Standard operating procedure of UF Plant.
Start-Up
The following procedures should be followed for the start-up of DOWTM Ultra filtration
Modules. Manually start the equipment during initial operation. Flush the UF parts to remove
the preservative used in shipping or the storage solution before starting the equipment.
Target a filtrate flow of 60% of design during initial operations. After 24 hours the filtrate flow
Can be adjusted to design conditions.
Pre-start Checks
1. The UF pre-treatment system should operate properly and the UF feed water should meet
The design requirements. Ensure that chemical addition points are properly located and that
Proper mixing of chemicals in the feed streams can occur. Check the addition of pretreatment
Chemicals.
2. Verify that the drain/waste collection system is functional
3. Verify that the PLC program is loaded and functioning
4. Complete and electrical system check. Verify that the instrumentation is working and
calibration is completed. Calibrate gauges and meters based on manufacturers’
recommendations.
5. Clean and connect interconnecting piping. Flush system without modules to remove
fabrication debris. During the flushing operation, check all pipe connections and valves for
leaks. Tighten connections where necessary.
6. Residual air should be removed from the system during start-up.
Check that all valves are closed and pumps are off before starting the system. Start the
equipment by following the steps below:
1. Pumps should be aligned, lubricated, and properly rotated.
2. Start the feed pump
3. Fill equipment and start a flush
4. Start the backwash pump
5. Set and adjust the backwash pressure
6. Set and adjust the inlet air pressure
7. Set backwash time interval
8. Set air scour time interval
9. Set backwash sequence
Module Flushing
The DOW Ultra filtration modules should be rinsed prior to startup to remove preservative fluid
shipped in the modules. Flushing should be performed until no foam is observed in the wash
water. Depending on the treatment application, additional rinsing or disposal of the filtrate
may be required.
NSF / ANSI Standard 61 certified modules require the following conditioning rinse prior to
producing potable water:
1. Rinse the modules at a feed rate of 40 LMH minimum for a period of 4 Hours.
2. Achieve a minimum total rinse volume of 160 LMH-Hours using the feed water available.
3. The concentrate bleed rate should be set from between 0% to 20% with the balance being
filtrate.
4. During the rinse cycle, perform standard cleaning protocols as defined per the
manufacturer’s recommendations which are specifically designed to consider the feed water
quality available.
5. The filtrate should be sent to the appropriate disposal system based on the regulations that
apply to the location where the conditioning rinse is carried out and not used as potable
water.
6. Local regulations may require additional conditioning of the system prior to producing
potable water
3.2 INTEGRITY TESTING PROCEDURES
Two methods are commonly used for integrity testing.
BUBBLE TEST
Leaking modules can be found using a skid pressure hold test and a transparent bubble tube.
1. Take the module out of the filtration mode.
2. Drain the module from the feed side.
3. Close feed and concentrate valve and align filtrate valve to allow flow to drain through the
transparent tube. Also isolate the bank of modules being tested from other operating banks of
modules.
4. Pressurize the drained side of the module with oil-free compressed air from the air inlet
valve, and slowly raise the air pressure to a maximum of 2 bars (29 psi). Some displaced
water will flow out the filtrate side.
If large continuous air bubbles appear in the transparent tube then the module has broken
fibers. Smaller and infrequent bubbles are the result of air diffusion through the pores of the
ultra filtration membrane.
PRESSURE HOLD/DECAY
1. Take the UF unit or module out of the filtration mode. Drain the water from the feed side of
the module. Close the feed and concentrate valves and keep the filtrate valve open.
2. Pressurize the membrane module with oil free compressed air from the air inlet valve, and
slowly raise the air pressure to a maximum of 2 bars (29 psi). Some displaced water will flow
out through the filtrate side for up to two minutes.
3. Close the air inlet valve.
. Hold the pressure for 10 minutes. The membrane is integral (no leaks) if the pressure drop
is lower than 0.2 bar (2.9 psi). If the pressure drop is greater than 0.2 bar in 10 minutes (2.9
psi in 10 minutes) then membrane fibers are compromised and require repair.
5. Repair the membrane following the “fiber test and repair procedure”.
SHUT DOWN
MANUAL SHUT DOWN
To conduct a manual shut down open the concentrate rinse valve and flush for 15 seconds.
Then slowly close the inlet valve
EQUIPMENT SHUT DOWN DURING AUTOMATIC OPERATION
The equipment will automatically stop or will not allow automatic operation if the feed pump
did not start when operation was initiated or the inlet or filtrate pressure is too high to operate.
LONG TERM EQUIPMENT SHUT DOWN
If the equipment is down for more than two days, operation for 30 to 60 minutes per day can
protect the equipment from bacterial fouling. If the equipment is down for more than seven
days apply a manual air scrub before turning off the equipment, add a storage solution (1%
NaHSO3), and close all valves. During long term storage, pH should be checked monthly.
Replace the storage solution if the pH is less than3. During shut down, the UF membrane
should always keep moist. The membrane components will be irreversibly damaged after
drying.
OPERATING AND CLEANING LOGS
Recording data is useful for tracking operating conditions and to optimize operations. The
frequency of data collection will depend on the use of the filtrate water. Attached are two logs
for use during operations. One is the Data Log Sheet for use during normal filtration and
operations. The second is the CIP Record Sheet, which is used to collect information from
the clean in place step.