T-14.472.478-Sh1-Oa-Work Method Statement For Pile Testing Works - Po 1369043 - LNG Jetty 3
T-14.472.478-Sh1-Oa-Work Method Statement For Pile Testing Works - Po 1369043 - LNG Jetty 3
{QRCODE}
UNIT 7000
WHEN REVISION HAS BEEN MADE TO THIS DOCUMENT THE INDEX OF ISSUE SHALL BE INDICATED IN A TRIANGLE NEAR
THE PART(S) CONCERNED
CLASSIFICATION: MOST CONFIDENTIAL CONFIDENTIAL RESTRICTED UNRESTRICTED
1 Introduction .....................................................................................................................................4
4 TEST LOADS..................................................................... 6
5 References ............................................................................ 8
6 resources ............................................................................. 9
11 Appendices .......................................................................... 36
Partners in the Nigeria LNG Limited invest on building a seventh train (production
line) in the Bonny LNG plant. This is intended to increase the production capacity of
six trains from 22 million MT/year to 30 million metric tons per year.
NLNG's near term expansion plans, called NLNG T7 Project, has the objective to
maximize current and generate additional value by expanding the existing NLNG
Complex with a Complete Train 7 (replica of the T6 as-is design and indicated as CT)
and a new Common Liquefaction Unit (indicated as CLU) that collects excess treated
gases from the existing trains and process it to LNG.
Marine facilities shall be provided for the safe approach, berthing, loading, and
departure of LNG Carriers (LNGCs) exporting LNG for the NLNG T7 Project. The
main items under marine facilities are the addition of a new LNG jetty (Jetty 3),
upgrade of the existing Former Aggregate Berth (F.A.B.) as Material Offloading
Facility (MOF) for the T7 project, the extension of the existing MOF Jetty 2, the
construction of a New Passenger Terminal (NPT) and the dredging of F.A.B. and
MOF areas.
As per the requirements in Section 8.8 of GFS IG 34.85.28-Gen., pile load tests shall
be an integral part of pile design and carried out for the Project.
(1) evaluate the construction method, and to check the sufficiency of the piling
equipment system;
(3) verify the design assumptions and confirm the bearing capacity;
A total of two pre-construction static load tests have been arranged for the LNG Jetty
3 pile foundation, one is selected nearshore for access trestle 42’’ piles, and one is
selected offshore for jetty head 56’’ piles. The exact location of test piles is shown in
Information of the two pre-construction static load tests piles has been summarized
in below.
Access jetty 1816.036 2605.376 +5.0 -44.0 42’’ PCPT19 11080 7500
Mooring &
breasting 1329.084 3107.367 +5.0 -50.0 56’’ PCPT05 12602 7950
dolphins
4 TEST LOADS
It is therefore, the maximum static test loads of 42’’ access trestle pile shall be:
The maximum static test loads of 56’’ mooring & breasting dolphins pile shall be:
Considered that these design pile loads in the SUBCONTRACTOR’s design report
are under the review process and not finalized yet. The maximum static pile test
loads are summarized below with some margin:
- Access trestle 42’’ piles: 7500kN for compression, 2000kN for tensile
- Mooring & breasting dolphins 56’’ piles: 12000kN for compression, 6500kN for
tensile.
Maximum
Structural Type of Pile Diameter of Pile length Test
test load
Unit Load Test pile (mm) Quantity method
(m)
(kN)
It was noted that in the CONTRACTOR’s specification, lateral load tests are also
requested to be carried out on a minimum number of sacrificial piles to be approved
by the CONTRACTOR to verify different soil conditions. However, as the piles will be
designed as long elastic piles with adequate embedded length, the lateral load and
any applied bending moment which can be carried by a long pile are determined
solely by the moment of resistance M of the pile shaft, but not subject to the lateral
resistance provided from surrounding soils. It is therefore the SUBCONTRACTOR
proposed to omit the lateral load test for long piles.
The dynamic load test will be carried out during test pile installation, prior to the static
load test.
5 REFERENCES
The static load tests and dynamic load test procedures shall comply with the
following codes, standards and project documents. Reference documents are shown
in Table 2.1 below.
