Robert Holmes Pre cons & site work
Sean G. Footings and Slab
Cesar Ibarra Masonry Walls; Steel Columns
Duval Hawkins MEP, Roof
Christian Ivey Interior finishes, Closeouts
WBS CODE (Level WBS CODE (Level
S.No. Group/Participant # WBS ID WBS CODE (Level 2) Activity Name Activity Desciption
1) 3)
1 Group 4 1000000 Bank Project
2 Purchase Order Recieved
3 4 / Robert Holmes 101000 Preconstruction
4 4 / Robert Holmes 1010100 Procurement
5 4 / Robert Holmes 1010101 Review estimate & Take-Off This includes finding any mistakes in quotes or take-offs and having a meeting with estimators w/ field supervisors.
6 4 / Robert Holmes 1010102 Order materials Order all materials for project
7 4 / Robert Holmes 1010103 Designate Responsibilites This includes explicitly designating project tasks to employees and subcontractors
Get enviromental,
construction, Equipment
8 4 / Robert Holmes 1010104 permits This includes procuring all lisences and permits for the site, parish, work, roadways, and state.
Structure Earned value Sytem
9 4 / Robert Holmes 1010105 (payment plan) This includes establishing a payment system and a plan to recieve the payment for the next stage of the project before beginning.
10 4 / Robert Holmes 1010106 Hire & Train Personell This entails drug testing, site specific training, safety training and machinery training
Acquire tools & Temporary
11 4 / Robert Holmes 1010107 Buildings This includes gathering all tools, specalty equipment, temporry building, bathrooms and tool shed.
Procure Constructon
12 4 / Robert Holmes 1010108 Equipment and trucks This includes gathering all equipment and vehicles
13 4 / Robert Holmes 1010200 Mobilization
14 4 / Robert Holmes 1010201 Transport assets to the jobsite This includes equipment, tools, buildings, and workforce to site
15 4 / Robert Holmes 1010202 Install Temporary Structures Install temporary Buildings like tool shed restrooms, and management building.
Install & distribute Temporary
16 4 / Robert Holmes 1010203 Utilities throughout site Installation of plumbing, sewage, and connection to power source and power distribution to buildings & hotspots among the site
17 4 / Robert Holmes 1010204 KickOff meeting with Client This entails showing the client our current progress and recieving th payment for sitework activities
18 4 / Robert Holmes Construction Start
19 4 / Robert Holmes 102000 Construction
20 4 / Robert Holmes 1020100 Site Work
This package includes demolishing existing structures, trees and shrubs on site with removal. This pacakge includes grading the site to designed the elvation and
excavation for footing and slab construction.
21 4 / Robert Holmes 1020101 Clear and Grade site
22 4 / Robert Holmes 1020102 Installing temporary roads This includes pouring gravel for parking lots, walkways and roadways
Installing erosion prevention &
23 4 / Robert Holmes 1020103 drainage This includes installing siltfences and drainage tubes for the site
24 4 / Robert Holmes Site work Complete
25 4 / Sean Grady 1030100 Footings
26 4 / Sean Grady 1030101 Excavate Footing Area Use excavator to dig footing and work area
27 4 / Sean Grady 1030102 Footing Formwork Build the footing formwork
28 4 / Sean Grady 1030103 Install Footing Rebar Install rebar reinforcment
29 4 / Sean Grady 1030104 Pour Footing Pour specified concrete for footings
30 4 / Sean Grady 1030105 Remove Formwork Remove formwork and backfill around the footings
31 4 / Sean Grady 1030106 Footings Complete
32 4 / Sean Grady 1030200 Slab
33 4 / Sean Grady 1030201 Slab Formwork Build Slab Formwork
34 4 / Sean Grady 1030202 Slab Rebar Install slab rebar reinforcement
35 4 / Sean Grady 1030203 Rough In SEW ELE PLUM Rough in utlilties for slab
36 4 / Sean Grady 1030204 Install Slab SEW ELE PLUM Installation of reinforcment and conduit, sewer, water lines.
