Lecture 2
Lecture 2
Hydrology
First requirement – Q (discharge)
Hydrology deals with occurrence and distribution of water over and under earth’s
surface.
Surface Water Hydrology
Ground Water Hydrology
Watershed, catchment area or drainage area: length of the river, size and shape of the
area it affects, tributaries, lakes, reservoirs etc.
Investigation of run-off for past few years is required for power potential studies of a
HPP.
Objectives of Hydrology
To obtain data regarding the stream flow of water that would be available,
To predict the yearly possible flow
To calculate the mean annual rainfall in the area under consideration from a record of the
annual rainfall for a number of years, say 25 to 30
To note the frequency of dry years
To find maximum rainfall and flood frequency
Various terms related to Hydrology
Rainfall is also known as precipitation and can be measured by rain gauges.
Some part of precipitation is lost due to evaporation, interception and transpiration.
Transpiration: Plants absorbing moisture and giving it off to the atmosphere
Stream flow = precipitation – losses
Stream flow = surface flow + percolation to ground
Surface flow is also known as run-off.
Hydrograph:
shows the variation of stream flow in m3 / s with time for a particular river site.
The time may be hour, week, month or a year.
The area under hydrograph gives the total volume of flow
Flow duration curve:
shows the percentage of time during the period when the flow was equal to
greater than the given flow.
The area under FDC gives the total quantity of run-off during a period
Mass curve
indicates the total volume of run-off in cubic meters up to a certain time.
the slope of the curve at any point shows the rate of flow at that time
Used for estimating the capacity of storage reservoir
Storage:
to ensure water availability during deficient flow and thus increasing the firm
capacity
Storage also results in more energy production
Pondage:
Storing water in small ponds near the power plant as the storage reservoir is
away from plant
To meet the power demand fluctuations over a short period of time e.g. 24 hours
Primary Power: power that will be available 90 % of the time
Secondary Power: power that will be available 75 % of the time
Dump Power: power that will be available 50 % of the time.
Maximum flow estimation: gives estimation of floods and helps in design of dam and
spillway.
Types of Dams
Components of a HPP
Figure 5: Forebay
Conduits
Headrace is a channel which lead the water to the turbine
Tailrace is a channel which carries water from the turbine
A canal is an open waterway excavated in natural ground following its contour.
A flume is an open channel erected on a surface above ground.
A tunnel is a closed channel excavated through an obstruction.
A pipeline is a closed conduit supported on the ground.
Penstocks are closed conduits for supplying water “under pressure” from head pond
to the turbines.
Tailrace:
A tailrace is required to discharge the water leaving the turbine into the river.
The design of the tail race should be such that water has a free exit.
Figure 12: Tail race
Power House
Hydraulic turbines
Electric generators
Governors
Gate valves
Relief valves
Water circulation pumps
Air ducts
Switch board and instruments
Storage batteries
Cranes
Switchyard
Step up transformers
Instrument transformers
Transmission lines
Comparison of Turbines
Table 3: Comparison of Turbines
Figure 14: Kaplan Turbine
Figure 15: Kaplan Turbine