Project-1
Project-1
Node (Event)
Activity
Dummy Activity
The events can be further classified into the following two
categories:
(i) Merge Event : An event which represents the joint
completion of more than one activity is known as a merge
event. This is shown in the following diagram
Burst Event
Activities :Activities in the network diagram represent
project operations (or tasks) to be conducted. As such each
activity except dummy activity requires resources and takes
a certain amount of time for completion. An arrow is
commonly used to represent an activity with its head
indicating the direction of progress in the project. Activities
are identified by the numbers of their starting (tail or
initial) event and ending (head, or terminal) event, for
example, an arrow (i, j) between two events; the tail event
i represents the start of the activity and the head event j
represents the completion of the activity
The activities can be further classified into the following
three categories:
(i) Predecessor Activity: An activity which must be
completed before one or more other activities start is
known as predecessor activity.
(ii) Successor Activity: An activity which starts immediately
after one or more of other activities are completed is
known as successor activity.
(iii)Dummy Activity: An activity which does not consume
either any resource and/or time is known as dummy
activity.
Activity
i j
B G 7
A 6
1 2 3
D F
5
3.Develop a network diagram for the following project
Activity Immediate
predecessor
Activity
A -
B -
C A
D B
E A
F C,D
G E
H E
I F,G
J H,I
4
E
H
G
A 3 C
F
1 5 6 I J
7
B D 8
2
Example 4: An assembly is to be made from two parts X
and Y. Both parts must be turned on a lathe. Y must be
polished whereas X need not be polished. The sequence of
activities, together with their predecessors, is given below.
B
G A
A 6 7 8
1 2
F
C
4 5
E
Example 5: Listed in the table are the activities and
sequencing necessary for a maintenance job on the
heat exchangers in a refinery
Draw a network diagram of the activities for the
project
Activity Description
Predecessor
Activity
A Dismantle pipe connection -
B Dismantle heater, closer and floating point A
C Remove the tube bundle B
D Clean the bolts B
E Clean heater and the floating head front B
F Clean the tube bundle C
G Clean the shell C
H Replace the tube bundle F,G
I Prepare shell present test D,E,H
J Prepare the pressure test and reassemble I
F 5
4
G D1
6
C
H
A B D
1 2 3 I
8 9 J
10
E
7 D2
6.Develop a network diagram for the following project
A B C D E F G H I
23 8 20 16 24 18 19 4 10
G(19)
2 5
C(20) H(4)
A(23)
D(16)
E(24)
3
* 7.Draw net work diagram for the following data.
Activity A B C D E F G H
Predecessor - - - A B B,C D,E,F E,F
G
D 6 7
2
A
1 B H
E
3 5
C
4 F
8. Draw a network diagrams from the following list of activities:
Activity Predecessor
I II III
A - - -
B - - -
C - - -
D A A A
E B A,B A,B
F B,C A,B,C B,C
G D,E,F D,E,F C
F D,E,F