Steam Turbine System

The document outlines the approval status of various drawings and documents related to the Sulut-1 CFSPP project, with contractor number T1-T-IKJ-LNJ-0881-M dated August 23, 2021. It includes a detailed list of P&ID (Piping and Instrumentation Diagram) documents, their revisions, and statuses, indicating that all listed documents are approved. Additionally, it emphasizes the contractor's responsibility to coordinate with PLN in case of any discrepancies or overlapping meanings in the project documentation.

Uploaded by

Dangol
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
172 views14 pages

Steam Turbine System

The document outlines the approval status of various drawings and documents related to the Sulut-1 CFSPP project, with contractor number T1-T-IKJ-LNJ-0881-M dated August 23, 2021. It includes a detailed list of P&ID (Piping and Instrumentation Diagram) documents, their revisions, and statuses, indicating that all listed documents are approved. Additionally, it emphasizes the contractor's responsibility to coordinate with PLN in case of any discrepancies or overlapping meanings in the project documentation.

Uploaded by

Dangol
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

Contractor No : T1-T-IKJ-LNJ-0881-M Dated : August 23, 2021 Received date : August 23, 2021

PLN Enjiniring No : 03.002/E02/PLNE/IX/2021 Dated : September 3, 2021

CCR OUT DATE


REVIEW FOR APPROVAL DRAWINGS / DOCUMENTS 001442 03/09/2021
DRAWING / DOCUMENT NUMBER DRAWING / DOCUMENT TITLE
PLN REV. CONTRACTOR REV. STATUS
10163B-00-M-52-YYG-0001-00- 7 T1-IK-000-PRS-PID-00001 7 A P&ID Legend, General Notes And Symbols (1 of 3)

10163B-00-M-52-HA-0002-00- 7 T1-IK-110-PRS-PID-00001 7 A P&ID Limestone Handling System

10163B-00-M-52-LB-0001-00- 7 T1-IK-110-PRS-PID-00003 7 A P&ID Ammonia Storage and Supply System (for SNCR)

10163B-00-M-52-HN-0001-00- 7 T1-IK-110-PRS-PID-00004 7 A P&ID Electrostatic Precipitator

10163B-00-M-52-HNE-0004-00- 7 T1-IK-110-PRS-PID-00005 7 A P&ID Stack System

10163B-00-M-52-LBA-0001-00- 7 T1-IK-210-PRS-PID-10001 7 A P&ID Unit 1 - Main Steam And Bypass System

10163B-00-M-52-LBG-0001-00- 7 T1-IK-210-PRS-PID-10002 7 A P&ID Auxiliary Steam System

10163B-00-M-52-STG-0001-00- 7 T1-IK-210-PRS-PID-10003 7 A P&ID Unit 1 - Lube Oil System

10163B-00-M-52-MA-0006-00- 7 T1-IK-210-PRS-PID-10004 7 A P&ID Unit 1 - Steam Turbine System

Note: The mechanical aspect comment from PLN technically applied


Reviewed by : Checked by :
for both project between Sulut and Timor, if there is any
discrepancy/same/overlapping meaning, contractor shall responsible
active to coordinate with PLN. PT. PLN Enjiniring
1/6 SULUT-1 CFSPP (2X50 MW)
Contractor No : T1-T-IKJ-LNJ-0881-M Dated : August 23, 2021 Received date : August 23, 2021
PLN Enjiniring No : 03.002/E02/PLNE/IX/2021 Dated : September 3, 2021

10163B-00-M-52-MAG-0002-00- 7 T1-IK-210-PRS-PID-10005 7 A P&ID Unit 1 - Gland Condenser System

10163B-00-M-52-LCA-0001-00- 7 T1-IK-220-PRS-PID-10001-01 7 A P&ID Unit 1 - Turbine Condenser System

10163B-00-M-52-LGA-0001-00- 7 T1-IK-220-PRS-PID-10001-02 7 A P&ID Unit 1 - Condensate Extraction Pump System

P&ID Unit 1 - Condensate Holding Storage Tank


10163B-00-M-52-LCP-0001-00- 7 T1-IK-220-PRS-PID-10001-03 7 A System

10163B-00-M-52-LCJ-0001-00- 7 T1-IK-220-PRS-PID-10002-01 7 A P&ID Unit 1 - LP Heater 1