37 4 / Sean Grady 1030205 Pour Slab on Grade Pour specified concrete for slab
38 4 / Sean Grady 1030206 Apply Additives Apply any additives needed for the specified concrete mixture
39 4 / Sean Grady 1030207 Remove Formwork Remove Slab Formwork
40 4 / Sean Grady 1030208 Apply Finish Apply finish on slab surface
41 4 / Sean Grady 1030209 Prepare For Masonry Clean slab and prepare it for Masonry
42 4 / Sean Grady 1030210 Slab Complete
43 4/Cesar Ibarra 1040000 Structural
44 4/Cesar Ibarra 1040100 Steel Erections
45 4/Cesar Ibarra 1040101 Install Columns Use boom lift and erect steel columns
46 4/Cesar Ibarra 1040102 Welding Weld neccessary joints
47 4/Cesar Ibarra 1040103 Inspections Inspect all weldings and make sure the steel is properly erected
48 4/Cesar Ibarra 1040201 Install Beams Use boom lift to jun steel joists from the columns
49 4/Cesar Ibarra 1040202 Install Supports Install wire and steel support from the columns to the beams
50 4/Cesar Ibarra 1040203 Inspections Inspect all steel work and ensure work is done properly
51 4/Cesar Ibarra 1040301 Frame Walls Frame all steel walls using aluminum channels
52 4/Cesar Ibarra 1040401 Install Deck Intall 10'x10' steel deck infront of the building
53 4/Cesar Ibarra Steel Erections Complete
54 4/Cesar Ibarra 1050000 Exterior Work
55 4/Cesar Ibarra 1050100 Masonry
56 4/Cesar Ibarra 1050101 Install Keystones Use forklift and install window keystones on all neccessary places
57 4/Cesar Ibarra 1050102 Install Wall Caps Install the wall caps on top of the brick wall
58 4/Cesar Ibarra 1050201 Home Wrap Wrap all the building with tyvek before brick work commences
59 4/Cesar Ibarra 1050202 Brick Ties Properly space brick ties to the plywood wall to provide proper support to brick wall
60 4/Cesar Ibarra 1050203 Reinforcing Steel Install rebar reinforcment into brick exterior wall
61 4/Cesar Ibarra 1050204 Embedded Flashing Embed flashing into mortor at the top of wall as mortor is still wet
62 4/Cesar Ibarra Masonry Complete
63 4/Duval Hawkins 1060000 Roof
64 4/Duval Hawkins 1060100 Roof Installation
65 4/Duval Hawkins 1060101 Install Roof Trusses Installation of roof trusses as per design specifications using cranes and skilled labor.
66 4/Duval Hawkins 1060102 Install Roof Sheating Fix roof sheating panels on top of trusses to provide a solid base for the roof covering
Waterproofing Membrane
67 4/Duval Hawkins 1060103 Installation Apply waterproof membrane over the roof sheating to protect against water infiltration
68 4/Duval Hawkins 1060104 Install Roof Insulation Install thermal insulation materials to meet the required energy efficiency standard
69 4/Duval Hawkins 1060105 Install Roof Decking Secure roof decking on top of the sheathing as a base for the final roof covering
70 4/Duval Hawkins 1060106 Install Flashing Install metal flashing and create roof valleys to channel rainwater away from critical areas
71 4/Duval Hawkins 1060107 Install Roof Shingles Lay shingles over the roof deck in accordance with project specifications
Install Gutters and
72 4/Duval Hawkins 1060108 Downspouts Set up gutters and downspouts to ensure proper drainage and water management from the roof
73 4/Duval Hawkins 1060109 Roof Inspections Conduct inspection to verify the quality of the roof installation and ensure compliance with building codes
74 4/Duval Hawkins Roof Complete
75 4/Duval Hawkins 1070000 MEP Installation
76 4/Duval Hawkins 1070100 HVAC
77 4/Duval Hawkins 1070101 Install HVAC Ductwork Install ducts for heating, ventilation, and air conditioning systems throughout the building
78 4/Duval Hawkins 1070102 Install HVAC Units Place and connect all HVAC units, including chillers, furnaces, or other system components
Install Air Diffusers and
79 4/Duval Hawkins 1070103 Grilles Install air diffusers, grilles, and registers to control airflow within the building
