Q2722411 The Roof which slopes in two directions so that the end formed by the intersection of slopes is a vertical triangle, is
A) Hip roof
B) Gambrel roof
C) Gable roof
D) Shed roof
_____________________________________________________________
Q2722566 For a steel construction as per CPWD specifications, Rivets shall be made from rivet bars of mild steel according to which of the following IS Codes?
A) IS 1148
B) IS 228
C) IS 814
D) IS 1367
n
tio
_____________________________________________________________
nc
Ju
Q2722506 The sewer pipes usually have to be designed and checked for
il
iv
C
Q2722463 The members of a pin-jointed truss are usually subjected to bending when
Q2722592 Extra widening refers to the additional width of carriageway that is required on a curved section of a road over
and above that required on a straight alignment.In this regard, the additional width required for a vehicle taking a horizontal curve is known as
Score Obtained : 1.0
A) Mechanical Widening
B) Motor Widening
C) Psychological Widening
D) Physical Widening
_____________________________________________________________
Q2722598 Match the following different Gauges adopted in India in List I with their corresponding Widths in List II.
Score Obtained : 1.0
_____________________________________________________________
Q2722409 Which of the following options is a type of Reinforced Concrete Slab directly supported on columns without the use of beams?
A) Flat slab
B) Block slab
C) Tiled slab
D) Ribbed slab
_____________________________________________________________
Q2722660 The total force on a curved surface submerged in liquid is the resultant of horizontal and vertical forces. In this regard, which force will be equal to the
total pressure force on the projected area of the curved surface on the vertical plane?
Score Obtained : 1.0
_____________________________________________________________
il
iv
C
Q2722612 The irrigation capacity of a unit of water is usually known as Duty. In this regards, Duty on capacity is also called as
A) outlet duty
B) capacity coefficient
C) quality duty
D) full supply coefficient
_____________________________________________________________
Q2722438 Which of the following general guidelines is INCORRECT while planning a Staircase for a building?
A) The respective dimensions of tread and riser for all the parallel steps should be the same in consecutive floor of a building
B) The minimum vertical headroom above any step should be 2 m
Q2722722 Find the hypotenusal allowance per chain of 30 m length, if the slope is 1 in 4. (Given: value of 1/cosθ = 1.03077)
A) 0.34 m
B) 0.30 m
C) 0.16 m
D) 0.92 m
_____________________________________________________________
Q2744218 Normally, shortening of a project duration results in which of the following options?
Score Obtained : 1.0
Q2721608 Which of the following options is a raw material used in the manufacture of cement, that is responsible for the grey color of OPC (Ordinary Portland
Cement)?
Score Obtained : 1.0
A) Silica
B) Iron oxide
C) Aluminium oxide
D) Sulphur trioxide
_____________________________________________________________
Q2722646 Which of the following options is NOT a type of dam classified on the basis of function?
A) Diversion Dam
B) Buttress Dam
C) Storage Dam
D) Flood Control Dam
_____________________________________________________________
Q2722721 The length of a survey line measured with a 20 m chain was found to be 520 m. When the chain was compared with a standard chain it was found to be
10 cm too long. The true length of the line in 'm' is
n
tio
A) 524.2 m
il
iv
B) 522.6 m
C
C) 532 m
D) 517.4 m
_____________________________________________________________
Q2744187 In the figure given below, the network of a small part of a project represents what among the following options?
Q2722396 A horizontal structural member provided above the doors and windows of a building to support load of the wall above it is known as
A) Slab
B) Stair
C) Lintel
D) Masonry
_____________________________________________________________
Q2722507 Read the following statements and choose the CORRECT option with respect to objectives of Sewage collection and disposal.
(i) An efficient sewerage scheme can provide a good sanitary environmental condition of city protecting public health.
(ii) An efficient sewerage scheme can also dispose of all liquid waste generated from community to a proper place to prevent a favorable condition for mosquito
breeding, fly developing or bacteria growing.
