# Activity ID Activity Name PKG NO. At Completion Start Finish Predecessor Details Successor Details Total 2024 2025 2026 2027
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1 May-18-27, Project Herring Level 4/5 Master Schedule - Developing (No constraint)
Project Herring Level 4/5 Master Schedule - Developing (No constraint)
2 PDP Key Milestones May-18-27, PDP Key Milestones
3 PDP I
4 P1-01 PDP I - Gate Review 0 Sep-30-23 A A1140: FS
5 PDP II Feb-28-24, PDP II
6 P2-01 PDP II - Kick off Meeting 0 Oct-13-23 A A1150: FS
7 P2-02 PDP II - Techincal Review 0 Nov-03-23 A A1155: FS
8 P2-03 PDP II - BEA Workshop 0 Nov-22-23 A A1170: FS
9 P2-04 PDP II - Gate Review 0 Feb-28-24 A1300: FS P3-1000: FS 129 PDP II - Gate Review
10 PDP III Jan-31-25, PDP III
11 P3-02 PDP III - NB-MOU Agr eement Signed 0 Jan-01-24 A P3-1030: FS PDP III - NB-MOU Agr eement Signed
12 P3-01 PDP III - Kick off Meeting 0 Aug-28-24 A P3-1000: FS PDP III - Kick off Meeting
13 P3-04 PDP III - PDRI Review 0 Nov-27-24 P3-1017: FS 644 PDP III - PDRI Review
14 P3-07 PDP III - BEA Wor kshop ( Combined with PDRI Together) 0 Nov-27-24 P3-1027: FS 644 PDP III - BEA Wor kshop ( Combined with PDRI Together)
15 P3-08 PDP III - Constructability Review 0 Dec-05-24 P3-1007: FS 638 PDP III - Constructability Review
16 P3-23 PDP III - Risk workshop 0 Dec-13-24 P3-1037: FS 632 PDP III - Risk workshop
17 P3-11 PDP III - Decision Package Review 0 Dec-30-24 P3-1014: FS 621 PDP III - Decision Package Review
18 P3-12 PDP III - Assur anc e Revi ew 0 Jan-07-25 P3-1004: FS 615 PDP III - Assur anc e Revi ew
19 P3-13 PDP III - Workshop 0 Jan-15-25 P3-1008: FS 609 PDP III - Workshop
20 P3-14 PDP III - Gate Readiness Review 0 Jan-23-25 P3-1009: FS 603 PDP III - Gate Readiness Review
21 P3-15 PDP III - Gate Review and Appr oval 0 Jan-31-25 P3-1010: FS A1650: FS 49 PDP III - Gate Review and Appr oval
22 PDP IVa Apr-17-26, PDP IVa
23 P4a-01 PDP IV - Kick off Meeting 0 Feb-03-25 A1650: FS 596 PDP IV - Kick off Meeting
24 P4a-05 PDP IV - Construction Started ( Year 0 Scope) 0 Jul-10-25 P4-2100: FS 483 PDP IV - Construction Started ( Year 0 Scope)
25 P4a-10 PDP IV - Mechanical Completion ( Year 0 Sc ope) 0 Apr-17-26 P4-2550: FS, P4-2505: FS, P4-2460: FS, P4-2380: FS, P4-2420: FS, P4-2340: 282
FS, P4-2295: FS, P4-2260: FS, P4-2230: FS, P4-2160: FS, P4-2630: FS PDP IV - Mechanical Completion ( Year 0 Sc ope)
26 PDP IVb May-18-27, PDP IVb
27 P4b-01 PDP IV - Plant Start-up ( Year 0 Sc ope) 0 May-15-26 P4-2140: FS, P4-2210: FS, P4b-10:
P4-2250:FS
FS, P4-2285: FS, P4-2330: FS, P4-2370: FS,0 P4-2410: FS, P4-2450: FS, P4-2495: FS, P4-2540: FS, P4-2610: FS PDP IV - Plant Start-up ( Year 0 Sc ope)
28 P4b-10 PDP IV - [Placeholder] Project Year 1&Year 2 Scope Execution ( TBD) 262 May-18-26 May-18-27 P4b-01: FS 0 PDP IV - [Placeholder] Project Year 1&Year 2 Scope Execution ( TBD )
29 PDP I Explore
30 Project M anagement
31 A1140 PDP I - Gate Review 0 Sep-30-23 A A1150: FS, P1- 01: FS
32 PDP II Develop Feb-28-24 A, PDP II Develop
33 Project M anagement Feb-28-24 A, Project Management
34 A1150 PDP II - Kick-off meeting 0 Oct-13-23 A Oct-13-23 A A1140: FS A1160: FS 15, A1155: FS 15, A1162: FS, P2-01: FS, A1190: FS, ES- 01.RFQ: FS
35 A1180 PDP II - Gate Review 1 Nov-09-23 A Nov-09-23 A A1170: FS -5 A1300: FS 17
36 A1170 PDP II - BEA Workshop 1 Nov-22-23 A Nov-22-23 A A1160: FS 12 A1300: FS, A1180: FS -5, P2-03: FS
37 A1160 PDP II - Techincal Review 1 Jan-01-24 A Jan-01-24 A A1150: FS 15 A1170: FS 12 PDP II - Techincal Review
38 A1155 PDP II - PDRI Review 1 Jan-01-24 A Jan-01-24 A A1150: FS 15 P2-02: FS PDP II - PDRI Review
39 A1162 PDP II - Preliminary Procurement Strategy Initiated 1 Jan-24-24 A Jan-24-24 A A1150: FS A1300: FF PDP II - Preliminary Procurement Strategy Initiated
40 A1300 PDP II - Gate Review with Enterprise 26 Jan-24-24 A Feb-28-24 A A1162: FF, A1180: FS 17, A1170:
P2-04:FSFS, P3-1030: FS PDP II - Gate Review with Enterprise
41 Engineering
42 A1190 PDP II - Conceptual Design 12 Oct-13-23 A Oct-31-23 A A1150: FS
43 Procurement Jan-10-24 A, Proc urement
44 RFQ
45 ES-01.RFQ ES-01 - ESP (Basic and Detial Design) - RFQ ES-01 10 Oct-13-23 A Oct-27-23 A A1150: FS ES-01.TBE: FS
46 TBE Jan-10-24 A, TBE
47 ES-01.TBE ES-01 - ESP (Basic and Detial Design) - TBE ES-01 53 Oct-27-23 A Jan-10-24 A ES-01.RFQ: FS ES-01.CBE: FS ES-01 - ESP (Basic and Detial Design) - TBE
48 CBE
49 PO
50 PDP III Planning Jul-10-25, PDP III Planning
51 Build Project Management Jan-31-25, Build Project Management
52 P3-1024 PDP III - 1st Site visit 3 Jul-26-24 A Jul-30-24 A P3-1030: FS 12 ES-07.RFQ: FS, ES-03.RFQ: FS 70, P3-1017: FS 85 PDP III - 1st Site visit
53 P3-1000 PDP III - Kick off Meeting 1 Aug-28-24 A Aug-28-24 A P2-04: FS, P3-1030: FS 30 P3-1003: FS 41, P3-01: FS, A2286: FS, P3-1034: FS, P3- 1040: FS 90, P3-1027: FS 45, P3-1037: FS 45 PDP III - Kick off Meeting
54 P3-1034 PDP III - Permit Plan ( By Permit Lead) 20 Aug-29-24 Sep-25-24 P3-1000: FS ES-08.RFQ: FS -10 4 PDP III - Permit Plan ( By Permit Lead)
55 P3-1003 PDP III - Procurement Contract Strategy Updated 1 Oct-25-24 Oct-25-24 P3-1000: FS 41 P3-1005: FF 10, P3-1006: FF 10 84 PDP III - Procurement Contract Strategy Updated
56 P3-1017 PDP III - PDRI Review 1 Nov-27-24 Nov-27-24 P3-1024: FS 85 P3-04: FS, P3-1027: FF 55 PDP III - PDRI Review
57 P3-1027 PDP III - BEA Wor kshop ( Combined with PDRI Together) 1 Nov-27-24 Nov-27-24 P3-1000: FS 45, P3-1017: FF
P3-07: FS, P3-1007: FS 5 55 PDP III - BEA Wor kshop ( Combined with PDRI Together)
58 P3-1007 PDP III - Constructability Review 1 Dec-05-24 Dec-05-24 P3-1027: FS 5 P3-08: FS, A15460: FS, P3-1037: FS 5 55 PDP III - Constructability Review
59 P3-1037 PDP III - Risk Workshop 1 Dec-13-24 Dec-13-24 P3-1000: FS 45, P3-1007: FS
P3-23:
5 FS 632 PDP III - Risk Workshop
60 P3-1006 PDP III - Project Cost Estimation Updated 40 Nov-04-24 Dec-27-24 P3-1003: FF 10, CSA-02.BQ:
P3-1014:
FF 5, ACS-1.BQ:
FS FF 5, EEQ-01.BQ: FF 5, EEQ- 02.BQ:
49 FF 5, EEQ-03.BQ: FF 5, INS-01.BQ: FF 5, MEPI-01.BQ: FF 5, MEPI-02.BQ: FF 5, CSA-01.BQ: FF 3, IT-01.BQ: FF 5, IT-02.BQ: FF 5, PEQ-01.BQ: FF 5, PEQ-16.BQ: FF 5, PEQ-03.BQ: FF 5, PEQ-04.BQ: FF 5, PEQ-05.BQ: FF 5, PEQ-17.BQ: FF 5, PEQ-18.BQ:PDP
FF 5,
III PEQ-08.BQ:
- Project Cost
FFEstimation
5, PEQ-09.BQ:
Updated
FF 5, PEQ-10.BQ: FF 5, PEQ-11.BQ: FF 5, PEQ-13.BQ: FF 5, PEQ-19.BQ: FF 5, PEQ-14.BQ: FF 5, PEQ- 15.BQ: FF 5, FF- 01.BQ: FF 5, MEQ-02.BQ: FF 5, LEQ-01.BQ: FF 5, OEQ-01.BQ: FF 5, UEQ- 02.BQ: FF 5
61 P3-1005 PDP III - Project Level4/5 Master Schedule update 40 Nov-04-24 Dec-27-24 P3-1003: FF 10, ACS-1.BQ:P3-1014:
FF 5, CSA-01.BQ:
FS FF 5, CSA-02.BQ: FF 5, ES-03.BQ:
49FF 5, EEQ-01.BQ: FF 5, EEQ-02.BQ: FF 5, EEQ-03.BQ: FF 5, INS- 01.BQ: FF 5, MEPI-01.BQ: FF 5, MEPI-02.BQ: FF 5, IT-01.BQ: FF 5, IT-02.BQ: FF 5, PEQ-01.BQ: FF 5, PEQ-16.BQ: FF 5, PEQ-03.BQ: FF 5, PEQ-04.BQ: FF 5, PEQ-05.BQ: FF 5, PEQ-17.BQ: PDP
FF 5, III
PEQ-18.BQ:
- Project Level4/5
FF 5, PEQ-08.BQ:
Master Schedule
FF 5, PEQ-09.BQ:
update FF 5, PEQ-10.BQ: FF 5, PEQ-11.BQ: FF 5, PEQ-13.BQ: FF 5, PEQ- 19.BQ: FF 5, PEQ-14.BQ: FF 5, PEQ-15.BQ: FF 5, FF-01.BQ: FF 5, MEQ-02.BQ: FF 5, LEQ-01.BQ: FF 5, OEQ-01.BQ: FF 5, UEQ- 02.BQ: FF 5, A15460: FF 5
62 P3-1014 PDP III - Decision Support Package Reiew 1 Dec-30-24 Dec-30-24 P3-1005: FS, P3-1006: FS P3-1004: FS 5, P3-11: FS 49 PDP III - Decision Support Package Reiew
63 P3-1004 PDP III - Assur anc e Revi ew 1 Jan-07-25 Jan-07-25 P3-1014: FS 5 P3-12: FS, P3-1008: FS 5 49 PDP III - Assur anc e Revi ew
64 P3-1008 PDP III - Workshop 1 Jan-15-25 Jan-15-25 P3-1004: FS 5 P3-1010: FS 5, P3-13: FS, P3-1009: FS 5 49 PDP III - Workshop
65 P3-1009 PDP III - Gate Readiness Review 1 Jan-23-25 Jan-23-25 P3-1008: FS 5 P3-14: FS 603 PDP III - Gate Readiness Review
66 P3-1010 PDP III - Gate Review and Appr oval 7 Jan-23-25 Jan-31-25 P3-1008: FS 5 A1650: FS, P3-15: FS 49 PDP III - Gate Review and Appr oval
67 Business Jan-29-25, Business
68 P3-1030 [Placeholder] NB-MOU Agreement Si gned 93 Feb-29-24 A Jul-09-24 A A1300: FS P3-1000: FS 30, P3-1024: FS 12, P3-02: FS [Placeholder] NB-MOU Agreement Si gned
69 P3-1040 New Entity BOI Registered 0 Jan-01-25 P3-1000: FS 90 P3-1050: FS 20 51 New Entity BOI Registered
70 P3-1050 Leasing Contract Signed 0 Jan-29-25 P3-1040: FS 20 A1650: FS 51 Leasing Contract Signed
71 Land&Utility Tie-in Dec-12-24, Land&Utility Tie-i n
72 A15460 Utility tie-in condition clarification ??? ??? 5 Dec-06-24 Dec-12-24 P3-1007: FS P3-1005: FF 5 55 Utility tie-in condition clarification ???
73 Permit Jul-10-25, Permit
74 ECC Jun-10-25, ECC
75 ECC.01 Environmental Impact Assessment ( EIA) Preprati on ES-08 15 Nov-04-24 Nov-22-24 ES-08.PO: FS ECC.02: FS 0 Environmental Impact Assessment ( EIA) Preprati on
76 ECC.02 Environmental Impact Statement (EIS) Report ES-08 15 Nov-25-24 Dec-13-24 ECC.01: FS ECC.03: FS 0 Environmental Impact Statement (EIS) Report
77 ECC.03 Environmental Compliance Certificate (ECC) Submission and Approval ES-08 127 Dec-16-24 Jun-10-25 ECC.02: FS A15410: FF 22, A1680: FS 0 Environmental Compliance Certificate (ECC) Submission and Approval
78 Build Permit Jul-10-25, Build Permit
79 A15410 Building Permit (Need to confirmed with Permit Lead) Build Team 100 Feb-21-25 Jul-10-25 ECC.03: FF 22 A1640: FS 0 Building Permit (Need to confirmed with Permit Lead)
80 Engineering Feb-13-25, Engineering
81 G0 General Dec-17-24, G0 General
82 A2281 G0 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A2284: FF 22, A2282: FS, A2283: FS G0 - Process Design - P&ID
83 A2287 G0 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A2282: FF 1 A2290: FS, A2300: FS G0 - Equiment Reference Drawings ( From WDI)
84 A2288 G0 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A2282: FF 1 A2290: FS, A2300: FS G0 - Equiment Reference Drawings ( From Operation Team)
85 A2280 G0 - General Layout Completed ES-01 20 Sep-23-24 A Oct-20-24 A A2282: FF A2420: FS, A2880: FS, A2250: FS, A2010: FS, A2020: FS, A2030: FS, A2060: FS, A2180: FS, A2290: FS, A2300: FS, A9120: FS, ES-06.RFQ: FS 10, A9340: FF G0 - General Layout Completed
86 A2282 G0 - Core Process Equipment List & Spec. Completed ES-01 20 Sep-23-24 A Oct-20-24 A A2281: FS A2280: FF, PEQ-01.RFQ: FS 5, PEQ-16.RFQ: FS 5, PEQ-03.RFQ: FS 5, PEQ- 04.RFQ: FS 5, PEQ-05.RFQ: FS 5, PEQ- 17.RFQ: FS 5, PEQ-18.RFQ: FS 5, PEQ- 08.RFQ: FS 5, PEQ-09.RFQ: FS 5, PEQ- 10.RFQ: FS 5, PEQ -11.RFQ: FS 5, PEQ-13.RFQ: FS 5, PEQ-19.RFQ:
G0 - Core
FS 5,Process
A2287: FF
Equipment
1, A2288:
List
FF&1Spec. Completed
87 A2286 G0 - IT &CCTV upgrade Detail Requirement Development???? ( Need to be confirmed withCargill
IT lead) 45 Aug-29-24 Oct-30-24 P3-1000: FS IT-01.RFQ: FS 5, IT-02.RFQ: FS 5 66 G0 - IT &CCTV upgrade Detail Requirement Development???? ( Need to be confirmed with IT lead)
88 A2284 G0 - Valve & Instrument (list & Spec .) ES-01 26 Oct-09-24 A Nov-13-24 A2281: FF 22 A9050: SS, INS-01.RFQ: FS 4 57 G0 - Valve & Instrument (list & Spec .)
89 A2289 G0 - Electrical equipment list & Spec. ES-01 5 Nov-14-24 Nov-20-24 A2283: FF A2270: FS, EEQ-01.RFQ: FS, EEQ-02.RFQ: FS 49 G0 - Electrical equipment list & Spec.
90 A2283 G0 - Electrical equipment and sigle line diagram ES-01 43 Sep-23-24 A Nov-20-24 A2281: FS A2289: FF 49 G0 - Electrical equipment and sigle line diagram
91 A2291 G0 - MTO (MEPI) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A2020: FS, A2180: FS, A2270:
MEPI-01.RFQ:
FF 2, A2420:FSFS, A2880: FS, A9050: FS, A2250: FS,
49 A9120: FS G0 - MTO (MEPI) Issued for Bidding/Quotation
92 A2292 G0 - MTO (CSA) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A2010: FS, A2030: FS, A2060:
CSA-02.RFQ:
FS, A2300:FS,
FS,FF-01.RFQ:
A2290: FS, FS
A2300: FF, A2180: FS 49 G0 - MTO (CSA) Issued for Bidding/Quotation
93 A2302 G0 - Detail Design Competed ES-01 14 Nov-28-24 Dec-17-24 A2010: FS, A2020: FS, A2030:
A13290:
FS, A2060:
FS FS, A2250: FS, A2270: FS, A2300: FS,
150A2420: FS, A2880: FS, A9050: FS G0 - Detail Design Competed
94 G0.1 Entrance and Exit - Retrofit / Reinforcement Nov-22-24, G0.1 Entrance and Exit - Retrofit / Reinforcement
95 A2010 PDP III Detail Design (Structural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2292: FS, A2302: FS 49 PDP III Detail Design (Structural) - Reinforcement Design
96 A2020 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2291: FS, A2302: FS 49 PDP III Detail Design (Architectural Electrical)
97 A2030 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2292: FS, A2302: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
98 G0.2 Road Work - Pedestrian Walkway/Truck Parki ng Area/Car Parking Area/Motorcycle Parki ng Area Nov-22-24, G0.2 Road Work - Pedestrian W alkway/Tr uck Parking Area/Car Parking Ar ea/Motorcy cle Par king Area
99 A2060 PDP III Detail Design (Civil) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2292: FS, A2302: FS 49 PDP III Detail Design (Civil) - Reinforcement Design
100 G0.3 Fire Fighting system Nov-22-24, G0.3 Fire Fighting system
101 A2180 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2291: FS, A2292: FS 49 PDP III Detail Design (Fire Fighting)
102 G0.4 Telecom system(??? ) Nov-22-24, G0.4 Telecom system( ???)
103 A9120 PDP III Detail Design (Telecom???) ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2291: FS 49 PDP III Detail Design (Telecom???)
104 G0.6 Rainwater Harvesting system - Retrofit / Reinforcement Nov-27-24, G0.6 Rainwater Harvesting system - Retrofit / Reinforcement
105 A9050 PDP III Detail Design (Instrument and Autovalve) ES-01 25 Oct-09-24 Nov-12-24 A2284: SS A2291: FS, A2302: FS 57 PDP III Detail Design (Instrument and Autovalve)
106 A2250 PDP III Detail Design (Painting) ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2291: FS, A2302: FS 49 PDP III Detail Design (Painting)
107 A2290 PDP III Detail Design (Civil) - New Design ES-01 25 Oct-21-24 Nov-22-24 A2280: FS, A2287: FS, A2288:
A2292:
FS FS 49 PDP III Detail Design (Civil) - New Design
108 A2300 PDP III Detail Design (Structural) - New Design ES-01 25 Oct-21-24 Nov-22-24 A2280: FS, A2287: FS, A2288:
A2292:
FS FS, A2292: FF, A2302: FS 49 PDP III Detail Design (Structural) - New Design
109 A2420 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2291: FS, A2302: FS 49 PDP III Detail Design (Plumbing)
110 A2880 PDP III Detail Design (Insulation) ES-01 25 Oct-21-24 Nov-22-24 A2280: FS A2291: FS, A2302: FS 49 PDP III Detail Design (Insulation)
111 A2270 PDP III Detail Design (Electrical) ES-01 5 Nov-21-24 Nov-27-24 A2289: FS A2291: FF 2, A2302: FS 49 PDP III Detail Design (Electrical)
112 B0. Administ rative Buildings Dec-12-24, B0. Administrati ve Buildings
113 A9340 B0 - General Layout Completed ES-01 10 Oct-07-24 A Oct-20-24 A ES-01.PO: FS 22, A2280: FFA9201: FS, A9190: FS, A9200: FS, A9210: FS, A9380: FS, A9381: FS, A9410: FS, A9420: FS, A9430: FS, A9440: FS, A9450: FS, A9470: FS, A9480: FS, A9220: FS, A9500: FS, A9490: FS, A9510: FS, A9520: FS, A9530: FS, A9550: FS, A9560: FS, A9400: FS B0 - General Layout Completed
114 A9400 B0 - Office Furniture List??? ( Neet to check with Operation Lead) Cargill 5 Oct-21-24 Oct-25-24 A9340: FS OEQ-01.RFQ: FS 9 B0 - Office Furniture List??? ( Neet to check with Operation Lead)
115 A9410 B0 - Lab Equipment List & Spec. ( Need to be confirmend with FSQR Lead) Cargill 20 Oct-21-24 Nov-15-24 A9340: FS LEQ-01.RFQ: FS 59 B0 - Lab Equipment List & Spec. ( Need to be confirmend with FSQR Lead)
116 A9250 B0 - MTO (CSA) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A9201: FS, A9200: FS, A9210:
CSA-02.RFQ:
FS, A9190:FS
FS, A9380: FS, A9381: FS, A9220: FS,49
A9490: FS, A9500: FS, A9510: FS, A9520: FS, A9530: FS, A9550: FS, A9560: FS, A9420: FS, A9430: FS, A9440: FS, A9450: FS, A9470: FS, A9480: FS B0 - MTO (CSA) Issued for Bidding/Quotation
117 A9370 B0 - Detail Design Competed ES-01 14 Nov-25-24 Dec-12-24 A9201: FS, A9190: FS, A9200:
A15280:
FS, A9210:
FS FS, A9380: FS, A9381: FS 156 B0 - Detail Design Competed
118 B0.1 Laboratory Fixture Nov-22-24, B0.1 Laboratory Fixture
119 A9201 PDP III Detail Design (Architectural) - New Design ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS, A9370: FS 49 PDP III Detail Design (Architectural) - New Design
120 A9190 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9370: FS, A9250: FS 49 PDP III Detail Design (Architectural Electrical)
121 A9200 PDP III Detail Design (HAVC) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS, A9370: FS 49 PDP III Detail Design (HAVC)
122 A9380 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS, A9370: FS 49 PDP III Detail Design (Fire Fighting)
123 A9381 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS, A9370: FS 49 PDP III Detail Design (Plumbing)
124 B0.2 Office Fixture Nov-22-24, B0.2 Office Fixture
125 A9210 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS, A9370: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
126 A9420 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
127 A9430 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Architectural Electrical)
128 A9440 PDP III Detail Design (HAVC) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (HAVC)
129 A9450 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Fire Fighting)
130 A9470 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Plumbing)
131 A9480 PDP III Detail Design (Dismantle) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Dismantle)
132 B0.3 Modify of storage Room/Employee Locker Room Nov-22-24, B0.3 Modify of storage Room/Employee Locker Room
133 A9220 PDP III Detail Design (Civil) - New Design ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Civil) - New Design
134 A9490 PDP III Detail Design (Structrual) - New Design ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Structrual) - New Design
135 A9500 PDP III Detail Design (Architectural) - New Design ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Architectural) - New Design
136 A9510 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Architectural Electrical)
137 A9520 PDP III Detail Design (HAVC) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (HAVC)
138 A9530 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Fire Fighting)
139 A9550 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Plumbing)
140 A9560 PDP III Detail Design (Dismantle) ES-01 25 Oct-21-24 Nov-22-24 A9340: FS A9250: FS 49 PDP III Detail Design (Dismantle)
141 B1. Dry Copra Warehouse - Ret rofi t / Reinforcement Dec-17-24, B1. Dry Copra War ehouse - Retrofi t / Reinforcement
142 A9570 B1 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A9580: FF 22, A9720: FS 10, A9730: FS B1 - Process Design - P&ID
143 A9690 B1 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A9720: FF 1 A9860: FS, A9870: FS B1 - Equiment Reference Drawings ( From WDI)
144 A9700 B1 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A9720: FF 1 A9860: FS, A9870: FS B1 - Equiment Reference Drawings ( From Operation Team)
145 A9710 B1 - General Layout Completed ES-01 20 Sep-23-24 A Oct-20-24 A A9720: FF A9870: FS, A9860: FS, A9880: FS, A9900: FS, A9910: FS, A9920: FS, A9930: FS B1 - General Layout Completed
146 A9720 B1 - Core Process Equipment List & Spec. Completed ES-01 10 Oct-07-24 A Oct-20-24 A A9570: FS 10 A9710: FF, A9931: FS, A9932: FS, PEQ- 01.RFQ: FS 5, PEQ-16.RFQ: FS 5, PEQ- 03.RFQ: FS 5, PEQ-04.RFQ: FS 5, PEQ- 05.RFQ: FS 5, PEQ-17.RFQ: FS 5, PEQ- 18.RFQ: FS 5, PEQ-08.RFQ: FS 5, PEQ-09.RFQ: FS 5, PEQ-10.RFQ: FS 5, PEQ-11.RFQ: FS 5, PEQ-13.RFQ:
B1 - CoreFS
Process
5, PEQ-19.RFQ:
EquipmentFS
List
5, &
A9700:
Spec.FF
Completed
1, A9690: FF 1
147 A9580 B1 - Valve & Instr ument (li st & Spec.) ES-01 26 Oct-09-24 A Nov-13-24 A9570: FF 22 A9950: FS, INS-01.RFQ: FS 4 51 B1 - Valve & Instrument (li st & Spec.)
148 A9600 B1 - Electrical equipment list & Spec. ES-01 5 Nov-07-24 Nov-13-24 A9730: FF A9940: FS, EEQ-01.RFQ: FS, EEQ-02.RFQ: FS 51 B1 - Electrical equipment list & Spec.
149 A9730 B1 - Electrical equipment and sigle line diagram ES-01 38 Sep-23-24 A Nov-13-24 A9570: FS A9600: FF, A15490: FF 51 B1 - Electrical equipment and sigle line diagram
150 A15490 B1 - Motro list & Spec. ES-01 5 Nov-07-24 Nov-13-24 A9730: FF A9940: FS, EEQ-03.RFQ: FS 51 B1 - Motro list & Spec.
151 A9670 B1 - MTO (MEPI) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A9910: FS, A9940: FF, A9950:
MEPI-01.RFQ:
FF, A9931: FS,
FS,A9932:
MEPI-02.RFQ:
FS FS 49 B1 - MTO (MEPI) Issued for Bidding/Quotation
152 A9680 B1 - MTO (CSA) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A9860: FS, A9870: FS, A9880:
CSA-01.RFQ:
FS, A9900:FS,
FS,CSA-02.RFQ:
A9920: FS, A9930:
FS, FF-01.RFQ:
FS FS 49 B1 - MTO (CSA) Issued for Bidding/Quotation
153 A9740 B1 - Detail Design Competed ES-01 14 Nov-28-24 Dec-17-24 A9860: FS, A9870: FS, A9880:
A15290:
FS, A9900:
FS FS, A9910: FS, A9920: FS, A9930: FS,
172A9950: FS B1 - Detail Design Competed
154 B1.1 Dry Copra Warehouse Nov-27-24, B1.1 Dry Copra Warehouse
155 A9860 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A9710: FS, A9700: FS, A9690:
A9680:
FS FS, A9740: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
156 A9870 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A9710: FS, A9700: FS, A9690:
A9680:
FS FS, A9740: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
157 A9880 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A9710: FS A9680: FS, A9740: FS 49 PDP III Detail Design (Architectural Electrical)
158 A9900 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A9710: FS A9680: FS, A9740: FS 49 PDP III Detail Design (Fire Fighting)
159 A9910 PDP III Detail Design (Telecom,Fire Alarm, Badge, Broadcast,???) ES-01 25 Oct-21-24 Nov-22-24 A9710: FS A9670: FS, A9740: FS 49 PDP III Detail Design (Telecom,Fire Alarm, Badge, Broadcast,???)
160 A9920 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A9710: FS A9680: FS, A9740: FS 49 PDP III Detail Design (Plumbing)
161 A9930 PDP III Detail Design (Dismantle) ES-01 25 Oct-21-24 Nov-22-24 A9710: FS A9680: FS, A9740: FS 49 PDP III Detail Design (Dismantle)
162 A9931 PDP III Detail Design (Mechanical New) ES-01 25 Oct-21-24 Nov-22-24 A9720: FS A9670: FS 49 PDP III Detail Design (Mechanical New)
163 A9932 PDP III Detail Design (Mechanical Retrofit) ??? 25 Oct-21-24 Nov-22-24 A9720: FS A9670: FS 49 PDP III Detail Design (Mechanical Retrofit)
164 A9940 PDP III Detail Design (Electrical) ES-01 10 Nov-14-24 Nov-27-24 A9600: FS, A15490: FS A9670: FF 51 PDP III Detail Design (Electrical)
165 A9950 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A9580: FS A9670: FF, A9740: FS 51 PDP III Detail Design (Instrument and Autovalve)
166 B2. Oil Mill Operations Dec-18-24, B2. Oil Mill Operations
167 A10210 B2 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A10220: FF 22, A10230: FF 39, A10310: FS 10, A10320: FS B2 - Process Design - P&ID
168 A10280 B2 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A10310: FF 1 A10340: FS, A10350: FS, A10635: FS, A10630: FS, A10640: FS, A10650: FS B2 - Equiment Reference Drawings ( From WDI)
169 A10290 B2 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A10310: FF 1 A10340: FS, A10350: FS, A10635: FS, A10640: FS, A10650: FS, A10630: FS B2 - Equiment Reference Drawings ( From Operation Team)
170 A10300 B2 - General Layout Completed ES-01 10 Oct-07-24 A Oct-20-24 A A10310: FF A10350: FS, A10340: FS, A10360: FS, A10370: FS, A10390: FS, A10400: FS, A10470: FS, A10820: FS, A10635: FS, A10630: FS, A10670: FS, A10640: FS, A10660: FS, A10650: FS, A10710: FS B2 - General Layout Completed
171 A10310 B2 - Core Process Equipment List & Spec. Completed ES-01 10 Oct-07-24 A Oct-20-24 A A10210: FS 10 A10300: FF, A10750: FS, A10770: FS, A10800: FS, A10760: FS, A10790: FS, A10440: FS, A10810: FS, PEQ-01.RFQ: FS 5, PEQ-16.RFQ: FS 5, PEQ-03.RFQ: FS 5, PEQ-04.RFQ: FS 5, PEQ-05.RFQ: FS 5, PEQ-17.RFQ: FS 5, PEQ-18.RFQ: FS 5, PEQ-08.RFQ: FS 5,
B2PEQ-09.RFQ:
- Core Process
FSEquipment
5, PEQ-10.RFQ:
List & FS
Spec.
