Comprehensive RICS-Based Quantity Surveying Interview Guide
Category A: General Knowledge and Basics
1. What are the primary responsibilities of a Quantity Surveyor?
• Preparing cost estimates, managing budgets, performing risk assessments, and ensuring financial
viability for construction projects.
2. Define Gross Internal Area (GIA) and Gross External Area (GEA).
• GIA: Total enclosed floor area within the external walls.
• GEA: Includes all external wall thicknesses and roofed areas.
3. What is the difference between a Bill of Quantities (BOQ) and a Schedule of Rates (SOR)?
• BOQ: Lists quantities of materials and work required.
• SOR: Provides unit rates for predefined work without specific quantities.
4. Explain retention in construction contracts.
• Retention is a percentage withheld from interim payments to ensure contract completion and
defect rectifications.
5. What is a Prime Cost Sum?
• An allowance for undefined work or materials, subject to later confirmation.
6. Define contingency sums in a project budget.
• Funds allocated for unforeseen or uncertain costs within the project.
7. What is the significance of the Base Date in FIDIC contracts?
• Establishes a reference for determining foreseeable conditions and risks.
8. Describe the process of value engineering.
• Analyzing functions of components to optimize costs without compromising quality.
9. What is a Final Account in construction?
• A comprehensive statement of the project’s cost upon completion, including adjustments for
variations and claims.
10. What are provisional sums?
• Budget allowances for work not fully defined at the time of tender.
Category B: Pre-Contract and Procurement
11. What are the common procurement methods in construction?
• Traditional (Design-Bid-Build), Design and Build, Management Contracting, and Construction
Management.
12. How do you prepare a cost plan?
• By breaking down project elements into costs using historical data and benchmarking.
13. What is two-stage tendering?
• Contractors submit preliminary tenders first, followed by detailed pricing after further design
development.
14. How do you ensure tender compliance?
• By thoroughly reviewing tender submissions against contract documents and client requirements.
15. Define Lump Sum and Re-measure contracts.
• Lump Sum: Fixed total price for the entire project.
• Re-measure: Payment based on actual quantities of work executed.
16. What is the role of a Quantity Surveyor in the pre-tender stage?
• Preparing cost estimates, BOQs, tender documents, and advising on procurement strategy.
17. Explain the term ‘lowest responsive bid.’
• The bid offering the lowest price while meeting all technical and contractual requirements.
18. What is a cost-plus contract?
• Contractor’s payment is based on actual costs plus an agreed profit margin.
19. What is the difference between direct and indirect costs?
• Direct Costs: Costs directly related to construction (e.g., labor, materials).
• Indirect Costs: Overheads and administrative expenses.
20. How do you prepare a tender report?
• By summarizing and analyzing received tenders, comparing them against evaluation criteria, and
providing recommendations.
Category C: Measurement and Valuation
21. What are the key principles of measurement?
• Following standard methods like RICS NRM or SMM7 for consistency and accuracy.
22. How do you measure excavation quantities?
• Using drawings to calculate the volume based on length × width × depth.
23. What is the purpose of a Schedule of Quantities?
• Provides a breakdown of work elements with quantities for pricing and progress monitoring.
24. Explain how you value variations.
• By assessing additional work against contract rates or agreed new rates.
25. How do you assess preliminaries in a BOQ?
• By allocating costs for site setup, temporary works, and management.
26. What is the role of dayworks in construction?
• Recording work performed on an hourly or daily basis, typically for unforeseen tasks.
27. How do you handle unmeasured work in contracts?
• Agree on rates and quantities through negotiation and remeasurement.
28. Define ‘profit margin’ in cost estimation.
• The percentage of profit added to project costs.
29. How do you calculate overhead recovery?
• Allocating indirect costs proportionally to project value or direct costs.
30. What are the challenges in measuring MEP works?
• Complexity due to intricate systems, variations, and coordination requirements.