Score Obtained : 1.0
Q2722599 Read the following statements and choose the CORRECT option with respect to the components of a railway track.
(i) The Granular bed resting on formation and supporting sleepers over it is known as Ballast.
(ii) The Steel sections laid along two parallel lines over sleepers are known as Rails.
Score Obtained : 1.0
Q2722568 While submitting the tender form, the contractor has to deposit a certain amount called Earnest Money. Usually this deposit can be approximately taken
as
Score Obtained : 1.0
C)
nc
_____________________________________________________________
C
Q2722513 The process of ‘lagooning’ serves which of the following purposes in a wastewater treatment plant?
Q2722596 The reduction in gradient at the horizontal curve because of the additional tractive force required due to curve resistance is known as Grade
Compensation. As per Indian Railway provision, the grade compensation per degree of curve for Broad Gauge track is
A) 0.03%
B) 0.05%
C) 0.04%
D) 0.02%
_____________________________________________________________
Q2721607 Which of the following types of lime usually slakes with difficulty and is mostly used in the constructions near damp places?
A) only (ii)
B) Only (i)
C) All (i), (ii), (iii)
D) Only (iii)
_____________________________________________________________
Q2722535 In long wall and short wall method of a building estimation, if 'l" is the center to center length of wall "d" is the breadth of the wall, then length of long wall
(out to out) is given by
Score Obtained : 1.0
A) l+d
B) l-d
C) l+2d
D) l-2d
_____________________________________________________________
Q2722679 For analysing two-dimensional irrotational flow problems, a flownet is required that is usually drawn using a series of lines. In this regard, a line along
which the velocity potential is constant is known as
Score Obtained : -0.25
A) Equipotential Line
B) Stream Line
C) Streak Line
D) Di-potential Line
_____________________________________________________________
Q2722613 In an open channel flow of fluids, Hydraulic Jump usually occurs when the flow changes from
B)
tio
_____________________________________________________________
Q2722421 Generally, in R.C.C sections, the depth of the neutral axis usually determines the type of section. For an under reinforced section, the actual neutral
axis lies:
Score Obtained : -0.25
Q2722746 Which of the following options is generally considered as the longest of the main survey lines in Chain Surveying?
A) Base Line
B) Oblique Offset
C) Tie Line
D) Check Line
_____________________________________________________________
Q2744234 Which of the following construction equipments is suitable for improving the strength, by decreasing the porosity and increasing the density of Soil?
A) Compaction Equipment
B) Hauling Equipment
C) Hoisting Equipment
D) Excavating Equipment
_____________________________________________________________
Q2744203 Gap graded aggregate is recommended for mixes of low workability since
Q2721622 Granite stone is a widely used building stone, mainly composed of quartz, feldspar and mica. Which of the following options is INCORRECT about this
stone in general?
Score Obtained : 1.0
Q2722631 For a crop, if the optimum depth of kor watering is 19 cms, then the outlet factor (outlet duty) for the crop for a four week period in hectares/cumec, is
n
tio
A) 1720.63 hectares/cumec
il
iv
C
B) 1472.26 hectares/cumec
C) 1273.26 hectares/cumec
D) 1372.26 hectares/cumec
_____________________________________________________________
Q2722729 Surveying is done to take measurements of objects in a horizontal plane for locating objects on the surface of the earth, before any construction of a
structure is started. During this process the fundamental principle that is followed is to work from the
Score Obtained : 1.0
Q2721584 Identify the test to check the presence of poorly weathering calcium carbonate in sandstone as a building material among the given options.