Table 2.1 Reference Documents
6 RESOURCES
The resources considered necessary to safely and efficiently undertake the pile
testing works are outlined in this section.
6.1 Manpower
Table 3.1 List of Manpower
Total 10
Note: All equipment must be supplied with valid calibration certificates issued by approved and
recognized testing facilities for use and must be checked for condition and safety before work
commences by a trained safety officer.
The pile static load test shall be performed in accordance with the requirements of
specification. Two non-structural test piles will be installed for the static compression
and tensile load tests. For a test pile, tensile load test will be carried out followed by
the compression load test. Time intervals between performing different load tests
shall comply with specification or as permitted by the Company Representative. Piles
shall not be subjected to any load before starting the test.
Pile
Pile Pile Pile top Pile tip Wall Reference
diameter
location length(m) level(m) level(m) thickness(mm) borehole
(mm)
Mooring &
breasting
1422 55 +5.0 -50.0 22.23 BH01
dolphins
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Table 7.1-2 Test Pile details
Pile location Maximum test load (kN) Maximum test load (kN)
Mooring/breasting
dolphins 12000 6500
Note: Compression and tensile are all carried out on the same test pile but at different times.
The static compression load test shall be carried out according to ASTM
D1143/D1143M-20. Anchor piles are required to provide the reaction force and these
consist of four steel tubular piles located around the test pile. The anchor piles will be
linked with steel beams to provide the test pile reaction system. If the reaction force
provided by the anchor piles is not enough for the compression load test, the
kentledge will be loaded to increase the reaction force.
Hydraulic jacks will be placed on the top of test pile and independent piles will be
used as reference piles. Dial gauges will be placed on the reference girders
supported between the reference piles to measure the pile top displacement of the
test pile.
All test equipment will be ‘zeroed’ before commencement of the test and monitored
for excessive movement of the reference beam. The pile position for the load test is
shown in Figures 7.1. Four non-working piles will be used as anchor piles and two
non-working piles will be used as reference piles.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Anchor pile
(D=800mm)
Reference Reference
pile pile
Test pile
(D=1067mm,1422mm)
Anchor pile
(D=800mm)
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
7.1.2 Loading Equipment
The test pile reaction system consists of one main girder, two secondary girders and
other tie girders including pulling bars and plugs.
A precise pressure gauge (precision class 0.4) will be installed on the high pressure
oil pump for loading and unloading. The applied load is measured by means of the
load cells located between the hydraulic jack and main girder at the same time.
Four dial gauges ( Precision Class 0.01mm ) will be placed on the Reference
Girders to measure the 'pile top' displacement.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
During the test, dial gauges installed on the anchor pile shall be read.
The arrangement of the reaction system and test platform are shown in Figure
7.2~7.6.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Figure7.2 Static Axial Compression Load Test
Screw Cap
Distribution Beam
Main Girder
Screw Cap Load cell
Distribution Beam
Hydraulic Jacks(320t)
Reference Pulling Rod of Anchor Pile Bearing Plate Reference
Secondary Girder
Beam Plug Dial Gauge
Spot Welding Beam
Figure7.3 Equipment installation for the static axial compression load test
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Anchor pile
Second girder (D=800mm)
Main girder
Reference
girder
Anchor pile
(D=800mm) Second girder
Layout plan
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
COMPANY Project No: B190170NTP
LOCATION: BONNY ISLAND, NIGERIA PROJECT: NLNG TRAIN 7
CONTRACTOR Project No: N88480
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Figure7.5 Detail Drawing of the Anchor Pile Connection
Reference pile
Reference girder
Reference girder
I-steel56a
Anchor ear
unit:mm
But according to our loading equipment, loading mode and previous test experience
of this test, it is difficult to meet the requirements of Constant Rate of Penetration
Test. Because the settlement rate of the pile is difficult to control. Therefore, it is
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
requested to change the test procedure to Procedure B: Maintained Test in ASTM
D1143-20.
The loading procedure should start by a load of maximum 0.05P in order to check
the loading and measurement equipment. The pile load shall be increased in steps
and each step shall be held constant over a certain specified duration. The maximum
test load P shall be reached in minimum 10 load steps.