10163B-00-M-52-LCJ-0003-00- 7 T1-IK-220-PRS-PID-10002-02 7 A P&ID Unit 1 - LP Heater 2

10163B-00-M-52-LAA-0001-00- 7 T1-IK-220-PRS-PID-10003-01 7 A &ID Unit 1 - Deaerator System

10163B-00-M-52-LCH-0001-00- 7 T1-IK-220-PRS-PID-10004-01 7 A P&ID Unit 1 - HP Heater 1

10163B-00-M-52-LCH-0003-00- 7 T1-IK-220-PRS-PID-10004-02 7 A P&ID Unit 1 - HP Heater 2

10163B-00-M-52-MAJ-0003-00- 7 T1-IK-220-PRS-PID-10005 7 A P&ID Unit 1 - Condenser Vacuum System

10163B-00-M-52-LCM-0001-00- 7 T1-IK-220-PRS-PID-10006-01 7 A P&ID Unit 1 - HP Drain Flash System

10163B-00-M-52-LCM-0002-00- 7 T1-IK-220-PRS-PID-10006-02 7 A P&ID Unit 1 - LP Drain Flash System

Note: The mechanical aspect comment from PLN technically applied


Reviewed by : Checked by :
for both project between Sulut and Timor, if there is any
discrepancy/same/overlapping meaning, contractor shall responsible
active to coordinate with PLN. PT. PLN Enjiniring
2/6 SULUT-1 CFSPP (2X50 MW)
Contractor No : T1-T-IKJ-LNJ-0881-M Dated : August 23, 2021 Received date : August 23, 2021
PLN Enjiniring No : 03.002/E02/PLNE/IX/2021 Dated : September 3, 2021

10163B-00-M-52-PG-0001-00- 7 T1-IK-220-PRS-PID-10007 7 A P&ID Cooling Water Pump System

10163B-00-M-52-PGA-0001-00- 7 T1-IK-220-PRS-PID-10008-01 7 A P&ID Unit 1 - Closed Cooling Water System

10163B-00-M-52-PGA-0001-00- 7 T1-IK-220-PRS-PID-10008-02 7 A P&ID Unit 1 - Closed Cooling Water Distribution

10163B-00-M-52-PBQ-0001-00- 7 T1-IK-220-PRS-PID-10009 7 A P&ID Electro-Chlorination System

10163B-00-M-52-PG-0006-00- 7 T1-IK-220-PRS-PID-10010 7 A P&ID Auxiliary Cooling Water Pump System

10163B-00-M-52-PAB-0001-00- 7 T1-IK-220-PRS-PID-10011 7 A P&ID Sea Water Return System

P&ID Unit 1 - Condenser Water Side Evacuation


10163B-00-M-52-MAJ-0003-00- 7 T1-IK-220-PRS-PID-10012 7 A System

10163B-00-M-52-LBA-0002-00- 7 T1-IK-230-PRS-PID-20001 7 A P&ID Unit 2 - Main Steam And Bypass System

10163B-00-M-52-STG-0002-00- 7 T1-IK-230-PRS-PID-20003 7 A P&ID Unit 2 - Lube Oil System

10163B-00-M-52-MAV-0007-00- 7 T1-IK-230-PRS-PID-20004 7 A P&ID Unit 2 - Steam Turbine System

10163B-00-M-52-LW-0001-00-1 7 T1-IK-230-PRS-PID-20005 7 A P&ID Unit 2 - Gland Condenser System

10163B-00-M-52-LCA-0002-00- 7 T1-IK-240-PRS-PID-20001-01 7 A P&ID Unit 2 - Turbine Condenser System

Note: The mechanical aspect comment from PLN technically applied


Reviewed by : Checked by :
for both project between Sulut and Timor, if there is any
discrepancy/same/overlapping meaning, contractor shall responsible
active to coordinate with PLN. PT. PLN Enjiniring
3/6 SULUT-1 CFSPP (2X50 MW)
Contractor No : T1-T-IKJ-LNJ-0881-M Dated : August 23, 2021 Received date : August 23, 2021
PLN Enjiniring No : 03.002/E02/PLNE/IX/2021 Dated : September 3, 2021

10163B-00-M-52-LCA-0001-00- 7 T1-IK-240-PRS-PID-20001-02 7 A P&ID Unit 2 - Condensate Extraction Pump System

P&ID Unit 2 - Condensate Holding Storage Tank


10163B-00-M-52-LCP-0002-00- 7 T1-IK-240-PRS-PID-20001-03 7 A System

10163B-00-M-52-LCJ-0002-00- 7 T1-IK-240-PRS-PID-20002-01 7 A P&ID Unit 2 - LP Heater 1

10163B-00-M-52-LCJ-0004-00- 7 T1-IK-240-PRS-PID-20002-02 7 A P&ID Unit 2 - LP Heater 2

10163B-00-M-52-LAA-0002-00- 7 T1-IK-240-PRS-PID-20003-01 7 A P&ID Unit 2 - Deaerator System

10163B-00-M-52-LCH-0001-00- 7 T1-IK-240-PRS-PID-20004-01 7 A P&ID Unit 2 - HP Heater 1

10163B-00-M-52-LCH-0002-00- 7 T1-IK-240-PRS-PID-20004-02 7 A P&ID Unit 2 - HP Heater 2

10163B-00-M-52-MAJ-0002-00- 7 T1-IK-240-PRS-PID-20005 7 A P&ID Unit 2 - Condenser Vacuum System

10163B-00-M-52-LCM-0002-00- 7 T1-IK-240-PRS-PID-20006-01 7 A P&ID Unit 2 - HP Drain Flash System

10163B-00-M-52-LCM-0002-00- 7 T1-IK-240-PRS-PID-20006-02 7 A P&ID Unit 2 - LP Drain Flash System

10163B-00-M-52-PGA-0002-00- 7 T1-IK-240-PRS-PID-20002-01 7 A P&ID Unit 2 - Closed Cooling Water System

10163B-00-M-52-PGA-0001-00- 7 T1-IK-240-PRS-PID-20008-02 7 A P&ID Unit 2 - Closed Cooling Water Distribution

Note: The mechanical aspect comment from PLN technically applied


Reviewed by : Checked by :
for both project between Sulut and Timor, if there is any
discrepancy/same/overlapping meaning, contractor shall responsible
active to coordinate with PLN. PT. PLN Enjiniring
4/6 SULUT-1 CFSPP (2X50 MW)
Contractor No : T1-T-IKJ-LNJ-0881-M Dated : August 23, 2021 Received date : August 23, 2021
PLN Enjiniring No : 03.002/E02/PLNE/IX/2021 Dated : September 3, 2021

P&ID Unit 2 - Condenser Water Side Evacuation


10163B-00-M-52-MAJ-0004-00- 7 T1-IK-240-PRS-PID-20012 7 A System

10163B-00-M-52-GAC-0001-00- 7 T1-IK-310-PRS-PID-00001 7 A P&ID Service Water Distribution

10163B-00-M-52-G-0001-00- 7 T1-IK-310-PRS-PID-00002 7 A P&ID Demin Water Distribution

10163B-00-M-52-QEB-0001-00- 7 T1-IK-340-PRS-PID-00001-01 7 A P&ID Instrument Air System

10163B-00-M-52-QEB-0002-00- 7 T1-IK-340-PRS-PID-00001-02 7 A P&ID Instrument Air Distribution

10163B-00-M-52-QFA-0001-00- 7 T1-IK-340-PRS-PID-00002 7 A P&ID Service Air Distribution

10163B-00-M-52-RZ-0001-00- 7 T1-IK-340-PRS-PID-00004 7 A P&ID Nitrogen Rack And Distribution

10163B-00-M-52-QC-0001-00- 7 T1-IK-350-PRS-PID-10001 7 A P&ID Chemical Injection System (1 of 2)

10163B-00-M-52-QC-0003-00- 7 T1-IK-350-PRS-PID-10002 7 A P&ID Chemical Injection System (2 of 2)

10163B-00-M-52-QU-0001-00- 7 T1-IK-360-PRS-PID-10001 7 A P&ID Unit 1 - Sampling Rack System

10163B-00-M-52-QU-0002-00- 7 T1-IK-360-PRS-PID-20001 7 A P&ID Unit 2 - Sampling Rack System

10163B-00-M-52-HJ-0002-00- 7 T1-IK-410-PRS-PID-00001 7 A P&ID Fuel Oil Unloading System

