The document is a report on the erection and testing of the Circuit Breaker Type SB6m SB6 72, detailing material control, erection processes, and testing results. It includes sections on quality control, SF6 gas pressure, and various operational tests, concluding with the status of the circuit breaker regarding energization. The report indicates whether the circuit breaker can be energized based on the findings and any defects noted during the inspection.

Uploaded by

vutnm94
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
29 views6 pages

Mod 100 BUS Ed 3 SB6m 145-245kV INGLESE

The document is a report on the erection and testing of the Circuit Breaker Type SB6m SB6 72, detailing material control, erection processes, and testing results. It includes sections on quality control, SF6 gas pressure, and various operational tests, concluding with the status of the circuit breaker regarding energization. The report indicates whether the circuit breaker can be energized based on the findings and any defects noted during the inspection.

Uploaded by

vutnm94
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Report of :

O Erection
O Testing
Transmission & Distribution
Circuit Breaker Type SB6m SB6 72
Mod. 100 BUS Ed. 3 Eng Pag.1 di 6

Copy at : q GQ/ ....................………….….... q Client . ................………….….... q


.................…………………

Serial N. Supply Order Item Fider

Voltage (KV) Rated Current (A) Breaking Capacity (kA)

Plant Customer

Assembly Drawing Schematic Diagram

OPTIONAL
q Second opening circuit q ......................................
q De energized opening circuit q ......................................

1 CONTROL OF MATERIALS BEFORE ERECTION


1 QUANTITY CONTROL q Complete
q Material missing and or not corresponding to the packing list
(see enclosed list ............. )
q Material not corresponding the packing list
(see enclosed list ............. )
q Wrong packing list
(See enclosed list ............. )
2 QUALITY CONTROL
- Packing q Perfect q damaged ( see note attached .......................)
- Material q Perfect q damaged ( see note attached .......................)
3 – STORAGE BEFORE ERECTION :
q No q Indoor q Outdoor
q Correct R Not Correct (Storage Period ...............)

- Damage Due to Incorrect storage :

q No q Oxidation q Breakage q ......................


(See note attached ...........................)
4 - SF6 gas pressure in the pole before erection :

Polo R MPa Polo S MPa Polo T MPa q Adeguated


q Not adeguated

Business Unit Services Nuova Magrini Galileo – Via Circonvallazione est n° 1 – 24040 Stezzano Bergamo
Report of :
O Erection
O Testing
Transmission & Distribution
Circuit Breaker Type SB6m SB6 72
Mod. 100 BUS Ed. 3 Eng Pag.2 di 6

2 ERECTION
Personnel of erection :
q NMG q Sub contractor .......................... q Sub contractor ......................
With NMG supervision Without NMG supervision

Correspondence of materials to the dimension drawing :


q Yes q No (See note attached .................)

Correspondence of civil works to the dimension drawing:


q Yes q No (See note attached .................)

Difficulties of erection :
q Yes (see note attached ...............) q No

ERECTION PERIOD FROM TO

3 CONTROL AND TEST


1 q Control of pressure in the poles
Interrupting Unit : R MPa q Correct
S MPa q Not correct
Temp. ................... °C T Mpa..

2 q Control of correct assembly and regulation of transmission road


(Only for Circuit Breaker Type SB6m TRIP)
q Correct q Not correct

3 q Control of correct erection poles and base frame


q Correct q Not correct

4 q Control of correct erection Control cubical


q Correct q Not correct

5 q Control of correct erection densostat SF6 Gas


q Correct q Not correct

6 q Control correct Arrangement Interconnection Control Cubical/Mechanism/s


densostat/s

Business Unit Services Nuova Magrini Galileo – Via Circonvallazione est n° 1 – 24040 Stezzano Bergamo
Report of O Erection :
O Testing
Transmission & Distribution
Circuit Breaker Type SB6m SB6 72
Mod. 100 BUS Ed. 3 Eng Pag.3 di 6

q Correct q Not correct


7 q Control correct earth connection
q Correct q Not correct
8 qControl of operating mechanism
q Closing and Opening operation without damaged
q Control of regulation Pole R Vulcain operating mechanism (OnlyCircuitBreakerTypeSB6mTRIPOLARI)
Reference TEST 1 TEST 2 TEST 3
ANGLE IN OPENING POSITION.
ANGLE IN CLOSE POSITION.
ANGLE OF EXTERNAL CRANCK 52°+0°-1° (camera AF8)
51°+0°-1° (camera TSB)

Rated value Rated value Rated value Measured value


SB6m 145÷170 SB6m 245 . SB6 72
Loding time spring charge [s] ≤ 20 (≤ 10) ≤ 20 ≤ 10 R S T
Spring charge motor absorbment (110Vdc) [A] ≤ 7,3 (5) ≤ 7,3 ≤ 2,5
Spring charge motor absorbment (220Vdc) [A] ≤ 3.7 ≤ 3,7 ≤ 1,6
Spring charge motor absorbment (125Vdc) [A] ≤ 6.4 ≤ 6,4 ≤ 2,8
Spring charge motor absorbment (230Vac-50Hz) [A] ≤ 3.5 ≤ 3,5
Spring charge motor absorb (48Vdc) [A] ≤ 16.7

