Cost Breakdown Format
Cost Breakdown Format
1FS
2 Bulk Excavation for basement work
3 Back fill to exterior side of the basement 5FS
Damp Proof Work
Placement of Damp Proof polyethine sheet
7FS+7 days
4 above lean concrete 2 days
Placement of Damp Proof polyethine sheet
10FS+14 days
5 to exterior side of shear wall 2 days
2SS, 3FF
6 Cartaway excavated materials
Concrete Work
7 C-5 Lean Concrete 2FS
8 C-25 Mat Footing 14,15,16
9 C-25 Footing Column 12FS
10 Shear wall concreting 13FS
11 Form Work for Mat Footing 4FS
12 Form work for Footing Column 16FS
13 Form work for shear wall 8FS+3days
14 Reinforcement for Mat footing 7FS+7 days
15 Reinforcement for shear wall 14FS
16 Reinforcement for basement column 14FS
N.B.
Optimize your resource during duration Computation. Meet minimum efficiency of 100% for your allocation
Compute Duration, assign manpower, material, and equipment for the activities above.
Man Power Resourse Material Resourse Machine Resourse Unit Contract Qty
Fill your resouce from Mekelle Rate
D.Paver[8],Dl[16],FM[2] m2 2000
D.Paver[8],Dl[16],FM[2] m2 2000
Loader[1],DumpTruck[5
L.C[2] ] m3 3150
Fm[1],Mason[4],DL[24] m2 100
Fm[4],Mason[16],DL[96],OP[3] Mixer[1.5].Vibrator[1.5] m3 50
Fm[0.25],Mason[1],DL[6],OP[0.18] Mixer[0.09].Vibrator[0.09 m3 1.2
Fm[8],Mason[32],DL[192],OP[6] Mixer[3].Vibrator[3] m3 450
C[4],A.C[4],DL[4],FM[1] m2 54
C[2],A.C[2],DL[2],FM[0.5] m2 20
C[1],A.C[1],DL[1],FM[0.25] m2 9.6
Bar Bender[8],DL[8],FM[2] kg 2492
Bar Bender[8],DL[8],FM[2] kg 1600
Bar Bender[1],DL[1],FM[0.25] kg 120
48
Backfill around masonry, footing pad and column using selected excavated materials
A .MATERIAL B.MANPOWER
RATE Factor
TYPE UNIT QTY. Type No.
(BIRR) Cost per Unit
- - Daily Labor 1
- - Forman 1
- -
- -
- -
TOTAL ' A' (BIRR) 0 - TOTAL 'B' (BIRR)
1.MATERIAL TOTAL " A " - - 2. Manpower Total " B " devided by daily ou
1. DIRECT COST = "1" + " 2 " + " 3 " in Birr
Profit = 7 % of the direct cost 12.25 Overhead= 17
Profit percentage out of the total cost = 0.0565 Overhead Cost percentage o
Hard core
A .MATERIAL B.MANPOWER
RATE Factor
TYPE UNIT QTY. Type No.
(BIRR) Cost per Unit
Basaltic s m2 0.26 375.00 97.50 0.59 Daily Labor 1
- - Forman 1
- -
- -
- -
TOTAL ' A' (BIRR) 97.5 0.59 TOTAL 'B' (BIRR)
1.MATERIAL TOTAL " A " 97.50 0.59339 2. Manpower Total " B " devided by daily ou
1. DIRECT COST = "1" + " 2 " + " 3 " in Birr
Profit = 7 % of the direct cost 9.28 Overhead= 17
Profit percentage out of the total cost = 0.0565 Overhead Cost percentage o
Lean Concrete
A .MATERIAL B.MANPOWER
RATE Factor
TYPE UNIT QTY. Type No.
(BIRR) Cost per Unit
Gravel m3 0.85 716.85 609.32 0.14 Masone 1.00
Cement qtl 1.6 1200.00 1,920.00 0.43 D. labour 22.00
Sand m3 0.50 597.37 298.69 0.07 Forman 1.00
Water m3 0.07 20.00 1.40 0.00
- -
TOTAL ' A' (BIRR) 2829.41 0.64 TOTAL 'B' (BIRR)
1.MATERIAL TOTAL " A " 2,829.41 0.64061 2. Manpower Total " B " devided by daily ou
1. DIRECT COST = "1" + " 2 " + " 3 " in Birr
Profit = 7 % of the direct cost 249.33 Overhead= 17
Profit percentage out of the total cost = 0.0565 Overhead Cost percentage o
Mass Concrete
A .MATERIAL B.MANPOWER
RATE Factor
TYPE UNIT QTY. Type No.
