Wiring Works
Wiring Works
Prerequisites-
1.Induction, Screening, Medical Fitness Certificate and ID card should issued before entry. 2. Tool Box Talk. 3. JST Before to deploy the work 4. Ensure work
Permit (General, Height, Lifting, Scaffold erection and dismantling) before start of the work. 5.Ensure Mandatory / Job specific PPE'S (Helmet, safety shoes,
Reflective jacket, Goggles, Nose mask, Hand gloves, Safety harness).
3.a. Ensure appropriate PPE while handling the material. (hand gloves,
nose mask, goggles)
3.b. Ensure to Deploy sufficient man power to complete the task
3.d. Ensure Continuous Supervision
1.a. Prior to start the work, Height work permit has to be taken
1.b. Ensure to take Scaffold Erection & Dismantling permit
1.c. Ensure safety harness above 1.8mts
1. Fall of person 1.d. Competent person need to perform the job
2. Fall of materials
3. finger punctures 1.e. Need to provide proper working platform as per scaffold inspection
checklist..
4. Excessive Noise 1.f. Safety Harness has to inspected as per the inspection checklist
1.g. Do not move the scaffold from one place to another place with
person on it. Site Engineer/
3 Mobile scaffold usage
5. Scaffold collapse Safety Engineer
6. Incompetent Person 2.a. Ensure catching net above 2mts
2.b. Hand tools has to be used with hand roil tie
7. Scaffold roll over 2.c. Ensure barricading while usage of
8. Electrocution scaffolding
9. Horseplay 2.d. No materials shall be stored on working platform ensure no rolling
10. Slip & trip type materials also not to be kept on working platform
3.a. Ensure Competent person need to perform the job.
1.a To prevent collision of boom lift with other vehicles or plants in the
vicinity, use signs, traffic cones and barricades
1.b In areas where boom lift is to be used, all travelling overhead cranes
Site Engineer/
work location safety 1. Collision must be isolated and tagged out.
Safety Engineer
1.c When the boom is raised, do not allow persons near the machine.
1.d On completion, store the machine in a secure area, lower the boom
fully and remove the key.
2.a Use the cones, signs and barricades to protect the work area.
Site Engineer/
2. Falling objects
Safety Engineer
3.a Do not allow unauthorized entry and use Site Engineer/
3. Unauthorized use
Safety Engineer
4.a Inspect the path which the machine will be traversing. Make sure
there is adequate clearing and that the surface will not make the
machine lose stability while travelling. Site Engineer/
4. Instability 4.b Before travelling, make sure that the boom is retracted and is Safety Engineer
lowered.
4.c Make sure the cage gates remain closed.
1.a Make sure all persons in the EWP bucket are wearing proper safety
harnesses to prevent them from falling.
1.b Ensure safety harness has to be checked as per the inspected
checklist
1.c When in an elevated position, never open the gates.
Site Engineer/
Working at heights 1. Persons falling 1.d Never try to climb on, sit or stand on platform guard rails.
Safety Engineer
1.e Ensure high drive cutout is in working condition before start the
activity
1.f Make sure the anchor points in the platform are in proper condition
2.a Ensure not more than 3 members loaded at a time in the platform Site Engineer/
2. Overloading of platform 2.b Make sure never to exceed the safe working load of the EWP. Safety Engineer
3.a The total load in the bucket of the EWP, including all materials,
equipment, tools and personnel must never exceed the safe working
Site Engineer/
load of the unit.
3. Falling objects Safety Engineer
3.b Never use the boom lift as a crane for lifting materials. Carry loads
within the confines of the platform cage only.
4.a Before commencing work, make sure the electric wires are either Site Engineer/
4. Electric shock
de-energized or must be insulated in the properly Safety Engineer
2. Fire Hazards 2.a Isolate Ignition sources include pilot lights, stoves, heaters,
cigarettes, matches/lighters, grinding, welding, power points, lighting, Site Engineer/
light switches, radio transmitters, mobile phones, battery powered Safety Engineer
forklifts etc
3.a Avoid breathing vapors or contact with fuel, If clothing is splashed
with fuel, change it immediately
3. Chemical exposure (fuel,
3.b Never Siphon or swallow fuel as this can be fatal Site Engineer/
lubricants)
3.c Do not eat, drink or smoke during/after-handling fuel until hands are Safety Engineer
carefully washed.
3.d Shower and wash immediately after work.
1.a Need to place them at flat surface area.
1.b Ensure rubber feet for firm grip
1.c Deploy one person need to hold the Ladder.
1.d Ensure spreader without damage locking mechanism
6.c Ensure proper gripping to the ladder legs and stoppers should be
provide to avoid slips of ladder.
2.a Ensure Hand tools has to tie with hand tool tie
1. Cut, Hit injury & Sharp
2.b Insulated hand tools must be used, and hand grip must be provided
edges
Pulling of Wires through to avoid slippages Site Engineer/
6 2. Slippage of hand tools or
GI Spring 2.c Continuous effective supervision must be insured Safety Engineer
Improper tools
3. Unauthorized entry
3.a Authorized persons has to enter into the work area
3.b Ensure work area should be barricaded and signage's need to be
displayed
1. Cut, Hit injury & Sharp 2.a Insulated hand tools must be used, and hand grip must be provided
edges to avoid slippage Site Engineer/
8 Termination
2. Improper tools 2.b Continuous effective supervision must be insured Safety Engineer
3. Incompetent person
3.a. Experienced / Competent person need to perform the job
3.b. Ensure that work area should be barricaded and signage's need to
be displayed
Prepared by Reviewed by Reviewed by Reviewed by Reviewed and Approved by Reviewed and Approved by
Micron EHS Engineer Micron Project Manager FABS Site Engineer FABS EHS Engineer BOSCH EHS Manager BOSCH Project Manager