Work Methodology For Fuel Oil Tank Foundation
Work Methodology For Fuel Oil Tank Foundation
Engineer will provide with necessary men, material and instructions for
such checking. This checking by the engineer prior to start of the work will
in no way absolve the contractor of his responsibility of carrying out the
work to true lines and levels and grades as per drawing and subsequent
corrections , if necessary , in case any errors and noticed in the contractors
work at any stage.
3) The boundary points of the fuel oil tank foundation mentioned on the
above are demarcated on ground.
1.0 Objective
2.0 Scope
This procedure is applicable for backfilling and area compaction work
at our project.
3.0 Reference
4.0 Details
Spade
Basket
Pick
Shovel
4.2 Machinery
Hand rammer
Plate Compactor
Dumper
Any mechanical means(if applicable)
b) Backfilling shall be carried out layer by layer using soils from dumps
designated/approved by the Owner. For each specified dump,
laboratory tests shall be carried out by QC engineers for
determination of optimum dry density and optimum moisture
content in terms of both Proctor Density and Modified Proctor
Density and the results shall be intimated to site execution group.
c) As soon as the work in foundations have been accepted and measured, the
spaces around the foundation structures in pits and trenches shall be cleared of
all debris, brick bats, mortar droppings etc. and shall be filled with earth in layers
not exceeding 150mm, each layer being watered as per the Proctor Density
requirement, rammed and properly consolidated and compacted before the
succeeding layer is laid. Each layer shall be compacted to a dry density not less
than ninety five percent (95%) for Road works and other places minimum of 80%
of the maximum Standard Proctor Dry Density. Standard Proctor Density tests
shall be conducted by the Contractor on soil proposed to be used in the backfill.
Field density tests shall be conducted as directed by the Engineer. Subsequent
filling shall be done only after ensuring satisfactory mechanical compaction of
previous layer. Earth shall be rammed with approved mechanical compaction
machine. No manual compaction shall be done. The final surface shall be trimmed
and leveled to proper profile as indicated in the drawings and as directed by the
Engineer. All backfilling shall be carried out with prior approval of Engineer after
ensuring that no underground services are to be laid in the area.
Reinforcement :-
Before starting the concrete, reinforcement and shuttering are the most
important part. Reinforcement is used to hold the tensile stress of the concrete.
Form Work :-
1. Objective
2. Scope
This procedure is applicable for all types of Formwork for the concrete
shapes indicated in the Owner’s drawings and Technical Specification
under scope of the Contractor for the project.
3. Reference
This Procedure is based on the requirements of the Owner’s Technical
Specification for Package-IV Civil/Structural works, applicable Indian
and foreign standards, Owner’s PO Document and the relevant sections
of the Contractor’s Project Quality Manual . Definitions and
nomenclature applied in this document are in conformity with ACIL’s
QMSP.
Resource Deployment
The Contractor shall deploy any or all of the following resources as dictated by the type of
formwork.
4.3 Material
4.4 Consumable
Wire nails
Form Oil except for surfaces to be painted later.
4.5 Manpower
Adequate skilled, semi-skilled and unskilled manpower shall be arranged for
every activity described hereafter.
4. Procedure Details
5.1 General
The form work shall consist of but not limited to shores, bracings, sides of
beams, columns, walls, rafts and bottom of slabs including ties, anchors,
inserts, hangers, false work, wedges etc. complete, which shall be properly
planned for the work. For the floors, supports can be taken from the floors
down below with prior permission of the Owner’s Engineer. Wherever
required provision shall be made to support the floor shuttering by means of
trusses, which shall be spanned from the near by walls/ columns.
5.2.1 Formwork
i) All horizontal forms shall be constructed for pressures from the dead
load of the concrete and embedments and a minimum live load of
200 kg/m2. For any additional loads, the formwork shall be suitably
designed.
a) Dead Load
Concrete load -- 2500 kg/cum. (set concrete)
Self weight -- as per design.
Top formwork -- as per design
Reinforcement in Un-concreted area -- 200 Kg/sqm on plan
area
b) Live Load
As far as possible MS tie rods left in type shall be used for supporting
all forms. Retrievable type can also be used with the prior approval of
the Engineer. Tie rods shall have provision for removal of a section of
each rod at surface of the concrete to a depth of approximately 50mm.
All holes left by the removal of conical nuts or other removable fixtures
embedded in the face of the concrete shall be filled and finished with
cement-sand mortar in a manner specified in the finishing specification.
Use of internal through ties in the structures below ground level shall
not be permitted. Threaded inserts embedded on each face of the wall
shall be cut for attaching the forms to previously placed concrete. No
tie rods shall be directly welded onto the wall liners.
Through Tie rods shall be permitted only upon approval of the Engineer
and when permitted shall be cut off flush with the face of the concrete,
or the countersunk, filled and finished, as required by the Engineer, in
the manner specified under the finishing specification. Measures shall
be taken to prevent rust stains on concrete.
5.6 Joints
Forms and their supports shall not be removed without the approval of
the Engineer. Improper methods of removal of formwork likely to cause
overstressing or damage to the concrete shall not be used. Supports
shall be removed in such a manner as to permit the concrete to
uniformly and gradually take the stresses due to its own weight.
Table Showing Formwork Release Times for Concrete with Ordinary Portland
Cement
Striking shall be done slowly with utmost care to avoid any damage to
concrete surfaces or any projections on it and without shock or
vibrations, by gently easing the wedges/ jacks. If after removing the
formwork, it is found that timber has been embedded in the concrete, it
shall be removed and made good as approved.
Tie rods, clamps form bolts etc., which must be entirely removed from
the walls or similar structure shall be loosened not sooner than 24
hours after the concrete was deposited.
