Exp16 estimation .pdfnew

The document provides detailed measurements and quantities for construction activities including excavation, PCC, brick work, DPC, and various finishing works for long and short walls. It includes calculations for materials required, deductions for doors and windows, and totals for each category. The overall totals for various construction components are also summarized, indicating the scope of the project.

Uploaded by

hridyas303
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views2 pages

Exp16 estimation .pdfnew

The document provides detailed measurements and quantities for construction activities including excavation, PCC, brick work, DPC, and various finishing works for long and short walls. It includes calculations for materials required, deductions for doors and windows, and totals for each category. The overall totals for various construction components are also summarized, indicating the scope of the project.

Uploaded by

hridyas303
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CENTER LINE LENGTH OF LONG WALL 16.

4
CENTER LINE LENGTH OF SHORT WALL 7.2

SL NO DESCRIPTION NO LENGTH BREADTH HEIGHT QUANTITY UNIT REMARKS

1 Excavation

Long wall 2 17.3 0.9 0.8 24.912 16.4+0.9=17.3

Short wall 3 6.3 0.9 0.8 13.608 7.2-0.9=6.3


Total 38.52 Cum

2 PCC 1:4:8

Long wall 2 17.3 0.9 0.2 6.228 16.4+0.9=17.3


Short wall 3 6.3 0.9 0.2 3.402 7.2-0.9=6.3

Total 9.63 Cum

Brick work in Foundation


3
& Plinth

F1(Long wall) 2 17 0.6 0.6 12.24 16.4+0.6=17

F1(Short wall) 3 6.6 0.6 0.6 7.128 7.2-0.6=6.6

Plinth (Long wall ) 2 16.85 0.45 0.45 6.82425 16.4+0.45=16.85

Plinth (short wall ) 3 6.75 0.45 0.45 4.100625 7.2-0.45=6.75

Total 30.292875 Cum


4 DPC

Long wall 2 16.85 0.45 - 15.165 16.4+0.45=16.85


Short wall 3 6.75 0.45 - 9.1125 7.2-0.45=6.75
Total 24.2775 Sqm

Deduct

Door 2 0.9 0.45 - 0.81


Total Deduction 23.4675 Sqm 24.2775-0.81=23.4675
Brick work in Super
5
Structure
Long wall 2 16.6 0.2 3 19.92 16.4+0.2=16.6
Short wall 3 7 0.2 3 12.6 7.2-0.2=7
Total 32.52 Cum

Deduction

Door 2 0.9 0.2 2 0.72

Window 2 1.4 0.2 1.5 0.84


Lintel

Long wall 2 16.6 0.2 0.15 0.996 16.4+0.2=16.6

Short wall 3 7 0.2 0.15 0.63 7.2-0.2=7


Total 3.186 Cum
Total Deduction 29.334 Cum 32.52-3.186=29.334

6 RCC Work

Lintel

Long wall 2 16.6 0.2 0.15 0.996 16.4+0.2=16.6

Short wall 3 7 0.2 0.15 0.63 7.2-0.2=7

Total 1.626 Cum

7 Sunshade

Long Wall 2 17.8 0.6 0.075 1.602 8+8+0.2+0.2+0.2+0.6+0.6=17.8


Short wall 2 7.4 0.6 0.075 0.666 7+0.2+0.2=7.4

Total 2.268 Cum

8 Roof 1 17.2 8 0.12 16.512 Cum 0.3+0.2+8+0.2+8+0.2+0.3=17.2

Total 20.406 Cum 1.626+2.268+16.512=20.406

9 Earth Filling 2 7.75 6.75 0.35 36.61875 Cum 8-0.125-0.125=7.75

10 PCC 1:3:6 In Floor 2 7.75 6.75 0.1 10.463 Cum 7-0.125-0.125=6.75

Wood Work in Frames of


11
Doors & Windows

Door 2 5.8 0.1 0.075 0.087 0.9+0.9+2+2=5.8

Window 2 8.8 0.1 0.075 0.132 (1.5*4)+(1.4*2)=8.8

Total 0.219 Cum

Wood work in Shutter of


12
Doors & Windows

Door 2 0.9 2 3.6

Window 2 1.4 1.5 4.2


Total 7.8 Sqm

13 Plastering 12mm Thick

Inside 2 30 3 180 (8+8+7+7)=30

Outside 1 48 3 144 16.6+7.4+16.6+7.4=48

Total 324 Sqm

14 Plastering 6mm Thick 2 8 7 112 Sqm

15 White Washing

Inside 2 30 3 180 (8+8+7+7)=30

Outside 1 48 3 144 16.6+7.4+16.6+7.4=48

Top 2 8 7 112

Total 436 Sqm

16 Floor Tile 2 8 7 112 Sqm

17 Painting

Inside 2 30 3 180 (8+8+7+7)=30

Outside 1 48 3 144 16.6+7.4+16.6+7.4=48

Top 2 8 7 112

Total 436 Sqm