Lecture 5
Lecture 5
1
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT) is a project management tool used
to analyse and represent the tasks involved in completing a given project. It is used to
estimate the time and cost of a project by breaking it down into smaller, more
manageable components and charting the interdependencies between the tasks. PERT
charts allow project managers to identify and address critical paths and bottlenecks,
helping to ensure that projects are completed on time and within budget.
Purpose of PERT
Program Evaluation and Review Technique (PERT) is an important tool used in
project management. It is used to identify task dependencies and critical paths, plan
resources, estimate task duration, and identify potential risks. It also helps to define
and sequence activities, coordinate resources, and track progress. PERT is useful in
project planning because it allows project managers to accurately predict project
completion time, costs, and resource utilization. With PERT, project managers can also
identify potential risks and develop strategies to mitigate them. By using PERT, project
managers can ensure that projects are completed on time and within budget.
Advantages of PERT
Here are several benefits of using PERT in project management:
2
1. It helps maximize the use of resources.
2. It makes project planning more manageable.
3. It's useful even if there is little or no previous schedule data.
4. It enables project managers to better estimate or determine a more definite
completion date.
Disadvantages of PERT
Like any other method, PERT comes with its share of limitations:
1. In complex projects, many find PERT hard to interpret, so they may also use a
Gantt chart, another popular method for project management.
2. It can be tedious to update, modify, and maintain the PERT diagram.
3. It entails a subjective time analysis of activities and, for those who are less
experienced or are biased, this may affect the project’s schedule.
3
Course: construction Management
Class: 3 Mustansiriya University
ourse: construction Management
ass: 3 Lecture No.8 Mustansiriya University
Collage of Engineering /Water Recourse Dept.
ecture No.8 Prepared by: Assist. Prof. Dr. Faris Waleed Jawad
Collage of Engineering /Water Recourse Dept.
epared by: Assist. Prof. Dr. Faris Waleed Jawad
is the average time the task would require if the task were repeated on
is the average time the task would require if the task were repeated on
a number of occasions over an extended period of time ).
a number of occasions over an extended period of time ).
𝑶+𝟒𝒎+𝑷
te = ---------- (1)
𝑶+𝟒𝒎+𝑷 𝟔
te = ---------- (1)
𝟔
o: optimistic time, m= most likely time and P= probability
o: optimistic
Where: time, m=
o: optimistic mostm:
Time; likely time andtime;
P= probability
The mean time most
of thelikely
project andto:p: pessimistic time
equals
Themean
The meantime
time
ofof
thethe project
project equals
equals to: to:
TE = ∑𝑛𝑖=1 𝑡𝑒𝑖 for each activity on the critical path --------(2)
𝑛
TE = 𝑖=1 𝑡𝑒𝑖
∑ for each activity on the critical path --------(2)
𝝈 = 𝑺. 𝑫 = √𝚺𝑽 … … … … … … .. (𝟒)
4
:( ﻟﻔﻌﺎﻟﯿﺎت اﻟﻤﺴﺎر اﻟﺤﺮج ﻣﻦ اﻟﻤﻌﺎدﻟﺔ ادﻧﺎهσcp = Standard deviation) اﯾﺠﺎد اﻻﻧﺤﺮاف اﻟﻤﻌﯿﺎري-5
Figure
Figure (6-1): 1:Distribution
Distribution of normal
of normal probability
probability
Page 2 of 6.
5 Compute the area under curve (Z) to find the probability of project
completion at the duration previously predicted:
𝒁 = (𝑻𝒔 − 𝑻𝒆)/𝝈 = (𝐄𝐱𝐩𝐞𝐜𝐭𝐞𝐝 𝐓𝐢𝐦𝐞– 𝐌𝐞𝐚𝐧 𝐓𝐢𝐦𝐞)/𝐒𝐃 … … … … … … (𝟓)
TS: Specified time for the project (Should be given to find out if the probability of
project completion would be within that time or more than it).
TE: The expected time for the project (it represents the length of the critical path
calculated by critical path method).
Hint:
If Z≥ 0 then probability = 0.5 +A1
If Z≤ 0 then probability = 0.5 –A2
7. The probability can be obtained based on Z value.
5
Table 2: Normal Distribution Function
6
Course: construction Management
Class: 3 Mustansiriya University
Lecture No.8 Collage of Engineering /Water Recourse Dept.
Table 3:by:
Prepared Standard Normal
Assist. Prof. Table
Dr. Faris (Z) Jawad
Waleed
Example 5-1:
Example 6-1: For a particular activity of a project, time estimates received from two
For a particular activity of a project, time estimates received from two engineers X and
Y are shown as
engineers X follows:
and Y are shown as follows:
Engineer o m p |Pag e4
StateState
whowho
is more certain
is more about
certain thethe
about time forfor
time completion ofof
completion thethejob.
job?
Sol./ 7
The degree of uncertainty is measured by the variance of time estimates
Sol./
The degree of uncertainty is measured by the variance of time estimates.
The variance of time estimates for the times given by engineer X is computed using
the formula 𝑉𝑎𝑟𝑖𝑎𝑛𝑐𝑒 (𝑉) = 𝝈𝟐 = ((𝒑 − 𝒐)/𝟔)𝟐 … … … … … . (𝟑)
[(8 - 4)/6]2 = 0.4356
• The variance of time estimates for the times given by engineer Y is [(8 - 3)/6]2
= 0.69
• The variance of time estimates given by engineer Y is more. It is well known,
greater the variance, greater will be uncertainty.
