3/30/2018 Critical success factors across the project life cycle
Critical success factors across the project life cycle
definitions and measurement techniques
ARTICLE ǀ Skill Development ǀ June 1988
Project Management Journal
Pinto, Jeffrey K. | Slevin, Dennis P.
How to cite this article:
Pinto, J. K. & Slevin, D. P. (1988). Critical success factors across the project life cycle: de nitions and measurement techniques. Project
Management Journal, 19(3), 67 75.
Reprints and Permissions
Dennis P. Slevin, Graduate School of Business, University of Pittsburgh
Introduction
Attempts to understand the process of project management, involving the successful implementation of projects in organizations, represent a
problem of continual concern and interest to both researchers and project managers. Much has been written to assist project managers in their
efforts to more effectively manage and guide a variety of organizational projects. Both empirical and conceptual approaches have been applied
to the study of the project implementation process. As a result, a wide range of critical factors or project dynamics have been uncovered which
have been found to signi cantly contribute to project success (e.g., suf cient available resources or top management support). While these
ndings have had an important impact on project managers, helping them to better manage their projects to completion, few researchers have
attempted to determine how the importance of these critical factors may uctuate as a result of changes in the life cycle of the project. In
other words, it may be likely that some critical factors become more or less critical to project success depending upon the phase in its life cycle
the project currently occupies.
The purpose of this article is to report on the results of a recent study that was conducted in an effort to test the importance of those factors
that have long been believed to be critical to project success. Over 600 questionnaires were mailed to project managers and members of the
Project Management Institute (PMI). The response rate and interest level generated from this study have been quite strong; over 400
questionnaires were returned, indicating a response rate in excess of 71%.
Speci cally, this study resulted in two important ndings:
1) The validation of a set of factors previously discovered as critical to project implementation success [1].
2) The determination that these factors are not of equal and stable importance over the life of the project. Rather, different sets of these factors
become more critical to project success at different phases in the project life cycle.
The results of this study have important implications for project managers and researchers in the project management eld. First, a set of ten
critical success factors were determined that improve the prediction of project implementation success. Second, this study demonstrates that it
is insuf cient to simply ask the question, Which factors are most important to project success? It will be shown, using project life cycles, that
the relative importance of various critical factors are subject to dramatic changes at different phases in the project implementation process.
Finally, this research offers support for use of the Project Implementation Pro le (PIP) [1] as an instrument to assess project performance and
predict project success based on responses across the ten critical factors.
Project Critical Success Factors
Research in the area of critical success factors in project management and implementation has been conducted for several years. Many examples
exist of both empirical studies aimed at determining critical success factors [2] [3] as well as conceptual research approaches [4] [5] [6] which
have developed theoretical frameworks or models listing several of those factors seen as critical to project success. As a result of the wide range
of work on project critical success factors, it appears that consensus is beginning to develop on identifying those areas or dynamics critical for
project implementation success.
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 1/11
3/30/2018 Critical success factors across the project life cycle
Recent work by Slevin and Pinto [1] [7] has led to both the development of a ten factor model of the project implementation process and an
instrument which may be used to empirically monitor the current state of each of the ten critical factors throughout a project’s life. These ten
characteristics represent those characteristics found to be critical to project implementation success. (For a more in-depth discussion of how
these factors were developed and some of the important considerations included within each of the factors, see [1]). The ten critical success
factors can be brie y de ned:
1. Project mission Initial clarity of goals and general directions.
2. Top management support -Willingness of top management to provide the necessary resources and authority/power for project success.
3. Project schedule/plans A detailed speci cation of the individual action steps required for project implementation.
4. Client consultation Communication, consultation, and active listening to all impacted parties.
5. Personnel Recruitment, selection, and training of the necessary personnel for the project team.
6. Technical tasks Availability of the required technology and expertise to accomplish the speci c technical action steps.
7. Client acceptance The act of selling the nal project to its ultimate intended users.
8. Monitoring and feedback Timely provision of comprehensive control information at each phase in the implementation process.
9. Communication The provision of an appropriate network and necessary data to all key factors in the project implementation.