Note: The mechanical aspect comment from PLN technically applied


Reviewed by : Checked by :
for both project between Sulut and Timor, if there is any
discrepancy/same/overlapping meaning, contractor shall responsible
active to coordinate with PLN. PT. PLN Enjiniring
5/6 SULUT-1 CFSPP (2X50 MW)
Contractor No : T1-T-IKJ-LNJ-0881-M Dated : August 23, 2021 Received date : August 23, 2021
PLN Enjiniring No : 03.002/E02/PLNE/IX/2021 Dated : September 3, 2021

10163B-00-M-52-EGA-0001-00- 7 T1-IK-410-PRS-PID-00002 7 A P&ID Fuel Oil Storage and Supply System

10163B-00-M-52-EBA-0001-00- 7 T1-IK-420-PRS-PID-00001 7 A P&ID Coal Handling System (1 of 3)

10163B-00-M-52-EBA-0002-00- 7 T1-IK-420-PRS-PID-00002 7 A P&ID Coal Handling System (2 of 3)

10163B-00-M-52-ETG-0001-00- 7 T1-IK-510-PRS-PID-10002 7 A P&ID Unit 1 - Fly Ash Handling System

10163B-00-M-52-ETG-0002-00- 7 T1-IK-510-PRS-PID-20002 7 A P&ID Unit 2 - Fly Ash Handling System

Comm’t Comm’t
PLN’S COMMENTS CONTRACTOR’S RESPONSE
No. No.
APPROVED
1. APPROVAL DOES NOT RELIEVE CONTRACTOR FROM RESPONSIBILITY FOR ERRORS OR
DEVIATIONS FROM CONTRACT REQUIREMENTS

Note: The mechanical aspect comment from PLN technically applied


Reviewed by : Checked by :
for both project between Sulut and Timor, if there is any
discrepancy/same/overlapping meaning, contractor shall responsible
active to coordinate with PLN. PT. PLN Enjiniring
6/6 SULUT-1 CFSPP (2X50 MW)
Contractor No : Dated : Received date :
PLN Pusenlis No : Dated :
JELAS
CCR OUT DATE
REVIEW FOR APPROVAL DRAWINGS / DOCUMENTS
DRAWING / DOCUMENT NUMBER
DRAWING / DOCUMENT TITLE
PLN REV. CONTRACTOR REV. STATUS
P&ID UNIT-1 STEAM TURBINE SYSTEM
10163B-00-M-52-MA-0006-00- 4 T1-IK-210-PRS-PID-10004 4

Comm’t Comm’t
CONTRACTOR’S CHANGING CONTRACTOR’S RESPONSE
No. No.
1. (G,6) Updated and consistent with the latest interface list
Change size and pipe class material of line 11MAW40-BR301 from DN25-AB1 to DN40-BA2 data from SIEMENS.

2. (E6, F6) Updated and consistent with the latest interface list
Add 1 nozzle connection from turbine (SI1-202) and 1 line connection (SI1-227) 11MAW40- data from SIEMENS.
BR302-25-BA2-H.

Note: The mechanical aspect comment from PLN technically can be


Reviewed by : Checked by :
applied for both project between Sulut and Timor, if there is any
discrepancy/overlapping meaning contractor shall responsible active
to coordinate with PLN. 1/2 PT PLN (Persero) Pusat Enjiniring Ketenagalistrikan
TIMOR-1 CFSPP (2X50 MW)
Contractor No : Dated : Received date :
PLN Pusenlis No : Dated :
3. (F7, B4, B5) Engineering development aims for easier operation
Add tag balloon to indicate remote from DCS for and start-up purpose
-MOV-11LBA10AA102105
-MSV-11LBA10AA103
-MOV-11MAW10AA101

4. (E7-A7) In normal condition, supplying steam to gland


Add line to DEA for GSC Hot Standby scenario with additional RO to reduce pressure to match the steam is not required since turbine is self-sealing.
operating pressure at destination. Hence the steam inside the pipe to GSC is stagnant,
during this stagnancy the steam may condense and
leading to reduce the superheated temperature. In
order to keep the superheated temperature of the
steam in GSC line therefore the steam shall be flow
to prevent stagnancy. So additional line completed
with RO is added to avoid stagnancy.

5. (E5) Updated as pes latest interface list data from


Revised tapping and line size for line 11LBS10-BR003. SIEMENS.