• Thus, time estimates of engineer X have more certainty.
Note: If the project has two critical paths, the critical path with the higher variance
(standard deviation) should be chosen to calculate the specified probability.
Example 5-2:
If the mean duration of a project is 40 weeks. Find the following (use V= 14.58):
S.D = √∑𝑉
S.D = √14.58 = 3.82
Then: A=0.4049
P = 0.45
P= 0.5 + A
Sol:/
Solution:
Solution:
Activity O M P Te Variance
Activity O M P Te Variance
𝑷−𝑶 2
𝑶+𝟒𝒎+𝑷 ( )
=𝑶+𝟒𝒎+𝑷 𝑷−𝑶
( 𝟔)2
𝟔
= 𝟔
𝟔
1-2 6 9 15 9.5
1-2 6 9 15 9.5
1-3 2 4 8 4.3* (1)2
1-3 2 4 8 4.3* (1)2
2-4 6 8 10 8
2-4 6 8 10 8
3-5 4 7 12 7.3* (1.33)2
3-5 4 7 12 7.3* (1.33)2
4-6 0 0 0 0
4-6 0 0 0 0
4-9 2 3 6 3.3
4-9 2 3 6 3.3
5-6 4 7 9 6.8
5-6 4 7 9 6.8
2
5-7 5 9 11 8.7* (1)
2
5-7 5 9 11 8.7* (1)
6-8 1 2 4 2.2
6-8 1 2 4 2.2
2
7-8 2 3 5 3.2* (0.5)
2
7-8 2 3 5 3.2* (0.5)
2
8-10 2 4 5 3.8* (0.5)
2
8-10 2 4 5 3.8* (0.5)
9-10 1 4 6 3.8
9-10 1 4 6 3.8
10-11 2 3 5 3.2* (0.5)2
10-11 2 3 5 3.2* (0.5)2
|Pag e6
|Pag e6
9
S.D=√∑𝑉= SD≡√(1)2 +(1.33)2 +(1)2 +(0.5)2 +(10.5)2 +(0.5)2
S.D= 2.13
10
Collage of Engineering /Water Recourse Dept.
Prepared by: Assist. Prof. Dr. Faris Waleed Jawad
Project Evaluation Review Technique: PERT analysis technique.
Project Evaluation Review Technique: PERT analysis technique.
Example
Example 5-4:3
Example
ForFor
the the 3 datadata
project
project shown
shown in table
in table below.
below. Find
Find the the expected
expected timetime to achieve
to achieve the
For the
the project
probabilitydata
of shown
67%. in table
Assume below.
M=2O
probability of 67%. Assume M=2O and P=3O. Find
and the
P=3O. expected time to achieve
the probability of 67%. Assume M=2O and P=3O.
Activity 1-2 1-3 1-4 2-3 2-5 3-5 4-6 5-7 7-8 6-8 8-9 9-10
O
Activity 1-2 2 1-3 7 1-4 4 2-3 5 2-5 8 3-5 9 4-6 7 5-7 6 7-8 4 6-8 5 8-9 3 9-102
O 2 7 4 5 8 9 7 6 4 5 3 2
Sol/:
Solution:
Solution:
Activity O M P Te Variance
Activity O M P Te Variance
𝑷−𝑶 2
𝑶+𝟒𝒎+𝑷 ( )
=
𝑶+𝟒𝒎+𝑷 (
𝑷−𝑶𝟔 2
)
𝟔
= 𝟔
𝟔
1-2 2 4 6 4* (0.67)2
1-2 2 4 6 4* (0.67)2 2
1-3 7 14 21 14* (2.33)
1-3 7 14 21 14* (2.33)2
1-4 4 8 12 8
1-4 4 8 12 8
2-3 5 10 15 10* (1.67)2
2-3 5 10 15 10* (1.67)2
2-5 8 16 24 16
2-5 8 16 24 16
3-5 9 18 27 18* (3)2
3-5 9 18 27 18* (3)2
4-6 7 14 21 14
4-6 7 14 21 14
5-7 6 12 18 12* (2)2
5-7 6 12 18 12* (2)2 2
7-8 4 8 12 8* (1.33)
7-8 4 8 12 8* (1.33)2
6-8 5 10 15 10
6-8 5 10 15 10
8-9 3 6 9 6* (1)2
8-9 3 6 9 6* (1)2 2
9-10 2 4 6 4* (0.67)
9-10 2 4 6 4* (0.67)2
|Pag e1
|Pag e1
11
S.D = √∑ 𝑉 =
𝑆D = √(0.67)2 + (2.33)2 + (1.67)2 + (3)2 + (2)2 +(1.33)2 +(1)2 + + (0.67)2
S.D= 4.99
P=0.67= 0.5 + A
Then A= 0.67-0.5=0.17
From the Standard Normal Table (Z); Z= 0.44
Z= (𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑇𝑖𝑚𝑒−𝑀𝑒𝑎𝑛 𝑇𝑖𝑚𝑒)/SD=
0.44= (𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑇𝑖𝑚𝑒−62)/4.99
(0.44*4.99) = 𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑇𝑖𝑚𝑒−62
2.1956= 𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑇𝑖𝑚𝑒−62
Expected Time= 2.2 + 62
Then Expected time = 64.2 ~ 65 days.
12