Hole Hon Nur

The document outlines the detailed cost estimation for various construction works by Karnataka Rural Infrastructure Development Limited in the Shivamogga sub-division, including steel work, roofing, painting, and concrete laying. It provides specifications, quantities, rates, and total amounts for each item, culminating in a grand total of 7,00,000.00 after accounting for additional charges and GST. The document is structured according to the PWD CSR 2023-24 guidelines.

Uploaded by

Kridl smg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views2 pages

Hole Hon Nur

The document outlines the detailed cost estimation for various construction works by Karnataka Rural Infrastructure Development Limited in the Shivamogga sub-division, including steel work, roofing, painting, and concrete laying. It provides specifications, quantities, rates, and total amounts for each item, culminating in a grand total of 7,00,000.00 after accounting for additional charges and GST. The document is structured according to the PWD CSR 2023-24 guidelines.

Uploaded by

Kridl smg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

KARNATAKA RURAL INFRASTRUCTURE DEVELOPMENT LIMITED.

SHIVAMOGGA SUB DIVISION


PÁªÀ ÄUÁjAiÀ Ä ºÉ ¸À gÀ Ä :-ಭ ವ ೖತ ಸಂಪಕ ೕಂದ ದ ೕ
ವ ಅಳವ ೕ ೕ ಅಳವ ಮ
( Based on PWD CSR 2023-24 Vol-I, II & III of Shimoga Circle )
Sl Item of Work Nos L B D Qty Rate Amount
1 Providing and fixing Steel work in built up tubular (round, square or rectangular
hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and
applying a priming coat of approved steel primer, including welding and bolted with
special shaped washers etc. complete. Hot finished seamless type tubes including
cost of materials, labour, usage charges of machinery complete as per specifications
and as per directions of the Engineer-in-Charge.( PWD SR 2023-24, pg-82,item
11.16.2 vol -2)
Area-1 1 15.80 12.15 191.97
Area-2 1 5.85 2.75 16.09
sqm 208.06
10Kg /Sqm 2080.58
Staircase from GF to FF 1 3.70 1.50 sqm 5.55
84Kg /Sqm 466.20
Basic rate 147.00
Add. A.W 5% 7.35
Total 154.35 sqm 2546.78 154.35 3,93,095.00
2 Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch
of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated
thickness with zinc coating 120 g/m2 as per IS: 277, in 240 mpa steel grade, 5-7
microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns.
Sheet should have protective guard film of 25 microns minimum to avoid scratches
during transportation and should be supplied in single length upto 12 m or as desired
by Engineer_x005f_x005f_x005f_x005f_x0002_in-charge. The sheet shall be fixed
using self drilling/self tapping screws of size (5.5x 55 mm) with EPDM seal,
complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost
of purlins, rafters and trusses and including cutting to size and shape wherever
required..( PWD SR 2023-24, pg-26 ,item 7.38vol -2)
Area-1 1.00 15.80 12.15 191.97
Area-2 1.00 5.85 2.75 16.09
Basic rate 568.00 ;
Add. A.W 5% 28.40
Total 596.40 sqm 208.06 596.40 1,24,085.00
3 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm
(+0.05 %) total coated thickness, Zinc coating 120 g/m2 as per IS: 277, in 240 mpa
steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top
coat 15-18 microns using self drilling/ self tapping screws complete : Gutter (600
mm over all girth) .( PWD SR 2023-24, pg-26 ,item 7.39.1vol -2)
Area-1 2 15.80 31.60
Basic rate 451.00
Add. A.W 5% 22.55
Total 473.55 Meter 31.60 473.55 14,964.00
4 Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two
coat applied @ 0.90L/10 m² over an under coat of primer applied @ 0.80 L/10 m² of
approved brand and manufacture including preparing the surface after thorougly
cleaning oil, grease, dirt and foreign matter, cost of materials, labour complete as per
specifications and as per directions of Engineer-in-charge.( PWD SR 2023-24, pg-47
,item 8.33.3 vol -2)
Area-1 1.00 15.80 12.15 191.97
Area-2 1.00 5.85 2.75 16.09
208.06
Staircase from GF to FF 5.55
Basic rate 139.00
Add. A.W 5% 6.95
Total 145.95 sqm 213.61 145.95 31,176.00
5 Providing and laying in position Cement Concrete for levelling course for all works
in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine
aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150
mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of
all materials of quality, labour, Usage charges of machinery, curing, and all the other
appurtenances required to complete the work as per technical specifications.( PWD
SR 2023-24, pg-15 ,item no 2.1.4 vol -1)
Column end concrete
Area-1 8.00 0.30 0.30 0.90 0.65
Area-2 4.00 0.30 0.30 0.90 0.32
Basic rate 6217.00
Add. A.W 5% 310.85
Total 6527.85 cum 0.97 6527.85 6,345.00
Sub Total 5,69,665.00
Third Party Charges 1.0% 5,696.65
Sub Total - 1 5,75,361.65
KRIDL Charges 3% 17,260.85
Sub Total- 2 5,92,622.50
Add GST Charges 18% 1,06,672.00
Sub Total- 3 6,99,294.50
Rounding off 705.50
GRAND TOTAL 7,00,000.00

AE/JE Assistant Executive Engineer


KRID Ltd. Shivamogga KRID. Ltd. Shivamogga