(BIRR) Cost per Unit
Gravel m3 0.82 716.85 587.81 0.09 Masone 1.00
Cement qtl 2.8 1200.00 3,360.00 0.54 D. labour 22.00
Sand m3 0.53 597.37 316.61 0.05 Forman 1.00
Water m3 0.08 20.00 1.60 0.00
- -
TOTAL ' A' (BIRR) 4266.02 0.69 TOTAL 'B' (BIRR)
1.MATERIAL TOTAL " A " 4,266.02 0.68827 2. Manpower Total " B " devided by daily ou
1. DIRECT COST = "1" + " 2 " + " 3 " in Birr
Profit = 7 % of the direct cost 349.90 Overhead= 17
Profit percentage out of the total cost = 0.0565 Overhead Cost percentage o
C25 concrete
A .MATERIAL B.MANPOWER
RATE Factor
TYPE UNIT QTY. Type No.
(BIRR) Cost per Unit
Gravel m3 0.68 716.85 487.46 0.07 Masone 1.00
Cement qtl 3.60 1200.00 4,320.00 0.61 D. labour 22.00
Sand m3 0.46 597.37 274.79 0.04 Forman 1.00
Water m3 0.12 20.00 2.40 0.00 Operator 2.00
- -
TOTAL ' A' (BIRR) 5084.65 0.72 TOTAL 'B' (BIRR)
1.MATERIAL TOTAL " A " 5,084.65 0.71817 2. Manpower Total " B " devided by daily ou
1. DIRECT COST = "1" + " 2 " + " 3 " in Birr
Profit = 7 % of the direct cost 399.68 Overhead= 17
Profit percentage out of the total cost = 0.0565 Overhead Cost percentage o
Reinforcement
A .MATERIAL B.MANPOWER
RATE Factor
TYPE UNIT QTY. Type No.
(BIRR) Cost per Unit
ReinforcemKg 1.05 60.00 63.00 0.64 Bar bender 1.00
Wire Kg 0.06 50.00 3.00 0.03 D. labour 1.00
- - Forman 1.00
- -
- -
TOTAL ' A' (BIRR) 66 0.68 TOTAL 'B' (BIRR)
1.MATERIAL TOTAL " A " 66.00 0.67533 2. Manpower Total " B " devided by daily ou
1. DIRECT COST = "1" + " 2 " + " 3 " in Birr
Profit = 7 % of the direct cost 5.52 Overhead= 17
Profit percentage out of the total cost = 0.0565 Overhead Cost percentage o
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 347.20 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 434.00 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 434.00 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 217.00 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
400.00 3,200.00 0.3632
- -
- -
- -
- -
IRR) 3,200.00 0.3632
ded by daily output 191.16 0.3632
out of the total cost = 0.8065
st per unit/ Unit rate 526.36 Birr/unit
al cost percentage = 1.00
m2/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8064
st per unit/ Unit rate 164.31 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 4,416.76 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 6,198.17 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
250.00 2,000.00 0.0166
62.50 500.00 0.0042
- -
- -
- -
IRR) 2,500.00 0.0208
ded by daily output 147.06 0.0208
out of the total cost = 0.8065
st per unit/ Unit rate 7,079.97 Birr/unit
al cost percentage = 1.00
Kg/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8064
st per unit/ Unit rate 97.73 Birr/unit
al cost percentage = 1.00
m2/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 1,615.56 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 5,117.28 Birr/unit
al cost percentage = 1.00
m3/day
IPMENT
Rental rate Daily cost Factor
(birr / hr ) (birr)
- -
- -
- -
- -
- -
