0% found this document useful (0 votes)
15 views4 pages

DAILY PROGRESS REPORT-04-09-2023 (Mechanical Maintenance) : Sigma Powertech Limited

The daily progress report for mechanical maintenance on 04-09-2023 details various tasks including the installation of charge air filter duct pipes, fabrication of exhaust duct pipe elbows, modifications to exhaust duct pipes, and the fabrication of engine auxiliary module stairs. Additionally, it outlines the ongoing fabrication of engine to radiator cooling water pipe connections. The report highlights the progress made in welding, alignment, and cutting of materials for these tasks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views4 pages

DAILY PROGRESS REPORT-04-09-2023 (Mechanical Maintenance) : Sigma Powertech Limited

The daily progress report for mechanical maintenance on 04-09-2023 details various tasks including the installation of charge air filter duct pipes, fabrication of exhaust duct pipe elbows, modifications to exhaust duct pipes, and the fabrication of engine auxiliary module stairs. Additionally, it outlines the ongoing fabrication of engine to radiator cooling water pipe connections. The report highlights the progress made in welding, alignment, and cutting of materials for these tasks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Description: Document ref.

: Issue date: 04-09-2023


Work Report
Revision Status: 00 Effective date:
Ref. ISO Prepared by: Md Razib Shekh Reviewed by:
Mechanical Maintenance Representative Approved by:

SIGMA POWERTECH LIMITED

DAILY PROGRESS REPORT-04-09-2023


(MECHANICAL MAINTENANCE)

This document is the property of Sigma Powertech Limited. Any kind of plagiarism in whole or partially is
not allowed without any written consent
Description: Document ref.: Issue date: 04-09-2023
Work Report
Revision Status: 00 Effective date:
Ref. ISO Prepared by: Md Razib Shekh Reviewed by:
Mechanical Maintenance Representative Approved by:

1. Charge Air Filter duct pipe installation:


 SG#03 A bank charge air duct pipe outer area faulty welding joint buffing done.
 SG#03 A bank charge air duct pipe outer area faulty welding joint re-welded.
 SG#03 B bank charge air duct pipe outer area faulty welding joint buffing is in progress.

2. Exhaust duct pipe elbow fabrication:


 SG#01 silencer side one support shoe aligned with duct pipe.
 SG#01 silencer side one support shoe primary welding done.
 SG#01 exhaust duct pipe inner area welding joint buffing is in progress.
 One 45 degree elbow fabrication for SG#03 exhaust duct pipe is in progress.
Description: Document ref.: Issue date: 04-09-2023
Work Report
Revision Status: 00 Effective date:
Ref. ISO Prepared by: Md Razib Shekh Reviewed by:
Mechanical Maintenance Representative Approved by:

3. Exhaust duct pipe modification & installation:


 SG#04 exhaust duct pipe modification is in progress.
 One 45 degree elbow primarily welded with silencer side short pipe.
 One tail pipe placed over SG#02 exhaust duct pipe support.
 Tail pipe aligned with SG#02 exhaust duct pipe.
 SG#02 exhaust duct pipe & tail pipe primary welding is in progress.

4. Engine Auxiliary module stair fabrication:


 SG#03 engine auxiliary module stair fabrication is in progress.
 Angle bar cutting done for stair platform fabrication.
 04 nos. metal plate cutting done for platform leg fabrication.
 C-channels welded & one platform making done.
 Engine Auxiliary module stair final welding is in progress.
Description: Document ref.: Issue date: 04-09-2023
Work Report
Revision Status: 00 Effective date:
Ref. ISO Prepared by: Md Razib Shekh Reviewed by:
Mechanical Maintenance Representative Approved by:

5. Engine to Radiator cooling water pipe connection fabrication:


 SG#01, 02 & 03 engine to radiator cooling water pipeline fabrication is in progress.
 03 nos. 6 inch pipe cutting done.
 All pipe end side grinded as V shape.
 06 nos. 6 inch elbow both end side grinded as V shape.
 02 nos.6 inch pipe & elbow final welding done.
 06 nos. 6 inch pipe & elbow primary welding done.
 06 nos. pipes placed over pipe support.
 04 nos. 3 inch pipe shifted to radiator area.