Mos FF Piping
Mos FF Piping
1
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
1.0 INTRODUCTION 3
5.0 RESPONSIBILITIES 4
4
6.0 SEQUENCE AND METHOD 5
11.0 SUPERVISION 21
16.0 APPENDICES 24
2
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
1. INTRODUCTION
This Method Statement covers the installation of Pipes & Fittings for Fire Protection
Systems. This procedure is to define the method used to ensure that the Fire Protection
Systems installation has been carried out as per contract requirements.
The Fire Fighting system consists of Fire Pumps, Pipes & fittings, valves, zone control
valve and assemblies. It shall be used to protect the human life and storage material inside the
building in case of fire by providing Sprinklers, Hose Reels, Landing Valves and Breeching inlet.
The system shall operate by monitoring pressure and flow of water inside the pipe lines through
the flow switches interface with fire alarm system controls.
2. SCOPE OF WORKS
2.1.1 All materials received at site shall be inspected and stored properly upon
received.
2.1.2 All installation / construction works shall be carried out in compliance with
the approved shop drawings and project specification.
2.1.3 Installation and Inspection shall be conducted by PEW and demonstrated to
the inspector / Engineer.
2.1.4 Fire Fighting piping and fitting is installed in according with local Regulation
and Recommendation of International code of practice.
2.1.5 Verification of inspection checklists, which will be submitted later, shall be
witnessed, recorded, and signed by the site inspector/ representative.
3. Reference Documents
Drawings: APPROVED SHOP DRAWINGS/TYPICAL DETAIL DRAWINGS
3
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
The Drawings and Installation details of manufacturer should provide enough details for
the installation to be carried out. In the absence of any information, the above documents
should be referred.
5. RESPONSIBILITIES
5.1. The Construction Manager is over-all responsible for the implementation of the method
statement, to ensure that the team of engineers & foremen are aware of this MS and,
to ensure that all resources (labour, material and equipment) are available to carry out
the work as planned.
5.2. The Sr. Project Engineer is responsible to carry out the work as per approved MS. He
is also available to ensure adequate equipment for mobilization works are in place
prior to starting of work.
5.3. QA/QC Engineer is responsible to ensure work has been done as per the
specifications & approved Shop drawings, inspections are done as per Quality Control
Procedure and the inspection & test plan.
4
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
5.4. The Safety Engineer is responsible that all Safety precautions are in place, and that all
personnel on site are using required Personal Protective Equipment (helmet, gloves,
Safety shoes, coveralls, eye protection, etc.). He must also ensure that all relevant
permissions / work permits are available for the works.
6.1.1 Ensure that all safety requirements are in place in accordance with project
safety plan.
6.1.2 Ensure that the latest revision of the approved issued for construction
drawing is used.
6.1.3 All material will be ordered after approval of the drawings and technical
submittals.
6.1.4 All material will be transported to the site by the supplier and care shall be
taken by the store keeper to ensure that all the materials are not damaged
during transit.
6.1.5 Special care shall be taken by the storekeeper to protect the Firefighting
pipes & fittings from physical damage and direct sun light. All materials shall
be stored in shaded area
6.1.6 On receipt of the material at site, QA/QC Engineer/Site Engineer shall
inspect the material internally and inspection shall be offered to the Engineer
for approval in MDIR (Material Delivery Inspection Request) form.
6.1.7 Ensure all the material used, have passed receiving inspection in
accordance with QA procedures and are not damaged or defective. Any
5
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
non-conforming material must be labelled by storekeeper and returned to
quarantine area in accordance with QA procedure.
6.1.8 Ensure that all plumbers and helpers are aware of the correct materials
handling and installation procedures to ensure best quality of workmanship.
Training shall be provided by site engineers/supervisors as and when
required.
6.1.9 All Fire Fighting pipes & fittings shall be cleaned before installation.
6.1.10 Main contractor to ensure that prior to installation of Fire Fighting pipes, all
building surfaces to which supporting systems are being installed are
completed to acceptable tolerance and are in a suitably clean and dry
condition. Any unsatisfactory conditions are to be reported to Project
Manager and installation shall not proceed until corrective action measures
have been taken by him.