10. Trouble-shooting Ability to handle unexpected crises and deviations from plan.
In addition to these ten critical success factors, all of which to some degree are within the control of the project team, four additional factors
were included in this study. Both research and interviews with a variety of project managers have suggested the importance of these factors for
project success. These factors represent critical areas or issues that are often considered beyond the control of the project team, but which
nevertheless are felt to have an important impact on project success. The four factors are labeled as external to the project implementation
process and can be de ned as:
1. Characteristics of the project team leader Competence of the project leader (administratively, interpersonally, and technically) and the
amount of authority available to perform his/her duties.
2. Power and politics The degree of political activity within the organization and perception of the project as furthering an organization
member’s self interests.
3. Environmental events The likelihood of external organizational or environmental factors impacting on the operations of the project team,
either positively or negatively.
4. Urgency The perception of the importance of the project or the need to implement the project as soon as possible.
The Project Life Cycle
The use of life cycles in project management is not a new concept to most project managers. Much has been written on the use of life cycle
analysis and its impact on project management [8] [9]. Life cycles have been used to explain the impact of a variety of behavioral issues on the
project organization. For example, studies have examined propensity toward con ict and effective con ict management styles at different
phases in the life cycle [10]. Other research has argued that leadership styles of the project manager must change at different phases in the
project life cycle [8], These and other authors have presented a strong case for the inclusion of the project life cycle phase into investigations of
the dynamics of the project implementation process.
In this study, a four-phase life cycle has been employed (see Figure 1). The initial phase, Conceptualization, refers to the point at which a strategic
need has been recognized by top management. Typically, preliminary goals and alternatives for the project are established at this point, along
with exploring the availability of the means (resources) to accomplish these goals. Conceptualization often involves an initial feasibility decision
requiring that management answer questions such as:
What is the problem?
Will the development of a project solve that problem?
What are the speci c goals of the project?
Do we have the resources to create and support the project?
The second phase in the project life cycle is referred to as the Planning phase. In this phase, once top management has given the Go ahead to
launch the project, a more formalized set of plans to accomplish the initially developed goals are established. Some of the well-known planning
functions are determining the availability of needed resources, budgeting, and the allocation of speci c tasks.
The third phase is labeled Execution. It is during the execution phase that the actual work of the project is performed. Suf cient materials and
resources are procured and transformed into the intended project result. During this, phase, performance capabilities are continually tested to
ensure that the project performs as intended.
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 2/11
3/30/2018 Critical success factors across the project life cycle
The fourth and nal phase in the project life cycle is called the Termination phase. Once the project has been completed, the project team is
often disbanded and personnel are reassigned to other duties, resources that were secured for the project are now released back to the parent
organization, and the project is transferred to its intended users.
Figure 1.Phases in the Project Life Cycle
(Adams & Barndt, 1978; King & Cleland, 1983)
As Figure 1 shows, in addition to demonstrating the four distinct phases in the project life cycle, the model also speci es the level of
organizational effort (resources, man-hours, and so forth) necessary to adequately perform the tasks associated with each project phase. As one
would expect, during the early Conceptualization and Planning phases, resource and effort requirement are often minimal, increasing rapidly
during late Planning and Execution, before diminishing again in the project’s Termination. As a result, the concept of project life cycles is useful
for project managers, not only through distinguishing among distinct phases in the project’s life, but also through indicating likely resource
requirements associated with each project phase.
This study was conducted to show the added impact that project life cycles can have on critical success factors. It was argued that different sets
of these factors should be found to be more or less critical to project success depending upon the current phase in the project life cycle. The
focus of our research was to test this idea.
The Study
The Data Sample
Questionnaires were mailed to over 600 members of the Project Management Institute (PMI) a national organization of project managers. Due
to terminations, retirements, and other reasons, a total of 586 project managers were capable of responding to the questionnaire of which 418
were usable, resulting in a response rate exceeding 71%. This response rate was 3 to 5 times the national norm for mail surveys, indicating the
considerable interest of this topic to project managers.
Three types of questionnaires were randomly mailed to the sample. One questionnaire asked the respondent to think of a successful project in
which they were currently involved or had recently completed. The second questionnaire type asked the subject to consider an unsuccessful
project with which they had experience. The third type of questionnaire did not specify the type of project for them to consider. Three types of
questionnaires were used to ensure a wide sample of projects, both in terms of phase of project completion and nal outcome (successes and
failures).
Table 1 shows the distribution of projects in the sample. While there was a wide cross-section of projects represented, construction projects
made up 44% of the sample. The industries represented in the sample were from the manufacturing as well as service sectors and included a
mixture from the public and private domains. Projects included in the sample ranged from a $5,000 test study conducted in a small rm to a $2
billion dollar government funded research project.
Table 1
Frequency Distributions on Type of Project
Type Absolute Frequency Relative Frequency Cumulative Frequency
Construction 185 44.3% 44.3%
Hardware, Equipment, or Appliance Development 40 9.6% 53.9%
Food, Drug, or Soft Goods Development 58 13.9% 67.8%
New or Improved Software Development 61 14.6% 82.4%
Service or Test 12 2.9% 85.3%
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 3/11
3/30/2018 Critical success factors across the project life cycle
Study 13 3.1% 88.4%
Departmental Reorganization or Move to a New Facility 17 4.1% 92.5%
Miscellaneous 32 7.5% 100.0%
Total 418
Table 2 shows the breakdown of respondents to the questionnaire by the position they occupy. Not surprisingly, the majority (50.2%) of those
responding to the questionnaire were project managers. However, a signi cant percentage of responses came from other members of the project
team, including administrators, technical personnel, and others. This diversity of respondents indicates that the data sample represented a wide
range of perspectives.
Before completing the questionnaire, each respondent was asked to think of a project in which they were involved that was currently under way
or recently completed. This project was to be their frame of reference while completing the questionnaire. The four phase project life cycle
model discussed earlier was included in the questionnaire and was used to identify the current phase of each project.
Table 2
Frequency Distributions on Position of Respondent
Role Absolute Frequency Relative Frequency Cumulative Frequency
Project manager 210 50.2% 50.2%
Manager on Project Team 55 13.2% 63.4%
Project Team Member Technical 25 5.9% 69.3%
Project Team Member Administrative 57 13.6% 82.9%
Member of Business Unit Affected by the Project 11 2.6% 85.5%
Other 60 14.5% 100.0%
Total 418
Table 3 shows the breakdown of responses by project phase. As can be seen, 36 (8.6%) of the responses were based on projects in the
Conceptual phase. 73 (17.5%) of the projects reported on were in the Planning phase, 202 (48.3%) of the projects were in the Execution phase
and 107 (25.6%) of the projects were undergoing project Termination.
Questionaire
The Project Implementation Pro le (PIP) was used to identify critica success factors and subsequent factor scores over the project life cycle. The
PIP requires participants to indicate their level of agreement on a 7-point scale to a series of 72 questions covering the 10 critical factors and the
4 additional external factors felt to be related to project implementation success. The 7-point scale required responses ranging from Strongly
Agree to Strongly Disagree for each item.
Project Success
The PIP’s measure of project success is an average of 13 items comprising assessments of adherence to budget and schedule, project performance
capabilities, technical validity, organizational validity, and organizational effectiveness. The measure of success was speci cally constructed to be
multidimensional in an effort to include, as nearly as possible, all aspects associated with project implementation success.
Traditionally, there has been general agreement that any assessment of project success must include measures of budgetary and schedule
adherence, as well as the con rmation of performance capabilities. In addition, it has been suggested that in order for the project to be
considered successful, it must be technically valid. In other words, the project must work and it must be a technically correct solution to the
problem for which the project was initiated [11]. Further, the project must be organizationally valid. In other words, the project to be
implemented must t the organization or clients for whom it is intended, and they must make use of it. Finally, the project to be implemented
should result in some form of improved level of organizational effectiveness or decision making [12]. The client’s organization should be assessed
as being more effective as a result of the implemented project. To summarize, project success was measured based on the following
characteristics:
Adherence to Budget
Adherence to Schedule
Level of Performance Achieved
Technical Validity
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 4/11
3/30/2018 Critical success factors across the project life cycle
Organizational Validity
Organizational Effectiveness
Results
As previously stated, the rst objective of this study was to provide empirical evidence that the set of ten critical success factors were
signi cantly related to project success. In addition to the ten critical factors, the four external factors (Characteristics of the Project Team Leader,
Power and Politics, etc.) were also evaluated to determine if they had any ability to predict project success.
Table 3
Frequency Distributions on Phase of Project
Phase Absolute Frequency Relative Frequency Cumulative Frequency
Conceptual 36 8.6% 8.6%
Planning 73 17.5% 26.1%
Execution 202 48.3% 74.4%
Termination 107 25.6% 100.0%
Total 418
Table 4
Regression Results of Ability of
Each Critical Factor to Predict Project Success
Variable Beta T Sig.T
Project Mission .72 19.9 p<.01
Top Management Support .32 10.6 p<.01
Schedule/plans .32 10.92 p<.01
Client Consultation .39 11.86 p<.01
Personnel .31 10.54 p<.01
Technical Tasks .43 11.25 p<.01
Client Acceptance .39 11.46 p<.01
Monitoring and Feedback .29 10.89 p<.01
Communication .32 10.38 p<.01
Trouble-shooting .35 11.15 p<.01
Leadership .43 12.44 p<.01
Power and Politics .11 3.71 p<.01
Environmental Effects .15 4.52 p<.01
Urgency .32 7.18 p<.01
The ability of each critical factor in predicting project implementation success is shown in Table 4. Each of the critical factors was tested
independently against project success. As can be seen from Table 4, all 14 of the critical factors which were used in the study were shown to be
signi cantly related to project success. Both the Beta value and the Tstatistic represent the strength of the relationship which exists between
each critical factor and project success. As a result, one of the rst conclusions from this study is that the 10 critical success factors and the 4
external factors were shown to each be predictive of project success. Further, the table indicates that the most signi cant relationships (most
important individual factors) among the variables were between Success and Project Mission, Characteristics of the Project Team Leader,
Technical Tasks, Client Consultation, and Client Acceptance.
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 5/11
3/30/2018 Critical success factors across the project life cycle
Table 5
Key Factors for Each Phase of the Project Life
Cycle From Stepwise Regression Analysis
Stage of Project Life Cycle Number of Projects Factors Adjusted ΔR2 Adjusted R2 Sig. R2
Conceptual .36 Mission .57 .57 p<.01
Client Consultation .07 .64 p<.01
Planning 73 Mission .55 .55 p<.01
Top Mgmt.Support .06 .61 p<.01
Client Acceptance .02 .63 p<.01
Urgency .02 .65 p<.01
Execution 202 Mission .50 .50 p<.01
Leadership .06 .56 p<.01
Trouble-shooting .05 .61 p<.01
Schedule/Plans .02 .63 p<.01
Technical Tasks .01 .65 p<.01
Client Consultation .01 .66 p<.01
Termination 107 Technical Tasks .45 .45 p<.01
Mission .12 .57 p<.01
Client Consultation .03 .60 p<.01
Because a second key purpose of this research was to test the relative stability of the critical factors across the project life cycle, a second
analysis was performed. In this test, the 14 factors were not examined individually. Rather, all 14 variables were tested simultaneously at each of
the four project life cycle phases to determine which of the set were most important at each project phase. For each project phase, a stepwise
regression technique tested all 14 variables and initially selected the single variable that was most important in predicting project success. At the
next step the computer selected the second-most important variable. This process continued until all variables were included, in order of
importance, or until only those factors which were signi cant were included.
Table 5 shows the results of the stepwise regression across the four project life cycle phases. In the Conceptual phase the Project Mission and
Client Consultation were the two key factors related to project success, with an adjusted r-square value of .64. In other words, at the Conceptual
phase in a project, two factors (Project Mission and Client Consultation) are capable of predicting 64% of the causes of project success. In the
Planning Phase, Project Mission, Top Management Support, Client Acceptance, and Urgency were the key factors explaining 65% of the reason
for project success. For the Execution phase, Project Mission, Characteristics of the Project Team Leader, Trouble-shooting, Project
Schedule/Plans, Technical Tasks, and Client Consultation together accounted for 66% of the causes of project success. Finally, at the phase of
project Termination, Technical Tasks, Project Mission, and Client Consultation had an r-square value of .60.
Phase 1: Conceptualization
Project Mission
Client Consultation
Action Implications for the Project Manager:
1. Insist on a clearly speci ed and on-target project mission.
2. Consult with your important clients at the very outset of the project life cycle.
Phase 2: Planning
Project Mission
Top Management Support
Client Acceptance
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 6/11
3/30/2018 Critical success factors across the project life cycle
Urgency
Action Implications for the Project Manager:
1. Continue to re ne and specify the project mission stay on target.
2. Insist on top management support in terms of resources and authority.
3. Go beyond client consultation and address the important issue of client acceptance. What actions can we take to help sell our ideas to the
clients?
4. Create a perceived sense of urgency for the project in the parent organization and among the project team.
Phase 3: Execution
Project Mission
Characteristics of the Project Team Leader
Trouble-shooting
Project Schedule/Plans
Technical Tasks
Client Consultation
Action Implications for the Project Manager:
1. Continue to look back to the Project Mission for direction. Make sure you and your project team are staying on target.
2. Use good management skills as the Project Leader. Although these characteristics may seem to be somewhat inherent and unchangeable, the
use of effective management training and appropriate management tools can enhance the characteristics and skills of any project manager.
3. Start the trouble-shooting process at this phase. Now that you have actually started the project execution, you must have procedures for
detecting and correcting the errors that crop up.
4. Develop and adhere to a comprehensive schedule and/or set of plans for the implementation. You might even consider the use of project
management software at this phase to keep all of the items in control.
5. Initiate the execution of the technical tasks. Make sure that you have quality technical experts and adequate technology to support the
project.
6. Don’t forget the client. Maintain an effective two-way communication ow with the user.
Phase 4: Termination
Technical Tasks
Project Mission
Client Consultation
Action Implications for the Project Manager:
1. As you terminate the project, make sure that the technical system is ne-tuned and working at maximum effectiveness.
2. Even at this phase, don’t forget the project mission (why this project was developed). Are there any changes that you could make in this nal
phase to make sure that the project stays on target?
3. Stay close to the client and try to make sure that you have a satis ed project user before you leave for good.
Implications for Project Managers
As one can see, a general pattern emerges from these research results that would be useful for the project manager over a broad range of
projects.
1. Don’t forget the project mission The rst nding relates to the importance of the factor Project Mission across all four stages in the project
life cycle. Intuitively, it is not surprising that the mission should have an important impact on project success, particularly early in the project’s
life. What is surprising, however, is that a focus on the Project Mission continues to remain of great importance throughout the implementation
of the project. This result suggests the need to keep the goals and purposes of the project being implemented always in the forefront. Further,
the purpose of and goals for the project need to be made apparent not only to a few select members of the project team, but to all project team
members. A large proportion of those responding to this study were not project managers, but team members of varying levels. These
respondents also indicated the importance of Project Mission at all life cycle phases. An effective management strategy is to continually
emphasize the purpose of the project to all team members, keeping the goals in focus throughout the life of the project.
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 7/11
3/30/2018 Critical success factors across the project life cycle
2. Client consultation: Keep the channels open A second interesting nding is the importance of interaction with the project’s clients
throughout the life of the project. Client consultation a communicating, listening, and feedback activity was very important at three of the
four life cycle stages: Conceptualization, Execution, and Termination. Client Acceptance a selling function was of prime importance during
the Planning phase. A possible conclusion drawn from these results would be that the project team must rst listen and ask questions, then sell
their ideas, project capabilities, and time frame to completion, then engage in continuous two-way communication throughout the life of the
project. As was implied previously, these results suggest that it would be a mistake for the project team to initially talk to clients and
subsequently sever this connection to go off and develop the project on their own. As stated above, it is important to keep the channels open.
3. Be meticulous about schedules As the strategic plan for the project is implemented, it is essential that the effective project manager put
together a schedule and/or set of plans for the project and use it on a regular basis. The schedule represents a highly important and necessary
element to successful project execution. During the actual work of the project, the schedule often functions as the sole feedback mechanism to
many project members in assessing how the project is proceeding. As a result, proper attention to schedules represents an important
consideration for both project leaders and team members, not only in terms of actual time frame to completion, but also as a periodic check-list
for feedback on project performance.
4. Make sure we have the technical means to succeed Another result of this study is the determination that Technical Tasks are important for
project success during the Execution and Termination phases of the project. Technical Tasks argues for adequate technology and competent
personnel to assist in the technical action steps of the implementation. This result, along with the nding that Troubleshooting and
Schedule/Plans were critical during the Execution phase suggests that tactical issues become more important to project success as the project
progresses through its life cycle. Tactics implies those operational activities that are performed in support of strategic plans. While this result
appears to be obvious, it needs to be considered in light of the fact that Project Mission, a strategy/planning activity, is critical throughout the
project’s life. Project strategy and tactics must work hand-in-hand, particularly during Execution and Termination, in order to ensure greater
likelihood of success.
5. Project leadership: It CAN make a difference Much has been written about the important positive effects a competent leader can have on
his/her project team and the resulting success of the project. While the ndings support these conclusions, they further suggest that project
leadership becomes most important during the actual work, or execution of the project. At this point, the various competencies of the project
team leader (technical, administrative, and interpersonal) are most crucial for project success. While the project team leader will assume various
roles throughout the project development (motivator, con ict resolver, visionary, etc.), project team leadership can make its presence felt
most during the project’s Execution.
6. Make the project important A last nding from the study was the positive impact of perceived urgency or importance on project success,
particularly during the Planning phase. In one sense, it seems obvious to tell project managers that important or urgent projects have a better
chance for success, but the point bears emphasizing. Not all projects run through an organization are seen as urgent, or even necessary. In spite
of the pronouncements of project managers or top management, in many instances project team members perceive their project as routine, dull,
or pointless. As the results point out, the perception of a project as important or unique can have strong impact on its likelihood for success. This
nding is particularly true during the Planning phase of the project life cycle. An implication for project managers would be to attempt to instill
within the project team a feeling that what they are engaged in has importance for them as a project team, for the parent organization, and for
the clients for whom the project is intended.
Figure 2. Summary of Study Results: Critical Factors at Each Project Phase
Conclusions
The purpose of this article has been to report on some of the important ndings resulting from a large-scale study investigating the role of
speci c critical factors in project implementation success. The results support much of the theoretical and empirical work that have been done to
date on the role these factors play in project success. The importance of several of these critical factors to project success should not be
intuitively surprising to many project managers. However, it was proven through this analysis that it is insuf cient to simply ask the question,
What factors are most important to project success? The answer was shown to depend on the phase of the life cycle in which the project
resides. As a result, project managers are presented with empirical evidence suggesting that attention be paid to speci c sets of critical factors at
each of the four project life cycle phases. These factors were shown to have a powerful impact on project success, in some cases accounting for
up to 66% of the causes of successful project implementation.
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 8/11
3/30/2018 Critical success factors across the project life cycle
Successful project implementation can be a dif cult, complex task. The project manager is continually bombarded with a wide variety of input
and information from project team members, the parent organization, and clients. The practical bene t of the research that has been reported in
this article has been to help in clarifying not only the roles that a successful project manager must undertake, but also those duties which have
been shown to contribute to successful project implementation. It is hoped that through focusing attention on these roles and critical factors,
the project manager will be in a better position to actively monitor and steer his/her future projects toward a successful conclusion.
References
1. Slevin, D.P. &l Pinto, J.K., The Project Implementation Pro le: New Tool for Project Managers. Project Management Journal, 1986, XVII(4), 57-
70.
2. Baker, B.N., Murphy, D.C. & Fisher, D., Factors Affecting Project Success, in Project Management Handbook, ed., D.I. Cleland & W.R. King. New
York: Van Nostrand Reinhold Co., 1983, 669-685.
3. Thamhain, H.J. & Wilemon, D.I., Criteria For Controlling Projects According to Plan. Project Management Journal, 1986, vol. XVII, no. 3, 75-81.
4. Cleland, D.I. & King, W.R. Systems Analysis and Project Management. New York: McGraw-Hill Inc., 1983.
5. Archibald, R.D. Managing High-Technology Programs and Projects. New York: John Wiley and Sons, 1976.
6. Locke, D. Project Management. New York: St. Martins Press, 1984.
7. Pinto, J.K. & Slevin, D.P., Critical Factors in Successful Project Implementation. IEEE Transactions on Engineering Management, 1987, EM-34(1),
22-27.
8. Adams, J.R. & Barndt, S.E., Behavioral Implications of the Project Life Cycle. In Project Management Handbook, ed. D.I. Cleland & W.R. King.
New York: Van Nostrand Reinhold Co., 1983, 222-245.
9. King, W.R. & Cleland, D.I., Life Cycle Management. In Project Management Handbook, ed. D.I. Cleland & W.R. King. New York: Van Nostrand
Reinhold Co., 1983, 209-221.
10. Thamhain, H.J. & Wilemon, D.L., Con ict Management in Project Life Cycles. Sloan Management Review, 17, 1975, 31-50.
11. Schultz, R.L. & Slevin, D.P., Implementation and Management Innovation. In Implementing Operations Research and Management Science,
ed. R.L. Schultz & D.P. Slevin. New York: Elsevier, 1975, 3-22.
