HRE Midterms
HRE Midterms
(1) All suitable material removed from the excavation shall be used in the
DPWH Standard Specifications for Public Works and Highways, Bridges, and formation of the embankment, subgrade, shoulder, slopes, beddings,
Airports and backfills for structures, and for other purposes shown on the plans
or as directed
Item 100. Clearing and Grubbing (2) The engineer will designate as unsuitable those soils that cannot be
- Clearing, grubbing, removing, and disposing of all vegetation and properly compacted in embankments. All unsuitable material shall be
debris as designated in the contract, except those objects that are disposed of off as shown on the plans or as directed without delay to
designated to remain in place or are to be removed in consonance with the contractor
other provisions of this specifications (3) Only approved materials shall be used in the construction of
- The work shall also include the preservation from injury or defacement embankments and backfills
of all objects designated to remain (4) All excess material, including rock and boulders that cannot be used in
- All surface of objects and all trees, stumps, roots, and other protruding embankments shall be disposed of as directed
obstructions, not designated to remain, shall be cleared and/or (5) Material encountered in the excavation and determined by the
grubbed, including mowing as required engineer as suitable for topping, road finishing, slope protection, or
other purposes shall be conserved and utilized as directed by the
Method of Measurement engineer
1. Area basis – the work to be paid for shall be the number of hectares
and fractions acceptably cleared and grubbed within the limits Item 103. Structure Excavation
indicated on the plans or as may be adjusted in the field staking by the - Necessary excavation for the foundation of bridges, culverts,
engineer | areas, not within the clearing and grubbing will not be underdrains, and other structures not otherwise provided for in the
measured for payment specifications, except as otherwise provided for pipe culverts, the
2. Lump-Sum basis – when the bill of quantities contains a clearing and backfilling of completed structures, and the disposal of all excavated
grubbing lump-sum item, no measurement of the area will be made for surplus materials, shall be in accordance with these specifications and
such an item in reasonably close conformity with the plans or as established by the
3. Individual Unit basis (selective clearing) – the diameter of trees will be engineer
measured at a height of 1.4 m (54 inches) above the ground | trees - Necessary diverting of live streams, bailing, pumping, draining,
less than 150 mm (6 inches) in diameter will not be measured for sheeting, bracing, and the necessary construction of cribs and
payment cofferdams, and furnishing the materials, therefore, and the
subsequent removal of cribs and cofferdams and the placing of all
When a bill of quantities indicates the measurement of trees on an individual unit necessary backfill
basis, the units will be designated and measured in accordance with the following - Furnishing and placing of approved foundation fill material to replace
schedule of sizes unsuitable material encountered below the foundation elevation of
Diameter at height of 1.14 m Pay Item Designation structures
Over 150 mm to 900 mm Small - No allowance will be made for the classification of different types of
Over 900 mm Large material encountered
Payment will be made under Utilization of Excavated Materials – all excavated materials, so far as suitable,
Pay Item Number Description Unit of Measurement shall be utilized as backfill or embankment | surplus materials shall be disposed of
100 (1) Clearing and Grubbing Hectare in such a manner as not to obstruct the stream or otherwise impair the efficiency
100 (2) Clearing and Grubbing Lump Sum or appearance of the structure | no excavated materials shall be deposited at any
Individual Removal of time so as to endanger the partly finished structure
100 (3) Each
Trees, Small
Individual removal of Item 104. Embankment
100 (4) Each
Trees, Large Unsuitable Material – material other than suitable materials such as:
(1) Materials containing detrimental quantities of organic materials, such
Item 101. Removal of Structures and Obstructions as grass, roots, and sewerage
- Removal wholly or in part, and satisfactory disposal of all buildings, (2) Organic souls such as peat and muck
fences, structures, old pavements, abandoned pipelines, and any other (3) Soils with a liquid limit exceeding 80 and/or plasticity index exceeding
obstructions which are not designated or permitted to remain, except 55
for the obstructions to be removed and disposed of under other items (4) Soils with a natural water content exceeding 100%
in the contract (5) Soils with very low natural density, 800 kg/m3 or lower
- It shall also include the salvaging of designated materials and (6) Soils that cannot be properly compacted as determined by the
backfilling the resulting trenches, holes, and pits engineer
Removal of existing bridges, culverts, and other drainage structures Item 105. Subgrade Preparation
- All existing bridges, culverts, and other drainage structures in use by - Preparation of the subgrade for the support of overlying structural
traffic shall not be removed until satisfactory arrangements have been layers
made to accommodate traffic - It shall extend to the full width of the roadway unless authorized by the
- The removal of existing culverts within embankment areas will be engineer subgrade preparation shall be done unless the contractor is
required only as necessary for the installation of new structures able to start immediately the construction of the pavement structure
- Abandoned culverts shall be broken down, crushed and sealed or
plugged Material Requirements – unless otherwise stated in the contract and except when
the subgrade is in rock-cut, all materials below subgrade level to a depth of 150
Removal of Existing Pavement, Sidewalks, Curbs, etc. mm or to such greater depth as may be specified shall meet the requirements of
All concrete pavement, base course, sidewalks, curbs, gutters, etc., are section 104 material requirements
designated for removal, and shall be:
(1) Broken into pieces and used for riprap on the project
(2) Broken into pieces, the size of which shall not exceed 300 mm (12
inches) in any dimension, and stockpiled at designated locations on
the project for use by the government
(3) Otherwise demolished and disposed of as directed by the engineer.