80 4/Duval Hawkins 1070104 Install Refrigerant Lines Set up refrigerant lines connecting indoor and outdoor units in the HVAC system
81 4/Duval Hawkins 1070105 Test HVAC System Perform testing and balancing of the HVAC system to ensure proper operation and air circulation
82 4/Duval Hawkins 1070200 Electrical
83 4/Duval Hawkins 1070201 Install Electrical Conduits Run electrical conduits through walls and ceilings, connecting to junction boxes
Install Wiring and Circuit
84 4/Duval Hawkins 1070202 Breakers Install wiring throughout the building and connect it to circuit breakers in the electrical panel
85 4/Duval Hawkins 1070203 Install Light Fixtures Set up lighting fixtures, power outlets, and switches according to design plans
86 4/Duval Hawkins 1070204 Install Electrical Panels Install main electrical panels and transformers to manage the building's electrical load
87 4/Duval Hawkins 1070205 Electrical System Testing Test the electrical system to ensure proper functionality and adherence to safety standards
88 4/Duval Hawkins 1070300 Plumbing
89 4/Duval Hawkins 1070301 Install Plumbing Rough-In Run water, drainage, and waste pipes through walls and floors before wall closure
90 4/Duval Hawkins 1070302 Pressure Testing On Lines Test water lines for leaks and ensure pressure stability
91 4/Duval Hawkins 1070303 Install Plumbing Fixtures Install and connect sinks, toilets, and showers as per design
92 4/Duval Hawkins MEP Complete
93 4/Christian Ivey 1080000 Architecture finishings
94 4/Christian Ivey 1080100 Interior Finishes
95 4/Christian Ivey 1080101 Drywall Installation This includes using screws, drywall sheets, mud, drywall tape, and sanding to create a smooth interior wall
96 4/Christian Ivey 1080102 Interior Painting This includes application of any primer and paint to interior surfaces such as walls and ceilings
97 4/Christian Ivey 1080103 Ceiling FInishes This includes adding selected tiles to interior ceilings
98 4/Christian Ivey 1080104 Doors and Windows This includes the installation of selected doors and windows along with necessary hardware
99 4/Christian Ivey 1080105 Interior Carpentry This includes interior work such as trim to the doors, windows, walls
100 4/Christian Ivey 1080106 Flooring This includes installation of selected flooring throughout building
101 4/Christian Ivey 1080107 Fixtures This includes the installation of light fixtures, bathroom fixtures and appliances
102 4/Christian Ivey 1090000 Closeout Interior Finish Walkthrough
103 4/Christian Ivey 1090101 Punch List This includes a variety of small tasks surrounding all areas that must be dealt with
104 4/Christian Ivey 1090102 Inspections Construction, safety, architectural inspections that are required by the government and other parties, completed by a variety of inspectors
105 4/Christian Ivey 1090103 Systems Testing Testing of all HVAC, plumbing, electrical, and systems installed on the project
106 4/Christian Ivey 1090104 Final Cleanup Cleanup of any debris or garbage to prepare building for owner
107 4/Christian Ivey 1090105 Final Walkkthrough Walkthrough with owner and any necessary parties, overviewing the entire project
108 4/Christian Ivey 1090106 Drawings (As-Built) Final Drawing must be made that match final construction of building
109 4/Christian Ivey 1090107 Documentation Delivery of any permits, certificates, records, and other documents
110 4/Christian Ivey 1090108 Financial Closeout This includes processing of final contracts and final payments to subs and suppliers
111 4/Christian Ivey 1090109 Client Sign-off Receive final contract sign-off from owner accepting completion of project. Hand keys over to owner
112 4/Christian Ivey 1090110 Lien Release Lien waivers accepting there are no more claims on project