IRR) - -
ded by daily output - -
out of the total cost = 0.8065
st per unit/ Unit rate 3,936.59 Birr/unit
al cost percentage = 1.00
11-1000 - 5000-6000 Trades Of Works Contract
Direct Expenses
Amount
11- 5100 Costs / Expenses Direct
W/ Profit Cost Materials Labors
11- 5110 Sub Structure
11-5111-6010 Earth Works
11-5111-6011 Clear and remove top soil 1.00 0.81 0.00 0.81
Cummulative BCWS
3,030,000.00
2,530,000.00
2,030,000.00
1,530,000.00 1,378,
1,030,000.00 926,818.53
530,000.00 419,522.90
92,863.11
30,000.00
1 2 3
Months
Row 42
Year 2024 G.C
Month 1 2 3
Total Cost
Start Finish
Mon 5/6/24 Tue 9/24/24
30,000.00 Mon 5/6/24 Wed 5/22/24 30,000.00
Wed 5/22/24 Tue 9/24/24
Wed 5/22/24 Thu 9/19/24
4,340.00 Wed 5/22/24 Thu 5/23/24 4,340.00
69,440.00 Thu 5/23/24 Thu 6/13/24 42,732.31 26,707.69
13,020.00 Thu 7/25/24 Tue 7/30/24 13,020.00
21,700.00 Thu 6/13/24 Tue 6/18/24 21,700.00
- Mon 7/22/24 Thu 9/12/24
6,510.00 Wed 8/14/24 Fri 8/16/24
9,765.00 Mon 7/22/24 Thu 7/25/24 9,765.00
3,255.00 Wed 9/11/24 Thu 9/12/24
15,790.80 Thu 5/23/24 Mon 6/24/24 15,790.80
32,862.00 Thu 9/12/24 Thu 9/19/24
- Tue 6/18/24 Tue 9/24/24
- Wed 6/19/24 Mon 8/19/24
106,002.24 Wed 6/19/24 Thu 6/20/24 106,002.24
106,002.24 Tue 7/30/24 Wed 7/31/24 106,002.24
53,001.12 Fri 8/16/24 Mon 8/19/24
1,239,634.00 Thu 9/19/24 Tue 9/24/24
- Fri 6/28/24 Fri 8/30/24
212,399.10 Fri 6/28/24 Thu 7/4/24 38,618.02 173,781.08
106,199.55 Mon 7/8/24 Wed 7/10/24 106,199.55
106,199.55 Tue 8/27/24 Fri 8/30/24
- Wed 6/26/24 Mon 8/26/24
46,910.40 Wed 6/26/24 Thu 6/27/24 46,910.40
15,636.80 Thu 6/27/24 Fri 6/28/24 15,636.80
15,636.80 Mon 8/26/24 Mon 8/26/24
- Tue 6/18/24 Tue 8/27/24
71,084.64 Tue 6/18/24 Wed 6/19/24 71,084.64
35,542.32 Fri 7/5/24 Mon 7/8/24 35,542.32
106,626.96 Mon 8/26/24 Tue 8/27/24
- Wed 7/31/24 Fri 8/2/24
163,752.96 Thu 8/1/24 Fri 8/2/24
62,985.44 Wed 7/31/24 Thu 8/1/24 62,985.44
2,654,296.92 92,863.11 326,659.79 507,295.63
Schedule in Birr (BCWS) 92,863.11 326,659.79 507,295.63
Schedule in % (BCWS) 3.00% 12.00% 19.00%
Birr 92,863.11 419,522.90 926,818.53
Performed in Birr (BCWP) 69,647.33 342,992.78 532,660.41
Performed in % (BCWP) 3.00% 13.00% 20.00%
Birr 69,647.33 412,640.11 945,300.52
formed in Birr (ACWP) 76,612.06 377,292.06 585,926.45
formed in % (ACWP) 3.00% 14.00% 22.00%
Birr 76,612.06 453,904.12 1,039,830.58
2,654,296.92
1,378,545.92
926,818.53
419,522.90
2 3 4 5
Months
Row 42
24 G.C
4 5 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
6,510.00
3,255.00
32,862.00
53,001.12
1,239,634.00
106,199.55
15,636.80
106,626.96
163,752.96
451,727.39 1,275,751.00
451,727.39 1,275,751.00
17.00% 48.00%
1,378,545.92 2,654,296.92
474,313.76 1,234,682.64
18.00% 47.00%
1,419,614.28 2,654,296.92
521,745.14 1,358,150.90
20.00% 51.00%
1,561,575.71 2,919,726.61
#VALUE! #VALUE! 1 2 3 4 5 6
7 8 9 10 11 12 13 14
15 16 17 18 19 20 21 22
23 24 25 26 27 28 29 30
Annex-B2
Project:
Contractor:
Consultant:
Item
Description QTY Value in Birr Value in %
no.