When specified, ballast, gravel, bituminous materials, or other
surfacing pavement materials shall be removed and stockpiled as
required in subsection 101.2, otherwise, such materials shall be
disposed of as directed
Material Requirements
- Hard, durable particles or fragments of stone, or gravel crushed to the
size and the quality requirements of this item
- Composite material shall be free from vegetable matter and lumps or
balls of clay, and shall be of such nature that it can be compacted
readily to form a firm, stable base
Grading Requirements
Sieve Designation Mass Percent Passing
Standard, mm Alternate US Standard Grading A Grading B
37.5 1 – ½” 100 -
25.0 1” - 100
19.0 ¾” 60 – 85 -
12.5 ½” - 60 – 90
4.75 No. 4 30 – 55 35 – 65
0.425 No. 40 8 – 25 10 – 30
0.075 No. 200 2 – 14 5 – 15
Rebar Size Linear Weight Diameter Lateral Area
Item 300. Aggregate Surface Course
U.S SI lb/ft kg/m in mm in2 mm2
- Wearing or top course composed of gravel or crushed aggregate and
3 #10 0.38 0.56 0.38 9.53 0.11 71.00
binder material, whichever is called for in the bill of quantities,
4 #13 0.67 1.00 0.50 12.70 0.20 129.00
constructed on a prepared base in accordance with this specification
5 #16 1.04 1.56 0.63 15.88 0.31 200.00
and in conformity with the lines, grades, and typical cross-sections
6 #19 1.50 2.24 0.75 19.05 0.44 284.00
shown on the plans
7 #22 2.04 3.05 0.88 22.23 0.60 387.00
8 #25 2.67 3.98 1.00 25.40 0.79 509.00
Placing & Compacting 9 #29 3.40 5.07 1.13 28.65 1.00 645.00
- When uniformly mixed, the mixture shall be spread to the planned 10 #32 4.30 6.42 1.27 32.26 1.27 819.00
thickness for compaction 11 #36 5.31 7.92 1.41 35.81 1.56 1006.00
- When the required thickness is 150 mm or less, the material may be 12 #38 5.99 8.93 1.50 38.10 1.77 1140.09
spread and compacted in one layer 14 #43 7.65 11.41 1.69 43.00 2.25 1452.00
- Where the required thickness is more than 150 mm, the aggregate 16 #50 10.65 15.88 2.00 50.80 3.14 2026.83
subbase shall be spread and compacted in two or more layers of 18 #57 13.60 20.28 2.26 57.33 4.00 2581.00
approximately equal thickness 20 #64 16.63 24.82 2.50 63.50 4.91 3166.92
- Maximum compacted thickness of any layer shall not exceed 150 mm
- All subsequent layers shall be spread and compacted in a similar Admixtures – air-entraining admixture shall conform to the requirements AASHTO
manner M-154 | chemical admixtures, if specified or permitted, shall conform to the
requirements of AASHTO M-194 | fly ash, if specified or permitted as a mineral
Grading Requirements admixture and as 20% partial replacement of portland cement in concrete mix shall
Sieve Designation Mass Percent Passing conform to the requirements of ASTM C-618 | admixtures should be added only to
Alternate the concrete mix to produce some desired modifications to the properties of
Standard, Grading Grading Grading Grading
US concrete where necessary, but not as partial replacement of cement
mm A B C D
Standard
25 1” 100 100 100 100
Curing Materials Requirements
9.5 3/8” 50 – 85 60 – 100 - -
Burlap Cloth AASHTO M-182
4.75 No. 4 35 – 65 50 – 85 55 – 100 70 – 100
Liquid Membrane Forming
2.00 No. 10 25 – 50 40 – 70 40 – 100 55 – 100 Compounds
AASHTO M-148
0.425 No. 40 15 – 30 25 – 45 20 – 50 30 – 70 Sheeting (film) materials AASHTO M-171
0.075 No. 200 5 – 20 5 – 20 6 – 20 8 – 25 Cotton mats and water-proof paper can be used
Equipment – tools necessary for handling materials and performing all parts of the Pavement Thickness – the intent of this specification is that the pavement has a
work shall be approved by the engineer as to design, capacity, and mechanical uniform thickness as called for on the plans for the average of each lot as defined
condition | shall be at the job site sufficiently ahead of the start of construction | after the pavement has met all surface smoothness requirements, cores for
operations to be examined thoroughly and approved thickness measurements will be taken
(1) Batching Plant and Equipment
- Shall include bins, weighing hoppers, and scales for fine aggregate and FAILURES, MAINTENANCE, AND REHABILITATION OF TRANSPORTATION
for each size of coarse aggregate INFRASTRUCTURE
- If cement is used in bulk, a bin, a hopper, and a separate scale for
cement shall be included Highway Maintenance – begins just after the construction, reconstruction, or
- Weighing hopper shall be properly sealed and vented to preclude rehabilitation of the roadway facilities | maintenance: preservation and keeping of
dusting operation each type of roadway, roadside, structures, and facilities as nearly as possible in
- Batch plant shall be equipped with a suitable non-resettable batch its original condition as constructed or as subsequently improved the operation of