Q2722570 For Stone Masonry or structural concrete, the categories for measurement of items, should be measured separately and the heights should be
described first from foundation to plinth level and then from
Score Obtained : 1.0
_____________________________________________________________
Q2722558 The percentage of estimated cost of building works for sanitary and water works are usually provided as
A) 50% to 60%
B) 22% to 42%
C) 8% to 10 %
D) 4% to 6%
_____________________________________________________________
Q2722617 In weirs and barrages, for the oscillating jump of flows, the Froude number usually lies in the range of
A) 10 to 11
B) 4.6 to 9.0
C) 1 to 2.0
D) 2.5 to 4.5
_____________________________________________________________
n
tio
nc
Ju
il
iv
C
Q2722469
For the pin-jointed truss shown in the figure above, identify whether the truss is
A) Only (i)
B) Only (iii)
C) Only (ii)
D) Both (ii) and (iii)
_____________________________________________________________
Q2722483 When an inclined load is acting on a beam, then the inclined load is resolved into two components namely vertical and horizontal. Read the following
statements and choose the CORRECT option with respect to effects of these components.
A) Offset Rod
B) Ranging Rod
C) Plumb Bob
D) Tape
_____________________________________________________________
Q2722605 A track structure which permits movement of train from one track to another refers to which of the following options?
A) Bearing Plate
B) Anchor
C) Stuart Key
D) Turnout
_____________________________________________________________
Q2744231 The versatile equipment used for clearing the construction sites of debris and rubbish, and very efficient for short haul application up to 100 m is
A) Dumper Truck
B) Tipper
C) Crane
D) Bulldozer
_____________________________________________________________
Q2721591 Read the following statements and choose the CORRECT option.
n
(i) A freshly cut stone carries some natural moisture known as Quarry Sap, which makes it soft and workable.
tio
nc
(ii) To make the stone weather resistant and useful for constructions, a process called dressing is done that removes the Quarry Sap from the stone.
Ju
il
iv
C
A) 1 to 1.5 kg
B) 7 to 7.5 kg
C) 5 to 5.5 kg
D) 3 to 3.5 kg
_____________________________________________________________
Q2726549 Read the following statements and choose the CORRECT option with respect to the precautions taken against cavitation.
(i) The pressure of the flowing liquid in any part of the hydraulic system should be above its vapour pressure.
(ii) The cavitation resistant materials such as aluminium-bronze and stainless steel should be used for Centrifugal Pumps or components of the hydraulic
system.
Score Obtained : -0.25
Q2722644 The ratio of the area irrigated in the Rabi season to the area irrigated in the Kharif season is known as
A) Crop Ratio
B) Irrigated Ratio
C) Season Ratio
D) Overlap Ratio
_____________________________________________________________
Q2722424 If in a reinforced concrete column the cross sectional area of a steel bar is As and that of concrete is Ac, then the equivalent area of the section in
terms of concrete is expressed as (Given m= modular ratio)
Score Obtained : 1.0
A) As -mAc
B) As +mAc
C) Ac-mAs
D) Ac+mAs
_____________________________________________________________
n
tio
Q2722429 In a RCC column, as per IS 456: 2000, the maximum pitch of the lateral ties (transverse reinforcement) should be equal to what among the following
nc
options?
Ju
il
(ii) sixteen times the smallest diameter of the longitudinal reinforcement bar to be tied.
C
Q2722745 Which of the following options is NOT an example of Instrumental errors in Plane Table Surveying?
Q2744191 Read the following statements and choose the CORRECT option with respect to the rules for drawing a network for project management.
(i) Each activity is represented by one and only one arrow in the network.
(iii) For coding alphabets are used for all activities including the dummy activity and numbers for events.
Q2744183 The minimum time in which activity can be finished but leads to the maximum cost of project is known as
A) Standard Time
B) Slow Time
C) Normal Time
D) Crash Time
_____________________________________________________________
Q2722557 The revised estimates are prepared when the expenditure on work exceeds or is likely to exceed the amount of administrative sanction by more than
A) 5%
B) 1.5%
C) 3.5%
D) 0.5%
_____________________________________________________________
Q2722567 With reference to CPWD specifications for formwork in general read the following statements and choose the CORRECT option.
(i) Centering, and shuttering where exceeding 1.5 metre height in one floor shall be measured and paid for separately.