5, PEQ-11.RFQ:
Completed FS 5, PEQ-13.RFQ: FS 5, PEQ-19.RFQ: FS 5, A10290: FF 1, A10280: FF 1
172 A10220 B2 - Valve & Instr ument (li st & Spec.) ES-01 26 Oct-09-24 A Nov-13-24 A10210: FF 22 A10420: FS, A10720: FS, INS-01.RFQ: FS 4 51 B2 - Valve & Instrument (li st & Spec.)
173 A10240 B2 - Electrical equipment list & Spec. ES-01 5 Nov-07-24 Nov-13-24 A10320: FF A10410: FS, EEQ-01.RFQ: FS, EEQ-02.RFQ: FS 51 B2 - Electrical equipment list & Spec.
174 A10320 B2 - Electrical equipment and sigle line diagram ES-01 38 Sep-23-24 A Nov-13-24 A10210: FS A10240: FF, A10840: FS, A15500: FF 51 B2 - Electrical equipment and sigle line diagram
175 A15500 B2 - Motor list & Spec. ES-01 5 Nov-07-24 Nov-13-24 A10320: FF A10410: FS, EEQ-03.RFQ: FS 51 B2 - Motor list & Spec.
176 A10230 B2 - Automation ( I&O list) & Spec. Cargill 15 Oct-25-24 Nov-14-24 A10210: FF 39 A10430: FS, A10730: FS, ACS- 1.RFQ: FS 5 55 B2 - Automation ( I&O list) & Spec.
177 A10260 B2 - MTO (MEPI) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A10410: FF, A10420: FF, A10760:
MEPI-01.RFQ:
FS, A10770:
FS, MEPI-02.RFQ:
FS, A10800: FS,
FSA10790: FS, A10720:
49 FF, A10840: FF B2 - MTO (MEPI) Issued for Bidding/Quotation
178 A10270 B2 - MTO (CSA) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A10340: FS, A10350: FS, A10360:
CSA-02.RFQ:
FS, A10370:
FS, CSA-01.RFQ:
FS, A10390: FS, FF-01.RFQ:
A10400: FS,FS
A10470:
49 FS, A10820: FS, A10630: FS, A10635: FS, A10640: FS, A10650: FS, A10660: FS, A10670: FS, A10710: FS B2 - MTO (CSA) Issued for Bidding/Quotation
179 A10330 B2 - Detail Design Competed ES-01 14 Nov-29-24 Dec-18-24 A10430: FS, A10340: FS, A10350:
A15300:FS,
FSA10360: FS, A10370: FS, A10390: FS, A10400:
127 FS, A10420: FS, A10730: FS B2 - Detail Design Competed
180 B2.1 Building Reinforce including MCC Room - Retrofit / Reinforcement Nov-28-24, B2.1 Building Reinforce including MCC Room - Retrofit / Reinforcement
181 A10340 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A10300: FS, A10280: FS, A10290:
A10270:FSFS, A10330: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
182 A10350 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A10300: FS, A10280: FS, A10290:
A10270:FSFS, A10330: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
183 A10360 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS, A10330: FS 49 PDP III Detail Design (Architectural Electrical)
184 A10370 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS, A10330: FS 49 PDP III Detail Design (Fire Fighting)
185 A10390 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS, A10330: FS 49 PDP III Detail Design (Plumbing)
186 A10400 PDP III Detail Design (Dismantle) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS, A10330: FS 49 PDP III Detail Design (Dismantle)
187 A10750 PDP III Detail Design (Mechanical Retrofit) ??? 25 Oct-21-24 Nov-22-24 A10310: FS 647 PDP III Detail Design (Mechanical Retrofit)
188 A10760 PDP III Detail Design (Mechanical New) ES-01 25 Oct-21-24 Nov-22-24 A10310: FS A10260: FS 49 PDP III Detail Design (Mechanical New)
189 A10770 PDP III Detail Design (Piping) ES-01 25 Oct-21-24 Nov-22-24 A10310: FS A10260: FS 49 PDP III Detail Design (Piping)
190 A10790 PDP III Detail Design (Insulation) ES-01 25 Oct-21-24 Nov-22-24 A10310: FS A10260: FS 49 PDP III Detail Design (Insulation)
191 A10800 PDP III Detail Design (Painting) ES-01 25 Oct-21-24 Nov-22-24 A10310: FS A10260: FS 49 PDP III Detail Design (Painting)
192 A10410 PDP III Detail Design (Electrical) ES-01 10 Nov-14-24 Nov-27-24 A10240: FS, A15500: FS A10260: FF 51 PDP III Detail Design (Electrical)
193 A10420 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A10220: FS A10260: FF, A10330: FS 51 PDP III Detail Design (Instrument and Autovalve)
194 A10430 PDP III Detail Design (Automation) ES-01 10 Nov-15-24 Nov-28-24 A10230: FS A10330: FS 127 PDP III Detail Design (Automation)
195 B2.2 Expeller Retrofit Nov-22-24, B2.2 Expeller Retrofit
196 A10440 PDP III Detail Design (Mechanical Retrofit) ??? 25 Oct-21-24 Nov-22-24 A10310: FS 647 PDP III Detail Design (Mechanical Retrofit)
197 A10470 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS 49 PDP III Detail Design (Fire Fighting)
198 B2.3 Transport Equipment Retrofit Nov-22-24, B2.3 Transpor t Equipment Retrofit
199 A10810 PDP III Detail Design (Mechanical Retrofit) ??? 25 Oct-21-24 Nov-22-24 A10310: FS 647 PDP III Detail Design (Mechanical Retrofit)
200 A10820 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS 49 PDP III Detail Design (Fire Fighting)
201 B2.4 13.2 KVA Transformer Nov-28-24, B2.4 13.2 KVA Transformer
202 A10640 PDP III Detail Design (Structrual) - New Design ES-01 25 Oct-21-24 Nov-22-24 A10300: FS, A10280: FS, A10290:
A10270:FSFS 49 PDP III Detail Design (Structrual) - New Design
203 A10650 PDP III Detail Design (Architectural) - New Design ES-01 25 Oct-21-24 Nov-22-24 A10300: FS, A10280: FS, A10290:
A10270:FSFS 49 PDP III Detail Design (Architectural) - New Design
Actual Work Critical Remaining Work Summary Page 1 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Project Herring Level 4/5 Master Schedule - Developing (No constraint) Herring L4/L5 Layout Nov-18-24 05:21
# Activity ID Activity Name PKG NO. At Completion Start Finish Predecessor Details Successor Details Total 2024 2025 2026 2027
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
204 A10660 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS 49 PDP III Detail Design (Architectural Electrical)
205 A10670 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS 49 PDP III Detail Design (Fire Fighting)
206 A10635 PDP III Detail Design (Civil) - New Design ES-01 25 Oct-21-24 Nov-22-24 A10300: FS, A10280: FS, A10290:
A10270:FSFS 49 PDP III Detail Design (Civil) - New Design
207 A10630 PDP III Detail Design (Pilling) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS, A10280: FS, A10290:
A10270:FSFS 49 PDP III Detail Design (Pilling)
208 A10710 PDP III Detail Design (HAVC) ES-01 25 Oct-21-24 Nov-22-24 A10300: FS A10270: FS 49 PDP III Detail Design (HAVC)
209 A10720 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A10220: FS A10260: FF 51 PDP III Detail Design (Instrument and Autovalve)
210 A10840 PDP III Detail Design (Electrical) ES-01 10 Nov-14-24 Nov-27-24 A10320: FS A10260: FF 51 PDP III Detail Design (Electrical)
211 A10730 PDP III Detail Design (Automation) Cargill 10 Nov-15-24 Nov-28-24 A10230: FS A10330: FS 127 PDP III Detail Design (Automation)
212 B3. Finish Good Copra Warehouse - Retrofit / Reinforcement Dec-17-24, B3. Finish Good Copra Warehouse - Retrofit / Reinforcement
213 A9970 B3 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A9980: FF 22, A10070: FS 10, A10080: FS B3 - Process Design - P&ID
214 A10040 B3 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A10070: FF 1 A10100: FS, A10100: FF B3 - Equiment Reference Drawings ( From WDI)
215 A10050 B3 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A10070: FF 1 A10100: FS, A10110: FS B3 - Equiment Reference Drawings ( From Operation Team)
216 A10060 B3 - General Layout Completed ES-01 10 Oct-07-24 A Oct-20-24 A A10070: FF A10110: FS, A10100: FS, A10120: FS, A10130: FS, A10150: FS, A10160: FS B3 - General Layout Completed
217 A10070 B3 - Core Process Equipment List & Spec. Completed ES-01 10 Oct-07-24 A Oct-20-24 A A9970: FS 10 A10060: FF, A10740: FS, A10200: FS, PEQ- 01.RFQ: FS 5, PEQ-16.RFQ: FS 5, PEQ- 03.RFQ: FS 5, PEQ-04.RFQ: FS 5, PEQ- 05.RFQ: FS 5, PEQ-17.RFQ: FS 5, PEQ- 18.RFQ: FS 5, PEQ-08.RFQ: FS 5, PEQ- 09.RFQ: FS 5, PEQ-10.RFQ: FS 5, PEQ- 11.RFQ: FS 5, PEQ-13.RFQ:
B3 - Core Process
FS 5, PEQ-19.RFQ:
Equipment List
FS&5,
Spec.
A10040:
Completed
FF 1, A10050: FF 1
218 A9980 B3 - Valve & Instr ument (li st & Spec.) ES-01 26 Oct-09-24 A Nov-13-24 A9970: FF 22 A10180: FS, INS-01.RFQ: FS 4 51 B3 - Valve & Instrument (li st & Spec.)
219 A10000 B3 - Electrical equipment list & Spec. ES-01 5 Nov-07-24 Nov-13-24 A10080: FF A10170: SS, EEQ-01.RFQ: FS, EEQ-02.RFQ: FS 51 B3 - Electrical equipment list & Spec.
220 A10080 B3 - Electrical equipment and sigle line diagram ES-01 38 Sep-23-24 A Nov-13-24 A9970: FS A10000: FF, A15510: FF 51 B3 - Electrical equipment and sigle line diagram
221 A15510 B3 - Motor list & Spec. ES-01 5 Nov-07-24 Nov-13-24 A10080: FF A10170: SS, EEQ-03.RFQ: FS 51 B3 - Motor list & Spec.
222 A10020 B3 - MTO (MEPI) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A10170: FF, A10180: FF, A10200:
MEPI-01.RFQ:
FS FS, MEPI-02.RFQ: FS 49 B3 - MTO (MEPI) Issued for Bidding/Quotation
223 A10030 B3 - MTO (CSA) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A10100: FS, A10110: FS, A10120:
CSA-01.RFQ:
FS, A10130:
FS, CSA-02.RFQ:
FS, A10150: FS, FF-01.RFQ:
A10160: FS FS 49 B3 - MTO (CSA) Issued for Bidding/Quotation
224 A10090 B3 - Detail Design Competed ES-01 14 Nov-28-24 Dec-17-24 A10100: FS, A10110: FS, A10120:
A15305:FS,
FSA10130: FS, A10150: FS, A10160: FS, A10180:
167 FS B3 - Detail Design Competed
225 B3.1 Finish Good Copra W arehouse Nov-27-24, B3.1 Finish Good Copra War ehouse
226 A10100 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A10060: FS, A10040: FS, A10050:
A10030:FS,
FS,A10040:
A10090:
FFFS 49 PDP III Detail Design (Structrual) - Reinforcement Design
227 A10110 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A10060: FS, A10050: FS A10030: FS, A10090: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
228 A10120 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A10060: FS A10030: FS, A10090: FS 49 PDP III Detail Design (Architectural Electrical)
229 A10130 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A10060: FS A10030: FS, A10090: FS 49 PDP III Detail Design (Fire Fighting)
230 A10150 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A10060: FS A10030: FS, A10090: FS 49 PDP III Detail Design (Plumbing)
231 A10160 PDP III Detail Design (Dismantle) ES-01 25 Oct-21-24 Nov-22-24 A10060: FS A10030: FS, A10090: FS 49 PDP III Detail Design (Dismantle)
232 A10200 PDP III Detail Design (Mechanical New) ES-01 25 Oct-21-24 Nov-22-24 A10070: FS A10020: FS 49 PDP III Detail Design (Mechanical New)
233 A10740 PDP III Detail Design (Mechanical Retrofit) ??? 25 Oct-21-24 Nov-22-24 A10070: FS 647 PDP III Detail Design (Mechanical Retrofit)
234 A10170 PDP III Detail Design (Electrical) ES-01 15 Nov-07-24 Nov-27-24 A10000: SS, A15510: SS A10020: FF 51 PDP III Detail Design (Electrical)
235 A10180 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A9980: FS A10020: FF, A10090: FS 51 PDP III Detail Design (Instrument and Autovalve)
236 U0. Utilities Jan-30-25, U0. Utilities
237 A10850 U0 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A10860: FF 22, A10950: FS 10, A10960: FS U0 - Process Design - P&ID
238 A10920 U0 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A10950: FF 1 A10980: FS, A10990: FS, A11100: FS, A11110: FS, A11120: FS, A11487: FS, A11488: FS, A11489: FS, A11340: FS, A11350: FS U0 - Equiment Reference Drawings ( From WDI)
239 A10930 U0 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A10950: FF 1 A11100: FS, A11110: FS, A11120: FS, A10980: FS, A10990: FS, A11487: FS, A11488: FS, A11489: FS, A11340: FS, A11350: FS U0 - Equiment Reference Drawings ( From Operation Team)
240 A10940 U0 - General Layout Completed ES-01 33 Sep-16-24 Oct-30-24 A10950: FF A10990: FS, A10980: FS, A11000: FS, A11030: FS, A11110:
66 FS, A11100: FS, A11120: FS, A11130: FS, A11150: FS, A11350: FS, A11340: FS, A11360: FS, A11370: FS, A11390: FS, A11400: FS, A11488: FS, A11487: FS, A11489: FS, A11490: FS, A11491: FS, A11497: FS, A11498:
U0 - General
FS Layout Completed
241 A10950 U0 - Core Process Equipment List & Spec. Completed ( Without WWTP Proposal) ES-01 18 Oct-07-24 A Oct-30-24 A10850: FS 10 A10940: FF, A11090: FS, A11080: FS, A11210: FS, A11450:
-12 FS, A11440: FS, A11484: FS, PEQ-01.RFQ: FS 5, PEQ-16.RFQ: FS 5, PEQ-03.RFQ: FS 5, PEQ-04.RFQ: FS 5, PEQ-05.RFQ: FS 5, PEQ-17.RFQ: FS 5, PEQ-18.RFQ: FS 5, PEQ-08.RFQ: FS 5, PEQ-09.RFQ: FS 5,
U0PEQ-10.RFQ:
- Core Process
FS 5,
Equipment
PEQ-11.RFQ:
List &FS
Spec.
5, PEQ-13.R
Completed
FQ:( Without
FS 5, PEQ-
WWTP
19.RFQ:
Proposal)
FS 5, A10930: FF 1, A10920: FF 1, UEQ-02.RFQ: FS
242 A10860 U0 - Valve & Instr ument (li st & Spec.) ES-01 26 Oct-09-24 A Nov-13-24 A10850: FF 22 A11060: FS, A11180: FS, A11420: FS, A11485: FS, INS-01.RFQ:
57 FS 4 U0 - Valve & Instrument (li st & Spec.)
243 A10880 U0 - Electrical equipment list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A10960: FF A11050: FS, A11170: FS, A11410: FS, A11470: FS, A11480:
59 FS, A11481: FS, A11482: FS, A11483: FS, A11493: FS, A11494: FS, A11495: FS, A11496: FS, EEQ-01.RFQ: FS, EEQ-02.RFQ: FS U0 - Electrical equipment list & Spec.
244 A10960 U0 - Electrical equipment and sigle line diagram ES-01 40 Sep-23-24 A Nov-15-24 A10850: FS A10880: FF 59 U0 - Electrical equipment and sigle line diagram
245 A15570 U0 - WW TP proposal from Vendor UEQ-02 8 Nov-11- 24 Nov-20-24 UEQ-02.RFQ: FS A15580: FS 61 U0 - WWTP proposal from Vendor
246 A15580 U0 - Core Process Equipment List & Spec. Updated ES-01 10 Nov-21-24 Dec-04-24 A15570: FS A10900: FF 5, A10910: FF 5 61 U0 - Core Process Equipment List & Spec. Updated
247 A10900 U0 - MTO (MEPI) Issued for Bidding/Quotation ES-01 5 Dec-05-24 Dec-11-24 A11050: FS, A11060: FS, A11080:
MEPI-01.RFQ:
FS, A11170:
FS -20,
FS, MEPI-02.RFQ:
A11180: FS, A11410:
FS -20 FS, A11420:
61 FS, A11440: FS, A11470: FS, A11480: FS, A11481: FS, A11482: FS, A11483: FS, A11493: FS, A11485: FS, A11494: FS, A11495: FS, A11496: FS, A11484: FS, A15580: FF 5 U0 - MTO (MEPI) Issued for Bidding/Quotation
248 A10910 U0 - MTO (CSA) Issued for Bidding/Quotation ES-01 5 Dec-05-24 Dec-11-24 A10980: FS, A10990: FS, A11000:
CSA-02.RFQ:
FS, A11030:
FS -20,
FS,CSA-01.RFQ:
A11100: FS, A11110:
FS -20, FF-01.RFQ:
FS, A11120:
61 FSFS,-20
A11130: FS, A11150: FS, A11340: FS, A11350: FS, A11360: FS, A11370: FS, A11390: FS, A11400: FS, A11487: FS, A11488: FS, A11489: FS, A11490: FS, A11491: FS, A11497: FS, A11498: FS, A11484: FS, A15580: FF 5 U0 - MTO (CSA) Issued for Bidding/Quotation
249 A15400 U0 - Geo Survey Report ES-06 22 Dec-02-24 Dec-31-24 ES-06.PO: FS A10970: FF 22 140 U0 - Geo Survey Report
250 A10970 U0 - Detail Design Competed ES-01 14 Jan-13-25 Jan-30-25 A10980: FS, A10990: FS, A11000:
A15310:FS,
FSA11030: FS, A11060: FS, A11100: FS, A11110:
140 FS, A11120: FS, A11130: FS, A11150: FS, A11180: FS, A11340: FS, A11350: FS, A11360: FS, A11370: FS, A11390: FS, A11400: FS, A11420: FS, A11487: FS, A11488: FS, A11489: FS, A11490: FS, A11491: FS, A11485: FS, A11497: FS, A11498: FS, A15400: FF 22 U0 - Detail Design Competed
251 U0.1 Raw W ater Treatment - Retrofit / Reinforcement Nov-29-24, U0.1 Raw Wat er Treatment - Retrofit / Reinforcement
252 A10980 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10920: FS, A10930:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Structrual) - Reinforcement Design
253 A10990 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10920: FS, A10930:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Architectural) - Reinforcement Design
254 A11000 PDP III Detail Design (Architectural Electrical) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Architectural Electrical)
255 A11030 PDP III Detail Design (Plumbing) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Plumbing)
256 A11060 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A10860: FS A10900: FS, A10970: FS 66 PDP III Detail Design (Instrument and Autovalve)
257 A11080 PDP III Detail Design (Mechanical New) ES-01 20 Oct-31-24 Nov-27-24 A10950: FS A10900: FS 66 PDP III Detail Design (Mechanical New)
258 A11090 PDP III Detail Design (Mechanical Retrofit) ??? 20 Oct-31-24 Nov-27-24 A10950: FS 644 PDP III Detail Design (Mechanical Retrofit)
259 A11050 PDP III Detail Design (Piping) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Piping)
260 A11470 PDP III Detail Design (Insulation) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Insulation)
261 A11480 PDP III Detail Design (Painting) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Painting)
262 U0.3 Fire Water Tank/Water Storage Tank - Retrofit / Rei nforcement Nov-29-24, U0.3 Fire Water Tank/Wat er St orage Tank - Retrofit / Reinforcement
263 A11100 PDP III Detail Design (Civil) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10920: FS, A10930:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Civil) - Reinforcement Design
264 A11110 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10920: FS, A10930:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Structrual) - Reinforcement Design
265 A11120 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10920: FS, A10930:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Architectural) - Reinforcement Design
266 A11130 PDP III Detail Design (Architectural Electrical) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Architectural Electrical)
267 A11150 PDP III Detail Design (Plumbing) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Plumbing)
268 A11180 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A10860: FS A10900: FS, A10970: FS 66 PDP III Detail Design (Instrument and Autovalve)
269 A11210 PDP III Detail Design (Mechanical Retrofit) ??? 20 Oct-31-24 Nov-27-24 A10950: FS 644 PDP III Detail Design (Mechanical Retrofit)
270 A11170 PDP III Detail Design (Electrical) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Electrical)
271 A11481 PDP III Detail Design (Piping) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Piping)
272 A11482 PDP III Detail Design (Insulation) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Insulation)
273 A11483 PDP III Detail Design (Painting) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Painting)
274 U0.4 W ast e Water Treatment - New Design Nov-29-24, U0.4 Waste Water Treatment - New Design
275 A11487 PDP III Detail Design (Civil) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10920: FS, A10930:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Civil) - Reinforcement Design
276 A11488 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10920: FS, A10930:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Structrual) - Reinforcement Design
277 A11489 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10920: FS, A10930:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Architectural) - Reinforcement Design
278 A11490 PDP III Detail Design (Architectural Electrical) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Architectural Electrical)
279 A11491 PDP III Detail Design (Plumbing) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Plumbing)
280 A11485 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A10860: FS A10900: FS, A10970: FS 66 PDP III Detail Design (Instrument and Autovalve)
281 A11484 PDP III Detail Design (Mechanical Retrofit) ??? 20 Oct-31-24 Nov-27-24 A10950: FS A10900: FS, A10910: FS 66 PDP III Detail Design (Mechanical Retrofit)
282 A11497 PDP III Detail Design (Structrual) - New Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Structrual) - New Design
283 A11498 PDP III Detail Design (Civil) - New Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Civil) - New Design
284 A11493 PDP III Detail Design (Electrical) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Electrical)
285 A11494 PDP III Detail Design (Piping) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Piping)
286 A11495 PDP III Detail Design (Insulation) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Insulation)
287 A11496 PDP III Detail Design (Painting) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Painting)
288 U0.5 Cooling tower ??? Nov-29-24, U0.5 Cooling tower ???
289 A11340 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10930: FS, A10920:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Structrual) - Reinforcement Design
290 A11350 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 20 Oct-31-24 Nov-27-24 A10940: FS, A10930: FS, A10920:
A10910:FSFS, A10970: FS 66 PDP III Detail Design (Architectural) - Reinforcement Design
291 A11360 PDP III Detail Design (Architectural Electrical) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Architectural Electrical)
292 A11370 PDP III Detail Design (Fire Fighting) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Fire Fighting)
293 A11390 PDP III Detail Design (Plumbing) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Plumbing)
294 A11400 PDP III Detail Design (Dismantle) ES-01 20 Oct-31-24 Nov-27-24 A10940: FS A10910: FS, A10970: FS 66 PDP III Detail Design (Dismantle)
295 A11420 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A10860: FS A10900: FS, A10970: FS 66 PDP III Detail Design (Instrument and Autovalve)
296 A11440 PDP III Detail Design (Mechanical New) ES-01 20 Oct-31-24 Nov-27-24 A10950: FS A10900: FS 66 PDP III Detail Design (Mechanical New)
297 A11450 PDP III Detail Design (Mechanical Retrofit) ??? 20 Oct-31-24 Nov-27-24 A10950: FS 644 PDP III Detail Design (Mechanical Retrofit)
298 A11410 PDP III Detail Design (Electrical) ES-01 10 Nov-18-24 Nov-29-24 A10880: FS A10900: FS 64 PDP III Detail Design (Electrical)
299 U1. Utility Building Dec-17-24, U1. Utility Building
300 A11588 U1 - Boilder Feed system inputs from Boiler Vendor (Ther max) 5 Jan-01-24 Jan-05-24 U1
877
- Boilder Feed system inputs from Boiler Vendor (Ther max)
301 A11503 U1 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A11508: FF 22, A11553: FS 10, A11558: FS U1 - Process Design - P&ID
302 A11538 U1 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A11553: FF 1 A11568: FS, A11573: FS, A11613: FS, A11618: FS, A11623: FS, A11743: FS, A11748: FS, A11753: FS, A11828: FS, A11833: FS, A11908: FS, A11903: FS U1 - Equiment Reference Drawings ( From WDI)
303 A11543 U1 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A11553: FF 1 A11908: FS, A11903: FS, A11828: FS, A11833: FS, A11743: FS, A11748: FS, A11753: FS, A11803: FS, A11808: FS, A11613: FS, A11618: FS, A11623: FS, A11568: FS, A11573: FS U1 - Equiment Reference Drawings ( From Operation Team)
304 A11548 U1 - General Layout Completed ES-01 10 Oct-07-24 A Oct-20-24 A A11553: FF A11573: FS, A11568: FS, A11578: FS, A11583: FS, A11618: FS, A11613: FS, A11623: FS, A11628: FS, A11633: FS, A11748: FS, A11743: FS, A11753: FS, A11758: FS, A11763: FS, A11803: FS, A11808: FS, A11813: FS, A11823: FS, A11833: FS, A11828: FS, A11838:
U1FS,
- General
A11848:Layout
FS, A11858:
Completed
FS, A11898: FS, A11903: FS, A11908: FS, A11593: FS
305 A11553 U1 - Core Process Equipment List & Spec. Completed ES-01 10 Oct-07-24 A Oct-20-24 A A11503: FS 10 A11548: FF, A11653: FS, A11783: FS, A11728: FS, A11733: FS, A11738: FS, A11868: FS, A11788: FS, A11793: FS, A11798: FS, A11873: FS, A11878: FS, A11883: FS, A11913: FS, PEQ- 01.RFQ: FS 5, PEQ-16.RFQ: FS 5, PEQ- 03.RFQ: FS 5, PEQ-04.RFQ: FS 5, PEQ-
U1 05.RFQ:
- Core Process
FS 5, PEQ-17.RFQ:
Equipment List
FS &5,Spec.
PEQ- 18.RFQ:
Completed
FS 5, PEQ-08.RFQ: FS 5, PEQ- 09.RFQ: FS 5, PEQ-10.RFQ: FS 5, PEQ- 11.RFQ: FS 5, PEQ-13.RFQ: FS 5, PEQ-19.RFQ: FS 5, A11538: FF 1, A11543: FF 1
306 A11593 U1 - Maintenance Equipment List & Spec. Cargill? 5 Oct-21-24 Oct-25-24 A11548: FS MEQ-01.RFQ: FS, MEQ-02.RFQ: FS 9 U1 - Maintenance Equipment List & Spec.
307 A11508 U1 - Valve & Instr ument (li st & Spec.) ES-01 26 Oct-09-24 A Nov-13-24 A11503: FF 22 A11643: FS, A11773: FS, A11888: FS, INS-01.RFQ: FS
514 U1 - Valve & Instrument (li st & Spec.)
308 A11518 U1 - Electrical equipment list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A11558: FF A11638: FS, A11768: FS, A11918: FS, EEQ-01.RFQ: 49
FS, EEQ-02.RFQ: FS U1 - Electrical equipment list & Spec.
309 A11558 U1 - Electrical equipment and sigle line diagram ES-01 40 Sep-23-24 A Nov-15-24 A11503: FS A11518: FF, A15520: FF 49 U1 - Electrical equipment and sigle line diagram
310 A15520 U1 - Motor list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A11558: FF A11638: FS, A11768: FS, A11918: FS, EEQ-03.RFQ: 49
FS U1 - Motor list & Spec.
