concrete.
Recommended characteristics of concrete by EN 206-1 :2013
Exposure
Item Category class Condition
1 Freezing and F0 Concrete not exposed to freezing-a nd-t hawing cycles
thawing (F)
F1 Concrete exposed to freezing-a nd-t hawing cycles with
limited exposure to water
F2 Concrete exposed to freezing-a nd-t hawing cycles with
frequent exposure to water
F3 Concrete exposed to freezing-and-thawing cycles with frequent
exposure to water and exposure to deicing chemicals
2 Sulfate (S) Water-s oluble sulfate (SO 42–) Dissolved sulfate (SO 42–)
in soil, percent (%) by mass [1] in water, ppm [2]
S0 SO 42– < 0.10 SO 42– < 150
S1 0.10 ≤ SO 42– < 0.20 150 ≤ SO 42– < 1,500 or
seawater
S2 0.20 ≤ SO 42– ≤ 2.00 1,500 ≤ SO 42– ≤ 10,000
S3 SO 42– > 2.00 SO 42– >10,000
3 In contact W0 Concrete dry in service
with water
(W) W1 Concrete in contact with water and low permeability is required
W2 Concrete in contact with water where low permeability is required
4 Corrosion C0 Concrete dry or protected from moisture
protection of
reinforcement C1 Concrete exposed to moisture but not to an external source of
(C) chlorides
C2 Concrete exposed to moisture and an external source
of chlorides from deicing chemicals, salt, brackish water,
seawater, or spray from these sources
Special Table Notes:
Percent sulfate by mass in soil shall be determined by ASTM C1580.
[1]
Concentration of dissolved sulfates in water, in ppm, shall be determined by ASTM D516 or ASTM D4130.
[2]
newgenrtpdf
Table 12.9 Requirements for concrete by exposure class.
738
Summary of requirements for concrete by exposure class by per ACI 318-1 9, Table 19.3.2.1
739
740 Handbook of Precast Segmental Tunnel Lining Systems
Another difference between the two codes is that ACI 318-19 does not set requirements for
minimum cement content. Also, in contrast to EN 1992-1-1:2004, the minimum amount
of concrete cover required by ACI 318-19 for corrosion protection of reinforcement is a
function of casting type. The two concrete casting types considered in ACI 318-19 for this
matter are cast-in-place and precast concrete manufactured under plant conditions. For pre-
cast elements such as tunnel segments, ACI 318-19 categorizes the minimum cover based
on exposure conditions into two categories of exposed or not exposed to weather or in con-
tact with the ground. Additional considerations for concrete cover over reinforcement in
Specified cover
Concrete Structural
Item exposure member Reinforcement details Metric Imperial
1 Exposed to Walls No.14 and No.18 bars; 38 mm 1-1 /2 ”
weather or tendons larger than 1-1 /2 ”
in contact (38 mm) diameter
with ground
No.11 bars and smaller, W31 19 mm 3/4 ”
or D31 wire and smaller;
tendons and strands 1-1 /2 ”
(38 mm) diameter and smaller
All other No.14 and No.18 bars; 51 mm 2”
tendons larger than 1-1 /2 ”
(38 mm) diameter
No.6 through No.11 bars, 38 mm 1-1 /2 ”
tendons and strands larger
than 5/8 ” (16 mm) diameter
through 1-1 /2 ” (38 mm)
diameter
No.5 bar, W31 or D31 32 mm 1-1 /4 ”
wire and smaller; tendons
and strands 5/8 ” (16 mm)
diameter or smaller
2 Not exposed Slab, joists No.14 and No.18 bars; 32 mm 1-1 /4 ”
to weather and walls tendons larger than 1-1 /2 ”
or in contact (38 mm) diameter
with ground
Tendons and strands 1-1 /2 ” 19 mm 3/4 ”
(38mm) diameter and smaller
No.11 bar, W31 and D31 wire 16 mm 5/8 ”
and smaller sizes
Beams, Primary reinforcement Greater of
columns, d b and 5/
pedestals 8” (16 mm)
and tension and need not
ties exceed 1-1 /2 ”
(38 mm)
Stirrups, ties, spirals and 9.5 mm 3/8 ”
hoops
Durability and service life of precast segmental linings 741
ACI 318-19, are the types of members categorized into two categories of walls or all other
(Table 12.10).
The last parameter affecting the concrete cover selection considered in ACI 318-19, is the
size of reinforcing bars. For the tunnel lining, the concrete and member categories should
be selected as “exposed to weather or in contact with ground” and “all other,” respectively.
Because reinforcing bars smaller than or equal to No.6 (metric bar size No.19) are commonly
used in precast tunnel segments, for corrosion exposure class C2 typically encountered in
tunnels, ACI 318-19 specifies a minimum cover of 1.25 to 1.50 inches (32 to 38 mm). This
is in contrast with EN 1992-1-1:2004, which requires different minimum concrete covers,
ranging from 0.40 to 1.8 inches (10 to 45 mm), based on the source of corrosion that can
be either carbonation, chloride ions other than seawater, or seawater exposure.
Following recommendations of ACI 318-19, when a concrete structure is subject to
freezing-and-thawing (exposure classes F1, F2 or F3), the concrete should be air entrained.
The minimum air content should be selected based on the nominal maximum aggregate
size (MAS) of concrete as presented in Table 12.11 (ACI 318-19, Table 19.3.3.1). However,
this code allows for a reduction of air content by 1% from the values in Table 12.11, when
specified compressive strength is higher than 5,000 psi (35 MPa). Precast concrete seg-
ments always have a higher strength than this value, and the nominal MAS is often between
0.50 inches (12.5 mm) and 0.75 inches (19 mm).
For precast concrete tunnel segments subject to freezing-and-thawing, an exposure class
F2 or F3 is commonly selected. Therefore, referring to Table 12.11, and considering the
MAS and 1% reduction allowance for concrete strength of 5,000 psi (35 MPa) or higher,
air content of 5 and 6% are recommended for concrete with MAS of 0.75 inches (19 mm)
and 0.50 inches (12.5 mm), respectively.
Consideration of a common exposure class example, such as when the concrete lining
is exposed to chloride-induced corrosion, can help provide insight into how disparate the
ACI and EN concrete codes are. For this purpose, requirements of exposure category C2 of
ACI 318-19 are compared with exposure class XS3/XD3 of EN 1992-1-1:2004. ACI code
requires a maximum water/cement ratio of 0.40 and a minimum compressive strength of
5,000 psi (35 MPa) whereas EN code requires a maximum water/cement ratio of 0.45, a
minimum compressive strength of 5,000 psi (35 MPa), and a minimum cement content of
742 Handbook of Precast Segmental Tunnel Lining Systems
575 lbs/yd3 (340 kg/m3). Minimum concrete cover of 1.5 inches (38 mm) specified by ACI
318-19 for reinforcing bar No.6 (metric bar size No.19) can be compared to the 1.8 inches
(45 mm) EN 1992-1-1:2004 requirement. This example shows that, despite the differences
between the two methods, the concrete requirements set forth by both codes for the same
exposure condition are similar and will most likely result in similar, if not identical, concrete
specifications (Bakhshi and Nasri, 2018b).
Exposure
Item class Definition and condition
1 C-X L Structurally reinforced concrete exposed to chlorides or other severe
environments with or without freezing and thawing conditions, with
higher durability performance expectations than the C-1 classes.
2 C-1 Structurally reinforced concrete exposed to chlorides with or without
freezing and thawing conditions. Examples:
• Bridge decks, parking decks and ramps
• Portions of structures exposed to seawater located within the tidal
and splash zones
• Concrete exposed to seawater spray, and saltwater pools
For seawater or seawater-s pray exposures the requirements for S-3
exposure also have to be met.
3 C-2 Non-s tructurally reinforced (i.e. plain) concrete exposed to chlorides
and freezing and thawing. Examples:
• Garage floors, porches and step,
• Pavements, sidewalks, curbs, and gutters
4 C-3 Continuously submerged concrete exposed to chlorides, but not to
freezing and thawing. Examples:
• Underwater portions of structures exposed to seawater.
For seawater or seawater-s pray exposures the requirements for S-3
exposure also have to be met
5 C-4 Non-s tructurally reinforced concrete exposed to chlorides, but not to
freezing and thawing. Examples:
• Underground parking slabs on-g rade
6 F-1 Concrete exposed to freezing and thawing in a saturated condition, but
not to chlorides. Examples:
• Pool decks, patios and tennis courts
• Freshwater pools and freshwater control structures
Durability and service life of precast segmental linings 743
Exposure
Item class Definition and condition
7 F-2 Concrete in an unsaturated condition exposed to freezing and thawing,
but not to chlorides. Examples:
• Exterior walls and columns
8 N Concrete that when in service is neither exposed to chlorides nor
to freezing and thawing nor to sulfates, either in a wet or dry
environment. Examples:
• Footings and interior slabs
• Walls and columns
9 N-C F Interior concrete floors with a steel-t rowel finish that are not exposed
to chlorides, nor to sulfates either in a wet or dry environment.
Examples:
• Interior floors, surface covered applications (carpet, vinyl tile)
• Surface exposed applications (with or without floor hardener)
• Ice-h ockey rinks and freezer warehouse floors
10 A-X L Structurally reinforced concrete exposed to:
• Severe manure and/o r silage gases, with or without freeze-– t haw
exposure
• Concrete exposed to the vapor above municipal sewage or industrial
effluent, where hydrogen sulfide gas might be generated, with higher
durability performance expectations than A-1 class
11 A-1 Structurally reinforced concrete exposed to severe manure and/
or silage gases, with or without freeze-t haw exposure. Concrete
exposed to the vapor above municipal sewage or industrial effluent,
where hydrogen sulfide gas might be generated. Examples:
• Reinforced beams, slabs, and columns over manure pits
• Silos, canals, and pig slats; and access holes, enclosed chambers
• Pipes that are partially filled with effluents
12 A-2 Structurally reinforced concrete exposed to moderate to severe
manure and/o r silage gases and liquids, with or without freeze-t haw
exposure. Examples:
• Reinforced walls in exterior manure tanks
• Silos and feed bunkers, and exterior slabs
13 A-3 Structurally reinforced concrete exposed to moderate to severe
manure and/o r silage gases and liquids, with or without freeze-
thaw exposure in a continuously submerged condition. Concrete
continuously submerged in municipal or industrial effluents.