(ii) No deductions from the shuttering due to the openings/ obstructions shall be made if the area of each openings/ obstructions does not exceed 0.1 square
metre.
Score Obtained : 0.0
n
tio
nc
Q2722499 For the conveyance of water various types of valves are used for different purposes in a water distribution system. In this regard, the valve, which
allows the flow of water only in one direction, is known as
Score Obtained : 1.0
A) Sluice valve
B) Butterfly valve
C) Check valve
D) Gate valve
_____________________________________________________________
Q2722476 Which of the following options is the CORRECT statement, according to Lami's Theorem?
A) If three forces acting at a point are in equilibrium, then each force is proportional to the sine of the angle between the other two
B) If three forces acting at a point are in equilibrium, then each force is proportional to the tangent of the angle between the other two
C) The three forces acting at a point kept in equilibrium must be equal to each other
D) If three forces acting at a point are in equilibrium, then each force is proportional to the cosine of the angle between the other two
_____________________________________________________________
Q2722589 The radius of the horizontal curve (R), for a design speed of (V) 100 kmph with the maximum values of (superelevation) e = 0.07 and (coefficient of
friction) f = 0.15, can be calculated using which of the following equations?
Score Obtained : 1.0
A)
B)
C)
D)
_____________________________________________________________
Q2744204 An aggregate is termed as elongated when its greatest dimension (length) is greater than
_____________________________________________________________
Q2726562 Gauge pressure is usually defined as a pressure which is measured using Atmospheric Pressure as Datum. Gauge pressure at a point in a fluid is
equal to
Score Obtained : 1.0
n
tio
_____________________________________________________________
Q2722677 The depth of the centre of pressure on a vertical rectangular gate (4 m wide, 3 m deep) with water up to top surface, is
A) 1.5 m
B) 1.0 m
C) 2.5 m
D) 2.0 m
_____________________________________________________________
Q2722447 Read the following statements and choose the CORRECT option with regards to Splicing of reinforcement bars.
(i) For the constructional requirements at site, Splicing of reinforcing bars is done that transfers the axial force from the terminating bar to the connecting bar.
(ii) Lap splices should not be used for bars larger than 12 mm and End-bearing splices shall be used only for bars in tension.
Score Obtained : 1.0
Q2722443 In case of a Cantilever beam, as per IS:456-2000, what is the basic value of span to effective depth ratio for spans up to 10 m?
A) 7
B) 20
C) 26
D) 30
_____________________________________________________________
Q2744225 Under which of the following conditions needle scaffolding is usually adopted for construction?
A) When construction work is carried out at very high level in case of high-rise buildings
B) Construction of the lower part of the wall is to be carried out inside a room
C) When minor repairs or painting works are required inside the rooms
D) Enough space is available to provide bracings and ledgers
_____________________________________________________________
Q2744188 In a project network analysis, Forward Pass method is used to determine which aspect of various activities?
Q2721600 Select the CORRECT sequence of given steps in the manufacturing process of Bricks.
1. Moulding of Bricks
2. Preparation of Brick Earth
3. Burning of Bricks
4. Drying of Bricks
Score Obtained : 1.0
A) 3 - 4 - 1- 2
n
tio
B) 1 - 2 - 4- 3
nc
Ju
C) 4 - 1 - 2- 3
il
D)
iv
2 - 1 - 4- 3
C
_____________________________________________________________
Q2722294 In a certain type of scaffolding the working platform is supported on movable tripods or ladders. This is generally used for work inside the room, such
as paintings, and repairs up to a height of 5m. Identify this type of scaffolding among the following options.