Note: The mechanical aspect comment from PLN technically can be


Reviewed by : Checked by :
applied for both project between Sulut and Timor, if there is any
discrepancy/overlapping meaning contractor shall responsible active
to coordinate with PLN. 2/2 PT PLN (Persero) Pusat Enjiniring Ketenagalistrikan
TIMOR-1 CFSPP (2X50 MW)
Contractor No : Dated : Received date :
PLN Pusenlis No : Dated :

6. (B3, B2, B1, G1, F1 dan H1) Line class and size to be changed to fulfill the
Update Line class and size as per drafted bellow operating condition stated in the latest interface list
from Siemens.

Note: The mechanical aspect comment from PLN technically can be


Reviewed by : Checked by :
applied for both project between Sulut and Timor, if there is any
discrepancy/overlapping meaning contractor shall responsible active
to coordinate with PLN. 3/2 PT PLN (Persero) Pusat Enjiniring Ketenagalistrikan
TIMOR-1 CFSPP (2X50 MW)
Contractor No : Dated : Received date :
PLN Pusenlis No : Dated :
7. (B5) Incorporating requirement from RO vendor.
Add reducer DN200 x DN150 between RO-11LBA10-BP001 and MOV-11LBA10-AA102 and add
another reducer at RO downstream

8. (B4) Drain already covered by steam trap


Delete Drain Vlave AA801 & AA802 at line 11LBA10-BR001-250-FA1-H 11LBA10AB0004. This steam trap is located at
lowest point.

Moreover drain through steam trap is more save


because it will flows to LP drain flash tank.

Note: The mechanical aspect comment from PLN technically can be


Reviewed by : Checked by :
applied for both project between Sulut and Timor, if there is any
discrepancy/overlapping meaning contractor shall responsible active
to coordinate with PLN. 4/2 PT PLN (Persero) Pusat Enjiniring Ketenagalistrikan
TIMOR-1 CFSPP (2X50 MW)
Contractor No : Dated : Received date :
PLN Pusenlis No : Dated :
9. (C5) Engineering Development for piping information.
Add Line No at upstream MOV-11LBA10AA102 (11LBA10BR007-100-FA1-H)

10. (B5) Engineering Development for piping information.


Add two phase indication at line 11LBA10-BR006 and change insulation indication from “H” to “P”
Since the steam / condensate outlet MOV is routed
(drained) to LP Drain (atmospheric condition)
hence no need for heat preservation.

Note: The mechanical aspect comment from PLN technically can be


Reviewed by : Checked by :
applied for both project between Sulut and Timor, if there is any
discrepancy/overlapping meaning contractor shall responsible active
to coordinate with PLN. 5/2 PT PLN (Persero) Pusat Enjiniring Ketenagalistrikan
TIMOR-1 CFSPP (2X50 MW)
Contractor No : Dated : Received date :
PLN Pusenlis No : Dated :
11. (C4) Change tapping according to PIPING updated
Change tapping for 11LBA10-BR307-25-FA2-H and 11LBA10-BR007-100-AB2-H routing.

(G5, H5, G4, H4, G3, H3, G2, H2,) Updated based on as explained on PROCESS
Add Interlock detail as per drafted bellow DESCRIPTION AND OPERATING
PHILOSOPHY document no T1-IK-000-PRS-STU-
00001

Note: The mechanical aspect comment from PLN technically can be


Reviewed by : Checked by :
applied for both project between Sulut and Timor, if there is any
discrepancy/overlapping meaning contractor shall responsible active
to coordinate with PLN. 6/2 PT PLN (Persero) Pusat Enjiniring Ketenagalistrikan
TIMOR-1 CFSPP (2X50 MW)
Contractor No : Dated : Received date :
PLN Pusenlis No : Dated :
(B4, B5, B6) Change due to duplication tag no transmitter with
Change tag as per listed bellow SHI scope
PT-11/12LBA10CP202 ----> PT-11/12LBA10CP205
TT-11/12LBA10CT202 ----> TT-11/12LBA10CT204
MOV-11/12LBA10AA102 ----> MOV-11/12LBA10AA105

(D5) Updated for clearer line identification


Add line number for connection from SI1-197

Note: The mechanical aspect comment from PLN technically can be


Reviewed by : Checked by :
applied for both project between Sulut and Timor, if there is any
discrepancy/overlapping meaning contractor shall responsible active
to coordinate with PLN. 7/2 PT PLN (Persero) Pusat Enjiniring Ketenagalistrikan
TIMOR-1 CFSPP (2X50 MW)