0% found this document useful (0 votes)
9 views3 pages

Smart3D-X Installation Condition Requirements - EN - 2024

The document outlines the installation requirements for Smart3D-X equipment, including specific dimensions for X-ray rooms and workstation areas, as well as power supply and safety requirements. It emphasizes the need for proper shielding, grounding, and interconnections between equipment, along with environmental conditions for operation. Additionally, it highlights the importance of a reliable internet connection and system compatibility for external PCs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views3 pages

Smart3D-X Installation Condition Requirements - EN - 2024

The document outlines the installation requirements for Smart3D-X equipment, including specific dimensions for X-ray rooms and workstation areas, as well as power supply and safety requirements. It emphasizes the need for proper shielding, grounding, and interconnections between equipment, along with environmental conditions for operation. Additionally, it highlights the importance of a reliable internet connection and system compatibility for external PCs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Smart3D-X Installation Condition Requirements

(Reference)

1. Equipment Dimensions (with Ceph)


2. Installation conditions (recommended):

Item Requirements Notes

Not Less Than:


CT+Pano 1.6m(L) × 2.0m(D) × 2.4m(H);
Door of Room:≥ 0.5m It is not recommended to open the door
X-ray Room
Not Less Than: inward.
CT + Pano + Ceph 2.5m(L) × 2.0m(D) × 2.4m(H);
Door of Room:≥ 0.5m

Installation Space
Workstation Not Less Than: It is recommended to have a separate
Room 1.5m(L) × 1.0m(D) × 2.4m(H); room for the CT workstation.

Floor Ground load-bearing >250kg Record the number of floors

The wall or floor building material


Mounting Type On the Wall OR On the Floor
should be suitable for punching and
fixing

- Wall, Door and Window ≥ 2mmPb, equivalent;


Floor slabs, wall vents and ventilation ducts or conduits, Please observe local radiation protection
X-ray Room
etc., are required to meet the above shielding regulations.
Radioprotection (recommended)
requirements.

Workstation
-
Room

- Voltage:single phase, 220/230VAC, ±10%;


- Frequency:50/60Hz;
1. Must be well grounded.
- Power supply resistance ≤1.0Ω;
2. Direct connection is required. (If you
X-ray Room - Power Capacity:2.5kVA;
Power Supply choose a plug connection, please
- Independent Outlet
Requirements purchase it locally)
- UPS or voltage Stabilizer (at least 3.5kVA capacity)
is highly recommended

Workstation It is highly recommended to have a UPS for the


Room workstation

Available for:
External interlocking connections are available if Power-on Indicator(24V),Exposure
Safety X-ray Room
required. Indicator(24V),Interlock、
Emergency Stop Interlock Interface

Between CT If the workstation is placed outside the X-ray room, the


Inter-connections Machine and hole will need to be punched in the wall to pass through Two or three 10m-Ethernet cables
Workstation the cables.

For activating software licenses, remote


assistance to support services such as
Internet A good Internet is necessary
calibration, troubleshooting, and
upgrades etc.

- System Requirements:
Network
Windows 7 or any newer operating system, and the
Requirements
External PCs operating environment with runtime library of VC2010,
with Imaging 2015 and .net framework version 4.5 and above.
Viewer (if need) - The external PC should be on the same LAN network
as the CT workstation

Temperatures: 10~35℃
Operation Equipment
Humidity: 20%~80%
Environments Room
Atmospheric Pressure: 760~1060hPa

Other Special
Record and Asses the request from the Customers.
Demand