Score Obtained : 0.0
A) Trestle Scaffolding
B) Patented Scaffolding
C) Cantilever Scaffolding
D) Double Scaffolding
_____________________________________________________________
Q2726660 Viscosity is a measure of the reluctance of the fluid to yield to shear when the fluid is in motion. The dimensions of dynamic viscosity and kinematic
viscosity respectively are
A) FL-2T, L2 T-1
B) FL-2T, FL-1
C) FL-1 T-1, L2 T-1
D) L2 T-1, FL-2 T
_____________________________________________________________
Q2722674 During a motion of fluid, the path traced by the fluid can be stream lines, streak lines or path lines. These three may coincide in the case of
A) steady flow
B) turbulent flow only
C) non-uniform flow
D) unsteady flow
_____________________________________________________________
Q2722508 Which of the following options is an example of Sub-surface raw water source?
A) Streams
B) Rivers
C) Infiltration Wells
D) Lakes
_____________________________________________________________
A) Three-Hinged Arch
B) Simply Supported Beam
C) Single Overhanging Beam
D) Fixed Beam
_____________________________________________________________
Q2722437 For determining the strength of a structure, under the limit state of collapse as per IS 456: 2000, the partial safety factors for Concrete and Steel
respectively are
Score Obtained : 1.0
D)
tio
_____________________________________________________________
Ju
il
iv
Q2722736 The revenue chain is 33 feet long and divided into 16 links. It is used for
C
Q2744199 The process of cutting off the excess wet concrete to bring the top surface of a slab to the proper grade and smoothness is known as
A) screeding
B) trowelling
C) floating
D) finishing
_____________________________________________________________
Q2744184 If to, tp and tm are optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time te of the activity will be one sixth of
A) (tm +3to+tp)
B) (3to+ tm + tp)
C) (to+4tm +tp)
D) (tm +4to+tp)
_____________________________________________________________
Q2722404 As a general rule in India, the relation between height and width of a Door is given as:
Q2722654 A rectangular plane surface that lies in a vertical plane in water is 2 m wide and 3 m deep. Find the Total pressure if the upper edge is horizontal and 2
m below the free water surface.
Score Obtained : 1.0
A) 106.01 kN
B) 206.01 kN
C) 306.01 kN
D) 406.01 kN
_____________________________________________________________
_____________________________________________________________
Q2722440 The size of the fillet weld used as connection in steel structures is specified by
D)
C
_____________________________________________________________
Q2722595 Standard gauge is the most widely used gauge in the World, for which the width is equal to
A) 1435 mm
B) 1676 mm
C) 1365 mm
D) 1525 mm
_____________________________________________________________
Q2744219 In CPM network analysis of a project, the disconnection of an activity before the completion of all activities in a network diagram is known as
A) Mathematical error
B) Redunancy error
C) Dangling error
D) Looping error
_____________________________________________________________
A) The bearing pressure at the base of foundation can exceed the allowable soil pressure
B) It prevents the differential settlement of a structure
C) It transfers the load to the column directly
D) The foundations of residential building take the load of the Slab alone from the superstructure above it
_____________________________________________________________
Q2722288 Given below are statements with respect to the components of a Staircase in general.
(a) A vertical member is placed at the ends of flights in a staircase to connect the ends of the Strings and Handrails.
(b) A vertical member of wood or metal usually supports the Handrail in a Staircase.
A) Statement (a) refers to -->> Nosing and Statement (b) refers to -->> Soffit
B) Statement (a) refers to -->> Soffit and Statement (b) refers to -->> Nosing
C) Statement (a) refers to -->> Baluster and Statement (b) refers to -->> Newel Post
D) Statement (a) refers to -->> Newel Post and Statement (b) refers to -->> Baluster
_____________________________________________________________
Q2722562 The ground for the formation level of a Highway construction is of uniform gradient with longitudinal slope. Here the quantity of earthwork can be
calculated using which of the following options?