311 A11528 U1 - MTO (MEPI) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A11638: FF, A11643: FF, A11728:
MEPI-01.RFQ:
FS, A11733:
FS, FS,
MEPI-02.RFQ:
A11738: FS,FS
A11768: FF, A11773:
49 FF, A11788: FS, A11793: FS, A11798: FS, A11868: FS, A11888: FF, A11873: FS, A11878: FS, A11883: FS, A11913: FS, A11918: FF U1 - MTO (MEPI) Issued for Bidding/Quotation
312 A11533 U1 - MTO (CSA) Issued for Bidding/Quotation ES-01 5 Nov-25-24 Nov-29-24 A11568: FS, A11573: FS, A11578:
CSA-02.RFQ:
FS, A11583:
FS, CSA-01.RFQ:
FS, A11613: FS,
FS, A11618:
FF-01.RFQ:
FS, A11623:
FS 49 FS, A11628: FS, A11633: FS, A11743: FS, A11748: FS, A11753: FS, A11758: FS, A11763: FS, A11803: FS, A11808: FS, A11813: FS, A11823: FS, A11828: FS, A11833: FS, A11838: FS, A11848: FS, A11858: FS, A11898: FS, A11903: FS, U1
A11908:
- MTOFS
(CSA) Issued for Bidding/Quotation
313 A11563 U1 - Detail Design Competed ES-01 14 Nov-28-24 Dec-17-24 A11568: FS, A11573: FS, A11578:
A15315:
FS,FS
A11583: FS, A11613: FS, A11618: FS, A11623:
167 FS, A11628: FS, A11633: FS, A11643: FS, A11743: FS, A11748: FS, A11753: FS, A11758: FS, A11763: FS, A11773: FS, A11803: FS, A11808: FS, A11813: FS, A11823: FS, A11828: FS, A11833: FS, A11838: FS, A11848: FS, A11858: FS, A11888: FS, A11898:
U1 - Detail
FS,Design
A11903:
Competed
FS, A11908: FS
314 U1.1 Boiler building/U1.1 Air Compressor room/ Mai ntenance workshop - Retrofit / Reinforcement Nov-22-24, U1.1 Boiler building/U1.1 Air Compressor room/ Maintenance wor kshop - Ret rofi t / Reinfor cement
315 A11568 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
316 A11573 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
317 A11578 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Architectural Electrical)
318 A11583 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Plumbing)
319 A11813 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Fire Fighting)
320 A11823 PDP III Detail Design (Dismantle) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Dismantle)
321 U1.2.Biomass Thermax Boiler(Steam system) Nov-29-24, U1.2.Biomass Thermax Boiler(Steam system)
322 A11728 PDP III Detail Design (Piping) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Piping)
323 A11733 PDP III Detail Design (Insulation) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Insulation)
324 A11738 PDP III Detail Design (Painting) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Painting)
325 A11613 PDP III Detail Design (Civil) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Civil) - Reinforcement Design
326 A11618 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
327 A11623 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
328 A11628 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Architectural Electrical)
329 A11633 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Plumbing)
330 A11653 PDP III Detail Design (Mechanical Retrofit) ??? 25 Oct-21-24 Nov-22-24 A11553: FS 647 PDP III Detail Design (Mechanical Retrofit)
331 A11858 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Fire Fighting)
332 A11643 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A11508: FS A11528: FF, A11563: FS 51 PDP III Detail Design (Instrument and Autovalve)
333 A11638 PDP III Detail Design (Electrical) ES-01 10 Nov-18-24 Nov-29-24 A11518: FS, A15520: FS A11528: FF 49 PDP III Detail Design (Electrical)
334 U1.4 Air Compressor & system Nov-29-24, U1.4 Air Compressor & sy stem
335 A11788 PDP III Detail Design (Piping) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Piping)
336 A11793 PDP III Detail Design (Insulation) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Insulation)
337 A11798 PDP III Detail Design (Painting) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Painting)
338 A11743 PDP III Detail Design (Civil) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Civil) - Reinforcement Design
339 A11748 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
340 A11753 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
341 A11758 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Architectural Electrical)
342 A11763 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Plumbing)
343 A11783 PDP III Detail Design (Mechanical Retrofit) ??? 25 Oct-21-24 Nov-22-24 A11553: FS 647 PDP III Detail Design (Mechanical Retrofit)
344 A11803 PDP III Detail Design (Structrual) - New Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11543: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Structrual) - New Design
345 A11808 PDP III Detail Design (Civil) - New Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11543: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Civil) - New Design
346 A11868 PDP III Detail Design (Mechanical New) ES-01 25 Oct-21-24 Nov-22-24 A11553: FS A11528: FS 49 PDP III Detail Design (Mechanical New)
347 A11773 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A11508: FS A11528: FF, A11563: FS 51 PDP III Detail Design (Instrument and Autovalve)
348 A11768 PDP III Detail Design (Electrical) ES-01 10 Nov-18-24 Nov-29-24 A11518: FS, A15520: FS A11528: FF 49 PDP III Detail Design (Electrical)
349 U1.5 Coconut shell storage (for biomass boiler) Nov-29-24, U1.5 Coconut shell storage (for biomass boiler)
350 A11873 PDP III Detail Design (Piping) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Piping)
351 A11878 PDP III Detail Design (Insulation) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Insulation)
352 A11883 PDP III Detail Design (Painting) ES-01 14 Oct-21-24 Nov-07-24 A11553: FS A11528: FS 60 PDP III Detail Design (Painting)
353 A11828 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
354 A11833 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
355 A11838 PDP III Detail Design (Architectural Electrical) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Architectural Electrical)
356 A11848 PDP III Detail Design (Fire Fighting) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Fire Fighting)
357 A11898 PDP III Detail Design (Plumbing) ES-01 25 Oct-21-24 Nov-22-24 A11548: FS A11533: FS, A11563: FS 49 PDP III Detail Design (Plumbing)
358 A11903 PDP III Detail Design (Structrual) - New Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Structrual) - New Design
359 A11908 PDP III Detail Design (Civil) - New Design ES-01 25 Oct-21-24 Nov-22-24 A11548: FS, A11538: FS, A11543:
A11533:
FSFS, A11563: FS 49 PDP III Detail Design (Civil) - New Design
360 A11913 PDP III Detail Design (Mechanical New) ES-01 25 Oct-21-24 Nov-22-24 A11553: FS A11528: FS 49 PDP III Detail Design (Mechanical New)
361 A11888 PDP III Detail Design (Instrument and Autovalve) ES-01 10 Nov-14-24 Nov-27-24 A11508: FS A11528: FF, A11563: FS 51 PDP III Detail Design (Instrument and Autovalve)
362 A11918 PDP III Detail Design (Electrical) ES-01 10 Nov-18-24 Nov-29-24 A11518: FS, A15520: FS A11528: FF 49 PDP III Detail Design (Electrical)
363 P1. Dumping Area Dec-31-24, P1. Dumping Ar ea
364 A11923 P1 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A11928: FF 22, A11973: FS 10, A11978: FS P1 - Process Design - P&ID
365 A11958 P1 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A11973: FF 1 A11988: FS, A11993: FS, A12243: FS, A12248: FS, A12253: FS, A12258: FS, A12288: FS, A12293: FS, A12133: FS, A12128: FS, A12303: FS, A12158: FS, A12228: FS, A12323: FS, A12328: FS, A12333: FS, A12363: FS, A12368: FS, A12373: FS, A12378: FS, A12418:
P1 - Equiment
FS, A12423:
Reference
FS, A12428:
DrawingsFS( From WDI)
366 A11963 P1 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A11973: FF 1 A11988: FS, A11993: FS, A12243: FS, A12248: FS, A12253: FS, A12258: FS, A12288: FS, A12293: FS, A12133: FS, A12128: FS, A12303: FS, A12158: FS, A12228: FS, A12323: FS, A12328: FS, A12333: FS, A12363: FS, A12368: FS, A12373: FS, A12378: FS, A12418:
P1 - Equiment
FS, A12423:
Reference
FS, A12428:
DrawingsFS( From Operation Team)
367 A11973 P1 - Core Process Equipment List & Spec. Completed ES-01 18 Oct-07-24 A Oct-30-24 A A11923: FS 10 A11968: FF, A12048: FS, A12188: FS, A12343: FS, A12433: FS, PEQ- 01.RFQ: FS 5, PEQ-16.RFQ: FS 5, PEQ- 03.RFQ: FS 5, PEQ-04.RFQ: FS 5, PEQ- 05.RFQ: FS 5, PEQ-17.RFQ: FS 5, PEQ- 18.RFQ: FS 5, PEQ-08.RFQ: FS 5, PEQ- 09.RFQ: FS 5, PEQ-10.RFQ: FS 5, PEQ-
P111.RFQ:
- Core Process
FS 5, PEQ-13.RFQ:
Equipment List
FS 5,& PEQ-19.RFQ:
Spec. Completed
FS 5, A11958: FF 1, A11963: FF 1
368 A11968 P1 - General Layout Completed ES-01 18 Oct-07-24 A Oct-30-24 A A11973: FF A11993: FS, A11988: FS, A11998: FS, A12003: FS, A12083: FS, A12128: FS, A12133: FS, A12138: FS, A12148: FS, A12158: FS, A12163: FS, A12228: FS, A12243: FS, A12248: FS, A12258: FS, A12253: FS, A12263: FS, A12268: FS, A12283: FS, A12288: FS, A12293: FS,P1
A12303:
- General
FS,Layout
A12318:
Completed
FS, A12323: FS, A12328: FS, A12333: FS, A12338: FS, A12363: FS, A12368: FS, A12373: FS, A12378: FS, A12383: FS, A12388: FS, A12393: FS, A12398: FS, A12418: FS, A12423: FS, A12428: FS
369 A11978 P1 - Electrical equipment and sigle line diagram ES-01 32 Sep-26-24 A Nov-08-24 A11923: FS A11938: FS, A15530: FS 51 P1 - Electrical equipment and sigle line diagram
370 A11928 P1 - Valve & Instr ument (li st & Spec.) ES-01 26 Oct-09-24 A Nov-13-24 A11923: FF 22 A12098: FS, A12353: FS, A12408: FS, A12438: FS, INS-01.RFQ:
49 FS 4 P1 - Valve & Instrument (li st & Spec.)
371 A11938 P1 - Electrical equipment list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A11978: FS A12093: FS, A12348: FS, A12448: FS, EEQ-01.RFQ:51
FS, EEQ- 02.RFQ: FS P1 - Electrical equipment list & Spec.
372 A15530 P1 - Motor list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A11978: FS A12093: FS, A12348: FS, A12448: FS, EEQ-03.RFQ:51
FS P1 - Motor list & Spec.
373 A11948 P1 - MTO (MEPI) Issued for Bidding/Quotation ES-01 4 Nov-26-24 Nov-29-24 A12093: FF, A12098: FS, A12188:
MEPI-01.RFQ:
FS, A12048:
FS, MEPI-02.RFQ:
FS, A12343: FS,
FSA12348: FF, A12353:
49 FS, A12408: FS, A12433: FS, A12438: FS, A12448: FF P1 - MTO (MEPI) Issued for Bidding/Quotation
374 A11953 P1 - MTO (CSA) Issued for Bidding/Quotation ES-01 4 Nov-26-24 Nov-29-24 A11988: FS, A11993: FS, A11998:
CSA-02.RFQ:
FS, A12003:
FS, CSA-01.RFQ:
FS, A12083: FS,
FS, A12128:
FF-01.RFQ:
FS,FS
A12133:
49 FS, A12138: FS, A12148: FS, A12158: FS, A12163: FS, A12228: FS, A12243: FS, A12248: FS, A12253: FS, A12258: FS, A12263: FS, A12268: FS, A12283: FS, A12288: FS, A12293: FS, A12303: FS, A12318: FS, A12323: FS, A12328: FS,
P1 A12333:
- MTO (CSA)
FS, A12338:
Issued for
FS,Bidding/Quotation
A12363: FS, A12368: FS, A12373: FS, A12378: FS, A12383: FS, A12388: FS, A12393: FS, A12398: FS, A12418: FS, A12423: FS, A12428: FS
375 A11983 P1 - Detail Design Competed ES-01 14 Dec-12-24 Dec-31-24 A11988: FS, A11993: FS, A11998:
A15320:
FS,FS
A12003: FS, A12083: FS, A12098: FS, A12128:
158 FS, A12133: FS, A12138: FS, A12148: FS, A12158: FS, A12163: FS, A12228: FS, A12243: FS, A12248: FS, A12253: FS, A12258: FS, A12263: FS, A12268: FS, A12283: FS, A12288: FS, A12293: FS, A12048: FS, A12303: FS, A12318: FS, A12323: FS, A12328:P1FS,
- Detail
A12333:
Design
FS, A12338:
Competed
FS, A12343: FS, A12353: FS, A12363: FS, A12368: FS, A12373: FS, A12378: FS, A12383: FS, A12388: FS, A12393: FS, A12398: FS, A12408: FS, A12418: FS, A12423: FS, A12428: FS, A12433: FS, A12438: FS, A15450: FF
376 A15450 P1 - Geo Survey Report ES-06 22 Dec-02-24 Dec-31-24 ES-06.PO: FS A11983: FF 158 P1 - Geo Survey Report
377 P1.1 Clearing and Area Preparation Nov-25-24, P1.1 Clearing and Area Prepar ation
378 A11988 PDP III Detail Design (Pilling) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Pilling)
379 A11993 PDP III Detail Design (Architectural) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Architectural) - New Design
380 A11998 PDP III Detail Design (Architectural Electrical) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Architectural Electrical)
381 A12003 PDP III Detail Design (Plumbing) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Plumbing)
382 A12138 PDP III Detail Design (Fire Fighting) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Fire Fighting)
383 A12148 PDP III Detail Design (Dismantle) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Dismantle)
384 A12243 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Structrual) - New Design
385 A12248 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Civil) - New Design
386 P1.2 Construction of Dumping Nov-25-24, P1.2 Construction of Dumping
387 A12048 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A11973: FS A11948: FS, A11983: FS 49 PDP III Detail Design (Mechanical New)
388 A12253 PDP III Detail Design (Pilling) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Pilling)
389 A12258 PDP III Detail Design (Architectural) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Architectural) - New Design
390 A12263 PDP III Detail Design (Architectural Electrical) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Architectural Electrical)
391 A12268 PDP III Detail Design (Plumbing) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Plumbing)
392 A12283 PDP III Detail Design (Dismantle) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Dismantle)
393 A12288 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Structrual) - New Design
394 A12293 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Civil) - New Design
395 P1.3 Elevator and Provision of Belt conveyor from Dumping to connect Jetty belt Nov-27-24, P1.3 Elevator and Provision of Belt conveyor from Dumping to connect Jetty belt
396 A12083 PDP III Detail Design (Architectural Electrical) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Architectural Electrical)
397 A12098 PDP III Detail Design (Instrument and Autovalve) ES-01 8 Nov-14-24 Nov-25-24 A11928: FS A11948: FS, A11983: FS 49 PDP III Detail Design (Instrument and Autovalve)
398 A12128 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Structrual) - New Design
399 A12133 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Civil) - New Design
400 A12188 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A11973: FS A11948: FS 49 PDP III Detail Design (Mechanical New)
401 A12303 PDP III Detail Design (Pilling) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Pilling)
402 A12318 PDP III Detail Design (Dismantle) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Dismantle)
403 A12093 PDP III Detail Design (Electrical) ES-01 8 Nov-18-24 Nov-27-24 A11938: FS, A15530: FS A11948: FF 51 PDP III Detail Design (Electrical)
404 P1.5 Road Pavement Nov-25-24, P1.5 Road Pavement
405 A12158 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
406 A12163 PDP III Detail Design (Architectural Electrical) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Architectural Electrical)
407 A12228 PDP III Detail Design (Civil) - Reinforcement Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Civil) - Reinforcement Design
Actual Work Critical Remaining Work Summary Page 2 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Project Herring Level 4/5 Master Schedule - Developing (No constraint) Herring L4/L5 Layout Nov-18-24 05:21
# Activity ID Activity Name PKG NO. At Completion Start Finish Predecessor Details Successor Details Total 2024 2025 2026 2027
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
408 P1.6 Construction of Truck Scale Nov-27-24, P1.6 Construction of Truc k Scale
409 A12323 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Civil) - New Design
410 A12328 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Structrual) - New Design
411 A12333 PDP III Detail Design (Architectural) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Architectural) - New Design
412 A12338 PDP III Detail Design (Architectural Electrical) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Architectural Electrical)
413 A12343 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A11973: FS A11948: FS, A11983: FS 49 PDP III Detail Design (Mechanical New)
414 A12353 PDP III Detail Design (Instrument and Autovalve) ES-01 8 Nov-14-24 Nov-25-24 A11928: FS A11948: FS, A11983: FS 49 PDP III Detail Design (Instrument and Autovalve)
415 A12348 PDP III Detail Design (Electrical) ES-01 8 Nov-18-24 Nov-27-24 A11938: FS, A15530: FS A11948: FF 51 PDP III Detail Design (Electrical)
416 P1.7 Construction of Scale House Nov-25-24, P1.7 Construction of Scale House
417 A12363 PDP III Detail Design (Pilling) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Pilling)
418 A12368 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Civil) - New Design
419 A12373 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Structrual) - New Design
420 A12378 PDP III Detail Design (Architectural) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Architectural) - New Design
421 A12383 PDP III Detail Design (Architectural Electrical) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Architectural Electrical)
422 A12388 PDP III Detail Design (HVAC) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (HVAC)
423 A12393 PDP III Detail Design (Plumbing) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Plumbing)
424 A12398 PDP III Detail Design (Fire Fighting) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS A11953: FS, A11983: FS 49 PDP III Detail Design (Fire Fighting)
425 A12408 PDP III Detail Design (Instrument and Autovalve) ES-01 8 Nov-14-24 Nov-25-24 A11928: FS A11948: FS, A11983: FS 49 PDP III Detail Design (Instrument and Autovalve)
426 P1.8 Feeding hopper Nov-27-24, P1.8 Feeding hopper
427 A12418 PDP III Detail Design (Pilling) ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Pilling)
428 A12423 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Civil) - New Design
429 A12428 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A11968: FS, A11958: FS, A11963:
A11953:
FSFS, A11983: FS 49 PDP III Detail Design (Structrual) - New Design
430 A12433 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A11973: FS A11948: FS, A11983: FS 49 PDP III Detail Design (Mechanical New)
431 A12438 PDP III Detail Design (Instrument and Autovalve) ES-01 8 Nov-14-24 Nov-25-24 A11928: FS A11948: FS, A11983: FS 49 PDP III Detail Design (Instrument and Autovalve)
432 A12448 PDP III Detail Design (Electrical) ES-01 8 Nov-18-24 Nov-27-24 A11938: FS, A15530: FS A11948: FF 51 PDP III Detail Design (Electrical)
433 J0. Jetty Feb-13-25, J0. Jetty
434 A12453 J0 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-20-24 ES-01.PO: FS A12458: FF 22, A12463: FF 22, A12503: FS 10, A12508:
0 FS J0 - Process Design - P&ID
435 A12488 J0 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A12503: FF 1 A12518: FS, A12523: FS, A12528: FS, A13143: FS, A13148: FS, A12648: FS, A12653: FS, A13158: FS, A13178: FS, A13183: FS, A13188: FS, A13193: FS, A13198: FS, A13203: FS, A12713: FS, A12718: FS, A12723: FS, A13208: FS, A13213: FS, A12768: FS, A12773:
J0 - Equiment
FS, A12778:
Reference
FS Drawings ( From WDI)
436 A12493 J0 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A12503: FF 1 A12518: FS, A12528: FS, A13143: FS, A12523: FS, A13148: FS, A12648: FS, A12653: FS, A13158: FS, A13178: FS, A13183: FS, A13188: FS, A13193: FS, A13198: FS, A13203: FS, A12713: FS, A12718: FS, A12723: FS, A13208: FS, A13213: FS, A12768: FS, A12773:
J0 - Equiment
FS, A12778:
Reference
FS Drawings ( From Operation Team)
437 A12463 J0 - Automati on ( I&O list) & Spec. Cargill 10 Oct-09-24 Oct-22-24 A12453: FF 22 A13168: FS 656 J0 - Automati on ( I&O list) & Spec.
438 A12503 J0 - Core Process Equipment List & Spec. Completed ES-01 18 Oct-07-24 A Oct-30-24 A A12453: FS 10 A12498: FF, A12538: FS, A12783: FS, A13223: FS, A13228: FS, A13233: FS, PEQ-01.RFQ: FS 5, PEQ- 16.RFQ: FS 5, PEQ-03.RFQ: FS 5, PEQ- 04.RFQ: FS 5, PEQ-05.RFQ: FS 5, PEQ- 17.RFQ: FS 5, PEQ-18.RFQ: FS 5, PEQ- 08.RFQ: FS 5, PEQ-09.RFQ: FS 5, PEQ- 10.RFQ:
J0 -FS
Core
5, PEQ-11.RFQ:
Process Equipment
FS 5, PEQ-13.RFQ:
List & Spec. Completed
FS 5, PEQ-19.RFQ: FS 5, PEQ-14.RFQ: FS 5, PEQ-15.RFQ: FS 5, A12488: FF 1, A12493: FF 1
439 A12498 J0 - General Layout Completed ES-01 18 Oct-07-24 A Oct-30-24 A A12503: FF A12523: FS, A12518: FS, A12528: FS, A12648: FS, A12653: FS, A12713: FS, A12718: FS, A12723: FS, A12768: FS, A12773: FS, A12778: FS, A13143: FS, A13148: FS, A13158: FS, A13178: FS, A13183: FS, A13188: FS, A13193: FS, A13198: FS, A13203: FS, A13208: FS,
J0A13213:
- General
FS,Layout
A13218:
Completed
FS
440 A12458 J0 - Valve & Instrument (list & Spec .) ES-01 26 Oct-09-24 A Nov-13-24 A12453: FF 22 A12788: FS, A13163: FS, INS-01.RFQ: FS 4 49 J0 - Valve & Instrument (list & Spec .)
441 A12468 J0 - Electrical equipment list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A12508: FF A12798: FS, A13173: FS, EEQ- 01.RFQ: FS, EEQ-02.RFQ:
51 FS J0 - Electrical equipment list & Spec.
442 A12508 J0 - Electrical equipment and sigle line diagram ES-01 37 Sep-26-24 A Nov-15-24 A12453: FS A12468: FF, A15540: FF 51 J0 - Electrical equipment and sigle line diagram
443 A15540 J0 - Motor list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A12508: FF A12798: FS, A13173: FS, EEQ- 03.RFQ: FS 51 J0 - Motor list & Spec.
444 A12478 J0 - MTO (MEPI) Issued for Bidding/Quotation ES-01 4 Nov-26-24 Nov-29-24 A12538: FS, A12783: FS, A12788:
MEPI-01.RFQ:
FS, A12798:
FS, MEPI-02.RFQ:
FF, A13163: FS,
FSA13173: FF, A13223:
49 FS, A13228: FS, A13233: FS J0 - MTO (MEPI) Issued for Bidding/Quotation
445 A12483 J0 - MTO (CSA) Issued for Bidding/Quotation ES-01 4 Nov-26-24 Nov-29-24 A12518: FS, A12523: FS, A12528:
CSA-02.RFQ:
FS, A12648:
FS, CSA-01.RFQ:
FS, A12653: FS, FF-01.RFQ:
A12713: FS,FS
A12718:
49 FS, A12723: FS, A12768: FS, A12773: FS, A12778: FS, A13158: FS, A13188: FS, A13193: FS, A13198: FS, A13203: FS, A13218: FS J0 - MTO (CSA) Issued for Bidding/Quotation
446 A12533 J0 - Jetty Insepction Report and Cost & Schedule Assement ES-07 38 Oct-09-24 Nov-29-24 ES-07.PO: FS A13143: FS, A13148: FS, A13178: FS, A13183: FS, 131
A13208: FS, A13213: FS J0 - Jetty Insepction Report and Cost & Schedule Assement
447 A12513 J0 - Detail Design Competed ES-01 48 Dec-10-24 Feb-13-25 A12518: FS, A12523: FS, A12528:
A15325:FS,
FSA12648: FS, A12653: FS, A12538: FS, A12713:
131 FS, A12718: FS, A12723: FS, A12768: FS, A12773: FS, A12778: FS, A12783: FS, A12788: FS, A13143: FS, A13148: FS, A13158: FS, A13163: FS, A13178: FS, A13183: FS, A13188: FS, A13193: FS, A13198: FS, A13203: FS, A13208: FS, A13213: FS, A13218: FS, A13223: FS, A13228: FS, A13233:
J0 - Detail
FSDesign Competed
448 J0.1 Modification of Jetty Pier to accommodate the crane & tower Dec-09-24, J0.1 Modification of Jetty Pier to accommodate the crane & tower
449 A12518 PDP III Detail Design (Pilling) ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Pilling)
450 A12523 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Civil) - New Design
451 A12528 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Structrual) - New Design
452 A13143 PDP III Detail Design (Civil) - Reinforcement Design ES-07 6 Dec-02-24 Dec-09-24 A12498: FS, A12533: FS, A12488:
A12513:FS,
FS,A12493:
CSA-03-RFQ:
FS FS 131 PDP III Detail Design (Civil) - Reinforcement Design
453 A13148 PDP III Detail Design (Structrual) - Reinforcement Design ES-07 6 Dec-02-24 Dec-09-24 A12498: FS, A12533: FS, A12488:
A12513:FS,
FS,A12493:
CSA-03-RFQ:
FS FS 131 PDP III Detail Design (Structrual) - Reinforcement Design
454 J0.3 Installtion of Jetty Crane, hopper, st eel tower Nov-27-24, J0.3 Installtion of Jetty Crane, hopper, steel tower
455 A13168 PDP III Detail Design (Automation) Cargill 14 Oct-23-24 Nov-11- 24 A12463: FS 656 PDP III Detail Design (Automation)
456 A12538 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A12503: FS A12478: FS, A12513: FS 49 PDP III Detail Design (Mechanical New)
457 A12648 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Structrual) - New Design
458 A12653 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Civil) - New Design
459 A13158 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Structrual) - New Design
460 A13163 PDP III Detail Design (Instrument and Autovalve) ES-01 8 Nov-14-24 Nov-25-24 A12458: FS A12478: FS, A12513: FS 49 PDP III Detail Design (Instrument and Autovalve)
461 A13173 PDP III Detail Design (Electrical) ES-01 8 Nov-18-24 Nov-27-24 A12468: FS, A15540: FS A12478: FF 51 PDP III Detail Design (Electrical)
462 J0.4 Pier Assesment Dec-09-24, J0.4 Pier Assesment
463 A13178 PDP III Detail Design (Civil) - Reinforcement Design ES-07 6 Dec-02-24 Dec-09-24 A12498: FS, A12533: FS, A12488:
A12513:FS,
FS,A12493:
CSA-03-RFQ:
FS FS 131 PDP III Detail Design (Civil) - Reinforcement Design
464 A13183 PDP III Detail Design (Structrual) - Reinforcement Design ES-07 6 Dec-02-24 Dec-09-24 A12498: FS, A12533: FS, A12488:
A12513:FS,
FS,A12493:
CSA-03-RFQ:
FS FS 131 PDP III Detail Design (Structrual) - Reinforcement Design
465 J0.5 Handrail/ Fencing Nov-25-24, J0.5 Handrail/ Fencing
466 A13188 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Civil) - New Design
467 A13193 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Structrual) - New Design
468 J0.6 Security Post + Gate Nov-25-24, J0.6 Security Post + Gate
469 A13198 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Civil) - New Design
470 A13203 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Structrual) - New Design
471 J0.7 Jetty Improvement for Breasting dolphin and Intermediate feders Dec-09-24, J0.7 Jetty Improvement for Breasting dolphin and Intermediate feders
472 A12713 PDP III Detail Design (Pilling) ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Pilling)
473 A12718 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Civil) - New Design
474 A12723 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Structrual) - New Design
475 A13208 PDP III Detail Design (Civil) - Reinforcement Design ES-07 6 Dec-02-24 Dec-09-24 A12498: FS, A12533: FS, A12488:
A12513:FS,
FS,A12493:
CSA-03-RFQ:
FS FS 131 PDP III Detail Design (Civil) - Reinforcement Design
476 A13213 PDP III Detail Design (Structrual) - Reinforcement Design ES-07 6 Dec-02-24 Dec-09-24 A12498: FS, A12533: FS, A12488:
A12513:FS,
FS,A12493:
CSA-03-RFQ:
FS FS 131 PDP III Detail Design (Structrual) - Reinforcement Design
477 J0.8 Copra Unloading belt conveyor 240 meters long Nov-27-24, J0.8 Copra Unloading belt conveyor 240 meters long
478 A12768 PDP III Detail Design (Pilling) ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Pilling)
479 A12773 PDP III Detail Design (Civil) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Civil) - New Design
480 A12778 PDP III Detail Design (Structrual) - New Design ES-01 18 Oct-31-24 Nov-25-24 A12498: FS, A12488: FS, A12493:
A12483:FSFS, A12513: FS 49 PDP III Detail Design (Structrual) - New Design
481 A12783 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A12503: FS A12478: FS, A12513: FS 49 PDP III Detail Design (Mechanical New)
482 A12788 PDP III Detail Design (Instrument and Autovalve) ES-01 8 Nov-14-24 Nov-25-24 A12458: FS A12478: FS, A12513: FS 49 PDP III Detail Design (Instrument and Autovalve)
483 A13218 PDP III Detail Design (Architectural Electrical (lighting, lightening, grounding, etc.)) ES-01 18 Oct-31-24 Nov-25-24 A12498: FS A12483: FS, A12513: FS 49 PDP III Detail Design (Architectural Electrical (lighting, lightening, grounding, etc.))
484 A13223 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A12503: FS A12478: FS, A12513: FS 49 PDP III Detail Design (Mechanical New)
485 A13228 PDP III Detail Design (Piping) ES-01 18 Oct-31-24 Nov-25-24 A12503: FS A12478: FS, A12513: FS 49 PDP III Detail Design (Piping)
486 A13233 PDP III Detail Design (Painting) ES-01 18 Oct-31-24 Nov-25-24 A12503: FS A12478: FS, A12513: FS 49 PDP III Detail Design (Painting)
487 A12798 PDP III Detail Design (Electrical) ES-01 8 Nov-18-24 Nov-27-24 A12468: FS, A15540: FS A12478: FF 51 PDP III Detail Design (Electrical)
488 T1. Tank Farm A Dec-13-24, T1. Tank Farm A
489 A12803 T1 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A12808: FF 22, A12853: FS 10, A12858: FS T1 - Process Design - P&ID
490 A12838 T1 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A12853: FF 1 A12868: FS, A12873: FS T1 - Equiment Reference Drawings ( From WDI)
491 A12843 T1 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A12853: FF 1 A12868: FS, A12873: FS T1 - Equiment Reference Drawings ( From Operation Team)
492 A12853 T1 - Core Process Equipment List & Spec. Completed ES-01 18 Oct-07-24 A Oct-30-24 A A12803: FS 10 A12848: FF, A12983: FS, A12993: FS, A13003: FS, A12988: FS, A12998: FS, PEQ-01.RFQ: FS 5, PEQ- 16.RFQ: FS 5, PEQ-03.RFQ: FS 5, PEQ- 04.RFQ: FS 5, PEQ-05.RFQ: FS 5, PEQ- 17.RFQ: FS 5, PEQ-18.RFQ: FS 5, PEQ- 08.RFQ: FS 5, PEQ-09.RFQ: FS 5, PEQ- 10.RFQ:
T1 -FS
Core
5, PEQ-11.RFQ:
Process Equipment
FS 5, PEQ-13.RFQ:
List & Spec. Completed
FS 5, PEQ-19.RFQ: FS 5, A12838: FF 1, A12843: FF 1
493 A12848 T1 - General Layout Completed ES-01 18 Oct-07-24 A Oct-30-24 A A12853: FF A12873: FS, A12868: FS, A12878: FS, A12883: FS, A12893: FS T1 - General Layout Completed
494 A12808 T1 - Valve & Instrument (list & Spec .) ES-01 26 Oct-09-24 A Nov-13-24 A12803: FF 22 A12908: FS, INS-01.RFQ: FS 4 49 T1 - Valve & Instrument (list & Spec .)