Examples:
• Interior gutter walls, beams, slabs, and columns
• Sewage pipes that are continuously full (e.g., force mains)
• Submerged portions of sewage treatment structures
14 A-4 Non-s tructurally reinforced concrete exposed to moderate manure
and/o r silage gases and liquids, without freeze-t haw exposure.
Examples:
• Interior slabs on grade
15 S-1 Concrete subjected to very severe sulfate exposures (Tables 2 and 3).
(Continued)
744 Handbook of Precast Segmental Tunnel Lining Systems
Exposure
Item class Definition and condition
16 S-2 Concrete subjected to severe sulfate exposure (Tables 2 and 3).
17 S-3 Concrete subjected to moderate sulfate exposure and to seawater or
seawater spray
(Tables 2 and 3).
18 R-1 Residential concrete for footings for:
• Walls and columns
• Fireplaces and chimneys
19 R-2 Residential concrete for:
• Foundation walls
• Grade beams and piers, etc.
20 R-3 Residential concrete for interior slabs on ground not exposed to
freezing and thawing or de-icing salts.
Source: CSA A23.1:19, Table 1.
Table Notes:
1
“C” Classes pertain to chloride exposure
2
“F” Classes pertain to freezing and thawing exposure without chlorides
3
“N” Class is exposed to neither chlorides not freezing and thawing
4
All classes of concrete exposed to sulphates shall comply with the minimum requirements of Class S, as
noted in Tables 2 and 3 (of CSA A23.1:19). In particular, exposure classes A1 to A-4 and A-X L in municipal
sewage elements could be subjected to sulphate exposure.
5
No hydraulic cement concrete will be entirely resistant in severe acid exposures. The resistance of
hydraulic cement concrete in such exposures is largely dependent on its resistance to penetration of fluids.
6
Decision of exposure class should be based upon the service conditions of the structure or structural
element, and not upon the condition during construction.
The CSA code takes an approach towards concrete exposure classes that is relatively
similar to that of ACI 318-19. However, one of the differences between the two codes is
the exposure class W, which is defined in ACI 318-19 for concrete elements in contact with
water but does not exist in the Canadian code. Also, exposure class N in CSA A23.1-19,
which does not exist in ACI 318-19, is basically equivalent to exposure classes C0, F0 and S0
combined. Another difference between the two codes is the two additional exposure classes
in CSA code: exposure class A and exposure class R. exposure class A in CSA A23.1-19 is
related to concrete exposure to the manure and silage gases or liquids, and the vapor above
the municipal sewage or the industrial effluent. Examples of such structures are tanks, silos,
canals and pipes, which are considered environmental structures.
ACI set durability requirements for such structures not in ACI 318-19, but in another
code specific to environmental structures: ACI 350-06. Exposure class A in CSA can be
applied to sewage and waste-water tunnels. One last major difference between ACI and
CSA codes regarding exposure classification, is the exposure class R in CSA code which
does not exist in ACI 318-19 and is specifically defined for residential concrete. This specific
exposure class is not relevant to tunnels, and therefore, will not be discussed in this chapter.
The exposure category C in CSA A23.1-19 corresponds to all reinforced concrete exposed
to chloride. Therefore, this CSA category is equivalent to category C in ACI 318-19 and can
be compared to XC, XD/XS exposure classes in EN 1992-1-1 (2004) and EN 206-1 (2013).
Because tunnel linings are usually designed for a service life of more than 100 years, the rec-
ommended exposure class for chloride-induced corrosion based on CSA code is C-XL. This
newgenrtpdf
Table 12.13 Requirements for exposure classes by the Canadian Standards Association.
Definitions of C, F, N, A and S exposure classes per the Canadian Standards Association
(Continued)
745
newgenrtpdf
Table 12.13 (Continued)
746
Air content category Curing type
exposure class is defined for structures with higher durability performance expectations
than the C-1 class, which is often defined for a service life of less than 100 years.
The recommended exposure class for sewage and waste-water tunnels is A-XL, which
is applied to structures with higher durability expectations than exposure class A-1, with
usual service life expectancy of less than 100 years. Exposure category F deals with con-
crete elements exposed to freezing and thawing but not subject to chloride penetration. This
category corresponds to ACI 318-19 exposure class F but is less specific. Once tunnels are
subject to freezing-and-thawing, near portal areas for example, exposure class F-1 should
be selected for specifying concrete requirements. Similar to ACI 318-19, CSA A23.1-19 only
considers sulfate attack category S, while EN 1992-1-1 (2004) and EN 206-1 (2013) cover a
wide range of chemical attacks to different types of ions and acids other than sulfate. When
tunnels are subject to sulfate attack, an exposure class between S1 and S3 is selected based
on the amount of water-soluble sulfate found in soil and groundwater (Table 12.14).
Much like ACI 318-19 and in contrast with Eurocode, CSA code does not have any
requirements for the minimum cement content for different exposure classes. As shown in
Table 12.13, the main concrete requirements of CSA are the maximum water-to-cementing
materials ratio (water/cement ratio), the minimum compressive strength, the minimum air
content (Table 12.15), the curing type, and the maximum chloride ion penetrability. Note
that curing type requirements of CSA A23.1-19 do not apply to precast elements and are
only applicable to cast-in-place concrete.
When the tunnel lining is exposed to chloride penetration or deterioration may occur due
to sewage exposure, concrete requirements of Table 12.13 for exposure class C-XL or A-XL
should be met. These include a maximum water/cement ratio of 0.40, a minimum compres-
sive strength of 7,250 psi (50 MPa) within 56 days, a minimum air content according to
Table 12.15 (CSA A23.1-19, Table 4), and a maximum chloride ion penetration of 1,000
coulombs after 91 days of curing. Because maximum aggregate size (MAS) for precast seg-
ments is usually between 0.55 to 0.78 inches (14 to 20 mm), the required air content for
exposure class C-XL or A-XL based on CSA code is 5 to 8%.
For the tunnel lining subject to freezing and thawing, concrete requirements for exposure
class F-1 is water/cement ratio of less than 0.50, minimum compressive strength of 4,350
psi (30 MPa) at 28 days, and minimum air content of 5 to 8% (see Table 12.13 and 12.15).
Concrete requirements of CSA A23.1-19 for structures exposed to sulfate attack (exposure
class S) are presented in Tables 12.13 and 12.14, which may vary according to the amount
of the soluble sulfate that the tunnel lining is exposed to.
For durability against chloride penetration, similar to ACI 318-19 and EN 1992-1-
1:2004, the minimum concrete cover required by CSA is a function of exposure conditions.
As shown in Table 12.16 (CSA A23.1-19, Tables 17), CSA A23.1-19 categorizes the min
imum cover primarily based on exposure conditions and element types. Additionally, CSA
code limits the ratios between the concrete cover and the nominal bar diameter, as well as
the concrete cover and nominal MAS. Nonetheless, in precast tunnel segments with MAS
and rebar diameter of less than 0.78 inches (20 mm), CSA limitations of the minimum cover
related to these parameters do not govern.
Because tunnel linings are always cast against and permanently exposed to earth, CSA
requires a minimum cover of 2.95 inches (75 mm) for all different exposure conditions.
However, CSA A23.4-16 (2021), which provides specific standards for precast concrete in
Canada, allows a reduction of concrete cover from the values set forth by CSA A23.1-19 for
cast-in-place concrete. Greater dimensional control of formed concrete, tighter tolerances
on placement of reinforcing, and better quality of concrete in plant-controlled conditions
newgenrtpdf
748
Table 12.14 Additional requirements for concrete subject to sulphate attack.
Definition of additional requirements for concrete subject to sulphate attack per Canadian Standards Association (CSA
Performance
requirements 6
Water soluble
Water-s oluble sulfate (SO 4) Sulfate (SO 4) Maximum expansion
sulfate (SO 4) in in recycled in groundwater Cementing when tested using CSA
Exposure Degree of soil sample 2 aggregate sample samples 3 materials A3004- C 8 (%)
Item class exposure (%) (%) (mg/l ) to be used 4 6 months 12 months 7
1 S-1 Very severe > 2.0 > 2.0 > 10,000 HS 5, HSb, HSLb or 0.05 0.1
Hse
2 S-2 Severe 0.20 to 2.0 0.60 to 2.0 1,500 to 10,000 HS 5, HSb, HSLb or 0.05 0.1
Hse
3 S-3 Moderate 0.10 to 0.20 0.20 to 0.60 150 to 1,500 MS, MSb, MSe, MSLb, 0.1
(including seawater LH, LHb, HS 5, HSb,
exposure) 1 HSLb or Hse
Table Notes:
1
For seawater exposure, also see CSA A23.1:19, clause 4.1.1.5.
2
In accordance with CSA A23.2-3 B.
3
In accordance with CSA A23.2-2 B.
4
Where combination of supplementary cementitious materials and Portland, Portland-limestone, or blended hydraulic cements are to be used in the concrete
mix design instead of the cementitious materials listed, and provided they meet the performance requirements demonstrating equivalent performance against
sulphate exposure, they shall be designated as MS equivalent (MSe) of HS equivalent (HSe) in the relevant sulphate exposures (see CSA 23.1 clause 4.1.1.6.2,
4.2.1.1, 4.2.1.3 and 4.2.1.4.
5
Type HS cement shall not be used in reinforced concrete exposed to bot chlorides and sulphates, including seawater. See CSA A23.1, clause 4.1.1.6.3.
6
For demonstrating equivalent performance, use the testing frequency in Table 1 of CSA A3004-A 1 and see the applicable notes to Table A3 in CSA A3001 with
regard to re-e stablishing compliance of the composition of the cementitious materials used to establish compliance charges.
7
If the expansion is greater than 0.05% at 6 months but less than 0.10% at one year, the cementitious materials combination under test shall be considered to
have passed.
Special Notes:
1
Limestone fillers shall not be used in concrete for any exposure class S listed in CSA A3001, Tables 1 to 3. Portland-limestone cement shall not be used as
the sole cementitious materials in concrete for any exposure class S in CSA A3001, Table 1 to 3. However, blended hydraulic cements, or combinations of
Portland-limestone cement and the minimum levels of supplementary cementitious materials listed in CSA A3001, Table 9, and also meeting the test require-
ments in CSA A3001, Table 5 may be used in any exposure class S listed in listed in Tables 1 to 3.
Durability and service life of precast segmental linings 749
are among the reasons provided by CSA A23.4-16 for justifying this reduction. Concrete
cover limitations by CSA A23.4-16 for precast elements as a function of exposure condition
is shown in Table 12.17 (CSA A23.4-16, Table 1). Piles are the closest element type in this
table to the tunnel lining and, therefore, for exposure classes C-XL or F-1/F-2, designing a
minimum cover of 1.57 inches (40 mm) is adequate in this example.
x
C ( x, t ) = C0 + (Cs − C0 ) 1 − (12.1)
2 Dt
newgenrtpdf
Table 12.17 Cover to reinforcement, tendon sheaths and ducts.
Recommendations for minimum cover to reinforcement, tendon sheaths and ducts per the Canadian Standards Association (CSA
A23.4-1 6, Table 1) (unit is in mm; multiply by 0.039 to convert to inches)
Exposure
Chlorides, sulphates, manure,
sewage and industrial effluents
Protection systemsⴕ
Not Earth or Unprotected
Item Description exposedⱡ weather concrete A B, C, D, E F, G, H, J, K
1 Exposure condition (see N F-1 , F-2 C-1 , C-3 , A-1 , C-X L C-1 , C-3 , A- C-1 , C-3 , A-1 , C-1 , C-3 ,
Table 2 of CSA A23.1) A-2 , A-3 , S-1 , 1, A-2 , A-3 , A-2 , A-3 , S-1 , A-1 , A-2 ,
S-2 , S-3 S-1 , S-2 , S-3 S-2 , S-3 A-3 , S-1 ,
S-2 , S-3
(Continued)
751
newgenrtpdf
Table 12.17 (Continued)
752
Table Notes:
*
The cover for precast concrete is reduced from the cover used in cast-in-p lace concrete because of greater dimensional control of formed concrete, tighter
where
C ( x, t ) is the chloride concentration in concrete at depth x and time t ;
C0 is initial chloride concentration in concrete;
Cs is the chloride concentration at the surface of concrete;
erf is the error function; and
D is the chloride diffusion coefficient.
The corrosion initiation time, Ti, happens when the chloride concentration at the reinforce-
ment cover depth of d reaches a critical value Ccr . The initial chloride concentration in
concrete, C0 , can be assumed zero ( C0 = 0 ). When solving the above equation for the cor-
rosion initiation time, Ti, C ( x, t ) is replaced by Ccr ( C ( x, t ) = Ccr ) while t is replaced by
Ti ( t = Ti ), and x is replaced by d or x = d . The solution to Equation (12.1) is, therefore,
d2 2
Ti = A (12.2)
4D
where
1
A= (12.3)
Ccr
1 − C
s
Note that is the inverse of the error function. Following experimental observations, most
service life prediction models predict the chloride diffusion coefficient in concrete will
decrease with time. A common equation in use is presented in Equation (12.4).
754 Handbook of Precast Segmental Tunnel Lining Systems
a
t
D = D0 0 for t ≤ t a (12.4)
t
where
D is the chloride diffusion coefficient at age t ;
D0 is the chloride diffusion coefficient measured at reference age t0 ; and
a is an exponent that indicates the effect of aging.
• First, it is very difficult to determine parameters Cs and Ccr , and their ratio may affect
the computation of Ti by a factor of up to 4 (Torrent, 2017).
• Second, there are uncertainties with regard to validity of the power decay function
[Equation (12.4)] and the proposed values for age exponent a (Gulikers, 2006, 2011).
• Third, the variation of values considered for exponent a can lead to variation of Ti by
several orders of magnitude (Torrent, 2013, 2017).
While Life-365 (2012) limits t a to 25 years, DuraCrete (Engelund et al., 2000) and fib
Bulletin No.34 (2006) models do not set limitations for this parameter, which seems
unreasonable. Limiting the t a parameter to a year or less can be justified based on obser-
vations ensuring that after an appropriate curing period, there will be no substantial
decrease in chloride permeability under jobsite conditions (Di Pace et al., 2019). At the
time of service life design, determining parameter a is practically impossible for design-
ers due to the long-term nature of this exponent. Designer’s reliance on the service life
models, especially on proposed values for parameters a and t a , which may not match
with the jobsite conditions can result in incorrect computation of service life parameter
( Ti ) and is problematic.
To alleviate this problem, a simple yet robust method has been proposed by Torrent
(2015). Although this method is based on Equations (12.2) to (12.4), unclear parameters
are taken-out to remove uncertainties. This simple method can be used for preliminary
service-life design, and designers would be able to check whether a sophisticated calculation
can provide a reasonable prediction. Solutions of this simplified model are presented as a
chart in Figure 12.27 for the exposure class XD3/XS3 per EN 1992-1-1:2004. As discussed
in section 12.10.1, this exposure class (XD3/XS3) is applicable to the case of tunnel linings
subject to chloride penetration and can be directly used for preliminary service-life design
of precast tunnel segments.
While using these models for predicting service life is reasonable for structures subject
to severe environments, for less severe environments, these models may result in too conser-
vative predictions (Di Pace et al., 2019). Particularly in the case of carbonation-induced
Durability and service life of precast segmental linings 755
corrosion, it is necessary to take propagation time into account. For example, in high-
performance concrete with concrete covers of 3.0 to 3.5 inches (75 to 90 mm), predicted
propagation time could be more than 20 years before any localized cracking or spalling, as
the serviceability limit state (SLS) appears (Di Pace et al., 2019).
During the design phase, in addition to guidelines on mixture characteristics, a com-
prehensive experimental program should be carried-out on concrete mixtures to include
chloride permeability tests. One of the most common tests is the rapid chloride perme-
ability test (RCPT) per ASTM C1202 (2019), which measures the electrical charge, Q
(in coulombs), passed through the concrete in 6 hours. Equation (12.5) proposed by Olek
et al. (2002) can be used to estimate the chloride diffusivity from the electrical charge, Q,
determined by RCPT.
Experimental results for precast concrete tunnel segments, when tested according to ASTM
C1202 (2019), usually range between 300 to 700 coulombs. Using Equation (12.5), this
translates into a diffusion coefficient of 1 to 1.8 ×10−12 m2 /s . An example following the
simplified service life prediction model of Figure 12.27 considers the design service life of
a tunnel exposed to chloride-induced corrosion at 100 years; the designed concrete cover
over reinforcement is in the range of 1.25 to 1.8 inches (32 to 45 mm). This result is in
agreement with prescriptive-based code recommendations of ACI 318-19, CSA A23.1-19
and EN 1992-1-1:2004, which require a minimum cover of 1.5 inches (38 mm), 1.6 inches
(40 mm) and 1.8 inches (45 mm) for a similar exposure class, respectively.
756 Handbook of Precast Segmental Tunnel Lining Systems
DuraCrete Service life model (Engelund et al., 2000) was used in Han et al. (2003) study
to evaluate the required service life of 100 years. For service life design when concrete is
exposed to carbonation, a deterioration model based on Fick's first law of diffusion was
adopted, which is presented in Equation (12.6).
a
2.ke .kc .kt .Cs t
x (t ) = . t. 0 (12.6)
RCarb t
where
x (t ) is the carbonation depth at the exposure time t ;
RCarb is the effective carbonation resistance of concrete;
Cs is concentration of the passivator at the concrete surface;
ke is a constant parameter, which considers the effect of environment on RCarb (e.g. real-
istic moisture history at the concrete surface during use);
kc is a constant parameter, which considers the effect of execution on RCarb (e.g. influ-
ence of curing);
kt is a constant parameter which considers the effect of test method on RCarb ;
t0 is the reference period (e.g. 1 year); and
a is a constant parameter which considers the effect of meso climatic conditions (e.g.
orientation and placing of structure).
Durability and service life of precast segmental linings 757
For chloride induced corrosion, Equations (12.7) and (12.8) based on Fick’s second law
of diffusion were adopted.
a
t
x (t ) = 2.k. DRCM ,0 .ke .kc .kt .t. 0 (12.7)
t
C
k = 1 − cr (12.8)
Cs
where
x (t ) is the depth of critical chloride concentration at the exposure time of t ;
DRCM,0 is the chloride diffusion coefficient at defined compaction, curing and environ-
mental conditions, measured at time t0 ;
Ccr is the critical chloride concentration;
Cs is the surface chloride concentration;
ke is a constant parameter which considers the effect of environment on DRCM ,0 ;
kc is a constant parameter which considers the effect of execution on DRCM,0 (e.g. influ-
ence of curing);
kt is a constant parameter which considers the effect of test method on DRCM ,0 ;
t0 is the reference period (e.g. 28 days); and
a is the age exponent, which takes into account the effect of age and the environmental
condition on the measured material property.
Equations (12.7) to (12.8) are basically the same as Equations (12.2) to (12.4), only
with a different organization when D0 in Equations (12.2) and (12.4) are replaced by
DRCM ,0 .ke .kc .kt . This is because the DuraCrete Service life model (Engelund et al., 2000) takes
into account the effect of the differing initial chloride diffusion coefficient between jobsite
and the pre-construction laboratory testing conditions by proposing ke , kc , and kt as mul-
tipliers to D0 .
In this project, the corrosion initiation time was conservatively considered as a service-
ability limit state (SLS) because of the difficulty and the cost impact of repair and mainten-
ance during the service life of the tunnel. Project technical requirements defined a reliability
index β of 1.8 for the probabilistic calculations for tunnel structures with a design service
life of 100 years. As presented in Equation (12.9), reliability-based calculations were carried
out according to the DuraCrete method (Engelund et al., 2000).
g x (t ) = d − x (t ) = 0 (12.9)
where
g x (t ) is the limit state function for carbonation or chloride diffusion;
d is the designed concrete cover; and
x (t ) is the carbonation depth or chloride penetration depth calculated by Equation
(12.6) or (12.7), whichever applies.
758 Handbook of Precast Segmental Tunnel Lining Systems
Considering Ti as the intended design service life, the reliability calculation can be
expressed by Equation (12.10).
where
Pf (Ti ) is the probability of the critical carbonation/chloride penetration depth exceed-
ing the designed concrete cover over reinforcement within the intended design service
life Ti ;
Ptargert is the accepted maximum value of the failure probability;
Φ is the standard normal distribution function (with mean value of 0 and standard devi-
ation of 1); and
β is the reliability index (e.g. 1.80).
Values
Item Parameters Unit of measure Mean Standard deviation Distribution
1 xc mm 35 5 Lognormal
2 D RCM,0 10 –12 m²/s 3.4 1.1 Normal
3 C cr wt.–% / binder 1.0 0.2 Normal
4 N – 0.8 0.07 Beta a = 0; b = 1
5 Kt – 1.0 – Deterministic
6 Ke – 2.704 1.292 Gamma
7 kc – 1.8 0.4 Beta a = 1; b = 4
8 Cs wt.–% / binder 2.7 0.11 Normal
9 t0 year 0.0767 Deterministic
Source: Han et al., 2003.
Figure 12.28 Reliability index for durability of Green Heart Tunnel segment joints.
Note: Reliability index ( ² ) for durability of Green Heart Tunnel segment joints calculated by
Han et al. (2003) as a function of chloride exposure time ( t ) when designed concrete cover is
1.38 inches (35 mm).
be classified according to the defect class outlined in Table 12.20, which provides proce
dures for repairing segment defects, including descriptions of damage types and extents, in
accordance with ACI 224R-01 and ACI 503.4-92(03). Note that for certain defect types,
the repair procedure must be provided by the segment manufacturer, contractor, or both,
and reviewed by the designer before approval and implementation. Segments identified for
repair but listed as “segment rejection” in Table 12.20 should be immediately discarded and
not used for installing segmental rings.
For post-erection repairs, it is important to address all oil stains and unsightly segments
by cleaning and repairing them before erection. Any stained segments should be cleaned
either during or after erection. Cracks in the segments and water infiltration through gaskets
after erection must be repaired using materials and procedures that have been examined
and approved by the designer. Table 12.21 presents procedures for repairing segment and
joint defects, providing descriptions of the type and extent of damage, as well as repair
procedures for segment defects that occur during and after installation by the tunnel boring
machine.
newgenrtpdf
Table 12.20 Materials and procedures for repairing segment defects
761
762 Handbook of Precast Segmental Tunnel Lining Systems
1 Repair procedure 1
a. Materials
i. Cement type MS
ii. Silica sand
iii. Mix one part cement with 2.5 parts sand, using a water/cement ratio of 0.4.
b. Procedure
i. Clean and wire brush off all dirt and dust from areas to be filled. Dampen repair
area with water.
ii. Measure and mix cement and sand with water in accordance with the instruc-
tions. Do not add additional water to the mixture after it has already been mixed
to adjust its consistency, which can negatively affect the strength and quality of
the repair.
iii. Fill the repair area, and sack rub the finished surface.
2 Repair procedure 2
a. To be used in areas less than 1.6 inches (40 mm) long and 0.6 inches (15 mm) deep.
b. Material
i. SIKADUR 31 epoxy mortar or equivalent mortar is acceptable.
ii. Mix in a one-to-one ratio by volume by adding oven-dried silica sand until a uni-
form and consistent mix is achieved. Do not mix a quantity larger than can be
used within 30 minutes.
c. Procedure
i. Repair area must be dry. Remove any dust, laitance, grease, oils, or loose materi-
als from the area to be repaired and wire brushed.
ii. Place mixed materials into the void, working the material by trowel or spatula to
ensure bond. Strike off level to existing concrete.
iii. Cure the epoxy mortar at a minimum temperature of 5 degrees Celsius.
iv. Ensure accurate profile by removing any excess mortar by grinding.
3 Repair procedure 3
a. To be used in areas more than 1.6 inches (40 mm) long and 0.6 inches (15 mm) deep.
b. Material
i. Master Builders EMACO S88-CA or equivalent.
ii. Mix at the rate of 55 lb (25 kg) Bag EMACO with 0.7 gallons (2.7 liters) to 1
gallons (3.8 liters) of water (10.5–15% by weight).
c. Procedure
i. Saw-cut all edges of repair to a depth of 0.6 inches (15 mm) with a circular saw.
ii. Break back to sound concrete and remove surplus material by low impact
method. Clean and wire brush off loose particles, dirt and dust from areas to
be filled. Soak burlap or sponge over the repair area to dampen for a period of
2 hours.
iii. Measure and mix the patching compound with water in accordance with the
manufacturer’s instructions. Do not retemper mixture with water.
iv. Fill the repair area, finish open edges with a steel trowel and use temporary form-
work when necessary, ensuring that repair material is thoroughly compacted.
Strike off level to existing concrete.
v. Place a damp cloth over the repair area and leave it damp for a period of 7 days
until the repair material has sufficiently hardened.
Durability and service life of precast segmental linings 763
Table 12.21 Materials and procedures for repairing segment defects after installation by the
tunnel boring machine
Class of
damage/ defect Description Location Extent Remedy
Class G2 All types of All locations Crack opening Use Sikadur 55 SLV or
structural cracks in between equivalent. Repair procedure
damage dry or damp 0.012 inches to be submitted for designer’s
conditions (0.30 mm) and approval
0.12 inches
Class G3 All types of (3 mm) Use Sika Injection-2 16 or
structural cracks in wet equivalent. Repair procedure
damage conditions to be submitted for designer’s
approval
Class G4 All types of Opening > Repair procedure to be
structural cracks 0.12 inches submitted for designer’s
damage (3 mm) approval
Class J Gaskets Water Use Sika Inject-2 15 or
water infiltration equivalent. Repair procedure
infiltration through according to section 10.7 of
gaskets ACI 533.5R-2 0
BIBLIOGRAPHY
For preparation of this chapter, the following references were used, which are categorized into two
categories of authority published documents and authoreddocuments.
BRITISH TUNNELING SOCIETY (BTS) AND THE INSTITUTION OF CIVIL ENGINEERS (ICE)
AFTES:2005, Recommendations for the Design, Production, and Installation of Segmental Ring
Recommendation for the Design, Sizing and Construction of Precast Concrete Segments
Installed at the Rear of a Tunnel Boring Machine (TBM)s.
DAUB:2013, Lining Segment Design: Recommendations for the Design, Production, and Installation
of Segmental Rings.
LTA 2010, Civil Design Criteria for Road and Rail Transit Systems.
AUTHORED DOCUMENTS
Abbas, S., 2014, Structural and Durability Performance of Precast Segmental Tunnel Linings, PhD
dissertation, University of Western Ontario, London, Ontario, Canada.
Bakhshi, M., and Nasri, V., 2018a, “Tunnel Segmental Lining Durability,” Proceedings of TT2018-
TAC/NASTT-NW Tunnelling and Trenchless Conference, Edmonton, Alberta, Canada.
Bakhshi, M., and Nasri, V., 2018b, “Durability Design of Segmental Linings for Intended Service
Life of Tunnels,” Proceedings of Sixth International Conference on Durability of Concrete
Structures, Leeds, United Kingdom.
Bertolini, L., Carsana, M., and Pedeferri, P., 2007, “Corrosion Behaviour of Steel in Concrete in the
Presence of Stray Current,” Corrosion Science, Volume 49, No. 3, pp. 1056–1068. doi: 10.1016/
j.corsci.2006.05.048.
Brenna, M., Dolara, A., Leva, S., and Zaninelli, D., 2010, “Effects of the DC Stray Currents on
Subway Tunnel Structures Evaluated by FEM Analysis,” Power and Energy Society General
Meeting, 2010 IEEE, Minneapolis, MN, pp. 1–7.
Di Pace, G., Morales, L.E., Torrent, R., and Bueno, V., 2019, “From Cradle to Maturity,” Concrete
International, Volume 41, No.4, pp. 47–54.
Dolara, A., Foiadelli, F., and Leva, S., 2012, “Stray Current Effects Mitigation in Subway Tunnels,”
IEEE Transactions on Power Delivery, Volume 27, No.4, pp. 2304– 2311. doi: 10.1109/
TPWRD.2012.2203829.
Edvardsen, C., Müller, S., Nell, W., and Eberli, M., 2017, “Steel Fibre Reinforced Concrete for Tunnel
Lining Segments—Design, Durability Aspects and Case Studies on Contemporary Projects,”
Proceedings of STUVA Conference 2017 (49 Forschung +Praxis: STUVA- Tagung 2017),
Stuttgart, Germany, pp. 184–189.
Engelund, S., Edvardsen, C., and Mohr, L., 2000, General Guidelines for Durability Design and
Redesign: DuraCrete— Probabilistic Performance Based Durability Design of Concrete
Structures, Contract BRPR- CT95- 0132, Project BE95- 1347, Volume 15, Lyngby,
Denmark, 109 p.
Graeff, A., Pilakoutas, K., Lynsdale, C., and Neocleous, K., 2009, “Corrosion Durability of Recycled
Steel Fibre Reinforced Concrete,” Article No.7, Intersections/Intersectii, Volume 6, No.4,
pp. 77–89.
Gulikers, J., 2006, “Considerations on the Reliability of Service Life Predictions Using a Probabilistic
Approach,” Journal of Physics IV, France, Volume 136, pp. 233–241.
Gulikers, J., 2011, “Practical Implications of Performance Specifications for Durability Design of
Reinforced Concrete Structures,” Proceedings of the fib Workshop on Performance- Based
Specifications for Concrete, F. Dehn and H. Beushausen, editors, June 2011, Leipzig, Germany,
pp. 341–350, 2011.
Han, N., Taibi, Y., and Kooiman, A., 2003, “Performance and Reliability Based Service Life Design
for the Green Hart Tunnel,” Proceedings of the World Tunnelling Congress 2003, Amesterdam,
Netherlands, pp. 12–17.
Helsing, E., and Mueller, U., 2013, Beständighet av cement och betong i tunnelmiljö (Resistance
to Cement and Concrete in Tunnel Environment), Seminarium Vatten i anläggningsbyggande
(Seminar on Water in Construction), Göteborg, Sweden.
ITA Working Group on Maintenance and Repair of Underground Structures, 1991, “Report on the
Damaging Effects of Water on Tunnels During their Working Life,” Tunnelling and Underground
Space Technology, Volume 6, No.1, pp. 11–76. doi: 10.1016/0886-7798(91)90005-O.
766 Handbook of Precast Segmental Tunnel Lining Systems
Kemp, R., 2007, Traction Energy Metrics, Rail Safety and Standards Board, Lancaster University,
United Kingdom.
Li, Q., Yu, H., Ma, H., Chen, S.; and Liu, S., 2014, “Test on Durability of Shield Tunnel Concrete
Segment under Coupling Multi-Factors,” Open Civil Engineering Journal, Volume 8, No.1,
pp. 451–457. doi: 10.2174/1874149501408010451.
Li, Q., Li, K., Zhou, X., Zhang, Q., and Fan, Z., 2015, “Model-Based Durability Design of Concrete
Structures in Hong Kong-Zhuhai-Macau Sea Link Project,” Structural Safety, Volume 53,
March 2015, pp. 1–12.
