Cost Accounting Test Bank
Cost Accounting Test Bank
Only Statement 2 is true. Statement 2 Raw materials for one company are often
the finished product of another company. T
Question 3
Statement 1 The term "relevant range" as used in cost Both statements are false.
accounting means the range over which cost relationship
are valid. T Both statements are true.
Statement 2 Within the relevant range a change in
activity results in a change in variable cost per unit and Only Statement 1 is true
total fixed costs. F
Only Statement 1 is false.
Both statements are false.
Question 7
Only Statement 2 is true. Statement 1 Health and accident insurance is a semi-
variable cost. T
Both statements are true.
Statement 2 Salaries paid to department heads,
Only Statement 1 is true. inspectors, material handlers and factory maintenance
personnel are considered as indirect labor cost. T
Question 4
Statement 1 A factory overhead cost can either be a Both statements are true.
fixed cost or a variable cost. T
Statement 2 The balance of the Materials account Only Statement 2 is true.
represents the cost of all materials purchased and on
hand to be used in the manufacturing process including Both statements are false.
raw materials, pre-fabricated parts and other factory and
supplies. T Only Statement 1 is true.
Question 10 Question 15
Statement 1 Supplies needed for use in the factory are Direct costs are traced in the same way for actual
issued on the basis of job cost sheets. F costing and normal costing.
Statement 2 Expenses that are fixed at management's Group of answer choices
discretion at a certain level for the period are referred to
as committed fixed costs. F True
Question 11 False
Overapplied factory overhead would result if factory
overhead costs incurred were greater than Question 17
costs charged to production. In job order costing, when materials are returned to the
storekeeper that were previously issued to the factory for
True cleaning supplies, the journal entry should be made to:
DR. Materials: CR. Factory Overhead Control three months, the actual direct labor hours and the total
factory overhead allocated were as follows:
Question 18
When a manufacturing company has a highly automated October
plant producing many different products, probably the November December
most appropriate basis of applying factory overhead
costs to Work in Process is: Direct labor hours............... 2,500
3,000 5,000
units processed
Total factory overhead allocated............. P80,000
machine hours P75,000 P100,000
direct labor cost Based on this information, the estimated variable cost
per direct labor hour was:
direct labor hours
P8.00
Question 19
Under a job order cost system, the peso amount of the
entry to transfer the inventory from Finished Goods to
Cost of Goods Sold is the sum of the costs charged to all
jobs:
Question 20 July 1,
Zirel Company had the following account balances and balance..............................................................................
results from operations for the month of July: .............................................. P 12,000
of P2,250. What was the amount of direct materials close the estimated overhead account to actual
charged to Job 1040? overhead.
Question 25
Finished Goods is debited and Cost of Goods Sold is
credited for:
Question 26
Winkel Woodcrafters produces special-order wood
P4,250
products. The company uses job order costing for
Question 23
pricing and cost accumulation purposes. The following
Wailhi Co. estimated Department A's overhead at
costs were incurred on two recent jobs:
P255,000 for the period based on an estimated volume
of 100,000 direct labor hours. At the end of the period,
Cost Item Job Order #20
the factory overhead control account for Department A
Job Order #30
had a balance of P265,500; actual direct labor hours
were 105,000.
Direct materials:
What was the over- or under-applied overhead for the
period?
Issued.................................................. P6,500
P8,000
Returned.............................................. 500
0
Question 27
Winkel Woodcrafters produces special-order wood
products. The company uses job order costing
Direct materials:
P68,250
Issued.................................................. P6,500 Question 28
P8,000 The logical explanation for an entry that includes a debit
to Factory Overhead Control and a credit to Prepaid
Returned.............................................. 500 Insurance is that
0
insurance was paid on production equipment.
Indirect materials used............................. 500
400 the insurance company sent the company a refund of its
policy premium.
Direct labor............................................... P9,000
P15,000 overhead for insurance was applied to production.
Direct labor rate....................................... P9 per hour insurance for production equipment expired.
P10 per hour
Question 29
Overhead application rate........................ P10 per direct M Corp. manufactures a product and uses a job-order-
labor hour P15 per direct labor hour cost system. During May, the following
The company adds 50% markup on cost in determining costs were incurred in completing Job M1: direct
the amount to be charged for each job. materials, P13,700; direct labor, P4,800;
administrative, P1,400; and selling, P5,600.
an information databank
Overhead was applied at the rate of P25 per machine
hour, and Job M1 required 800 machine source documents
Question 33
Which of the following statements about normal costing
is TRUE?
Question: 34
Job-cost records of LV Company contained the following
data:
Total Cost
Date Date Date
of Job
P5.50
Job No. Started Finished Sold
at June 30
Question 30
220 May 18 June 12 June 20
A job order cost accumulation system is most suitable
P6,000
where:
221 May 20 June 19 June 21
homogeneous products are produced.