Each loading and unloading step shall be maintained for a minimum duration, which
should be the same for all loading steps and the same for all unloading steps
respectively. A minimum duration of 60 min is recommended for the loading steps.
The loading and unloading procedures are shown in Table 7.4 and 7.5.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Table7.4 Loading and unloading procedure for pile compression load test in trestle
1 0.1P 750 60
2 0.2P 1500 60
3 0.3P 2250 60
4 0.4P 3000 60
5 0.5P 3750 60
6 0.6P 4500 60
Loading
7 0.7P 5250 60
8 0.8P 6000 60
9 0.9P 6750 60
10 P 7500 120
11 0.75P 5625 10
12 0.50P 3750 10
Unloading
13 0.25P 1875 10
14 0 0 60
Table7.5 Loading and unloading procedure for pile compression load test in mooring/breasting
dolphins
1 0.1P 1200 60
2 0.2P 2400 60
3 0.3P 3600 60
Loading
4 0.4P 4800 60
5 0.5P 6000 60
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Load the Minimum
Serial Pile Top Load Maintenance Time State of
Number load (kN) per Stage Load (min)
(kN) Load
6 0.6P 7200 60
7 0.7P 8400 60
8 0.8P 9600 60
9 0.9P 10800 60
10 P 12000 120
11 0.75P 9000 10
12 0.50P 6000 10
Unloading
13 0.25P 3000 10
14 0 0 60
1. Record test readings taken before and after the application of each load increment or
decrement. During each load interval, record additional readings taken at 5, 10, and 20 min
following application of the load increment, and every 20 min thereafter as needed, and as
applicable depending on the length of the increment.
2. If pile failure occurs, record readings taken immediately before removing any load.
During each unloading decrement, record readings taken at time intervals of 2 min following
partial removal of load, for up to 10 min and every 10 min. Record final readings 1 h after
removing all load.
3. Following each load increment, the load will remain at least for the time shown in the
table above until the settling rate is less than 0.25mm / h and decreases gradually. The
settlement rate will be calculated from the slope of the curve, which is obtained by plotting
the relationship between the settlement value and time and drawing a smooth curve from
these points.
4. Terminate the load condition If one of the following conditions occurs, stop the load and
enter the uninstaller:
(a) When reaching the maximum test loads of the trestle test pile and mooring/breasting
dolphins test piles as specified in Table 4.2;
COMPANY Project No: B190170NTP
LOCATION: BONNY ISLAND, NIGERIA PROJECT: NLNG TRAIN 7
CONTRACTOR Project No: N88480
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
(b)the ultimate resistance mobilized at a pile head penetration equal to 10 % of the pile
diameter;
But according to our loading equipment, loading mode and previous test experience
of this test, it is difficult to meet the requirements of Constant Rate of Penetration
Test. Because the settlement rate of the pile is difficult to control. Therefore, it is
requested to change the test procedure to Procedure B: Maintained Test in ASTM
D3689/3689-22.
The static tensile load test may be conducted after the static compression test with
the time interval between these tests to be not less than 3 days.
The load reaction system for the static tensile test is similar to the system for the
compression test with one difference. The system includes one main girder, two
secondary girders and other tie girders with pulling bars and plugs. The difference is
that the jacks are put on the top of the main girder instead of being put on top of the
pile for loading and unloading.
Before the test commences, it is necessary to form a wide slot or ‘cut-out’ at the top
of the steel tubular anchor piles for securely locating the secondary girders. When
the test begins, Jacks are positioned on top of the main girder to load and unload it,
as shown in Figure 7.7. The reaction system for the static tensile load test is shown
in Figure 7.8 and the arrangement of the jacks on top of the main girder is shown in
Figure 7.9.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
The loading equipment and observation equipment are the same with the
compression test, the detail can be seen in 7.1.2 and 7.1.3.