Life-365 Service Life Prediction ModelTM and Computer Program for Predicting the Service Life and
Life-Cycle Cost of Reinforced Concrete Exposed to Chlorides, 2012, Life-365 Consortium II,
80 p. Washington DC.
Nilsson, L.O., 2012, “Transport Processes in the Microstructure of Concrete and Their Relevance
for Durability,” Second International Conference on Microstructural-Related Durability of
Cementitious Composites, Amsterdam, The Netherlands, 8 p.
Olek, J., Lu, A., Feng, X., and Magee, B. (2002). “Performance-related specifications for concrete
bridge superstructures.” Vol. 2, High-Performance Concrete, Rep. No. FHWA/INDOT/JTRP-
2001/08-II, Joint Transportation Research program, Purdue Univ., West Lafayette, Ind.
Rashidi, S., and Nasri, V., 2012, Mitigation of the Corrosion Risk for Large Concrete Sewer Tunnels,
ITA-AITES World Tunnel Congress (WTC) 2012, Bangkok, Thailand.
RCP, 1997, “STRUREL—A Structural Reliability Analysis Program System,” RCP Consulting
GmbH, München.
Sigl, O., Raupach, M., and Rieker, L., 2000, “Durability Design of Concrete Tunnel Lining Segments,”
25th Conference on Our World in Concrete and Structures, 23–24 August 2000, Singapore.
Solgaard, A.O.S., Carsana, M., Geiker, M. R., Küter, A., and Bertolini, L., 2013, “Experimental
Observations of Stray Current Effects on Steel Fibres Embedded in Mortar,” Corrosion Science,
Volume 74, pp. 1–12. doi: 10.1016/j.corsci.2013.03.014.
Tang, K., 2017, “Stray Current Induced Corrosion of Steel Fibre Reinforced Concrete,” Cement and
Concrete Research, Volume 100, pp. 445–456. doi: 10.1016/j.cemconres.2017.08.004.
Torrent, R., 2013, “Service Life Prediction: Theorecrete, Labcrete and Realcrete Approaches,” SCTM3
Conference, Kyoto, Japan.
Torrent, R., 2017, “The Reference Approach to Service Life Design,” High Tech Concrete: Where
Technology and Engineering Meet, D.A. Hordijk and M. Luković, editors, Springer Cham,
Maastricht, The Netherlands, pp. 2224–2233.
Tuutti, K., 1982, Corrosion of Steel in Concrete, Research Report No.4.82, CBI (Swedish Cement and
Concrete Research Institute), Stockholm, Sweden, 468 p.
Wang, C., Li, W., Wang, Y., Xu, S., and Fan, M., 2018, “Stray Current Distributing Model in the
Subway System: A Review and Outlook,” International Journal of Electrochemical Science,
Volume 13, pp. 1700–1727. doi: 10.20964/2018.02.16.
Chapter 13
DOI: 10.1201/9781032675541-13
768 Handbook of Precast Segmental Tunnel Lining Systems
process thus better enabling the TBM team to build “round rings”. There is an old saying
within the tunnel segment industry “a round ring solves many problems”.
[segment-to-segment and circumferential joint faces (ring-to-ring)]. Wood pins were the
first dowels, they were introduced in the 1960’s as ring-to-ring alignment devices for pri-
mary segments. These were cones tapered on each end that were installed in tapered holes
cast into the face of each segment. When the dowel engaged it helped to align each segment
and when the TBM propel jacks pushed each segment home the friction force between the
dowel and the wall of the cast-in hole created a resistance restricting segment movement
when the shove jacks propelled the digger shield forward mining for the next ring. Wood
dowels were used on segments without gaskets as the wood dowels could not keep gasket
seals compressed.
Figure 13.3 C onex wood dowels – MWRA Effluent Outfall Tunnel Project – Photo Courtesy
Sehulster Tunnels.
Note: Conex wood dowels installed in the circumferential joint of the test ring at the cast-
ing plant.
high-speed rail systems and highway tunnels; i.e., Port of Miami Tunnel, Alaskan Way
Tunnel remove the bolts because over time even properly installed bolts can vibrate loose
and then become a potential safety hazard to vehicles traveling through the tunnel. This
practice varies by standard industry practice in a particular country and the position of the
design engineer regarding final lining design requirements.
sewer tunnel and more efficient air flow for transportation tunnels. The international tunnel
industry wanted a circumferential joint connection system that met the following criteria:
With the new concept, designers and innovative precasters began to develop better circum-
ferential joint connection systems that would meet the above market objectives.
the dowel can be manufactured with a high-strength steel axis that is completely embedded
in the dowel during the injection molding process, thus providing a high-strength dowel
that will not corrode as shown in Figure 13.9.
In early version of this concept, the dowel was symmetrical on both ends, as illustrated in
Figures 13.9 and 13.10. Workers had to seat the dowels in the previously installed ring by
“hammering” the dowel to where it would remain straight for engagement to the next ring.
The force of the TBM shove jacks will close the ring and then the dowels would be fully
anchored. The next development in the product development process has been to remove
the “hammering” operation by the tunnel workers to initially seat the dowel thus greatly
simplifying and standardizing ring assembly in the tunnel.
This was achieved by having a threaded end on one end of the dowel as shown in
Figure 13.11. The workers then can screw the dowel’s threaded end into a plastic socket that
is cast into the circumferential face of the previously installed ring. This can be done using an
air wrench and socket thus improving on installation time and ring build quality as the dowel
now cannot be easily damaged. This has proven to be a very effective industry innovation.
The industry developed bicones that are American football shaped plastic cones that are
available in different diameters, lengths, some have additional center core reinforcement of
a hard plastic or a steel axis to provide increased shear resistance as shown in Figure 13.12.
These devices are placed in block-outs cast into the circumferential joint faces of the segment
and are installed in the ring at the time of erection in the tunnel. For projects where the
steel bolts are removed after ring assembly, bicones are typically used to provide long-term
shear resistance for the circumferential joint connection, project example Port of Miami
Tunnel, Miami, Florida and Alaskan Way Tunnel, Seattle, Washington in the United States.
tunnel lining system that provides a smooth intrados surface (without pockets). Pockets in
final lining segments create waster turbulence in water and sewer tunnels and wind turbu-
lence in ventilated transportation tunnels. A common practice now is to use guide rods, as
noted in Section 13.2.11, then remove the bolts after the backfill grout has set. Based on
certain geological conditions designers will prefer that the radial joints have a permanent
structural connection.
In the 2000’s, the Japanese developed and experimented with a steel radial joint con-
nection system that was used on some domestic projects but failed to gain any acceptance
in the international tunnel construction industry. Other systems have been attempted that
connected reinforcing cages through small pockets in the lining but tended to be project
specific experiments.
In the 2010’s, the French tunnel contractors gave serious consideration to the need to
develop a mechanical connection system for the radial joints that would be structurally
sound, non-corrosive and simple to install. Optimas Solutions, a French based segment
componentry supplier developed a system that met the criteria of the tunnel contractors.
The system consists of two main components. A plastic male tapered dowel that during ring
assembly enters a mating plastic cone. When the TBM shove jacks push the segment home
the tapered cone properly aligns the radial joint as it enters the female cone. Once in place
and the circumferential connectors are engaged the radial joint is permanently fixed and the
segmental lining has “pocket free” intrados face. Refer to Figure 13.13 that shows details
of the connection concept.
These are standard high-performance bicones whereby a steel sleeve with an internal thread
that replaces the standard solid steel axis. Steel tie-rods with threaded ends, are installed
through tubes cast in the segment, connect into the bicones. When tightened during segment
installation to a predetermined torque, force pulls the recently assembled ring segments
towards the previously installed ring creating a very high- tension force thus keeping
the gasket compressed. In seismic situations the bicone helps to increase the survivability
rate of the segmental tunnel lining. The system has been incorporated into the Los Angeles,
California Metro Purple Line, Sections 2 and 3 in the cross-passage break-out areas. The
system eliminates the building of a steel framework commonly called “hamster cages” in
the tunnel.
special embedded stud system. The new design eliminates the need to have to glue the
plastic rods in casting plant. Throughout the world gluing operations using a hazardous
material now requires special plant ventilation isolation systems for worker protection. The
embedded guide rod design creates a positive connection to the segment that will withstand
extended periods of outside storage even in cold weather climates.
systems to segment faces which was an attempt to seal the segmental lining. The primary
purpose of the seals was to seal the lining to prevent backfill grout from entering into the
working area of the tunnel. Permanent waterproofing was to be achieved by a final lining
steel or concrete pipe (water and sewer tunnels) or a cast-in-place concrete lining (transpor-
tation tunnels).
impact the selection of the gasket material. Over time it was determined that the best
material to be used for tunnel gaskets was EPDM (ethylene propylene diene monomer rub-
ber) is a type of synthetic rubber that is used in many industrial applications. Tunnel seg-
ments may have to be stored outside for extended periods of time if a project is delayed
plus owners were requiring a design life of 100 years, i.e. Channel Tunnel located between
France and England, it has been determined by the industry that EBDM best meets these
performance requirements and thus EPDM has become the standard polymer rubber com-
pound used in the tunnel industry.
Neoprene or other materials are still used in projects where high concentrations of hydro-
carbons will be encountered but special precautions are needed for the outside storage of
the segments or the gasket installation must occur at the project site just before the segments
are taken into the tunnel.
the segments were manufactured on a carousel or stationary casting system. A more recent
industry innovation has been the introduction of “anchored gaskets”. This gasket design
has feet at the base of the gasket that are designed to protrude into the concrete matrix at
the time of casting thus when demolded the gasket will be “anchored” to the precast seg-
ment as shown in Figure 13.20. The gasket is placed in the casting form prior to casting, it is
anchored to the mold with fins on the gasket profile that are anchored into grooves
machined into the steel mold side flanges. The gaskets will release from the side molds when
the segment is demolded. The gasket is now permanently anchored to the segment and can
now be sent to the storge yard.
to the proper intrados and extrados radii before being fabricated into cage assemblies that
are then placed in the steel casing molds at the casting facility. Please refer to Figure 13.21.
The cages are fabricated to very tight dimensional tolerances to meet tight reinforcement
placement tolerances as specified by the lining designer.
