Project Name:
SAUDI PIF3 SAAD2 SOLAR POWER
PROJECT
RFI/WIR Ref. No. SAAD2-RFI--PVB-2-73-FQC-TW-001-00
REQUEST FOR INSPECTION/ WORK INSPECTION REQUEST
MoS Ref. No. SAAD2-PVB-FQE-MS-LVDC-001-03
(RFI/WIR) ITP/FQP Ref. No. SAAD2-PVB-FQE-FQP-LVDC-001
Discipline: Civil Mechanical Electrical I&C Machinery
ICL Ref. No. SAAD2-GEN-FQC-ICL-CTW-001-00
Welding Piping Other (pls specify)
SECTION – 1: DETAILS OF INSPECTION
Inspection Level as per ITP ITP Item/ Sr. No. Subcontractor Contractor TPI/TPL PC /Owner
2.2 H H W W
Location/Area: PV Plant Zone: Block:
Block: 73 -West Equipment: Structure:
Element: Drawing Nos:
Inspection Type: Construction Materials Material Approval:
PC/OE Inspection Date:20/08/2024 Time: RFI Submission Date: 19/08/2024 Time:
Supporting Documents attachment
ICL DWGs Survey Rept. MTC’s/ Test Rept. Packing list Shipping doc. Delivery Rept. Photos Other pls Specify
Description of Inspection: LV Trenching Works W
ASSOCIATED EPC DISCIPLINES INSPECTION & APPROVAL:
Discipline Comments
Survey
Civil & Architecture
Steel Structure
Mechanical
Electrical
Others (Specify)
Others (Govt. or local
Subcontractor QC EPC Construction EPC QC
auth.)
Name
Signature
Date
SECTION-2- RFI ACKNOWLEMENT FROM PC/ OWNER:
Acknowledged Return with
comments
Supporting Document/Objective evidence
Comments:
SECTION – 3: OWNER ENGINEER INSPECTION COMMENTS
Supporting Document/Objective evidence
Approved Approved with comments
Rejected
Form no. ACWA-PEOS-QAF-0002 REV.0 Date: February 20, 2024
Project Name:
SAUDI PIF3 SAAD2 SOLAR POWER
PROJECT
OWNER/PC ENGINEER SIGNATURE: DATE: TIME:
Form no. ACWA-PEOS-QAF-0002 REV.0 Date: February 20, 2024