6.1.11 Ladders, step ladders and scaffoldings during construction will be used at
site as per the safety plan. All Ladders shall be inspected prior to use, and
scaffold shall be erected as per requirement and inspected and certified
prior to use.
6.1.12 Prior to start the work, engineers/supervisors from the execution team shall
ensure that the latest approved construction drawings are available at site.
6.1.13 Installation of Fire Fighting pipes shall be coordinated with architectural,
structural and MEP works for a fit for purpose installation. Any deviation
shall be intimated to the engineer for approval prior to start of the work.
6.1.14 Supervisor shall ensure equipment and correct tools are available for
installation and to achieve compliance with the contract requirements.
6
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
7
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
Keep all brushes clean and serviceable condition and thoroughly clean out brushes
before applying the paint.
The first coat paint on pipe or board finishing shall include such repeated touching up to
produce a uniform colour.
Apply the second coat and make sure that is it dry before shifting to the site
Paint only in a well-ventilated area for avoiding poisoning with thinner.
Attention to all material and floor on the painting area for avoid paint dripping
8
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
7.4 INSTALLATON OF DROP IN ANCHOR IN RCC SLAB
With reference to the approved floor plan shop drawings and the coordination drawings,
all routes shall be carefully marked at the bottom of the precast hollow core slab by
Foreman using a marker and chalk powder and shall be reconfirmed the routes with
related MEP services for any clashes.
Location of pipe support shall be marked on the soffit of precast Hollow core slabs as
shown in the approved shop drawing.
Marking the location shall be done by coordinating with Main Contractor in order to
prevent damage to the reinforcement strands. The measurement between reinforced
strands and from the edge of slab to reinforcement strand shall be followed as per the
construction drawing of hollow core precast slab.
The exact location at these strands can be identified with the above method and care
shall be taken to avoid damaging the same while drilling the required hole.
Holes of the required sizes shall be made by drilling machine where the marking has
been done.
Approved Double insulated tools, inspected, colour coded will be used
Supporting arrangements shall be provided with proper fixing arrangements.
Approved Anchor shall be inserted within the hole, utilizing the proper tools and
according to manufactures recommendation and site demonstration.
9
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
7.5 Installation of Pipe Supports
Pipe Support spacing shall be provided as per the relevant approvedshopsdrawing.
Pipe mains running in shafts shall be supported by galvanized split clamps at all levels,
so that the entire load can be uniformly distributed.
Pipeline supports shall not be attached to any plant or terminal unit.
All pipes shall be fixed and shall be run in parallel to the height as
Per approved co-ordinated shop drawing.
All open ends shall be protected by plastic caps and shall be removed at the time
Of straight joints for successive pipe connection.
Before installing any pipe work at high level, site engineer shall ensure that all dirt,
Scale and other foreign matter is removed from inside the piping before fixing.
Threaded pipes shall be joined with other pipes with approved boss white and jute/
Teflon tape for small size pipes.
10
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
The pipes shall be tightened with pipe wrench to the required tightening pressure.
Union/ Couplings of approved materials shall be provided for connecting the pipes.
Joints in threaded steel pipe shall conform to ANSI standards.
Ensure and confirm the Cut pipe ends shall be clean, square, and free from
Distortion.
Ensure and confirm the smooth and reamed to a distinct countersink.
All joints shall be carefully reamed and jointing compound/ tape should be applied
On male threads only.
Ensure and confirm the jointing between lengths of pipe work and fittings shall be
Carried out in such a manner that a continuous smooth bore is maintained with the
Joint.
Ensure and confirm, no lipping or protrusion of the jointing material with the
Jointing material within the bore of the joints.
Adequate lighting and no smoking to be ensured.
The pipes and fittings shall be painted as per approved material submittal.
11
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
65 1.98
80 1.98
90 2.1
100 2.1
125 2.1
160 2.15
200 2.33
12
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
Ensure and confirm the jointing between lengths of pipe work and fittings shall be carried
out in such a manner that a continuous smooth bore is maintained with the joint.
