Weekly Report No.18
Weekly Report No.18
Civil Works for the Sewerage System Development in Ta Khmau Town Project
Contractor SCOPE OF WORK BASE RECORD DATE
Kumho-Techcross Joint Venture ꞏ Wastewater Treatment Plant / Pumping Station 7nos
1-Mar-25 till 7-Mar-25
ꞏ Sewer 125.29km / Stormwater Pipeline 5.37km
Contract No.: MPWT-EDCF-KHM-20-CB01 REPORT NO.018 MEETING VENUE : Site Office
1. Weekly Progress
1-1 Quantity 1-2 Percentage (Based on Revised No.2)
This week Cumulative
No. Description Unit Contract Plan Actual Different No. Description Contract
Plan Actual Plan Actual
1 Preliminaries and General LS 1 0.569 0.541 -0.03 1 Preliminaries and General 3.88% 0.06% 0.03% 2.21% 2.10%
Gravity Pipe m 88,303 2 Tertiary Sewage Pipeline 28.77%
2 Tertairy Force Pipe m 109 2-1 Civil 28.52%
Pump set 6 2-2 Mechinical 0.13%
Gravity Pipe m 15,259 2-3 Electrical 0.13%
3 Secondary
Pressure Pipe m 860 3 Secondary and Main Trunks 15.02%
Gravity Pipe m 2,182 4 Compact Pumping Station 1.83%
4 Main Trunk
Pressure Pipe m 4,660 4-1 Civil 0.80%
Compact Concrete m3 653 4-2 Mechinical 0.75%
5
Pump Pump set 6 4-3 Electrical 0.29%
Concrete m3 1,185 5 Main Pumping Station 2.19%
6 Main Pump
Pump set 3 5-1 Civil 0.69%
Embankment m³ 1,152,718 57,078 9,365.00 (47,713) 5-2 Mechanical 0.74%
Concrete m³ 20,454 5-3 Electrical 0.45%
7 WWTP
Architect set 5 5-4 Architecture 0.15%
Pump lot 1 5-5 Architecture Facilities (M&E) 0.15%
Storm Hume Pipe m³ 3,961 6 Wastewater Treatment Plant 29.30% 0.16% 0.02% 0.89% 0.55%
8
water Box Culvert m³ 1,406 6-1 Civil 27.12% 0.16% 0.02% 0.89% 0.55%
1. Preliminaries and General 6-2 Mechanical 0.57%
ꞏ Installation of WWTP Signboard (24.Feb.2025 → 02.Mar.2025) 6-3 Electrical 0.69%
ꞏ Equipment Insurance for WWTP (04.Mar.2025) 6-4 Architecture 0.53%
ꞏ Checking of all existing sewer pipelines including all existing discharges into Storm Drain within the project 6-5 Architecture Facilities (M&E) 0.39%
area (01.Mar.2025 → 07.Mar.2025) 7 Stormwater Pipeline 5.97%
ꞏ Motor cycle number plate (Requested on 06.Feb.2025) → Processing 8 O&M Equipment 1.14%
ꞏ Order Vehicle A-1 3ea, A-2 2ea, B 5ea → Expected Deliver Date A-1 June.2025, A-2 : Apr.2025, B : Apr.2025 9 Commissioning & O&M Training 0.88%
9-1 Commissioning & Training 0.26%
2. Wastewater Treatment Plant 9-2 O&M Training Cost for DLP period 0.62%
ꞏ Site Clearing and grubbing, Dewatering, Grading and Compaction 10 Specified Provisional Sums 10.17%
ꞏ Removal unsuitable Soil and Disposal Schedule of Daywork 0.86% 0.01% 0.00% 0.01% 0.00%
ꞏ Embankment Work TOTAL 100.00% 0.22% 0.05% 3.10% 2.65%
Cummulative Weekly Actual
Division
Plan(A) Actual (B) (B-A) Last This Next
Progress 3.10% 2.65% -0.45% 0.04% 0.05% 0.05%
2. Manpower Status
Up to Last This week (B) Cumulative Up to Last This week (B) Cumulative
Description Description
Week (A) (A+B) Week (A) (A+B)
Per Day Total Per Day Total
1) OFFICE MANPOWER 2,201 28 167 2,368 2) SITE MANPOWER 2,301 45~61 379 2,680
Engineer 1,309 17 6 102 1,411 Engineer 1,024 13~17 6~7 106 1,130
Supervisor 177 2 6~7 13 190 Supervisor
Lab. Engineer 210 3 6~7 19 229 Common Labour 229 12~18 7 113 342
Skill Labour Foreman 131 3 7 21 152
Common Labour 211 3 6 18 229 Skill Labour 211 211
Driver 294 3 6~7 15 309 Operator/Driver 706 17~23 6~7 139 845
Cummulative 1) + 2)
Division
Office Site Total Last This Next
Manpower 2,368 2,680 5,048 505 546 650
3. Equipment Status
Up to Last This week (B) Cumulative Up to Last This week (B) Cumulative
Description Description
Week (A) (A+B) Week (A) (A+B)
No. Day Total No. Day Total
1) Equipment 422 6~8 77 499 2) Vehicle 380 9 63 443
Excavator 157 3 7 21 178 Mixer Truck
Bulldozer 93 1 6~7 6 99 Water Truck 26 1 7 7 33
Motor Grader 27 1~2 7 13 40 Fuel Truck 10 10
Roller 145 2~3 7 37 182 Small Dump Truck 80 80
Dump Truck 264 8 7 56 320
Cummulative 1) + 2)
Division
Euip. Vehicle Total Last This Next
Equipment 499 443 942 144 140 150
4. Description Activity (1/2)
This week Next week
1) Preliminaries and General 1) Preliminaries and General
ꞏ Submit the Proposal Letter for the Contractor's and Engineer's Office & Accommodation ꞏ Maintain safety devices and tool box meeting at WWTP and Site
(14.Mar.2025)
ꞏ Maintain safety devices and tool box meeting at WWTP (in Everyday)
ꞏ Resubmission of EMP (06.Mar.2025) 2) Pipe Line Works
ꞏ Submit Monthly Progress Report and HSE Monthly Report. (06 Mar 2025) ꞏ Submission of Subcontractor's Prior Consent Additional Document (HSE, QA/QC Plan, Inspection Plan)
2) Pipe Line Works (14.Mar.2025)
ꞏ Submission of Subcontractor's Prior Consent Additional Document (HSE, QA/QC Plan, Inspection ꞏ Resubmit method statement of stormwater. (14.Mar.2025)
Plan) (03.Mar.2025) ꞏ Resubmit Manhole Cover Design (after confirm the design + 2days later)
ꞏ Resubmit method statement of stormwater. (Expected 14.Mar.2025) ꞏ Check of all existing sewer pipelines including all existing discharges into Storm Drain within the project
ꞏ Resubmit Manhole Cover Design (after confirm the design + 2days later) (Manhole locations, alignment, exising obstacles)
ꞏ Check the site conditions (Manhole locations, alignment, exising obstacles)
(01.Mar.2025 → 07.Mar.2025)
ꞏ Sketch shop drawing for precast manhole
3) Survey Work
ꞏ Submission of Location All Pumping Station Boundary (3.Mar.2025)
4. Description Activity (2/2)
This week Next week
3) Wastewater Treatment Plant
4) Wastewater Treatment Plant
ꞏ Site Clearing, Removal unsuitable soil and disposal
ꞏ Site Clearing, Removal unsuitable soil and disposal
ꞏ Embankment Work
ꞏ Embankment Work
ꞏ Resubmission of Bailey Bridge Cost Estimation (14.Mar.2025)
ꞏ Resubmission of Bailey Bridge Cost Estimation (14.Mar.2025)
ꞏ Mine / UXO Detection (10.Mar.2025)
ꞏ Mine / UXO Detection (Expect on 10.Mar.2025)
ꞏ Resubmission of Request for Approval of Method Statement Geotecnical & Soil Investigation
(3.Mar.2025)
4) Other Activities
ꞏ Request for Approval Embankment Materials Source from borrow pit No.4 and 5 (3.Mar.2025)
ꞏ Submission Plan of Household Connection Plan - Promotion & Design (14.Mar.2025)
ꞏ Make cofferdam for block B and C (04.Mar.2025 → 07.Mar.2025)
ꞏ Resubmission of Tax Exemption Confirm letter (14.Mar.2025)
5) Other Activities
ꞏ Submission Plan of Household Connection Plan - Promotion & Design (14.Mar.2025)
ꞏ Resubmission of Tax Exemption Confirm letter (Expected on 14.Mar.2025)
ꞏ Preparation of Factory inspection (4.Mar.2025)
ꞏ Resubmission of Topographical Survey Result Report (3.Mar.2025)