Load cell
Screw Cap
Distribution Beam Hydraulic Jacks(320t)
Pulling Ro of Main Girder
Pulling Rod of tensile
Figure 7.8 Equipment Arrangement for the Static Tensile Load Test
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
pulling bar
balance girder
main girder
Jack
tie girder
Figure 7.9 Plan view of the jacks on the top of the main girder
The procedure B ‘Maintained Test’ from ASTM D3689/D3689M-22 will be used. The
loading and unloading procedures for the pile load tests are shown in Table 7.6 and
7.7.
Table7.6 Loading and unloading procedure for pile tensile load test in trestle
1 0.1P 200 60
2 0.2P 400 60
3 0.3P 600 60
4 0.4P 800 60
5 0.5P 1000 60
6 0.6P 1200 60
Loading
7 0.7P 1400 60
8 0.8P 1600 60
9 0.9P 1800 60
10 P 2000 120
11 0.75P 1500 10
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
12 0.50P 1000 10
Unloading
13 0.25P 500 10
14 0 0 60
Table7.7 Loading and unloading procedure for pile tensile load test in mooring/breasting
dolphins
1 0.1P 650 60
2 0.2P 1300 60
3 0.3P 1950 60
4 0.4P 2600 60
5 0.5P 3250 60
6 0.6P 3900 60
Loading
7 0.7P 4550 60
8 0.8P 5200 60
9 0.9P 5850 60
10 P 6500 120
11 0.75P 4875 10
12 0.50P 3250 10
Unloading
13 0.25P 1625 10
14 0 0 60
1、Record test readings taken before and after the application of each load
increment or decrement.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
During each load interval, record additional readings taken at 5, 10, and 20 min
following application of the load increment, and every 20 min thereafter as needed,
and as applicable depending on the length of the increment.
2、If pile failure occurs, record readings taken immediately before removing any load.
During each unloading decrement, record readings taken at time intervals of 2 min
following partial removal of load, for up to 10 min and every 10 min. Record final
readings 1 h after removing all load.
3、 Following each load increment, the load will remain at least for the time shown in
the table above until the settling rate is less than 0.25mm / h and decreases
gradually. The settlement rate will be calculated from the slope of the curve, which is
obtained by plotting the relationship between the settlement value and time and
drawing a smooth curve from these points.
4、 Terminate the load condition If one of the following conditions occurs, stop the
load and enter the uninstaller:
( a ) When reaching the maximum test loads of the trestle test pile and
mooring/breasting dolphins test piles as specified in Table 4.2;
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
(2) Particular description of the test pile, including piling record and data for pile
construction and testing;
(3) Statement of the test method and test equipment, including figures and photos
of the reaction system, deformation measurement equipment, position, size and
reference elevation of the tested pile;
(4) ) Test procedure and result, including test record, curve of load-
settlement, curve of time-settlement, and ultimate resisting-pull up capacity.
(5) Test procedure and results, including test records, curve of load-settlement,
curve of time-settlement, and ultimate tensile (pull-out) capacity.
Assuming the pile is a one-dimensional linear elastic bar, the impedance can be
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
calculated by multiplying unit specific density by the wave speed and cross-sectional
area. Alternatively, it can be calculated by multiplying the cross-sectional area by
Young’s Modulus of Elasticity and dividing the product by the strain wave speed.
Where:
Z = impedance
A = cross-sectional area
c = wave speed, the speed with which a strain wave propagates through a pile.
= mass density.
Pile stress-strain relationship can be written as:
E (2)
F A E (3)
Assuming the resistance of soil is composed of static resistance and dynamic
resistance:
R Rs Rd (4)
2u 2 2u R
c
x 2 A
t 2
(5)(5)
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
According to the measured force and velocity curves, namely, F(t )andV(t ), the
following equation can be derived to determine the bearing capacity of pile.
F (t1 ) Z V (t1 ) F (t2 ) Z V (t2 )
1 Jc (1 J )
c 2
Rc 2 (6) (6)
Where:
t1 =time of impact
t2 t1 2L / C
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
8.3 Testing Procedure
(1) The sensors shall be attached by bolts through the steel(concrete) wall of the
pile. Prior to driving the steel tubular pile(PHC pile) into the ground, the bolt holes
shall be drilled and located at least 1.5 times the pile diameter from the top of the pile.
