Chapter 3
Chapter 3
Chapter Three
3. Classification & Site configuration of Hydropower Developments
3.1. Classification and Basis
Hydropower plants could be classified based on
The hydraulic features of the plant
Location & topographical features
Presence or absence of storage
Installed capacity of the plant
The range of operating heads
Operating features etc.
A complete understanding of the type requires information under all such categories. The entire above
classification basis is not mutually exclusive.
Classification based on hydraulic features
The basic hydraulic principle governs the type.
1. Conventional Hydro-plants
Use normally available hydraulic energy of the flow of the river.
Run-of river plant, diversion plant, storage plant
2. Pumped storage plants
Use the concept of recycling the same water.
Normally used with areas with a shortage of water
It generates energy for peak load, and at off-peak periods, water is pumped back for
future use.
A pumped storage plant is an economical addition to a system, which increases the
load factor of other systems and provides additional capacity to meet the peak load.
3. Unconventional Hydro-plants
i) Tidal power plant
Use the tidal energy of the seawater.
Very few have been constructed due to structural complication.
ii) Wave power plant
iii) Depression power plant
HP generated by diverting an ample source of water in the natural depression
Water level in the depression is controlled by evaporation
Classification based on operation
Based on actual operation in meeting the demand one can have:
Isolated plant - operating independently (not common now a days)
Interconnected in to grids
Page 1 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Thus in a grid system, a power station may be distinguished as a base load plant or peak load plant.
Hydropower plants are best suited as peak load plants, because hydropower plants can start relatively
quickly and can thus accept load quickly.
Page 2 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Block power plant Twin block plant Island plant pier head plant Submersible plant
Figure 3-2: - Run-off-River Plant Arrangement
2. Valley dam plants (medium to high head plants)
Page 3 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Page 4 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Figure 3-7: - A typical run of river hydroelectric station using a dam and in-stream powerhouse
Page 5 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Figure 3-8: - A typical Valley dam plant [storage-type] hydroelectric station with a powerhouse builds at
the toe of the dam
Diversion canal plant
The distinguishing feature is the presence of power canal that diverts the water from the
mainstream channel.
The power house is provided at suitable location along the stretch of the canal
The water often flowing through the turbine is brought back to the old stream.
Diversion canal plants are generally low head or medium head plants.
They do not have storage.
Pondage requirement is met through a pool called fore-bay located just u/s of the powerhouse.
Page 6 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
I. If the river has a natural fall, diverting the water from u/s side of the fall & locating the
powerhouse at the d/s side of the fall provide the required head.
II. In inter-basin diversion, water may be diverted from a higher-level river to a lower river
through a diversion canal to the powerhouse located at the lower river.
Main structures of the diversion canal plant:
Diversion weir with its appurtenant structures.
Diversion canal intake with its ancillary works such as sills, trash racks, skimmer wall, sluice,
settling basin, de-silting basin, de-silting canal, silt exclusion arrangement is needed in some
sediment-laden streams.
Bridges and culverts of the canal.
Fore bay & its appurtenant structures.
Page 7 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Figure 3-9: - Layout of the project showing an embankment dam creating a reservoir with a high head
Figure 3-10: - Sectional view through the water conducting system for hydropower
This kind of plant generates energy for peak load, & at off peak period water is pumped back for
future use. During off peak periods excess power available from some other plants in the system is
used in pumping backwater from the lower reservoir.
Various arrangements are possible for higher and lower reservoirs:
1. Both reservoirs in a single river
2. Two reservoirs on two separate rivers close to each other and flowing at different elevations
3. Higher reservoir an artificially constructed pool and the lower reservoir on natural river
4. The lower reservoir in a natural lake while the higher is artificial
Page 8 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Figure 3-11: - pumped-storage scheme developments with upper and lower ponds in the same river
Page 9 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Dead storage
This is a storage capacity of the reservoir provided to accommodate the deposition of silt in the
reservoir. It is expected that the dead storage space will eventually fill up with sediment at which time
one says the dam has served its full purpose. The life of a reservoir is dependent on the silting capacity
of the reservoir. Provisions for flushing out silt through deep-seated bottom outlets/sluices is made in
most dams. However, this has a limited effectiveness.
Evaporation Loss
Provision should be made for evaporation since it is an important loss item actual evaporation rate
depends upon location & meteorological factors. In arid and semi-arid regions, at least 2 to 2.5m of
depth should be added as a rule of thumb.
a. Sudden increase or decrease in load on the turbine. The pondage would provide the
extra water when needed and retain excess water when not needed.
b. The load and thus the water demand may be steady but the supply may undergo a
change. Breaches in the supply canal may lead to this.
Pondage capacity is determination for varying inflow is similar to storage capacity determination.
If hourly inflows for a typical day are known, one can calculate the average hourly requirement and
determine the total maximum cumulative departures from the average over a 24-hour period. This
will then be the pondage needed to equalize the daily flow fluctuations.
Page 11 of 12
Lecture Note, 2024/25
Hydropower Engineering, Chapter 3
Page 12 of 12
Lecture Note, 2024/25