Ensure and confirm, no lipping or protrusion of the jointing material with the jointing
material within the bore of the joints.
The pipes and fittings shall be painted as per approved document.
All people should use scaffold for access to height, trained people will be only employed.
13
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
All the pipes shall be joined with reducing coupling wherever required as per
riser diagram.
Reducing coupling designed with rubber gasket prevent smaller pipe from
telescoping in to larger pipe during vertical assembly.
The pipes and coupling shall be tightened with torque spanner to the required
tightening torque.
Ensure and confirm the smooth and reamed to a distinct countersink.
Ensure and confirm the jointing between lengths of pipe work and fittings shall
be carried out in such a manner that a continuous smooth bore is
maintained with the joint.
Ensure and confirm, no lipping or protrusion of the jointing material with the
jointing material within the bore of the joints.
14
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
The pipes and fittings shall be painted as per approved document
All the pipes shall be joined with flange coupling wherever required as per
raiser diagram and site condition.
Flange coupling allows for direct connection of grooved system.
The pipes shall be tightened with torque spanner set to the required tightening
torque.
Ensure and confirm the smooth and reamed to a distinct countersink.
Ensure and confirm the jointing between lengths of pipe work and fittings shall
be carried out in such a manner that a continuous smooth bore is
maintained with the joint.
Ensure and confirm, no lipping or protrusion of the jointing material with the
jointing material within the bore of the joints.
The pipes and fittings shall be painted as per approved document.
All the pipes shall be joined with elbow wherever required as per shop drawing
and site requirement.
Elbow shall be joined with pipe using grooved coupling. Various types of elbow
shall be used such as 90°, 45° etc.
15
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
The pipes shall be tightened with torque spanner set to the required tightening
torque.
Ensure and confirm the smooth and reamed to a distinct countersink.
Ensure and confirm the jointing between lengths of pipe work and fittings shall
be carried out in such a manner that a continuous smooth bore is
maintained with the joint.
Ensure and confirm, no lipping or protrusion of the jointing material with the
Jointing material within the bore of the joints.
The pipes and fittings shall be painted as per approved document.
All the pipes shall be joined with reducing tee wherever required as per shop drawing.
Reducing Tees shall be joined with pipe where the branches are taken from main line.
The pipes shall be tightened with pipe wrench to the required tightening pressure.
Ensure and confirm the smooth and reamed to a distinct countersink.
Ensure and confirm the jointing between lengths of pipe work and fittings shall be carried
out in such a manner that a continuous smooth bore is maintained with the joint.
Ensure and confirm, no lipping or protrusion of the jointing material with the jointing
material within the bore of the joints.
The pipes and fittings shall be painted as per approved document.
16
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
Ensure and confirm the smooth and reamed to a distinct countersink.
Ensure and confirm the jointing between lengths of pipe work and fittings shall be carried
out in such a manner that a continuous smooth bore is maintained with the joint.
Ensure and confirm, no lipping or protrusion of the jointing material with the jointing
material within the bore of the joints.
The pipes and fittings shall be painted as per approved document.
All the pipes shall be joined with Concentric Reducer where the pipes are getting
reduced and concentric with main line as per shop drawing and site requirement.
All the pipes shall be joined with Eccentric Reducer where the pipes are getting reduced
and off set with main line as per shop drawing.
The pipes shall be tightened with torque spanner to the required tightening torque.
Ensure and confirm the smooth and reamed to a distinct countersink of the pipes.
Ensure and confirm the jointing between lengths of pipe work and fittings shall be
carried out in such a manner that a continuous smooth bore is maintained with the joint.
17
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
Ensure and confirm, no lipping or protrusion of the jointing material with the jointing
material within the bore of the joints.
The pipes and fittings shall be painted as per approved document.
7.16 Pipe Fittings (Gate Valves, Drain Valves, Butterfly Valve, Non Return Valve,
Pressure Reducing Valve, Lock shield Valve, Landing Valve, Breeching Inlet
Valve, Alarm Check Valve)
The above fittings shall be provided as per approved shop drawing as applicable
wherever it is required.