For durability reasons these polymer fibers are predominantly made of polypropylene,
having a nominal length of typically 50 to 65 mm (2.0 to 2.6 inches) and a tensile strength
ranging from 500 to 700 MPa (72,500 to 101,500 psi). The fibers are manufactured in con-
formity to ASTM C1116 and DIN EN 14889-2. The key advantages are that they provide a
more uniform reinforcement matrix as compared to traditional steel bars, contributing to a
reduction in cracking and spalling during transient and permanent load stages of the tunnel
segments. Furthermore, MSF is non-corrosive, a property that has driven its use in many
applications where durability is a concern. The non-corrosive property may also allow for a
reduction of concrete cover required solely for serviceability limit states, such as corrosion
prevention, which in return reduces material usage. Further environmental benefits include
reduced carbon footprint.
Extensive full-scale segment testing has been conducted by BarChip at the University of
Brescia, Italy, which demonstrated MSF reinforced concrete can meet the requirements of
MC 2010 for flexural requirements, minimum shear reinforcement, splitting and spalling
requirements. For test details refer to the “Performance of Tunnel Segments Reinforced
with Synthetic Macro Fibers” by Ralf Winterberg.
To date BarChip MSF has been used in multiple segmental tunnel linings, including the
Harefield to Southall Gas Transfer Tunnel, UK (2009), Pista Nueva Malaga Rail Tunnel,
Spain (2009), Santoña- Laredo Central Interceptor Collector, Spain (2016), and the
Blacksnake Creek CSO Tunnel, USA (2020). In North America the use of MSF is currently
limited to sewer tunnel applications as some designers are concerned about the long-term
creep “elongation” if applied to transportation tunnels. The industry is addressing these
issues and for sewer tunnels under compression this is not a major concern.
BarChip MSF fibers were successfully implemented into the precast segmental lining for
the Blacksnake Creek CSO Tunnel in St. Joseph, MO, United States. The sewer tunnel
project consisted of 2.0 km (1.25 miles) of a six-piece universal ring, 2.74 m (9.0 foot)
internal diameter, 1.2 m (4.0 foot) segment width with a 12.7 mm (0.5 inch) ring taper.
Dowels were used in the circumferential joint connection with steel bolts used in the radial
joint connection. A steel ball lifting device was used for segment erection in the TBM. As
discussed earlier in this chapter this ball lifting method can induce increased stresses in the
segment during handling. At the utilized dosage rate of 7.0 kg/m3 (12 lbs/yd3) the MSF
system worked fine.
The tunnel drive using an EPB TBM was initiated in soft ground (23%), then transitioned
into rock (63%), then to a mixed face condition (14%). The segment design using the MSF
system performed well in all three geological conditions. This was the first application of
macro synthetic fibers in a full-scale tunnel project in North America and the project was
both a technical and commercial success.
recovery shafts, the GFRP bars are made part of the slurry reinforcement cage at TBM
break-out “tunnel eye” area so the TBM head can easily cut through the support-of-
excavation wall without damaging the TBM cutterhead, this has become a common
industry practice.
very expensive due to the extensive fabrication costs and the special fire-resistant coating
that was required post-fabrication.
The tunnel contractor, the same for both contract sections, in conjunction with their
tunnel Design Engineer of Record, developed an alternative to the fabricated steel liner to
be used in the seismic area. The alternative is called a “composite segmental lining” that
consisted of the following as illustrated in Figure 13.30.
The “composite segmental lining” has the same dimensions as the standard segmental lin-
ing since these segments are cast in a standard precast segmental tunnel lining forms. The
embedded steel plates are anchored to the intrados face of the precast segment with Nelson
studs. A seismic event typically induces high tensile and shear stresses in the tunnel final lin-
ing. The anchored steel plate is designed to provide stability to the precast segmental tunnel
lining by binding the concrete together to create a unitized structure after a seismic event.
A movement may occur during a seismic event. The system has steel expansion plates to
cover and contain movement in the circumferential joint. The plates are designed to prevent
the infiltration of soil in the event of the circumferential joints could open during a seismic
event. The revised segment design also incorporates a post-tensioned rebar reinforcement
system cast into the special seismic section segments and circumferential dowels with special
yielding characteristics.
This system is a real innovation for the tunnel industry as it met the owner’s design
requirement for a “flexible” lining and provides a lower cost solution than an all-steel fab-
ricated tunnel lining for the seismic areas (del Amo et al., 2021).
reinforced concrete liner)]. Typical occurrences for such applications are for water or sewer
conveyance.
Various ingenious and special methods (as cited by Szechy, 1966) have been implemented
in the past to lock in prestress in the segments to carry low internal water pressure. These
include the following:
• The Keiser method (1960) incorporating pressure grouting to 150% of the work-
ing load
• A 4.2 and 4.9 m (14 and 16 foot) diameter sewer tunnel under the Seine (Lalande,
1949) incorporating tensioning jacks and an external prestressing steel band around
the segment’s extrados and a reinforced shotcrete internal liner, and
• A sewer 4.5 m (14.7 foot) diameter tunnel under the Rhine (Hochtief Nachrichten,
1960), incorporating prestressing bar between joints.
Modern precast concrete segment technology has incorporated internal connecting steel
between the segment to transfer and carry the internal pressure. These include the following:
• A 3.35 m (11 foot) diameter outfall tunnel in San Diego incorporating internal rebar
hoop steel connected by bearing/stress transfer plates between segments (Kaneshiro
et al., 1996) (refer to Figure 13.31).
Figure 13.31 Continuous hoop rebar joined by cast iron bearing transfer plates.
Note: Continuous hoop reinforcing steel joined by cast iron bearing transfer plates during
assembly in segment forms.
Innovative products and applications 793
Figure 13.32 Continuous hoop bar with special C- and H-s hape connectors system.
Note: Continuous hoop reinforcing steel joined by cast iron bearing transfer plates during
assembly in segment forms.
Source: Obayashi, 2023.
• An outfall 10.4m (34-feet) outside diameter tunnel for the Metropolitan Area Outer
Discharge Channel in Tokyo Bay incorporating internal rebar hoop steel connected
by C-shaped connectors, which are in turn butted together with H-shape connectors
(Miyao, et al., 1999, Obayashi Corp., 2023). Refer to Figure 13.32. A description of
the key features of this system is as follows:
• Radial joints incorporate wedges inserted along the tunnel axis by incorporating
C-shaped connectors that are embedded on the joint surface. When the two seg-
ments are butted together, those create an H-shaped space. Then an H-shaped
connector is inserted into the space to fasten the two segments together.
• Gaps in the H-shaped connectors are filled with quick-set, non-shrink cement
paste for corrosion resistance.
• Circumferential joints incorporate push grips (wedge pins) that retain the expansion
force of the seals between rings so that water tightness is assured. Also, the circum-
ferential joint is a tongue and groove configuration to accommodate shear forces.
Four 2.7 to 3.7 m (9 to 12 foot) outside diameter effluent tunnels in Japan where the design
was incorporated:
The Thun Flood Relief Tunnel, 6.0 m (19.7 foot) outside diameter in Switzerland (Kohler and
Rupp, 2008; Haefliger, 2009), and the Los Angeles County Sanitation District’s (LACSD)
794 Handbook of Precast Segmental Tunnel Lining Systems
Effluent Outfall Tunnel (Van Greunen et al., 2016; Cimiotti et al., 2021) incorporated con-
tinuous post-tensioned tendons (Figure 13.33).
The LACSD 5.5 m (18 foot) internal diameter tunnel is the first application of a post-
tensioning system in the USA and the extent is the largest worldwide. The contractor’s
design for this project included a flat duct system to improve constructability (Figure 13.34),
compared to the Japanese and referenced design. Optimization details of the post-tensioning
system are provided in Cimiotti et al. (2021).
In summary, strategies to carry low internal water pressures when designing precast con-
crete segment liners requires the following considerations:
Figure 13.33 Continuous post-t ensioned segment lining method ( Japanese round anchor).
Note: Continuous hoop reinforcing steel joined by cast iron bearing transfer plates during
assembly in segment forms.
Source: Nishikawa, 2003
Innovative products and applications 795
Areas for further innovation and evaluation may include the following “embryonic” alter-
native material systems such as
Project Details
The TBM was supplied by Robbins. They designed a special ventilation system to deal with
the presence of methane and included a rescue chamber on the nine-section back-up gantry.
The TBM had an innovative disassembly design that enabled the center core of the TBM to
be unbolted and retrieved back through the 7.0 m (23 feet) internal diameter precast seg-
mental lining, this facilitated one TBM to be used for both declines.
Construction of the project was initiated in July, 2012 and both declines were completed
by March, 2015, ahead of the initial desired completion date based on conventional drill
and blast decline construction. All parties involved viewed this innovation solution a suc-
cess as the work was done safely and completed on time.
tunnel lining as the final lining. The TBM provided mining efficiency in the soft rock Redcar
Mudstone geological conditions. Precast segmental tunnel linings with a gasket sealing
system will isolate the Mineral Transportation System (MTS) from the protected wood-
lands above.
Tunnel construction was started in 2020 by Strabag. Their contract is for the 37
km (23.6 miles) of the MTS. Tunneling is advancing well. This innovative precast seg-
mental tunnel lining concept solved a sensitive environmental issue and has allowed the
798 Handbook of Precast Segmental Tunnel Lining Systems
project to advance forward. Strabag states that they are building a sustainable tunnel
system as they sourced local sand and aggregates for the segment manufacturing and
are using modern diesel-electric hybrid tunnel locomotives that incorporate a kinetic
energy recovery system while reducing emissions resulting in a very innovative tunnel
project.
intrados face of the segment. The gaskets prevent external ground water from entering
the shaft.
The south structure was constructed first using a Herrenknecht vertical shaft sinking
machine. The shaft was lined with specially designed and manufactured precast segmental
shaft lining segments.
The system performed as planned and designed. The south structure VSM excavation began
in January 2012 and was completed in June 2012. The VSM/precast lining system was then
used to construct the north shaft.
have extensive utility corridor tunnel systems and other metropolitan areas are currently
implanting or planning such underground structures as a precast segmental tunnel lining
provides an excellent surface for the attachment of the many utilities. These tunnels are typ-
ically in the range of 4.0 to 6.0 m (13.12 to 19.68 feet) diameter.
Examples of oil and gas energy pipeline projects in North America include the following.
Project details:
• 6.4 km (4.0 miles) of tunnel to be built by TBM and using a precast segmental tunnel
lining for support and watertight construction.
Status:
Project Details:
• 2.6 km (1.64 miles) of tunnel being built with TBM /PSTL construction
Status:
• Contain twin gas pipelines running from Coquitlam, BC to Woodfibre LNG Plant
Project Details:
• 3.8 km (2.36 miles) of tunnel to be built with TBM and using a precast segmental
tunnel lining for support and watertight construction.
