0% found this document useful (0 votes)
48 views1 page

Gantt Project Planner

The document outlines a project planner with various activities, their planned start dates, durations, actual start dates, and completion percentages. All listed activities, including flooring, paint work, and installation tasks, currently show 0% completion. The planner allows for tracking progress over a specified period.

Uploaded by

Nauman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views1 page

Gantt Project Planner

The document outlines a project planner with various activities, their planned start dates, durations, actual start dates, and completion percentages. All listed activities, including flooring, paint work, and installation tasks, currently show 0% completion. The planner allows for tracking progress over a specified period.

Uploaded by

Nauman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Planner

Select a period to highlight at right. A legend describing the charting follows. Period Highlight: 1 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)

ACTUAL
ACTIVITY PLAN START PLAN DURATION ACTUAL START PERCENT COMPLETE
DURATION PERIODS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60
Porcelain tiles 0%
flooring 15 35 0 0
0%
Paint work 20 40 0 0
0%
Gypsum Walls 1 20 0 0
External side 0%
Graphi paint 20 25 0 0
0%
False Ceiling 1 15 0 0
Wooden Walls and 0%
ceiling Mounted 10 20 0 0
0%
Curtain Walls 20 25 0 0
0%
Canopy 15 20 0 0
0%
Electric fixtures 20 25 0 0
0%
sttaircase Marble 15 25 0 0
Aluminium 0%
Staircase 20 25 0 0
Placement of 0%
Furniture 25 30 0 0
Grass/Planters/ 0%
Truff 25 30 0 0
0%
Kitchen accessories 25 35 0 0
Aluminium works 0%
complete 35 40 0 0
Placement of doors 0%
and windows 10 15 0 0
0%
Activity 17 11 2 0 0
0%
Activity 18 12 6 0 0
0%
Activity 19 12 1 0 0
0%
Activity 20 14 5 0 0
0%
Activity 21 14 8 0 0
0%
Activity 22 14 7 0 0
0%
Activity 23 15 4 0 0
0%
Activity 24 15 5 0 0
0%
Activity 25 15 8 0 0
0%
Activity 26 16 28 0 0

You might also like