495 A12818 T1 - Electrical equipment list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A12858: FF A12903: FS, EEQ-01.RFQ: FS 51 T1 - Electrical equipment list & Spec.
496 A12858 T1 - Electrical equipment and sigle line diagram ES-01 40 Sep-23-24 A Nov-15-24 A12803: FS A12818: FF, EEQ-02.RFQ: FS, A15560: FF 51 T1 - Electrical equipment and sigle line diagram
497 A15560 T1 - Motor list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A12858: FF A12903: FS, EEQ-03.RFQ: FS 51 T1 - Motor list & Spec.
498 A12828 T1 - MTO (MEPI) Issued for Bidding/Quotation ES-01 4 Nov-26-24 Nov-29-24 A12903: FF, A12908: FS, A12988:
MEPI-01.RFQ:
FS, A12993:
FS, MEPI-02.RFQ:
FS, A13003: FS,
FSA12998: FS 49 T1 - MTO (MEPI) Issued for Bidding/Quotation
499 A12833 T1 - MTO (CSA) Issued for Bidding/Quotation ES-01 4 Nov-26-24 Nov-29-24 A12868: FS, A12873: FS, A12878:
CSA-02.RFQ:
FS, A12883:
FS, CSA-01.RFQ:
FS, A12893: FS,
FS FF-01.RFQ: FS 49 T1 - MTO (CSA) Issued for Bidding/Quotation
500 A12863 T1 - Detail Design Competed ES-01 14 Nov-26-24 Dec-13-24 A12868: FS, A12873: FS, A12878:
A15330:FS,
FSA12883: FS, A12893: FS, A12908: FS 149 T1 - Detail Design Competed
501 T1. Tank Farm A Nov-27-24, T1. Tank Farm A
502 A12868 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 18 Oct-31-24 Nov-25-24 A12848: FS, A12838: FS, A12843:
A12833:FSFS, A12863: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
503 A12873 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 18 Oct-31-24 Nov-25-24 A12848: FS, A12838: FS, A12843:
A12833:FSFS, A12863: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
504 A12878 PDP III Detail Design (Architectural Electrical) ES-01 18 Oct-31-24 Nov-25-24 A12848: FS A12833: FS, A12863: FS 49 PDP III Detail Design (Architectural Electrical)
505 A12883 PDP III Detail Design (Fire Fighting) ES-01 18 Oct-31-24 Nov-25-24 A12848: FS A12833: FS, A12863: FS 49 PDP III Detail Design (Fire Fighting)
506 A12893 PDP III Detail Design (Plumbing) ES-01 18 Oct-31-24 Nov-25-24 A12848: FS A12833: FS, A12863: FS 49 PDP III Detail Design (Plumbing)
507 A12908 PDP III Detail Design (Instrument and Autovalve) ES-01 8 Nov-14-24 Nov-25-24 A12808: FS A12828: FS, A12863: FS 49 PDP III Detail Design (Instrument and Autovalve)
508 A12983 PDP III Detail Design (Mechanical Retrofit) ??? 18 Oct-31-24 Nov-25-24 A12853: FS 646 PDP III Detail Design (Mechanical Retrofit)
509 A12988 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A12853: FS A12828: FS 49 PDP III Detail Design (Mechanical New)
510 A12993 PDP III Detail Design (Piping) ES-01 18 Oct-31-24 Nov-25-24 A12853: FS A12828: FS 49 PDP III Detail Design (Piping)
511 A12998 PDP III Detail Design (Insulation) ES-01 18 Oct-31-24 Nov-25-24 A12853: FS A12828: FS 49 PDP III Detail Design (Insulation)
512 A13003 PDP III Detail Design (Painting) ES-01 18 Oct-31-24 Nov-25-24 A12853: FS A12828: FS 49 PDP III Detail Design (Painting)
513 A12903 PDP III Detail Design (Electrical) ES-01 8 Nov-18-24 Nov-27-24 A12818: FS, A15560: FS A12828: FF 51 PDP III Detail Design (Electrical)
514 T2. Tank Farm B Dec-13-24, T2. Tank Farm B
515 A13008 T2 - Process Design - P&ID ES-01 27 Aug-15-24 A Sep-22-24 A ES-01.PO: FS A13013: FF 22, A13058: FS 10, A13063: FS T2 - Process Design - P&ID
516 A13043 T2 - Equiment Reference Drawings ( From WDI) ES-01 10 Oct-02-24 A Oct-15-24 A A13058: FF 1 A13073: FS, A13078: FS T2 - Equiment Reference Drawings ( From WDI)
517 A13048 T2 - Equiment Reference Drawings ( From Operation Team) Cargill 10 Oct-02-24 A Oct-15-24 A A13058: FF 1 A13073: FS, A13078: FS T2 - Equiment Reference Drawings ( From Operation Team)
518 A13058 T2 - Core Process Equipment List & Spec. Completed ES-01 18 Oct-07-24 A Oct-30-24 A A13008: FS 10 A13053: FF, A13118: FS, A13128: FS, A13138: FS, A13123: FS, A13133: FS, PEQ-01.RFQ: FS 5, PEQ-16.RFQ: FS 5, PEQ-03.RFQ: FS 5, PEQ-04.RFQ: FS 5, PEQ-05.RFQ: FS 5, PEQ-17.RFQ: FS 5, PEQ-18.RFQ: FS 5, PEQ-08.RFQ: FS 5, PEQ-09.RFQ: FS 5, PEQ-10.RFQ:
T2 -FS
Core
5, PEQ-11.R
Process Equipment
FQ: FS 5, PEQ-13.RFQ:
List & Spec. Completed
FS 5, PEQ-19.RFQ: FS 5, A13043: FF 1, A13048: FF 1
519 A13053 T2 - General Layout Completed ES-01 18 Oct-07-24 A Oct-30-24 A A13058: FF A13078: FS, A13073: FS, A13083: FS, A13088: FS, A13098: FS T2 - General Layout Completed
520 A13013 T2 - Valve & Instrument (list & Spec .) ES-01 26 Oct-09-24 A Nov-13-24 A13008: FF 22 A13108: FS, INS-01.RFQ: FS 4 49 T2 - Valve & Instrument (list & Spec .)
521 A13023 T2 - Electrical equipment list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A13063: FF A13103: FS, EEQ-01.RFQ: FS, EEQ-02.RFQ: FS 51 T2 - Electrical equipment list & Spec.
522 A13063 T2 - Electrical equipment and sigle line diagram ES-01 40 Sep-23-24 A Nov-15-24 A13008: FS A13023: FF, A15550: FF 51 T2 - Electrical equipment and sigle line diagram
523 A15550 T2 - Motor list & Spec. ES-01 5 Nov-11- 24 Nov-15-24 A13063: FF A13103: FS, EEQ-03.RFQ: FS 51 T2 - Motor list & Spec.
524 A13033 T2 - MTO (MEPI) Issued for Bidding/Quotation ES-01 4 Nov-26-24 Nov-29-24 A13103: FF, A13108: FS, A13123:
MEPI-01.RFQ:
FS, A13128:
FS, MEPI-02.RFQ:
FS, A13138: FS,
FSA13133: FS 49 T2 - MTO (MEPI) Issued for Bidding/Quotation
525 A13038 T2 - MTO (CSA) Issued for Bidding/Quotation ES-01 4 Nov-26-24 Nov-29-24 A13073: FS, A13078: FS, A13083:
CSA-02.RFQ:
FS, A13088:
FS, CSA-01.RFQ:
FS, A13098: FS,
FS FF-01.RFQ: FS 49 T2 - MTO (CSA) Issued for Bidding/Quotation
526 A13068 T2 - Detail Design Competed ES-01 14 Nov-26-24 Dec-13-24 A13073: FS, A13078: FS, A13083:
A15335:FS,
FSA13088: FS, A13098: FS, A13108: FS 149 T2 - Detail Design Competed
527 T2. Tank Farm B Nov-27-24, T2. Tank Farm B
528 A13073 PDP III Detail Design (Structrual) - Reinforcement Design ES-01 18 Oct-31-24 Nov-25-24 A13053: FS, A13043: FS, A13048:
A13038:FSFS, A13068: FS 49 PDP III Detail Design (Structrual) - Reinforcement Design
529 A13078 PDP III Detail Design (Architectural) - Reinforcement Design ES-01 18 Oct-31-24 Nov-25-24 A13053: FS, A13043: FS, A13048:
A13038:FSFS, A13068: FS 49 PDP III Detail Design (Architectural) - Reinforcement Design
530 A13083 PDP III Detail Design (Architectural Electrical) ES-01 18 Oct-31-24 Nov-25-24 A13053: FS A13038: FS, A13068: FS 49 PDP III Detail Design (Architectural Electrical)
531 A13088 PDP III Detail Design (Fire Fighting) ES-01 18 Oct-31-24 Nov-25-24 A13053: FS A13038: FS, A13068: FS 49 PDP III Detail Design (Fire Fighting)
532 A13098 PDP III Detail Design (Plumbing) ES-01 18 Oct-31-24 Nov-25-24 A13053: FS A13038: FS, A13068: FS 49 PDP III Detail Design (Plumbing)
533 A13108 PDP III Detail Design (Instrument and Autovalve) ES-01 8 Nov-14-24 Nov-25-24 A13013: FS A13033: FS, A13068: FS 49 PDP III Detail Design (Instrument and Autovalve)
534 A13118 PDP III Detail Design (Mechanical Retrofit) ??? 18 Oct-31-24 Nov-25-24 A13058: FS 646 PDP III Detail Design (Mechanical Retrofit)
535 A13123 PDP III Detail Design (Mechanical New) ES-01 18 Oct-31-24 Nov-25-24 A13058: FS A13033: FS 49 PDP III Detail Design (Mechanical New)
536 A13128 PDP III Detail Design (Piping) ES-01 18 Oct-31-24 Nov-25-24 A13058: FS A13033: FS 49 PDP III Detail Design (Piping)
537 A13133 PDP III Detail Design (Insulation) ES-01 18 Oct-31-24 Nov-25-24 A13058: FS A13033: FS 49 PDP III Detail Design (Insulation)
538 A13138 PDP III Detail Design (Painting) ES-01 18 Oct-31-24 Nov-25-24 A13058: FS A13033: FS 49 PDP III Detail Design (Painting)
539 A13103 PDP III Detail Design (Electrical) ES-01 8 Nov-18-24 Nov-27-24 A13023: FS, A15550: FS A13033: FF 51 PDP III Detail Design (Electrical)
540 Procurement Jan-27-25, Procurement
541 RFQ Dec-16-24, RFQ
542 ES-07.RFQ Jetty Inspection & Assessment Servic e - RFQ ES-07 5 Aug-07-24 A Aug-13-24 A P3-1024: FS ES-07.TBE: FS Jetty Inspection & Assessment Servic e - RFQ
543 ES-08.RFQ Environmental Clearance Certificate - RFQ ES-08 3 Sep-18-24 A Sep-20-24 A P3-1034: FS -10 ES-08.TBE: FS Environmental Clearance Certificate - RFQ
544 PEQ-18.RFQ New Verti cal filter - RFQ PEQ-18 7 Oct-25-24 A Nov-04-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-18.TBE:
FS 5, FS,
A10070:
PEQ-18.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 New Verti cal f ilter - RFQ
545 PEQ-03.RFQ Copra Dumping Station package (New) - RFQ PEQ-03 2 Nov-02-24 A Nov-06-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-03.TBE:
FS 5, FS,
A10070:
PEQ-03.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Copra Dumping Station package (New) - RFQ
546 PEQ-01.RFQ Air Compressor (New) - RFQ PEQ-01 3 Nov-02-24 A Nov-06-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-01.TBE:
FS 5, FS,
A10070:
PEQ-01.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Air Compressor (New) - RFQ
547 PEQ-05.RFQ Copra Grinder improvement (Existing) - RFQ PEQ-05 6 Oct-31-24 A Nov-07-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-05.TBE:
FS 5, FS,
A10070:
PEQ-05.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Copra Grinder improvement (Existing) - RFQ
548 PEQ-17.RFQ Cooling tower system - RFQ PEQ-17 6 Oct-31-24 A Nov-07-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-17.TBE:
FS 5, FS,
A10070:
PEQ-17.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Cooling tower system - RFQ
549 PEQ-11.RFQ Processing Pump (New+ Existing) - RFQ PEQ-11 6 Oct-31-24 A Nov-07-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-11.TBE:
FS 5, FS,
A10070:
PEQ-11.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Processing Pump (New+ Existing) - RFQ
550 PEQ-19.RFQ Ship Loader - RFQ PEQ-19 1 Nov-07-24 A Nov-07-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-19.TBE:
FS 5, FS,
A10070:
PEQ-19.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Ship Loader - RFQ
551 UEQ-02.RFQ Purified water package improvement(Existing)- RFQ UEQ-02 10 Oct-28-24 A Nov-08-24 A A10950: FS UEQ-02.TBE: FS, UEQ-02.BQ: FS, A15570: FS Purified water package improvement(Existing)- RFQ
552 PEQ-08.RFQ Expeller improvement(Existing) - RFQ PEQ-08 6 Nov-01-24 A Nov-08-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-08.TBE:
FS 5, FS,
A10070:
PEQ-08.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Expeller improvement(Existing) - RFQ
553 ES-06.RFQ Geo technical Investigation - RFQ ES-06 6 Nov-01-24 A Nov-08-24 A A2280: FS 10 ES-06.TBE: FS Geo technical Investigation - RFQ
554 PEQ-16.RFQ Cyclone System - RFQ PEQ-16 4 Nov-06-24 A Nov-11- 24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-16.TBE:
FS 5, FS,
A10070:
PEQ-16.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Cyclone System - RFQ
555 PEQ-09.RFQ Individual Cookers/Centralized (New) - RFQ PEQ-09 2 Nov-08-24 A Nov-11- 24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-09.TBE:
FS 5, FS,
A10070:
PEQ-09.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Individual Cookers/Centralized (New) - RFQ
556 PEQ-10.RFQ Centralized cooker improvement (Existing) - RFQ PEQ-10 7 Nov-01-24 A Nov-11- 24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-10.TBE:
FS 5, FS,
A10070:
PEQ-10.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Centralized cooker improvement (Existing) - RFQ
557 ES-03.RFQ Thermax Boiler Service - RFQ ES-03 5 Nov-06-24 Nov-12-24 P3-1024: FS 70 ES-03.TBE: FS, ES-03.BQ: FS 67 Thermax Boiler Service - RFQ
558 PEQ-13.RFQ Process Cooler Equipment (New+Existing) - RFQ PEQ-13 14 Oct-25-24 A Nov-13-24 A A2282: FS 5, A9720: FS 5, A10310:
PEQ-13.TBE:
FS 5, FS,
A10070:
PEQ-13.BQ:
FS 5, A10950:
FS FS 5, A11553: FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Process Cooler Equipment (New+Existing) - RFQ
559 IT-01. RFQ IT Hardware - RFQ IT-01 5 Nov-07-24 Nov-13-24 A2286: FS 5 IT-01.TBE: FS, IT-01.BQ: FS 66 IT Hardware - RFQ
560 IT-02. RFQ IT Software/Applications - RFQ IT-01 5 Nov-07-24 Nov-13-24 A2286: FS 5 IT-02.TBE: FS, IT-02.BQ: FS 66 IT Software/Applications - RFQ
561 PEQ-04.RFQ Bucket Elevator (New) - RFQ PEQ-04 5 Nov-07-24 Nov-13-24 A2282: FS 5, A9720: FS 5, A10310:
PEQ-04.TBE:
FS 5, FS,
A10070:
PEQ-04.BQ:
FS 5, A10950:
FS FS 5, A11553: 66
FS 5, A11973: FS 5, A12503: FS 5, A12853: FS 5, A13058: FS 5 Bucket Elevator (New) - RFQ
562 PEQ-14.RFQ Jetty Conveyor System (New) - RFQ PEQ-14 5 Nov-07-24 Nov-13-24 A12503: FS 5 PEQ-14.TBE: FS, PEQ-14.BQ: FS 66 Jetty Conveyor System (New) - RFQ
563 PEQ-15.RFQ Jetty Crane (New) - RFQ PEQ-15 5 Nov-07-24 A Nov-13-24 A12503: FS 5 PEQ-15.TBE: FS, PEQ-15.BQ: FS 66 Jetty Crane (New) - RFQ
564 MEQ-02.RFQ Maintenance Equipment Package (New) - RFQ MEQ-02 5 Nov-08-24 A Nov-14-24 A11593: FS MEQ-02.TBE: FS, MEQ-02.BQ: FS 65 Maintenance Equipment Package (New) - RFQ
565 OEQ-01.RFQ Admin Office Furniture - RFQ QEQ-01 5 Nov-08-24 A Nov-14-24 A9400: FS OEQ-01.BQ: FS 65 Admin Office Furniture - RFQ
566 LEQ-01.RFQ Lab Equipment (New) - RFQ LEQ-01 5 Nov-18-24 Nov-22-24 A9410: FS LEQ-01.TBE: FS, LEQ-01.BQ: FS 59 Lab Equipment (New) - RFQ
567 EEQ-03.RFQ Motor(New) for retrofit equipment - RFQ EEQ-03 5 Nov-18-24 Nov-22-24 A15490: FS, A15500: FS, A15510:
EEQ-03.BQ:
FS, A15520:
FS, EEQ-03.TBE:
FS, A15530:
FSFS, A15540: FS, A15550:
59 FS, A15560: FS Motor(New) for retrofit equipment - RFQ
568 INS-01.RFQ Instrument (New) - RFQ INS-01 5 Nov-20-24 Nov-26-24 A2284: FS 4, A9580: FS 4, A10220:
INS-01.TBE:
FS 4,FS,
A9980:
INS-01.BQ:
FS 4, A10860:
FS FS 4, A11508: FS
574, A11928: FS 4, A12458: FS 4, A12808: FS 4, A13013: FS 4 Instrument (New) - RFQ
569 EEQ-01.RFQ HV+Tr ansformer (New) - RFQ EEQ-01 5 Nov-21-24 Nov-27-24 A2289: FS, A9600: FS, A10240:
EEQ-01.TBE:
FS, A10000:
FS,FS,
EEQ-01.BQ:
A10880: FS,
FS A11518: FS, A11938:
56 FS, A12468: FS, A12818: FS, A13023: FS HV+Tr ansformer (New) - RFQ
570 EEQ-02.RFQ MCC (New) - RFQ EEQ-02 5 Nov-21-24 Nov-27-24 A2289: FS, A9600: FS, A10240:
ES-02.RFQ:
FS, A10000:
SS 10,
FS,EEQ-02.TBE:
A10880: FS, FS,
A11518:
EEQ-02.BQ:
FS, A11938:
FS
56 FS, A12468: FS, A12858: FS, A13023: FS MCC (New) - RFQ
571 ACS-1.RFQ Automation(New) - RFQ ACS-01 5 Nov-22-24 Nov-28-24 A10230: FS 5 ACS-1.BQ: FS, ACS-01.TBE: FS 55 Automation(New) - RFQ
572 CSA-02.RFQ CSA Construction (GC) - RFQ CSA-02 5 Dec-02-24 Dec-06-24 A2292: FS, A9680: FS, A10030:
CSA-02.TBE:
FS, A10270:
FS,FS,
CSA-02.BQ:
A10910: FS
FS- 20, A11533: FS, A11953:
49 FS, A12483: FS, A12833: FS, A13038: FS, A9250: FS CSA Construction (GC) - RFQ
573 MEPI-01.RFQ MEPI (Mechanical&Piping) Construction (GC) - RFQ MEPI-01 5 Dec-02-24 Dec-06-24 A2291: FS, A9670: FS, A10020:
MEPI-01.TBE:
FS, A10260:
FS,FS,
MEPI-01.BQ:
A10900: FSFS
- 20, A11528: FS, A11948:
49 FS, A12478: FS, A12828: FS, A13033: FS MEPI (Mechanical&Piping) Construction (GC) - RFQ
574 MEPI-02.RFQ EAI Installation (GC) - RFQ MEPI-02 5 Dec-02-24 Dec-06-24 A9670: FS, A10020: FS, A10260:
MEPI-02.TBE:
FS, A10900:
FS, FS
MEPI-02.BQ:
-20, A11528:
FS FS, A11948: FS, A12478:
49 FS, A12828: FS, A13033: FS EAI Installation (GC) - RFQ
575 CSA-01.RFQ Misc. Construction - RFQ CSA-01 5 Dec-02-24 Dec-06-24 A9680: FS, A10030: FS, A10270:
CSA-01.TBE:
FS, A10910:
FS, CSA-01.BQ:
FS -20, A11533:
FS FS, A11953: FS, A12483:
49 FS, A12833: FS, A13038: FS Misc. Construction - RFQ
576 FF-01.RFQ Fire Fighting - RFQ FF-01 5 Dec-02-24 Dec-06-24 A2292: FS, A9680: FS, A10030:
FF-01.TBE:
FS, A10270:
FS, FF-01.BQ:
FS, A10910:
FS FS - 20, A11533: FS, A11953:
49 FS, A12483: FS, A12833: FS, A13038: FS Fire Fighting - RFQ
577 CSA-03-RFQ Jetty Improvement & Construction - RFQ CSA-03 5 Dec-10-24 Dec-16-24 A13178: FS, A13183: FS, A13143:
CSA-03.TBE:
FS, A13148:
FS FS, A13208: FS, A13213: FS 134 Jetty Improvement & Construction - RFQ
578 Budgetary Quotation and Clarificaiton Dec-20-24, Budgetary Quotation and Clarificaiton
579 PEQ-18.BQ New Verti cal filter - Budgetary Quote PEQ-18 10 Nov-05-24 Nov-18-24 PEQ-18.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 73 New Verti cal filter - Budgetary Quote
580 PEQ-03.BQ Copra Dumping Station package (New) - Budgetary Quote PEQ-03 10 Nov-06-24 Nov-19-24 PEQ-03.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 72 Copra Dumping Station package (New) - Budgetary Quote
581 PEQ-01.BQ Air Compressor (New) - Budgetary Quote PEQ-01 10 Nov-07-24 Nov-20-24 PEQ-01.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 71 Air Compressor (New) - Budgetary Quote
582 PEQ-05.BQ Copra Grinder improvement (Existing) - Budgetary Quote PEQ-05 10 Nov-08-24 Nov-21-24 PEQ-05.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 70 Copra Grinder improvement (Existing) - Budgetary Quote
583 PEQ-17.BQ Cooling tower system - Budgetary Quote PEQ-17 10 Nov-08-24 Nov-21-24 PEQ-17.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 70 Cooling tower system - Budgetary Quote
584 PEQ-11.BQ Processing Pump (New+ Existing) - Budgetary Quote PEQ-11 10 Nov-08-24 Nov-21-24 PEQ-11.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 70 Processing Pump (New+ Existing) - Budgetary Quote
585 PEQ-19.BQ Ship Loader - Budgetary Quote PEQ-19 10 Nov-08-24 Nov-21-24 PEQ-19.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 70 Ship Loader - Budgetary Quote
586 PEQ-08.BQ Expeller improvement(Existing) - Budgetary Quote PEQ-08 10 Nov-11- 24 Nov-22-24 PEQ-08.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 69 Expeller improvement(Existing) - Budgetary Quote
587 UEQ-02.BQ Purified water package improvement (Existing) - Budgetary Quote UEQ-02 10 Nov-11- 24 Nov-22-24 UEQ-02.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 69 Purified water package improvement (Existing) - Budgetary Quote
588 PEQ-16.BQ Cyclone System - Budgetary Quote PEQ-16 10 Nov-12-24 Nov-25-24 PEQ-16.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 68 Cyclone System - Budgetary Quote
589 PEQ-09.BQ Individual Cookers/Centralized (New) - Budgetary Quote PEQ-09 10 Nov-12-24 Nov-25-24 PEQ-09.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 68 Individual Cookers/Centralized (New) - Budgetary Quote
590 PEQ-10.BQ Centralized cooker improvement (Existing) - Budgetary Quote PEQ-10 10 Nov-12-24 Nov-25-24 PEQ-10.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 68 Centralized cooker improvement (Existing) - Budgetary Quote
591 ES-03.BQ Thermax Boiler Service - Budgetary Quote ES-03 10 Nov-13-24 Nov-26-24 ES-03.RFQ: FS P3-1005: FF 5 67 Thermax Boiler Service - Budgetary Quote
592 IT-01. BQ IT Hardware - Budgetary Quote IT-01 10 Nov-14-24 Nov-27-24 IT-01.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 66 IT Hardware - Budgetary Quote
593 IT-02. BQ IT Software/Applications - Budgetary Quote IT-01 10 Nov-14-24 Nov-27-24 IT-02.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 66 IT Software/Applications - Budgetary Quote
594 PEQ-04.BQ Bucket Elevator (New) - Budgetary Quote PEQ-04 10 Nov-14-24 Nov-27-24 PEQ-04.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 66 Bucket Elevator (New) - Budgetary Quote
595 PEQ-13.BQ Process Cooler Equipment (New+Existing) - Process Equipment - Budgetary Quote PEQ-13 10 Nov-14-24 Nov-27-24 PEQ-13.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 66 Process Cooler Equipment (New+Existing) - Process Equipment - Budgetary Quote
596 PEQ-14.BQ Jetty Conveyor System (New) - Budgetary Quote PEQ-14 10 Nov-14-24 Nov-27-24 PEQ-14.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 66 Jetty Conveyor System (New) - Budgetary Quote
597 PEQ-15.BQ Jetty Crane (New) - Budgetary Quote PEQ-15 10 Nov-14-24 Nov-27-24 PEQ-15.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 66 Jetty Crane (New) - Budgetary Quote
598 MEQ-02.BQ Maintenance Equipment Package (New) - Budgetary Quote MEQ-02 10 Nov-15-24 Nov-28-24 MEQ-02.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 65 Maintenance Equipment Package (New) - Budgetary Quote
599 OEQ-01.BQ Admin Office Furniture - Budgetary Quote QEQ-01 10 Nov-15-24 Nov-28-24 OEQ-01.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 65 Admin Office Furniture - Budgetary Quote
600 EEQ-03.BQ Motor(New) - Budgetary Quote EEQ-03 10 Nov-25-24 Dec-06-24 EEQ-03.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 59 Motor(New) - Budgetary Quote
601 LEQ-01.BQ Lab Equipment (New) - Budgetary Quote LEQ-01 10 Nov-25-24 Dec-06-24 LEQ-01.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 59 Lab Equipment (New) - Budgetary Quote
602 INS-01.BQ Instrument (New) - Budgetary Quote INS-01 10 Nov-27-24 Dec-10-24 INS-01.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 57 Instrument (New) - Budgetary Quote
603 EEQ-01.BQ HV+Tr ansformer (New) - Budgetary Quote EEQ-01 10 Nov-28-24 Dec-11-24 EEQ-01.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 56 HV+Transformer (New) - Budgetary Quote
604 EEQ-02.BQ MCC (New) - Budgetary Quote EEQ-02 10 Nov-28-24 Dec-11-24 EEQ-02.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 56 MCC (New) - Budgetary Quote
605 ACS-1.BQ Automation(New) - Budgetary Quote ACS-01 10 Nov-29-24 Dec-12-24 ACS-1.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 55 Automation(New) - Budgetary Quote
606 CSA-02.BQ CSA Construction (GC) - Budgetar y Quote CSA-02 10 Dec-09-24 Dec-20-24 CSA-02.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 49 CSA Construction (GC) - Budgetar y Quote
607 MEPI-01.BQ MEPI (Mechanical&Piping) Construction (GC) - Budgetary Quote MEPI-01 10 Dec-09-24 Dec-20-24 MEPI-01.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 49 MEPI (Mechanical&Piping) Construction (GC) - Budgetary Quote
608 MEPI-02.BQ EAI Installation (GC) - Budgetary Quote MEPI-02 10 Dec-09-24 Dec-20-24 MEPI-02.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 49 EAI Installation (GC) - Budgetary Quote
609 CSA-01.BQ Misc. Construction - Budgetary Quote CSA-01 10 Dec-09-24 Dec-20-24 CSA-01.RFQ: FS P3-1005: FF 5, P3-1006: FF 3 49 Misc. Construction - Budgetary Quote
610 FF-01.BQ Fire Fighting - Budgetary Quote FF-01 10 Dec-09-24 Dec-20-24 FF-01.RFQ: FS P3-1006: FF 5, P3-1005: FF 5 49 Fire Fighting - Budgetary Quote
611 TBE Jan-06-25, TBE
Actual Work Critical Remaining Work Summary Page 3 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Project Herring Level 4/5 Master Schedule - Developing (No constraint) Herring L4/L5 Layout Nov-18-24 05:21
# Activity ID Activity Name PKG NO. At Completion Start Finish Predecessor Details Successor Details Total 2024 2025 2026 2027
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
612 ES-07.TBE Jetty Inspection & Assessment Servic e - TBE ES-07 15 Aug-14-24 Sep-03-24 ES-07.RFQ: FS ES-07.CBE: FS 131 Jetty Inspection & Assessment Servic e - TBE
613 ES-08.TBE Environmental Clearance Certificate - TBE ES-08 10 Sep-23-24 A Oct-04-24 ES-08.RFQ: FS ES-08.CBE: FS 0 Environmental Clearance Certificate - TBE
614 ES-06.TBE Geo technical Investigation - TBE ES-06 5 Nov-11- 24 Nov-15-24 ES-06.RFQ: FS ES-06.CBE: FS 140 Geo technical Investigation - TBE