12. Schultz, R.L. & Slevin, D.P., Introduction: The Implementation Problem. In The Implementation of Management Science, ed. R. Doktor, R.L.
Schultz D.P. Slevin. Amsterdam: North-Holland, 1979, 1-15.
SAN FRANCISCO
is full of surprises. It’s a place where dragons, bocce ball players, sidewalk stringed quartets, kite iers and caligraphy street signs are part of the
everyday land’ scape... where you can scale homegrown alps in antique cable cars, walk across the Paci c (on the Gold’ en Gate Bridge),
serpentine down a street that looks like a slalom run and island-hop by ferry. It’s a city for all seasons with mild winters, springlike summers,
views that rival Rio’s and stores on a par with Paris’.
And it’s a terrible place to diet.
Jeffrey K. Pinto is Assistant Professor of Organization Theory in the University of Cincinnati’s Management Department. He received both his
Ph.D. and M.B.A. degrees in Organization Theory from the University of Pittsburgh and holds a B.A. in History and B.S. in Business Administration
from the University of Maryland. Professor Pinto has been published in a variety of professional journals in the areas of project management,
implementation, research methodology, and leadership and motivation. His research interests include the study of project management, and the
processes by which organizations implement innovations and advanced technologies. In addition, Dr. Pinto has had consulting experience with
several Fortune 500 companies.
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 9/11
3/30/2018 Critical success factors across the project life cycle
Dr. Dennis P. Slevin is Associate Professor of Business Administration at the University of Pittsburgh’s Graduate School of Business. Dr. Slevin has
had extensive experience as a line manager, including service as the CEO of four different companies; he presently serves as director of several
corporations and consults widely. He is also the co-editor or author of ve books and publishes in numerous professional journals.
Up against a wall of deadlines and delays, you don’t need a schedule that doesn’t meet spec.
approval is no problem
PMS80 project management software is used and approved by government agencies. Because it’s powerful enough to handle 30,000
activities per project. Flexible enough to look and feel like Lotus” or any other software. Fast enough to run 1,000 tasks in 55 seconds. And
easy enough to schedule, sort and print any report with a single keystroke.
Our timescale arrow diagram is state-of-the-art. Instead of papering a wall with a schedule even your engineers can’t follow, you can put your
entire project on one clear, concise sheet. At a glance you can pinpoint potential problems from start to nish. Nail down the work sequence.
And identify the critical path.
If you’re starting to see why our software gets used and approved on so many successful projects, call today for a free brochure. Or order
our full-feature demo.
PMS80
Software for
Project Management
Success
Pinnell Engineering, Inc.
5441 S.W. Macadam, Suite 208
Portland, OR 97201
(503) 243-2246
MS-DOS and Unix
https://www.pmi.org/learning/library/critical-success-factors-project-life-cycle-2131 10/11
3/30/2018 Critical success factors across the project life cycle
This material has been reproduced with the permission of the copyright owner. Unauthorized reproduction of this material is strictly prohibited.
For permission to reproduce this material, please contact PMI.
Related Content
ARTICLE ǀ Skill Development ǀ 23 March 2018
How to Conquer Certifications
By carefully planning her pursuit of the PMP certi cation, a project professional learned lessons for a
lifetime.
ARTICLE ǀ Team Building , Resource Management , Skill Development ǀ 1 March 2018
PM Network
Remote Support
By Vergini, Sante ǀ There's a gap for remote workers. I discovered it during a recent business process outsourcing implementation
project I managed. Although more than 70 percent of the employees worked from home, none…
ARTICLE ǀ Team Building , Skill Development ǀ 1 March 2018
PM Network
Out of Office
By Huber, Michael ǀ Many people envision working remotely as a dream and it can be. However, it can be challenging for remote
workers to avoid a sense of isolation and stay engaged. In my six years of working remotely,…
ARTICLE ǀ Skill Development ǀ 9 February 2018
Ready for Tomorrow
Ready for Tomorrow?
Project professionals must future-proof their careers. That means adapting to change and becoming a
strategic thinker.
ARTICLE ǀ Skill Development ǀ 1 February 2018
PM Network
Time for a Shift
By Scott, Lindsay ǀ Project management professional Lindsay Scott answers questions about job hunting and career changes.