counter which will correctly indicate the number of batches highway facilities and services to provide satisfactory and safe transportation
proportioned
Objectives of Highway Maintenance
Forms (1) Highway programs and activities are measured by the number of
- Shall be of steel, of an approved section, and of depth equal to the expenditures for the construction of new facilities and reconstruction of
thickness of the pavement at the edge the existing structure with the aim of keeping up with traffic demand
- Base of the forms shall be of sufficient width to provide necessary (2) Maintenance has its own role: by giving priority to local, rural, and
stability in all directions urban facilities particularly the paving and rehabilitation after the
- Flange braces must extend outward on the base to not less than 2/3 construction has been completed
the height of the form (3) Maintenance is focused on the do betterment projects | it includes
- All forms shall be rigidly supported on a bed of thoroughly compacted grading and paving for short alignment changes, correct steep grades
material during the entire operation of placing and finishing the or sharp curves, re-surfacing and mulching, planting, flood, and erosion
concrete control
- Shall be provided with adequate devices for secure setting so that
when in place, they will withstand, without visible spring or settlement, Relationship between Design, Construction, and Maintenance
the impact and vibration of the consolidation and finishing or paving (1) Poor preparation of the base, insufficient slab thickness, and poor
equipment mixture ratio will only result in very expensive road repair | indeed,
- Unless waterproof subgrade or base course cover material is specified, management absorbed the end result of design and construction
the subgrade or base course shall be uniformly moist when the inefficiency
concrete is placed | if it subsequently becomes too dry, the subgrade (2) Poor drainage design will mean erosion or deposition of materials than
or base course shall be sprinkled, but the method of sprinkling shall not requires costly clean-up operations
be such as to form mud or pools of water (3) Sharp ditches and steep slopes require costly manual labor
- Mixed concrete from the central mixing plant shall be transported in maintenance as compared to flat ditches and slopes that allow
truck mixers, truck agitators, or non-agitating trucks specified equipment to work at a lower cost
- The time elapsed from the time water is added to the mix until the (4) Narrow road lanes usually forced large and heavy vehicles to travel
concrete is deposited in place at the site shall not exceed forty-five (45) with one set of wheels near the edge or off the pavement, giving the
minutes when the concrete is hauled in non-agitating trucks, not ninety maintenance personnel serious problems in the care of pavement
(90) minutes when hauled in truck mixers or truck agitators, except that edges and the shoulder
in hot weather or under other conditions contributing to quick hardening
of the concrete, the maximum allowable time may be reduced by the Maintenance is categorized into
engineer (1) Road Surface Maintenance
- Concrete in place within (90) minutes from the time the ingredients - Unlike construction involving a high volume of work, maintenance
were charged into the mixing drum or that has developed initial set operation, deals with a small amount of work at separate locations |
shall not be used and requires speed performance to cause the least possible disruption
- Retempering of concrete or mortar which has partially hardened, that and danger to traffic
is remixing without additional cement, aggregate, or water, shall not be - Maintenance operations require
permitted • For gravel roads, blading and periodic re-shaping or resurfacing
is a routine periodic maintenance activity
Test Specimens • For the surface treatment of low-type bituminous pavement,
- As work progresses, at least (1) set consisting of (3) concrete beam maintenance could be patching, seal coating, remixing, and
test specimens, 150 mm x 150 mm x 525 mm or 900 mm shall be taken relaying
from each 330 m2 of pavement, 230 mm depth, or fraction thereof • For slick asphalt surface, roughening, burning or non-skid seal is
placed each day required
- Shall be made under the supervision of the engineer, and the • For concrete roads, maintenance could be removal and
contractor shall provide all concrete and other facilities necessary in replacement or filling of damaged areas | sometimes joint sealing
making the test specimens and shall protect them from damage by or mud-jacking or under-sealing is relatively common
construction operations maintenance work
- Cylinder samples shall not be used as a substitute for determining the
adequacy of the strength of concrete