Building Estimation Excel Sheet 1

The document provides a detailed building estimation quantity sheet, including calculations for earthwork, foundation, columns, beams, and brickwork. It outlines dimensions, quantities, and volumes for various construction elements, along with deductions for doors and windows. Additionally, it includes links for obtaining unprotected codes related to building estimation resources.

Uploaded by

Nandhu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
100 views11 pages

Building Estimation Excel Sheet 1

The document provides a detailed building estimation quantity sheet, including calculations for earthwork, foundation, columns, beams, and brickwork. It outlines dimensions, quantities, and volumes for various construction elements, along with deductions for doors and windows. Additionally, it includes links for obtaining unprotected codes related to building estimation resources.

Uploaded by

Nandhu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 11

To Get Unprot

http://civiconcepts.com/b

Centre Line =

H1=
H2=

V1

C.L.=

W1
To Get Unprotect Code Follow Link:
://civiconcepts.com/building-estimation-excel-sheet/#

Sum of Centre Line of Horizontal Wall +


Sum of Centre Line of Vertical Wall

0.15+3+0.3+4+0.15 (7.6 *3) 22.8


0.15+3+0.15 (3.3 * 1) 3.3
SUM 26.1
0.15+4+0.3+6+0.15 10.6*3 31.8

26.1 + 31.8 57.9

NO. OF JUNCTION 8
Column Size 300 mm x 300 mm

Beam Size 300 mm x 300 mm


Building Estimation h
QUANTITY SHEET
Widht/ Height/
Length
Sr. No. Item Description No. Breadth Depth Quantity
(m)
(m) (m)

1 Earthwork in Excavation in
Foundation:
Footing (1m x 1m) 12 1.50 1.50 1.50 40.50 cu m
Depth From GL = 1.5 m

2 P.P.C. in Foundation
Footing (1m x 1m) 12 1.3 1.3 0.1 2.03 cu m
Thickness = 0.10

3 Column(300mm x 300mm)
Base(1m x 1m) 12 1.00 1.00 0.15 1.80 cu m
Thickness = 0.15
Stem(0.30 x0.30)
height= 1.25+0.55 = 1.80 m 12 0.30 0.30 1.80 1.94 cu m
Total 3.74 cu m

4 Plinth Beam
Beam (300 mm x 300 mm)
Beam - 1 (3m length) 4 3.00 0.30 0.30 1.08 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.30 2.52 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.30 0.92 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.30 0.62 cu m
Total 5.14 cu m
5 Earth Filling in Plinth
Bed Room (3m x 4m) 1 3.00 4.00 0.45 5.40 cu m
Kitchen + Dining (4m x 4m) 1 4.00 4.00 0.45 7.20 cu m
Drawing (4m x 6m) 1 4.00 6.00 0.45 10.80 cu m
Bath/ W.C. (3m x 2.3m) 1 3.00 2.30 0.45 3.11 cu m
Varandah (3m x 3.4m) 1 3.00 3.40 0.45 4.59 cu m
Total 31.10 cu m

6 Damp Proof Course(DPC)


57.9 - ((0.3/2)*8)
56.7 1 56.70 0.30 17.01 sq. m

7 Brick Work in Super Structure


57.9 - ((0.3/2)*8)
56.7 1 56.70 0.30 3.00 51.03 cu m

Bath / WC Wall:
W1, L = 1.5 m , B= 0.10 m 1 1.50 0.10 3.00 0.45 cu m
W2, L=0.8 m, B= 0.10 m(2.3-1.5) 1 0.80 0.10 3.00 0.24 cu m
Total 51.72 cu m
Deduction:
Door:
D(1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
D1(1.00 X 2.10 m) 1 1.00 0.30 2.10 0.63 cu m
D2(0.75 X 2.10 m) 2 0.75 0.30 2.10 0.95 cu m
MS (1.20 X 2.10 m) 1 1.20 0.30 2.10 0.76 cu m
Windows:
W(2.00 X 1.20 m) 1 2.00 0.30 1.20 0.72 cu m
W1(1.50 X 1.20 m) 3 1.50 0.30 1.20 1.62 cu m
W2(1.20 X 1.00 m) 2 1.20 0.30 1.00 0.72 cu m
W3(1.20 X 1.20 m) 2 1.20 0.30 1.20 0.86 cu m
Ventilation:
V(0.90 x 0.60 m) 1 0.90 0.30 0.60 0.16 cu m
V1 (0.60 x 0.60 m) 1 0.60 0.30 0.60 0.11 cu m
Cupboard:
CB(1.50 x 1.80 m) 1 1.50 0.15 1.80 0.40 cu m
CB1 (1.20 x 1.80 m) 1 1.2 0.15 1.80 0.32 cu m
Open:
O (1.20 x 2.10) 2 1.20 0.30 2.10 1.51 cu m
Total 9.52 cu m
Lintel:
Door:
D(1.20 X 2.10 m)(L= 1.20+0.15+0.15) 1 1.50 0.30 0.15 0.07 cu m
D1(1.00 X 2.10 m) 1 1.30 0.30 0.15 0.06 cu m
D2(0.75 X 2.10 m) 2 1.05 0.30 0.15 0.09 cu m
MS (1.20 X 2.10 m) 1 1.50 0.30 0.15 0.07 cu m
Windows:
W(2.00 X 1.20 m) 1 2.30 0.30 0.15 0.10 cu m
W1(1.50 X 1.20 m) 3 1.80 0.30 0.15 0.24 cu m
W2(1.20 X 1.00 m) 2 1.50 0.30 0.15 0.13 cu m
W3(1.20 X 1.20 m) 2 1.50 0.30 0.15 0.13 cu m
Ventilation:
V(0.90 x 0.60 m) 1 1.20 0.30 0.15 0.05 cu m
V1 (0.60 x 0.60 m) 1 0.90 0.30 0.15 0.04 cu m
Open:
O (1.20 x 2.10) 2 1.50 0.30 0.15 0.13 cu m
Total 1.13 cu m

Total Brickwork after deduction Total 41.06 cu m

Beam (300 mm x 300 mm)


Beam - 1 (3m length) 4 3.00 0.30 0.23 0.83 cu m
Beam - 2 (4m length) 7 4.00 0.30 0.23 1.93 cu m
Beam - 3 (3.4m length) 3 3.40 0.30 0.23 0.70 cu m
Beam - 4 (2.3m length) 3 2.30 0.30 0.23 0.48 cu m
Total 3.94 cu m

8 Slab
L = 7.9 m
B = 10.9 m
H = 0.10 1 7.90 10.90 0.10 8.61 cu m
To Get Unprotect Code Follow Link:
http://civiconcepts.com/building-estimation-excel-sheet/#

1m

1 .30m PCC 10 mm Thick

0.25 m 0.25 m
1.5 m 1m

1m
1.5 m
150 mm
150 mm

Door Length Bearing


150 mm