1 Sand 18.89 11,282.75 39.50
2 Aggregate 24.11 17,282.55 60.50
4 HCB Class B - size 40x20x20cm #DIV/0! - -
5 Stone for masonry #DIV/0! - -
6 Stone for Hardcore #DIV/0! - -
8 Selected Material #DIV/0! - -
10 Reinforcement for footing pad #DIV/0! - -
11 Reinforcement for footing column #DIV/0! - -
12 Reinforcement for grade beam #DIV/0! - -
13 Diam. 12 #DIV/0! - -
14 Diam. 10 #DIV/0! - -
15 Diam. 8 #VALUE! - -
16 Diam. 6 #DIV/0! - -
18 Cement PPC - - -
ROOFING - - -
21 Bitumen at the rate of 0 .7kg/m2 #DIV/0! - -
22 PVC of size 110mm #DIV/0! - -
CARPENTRY AND JOINERY #DIV/0! - -
23 D1-90x 240 x6 #DIV/0! - -
24 D2 - 70x 240 x6 #DIV/0! - -
METAL WORK(glazed door &
windows) #DIV/0! - -
26 W - 40 x 40 x4 #DIV/0! - -
27 W- 130 x 100 x 4 #DIV/0! - -
28 W-100 x 40 x 5 #DIV/0! - -
29 W-120 x 160 x2 #DIV/0! - -
30 W-170 x 160 x 6 #DIV/0! - -
31 W- 686 x 240 x 1 #VALUE! - -
32 W-245x100x2 #DIV/0! - -
33 W-615 x 100 x 2 - - -
34 W-303 x 240 x 1 - - -
35 W-317 x240x1 - - -
36 W-390 x 240 x 1 - - -
37 W-245 x 240 x 1 #DIV/0! - -
38 W-317 x 240 x1 #DIV/0! - -
39 D-384 x 240 x 1 #DIV/0! - -
40 D-240 x 80 x4 #DIV/0! - -
41 D-225 x 140 x 2 #DIV/0! - -
42 D-120 x 250 x 4 #DIV/0! - -
43 D-247 x 225 x2 #DIV/0! - -
44 D-258 x 225 x 2 #DIV/0! - -
45 D-205 x 62 x 4 #DIV/0! - -
46 D-205 x 100 x 4 #VALUE! - -
47 D-225 x 127 x 2 #DIV/0! - -
48 D-225 x 122 x 2 - - -
49 D-225 x 92 x 8 - - -
FINISHING WORK - - -
50 25*25*25mm thick class A quality terrazo - - -
51 20*20*25mm thick class A qualityterrazo #DIV/0! - -
52 25*25*25mm thick class A quality ceramic #DIV/0! - -
53 30*30*10mm thick class A quality ceramic #DIV/0! - -
100mm height and 10mm thick ceramic
54
tile skirting #DIV/0! - -
30mm height and 15mm thick marbel tile
55
skirting #DIV/0! - -
56 Trade of size 120 x 30 cm x 20 #DIV/0! - -
57 Risers of size 120 x 15cm x 20 #DIV/0! - -
300mm width & 30mm thick white marble
58
window sill #DIV/0! - -
GLAZING #DIV/0! - -
6mm thick tinted glass free from defects
59 fixed to aluminume door and windows #VALUE! - -
PAINTING #DIV/0! - -
60 quartez paint - - -
61 plastic paint - - -
SANITARY INSTALLATION #DIV/0! - -
62 a. Diam. 15mm - - -
63 b. Diam. 20mm #DIV/0! - -
64 c. Diam. 25mm #DIV/0! - -
European made gate value #DIV/0! - -
65 a. Diam. 15mm #DIV/0! - -
66 b. Diam. 20 mm #DIV/0! - -
67 c. Diam. 25mm #DIV/0! - -
68 hand wash basin of size 500x405mm #DIV/0! - -
Europran made WC made of white
69 vitreous china with low flush #DIV/0! - -
70 shower unit of 80x80cm #DIV/0! - -
71 shower 80lit capacity water heater #DIV/0! - -
soap holder white vetreous china size
72 150x150mm #DIV/0! - -
chrome tubular metal rolled towel hunger
73 with all accessories. #DIV/0! - -
74 diam. 50mm floor drain including cast iron #DIV/0! - -
toilet paper holder white vetreous china
75 size 150x150mm #DIV/0! - -
Rigid plastic pipes (PVC) #DIV/0! - -
76 a. Diam. 50mm #DIV/0! - -
77 a. Diam. 110mm #DIV/0! - -