Note : The value among parenthesis are refer only for Circuit Breaker type SB6m 145-170 kV UNI
q Check correct functionality of operation counter
q Check correct mechanical position indicator CB
q Check correct mechanical spring status indicator
9 q Check correct sequence densostat contact
q Correct q Not correct
Rated value Misured Value
See schematic R (tripolare) S T
Diagram
Low pressure alarm

1° opening circuit lock

2° opening circuit lock

Temperatura amb. [°C]


20°
Gas Umidity mesurament
Rated Value Misured Value

Riferimento R S T
Umidity gas [PPm ≤ 150
]

Business Unit Services Nuova Magrini Galileo – Via Circonvallazione est n° 1 – 24040 Stezzano Bergamo
Report of :
O Erection
O Testing
Transmission & Distribution
Circuit Breaker Type SB6m SB6 72
Mod. 100 BUS Ed. 3 Eng Pag.4 di 6

Unconformty Mesured Adopted


q None q Density meter replaced
q Density meter unset q ........................................
q Gas leakage from interrupting unit q ........................................

10 q Control of regular performance of operating cycles Result


Cycle O – 03” – CO – 1’ – CO Starting conditions: Motor stop q Positive
q Negative

11 q Control of operating times


q Control of main circuit times (at RV– RP)
Referd Value Measured Value
Chamber type Chamber type SB6m SB6 72 kV POLE
AF8 TSB 245
R S T
Solo SB6m 145 SB6m 145/170 kV
Closing Time [ms 77±6 79±6 (74±6) 65±6 57±5
]

Opening Time 1° circuit [ms 27±3 28±4 (31±3) 27±3 36±5


]

Opening Time 2° circuit [ms 27±3 28±4 (31±3) 27±3 36±5


]

Cycle C-O1 [ms 42±5 40±5 (30±5) 30±8 33±5


]

Cycle C-O2 [ms 42±5 40±5 (30±5) 30±8 33±5


]

Phase Discrepancy (Cl) [ms ≤5 ≤ 5 (≤ 5) ≤5 ≤5


]

Phase Discrepancy (OP 1°) [ms ≤ 3,3 ≤ 3,3 (≤ 3,3) ≤ 3,3 ≤ 3,3
]

Phase Discrepancy (OP 2°) [ms ≤ 3,3 ≤ 3,3 (≤ 3,3) ≤ 3,3 ≤ 3,3
]
Value among the parenthesis are referred only for CB type SB6m UNI 145-170kV.
Unconformity Measure Adopted
q None q ........................................
q Opening Time out of tolerance q ........................................
q Closing Time out of tolerance q ........................................
q Phase discrepancy out of tolerance q …....................................
q ........................................ ( See note attached .................)

Business Unit Services Nuova Magrini Galileo – Via Circonvallazione est n° 1 – 24040 Stezzano Bergamo
Report of :
O Erection
O Testing
Transmission & Distribution
Circuit Breaker Type SB6m SB6 72
Mod. 100 BUS Ed. 3 Eng Pag.5 di 6

12 q Functional Test

q Absorbment heater and ant condensation Heater (A)


Rated Value Measure Value
See Schematic Diagram
Heater resistance Control Cubical [A]

Ant condensation heater Control Cubical [A]

Heater resistance operating mechanism/s [A]

Ant condesation Heater Operating mechanism/i [A]

q Control of Auxiliary Contact


q Check segalization and locks

Unconformity Measure Adopted


q None q Wiring modification
q Wiring not corresponding to schematic diagram q Replaced aux components
q Aux component not corrisponding q ........................................
q Missing aux conponents q ........................................
q Foulty Aux conponents q ........................................
q ........................................ q ........................................
(See Note Attached .................)

13 q Contact resistance mesurament


Valore di Valore Misurato
Riferimento R S T
POLE SB6m 145-170 kV [µΩ] 39±3 Chamber AF8
32±5 Chamber TSB e Uni
POLE SB6m 245 kV [µΩ] 35±5
POLOE SB6 72 [µΩ] 23±6
POLE+CLEMPS [µΩ] Pole +20

CONCLUSIONS
q The control have been performed successfully and the Circuit Breaker can be energized
q The defect found have been eliminated the Circuit Breaker can be energized.
q For The completation of the circuit Breaker Following works must be done :
Note: ......................................................................................................................................
................................................................................................................................................
Business Unit Services Nuova Magrini Galileo – Via Circonvallazione est n° 1 – 24040 Stezzano Bergamo
Report of O Erection :
O Testing
Transmission & Distribution
Circuit Breaker Type SB6m SB6 72
Mod. 100 BUS Ed. 3 Eng Pag.6 di 6

................................................................................................................................................
................................................................................................................................................
................................................................................................................................................

q Anyhow the Circuit Breaker can be energized.


q The circuit breaker has not completely inspected and therefore cannot energized..
q The circuit breaker shows major defects and cannot be energized.
q ................................................................................................................................................
Has been felled a report of faulty/ Defect q No q Yes N° ..............
The Circuit Breaker has been put in service q Yes (in date ............) q No
Date Name : Signature of Operator
For Client
....................................................................................................................

Business Unit Services Nuova Magrini Galileo – Via Circonvallazione est n° 1 – 24040 Stezzano Bergamo