615 PEQ-18.TBE New Verti cal filter- TBE PEQ-18 15 Nov-05-24 Nov-25-24 PEQ-18.RFQ: FS PEQ-18.CBE: FS 94 New Verti cal filter- TBE
616 PEQ-03.TBE Copra Dumping Stattion package (New) - TBE PEQ-03 15 Nov-06-24 Nov-26-24 PEQ-03.RFQ: FS PEQ-03.CBE: FS 133 Copra Dumping Stattion package (New) - TBE
617 PEQ-01.TBE Air compressor (New) - TBE PEQ-01 15 Nov-07-24 Nov-27-24 PEQ-01.RFQ: FS PEQ-01.CBE: FS 131 Air compressor (New) - TBE
618 PEQ-05.TBE Copra Grinder improvement (Existing)- TBE PEQ-05 15 Nov-08-24 Nov-28-24 PEQ-05.RFQ: FS PEQ-05.CBE: FS 86 Copra Grinder improvement (Existing)- TBE
619 PEQ-17.TBE Cooling tower system- TBE PEQ-17 15 Nov-08-24 Nov-28-24 PEQ-17.RFQ: FS PEQ-17.CBE: FS 86 Cooling tower system- TBE
620 PEQ-11.TBE Processing Pump (New+ Existing)- TBE PEQ-11 15 Nov-08-24 Nov-28-24 PEQ-11.RFQ: FS PEQ-11.CBE: FS 86 Processing Pump (New+ Existing)- TBE
621 PEQ-19.TBE Ship Loader- TBE PEQ-19 15 Nov-08-24 Nov-28-24 PEQ-19.RFQ: FS PEQ-19.CBE: FS 86 Ship Loader- TBE
622 PEQ-08.TBE Expeller improvement(Existing)- TBE PEQ-08 15 Nov-11- 24 Nov-29-24 PEQ-08.RFQ: FS PEQ-08.CBE: FS 85 Expeller improvement(Existing)- TBE
623 UEQ-02.TBE Purified water package improvement(Existing)- TBE UEQ-02 15 Nov-11- 24 Nov-29-24 UEQ-02.RFQ: FS UEQ-02.CBE: FS 129 Purified water package improvement(Existing)- TBE
624 EEQ-03.TBE Motor(New) for retrofit equipment - TBE EEQ-03 5 Nov-25-24 Nov-29-24 EEQ-03.RFQ: FS EEQ-03.CBE: FS 502 Motor(New) for retrofit equipment - TBE
625 PEQ-16.TBE Cyclone System - TBE PEQ-16 15 Nov-12-24 Dec-02-24 PEQ-16.RFQ: FS PEQ-16.CBE: FS 128 Cyclone System - TBE
626 PEQ-09.TBE Individual Cookers (New)- TBE PEQ-09 15 Nov-12-24 Dec-02-24 PEQ-09.RFQ: FS PEQ-09.CBE: FS 89 Individual Cookers (New)- TBE
627 PEQ-10.TBE Centralized cooker improvement(Existing)- TBE PEQ-10 15 Nov-12-24 Dec-02-24 PEQ-10.RFQ: FS PEQ-10.CBE: FS 84 Centralized cooker improvement(Existing)- TBE
628 ES-03.TBE Thermax Boiler Service - TBE ES-03 15 Nov-13-24 Dec-03-24 ES-03.RFQ: FS ES-03.CBE: FS 242 Thermax Boiler Service - TBE
629 IT-01. TBE IT Hardware - TBE IT-01 15 Nov-14-24 Dec-04-24 IT-01.RFQ: FS IT-01.CBE: FS 177 IT Hardware - TBE
630 PEQ-14.TBE Jetty Conveyor System - TBE PEQ-14 15 Nov-14-24 Dec-04-24 PEQ-14.RFQ: FS PEQ-14.CBE: FS 127 Jetty Conveyor System - TBE
631 PEQ-15.TBE Jetty Crane - TBE PEQ-15 15 Nov-14-24 Dec-04-24 PEQ-15.RFQ: FS PEQ-15.CBE: FS 127 Jetty Crane - TBE
632 PEQ-04.TBE Bucket Elevator - TBE PEQ-04 15 Nov-14-24 Dec-04-24 PEQ-04.RFQ: FS PEQ-04.CBE: FS 106 Bucket Elevator - TBE
633 PEQ-13.TBE Process Cooler Equipment (New+Existing)- TBE PEQ-13 15 Nov-14-24 Dec-04-24 PEQ-13.RFQ: FS PEQ-13.CBE: FS 126 Process Cooler Equipment (New+Existing)- TBE
634 IT-02. TBE IT Software/Applications - TBE IT-02 15 Nov-14-24 Dec-04-24 IT-02.RFQ: FS IT-02.CBE: FS 177 IT Software/Applications - TBE
635 MEQ-02.TBE Maintenance Equpment Package (New)- TBE MEQ-02 15 Nov-15-24 Dec-05-24 MEQ-02.RFQ: FS MEQ-02.CBE: FS 216 Maintenance Equpment Package (New)- TBE
636 LEQ-01.TBE Lab Equipments - TBE LEQ-01 15 Nov-25-24 Dec-13-24 LEQ-01.RFQ: FS LEQ-01.CBE: FS 100 Lab Equipments - TBE
637 INS-01.TBE Instrument (New) - TBE INS-01 15 Nov-27-24 Dec-17-24 INS-01.RFQ: FS INS-01.CBE: FS 73 Instrument (New) - TBE
638 EEQ-01.TBE HV+Tr ansformer (New) - TBE EEQ-01 15 Nov-28-24 Dec-18-24 EEQ-01.RFQ: FS EEQ-01.CBE: FS 83 HV+Transformer (New) - TBE
639 EEQ-02.TBE MCC (New) - TBE EEQ-02 15 Nov-28-24 Dec-18-24 EEQ-02.RFQ: FS EEQ-02.CBE: FS 72 MCC (New) - TBE
640 ACS-01.TBE Automation(New) - TBE ACS-01 15 Nov-29-24 Dec-19-24 ACS-1.RFQ: FS ACS-01.CBE: FS 206 Automation(New) - TBE
641 CSA-01.TBE Misc. Construction - TBE CSA-01 15 Dec-09-24 Dec-27-24 CSA-01.RFQ: FS CSA-01.CBE: FS 114 Misc. Construction - TBE
642 CSA-02.TBE CSA Construction (GC) - TBE CSA-02 15 Dec-09-24 Dec-27-24 CSA-02.RFQ: FS CSA-02.CBE: FS 114 CSA Const ruction (GC) - TBE
643 MEPI-01.TBE MEPI (Mechanical&Piping) Construction (GC) - TBE MEPI-01 15 Dec-09-24 Dec-27-24 MEPI-01.RFQ: FS MEPI-01.CBE: FS 199 MEPI (Mechanical&Piping) Construction (GC) - TBE
644 MEPI-02.TBE EAI Installation (GC) - TBE MEPI-02 15 Dec-09-24 Dec-27-24 MEPI-02.RFQ: FS MEPI-02.CBE: FS 249 EAI Installation (GC) - TBE
645 FF-01.TBE Fire Fighting - TBE FF-01 15 Dec-09-24 Dec-27-24 FF-01.RFQ: FS FF-01.CBE: FS 249 Fire Fighting - TBE
646 CSA-03.TBE Jetty improvement and construction - TBE CSA-03 15 Dec-17-24 Jan-06-25 CSA-03-RFQ: FS CSA-03.CBE: FS 134 Jetty improvement and construction - TBE
647 CBE Jan-27-25, CBE
648 ES-01.CBE ESP (Basic and Detial Design) - CBE ES-01 136 Jan-10-24 A Jul-17-24 A ES-01.TBE: FS ES-01.PO: FS ESP (Basic and Detial Design) - CBE
649 ES-07.CBE Jetty Inspection & Assessment Servic e - CBE ES-07 15 Sep-04-24 Sep-24-24 ES-07.TBE: FS ES-07.PO: FS 131 Jetty Inspection & Assessment Servic e - CBE
650 ES-08.CBE Environmental Clearance Certificate - CBE ES-08 10 Oct-07-24 Oct-18-24 ES-08.TBE: FS ES-08.PO: FS 0 Environmental Clearance Certificate - CBE
651 ES-06.CBE Geo technical Investigation - CBE ES-06 10 Nov-18-24 Nov-29-24 ES-06.TBE: FS ES-06.PO: FF 140 Geo technical Investigation - CBE
652 PEQ-18.CBE New Verti cal filter- CBE PEQ-18 10 Nov-26-24 Dec-09-24 PEQ-18.TBE: FS PEQ-18.PO: FS 94 New Verti cal f ilter- CBE
653 PEQ-03.CBE Copra Dumping Stattion package (New) - CBE PEQ-03 10 Nov-27-24 Dec-10-24 PEQ-03.TBE: FS PEQ-03.PO: FS 133 Copra Dumping Stattion package (New) - CBE
654 PEQ-01.CBE Air compressor (New) - CBE PEQ-01 10 Nov-28-24 Dec-11-24 PEQ-01.TBE: FS PEQ-01.PO: FS 131 Air compressor (New) - CBE
655 PEQ-05.CBE Copra Grinder improvement (Existing)- CBE PEQ-05 10 Nov-29-24 Dec-12-24 PEQ-05.TBE: FS PEQ-05.PO: FS 86 Copra Grinder improvement (Existing)- CBE
656 PEQ-17.CBE Cooling tower system- CBE PEQ-17 10 Nov-29-24 Dec-12-24 PEQ-17.TBE: FS PEQ-17.PO: FS 86 Cooling tower system- CBE
657 PEQ-11.CBE Processing Pump (New+ Existing)- CBE PEQ-11 10 Nov-29-24 Dec-12-24 PEQ-11.TBE: FS PEQ-11.PO: FS 86 Processing Pump (New+ Existing)- CBE
658 PEQ-19.CBE Ship Loader- CBE PEQ-19 10 Nov-29-24 Dec-12-24 PEQ-19.TBE: FS PEQ-19.PO: FS 86 Ship Loader- CBE
659 PEQ-08.CBE Expeller improvement(Existing)- CBE PEQ-08 10 Dec-02-24 Dec-13-24 PEQ-08.TBE: FS PEQ-08.PO: FS 85 Expeller improvement(Existing)- CBE
660 UEQ-02.CBE Purified water package improvement(Existing)- CBE UEQ-02 10 Dec-02-24 Dec-13-24 UEQ-02.TBE: FS UEQ-02.PO: FS 129 Purified water package improvement(Existing)- CBE
661 EEQ-03.CBE Motor(New) for retrofit equipment - CBE EEQ-03 10 Dec-02-24 Dec-13-24 EEQ-03.TBE: FS EEQ-03.PO: FS 502 Motor(New) for retrofit equipment - CBE
662 PEQ-16.CBE Cyclone System - CBE PEQ-16 10 Dec-03-24 Dec-16-24 PEQ-16.TBE: FS PEQ-16.PO: FS 128 Cyclone System - CBE
663 PEQ-09.CBE Individual Cookers (New)- CBE PEQ-09 10 Dec-03-24 Dec-16-24 PEQ-09.TBE: FS PEQ-09.PO: FS 89 Individual Cookers (New)- CBE
664 PEQ-10.CBE Centralized cooker improvement(Existing)- CBE PEQ-10 10 Dec-03-24 Dec-16-24 PEQ-10.TBE: FS PEQ-10.PO: FS 84 Centralized cooker improvement(Existing)- CBE
665 ES-03.CBE Thermax Boiler Service - CBE ES-03 10 Dec-04-24 Dec-17-24 ES-03.TBE: FS ES-03.PO: FS 242 Thermax Boiler Service - CBE
666 IT-01. CBE IT Hardware - CBE IT-01 10 Dec-05-24 Dec-18-24 IT-01.TBE: FS IT-01.PO: FS 177 IT Hardware - CBE
667 PEQ-14.CBE Jetty Conveyor System - CBE PEQ-14 10 Dec-05-24 Dec-18-24 PEQ-14.TBE: FS PEQ-14.PO: FS 127 Jetty Conveyor System - CBE
668 PEQ-15.CBE Jetty Crane - CBE PEQ-15 10 Dec-05-24 Dec-18-24 PEQ-15.TBE: FS PEQ-15.PO: FS 127 Jetty Crane - CBE
669 PEQ-04.CBE Bucket Elevator - CBE PEQ-04 10 Dec-05-24 Dec-18-24 PEQ-04.TBE: FS PEQ-04.PO: FS 106 Bucket Elevator - CBE
670 PEQ-13.CBE Process Cooler Equipment (New+Existing)- CBE PEQ-13 10 Dec-05-24 Dec-18-24 PEQ-13.TBE: FS PEQ-13.PO: FS 126 Process Cooler Equipment (New+Existing)- CBE
671 IT-02. CBE IT Software/Applications - CBE IT-02 10 Dec-05-24 Dec-18-24 IT-02.TBE: FS IT-02.PO: FS 177 IT Software/Applications - CBE
672 MEQ-02.CBE Maintenance Equpment Package (New)- CBE MEQ-02 10 Dec-06-24 Dec-19-24 MEQ-02.TBE: FS MEQ-02.PO: FS 216 Maintenance Equpment Package (New)- CBE
673 LEQ-01.CBE Lab Equipments - CBE LEQ-01 10 Dec-16-24 Dec-27-24 LEQ-01.TBE: FS LEQ-01.PO: FS 100 Lab Equipments - CBE
674 INS-01.CBE Instrument (New) - CBE INS-01 10 Dec-18-24 Dec-31-24 INS-01.TBE: FS INS-01.PO: FS 73 Instrument (New) - CBE
675 EEQ-01.CBE HV+Tr ansformer (New) - CBE EEQ-01 10 Dec-19-24 Jan-01-25 EEQ-01.TBE: FS EEQ-01.PO: FS 83 HV+Tr ansformer (New) - CBE
676 EEQ-02.CBE MCC (New) - CBE EEQ-02 10 Dec-19-24 Jan-01-25 EEQ-02.TBE: FS EEQ-02.PO: FS 72 MCC (New) - CBE
677 ACS-01.CBE Automation(New) - CBE ACS-01 10 Dec-20-24 Jan-02-25 ACS-01.TBE: FS ACS-01.PO: FS 206 Automation(New) - CBE
678 CSA-01.CBE Misc. Construction - CBE CSA-01 15 Dec-30-24 Jan-17-25 CSA-01.TBE: FS CSA-01.PO: FS 114 Misc. Construction - CBE
679 CSA-02.CBE CSA Construction (GC) - CBE CSA-02 15 Dec-30-24 Jan-17-25 CSA-02.TBE: FS CSA-02.PO: FS 114 CSA Construction (GC) - CBE
680 MEPI-01.CBE MEPI (Mechanical&Piping) Construction (GC) - CBE MEPI-01 15 Dec-30-24 Jan-17-25 MEPI-01.TBE: FS MEPI-01.PO: FS 199 MEPI (Mechanical&Piping) Construction (GC) - CBE
681 MEPI-02.CBE EAI Installation (GC) - CBE MEPI-02 15 Dec-30-24 Jan-17-25 MEPI-02.TBE: FS MEPI-02.PO: FS 249 EAI Installation (GC) - CBE
682 FF-01.CBE Fire Fighting - CBE FF-01 15 Dec-30-24 Jan-17-25 FF-01.TBE: FS FF-01.PO: FS 249 Fire Fighting - CBE
683 CSA-03.CBE Jetty improvement and construction - CBE CSA-03 15 Jan-07-25 Jan-27-25 CSA-03.TBE: FS CSA-03.PO: FS 134 Jetty improvement and construction - CBE
684 PO Nov-29-24, PO
685 ES-01.PO ESP (Basic and Detial Design) - PO ES-01 20 Jul-18-24 A Aug-14-24 A ES-01.CBE: FS A2281: FS, A9570: FS, A9970: FS, A10210: FS, A10850: FS, A11503: FS, A11923: FS, A12453: FS, A12803: FS, A13008: FS, A9340: FS 22 ESP (Basic and Detial Design) - PO
686 ES-07.PO Jetty Inspection & Assessment Servic e - PO ES-07 10 Sep-25-24 Oct-08-24 ES-07.CBE: FS A12533: FS 131 Jetty Inspection & Assessment Servic e - PO
687 ES-08.PO Environmental Clearance Certificate - PO ES-08 10 Oct-21-24 Nov-01-24 ES-08.CBE: FS ECC.01: FS 0 Environmental Clearance Certificate - PO
688 ES-06.PO Geo technical Investigation - PO ES-06 5 Nov-25-24 Nov-29-24 ES-06.CBE: FF A15400: FS, A15450: FS 140 Geo technical Investigation - PO
689 PDP IV Execution ( Y0 Scope) May-15-26, PDP IV Execution (Y0 Scope)
690 Build Project Management Apr-21-25, Build Project Management
691 A1650 PDPIV - Kick-off Meeting 1 Feb-03-25 Feb-03-25 P3-1010: FS, P3-15: FS, P3-1050:
P4a-01:FS
FS, MEQ-02.PO: FS, UEQ-02.PO: FS, PEQ-13.PO:
49 FS, PEQ-19.PO: FS, PEQ-11.PO: FS, PEQ-10.PO: FS, PEQ-09.PO: FS, PEQ-08.PO: FS, PEQ- 18.PO: FS, PEQ- 17.PO: FS, PEQ-05.PO: FS, PEQ-04.PO: FS, PEQ-15.PO: FS, PEQ-14.PO: FS, CSA-03.PO: FS 22, ES-03.PO: FS, IT-01.PO: FS, MEQ-01.PO: FS, LEQ- 01.PO: FS, PEQ-03.
PDPIVPO:- FS,
Kick-off
PEQ-16.PO:
Meeting FS, FF-01.PO: FS, PEQ-01.PO: FS, MEPI-02.PO: FS 22, ACS-01.PO: FS, INS-01.PO: FS, EEQ-02.PO: FS, EEQ-01.PO: FS, MEPI-01.PO: FS 22, CSA-02.PO: FS 22, ES-02.PO: FS, CSA-01.PO: FS 22, IT-02.PO: FS, MEQ-01.RFQ: FS, ES-02.RFQ: FS, EEQ-03.PO: FS
692 A1660 PDPIV - Project Start-up ( Year 0 Scope) 5 Apr-15-25 Apr-21-25 ES-02.PO: FS 541 PDPIV - Project Start-up ( Year 0 Scope)
693 Business
694 Land&Utility Tie-in Jan-05-24, Land&Utility Tie-in
695 A15470 Land handover 5 Jan-01-24 Jan-05-24 P4-2110: FS Land
397 handover
696 A15480 Utility Ti e-in Condition Available 5 Jan-01-24 Jan-05-24 P4-2110: FS Utility
397 Ti e-in Condition Available
697 Permit Jul-10-25, Permit
698 A15420 Water Permit (Need to update by Permi t Lead)??? Build Team 0 Jan-01-24 Water
882Permit (Need to update by Permi t Lead)???
699 A15440 Waster Water Disc harge Permit (Need to update by Permit Lead)??? Build Team 0 Jan-01-24 Waster
882Water Disc harge Permit (Need to update by Permit Lead)???
700 A1680 ECC Awarded ES-08 0 Jun-10-25 ECC.03: FS P4-2305: FS, P4-2270: FS, P4-2170: FS, P4-2265: FS,
22 P4-2100: FF, P4-2665: FS, P4- 2315: FS, P4-2350: FS, P4-2395: FS, P4-2430: FS, P4-2355: FS, P4-2390: FS, P4-2470: FS, P4-2435: FS, P4-2480: FS, P4- 2515: FS, P4-2525: FS, P4-2560: FS, P4-2650: FS, P4-2580: FS ECC Awarded
701 A1640 Build Permit Awarded Build Team 0 Jul-10-25 A15410: FS P4-2305: FS, P4-2270: FS, P4-2170: FS, P4-2265: FS,0 P4-2100: FF, P4-2665: FS, P4- 2315: FS, P4-2350: FS, P4-2430: FS, P4-2395: FS, P4-2355: FS, P4-2390: FS, P4-2470: FS, P4-2435: FS, P4-2480: FS, P4- 2515: FS, P4-2560: FS, P4-2525: FS, P4-2580: FS, P4-2650: FS Build Permit Awarded
702 During contruction
703 Engineering Apr-21-25, Engineering
704 G0. General Apr-21-25, G0. General
705 A13290 Construction Drawings ??? 10 Apr-08-25 Apr-21-25 A2302: FS, INS-01.DW G: FF
P4-2100:
15 FF 10 71 Construction Drawings
706 B0. Administ rative Buildings Apr-21-25, B0. Admi ni strative Buildings
707 A15280 Construction Drawings 10 Apr-08-25 Apr-21-25 LEQ-01.DW G: FF 15, A9370:
P4-2170:
FS FF 10 74 Construction Drawings
708 B1. Dry Copra Warehouse Apr-21-25, B1. Dry Copra Warehouse
709 A15290 Construction Drawings 10 Apr-08-25 Apr-21-25 PEQ-16.DWG: FF 15, A9740:
P4-2235:
FS, PEQ-04.DWG:
FF 10 FF 10, INS-01.DWG: FF 15 93 Construction Drawings
710 B2. Oil Mill Operations Apr-21-25, B2. Oil Mill Operations
711 A15300 Construction Drawings 10 Apr-08-25 Apr-21-25 A10330: FS, EEQ-02.DWG:P4-2270:
FF 15, PEQ-05.DWG:
FS 10 FF 15, PEQ-17.DWG: FF 15, 49
PEQ-08.DW G: FF 15, PEQ-10.DWG: FF 15, PEQ-19.DWG: FF 15, PEQ-11.DWG: FF 15, PEQ-18.DWG: FS, PEQ-09.DWG: FS, INS-01.DWG: FF 15 Construction Drawings
712 B3. Finish Good Copra Warehouse Apr-21-25, B3. Finish Good Copra Warehouse
713 A15305 Construction Drawings 10 Apr-08-25 Apr-21-25 A10090: FS, PEQ-04.DWG:P4-2315:
FF 10, INS-01.DWG:
FF 10 FF 15 88 Construction Drawings
714 U0. Utilities Apr-21-25, U0. Utilities
715 A15310 Construction Drawings 10 Apr-08-25 Apr-21-25 A10970: FS, UEQ-02.DWG:P4-2395:
FF 15, PEQ-13.DWG:
FF 10 FF 15, INS-01.DWG: FF 15 93 Construction Drawings
716 U1. Utility Building Apr-14-25, U1. Utility Building
717 A15315 Construction Drawings 10 Apr-01-25 Apr-14-25 A11563: FS, PEQ-01.DWG:P4-2355:
FS FF 10 93 Construction Drawings
718 P1. Dumping Area Apr-14-25, P1. Dumping Area
719 A15320 Construction Drawings 10 Apr-01-25 Apr-14-25 A11983: FS, PEQ-16.DWG:P4-2435:
FF 10, PEQ-03.DW
FF 10 G: FF 10, PEQ-04.DWG: FF 10, 94
INS-01.DWG: FF 10 Construction Drawings
720 J0. Jetty Apr-21-25, J0. Jetty
721 A15325 Construction Drawings 10 Apr-08-25 Apr-21-25 PEQ-15.DWG: FF 15, PEQ-14.DWG:
P4-2480: FF
FF10
15, A12513: FS, INS-01.DW G: FF 15 94 Construction Drawings
722 T1. Tank Farm A Apr-21-25, T1. Tank Farm A
723 A15330 Construction Drawings 10 Apr-08-25 Apr-21-25 A12863: FS, INS-01.DWG: FF
P4-2525:
15 FF 10 68 Construction Drawings
724 T2. Tank Farm B Apr-21-25, T2. Tank Farm B
725 A15335 Construction Drawings 10 Apr-08-25 Apr-21-25 A13068: FS, PEQ-04.DWG:P4-2580:
FF 10, INS-01.DWG:
FF 10 FF 15 68 Construction Drawings
726 Procurement Dec-18-25, Procurement
727 RFQ Feb-17-25, RFQ
728 ES-02.RFQ Arc Flash Analysis Service - RFQ ES-02 10 Feb-04-25 Feb-17-25 EEQ-02.RFQ: SS 10, A1650:ES-02.TBE:
FS FS 541 Arc Flash Analysis Service - RFQ
729 MEQ-01.RFQ Heavy Equipment (New) - RFQ MEQ-01 10 Feb-04-25 Feb-17-25 A11593: FS, A1650: FS MEQ-01.TBE: FS 144 Heavy Equipment (New) - RFQ
730 TBE Mar-10-25, TBE
731 ES-02.TBE Arc flash analysis Serivce - TBE ES-02 15 Feb-18-25 Mar-10-25 ES-02.RFQ: FS ES-02.CBE: FS 541 Arc flash analysis Serivce - TBE
732 MEQ-01.TBE Heavey Equipments (New) - TBE MEQ-01 15 Feb-18-25 Mar-10-25 MEQ-01.RFQ: FS MEQ-01.CBE: FS 144 Heavey Equipments (New) - TBE
733 CBE Mar-31-25, CBE
734 ES-02.CBE Arc flash analysis Serivce - CBE ES-02 15 Mar-11-25 Mar-31-25 ES-02.TBE: FS ES-02.PO: FS 541 Arc flash analysis Serivce - CBE
735 MEQ-01.CBE Heavey Equipments (New) - CBE MEQ-01 15 Mar-11-25 Mar-31-25 MEQ-01.TBE: FS MEQ-01.PO: FS 144 Heavey Equipments (New) - CBE
736 PO Apr-14-25, PO
737 EEQ-01.PO HV+Tr ansformer (New) - PO EEQ-01 10 Feb-04-25 Feb-17-25 A1650: FS, EEQ-01.CBE: FS
EEQ-01.DEL: FS 60 HV+Tr ansformer (New) - PO
738 EEQ-02.PO MCC (New) - PO EEQ-02 10 Feb-04-25 Feb-17-25 A1650: FS, EEQ-02.CBE: FS
EEQ-02.DEL: FS, EEQ-02.DWG: FS 49 MCC (New) - PO
739 INS-01.PO Instrument (New) - PO INS-01 10 Feb-04-25 Feb-17-25 A1650: FS, INS-01.CBE: FSINS-01.DEL: FS, INS-01.DW G: FS, INS-01.DEL5: FS,49INS-01.DEL10: FS, INS-01.DEL15: FS, INS-01.DEL20: FS, INS-01.DEL25: FS, INS-01.DEL30: FS, INS-01.DEL35: FS, INS-01.DEL40: FS, INS-01.DEL45: FS, INS-01.DEL50: FS, INS-01.DEL55: FS, INS-01.DEL60: FS, INS-01.DEL65: FS, INS-01.DEL70: FS, INS-01.DEL80: FS, INS-01.DEL85: FS,Instrument
INS-01.DEL90:
(New)FS
- PO
740 ACS-01.PO Automation(New) - PO ACS-01 10 Feb-04-25 Feb-17-25 A1650: FS, ACS-01.CBE: FSP4-2310: FS 184 Automation(New) - PO
741 PEQ-01.PO Air compressor (New) - PO PEQ-01 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-01.CBE: FS
PEQ-01.DEL: FS, PEQ-01.DWG: FS 93 Air compressor (New) - PO
742 FF-01.PO Fire Fighting - PO FF-01 10 Feb-04-25 Feb-17-25 A1650: FS, FF-01.CBE: FS A13310: FS, A14475: FS, A14650: FS, A14700: FS, 238
A15005: FS, A15110: FS, A15255: FS, A13535: FS, A13480: FS, A15340: FS, A15345: FS, A15350: FS, A15355: FS, P4-2685: FS 5, P4-2700: FS 5, P4-2705: FS 5 Fire Fighting - PO
743 MEQ-02.PO Maintenance Equpment Package (New)- PO MEQ-02 10 Feb-04-25 Feb-17-25 A1650: FS, MEQ-02.CBE: FS
MEQ-02.DEL: FS 184 Maintenance Equpment Package (New)- PO
744 PEQ-16.PO Cyclone System - PO PEQ-16 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-16.CBE: FS
PEQ-16.DEL: FS, PEQ-16.DWG: FS, PEQ-16.DEL5:93
FS, PEQ-16.DEL10: FS, PEQ-16.DEL15: FS Cyclone System - PO
745 PEQ-03.PO Copra Dumping Stattion package (New) - PO PEQ-03 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-03.CBE: FS
PEQ-03.DEL: FS, PEQ-03.DWG: FS 94 Copra Dumping Stattion package (New) - PO
746 LEQ-01.PO Lab Equipments - PO LEQ-01 10 Feb-04-25 Feb-17-25 A1650: FS, LEQ-01.CBE: FSLEQ-01.DWG: FS, LEQ-01.DEL: FS 74 Lab Equipments - PO
747 IT-01. PO IT Hardware - PO IT-01 10 Feb-04-25 Feb-17-25 A1650: FS, IT-01.CBE: FS P4-2150: FS, P4-2220: FS 5 144 IT Hardware - PO
748 ES-03.PO Thermax Boiler Service - PO ES-03 10 Feb-04-25 Feb-17-25 A1650: FS, ES-03.CBE: FS A13955: FS, A14130: FS, A14245: FS 208 Thermax Boiler Service - PO
749 PEQ-14.PO Jetty Conveyor System - PO PEQ-14 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-14.CBE: FS
PEQ-14.DEL: FS, PEQ-14.DWG: FS 94 Jetty Conveyor System - PO
750 PEQ-15.PO Jetty Crane - PO PEQ-15 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-15.CBE: FS
PEQ-15.DEL: FS, PEQ-15.DWG: FS 94 Jetty Crane - PO
751 PEQ-04.PO Bucket Elevator - PO PEQ-04 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-04.CBE: FS
PEQ-04.DEL: FS, PEQ-04.DWG: FS, PEQ-04.DEL5:73
FS, PEQ-04.DEL10: FS, PEQ-04.DEL15: FS, PEQ-04.DEL20: FS Bucket Elevator - PO
752 PEQ-05.PO Copra Grinder improvement (Existing)- PO PEQ-05 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-05.CBE: FS
PEQ-05.DWG: FS, A13785: FS, A15360: FS, A15365:49FS, A15370: FS Copra Grinder improvement (Existing)- PO
753 PEQ-17.PO Cooling tower system- PO PEQ-17 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-17.CBE: FS
PEQ-17.DWG: FS, A15360: FS 49 Cooling tower system- PO
754 PEQ-18.PO New Verti cal filter- PO PEQ-18 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-18.CBE: FS
PEQ-18.DWG: FS, A15365: FS 54 New Verti cal f ilter- PO
755 PEQ-08.PO Expeller improvement(Existing)- PO PEQ-08 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-08.CBE: FS
PEQ-08.DWG: FS, A13780: FS 49 Expeller improvement(Existing)- PO
756 PEQ-09.PO Individual Cookers (New)- PO PEQ-09 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-09.CBE: FS
PEQ-09.DEL: FS, PEQ-09.DWG: FS 54 Individual Cookers (New)- PO
757 PEQ-10.PO Centralized cooker improvement(Existing)- PO PEQ-10 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-10.CBE: FS
PEQ-10.DWG: FS, A15370: FS 49 Centralized cooker improvement(Existing)- PO
758 PEQ-11.PO Processing Pump (New+ Existing)- PO PEQ-11 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-11.CBE: FSPEQ-11.DWG: FS, PEQ-11.DEL5: FS, PEQ-11.DEL10:
49 FS, PEQ-11.DEL15: FS Processing Pump (New+ Existing)- PO
759 PEQ-19.PO Ship Loader- PO PEQ-19 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-19.CBE: FS
PEQ-19.DWG: FS 49 Ship Loader- PO
760 PEQ-13.PO Process Cooler Equipment (New+Existing)- PO PEQ-13 10 Feb-04-25 Feb-17-25 A1650: FS, PEQ-13.CBE: FS
PEQ-13.DEL: FS, PEQ-13.DWG: FS 93 Process Cooler Equipment (New+Existing)- PO
761 UEQ-02.PO Purified water package improvement(Existing)- PO UEQ-02 10 Feb-04-25 Feb-17-25 A1650: FS, UEQ-02.CBE: FS
UEQ-02.DWG: FS 93 Purified water package improvement(Existing)- PO
762 IT-02. PO IT Software/Applications- PO IT-02 10 Feb-04-25 Feb-17-25 A1650: FS, IT-02.CBE: FS P4-2150: FS, P4-2220: FS 5 144 IT Software/Applications- PO
763 EEQ-03.PO Motor(New) for retrofit equipment - PO EEQ-03 10 Feb-04-25 Feb-17-25 EEQ-03.CBE: FS, A1650: FSEEQ-03.DWG: FS, EEQ-03.DEL: FS, EEQ-03.DEL10:
466FS, EEQ-03.DEL20: FS, EEQ-03.DEL30: FS, EEQ-03.DEL40: FS, EEQ-03.DEL50: FS, EEQ-03.DEL60: FS, EEQ-03.DEL70: FS, EEQ-03.DEL80: FS, EEQ-03.DEL90: FS, EEQ-03.DEL100: FS, EEQ-03.DEL110: FS Motor(New) for retrofit equipment - PO
764 CSA-01.PO Misc. Construction - PO CSA-01 10 Mar-06-25 Mar-19-25 A1650: FS 22, CSA-01.CBE:P4-2110:
FS FS, P4-2240: FS, P4-2275: FS, P4-2320: FS,
81 P4- 2360: FS, P4-2400: FS, P4-2440: FS, P4-2485: FS, P4- 2530: FS, P4-2590: FS, P4-2180: FS Misc. Construction - PO
765 CSA-02.PO CSA Construction (GC) - PO CSA-02 10 Mar-06-25 Mar-19-25 A1650: FS 22, CSA-02.CBE:P4-2100:
FS FS, P4-2170: FS, P4-2235: FS, P4-2270: FS,
81 P4-2315: FS, P4-2355: FS, P4-2395: FS, P4-2435: FS, P4-2480: FS, P4-2525: FS, P4-2580: FS CSA Construction (GC) - PO
766 MEPI-01.PO MEPI (Mechanical&Piping) Construction (GC) - PO MEPI-01 10 Mar-06-25 Mar-19-25 A1650: FS 22, MEPI-01.CBE:
P4-2236:
FS FS, P4-2305: FS, P4-2350: FS, P4-2390: 166
FS, P4-2430: FS, P4-2470: FS, P4-2515: FS, P4-2560: FS, P4-2650: FS, P4-2665: FS, P4-2265: FS MEPI (Mechanical&Piping) Construction (GC) - PO
767 MEPI-02.PO EAI Installation (GC) - PO MEPI-02 10 Mar-06-25 Mar-19-25 A1650: FS 22, MEPI-02.CBE:
A13695:
FS FS, A13710: FS, A13340: FS, A13830: FS, 216
P4-2475: FS, P4-2520: FS, P4-2565: FS, P4-2660: FS, P4-2670: FS, P4-2675: FS, P4-2680: FS, P4-2690: FS, P4-2695: FS, P4-2715: FS EAI Installation (GC) - PO
