The document outlines the development schedule for a 6-lane green field Kanpur Ring Road project, detailing tasks, durations, start and finish dates, and dependencies. The project spans from March 2025 to September 2027, with various milestones and construction phases including earthworks, road construction, and installation of infrastructure. Key components include the construction of bridges, culverts, and service roads, along with associated electrical works.

Uploaded by

negi.abhishek202
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views3 pages

Work Program

The document outlines the development schedule for a 6-lane green field Kanpur Ring Road project, detailing tasks, durations, start and finish dates, and dependencies. The project spans from March 2025 to September 2027, with various milestones and construction phases including earthworks, road construction, and installation of infrastructure. Key components include the construction of bridges, culverts, and service roads, along with associated electrical works.

Uploaded by

negi.abhishek202
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

ID Task Name Duration Start Finish Predecessors Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half

Predecessors Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
0 Development of 6 lane green field Kanpur Ring Road 910 days 25 Mar '25 20 Sep '27
(Package-IIB starts from Design Ch.32+090 to Ch. 51+200
around Kanpur city (Length=19.110 kms in the state of
Uttar Pradesh on EPC Mode
1 1 Mile Stone-1 318 days 25 Mar '25 05 Feb '26
2 2 Mile Stone-2 228 days 06 Feb '26 21 Sep '26 1
3 3 Mile Stone-3 228 days 22 Sep '26 07 May '27 2
4 4 Schedule Completion 136 days 08 May '27 20 Sep '27 3
5
6 5 Development of 6 lane green field Kanpur Ring Road 910 days 25 Mar '25 20 Sep '27
(Package-IIB starts from Design Ch.32+090 to Ch. 51+200
around Kanpur city (Length=19.110 kms in the state of
Uttar Pradesh on EPC Mode
7 5.1 Submission of Design, Drawing & other Documents 90 days 25 Mar '25 22 Jun '25
8
9 5.2 Reconstruction/New 2-Lane realignment/ 653 days 14 May '25 25 Feb '27
Bypass (Flexible Pavement)
10 5.2.1 Earthwork upto top of the subgrade 471 days 14 May '25 27 Aug '26 7SS+50 days
11 5.2.2 Sub Base Course (GSB) 108 days 14 Jul '26 29 Oct '26 10FS-45 days
12 5.2.3 non Bituminous Base Course (WMM) 108 days 15 Sep '26 31 Dec '26 11FS-45 days
13 5.2.4 Bituminous Base Course 90 days 02 Nov '26 30 Jan '27 12FS-60 days
14 5.2.5 Wearing Coat 26 days 31 Jan '27 25 Feb '27 13
15
16 5.3 Reconstruction/New Service Road (Flexible 222 days 30 Apr '26 07 Dec '26
Pavement)
17 5.3.1 Earthwork upto top of the subgrade 117 days 30 Apr '26 24 Aug '26 10FS-120 days
18 5.3.2 Sub Base Course (GSB 50 days 10 Aug '26 28 Sep '26 17FS-15 days
19 5.3.3 Non Bituminous Base Course (WMM 50 days 09 Sep '26 28 Oct '26 18SS+30 days
20 5.3.4 Bituminous Base Course 30 days 19 Oct '26 17 Nov '26 19SS+40 days
21 5.3.5 Wearing Coat 20 days 18 Nov '26 07 Dec '26 20
22
23 5.4 Reconstruction & New Culverts on existing 276 days 30 Oct '26 01 Aug '27 11
road, realignments, bypasses Culvert (length<6m)
24
25 5.5 New Minor Bridges (Length>6m and <60m) 395 days 13 Jun '26 12 Jul '27
26 5.5.1 Foundation + Substructure: On completion of 183 days 13 Jun '26 12 Dec '26 37
the foundation work including foundations for
wing and return walls, abutments, piers upto the
27 5.5.2 Super-structure: On completion of the super 92 days 11 Feb '27 13 May '27 26FS+60 days
structure in all respects including wearing coat,
bearings, expansion joints, handrails, crash barriers,
28 5.5.3 Approaches: On completion of approaches 28 days 11 Jun '27 08 Jul '27 27FS+28 days
including retaining walls, stone pitching, protection
29 5.5.4 Guide Bunds and River Training Works: On completion 14 May
60 days of guide '27 and
bunds 12 river
Jul '27training
27 works complete in all respects.
30
31 5.6 New Underpasses/ Overpasses 468 days 14 May '25 24 Aug '26
32 5.6.1 Foundation + Substructure: On completion of 417 days 14 May '25 04 Jul '26 7SS+50 days
the foundation work including foundations for
wing and return walls, abutments, piers upto the