The above shall be installed at locations where easy accessible point available for easy
maintenance.
Clean pipes, flanges and coupling before installation begin.
Check if the valve closes hard may be due to debris lodged in the sealing area.
The valve never should be forced to seal by a wrench to the hand wheel. These distort
the valve components (or) score the sealing surface.
The inlet and outlet pipe adjacent to the valve should be properly supported to prevent
excessive stress on the valve body.
The valve should not be used to force a pipe line in to the position as this may result in
distortion of the valve body.
Ensure and confirm that fitting shall be threaded type and shall be fixed with Teflon/
Shellac and boss white & jute up to 50mm die pipes.
Ensure and confirm that fittings sizes above 50mm to 500 mm shall be Grooved type
with ceiling gasket rubber rings, as per approved material list.
18
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
Automatic air vents shall be provided at the highest point to purge free air that high
pressure during normal operation.
7.18 Drain Valves
The drain valves shall be installed to blow-off sediments from strainers and tanks at
lower level.
The drain points shall be provided at low points for draining and locate where easily
accessible.
7.19 Visual Inspection of Installed Pipe work
The system shall be visually inspected by engineer to ensure that the correct
installation procedures have been followed and that the pipes and fittings are
adequately supported and restrained in the prescribed manner. The inspection shall be
offered for Engineer’s approval.
7.20 Painting
Pipes and fittings shall be painted with approved paint & primer maintaining DFT of 80
to 90 microns.
7.21 Hydraulic Testing
o Hydraulic testing for firefighting pipe shall be carried out with certificates
machine.
o There should be competent person for the hydro testing for firefighting pipes
o Before raising the pressure all open point should be closed.
o Proper barricade the area and put singes/board with emergency contact no.
o Keep monitoring the pressure and release the pressure before leaving the site
Completed works shall be protected from damage by ensuring pipes are protected
With end caps are provided on pipe ends to prevent entry of any foreign materials inside
19
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
Piping system.
Plastic end caps cover all open ends.
7.23 PROGRAM
As per Approved base line program
1) Labour
A. Construction Manager.
B. Project Engineer/Site Engineer – 1 No.
C. QA/QC Engineer/Inspector- 1 No.
D. Foreman/Charge-hand - 1 No.
E. Pipe fitter - 6 Nos.
2) Plant & Equipment
Fitters Tool Box shall consist of the following tools and tackles.
Spanners
Bench-vice with adjustable c-clamp as required.
Pipe grooving Machine
Working table to place tools on with required adjustable pipe supporters.
Hacksaw frame with blade.
General purpose tools.
20
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
Welding Machine.
3) Material Requirements
A. FF Pipes and fittings as per approved material submittal.
B. Grooved Couplings
C. Other associated materials as specified in Technical Submittals.
4) Personnel Protective Equipment:
A. Helmets
B. Safety Shoes
C. Coveralls
D. Masks
E. Hand Gloves
F. Safety Goggles
11.0 SUPERVISION
The supervision of these works will be under the direct control of the Construction Manager
assisted by the Project Engineer, Site Engineer and Foreman with the back – up from the
Technical Engineer. All Subcontractor works will be coordinated and controlled by the
Construction Manager. A full-time competent Subcontractor Project Supervisor shall be
deployed to the site.
21
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
22
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
Role and
Name Phone No. E-mail Address
Organization
[email protected]
Eng. MOMEN Project Manager +971 52 358 5218
m
Eng. Kamran Project Engineer/Naffco +971 50 176 3291 [email protected]
23
Project Name. B+G+3P+16 HOTEL APPARTMENT BUILDING
Client: PLATINIUM TOWER
Consultant: EDMAC ENGINEERING CONSULTANT
Main Contractor: NANTONG CONSTRUCTION GROUP
MEP Contractor NORTH FORTY THREE REAL ESTATE
Document No.: REV:
Document Title: Method statement of Installation of Fire
Fighting Pipes & Fitting
24