78 b. Diam. 160mm #DIV/0! - -
79 2m3 capacity Roto water tank #DIV/0! - -
Rectangular manhole on the sanitary
sewer #DIV/0! - -
80 a) size of 600x600x600mm #DIV/0! - -
81 b) size of 700x700x700mm #DIV/0! - -
ELECTRICAL INSTALLATION #DIV/0! - -
82 4pcs ACB32A, 3phase #DIV/0! - -
pvc insulated condutors of 2x2.5mm2 in
83 thermoplasti conduits of f 13.5mm #DIV/0! - -
84 socket outlet of 16A, single phase #DIV/0! - -
85 socket outlet of 20A, single phase #DIV/0! - -
Telephone outlets with all accessories and
86 conduits of diam.19mm. #DIV/0! - -
TV outlets with all accessories and
87 conduits of diam.19mm. #DIV/0! - -
88 RZB 55152.002+E2/ 60 #DIV/0! - -
89 Philips TCS 098/2.36+2xTLD36W. #DIV/0! - -
90 RZB 21004.002 +E27/60W. #DIV/0! - -
91 Construct 240m3 septic tank #DIV/0! - -
Total Cost 28,565.30 100.00
Project Amount
Completion Date
Months
1 2 3 4 5 6 7
11,282.75
17,282.55
- - - - - - -
t 4326037.93
nt date Apr-09
te Apr-10
8 9 10 11 12
- - - - -
Project:
Contractor:
Labor Sch
Consultant:
Value in Value in
Item no. Description No.
Birr % 1
1 Forman 30.68 15,340.11 11.16 6,423.08
2 Carpenter - - -
3 Mason 2.72 1,632.51 1.19
4 Bar Bender - - -
5 Plasterer - - -
6 Chiseller - - -
7 Tiller - - -
8 Electrician - - -
9 Plumber - - -
10 Painter - - -
11 Glazer - - -
12 Welder - - -
13 Operator 5.29 2,117.65 1.54
14 Gang Chief - - -
15 Daily Laborer 394.66 118,397.65 86.11 38,538.46
16 Helper - - -
17 Truck Driver - - -
Total Cost 137,487.91 100.00 44,961.54
Project Amount:
Commencement date:
Labor Schedule
Completion Date:
Months
2 3 4 5 6 7 8 9
7,417.03 1,500.00
1,632.51
256.68 1,860.96
55,019.18 24,840.00
64,325.41 28,200.96 - - - - - -
10 11 12
- - -
Project:
Contractor:
Equipment Sch
Consultant:
Value in
Item no. Description No. Value in Birr
% 1 2
1 Dozer - -
2 Loader - -
3 Excavator - -
4 Back hoe Loader - -
5 Grader - -
6 Crusher - -
7 Mixer - 750 Lit. - -
8 Mixer - 500 Lit. 3.53 7,058.83 48.49 641.71
9 Dump truck 1.79 5,734.77 39.39 5,734.77
10 Dumper - -
11 Vibrator 1,764.71 12.12 160.43
12 Rebar Cutter - -
13 Compactor - -
14 Welding Machine - -
15 Grinding Machine - -
16 Hand Compactor - -
17 Set of Tools - -
18 Metal Cutter - -
19 Tile Cutter - -
20 Polishing Machine - -
21 Scaffolding - -
22 Pipe thread - -
Total Cost 14,558.31 100.00 5,734.77 802.14
Project Amount
Completion Date
Months
3 4 5 6 7 8 9 10 11
4,652.41 1,764.71
1,163.10 441.18
5,815.51 2,205.89 - - - - - - -
12
-
ROAD CONSTRUCTIO
SERIA MACHINE CREW
TASKS UNDER EACH
L TYPE OF OPERATION UNIT
OPERATION
NO DESCRIPTION NO
Bulldozer - D8R 1
Clearing &
1 CLEARING & GRUBBING HA
Grubbing
Bulldozer - D8R 1
Motor Grader 1
Road Bed
2 ROAD BED PREPARATION M2 Vibratory Roller 1
Preparation
Water Truck 1
Bulldozer - D8R 1
Normal Excavation BM3
Bulldozer - D8R 1
Intermediate
BM3
Excavation
Bulldozer - D8R 1
Blasted Rock
BM3
Excavation
Blasting Machine 1
Bulldozer - D8R 1
Material Production BM3
Bulldozer - D8R 1