Page 1
ID Task Name Duration Start Finish Predecessors Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
33 5.6.2 Super-structure: On completion of the super 320 days 12 Aug '25 27 Jun '26 32SS+90 days
structure in all respects including wearing coat,
bearings, expansion joints, handrails, crash barriers,
34 5.6.3 Wearing Coat In case of Overpass - wearing 30 days 26 Jul '26 24 Aug '26 33FS+28 days
coat including expansion joints complete in all
respects as specified and b) in case of underpass
35 5.6.4 Approaches: On completion of approaches including 21 days 28walls,
retaining Jun '26Reinforced
18 Jul '26 33walls, stone pitching, protection works complete in all respect, test on completion in all respect and fit for use.
Earth
36
37 5.7 RUB 245 days 11 Oct '25 12 Jun '26
38 5.7.1 Foundation 50 days 11 Oct '25 29 Nov '25 10SS+150 days
39 5.7.2 Sub-structure 60 days 10 Dec '25 07 Feb '26 38SS+60 days
40 5.7.3 Super-structure (including bearings) 58 days 08 Mar '26 04 May '26 39FS+28 days
41 5.7.4 Wearing Coat In case of ROB - wearing coat including1 day expansion
12 Junjoints
'26 complete
12 Jun '26in 42FS+28 daysas specified in case of RUB rigid pavement under RUB including drainage facility complete in all respects as specified.
all respects
42 5.7.5 Miscellaneous items like hand rails, crash barrier,10 daysmarkings
road 05 May
etc'26 14 May '26 40
43 5.7.6 Wing Wall / Retrun Wall 15 days 08 Feb '26 22 Feb '26 39

44 5.7.7 Approaches: approaches including retaining walls,7 stone


days pitching
05 May
&'26 11 Mayworks
protection '26 40
45
46 5.8 New Elevated Section/ Flyover/ Grade Separators759 days 23 Jun '25 21 Jul '27
47 5.8.1 Foundation 405 days 23 Jun '25 01 Aug '26 7
48 5.8.2 Sub-structure 513 days 22 Aug '25 16 Jan '27 47SS+60 days
49 5.8.3 Super-structure including bearings 277 days 21 Jul '26 23 Apr '27 48FS-180 days
50 5.8.4 Wearing Coat In case of ROB - wearing coat 44 days 08 Jun '27 21 Jul '27 53
including expansion joints complete in all respects
as specified in case of RUB rigid pavement under
RUB including drainage facility complete in all
51 5.8.5 Miscellaneous items like hand rails, crash 173 days 25 Nov '26 16 May '27 49FS-150 days
barrier, road markings etc
52 5.8.6 Wing Wall / Retrun Wall 15 days 24 Apr '27 08 May '27 49
53 5.8.7 Approaches: approaches including retaining 30 days 09 May '27 07 Jun '27 52
walls, stone pitching & protection works
54
55 5.9 Other Work 830 days 13 Jun '25 20 Sep '27
56 5.9.1 Toll Plaza 180 days 01 Jan '27 29 Jun '27
57 5.9.2 Road side drains 113 days 02 Nov '26 22 Feb '27 20SS,13SS
58 5.9.3 Road signs, Marking, Km. Stone, Safety Devices61
etc.days 22 Jul '27 20 Sep '27 46,9,16
59 5.9.4 Bus Bays 50 days 31 Jan '27 21 Mar '27 21SS,14SS
60 5.9.5 Road Side Plantation 96 days 02 Nov '26 05 Feb '27 57SS
61 5.9.6 Protection Works other than approaches to 166 days 09 Feb '26 24 Jul '26 10FS-200 days
the bridges, elevated sections/ Flyover/ Grade
separator and ROBs/ RUBs
62 5.9.7 RE Wall 309 days 13 Jun '25 17 Apr '26 10SS+30 days
63 5.9.8 Other Miscellaneous works including 70 days 02 Nov '26 10 Jan '27 20SS,13SS
conecting road & junction under Grade separator.
64 5.9.9 Development of NHAI Office 250 days 01 Jan '27 07 Sep '27 56SS
65
66 5.10 EHT Line & EHT Crossings 180 days 25 Mar '25 20 Sep '25
67 5.10.1 Erection of Poles 120 days 25 Mar '25 22 Jul '25
68 5.10.2 Conductor stringing including laying of cable 90 days 09 May '25 06 Aug '25 67SS+45 days

Page 2
ID Task Name Duration Start Finish Predecessors Half 1, 2025 Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027 Half 2, 2027
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
69 5.10.3 DTR Erection (if involved) 90 days 24 May '25 21 Aug '25 68SS+15 days
70 5.10.4 Charging of line including dismantling and 30 days 22 Aug '25 20 Sep '25 69
site clearnace
71
72 5.11 HT/LT Lines & HT LT Crossing 240 days 25 Mar '25 19 Nov '25
73 5.11.1 Erection of Poles 180 days 25 Mar '25 20 Sep '25
74 5.11.2 Conductor stringing including laying of cable 150 days 09 May '25 05 Oct '25 73SS+45 days
75 5.11.3 DTR Erection (if involved) 120 days 23 Jun '25 20 Oct '25 74SS+45 days
76 5.11.4 Charging of line including dismantling and 30 days 21 Oct '25 19 Nov '25 75
site clearnace