A) Only a and c
B) Only c
C) Only b
D) All a, b and c
_____________________________________________________________
Q2722547 As per the General Building Requirements in India, the horizontal distance of a building site from High voltage lines upto and including 11,000 volts
should be atleast
n
A) 0.9 m
il
B) 0.5 m
iv
C
C) 1.2 m
D) 0.2 m
_____________________________________________________________
Q2722498 The water is filtered through the beds of fine granular material, such as sand for removing or reducing impurities in water through the process of
Filtration. The Rate of filtration (Litres/hour/m2) for Rapid Sand Filter is generally in the range of
Score Obtained : 1.0
A) 10 to 100
B) 8000 to 10000
C) 3000 to 6000
D) 150 to 2000
_____________________________________________________________
Q2722520 A valve that is used to completely shut off fluid flow or, in the fully open position, provide full flow in a pipeline and generally NOT suitable for throttling
applications, is known as
Score Obtained : 1.0
A) Check valve
B) Sluice valve
C) Gate valve
D) Washout valve
_____________________________________________________________
Q2722489 Read the following statements and choose the CORRECT option with respect to the forces in a member of a Truss in general.
i. The force in a member will be Compressive if the member pushes the joint to which it is connected.
ii. The force in a member will be Tensile if the member pulls the joint to which it is connected.
Q2722492 Read the following statements and choose the CORRECT option with respect to Moment Distribution Method of analysis of structures.
i. Moment Distribution Method of analysis is a convenient way to analyze only the determinate beams and frames.
ii. In this method, the distributed moments in the ends of members meeting at a joint cause moments in the other ends, which are assumed to be fixed.
These induced moments at the other ends are called carry-over moments.
Q2722587 With regards to the shape test of aggregates for pavement construction, the elongation index of an aggregate is defined as the percentage by weight
of particles whose greatest dimension (length) is
Score Obtained : 1.0
Q2722579 As per IRC recommendations, on a National Highway in rolling terrain, the ruling design speed should be
nc
Ju
A) 150 kmph
B) 70 kmph
C) 60 kmph
D) 80 kmph
_____________________________________________________________
Q2744202 The process of mixing some mortar in the mixer at the beginning of the first batch concrete mixing is called as
A) accelerating
B) borrowing
C) buttering
D) initiating
_____________________________________________________________
Q2744237 The verticle plank which remains in contact with side of the trench and directly resist pressure from the side of a trench during excavation and
trenching, is called as
Score Obtained : 0.0
A) Bracings
B) Wale
C) Sheathing
D) Ledgers
_____________________________________________________________
Q2721609 According to ASTM standards, Coarse aggregates are identified when they are retained on
A) 4.75 mm sieve
B) 6 mm sieve
C) 10 mm sieve
D) 8.75 mm sieve
_____________________________________________________________
Q2722287 Generally in a brickwork, the type of bond in which all bricks are laid as headers on the faces of the wall is known as
A) Stretcher Bond
B) Header Bond
C) Flemish Bond
D) English Bond
_____________________________________________________________
Q2722643 If base period for a particular crop is 50 days and the duty of the canal is 500 hectares per cumec, then the depth of water will be
A) 8.64 cm
B) 0.864 cm
C) 864 cm
D) 86.4 cm
_____________________________________________________________
Q2722521 The maximum daily demand at a water purification plant has been estimated as 12 million litres per day. Find the length of the sedimentation tank
required if a detention period of 5 hours and the velocity of flow of 20 cm/minute is assumed.
Score Obtained : 0.0
A) 50 m
B) 70 m
n
tio
C) 60 m
nc
D) 80 m
Ju
il
_____________________________________________________________
iv
C
Q2722446 As per IS:456-2000, the lap length including anchorage value of hooks for direct tension in bars shall be (Given: Ld = Development Length of bars
and Φ is the nominal diameter of the bar.)
Q2722738 A line on a map joining points of equal elevation is a contour line. These lines intersect the ridge lines usually at what angle?
A) 30°
B) 45°
C) 90°
D) 0°
_____________________________________________________________
Q2744189 Which of the following options is a project planning technique that considers the uncertainty factor of various activities?
A) CPM
B) Neither CPM nor PERT
C) Both CPM and PERT
D) PERT
_____________________________________________________________
C
iv
il
Ju
nc
tio
n