PAL will be used here, which includes 2 strain transducers and 2 acceleration
transducers. Sketch of locations of accelerometers and strain transducers is shown
in Figure 8.2.
(3) Once test preparation is completed, the hammer commences pile driving.
Results are then obtained from the dynamic load test and shall not be disrupted until
the required signal has been recorded.
(4) For test piles, PDA testing would be carried out throughout the installation of the
pile. 7 days after the initial driving, preliminary piles would be re-tapped. For
permanent piles, PDA testing would be carried out at the conclusion of pile
installation.
(5) The procedure of re-tapping is identical with the initial driving. Install the
transducers using the holes which are already drilled. Then, connect main cables to
the piling analyzer and input the pile parameters. Re-tapping of a pile may involve up
to 50 hammer blows per pile penetration of as much as 150 mm.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
D
Acc 1
Strain 1
1.5D
D
Strain transducer
Steel pile
Strain 2
(3) Maximum measured force applied to the pile head, maximum measured pile
head velocity, and maximum energy imparted to the pile.
(4) Graphical presentation of the recorded force and velocity in the time domain for
representative blow of each pile tested.
(5) Bearing capacity (for initial driving test) and ultimate bearing capacity (for re-
tapped test).
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
(6) CAPWAP analysis results of skin and toe resistance.
(7) Load versus force graph (Q-S curve) of the simulated static load test.
(8) Assessment of the test results with respect to pile capacity and integrity.
(2) All equipment must be calibrated and checked before the test to ensure it is
working correctly;
(3) The reference piles and reference beams must be totally independent of the
anchor piles or test pile;
(4) The reference beams must be shaded from direct sunlight to minimise the effects
of high temperatures.
(5) If the pressure in the jacks fall during the load holding period, the pump must be
restarted immediately to reinstate the pressure.
(6) During the test, piling operations within a distance of 50m should cease including
all tests producing vibration and impact.
(7) The test procedure must strictly follow the requirements of the specification.
(8) Any deviation from the anticipated load increment and data measurement
procedures should be recorded.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
9.2 Health and Safety
(1) This project shall be executed in full compliance with all safety procedures and
standards as required by the contract. This includes the establishment of the project
safety team.
(2) Regular safety awareness programs shall be conducted to instill the safety
culture and awareness on the construction site. This project shall have the "Safety
First, Focus on Prevention" policy.
(4) Safety helmets and life jackets are compulsory when working on the platform.
(5) Testing personnel must pay attention during the change of test equipment and
anchor piles during loading. If any unexpected situation develops, the test should
pause and safety checks must be carried out before recommencing the test.
(6) Testing cannot be carried out in foul weather such as gales, or great waves to
maintain personnel safety.
(7) All unloading, installation of plant and equipment and erection of cranes must be
supervised by experienced and fully trained personnel. A superintendent or similar
will be specifically appointed to ensure that these operations are carried out safety
and to the required procedures.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
(2) The rubbish and waste from off-shore construction activity must be regularly
removed by barge to the on-shore approved dumping ground.
10 TIME SCHEDULE
Time schedule of the one pile load test (trestle test pile) is shown in Table 10.1. The
other one pile load tests will be carried out depending on site conditions.
6 Checking 2 days
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
11 APPENDICES
No Appendix Title
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
APPENDIX 1 GEOTECHNICAL CALCULATIONS AND VERIFICATION OF
THE ANCHOR SYSTEM
Anchor pile calculation for the approach trestle test pile and working platform test pile using
API method.
Approach
Trestle BH04 35 0.8 +5.0 -30.0 +2.5 124
Mooring/b
reasting BH01 57 0.9 +5.0 -52.0 -14.0 282
dolphins
Cohensionless
Soil layer Cohesive soil(i.e.Clay)
Soil(i.e.sand)
layer
layer
bottom
thicknes friction
Laye soil s
elevatio γ Su PO` Φ α β PO`
limit
r NO type n
layer layer
thickness bottom γ friction
Layer soil Su PO` Φ α β PO`
elevation limit
NO type m m, CD kN/m³ kPa kPa Su/po` kPa kPa
Uplift
layer Unit Accumulated
friction
layer bottom Friction shaft Pile of the Uplift shaft
Layer soil thickness elevation limit capacity Reduction diameter layer capacity
NO type factor(lift)
m mCD kPa kPa m kN (kN)
Uplift
layer Unit Accumulated
friction
layer bottom Friction shaft Pile Uplift shaft
of the
Layer soil thickness elevation limit capacity Reduction diameter layer capacity
NO type factor(lift)
m mCD kPa kPa m kN (kN)
Mooring/b
reasting
dolphins 14529.99 800 1128.5 16458.49 12000 1.37 YES
The calculated uplift shaft capacity is more than required uplift shaft capacity. Safe.