Material Production BM3
Bulldozer - D8R 1
Material Production BM3
7 NATURAL SUB-BASE
Wheel Loader - 3m3 1
Hauling to Placing LM3
Dump Truck - 12m3 13
7 NATURAL SUB-BASE
Motor Grader 1
Vibratory Roller 1
Sub-base Placing CM3
Water Truck 2
Bulldozer - D8R 1
Material Production BM3
Material Crushing
Crushing Plant - 100TPH 1
8 CRUSHED SUB-BASE
LM3 Wheel Loader - 3m3 1
Blasting Machine 1
Material Crushing
9 CRUSHED ROAD BASE
LM3 Wheel Loader - 3m3 1
Material Crushing
Crushing Plant - 100 TPH 1
LM3 Wheel Loader - 3m3 1
Asphalt Distributor 1
Prime Coat
10 PRIME COAT M2 Air Blower 3
Application
Asphalt Distributor 1
Tack Coat
11 TACK COAT M2 Water Truck 1
Application
Air Blower 3
Blasting Machine 1
Quarry Production - ISUZU Truck 1
BM3
Blasting
Asphalt Hauling to
Placing TON Dump Truck - 12m3 7
Asphalt Paver 1
Smooth Steel Roller 1
Asphalt Placing - Pneumatic Tired Roller 2
TON
5cm Thick Asphalt Cutter 1
Air Blower 2
Blasting Machine 1
Quarry Production - ISUZU Truck 1
BM3
Blasting
Quarry Production -
LM3
Rock breaking Excavator with Hydraulic breaker
1
Hauling to Crushing Chain Excavator - 1.5m3 1
LM3
Plant Dump Truck - 9m3 3
Crushing Plant - 75 TPH 1
LM3 Wheel Loader - 3m3 1
Aggregate Crushing
Crushing Plant - 100 TPH 1
LM3 Wheel Loader - 3m3 1
Air Compressor 1
Asphalt Boiler 1
Asphalt Distributor 1
Second Surface Chip Spreader 1
M2
Treatment Smooth Steel Roller 1
Pneumatic Tired Roller 1
Air Compressor 1
Asphalt Boiler 1
Asphalt Distributor 1
Third Surface Chip Spreader 1
M2
Treatment Smooth Steel Roller 1
Pneumatic Tired Roller 1
Air Compressor 1
15 PIPE HAULING
Pipe Diameter -
PCS
36''/900mm
Pipe Diameter -
PCS
36''/900mm
PIPE INSTALLATION
Pipe Diameter -
16 PCS
CLASS A 42''/1060mm
BEDDING
Pipe Diameter -
PCS
48''/1200mm
Pipe Diameter -
PCS
36''/900mm
PIPE INSTALLATION
Pipe Diameter -
17 PCS
CLASS B 42''/1060mm
BEDDING
Pipe Diameter -
PCS
48''/1200mm
Pipe Diameter -
PCS
36''/900mm
PIPE INSTALLATION
Pipe Diameter -
18 PCS
CLASS C 42''/1060mm
BEDDING
Pipe Diameter -
PCS
48''/1200mm
Pipe Diameter -
PCS
48''/1200mm
Minor Drainage
M3
Structures
STONE MASONRY
19
CLASS B Retaining Wall +
M3
Major Structures
Paved Waterway M2
Pipe Culvert KG
Box Culvert KG
20 REINFORCEMENT
Reinforcement bar cutter
Slab Culvert KG
Slab Culvert KG
Bridge Structure KG
21 CONCRETE WORKS
Concrete Mixer 500 Ltrs 2
Concrete Vibrator 4
Water Truck 1
Concrete Class C M3
Water Tanker 10,000 Ltr 1
Slab Culvert M2
Bridge Structure M2
Excavator 1
Cut to Spoil LM3
Dump Truck - 12m3 3
NORMAL USING
EXCAVATOR Excavator 1
23 Borrow to Fill LM3
(EXCAVATION +
HAULING)
NORMAL USING
EXCAVATOR
23 Borrow to Fill LM3
(EXCAVATION + Dump Truck - 12m3 4
HAULING)
Excavator 1
Natural Subbase LM3
Dump Truck - 12m3 7
Excavator 1
Normal Excavation LM3
Dump Truck - 12m3 3
STRUCTURAL Compressor 1
24 EXCAVATION
Jack Hammer 2
Hard Excavation BM3
Blasting Machine
Unskilled Labour 2
Earthwork Foreman 1
Grade Checker /Data Collecto 1