768 CSA-03.PO Jetty improvement and construction - PO CSA-03 10 Mar-06-25 Mar-19-25 A1650: FS 22, CSA-03.CBE:P4-2570:
FS FS 107 Jetty improvement and construction - PO
769 ES-02.PO Arc flash analysis Serivce - PO ES-02 10 Apr-01-25 Apr-14-25 A1650: FS, ES-02.CBE: FS A1660: FS 541 Arc flash analysis Serivce - PO
770 MEQ-01.PO Heavey Equipments (New) - PO MEQ-01 10 Apr-01-25 Apr-14-25 A1650: FS, MEQ-01.CBE: FS
MEQ-01.DEL: FS 144 Heavey Equipments (New) - PO
771 Equipment Document Submittal Mar-31-25, Equipment Document Submittal
772 EEQ-02.DWG MCC (New)- Equipment Drawings EEQ-02 30 Feb-18-25 Mar-31-25 EEQ-02.PO: FS A15300: FF 15 49 MCC (New)- Equipment Drawings
773 INS-01.DW G Instrument (New)- Equipment Drawings INS-01 30 Feb-18-25 Mar-31-25 INS-01.PO: FS A13290: FF 15, A15290: FF 15, A15300: FF 15, A15305:
49 FF 15, A15310: FF 15, A15320: FF 10, A15325: FF 15, A15330: FF 15, A15335: FF 15 Instrument (New)- Equipment Drawings
774 PEQ-01.DWG Air compressor (New)- Equipment Drawings PEQ-01 30 Feb-18-25 Mar-31-25 PEQ-01.PO: FS A15315: FS 93 Air compressor (New)- Equipment Drawings
775 PEQ-16.DWG Cyclone System- Equipment Drawings PEQ-16 30 Feb-18-25 Mar-31-25 PEQ-16.PO: FS A15290: FF 15, A15320: FF 10 93 Cyclone System- Equipment Drawings
776 PEQ-03.DWG Copra Dumping Stattion package (New)- Equipment Drawings PEQ-03 30 Feb-18-25 Mar-31-25 PEQ-03.PO: FS A15320: FF 10 94 Copra Dumping Stattion package (New)- Equipment Drawings
777 LEQ-01.DWG Lab Equipments- Equipment Drawings LEQ-01 30 Feb-18-25 Mar-31-25 LEQ-01.PO: FS A15280: FF 15 74 Lab Equipments- Equipment Drawings
778 PEQ-14.DWG Jetty Conveyor System- Equipment Drawings PEQ-14 30 Feb-18-25 Mar-31-25 PEQ-14.PO: FS A15325: FF 15 94 Jetty Conveyor System- Equipment Drawings
779 PEQ-15.DWG Jetty Crane- Equipment Drawings PEQ-15 30 Feb-18-25 Mar-31-25 PEQ-15.PO: FS A15325: FF 15 94 Jetty Crane- Equipment Drawings
780 PEQ-04.DWG Bucket Elevator- Equipment Drawings PEQ-04 30 Feb-18-25 Mar-31-25 PEQ-04.PO: FS A15320: FF 10, A15335: FF 10, A15290: FF 10, A15305:
73 FF 10 Bucket Elevator- Equipment Drawings
781 PEQ-05.DWG Copra Grinder improvement (Existing)- Equipment Drawings PEQ-05 30 Feb-18-25 Mar-31-25 PEQ-05.PO: FS A15300: FF 15 49 Copra Grinder improvement (Existing)- Equipment Drawings
782 PEQ-17.DWG Cooling tower system- Equipment Drawings PEQ-17 30 Feb-18-25 Mar-31-25 PEQ-17.PO: FS A15300: FF 15 49 Cooling tower system- Equipment Drawings
783 PEQ-18.DWG New Verti cal filter- Equipment Drawings PEQ-18 30 Feb-18-25 Mar-31-25 PEQ-18.PO: FS A15300: FS 54 New Verti cal f ilter- Equipment Drawings
784 PEQ-08.DWG Expeller improvement(Existing)- Equipment Drawings PEQ-08 30 Feb-18-25 Mar-31-25 PEQ-08.PO: FS A15300: FF 15 49 Expeller improvement(Existing)- Equipment Drawings
785 PEQ-09.DWG Individual Cookers/Centralized Cooker (New)- Equipment Drawings PEQ-09 30 Feb-18-25 Mar-31-25 PEQ-09.PO: FS A15300: FS 54 Individual Cookers/Centralized Cooker (New)- Equipment Drawings
786 PEQ-10.DWG Centralized cooker improvement(Existing)- Equipment Drawings PEQ-10 30 Feb-18-25 Mar-31-25 PEQ-10.PO: FS A15300: FF 15 49 Centralized cooker improvement(Existing)- Equipment Drawings
787 PEQ-11.DWG Processing Pump (New+ Existing)- Equipment Drawings PEQ-11 30 Feb-18-25 Mar-31-25 PEQ-11.PO: FS A15300: FF 15 49 Processing Pump (New+ Existing)- Equipment Drawings
788 PEQ-19.DWG Ship Loader- Equipment Drawings PEQ-19 30 Feb-18-25 Mar-31-25 PEQ-19.PO: FS A15300: FF 15 49 Ship Loader- Equipment Drawings
789 PEQ-13.DWG Process Cooler Equipment (New+Existing)- Equipment Drawings PEQ-13 30 Feb-18-25 Mar-31-25 PEQ-13.PO: FS A15310: FF 15 93 Process Cooler Equipment (New+Existing)- Equipment Drawings
790 UEQ-02.DWG Purified water package improvement(Existing) - Equipment Drawings UEQ-02 30 Feb-18-25 Mar-31-25 UEQ-02.PO: FS A15310: FF 15 93 Purified water package improvement(Existing) - Equipment Drawings
791 EEQ-03.DWG Motor (New)- Equipment Drawings EEQ-03 30 Feb-18-25 Mar-31-25 EEQ-03.PO: FS 556 Motor (New)- Equipment Drawings
792 Manufacturing Delivery at Site Dec-18-25, Manufacturing Delivery at Site
793 G0. General Aug-04-25, G0. General
794 G0.6 Rainwater Harvesting system Aug-04-25, G0.6 Rainwater Harvesting system
795 INS-01.DEL Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A13390: FF 20 162 Instrument (New) - Manufacturing and Delivery at Site
796 B0. Administ rative Buil di ngs Aug-04-25, B0. Admi ni strative Buildings
797 B0.1 Laboratory Fixture Aug-04-25, B0.1 Laboratory Fixture
798 LEQ-01.DEL Lab Equipments - Manufacturing and Delivery at Site LEQ-01 120 Feb-18-25 Aug-04-25 LEQ-01.PO: FS A13420: FS 104 Lab Equipments - Manufacturing and Delivery at Site
799 B1. Dry Copra Warehouse Aug-04-25, B1. Dry Copra Warehouse
800 B1.1 Dry Copra Warehouse Aug-04-25, B1.1 Dry Copra Warehouse
801 PEQ-04.DEL Bucket Elevator - Manufacturing and Delivery at Site PEQ-04 120 Feb-18-25 Aug-04-25 PEQ-04.PO: FS A15010: FF 20, A13685: FF 20 98 Bucket Elevator - Manufacturing and Delivery at Site
802 PEQ-16.DEL5 Cyclone System - Manufacturing and Delivery at Site PEQ-16 120 Feb-18-25 Aug-04-25 PEQ-16.PO: FS A13685: FF 20 98 Cyclone System - Manufacturing and Delivery at Site
803 INS-01.DEL5 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A13710: FF 20 158 Instrument (New) - Manufacturing and Delivery at Site
804 EEQ-03.DEL Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
805 B2. Oil Mill Operations Dec-18-25, B2. Oil Mill Operations
806 B2.2 Expeller Retrofit Aug-04-25, B2.2 Expeller Retrofit
807 EEQ-03.DEL10 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
808 B2.3 Process equipment retrofit Aug-04-25, B2.3 Process equipment retrofit
809 EEQ-03.DEL20 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
810 B2.4 13.2 KVA Transformer Dec-18-25, B2.4 13.2 KVA Transformer
811 EEQ-02.DEL MCC (New) - Manufacturing and Delivery at Site EEQ-02 120 Feb-18-25 Aug-04-25 EEQ-02.PO: FS A13830: FF 20 158 MCC (New) - Manufacturing and Delivery at Site
812 INS-01.DEL10 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A13835: FF 20 158 Instrument (New) - Manufacturing and Delivery at Site
813 EEQ-03.DEL30 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
814 EEQ-01.DEL HV+Tr ansformer (New) - Manufacturing and Deli ver y at Site EEQ-01 218 Feb-18-25 Dec-18-25 EEQ-01.PO: FS A13830: FF 20 60 HV+Tr ansformer (New) - Manufacturing and Deli very at Site
815 B2.5??? New Equipment Installation Aug-04-25, B2.5??? New Equipment Installation
Actual Work Critical Remaining Work Summary Page 4 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Project Herring Level 4/5 Master Schedule - Developing (No constraint) Herring L4/L5 Layout Nov-18-24 05:21
# Activity ID Activity Name PKG NO. At Completion Start Finish Predecessor Details Successor Details Total 2024 2025 2026 2027
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
816 PEQ-09.DEL Individual Cookers (New) - Manufacturing and Delivery at Site PEQ-09 120 Feb-18-25 Aug-04-25 PEQ-09.PO: FS A15375: FF 20 128 Individual Cookers (New) - Manufacturing and Delivery at Site
817 PEQ-11.DEL5 Processing Pump (New+ Existing) - Manufacturing and Delivery at Site PEQ-11 120 Feb-18-25 Aug-04-25 PEQ-11.PO: FS A15385: FF 20 128 Processing Pump (New+ Existing) - Manufacturing and Delivery at Site
818 INS-01.DEL90 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A15390: FF 20 158 Instrument (New) - Manufacturing and Delivery at Site
819 EEQ-03.DEL40 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
820 B3. Finish Good Copra Warehouse Aug-04-25, B3. Finish Good Copra Warehouse
821 B3.1 Finish Good Copra Warehouse Aug-04-25, B3.1 Finish Good Copra Warehouse
822 PEQ-16.DEL15 Cyclone System - Manufacturing and Delivery at Site PEQ-16 120 Feb-18-25 Aug-04-25 PEQ-16.PO: FS A13845: FF 20 98 Cyclone System - Manufacturing and Delivery at Site
823 PEQ-04.DEL5 Bucket Elevator - Manufacturing and Delivery at Site PEQ-04 120 Feb-18-25 Aug-04-25 PEQ-04.PO: FS A15010: FF 20, A13845: FF 20 98 Bucket Elevator - Manufacturing and Delivery at Site
824 INS-01.DEL15 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A13870: FF 20 158 Instrument (New) - Manufacturing and Delivery at Site
825 EEQ-03.DEL50 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
826 U0. Utilities Aug-04-25, U0. Utilities
827 U0.1 Raw Water Treatment Aug-04-25, U0.1 Raw Water Treatment
828 INS-01.DEL20 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14260: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
829 U0.3 Fire Water Tank Aug-04-25, U0.3 Fire Water Tank
830 PEQ-11.DEL15 Processing Pump (New+ Existing) - Manufacturing and Delivery at Site PEQ-11 120 Feb-18-25 Aug-04-25 PEQ-11.PO: FS A14095: FF 20 103 Processing Pump (New+ Existing) - Manufacturing and Delivery at Site
831 INS-01.DEL25 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14120: FS 20 133 Instrument (New) - Manufacturing and Delivery at Site
832 U0.4 Waste Water Treatment Aug-04-25, U0.4 Waste Water Treatment
833 INS-01.DEL30 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14165: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
834 U0.5 Cooling tower Aug-04-25, U0.5 Cooling tower
835 PEQ-13.DEL Process Cooler Equipment (New+Existing) - Manufacturing and Delivery at Site PEQ-13 120 Feb-18-25 Aug-04-25 PEQ-13.PO: FS A14185: FF 20 103 Process Cooler Equipment (New+Existing) - Manufacturing and Delivery at Site
836 PEQ-11.DEL10 Processing Pump (New+ Existing) - Manufacturing and Delivery at Site PEQ-11 120 Feb-18-25 Aug-04-25 PEQ-11.PO: FS A14185: FF 20 103 Processing Pump (New+ Existing) - Manufacturing and Delivery at Site
837 EEQ-03.DEL60 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
838 U1. Utility Building Sep-29-25, U1. Utility Building
839 U1.1 Maintenance workshop Sep-29-25, U1.1 Maintenance workshop
840 MEQ-02.DEL Maintenance Equpment Package (New) - Manufacturing and Delivery at Site MEQ-02 120 Feb-18-25 Aug-04-25 MEQ-02.PO: FS P4-2370: FS 184 Maintenance Equpment Package (New) - Manufacturing and Delivery at Site
841 MEQ-01.DEL Heavey Equipments (New) - Manufacturing and Delivery at Site MEQ-01 120 Apr-15-25 Sep-29-25 MEQ-01.PO: FS P4-2370: FS 144 Heavey Equipments (New) - Manufacturing and Delivery at Site
842 U1.2. Biomass Thermax Boiler(Steam system) Aug-04-25, U1.2. Biomass Thermax Boiler(Steam system)
843 INS-01.DEL35 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A13970: FF 20 158 Instrument (New) - Manufacturing and Delivery at Site
844 EEQ-03.DEL70 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
845 U1.4 Air Compressor & system Aug-04-25, U1.4 Air Compressor & system
846 PEQ-01.DEL Air compressor (New) - Manufacturing and Delivery at Site PEQ-01 120 Feb-18-25 Aug-04-25 PEQ-01.PO: FS A13980: FF 20 98 Air compressor (New) - Manufacturing and Delivery at Site
847 INS-01.DEL85 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14005: FF 20 158 Instrument (New) - Manufacturing and Delivery at Site
848 P1. Dumping Area Aug-04-25, P1. Dumping Area
849 P1.3 Elevator and Provision of Belt conveyor from Dumping to connect Jetty belt Aug-04-25, P1.3 Elevator and Provision of Belt conveyor from Dumping to connect Jetty belt
850 PEQ-16.DEL Cyclone System - Manufacturing and Delivery at Site PEQ-16 120 Feb-18-25 Aug-04-25 PEQ-16.PO: FS A14505: FF 20 119 Cyclone System - Manufacturing and Delivery at Site
851 PEQ-04.DEL10 Bucket Elevator - Manufacturing and Delivery at Site PEQ-04 120 Feb-18-25 Aug-04-25 PEQ-04.PO: FS A15010: FF 20, A14505: FS 20 97 Bucket Elevator - Manufacturing and Delivery at Site
852 INS-01.DEL70 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14525: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
853 EEQ-03.DEL80 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
854 P1.6 Construction of Truck Scale Aug-04-25, P1.6 Construction of Truck Scale
855 PEQ-03.DEL Copra Dumping Station package (New) - Manufacturing and Delivery at Site PEQ-03 120 Feb-18-25 Aug-04-25 PEQ-03.PO: FS A14640: FF 20 119 Copra Dumping Station package (New) - Manufacturing and Delivery at Site
856 INS-01.DEL80 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14660: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
857 P1.7 Construction of Scale House Aug-04-25, P1.7 Construction of Scale House
858 INS-01.DEL40 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14660: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
859 P1.8 Feeding hopper Aug-04-25, P1.8 Feeding hopper
860 INS-01.DEL45 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14660: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
861 J0. Jetty Aug-04-25, J0. Jetty
862 J0.3 Installtion of Jetty Crane, hopper, steel tower Aug-04-25, J0.3 Installtion of Jetty Crane, hopper, steel tower
863 PEQ-15.DEL Jetty Crane - Manufacturing and Delivery at Site PEQ-15 120 Feb-18-25 Aug-04-25 PEQ-15.PO: FS A14720: FF 20 99 Jetty Crane - Manufacturing and Delivery at Site
864 INS-01.DEL60 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14745: FF 20 159 Instrument (New) - Manufacturing and Delivery at Site
865 J0.8 Copra Unloading belt conveyor 240 meters long Aug-04-25, J0.8 Copra Unloading belt conveyor 240 meters long
866 PEQ-14.DEL Jetty Conveyor System - Manufacturing and Delivery at Site PEQ-14 120 Feb-18-25 Aug-04-25 PEQ-14.PO: FS A14960: FF 22 117 Jetty Conveyor System - Manufacturing and Delivery at Site
867 PEQ-16.DEL10 Cyclone System - Manufacturing and Delivery at Site PEQ-16 120 Feb-18-25 Aug-04-25 PEQ-16.PO: FS A14960: FF 20 119 Cyclone System - Manufacturing and Delivery at Site
868 PEQ-04.DEL20 Bucket Elevator - Manufacturing and Delivery at Site PEQ-04 120 Feb-18-25 Aug-04-25 PEQ-04.PO: FS A15010: FF 20 103 Bucket Elevator - Manufacturing and Delivery at Site
869 INS-01.DEL65 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14985: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
870 EEQ-03.DEL90 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
871 T1. Tank Farm A Aug-04-25, T1. Tank Farm A
872 T1. Tank Farm A (Including Handrail&Fencing) Aug-04-25, T1. Tank Farm A (I ncluding Handrail&Fencing)
873 INS-01.DEL50 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A14985: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
874 EEQ-03.DEL100 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
875 T2. Tank Farm B Aug-04-25, T2. Tank Farm B
876 T2. Tank Farm B (Including Handrail&Fencing) Aug-04-25, T2. Tank Farm B (Including Handrail&Fencing)
877 PEQ-04.DEL15 Bucket Elevator - Manufacturing and Delivery at Site PEQ-04 120 Feb-18-25 Aug-04-25 PEQ-04.PO: FS A15010: FF 20 103 Bucket Elevator - Manufacturing and Delivery at Site
878 INS-01.DEL55 Instrument (New) - Manufacturing and Delivery at Site INS-01 120 Feb-18-25 Aug-04-25 INS-01.PO: FS A15035: FF 20 163 Instrument (New) - Manufacturing and Delivery at Site
879 EEQ-03.DEL110 Motor(New) - Manufacturing and Delivery at Site EEQ-03 120 Feb-18-25 Aug-04-25 EEQ-03.PO: FS 466 Motor(New) - Manufacturing and Delivery at Site
880 Construction Apr-17-26, Construction
881 G0 General Mar-17-26, G0 General
882 P4-2110 G0 - Temp. Road & Fence/Power/Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS, A15470: FS,
P4-2100:
A15480:FF
FS 84 G0 - Temp. Road & Fence/Power/Water/Office etc..
883 P4-2670 G0 - EAI Installation Contractor Mobilization MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A13390: FS, A13340: FS 216 G0 - EAI Installation Contractor Mobilization
884 P4-2100 G0 - CSA Contractor Mobi li zation and Si te Preparation CSA-02 20 Jun-13-25 Jul-10-25 CSA-02.PO: FS, A13290: FFA13250:
10, P4-2110:
FS, A13260:
FF, A1640:
FS, A13300:
FF, A1680:
FS,FFA13370: FS, P4a-05:
23 FS G0 - CSA Contractor Mobi li zation and Si te Preparation
885 P4-2150 G0 - IT system HW Manufacturing and SW development IT-01/IT-02 120 Feb-18-25 Aug-04-25 IT-01.PO: FS, IT-02.PO: FS P4-2130: FS 144 G0 - IT system HW Manufacturing and SW development
886 P4-2665 G0 - MEPI (Mechanical & Piping) Contractor Mobilization MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1640: FS,A13360:
A1680: FS
FS 91 G0 - MEPI (Mechanical & Piping) Contractor Mobilization
887 P4-2130 G0 - IT system Site Integration IT-01/IT-02 40 Aug-05-25 Sep-29-25 P4-2150: FS P4-2140: FS 144 G0 - IT system Site Integration
888 P4-2160 G0 - Mechanical Completion MEPI-01 1 Mar-17-26 Mar-17-26 A13330: FS P4-2140: FS, P4-2140: FF, P4a-10: FS 23 G0 - Mechanical Completion
889 G0.1 Entrance and Exit Feb-11-26, G0. 1 Ent rance and Exit
890 A13250 Structural - Reinforcement CSA-02 66 Jul-11-25 Oct-10-25 P4-2100: FS A13260: FS 329 Structural - Reinforcement
891 A13260 Architectural - Reinforcement CSA-02 66 Oct-13-25 Jan-12-26 P4-2100: FS, A13250: FS A13270: FS 329 Architectural - Reinforcement
892 A13270 Architectural Electrical (lighting, lightening, grounding, etc.) Installation CSA-02 22 Jan-13-26 Feb-11-26 A13260: FS 329 Architectural Electrical (lighting, lightening, grounding, etc.) Installation
893 G0.2 Road Work - Pedestrian Walkway/Truck Parki ng Area/Car Parking Area/Motorcycle Parki ng Area Oct-10-25, G0.2 Road Work - Pedestrian Walkway/Truck Parking Area/Car Parking Ar ea/Motorcy cle Par king Area
894 A13300 Civil - Reinforcement CSA-02 66 Jul-11-25 Oct-10-25 P4-2100: FS 417 Civil - Reinforcement
895 G0.3 Fire fighting system??? May-20-25, G0.3 Fire fighting system???
896 A13310 Fire Fighting system Site Integration FF-01 66 Feb-18-25 May-20-25 FF-01.PO: FS 520 Fire Fighting system Site Integration
897 G0.4 Telecom system() ??? Apr-01-24, G0.4 Telecom system( )???
898 A13320 Telecom system Site Integration EEQ-04?? 66 Jan-01-24 Apr-01-24 816 Telecom system Site Integration
899 G0.6 Rainwater Harvesting system Mar-16-26, G0.6 Rainwater Harvesting system
900 A13370 Civil Construction CSA-02 44 Jul-11-25 Sep-10-25 P4-2100: FS A13380: FS 23 Civil Construction
901 A13380 Structural Construction CSA-02 44 Sep-11-25 Nov-11- 25 A13370: FS A13360: FS 23 Structural Construction
902 A13360 Piping Installation MEPI-01 44 Nov-12-25 Jan-12-26 A13380: FS, P4-2665: FS A13340: FS, A13390: FS 23 Piping Installation
903 A13340 Electrical Installation MEPI-02 44 Jan-13-26 Mar-13-26 A13360: FS, MEPI-02.PO: FS,
A13330:
P4-2670:
FS FS 23 Electrical Installation
904 A13390 Instrument and Autovalve Installation MEPI-02 44 Jan-13-26 Mar-13-26 A13360: FS, INS-01.DEL: FF
A13330:
20, P4-2670:
FS FS 23 Instrument and Autovalve Installation
905 A13330 Unit Mechanical Completion MEPI-01 1 Mar-16-26 Mar-16-26 A13340: FS, A13390: FS P4-2160: FS 23 Unit Mechanical Completion
906 B0. Administ rative Buildings Apr-09-26, B0. Admi ni strative Buildings
907 P4-2180 B0 - Temp. Road & Fence/Power /Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS P4-2170: FF 87 B0 - Temp. Road & Fence/Power/Water/Office etc..
908 P4-2170 B0 - CSA Contractor Mobilization and Site Preparation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, A15280: FFA13430:
10, P4-2180:
FS, A13500:
FF, A1640:
FS, A13560:
FS, A1680:
FS FS 6 B0 - CSA Cont ractor Mobilization and Site Preparation
909 P4-2265 B0 - MEPI (Mechanical & Piping) Contractor Mobilization MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1640: FS,A13420:
A1680: FS,
FS A13530: FS, A13575: FS 101 B0 - MEPI (Mechanical & Piping) Contractor Mobilization
910 P4-2220 B0 - IT System HW Manufacturing and SW development IT-01/IT-02 120 Feb-25-25 Aug-11-25 IT-01.PO: FS 5, IT-02.PO: FS
P4-2200:
5 FS 159 B0 - IT System HW Manufacturing and SW development
911 P4-2200 B0 - IT System Site Integration IT-01/IT-02 20 Aug-12-25 Sep-08-25 P4-2220: FS P4-2210: FS 159 B0 - IT System Site Integration
912 P4-2230 B0 - Mechanical Completion MEPI-01 5 Apr-03-26 Apr-09-26 A13460: FS, A13595: FS, A13550:
P4-2210:
FS,FS,
A13520:
P4a-10:
FFFS 6 B0 - Mechanical Completion
913 A13520 B0 - Fire Fighting System Site Integration FF-01 20 Mar-13-26 Apr-09-26 A13480: FS, A13535: FS, A15340:
P4-2230:
FS FF 6 B0 - Fire Fighting System Site Integration
914 B0.1 Laboratory Fixture Dec-12-25, B0.1 Laboratory Fixture
915 A13500 Architectural Construction CSA-02 30 Aug-08-25 Sep-18-25 P4-2170: FS A13420: FS 71 Architectural Construction
916 A13420 New Equipment Installation MEPI-01 30 Sep-19-25 Oct-30-25 A13500: FS, LEQ-01.DEL: FS,
A13480:
P4-2265:
FS FS 71 New Equipment Installation
917 A13480 Fire Fighting Pipe Installation FF-01 30 Oct-31-25 Dec-11-25 A13420: FS, FF-01.PO: FS A13460: FS, A13520: FS 71 Fire Fighting Pipe Installation
918 A13460 Unit Mechanical Completion MEPI-01 1 Dec-12-25 Dec-12-25 A13480: FS P4-2230: FS 85 Unit Mechanical Completion
919 B0.2 Office Fixture Jan-30-26, B0.2 Office Fixture
920 A13430 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2170: FS A13555: FS 36 Dismantle
921 A13555 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A13430: FS A13525: FS 36 Structural Construction
922 A13525 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A13555: FS A13530: FS 36 Architectural Construction
923 A13530 Equipment Installation MEPI-01 30 Nov-07-25 Dec-18-25 A13525: FS, P4-2265: FS A13535: FS, A15345: FS 36 Equipment Installation
924 A13535 Fire Fighting Pipe Installation FF-01 30 Dec-19-25 Jan-29-26 A13530: FS, FF-01.PO: FS A13550: FS, A13520: FS 36 Fire Fighting Pipe Installation
925 A13550 Unit Mechanical Completion MEPI-01 1 Jan-30-26 Jan-30-26 A13535: FS P4-2230: FS 50 Unit Mechanical Completion
926 B0.3 Modify of storage room/B0.3 Employee Locker room Mar-13-26, B0.3 Modify of storage room/B0.3 Employee Locker room
927 A13560 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2170: FS A13565: FS 6 Dismantle
928 A13565 Civil Construction CSA-02 30 Aug-15-25 Sep-25-25 A13560: FS A13600: FS 6 Civil Construction
929 A13600 Structural Construction CSA-02 30 Sep-26-25 Nov-06-25 A13565: FS A13570: FS 6 Structural Construction
930 A13570 Architectural Construction CSA-02 30 Nov-07-25 Dec-18-25 A13600: FS A13575: FS 6 Architectural Construction
931 A13575 Equipment Installation MEPI-01 30 Dec-19-25 Jan-29-26 A13570: FS, P4-2265: FS A15340: FS 6 Equipment Installation
932 A15340 Fire Fighting Pipe Installation FF-01 30 Jan-30-26 Mar-12-26 FF-01.PO: FS, A13575: FS A13520: FS, A13595: FS 6 Fire Fighting Pipe Installation
933 A13595 Unit Mechanical Completion MEPI-01 1 Mar-13-26 Mar-13-26 A15340: FS P4-2230: FS 20 Unit Mechanical Completion
934 B1. Dry Copra Warehouse Feb-26-26, B1. Dry Copra Warehouse
935 P4-2240 B1 - Temp. Road & Fence/Power /Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS P4-2235: FF 106 B1 - Temp. Road & Fence/Power/Water/Office etc..
936 P4-2236 B1 - MEPI (Mechanical & Piping) Contractor Mobilization MEPI-01 20 Mar-20-25 Apr-16-25 MEPI-01.PO: FS A13685: FS 166 B1 - MEPI (Mechanical & Piping) Contractor Mobilization
937 P4-2235 B1 - CSA Contractor Mobilization and Site Preparation CSA-02 20 Apr-08-25 May-05-25 CSA-02.PO: FS, A15290: FFA13720:
10, P4-2240:
FS FF 93 B1 - CSA Contractor Mobilization and Site Preparation
938 P4-2675 B1 - EAI Installation Contractor Mobilization MEPI-02 20 Sep-23-25 Oct-21-25 MEPI-02.PO: FS, A13695: SF, A13710: SF 411 B1 - EAI Installation Contractor Mobilization
939 P4-2260 B1 - Mechanical Completion MEPI-01 5 Feb-20-26 Feb-26-26 A13690: FS, P4-2248: FF P4-2250: FS, P4a-10: FS 36 B1 - Mechanical Completion
940 P4-2248 B1 - Fire Fighting System Site Integration FF-01 20 Jan-30-26 Feb-26-26 A15345: FS P4-2260: FF 36 B1 - Fire Fighting System Site Integration
941 B1.1 Dry Copra Warehouse Jan-30-26, B1.1 Dry Copra Warehouse
942 A13720 Structural Construction CSA-02 30 May-06-25 Jun-16-25 P4-2235: FS A13705: FS 93 Structural Construction
943 A13705 Architectural Construction CSA-02 30 Jun-17-25 Jul-28-25 A13720: FS A13685: FS 93 Architectural Construction
944 A13685 New Equipment Installation MEPI-01 30 Jul-29-25 Sep-08-25 A13705: FS, PEQ-16.DEL5:A13700:
FF 20, PEQ-04.DEL:
FS FF 20, P4-2236: FS 93 New Equipment Installation
945 A13700 Piping Installation MEPI-01 30 Sep-09-25 Oct-20-25 A13685: FS A13695: FS, A13710: FS 93 Piping Installation
946 A13695 Electrical Installation MEPI-02 30 Oct-21-25 Dec-01-25 A13700: FS, MEPI-02.PO: FS
A13690: FS, P4-2675: SF 93 Electrical Installation
947 A13710 Instrument and Autovalve Installation MEPI-02 30 Oct-21-25 Dec-01-25 A13700: FS, MEPI-02.PO: FS,
A13690:
INS-01.DEL5:
FS, P4-2675:
FF 20SF 93 Instrument and Autovalve Installation
948 A15345 Fire Fighting Pipe Installation FF-01 30 Dec-19-25 Jan-29-26 A13530: FS, FF-01.PO: FS A13690: FS, P4-2248: FS 36 Fire Fighting Pipe Installation
949 A13690 Unit Mechanical Completion MEPI-01 1 Jan-30-26 Jan-30-26 A13695: FS, A13710: FS, A15345:
P4-2260:
FS FS 50 Unit Mechanical Completion
950 B2. Oil Mill Operations Apr-16-26, B2. Oil Mill Operations
951 P4-2275 B2 - Temp. Road & Fence/Power /Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS A13760: FS 82 B2 - Temp. Road & Fence/Power/Water/Office etc..
952 P4-2680 B2 - EAI Installation Contractor Mobilization MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A13830: FS, A13740: FS 226 B2 - EAI Installation Contractor Mobilization
953 P4-2310 B2 - Automation sy stem Site Integration ACS-01 120 Feb-18-25 Aug-04-25 ACS-01.PO: FS P4-2295: FF 184 B2 - Aut omation sy stem Site Integration
954 P4-2270 B2 - CSA Contractor Mobilization and Site Preparation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, A15300: FSA13760:
10, A1640:
FS, A13800:
FS, A1680:
FSFS 1 B2 - CSA Cont ractor Mobilization and Site Preparation
955 P4-2305 B2 - MEPI (Mechanical & Piping) Contractor Mobilization MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1680: FS,A13730:
A1640: FS,
FS A13815: FS 85 B2 - MEPI (Mechanical & Piping) Contractor Mobilization
956 P4-2300 B2 - Fire Fighting System Site Integration FF-01 20 Jan-30-26 Feb-26-26 A15350: FS, A15355: FS P4-2295: FF 36 B2 - Fire Fighting System Site Integration
957 P4-2295 B2 - Mechanical Completion MEPI-01 5 Apr-10-26 Apr-16-26 A13735: FS, A13840: FS, P4-
P4-2285:
2300: FFFS,
, A13790:
P4a-10:
FS,
FSA13795: FS, P4-2310: FF, A15380:
1 FS B2 - Mechanical Completion
958 B2.1 Building reinforce including MCC room Mar-13-26, B2.1 Building reinforce including MCC room
959 A13760 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2270: FS, P4-2275: FS A13775: FS 1 Dismantle
960 A13775 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A13760: FS A13750: FS 1 Structural Construction
961 A13750 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A13775: FS A13730: FS, A13780: FS, A13785: FS, A15360: FS, A15365:
1 FS, A15370: FS, A15375: FS, A15385: FS Architectural Construction
962 A13730 Equipment Installation MEPI-01 30 Nov-07-25 Dec-18-25 A13750: FS, P4-2305: FS A13745: FS, A15350: FS, A15355: FS 20 Equipment Installation
963 A13745 Piping Installation MEPI-01 30 Dec-19-25 Jan-29-26 A13730: FS A13740: FS, A13755: FS 20 Piping Installation
964 A15350 Fire Fighting Pipe Installation FF-01 30 Dec-19-25 Jan-29-26 A13730: FS, FF-01.PO: FS A13740: FS, A13755: FS, P4- 2300: FS 20 Fire Fighting Pipe Installation
965 A13740 Electrical Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13745: FS, A15350: FS, P4-
A13735:
2680: FS
FS 20 Electrical Installation
966 A13755 Instrument and Autovalve Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13745: FS, A15350: FS A13735: FS 20 Instrument and Autovalve Installation
967 A13735 Unit Mechanical Completion MEPI-01 1 Mar-13-26 Mar-13-26 A13740: FS, A13755: FS P4-2295: FS 20 Unit Mechanical Completion
968 B2.2 Expeller retrofit Apr-09-26, B2.2 Expeller retrofit
969 A13780 Expeller Equipment Retrofit PEQ-08 80 Nov-07-25 Feb-26-26 PEQ-08.PO: FS, A13750: FSA13790: FS 1 Expeller Equipment Retrofit
970 A13790 Unit Mechanical Completion MEPI-01 30 Feb-27-26 Apr-09-26 A13780: FS P4-2295: FS 1 Unit Mechanical Completion
971 B2.3 Process equipment retrofit Feb-27-26, B2.3 Process equipment retrofit
972 A13785 Copra Grinder Retrofit PEQ-05 80 Nov-07-25 Feb-26-26 PEQ-05.PO: FS, A13750: FSA13795: FS 30 Copra Grinder Retrofit
973 A15360 Cracker Retrofit PEQ-17 80 Nov-07-25 Feb-26-26 PEQ-05.PO: FS, A13750: FS,
A13795:
PEQ-17.PO:
FS FS 30 Cracker Retrofit
974 A15365 Flaker Retrofit PEQ-18 80 Nov-07-25 Feb-26-26 PEQ-05.PO: FS, A13750: FS,
A13795:
PEQ-18.PO:
FS FS 30 Flaker Retrofit
975 A15370 Centralized Cooker Retrofit PEQ-10 80 Nov-07-25 Feb-26-26 PEQ-05.PO: FS, A13750: FS,
A13795:
PEQ-10.PO:
FS FS 30 Centralized Cooker Retrofit
976 A13795 Unit Mechanical Completion MEPI-01 1 Feb-27-26 Feb-27-26 A13785: FS, A15360: FS, A15365:
P4-2295:
FS,FS
A15370: FS 30 Unit Mechanical Completion
977 B2.4 13.2 KVA Transformer Mar-13-26, B2.4 13.2 KVA Transformer
978 A13800 Civil Construction CSA-02 5 Aug-08-25 Aug-14-25 P4-2270: FS A13805: FS 20 Civil Construction
979 A13805 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A13800: FS A13810: FS 20 Structural Construction
980 A13810 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A13805: FS A13815: FS 20 Architectural Construction
981 A13815 Equipment Installation MEPI-01 30 Nov-07-25 Dec-18-25 A13810: FS, P4-2305: FS A13825: FS 20 Equipment Installation
982 A13825 Piping Installation MEPI-01 30 Dec-19-25 Jan-29-26 A13815: FS A13830: FS, A13835: FS 20 Piping Installation
983 A15355 Fire Fighting Pipe Installation FF-01 30 Dec-19-25 Jan-29-26 A13730: FS, FF-01.PO: FS P4-2300: FS 36 Fire Fighting Pipe Installation
984 A13830 Electrical Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13825: FS, MEPI-02.PO: FS,
A13840:
EEQ-02.DEL:
FS FF 20, EEQ-01.DEL: FF 20, P4-2680:
20 FS Electrical Installation
985 A13835 Instrument and Autovalve Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13825: FS, INS-01.DEL10:A13840:
FF 20 FS 20 Instrument and Autovalve Installation
986 A13840 Unit Mechanical Completion MEPI-01 1 Mar-13-26 Mar-13-26 A13830: FS, A13835: FS P4-2295: FS 20 Unit Mechanical Completion
987 B2.5 New Process Equipment Installation ( Need to updated with BPM and EM) Feb-13-26, B2.5 New Process Equipment Installation ( Need to updated with BPM and EM)
988 A15375 Individual Cookers Installation ( Y1 Scope?) PEQ-09 40 Nov-07-25 Jan-01-26 A13750: FS, PEQ-09.DEL: FF
A15380:
20 FS, A15390: FS 40 Individual Cookers Installation ( Y1 Scope?)
989 A15385 Processing Pump Installation PEQ-11 40 Nov-07-25 Jan-01-26 A13750: FS, PEQ-11.DEL5:A15380:
FF 20 FS, A15390: FS 40 Processing Pump Installation
990 A15390 Instrument and Autovalve Installation MEPI-02 30 Jan-02-26 Feb-12-26 INS-01.DEL90: FF 20, A15375:
A15380:
FS, A15385:
FS FS 40 Instrument and Autovalve Installation
991 A15380 Unit Mechanical Completion MEPI-01 1 Feb-13-26 Feb-13-26 A15375: FS, A15385: FS, A15390:
P4-2295:
FS FS 40 Unit Mechanical Completion
992 B3. Finish Good Copra Warehouse Mar-20-26, B3. Finish Good Copra Warehouse
993 P4-2320 B3 - Temp. Road & Fence/Power /Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS A13875: FS, P4-2315: FF 101 B3 - Temp. Road & Fence/Power/Water/Office etc..
994 P4-2690 B3 - EAI Installation Contractor Mobilization MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A13855: FS 226 B3 - EAI Installation Contractor Mobilization
995 P4-2315 B3 - CSA Contractor Mobilization and Site Preparation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, A15305: FFA13875:
10, P4-2320:
FS FF, A1640: FS, A1680: FS 20 B3 - CSA Cont ractor Mobilization and Site Preparation
996 P4-2350 B3 - MEPI (Mechanical & Piping) Contractor Mobilization MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1640: FS,A13845:
A1680: FS
FS 85 B3 - MEPI (Mechanical & Piping) Contractor Mobilization
997 P4-2345 B3 - Fire Fighting System Site Integration FF-01 20 Jan-30-26 Feb-26-26 P4-2685: FS P4-2340: FF 36 B3 - Fire Fighting System Site Integration
998 P4-2340 B3 - Mechanical Completion MEPI-01 5 Mar-16-26 Mar-20-26 A13850: FS, P4-2345: FF P4-2330: FS, P4a-10: FS 20 B3 - Mechanical Completion
999 B3.1 Finish Good Copra W arehouse Mar-13-26, B3.1 Finish Good Copra W arehouse
1000 A13875 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2315: FS, P4-2320: FS A13885: FS 20 Dismantle
1001 A13885 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A13875: FS A13865: FS 20 Structural Construction
1002 A13865 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A13885: FS A13845: FS 20 Architectural Construction
1003 A13845 Equipment Installation MEPI-01 30 Nov-07-25 Dec-18-25 A13865: FS, PEQ-16.DEL15:
A13860:
FF 20, FS,
PEQ-04.DEL5:
P4-2685: FSFF 20, P4-2350: FS 20 Equipment Installation
1004 A13860 Piping Installation MEPI-01 30 Dec-19-25 Jan-29-26 A13845: FS A13855: FS, A13870: FS 20 Piping Installation
1005 P4-2685 Fire Fighting Pipe Installation FF-01 30 Dec-19-25 Jan-29-26 FF-01.PO: FS 5, A13845: FSA13850: FS, P4-2345: FS 36 Fire Fighting Pipe Installation
1006 A13855 Electrical Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13860: FS, P4-2690: FS A13850: FS 20 Electrical Installation
1007 A13870 Instrument and Autovalve Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13860: FS, INS-01.DEL15:A13850:
FF 20 FS 20 Instrument and Autovalve Installation
1008 A13850 Unit Mechanical Completion MEPI-01 1 Mar-13-26 Mar-13-26 A13855: FS, A13870: FS, P4-
P4-2340:
2685: FSFS 20 Unit Mechanical Completion
1009 U0. Utilities Mar-13-26, U0. Utilities
1010 P4-2400 U0 - Temp. Road & Fence/Power /Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS A14170: FS, A14230: FS, A14220: FS, P4-2395: FF106 U0 - Temp. Road & Fence/Power/Water/Office etc..
1011 P4-2695 U0 - EAI Installation Contractor Mobilization MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A14255: FS, A14105: FS, A14150: FS, A14195: FS 231 U0 - EAI Installation Contractor Mobilization
1012 P4-2395 U0 - CSA Contractor Mobilization and Site Preparation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, A15310: FFA14125:
10, P4-2400:
FS, A14170:
FF, A1680:
FS, A14230:
FS, A1640:
FS,FS
A14220: FS 25 U0 - CSA Cont ractor Mobilization and Site Preparation
1013 P4-2430 U0 - MEPI (Mechanical & Piping) Contractor Mobilization MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1680: FS,A14240:
A1640: FS,
FS A14095: FS, A14140: FS, A14185: FS 90 U0 - MEPI (Mechanical & Piping) Contractor Mobilization
1014 P4-2420 U0 - Mechanical Completion MEPI-01 5 Mar-09-26 Mar-13-26 A14100: FF, A14145: FF, A14190:
P4-2410:
FF, A14265:
FS, P4a-10:
FF FS 25 U0 - Mechanical Completion
1015 U0.1 Raw W ater Treatment Mar-06-26, U0.1 Raw Water Treatment
1016 A14230 Structural Construction CSA-02 30 Aug-08-25 Sep-18-25 P4-2395: FS, P4-2400: FS A14235: FS 30 Structural Construction
1017 A14235 Architectural Construction CSA-02 30 Sep-19-25 Oct-30-25 A14230: FS A14240: FS, A14245: FS 30 Architectural Construction
1018 A14240 New Equipment Installation MEPI-01 30 Oct-31-25 Dec-11-25 A14235: FS, P4-2430: FS A14250: FS 30 New Equipment Installation
1019 A14245 Existing Equipment Retrofit ES-03 30 Oct-31-25 Dec-11-25 A14235: FS, ES-03.PO: FS A14250: FS 30 Existing Equipment Retrofit
Actual Work Critical Remaining Work Summary Page 5 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Project Herring Level 4/5 Master Schedule - Developing (No constraint) Herring L4/L5 Layout Nov-18-24 05:21
# Activity ID Activity Name PKG NO. At Completion Start Finish Predecessor Details Successor Details Total 2024 2025 2026 2027
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1020 A14250 Piping Installation MEPI-01 30 Dec-12-25 Jan-22-26 A14240: FS, A14245: FS A14255: FS, A14260: FS 30 Piping Installation
1021 A14255 Electrical Installation MEPI-02 30 Jan-23-26 Mar-05-26 A14250: FS, P4-2695: FS A14265: FS 30 Electrical Installation
1022 A14260 Instrument and Autovalve Installation MEPI-02 30 Jan-23-26 Mar-05-26 A14250: FS, INS-01.DEL20:A14265:
FF 20 FS 30 Instrument and Autovalve Installation
1023 A14265 Unit Mechanical Completion MEPI-01 1 Mar-06-26 Mar-06-26 A14255: FS, A14260: FS P4-2420: FF 30 Unit Mechanical Completion
1024 U0.3 Fire Water Tank/Water Storage Tank Mar-13-26, U0.3 Fire Water Tank/Water Storage Tank
1025 A14125 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2395: FS A14135: FS 25 Dismantle
1026 A14135 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A14125: FS A14115: FS 25 Structural Construction
1027 A14115 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A14135: FS A14095: FS, A14130: FS 25 Architectural Construction
1028 A14095 New Equipment Installation MEPI-01 30 Nov-07-25 Dec-18-25 A14115: FS, PEQ-11.DEL15:
A14110:
FF 20, FS
P4-2430: FS 25 New Equipment Installation
1029 A14130 Existing Equipment Retrofit ES-03 30 Nov-07-25 Dec-18-25 A14115: FS, ES- 03.PO: FS A14110: FS 25 Existing Equipment Retrofit
1030 A14110 Piping Installation MEPI-01 30 Dec-19-25 Jan-29-26 A14095: FS, A14130: FS A14105: FS, A14120: FS 25 Piping Installation
1031 A14105 Electrical Installation MEPI-02 30 Jan-30-26 Mar-12-26 A14110: FS, P4-2695: FS A14100: FS 25 Electrical Installation
1032 A14120 Instrument and Autovalve Installation MEPI-02 30 Jan-30-26 Mar-12-26 A14110: FS, INS-01.DEL25:A14100:
FS 20 FS 25 Instrument and Autovalve Installation
1033 A14100 Unit Mechanical Completion MEPI-01 1 Mar-13-26 Mar-13-26 A14105: FS, A14120: FS P4-2420: FF 25 Unit Mechanical Completion
1034 U0.4 W ast e Water Treatment Mar-13-26, U0.4 Waste W ater Treatment
1035 A14170 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2395: FS, P4-2400: FS A14180: FS 25 Dismantle
1036 A14180 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A14170: FS A14160: FS 25 Structural Construction
1037 A14160 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A14180: FS A14140: FS, A14175: FS 25 Architectural Construction
1038 A14140 New Equipment Installation MEPI-01 30 Nov-07-25 Dec-18-25 A14160: FS, P4-2430: FS A14155: FS 25 New Equipment Installation
1039 A14175 Existing Equipment Retrofit ??? 30 Nov-07-25 Dec-18-25 A14160: FS A14155: FS 25 Existing Equipment Retrofit
1040 A14155 Piping Installation MEPI-01 30 Dec-19-25 Jan-29-26 A14140: FS, A14175: FS A14150: FS, A14165: FS 25 Piping Installation
1041 A14150 Electrical Installation MEPI-02 30 Jan-30-26 Mar-12-26 A14155: FS, P4-2695: FS A14145: FS 25 Electrical Installation
1042 A14165 Instrument and Autovalve Installation MEPI-02 30 Jan-30-26 Mar-12-26 A14155: FS, INS-01.DEL30:A14145:
FF 20 FS 25 Instrument and Autovalve Installation
1043 A14145 Unit Mechanical Completion MEPI-01 1 Mar-13-26 Mar-13-26 A14150: FS, A14165: FS P4-2420: FF 25 Unit Mechanical Completion
1044 U0.5 Cooling tower ??? ( Need to confirmed with EM and BPM) Mar-06-26, U0.5 Cooling tower ??? ( Need to confirmed with EM and BPM)
1045 A14220 Structural Construction CSA-02 30 Aug-08-25 Sep-18-25 P4-2400: FS, P4-2395: FS A14205: FS 30 Structural Construction
1046 A14205 Architectural Construction CSA-02 30 Sep-19-25 Oct-30-25 A14220: FS A14185: FS, A14215: FS 30 Architectural Construction
1047 A14185 New Equipment Installation MEPI-01 30 Oct-31-25 Dec-11-25 A14205: FS, PEQ-13.DEL: FF
A14200:
20, PEQ-11.DEL10:
FS FF 20, P4-2430: FS 30 New Equipment Installation
1048 A14215 Existing Equipment Retrofit ??? 30 Oct-31-25 Dec-11-25 A14205: FS A14200: FS 30 Existing Equipment Retrofit
1049 A14200 Piping Installation MEPI-01 30 Dec-12-25 Jan-22-26 A14185: FS, A14215: FS A14195: FS, A14210: FS 30 Piping Installation
1050 A14195 Electrical Installation MEPI-02 30 Jan-23-26 Mar-05-26 A14200: FS, P4-2695: FS A14190: FS 30 Electrical Installation
1051 A14210 Instrument and Autovalve Installation MEPI-02 30 Jan-23-26 Mar-05-26 A14200: FS A14190: FS 30 Instrument and Autovalve Installation
1052 A14190 Unit Mechanical Completion MEPI-01 1 Mar-06-26 Mar-06-26 A14195: FS, A14210: FS P4-2420: FF 30 Unit Mechanical Completion
1053 U1. Utility Building Mar-20-26, U1. Utility Building
1054 P4-2360 U1 - Temp. Road & Fence/Power /Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS A13920: FS, A13935: FS, A14010: FS 101 U1 - Temp. Road & Fence/Power/Water/Office etc..
1055 P4-2715 U1 - EAI Installation Contractor Mobilization MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A13965: FS, A13970: FS, A14005: FS, A13990: FS, 226
A14035: FS, A14050: FS U1 - EAI Installation Contractor Mobilization
1056 P4-2355 U1 - CSA Contractor Mobilization and Site Preparation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, A15315: FFA13920:
10, A1680:
FS, FS,
A13935:
A1640:
FS,FS
A14010: FS, A14065: FS 20 U1 - CSA Cont ractor Mobilization and Site Preparation
1057 P4-2390 U1 - MEPI Contractor Mobilization and Site Preparation MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1640: FS,A13905:
A1680: FS,
FS A13950: FS, A13980: FS, A14025: FS 85 U1 - MEPI Contractor Mobilization and Site Preparation
1058 P4-2385 U1 - Fire Fighting System Site Integration FF-01 20 Jan-23-26 Feb-19-26 P4-2700: FS, P4-2705: FS P4-2380: FF 41 U1 - Fire Fighting System Site Integration
1059 P4-2380 U1 - Mechanical Completion MEPI-01 5 Mar-16-26 Mar-20-26 A13895: FS, A13975: FS, A13985:
P4-2370:
FS,FS,
A14030:
P4a-10:
FS,FS
P4-2385: FF 20 U1 - Mechanical Completion
1060 U1.1 Boiler building/Air Compressor room/U1.1 Maintenance workshop Dec-25-25, U1.1 Boiler building/Air Compressor room/U1.1 Maintenance workshop
1061 A13920 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2355: FS, P4-2360: FS A13930: FS 66 Dismantle
1062 A13930 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A13920: FS A13910: FS, A13905: FS 66 Structural Construction
1063 A13905 Piping Installation MEPI-01 30 Sep-26-25 Nov-06-25 A13930: FS, P4-2390: FS A13895: FS 106 Piping Installation
1064 A13910 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A13930: FS P4-2700: FS 66 Architectural Construction
1065 P4-2700 Fire Fighting Pipe Installation FF-01 30 Nov-07-25 Dec-18-25 FF-01.PO: FS 5, A13910: FSP4-2385: FS, A13895: FS 66 Fire Fighting Pipe Installation
1066 A13895 Unit Mechanical Completion MEPI-01 5 Dec-19-25 Dec-25-25 A13905: FS, P4-2700: FS P4-2380: FS 76 Unit Mechanical Completion
1067 U1.2.Biomass Thermax Boiler(Steam system) Mar-13-26, U1.2.Biomass Thermax Boiler(Steam system)
1068 A13935 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2355: FS, P4-2360: FS A13940: FS 20 Dismantle
1069 A13940 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A13935: FS A13945: FS 20 Structural Construction
1070 A13945 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A13940: FS A13950: FS, A13955: FS 20 Architectural Construction
1071 A13950 New Equipment Installation MEPI-01 30 Nov-07-25 Dec-18-25 A13945: FS, P4-2390: FS A13960: FS 20 New Equipment Installation
1072 A13955 Existing Boiler Retrofit ES-03 30 Nov-07-25 Dec-18-25 A13945: FS, ES-03.PO: FS A13960: FS 20 Existing Boiler Retrofit
1073 A13960 Piping Installation MEPI-01 30 Dec-19-25 Jan-29-26 A13950: FS, A13955: FS A13965: FS, A13970: FS 20 Piping Installation
1074 A13965 Electrical Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13960: FS, P4-2715: FS A13975: FS 20 Electrical Installation
1075 A13970 Instrument and Autovalve Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13960: FS, INS-01.DEL35:A13975:
FF 20, P4-2715:
FS FS 20 Instrument and Autovalve Installation
1076 A13975 Unit Mechanical Completion MEPI-01 1 Mar-13-26 Mar-13-26 A13965: FS, A13970: FS P4-2380: FS 20 Unit Mechanical Completion
1077 U1.4 Air Compressor & system Mar-13-26, U1.4 Ai r Compressor & syst em
1078 A14010 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2355: FS, P4-2360: FS A14020: FS 20 Dismantle
1079 A14020 Structural Construction CSA-02 30 Aug-15-25 Sep-25-25 A14010: FS A14000: FS 20 Structural Construction
1080 A14000 Architectural Construction CSA-02 30 Sep-26-25 Nov-06-25 A14020: FS A13980: FS, A14015: FS 20 Architectural Construction
1081 A13980 New Equipment Installation MEPI-01 30 Nov-07-25 Dec-18-25 A14000: FS, PEQ-01.DEL: FF
A13995:
20, P4-2390:
FS FS 20 New Equipment Installation
1082 A14015 Existing Equipment Retrofit ??? 30 Nov-07-25 Dec-18-25 A14000: FS A13995: FS 20 Existing Equipment Retrofit
1083 A13995 Piping Installation MEPI-01 30 Dec-19-25 Jan-29-26 A13980: FS, A14015: FS A13990: FS, A14005: FS 20 Piping Installation
1084 A13990 Electrical Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13995: FS, P4-2715: FS A13985: FS 20 Electrical Installation
1085 A14005 Instrument and Autovalve Installation MEPI-02 30 Jan-30-26 Mar-12-26 A13995: FS, INS-01.DEL85:A13985:
FF 20, P4-2715:
FS FS 20 Instrument and Autovalve Installation
1086 A13985 Unit Mechanical Completion MEPI-01 1 Mar-13-26 Mar-13-26 A13990: FS, A14005: FS P4-2380: FS 20 Unit Mechanical Completion
1087 U1.5 Coconut shell storage (for biomass boiler) Mar-06-26, U1.5 Coconut shell storage (for biomass boiler)
1088 A14065 Structural Construction CSA-02 30 Aug-08-25 Sep-18-25 P4-2355: FS A14045: FS 25 Structural Construction
1089 A14045 Architectural Construction CSA-02 30 Sep-19-25 Oct-30-25 A14065: FS A14025: FS, A14060: FS 25 Architectural Construction
1090 A14025 New Equipment Installation MEPI-01 30 Oct-31-25 Dec-11-25 A14045: FS, P4-2390: FS A14040: FS, P4-2705: FS 25 New Equipment Installation
1091 A14060 Existing Equipment Retrofit ??? 30 Oct-31-25 Dec-11-25 A14045: FS A14040: FS 25 Existing Equipment Retrofit
1092 A14040 Piping Installation MEPI-01 30 Dec-12-25 Jan-22-26 A14025: FS, A14060: FS A14035: FS, A14050: FS 25 Piping Installation
1093 P4-2705 Fire Fighting Pipe Installation FF-01 30 Dec-12-25 Jan-22-26 FF-01.PO: FS 5, A14025: FSP4-2385: FS, A14030: FS 41 Fire Fighting Pipe Installation
1094 A14035 Electrical Installation MEPI-02 30 Jan-23-26 Mar-05-26 A14040: FS, P4-2715: FS A14030: FS 25 Electrical Installation
1095 A14050 Instrument and Autovalve Installation MEPI-02 30 Jan-23-26 Mar-05-26 A14040: FS, P4-2715: FS A14030: FS 25 Instrument and Autovalve Installation
1096 A14030 Unit Mechanical Completion MEPI-01 1 Mar-06-26 Mar-06-26 A14035: FS, A14050: FS, P4-
P4-2380:
2705: FSFS 25 Unit Mechanical Completion
1097 P1. Dumping Area Mar-19-26, P1. Dumping Ar ea
1098 P4-2440 P1 - Temp. Road & Fence/Power /Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS P4-2435: FF 102 P1 - Temp. Road & Fence/Power/Water/Office etc..
1099 P4-2475 P1 - EAI Installation Contractor Mobilization and Site Preparation MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A14705: FS, A14710: FS, A14610: FS, A14655: FS, 239
A14660: FS, A14520: FS, A14525: FS, A14280: FS, A14295: FS P1 - EAI Installation Contractor Mobilization and Site Preparation
1100 P4-2435 P1 - CSA Contractor Mobilization and Site Preparation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, P4-2440: FF,
A14300:
A15320:
FS,FFA14395:
10, A1640:
FS, A14445:
FS, A1680:
FS,FS
A14480: FS, A14585:
21 FS, A14620: FS, A14670: FS P1 - CSA Cont ractor Mobilization and Site Preparation
1101 P4-2470 P1 - MEPI (Mechanical & Piping) Contractor Mobilization and Site Preparation MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1680: FS,A14270:
A1640: FS,
FS A14505: FS, A14640: FS, A14605: FS, A14690:
114 FS P1 - MEPI (Mechanical & Piping) Contractor Mobilization and Site Preparation
1102 P4-2465 P1 - Fire Fighting System Site Integration FF-01 20 Feb-17-26 Mar-16-26 A14475: FS, A14650: FS, A14700:
P4-2460:
FS FF 24 P1 - Fire Fighting System Site Integration
1103 P4-2460 P1 - Mechanical Completion MEPI-01 5 Mar-13-26 Mar-19-26 A14275: FF, A14365: FF, A14405:
P4-2450:
FF, P4-2465:
FS, P4a-10:
FF,FS
A14530: FF, A14615: FF, A14665:
21 FF, A14715: FF P1 - Mechanical Completion
1104 P1.1 Clearing and Area Preparation Jan-30-26, P1.1 Clearing and Area Preparation
1105 A14445 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2435: FS A14455: FS, A14460: FS 55 Dismantle
1106 A14460 Pilling CSA-02 30 Aug-15-25 Sep-25-25 A14445: FS A14455: FS 55 Pilling
1107 A14455 Civil Construction CSA-02 30 Sep-26-25 Nov-06-25 A14445: FS, A14460: FS A14435: FS 55 Civil Construction
1108 A14435 Structural Construction CSA-02 30 Nov-07-25 Dec-18-25 A14455: FS, A14470: FS, A14490:
A14420:FS,
FSA14590: FS, A14625: FS, A14675: FS 55 Structural Construction
1109 A14420 Architectural Construction CSA-02 30 Dec-19-25 Jan-29-26 A14435: FS A14405: FS 55 Architectural Construction
1110 A14405 Unit Mechanical Completion MEPI-01 1 Jan-30-26 Jan-30-26 A14420: FS P4-2460: FF 55 Unit Mechanical Completion
1111 P1.2 Construction of Dumping Mar-19-26, P1.2 Construction of Dumping
1112 A14300 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2435: FS A14465: FS 21 Dismantle
1113 A14465 Pilling CSA-02 22 Aug-15-25 Sep-15-25 A14300: FS A14470: FS 21 Pilling
1114 A14470 Civil Construction CSA-02 22 Sep-16-25 Oct-15-25 A14465: FS A14435: FS, A14310: FS 21 Civil Construction
1115 A14310 Structural Construction CSA-02 22 Oct-16-25 Nov-14-25 A14470: FS A14290: FS 21 Structural Construction
1116 A14290 Architectural Construction CSA-02 22 Nov-17-25 Dec-16-25 A14310: FS A14270: FS 21 Architectural Construction
1117 A14270 Equipment Installation MEPI-01 22 Dec-17-25 Jan-15-26 A14290: FS, P4-2470: FS A14285: FS, A14475: FS 21 Equipment Installation
1118 A14285 Piping Installation MEPI-01 22 Jan-16-26 Feb-16-26 A14270: FS A14280: FS, A14295: FS 21 Piping Installation
1119 A14475 Fire Fighting Pipe Installation FF-01 22 Jan-16-26 Feb-16-26 A14270: FS, FF-01.PO: FS A14275: FS, P4-2465: FS 24 Fire Fighting Pipe Installation
1120 A14280 Electrical Installation MEPI-02 22 Feb-17-26 Mar-18-26 A14285: FS, P4-2475: FS A14275: FS 21 Electrical Installation
1121 A14295 Instrument and Autovalve Installation MEPI-02 22 Feb-17-26 Mar-18-26 A14285: FS, P4-2475: FS A14275: FS 21 Instrument and Autovalve Installation
1122 A14275 Unit Mechanical Completion MEPI-01 1 Mar-19-26 Mar-19-26 A14280: FS, A14295: FS, A14475:
P4-2460:
FS FF 21 Unit Mechanical Completion
1123 P1.3 Elevator and Provision of Belt conveyor from Dumping to connect Jetty belt Mar-19-26, P1.3 Elevator and Provision of Belt conveyor from Dumping to connect Jetty belt
1124 A14480 Dismantle CSA-02 5 Aug-08-25 Aug-14-25 P4-2435: FS A14485: FS 21 Dismantle
1125 A14485 Pilling CSA-02 22 Aug-15-25 Sep-15-25 A14480: FS A14490: FS 21 Pilling
1126 A14490 Civil Construction CSA-02 22 Sep-16-25 Oct-15-25 A14485: FS A14435: FS, A14495: FS 21 Civil Construction
1127 A14495 Structural Construction CSA-02 22 Oct-16-25 Nov-14-25 A14490: FS A14500: FS 21 Structural Construction
1128 A14500 Architectural Construction CSA-02 22 Nov-17-25 Dec-16-25 A14495: FS A14505: FS 21 Architectural Construction
1129 A14505 New Equipment Installation MEPI-01 22 Dec-17-25 Jan-15-26 A14500: FS, PEQ-16.DEL: FF
A14510:
20, PEQ-04.DEL10:
FS FS 20, P4-2470: FS 21 New Equipment Installation
1130 A14510 Piping Installation MEPI-01 22 Jan-16-26 Feb-16-26 A14505: FS A14520: FS, A14525: FS 21 Piping Installation
1131 A14520 Electrical Installation MEPI-02 22 Feb-17-26 Mar-18-26 A14510: FS, P4-2475: FS A14530: FS 21 Electrical Installation
1132 A14525 Instrument and Autovalve Installation MEPI-02 22 Feb-17-26 Mar-18-26 A14510: FS, INS-01.DEL70:A14530:
FF 20, P4-2475:
FS FS 21 Instrument and Autovalve Installation
1133 A14530 Unit Mechanical Completion MEPI-01 1 Mar-19-26 Mar-19-26 A14520: FS, A14525: FS P4-2460: FF 21 Unit Mechanical Completion
1134 P1.5 Road Pavement Dec-12-25, P1.5 Road Pavement
1135 A14395 Civil- Reinforcement CSA-02 30 Aug-08-25 Sep-18-25 P4-2435: FS A14380: FS 90 Civil- Reinforcement
1136 A14380 Architectural- Reinforcement CSA-02 30 Sep-19-25 Oct-30-25 A14395: FS A14360: FS 90 Architectural- Reinforcement
1137 A14360 Architectural Electrical (lighting, lightening, grounding, etc.) MEPI-01 30 Oct-31-25 Dec-11-25 A14380: FS A14365: FS 90 Architectural Electrical (lighting, lightening, grounding, etc.)
1138 A14365 Unit Mechanical Completion MEPI-01 1 Dec-12-25 Dec-12-25 A14360: FS P4-2460: FF 90 Unit Mechanical Completion
1139 P1.6 Construction of Truck Scale Mar-12-26, P1.6 Construction of Tr uck Scale
1140 A14620 Pilling CSA-02 22 Aug-08-25 Sep-08-25 P4-2435: FS A14625: FS 26 Pilling
1141 A14625 Civil Construction CSA-02 22 Sep-09-25 Oct-08-25 A14620: FS A14435: FS, A14630: FS 26 Civil Construction
1142 A14630 Structural Construction CSA-02 22 Oct-09-25 Nov-07-25 A14625: FS A14635: FS 26 Structural Construction
1143 A14635 Architectural Construction CSA-02 22 Nov-10-25 Dec-09-25 A14630: FS A14640: FS 26 Architectural Construction
1144 A14640 New Equipment Installation MEPI-01 22 Dec-10-25 Jan-08-26 A14635: FS, PEQ-03.DEL: FF
A14645:
20, P4-2470:
FS, A14650:
FS FS 26 New Equipment Installation
1145 A14645 Piping Installation MEPI-01 22 Jan-09-26 Feb-09-26 A14640: FS A14655: FS, A14660: FS 26 Piping Installation
1146 A14650 Fire Fighting Pipe Installation FF-01 22 Jan-09-26 Feb-09-26 A14640: FS, FF-01.PO: FS A14665: FS, P4-2465: FS 29 Fire Fighting Pipe Installation
1147 A14655 Electrical Installation MEPI-02 22 Feb-10-26 Mar-11-26 A14645: FS, P4-2475: FS A14665: FS 26 Electrical Installation
1148 A14660 Instrument and Autovalve Installation MEPI-02 22 Feb-10-26 Mar-11-26 A14645: FS, INS-01.DEL80:A14665:
FF 20, INS-01.DEL40:
FS FF 20, INS-01.DEL45: FF 20,26
P4-2475: FS Instrument and Autovalve Installation
1149 A14665 Unit Mechanical Completion MEPI-01 1 Mar-12-26 Mar-12-26 A14655: FS, A14660: FS, A14650:
P4-2460:
FS FF 26 Unit Mechanical Completion
1150 P1.7 Construction of Scale House Feb-10-26, P1.7 Construction of Scale House
1151 A14585 Pilling CSA-02 22 Aug-08-25 Sep-08-25 P4-2435: FS A14590: FS 48 Pilling
1152 A14590 Civil Construction CSA-02 22 Sep-09-25 Oct-08-25 A14585: FS A14435: FS, A14595: FS 48 Civil Construction
1153 A14595 Structural Construction CSA-02 22 Oct-09-25 Nov-07-25 A14590: FS A14600: FS 48 Structural Construction
1154 A14600 Architectural Construction CSA-02 22 Nov-10-25 Dec-09-25 A14595: FS A14605: FS 48 Architectural Construction
1155 A14605 Piping Installation MEPI-01 22 Dec-10-25 Jan-08-26 A14600: FS, P4-2470: FS A14610: FS 48 Piping Installation
1156 A14610 Instrument and Autovalve Installation MEPI-02 22 Jan-09-26 Feb-09-26 A14605: FS, P4-2475: FS A14615: FS 48 Instrument and Autovalve Installation
1157 A14615 Unit Mechanical Completion MEPI-01 1 Feb-10-26 Feb-10-26 A14610: FS P4-2460: FF 48 Unit Mechanical Completion
1158 P1.8 Feeding hopper Mar-12-26, P1.8 Feeding hopper
1159 A14670 Pilling CSA-02 22 Aug-08-25 Sep-08-25 P4-2435: FS A14675: FS 26 Pilling
1160 A14675 Civil Construction CSA-02 22 Sep-09-25 Oct-08-25 A14670: FS A14435: FS, A14680: FS 26 Civil Construction
1161 A14680 Structural Construction CSA-02 22 Oct-09-25 Nov-07-25 A14675: FS A14685: FS 26 Structural Construction
1162 A14685 Architectural Construction CSA-02 22 Nov-10-25 Dec-09-25 A14680: FS A14690: FS 26 Architectural Construction
1163 A14690 New Equipment Installation MEPI-01 22 Dec-10-25 Jan-08-26 A14685: FS, P4-2470: FS A14695: FS, A14700: FS 26 New Equipment Installation
1164 A14695 Piping Installation MEPI-01 22 Jan-09-26 Feb-09-26 A14690: FS A14705: FS, A14710: FS 26 Piping Installation
1165 A14700 Fire Fighting Pipe Installation FF-01 22 Jan-09-26 Feb-09-26 A14690: FS, FF-01.PO: FS A14715: FS, P4-2465: FS 29 Fire Fighting Pipe Installation
1166 A14705 Electrical Installation MEPI-02 22 Feb-10-26 Mar-11-26 A14695: FS, P4-2475: FS A14715: FS 26 Electrical Installation
1167 A14710 Instrument and Autovalve Installation MEPI-02 22 Feb-10-26 Mar-11-26 A14695: FS, P4-2475: FS A14715: FS 26 Instrument and Autovalve Installation
1168 A14715 Unit Mechanical Completion MEPI-01 1 Mar-12-26 Mar-12-26 A14705: FS, A14710: FS, A14700:
P4-2460:
FS FF 26 Unit Mechanical Completion
1169 J0. Jetty Mar-12-26, J0. Jetty
1170 P4-2485 J0 - Temp. Road & Fence/Power/Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS P4-2480: FF 107 J0 - Temp. Road & Fence/Power/Water/Office etc..
1171 P4-2520 J0 - EAI Installation Contractor Mobilization and Site Preparation MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A14730: FS, A14745: FS, A14970: FS, A14985: FS 227 J0 - EAI Installation Contractor Mobilization and Site Preparation
1172 P4-2570 J0 - Jetty Improvement and Construnction Contractor Mobilization CSA-03 20 Mar-20-25 Apr-16-25 CSA-03.PO: FS P4-2480: FF, A14865: FS, A15165: FS 107 J0 - Jetty Improvement and Construnction Contractor Mobilization
1173 P4-2480 J0 - CSA Contractor Mobi lization and Si te Prepar ation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, P4-2485: FF,
A14905:
P4-2570:
FS, FF
A15000:
, A15325:
FS,FF
A15125:
10, A1680:
FS, A15145:
FS, A1640:
FS, FS
A14805:
26 FS J0 - CSA Contract or Mobi lization and Si te Prepar at ion
1174 P4-2515 J0 - MEPI (Mechanical & Piping) Contractor Mobilization and Site Preparation MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1640: FS,A14735:
A1680: FS,
FS A14975: FS, A14720: FS 86 J0 - MEPI (Mechanical & Piping) Contractor Mobilization and Site Preparation
1175 P4-2510 J0 - Fire Fighting System Site Integration FF-01 20 Feb-10-26 Mar-09-26 A15005: FS P4-2505: FF 29 J0 - Fire Fighting System Site Integration
1176 P4-2505 J0 - Mechanical Completion MEPI-01 5 Mar-06-26 Mar-12-26 A14725: FF, A14780: FF, P4-2510:
P4-2495:
FF,FS,
A14965:
P4a-10:
FF,FS
A14860: FS, A15135: FS, A15155:
26 FS, A14895: FS J0 - Mechanical Completion
1177 J0.1 Modification of Jetty Pier to accommodate the crane and tower Jan-23-26, J0.1 Modification of Jetty Pier to accommodate the crane and tower
1178 A14805 Pilling CSA-02 30 Aug-08-25 Sep-18-25 P4-2480: FS A14800: FS 60 Pilling
1179 A14800 Civil Construction CSA-02 30 Sep-19-25 Oct-30-25 A14805: FS A14790: FS 60 Civil Construction
1180 A14790 Structural Construction CSA-02 30 Oct-31-25 Dec-11-25 A14800: FS, A14865: FS, A14900:
A14785:FS,
FSA14995: FS, A15165: FS 60 Structural Construction
1181 A14785 Architectural Construction CSA-02 30 Dec-12-25 Jan-22-26 A14790: FS A14780: FS 60 Architectural Construction
1182 A14780 Unit Mechanical Completion MEPI-01 1 Jan-23-26 Jan-23-26 A14785: FS P4-2505: FF 60 Unit Mechanical Completion
1183 J0.3 Installtion of Jetty Crane, hopper, st eel tower Dec-18-25, J0.3 Installtion of Jetty Crane, hopper, steel tower
1184 A14720 New Equipment Installation MEPI-01 30 Aug-08-25 Sep-18-25 P4-2515: FS, PEQ-15.DEL: A14735:
FF 20 FS 86 New Equipment Installation
1185 A14735 Piping Installation MEPI-01 30 Sep-19-25 Oct-30-25 A14720: FS, P4-2515: FS A14730: FS, A14745: FS 86 Piping Installation
1186 A14730 Electrical Installation MEPI-02 30 Oct-31-25 Dec-11-25 A14735: FS, P4-2520: FS A14725: FS 86 Electrical Installation
1187 A14745 Instrument and Autovalve Installation MEPI-02 30 Oct-31-25 Dec-11-25 A14735: FS, P4-2520: FS, INS-01.DEL60:
A14725: FS FF 20 86 Instrument and Autovalve Installation
1188 A14725 Unit Mechanical Completion MEPI-01 5 Dec-12-25 Dec-18-25 A14730: FS, A14745: FS P4-2505: FF 86 Unit Mechanical Completion
1189 P1.3 Elevator andJ0.4 Pier Assesment Dec-11-25, P1.3 Elevator andJ0.4 Pier Assesment
1190 A14865 Civil- Reinforcement CSA-03 30 Apr-17-25 May-28-25 P4-2570: FS A14790: FS, A14860: FS 171 Civil- Reinforcement
1191 A14860 Structural- Reinforcement CSA-03 30 Oct-31-25 Dec-11-25 A14865: FS, A15165: FS P4-2505: FS 86 Structural- Reinforcement
1192 J0.5 Handrail/ Fencing Oct-30-25, J0.5 Handrail/ Fencing
1193 A15125 Civil Construction CSA-02 30 Aug-08-25 Sep-18-25 P4-2480: FS A15135: FS 116 Civil Construction
1194 A15135 Structural Construction CSA-02 30 Sep-19-25 Oct-30-25 A15125: FS P4-2505: FS 116 Structural Construction
1195 J0.6 Security Post + Gate Oct-30-25, J0.6 Security Post + Gate
1196 A15145 Civil Construction CSA-02 30 Aug-08-25 Sep-18-25 P4-2480: FS A15155: FS 116 Civil Construction
1197 A15155 Structural Construction CSA-02 30 Sep-19-25 Oct-30-25 A15145: FS P4-2505: FS 116 Structural Construction
1198 J0.7 Jetty Improvement for Breasting dolphin and Intermediate feders Dec-11-25, J 0.7 Jetty Improvement for Breasti ng dolphin and Intermediate feders
1199 A14905 Pilling CSA-02 30 Aug-08-25 Sep-18-25 P4-2480: FS A14900: FS, A15165: FS 60 Pilling
1200 A14900 Civil Construction CSA-02 30 Sep-19-25 Oct-30-25 A14905: FS A14790: FS, A14895: FS 60 Civil Construction
1201 A15165 Civil- Reinforcement CSA-03 30 Sep-19-25 Oct-30-25 P4-2570: FS, A14905: FS A14790: FS, A14860: FS 60 Civil- Reinforcement
1202 A14895 Structural Construction CSA-02 30 Oct-31-25 Dec-11-25 A14900: FS P4-2505: FS 86 Structural Construction
1203 J0.8 Copra Unloading belt conveyor 240 meters long ( Y1???) Mar-12-26, J0.8 Copra Unloading belt conveyor 240 meters long ( Y1???)
1204 A15000 Pilling CSA-02 22 Aug-08-25 Sep-08-25 P4-2480: FS A14995: FS 26 Pilling
1205 A14995 Civil Construction CSA-02 22 Sep-09-25 Oct-08-25 A15000: FS A14790: FS, A14990: FS 26 Civil Construction
1206 A14990 Structural Construction CSA-02 22 Oct-09-25 Nov-07-25 A14995: FS A14980: FS 26 Structural Construction
1207 A14980 Architectural Construction CSA-02 22 Nov-10-25 Dec-09-25 A14990: FS A14960: FS 26 Architectural Construction
1208 A14960 New Equipment Installation MEPI-01 22 Dec-10-25 Jan-08-26 A14980: FS, PEQ-14.DEL: FF
A14975:
22, PEQ-16.DEL10:
FS, A15005: FS
FF 20 26 New Equipment Installation
1209 A14975 Piping Installation MEPI-01 22 Jan-09-26 Feb-09-26 A14960: FS, P4-2515: FS A14970: FS, A14985: FS 26 Piping Installation
1210 A15005 Fire Fighting Pipe Installation FF-01 22 Jan-09-26 Feb-09-26 A14960: FS, FF-01.PO: FS A14965: FS, P4-2510: FS 29 Fire Fighting Pipe Installation
1211 A14970 Electrical Installation MEPI-02 22 Feb-10-26 Mar-11-26 A14975: FS, P4-2520: FS A14965: FS 26 Electrical Installation
1212 A14985 Instrument and Autovalve Installation MEPI-02 22 Feb-10-26 Mar-11-26 A14975: FS, P4-2520: FS, INS-01.DEL65:
A14965: FS FF 20, INS-01.DEL50: FF 20 26 Instrument and Autovalve Installation
1213 A14965 Unit Mechanical Completion MEPI-01 1 Mar-12-26 Mar-12-26 A14970: FS, A14985: FS, A15005:
P4-2505:
FS FF 26 Unit Mechanical Completion
1214 T1. Tank Farm A Apr-17-26, T1. Tank Farm A
1215 P4-2530 T1 - Temp. Road & Fence/Power/Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS P4-2525: FF 81 T1 - Temp. Road & Fence/Power/Water/Office etc..
1216 P4-2565 T1 - EAI Installation Contractor Mobilization MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A15020: FS, A15035: FS 231 T1 - EAI Installation Contractor Mobilization
1217 P4-2525 T1 - CSA Contractor Mobi lization and Si te Prepar ation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, P4-2530: FF,
A15100:
A15330:
FSFF 10, A1680: FS, A1640: FS 0 T1 - CSA Contract or Mobi lization and Si te Prepar at ion
1218 P4-2560 T1 - MEPI (Mechanical & Piping) Contractor Mobilization MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1680: FS,A15025:
A1640: FS,
FS A15010: FS 90 T1 - MEPI (Mechanical & Piping) Contractor Mobilization
1219 P4-2555 T1 - Fire Fighting System Site Integration FF-01 20 Mar-06-26 Apr-02-26 A15110: FS P4-2550: FF 11 T1 - Fire Fighting System Site Integration
1220 P4-2550 T1 - Mechanical Completion MEPI-01 5 Apr-13-26 Apr-17-26 A15015: FF, P4-2555: FF P4-2540: FS, P4a-10: FS 0 T1 - Mechanical Completion
1221 T1. Tank Farm A (Including Handrail&Fencing) Apr-17-26, T1. Tank Farm A (Includi ng Handrail&Fenc ing)
1222 A15100 Civil Construction CSA-02 30 Aug-08-25 Sep-18-25 P4-2525: FS A15045: FS 0 Civil Construction
1223 A15045 Structural Construction CSA-02 30 Sep-19-25 Oct-30-25 A15100: FS A15030: FS 0 Structural Construction
Actual Work Critical Remaining Work Summary Page 6 of 7 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Project Herring Level 4/5 Master Schedule - Developing (No constraint) Herring L4/L5 Layout Nov-18-24 05:21
# Activity ID Activity Name PKG NO. At Completion Start Finish Predecessor Details Successor Details Total 2024 2025 2026 2027
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1224 A15030 Architectural Construction CSA-02 30 Oct-31-25 Dec-11-25 A15045: FS A15010: FS, A15115: FS 0 Architectural Construction
1225 A15010 New Equipment Installation MEPI-01 30 Dec-12-25 Jan-22-26 A15030: FS, P4-2560: FS, PEQ-04.DEL:
A15025: FS, A15110:
FF 20, PEQ-04.DEL5:
FS FF 20, PEQ-04.DEL10:
0 FF 20, PEQ-04.DEL15: FF 20, PEQ-04.DEL20: FF 20 New Equipment Installation
1226 A15115 Existing Equipment Retrofit ??? 30 Dec-12-25 Jan-22-26 A15030: FS A15025: FS, A15110: FS 0 Existing Equipment Retrofit
1227 A15025 Piping Installation MEPI-01 30 Jan-23-26 Mar-05-26 A15010: FS, P4-2560: FS, A15115:
A15020:FS
FS, A15035: FS 0 Piping Installation
1228 A15110 Fire Fighting Pipe Installation FF-01 30 Jan-23-26 Mar-05-26 A15010: FS, FF-01.PO: FS, A15015:
A15115: FS,
FS P4-2555: FS 11 Fire Fighting Pipe Installation
1229 A15020 Electrical Installation MEPI-02 30 Mar-06-26 Apr-16-26 A15025: FS, P4-2565: FS A15015: FS 0 Electrical Installation
1230 A15035 Instrument and Autovalve Installation MEPI-02 30 Mar-06-26 Apr-16-26 A15025: FS, P4-2565: FS, INS-01.DEL55:
A15015: FS FF 20 0 Instrument and Autovalve Installation
1231 A15015 Unit Mechanical Completion MEPI-01 1 Apr-17-26 Apr-17-26 A15020: FS, A15035: FS, A15110:
P4-2550:
FS FF 0 Unit Mechanical Completion
1232 T2. Tank Farm B Apr-17-26, T2. Tank Farm B
1233 P4-2590 T2 - Temp. Road & Fence/Power/Water/Office etc.. CSA-01 20 Mar-20-25 Apr-16-25 CSA-01.PO: FS P4-2580: FF 81 T2 - Temp. Road & Fence/Power/Water/Office etc..
1234 P4-2660 T2 - EAI Installation Contractor Mobilization MEPI-02 20 Mar-20-25 Apr-16-25 MEPI-02.PO: FS A15195: FS, A15225: FS 231 T2 - EAI Installation Contractor Mobilization
1235 P4-2580 T2 - CSA Contractor Mobi lization and Si te Prepar ation CSA-02 20 Jul-11-25 Aug-07-25 CSA-02.PO: FS, P4-2590: FF,
A15245:
A15335:
FSFF 10, A1640: FS, A1680: FS 0 T2 - CSA Contract or Mobi lization and Si te Prepar at ion
1236 P4-2650 T2 - MEPI (Mechanical & Piping) Contractor Mobilization MEPI-01 20 Jul-11-25 Aug-07-25 MEPI-01.PO: FS, A1640: FS,A15205:
A1680: FS,
FS A15175: FS 90 T2 - MEPI (Mechanical & Piping) Contractor Mobilization
1237 P4-2640 T2 - Fire Fighting System Site Integration FF-01 20 Mar-06-26 Apr-02-26 A15255: FS P4-2630: FF 11 T2 - Fire Fighting System Site Integration
1238 P4-2630 T2 - Mechanical Completion MEPI-01 5 Apr-13-26 Apr-17-26 A15185: FF, P4-2640: FF P4-2610: FS, P4a-10: FS 0 T2 - Mechanical Completion
1239 T2. Tank Farm B (I ncluding Handrail&Fenci ng) Apr-17-26, T2. Tank Farm B (Including Handrail&Fenc ing)
1240 A15245 Civil Construction CSA-02 30 Aug-08-25 Sep-18-25 P4-2580: FS A15235: FS 0 Civil Construction
1241 A15235 Structural Construction CSA-02 30 Sep-19-25 Oct-30-25 A15245: FS A15215: FS 0 Structural Construction
1242 A15215 Architectural Construction CSA-02 30 Oct-31-25 Dec-11-25 A15235: FS A15175: FS, A15265: FS 0 Architectural Construction
1243 A15175 New Equipment Installation MEPI-01 30 Dec-12-25 Jan-22-26 A15215: FS, P4-2650: FS A15205: FS, A15255: FS 0 New Equipment Installation
1244 A15265 Existing Equipment Retrofit ??? 30 Dec-12-25 Jan-22-26 A15215: FS A15205: FS, A15255: FS 0 Existing Equipment Retrofit
1245 A15205 Piping Installation MEPI-01 30 Jan-23-26 Mar-05-26 A15175: FS, P4-2650: FS, A15265:
A15195:FS
FS, A15225: FS 0 Piping Installation
1246 A15255 Fire Fighting Pipe Installation FF-01 30 Jan-23-26 Mar-05-26 A15175: FS, FF-01.PO: FS, A15185:
A15265: FS,
FS P4-2640: FS 11 Fire Fighting Pipe Installation
1247 A15195 Electrical Installation MEPI-02 30 Mar-06-26 Apr-16-26 A15205: FS, P4-2660: FS A15185: FS 0 Electrical Installation
1248 A15225 Instrument and Autovalve Installation MEPI-02 30 Mar-06-26 Apr-16-26 A15205: FS, P4-2660: FS A15185: FS 0 Instrument and Autovalve Installation
1249 A15185 Unit Mechanical Completion MEPI-01 1 Apr-17-26 Apr-17-26 A15195: FS, A15225: FS, A15255:
P4-2630:
FS FF 0 Unit Mechanical Completion
1250 Commissioning and Start-up May-15-26, Commissioning and Start-up
1251 G0. General Apr-14-26, G0. General
1252 P4-2140 G0 - Commissioning and Start-up Cargill 20 Mar-18-26 Apr-14-26 P4-2160: FS, P4-2130: FS, P4b-01:
P4-2160:FS
FF 23 G0 - Commissioning and Start-up
1253 B0. Administ rative Buildings May-07-26, B0. Administ rati ve Buildings
1254 P4-2210 B0 - Commissiong and Start-up Cargill 20 Apr-10-26 May-07-26 P4-2230: FS, P4-2200: FS P4b-01: FS 6 B0 - Commissiong and Start-up
1255 B1. Dry Copra Warehouse Mar-26-26, B1. Dry Copra War ehouse
1256 P4-2250 B1 - Commissiong and Start-up Cargill 20 Feb-27-26 Mar-26-26 P4-2260: FS P4b-01: FS 36 B1 - Commissiong and Start-up
1257 B2. Oil Mill Operations May-14-26, B2. Oil Mill Operations
1258 P4-2285 B2 - Commissiong and Start-up Cargill 20 Apr-17-26 May-14-26 P4-2295: FS P4b-01: FS 1 B2 - Commissiong and Start-up
1259 B3. Finish Good Copra Warehouse Apr-17-26, B3. Finish Good Copra Warehouse
1260 P4-2330 B3 - Commissiong and Start-up Cargill 20 Mar-23-26 Apr-17-26 P4-2340: FS P4b-01: FS 20 B3 - Commissiong and Start-up
1261 U0. Utilities Apr-10-26, U0. Utilities
1262 P4-2410 U0 - Commissiong and Start-up Cargill 20 Mar-16-26 Apr-10-26 P4-2420: FS P4b-01: FS 25 U0 - Commissiong and Start-up
1263 U1. Utility Building Apr-17-26, U1. Utility Building
1264 P4-2370 U1 - Commissiong and Start-up Cargill 20 Mar-23-26 Apr-17-26 P4-2380: FS, MEQ-02.DEL:P4b-01:
FS, MEQ-01.DEL:
FS FS 20 U1 - Commissiong and Start-up
1265 P1. Dumping Area Apr-16-26, P1. Dumping Area
1266 P4-2450 P1 - Commissiong and Start-up Cargill 20 Mar-20-26 Apr-16-26 P4-2460: FS P4b-01: FS 21 P1 - Commissiong and Start-up
1267 J0. Jetty Apr-09-26, J0. Jetty
1268 P4-2495 J0 - Commissiong and Start-up Cargill 20 Mar-13-26 Apr-09-26 P4-2505: FS P4b-01: FS 26 J0 - Commissiong and Start-up
1269 T1. Tank Farm A May-15-26, T1. Tank Farm A
1270 P4-2540 T1 - Commissiong and Start-up Cargill 20 Apr-20-26 May-15-26 P4-2550: FS P4b-01: FS 0 T1 - Commissiong and Start-up
1271 T2. Tank Farm B May-15-26, T2. Tank Farm B
1272 P4-2610 T2 - Commissiong and Start-up Cargill 20 Apr-20-26 May-15-26 P4-2630: FS P4b-01: FS 0 T2 - Commissiong and Start-up
Actual Work Critical Remaining Work Summary Page 7 of 7 TASK filter: All Activities