P4,000
222 June 7 July 5 July 12
continuous processing is performed.
P7,000
223 June 10 June 28 July 1
mass production techniques are used.
P6,500
224 June 19 July 16 July 25
customized products are produced.
P8,000
The Work in Process Inventory at June 30 is:
Question 31
The process of charging factory overhead to Work in
Process on the basis of a predetermined application rate
multiplied by actual input is known as:
P15,00
normal costing
Question 35
Job-cost records of LV Company contained the following
Question 32
data:
Managers and accountants collect most of the cost
information that goes into their systems through:
Direct material P5,000
Total Cost
Date Date Date Direct labor (100 hours @ $7.25) P725
of Job
Job No. Started Finished Sold Machine hours incurred 40
at June 30
220 May 18 June 12 June 20 Predetermined overhead rate per machine hour P26
P6,000
221 May 20 June 19 June 21 At the end of March, what total cost appears on the job
P4,000 order cost sheet for Job #656?
222 June 7 July 5 July 12
P7,000
223 June 10 June 28 July 1
P6,500
224 June 19 July 16 July 25
P8,000
Finished Goods Inventory @ June 30 is:
P6,500
Question 36
Job-cost records of LV Company contained the following
data:
Total Cost
Date Date Date
P6,765
of Job
Job No. Started Finished Sold
Question 38
at June 30
220 May 18 June 12 June 20
P6,000
221 May 20 June 19 June 21
P4,000
222 June 7 July 5 July 12
P7,000
223 June 10 June 28 July 1
P6,500
224 June 19 July 16 July 25
P8,000
Cost of Goods Sold for June is:
P10,000
Question 37
Larena Corp. manufactures products on a job-order
basis. The job cost sheet for Job #656 shows the
following for March:
Overapplied overhead P 6,000
P974,000
P3,203 Question 41
Work in process inventory on December 31 of the
Question 39 current year is P44,000. Work in process inventory
Overhead is applied to jobs at the rate of 40% of direct increased by 60% during the year. Cost of goods
labor cost. Direct material of P1,250 and direct labor of manufactured amounted to P275,000.
P1,400 was expended on Job #145 during June. On What are the total manufacturing costs incurred in the
May 31, the balance of Job #145 was P2,800. The current year?
balance on June 30 is:
P6,010
Question 40
At the end of the last fiscal year, Manico Co. had the
following account balances: P291,500
Question 42 The manager is preparing a flexible budget for next year
In a decision analysis situation, which of the following and requires a breakdown of the cost of steam used in
costs is not likely to contain a variable cost component? its factory into the fixed and variable elements. The
following data on the cost of steam used and direct labor
overhead hours worked are available for the last 6 months of this
year:
labor
Month Cost of Steam
selling Direct Labor Hours
Question 45
When all manufacturing costs used in production are
attached to the products, whether direct or indirect,
variable or fixed, this is called:
absorption costing
process costing
P4.00
variable costing Question 47
The following information for Downy Inc. are provided for
Question 46 2022:
Dept. 1 40,000
Beginning 26,000 58,000
Ending
Dept. 2 3,000
Finished Goods ………….. P 750,000 P 5,000 14,000
550,000
Dept. 3 -0-
Work in process………….. 1,100,000 -0- -0–
875,000
Direct labor hours:
For the year 2022, the cost of goods manufactured and
gross profit were P 10,000,000 and P1,500,000, Dept. 1 500
respectively. Sales for the year was: 400 300
Dept. 2 200
250 350
Dept. 3 1,500
1,800 2,500
Machine hours:
Dept. 1 -0-
P11,700,000 -0- -0–
Dept. 1 P 12.00
150% of direct material cost
Dept. 2 18.00 P
8.00 per machine hour
Dept. 3 15.00
200% of direct labor cost
Job 101
Job 102 Job 103
Direct Material:
P25.75
Question 50
Lexy Co. uses job order costing and it has 3 jobs in
process: Job #6, Job #7 and Job #8. The following
information is available from its records:
Raw materials used P120,000; direct labor per hour is
P8.50 and predetermined overhead rate is 120% based
on direct labor cost. Direct material was requisitioned as
follows for each job respectively: 30% for Job #6; 25%
for Job #7; 25% for Job #8; the balance for indirect
material requisition. Direct labor hours per job are 2,500
for Job #6; 3,100 for Job #7 and 4,200 for Job #8.
Indirect labor is P33,000. Other actual overhead costs
totaled P36,000. How much is the prime cost for Job
#6?
P215,200
Question 49
Total Units of Product Average Fixed Cost Average
Variable Cost Average Total Cost
6 P 15.00
P 25.00 P 40.00
7 12.86
24.00 36.86
8 11.25
23.50 34.75
P57,250
9 10.00
23.75 33.75