Water Truck Helper 1 500
Unskilled Labour 4
Unskilled Labour 2
Earthwork Foreman 0.5
Grade Checker /Data Collecto 1 75
Unskilled Labour 2
Earthwork Foreman 0.5
Grade Checker /Data Collecto 1 75
Unskilled Labour 2
Quarry Foreman 1
Data Collector 1 147
Unskilled Labour 2
Power Jel KG 0.16 Blasting Technician 1
ANFO KG 0.64 Assistant/Data Collector 1
147
Detonator PCS 0.02 Unskilled Labour 15
Detonating Cord M 0.7
Load Counter/Data Collector 2
240
Unskilled Labour 2
Load Counter/Data Collector 2
240
Crusher Foreman 1
Load Counter/Data Collector 1 50
Unskilled Labour 6
Crusher Foreman 1
Load Counter/Data Collector 1 67
Unskilled Labour 6
Load Counter/Data Collector 1
240
Pavement Foreman 1
Grade Checker /Data Collecto 1
88
Water Truck Helper 2
Unskilled Labour 20
Quarry Foreman 1
Data Collector 1 147
Unskilled Labour 2
Power Jel KG 0.16 Blasting Technician 1
ANFO KG 0.64 Assistant/Data Collector 1
147
Detonator PCS 0.02 Unskilled Labour 15
Detonating Cord M 0.7
Crusher Foreman 1
35
Load Counter/Data Collector 1 35
Unskilled Labour 6
Crusher Foreman 1
Load Counter/Data Collector 1 45
Unskilled Labour 6
Load Counter/Data Collector 1
240
Pavement Foreman 1
Grade Checker /Data Collecto 1
70
Water Truck Helper 2
Unskilled Labour 25
Bitumen - MC30 LTR 0.80 Asphalt Foreman 1
Asphalt Distributor Helper 1 1050
Unskilled Labour 3
Bitumen - RC70 KG 0.10 Asphalt Distributor Helper 1
Water Truck Helper 1 1050
Unskilled Labour 3
Quarry Foreman 1
Data Collector 1 147
Unskilled Labour 2
Power Jel KG 0.16 Blasting Technician 1
ANFO KG 0.64 Assistant/Data Collector 1
147
Detonator PCS 0.02 Unskilled Labour 15
Detonating Cord M 0.7
Data Collector 1
120
Crusher Foreman 1
Load Counter/Data Collector 1 24
Unskilled Labour 6
Crusher Foreman 1
Load Counter/Data Collector 1 30
Unskilled Labour 6
Load Counter/Data Collector 1
240
Crusher Foreman 1
Load Counter/Data Collector 1 24
Unskilled Labour 6
Crusher Foreman 1
Load Counter/Data Collector 1 30
Unskilled Labour 6
Load Counter/Data Collector 1
20
Unskilled Labour 6
Class A Bedding M3 0.23 Mason 2
Cement Mortar 1:2 M3 ### Gang Leader / Data Collector 1 1.43
Unskilled Labour 6
Class A Bedding M3 0.26 Mason 2
Cement Mortar 1:2 M3 ### Gang Leader / Data Collector 1 1.43
Unskilled Labour 6
Class B Bedding M3 0.76 Mason 2
Cement Mortar 1:2 M3 ### Gang Leader / Data Collector 1 1.43
Unskilled Labour 6
Class B Bedding M3 0.93 Mason 2
Cement Mortar 1:2 M3 ### Gang Leader / Data Collector 1 1.43
Unskilled Labour 6
Class B Bedding M3 1.09 Mason 2
Cement Mortar 1:2 M3 ### Gang Leader / Data Collector 1 1.43
Unskilled Labour 6
Class C Bedding M3 0.11 Mason 2
Cement Mortar 1:2 M3 ### Gang Leader / Data Collector 1 1.43
Unskilled Labour 6
Class C Bedding M3 0.13 Mason 2
Cement Mortar 1:2 M3 ### Gang Leader / Data Collector 1 1.43
Unskilled Labour 6
Class C Bedding M3 0.14 Mason 2
Cement Mortar 1:2 M3 ### Gang Leader / Data Collector 1 1.43
1.43
Unskilled Labour 6