Status:
Throughout the world it is common practice to put oil and gas pipelines inside tunnels for
the reasons noted above, there are many of these types of tunnels in operation and being
planned for Eastern Europe/Western Asia used in the transport of energy to Western Europe
and the Black Sea ports.
• Computer chips or RFID (radio frequency identification) card that are embedded in
the concrete
• Marking plate, face mounted, with a numbering sequence for visual observation
• Marking plate, face mounted, with a bar code system that can be scanned
Marking location is important. Most owner quality control programs want to be able to
identify each segment when it is the stack in storage and then after the segment had been
installed in the tunnel. This requires that two marking plates be placed on the segment at
the time of manufacture. Please refer to Figure 13.39.
• Location 1 –on the radial joint face so each marker can be read in a stack during
storage
• Location 2 –on the intrados face so the marker can be read in the completed tunnel
grown significantly in the last 15 years (Cubeta, 2008). They were approved and specified
as an alternative for a sewage project in the USA, but not part of the winning project
because of cost (Klein et al., 2010). Tauber Rohrbau GmbH & Co. has been building
small diameter three-piece segments from 1.0 to 3.0 m (3.3 to 9.8 feet) in diameter using
polymer concrete conforming to DIN 54815-1,–2 (Maguire and Iskander, 2008; Tauber
Rohrbau GmbH & Co, 2021). More recently, the Dubai Strategic Sewerage Tunnels
System is specifying polymer concrete 60 m (197 feet) upstream and downstream (Monks,
2021) of drop shafts and Detroit, Michigan’s Oakland-Macomb Northeast Interceptor
relining will incorporate a four-piece, 4.9 m (16 foot) internal diameter polymer segments
(Asadollahi, 2021).
Technological advancements in formulations, manufacturing and design have made
precast polymer concrete tunnel segments considerably more practical and cost-effective.
Precast polymer concrete has been a consideration for tunnel segments based on its
806 Handbook of Precast Segmental Tunnel Lining Systems
superior corrosion resistance and physical properties compared to thin-film polymer coated
(embedded fiberglass or spray on epoxy liners) or mechanically or chemically bonded
thermo-plastic sheets; e.g. PVC or HDPE, lined with conventional Portland cement concrete
segments, which have limitations with respect to external pressure.
In general, polymer concrete is approximately 4 to 6 times stronger than conventional
concrete, such that precast polymer concrete segments could be produced as much as 50%
thinner than conventional concrete segments, and as much as 50% lighter, based on newly
developed and patented core technology. Precast polymer concrete is made from various
thermo-setting polymer binders, such as polyester, vinyl ester, polyurea and epoxy resins,
combined with inert aggregate fillers. Historically, these traditional binder systems have
had issues. All resin systems are not the same and may contain volatile organic compounds
(VOC) and hazardous air pollutants (HAP), making it difficult to permit and subject workers
to occupational safety and health problems. Also, some resin systems have high shrinkage,
high exothermic reaction, and cannot integrate reinforcing steel because of their differential
thermal properties. While other resin systems, containing VOC’s, HAP’s, and exhibiting
thermal and shrinkage issues are designed such that these are not obstacles to polymer con-
crete production.
Until recently, precast polymer concrete has been produced in small, manually operated,
batch plants, culminating in increased handling, questionable QA/QC and increased manu-
facturing costs. Polymer concrete producers are adapting to automated batching systems
and RFID microchip technology used in conventional concrete production.
In the case of vehicular tunnels, where corrosion is not an issue, segments can be designed
and manufactured using waffle designs, reducing the overall raw material volumes and cost.
However, waffled designs cannot be utilized in sanitary sewer tunnels due to sanitary sew-
age flow characteristics and turbulence created by waffle designs. A smooth internal surface
is essential. New and innovative polymer concrete segment design allows for a significant
reduction in the volume and weight of polymer concrete segments, while still maintaining a
smooth internal and external surface along with preserving physical and corrosion resistant
properties. By integrating and positioning lightweight cores within the polymer concrete
matrix, the polymer concrete tunnel segment can carry basically the same loads, as if it were
a solid polymer concrete segment (Cubeta and Kaneshiro, 2021). See Figure 13.42. This
innovative technology makes precast polymer concrete tunnel segments a cost-effective, cor-
rosion resistant alternative to thin-film coated or sheet-lined conventional Portland cement
concrete segmental tunnel lining systems.
many of the loads are cyclical. The industry need is for a system that will rebound after a
seismic event or if the external load relaxes due to a variety of possible reasons.
811
812 Handbook of Precast Segmental Tunnel Lining Systems
Figure 13.45 Installation of precast segmental lining after Station Cavern Excavation – Paris Metro.
Note: Special machine used for the ring erection consisting of 11 segments 1.2 m long and 0.8 m
thick (4.0 × 2.6 feet).
Innovative products and applications 813
repurposed from their original functions. Please refer to Figure 13.50 below, showing and
tunnel relining operation underway.
The benefits from relining tunnel and underground facilities with precast segment tunnel
lining includes the following for example
To address these issues, an innovative method using the mechanized tunneling to build the
cross-passage adits was used recently by Bouygues for the Tuen Mun Chek Lap Kok Link
(TMCLK) project in Hong Kong (Figure 13.57 and 13.58). In this method, a microtun
neling machine is used to bore the cross-passage adit by launching the MTBM from one
tunnel and retrieving it in the parallel tunnel. The cross-passages were bored by MTBM
while the main tunnel was still under construction. To be able to have a simultaneous con-
struction of the main tunnels and the cross-passage tunnel connecting them and allow for
the continuous logistics of the main tunnel excavation, the internal diameter of the main
tunnels should be at least 10 m (32.8 feet). The 4.5 km (2.75 mile) long subsea section of
the TMCLK tunnel consists of two road tubes each with two traffic lanes in one direction.
These tunnels were built using two slurry TBMs [14 m (45.9 foot) excavation diameter]
to overcome the challenging ground conditions and the surrounding water pressure higher
than 5 bar (72 psi) at the tunnel face.
One of these TBMs started its drive with the world’s largest diameter 17.63 m (57.8
feet) along the first 630 m (2,070 feet) approach structure at the portal area before being
818 Handbook of Precast Segmental Tunnel Lining Systems
reconfigured into a 14 m (45.9 feet) diameter TBM (Combe and Schwob, 2021). For cutting
tools replacement, saturation diving and fully automatic robotic arms were developed
to change a total of about 2,000 disc cutters on both TBM cutterheads. For TMCLK in
addition to the new solutions used for TBM tunneling, innovative design concepts were
developed for the construction of the approach structures shafts including a 500 m (1,640
feet) long and 43 m (141 feet) deep “caterpillar shape” cofferdam with 15 cells.
As explained above, several major innovative solutions were used for the construction
of this mega project. However, the focus of this section is on the construction of 46 subsea
cross-passages between the two parallel subsea road tunnels for which an innovative mecha-
nized tunneling method using a MBTM was applied for the first time. This method can also
be used to connect the tunnel to a shaft by launching the MTBM either from the shaft or
from the tunnel depending on the project construction approach. In transportation tunnels,
Innovative products and applications 819
this shaft can be a ventilation or an emergency egress shaft. Similar type of connection
between a tunnel and a shaft also exists in the case of water and wastewater projects when
a drop shaft or a distribution shaft is connected to the main tunnel.
National Fire Protection Association (NFPA) 502, the fire protection standard for road
tunnels requires a maximum spacing of 300 m (985 feet) between cross-passages. However,
for TMCLK project, a maximum spacing of 100 m (330 feet) was used to provide a higher
fire safety standard. The initial design was suggesting the use of ground freezing method
which is typically used to build cross-passages in grounds with high permeability and high
hydrostatic pressure. To reduce the risk and to remain within the tight schedule of the
project, the ground freezing design was changed to the use of microtunneling method and
jacking precast pipes to build the cross-passage tunnels. Figures 13.59 and 13.60 show the
concept of this solution and how it can allow the simultaneous construction of the main
820 Handbook of Precast Segmental Tunnel Lining Systems
tunnels and the cross-passage adits when the diameter of the main tunnels is large enough
to allow for the concurrent construction logistics.
As shown below in Figures 13.61 and 13.62, the main challenge for the application of
this method is the layout and the design of the launch and retrieval areas for the MTBM
to allow the continuation of the main tunnels TBM excavation. At the cross-passage loca-
tions, fiberglass reinforcing bars are used for the main tunnel segmental liner to allow for
the MTBM to bore through the segments. Also, on both sides of the MBTM drive, the
main tunnel liner needs to be reinforced with an end wall to allow for jacking forces to
Innovative products and applications 821
be adequately supported and distributed through the main tunnel liner and to prevent the
ovalization of the main tunnel rings. In addition, this wall allows the installation of a sealing
system to prevent the leakage during the temporary phase of construction and the per-
manent phase of operation.
For TMCLK project, 46 separate cross-passages typically about 13 m (42.6 feet) long were
built using two 3.65 m (12.0 foot) diameter slurry MTBM (Herrenknecht AVN 3000) for
excavating the ground and installing the precast concrete pipes for the permanent liner of
the adit. The average time needed for the construction of one cross-passage was 20 days
including transportation, assembly, microtunneling and disassembly. The specially designed
compact microtunneling equipment was used on both launching and receiving sides to min-
imize the microtunneling construction space required and to allow continuously keeping
one lane open for the main tunnel construction traffic. After the MTBM breaks into the
steel bell cap on the receiving side, the watertightness is temporarily ensured by grouting the
cross-passage adit and the main tunnel interface, then the pressure inside the bell is lowered
and finally the bell is opened and the MTBM is retrieved.
In summary, the TMCLK project demonstrated the innovative use of mechanized tun-
neling for cross-passage construction alongside with the main tunnel excavation. This
method can be applied practically in all type of geological and hydrogeological condi-
tions. If the internal diameter of the main tunnel is more than 10 m (32.8 feet) the exca-
vation of the cross-passages can be performed concurrently with the boring of the main
tunnels. This mechanized cross-passage construction method will increase the safety and
reduce the overall risk while at the same time it will result in major reduction in the con-
struction time and cost. In addition, the use of this method can be further extended to
the case of adit construction between the main tunnel and a shaft for transportation and
water projects.
