Scope of Works
The Project Works include the construction of three blocks of apartments, each with 8 levels of residential units
as well as a health club and other amenities.
Site preparation
Excavation to reduced levels
Excavation for foundations
Mass and reinforced concrete works
Steel fixing
Form work
Walling
Plastering
Electrical & Mechanical Installation
Roof drainage
Finishing works and;
External works.
2
Clerk of Works Weekly Report
Project Photo Showing Construction Progress of Block A, 67.26%, Block B, 65.81% & Block C, 62.77%
3
Clerk of Works Weekly Report
3.0 Construction activities undertaken during the week
Progress of Work as per the Main Contractor’s critical path Program
Finish Work
Activity Description Start Date Remarks
Date Done (%)
BLOCK A
Floor screeding 8th floor 24/10/2022 29/10/2022 90
Pressure testing (Gravity pressure test) 27/10/2022 31/10/2022 80
Plaster snags and openings
BLOCK B
External plaster (beam and copping finishes
Internal wall plaster on 2nd floor 3/10/2022 6/11/2022 75
Electrical conducting on 1st floor
BLOCK C
Internal wall plaster on 8th floor 26/10/2022 5/10/2022 25
Plumbing( piping for water supply and drainage)
EXTERNAL WORKS
Steel reinforcement and Formwork for RCC retaining
wall
Concrete casting for external stair case
Steel reinforcements, formwork and Casting of concrete
beam for the retaining wall
Excavation, blinding, steel reinforcement fixing and
24/10/2022 24/11/2022 10
concrete casting for retaining wall foundation
4
Clerk of Works Weekly Report
4.0 Contractor’s Work Force on Site, Weather Report and Materials Delivered
Trades (Workers of the Main Contractor
and Subcontractors)
Weekly attendances of workers at Lubowa site for the date of Monday 22nd –Saturday 27th August 2022
Trade Monda Tuesday Wednesday Thursday Friday Saturday
y
Supervisors 03 03 03 03 03 03
Site engineer 01 01 01 01 01 01
Site QS 01 01 01 01 01 01
Foremen 04 04 04 04 04 04
Safety officer 01 01 01 01 01 01
carpenters 02 02 02 02 02 02
Steel fixers 04 04 04 04 04 04
Block work Team/Plaster/Con (masons) 17 17 17 17 17 17
Electricians 09 09 09 09 09 09
Plumbers & AC 22 22 22 22 22 22
Site nurse 01 01 01 01 01 01
Mechanic 02 02 02 02 02 02
Driver 01 01 01 01 01 01
Operator 04 04 04 04 04 04
Store keepers 03 03 03 03 03 03
Askari 05 05 05 05 05 05
Unskilled laborers 85 85 85 85 85 85
Total 176 176 176 176 176 176
Weather Report
5
Clerk of Works Weekly Report
Drawings/ Information Received On-Site
item Description Date
Client proposed change of drainage soil and waste pipes in the lower ground floor from 4”
1
to 6’’ due to increased volume of waste.
Additional waste and soil pipes to be introduced for ground floor so that upper floors and
2
ground floor have separate lines
Information Required
Item Description Date
1 Plumbing details for the swimming pool
2 Details for generator and transformer bases
3 Details for covering the exposed drainage pipes on external walls