The maximum compression test load maybe 12000kN and the maximum tensile test load is
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
6500kN.
The material of the reaction frame is Q345 steel and its performance is shown in Table. A.2.1.
The main girder adopts a box section form and the elevation and cross section is shown in
Figure A.2.1.
B A
B A
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
The design calculation diagram is shown in Figure A.2.2. and the span of the main girder
is10.0m
12000kN
Mmax=30000kN·m
Figure A.2.2. Calculation diagram of main girder
BH 3 bh3 1.161.831.11.73
W 0.126m 3
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
2
6H 61.8
The maximum stress at the middle of the main girder is as follow:
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
, safe
<L/400=10000/400=25.0mm, safe.
The above calculation shows that the section size meets the requirements for bearing capacity.
The length of the secondary girder is actually 13.6 meters and the span is 10.0 m.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
6000kN
Mmax=15000kN·m
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
The maximum test load is 12400kN and the force of each secondary girder is 6200kN. The force of each anchor
<L/400=9000/400=22.5mm, safe.
The above calculation shows that the section size meets the requirements for bearing capacity.
The maximum test load is 12000kN which is shared by 8 pull rods. The tensile of each pull rod:
P=12000/8=1500kN. The diameter of each rod is 140mm, thread is M115×6, thread pitch
t=6mm, effective diameter of rod at the thread de=d-1.0825t=133.505mm. A typical pull rod of
the main girder is shown in Figure A.2.5.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Area of thread of pull rod:
Maximum tensile stress of thread:
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
, , it satisfies the strength.
The maximum test load is 6600kN which is shared by 4 pull rods. The tensile force of each pull
rod: P=7000/4=1750kN. The diameter of each rod is 140mm, thread is M110×6, thread pitch
t=6mm, effective diameter of rod at thread de=d-1.0825t=133.505mm.
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
, , So satisfies the strength requirement.
The maximum test load is 12000kN, and acted by 8 pull rods. Tensile of each pull rod:
12000/8=1500kN.
The diameter of pull rod of anchor pile is the same as the diameter of pull rod of main girder,
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
and the tensile force is also the same. The most unfavorable position is the hole for bolt. The
maximum tensile stress:
1960
350
40
60
60
50 d=50 50 30 220 35
360
280
350
1.Web:302801960
60
1 0
6 1
0 2 A
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
1960 S
e
c
t
i
120 160 o
n
A
-
A
350
40
B
30 220 35
350
156
360
280
B
350
A 276
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
1500kN 1500kN
Load distribution
Mmax=222.0kNm
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
The maximum stress of section A-A is as follow:
, safe
The maximum stress of section B-B is as follow:
, safe
So it satisfies the strength requirement.
Distribution beam of pull rod of tensile is the same as distribution beam of pull rod of anchor
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
pile. The maximum test load is 7000kN which is connected to 4 pull rods. The tensile of each
pull rod: 7000/4=1750kN.
1500kN
Mmax=933kN·m
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
CONTRACTOR Doc No: LG70-ZX-E-72478
UNIT: 7000
Appendix 3 RECORD TABLES OF PILE TESTING
Hydraulic
jacks: Dial gauges:
Record: Check:
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3
Dynamic load Testing of Piles
Table No: Page of
Subdivisional
Project work Code Condition
Type of
hammer
Apparatus Hammer weight Pile cushion
Status of apparatus
WORK METHOD STATEMENT FOR PILE TESTING COMPANY Doc No: T-14.472.478
WORKS - PO 1369043 - LNG JETTY 3