822 Handbook of Precast Segmental Tunnel Lining Systems
PUBLISHED STANDARDS
• ASTM A496 Standard Specification for Steel Wire, Deformed, for Concrete Reinforcement
• ASTM C1116 Standard Specification for Fiber-Reinforced Concrete
• DIN 14889-2 Fibres for Concrete–Part 2: Polymer Fibres–Definitions, Specifications and Conformity
• DIN 54815-1 Pipes Made of Filled Polyester Resin Moulding Materials–Dimensions,
TECHNICAL CONFERENCES
DRK European Tunnel Seminar No.6, “Segmental Lining Design– Design Solutions for Urban
Tunnelling Projects”, Wolf Friedmann and Jan Franzius, 22 Sep 2009.
2021 RETC Paper, “Performance of Tunnel Segments Reinforced with Synthetic Macro Fibers”, Ralf
Winterberg (Lead Author), pp. 837–883.
2013 RETC Proceedings, “King County Uses New Shaft Technology on the Ballard Siphon Project”,
Kaneshiro et al., 2013, pp. 719–727.
2016 Seventh International Conference & Exhibition on Mass Mining, Sydney, NSW.
2021 RETC Paper, “Composite Segmental Lining to Resist a Fault Failure”, Angel Del Amo, Bingzhi,
Yang, Robert Goodfellow, Girish Roy , pp. 444–455.
A+B grouts, 644, 665 Annular grout, see also Grout equipment; Grout
Absorber pipes injection methods; Grout mixes; Mix
coupled, 818 design development
coupling of, 817 backfilling, 629
fitted in cage, 816, 817 classification
Accelerating admixtures, 271 by amount of cement, 632
Accelerators, 272, 654, 696 grout components, 633–634, 650
Acid attack filling at crown, 677
cement hydration products, 714–715 ground loosening, 631
concentrations of aggressive acids, 714 liner ring, 631
ACI 350 recommendations, 255–256 objectives, 630
Admixtures, 654–655 quality control, 694–695
Advanced systems without drilling, 389 ring widths, 631
Aggregates rock tunnels, 631
coarse, 265 support, liner rings, 622–623
compressible packing models, 267 TBM and segmental lining, 630
compressive strength, 264 TBM tail shield, 641–643
fine, 265–266 Anti-washout admixtures, 655
normal weight steel fiber reinforced concrete, Arrowhead Tunnels Project, 49
265 ASTM C1609–standard test method, 203, 216,
packing approaches, 266–267 273, 274, 275, 277, 303–309, 547, 548
project/owner-specific properties, 264 Asymmetrical dowel system, 364, 365
Air-cooled slag, 263 Automated digital quality control tracking
Air entrainment admixtures, 269–270 system, 573–577
Air vibrators, 461, 462, 503 Automatic fiber dosing equipment, 318–319
Albvorlandtunnel, Germany, 462, 503, 505 Automation, 494, 625–626, 809
Alkali-activated cementitious materials Axial force-bending moment interaction
(AACM), 331, 503–504 diagram, 151–152, 203–204, 211,
Alkali-aggregate reaction (AAR), 272, 332, 213–215
715–716
Alkali-silica reaction (ASR), 332, 728 Back-calculation parameters, 274
Alluvial soils, 55 Backfill grouting, 47–48
American Concrete Institute (ACI) method, 97, Banana bolts, 356
99, 734–742 Barcelona indirect tensile strength test, 303
American Society for Testing Materials (ASTM), BarChip macro synthetic fiber, 784
93, 264, 584, 706, 763 Bar reinforcement, 33, 38, 229, 312, 324, 327,
The Anacostia River CSO project, 671 331, 339, 340
Anchored gaskets, 433–436, 554, 781–782 Barton–Bandis joint model, 87
Anchored (non-glued) guide rods, 367–369 Batching and mixing equipment
Anchored guide rod system, 779 metropolitan area, 655
Anchored plastic dowel with steel center axis, one-component grouts, 656–657
774–775 two-component grouts, 657–658
Anchor installation, 390 Batch plant, 470–471, 665–666, 673–674
826 Index
Bay Area Rapid Transit (BART) system tunnels, Carousel segment production, 522–524
18–22 Carrousel and stationary production
Beam molds, 54, 547 arguments, 477
Beam-spring method, 161–164 with concreting chamber and curing tunnel,
Beam test report and parameters, 550 477
Bedded beam method, 161 crane-based concrete distribution system, 477
Bentonite, 651, 653 maintenance, 478
Bi-component grouts, 644 segment production facilities, 478
Bicones and center cones, 775–776 Cast-in channel systems
designated concrete socket, 366 anchor installation, 390
range of shapes and sizes, 365, 366 cast-in-place systems, 391
segment circumferential joint, 376, 378 curved, 391, 393–395
shear resistance, 367 curved fastening system, 391, 392
with tie-rods, 777–778 embedded fastening systems, 386, 389, 390
Bituminous packers, 370–371 high-speed railway tunnel cross-section, 392
Blacksnake Creek CSO Tunnel, 343, 784, 785 load directions, 391
Bleed test, 689, 690 serrated, 391
Boltless radial (longitudinal) joint connection Cast iron segment forming system, 41
systems, 379–380, 774 Cast iron tunnel liner segments at St. Clair
Bored hard rock tunnels, 28, 29 Tunnel, 588, 589
Borings and test pits, 70 Cement hydration
Break-out analysis, 194–197 concrete gaining strength and durability, 257
The Brundtland Commission, 324 fly ash, 261–263
Buchan, C. V. (Great Britain), 22 limestone, 264
Bucklock Sof-Clip couplers, 361 metakaolin, 263–264
Buckskin Mountains Tunnel, 28, 31 Portland cement, 257–258
Buc-Lock, 22 SCM, 258–260
Building information modeling (BIM) silica fume (microsilica), 260–261
crucifix joints, 117, 122, 124–126 slag cement, 263
ring length optimization, 105, 115 tri-and di-calcium silicates phases, 257
slight size adjustment of one segment, Zeta potential, 257
117–122 Cementitious products, 650–651
Bursting forces, 140 Channel Tunnel Project, 369
Channel Tunnel Rail Link (CTRL) project, 321,
Camlock Radial Joint Connection System, 35 328
Canadian Standards Association (CSA) method, Charcon tunnels (Great Britain), 22–24
742, 751 Chemical admixtures
Carbonation-induced corrosion, 736 accelerating, 271
Carbon cure method, 229 air entrainment, 269–270
Carbon footprint analysis components of, 268
aggregate quantities, 229 fresh state/post-hardening properties, 268
carbon cure method, 229 mechanisms, 268
cementitious materials, 228–229 mixtures proportioning, 271–272
CO2 emission primary and secondary functions, 268
drilling and blasting method, 232–233 retarding, 270–271
from electricity, 231–232 specialty, 271
emission produced during blasting, 232, WRA, 270
233 Chloride-induced reinforcement corrosion
fuel consumption, 230–231 damaged/corroded tunnels, 710
hydraulic break hammer, 233–234 degradation in tunnels, 710
loading and transportation, 235 loss of reinforcement, 711
road header, 233 Circular rings, see also Building information
rock waste transportation, 235 modeling (BIM)
TBM, 234–235 geometry of key segment, 114
fiber reinforcement, 229 internal diameter, 99–102
global warming and GHG emissions, 228 length, 104–106
Montreal Blue Line Extension, 236–238 ring segmentation, 109–111
Carousel casting system, 583 segmental ring systems, 105–109
Index 827
399, 514, 537, 547–551, 721, 725, 726, deformations, 152, 157
see also Preconstruction testing design codes, 154
characteristics of, 298–302 Groene Hart Tunnel, 151, 154
durability benefits, 328–331 shear forces, 152, 158
economic benefits, 328 TBM shield, 151, 152
Steel fibers TBM Tunnel Project, 152, 155, 156
appropriate fiber usages, 297 TBM launch, 623–624
attributes effecting performance, 298 TBM tail shield
dimensional tolerances, 298, 299 differential thrust cylinder extension, 612
dispersion of fresh concrete, 543–545 liner ring, 610–611
glued, 538–539, 541–543 ring positions, 612–613
logistics and storage of, 537 steering, 609–610
loose steel fibers, 543 tunnel alignment ahead, 611–612
vs. macro-synthetic fibers, 295–297 TBM technology
metering of, 538–543 design improvements, 768
precast segments, 296–298 guidance systems, 768
reception of, 537–538 innovations, 768
recommendations, 298, 537 segment erector technology, 768
reinforced concrete, 551 vacuum lifting, 768–769
reinforcement, 783–784 TBM thrust jack forces, 373
Storage yard accidental removal, 132
layout, 591, 593, 594 3D NFEA program, 144
segment stack, 590–591 eccentricities and load factors, 139
Stray current corrosion, see also Mitigation Iyengar diagram, 141, 142
methods linear elastic finite element analysis, 141,
corrosive effect, 718 143–145
defined, 717 nominal machines thrust, 136
electric trains, 716–717 radial section cut through circumferential
rail tunnels, 716 joint, 138
train catenary stray currents, 717 rendered 3D view, 137
Stress-relaxation tests, 441 rock thrust, 135
defined, 422 simplified equations, 140–141
diagram, 423, 424 SLS of cracking, 136–137
STUVA recommendations, 422, 423, 447 stress distribution under, 137
test rail assembly, 423 transverse view, circumferential joint, 139
tests rails for gaskets, 422 TBM trailing gear
Sulfate attack dependency, 602–603
external sulfate attack damage process, 713, individual segment unloading, 606–608
714 mechanical lifting, 603–605
water-soluble sulfate ions, 713 segment stack unloading, 608–609
Sulfonated naphthalene formaldehyde segment supply and unloading, 602
condensates (BNS), 654 vacuum lifting, 603, 605, 606
Supplemental geotechnical borings, 71 Technical developments in modern era, see also
Supplementary cementitious materials (SCM), Health and safety provisions
258–260 concrete mix designs, 38
Sustainability assessments, 325–326 logistics of supply, 43–46
reinforcing materials, 38–39
Tail skin back grouting pressure segment molds and production systems,
AASHTO DCRT-1-2010, 148 39–42
backfilling, tail skin void, 148 Temporary “full-moon” support frames, 195
design check, 151 Temporary “half-moon” support frames, 196
grout pressure, 147–148 Temporary steel bracing, 194
model, 149 Tension rod suspension system, 397, 398
results, 150 Test batch preparation, 685, 686
tail void back-grouting, 149 Testing equipment and apparatus, 685
TBM back-up load Test rail assembly, 423
axial forces, 152, 157 Test rings
bending moments, 152, 158 construction, 465–466
838 Index