Unskilled Labour 10
Reinforcement KG 1.05 Bar Bender Foreman 1
Tie Wire KG 0.02 Bar Bender 10
300
Gang Leader / Data Collector 1
Unskilled Labour 10
Cement KG 420 Concrete Foreman 1
Fine Aggregate M3 0.47 Mason 4
Coarse Aggregate M3 0.84 Carpenter 2
6.00
Bar Bender 1
Gang Leader / Data Collector 1
Unskilled Labour 90
Cement KG 336 Concrete Foreman 1
Fine Aggregate M3 0.53 Mason 4
Coarse Aggregate M3 0.79 Carpenter 2
6.00
Bar Bender 1
Gang Leader / Data Collector 1
Unskilled Labour 90
Steel Panel M2 1.05 Carpenter Foreman 1
Eucalyptus M 15.00 Carpenter 10
6.00
Nails KG 0.40 Data Collector 1
Binding Wire 2.5m KG 0.15 Unskilled Labour 20
Steel Panel M2 1.05 Carpenter Foreman 1
Eucalyptus M 21.00 Carpenter 10
3.50
Nails KG 0.56 Data Collector 1
Binding Wire 2.5m KG 0.21 Unskilled Labour 20
Steel Panel M2 1.05 Carpenter Foreman 1
Eucalyptus M 21.00 Carpenter 10
4.00
Nails KG 0.56 Data Collector 1
Binding Wire 2.5m KG 0.21 Unskilled Labour 20
SUR = 1.5 Ha/day - 10 Hrs for D8R ERA Standard Performance Day = 7 Hours
ERA = 350Bm3/day
33m/hr diam 75mm & 2.5m x 2.5m Plot size … 11.25m x 50m x 5m ….. 6 x 21 = 126 holes
Bank/Loose = 0.6
Bank/Compacted = 1.14
SUR = 350 M/10 Hrs (11m wide + 20cm thick) Number of Water Trucks Depends
on the
1 Pavement Foreman for 2 Graders Haulage Distance to Water
Supply Point with 15 Km/Hr
Loose/Compacted = 1.43
Bank/Compacted = 1.14
75TPH/1.5
100TPH/1.5
33m/hr diam 75mm & 2.5m x 2.5m Plot size … 11.25m x 50m x 5m ….. 6 x 21 = 126 holes
Bank/Loose = 0.6
SAME AS DRILLING
EQUIVALENT TO HAULING
Loader Cycle Time = 45 sec/1.5
Hauling Distance = 1 Km Lm3
Dump Truck Speed = 15 Km/hr Bank/Loose = 0.6
ERA = 21 LM3/HR
ERA = 39 LM3/HR
1.5KM/10 Hours
1.5KM/10 Hours
33m/hr diam 75mm & 2.5m x 2.5m Plot size … 11.25m x 50m x 5m ….. 6 x 21 = 126 holes
Bank/Loose = 0.6
SAME AS DRILLING
EQUIVALENT TO HAULING
Loader Cycle Time = 45 sec/1.5
Hauling Distance = 1 Km Lm3
Dump Truck Speed = 15 Km/hr Bank/Loose = 0.6
33m/hr diam 75mm & 2.5m x 2.5m Plot size … 11.25m x 50m x 5m ….. 6 x 21 = 126 holes
Bank/Loose = 0.6
SAME AS DRILLING
EQUIVALENT TO HAULING
Loader Cycle Time = 45 sec/1.5
Hauling Distance = 1 Km Lm3
Dump Truck Speed = 15 Km/hr Bank/Loose = 0.6
Aggregate Consumption =
0.02m3/m2
DUMP TRUCK SPEED
0 - 2 Km Hauling Distance
…..... 15 Km/Hr
2 - 5 Km Hauling Distance
SAME AS SECOND COAT …….. 25 Km/Hr
> 5 Km Hauling Distance
…….... 35 Km/Hr
Reinforcement = 23.40 Kg
Material Wastage = 5%
Reinforcement = 31.30 Kg
Material Wastage = 5%
Reinforcement = 51.82 Kg
Material Wastage = 5%
Thickness = 20 Cm
Cutting=20%, Fixing=30%
1 Bar Bender + 1 Unskilled Labour = 20 KG/Hr and Fixing=50%
Incase No Roller = 10 DL = 1
CM3/HR
15 M3 / Day - 10 Hrs
15 M3 / Day - 10 Hrs
. 6 x 21 = 126 holes
0.858
. 6 x 21 = 126 holes
1:06 1:12
1:12 1:18
1:18 1:24
1:30 1:36
1:36 1:42
1:42 1:48
1:48 1:54
. 6 x 21 = 126 holes
hr), 12-19(13m3/hr)
/hr), 12-19(12m3/hr)
/Cm3 of AC
. 6 x 21 = 126 holes