Category D: Post-Contract and Cost Control
31. What is Cost Value Reconciliation (CVR)?
• Comparing project costs incurred to value earned to monitor financial performance.
32. How do you evaluate contractor claims for delays?
• By reviewing critical path analysis and substantiating claims with records.
33. What is the importance of a cash flow forecast?
• Ensures sufficient funding availability and identifies potential financial shortfalls.
34. How do you manage variations during a project?
• Through clear documentation, valuation, and client approval before execution.
35. What is the difference between liquidated and ascertained damages?
• Liquidated Damages: Pre-agreed amounts for delays.
• Ascertained Damages: Calculated after breaches occur.
36. How do you handle contractor’s interim valuations?
• By verifying progress on-site, measuring quantities, and checking compliance with contract terms.
37. What is retention release, and when does it occur?
• Releasing retained amounts upon achieving practical completion and rectifying defects.
38. How do you reconcile discrepancies in payment applications?
• By comparing contractor claims against site records and contract terms.
39. How do you approach final account negotiations?
• By ensuring all variations and claims are agreed upon, supported by clear documentation.
40. What is the role of a Quantity Surveyor in dispute resolution?
• Acting as an expert witness, providing cost analysis, and mediating between parties.
Category E: Advanced Scenarios and Technical Knowledge
41. What are the key obligations of the Employer under FIDIC contracts?
• Ensuring site access, issuing instructions, and making timely payments.
42. How do you interpret Sub-Clause 20.1 (Contractor’s Claims) in FIDIC?
• The contractor must notify claims within 28 days of becoming aware of the event.
43. Explain the purpose of Sub-Clause 13.1 in FIDIC regarding variations.
• Allows the Engineer to instruct changes to the works without invalidating the contract.
44. How do you handle disputes arising from an Engineer’s Determination under FIDIC?
• Escalate to Dispute Adjudication Board (DAB) or arbitration as per Sub-Clause 20.4.
45. What is the difference between NEC Option A and Option C?
• Option A: Lump sum with activity schedule. Option C: Target cost with pain/gain share.
46. Explain the term ‘Early Warning’ in NEC contracts.
• Parties must notify risks that could affect cost, time, or quality as soon as possible.
47. What is the significance of Defined Cost in NEC?
• It forms the basis for assessing payments and compensation events.
48. How do you apply Building Information Modeling (BIM) in cost planning?
• Use BIM models to extract quantities and integrate with cost databases for accurate budgeting.
49. What is 4D BIM, and how does it enhance project management?
• Adds scheduling data to 3D models for visualizing construction sequences.
50. How do you ensure data accuracy in a BIM-based QS environment?
• Regularly update models and validate extracted quantities against drawings.
51. Describe the process of assessing prolongation claims in FIDIC.
• Analyze delays on the critical path and evaluate cost impacts per Sub-Clause 8.4.
52. How do you manage concurrent delays in NEC contracts?
• Use project schedules to segregate contractor delays from employer-driven delays.
53. What is a Cost Breakdown Structure (CBS), and why is it important?
• A hierarchical breakdown of project costs to monitor and control expenses.
54. How do you apply escalation formulas for material price adjustments?
• Use base date indices to calculate cost changes for specified materials.
55. What is Earned Value Management (EVM), and how does it help in cost control?
• A technique to measure project performance against planned cost and time.
56. Explain how compensation events are managed in NEC contracts.
• Submit quotations for additional time or cost, assessed based on Defined Cost principles.
57. What are the limitations of BIM in Quantity Surveying?
• Inaccurate models, software compatibility issues, and lack of standardized practices.
58. How do you approach life cycle costing for sustainable projects?
• Assess initial, operational, and disposal costs to determine the most cost-effective solutions.
59. How do you use historical data in preparing feasibility studies?
• Leverage cost databases from similar projects to benchmark and forecast expenses.
60. What is the importance of Key Performance Indicators (KPIs) in project monitoring?
• KPIs track progress in areas like cost, time, and quality to ensure project success.