All pre-cast units shall be cast in a suitable yard, bed or platform with
firm foundation and free from wind. The platform shall have a smooth
plaster finish. The yard shall be fenced and shall have a curing tank of
adequate size. The Contractor shall be responsible for the accuracy of
the level and shape of the bed or platform. A suitable serial number
and the date of casting shall be impressed or printed on each unit.
Each unit shall be concreted in one operation. Reinforced concrete
members shall be marked to indicate the upper surface.
The form shall be of steel sheets with rigid steel frames. All
components of formwork shall be so held that during casting there is
no deformation of the form resulting in the concrete units not
conforming to dimensions indicated in the drawings. The shuttering
shall be made with a tolerance of (+/-) 3mm in all directions.
The side shutters shall not be struck in less than 24 hours for Ordinary
Portland Cement and 72 hours for Portland Pozzolana Cement after
concreting and no pre-cast unit shall be lifted during striking the form.
+50mm to –12mm
1. Dimensions in Plan
2. Eccentricity 0.02 times the width of
the footing in direction of
deviation but not more
than 50 mm.
CONCRETING:--
5. Objective
6. Scope
7. Resource Deployment
The Contractor shall deploy any or all of the following resources as dictated
by the volume and nature of concrete work.
Concrete Pump.
Concrete pipeline
7.2. Plant & Machineries (contd)
7.3. Manpower
Adequate skilled, semi-skilled and unskilled manpower shall be arranged for
every activity described hereafter.
8. Procedure Details
i) The vibrator shall penetrate full in the layer being placed and also
penetrate the layer below by about 50 mm while it is still plastic,
to ensure good bond and homogeneity between the two layers
and prevent the formation of cold joints.
j) Care shall be taken to prevent contact of vibrators against
reinforcement steel. Vibrators shall not be brought in contact
with reinforcement steel after start of initial set. Vibrators shall
not be allowed to come in contact with forms or finished surfaces
and embedment.
a) Rigid Pipelines
b) Couplings
The couplings provided to connect both flexible and rigid pipe
sections shall be adequate in strength to withstand handling during
erection of the pipe system, misalignments, and poor support along
the lines. They should be nominally rated for at least 3.45 MPa and
greater for rising over 30 meters. The strength and tightness of
joints shall be guaranteed. Couplings shall be designed to allow
replacement of any pipe section without moving other pipe sections,
and shall provide a full internal cross-section with no obstructions or
crevices to disrupt the smooth flow of concrete.
.
The Contractor shall ensure that obstructions are not found in the
pipe due to interruption in the feed of the concrete by more than
30 to 45 minutes. Minor blockages shall be cleared by operating a
few strokes of the pump in reverse momentarily and then by
returning to normal forward pumping. If this fails, a succession
of reverse and forward strokes shall be carried out to remove the
blockage. Should this fail also, the blockage may be due to air
lock and the entrapped air has to be removed.
c) The use or otherwise of epoxy for the repair work will be at the
discretion of the Owner’s Engineer. Epoxy shall be applied in
strict accordance with the instructions of the manufacturer.
Epoxy shall be used as a bonding agent prior to placing fresh
concrete. The Contractor for this job shall arrange approved
material.
Brickwork:
BRICK WORK IS DONE IN ONLY DRAIN SUMP.
Purpose
1. Spade.
2. Shovel.
3. Basket.
4. Mason tools.
Reference IS Codes
Material
All Bricks used must be approved prior to the actual use at site.
Bricks are to be checked for its dimension, straightness, strength and
efflorescence
Bricks shall be sound, hard and homogenous in texture, well burnt and deep red,
cherry copper coloured of regular shape and size.
The minimum crushing strength should not be less than 50 kg/cm 2.
Workmanship as & when applicable:-
Mortar for brick masonry shall consist of cement and sand and will in the
proportion of 1:5 for brickwork of thickness one brick and above 1:4 for brickwork
of thickness half or below, unless otherwise specified in the respective items of
work.
For preparing cement mortar, the ingredients shall first be mixed thoroughly in
dry condition.
Water shall then be added and mixing continued to give a uniform mix of required
consistency. Mixing shall be done in the mechanical mixer unless hand mixing is
specifically permitted by the engineer.
The mortar thus mixed shall be used as soon as possible, preferably within 30
minutes from the time water is added to the cement.
Any mortar which is partially set shall be rejected and shall be removed forthwith
from the site.
Bricks shall be thoroughly splashed with clean water at least one hour
immediately before being laid.
Brickwork 250mm thick shall be laid in English bond unless otherwise specified.
Each brick shall be slightly pressed into the mortar and shoved into the final
position so as to embed the brick fully in the mortar. Only full size bricks shall be
used for the works and cut bricks utilized only to make up required wall length or
for bonding.
Bricks shall be laid with frogs uppermost.
All brickwork shall be plumb, square and true to dimension shown.
Vertical joints in alternate courses shall come directly one over another and be in
line. Horizontal courses shall be leveled.
The thickness of the brick courses shall be kept uniform.
In case of one brick thick and half brick thick wall, at least one face should be kept
smooth and plane, even if the other is slightly rough due to variation in size of the
bricks.
The thickness of the joints shall not be less than 6 mm and not more than 10 to
12mm. Raking of joints should be properly done.
Brickwork shall be kept constantly moist on all the faces after 24 hrs laying for 7
days.
Double scaffolding having two sets of vertical supports shall be provided to
facilitate execution of masonry works. Scaffolding shall be properly maintained
during the entire period of construction.
PVC mesh fabric shall be provided at the junction of brick masonry and concrete
before taking up the plastering work.
Transoms and Mullions are to be fixed as per the drawing
Brickworks shall be kept clean and free from damages, discoloration, etc, at all
times.
Miscellaneous: