Method Statement
Method Statement
WORK METHOD
1. Purpose
The purpose of this document is to describe the process of aluminum window works in
compliance with all the required specifications, standards, and proper construction procedures for
the building is finishing work.
The scope of works are including the removal of existing windows and glass also the installation,
delivery of windows and glass.
3. Mobilization:
Mobilization shall consist of obtaining all required permits to initiate the project which is approved by
responsible authorities. After this part all the required materials and equipment will brought inside of
site to initiate the work. Before starting any kind of activity, other basics and safety inductions will be
conducted and laid in designated area.
4. SITE CLEARANCE:
PTW will be secured before starting the work, Safety is the prime factor to consider at any
construction progress, to ensure safety, we will barricade the surrounding area of the site using
barricading tape and warning signs. Proper work access will be arranged by us with safety procedures.
Respective authorities will assign a yard area which will be used as shelter for laborers. It shall fulfill
all the electrical requirements for Power tools.
5. METHODOLOGY:
Adequate PPEs required will be distributed and toolbox talk will be given to workers.
The existing fire alarm equipment needs to be isolated before work may begin, either with the help
of or in the presence of the appropriate authority.
All the waste and debris will be disposed of to the municipality approved dumb yards
Power to be isolated from the area and temporary DB to be provided with Safety lock and signages
( LOTO procedure will be implemented)
PPEs like face masks and hand gloves will be provided at site.
Social distancing will be followed at site and works will be allocated accordingly
Work sites will be protected and will be covered to prevent unauthorized entry
Entry and exit route to the worksite will be protected (without disturbing emergency exit)
Materials storage area will be selected as per the client instruction and the area will be protected
and cleaned daily.
Handling of Materials
Material manual handling - shall be suitably assessed for its work method and to identify where
manual handling is required and provide the necessary control measures.
No employee shall be asked to carry loads above his capacity, and in any case no loads shall exceed
25kgs. Provide toolbox talk on the lift using the ‘Five stage method’ (below) prior to manual
handling.
Lift smoothly and evenly with your legs taking the strain. (It is important not to twist your trunk
or to jerk or shove your body)
Hold the load close to your body
The area of installation for the Aluminum and Glazing must be free from any obstruction and other operations.
Opening must be free of wet concrete works prior to installation of aluminum frames. All aluminum frames
are protected with protection films. And in case unavoidable concrete works will be done within one (1) meter
of the aluminum frames, contractors involved shall cover the said frames with polyethylene sheets or any
protective sheets to avoid damage to the installed materials. Fabricated aluminum and glazing products will be
delivered in complete sets of good quality, and shall be delivered to site pre-cut, pre-notched, bracketed for
both vertical and horizontal frames connection and covered with protective tapes. Fabrication will be
supervised and instructed. A temporary staging area must be made available to site where to offload deliveries
and from which distribution can be made.
Window Installation
Verify the opening dimension and angles and levels from finish floor line reference to ensure that
frames fit the openings. Align and fit the door in frame to each desired location and elevation.
Fix door frames by anchor bolts located as per approved shop drawings and to be covered by wood
caps later.
Install, align, and fit the doors in frames with uniform clearance and bevel to provide 3mm at heads,
jambs and between pairs of doors, bottom of door to top of decorative floor finish or covering as per
approved shop drawings.
Architraves’ will be fixed by nail and to be covered by wood putty. All surrounding gaps will be
filled with silicone.
Apply the 6mm back printed glass on one side of the door using silicon and give necessary supports
if required.
Completed wood doors shall operate freely and smoothly without rattle or bound condition.
Clean stains and traces of cleaning fluid.
HSE REQUIREMENTS:
*Safety induction will be attended by our manpower before entering the Site.
*Toolbox Talk will be conducted every day before starting the work.
*Required mandatory PPE will be worn by all.
• Safety Shoes
• Safety Helmet
• Dust Mask
• Safety Goggles
• Safety Harness (Work at Height)
*The PTW will be taken before starting the work and it will be surrendered after completion of work
as per the rules of Site management team
*Gate Pass for all the Vehicles/Machinery will be obtained in advance before entering the facility.
Safety is the prime factor to consider at any construction project. To ensure safety we will isolate the
surrounding area of the site using barricading tape and warning signs. Proper work access will be
arranged by us with safety procedures.
All safety precautions and mandatory PPE are to be discussed in “Toolbox Talk”
understood, followed and regularly monitored.
A job specific toolbox talk shall be conducted by supervisor, permit acceptor, about
risk assessment. The statement of the method will be explained to the working team
and ensure that all team members are aware of work-related hazards, risk and control
measures.
Safe and quality hand tools shall be provided for all jobs, where hand and portable power
tools are used. All tools will be free of defects and maintained in good condition.
All electrical hand tools will be properly grounded and double insulated type.
All electrical portable hand tools equipment’s shall be PAT tested with displayed the
proper PAT sticker. It shall be the individual workman responsibility for daily
inspection, safe use and proper storage of electrical hand tools.
Proper barricading to be ensured according to procedures and displays the safety signage
on locations.
The existing widow frame can then be removed from the wall; this will be done by removing
the frame fixings where accessible and then by cutting through the frame using a
reciprocating and levering the framework from the wall with a wrecking/pry bar.
The old windows and frames will be carried by hand from the property to the waste skips to
be removed from site and disposed of via licensed waste carried for disposal at a licensed
waste site. All broken glass will be placed into heavy duty waste sacks and care will be taken
to avoid overloading and puncturing the sides of the bags.
Care must however be exercised when handling glass and care must be taken avoid breaking
the glass as this increases the risks of injury.
Prior to the fitting of the new window and window frame, the walls must be checked to
ensure that they are sound and that any old fixings have been removed and disposed of were
sections of the
wall have been damaged or are not suitable, the area should be made good or alternative
fixings used.
Clean the area and prepare the recess for the installation of the new windows. Fit the new
window frame into position, ensuring a tight fit and ensuring that the frame is plumb and
square.
Use packers where necessary to secure the frame in position and then drill through the frame
into the masonry wall for the frame fixings. A minimum of 2 frame fixings should be used on
each element of the window frame, though for long windows additional fixings will be
required.
Once the frame fixings have been inserted and securely fixed /tightened, the back of the frame
should be filled with expanding foam to provide added protection against the weather, water
ingress and from unwanted noise.
Once the windows and frames have been installed, the glazing units can be inserted. Each unit
should be installed and secured into position with the appropriate beading/seals. The glazed
panels can then be carefully lifted into position, cut resistant grip gloves should be always
worn when lifting glazed units and for large panels a minimum of 2 persons should be used to
lift and secure the panels in place. The use of suction lifters should also be used to provide a
safe and secure grip when lifting large and heavy glass panels/units.
The window frame should then be trimmed and sealed both internally and externally and the
area is made good.
Upon completion of the work, UOID will remove all rubbish, scrap and waste
materials/packaging from the premises and dispose of appropriately. Thoroughly vacuum and
clean through the area and all transit routes leaving the property in a clean and tidy state.
Care must be taken to ensure that the glass is not broken and that when handling glass and
windows, that appropriate cut resistant gloves always worn.
At the end of each working day, a check is to be made to ensure that all waste has been
removed from the site and placed into the appropriate waste containers/skips and that the site
is left in a clean and tidy state.
Delivery:
Before delivery the windows and their various components should be fully protected to ensure the
components remain in good condition until they are ready for installation.
All materials for delivery should be verified against the quantity and batch number stated in the
delivery order. All the required accessories, including friction stays, handles, locking devices,
fixing etc. should be delivered together with the main components.
Upon delivery on site, the materials should be checked for damages during transportation and that
the delivered materials are in compliance with the specifications. Any damage or incorrect
materials should be returned to the factory.
Storage:
Delivery of materials should be carefully planned according to the installation schedule so that the
only the required quantity of materials are stored on site, where the possibility of damage is
higher.
HOUSEKEEPING OF THE AREA
After completion of work as per scope, Entire housekeeping will be conducted once again
to remove all the debris and other refuses. The area will be free from Barricades and other
restrictor signs. All the tools and equipment will be taken away and the place will be
handed over in this part to fulfill the completion of work and PTW will be cancelled after
performing above mentioned.
Finally, after client visual inspection the Completion Report will be signed.
No unauthorized people are allowed on site during works, steps to be taken to ensure public are kept out of work
areas.
Area inspected before work commences daily, and at suitable intervals during the day.
Adequate Warning signs to be placed on visibly on site.
PPE to be always worn. (Gloves, face mask, etc)
All areas to be always kept clean and tidy to reduce tripping and slipping.
A record of MSDS for any chemical material used on site will be kept for emergency use.
Rev. No. Date Issue Prepared By: Reviewed & Approved By:
00 Project Manager
29/04/2025 QA/QC Engineer