MACRO PRECISION COMPONENTS Ref No
NO.131, 8TH MAIN, 3RD PHASE, MPC/QSP/PUR/10/F/04
PEENYA INDL.AREA, BANGALORE - 560058. Rev No:00
PH : +91 96111 22930
PURCHASE ORDER
M/S BLUE BELL ENGINEERING SOLUTION PVT LTD PO NO: MPC/PO/007/25-26
Address: #408, 7TH MAIN JAYANAGAR 2ND BLOCK DATE 16-Apr-25
BANGALORE-560011 Cost Center: For Methods(Software)
GSTIN:29AAECB4325N1ZE Ref Quote: BBE/ADSK/23-2024/ Macro
Date: 02-Apr-25
KIND ATTN: Mr.Anil Kumar PR NO: VERBAL
We are hereby pleased to place our order for the supply of the following materials in accordance with terms & conditions
GMAIL:
mentioned as
AMOUNT IN
SLNO Description QTY RATE IN INR UNIT Due Date
INR
Fusion with PowerMill Ultimate
Commercial Single-user Annual
1 Subscription Renewal Migration 1 67000.00 Nos 67,000.00
C3VM1-005652-L164
Fusion with PowerShape
Commercial Single-user Annual
2 Subscription Renewal Migration 1 24000.00 Nos 24,000.00
C3WM1-005652-L164
SubTotal 91000.00
CGST Tax @9% 8,190.00
SGST Tax @9% 8,190.00
Sub Total 1,07,380.00
Roundoff
TOTAL 1,07,380.00
RUPEES ONE LAKH SEVEN THOUSAND THREE HUNDRED EIGHTY ONLY.
Terms and Conditions:
1.Payment : 30 days from the date of the PO
2.Delivery: E-Delivered by 2-3 Days.
3.Taxes: 18% (GST).
3a.Note :Refer Annexure -I for purchase order guidelines.
4.If any defect/ rejections/ damages/ shortages to be compensated by free replacement or amount will be debited from your a/c.
5.This PO is valid up to 31-DEC-2025 only.
6.M/s : MPC has got every right to cancel this PO at any point of time if not satisfied.
Our GSTIN:29ADLPR6631A1ZG PAN:ADLPR6631A
For Macro Precision Components
Prepared By :Vivek M K Authorised Signatory
Annexure to PO
Annexure to PO NO MPC/PO/007/25-26 Dated 16-APR-25
a. Self-inspection reports of component pertaining to the external provider’s scope of work.
b. Always follow latest revision of drawings. Return obsolete to MPC.
1.2 Objective Evidence /Record retention
Inspection records logbooks for process parameters should be safely protected from damage and dispatched to MPC along with
external provider item.
External provider shall retain copy of verifiable objective evidence of inspection and test performed. The recodes shall be
available for evaluation for a greed of minimum _12_ years.
External provider shall mention all technical information on the report, specific to the scope of supply followed reference etc.
1.2 calibration system
All external calibration are to be performed by NABL, complaint with ISO/TEC 17025 with valid scope .Where such a laboratory is
not available ,calibration may be performed by original manufacture on prior intimation to MPC.
1.5 Non-conforming product
External provider to ensure that product that does not conform to specified requirements is not shipped to MPC. Dispositions of
use as is or repair for products shall require written authorization from MPC prior to shipment. On request by MPC, external
provider shall submit External provider corrective action reports (SCAR) for non-conformity.
1.6 Process /special process
If referred in the Po. External provider shall use MPC approved external providers for process /special process .This does not
relieve the external provider from responsibility to furnish acceptable supplies .External provider shall submit special process
validation report including qualification pf process ,equipment and personnel.
1.7 Statistical process.
External provider is expected to implement the key characteristics in to their manufacturing process to achieve and maintain a
state of statistical control and improve process capability
To inform MPC in advance for any critical items requirements.
1.8 Changes in product /process
Any change in processes ,sub tier external provider ,manufacturing location or any other major changes to be informed to MPC
before implementation .
1.9 Right of Access
External provider shall allow MPC representative, customer and regulatory authority to visit his factory for witness /audit of their
processes and product made for MPC .
1.10 Certificate of compliance
If indicated in the PO, External provider shall submit Certificate of compliance which includes MPC part number and drawing
revision ,PO number ,quantity ,date of dispatch and authorized representative signature .
It may also include heat number, batch code etc if applicable.
1.11 supply chain /Delivery requirements:
1.11.1 Any applicable requirement form MPC customer or from MPC shall be communicated to sub external provider also.
Delivery shall be as per our delivery schedule.
1.12 packing
External provider has to take responsibility of proper packing of our product till reach MPC without damage and also to ease to
open without affecting of packed product
1.13 counterfeit supplies
‘’ counterfeit supplies ‘’ means any material, component, part, assembly, sub - assembly, product and any other item forming part
of the supplies in which there is an indication by visual inspection, testing or other information that it may be a copy or substitute
made without legal right or authority or one whose material,performance ,identity or characteristics have been misrepresented by
the external provider ,manufacturer or a external provider in the External provider supply chain.
1.14 Awareness.
External provider has to take responsibility of giving awareness to his employees on their contribution to product or service
conformity, product safety and importance of ethical behaviour.
1.15 sub tier external provider
If the external provider outsources to their sub tier external provider, all the above clauses applicable to them. External provider
shall flow down all the applicable requirements to their sub tier external provider
Signature: