Volume-II of IV
Volume-II of IV
N-19535
TRANSCO 400kV OHL Works for Haffar, ICAD 4
Supply Division – Contracts & ICAD 5 (SASN Retirement)
(April 24)
REV.02
CONTENTS
VOLUME 1 OF 4
VOLUME 2 OF 4
VOLUME 3 OF 4
VOLUME 4 OF 4
SECTION IV/1 of VI
Technical Specifications
01. General
S-TR-GEN-CDF (Civil Design Fundamental) (Rev.0-2019) 19
S-TR-GEN-EDF (El Design Fundamental) (Rev.0-2023) 10
S-TR-GEN-GDF (Gen Conditions) (Rev.0-2010) 20
S-TR-GEN-ID (Component Marking) (Rev 3-2009)_AN 40
S-TR-GEN-PSTS Project Schedule Technical Specifications (June
39
2023) with Apendix A
S-TR-GEN-SFL (System Characteristics) (Rev.0-2013) 5
S-TR-GEN-SQA - ANNEX-01-1 (Rev.0-2009) 1
S-TR-GEN-SQA (Safety & Quality) (Rev.4-2009)-TR SR&L
23
Accommodation
S-TR-GEN-STC (Spec Tech Requ's) (Rev.0-2021) 11
Cabinet decision No 13 of 2009-Gen stds Labour Accommodation
26
- English
Transco SSR Summary - Guidance for Contractors v3-010809 8
TR-Project Quality Plan (Rev.0-2007) 8
04. Overhead Transmission Line
S-TR-OHL-AIR (Rev.0-2014) 6
S-TR-OHL-CON (Rev.0-2023) 10
S-TR-OHL-GEN (Rev.0-2009) 10
S-TR-OHL-HW (Rev.0-2018) 11
S-TR-OHL-INS (Rev.0-2018) 10
S-TR-OHL-OPGW (Rev.0-2018) 12
S-TR-OHL-SURV (Rev.0-2018) 6
S-TR-OHL-TOWER (Rev.0-2011) 32
11. Earthing and Corrosion
S-TR-CORR (Rev.0-2021) 18
S-TR-EARTH-GROUND (Rev.0-2009) 22
14. Civil
S-TR-CIVIL-CONCRETE (Rev.0-2018) 16
S-TR-CIVIL-FENCE (Rev.0-2009) 5
S-TR-CIVIL-GEN (Rev.0-2009) 9
S-TR-CIVIL-OHL (Rev.0-2018) 33
S-TR-CIVIL-SITE (Rev.0-2014) 8
S-TR-CIVIL-SOIL (Rev.0-2014) 8
S-TR-CIVIL-SURF (Rev.0-2009) 8
S-TR-CIVIL-WORK (Rev.0-2015) 24
SECTION IV/2 of VI
D-OHL-T-220 (Rev.0-2009) 2
D-OHL-T-400 (Rev.0-2009) 2
D-OHL-CON-T-400 ACSR-AW Cardinal (Rev 0-2015) 2
D-OHL-CON-T-400-220-132-ACSR Dove (Rev.0-2015) 2
D-OHL-CON-T-400-ACSS-AW Dove 14EHSA (Rev.0-2023) 2
D-OHL-INS-220-COMP - Dove Conductor (Rev.0-2009) -40mm
3
per kV
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -40mm
3
per kV
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -45mm
3
per kV
D-OHL-INS-400-Post -COMP - Dove Conductor (Rev.0-2023)-
3
45mm per kV
D-TR-OHL-INS-400-COMP-SUSP for all (Rev.1-2023) - 45mm
3
per kV
D-TR-OHL-INS-400-COMP-TENS-380KN -Cardinal (Rev.1-
3
2023) - 45mm per kV
D-TR-OHL-OPGW (Rev.0-2017) 6
D-TR-OHL-POL (Rev.0-2014) 3
SECTION IV/3 of VI
SECTION IV/4 of VI
General
Chapter D_Section 01_Commissioning Check List-General _rev 5 8
Chapter D_Section 02_Commissioning Check List-InC-Doc_rev1.1 3
ChapterD_General_rev2.1 1
Overhead Lines
ChapterA_Section 012_Cover_Commissioning CheckList-OHL
1
System Rev1.1
ChapterA_Section 12_Commissioning CheckList-OHL System
2
Rev1.1
0_COMMISSIONING CHECK LIST-rev1.1 1
01_AMMENDMENTS-0817 2
02_Commissioning CheckList-Table of Contents-rev 1.1 2
03_Executive Summary-rev 1.1 1
04_Record of CheckLists-rev 1.1 2
ChapterA_Commissioning Checklist (Electrical) Rev 2_10-05-
1
2022
&
The Cabinet:
Decided:
Article (1)
Definitions
1
Ministry The Ministry of Energy and
Infrastructure.
2
mechanical vehicle.
3
Weighing Station A fixed or mobile station
equipped with the tools and
equipment necessary to
monitor the compliance of
heavy vehicles with the
weights specified hereunder.
Article (2)
Article (3)
4
dimensions specified in Appendix (1) of this decree
under a transportation permit issued by the Ministry, or
by the Competent Authority, according to the
following controls:
5
Article (4)
6
Article (5)
Grievance
Collection of Fines
Article (7)
Executive Decisions
7
Article (8)
Repeals
Article (9)
_____________________________
Issued by us on:
8
Appendix (1)
Table (1):
Table (2):
9
5. Quadruple tandem axle 33 Tons
Table (3)
10
Appendix (2)
11
Sr. Violation Administrative Fine
Decree.
12
Cabinet Decision No. (13) of 2009
Approving the General Standards Manual for Group Labor Accommodation
and Related Services
The Cabinet,
Article one
The General Standards Manual for Group Labor Accommodation and Related Services,
attached hereto, shall be approved and applied to group labor accommodations with five
hundred or more laborers.
Article two
Effective 1/9/2009, the authorities concerned with granting group labor accommodation
licenses shall not grant licenses for this type of accommodation except in accordance with
this Decision.
Article three
within a maximum period of five years from 1/9/2009, any establishment operating in the
UAE and having a group labor accommodation for five hundred or more laborers shall
ensure that the conditions at the accommodation are in accordance with Article one
hereinabove.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
Article four
The Minister of Labor shall issue the necessary decisions concerning the following:
- Laying down general criteria for group accommodation for less than five hundred
laborers;
- Implementing the provisions hereof, provided that the respective decisions issued by
the Minister of Labor shall include transitional provisions and the appropriate rules
for execution, incentives and administrative penalties.
Article five
The provisions of this Decision, including the decisions issued by the Minister of Labor under
Article four hereof, shall apply to all UAE zones including the free zones.
Article six
This Decision shall be published in the official gazette and shall come into effect on the date
that is issued subject to the dates set out in Articles two and three hereof.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
The General Standards Manual for Group Labor Accommodation and Related
Services in the United Arab Emirates
Approved by Cabinet Decision No. (13) of 2009
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
Table of Contents
Subject Page
Introduction to Manual 7
1. Planning Standards 9
1.1. Site standards
1.2. Site coverage
2. Unit Design Requirements 10
2.1. General design requirements
2.2. Materials
2.3 Outdoor requirements
2.4. Ventilation and air conditioning
2.5. Lighting
2.6. Firefighting equipment and emergency exits
3. Residential Units Design 17
3.1. General requirements
3.2. Bedrooms
3.3. Sanitary facilities (bathrooms)
3.4. Kitchens
3.5. Mess hall
3.6. Services
3.7. Rest halls
3.8. Medical services
3.9. Laundry
3.10. Other services
4. Public Health Requirements 24
4.1. Waste disposal
4.2. Public health hazard control
5. Health and Safety Management 25
5.1. Accommodation management office
5.2. Health, safety and security
6. Utility Requirements 28
6.1. Water supply
6.2. Drinking water
6.3. Drinking water reservoirs
6.4. Water pumps
6.5. Cold water supply
6.6. Hot water supply
6.7. Firefighting water reservoirs
6.8. Firefighting water supply
6.9. Fire water pumps
6.10. Firefighting water system
6.11. Electricity supply
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
6.12. Gas supply
6.13. Sanitary drainage
6.14. Telecommunication services
7. Fire fighting Systems 39
7.1. Alarm systems
7.2. Public announcement and fire alarm system
8. Power Transformers 41
9. Transportation and Vehicle Safety Standards 42
10. Onsite rest period 44
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
Introduction
The requirements in this Manual are the basic standard for planning and building new labor
accommodation compounds, areas or cities and the related services. They are addressed to
consulting engineers and competent local authorities. Before issuing any work drawings and
detailed specifications for the housing compounds as part of the tendering process, the
design review process should be completed to ensure compliance with these specifications
before submitting the design to the concerned authority for approval.
For the purposes of these standards, the following definitions shall be adopted with regard
to labor accommodation:
1. Group accommodation, means any residential building or set of residential buildings
intended for labor accommodation and housing more than 500 persons;
2. Residential unit, means any building intended for labor accommodation and housing a
maximum of 1,000 persons;
3. Residential compound, means a site consisting of a number of residential units and
housing 1,000 – 5,000 persons, and surrounded by 2.2m high iron fencing;
4. Residential area/residential quarter, means a site consisting of a number of residential
compounds and housing a maximum of 35,000 persons;
5. Labor city, means a site consisting of a number of residential areas separated by main
roads and housing a maximum of 240,000 persons.
Note: The specifications and requirements of these standards shall apply to all residential
units and compounds. The specifications and requirements marked with an asterisk (*) are
additions that shall apply to residential compounds only.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
1. Planning Standards
1.2.2. The maximum building height should be compliant with the standards approved by
the competent local authorities.
1.2.3. The space in between the residential units should be compliant with the building
conditions and specifications adopted by the local department and shall be not less
than 5m.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
2.1.2. All the units should be designed according to the engineering standards and
specifications adopted by the competent local authorities.
2.1.3. The building should be compliant with all the sanitary and environmental conditions
and safety requirements to preserve the health and safety of its residents and
protect its internal and surrounding environment, such as the building materials, the
drinking water and sanitary drainage systems, the air conditioning systems, the
elevators, the emergency exits, the firefighting systems, internal air quality and the
common service utilities, according to the standards of the competent local
authorities and international specifications.
2.1.4. Periodical maintenance is required to ensure the fulfillment of all such requirements
throughout the occupation period thereof.
2.2. Materials
2.2.1. The units shall have concrete or cement blocks walls, and the flooring should be
made of concrete as well. The construction methods used for all buildings should be
complaint with the regulations, legislation and standards provided for under the laws
adopted by the competent local authorities.
2.2.2. All the building materials used should be environment‐friendly and public health‐
friendly. They shall not be flammable and should comply with the standards of the
Civil Defense Directorate.
2.2.3. The doors should be fireproof as per the standards of the Civil Defense Directorate.
2.2.4. In case of absence of regulations / legislations / competent local laws, the applicable
international standards shall govern.
2.3.2. The area should be sufficient for vehicle movement and parking, taking into
consideration the following:
‐ Control of site entrances and exits;
‐ Accessibility by emergency cars to all buildings;
‐ Food delivery, provision and storage;
‐ Garbage management (storage, collection and transportation);
‐ Bus stops and car parking;
‐ Fire prevention and alarm systems;
‐ Emergency exits and assembly points;
‐ Outdoor lighting.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
2.3.3. The safe passages of the facility should be indicated with instruction signs, and
waiting places should be provided at the bus stations and car stops for workers pick‐
up and assembly after drop‐ off.
2.4.2. The window area should take at least 10% of the room floor area, where 50% of the
windows should be openable.
2.4.3. A ventilation system should be installed in the bathrooms to discharge the air outside
the building and replace it with external air using the proper methods.
2.4.4. An aluminum window with curved sides for ventilation shall be fixed at the bottom
part of the door of every room or bathroom, to provide ventilation and create an air
current with the air coming from the adjacent area.
2.4.5. The internal air quality of the building should be preserved and external air should be
provided according to the averages stated in the following table:
2.4.6. Ventilation systems should be available in the bathrooms, storerooms, copy rooms,
computer rooms, kitchens, toilets, furnaces, changing/bathing rooms, swimming
pools and other areas that contain pollution sources. Pressure in these areas should
be lower than that in the adjacent internal areas and higher than that in the external
areas. The ventilation systems should directly lead outside the building and should be
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
installed in a way to prevent the return of pollutants into the building, at a distance
of at least 25 feet from air inlets.
2.4.7. The air in the kitchens, bathrooms and toilets should be renewed at the minimum
averages stated in the following table:
2.4.8. A control system should be available to control the temperature, humidity and air
speed and provide a comfortable ambience, fulfill the requirements and reduce
microbes and pollutants in all air‐conditioned places.
2.4.9. The relative humidity average should vary between 30% and 60% in all air‐
conditioned areas.
2.5. Lighting
2.5.1. All lighting units fixed in occupied areas should provide minimum lighting levels as
stated hereunder (as per safety considerations).
2.5.2. All the bulbs used should be low consumption light bulbs. Light fittings installed into
false ceilings should be used.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
2.5.3. The outdoor lighting should allow the pedestrians to distinguish the borders of the
sidewalks, direction changes, crossroads and any obstacles or potential risks.
2.5.4. The street alleys, changes in street gradation and any other potentially dangerous
locations should have more lighting than the passages.
2.5.5. The lighting poles/shafts should be placed in a way so as not to obstruct pedestrian
movement.
2.6.2. The emergency roads and passages should be provided with chargeable lighting
devices to be operated in case of power outage.
The residential units should be designed, built and equipped to ensure that occupants have
an acceptable level of comfort and safety in a clean and healthy environment.
3.1.2. In case of extra space available, after providing all the aforementioned services, this
space should be used for constructing bedrooms for the workers on the ground floor.
3.1.3. The drawings submitted for licensing should indicate the general location, horizontal
projections, facades, sections, constructional and electric plans, civil defense,
sanitary drainage, thermal insulation, roads, all the details regarding workshops,
doors, windows and installations and all that is required as per the engineering
standards adopted by the competent local authority.
3.2. Bedrooms
3.2.1. Each worker shall have a space of not less than 3m2.
3.2.2. The number of workers allowed per bedroom shall be 8 to 10 workers while
observing the specified space area for each worker.
3.2.3. The bedroom ceiling should be not less than 7 feet high.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
3.2.4. Each person should be provided with his own sleeping area even in the case of shifts.
3.2.5. Each person should be provided with a bed, side table and a 2m high closet with a
lock.
3.2.6. The space in between the beds should be not less than 36 inches from both sides and
from the upper and bottom sides. The bed height should be not less than 12 inches
from the ground. In case of bunk beds, the distance between the beds should be not
less than 48 inches from both sides and the rear side, provided that the distance
between the upper and the bottom bed shall be not less than 27 inches. Triple bunk
beds are not permitted.
3.2.7. The shoe racks should be placed at the entrance of every room for the workers to
place their shoes before going into the sleeping area.
3.2.8. No cooking stoves or washing machines may be used inside the bedrooms.
3.3.2. In the case of common bathrooms, one toilet should be available for every 8 people,
and any common bathroom should have at least 2 toilets.
3.3.3. One urinal should be provided for every 25 persons. If there is not enough water
pressure, the urinals should be supplied with enough water to be used after finishing.
3.3.4. One shower and one washbasin should be provided for every 8 people.
3.3.6. The washbasins should have mixers to control the temperature of the water used.
3.3.7. The toilet and bathroom designs should include fixtures to hang clothes and towels
and place the soap as well as mirrors and cabinets. Clothes and towel hangers made
of solid materials such as stainless steel should be available in sufficient quantities for
the number of intended users.
3.3.8. The window area should take at least 10% of the bathroom floor area, where at least
50% of the windows should be opened to the outside.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
3.3.9. No toilet, bathroom chemical substances or urinals may be placed in any room that is
used for other than toilet purposes.
3.3.11. The bathrooms and toilets should enjoy sanitary conditions and should be
cleaned at least once a day. Detergents should be used in the toilets.
3.4. Kitchens
3.4.1. Each residential unit should have a kitchen that is compliant with the public health
standards provided for by the concerned authority.
3.4.2. The kitchen should be managed by a licensed food service company or by a food staff
appointed by the accommodation facility management.
3.4.4. The kitchen should be equipped with a proper drainage system and a ventilation
outlet and/or a funnel, and the funnel should be at least 2m higher than the closest
building to the unit.
3.4.5. The gas cylinders should be placed outside the building and shaded from sunlight.
3.5.2. Each person should have an area of his own of at least 1.4m2 in the mess hall (and in
the TV and rest halls), which should accommodate at least one third of the total
number of residents in the unit.
3.5.3. A schedule specifying the meal times should be placed at the entrance of the mess
hall.
3.6. Services
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
3.7. Rest halls
3.7.1. The workers should have a rest hall with comfortable seats and a TV (within the mess
hall).
3.8.2. Each residential compound should have a medical clinic that is capable of providing
health services to all the residents and deal with the cases that require medical care
except for the cases requiring hospitalization. (*)
3.8.3. An isolation room for patients should be provided and equipped with all the
necessary furniture and equipment.
3.8.4. The clinic should be ready for operation 24/7 including the weekends, official
holidays and religious and national holidays. (*)
3.9. Laundry
3.9.1. Laundry services may be outsourced.
3.9.2. If laundry services are not outsourced, the accommodation management should
carry out the following:
‐ Provide laundry services according to an announced schedule and appoint a person
to be in charge of these services;
‐ Provide the unit with communal laundry facilities;
3.9.3. The communal laundry facilities should be on the ground floor of the residential unit.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
3.9.4. The communal laundry facilities should be designed according to the technical
specifications of the competent local authority.
3.9.5. The communal laundry facilities should be provided with all the required services
such as hot and cold water connections, ventilation and air conditioning, drainage
system and sufficient lighting.
3.10.2. Each residential unit should have a barber salon and a grocery store to be
used only by the residents and not by the public. In case a grocery store
exists, it shall not be allowed to sell food that spoil fast or that needs to be
cooked before consumption. Food preparation and packaging is permitted
inside the grocery store.
3.10.3. The compound should be provided with an ATM to enable the workers to
withdraw and transfer money. (*)
4.1.2. Sealed and washable trash containers should be provided in sufficient quantities.
4.1.3. At least one trash container should be provided and placed on a wooden, metal or
concrete stand, and the trash container and the surrounding area shall be kept clean
at all times.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
4.2.2. A company specialized in controlling public health hazards and licensed by the
competent local authority should be contracted to carry out extermination activities
as per an approved program. Records and reports of completed extermination works
should be kept.
5.1.2. The accommodation manager should keep a register of the residents in an updated
database.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
‐ Fire prevention and proper use of firefighting equipment;
‐ Responsibilities during emergency cases.
5.2.2. Copies of house rules signed by the accommodation manager should be printed and
placed in a visible manner on every floor, provided that the rules are in the language
understood by the residents of the units.
5.2.3. The house rules shall at least include the following points:
‐ Cleanliness;
‐ Clear prohibitions (smoking, cooking);
‐ Storage rule;
‐ Trash;
‐ Loud music;
‐ Tampering with the building equipment;
‐ Trash disposal;
‐ Water preservation;
‐ Visitors;
‐ Any other matter deemed necessary by the manager.
5.2.4. The employees, workers and visitors are not permitted to use tobacco products
whether for smoking or for other purposes inside the residential units, at 20 feet
from any entrance or at 20 feet from fresh air inlets. Using tobacco products is
permitted outdoors or in designated smoking places that are completely isolated
from non‐smoking areas by walls from ground to ceiling.
5.2.5. An electricity and water control option from outside the residential compound
should be available. (*)
5.2.6. The residential compound should be provided with surveillance cameras to monitor
every section in addition to the public announcement system. (*)
6. Utility Requirements
6.1.2. The following should be available in the residential units: underground reservoirs and
adjacent water pumps to supply drinking water to the entire site as well as
underground reservoirs and water pumps to feed the fire extinguishing systems,
outdoor hoses, indoor hoses and fire hose reel cabinets in each residential unit.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
6.1.3. The water systems should be installed, operated and maintained in a way to prevent
the growth of bacteria and other air carried microbes, as per the local laws and
regulations.
6.2.2. The water supply average to the residential unit should be based on the total number
of workers that the unit can accommodate, at an average of 35 gallons for each
person per day, and based on 2.5 times the consumption average per hour at peak
times.
6.2.3. All the bathrooms, showers, washbasins and kitchens should be supplied with hot
and cold water.
6.2.4. The water systems should be designed and supplied with water conservation
methods.
6.2.5. The water service poles should be separated from the electric service poles.
6.3.2. The reservoir shall be filled at least to the level of the maximum water consumption
of the residential unit.
6.4.2. A reserve diesel‐driven pump for drinking water with a capacity equaling that of the
main pump should be installed to operate simultaneously with the two main electric
pumps. The reserve pump will operate automatically in case of interruption of the
electric generator that feeds the electric drinking water pumps.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
6.4.3. Sufficient quantities of diesel fuel should be provided to operate the reserve pump at
full capacity and without interruption for 24 hours.
6.4.4. Each of the electric and diesel‐driven water pumps should have a reserve capacity of
135% compared to the normal pumping average of approximately 85% of the
generated capacity without overcharging the pump or the gear.
6.5.2. The outdoor water reservoirs should be covered with sunshades to guarantee cold
water in the summer.
6.5.3. Water coolers should be available in each residential unit according to the number of
workers per unit and/or the number of persons expected to use the unit.
6.5.4. The units should have separate cold water feeders with valves.
6.6.2. Hot water storage of a capacity of 1000 liters should be provided for kitchen use and
600 liters for ablution.
Note: It is recommended to use solar water systems for power conservation; electric heaters
may also be used. Modern technology has allowed the installation of a double heating
system that operates on both solar / and electric energy, where the heater starts by heating
the solar plates during the daytime and is electrically operated at other times.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
6.7.2. An underground firefighting water reservoir shall be built and supplied with a clean
water pump of a capacity up to 1000 liter/minute.
6.7.3. The concrete firefighting water reservoir shall be built as per the international water
storage standards. The reservoir shall be supplied with galvanized joints made of mild
steel to enable the installation of a withdrawal pump as well as an overflow water
pipe.
6.7.4. An overflow water connection, incoming water connection and withdrawal pump
connection should be installed.
6.7.5. An outflow prevention device should be installed on the withdrawal tube inside the
drain with the following dimensions of 1m x 2m x 1.5 m deep at the bottom of the
reservoir.
6.8.2. The store and warehouse areas should be supplied with automatic sprinkler systems.
The quantity of water required by the sprinkler systems is based on the water hose
system demand.
6.8.3. The outdoor and indoor hose systems installed in all the buildings are supplied with
an average of 2000 liters/minute for a period of 4 hours (240 minutes). Sufficient
water quantities shall be provided for the winded 30m long fire hoses fixed inside the
buildings.
6.8.4. The fire‐extinguishing water overflow can be added to the sprinkler systems at an
average of 3000 liters/minute for a period of two hours (120 minutes). The engineer
should verify the sprinklers’ ultimate need for water before finishing his work on the
fire pump.
6.8.5. The fire pumps should have a reserve capacity of 135% of the flow compared to
approximately 85% of the generated capacity without overcharging the pump or the
gear.
6.9.2. Two double fire pumps shall be installed, one is diesel operated and the other
electricity‐operated, in addition to a reserve pump installed in the underground fire
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
pump station, provided that these pumps have all the operation and control
accessories and devices as per the international fire prevention standards for fixed
pump installation.
6.10. The double pumps, reserve pump tubes, valves and backflow prevention valves are
installed near the firefighting water reservoir. A water flow detector with 2%
accuracy should be installed to test the flow process of the individual fire pumps.
6.11.2. The firefighting system should have sufficient diameter to allow the
transportation of water at the required average to the farthest point of the
pipeline system from both sides. These pipes should be installed by a
contractor specialized in fire prevention.
6.11.3. The firefighting pipeline system and isolation valve system should be installed
as per the international inspection, testing and maintenance standards for
firefighting pipes.
6.11.4. All the pipes, fittings and isolation valves shall be installed and tested based
on a pressure of 16 bars (1600 Pa).
6.11.5. The pipes and fittings shall be installed using a black steel tube with welded
fittings and fittings screwed on small pipes of less than 80mm diameter. All
the pipes shall be corrosion resistant. The hidden outdoor pipe shall be a 16
PVC pipe instead of a steel pipe.
6.11.6. All the section isolation valves, withdrawal pumps and distribution pumps
shall have opening/closing indicators. These indicators shall turn in clockwise
motion upon closing.
6.11.7. All the joints shall be fixed to the fire nozzles used by firefighters, and a
closing valve and a backflow prevention valve shall be fixed to the lower side
of the nozzles. These nozzles should be accessible from the ground floor by
the service passage to allow the easy connection of the pumps and use them
to support the pumping of the water towards the building on fire.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
6.11.8. The hose valve shall be installed to the underground fire pipeline system, at a
maximum distance of 15m from the nozzle joints used by the firefighters.
6.12.2. The submission and approval regulations of the Electricity and Water
Authority shall be strictly observed.
6.12.3. The power substations shall be installed and supplied with power, step‐down
transformers and a switchboard etc.
6.12.4. One electrical room shall be constructed on the ground floor per occupied
unit and shall be completely equipped with a switchboard and an engine
control device.
6.12.5. The devices and power distribution panels shall be distributed among the
floors, and separate isolating switches shall be installed for each light and
electric circuit across the area.
6.12.6. Separate electrical isolation devices shall be installed for the ventilation and
air conditioning systems. These devices shall be installed in the control rooms,
kitchens and other service areas.
6.12.7. Separate electrical isolation devices shall be installed for every heating device
installed inside the heaters.
6.12.8. The main air conditioning / cooling units shall be supplied with three‐phase
electric power systems that are disconnected individually in the relevant unit
location.
6.12.9. Electrical outlets shall be installed in the wall (5 AMP plug) as follows:
‐ In all bedrooms:
• A plug near every bed for personal use;
• In each room for electric appliances;
‐ Plugs shall be installed to the wall of each main corridor, with a 15m
distance in between the plugs, for the purpose of plugging in floor cleaning
devices.
‐ In all the occupied rooms such as the offices, warehouses, security offices,
control rooms, workshops, stores… to plug in cleaning devices, small electric
tools and electric appliances.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
‐ In all communal areas to plug in the required number of washing machines,
refrigerators, in‐wall air conditioners, vending machines and water coolers.
6.15.2. Public phones shall be installed near each residential unit, mess halls and
other common facilities. They shall be installed in weather‐tolerant booths
covered with sunshades. The telecommunications authority shall determine
the proper locations and number of public phones.
7. Firefighting Systems
All the fire prevention, detection and alarm systems, including the monitors, electric
installations and sprinkler systems, should be designed and installed as per the Civil Defense
standards.
7.1.2. Each unit should be provided with a fully systematic alarm system controlled from
within the unit by means of a systematic fire alarm panel. The alarm panels shall be
installed in secure places such as the security office on the ground floor /or the
kitchen.
7.1.3. Each fire alarm panel should be connected to a printer that will print out a summary
of the incident that occurred. This printer shall be fixed on the front side of the panel,
in addition to a plasma screen to determine the devices that have been activated in
each area.
7.1.4. All the fire alarm panels shall be supplied with 24V reserve batteries, provided that
these batteries are continuously charged by means of an internal charge unit,
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
allowing these batteries to operate the panel and the fire detectors in case of power
cut for a minimum period of 12 hours.
7.1.5. The fire monitors shall be installed on all the fire detectors so as to connect the
cables to each floor of the concerned unit. These monitors assist in instant alarm
reception in case the fire detector fails or its cable is cut off. They also replace any
defected area in the fire detector cable system.
7.1.6. The early detection systems shall be installed as per the international standards for
fire detection and alarm systems designed for buildings.
7.1.7. All the substations containing the pipes, the pump stations and other occupied
facilities shall be provided with an early fire detection system similar to the
aforementioned system.
7.1.8. The substation containing the pipes and the switchboard rooms in the residential
units shall have a firefighting system relying on the use of clean gas and that is
activated automatically by the early detection system.
7.1.9. The gas extinguishing system shall be installed as per the international standards on
gas extinguishing systems.
7.1.10. All the rooms where gas extinguishing systems are installed shall be insulated
in a way to ensure the preservation of the extinguishing gas in the secure area
at the proper concentration for at least 10 minutes.
7.1.11. In the case where sprinkler systems are installed in the building, separate
water connections should be installed for every set of control valves of the
sprinkler valves.
7.1.12. The main passages should be equipped with water spray nozzles.
7.2.2. The fire alarm system shall be activated manually by pressing the button/switch fixed
by the systematic fire alarm panel.
7.2.3. Alarm sirens shall be installed in all the occupied units, at a distance of 75m from
each other, with an intensity of 75dB across the unit.
7.2.4. The residential compound shall be equipped with a security system to monitor all the
sections of the unit and apply the public announcement system.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
8. Power Transformers
8.1. The oil‐cooled power transformers shall be placed as per the standards of the
Electricity and Water Authority.
9.1. The vehicles shall be subject to annual inspection by the competent local authority.
9.2. The vehicle should be surrounded by suitable lighting to help show its dimensions.
9.3. The name of the company employing the workers should be visibly placed on the
vehicle.
9.4. The maximum number of passengers allowed shall be clearly stated, where each
passenger shall have one seat.
9.5. Smoking inside the vehicle is prohibited as clearly stated by sticking a “No Smoking”
sign.
9.6. A “Frequent Stop” sign should be placed on the rear of the vehicle for warning.
9.7. A contact number should be clearly placed on the vehicle for remarks and
complaints.
9.8. The vehicle should be driven according to the speed signs on the road.
9.11. The vehicles should have handgrips from the inside to make it easier for the
passengers to get off.
9.12. The vehicle should have a first aid kit with easy access thereto. The kit should be
placed in a visible place.
9.13. The vehicle should have two fire extinguishers of at least 5kg each, one placed in the
front and the other at the back of the vehicle.
9.14. The vehicle should have at least six hammers to break the window glass in case of
emergency.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
9.15. Emergency windows should be placed in the front, middle and back of the vehicle.
The emergency exits should be indicated with signs.
9.18. The tires should have an adaptive breaking system that allows the vehicle to stop in
slippery places.
9.21. The passengers stop should be near their destination to avoid crossing the main
roads, unless pedestrian lanes are available.
9.22. During the weekends, transportation to and from the nearest public transportation
point should be provided, unless the transportation point is close to the residential
unit where the worker can reach it on foot (2km).
• Shades should be available at the work sites for the workers who wish to take a rest
period or eat.
• Food and drinking water should be available onsite and should be preserved in
proper health conditions.
• Toilets should be available near the work site.
• Proper sanitary ware should be available within the workers’ rest areas.
English Translation provided courtesy of the . Please direct any queries or questions
regarding this Standard to the Ministry of Labour Offices and not the Health Authority Abu Dhabi.
STANDARD TECHNICAL SPECIFICATIONS FOR ELECTRIC WORKS
GENERAL REQUIREMENTS
( SPECIFICATION )
CONTENTS
1 INTRODUCTION
The civil works are governed by the conditions of the electromechanical part, and as far as they
are not supplemented by data, by the conditions or specifications stipulated hereafter. However,
any local laws and regulations shall prevail, such as the "Abu Dhabi International Building Code
(2013)”.
Detailed execution features of the civil work are described in the relevant sections of the
Specifications.
This document shall represent the basic specification and information for calculating the lump
sum price of the works concerned, but they should not be considered to be a complete
description in every respect. Tender drawings indicate the intended layout of the works, but are
not to be taken as a complete and dimensional reference.
The price offered shall be understood as the total sum for the complete civil and finishing works
to suit the requirements and the functions of the Works concerned. Design and choice of
construction materials shall consider and ensure the reduction of future maintenance works, and
therefore, all civil elements shall be designed to minimise maintenance and to result in a durable
construction with a minimum design life of 40 years.
The Bidder/Contractor shall prepare all necessary design and detail drawings in accordance with
the Project requirements. However, the following guidelines design criteria shall be strictly
followed and applied in view of the proposed equipment, and are having priority over the Tender
drawing details.
EUROCODE CEN
European Committee for Standardisation
Central Secretariat
Rue de Stassart 36
B – 1050 Brussels
Belgium
UBC Uniform Building Code, 1997.
IBC International Building Code, 2009
DIN Deutsches Informationszentrum für Technische Regeln (DITR) in DIN
Deutsches Institut für Normung e.V.
Burggrafenstr. 4 – 10
10787 Berlin
Tel. +49 (0)30 2601-0 / Fax 2601-1260
ACI American Concrete Institute
P.O. Box 4754, Redford Station
Detroit, Michigan 28219, U.S.A.
ASTM American Society of Testing Materials
1916 Race Street, Philadelphia
Pennsylvania 19103, U.S.A.
AISC American Institute of Steel Construction
101 Park Avenue, New York
N.Y. 10017, U.S.A.
ASHRAE American Society of Heating, Refrigeration and Air-conditioning Engineers Inc.
1791 Tullie Circle, N.E., Atlanta, GA 30329 USA
Phone: (404)636-8400, Fax: (404)321-5478
ASHTO American Association of State Highway and Transportation Officials,
444 North Capitol Street, Suite 249,
Washington, D.C. 20001, USA,
Tel: +1 202 624-5800
NFPA National Fire Protection Agency
1 Batterymarch Park
P. O. Box 9101,
Quincy, Massachusetts, USA
Tel: +1 617 770-3000, Fax: +1 617 770-0700
BS British Standard
CIRIA Construction Industry Research and Information Association
The Bidder/Contractor shall clearly identify in his offer which of the acceptable Standards shall
be applied during design and execution for each part of his works. Standards for one type of
materials shall be of the same grouping, i.e. only BS, DIN or ASTM. Only if the selected group
of Standards does not offer guidelines for specific parts of design or execution, alternative
standards may be proposed.
The Bidder/Contractor shall ensure that the design and execution of civil works adheres at least
to the minimum requirements based on BS.
Execution of concrete works shall normally either follow BS or DIN Standards. All concrete
works shall further be executed in line with the CIRIA publication “Guide to the construction of
reinforced concrete in the Arabian Peninsular”.
Structural Steel works shall normally be designed and executed according to EUROCODES 3
and 4.
Other Standards may only be applied after explicit approval through TRANSCO.
The Bidder/Contractor shall provide all required drawings for Town Planning Department, Civil
Defence, TRANSCO, Municipality and other Authorities, which are mandatory to obtain
required (building) permits.
In addition to the basic tendered design to be offered, the Bidder/Contractor may propose
alternative type(s) of building and structures to be applied within the Project.
It is the Bidder’s/Contractor’s obligation to carry out complete Geotechnical Investigations to
determine all relevant soil conditions and parameters required for a sound and durable structural
design, including the design bearing capacity of the ground to determine type and size of
foundations and to determine the chemical soil and groundwater aggressiveness.
Bidder/Contractor shall note that complete civil design of the Grid Station must be finished and
approved by TRANSCO/ Engineer within three (3) months after date of Letter of Award. All civil
design inputs (loading and layouts) for all electrical equipment, MEP equipment (HVAC, Fire
Fighting and Crane) must be approved before start of Civil Structural Design.
3 MATERIALS
All materials proposed and their colours selected to be used within the Project shall be subject to
TRANSCO’s approval and shall comply with the Technical Specification and the defined
Standards.
Application of materials shall be in line with this Specification, but Manufacturer’s specific
instructions for the use and application of his material shall be complied with.
All work shall be executed by skilled workers in a workmanlike manner. Prior to the start of
execution the Bidder/Contractor shall verify that all conditions are suitable for the timely and
effective carrying out of his work.
Specified or requested testing of material shall only be carried out by a licensed office or institute
or an approved laboratory, conforming to accepted standards in accordance with the technical
data and approved by TRANSCO. Selection of samples for testing shall be made by TRANSCO
at Site.
For site testing of fresh concrete, at least equipment equivalent to "Set B" of "Der Deutsche
Beton Verein e.V." shall be provided and used.
If no approved laboratory for the further testing of concrete materials is available, equipment
equivalent to that listed as "Set C” or “Set D" of "Der Deutsche Beton Verein e.V." shall be
provided in addition.
19. A minimum slope of 1% and Floor Drains/Pits shall be provided in all rooms /areas, where
surface water may occur, e.g. the H.V.A.C. Plant Room, Fire Pump Room, Battery Rooms,
trenches, toilet, and Insulator Washing Equipment Room, etc.
20. SWG/SVC-hall floors and the transformer/shunt reactor basements shall have rigid
foundations to minimise differential settlements. If separate basements are provided, the
Bidder/Contractor shall provide proof for the maximum settlements, and shall provide
sufficiently sized compensators in the Switchgear (GIS). Reference is made to the GIS
specification.
21. External block walls, roofs, aluminium or metal clad walls and roofs, as well as all doors
and windows of all building shall provide adequate thermal insulation and shall be
approved by TRANSCO. The thermal transmission coefficient U of walls, including all
windows and doors, shall be equal to or less than 1.2 W/(m2 *K).
22. Distances and room partitions shall be designed according to the specified fire protection
standards. The design layout shall follow the requirements of preventive measures as
outlined in the relevant sections.
23. Unless local regulation require differently, all fire rated doors shall be designed in
accordance with NFPA, and all reinforced concrete structure members (slabs, beams,
frames, columns, etc) shall be designed in accordance with DIN V 18230, DIN 4102, or
NFPA 220 type 1, table 3, and to withstand at least the below listed fire ratings:
24. Transformer foundations shall be designed as a solid block foundation (not separate
beams/walls) and reinforced properly for all straining action including the effects during
casting and service life of the transformer.
25. Transformer bays/shunt reactor shall be designed and executed - in view of fire protection
and the required oil and water collection capacity - as follows:
Double walls shall be used between transformer bays and building walls, whereby
both walls shall be designed as fire separation.
Each transformer bay shall be enclosed by reinforced concrete cast in situ fire
protection walls on three sides. whereby these walls shall be designed as fire
separation (This Structural System Should be Confirmed by Transformer
Manufacturer).
All walls shall be at least 0.5 m higher than the highest transformer part (e.g. top of
tank). Design of the Bays, the Fire Walls, the Oil Tanks and the Fire Fighting
equipment shall meet NFPA and local regulations.
For 400KV & 220KV grid stations; transformer bays shall be separated from GIS
buildings, minimum separation distance shall be 3.0 to 4.0 meters and minimum
thickness of RC cast is situ fire wall shall be 400mm.
For 132 KV Multi storeyed substation within city area, double walls (solid block
including plastering +75mm cavity with insulation +RC cast in situ fire wall) shall be
given between GIS hall & Power Transformer bay, without expansion joint thus
transformer bay shall be integral part of building. And side fire walls shall be
reinforced concrete cast in situ with minimum thickness of 300mm.
The capacity of the oil collection area incorporated in the foundation has to be
designed according to the oil capacity of the transformer as well as the maximum
expected fire fighting water.
If specified and approved, joint oil/water separator tanks may be provided for groups
of transformer foundations. Reference is made to below listed sample drawing,
which is provided in the Drawings Section.
Drawing No. Title
TRANSCO GEN 01 01 Typical Oil Separator
Alternatively, such gates and fences may be constructed utilising powder coated
aluminium sections and profiles.
27. Each substation has to be equipped with fire alarm and fire fighting systems, which meet
NFPA regulations.
28. Wherever the soil investigation indicate a highest groundwater table (Considering seasonal
Fluctuation) within (2.5) meter below the lowest slab level, all reinforced concrete
structures below ground level (e.g. basement slabs & wall, trenches, etc.) shall be designed
as water retaining structure in accordance with BS 8007 and BS 8110. For substations
within the City of Abu Dhabi, the ground water level shall generally be considered at the
finish ground level.
29. Cable trenches shall be designed and provided for the foreseen future extension of the
Station (including consideration of all HV, MV, LV, HVAC, F.F. and control cables).
30. All cable recesses and openings to be provided for foreseen future extension (including
HV, MV, LV and control cables) shall be made 100% watertight and fire protected by an
approved method.
31. Provisional recesses and openings in floors of Switchgear, Control and Relay Rooms and
prepared for the foreseen future extension of the Station shall be covered by heavy duty
chequered plates, fire protected and – if required – thermally insulated.
32. Foundation and floor slab reinforcement shall have projecting galvanised earthing flags to
enable connection to the earthing grid of the Station.
33. All substation metalwork including transformer tank, cable screens, feeder pillar, doors and
any internal structural steel work shall be securely bonded together so that a firm metallic
connection existing between each of them and the substation earthing terminal.
34. External earth points as per requirement for equipment and system earthing shall also be
arranged to keep earth resistance to less than two ohms.
35. A/C unit mounted on roof / top roof shall be surrounded by screen walls (i.e. clustra block,
GRP, aluminium sections).
36. External/internal stair to roof/top roof to be provided. Note that external staircases open to
sky leading to the roof shall be structural steel with Hot Dip Galvanization and epoxy
coating.
37. Roof Parapet shall be flushed with peripheral beams, rather than roof gutter. Therefore,
Rain Water Outlet & Roof Water Proofing system to be submitted for Owner/Engineer
approval.
38. Expansion joints shall be located as determined during the structural design and marked in
the relevant drawings as per in CIRIA and Concrete Society’s – “Guide to the construction
of reinforced concrete in the Arabian Peninsular”.
39. Combine the Rooms in the Substation Building for Similar Equipment for TRANSCO and
DISCO’s Facilities as follows:
a) Single Common Battery room for TRANSCO & DISCO
b) Common Control & Protection/ Relay room but Separate for TRANSCO & DISCO
c) Single Common DC Chargers & LVAC room for TRANSCO & DISCO.
40. In GIS halls, HVAC Ducts (Supply & Return) shall be below Corbel Level & the
Maximum Headroom between the Top of Corbel to underneath/ soffit of Roof Beam/ Slab
shall be 2.30 meters.
41. In GIS halls, all External Peripheral Columns shall be kept flush from inside to reduce the
Internal Equipment Clearance.
42. All front Opening Equipment Panels shall have maximum clearance of 0.2 meters with
Rear wall for effective ventilation. The maximum clearance between Panels in two or more
rows facing face to face shall be 2.4 meters including panels in open door condition.
43. Unnecessary space to be left unbuilt (no walls, no roof, no FD/FP, no HVAC etc.) in order
to reduce the overall Built Up Area.
3. If required, pile foundations shall be provided with permanent casings wherever the ground
down to the bearing strata is highly aggressive or cannot support the newly cast pile.
4. Whenever required for the execution of the works, construction access roads shall be
provided by the Bidder/Contractor.
5. Maintenance access roads may be ordered by TRANSCO, if required along sections of the
line.
5 DESIGN CRITERIA
Following fundamental design criteria shall be strictly followed and applied in view of the
proposed equipment, and are having priority over the Tender drawing details and dimensions.
5.1 Stations
1. Design Criteria to be submitted shall include a description of the following:
Soil investigations/ Geophysical Survey
Codes and standards to be adopted in the design
All Loading to be adopted for the various elements of the structure
Method of Seismic & Wind Analysis.
Load factors and load combinations
Description of the design method and theories to be adopted.
All checks for Structural Stability & Serviceability.
2. Architectural scheme design
3. Base calculation of the structural design and general arrangement drawings shall include
the principle framing and loading calculations, as well as the information concerning the
expected forces in the relevant elements of the structure.
4. Architectural detail drawings (for Stations only) covering the electrical equipment
requirements shall be co-ordinated with Mechanical, Electrical and Plumbing (MEP)
drawings and shall include the following:
Plans, elevations and sections detailed enough to enable construction without
difficulties including Area Statement for Total Built Up Area.
Stair case details
Roofing and water proofing detail
Load drawings, showing all dead, equipment and live loads, including line loads
from walls etc.
Reinforcement details, bar bending schedules, following ACI/ BS simplified methods
for detailing, except where seismic/ductile connections are required. This detailing
should be elaborated and presented in more details.
Concrete protection details
Structural steel details of all members, their welds and other connections
Coatings and corrosion protection details
Detailed lists of steel structure members, plates, bolts (Connection & Anchor Bolts)
Details of sheet metals and claddings for walls and roofs, etc.
Details of walls, stairs and other members
Formwork drawings/calculations shall be submitted for information.
The design procedure for the project shall be as described above, but not necessary limited to the
above and shall be approved by TRANSCO before proceeding.
Different Method Road Crossing i.e Duct Bank, NDRC/ HDD, Pipe Jacking/ Micro
Tunnelling etc.
2. Structural details shall include the following:
Detailed structural calculations of all members and structures
Type of foundation to be applied
Reinforcement details, bar bending schedules, prepared in line with ACI/ BS
simplified methods for detailing, except where seismic/ductile connections are
required. These have to be elaborated and presented in more detail.
Concrete protection details
Structural steel details of all elements
Detailed lists of structural steel elements, welds, plates, bolts, and other connections
Coatings and corrosion protection details
All checks for Structural Stability & Serviceability.
The design procedure for the project shall be as described above, but not necessary limited
to the above and shall be approved by TRANSCO before proceeding.
2
- Plant Rooms (Fire Pump) 7.5 kN/m
2
- HVAC and Condenser Yard 5.0 kN/m
2
- Minimum Additional dead load for suspended ceiling, pipes, 1.0 kN/m
AC system, etc
- Roads and pavements, gutters SLW 60, DIN 1072
- Water tanks, septic tanks, etc. in road areas SLW 60, DIN 1072
- The Allowable total settlement should not exceed 25.00 mm in any case.
The Permissible Differential Settlement between foundations in substations & within
structures shall not exceed 10 mm or as per OEM requirements.
The site wind speed (Vs, as defined in BS-6399- Part2) shall be taken equal to the maximum
wind speed as mentioned above. Other parameters shall be considered in line with above
mentioned standard for calculation of Effective Wind Speed and Wind Pressure. The buildings
and structures governing wind load shall meet the serviceability requirements of BS.
DL = Dead Load
LL = Live Load
EL = Equipment Load
SL.x/z = Seismic load in X or Z Hor. direction
SL.Ver = Seismic load in Vertical Direction
WL.x/z = Wind Load in X or Z Hor. Direction
CL = Crane Load
For the design of buildings with crane, the longitudinal frame shall suitably consider surge loads
in longitudinal direction, from crane.
In case buildings/ Structures are proposed without expansion joint or violating the requirements
as per CIRIA, then that structure shall be analyzed for temperature stress in combination with
load cases as mentioned above.
Earth pressure for under ground structures will be calculated using coefficient of active earth
pressure (Ka) or earth pressure at rest (K0) depending on boundary condition.
Reinforced concrete members shall be designed with a crack width not more than 0.2 mm in
accordance with BS 8007. In case underground water doesn’t exist, no need to design for crack
width.
top of the boundary wall, 100 mm height of spikes option shall be fixed of metal strip
encased/fixed on top the panel.
Boundary walls shall normally be arranged at a distance of not less than 1.5 m from the plot
limits unless specified differently in the scope of works. However, for 132kV Substations inside
cities, it is required to keep one side or many sides of the building flushes to plot boundary so as
to reduce the length of the pre-cast boundary wall.
On filled plots (or plots to be filled) the boundary wall shall keep a distance of at least 3 m from
the edge of fill, where it has reached the final fill level. Contractor has to submit slope stability
calculations for O/E approval.
Alternatively, TRANSCO may specify security fencing around the plot. Such fence shall be at
least 3.00 m high chain link or – if approved or specified within the scope of works - mesh fence,
with additional arms for four strands of barbed wire at the top. The bottom of the fence mesh
shall be encased in a ground beam.
For every plot, at least two entrance gates have to be arranged within the boundary wall or
security perimeter fence. Each gate shall be a double winged road gate of at least 6.0 m clear
opening, with a separate pedestrian gate of 1.2 m width each. Transportation requirements for the
equipment may require larger openings and have to be considered.
Boundary wall shall be provided with external type of light fitting.
For details, reference shall be made to the below listed drawing, provided in the Drawings
Section:
Drawing No. Title
TRANSCO CIV 01 01 Pre-Cast Boundary Wall Details
GENERAL REQUIREMENTS
( SPECIFICATION )
CONTENTS
The following shall form the basis for each Bidder/Contractor to optimise his Proposal with
regard to local facts, and to prevailing technical realities.
The information given hereunder applies to all works in addition to the General Conditions,
Special Technical Requirements, System Characteristics, and Civil Design Fundamentals, unless
specified to greater detail in sections on specific installations..
Note:
for Equipment Operating phases and Freq. power power power impulse impulse impulse impulse impulse
(Um – IEC Voltage starpoint frequency frequency frequency voltage voltage voltage voltage voltage
60071) or Rated condition (Hz) withstand withstand withstand withstand withstand withstand withstand withstand
Voltage (Ur – voltage (1 voltage (1 voltage (1 (phase - (across (phase - (phase - (across
IEC 60694) min.) Phase min.) across min.) across phase and isolating earth and phase) isolating
to Phase, open switch isolating phase - distance) across open distance)
Phase to distance earth) switch)
Earth
420 kV 400 kV 3 - phase 50 525kV 650 kV 650 kV 1425 kV 1425 kV 1050 kV 1575 kV 900 kV
(+345 kV)
solid earth (+240 kV)
245 kV 220 kV 3 - phase 50 460 kV 460 kV 530 kV 1050 kV 1200 kV N.A. N.A. N.A.
solid earth
(Power Transformers, Part 3: Insulation Levels, Dielectric Tests and External Clearances in Air).
All electrical equipment shall be entirely suitable for use under the prevailing site conditions.
For insulation levels of transformers reference shall be made to the respective Standard Technical Specification and IEC 60076-3
Page 4 of 10
GENERAL REQUIREMENTS
Electrical Design Fundamentals
2. CLEARANCES IN AIR
400 3050/3600
220 1700/
132 1270/1475
Remarks: For OHTLs conductor clearances the maximum swing at maximum conductor sag of the
concerned OHTL conductor shall be considered (refer to DIN VDE 0210).
Important Note: 250 meters ahead of the points of which OHL crossing a public road; a
clear Sign Boards should be installed on the roadsides facing all traffic
directions (in a way not to be removed by public) defining the maximum
allowable vehicle height. Board shall be long lasting as OHL life and
according to the specifications of the drawing number (DWG TR CIV 15).
Remarks: For OHTLs conductor clearances the maximum swing at maximum conductor sag of the
concerned OHTL conductor shall be considered (refer to DIN VDE 0210).
2.7 Minimum Clearances of/to Underground Cables & Cables to other Services
Notes:
* distance from piles (horizontal)
** at cable crossings the space between the cable circuits shall be filled with CBS compound
Important Note:
Cable Crossing Clearances shall not influence transmission capacities (de-rating shall be
minimised) of the involved cables. Heat transfer calculations shall be submitted for approval to
prove that the proposed clearance shall not influence the crossed cables.
4. INSTALLATION HEIGHTS
The installation heights of center line of wiring accessories and other items of equipment shall
generally be as follows:
Socket outlet for supply to fan coil units of A/C split units 0.3 m below ceiling level
5. CREEPAGE DISTANCES
Due to the extreme climatic and pollution conditions, Specific Creepage Distances have to be
increased beyond those stipulated in IEC/TS 60815, and shall be as follows (based on the highest
rated phase to phase voltage, subjected to TRANSCO approval according to the installation
location environmental condition, and applicable to HV and MV installations):
Manufacturer's design
Gas insulated encapsulated installations
NOTES:
1- Specific Creepage Distance as defined in IEC 60815 (2008) based on line-to-line value of the
highest voltage for the equipment Even For line-to-earth insulation.
2- ‘Kd’ factor (based on insulator diameters) shall be taken into consideration during total
Creepage Distance calculations.
The substation and distribution auxiliary supply systems provide one or more of the following
voltages:
7. LIGHTING SYSTEMS
All light fittings shall be equipped with energy saving lamps.
8. LDC INTERFACING
The following Standard is applicable for the communication protocol (Control, Metering)
between the GTW of substation and LDC:
GENERAL REQUIREMENTS
( SPECIFICATION )
GENERAL CONDITIONS
CONTENTS
GENERAL CONDITIONS
The following shall form the basis for each Bidder/Contractor to optimise his Proposal with
regard to local facts, and to prevailing technical realities. The general information given
hereunder apply to all plants, equipment and materials, unless specified in more detail in sections
for special conditions or specific installations.
Location of Abu Dhabi City 24° 25’ 40” N, 54° 27’ 59” E
Location of Al Ain City 24° 13’ 13” N, 55° 45’ 32” E
Altitude above Sea Level ≤ 1000 m
Maximum barometric pressure (at sea level): Hecto Pascal 1030 1030
Maximum ambient relative humidity: % 100 100
Minimum ambient relative humidity: % 1 1
Average annual rainfall: mm 85 85
Maximum annual rainfall: mm 255 165
Maximum daily (24 h) rainfall: mm 34 40
Maximum hourly rainfall: mm 80 50
Maximum seawater temperature: °C 36 -
Minimum seawater temperature: °C 20 -
Maximum ground temperature at 1 m depth: °C 40 41
Design Wind Speed: Km/h 160 160
Seismic load acceleration factor (horizontal) g 0.2 0.2
Seismic coefficient / importance factor (according to 0.075 / 1 0.075 / 1
Zone 1 of Uniform Building Code):
Solar Radiation: W/m2 973 876
Isokeraunic Level: 7 thunderstorms per
year
The Bidder/Contractor must ensure that his installations will operate satisfactorily under all
climatic conditions as stated above, and especially the high solar radiation resulting in additional
heating of all installations exposed to direct sunlight has to be considered.
5 SERVICE EXPERIENCE
The Bidder/Contractor shall submit with his Bid statements and documentary evidence of service
experience of equipment, apparatus and materials offered. Unless the solicitation asks for
equipment or apparatus, which are of new technique, at least five years of satisfactory service
experience under similar climatic and environmental conditions are required for all apparatus and
equipment. For equipment, which does not satisfy the above conditions, explicit approval from
TRANSCO is required.
7.1 General
The Bidder/Contractor shall maintain control the latest revision of the relevant Bidder/Contractor
Documents, Drawings, and all CONTRACT Technical Specifications including referenced
International Standards of Codes relevant to site work, Procedures and Work Instruction, at the
location where work is being carried out.
The Bidder/Contractor must take into account and has to follow in any case the following
national codes:
¾ The Electricity Transmission Code (The Abu Dhabi Transmission and Despatch Company)
¾ The Metering and Data Exchange Code (The Abu Dhabi Transmission and Despatch
Company)
¾ TRANSCO System Safety Rules
¾ TRANSCO HSE Rules
¾ Rules of the Environmental Agency in the Emirate of Abu Dhabi
¾ ISO 9001 (Quality System Certification)
¾ ISO 14001 (Environmental Management Systems Certification).
Other than the above, ISO and IEC standards as well as IEEE and BS recommendations shall in
all cases rule unless specifically other standards are required, or other requirements are made in
these specifications. In addition to the applicable ISO and IEC standards, the Bidder/Contractor
may propose for his design other international or national standards, as long as there is no
contradiction to ISO/IEC. The Bidder/Contractor in such case has to submit a full set of English
language issues of such standard, and must prove item by item, that the standard he wishes to use
results in equipment, which is certain to satisfy the respective requirements of ISO/IEC. The
Bidder/Contractor may apply the proposed standard only after approval by TRANSCO.
All equipment, apparatus and material shall be standardized as far as possible without infringing
the functional and safety requirements of the specification. The standardization shall permit
interchange ability of any corresponding parts, and the number of different equipment of the
same basic functions shall be minimized as far as feasible.
8 TESTS
8.1 General
TRANSCO/Engineer reserve the right to visit Bidder/Contractor, SUB-Bidder/Contractor(S) or
VENDOR(S) works or any premises at any time during manufacture to verify conformance with
the requirements of the approved Specifications.
Witnessing of performance tests for major equipment shall be made by TRANSCO/ Engineer.
The list of equipments which require witnessing the tests and number of visits required for the
PROJECT shall be indicated by TRANSCO in the data sheet attached to this Specification. The
expenses for these visits including air tickets, transportation, lodging/boarding, etc. for
TRANSCO representatives shall be borne by TRANSCO.
If any retests need to be carried out due to non-conformity and these retests require a separate
visit then the expenses for retesting shall be borne by the Bidder/Contractor.
The material and equipment which generally are subject to witness and verify testing by
TRANSCO/Engineer shall include but shall not be limited to the following :
ELECTRICAL WORKS
• HV Switchgear
• Power transformers
• Electricity Meters
• Low voltage system cables, panel boards including interlocking and lighting
• D.C system
The exact requirement of material and equipment will be specified by TRANSCO in attached
data sheet.
All test procedures, Quality Control Plan, Inspection and Test Plan, Quality Control Record,
Reference Standards or Documents, etc., shall be submitted by the Bidder/Contractor to
TRANSCO/Engineer sufficiently in advance so that the same are approved and available with
TRANSCO/ENIGNEER at least twenty-one (21) days before the start of any tests.
The Bidder/Contractor shall rectify and remove the causes of such objections and the inspection
or test shall be repeated. Rejected or objected material, equipment or workmanship shall not
relieve the Bidder/Contractor from any obligation under the CONTRACT nor shall any
extension of CONTRACT completion time be allowed.
The quality control plan (QCP), once approved by TRANSCO/Engineer, will form the
contractual basis for quality control and shall be used as a guide to the monitoring of the
Bidder/Contractor, SUB-Bidder/Contractor(S), VENDOR(S) performance by
TRANSCO/Engineer and/or Third Party Inspection Agency (where applicable). The quality plan
must therefore be submitted to TRANSCO/Engineer and approved by them before any
manufacturing commences.
'Hold', 'Witness' and ‘Review’ points shall be indicated in the QCP, to indicate the intended
control / monitoring of the TRANSCO/Engineer, Bidder/Contractor, SUB-
Bidder/Contractor(S), and VENDOR(S).
The representative waives off the witness activity and advises for the test to proceed
without his presence. (Witness involvement varies between 0 to 100%)
In addition to “Review”, "Witness" and "Hold" points, inspection surveillance may also be
employed by TRANSCO/Engineer as an alternative method of monitoring the
Bidder/Contractor/SUB-Bidder/Contractor(S)/VENDOR(S). This will take the form of an
audit of a section of the agreed quality control plan where physical documentary evidence will
be required for compliance with requirements.
Where witness and hold points have been assigned to be performed in the presence of
TRANSCO/Engineer, the Bidder/Contractor shall notify TRANSCO/Engineer by fax or any
other means giving at least twenty one (21) working days advance notice for the pending tests.
The Bidder/Contractor shall also confirm within seven working (7) days prior to witness testing
that operations are on schedule, or otherwise.
- Items to be inspected.
- Document reference of approved Inspection and Test Plan (Quality Plan) and test procedure
that is relevant to the inspection or test of the item.
8.2 Definition
8.2.6.1 General
Details of Site Acceptance Tests are specified in Standard Technical Specification Part 21 (Site
Tests after Installation (SATs))
TRANSCO shall have the right to inspect at all times all tools, instruments, materials, staging,
equipment, templates, work technique, etc., used or to be used in the performance of the
WORKS.
TRANSCO shall have the right to condemn or reject tools, instruments, materials, staging,
equipment, templates, work technique, etc. if found not conforming to Specification or, if in
the opinion of TRANSCO that it is not in line with best engineering practice or, these may
lead into a non-conformance.
TRANSCO shall have the right to reject or condemn a completed assembly or sub-assembly if
items or components belonging to that assembly or sub-assembly are not inspected, tested or
witnessed by TRANSCO/Engineer, or by the Bidder/Contractor, as per the agreed Inspection
document e.g. ITP, QCP, Procedure, Method Statement, Standard or Code.
This right to reject or condemn a completed assembly or sub-assembly shall specifically apply
to situations where TRANSCO/Engineer is not afforded nor informed of a forthcoming
inspection or, TRANSCO/Engineer can not carry out inspection and testing, due to other
requirements specified in this Standard Specification.
Any defective work equipment or material not conforming to Specifications shall be rectified
by the Bidder/Contractor at no additional cost to TRANSCO.
No CONTRACT time extension shall be allowed for rectification or replacement of rejected work or
equipment.The inspection procedure for Material delivered to site shall be documented and approved
by TRANSCO/Engineer. Any damage to an item or to the protective coating due to
mishandling/transportation or manufacturing fault shall be assessed and reported in the Receive Cum
Damage Report. The Bidder/Contractor shall replace or rectify any defective or damaged item(s) as
advised by TRANSCO/Engineer. All costs for such replacement or rectification shall be borne by the
Bidder/Contractor.
The CONRACTOR shall submit to TRANSCO/Engineer the Inspection and Test Plan (ITP) for
all items not less than six (6) weeks prior to the schedule of tests. The ITP shall be reviewed and
approved by TRANSCO/Engineer and witness, review, hold and other intervention points shall
be noted in the ITP for the Bidder/Contractor to incorporate.
Site testing shall be in accordance with the requirements given in the approved Inspection and
Test Plan, Method Statements, Procedures, Technical Specifications, Schedules of Technical
Data and/or Tender Drawings of respective disciplines.
All test procedures and method statements shall be submitted by the Bidder/Contractor
sufficiently in advance so that the same are approved by TRANSCO/Engineer and available with
them at least fifteen (15) days before start of any tests.
A full formal record of all site testing shall be kept by the Bidder/Contractor.
To plan proper coordination of all inspection and test relevant to the particular WORK.
To identify inspection and test personnel who shall be involved in that particular WORK.
To ensure that all documents e.g. ITP, method statements, procedures, codes and standards,
specification, drawings, etc. are available and in the Approved Status.
To ensure all Inspection and Testing Equipment required are available and properly
calibrated.
The Bidder/Contractor shall provide the test equipment for the above-defined tests. The
Bidder/Contractor shall ensure that the test equipment is calibrated and suitable for these tests.
Calibration certificates shall be valid for at least six months.
After the final inspections/tests at site and, if TRANSCO/Engineer are satisfied with the
outcome, they then may agree for the WORK(S) to be accepted. In this connection,
requirements of preliminary and functional tests, trial operations, initial operation, provisional
acceptance and final acceptance given in General Technical Requirements will also have to be
complied with by the Bidder/Contractor.
The Inspection Check Lists and Test Records shall be used as back up for Completion
Certificates for the WORK(S). The Completion Certificate shall be signed and dated by
representatives of the Bidder/Contractor and TRANSCO/Engineer.
9 CORROSION PROTECTION
The climate in the U.A.E. being very humid and corrosive, special attention is to be paid to the
use of excellent quality galvanising material and paint.
All ferrous parts shall be hot-dip galvanized or electro-galvanized and shall not be subjected to
finishing operation on their threads after Zinc coating. The average and minimum weight of Zinc
coating shall be 380 and 305 gm/m2 respectively for hot dip method. The minimum thickness of
Zinc coating by electro-deposit method shall be in accordance with BS 729 or equivalent.
Fixings smaller than M10 must be made of stainless steel, grade 1.4301 (V2A).
For more details of corrosion protection, reference shall be made to the Standard Technical
Specification Part:
¾ S-TR-CORR - Corrosion Protection
A detailed Corrosion Protection/Painting description shall be submitted along with the Bid.
10.1 Marking
Each equipment, terminal strip, and each indicating and operating element shall be identified
with permanently attached plastic tags or labels of approved design. These tags/labels must be in
full match with those used in the drawings.
Each of the equipment must have its own rating plate with information according to the relevant
IEC. At least the following shall be available on the rating plate:
• TRANSCO
• PROJECT NAME
• Bidder/Contractor’S / SUB-Bidder/Contractor’S NAME
• PORT OF DESTINATION
• CONSIGNMENT SERIAL NO.
• GROSS WEIGHT
• NET WEIGHT
• SIZE OF BOX OR BUNDLE (LENGTH X WIDTH X HEIGHT)
• BRIEF INDICATION OF CONTENTS.
10.2 Packing
All equipment and material shall be packed in bundles/crates or seaworthy containers or packing
and no second hand timber shall be used.
All packing shall be suitable for transport from factories to the port of embarkation, sea/air
freight, rough handling at the port of destination and movement to and on the Site.
Before leaving the works, all equipment and fittings shall be painted or stamped in two places
with a distinguishing number or letter corresponding to those on an approved drawing and
material list. All markings shall be legible. Weatherproof tags where used, shall be durable,
securely attached and duplicated. The erection marks on galvanized material shall be stamped
before galvanizing and shall be clearly legible after galvanizing.
All equipment and material, together with the applicable instruction books, packing lists and
special site storage instructions, shall carefully be boxed, crated or otherwise adequately
protected for overseas shipment. All bright parts liable to rust shall receive an anti rusting coat
and shall be suitably protected. Flanges, studs and exposed machine surfaces shall be thoroughly
greased and protected before shipment. Any equipment susceptible to damage by water or high
humidity shall be encased in watertight and/or airtight, rugged containers and suitable desiccants
shall be placed inside each airtight container to ensure a low humidity atmosphere therein.
Special provisions shall be made regarding the prevailing severe local climatic conditions.
Shipping weights and dimensions of each box or package shall be determined in such a way as to
facilitate handling.
Further reference is made to the individual chapters of the Standard Technical Specification for
the equipment.
11 BIDDING DOCUMENTS
The Technical Data Sheets must be filled-in by typing (handwritten data and/or information are
not acceptable). If a particular item is not applicable, the letters NA (Not Applicable) shall be
typed in the corresponding provided space. For any data not duly inserted in the data sheets, the
most unfavorable data stated in other submitted Bids will be used for evaluation purposes.
If there are deviations from or additions to the Technical Specification and the Technical Data
Sheets, these must be stated together with its explanations/justifications on separate sheets. All
those points in which the Specifications and/or Technical Data Sheets cannot be fulfilled shall be
stated and explained separately.
The Bidder/Contractor may offer better values than required, (e.g. for test voltage levels, ratings,
etc.).
In case expressions "or equivalent", "or similar" etc. are used for manufacturer's names, these are
assumed to come into force only after approval of TRANSCO.
Undeclared Technical Deviations shall not be accepted and shall not be considered during the
Bidding process.
12 SPARE PARTS
The following documents must be supplied within bids to TRANSCO:
• Complete list of specified spare parts (if any) and consumable materials
• Complete list of recommended spare parts.
13 DOCUMENTATION
13.1 General
Documentations shall meet requirements as specified in Standard Technical Specification, Part:
The equipment supplied under this Contract shall be documented to the extent as to allow
TRANSCO, as well as the operator, to fully understand the product, its theory of operation, its
application, performance and maintenance.
Furthermore, it must enable TRANSCO to efficiently communicate with the manufacturer about
all aspects of operating, maintaining and servicing the switchgear.
The following documents must be submitted to TRANSCO:
• Bill of equipment showing complete re-ordering information for all replaceable parts
• Spare parts source, identification and price list
• Installation, operation and maintenance instructions.
Prior to shipment, copies of all routine test certificates/reports shall be made available to
TRANSCO. If, during testing, changes are made to the equipment, these deviations must be
corrected in the submitted drawings to reflect the final "as built" condition of the switchgear on
delivery.
These corrections must be completed immediately following the actual changes. The final set of
drawings/certified "as built" must be available prior to starting-up of the equipment.
All TRANSCO's data provided for this equipment shall show the equipment as specified and
ordered. Typical drawings are not acceptable unless they are revised to show only the equipment
being furnished. The format, standards, and quality and quantities of drawings shall be
manufacturer's standard, but shall be subject to TRANSCO's approval as per the requirements of
this Specification.
Language in all documents and drawings shall be in English; dimensions shall be in metric SI-
units.
13.4 Records
13.4.1 General
Records are “Documents stating results achieved or providing evidence of activities performed”
as defined by ISO 9000:2000 (3.7.7) shall be properly controlled and maintained throughout the
duration of the project. It can be any written account of facts obtained from an observation or an
event, a test, an inspection, a chart, a completed form or any document which furnishes objective
evidence of activities performed and the results achieved.
14 ENVIRONMENTAL RULES
Rules of the Environmental Agency in the Emirate of Abu Dhabi shall be followed.
GENERAL REQUIREMENTS
( SPECIFICATION )
COMPONENTS MARKING
CONTENTS
COMPONENTS MARKING
1 GENERAL
The following shall form the basis for each Bidder/Contractor to achieve uniform numbering and
identification of system components. The general information given hereunder applies to all
plant, equipment and material, unless specified to greater detail in sections on special conditions
or specific installations.
Letter Designation
Code Nominal/Operating Voltage (kV)
Color RAL BS 381 C
B >420
C 400 Blue 5015 166
D 220 Yellow 1021 309
E 132 Red 3000 537
N <1 Black 9005
P
Q Facilities for measuring and metering
R Facilities for Protection
T Facilities for Transformers
U Facilities for Control, Signalling and
Auxiliary Equipment
W Facilities for Control Rooms
X Central Facilities, e.g. Process Computers,
Alarm Systems
Y Facilities for Telecommunication
Z Lifting Gears and appliances
Exemption: Single-Lines diagrams displayed on SCMS screens at the substation level, the bay
designation numbers shall be without Latin letters (B01, C01, etc.), i.e. 01, 02, 03, etc. for all
voltage levels.
Subject Color
2.1.5 Switchgear
The following Identification Codes are applicable in TRANSCO`s T&D Systems.
Circuit Breaker S* Q 0
Earth Switch
Line Feeder S* Q 8
Reactor Feeder S* Q 8 1
Isolator
Line S* Q 9
Reactor S* Q 9 1
Voltage Transformer
BB 1A & BB 1 T 1 5
BB 1B T 1 6
BB 1C T 1 7
BB 2A & BB 2 T 2 5
BB 2B T 2 6
BB 2C T 2 7
Feeder (Line) T 5
Single line diagram presenting the above mentioned Equipment Coding is provided in the
Drawings Section is as follows:
Drawing No. Title
DWG TR GEN 02 01 Diagram Illustrating Principles for Naming of Switches
Power Transformer Terminal and Tapping Markings shall be applied as specified in:
¾ IEC 60616 - Terminal and tapping marking for power transformers
2.1.9 Reactors
2.1.11.1 Generators
2.1.11.1.1 Steam Turbine Generators
• Steam Turbine Generator 132kV Level ST20 to ST39
400kV Level ST60 to ST79
2.1.11.2 Gas Turbine Generators
• Gas Turbine Generator 132kV Level GT01 to GT19
400kV Level GT41 to GT59
For more Details, please refer also to the following part of the Standard Technical Specification,
Part 17:
The following letter codes shall be used for the designation of equipment location as per DIN
40719, Part 2.
Table: 2 Designation of Equipment Locations
A Circuit-Breaker Accessories
B Multiply, Re-Position, Decouple
C Instrument Transformer Accessories
D Compressor Air, Hydraulic
J Automatic, Closed-Loop Control
L Simulating Network, Voltage Selection
M Measurement
N System Services
P Recorder
Q Metering
R Protection
S Synchronising
T Transformers
U Auxiliaries
V Main, Secondary Bus bars, etc.
W Display, Operation, Supervision
X Alarm System
Y Telecommunication
The following letter codes shall be used for the designation of kind of item (as per IEC 60750;
1983):
shunt, thermistor
S Switching devices for control Control switch, push button, limit switch,
circuits, selectors selector switch, dial contact, connecting stage
T Transformers Voltage transformer, current transformer
U Modulators, changers (of Discriminator, demodulator, frequency changer,
electrical quantities) coder, inverter, converter
V Tubes, semiconductors Electronic tube, diode, transistor, thyristor
W Transmission paths, cables, Conductor, cable, busbar, waveguide, waveguide
busbars, waveguides, aerials directional coupler, dipole, parabolic aerial
X Terminals, plugs, sockets Connecting plug and socket, clip, test jack,
terminal board, soldering terminal strip, link,
cable sealing end and joint
Y Electrically operated Brake, clutch, pneumatic valve
mechanical device
Z Termination, bifurcator, hybrid
transformers, filters,
equalizers, limiters
A Alarm
C Control
M Tele Measurement
S Status
Example: OHTL between Grid Station A (existing Grid Station) and Grid Station B (new)
Lower number of switchgear (Grid Station A) bay to which the OHTL circuit is
connected shall be named circuit I and the OHTL connected to the higher
switchgear bay number shall be named circuit II (for example: Switchgear Bay No.
D06 shall be connected to OHTL circuit I and the next higher Bay Number (D12) of
the same Switchgear shall be connected to OHTL circuit II, a.s.o.).
Brown Phase 1 – L1
Black Phase 2 – L2
Grey Phase 3 – L3
Blue Neutral – N
Green and Yellow Protective Conductor
1 AIRPORT AIRP
2 BANAIYAS BYPS
3 MAHAWI MHWG
4 MADINAT KHALEEFA MDKH
5 MUSSAFAH (132kV) MOS1
EMIRATES STEEL INDUSTRY
6 ESIM
MUSSAFAH (220kV)
7 TAWEELAH ASIA NEW TANE
EXTENSION
8 TAWEELAH A 132 TWPSA
9 TAWEELAH A1 POWER TWPSA1
10 TAWEELAH B 132 TWPSB
11 MUSSAFAH (400kV & 220kV) MOSG
12 SALT & CHLORINE SLTC
13 SHAHAMA EAST SHME
14 SAMHA SMHG
15 TAWEELAH TWPS
16 UMM AL NAR UNPS
17 WATHBA WATH
18 MUSSAFAH GIC GRID STATION MGIC
1 GAYATHY GTHY
2 LIWA WEST LWST
3 RUWAI RUWS
4 SHUWAIHT (400kV & 220kV & 132kV) SHPS
5 SILA SILA
6 TAKREER (ADNOC) ADNC
7 HYDROGEN Power Plant (400kV) HPAD
1 MIRFA MRFA
2 MIRFA Power Station MRPS
3 MADINAT ZAYED (WR) WMZD
4 BU HASA 220kV BHSA
5 BAB 220kV BAAB
6 ASAB ASAB
7 HAMEEM HMEM
8 LIWA LIWA
9 ASAB Gas Development II ASGS
10 ASAB Gas Development III ONGS
2.1.17.11 GCC
7 AL WAGAN AWGG
8 CITY CENTER CTCC
9 DAHMA DHMG
10 MAZIYAD MZDG
11 RAMAH RMAG
12 SALAMAT SLMG
13 SANAIYA SNYG
14 SWEIHAN SWHG
15 ZAKHER ZAKG
16 AL AIN INDUSTRIAL CITY I AIAA
17 AL AIN INDUSTRIAL CITY II AIBB
18 AL AIN INDUSTRIAL CITY III AICC
Remarks:
* The Prefix ‘New’ is temporary where the Substation will be upgraded and have the original
Substation Name.
Extra writing between brackets following the Substation Name is not part of the Substation
Name, but explanatory.
a) Designation of
K12 Protection Relay (-K12 stands for Identification of Item, Table 3)
in Protection Cubicle 1 (+R1 stands for Location of Item, Table 2)
for 220 kV Switchbay No. 3 (=D03 stands for Higher Level Designation, Table 1).
b) Designation of
F1 Fuse (-F1 stands for Identification of Item, Table 3)
for Alarm System (+X stands for Location of Item, Table 2)
for 11 kV Switchbay No. 1 (=K01 stands for Higher Level Designation, Table 1).
=K01 +X -F1
c) Designation of
F1 MCB (-F1 stands for Identification of Item, Table 3)
for Transformer No. 2 Fan Motor (+T stands for Location of Item, Table 2)
for 132/11 kV (=E stands for Higher Level Designation, Table 1).
=E +T2 -F1
Ordinal Section P
P O S T L Ordinal Section P
5 5 5 5 Project Number
Ordinal section P is a four digit number, which stands for TRANSCO’s NUMBER OF THE
PROJECT.
Accordingly all documents/drawings for the total PROJECT will have at the beginning of their
CSD-Code the number: 5555.
Ordinal Section O
P O S T L Ordinal Section O
A A
Originator
Ordinal section O is a group of two letters (capitals) standing for the ORIGINATOR of the
particular document/drawing.
For a PROJECT the following symbols for the first letter (CSD position 5) for the Originator
could be used:
A OWNER
B
C
D
E
The second letter (CSD Position 6) can be related to the individual PARTS of the PROJECTS
and shall be applied as follows:
For Correspondence
A General Requirements
B Switchgear & Protection
C Transformers/Reactors/Resistors
D Metering Devices
E Substation Auxiliary Equipment
F Overhead Transmission & Distribution Lines
G Cables and Accessories
H SCMS-SCADA/RTU-FMS
I Communication
J Power Compensation
K Earthing/Lightning
L Fire Fighting
M Civil Works
N Electromechanical Services
O Street Lighting
P Corrosion Protection and Painting Color Codes
Q Cubicles & Enclosures
Ordinal Section S
P O S T L Ordinal Section S
N N N N Subject
Ordinal section S is a four digit number (CSD-Code Number) and identifies the SUBJECT dealt
with in the relevant drawing.
Preference shall be given to the following numbers:
5100 Civil Construction Structures
7000 Substation General
7100 Switchgears
7200 D. C. and A. C. Systems
7300 Transformers, Reactors, Capacitors, Converters
7400 Generators, Motors, Drives
7500 Cables
7600 Transmission Lines
7700 Electrical Control Rooms
7800 Ancillary Systems
7900 Communication Systems
Ordinal Section T
P O S T L Ordinal Section T
Type of Drawing
The letter (capital) forming ordinal section T defines the TYPE of document or drawing. These
letters to be used when establishing CSD-Code numbers are the following:
A Correspondence with TRANSCO / OWNER
B Correspondence with Bidders/Contractors of TRANSCO/Customer, etc.
C Correspondence with contracting parties (except A) concerning the implementation
of the PROJECT, e.g.: Banks, Insurance, CONSULTANT, Authorities
D Correspondence with others, without any contractual relationship as described under
C above
E Internal correspondence of CONSULTANT for matters of any kind, including notes
and file notes, travel reports and internal meeting reports, e.g.: within the Head
Office, with the Site Office(s)
F Contracts and orders of any kind
G Reports of any kind, e.g.: Project Reports, Studies, Expert's Opinion, Memoranda,
Work Reports, Progress Reports, Meeting Reports
H Technical Specifications of any kind
J Calculations, Graphs, Curves
L Test procedures, certificates, schedules
M Manuals, Plant/Process Descriptions, Operating Instructions
N Overall lay-out plans, Plot Plans, topographic maps
P Layout Arrangement and Installation Drawings of existing Plants and Installations,
e.g.: civil buildings, installations, mechanical and electrical equipment, switchyards,
Loading and Foundation Drawings, overhead lines, etc.
Q Arrangement Drawings, Layout Drawings, Loading Diagrams, Control Room
Proposals, Switchgear Lay-outs
R Principle and Schematic Diagrams: Single Line Diagrams, Flow Diagrams, P & I
Diagrams, Block Diagrams, Flow Balance Diagrams, Instrumentation and Control
Diagrams, Logic Diagrams, Functional Diagrams, Switching Diagrams (single phase)
S Design/Construction- and Detail Drawings: Dimensional Drawings, Workshop
Drawings, Civil Construction Drawings, Architectural Drawings, Erection Drawings,
Plans/Sections and Elevations, Fabrication Drawings, Isometrics
T Detail Connection and Installation Drawings, e.g.: Switching Drawings (3 phase),
Circuit Diagrams, Cable Layout (in Buildings), Wiring Diagrams, Sequence
diagrams, Interlocking diagrams
U Routing and profile drawings for overhead transmission lines, Cable routes, Profile
drawings
V Civil Drawings general, Shuttering Drawings
W Reinforcement drawings, bar bending drawings/lists
X Computer Programmes, Time Schedules and Networks, Organization Diagrams
Y Cash Flow / Time Schedules, Capacities/Costs
Z General Information, Administration, Organigrams
Ordinal Section L
P O S T L Ordinal Section L
N N N A
Current Number
....Revision Index
For drawings, ordinal section L is a three digit number from 001 to 999 (current number) and the
revision index of the drawing from A to Z, I and O being excluded in order to avoid possible
misunderstandings or mistakes.
In order to achieve an independent numbering for the different lots and subjects, the
Bidder/Contractor shall elaborate a list of all subjects for which individual series of drawing
numbers shall be used e.g. each individual subject of this list shall start with the next current
number, such as e.g.:
001 - 100 for HV Switchgear
101 - 200 for MV Switchgear
201 - 300 for LV Switchgear
301 - 400 for Capacitor Bank
401 - 500 for Station Services
501 - 600 for Control, Protection and Metering
601 - 700 for Cables
701 - 800 for OHTL
801 - 900 for Transformer
etc.
For letters, documents, etc., i.e. for correspondence the four digits of the Ordinal Section L shall
be used as a current number of letters, documents, reports and telexes starting with the number
0001.
The letter numbers shall be current numbers, starting at 0001, i.e. without considering different
Ordinal Sections "S" and "T" of the CSD-code.
5.1 Definition
RAL is the abbreviation of Rationalisierungs Ausschuß für Lieferbedingungen und
Gütesicherung.
Which in fact designates the German Institute for Quality Assurance and Certification e.V
5.2 Description
The RAL Design System has been developed for professional color design. It contains 1688
colors arranged in a systematic order. All the 7-digit color shades are defined as individual RAL
Colors. The difference between this and the RAL classic color collection is that the color codes
of the RAL Design System are not arranged arbitrarily. They indicate the technologically
measured values of Hue, Lightness and Chroma.
ATTACHMENT
Classification System of Documents (CSD) List of Subject Number for Drawings and
Documents
1000 CALCULATIONS
1100 Stability
1200 Load Flow
1300 Transmission Capacities
7130 LV Switchgear
7200 D. C. and A. C. Systems
7210 Battery Chargers
7220 Batteries
7300 Transformers, Reactors, Capacitors, Converters
7310 Theoretical Fundamentals, Design
7320 High Voltage and Medium Voltage Transformers
7330 Low Voltage Power transformers
7340 Transformer Accessories
7350 Reactors
7360 Capacitors
7370 Converters (Thyristor)
7400 Generators, Motors, Drives
7500 Cables
7510 HV Cables
7520 MV Cables
7530 LV Cables
7540 Cables for Instrumentation, Control and Telecommunication
7550 Cable Accessories
7560 Cable laying
7600 Transmission Lines
7610 Towers
7620 Foundations
7630 Sagging
7640 Insulators
7650 Conductors
7660 Accessories (Fittings, Clamps, etc.)
7700 Electrical Control Rooms
7710 Control Panels
7720 Synoptic Mosaic Panels
CONTENTS
1 INTRODUCTION ........................................................................................................... 5
2 GENERAL ....................................................................................................................... 5
3 SCOPE.............................................................................................................................. 5
4 ROLES AND RESPONSIBILITIES: ............................................................................ 5
5 THE CONTRACT PROGRAMME: ............................................................................. 6
5.1 INITIAL PROGRAMME (IP) ....................................................................................... 6
5.2 BASELINE PROGRAMME: ......................................................................................... 6
6 ENGINNERING DELIVERASBLES SCHEDULE: ................................................... 6
7 SOFTWARE FOR BASELINE PROGRAMME: ........................................................ 7
8 DEVELOPMENT OF BASE LINE PROGRAMME: PLANNING &
SCHEDULING REQUIREMENTS: ............................................................................. 7
9 PLANNING & SCHEDULING LEVELS ................................................................... 10
10 MANPOWER HISTOGRAM ...................................................................................... 12
11 PROGRESS ‘S’CURVES ............................................................................................. 12
12 CONTRACT AND INTERIM UPDATES .................................................................. 18
13 PROGRESS MEASUREMENT................................................................................... 18
14 PROGRESS REPORTING .......................................................................................... 19
15 COORDINATION PROCEDURE .............................................................................. 23
16 PROGRESS REVIEW MEETING ............................................................................. 23
17 TRANSCO REVIEW CYCLE ..................................................................................... 24
18 REVISION OF PLANNING & SCHEDULING DOCUMENTS ............................. 24
19 GENERAL REQUIREMENTS ................................................................................... 25
20 GLOSSARY ................................................................................................................... 27
21 APPENDIX A ................................................................................................................ 28
1 INTRODUCTION
The intent of this document is to set out the requirements of all parties who will participate in the
planning and scheduling of the contract. The contract schedule is regarded as the principal
control mechanism for the project and as such it is vital that all stakeholders fully understand
what is required of them from initial creation until project completion.
The contract schedule is neutral; it is there to serve the interests of all stakeholders and to help
deliver the project to all parties’ satisfaction within time, cost, and quality constraints. For it to
be of maximum value the information it contains must be as honest, realistic, and accurate as
possible. The requirements contained within this document are designed to ensure that the
schedule is produced and maintained in a manner that is both consistent and in line with
generally accepted good scheduling practice.
2 GENERAL
The principal rights and duties of the parties with respect to planning and scheduling are set forth
under any contract however, the following detailed requirements and procedures shall govern the
planning and scheduling activities under this contract.
3 SCOPE
The scope of this procedure includes the following:
• The development of schedules which represent the plan for execution of the services
consistent with TRANSCO requirement and reflecting the total scope.
• A monitoring and control system which continually compares actual performance with
planned performance and allows early review and corrective/preventive actions on
deviations.
• The default settings and modes of operation of the contract scheduling software package.
• The outline format and minimum content of progress and status reports.
These requirements are in addition to or expand upon the requirement set up elsewhere in the
contract documents.
required review and make sure that all TRANSCO’s requirements mentioned in this
specification document or elsewhere in the contract are satisfied.
The consultant shall delegate a single responsible to monitor and update the construction
activities in accordance with actual construction progress. This designated representative shall be
solely responsible to act on behalf of the Consultant/Contractor and to revise the schedules logic
in accordance with the terms of Contract Documents. The Consultant’s representative shall not
be replaced throughout the duration of the project without written consent by OWNER/Engineer.
In case of scheduled annual leave of the said representative, a proper replacement and
notification to OWNER shall be arranged by the Consultant in order not to disrupt work
continuity, which is under the responsibility of its representative.
optimum sequencing to ensure that they are available before start of construction work at Site.
Engineering progress measurement shall be developed and shall be submitted for
OWNER/Engineer review and approval and same shall be incorporated in the baseline
programme. Monthly updating of engineering deliverables with the status of each deliverables
shall form part of the Monthly report. Any changes from the approved engineering deliverables
shall be highlighted in the report.
Contractor may also utilise his in-house developed package(s) suitable for specific applications
(e.g. document control, procurement control, etc.). TRANSCO shall have the right to review and
to request amendment or amend all planning packages, applications such as, schedules,
procedures, to suit its requirements. Consultant/Contractor shall maintain a system which shall
be capable of tracking deliverables, assessing progress, maintaining Earned Value analysis
calculations, producing manpower histograms and ‘S’curves by discipline/Area, cash flow
distribution curves, payment requests and assets coding system, the system should be able to
identify problems areas and supporting the decision making process for corrective actions.
The systems shall be capable of producing normal and exception reports as may be required by
TRANSCO.
The CONTRACTOR would supply the licensed version (1 No. for OWNER HQ, 1 No. for
OWNER/ENGINEER Site team) of the latest Version of planning software to be used by
OWNER & ENGINEER.
The Baseline Programme is a detailed Programme that represents the entire lifecycle of the
projects under the PMC scope of work and must be in line with the Employer’s requirements and
delivery plan. Once the Baseline Programme is accepted by the Employer, it shall not be revised,
changed, or modified without the prior approval from Employer
In preparing the Baseline Programme, the PMC/Consultant shall meet the following criteria:
8.1 The programme covers the entire scope(s) of the contract work. A programme file
in. XER format must be provided with a detailed WBS showing all
deliverables/scope
8.2 All activities shall be properly linked and the early/late start and finish dates along
with the total float and critical path(s) shall be clearly identified
8.3 The activity list shall indicate the following data as a minimum but not limited to
the Activity ID, Activity Description, Duration, Early Start, Early Finish, Late
Start, Late Finish and Total Float
8.4 When performing CPM scheduling, the critical activities must be filtered using
the “Longest Path” method. For ‘near critical path’, activities with a total float of
no more than 21 calendar days are used.
8.5 The Work Breakdown Structure, Activity codes, Resource dictionary, Project
Calendar, and the level to which work elements are detailed shall be provided by
or agreed with the employer. The work breakdown structure (WBS) of the
schedule to be in line with the Contract BOQ and to follow the approach of
operative sub systems & systems. Appropriate breakdown for lots, circuits and the
relevant work packages shall be provided to clearly reflect the major phases of the
Project. Typically, the WBS Level 1 will be as follows:
WBS Code WBS Name
N000X.1 1-Milestones
N000X.2 2-General
N000X.3 3-Engineering
N000X.4 4-Procurement
N000X.5 5-Construction
N000X.6 6-PAC
N000X.7 7-FAC
No changes can be made to the contract WBS without the agreement of TRANSCO.
8.10 Use of Notebook Topics / Text fields: Whilst every effort is to be made to work
according to the approved schedule it is acknowledged that there will inevitably
be exceptions when for whatever reason it is not possible to do this. An activity
level notebook topic – ‘progress comments’ is to be used to record any relevant
information which relates to the progression of works i.e. outstanding approvals,
requests for information. This topic is to be clearly and fully displayed on the hard
copy PDF schedule that is issued along with the soft copy schedule file during
every update period.
Similarly, alterations to logic must be recorded in an activity level notebook topic
– ‘logic changes’ Changes in activity logic within the working schedule must
always be explained and fully justified.
8.11 Planning & Scheduling Package Settings: The software required in the
development of baseline, revised schedule and progress updates is primavera P6.
8.12 Out of Sequence Progress: Contractor / consultant shall carry out the works
according to the agreed contract schedule. Every effort should be made to
maintain the agreed contract schedule but if out of sequence working is
undertaken, for whatever reason, a full description of the out of sequence working
and a suitable explanation is to be given. Full note must also be made on the
impact of out of sequence working has had on the agreed contract schedule.
Appropriate modifications to schedule logic must be made to return the schedule
to the original sequence; logic changes are to be fully recorded using the notebook
topic as outlined above.
Level 1 (executive summary) WBS summarised to level 2 The entire project summarised
to single activities
representing broad phases.
Key milestones also shown
9.5 Schedule Level 3 – (control) Project by Phase / Area then work package
9.6 The level 3 schedule will cover the whole of the project and is the main source of
information for the monthly project report. As such it will contain all significant
milestones and cover all major elements of the project i.e., engineering,
procurement, installation, and commissioning. In instances where there are
multiple contractors / sub-contractors it will be a complete critical path method
schedule. This will then provide the framework by which individual contractors
can develop their own detailed level 4 working schedules within the sequencing
and timing constraints of the overall project.
look ahead layouts and reports used by discipline leads to control work and report
progress.
10 MANPOWER HISTOGRAM
Forecast required manpower histograms by discipline and at overall project level shall be
produced throughout the project duration at every reporting period. Consultant/contractor shall
mobilize adequate manpower resources to ensure works are accomplished in accordance with the
baseline plan.
The histograms shall be produced to depict the scheduled manpower planned and shall be
compared with actual manpower deployed on a weekly basis for the entire project duration.
The histogram shall be developed for the entire duration of the contract.
11 PROGRESS ‘S’CURVES
Progress ‘S’ Curves shall be developed based on the Level 3 Control Schedule and the various
activities weight factors (as a minimum one overall progress ‘S’ Curve will be generated) these
curves shall be updated on monthly basis to display actual progress versus planned progress as
well as projected trends for the remaining period through the project duration ‘S’ curve shall
show early and late profile. Updated ‘S’ Curves, together with updated manpower histograms to
be provided and shall be from the basis of progress reporting and monitoring with respect to the
contract schedule.
11.1 The total budget at completion of the schedule must be equal to the total Contract
value. Every activity in the schedule must be loaded with the corresponding BOQ
item as a resource, with relevant budget units and budget cost, and in case of
Lump Sum items, the quantities to be estimated initially.
11.2 The loading of the cost to the different activities of the schedule must be done in
line with the invoicing clause of the Contract (Terms of Payment, refer to the
General Conditions of Contract). This will require the costs to be split into
payables.
11.3 The cost for each resource will be the net payment amount (i.e. excluding the
advance payment % or the retention monies.
11.4 Wherever the Contract BOQ item defines the Work at a higher level than the
activities in the schedule, the BOQ cost to be estimated for different activities of
the Works and loaded in the schedule. These cost break ups later will have to be
approved by OWNER/ENGINEER & accordingly the cost loaded schedules
would be readjusted to reflect the OWNER / ENGINEER approval. This is
applicable to all lump sum items, to the Electromechanical & Instrumentation
activities.
11.5 Activities/resources shall be codded with relevant codes in line with the assets
unified code in the appendix for POWER and Water Projects.
11.6 All activities in the schedule to be loaded with the required resources particularly
Manpower & Equipment required to execute the activity. Submission & approval
of the Histogram is a must. Feasibility / availability report of the required
resources for doing the Works to be submitted along with the schedule.
11.7 Under the Engineering Design and approval WBS node, CONTRACTOR to
include a sufficient level of detail for the Engineering deliverable schedule, which
shall be planned at the proper time and shall be directly linked with the related
activities in the procurement and construction activities and to provide optimum
sequencing to ensure that they are available before start of construction work at
Site.
11.8 This schedule must clearly mention the details of sub contractor’s Scope of Work,
such information will need to be updated from time to time to reflect the latest
information.
11.9 All activities in the baseline programme shall have a limited duration less than 21
days except for the work packages for which the information at the time of
development of the baseline plan is not available as well as manufacturing and
shipment activities.
11.11 The base line schedule would also consider any external dependencies if any, and
also dependencies of different lots of the same package, if applicable.
11.12 Comprehensive lists of various tests to be carried out under different phases of
commissioning, as mentioned above, for all systems & sub systems would be
submitted for OWNER approval and would be based on various Contract
documents. This detailed schedule would be submitted for approval before the
start of any works for testing / pre commissioning / Commissioning Works.
11.13 From the procurement schedule, a detailed report must be generated for all the
major equipment / material to provide sufficient follow up information. Which
will:
11.14 The baseline schedules must show all major milestones, such as:-
11.14.1 Approved “Contractual” Start and Finish dates, and Site handing over dates.
11.14.2 Any dates for specific requirements from the OWNER/ENGINEER must be
shown very clearly.
11.14.3 Completion of Engineering activities, completion of Manufacturing activities, and
of Erection activities.
11.14.4 Milestones to show the placement of order for critical items & the delivery of
Critical items must be incorporated in the schedule.
11.14.5 Approval of all QCP/ ITP for starting the production of all major materials /
equipment.
11.15 Each activity in the network shall be assigned a resource to reflect the weightage
system, i.e the performance weight factor, which is based on agreed weightage
system, upon which Progress ‘S-curves’ will be generated and subsequently
monitored. The control schedule is explained in further detail under paragraph 7
below.
11.16 As a general policy, the use of constraints within the schedule is to be kept to an
absolute minimum. Only official contractual milestones may carry constraints,
and these are to be the least restrictive possible congruent with achieving the
objective of accurately modelling the required date. The following are the only
allowed cases for use of constraints:
• Only milestone type activities may carry a constraint, unless otherwise
justified by consultant/contractor
• Interface points to external schedules with external dates are to be clearly
identified.
• Every constraint used shall be documented and fully justified in the
schedule narrative.
• The use of constraints to suppress the float is expressly forbidden.
• The use of mandatory (hard) constraints is expressly forbidden unless the
use can be wholly justified.
The following table lists the available constraints and guidelines on usage
11.17 As a general policy, the use of multiple calendars within the schedule is to be kept
to the minimum required to realistically model the nature of the activities being
modelled, i.e. local working arrangements, typical trade working patterns. The
following conditions must be adhered to:
• All calendars are to be fully documented
• All calendars are to reflect as the working practice they are modelling
• Calendars must contain any local statutory holidays and / or contractually
specified non work periods
• The use of calendar nonworking periods to suppress float is expressly
forbidden.
11.18 All level 3 and 4 schedules are to be fully logic linked. All activities are to have
at least one predecessor activity and at least one successor activity, the only
exceptions being the project start milestone which will have no predecessor, and
the project finish milestone which will have no successor.
Logic links should be predominantly conventional finish – start (FS) type links.
Logic links of the start – start (SS) and finish – finish (FF) may also be used
where justified, as may the start – finish (SF) type link. The logic used must
reflect the sequencing as explained in the accompanying schedule narrative. The
use of unusual logic i.e. (SF) should also be covered within the narrative.
The use of lags between activities is to be kept to the minimum and cannot exceed
5% necessary to realistically model the intended relationship, and use of leads
(Negative lag) should be avoided. The following conditions must be adhered to:
• In every instance where a lag is used it must be justified in the
accompanying schedule narrative and recorded in the activity notebook /
text field.
• The use of lag as a substitute for an activity is expressly forbidden i.e. to
simulate approval periods or lead time. These must always be represented
as a discrete activity.
• The use of lag to suppress float is expressly forbidden.
• No critical task/path should contain any lag or lead
11.19 All level 3 and 4 schedules are to have a companion schedule narrative that
clearly explains the sequencing and underlying methodology that is depicted in
the schedule. The topics covered should include but are not limited to:
• Methodology and sequencing.
• Phasing and coding.
• Critical path and near critical paths.
• Explanation and justification of non-conventional logic where used.
13 PROGRESS MEASUREMENT
13.1 Responsibility
The reporting of progress shall be the responsibility of contractor. The Engineer/Consultant will
be responsible for review and approve the contractor’s submittal before reporting to TRANSCO.
The supporting documents, charts & photos relevant to the measurements of the actual field
progress are to be provided by consultant/contractor and shall be attached to the relevant monthly
Consultant / contractor shall progress the schedule monthly. Progress will be determined by the
following:
Once the schedule has been progressed a full analysis of variance will be carried out. The project
manager is responsible for notifying activity owners of any slippage and working with them to
implement the actions necessary to eliminate the slippage.
In addition, the cost wise analysis will be required in terms of comparison between Planned cash
flow to actual invoiced and a further comparison between value of work done at site and actual
invoiced.
14 PROGRESS REPORTING
Consultant/Contractor shall prepare and maintain a comprehensive set of controls for
documentation. These controls shall enable exception reports to be prepared speedily and to
support management reporting as required by TRANSCO from time to time. Details of various
reports to be submitted by consultant/contractor are given below:
14.2.3 The CONTRACTOR will also have to submit the hard copies of progress updates
in pre-agreed formats. This submission will be done on monthly basis although
the updates would be done on weekly basis.
14.2.4 A comprehensive list of all changes i.e. revised logic, durations, added
/amended/deleted activities, resource assignment changes
14.2.5 Comprehensive variance analysis against approved Contract Baseline covering:
▪ Start and Finish dates variances
▪ Cost and cash flow Variances
▪ Earned value variance analysis
14.2.6 Comprehensive variance analysis as above against the previous update with
commentary on trends
14.3 Updating Procedure:
14.3.1 CONTRACTOR shall perform the updating of the schedule on a monthly basis,
based on both cost and physical progress of Works, by entering the activities’
actual start and finish dates and comparing against the approved baseline schedule
by showing in the bar chart the targets bars for assessment.
14.3.2 Time related updating would be done by putting the remaining duration of the
activity for the balance work with proper reasoning of the same.
14.3.3 Cost related updating would be done by updating each resource associated with
the activity based on the actual units done.
14.3.4 Physical progress for activities will be updated by entering actual % complete in
the weightage actual units for each activity.
14.3.5 The following week, the progress figures must be checked in detail (backed up by
supporting documents) by a team comprising of QA/QC, QS & Planning
Engineer both from the Consultant & the CONTRACTOR and then these
corrected progress figures would be reflected in the overall progress. These
progress figures to be signed by the RE & the CONTRACTOR’s Project Manager
for their agreement.
14.3.6 All variations will be reflected in the schedule every 3 months or whenever the
need be and will be based on the proposal of the CONTRACTOR. Before
loading the Works covered under Variation into the schedule, the
CONTRACTOR must submit the same to OWNER/ENGINEER for progress
related comments. This submission will only be for the progress monitoring and
in no way give right to the CONTRACTOR for invoice these Works. Later, when
the processing & the approval of trend notice/variation are done, the budget
associated with this activity will be readjusted accordingly.
14.3.7 The updated schedule to be true reflection of the Site progress and the remaining
durations must reflect reality. The updated schedule must reflect the schedule
assumptions of the CONTRACTOR at the time of updating the schedule but not
the assumptions of few months ago.
14.3.8 The CONTRACTOR would advise OWNER/ENGINEER about all the out of
sequence progressing during the Week and the reasons for the same.
14.3.9 The CONTRACTOR need to submit every month the details of the resources
deployed on Site particularly manpower. The report must provide comparison of
the planned & actual productivity indices for major items; reasons for the
variations in productivity indices & the CONTRACTOR’s proposal to either
rectify the problem or to increase the resources based on the actual productivity
index.
14.3.10 An updated S-curve for the following must be submitted for the following- :
14.3.11 Updated histograms based on the actual Manpower & equipment on Site. These
Histograms to be submitted based on geographical areas of Site and various
disciplines.
14.3.12 3-months look ahead must be submitted derived from the latest baseline/revised
schedules from time to time.
14.3.13 From these 3 months look ahead, 1 month look ahead to be derived and must be
detailed enough by further breaking up the Works in order to monitor the Works
on daily basis and must be submitted along with the monthly report.
14.3.14 In the event of delays, the CONTRACTOR shall describe actions proposed to
overcome the adverse conditions & to maintain the planned Construction
Programme.
14.3.15 The Monthly Progress Meetings will be held on and the discussions will be based
on the updated schedule. Different phases of the project & their impact on each
other along with the slippages in the major milestones will be discussed in these
progress meetings.
14.3.16 Critical path analysis (with zero or negative total float) must be discussed in the
Weekly Progress Meetings & remedial actions to be discussed in order to recover.
14.3.17 On a Monthly basis, a status report on various authority approvals will have to be
submitted by the CONTRACTOR. In case there are some delays due to this
reason, the CONTRACTOR to explain the various steps planned to bring back the
schedule.
14.3.18 On a monthly basis the contractor will be required to submit the following cost
updates:
▪ Value of work done up to date (as per terms of payment and including the
Advanced payment)
▪ Actual value invoiced up to cut-off date
14.3.19 A tabular report reflecting the Design status of submittals from time to time. The
detailed time schedules must also be submitted for various Works requested by
the ENGINEER in order to closely monitor the Progress of Works.
Weekly progress report shall also include, but not be limited to the following details;
a) Progress statistics (weekly & cumulative) along with reasons for backlog if any,
separately for each area/system/discipline/facility…etc and overall progress.
b) Activities awaiting TRANSCO action/approval.
c) Updated S curve showing planned vs. actual progress (weekly & cumulative) at
the overall project level.
d) Procurement status report.
e) 3 weeks look – ahead program.
A deviation from the agreed schedule shall be identified and two (2) copies of this report shall be
submitted by the contractor to TRANSCO and consultant.
14.5 Daily Report (Construction)
Contractor shall prepare standard form for daily reports which shall be approved by TRANSCO.
It shall be the daily field log and the minimum information required shall be as follows:
This log shall be prepared and maintained daily at site and a copy shall be delivered to
Consultant Residence Engineer next morning.
15 COORDINATION PROCEDURE
15.1 Communication
The English Language shall be used for all correspondence, reports, instruction, drawings,
specifications etc.
As far as possible, all written communication shall be SITE level directly between Consultant
and contractor. All efforts shall be made to keep the correspondence to the minimum. If for
expediency, telephonic conversation shall be used; this shall be confirmed in writing two (2)
working days, by both PARTIES.
Consultant shall prepare and issue the Minutes of all his meetings with TRANSCO & Contractor
and shall be responsible for obtaining approval of these minutes prior to release within two (2)
working days.
The end user (/TRANSCO) representative shall attend the progress review meeting as an
observer.
The minutes of meeting shall be prepared by the consultant and submitted to TRANSCO for
review and approval prior distribution to all attendees.
Contractor shall submit along with any variation proposal a detailed evaluation of schedule
impact, if any, due to change in scope/sequence of work. Justification for schedule impact should
be accompanied by a logic network clearly highlighting the impact of such changes on the
completion of intermediate milestones as well as the overall project completion, if any.
Contractor shall note that the submission of any revised program/extension time request and
subsequent approval of same by TRANSCO, during the contract period shall not relieve the
consultant/contractor from his contractual obligations. All such revisions shall only be treated as
a part of the control mechanism for effective monitoring so as to arrest/reduce progress slippage.
CONTRACTOR will revise the schedule as and when required in order to reflect the changed
scenario of the Works. Not limited to the following. The CONTRACTOR must revise the
schedule in the following instances within 7 working days to show how he intends to recover the
lost time.
b) When programme does not represent the actual execution & progress of the
Works being performed on Site.
c) Where a change in the Work sequence is proposed or has been instituted by the
CONTRACTOR. Any such change should not, in any case, be made without the
OWNER/ENGINEER approval.
e) In case the CONTRACTOR thinks that the balance Works cannot be finished in
the remaining time & there is a need for the CONTRACTOR to apply for
Extension of Time.
Any/All revisions of the time schedule to be followed by the revision of cost loaded schedule.
Resources also must be adjusted to reflect the changed productivity levels for the major Works.
A comparison of old & new productivity levels must also be done with the reasons for the
change.
In case the CONTRACTOR reflects part or all of the requested extension of time in a revised
programme, before the ENGINEER has determined the CONTRACTOR’s proper time extension
entitlement, he shall do so at his own risk & responsibility and any Programme revised under
these circumstances shall only serve as a tool for monitoring the progress of the Works until such
time as the ENGINEER has determined the CONTRACTOR’s time extension entitlement.
The CONTRACTOR shall seek approval from OWNER/ENGINEER for the position of
Planning Manager/Engineer. In case OWNER/ENGINEER asks for a replacement of the
planning personnel, the CONTRACTOR would make sure that the replacement of this position
is done within 2 weeks from the formal notification of the ENGINEER.
Contractor / consultant will produce a recovery schedule if overall progress falls, or is forecast
fall more than 10% behind the approved contract baseline schedule. The recovery schedule will
address the causes of delay and reflect a realistic and viable sequence that will eliminate the
delay.
19 GENERAL REQUIREMENTS
TRANSCO reserves the right to add/delete/modify any or all the scheduling and reporting
requirements if deemed necessary to ensure effective control and monitoring. TRANSCO shall
discuss/explain all such changes/requirement and consultant/contractors shall always implement
the same until contract completion.
Consultant/contractor shall submit to TRANSCO electronic file(s) of the schedules and reports at
regular intervals for review & approval as applicable. Contractor / consultant shall comply with
all of the above and additionally:
• Submit the soft copy source file that was used to produce the PDF hard copy schedule
progress layout(s). This file is to be in Primavera. XER format or MSP .MPP format.
• All work packages are to be fully resource loaded to ensure that the project is logistically
viable and to facilitate the identification of potential resource deficiencies that could
result in schedule slippage
• Resources are to be smoothed and levelled to reduce avoidable peaks and troughs of
resource demand.
• Regularly measure performance against plan
• Take pre-emptive action to avoid unnecessary delays and stay on schedule
• Produce Ad hoc reports as and when requested in addition to the regular status reports
• Produce look ahead early warning reports based on schedule trends and progress to date
• Carry out ‘what if’ analysis as requested in support of potential authorised changes and
any scenario that may impact the schedule
• TRANSCO review / acceptance periods will be clearly identified in the schedule and will
be 20 working days or as otherwise stated.
• Activities that have interfaces to external or other contractors must be clearly identified
• At level 4, no activity is to have duration greater than 20 working days except for
overarching type activities (i.e., project management) or long lead procurement items.
• The planning team of the CONTRACTOR will have to undergo Quality Audit as and
when required by the OWNER/ENGINEER and will be performed as per the agreed
procedure.
• Detailed procedure for updating & revising the baseline schedule, in line with the
detailed Contract specifications, shall be submitted for OWNER / ENGINEER approval.
20 GLOSSARY
Work Break-Down Structure (WBS)
The work breakdown structure is a deliverable orientated, logical and hierarchical breakdown of
the products and services that will be delivered by the project. The top level represents the entire
project; each successive level breaks the project down into more detail.
Baseline
A complete, un-progressed copy of the approved contract schedule which is used as the
benchmark for performance measurement
Variance Analysis
The technique of determining the difference between planned and actual performance
Schedule Level (1 to 5)
This is the standard naming convention used to establish the typical scope and content of a
schedule at any given level.
Critical Path
This is the longest, unbroken sequence of activities within in a schedule spanning from the
project start milestone to the project finish milestone. A critical path is typified by having zero
total float and is depicted in a schedule as solid red.
Milestone
This is an activity type that has zero duration which is used to represent a significant event or
moment in time. Milestones are represented by a diamond symbol within a schedule.
Activity (Primavera)
This is the basic building block of a schedule and represents a discrete element of work.
Typically, several activities will be grouped and sequenced together within a work package
which will result in the creation of one or more deliverables.
21 APPENDIX A
Agenda of Session
1. General P6 Settings
2. Resource loading Pre-requisites
3. Weightages and BOQ Cost loading requirements
4. Standard WBS Level 1
5. General Activity Codes
6. Specific Activity Codes
7. Project Codes
8. Schedule Update Requirement
9. Things to Avoid in P6
10.Communication Channel & Data Sharing
11.Change Control
12.Recovery/Mitigation Schedule
13.Revised Baseline
14.Upcoming Initiatives
1-General P6 Settings
1.1 Project Window Setting
Following setting to be kept in project window, for baseline and updated schedule
Note: Schedule Must contain PAC and FAC activities and link logically within the network
diagram. PAC and FAC to be kept as “task dependent” activities not as “milestones”
Note: price/unit will only be given to material resource where BOQ cost will be loaded.
3-Weightage and BOQ Cost loading requirements
Weightage must be assigned as labour resource with given proportion at WBS level 1 based on the
type of projects. For contracts that are not awarded and baseline is not yet developed.
BOQ cost must be assigned as material resource in P6, and each main head should be summing up to
exact value given in BOQ. Activity codes must be assigned to capture the values. E.g., Foundation
cost in BOQ should match with Foundation cost assigned in P6.
4-Standard WBS Level 2
Level 1 of WBS should be as directed below regardless of type of project. Contractors can further
breakdown as per work requirement and their practices. If WBS level 1 name, is currently differing
from below given mentioned then they must be changed in baseline and the last update
- Milestones
- General
- Design/Engineering
- Procurement
- Construction & Testing
- Project Close-out (PAC & FAC)
7-Project Codes
Following project codes must be assigned prior to submission of baseline or updated Xer.
- Level 5 Schedule (code value = Level 5 Schedule)
- Level 5 Project ID (code value = N-xxxxx)
- Level 5 BLUP (code value = Baseline, Update)
The code values are shown below in attachments as well. The name and the value of the code
should be similar to the attachment, only code description can vary if end user need to change
8-Schedule Update Requirements
During monthly progress updates in p6, end users need to consider following directions
9-Things to Avoid in P6
Following things to be avoided in P6
12-Recovery/Mitigation Schedule
- If the reported progress variance exceeds beyond the threshold of -10% from the approved
baseline plan and is not recovered for two consecutive reporting cycles, then
Recovery/Mitigation schedule is required to be submitted by Contractor. However,
TRANSCO PM will take final decision for requirement of such schedule.
- Recovery/Mitigation schedule needs to be realistic and will align with the contractual
completion date of the project.
- Once the recovery/mitigation schedule is approved, then the reporting shall be done on this
schedule. Until then, approved Baseline shall be referred.
13-Revised Baseline
- If the reported progress variance and the forecast completion date of the project crosses the
threshold of recovery/mitigation despite efforts materialized by Contractor, then Contractor
will be advised to revise the schedule and provide the realistic expected completion date
considering all the events occurred and future probable events.
- If the float consumption of non-critical part of the schedule is not controlled then TRANSCO
may require detailed reasoning for float consumption and advice for re-baseline.
- Baseline revision will be done after seeking approval from Consultant and TRANSCO as a
result of time extension or management decision.
- While revising the baseline, the actual progress figures till that point will be considered as
planned and remaining effort shall be forecasted.
- Until the approval of Revised baseline, this schedule shall be used as a monitoring schedule
only.
- Once approved, all the reporting shall be done on the revised baseline including s-curves,
histograms, cash flows, etc.
14-Upcoming Initiatives
- For a robust and effective Project Planning & Control, few initiatives are in progress and will
soon be implemented across all TRANSCO Projects.
- Consultants and Contractors shall be notified regarding implementations in due course.
- Few of these initiatives include.
• Unified SMPR and Detailed monthly progress reporting template for both Power &
Water projects
GENERAL REQUIREMENTS
( SPECIFICATION )
SYSTEM CHARACTERISTICS
CONTENTS
SYSTEM CHARACTERISTICS
The following system characteristics and fault levels shall be taken into account for assessment
of the limit states of the electric network into which equipment under contract shall be operated.
The information given hereunder applies to all works in addition to the General Conditions,
Special Technical Requirements, Electrical and Civil Design Fundamentals, unless specified to
greater detail in sections on specific installations.
The design of all electrical equipment and installations shall allow it to operate without any
restriction under any possible combinations of limit states of the system.
1 SYSTEM VOLTAGES
The system voltages under steady state conditions are confined to the following limits, which
shall be used as planning criteria for network analysis as well as for dimensioning of equipment:
Remarks:
** U for Cables
After outage of any one equipment and without any adjustment or corrective measures, the
system voltage shall be within the limits of +/- 10% of the operating system voltage, and
voltages between +5% and +10% will be restored to the original voltage bandwidth within 15
minutes.
2 SYSTEM FREQUENCY
(Refer to: THE ABU DHABI TRANSMISSION AND DESPATCH COMPANY - The
Electricity Transmission Code, Page 53)
400 63 1
220 40 1
132 40* 3
Remarks:
ANNEX-01-1
GENERAL REQUIREMENTS
( SPECIFICATION )
CONTENTS
1 SAFETY ........................................................................................................................... 4
1.1 Standards ........................................................................................................................... 4
1.2 General .............................................................................................................................. 5
1.3 Safety Measures ................................................................................................................ 5
1.3.1 General .............................................................................................................................. 5
1.4 Touch Protection ............................................................................................................... 7
1.4.1 Touch and Step Voltage .................................................................................................... 7
1.4.2 Earthing System ................................................................................................................ 7
1.4.3 Lightning Protection.......................................................................................................... 7
1.4.4 General Fire Precautions ................................................................................................... 8
1.4.5 Escape Passages ................................................................................................................ 8
1.4.6 Standards, Instructional Pamphlets and Safety Sign Boards............................................. 8
1.4.7 Temperatures ..................................................................................................................... 9
2 QUALITY ASSURANCE REQUIREMENTS ............................................................. 9
2.1 General .............................................................................................................................. 9
2.2 Contractors Responsibilities............................................................................................ 10
2.3 Quality Assurance and Quality Control System.............................................................. 10
2.3.1 General ............................................................................................................................ 10
2.3.2 Bidder/Contractor Quality System .................................................................................. 10
2.3.3 Sub-Bidder/Contractor and/or Vendor Quality System................................................... 11
2.3.4 Quality System Processes................................................................................................ 11
2.3.5 Third Party Registration .................................................................................................. 11
2.3.6 Quality Documents to be submitted with Tender............................................................ 11
2.3.7 Quality Documents to be submitted after Tender Award................................................ 12
2.3.8 Quality Management during the CONTRACT ............................................................... 15
2.3.9 QA/QC and Verification Personnel................................................................................. 16
2.4 Quality Auditing.............................................................................................................. 17
2.4.1 General ............................................................................................................................ 17
2.4.2 Conduct of Audit/Audit Plan........................................................................................... 17
2.4.3 Audit Report.................................................................................................................... 18
2.4.4 Audit Schedule ................................................................................................................ 19
2.5 Third Party Inspection Agency (TPIA) ........................................................................... 19
2.6 Inspection Measuring and Test Equipment ..................................................................... 21
2.6.1 General ............................................................................................................................ 21
2.6.2 Calibration ....................................................................................................................... 21
3 HEALTH, SAFETY AND ENVIRONMENT (HSE) PLAN ..................................... 22
4 SAFETY SIGNS ............................................................................................................ 22
5 MANUAL FOR GROUP LABOR ACCOMMONDATION..................................... 22
6 TESTING LABORATORIES ...................................................................................... 23
6.1 Accredited Independent Testing Laboratories (IEC 17025, IEC 17020, EN 45004)...... 23
The following shall form the basis for each Bidder/Bidder/Contractor to optimise his Proposal
with regard to local facts, and to prevailing quality and safety requirements. The general
information given hereunder applies to all plant, equipment and material, unless else specified, to
greater detail in sections on special conditions or specific installations.
Further, general reference shall be made to the Safety Rules of TRANSCO subsidiaries as under:
• TRANSCO HSE PROCEDURE MANUAL
• TRANSCO System Safety Rules Summary – Guidance for Contractors, Competent
Persons and HSE Officers
which shall be followed by all Bidders/Contractors during contract execution, and which will be
made available in its latest version.
TRANSCO System and Safety Rules Requirements shall meet requirements as described in:
01 TR-ANNEX 3 -
1 SAFETY
1.1 Standards
The following Standards shall be applied:
IEC 60446 - Basis and safety principles for man-machine interface, marking and
identification
IEC 60621 - Electrical installations for outdoor sites under heavy conditions
(Describes protective measures intended to ensure the safety of
persons from electrical shock in normal service and in case of fault).
1
The Associated General Contractors of America
BS 5655 - Safety rules for the construction and installation of electric lifts
1.2 General
All installations under the contract shall be designed and constructed in a way that no hazards
can happen to the operators, the public or the installation itself, under normal operating
conditions or any fault in the transmission / distribution systems.
1.3.1 General
It is a prime objective of TRANSCO to obtain electrical installations that offer a maximum
degree of safety for the operators and bystanders under all normal operating and fault conditions.
In particular, it must be impossible to unwillingly, i.e. without the use of tools, touch live parts of
the Switchgear, or perform operations that lead to arcing faults.
i. For mechanical protection of all external parts, a minimum of Protection Class IP 4X for
Switchgear is required, i.e. totally enclosed and inaccessible for parts of particles of a size
larger than 1 mm in diameter during normal operation, but no protection against water. All
high voltage carrying parts must have a minimum class of protection of IP 65, i.e. totally
protected against contact with live parts, and dust-and water.
ii. Should internal arcing occur, the release of pressure into the atmosphere, (if any), shall be
in such a way that personnel standing at a position for operating the Switchgear, will not
get injured. Furthermore, no part of the enclosure or any loose parts may fly off the
Switchgear in such an event, and no holes shall be created in the enclosure during arcing.
All earthing connections must remain operational during and after an arc fault.
iii. All interlocks, which prevent potentially dangerous mal-operations must be constructed
such that they cannot be bypassed easily, i.e. the operator must use tools, keys or force to
bypass them.
iv. The earthing switch must be able to be padlocked in the "EARTHED" position.
v. With the earthing switch in the "ON" position, it must be possible to safely exchange the
breaker element while the remaining Switchgear is live.
vi. Energy storing mechanism of breakers must be totally enclosed with the Switchgear in the
operating condition.
vii. The name or numbering of a Switchgear bay, which has been determined during the
design stage shall be permanent unchangeable marking.
viii. Switchgear bay markings shall be fixed in such a way that they are clearly readable from
each operation point.
ix. Switch position indicators shall be fixed in such a way that they are clearly readable from
each operation point.
x. Busbar markings shall be fixed in such a way that they are clearly readable from each
location of the busbar area.
xi. A provision to separate the earthing system for testing shall be considered in the design.
xii. The fixing points of mobile earthing and short-circuiting devices (IEC 61138) at
Switchgear bays, shall be arranged in such a way, that termination can be carried out
without danger to life. (For fenced Switchgear bays it should be possible to earth the
equipment before the Switchgear bay fence gate can be opened).
xiii. According to the substation size, properly dimensioned grounding and short-circuiting
devices to IEC 61138, shall be available in sufficient numbers. Additionally a voltage
tester shall be made available in accordance with IEC 61010, IEC 61243. The equipment
shall be kept neatly arranged at an easily accessible location.
xiv. A single-line diagram shall be fixed at a central location in the Switchgear hall and in the
control room.
xv. Lighting fixtures shall be designed in such a way that maintenance of the same can be
carried out without danger to life.
xvi. For security reasons, in cases of power supply outages, an emergency lighting with
appropriate power supply system is provided. The emergency lighting and power supply
system shall guarantee emergency lighting and power supply and safety lighting to mark
or illuminate the rescue ways. If the normal lighting system is restored, the emergency
lighting system shall automatically be switched off to the stand-by position.
xvii. Portable emergency lighting with automatic switching ON possibilities, if the charging
voltage fails, has to be arranged additionally at suitable locations.
xviii. Heaters in panels, etc, shall have low surface temperatures.
xix. Portable CO2 and Dry Chemical Type (typically 2 litre) fire extinguisher of suitable sizes
shall be placed and fixed in the Switchgear hall, building entrances, etc. away from the
place, where fire is expected. These extinguishers shall be provided at selected places in
sufficient numbers. Furthermore containers with fire-extinguishing blankets as well as
first-aid devices shall be considered.
xx. Electric shock treatment chart duly framed in a conspicuous position in the Switchgear
room.
xxi. Danger notice in English/Arabic language shall be fixed on each door of the Switchgear
hall.
Salient points of structures shall be incorporated. All metallic projections such as air
conditioning cabins, vent pipes, railings, gutters, steel constructions, antenna, etc. on or above
the surfaces of the roofs shall be connected to the above mentioned network, or shall be used as
part of the protective system.
• The instructional pamphlet: First aid for accidents due to electrical appliance’. Identical
notices shall be displayed or fixed at the Switchgear. On the notice, reference indications to
doctors and hospitals shall be shown
• Other signboards (samples attached in 01 TR-ANNEX 1) shall be fixed at suitable
locations.
1.4.7 Temperatures
In all installations, the surface temperatures of any accessible part, which is expected to be
touched in normal operation, must not exceed 70°C.
The design has to be based on the allowable temperature rise as specified in the relevant
standards taking into account the prevailing maximum ambient temperatures as stated in the
General Design Fundamentals.
2.1 General
All Bidders/Contractors/Sub-contractors and manufacturers of equipment supplied under this
specification shall at the time of bidding and during the design/entire execution period of the
contract, be ISO 9001 or ISO 9000:2000 and ISO 14001 certified.
Furthermore, the Bidder/Bidder/Contractor shall exercise during the project all his internal
quality assurance procedures for which he has received the corresponding certification.
For all site works, the Bidder/Bidder/Contractor must establish in addition to his internal quality
assurance plan, a site quality assurance plan for approval by TRANSCO. The site quality
assurance plan shall cover the subjects of material receipt and testing, responsibilities during
construction and installation, supervision, countermeasures against faulty execution, testing after
installation as well as documentation of all the above.
Quality assurance plans shall meet requirements as specified in Standard Technical
Specification, TR-ANNEX 2:
The acceptance, approval or rejection, of WORKS nor the absence of these, shall not be
construed as a liability on the part of TRANSCO. In any event that the WORKS in question
are found to be defective later on, the sole responsibility lies with the Bidder/Contractor to
remove, replace or repair the defect in accordance with TRANSCO instruction. The
inspection and testing performed by TRANSCO shall not release the Bidder/Contractor from
his obligation under the CONTRACT, nor provide grounds for any extension of
CONTRACT time.
The WORK(S) shall be executed by qualified, experienced and competent personnel who
shall undertake their work in a safe and proficient manner.
All materials, equipment and plant components shall be suitable for arid conditions and
tropicalised to resist deterioration due to the severe prevailing local conditions including
high day time temperatures, high humidity and salt laden winds. Such protection shall
include, but not be restricted to, extra coating of protective materials, robust and protective
packaging, etc.
2.3.1 General
Bidder/Contractor shall be responsible to meet TRANSCO’s minimum requirements for the
Quality Assurance and Quality Control System. The Bidder/Contractor including his sub-
Bidder/Contractor and/or vendor shall ensure strict adherence to the following requirements in
the performance of WORK(S) under the CONTRACT.
The Bidder/Contractor shall remain ultimately responsible for the Quality of all material, plant
and equipment to be supplied, and all WORK(S) to be performed under the CONTRACT
including Sub-Bidder/Contractor’s and/or vendor’s.
Where a Bidder/Contractor and /or his sub-Bidder/Contractor do not have Third Party
Registration, they shall demonstrate that they have a Quality System that complies with ISO
9001:2000.
2.3.6.1 General
The required QA/QC Documents submitted along with the tender shall be used by TRANSCO to
evaluate the Bidder/Contractor’s capability to deliver a quality product or services that will
satisfy the CONTRACT requirements.
a) If the Bidder/Contractor has Third Party Registration, a valid copy of ISO 9001: 2000
Certificate.
Copies of System and Compliance Audit report with satisfactory result prepared by
TRANSCO/Engineer from another similar contract or project.
2.3.7.1 General
In the event of a successful tender or bid by the Bidder/Contractor, a project specific Project
Quality Plan (PQP) shall be prepared (refer to section 7.3) and submitted as per schedule set out
in CONTRACT documents, for TRANSCO/Engineer’s review and comments. The PQP shall
then be submitted to Head of QA/QC Department (or his nominated responsible person) in
TRANSCO for approval.
The approved PQP document shall form part of the CONTRACT. The PQP shall be the basis for
the whole Project Quality Management System implementation and shall be applied throughout
the full cycle of the CONTRACT.
All documents specified or listed in the PQP shall be collated or developed and submitted for
acceptance. Approval process shall follow the same approach as the PQP i.e. review by Engineer
and approval by TRANSCO. The same manner shall apply to sub-Bidder/Contractor’s quality
and work documents.
All documents, procedures, method statements, inspection and test plans, quality control plans,
etc that are listed in the approved Project Quality plan shall be prepared by the Bidder/Contractor
and approved by TRANSCO/Engineer. These documents are considered live documents and if
required, shall be subject to changes, revisions, amendments during the progress or cycle of
WORKS to meet requirements.
Additional documents, procedures, method statements, inspection and test plans, quality control
plans, etc that are not listed in the approved Project Quality plan but found to be required later on
during the execution of works shall be prepared by the Bidder/Contractor as advised by
TRANSCO/Engineer. The control and approval of which shall be in accordance with the normal
procedure.
The Bidder/Contractor shall be responsible for any discrepancies, errors or omissions in the
documents supplied by him, whether such documents have been approved or not.
The approval of revised document shall be as per original procedure and schedule as specified in
the CONTRACT or as advised TRANSCO/Engineer. The Bidder/Contractor shall take necessary
action to change as well all related document/s that are affected by the change / revision to any
document e.g. Project Quality Plan.
a) Index
b) Revision status, together with the control mechanism and a Distribution List. Distribution
shall be as per the CONTRACT but shall include the Head of QA/QC Department,
TRANSCO Projects Directorate.
d) Details on how the Bidder/Contractor’s corporate Quality System shall be applied and
implemented in the project, if applicable.
e) Detailed Scope of Work of the CONTRACT, together with a detailed description of all
Quality related aspects as applicable.
f) Identification of all main work activities and sub-activities to be controlled by the PQP.
h) Organizational structure specific to the CONTRACT identifying functions and job title of
all management and staff down to foreman level. Organizational structure shall establish
a detailed schedule of responsibilities for all key functions that will be utilized in the
i) Lists of applicable documents, Work Instructions, Inspection and Test Plans, and/or
Method Statements, etc. The lists shall be considered as Controlled Documents and shall
be subject to controls set in the Bidder/Contractor Document Control Procedure (see
section 7.0 Documentation).
3. List of CONTRACT specific Work Procedures, Work Instructions, Inspection and Test
Plans, Method Statements, etc., by Bidder/Contractor required to be developed for the
CONTRACT. Denote who is responsible for revising the documentation and the date
when it will be completed.
5. List of forms and formats with unique numbers that will be used in Bidder/Contractor’s
Quality Management System.
6. List of applicable Quality Control Plans (QCP) and / or Inspection and Test Plans (ITP)
to be used in the project. These shall include :
a. List of Corporate Quality Control Plans or Inspection and test Plans with current
revision status and issue date that shall be used on the CONTRACT without revision,
if any.
b. List of Corporate Quality Control Plans or Inspection and Test Plans with current
revision status and issue date that require revision before they meet the CONTRACT
requirements. Denote who is responsible for revising the documentation and the date
when it shall be completed, if any.
c. List of CONTRACT specific Quality Control Plans or Inspection and Test Plans
required to be developed for the CONTRACT. Denote who is responsible for revising
the documentation and the date when is shall be completed.
d. List of CONTRACT specific Quality Control Plans or Inspection and Test Plans by
Sub-Bidder/Contractor for assigned work activities, including those to be developed
or revised.
(Refer to section 9.0 Quality Assurance Auditing for details of Audit Execution Plan)
k) Where the services of a Third Party Certification is required by the CONTRACT, this
section of the Project Quality Plan shall :
2.3.7.4 Presentations
The Bidder/Contractor shall make a presentation for clarifications of Document submissions or
proposals if requested by TRANSCO/Engineer. All necessary arrangements to ensure proper and
successful presentation shall be prepared by the Bidder/Contractor prior to the event.
Presentation activities shall form part of the scope of work of the Bidder/Contractor including its
sub-contractors and/or vendors.
2.3.8.1 General
General and specific quality matters shall be reported by the Bidder/Bidder/Contractor in the
CONTRACT Weekly/Fortnightly/Monthly reports. Example of these quality matters are
summary of test and inspection carried out on site, analysis of Non-conformance and corrective
actions, areas of concern or weakness identified in the Quality System, and others that will be
specified and requested by TRANSCO/Engineer.
2.3.9.1 General
The Bidder/Contractor shall assign sufficient Quality Assurance / Inspection (Quality Control)
and Verification Personnel to the CONTRACT to ensure that the Quality Management System,
Quality Assurance and Quality Control are effectively established, implemented and maintained
throughout the CONTRACT.
Critical requirements that must be followed to ensure compliance to our System Safety Rules.
These include the following;
• The Authorised Person issuing a Safety Document to a Contractor’s Competent Person
must ensure that their competency is valid and permits them to undertake the work.
Check items such as, the Safety Document they can receive, which equipment they can
work on or which type of works they can do, the location they are limited to, the Method
Statement, etc.
• The Authorised Person must clearly identify some important general precautions that the
Competent Person must apply while executing the work.
• The Authorised Person must ensure that the same Competent Person is not receiving
more than one Safety Document. He/She has to make certain that the previous open
Safety Document, if any, has been cleared by the Competent Person before issue of the
new Safety Document. It is the responsibility of the Competent Person to clear the
existing open Safety Document prior to receiving another one. He must ensure that
he/she is not in possession of two Safety Documents simultaneously.
• Safety Documents are not transferable under any circumstance. Competent Persons must
fulfil their responsibility once they have received a Safety Document in their name. If the
Competent Person has to change for some reasons, then there must be a new Safety
Document for the intended works and then only after the previous one is cancelled.
• Competent Persons must only carry out works that is stated in the Safety Document.
They must read the Safety Document, understand it and clarify any aspect they are unsure
about with the Authorised Persons.
• The Competent Person must be on site when ANY works under the Safety Document are
being carried out. If for any reason they must leave the site, keeping the Safety Document
open, they must inform the issuing Authorised Person.
• The Authorised Person is responsible for demarcation of the Safe working area.
2.3.9.2 QA Engineer
The Bidder/Contractor shall assign a QA Engineer at each construction site. There shall be
sufficient inspection personnel to cover all disciplines work and activities, all Sub-
Bidder/Contractor’s work and off site facilities. They shall be independent of the work being
performed and shall have no other duties or responsibilities, unless prior approval in writing is
granted by TRANSCO.
QA Engineers shall report to the QA Manager, corporate or projects and QC Inspector to the QA
Engineer. The duties and responsibilities of QA Engineers and QC Inspectors shall be
established and documented in the PQP.
2.4.1 General
The Bidder/Contractor shall carry out Internal Audits of his Quality System and External Audits
of his Sub-Bidder/Contractor/s and/or vendors on a regular basis throughout the Project period.
Audits shall be carried out in accordance with a documented written Procedure duly reviewed
and approved by TRANSCO/Engineer.
certified Quality Management System Lead Auditor who has passed a Lead Auditor
course registered with IRCA
certified Internal Auditor who has passed an Internal Auditor course registered with
IRCA
The Audit Execution plan shall specify the procedure in the conduct of the audit and shall
include as a minimum:
1. Audit Objective
2. Scope of Audit
Audit Timetable
Auditing Method
TRANSCO/Engineer shall be included on the distribution list for all Bidder/Contractor’s Internal
and External Audit Notifications and shall be invited to participate in audits.
TRANSCO/Engineer reserves the right to choose whether to attend or not to attend the audit. If
TRANSCO/Engineer decides to attend the audit, it also reserves the right to join as an observer
or a member of the audit team.
The Third Party Inspection Agency (TPIA) appointed by TRANSCO shall be entitled at all
reasonable times during manufacture to inspect, examine and witness tests on the
Bidder/Contractor's, SUB-Bidder/Contractor's or VENDOR's or any manufacturer's premises, of
the materials and workmanship of all plant to be supplied under the CONTRACT. If part of the
said plant is being manufactured on some other premises, then the Bidder/Contractor shall obtain
for TPIA or his representatives permission to inspect, examine and test as if the said plant is
being manufactured at the Bidder/Contractor's premises. Such inspection, examination or testing
shall be at no extra cost to TRANSCO and shall not release the Bidder/Contractor from any
obligations under the CONTRACT.
Subsequent to material approval, placing of the order and commencement of production, the
Third Party Inspection Agency shall carry out inspection of the ordered materials/ equipment to
ensure conformity to the approved Specifications. The scope of the inspection shall include for
but not be limited to the following:
- Examine the manufacturer’s production procedures, compliance and compatibility with the
relevant approved Standards, technical specifications and technical schedules.
- Inspect and ensure that production, Quality Control and Quality Assurance Procedures are
adopted and implemented correctly in accordance with the latest approved International
Standards in this field (ISO 9001, 9002 and 9003).
- Review and approve production procedures and carry out approval tests as required in
accordance with the appropriate Standards.
- Witness of all mechanical acceptance tests carried out at the laboratories to ensure that the
samples conform to the requirements of the approved Specifications and applicable
Standards defined therein.
- Continual review of the manufacturer's data book to ensure that it is being kept up to date and
that all relevant documentation is contained therein.
- Verify that all ordered materials have been produced by and originate from the manufacturers
premises.
- Issue recommendation to release for shipment and endorse all shipping documents.
At the end of the complete inspection, the manufacturer Inspector shall issue a complete report
on the ordered materials/equipment confirming that the items are in accordance with the
approved Technical Specifications and Technical Schedules. The report shall also include all test
data and results performed at the manufacturer’s premises, shipment details and expected arrival
of the consignment at Abu Dhabi.
i) Non-conformity description.
The cost of any re-inspections due to the non-conformity will be borne by the Bidder/Contractor.
As and when any plant or equipment shall have passed the tests referred to in this Specification
which involves Third Party Inspection Agency, a certificate to that effect shall be furnished in
writing by the manufacturer/Bidder/Contractor/SUB-Bidder/Contractor/ VENDOR and TPIA.
2.6.1 General
The Bidder/Contractor shall supply all inspection, measuring and test equipment required for
inspection and testing. All equipment shall be robust and suitable for the working environment.
The equipment shall be calibrated at the start of the CONTRACT and re-calibrated as required
by the Manufacturer, CONTRACT specification(s), international codes and standard or, job
conditions.
The Bidder/Contractor shall provide, control, calibrate and maintain the inspection, measuring
and test equipment suitable to demonstrate the conformance of materials with the specified
requirements. Equipment shall be used in a manner which ensures that the measurement
uncertainty is known and consistent with the required measurement capability.
The Bidder/Contractor shall establish and maintain documented procedures to control calibrate
and maintain inspection, measuring and test equipment in accordance with the relevant clause of
ISO 9001:2000
2.6.2 Calibration
All calibration shall be carried out against certified equipment having known valid relationship
to internationally or nationally recognized standards. Records shall be available for review by
TRANSCO/Engineer and shall be kept and maintained by Bidder/Contractor at construction
site/work location. Instruction on the use and maintenance of the equipment shall be available at
the Work Site.
Bidder/Contractor shall ensure proper and adequate equipment handling, preservation and
storage to maintain its accuracy and fitness.
Calibration interval of all inspection, measuring and testing equipment shall be specified by the
Bidder/Contractor in a documented procedure that is acceptable to TRANSCO/Engineer.
01 TR-ANNEX 3 -
4 SAFETY SIGNS
The application of Safety Signs (enclosed in 01 TR-ANNEX 1) shall be as follows:
6 TESTING LABORATORIES
6.1 Accredited Independent Testing Laboratories (IEC 17025, IEC 17020, EN 45004)
The below listed Accredited Independent Testing Laboratories are accepted by TRANSCO:
Name Country
KEMA The Netherlands
EdF France
IPH Germany
PEHLA Germany
FGH Germany
CESI Italy
ASTA U.K.
Name Country
KEMA The Netherlands
PEHLA Germany
CESI Italy
ASTA U.K.
GENERAL REQUIREMENTS
( SPECIFICATION )
CONTENTS
The following shall form the basis for each Bidder/Contractor to optimise his Proposal with
regard to local facts, and to prevailing technical realities.
The general information given hereunder applies to all works in addition to the General
Conditions, System Characteristics, Electrical and Civil Design Fundamentals, unless specified
to greater detail in sections on specific installations.
2 FUTURE EXTENDABILITY
In addition to the design of installations under contract, the Bidder/Contractor has to provide by
his layout for future extensions as indicated in the scope of supply or tender layout drawings.
Such future extensions shall be facilitated without having to reconstruct any existing installations
or civil works, e.g. cable channels, buildings etc.
CO2-Bottles Rooms, 30 ± 2 K 25 ± 2 K n. a. 60 3 x 50
Stores, Janitor Rooms,
Staircases, Corridors, Aux.
Transformer, Capacitors,
Reactor, Compensator and
Inverter Rooms,
Trenches/Shafts, Cable
Floor/Basement/Tunnel
and similar Rooms
4 SOIL CONDITIONS
The following conditions are to be used for tender purposes only, but have to be verified by
Bidders/Contractors individually at actual where relevant, depending on the installation location:
Soil thermal resistivity (g) : 120 cm0C/W
Seabed : 80 cm0C/W
Al Ain Area:
29°C at 50 cm depth
Earth resistivity:
100 Ohm-m
5 LIGHTING SYSTEMS
5.2.1 Location: Relay and Telecommunication rooms, Control rooms and Offices
Recessed mounted, 600X600mm luminaire with 3900lm LED. Fixture shall sheet steel housing
with white color. Diffuser shall be UV-stabilized opal acrylic with luminaire efficiency greater
than 95lm/W. Protected to IP44 from below and IP20 from above. Complete with 4000k LED.
Fixture shall be CE or ENEC approved.
Recessed mounted, 600X600mm luminaire with 3900lm LED. Fixture shall sheet steel housing
with white color. Diffuser shall be UV‐stabilized opal acrylic with luminaire efficiency greater
than 95lm/W. Protected to IP44 from below and IP20 from above. Complete with 4000k LED.
Fixture shall be CE or ENEC approved.
Moisture‐proof diffuser luminaire LED. Body made of hardly flammable, glass fibre-reinforced
polyester (GRP). Non‐ageing polyurethane foam gasket (PU). LED optical system with ESD
protection, suspendable and clip‐fastenable mounted on white sheet steel reflector. Captive,
highly resistant, articulated catches made of polyamide (PA), or special steel catches (Inox).
Diffuser made of polycarbonate (PC) with internal longitudinal prisms or
polymethylmethacrylate (PMMA) with pearl structure or as clear version. With automatic
terminal. Completely halogen‐free luminaire. IFS / BRC approved. IP67 protection. Luminaire
shall ENEC or CE certified.
Slim surface/Wall mounted LED luminaire. Electronic, fixed output control gear. IP44
protection. Body
shall be white painted galvanized sheet steel, white plastic end caps and frosted acrylic diffuser.
Complete with 4000K LED. Fixture shall CE or ENEC certified.
Luminaire shall be LED high-bay includes die-cast Aluminium housing in matt, white. Powder-
coated cooling ribs for optimum thermal management and minimal dust accumulation. Cover of
transparent polymethylmethacrylate (PM) and additional glass cover (safety glass) for
challenging industrial applications. Colour temperature 4000 K. Sealed, high-efficiency optical
lens system, Luminaire with symmetric wide light distribution (wide beam) square, UGR <25.
Luminaire wired with halogen-free leads. degree of protection. Fixture shall CE or ENEC
certified.
Compact, lightweight, general purpose LED area floodlight. Large body with symmetrical or
asymmetric highly efficient beam light distribution. IP66, IK08 protection. Body shall be
die‐cast Aluminum (EN AC‐46000), painted grey with 4mm thick toughened enclosure glass.
Reversible mounting stirrup. Complete with 4000K LED. Fixture shall CE or ENEC protected.
Compact, lightweight, general purpose LED area floodlight. Small body with symmetrical or
asymmetric highly efficient beam light distribution. IP66, IK08 protection. Body shall be
die‐cast Aluminum (EN AC‐46000), painted grey with 4mm thick toughened enclosure glass.
Reversible mounting stirrup. Complete with 4000K LED. Fixture shall CE or ENEC protected.
The lighting design shall consider a maximum power allowance of 10.75W/sqm for the total
indoor area (the corridors shall not be considered for this average value) in order to achieve the
objective of energy efficiency.
The entry of natural daylight into switchgear building rooms through any kind of windows shall
not be reduced by air-conditioning ducts or any other structures.
• For panels facing the wall, 0.8 m space at any point when the doors are completely opened
• For the final extension, less than 90 % of the total space for panels shall be utilised.
SVC Hall
• Min. 2.5 m space for easy access, maintenance and repair or replacement of any equipment
(e.g. thyristor modules, etc.).
Power Transformer/Neutral Reactor or Resistor Bays
• Min. 1.5 m space from any part of the walls to any part of the Transformer/Neutral
Reactor/Resistor shall be maintained.
Capacitor Bank / Stand-By Diesel Generator Rooms
• Lifting Device hook height shall allow easy exchange of the largest part of the Capacitor
Bank / Stand-By Diesel Generator Set for maintenance or repair and for extensions
• Space for one additional Capacitor Bank/Stand-By Diesel Generator Set for replacement
(emergency) of one existing Capacitor Bank/Stand-By Diesel Generator Set
• Min. 1.5 m space from any part of the walls, I-beans, HVAC ducts (excluding the depth of
local control and wall mounted pilot wire cubicle, etc.) to any part of the Capacitor Bank /
Stand-By Diesel Generator shall be maintained.
Battery Room
• Min. 1.5 m space from any part of the battery bank(s) for easy access, maintenance and
repair or replacement of any battery cell
• The highest battery rack shall be kept at a level to allow easy maintenance of any battery
cell. No more than three tires shall be considered.
Any Electrical Room/Hall
• Min. 1.0 m space from the highest point of each equipment to the underside of lowest
concrete/steel beam shall be maintained.
Free Standing Panels
• Min. 1.0m space in front and at back side of battery charger, LVac, LVdc, Protection,
Telecom, etc. Panels.
7 PHASES ARRANGEMENT
• Switchgear
View from LCC to the Switchgear: RYB from left to right.
• Transformers
Highest voltage bushings (view from the side of the Transformer where the highest voltage
bushings are located): UVW (RYB) from left to right.
8 SOFTWARE
Prior to any computer programme calculation, the Bidder/Contractor shall agree with
OWNER/ENGINEER as to what type of software shall be applied.
If the finally agreed calculation software programme is already available with TRANSCO it
should be updated (if it is not the latest version) otherwise the applied software shall be supplied
to TRANSCO and a software training shall be included in the Contract price.
01 August 2009
Revision 3
TRANSCO HSEQ Department
TRANSCO GUIDANCE SHEET
This sheet will give you all the information you need to pass the test and interview successfully first time.
Transco want candidates to pass first time, but candidates must be prepared. PLEASE READ IT
THOROUGHLY
How to successfully become a Transco recognized Competent Person or a HSE Officer
3rd Party Contractors (for Competent Person)
1. Obtain from Transco Engineering Services Notice of Intent with drawing and bring the documents to the
Transco HSEQ Office, on the Ground Floor. You will then receive a copy of this Guidance booklet.
2. Obtain a Competent Person Interview Request letter from your company, which must include: See other
page for complete template as required and completed. Note required attachments.
o Clearly identify the project number, location & nature of work, (eg. Near 132 kV UG Cable/Crossing
Water Pipeline/Under Overhead Line) include in your letter the candidate detailed resume (CV).
o Appropriate Specific Work Method Statement including your Risk Assessment for the work you
wish to undertake near Transco facilities (3rd Party Contractors Only). Items to be covered in a Work
method Statement are; Scope, Terminology, References, Roles & Responsibilities, Emergency
Procedures, Significant Risks & Control measures, The Safe Method, Resources & Key
interfaces.
3. The appointed candidate must have the following qualification:
o Relevant professional qualification in the work required, electrical engineer for electrical work etc.
o Relevant work experience.
o A good basic HSE awareness of the work to be supervised and the associated hazards including
emergency procedures
o First aid & fire fighting training and present relevant certificates.
o Good communication skills in English. Must be able to demonstrate conducting a Toolbox Talk.
o Safety Officer /HSE Engineers not accepted to be appointed as a Competent Person.
4. Return all the above to the Transco HSEQ Office completed correctly and a test & interview date will be
arranged. This will be arranged within approximately 3 weeks after the request letter and relevant documents
have been received, completed correctly. Only then will an appointment be made for the test & interview. An
incorrect completed request letter or documents will delay the test and interview appointment.
5. The appointed candidate shall read & understand the Transco Contractor System Safety Rules Summary
(HSE Officers this will be the HSE Project Plan) on his own before attending the written test & interview. If
they are unsure on any items, they must seek help and assistance from their company’s senior HSE person.
They should also fully understand their company Risk Assessments and Method Statements for the works.
6. Candidates must come prepared, have spent at least 3/5 days reading and understanding this booklet,
only those that successfully score 90% and above on the test will proceed to the interview stage.
7. The test questions are multiple choice, although some written answers will be required, but all the answers
are contained within this booklet, (see following pages) and your companies Risk Assessments and Method
Statements. For HSE Officers, the questions are basic HSE questions that all HSE Officers should know.
8. The candidate must turn up on the given date and at the required time. Failure to turn up at the required time
will result in the test & interview being cancelled and counted as one unsuccessful attempt.
9. The candidates will only have two opportunities to be successful.
For Transco Project Contractors (2nd Party Competent Person or HSE Officer)
1. Clearly identify in their request letter the project number, location & nature of work (within Transco Premises),
include CV and any other approved competency certificates.
2. Follow step 2 to 9 above.
Submission of Requests for Test/Interview and/or any other related issues on the following working days and
working times:- (handled by HSEQ Assistant)
Date:
Reference No:
Contact e-mail:
To: HSEQ Manager
Abu Dhabi Transmission & Despatch Company (TRANSCO)
Please arrange for below mentioned to be interviewed by Transco HSE Engineer for qualifying as a
Competent Person for works near/on Transco premises.
We confirm that the Competent Person must never leave the work site during works commencing
under Transco System Safety Rules.
Regards,
Attachments:
- Candidate CV
- Reply Notice of Intent issued from Transco (first issue & latest renewal)
- Work Method Statement includes Risk Assessment
- Basic First Aid Training & Basic Fire Fighting Training Certificates copy
- Other Company Competency Certificates copy
- Passport copy with valid visa page or Labour card copy.
*Note: The appointed candidate shall read & understand the Transco System Safety Rules on his own
before attending the Written Exam & Interview. And present proof of achieving First Aid & Fire Fighting
Training.
SUMMARY SYSTEM SAFETY RULES (Rev.3 010809)
PRINCIPLES
1. System Safety Rules are intended to protect persons from inherited system hazards
2. Only competent persons can undertake works in TRANSCO premises after receiving a Safety Document (SD)
3. Authorized Person (AP) assesses all risks & applies System Safety precautions before issuing the (SD).
4. Equipment must be clearly identified in (SD) (matching equipment label on site)
5. Operation of equipment is by direct communication, operation by prearranged signals or timing is not allowed.
6. Competent Person (CP) must be present on site all time during work, controlling all activities & persons.
7. Safety Document must be retained by the CP on site.
GENERAL DEFINITIONS
Hazards Sources of dangers to persons
Safe Free from Hazards
System Equipment interconnected in a network (Electrical, Water, Telecom Network)
System Hazards Hazards present (inherited) in a system (Electrical, mechanical, chemical, pressure)
System Safety Precautions to control system hazards, applied by an Authorized Person.
Example: Isolation, earthing, safety document, safe method of work, applying demarcation,
danger / caution notices, labeling, venting, draining, purging & release of stored energy, PPE
General Hazards Non system Hazards like excavation, lifting, scaffolding, ladders, hot works, tools, etc.
General Safety Precautions to control non system hazards, maintained by a Competent Person
Example: Shoring, barriers, training, supervision, approved procedures, safe method of work,
inspection of certificates tools &equipment, on site risk assessment, toolbox talks, PPE etc.
Release of Energy Means Venting, draining, purging, or braking, or spring release.
Key Safe Key A unique Key for locking the Key Safe at work location, given to CP by the AP
High Voltage (HV) A voltage exceeding 1000 volts.
PPE Personal protective equipment (helmet, safety shoes, gloves, coveralls, high-vis etc.)
Receipt Means that CP has agreed that he/she fully understands the work and is satisfied of applied
system safety precautions and accepts full responsibility to maintain the safety and supervise
the work.
Clearance Means a declaration by the CP that all persons, materials & tools are removed from work
area and it is cleaned and tidy
LDC Load Dispatch Center
Isolation Point The point at which equipment has been isolated to provide physical separation
Primary Earth Conductor that protects from accidental operation while working on HV equipment (min. 95
2
mm )
Additional Earth Conductor that protects from induced voltage while working on HV equipment. (Min. 25 mm2)
Toolbox Talks An onsite communication between the CP and his/her working party before the start of work
conducted each day early in the morning. Must include, work to be done, hazards, control
measures, Emergency procedures, working environment, any changes from previous day,
check PPE and tools.
Earthing Schedule A schedule indicating the additional earth requirements for each stage of the work necessary
to control induced voltages as circumstances change
Safety Clearance The distance from the nearest exposed HV conductor not earthed, or from an insulator
supporting an exposed HV conductor, which must be maintained at all times to avoid danger
to persons. 5.5m for 400kv, 4m for 220kv, 3m for 132kv, 1.5m for all HV conductors up to
33kv, (Note: HV insulators minimum safety clearance distance= 0.5m)
DEFINITION OF AUTHORITIES
Competent Person (CP) A person, having suitable & sufficient technical Knowledge & experience to recognize &
avoid danger, use safe method of works & use appropriate PPE, receives & clear SD.
Authorized Person (AP) A competent person who have been additionally authorized to Issue & cancel Safety
documents, he assess all work risks & apply system safety precaution before start of any
work.
Control Person A person who controls the transmission system (from LDC) & coordinates system safety
activities
SAFETY DOCUMENT PROCEDURE (CP, only one SD, one place, at one time for your discipline)
No Person Actions
1 Competent Apply before 2 - 7 days from work start, include detailed method statement for work to AP
2 Authorised Review application for work & Submit to (LDC – planning section) for approval
3 LDC Approve application & return to authorised
4 Authorised Asses all risks on site, Apply System Safety Precautions, obtain consent from a Control
Person in LDC & finally sign & issue the Safety Document to the Competent Person.
Read, understand and check SD, only then sign & receive SD, conduct toolbox talk, start
5 work & maintain general safety, follow and only do the work on the SD, follow method
Competent
statement, supervise 100% of time, NEVER PROCEED IF YOU ARE UNSURE OR IN
DOUDT, always contact AP for help, advice and clarification.
6 Competent Sign clearance after completion of work & removal of persons, tools from location.
7 Authorised Sign cancellation after inspecting the work area
Permit to Work For works requiring secure isolation followed by Earthing or Release of stored
energy. See an example of a filled PTW for work on a Transformer (overleaf)
Limited Access Permit Safety is achieved by applying limits to work and/or work area. See an example of
a filled LAP for crossing an OHL (overleaf)
Sanction for Test For works requiring injection of high voltage or current and which may require the
removal of primary earths. All PTW must be cancelled first.
Lock Lock
Earth
Earth
The limits of Safe Work Area must be physically identified by Red & White tape or chain with Danger notices displayed at the
limits, facing into the Safe Work Area (inside). Work is not allowed on an established isolation point
5.5 meter
Safety-Key is locked inside Displayed facing Used to identify 400kv OHL safety clearance distance
key-safe by 1 Control-Key and into the Safe Work Area Points-of-Isolation measured from HV conductor
4 key-safe-keys
! Important: This summary is a simplified guide for understanding the basics of Transco’s System Safety Rules; it does not replace the
complete Transco System Safety Rules book for working on the system
VIOLATION OF SYSTEM SAFETY RULES
Common violations of Transco’s System Safety Rules (SSR) by Competent Persons include the following. Please
remember that this list is indicative only and not exhaustive.
• Competent Person receives safety document (LAP, PTW or SFT) and the work starts. While the works are in
progress, Competent Person is not available on site. This is a major violation. The competent must always be
present on site all the times supervising his working party for the period while the work is in progress.
• Competent Person receives more than one safety document. He may have finished his work; but as long the safety
document is not cleared by him and cancelled by the relevant AP, he/she cannot receive another safety document.
• Competent Person receives safety document for work that is not covered by his existing competency. This includes
both the project and nature of the work. It is responsibility of the CP not to apply for works that are not covered by
his competency.
• Competent Person take on work that is not compatible with the work, equipment and location mentioned in the
safety document. It has to be known that the CP is allowed to do only what is mentioned in the safety document. It
is for this purpose that CP is expected to read and understand the safety document before signing (or receiving) it.
PENALTIES
The above mentioned violations, though not exhaustive, are subject to penalty. Any competent person who is found to
have conducted these violations WILL have his COMPETENCY WITHDRAWN immediately and will not be considered
for competency again. There is zero tolerance to not complying; no matter how minor the violation may be.
This booklet is designed for TRANSCO Contractors & Contractors who
work near or on TRANSCO facilities.
This booklet is the property of TRANSCO, and cannot be used nor given
to outside party without prior authorisation.
First Appointment:
Name: __________________________________________________________________
Date: _______________________________Time________________________________
I agree to turn up on the correct date and time allocated for me and will come
prepared:-
Sign: ________________________________________
Second Appointment:
Name: __________________________________________________________________
Date: _______________________________Time________________________________
I agree to turn up on the correct date and time allocated for me and will come
prepared:-
Sign: ________________________________________
GENERAL REQUIREMENTS
( SPECIFICATION )
5.1 Preparation, Approval, Issue and Revision of the Project Quality Plans
6.0 Procedures, Work Instructions & Checklists (Corporate & Contract Specific)
TRANSCO Company
6 TRANSCO
Representative
Corporate
Quality Manual
Project
Quality Plan
Key Document
Work Instructions
Audit Checklists
(Note: The following listing is purely for example purposes and is not intended to be a definitive
list of Procedures for a particular type of Contract).
Contract Management
Contract Review
Project Quality Plan
Planning & Scheduling
Document Control
Labor, Materials & Plant Resourcing
Provisional Acceptance Certificate
Training
Quality Auditing
Technical Queries
Tend Notice & Variations
Control of Non-Conforming Product
Corrective Action
Third Party Certification (if required in Scope of Work)
Design
Design control
Drawing control
Design Verification & Technical Reviews
Control of Specifications, TRANSCO Standard Specification, Codes & Standards
Preparation of Requisitions
Materials Tracking & Reporting
Reviewing Vendor Documentation
As Built Information
Operation & Maintenance Manuals
Procurement
Mechanical Works
On Plot Piping
Off Plot Piping
Welding
Installation of Static Equipment
Installation of Rotating Equipment
Painting & Coating
Non-Destructive Examination NDE
Electrical Works
Safeguarding
Installing Instrumentation
Instrument Air Supply
System Cabling
DCS Systems
SCADA
Factory & Site Acceptance Testing
Installation of Telecommunication Equipment
APPENDIX B
S. No. Description of Equipment Tests required Number of visits Third Party Remarks
to be witnessed by TRANSCO/ Inspections
by TRANSCO/ ENGINEER’s required
ENGINEER’s Representatives
Representatives
(Yes/No) (Yes/No)
1. 3ph Electricity Meters Y 1 No
Direct Connected
3.
Notes:
(1) Details of equipment requiring witness testing by TRANSCO/ENGINEER’s representatives, number of visits and/or
Third Party Inspections shall be filled by TRANSCO considering the requirements of each project.
(2) Cost of witnessing the tests by TRANSCO representatives shall be borne by TRANSCO.
CONTENTS
1 GENERAL ....................................................................................................................... 3
1.1 Drawings .................................................................................................................................. 3
1.2 Equipment Identification and Color Codes ............................................................................. 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 General ..................................................................................................................................... 3
2.2 Red/White Painting .................................................................................................................. 3
2.3 Aircraft Warning Spheres ........................................................................................................ 4
2.4 Obstruction Light Equipment for Towers................................................................................ 4
2.5 Obstruction Light Equipment for Conductors (Optional) ....................................................... 5
2.6 Installation and Maintenance ................................................................................................... 6
2.7 Testing ...................................................................................................................................... 6
1 GENERAL
This part of the specification covers design, manufacture, testing, erection and commissioning of
overhead line aircraft warning systems.
For applicable technical standards, tests and general requirements please refer to:
S-TR-OHL-GEN - General Requirements (Applicable Technical Standards, Tests,
etc.)
1.1 Drawings
Typical Drawing for Obstruction Light for Conductors provided in the Drawings Section is as
follows:
Drawing No. Title
DWG TR OHL 07 01 Obstruction Light for Conductors
2 TECHNICAL DESCRIPTION
2.1 General
Line sections located in height restricted areas, or otherwise defined by TRANSCO shall be
provided with visual aids for denoting obstacles, conforming to the Chapter 6, Annex 14, to the
Convention on International Civil Aviation. The aids may comprise one, two or all three
measures detailed hereunder.
If actually required, corresponding provisions are made in Scope of Work/Scope of Supply and
Bills of Quantities.
The warning spheres shall be of Fiber Reinforced Polyester with a diameter of at least 600 mm.
Spheres shall consist of two individual halves for easy installation. The fixing clamps of the
spheres shall match the preformed armour rods to be supplied for each sphere, to be mounted
between sphere and earth wire/OPGW. Aircraft warning spheres shall be with drain holes.
Bolts/Nuts for fixing aircraft warning spheres shall have safe-lock-nuts.
In the preparation of the sag and tension tables, and for the tower calculation, the additional
weight and wind load shall be taken into consideration, regardless if warning spheres have to be
provided under this Contract, or in future only.
All systems shall be covered by a min. 5 years unconditional guarantee of a maintenance free
system performance. “System performance” shall be understood as the reliable automatic
illumination during all periods of darkness, with a visible minimum light intensity a stipulated by
the a.m. ICAO document.
For the system dimension, Bidder/Contractor’s attention is drawn to the fact that measurements
performed in the past on photovoltaic modules installed at 450 inclination (best compromise
between winter load and module self-cleaning) have revealed a drop in module output of 50-60%
due to dust accumulation within two months of installation. Module self-cleaning by rain cannot
be considered in the system dimensioning. Although the daily sunshine hours in Abu Dhabi
Emirate are generally high, there may be extended periods of overcast conditions. It has proven
advisable to design systems with not less than 5 days redundancy in terms of battery capacity.
Batteries and system controller/charge regulator shall be housed in suitable enclosure, protecting
these components from environmental affects like temperature peaks due to direct solar
radiation, dust, condensation, etc. For additional protection from direct sunlight, the enclosure
shall be placed in the shade of the photovoltaic module(s). The upper edge of the photovoltaic
module(s) and lamp shall be fitted with stainless steel needle strips, effectively preventing birds
from sitting in this location. All components shall be corrosion proof in a marine environment. If
stainless steel is used, only Grade A4 will be acceptable. Proposed LED lights are required to
bear the approval of Abu Dhabi Government’s Department of Civil Aviation. To minimise
degradation of luminous flow due to dust accumulation, the outer glass protection of the LED
cluster shall have a smooth surface.
Contractor need to specify in their Notice of Intent to Civil Aviation Department, if there is any
existing Over head line which is running parallel already equipped with Aircraft Warning
Spheres and Aircraft Warning Lights. Contractor should also ask about the type of light (such as
low and medium intensity) required in the Notice of intent.
For Road crossing towers including adjacent span and towers, Aircraft Warning Spheres and
Aircraft Warning Lights shall be installed.
tube; thus the light is not subject to the vibrations transmitted by the cable, thereby eliminating
risk of deterioration.
The auxiliary conductor shall consist of metallic material insulated from the overhead line
conductor to produce by capacitive effect the electrical energy necessary to operate the lamp.
The geometry of the auxiliary conductor shall depend on the overhead line and it’s operating
voltage. The auxiliary conductor shall consist of long tubes of high-grade aluminium; the
number and configuration shall be determined by the conditions of operation. The length of the
auxiliary tube is inversely proportional to the voltage of the overhead line. The system shall be
suspended by composite type silicone long rod insulators. Fittings shall be such as to avoid any
problem of electric coupling with the overhead line conductors and shall fit exactly the diameter
of the overhead line conductors.
2.7 Testing
Testing, sampling and the Site Acceptance Test (SAT) of the aircraft warning spheres,
obstruction light equipment and lighting the wires of high tension overhead line systems shall be
performed in accordance with the relevant Standards, and to be carried out after minimum one
month from erection.
Vendor/Contractor shall submit work method statements with the producers for TRANSCO
Review and Approval. And latest products catalogues including detailed specifications also to be
submitted.
SAT tests shall not be limited to the following tests/measurements (solar lamp glowing (day &
night), AWL output voltage, battery charger status).
If type test reports covering the offered equipment are available, repetition of these tests may be
waived, at TRANSCO’s discretion.
CONDUCTORS / EARTHWIRES
CONTENTS
1 GENERAL ....................................................................................................................... 3
1.1 Equipment Identification and Color Codes ....................................................................... 3
1.2 Sag and Tension Calculations ........................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 Conductors ........................................................................................................................ 3
2.1.1 Standards ........................................................................................................................... 3
2.1.2 Surface Conditions ............................................................................................................ 3
2.1.3 Reels .................................................................................................................................. 4
2.1.4 Adjustment of Metal Prices ............................................................................................... 4
2.2 Earthwire ........................................................................................................................... 4
2.2.1 Standards ........................................................................................................................... 5
2.2.2 Surface Conditions ............................................................................................................ 5
2.2.3 Shipment............................................................................................................................ 5
2.3 Installation of Conductors, Earthwires/OPGW and Accessories ...................................... 5
2.3.1 Requirements ..................................................................................................................... 5
2.3.2 Clearances ......................................................................................................................... 5
2.3.3 Laying of Conductors and Earthwire ................................................................................ 6
2.3.4 Splices ............................................................................................................................... 8
2.3.5 Sagging .............................................................................................................................. 9
2.3.6 Dampers, Spacers ............................................................................................................ 10
2.3.7 Jumper Loops .................................................................................................................. 10
CONDUCTORS / EARTHWIRES
1 GENERAL
This part of the specification covers design, manufacture, testing, erection and commissioning of
overhead line conductors.
For applicable technical standards, tests and general requirements please refer to:
➢ S-TR-OHL-GEN - General Requirements (Applicable Technical Standards, Tests,
etc.)
2 TECHNICAL DESCRIPTION
2.1 Conductors
The particulars of the conductors to be supplied shall be as indicated in Technical Data Sheets.
2.1.1 Standards
The conductors shall be manufactured and tested in accordance with Standards as indicated in
Technical Data Sheets.
Conductors to be applied in bundles shall be stranded on the same stranding machine in order to
minimize settling differences. Designation and number of the stranding machine and date of
manufacturing shall be provided to TRANSCO and must be stated on the conductor drums.
2.1.3 Reels
The conductors shall be delivered to erection sites on reels conforming to DIN 46 391. They
should contain nearly equal lengths of conductor with a minimum length per reel as indicated in
Technical Data Sheets. Returnable steel drums are also acceptable.
Reels shall be plastic clad inside. The reels shall be sufficiently sturdy and of sufficiently large
drum diameter to provide protection against damage during shipping, storing in tropics, handling
and stringing operations.
The reels shall be protected by a hard wooden lagging on the drum circumference with a total
thickness of at least 50 mm. The lagging shall be provided in two layers, suitably staggered in
order to avoid ingress of any foreign matter during transport and storage at Site. The lagging
shall be applied only after conclusion of the material acceptance test, at manufacturer’s premises.
For the test, all drums shall be open and accessible, for visual inspection.
For marking of the reels, reference shall be made to the Standard Technical Specification, Part:
➢ S-TR-OHL-GEN - General Requirements (Applicable Technical Standards, Tests,
etc.)
2.2 Earthwire
The particulars of the earthwire to be supplied shall be as indicated in Technical Data Sheets.
2.2.1 Standards
The earthwire shall be manufactured and tested in accordance with IEC and ASTM standards as
applicable or such other standards as may be approved and with the requirements set out in the
Technical Data Sheets.
2.2.3 Shipment
The same precautions as for the line conductors shall be taken for earth wires with regard to
packing and shipment.
2.3.1 Requirements
The conductors and earthwires shall be installed by tension stringing methods, only. Under no
circumstances shall the conductors and earthwire be allowed to come into contact with the
ground or the sea (as applicable) or with guards, scaffolds, etc. used to facilitate crossings.
In case of conductor damage during installation TRANSCO reserves the right to reject the
complete drum, which shall then be replaced at the Bidder’s/Contractor’s expense.
The Bidder/Contractor shall sag the conductors and earthwire in accordance with the initial sag
and tension tables to be prepared by him, based on the final sag and tension data.
2.3.2 Clearances
Requirements for the minimum clearances between live conductors and other objects, which
correspond to the final maximum conductor sag conditions, are stated in Schedule D of Standard
Technical Specification, Part:
➢ S-TR-OHL-T - HV Towers of Lattice Steel Design
For other objects, not listed in this Schedule, the requirements for minimum clearances shall
comply with Standard DIN/VDE 0210. In certain cases, to be communicated to the
Bidder/Contractor during line routing and survey, special clearances, exceeding Schedule D of
Standard Technical Specification, Part:
➢ S-TR-OHL-T - HV Towers of Lattice Steel Design
The stringing equipment and operation shall be such as to avoid over-stressing tower structures
or foundations. Any damage to towers or foundations occurring in such an operation shall be
made good at the expense of the Bidder/Contractor.
Conductors and earth wire shall be strung carefully to avoid loosening of strands, scraping, nicks
or other damage. Bends of less than the minimum bending radius of 20 times the
conductor/earthwire diameter will not be permitted.
After opening of the protective lagging, all conductor drums shall be carefully inspected, for
protruding nails or other potentially damaging items. During paying-out conductors and
earthwire/OPGW, they shall be inspected continuously for any damage, by running through
cotton waste rags, operated by staff designated specifically to this task. Any damage detected, as
well as any damage caused during stringing, shall immediately be reported to TRANSCO, who
will decide on the method of repair or replacement.
The stringing operation shall be executed with due regard to the safety of the OHL, of personnel
and the public. While conductors are being run out, and when being tensioned and finally clipped
in, all conductors shall be earthed by the Bidder/Contractor at points approved by TRANSCO.
For safety of airborne traffic, operating in height restricted areas, the earthwire shall be strung
prior to the conductor and the aircraft warning spheres shall be installed the same day the
earthwire is strung.
Crossing of Public Services :
When the Bidder/Contractor is about to carry out erection of the conductors along or across
power lines or telecommunication circuits or public roads, he shall be responsible for obtaining
consent from TRANSCO of the respective service for his intended work. The Bidder/Contractor
shall give adequate prior notice to the appropriate authorities of the date and time at which he
proposes to carry out the work.
The Bidder/Contractor shall supply and install all guard structures required for crossings over
electric supply and communication lines, roads, highways, obstructions, and for the protection of
the conductor. All guard structures shall be of adequate strength to withstand the stresses to
which they may be subjected. The erection and removal of guard structures is subject to the
approval of TRANSCO. Approved gantries for height restrictions at road crossings during
stringing shall be installed as advised by TRANSCO, without any extra costs.
In addition, the Bidder/Contractor shall supply and install a steel pole-mounted sign boards 250
meters ahead of the points of which OHL crossing a public road (in a way not to be removed by
public). Boards shall face all traffic directions defining the maximum allowable vehicle height.
Boards shall be long lasting as OHL life and according to the specifications of the drawing
number (DWG TR CIV 15).
The use of mid span compression joints for the purpose of pulling out conductors during erection
and the use of insulators and line materials in general for erection purposes will not be allowed.
Auxiliary erection clamps, or hauling devices shall be of approved design, and shall under
erection conditions, allow no relative movement of strands or layers of the conductors. If
required by TRANSCO this property shall be demonstrated by actual test.
Cutting of layers of conductors shall be carried out with tools designed not to damage underlying
strands. Cropping or shearing of complete conductors shall not be permitted. The cut ends of the
conductors and the joints, clamps and fittings attached to the conductors themselves, shall be
treated in an approved manner to prevent ingress of moisture.
Conductors for multi conductor bundles shall be pulled out together and treated in a similar
manner to ensure that the behaviour of each sub conductor remains compatible.
The sequence of running out shall be from the top downwards i.e. the earthwires shall be run out
first, followed by the conductors in succession.
The transmission lines may run parallel to and in fairly close proximity to other transmission
lines, which are energised. In such conditions dangerous voltage build up can occur in the line
being erected. The Bidder/Contractor shall provide suitable earthing procedures and safe
working practices to protect his workmen and others during construction of the line. Such
procedures shall form part of the HSE Plan and the Method Statement on construction to be
provided by the Bidder/Contractor and shall be to the approval of TRANSCO.
2.3.4 Splices
Distribution of conductor lengths available shall be optimized, to arrive at a minimum total
number of joints.
All joints on the conductor and earthwire shall be of compression type, in accordance with the
recommendations of the manufacturer for which all the necessary tools and equipment, such as
compressors, dies etc shall be arranged by the Bidder/Contractor. Each part of the joint shall be
cleaned by wire brush to make it free of rust or dirt etc. and properly greased with anti-corrosive
compound, if required, and as recommended by the manufacturer before the final compression is
done with the compressors.
In case a conductor is damaged, in one point only, to an extent not exceeding 1/6th of the strands
of the outermost layer, either broken or nicked deeper than one third of its diameter, a repair
sleeve shall be installed. Where this limit is exceeded, respectively the damage is not punctiform,
the damaged section of the conductor shall be cut and spliced with a strain compression joint.
The number and location of tension joints for conductor and earth wire shall be approved vy
TRANSCO/ENGINEER.
Tension joints (mid span joints) shall not be located at less than 15 m for the nearest conductor
clamp.
There shall be no more than one joint per conductor in any one span.
No joint shall be located in single span sections.
No splices shall be located in any span crossing main roads, major rivers, navigable canals,
major communication or power lines and in same conductors less than three spans apart.
The Bidder/Contractor shall keep a record of each joint, giving the location of the fitting, the
date of installation, proof of gauge application and the resistance measurement (ductor reading),
along with signature of responsible jointer and witnessing TRANSCO’s inspector.
A similar record shall be provided for all dead-end and jumper clamps.
2.3.5 Sagging
The “equivalent span” method shall be used for the line conductors and earthwire, according to
which the tension in any line section, i.e. between two tension towers, is that which would apply
to a single span equal to the square root of the figure arrived at by dividing the sum of the cubes
of the individual span lengths, in the section considered, by their sum.
Well ahead of the start of stringing works, the Bidder/Contractor shall submit to TRANSCO, for
approval, separate tables for initial and final sags and tensions of the conductor/earthwire. The
tables shall cover all individual line spans. Sags and tensions shall be computed for the
temperature range +5°C to +55°C for the initial, and +5°C to +80°C, for the final table, at 5°
increments. The loading conditions and sag and tension limitations shall be fully in accordance
with the approved sag and tension calculation submitted for the tower design purpose. The initial
sag-table shall include appropriate creep allowances and indicate insulator clipping offsets for all
suspension towers. The initial tensions and sags shall be calculated assuming that the creep
elongation is equal to the elongation produced by a specified temperature rise. The
Bidder/Contractor shall provide a long-term creep calculation for conductor/earthwire based on
ELECTRA publication No 75 by Working Group 22.05 of Study Committee No. 22 (Overhead
Lines).
The length of conductors or earthwires sagged in one operation shall be limited to the length that
can be sagged satisfactorily.
In order to dissipate the initial tension of conductors or earthwire, they shall be left in the
sheaves for at least 48 hours after stringing. Clipping-in shall be done latest 36 hours after
sagging.
Before sagging, the choice of control spans and the target setting calculations shall be submitted
for approval. The tension prescribed in the sag and tension tables shall not be exceeded by more
than 5% at any time during stringing and sagging operations.
Conductor temperature at the moment of sagging shall be checked by an accurate thermometer.
The core shall be pulled from a one meter length of conductor, the thermometer inserted into the
space vacated by the core, and the length of conductor shall be hung fully exposed to the sun at
average conductor height. The temperature reading after reaching a stable value shall be used as
the sagging temperature.
The sag shall be measured with a theodolite. Subject to the approval of TRANSCO, the
Bidder/Contractor may employ other methods of checking sag.
At sharp vertical angles, the sags and tensions shall be checked on both sides of the angle, the
conductor and earthwire shall be checked on the stringing sheaves for equality of tension on both
sides. The suspension insulator assemblies will normally assume vertical positions when
conductor is clamped.
The sag of the component conductors of any one phase bundle shall not differ by more than
25mm.
After clipping-in, sag control measurements shall be performed and recorded by the
Bidder/Contractor, under TRANSCO’s supervision, for a host of spans selected by TRANSCO,
at his discretion. This shall cover, but will not be limited to, at least two spans per line section.
Wherever sags are found outside the permitted tolerances, the entire section shall be put back
into running blocks and re-sagged properly.
Prior to line handing-over, the Bidder/Contractor shall measure and tabulate ground- and
obstacle clearances for all qualified crossing spans, and all other spans selected by TRANSCO.
The table shall comprise all relevant data, as distance of clearance point to the nearest tower,
ambient temperature at the time of measurement, extrapolated clearance at this point, for
maximum conductor temperature, etc., to TRANSCO’s satisfaction. After TRANSCO’s
approval, these data shall be inserted in the profile plans, at the appropriate locations.
GENERAL REQUIREMENTS
(Applicable Technical Standards, Tests, etc.)
CONTENTS
GENERAL REQUIREMENTS
(Applicable Technical Standards, Tests, etc.)
1.1 General
This part of the Specification shall cover:
¾ Design
¾ Manufacturing
¾ Factory Testing
¾ Marking and Packing
¾ Shipping
¾ Transportation to Site
¾ Installation
¾ Site Testing and Commissioning
Standard designs and models from the Bidder's/Contractor’s manufacturing program are
preferred, provided they meet the requirements of this Specification, and serve the intended
purpose.
It is not the intent to specify completely herein all the details of design and manufacturing of the
above Overhead Transmission/Distribution Line Components. It may be noted that norms
specified are the bare minimum that are required. All Overhead Transmission/Distribution Line
Components shall conform in all respects to high standards of engineering design and
workmanship and should be capable of performing continuous commercial operation within the
parameters guaranteed by the Bidder/Contractor in a manner acceptable to TRANSCO, who will
interpret the meanings of drawings and specifications and shall have power to reject any material
which in his judgement is not in accordance with the specifications and the guaranteed
parameters.
If a substantial improvement of any of the specified technical requirements, which is seen by the
Bidder/Contractor to provide economical advantages to TRANSCO, it is desired to be presented
in the Bid, this improvement may be proposed in addition to that, which conforms to the
specified design, as an alternative. However, it is not mandatory that the alternative design is to
be accepted, but shall be subject to the decision of TRANSCO upon evaluation of the same. The
difference in price shall be clearly stated in percentage/unit.
All material and equipment to be supplied under these Specifications shall be new and unused.
1.4 Drawings
Typical Drawings of the concerned Overhead Transmission/Distribution Lines Specifications are
attached to the respective Technical Standard Specification.
2.1.1 General
2.1.2.3 Conductors
IEC 60104 - Aluminium-magnesium-silicon alloy wire for OHTL
IEC 60888 - Zinc-coated steel wires for stranded conductors
IEC 60889 - Hard-drawn aluminium wire for OHTL conductor
IEC 61089 - Round wire concentric lay overhead electrical stranded
conductor
IEC 61232 - Aluminium-clad steel wires for electrical purposes
DIN 46391 - Delivery Drums for Conductors
ASTM B-549 - Standard Specification for Concentric Lay Stranded Conductors
ACSR/AW
ASTM B- 415 - Hard-drawn aluminium-clad steel wires
ASTM B-416 - Standard Specification for Concentric Lay Stranded Aluminium
Clad Steel Conductors
2.1.2.4 Insulators
IEC 61109 - Composite insulators for ac overhead lines with nominal
voltage greater than 1000 V
IEC 61211 - Insulators of ceramic material or glass for OHTLs with a
nominal voltage greater than 1 kV
IEC 61466 - Composite string insulator units for overhead lines with a
nominal voltage greater than 1 000 V, parts 1 and 2.
IEC 60383 - Insulators for overhead lines with nominal voltage above 1000 V
IEC 60587 - Test method for evaluating resistance to tracking and erosion of
electrical insulating materials under severe ambient conditions
IEC 60815 - Guide for the selection of insulators in respect of polluted
conditions
IEC 60471 - Dimensions of clevis and tongue couplings of string insulator
units
1996
DIN 48062-2 - Overhead Lines, clevis caps for insulators
DIN 48066-2 - Hinges, supporting hinges (for overhead power lines)
DIN 48068 - Protective fitting attachment; for overhead lines, connection
dimensions
DIN 48069-1 - Double eyes; without protective fitting attachment; for
overhead power lines
DIN 48069-2 - Double eyes, with protective fitting, for overhead power lines
DIN 48070-1 - Triangular yokes for overhead power lines (only form ‘AS’ to
be employed)
DIN 48073 - Connecting bolts for overhead power lines (only form ‘S’ to be
used)
DIN 48074 - Eyes and clevisses; connecting dimensions
DIN 48075 - Parallel groove clamps for aluminium stranded conductors and
for aluminium conductors steel-reinforced for overhead power
lines
DIN 48078-1 - Clevis straps for overhead lines; for coupling to connecting
bolts on the strap side (only forms ‘AS’, ‘BS’ to be used)
DIN 48083 - Press Dies for Compression Connections
DIN 48088/2 - Earth Clamping Bolts
DIN 48215 - Clamps and Connectors for Overhead Power Lines
DIN 48334 - Turnbuckles for overhead power lines
2.2 OPGW
ITU-T G. 650 - Definition and test methods for the relative parameters of single
mode fibres
ASTM B415-92 - Standard specification for hard drawn aluminium clad steel
wire
ASTM B416-81 - Concentric lay stranded aluminium clad steel wire
i. These specifications.
ii. Applicable Codes and Standards.
iii. Acceptable Alternative Codes and Standards.
The Bidder/Contractor shall note that compliance of the manufacturer with the provision of these
specifications does not relieve him from his responsibility to supply the equipment and
accessories of proper design, electrically and mechanically suited to meet the operating
guarantees at the specified service conditions.
3 APPLICABLE TESTS
Details of Tests are specified in Standard Technical Specification, Part:
S-TR-GEN-GDF - General Requirements – General Conditions
CONTENTS
1 GENERAL ....................................................................................................................... 3
1.1 Drawings ........................................................................................................................... 3
1.2 Equipment Identification and Color Codes ....................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 General .............................................................................................................................. 3
2.2 Insulator String Hardware ................................................................................................. 5
2.2.1 General .............................................................................................................................. 5
2.2.2 Arcing Rings...................................................................................................................... 5
2.2.3 Yoke Assembly ................................................................................................................. 6
2.3 Conductor and Earthwire Accessories............................................................................... 7
2.3.1 Compression Mid-Span Joints........................................................................................... 7
2.3.2 Repair Sleeves ................................................................................................................... 7
2.3.3 Suspension Clamps............................................................................................................ 7
2.3.4 Tension Clamps ................................................................................................................. 8
2.3.5 Damping/Spacing Devices ................................................................................................ 8
2.3.6 Jumper Loop Spacer ........................................................................................................ 11
1 GENERAL
This part of the specification covers design, manufacture, testing, erection and commissioning of
overhead line hardware and fittings.
For applicable technical standards, tests and general requirements please refer to:
S-TR-OHL-GEN - General Requirements (Applicable Technical Standards, Tests,
etc.)
1.1 Drawings
Typical Drawings for Conductor Clamps and OPGW & Earthwire Assembly provided in the
Drawings Section are as follows:
Drawing No. Title
DWG TR OHL 06 01 Conductor Clamps
DWG TR OHL 06 02 OPGW & Earthwire Suspension Assembly for all Voltage Levels
2 TECHNICAL DESCRIPTION
2.1 General
All hardware and accessories shall comply with the requirements of this Specification and shall
be manufactured and tested in accordance with IEC or DIN/VDE Standards. Other authoritative
national or international standards may be acceptable, subject to approval by TRANSCO, if the
requirements are equal to or exceed applicable IEC or VDE Standards. All hardware/accessories
shall conform to one single standard.
All parts shall be marked durably (embossing, for ferrous parts before galvanizing) with
mechanical and electrical rating.
All ferrous metal and iron parts of insulator- and line hardware shall be hot-dip galvanized. If
not otherwise specified, the zinc coating shall be at least 610 g/m² and it shall be tested in
accordance with the relevant standards.
Bolts shall be made of steel having a minimum tensile strength of grade 8.8 according to DIN
ISO898 Part 1. All bolts shall be locked with hot-dip galvanized nuts, which are to be secured in
a form-locking manner (form “S”, DIN 48073). Bolts secured by split pins and flat washers only
are not permitted. Split pins for securing nuts of fittings shall be of tinned copper or stainless
steel, washers shall be of stainless steel.
Clamps which are in direct contact with the conductor shall match the conductor material.
Elastomers or other non-metallic materials shall have good resistance to ageing and be capable
of withstanding temperatures between -40°C and +100°C, without change of essential properties.
The materials shall have adequate resistance to the effects of ozone, ultraviolet radiation and air
pollution over the entire temperature range. Further, these materials shall be non-conductive.
Also, these materials shall be bonded by vulcanization to the metal surfaces in order to avoid
crevice corrosion. To avoid potential separation and tracking paths on the elastomer surface
between elastomer and metallic parts, metallic flexible bridges are to be installed.
Design of hardware and accessories consisting of part assemblies like spacer dampers, dampers,
suspension clamps, etc. shall cater for captive interconnection of as many parts as possible to
ensure simple and safe mounting. This applies in particular to bolts, screws, washers and safety
sheets.
The hardware fittings offered shall be suitable for the employment of hot line maintenance
techniques so that usual hot line operations can be carried out with ease, speed and safety. The
technique adopted for hot line maintenance shall be generally bare hand method and hot stick
method. The Bidder/Contractor should clearly establish in the tender, the suitability of his
fittings for hot line maintenance.
Line side yoke plates shall have a notch and a working hole of suitable size to facilitate hot line
working. The design of the arcing rings shall be such that they can be easily replaced by
employing hot line maintenance techniques.
The design of all conductor/insulator hardware and accessories shall avoid sharp corners or
projections which would produce high electrical stress in normal working conditions. The
design of adjacent metal parts and mating surfaces shall be such as to prevent corrosion of the
contact surfaces and to maintain good electrical contact under service conditions.
Particular care shall be taken during manufacture of conductors and fittings and during
subsequent handling to ensure smooth surfaces.
Hardware and accessories shall conform to the standards stated below, if this Specification does
not stipulate otherwise:
Fittings for OHTL and Switchgear IEC/DIN/VDE0212
- static mechanical behaviour part 50
- dynamic mechanical behaviour of anti-vibration fittings part 51
- electrical contact behaviour of current carrying fittings part 52
under normal operating conditions
- partial discharge characteristics, tests part 53
Clevis caps for insulators
2.2.1 General
All insulator strings shall be equipped with appropriate protective devices, such as arcing rings.
The design of these protective devices shall support loading during the installation of insulator
strings and stringing of conductors and to reduce, as far as possible, damage to the conductors,
clamps, insulator strings and arcing rings under all flashover conditions.
of radiation shall be determined thus that no thermal damage to the insulant may occur. At the
final burning point, the plasma jet shall emerge about vertically to the insulator axis and burn
down stable without pendulum motions. The arcing accessory shall be provided with one final
burning point only.
The arcing accessory shall be made from solid material of small diameter (about 16 to 30 mm
diameter). It shall be avoided that the arc root will be supplied over a larger area (high moving
speed of arc root).
Electrodes shall be made from steel (low consumption, poor thermal conductivity). Aluminium
or aluminium alloys are not admissible (high consumption related with considerable pollution of
insulant).
The maximum admissible temperature of the electrode at the final burning point, with respect to
the zinc coating and loss of tensile strength of the electrode material must not exceed 400°C.
This requirement is met at a short circuit current density of not more than 70 A/mm², for a max.
duration of 1 second.
The attachment of the arcing accessory to the respective string element shall be designed thus
that a contact force of at least 40 kN can be applied, and that no welding will be produced during
short-circuit, which may impair the performance.
The live ring shall be corona free at highest system voltage.
The dimensions of arcing accessories shall be adapted to the insulator types employed, the
thermal and dynamic stresses and to the highest system voltage (insulation co-ordination).
The manufacturer shall be bound to prove the thermal and electrical performance of arcing
accessories, either by supply of acceptable type test reports, or by conducting of type tests in
presence of TRANSCO.
In consideration of the arising mechanical forces, design and mass of clamp shall be determined
such, that the mass moment of inertia of clamp related to the rotational axis is kept to a
minimum. The rotational axis of the clamp shall level with the longitudinal axis of the conductor.
It must be ensured that the tappet of the clamp body does not slip, but roll in the strap-hole under
longitudinal movement of the conductor.
The clamp manufacturer shall demonstrate to TRANSCO that the resonance of the system
“suspension clamp plus conductor” is far above of the highest relevant frequency of aeolian
vibrations.
The clamp shall be capable of withstanding a conductor tension equivalent to 50% of the
admissible maximum conductor tension without any conductor slippage. However, maximum
tower load shall not be exceeded, whichever is lower.
The clamping force, i.e. the size of the bolts shall be chosen such, that a contact force is
produced which satisfies the electrical and mechanical requirements. The body of the clamp
with it’s suspension devices must be capable to withstand the admissible thermal conductor
stress without any damage, in the event of a short-circuit. conductor wires in the vicinity of the
clamp shall not be damaged.
ii. Proper bundle spacing after short-circuit faults with the maximum allowable short-circuit
current. The Bidder/Contractor has to prove, either by test or calculation, that this
requirement is fulfilled.
iii. Suppression of aeolian vibrations and sub-span oscillations, to a level of alternate bending
strain of the conductor below 150 x 10-6 m per m over the relevant frequency range, at
suspension/tension and other fixing points, e.g. damper clamp or spacer clamp.
The Bidder/Contractor shall submit a full and complete specification of the system offered, with
drawings, calculations and a vibration study, showing the vibration intensity of the line with and
without the proposed system and giving also quantity per span and exact positions of devices
required.
Special attention shall be paid to spans with concentrated masses as e.g. warning spheres. The
vibration study must be based on measured values of the conductor’s mechanical self-damping
and on the dampers measured non-linear complex impedance. If no independently witnessed test
reports are available, to TRANSCO’s satisfaction, the tests shall be performed by the
Bidder/Contractor, in presence of TRANSCO.
The Bidder/Contractor shall also prove that the dampers and other fittings (e.g. spheres) are not
dynamically overloaded under service conditions, to avoid breakages of messenger cables,
clamps.
The Bidder/Contractor shall submit the final vibration study, based on the actual spans of the
OHTL.
The validity of the study shall be verified by actual vibration measurements, to be carried out by
the Bidder/Contractor using an approved third party other than the manufacturer on the
completed line, in a method satisfactory to TRANSCO.
The damping system proposed shall be only a combination of spacer dampers and stockbridge
dampers.
Approval of the vibration dampers proposed will be subject to satisfaction of the following test:
1. Dynamic characteristic test, giving power consumption and non-linear complex impedance
curves as function of the frequency for vibration velocities in the range from 0.025/m/s to
0.2 m/s.
The damper shall be vertically mounted on a shaker table and driven with constant table
velocities in the range from 0.025 m/s to 0.2 m/s over the frequency range of 150/D to
1500/D, where D is the conductor diameter in mm.
The frequency shall be continuously varied with 0.2 decades/minute over the frequency
range.
The reaction force and the phase between the reaction force and the velocity shall be
measured and power and impedance shall be plotted against the frequency over the given
frequency range for different vibration velocities as indicated above.
2. Fatigue test, showing the dynamic endurance of the damper.
The damper shall be driven for 10 exp. +8 cycles over a frequency range selected from the
vibrations study. Afterwards, the dynamic characteristic test shall be repeated. There shall
be no significant difference in the dynamic characteristic curves taken before and after the
fatigue test.
For more and detailed information see DIN VDE 0212 Part 51 (issue July 1986).
Approval of spacer dampers proposed will be subject to the following tests:
1. Fatigue test, showing the dynamic endurance of the spacer dampers and their impact on the
conductors.
Spacer dampers shall be mounted in a test span with the appropriate conductor bundle.
The bundle shall be driven for 10 exp. +8 cycles at a free span vibration angle of 0.0058
rad (bending angle of 20 minutes). There shall be no significant damage at the spacer
damper and on the conductors at the spacer clamps after the termination of the fatigue test.
The following tests shall be carried out for both, vibration dampers and spacer dampers:
1. Corona test, to be carried out in a virtually dark laboratory. Only one set up of
dampers/spacer dampers may be tested. The dampers shall be installed on the conductor
bundle.
The sample shall be subjected to 50 Hz voltage, to determine the corona extinction voltage
level. The corona extinction voltage is the voltage at which the dampers/spacer dampers
are free from visible and audible corona discharges.
The corona extinction voltage level shall not be less than the corona extinction voltage of
the bundle itself. For more and detailed information see DIN VDE 0212, Part 53 (issue
April 1985).
2. Accelerated Ageing test, demonstrating the long-term suitability of used Elastomers under
heat/ultraviolet cycles. The test procedure shall be proposed by the Bidder/Contractor,
subject to TRANSCO’s approval.
Additional requirements for Damping Devices:
1. Material
For material, reference is made to Clause 2.1 of this Chapter. In case of vibration dampers, the
messenger cable shall be made of stainless steel grade A4.
All material used shall withstand the exposure conditions encountered with a minimum operating
life of 30 years.
2. Design
Elastomers used shall be protected from direct ultraviolet radiation. Welding of parts will not be
accepted. When using screw-type clamps for the fixing, the average specific surface pressure
between conductor and channel of the clamp must not be less than 5 N/mm² and not more than
20 N/mm².
To maintain the manufacturers’ recommended torque and to avoid human errors; only colour
coded breakaway type bolts shall be provided on both rigid spacers and spacer dampers. The
required torque to break the head shall be marked on the drawings and also embossed on the
clamp body.
If one of the conductors forming a bundle should break, the spacer damper shall be able to
absorb any forces thereby produced. However, deformations leading to functional losses of the
damper are tolerable.
Performance of spacer dampers shall be free of noise.
In case of stockbridge dampers, the weight shall not be cast on the messenger cable. Further, the
weight shall be designed in a way that excludes any collection of water. The mass of damper
clamps shall not exceed 10% of the total damper weight.
3. Marking
Each vibration damper shall be durably marked with:
Origin, such as manufacturer’s name or trade mark
Manufacturer’s catalogue- or drawing number
Applicable conductor diameter range
Year of manufacture
Quality reference, on the bolts.
4. Installation
Damping devices shall be suitable for installation/removal by use of hotline techniques.
INSULATORS
CONTENTS
1 GENERAL ....................................................................................................................... 3
1.1 Drawings ........................................................................................................................... 3
1.2 Equipment Identification and Color Codes ....................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 4
2.1 Insulators ........................................................................................................................... 4
2.1.1 Insulator Strings ................................................................................................................ 4
2.1.2 Insulator Units ................................................................................................................... 4
2.2 Installation of Insulator Strings ......................................................................................... 8
2.3 Marking ............................................................................................................................. 9
2.4 Packing ............................................................................................................................ 10
HV INSULATORS
1 GENERAL
This part of the specification covers design, manufacture, testing, erection and commissioning of
HV overhead line insulators.
For applicable technical standards, tests and general requirements please refer to:
S-TR-OHL-GEN - General Requirements (Applicable Technical Standards, Tests,
etc.)
1.1 Drawings
Typical Drawings for OHL Insulators provided in the Drawings Section are as follows:
Drawing No. Title
DWG TR OHL 04 01 Single Suspension String 400 kV OHL
DWG TR OHL 04 02 Double Suspension String 400 kV OHL
DWG TR OHL 04 03 Single Tension String 400 kV OHL
DWG TR OHL 04 04 Double Tension String 400 kV OHL
DWG TR OHL 04 05 Single Suspension String 220/132 kV OHL
DWG TR OHL 04 06 Double Suspension String 220/132 kV OHL
DWG TR OHL 04 07 Single Tension String 220/132 kV OHL
DWG TR OHL 04 08 Double Tension String 220/132 kV OHL
2 TECHNICAL DESCRIPTION
2.1 Insulators
All insulator strings shall be type-tested in line with IEC 60383-2 (clause 12.3 applicable) and
IEC 60437 (RIV to comply with grade II, BS 137-2). Judgement of visible corona shall follow
VDE 0212 part 53.
The compatibility of all insulators fittings/accessories with the proposed insulator is required to
be confirmed by the manufacturer of that insulator in writing.
a) Core
The core shall consist of a high strength ECR (Electrical grade, Corrosion-Resistant)-glass-fibre
reinforced epoxy resin rod. The glass fibers shall be resistant against acid attacks in order to
prevent stress corrosion of the FRP rod.
The FRP rod shall be resistant against hydrolysis under service conditions.
b) Housing and Sheds
Core-housing and weathersheds shall be made of high temperature vulcanized (HTV) silicone
rubber, with a shore A hardness of not less than 60. The material shall be of blue/grey color and
be resistant against the ultra-violet radiation being present in the solar spectrum at ground level.
The track resistance of the material shall be min. class 1A 3.5 according to IEC 60587.
The core-housing shall have a minimum thickness of 3 mm.
The weathersheds shall provide an open aerodynamic profile without any under ribs. The
insulator profile shall follow strictly all provisions laid down in IEC 60815.
c) Assembly Methods
Two methods of assembly are acceptable:
1. Housing including sheds are applied onto the core in one single step. Any seams/burrs
protruding axially along the insulator, resulting from this process shall be removed
completely. Injection- or compression moulding is acceptable only in case the housing is
moulded in one single shot. Moulding in multiple steps may cause flaws and residual
stress in the joining seams and, therefore, shall not be applied.
2. A sheath is extruded seamlessly onto the core. The housing is completed by assembly of
moulded weathersheds onto the sheath. All parts of the insulating body, i.e. FRP rod,
sheath and sheds, are bonded together by vulcanization.
In case a Bidder prefers to offer an insulator design assembled in another way, he shall submit
his proposal with complete supporting documentation. Eventual acceptance is left entirely at
TRANSCO’s discretion.
d) Metal Fittings
The insulator shall be equipped with clevis caps confirming to IEC 60471, at either end. Caps
shall be of forged steel, hot-dip-galvanised to minimum thickness of 120m, other aspects for
galvanising shall be as described, in the Standard Technical Specification, Part:
The thickness of the zinc coat of the clevis caps shall exceed the normal standard. Whilst fully
maintaining adhesion, it shall not be less than 120 in any spot of the cap.
e) Interface Between Clevis Cap and FRP Core
The gap between fitting and core housing shall be sealed permanently against the ingress of
moisture. Sealing by compression only is not regarded to be permanently waterproof. Covering
the cap, even partly, with housing material is unacceptable due to electrical reasons. Sealing of
the interface by application of an elastomer with permanent elasticity is considered an acceptable
solution. The material shall adhere to the surface of the metal cap, as well as to the housing.
The following maximum electrical field stresses shall be considered in order to avoid any
premature ageing effects due to dry and water induced corona:
The E -field on the insulator sheath should not be permitted to exceed 0.42kV/mm
for more than 10 mm along the insulator surface.
The E-field should not exceed 1.8 kV/mm at any metal point (end fitting &
grading ring)
The electrical field stresses of the complete insulator set/string including grading rings
shall be calculated by means of finite element modelling (FEM) / boundary element
modelling (BEM) software.
2.1.2.1.3 Tests
Tests shall be performed in full, in accordance with IEC Standard 61109.
Amendments/clarifications to this standard are outlined below.
If design and type test reports covering the offered insulator are available, repetition of these
tests may be waived, at TRANSCO’s discretion.
a) Design Tests
The tracking and erosion test, Para 5.3.3, IEC 61109, shall be executed in line with
annex “C”.
b) Type Tests
Tolerances specified under Para 6 of IEC 61109 shall be amended, as follows:
Positive tolerances to the creepage path are not limited
Max. permissible distortion of clevis caps against each other is 2°
In addition to the type test according to IEC 61109, the resistance of the FRP core against
brittle fracture shall be proven by the:
Test on resistance of the fiber glass reinforced polymeric (FRP) core against stress
corrosion
This test shall be performed at ambient temperature to confirm the mechanical resistance
against stress corrosion of the FRP core.
Test Specimen
One insulator from the production line or one specimen is used. The specimen shall have a
length between the end-fittings of at least 10 times the core diameter. The end-fittings
shall be identical to those used in the production.
The housing of the insulator shall be removed in the middle part of the insulator on a
length of at least 150 mm. The visible core surface has to be smoothened by means of a
fine abrasive cloth (grain size 180). Remaining parts of the housing have to be removed
thoroughly.
An acid container made of polyethylene shall be arranged, surrounding the visible core
surface in such a way that the liquid can simply be poured into the container and no acid
comes into contact with the fittings. The size of the acid container shall be adapted in such
a way that the FRP core is surrounded by a liquid thickness of not less than 1 cm and a
liquid level of not less than 4 cm. The container shall be covered to limit evaporation of
the liquid to max. 5% of its volume during the test period.
Performance of Test
The insulator is subjected to a tensile load applied between the metal fittings. The tensile
load shall be increased rapidly but smoothly, from zero up to 67% of the specified
mechanical load (S.M.L.) and then be maintained at this value for 96 hours. Immediately
after applying the load, a nitric acid of a concentration of 1 n (1n = 63 g HNO3 added to
937 g water) shall be poured into the acid container. The acid must not come into contact
with the end-fittings.
Evaluation of the Test
The test is passed if no fracture of the core occurs during the 96 hours test.
c) Sampling Tests
Tolerances specified under Para 6. of IEC 61109 shall be amended, as outlined under the type
tests.
d) Routine Tests
Routine tests shall be performed on every insulator.
The following amendments are applicable to Para 8.2, IEC 61109:
Scaly crumblings are allowed at the edges of a shed only. However, the total amount of
crumblings shall not exceed a volume of approx. 100 mm3 per 1000 mm of insulator length
and an individual crumbling shall not exceed 50 mm3.
Individual protrusions up to 2 mm at the rim of the sheds are permissible, protrusion at the
shank is not permitted.
Moulding seams and burrs running in direction of the insulators axis shall be removed
completely.
2.1.2.2 Porcelain Long-Rod Type
Porcelain insulators shall be of long rod type with aerodynamic shape with alternating
large/small diameter sheds and with good self-cleaning properties suitable for desert and marine
contamination. The design must ensure that the shape of the insulator should mostly exclude a
critical reduction of the creepage distance as a result of accumulation of dust and sand.
Therefore, the surface must be smooth and underribs are not accepted. The ratio between shed
distance and-overhang shall be optimised for the application at the severe local ambient
conditions. Inclination of sheds shall be approximately 10 to 12 degrees on the upper and
approximately 2 degrees on the undershed.
The minimum creepage path shall not be less than 50 mm/kV rated voltage.
Porcelain shall be of high strength alumina type equivalent to KER 110.2 DIN 40685, brown
glazed equivalent to surface DIN 40686.
The insulator shall be equipped with clevis caps, conforming to IEC 60471, at either end. Caps
shall be of malleable or cast ductile iron according to IEC 60383 and be hot dip galvanized as
described in the Standard Technical Specification, Part:
S-TR-CORR - Corrosion Protection
The thickness of the zinc coat of the clevis caps shall exceed the normal standard. Whilst fully
maintaining adhesion, it shall not be less than 120 in any spot of the cap.
If TRANSCO is not satisfied with the standard of cleanliness, he may direct the
Bidder/Contractor to clean the insulators with an approved chemical solution.
The bending or straining of insulator strings, which may occur when insulator strings are picked
up by a rope sling placed near the center of the string, must be avoided. The rope sling shall
always be attached near the top unit of the insulator string.
Workmen shall not climb upon insulator strings. Access to the conductor clamping points shall
be provided only by use of suitable ladders/work platforms.
Hardware and accessories shall be handled carefully, to prevent contact with the ground. All
items shall be clean and inspected before installation for missing parts or visual defects. All
connections shall be made in accordance with the approved drawings and as recommended by
the manufacturer. Bolts shall be tightened to their specified torque, split pins inserted where
required and opened correctly, all in a good workmanlike manner, according to the best practice
of transmission line construction.
All split pins and lock nuts in each insulator string shall be carefully checked to ensure that they
are properly seated to avoid accidental uncoupling of insulator units. All split pins and lock nuts
shall be faced towards the step-bolt-legs of the tower to facilitate inspection.
Imperfectly or poorly galvanized hardware as determined by TRANSCO shall not be used. Such
pieces shall be replaced with new hardware.
2.3 Marking
Each insulator shall be marked legible and indelible, on it’s top shed or end fitting with the
following data:
i. Name or trade mark of the manufacturer
ii. Specified Mechanical Load (SML)
iii. Routine test load (RTL)
iv. Serial number
v. Year of manufacture
vi. Country of manufacturing
The marking performance shall be proven by the following tets:
Salt fog spraying test (minimum 60 cycles)
Fluorescent UV irradiation test (5,000hrs)
High temperature exposure test (100 degC – 32hrs)
Acid rain test ( 3 times spraying of PH-1 solution)
Scratch test
Sand blasting exposure test
2.4 Packing
Insulators shall be packed in crates, to safely prevent transport damage. Each crate shall contain
only insulator units of the same type. Crates shall be of hexagonal or rectangular cross-section.
Crates shall be wooden and should be close-boarded. They shall be manufactured from sound
seasoned softwoods and suitable for prolonged storage on site under the climatic conditions
present. They shall be steel-banded for additional strength at not less than three positions along
their length.
Crates shall be designed with internal struts or partitions to support insulators and prevent
insulator movement.
Insulators shall be fitted with retaining clips.
The guaranteed electro-mechanical strength and the type of the units in each crate shall be
clearly marked on each crate in a waterproof medium.
(32/72)
CONTENTS
1 GENERAL ....................................................................................................................... 3
1.1 Drawings ........................................................................................................................... 3
1.2 Equipment Identification and Color Codes ....................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 4
2.1 General .............................................................................................................................. 4
2.2 OPGW Metallic Unit ......................................................................................................... 4
2.3 Optical Units/Fibres .......................................................................................................... 5
2.3.1 Fibres ................................................................................................................................. 5
2.4 Identification of Fibre Color.............................................................................................. 6
2.5 OPGW Accessories ........................................................................................................... 6
2.5.1 General .............................................................................................................................. 6
2.5.2 Tension Set ........................................................................................................................ 7
2.5.3 Suspension Set................................................................................................................... 7
2.5.4 Dampers ............................................................................................................................ 7
2.6 OPGW Joint/Termination Boxes and Splices ................................................................... 7
2.7 OPGW Delivery Lengths .................................................................................................. 8
2.8 OPGW Reels ..................................................................................................................... 9
2.9 OPGW Installation ............................................................................................................ 9
2.10 OPGW Splicing and Termination ................................................................................... 10
2.11 Testing and Inspection of OPGW and related Accessories/Joint Boxes ......................... 10
1 GENERAL
This part of the specification covers design, manufacture, testing, installation and commissioning
of optical ground wire.
If a substantial improvement of any or all of the specified technical requirements, expressed or
implied herein, which is seen by the Bidder/Contractor to provide economical advantages to the
end user, is desired to be presented in the Bid, this may be given in addition to that, which
conforms to the specified design, as an alternative. However, it is not mandatory that the
alternative design is to be accepted, but shall be subject to the decision of TRANSCO upon
evaluation of the same. The difference in price shall be clearly stated in percentage/unit.
For applicable technical standards, tests and general requirements please refer to:
S-TR-OHL-GEN - General Requirements (Applicable Technical Standards, Tests,
etc.)
The Contractor shall confirm compliance with extended warranty for the proposed OPGW of ten
(10) years starting from the date of Provisional Acceptance Certificate (PAC) or from the date of
energising of the OHL whichever comes later. During extended warranty contractor shall
perform periodically end to end test every ‘12’ months.
1.1 Drawings
Typical Drawings for OPGW Tension Set / Suspension Set and Communication System using
OPGW provided in the Drawings Section are as follows:
Drawing No. Title
DWG TR OHL 05 02 OPGW Tension Set for Non-Jointing Towers
DWG TR OHL 05 03 Suspension Set for OPGW
DWG TR OHL 05 04 Simplified Drawing of the Communication System using OPGW and
u/g FOC (132 kV & 220 kV)
DWG TR OHL 05 05 Simplified Drawing of the Communication System using OPGW and
u/g FOC (400 kV)
DWG TR OHL 05 06 OPGW & Earthwire Tension Assembly for all Voltage Levels
2 TECHNICAL DESCRIPTION
2.1 General
The OPGW shall be designed to withstand the specified short circuit current, which is based on
the System Characteristics and Fault Levels, reference shall be made to Standard Technical
Specifications, Part:
S-TR-GEN-GDF - General Conditions
and all relevant Technical Data Sheets, without resulting in fibre de-coloration/de-gradation in
optical attenuation or mechanical damage to any of the OPGW components. It shall be able to
safely withstand the lightning strokes (it shall have Arc-proof characteristics) without damaging
the conductor or affecting the fibre optic unit/fibre characteristics. The minimum short circuit
current to withstand shall not be less 10 kA, for 1 sec [capacity (Is²x t) is approx. 100 kAsq. Sec]
in the case of double circuit 400 kV OHTL with two OPGWs and not less than 12 kA [capacity
(Is²x t) is approx. 150 kAsq. sec) in the case of double circuit 220 kV OHTL with single OPGW.
The OPGW must have mechanical and electrical features so as to be strung on HV & EHV over
head transmission lines towers with long spans (typical span length on 220 kV systems is 450 m
& on 400 kV systems is 500 m). This includes the bending and pulling forces during installation,
the tension during normal operation, the wind load and aeolian vibrations.
The OPGW shall be greased and can withstand heavy corrosion and chemical evaporation.
The total OPGW length shall be determined by the Bidder/Contractor taking into account sag,
splices, drops at the joint locations etc.
The OPGW associated with the OHTL circuits shall be such as one (no.) OPGW, in the case of
220 kV double circuit OHTL, whereas two (nos.) OPGWs to be installed on the double circuit
400 kV OHTL (one with each circuit OHL), if not otherwise specified.
In any offered OPGW design, the reserve length of fibre against the linear length of OPGW shall
be in such away that when the OPGW is subjected to 100% UTS and reaches the break point,
fiber should not break.
The wire strands shall be in close contact. The wires forming the outer strands of the OPGW
shall be designed to prevent bird-caging, strand popping and unravelling during normal handling
and installation.
The rated breaking strength of the completed OPGW shall be taken as sum of the rated breaking
strengths of the individual wires, calculated from their nominal diameter and the appropriate
specified minimum tensile strength. When determining the tensile strength, a safety factor of 2,5
shall be applied.
The same precautions as for the line conductors shall be taken for OPGW with regard to packing
and shipment as well as for adjustment of metal prices.
The OPGW shall be earthed to the tower steel work at each tower (at joint location tower both
sections of the OPGW shall be earthed). Approved clamps and bonding leads shall be used for
earth connections.
Approved end seals (waterproof & heat resistant) shall be fixed on the OPGW ends of each
drum, immediately after manufacturing and reeling the respective OPGW length. These end
seals shall not be removed until immediately prior to testing before installation/splicing at site.
No mid-span joints shall be allowed in the OPGW. All joints shall be performed at tower joint
box located above anti-climbing devices.
2.3.1 Fibres
The Cabled Fibre Core shall be of the Single Mode (SM) made of high grade ultra pure fused
slica glass coated over the cladding with UV-cured acrylate, (D-652 or D-655 to be defined in
the SoW). The fibre shall be suitable to operate safely and within the specifications under the
prevailing environmental conditions, e.g it shall be able to withstand the following temperatures:
Storage temperature range 0C to +55C
Installation temperature range 0C to +65C.
Operating Temperature (OPGW shall withstand a temperature range of 0C to +65C, however if
calculation for the solar effect on the metal surface proves higher range, the same shall be
considered in the design).
Temperature resulting from the rated fault current:
(for 1 sec) or during lightning up to +200C
The cabled SM fibres shall be designed to operate at 1310 & 1550 nm. Wavelengths with a low
light dispersion value ( 18 ps/nm.km) over the entire possible bandwidths above the specified
cut-off wavelength, which shall not be more than 1270 nm.
The fibre design shall be generally as per recommendations and standards made by International
Committees/Organisations as given above and all updated versions of the same at the time of
awarding the Contract.
No changes are to occur in the optical characteristics of the fibres up to 0,4% cable elongation.
The total number of fibres per each OPGW shall be as specified in the scope of supply (32/72).
Fibres shall be color coded in accordance with the relevant standards.
For the geometrical and optical details of the required fibre core, reference shall be made to the
respective Technical Data Sheets of these specifications.
The fibre optic unit and the outer stranded metallic wires shall serve together as an integral unit
to protect the optical fibres from degradation due to vibration and galloping, wind and ice loads,
wide temperature variations, lightning, chemical evaporation and fault current.
No changes are to occur in the optical characteristics of the fibres due to the OPGW elongation.
In order to protect the optical fibres from stresses due to the thermal coefficients of expansion
being different between it and the enclosure, or due to elongation of the enclosure under tensile
load to the cable, the excess length of optical fibre within the cable shall be chosen such that
there is no mechanical stress on them under neither the specified prevailing temperature (storage,
installation or operation) combined with the maximum tensile stress on the cable.
2.5.1 General
The OPGW shall be supplied with all fittings, mounting hardware/accessories and joint boxes,
required for a complete operational OPGW.
All fittings must be designed in such a way that no degradation of the optical transmission in the
fibres of the cable is encountered, under all service conditions. And it shall be able to withstand
UAE’s harsh environment as well as chemical evaporation.
The compatibility of all OPGW fittings with the proposed OPGW is required to be confirmed by
the manufacturer of that OPGW, in writing. Preference shall be given to the accessories from
the same manufacturer as that of the OPGW, which is also subjected to successful completion of
prequalification process.
The required hardware/accessories/fittings shall include, but not be limited to, tension set for
jointing tower, tension set for non jointing tower, tension set for terminal tower, vibration
dampers, ground wire bracket, turn buckle, parallel groove clamp, fastening clamp, suspension
set, armour grip suspension clamp, angle tower hardware, dead-end tower hardware, earth
bonding leads, clamps for vertically mounting OPGW on tower steel work and the respective
joint boxes as detailed below.
The OPGW shall be clamped at approx. one meter spacing on the tower and substation
gantry structures
All hardware and accessories of the OPGW shall comply with the requirements of these
Specifications and shall be manufactured and tested in accordance with all relevant IEC or
VDE Standards. All hardware/accessories shall conform to one single standard.
2.5.4 Dampers
All spans must be furnished by vibration dampers.
All dampers are to be mounted on armour rods. The damper clamp must be carefully adjusted to
the diameter of the cable with armour rods.
For vibration study/measurement, self-damping of OPGW and other technical- and testing
requirements refer to the respective clause under Conductor accessories.
To be used for OPGW-OPGW connection and shall be installed in the lower portion of the tower
or portal structure along the tower body, however above anti-climbing device. An extra stripped
off length of approx. 1.5 m of the fibres shall be left inside for repeat splices.
Type B
Joint box for connection of OPGW to the under ground optical fibre cable (OPGW-OFC). These
shall be in general similar to type A, except for the cable entry and shall be installed at the gantry
tower about 1m above the tower foundation surface.
Type C
To be used for OPGW-OPGW-OPGW connection when three OPGWs are required to be
interconnected, and shall be installed in the lower portion of the tower or portal structure along
their body, however above anti-climbing device. An extra stripped off length of approx. 1.5 m of
the fibres shall be left inside for repeat splices.
The junction box shall be insect-proof and water-tight with protection degree of IP55W (weather
proof), made of cast aluminium or stainless steel (min. grade ANSI 316) and shall be designed
such as to form an extremely rigid structure. A name plate shall be fixed on the front of the box
door and shall have the following information:
Type of J/B
Owner :
Consultant :
Manufacturer name :
Year of manufacture :
No. of fibres : .........S.M
Contract No. :
Cable length and direction :
Junction box technology shall ensure only bottom cable entry, quick removal of box cover giving
access to fibre splices, repair of fibre splicing at least three times during transmission line’s
working life, accordingly sufficient fibre length should be left loose inside the box. All jointing
materials, sufficient for all splices (equal to 1.2 times the number of fibres), including the
splicing sleeves, heat shrinking protective tubes, splice holder and cable holder should be
provided inside the box.
A thermal pad shall be placed on the outer spirals and thermal protection shall be at least
equivalent to that obtained with an aluminium sheet covered by 10 mm cellular polyethylene.
The inner end of the OPGW shall be fitted with a suitable cap to ensure water tightness. The
outer end shall be fitted with a watertight head compatible with cable pulling.
The contractor should take into account the extra loop of ’15’ meters at the joint box locations,
there loops shall be horizontal instead of vertical.
stringing. OPGW down-leads shall be long enough to enable a lowering the joint box to the
ground level for maintenance purpose.
b) Sample Tests
Test Item Test Passing Criteria
Construction To be checked against Technical data sheets
c) Routine Tests
Test Item Test Passing Criteria
1. Visual inspection
- Lay ratio
- Lay direction
d) Site Tests
Test Item Test Passing Criteria
Attenuation measurement: To be checked against Technical data sheets
- At both wavelengths 1310nm and
1550 nm.
- It shall be performed before
installation (on reels)
- And after installation from both
line ends (from splice box to
splice box at both gantries or
repeaters, as applicable.
Back scatter measurement from both no abnormalities along the cable and or at the joints or
directions connectors
Splice loss To be checked against Technical data sheets
e) Compatibility tests of the approved OPGW fittings and hardware with the approved
OPGW:
Since the OPGW manufacturer will be held responsible for the compatibility of the required
fittings for his OPGW, the compatibility tests shall be proposed by the OPGW manufacturer and
be performed at his premises, subject to approval by TRANSCO. TRANSCO have the right to
ask for performing additional compatibility tests if found necessary.
SURVEYING WORKS
CONTENTS
1 GENERAL ....................................................................................................................... 3
1.1 Drawings ........................................................................................................................... 3
1.2 Equipment Identification and Color Codes ....................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 General .............................................................................................................................. 3
2.2 Line Routing ...................................................................................................................... 3
2.3 Line Profile Survey ........................................................................................................... 4
2.4 Tower Site Survey ............................................................................................................. 5
2.5 Clearing of Right-of-Way ................................................................................................. 6
SURVEYING WORKS
1 GENERAL
This part of the specification covers overhead line routing, line profile survey, tower site survey,
clearing of right-of-way and access.
For applicable technical standards, tests and general requirements please refer to:
S-TR-OHL-GEN - General Requirements (Applicable Technical Standards, Tests,
etc.)
1.1 Drawings
Typical Drawing for Conceptual Clearances of OHL provided in the Drawings Section is as
follows:
Drawing No. Title
DWG TR OHL 01 01 Conceptual Clearance of OHL
2 TECHNICAL DESCRIPTION
2.1 General
The Bidder/Contractor shall keep damage within the right-of-way to a minimum, consistent with
the successful execution of the erection work. The Bidder/Contractor shall exercise all
precautions to avoid damage to crops and other property. The Bidder/Contractor shall comply
with all national and local regulations regarding barricades, detour arrangements, and warning
signs. Damage to roads, footpaths, bridges, ditches, etc., caused by the Bidder/Contractor shall
be repaired at his expense.
be determined precisely by differential GPS and submitted in formats as required by the different
government agencies. For Town Planning Dept., coordinates shall be prepared in UTM system
(datum Narwahn UAE), for the General Civil Aviation Authority WGS-84 geographical
coordinates are to be submitted. Other formats may be required additionally. The detailed route
maps shall be prepared by the Bidder/Contractor in the required quantity and are to be submitted
for TRANSCO’s approval, who will forward them to the department of Town Planning and other
relevant authorities, for their approval.
Approval of the maps by the Town Planning Department and other relevant authorities is a pre-
requisite to perform profile survey and tower spotting.
In mountainous areas, aerial survey using LIDAR technology shall be acceptable in order to
improve the quality and the accuracy of the survey, and expedite the line design process.
The Bidder/Contractor shall be prepared to amend the route, according to detailed requirements
of the authorities, until final approval is obtained. No additional costs will be considered for such
minor work. Amendments required after receipt of route approval by the authorities shall be
remunerated as per the relevant contractual rate for survey works.
Before the construction stage, route maps shall be amended for display of line access provisions
(refer to Technical Standard Specification, Part: S-CIVIL-OHL-Item 2.4).
time of measurement. All qualified crossings and approximations shall be covered by individual
clearance calculations, to be shown on the profile plan. Tower centre coordinates and all
elevations shall be reduced to UTM (Universal Transverse Mercator) Narwhan UAE datum, and
indicated on the profile plans.
The Bidder/Contractor shall locate and indicate bench marks and reference points already
existing in the project area for differential GPS positions. TRANSCO will render assistance to
the Bidder/Contractor in providing information about locations of the reference points. Where
these do not exist, the Bidder/Contractor shall provide such reference points in consultation with
e.g. the Town Planning Department, Public Works Department, etc.
The line route shall be marked in the field by timber survey pegs of sufficient length, with a
cross section of min. 50x50 mm, to be driven flush into the ground. The accurate centreline shall
be shown on the pegs by a single nail, to be driven into the peg’s top. Terminal and angle pegs
shall be secured by a concrete foundation, to TRANSCO’s approval. Straight line pegs shall be
driven along the OHL centerline, at a minimum of 4 per km, and to either side of every line
crossing. After approval of the tower distribution on the profile plans, tower centre pegs shall be
driven at site. After final approval of tower locations, which will be given by TRANSCO, after
detailed site inspection, insurance pegs shall be driven approx. 50 m to either side of each tower
centre peg, in line direction. Different kinds of pegs shall be distinguishable by a paint marking
system, to be submitted for TRANSCO’s approval.
All pegs or other marks shall be preserved until their removal is authorized by TRANSCO.
For the purpose of profile/tower location inspection by TRANSCO, all terminal-, angle-, and
other relevant line points shall be marked by red flags with a minimum size of 1.5 x 1.5 m, to be
mounted on min. 5 m high steel bases for HV lines and 1 x 1 m on 2 m high bases for MV lines.
The Bidder/Contractor shall minimize the number of tower locations between line angle points,
without exceeding the tower/conductor design limits. The tower distribution shall be performed
by means of a recognized computerized optimization program, to TRANSCO’s approval.
To facilitate approval of profile plans, the Bidder/Contractor shall provide TRANSCO with two
licensed copies of a/m program inclusive of all relevant survey- and other data in digital form,
and with three complete sets of transparent sag templates in perspex or similar material, 4 to 5
mm thick, based on the range of equivalent spans required, staggered at 50 m for HV lines and
20 m for MV lines, and for the conductor types and scales to be used. The templates shall be cut
precisely along the conductor catenary in still air, at maximum temperature (hot curve at 80°C).
The sag curve in still air, at minimum temperature (cold curve at 5°C), the span grid, the ground
clearance line, and all relevant details like design loading conditions, particulars of conductors,
equivalent span applicable, scales, etc. shall be engraved.
setting levels. It shall be ensured that the foundation concrete caps will have a minimum height
of 0,75 m above final ground level.
Relocation of a tower exceeding the longitudinal deviation limit will be allowed only if approved
by TRANSCO and for purposes of improving soil conditions for foundation work. Such
relocation shall in any case not exceed more than 10 m in either direction and will be allowed,
provided ground clearance is not impaired and specific loading of the particular tower is not
exceeded.
Towers in tangent positions shall be oriented with the transverse faces at right angles to the
transmission line centre line, and towers in angle positions shall be oriented with the transverse
face at right angles to the bisector of the deviation angle. Towers with asymmetrical crossarms
shall be offset from the theoretical centreline, so far as to even out the distance between
conductors of either tower side to the theoretical centreline.
As soon as the final tower locations are agreed and approved by TRANSCO, the
Bidder/Contractor shall submit a line schedule. The line schedule shall indicate route
designation, voltage, conductor type, number and size, tower numbers, tower types, body and leg
extensions, angles of deviation, insulator types, insulator string types, spans, equivalent spans,
section lengths, accumulated chainage, a “remarks” column in which details of crossings, etc.
can be entered. After the completion of various parts of the works further data, for instance the
foundation types for each tower, locations of mid span joints and repair sleeves, details of
counterpoise or special earthing requirements, and any other information deemed necessary by
TRANSCO shall be added to the line schedule.
( SPECIFICATION )
CONTENTS
1 GENERAL ....................................................................................................................... 3
1.1 Drawings ........................................................................................................................... 3
1.2 Equipment Identification and Color Codes ....................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 4
2.1 Towers............................................................................................................................... 4
2.1.1 General .............................................................................................................................. 4
2.1.2 Proven Tower Designs ...................................................................................................... 4
2.1.3 Material ............................................................................................................................. 4
2.1.4 Design................................................................................................................................ 4
2.1.5 Construction ...................................................................................................................... 6
2.1.6 Nuts and Bolts ................................................................................................................... 6
2.1.7 Anti-Climbing Devices, Step Bolts and Bird Guards........................................................ 7
2.1.8 Conductor and Earthwire Attachments ............................................................................. 8
2.1.9 Tower Grounding and Earth-Clamping Bolts ................................................................... 8
2.1.10 Solar Powered Aviation Hazard Lighting ......................................................................... 8
2.1.11 Workmanship .................................................................................................................... 9
2.1.12 Identification Plates......................................................................................................... 10
2.1.13 Tower Maintenance Safety Systems ............................................................................... 11
2.1.14 Marking, Packing and Handling...................................................................................... 11
2.1.15 Tower Locations.............................................................................................................. 12
2.1.16 Design Spans ................................................................................................................... 12
2.1.17 Design Loads................................................................................................................... 13
2.1.18 Full Scale Tower Load Test ............................................................................................ 15
2.1.19 Gantry and Gantry area ................................................................................................... 17
2.2 Erection of Towers .......................................................................................................... 18
2.2.1 General ............................................................................................................................ 18
2.2.2 Handling and Storage ...................................................................................................... 18
2.2.3 Erection ........................................................................................................................... 19
3 SCHEDULES OF OVER HEAD LINES .................................................................... 21
3.1 Schedule A ...................................................................................................................... 21
3.2 Schedule B1..................................................................................................................... 21
3.3 Schedule B2..................................................................................................................... 23
3.4 Schedule C1..................................................................................................................... 24
3.5 Schedule C2..................................................................................................................... 26
3.6 Schedule C3..................................................................................................................... 27
3.7 Schedule D ...................................................................................................................... 29
3.8 Schedule E ....................................................................................................................... 32
1 GENERAL
This part of the specification covers design, manufacture, testing, erection and commissioning of
HV overhead line towers of steel lattice design.
For applicable technical standards, tests and general requirements please refer to:
¾ S-TR-OHL-GEN - General Requirements (Applicable Technical Standards, Tests,
etc.)
1.1 Drawings
Typical Drawings for HV/MV Towers of Lattice Steel Design provided in the Drawings Section
are as follows:
Drawing No. Title
DWG TR OHL 02 01 Outline of 400 kV Suspension Tower (Type S±0)
DWG TR OHL 02 02 Outline of 400 kV Tension Tower (Type ±0)
DWG TR OHL 02 03 Outline of 220 kV Suspension Tower (Type S±0)
DWG TR OHL 02 04 Outline of 220 kV Tension Tower (Type ±0)
DWG TR OHL 02 05 Outline of 132 kV Suspension Tower (Type S±0)
DWG TR OHL 02 06 Outline of 132 kV Tension Tower (Type ±0)
DWG TR OHL 02 10-1 Tower Plates (400,000 V)
DWG TR OHL 02 10-2 Tower Plates (220,000 V)
DWG TR OHL 02 10-3 Tower Plates (132,000 V)
DWG TR OHL 02 11 Outline of 400 kV Suspension Tower (Type ±0) Alternative
DWG TR OHL 02 12 Outline of 400 kV Tension Tower (Type ±0) Alternative
DWG TR OHL 02 15 Airborne Observation Plate
2 TECHNICAL DESCRIPTION
2.1 Towers
2.1.1 General
Double circuit tower structures shall be of the self-supporting lattice type steel frame. The
general outlines of the towers, shall be as shown on the Drawing(s).
The members of the latticed structures shall be of hot rolled steel angle sections. All tower
material shall be factory made and entirely galvanized by the hot-dip process. The main data for
the overhead line is given in Schedule A. Basic tower types shall be as indicated in Schedule B.
2.1.3 Material
Material for the steel towers shall be of the type and grade most suitable for the application
intended and shall conform to the latest applicable standard, specifications and recommended
practices of the industry. Cold-formed steel angles, flat bars and rods shall not be used for tower
members.
Mild steel and/or high strength steel shall be used for the fabrication of towers. The quality of
steel to be used shall correspond to S275 J0 (for mild steel) and S355 J0 (for High Tensile Steel)
according to BS EN 10025 (latest Version). Reference is also made to Schedule B2.
For tower bolts reference shall be made to the relevant Article hereinafter.
All material shall be tested at the steel mill in accordance with the applicable specification and
standards under which they are manufactured. The Bidder/Contractor shall attach all the mill test
certificates with the report. Tests shall be conducted in accordance with approved quality plan.
The tests to be conducted shall include, but are not limited to, uniformity of galvanizing coating,
mechanical and chemical properties of all steel.
2.1.4 Design
This clause describes the basic requirements of the design procedure and its documentation. The
design shall be performed in accordance with VDE 0210 ‘Planning and Design of Overhead
Power Lines with Rated Voltages above 1 kV’ or ASCE 10-97 ‘Design of Latticed Steel
Transmission Structures’.
The design document of each type of tower shall include the following:
• Design criteria with grade of steel and minimum size for tower members and connections
and with maximum allowable slenderness ratio for tower members
• Calculation of the maximum wind pressure on the overhead line components
• Brief description of the software used for the structural analysis including explanation of
the computer model and load assumptions and combinations
• Sag and tension calculation for the required range of spans along with data sheets of
conductors and ground-wire, including all installed accessories and fittings. Tensions shall
be calculated using change-of-state equation with governing (starting) loading conditions
and tension limitations as specified in Schedules . Loading condition with quartering wind
shall be included in calculation as well. Sags shall be calculated using catenary formula
• Loading tables and loading trees prepared for the maximum external forces and for the
maximum tension in conductor and earthwire as per sag and tension calculation
• Calculation of the maximum swing angle of insulator strings, jumper loops, jumper strings
and complete conductor catenary span
• Calculation of the conductor clearance at mid-span in still air conditions
• Calculation of the member-wise wind load and self-weight of tower, including redundant
members
• Member design tables including member with size, length, gross area and radius of
gyration, compression and tension member forces, compression curve number, number and
size of bolts, bearing and shear stress, safety factors, including equations for calculation of
slenderness ratio as per relevant standard etc.
• Design of redundant members including buckling and bending criteria
• Foundation loads in global direction for each leg extension
• Design of stubs as per ASCE 10-97. Stub angles shall be at least 2 mm thicker than
attached steel leg angle and shall be fitted with cleats. The stub angle shall be completely
galvanised and shear connectors shall be designed to transfer entire axial and shear force.
Cleat connections shall be checked for shear and moment forces
• Design of anchor bolts as per ASCE 10-97. The design shall be supported with proper
figures
• Outline drawing and clearance diagram with member and bolt sizes and steel grade used.
The outline drawing shall include the redundant members. Tower height including
maximum sag, ground clearance and insulator length shall be indicated as well
• Copy of the computer input for the software used in the structural analysis and design of
tower.
The unit stresses in members and connections for the structural design calculation, based on the
design loading and design unbalanced loading (broken wire conditions) multiplied by safety
factor, indicated in Schedule C1, shall not exceed the yield stresses given in VDE 0210 or
ASCE-Standard 10-97. Connections shall be designed for the same member forces and according
to the above mentioned standards. The towers shall be designed with an overload capacity (factor
of safety) of f1 times the unbalanced design loading stipulated in the Specification. No damage
or permanent distortion of any members, bolts, connections of fittings or elongation of bolt holes
shall be permitted for these design conditions.
The slenderness ratios (L/r) of member given in the following table shall not be exceeded, where,
“L” is the buckling length of member as per the line diagram of the tower, and “r” is the
corresponding radius of gyration of the members.
• Tower legs, main compression members in l/r<150
cross arms and earth wire peak
• Other compression members carrying l/r<200
calculated stresses
• Redundant members l/r<250
The slenderness ratio of tension members shall be in accordance with the relevant standard used.
Other approved calculation methods may be applied according to the Standards specified or
otherwise approved by TRANSCO. In this case the calculated buckling resistance may not
exceed the VDE 0210 or ASCE-level.
2.1.5 Construction
The towers shall be of standard construction and shall be designed to reduce the number of
different parts to a minimum, thus facilitating transport and erection. No member shall be of
angles with dimensions less than 45 x 45 x 5 mm. The minimum thickness for legs and
compression members in cross arms and in earthwire peaks shall be 6 mm. Gusset plates shall
not be less than 6 mm thick.
The diameter of bolt holes for all types of towers shall not be more than 1.5 mm larger than the
nominal diameter of the bolt. All members of the towers shall be connected by bolts.
Connections of members shall be designed to avoid eccentricity as much as possible.
All members, except redundant members, carrying computed stress shall be connected with at
least two bolts.
All nuts and bolts shall be hot dip galvanized. Threads before galvanizing shall be coarse
threads. There shall be no excess of galvanizing at the root of the thread and nuts shall turn easily
on the completed bolts without excessive looseness. Nut threads shall be tapped after galvanizing
so as to produce a finger-free fit on the galvanizing. Bolts will be rejected if they are considered
by TRANSCO to have an excessively loose or tight fit.
The length of bolts and the length of thread shall be such that bearing is upon the shank and not
upon the threads. When in position all bolts or screwed rods shall project through the
corresponding nut, but such projection shall not exceed 8 mm nor less than 3 threads.
Each tower shall be fitted with an anti-climbing device to prevent unauthorized persons from
climbing the tower. The anti- climbing device shall be of either a spike type or a barbed wire
type of stainless steel and shall be fixed at a height of approx. 3 meters above the foundation. It
shall provide suitable gates adjacent to the step bolt legs to be locked with padlocks to
TRANSCO’s approval. Spikes shall be of solid design, have a sharp end, a minimum length of
250 mm and shall be pointed downwards. The maximum distance between spikes shall not be
more than 100 mm. The maximum distance between the strings of barbed wire shall be not more
than 200 mm. The horizontal separation of the strings of barbed wire shall be maintained by the
provision of spacers at a maximum distance of not more than 2 m.
For double circuit type towers step bolts shall be provided on two diagonally opposite tower
legs. They shall begin directly above the foundation and continue to the tower top. They shall be
spaced at a distance of 333 mm from center to center, distributed strictly alternating on the outer
sides of the leg angles. The spacing distance of all step bolts shall be equal on the entire tower.
Spacing tolerances according to VDE 0210/12.85 shall be accepted. Only the step bolts above
the anti climbing device shall be installed permanently on the tower. Bolts below the anti
climbing device shall either be installed, or be delivered to ENDUSER’s store.
All step bolts shall be at least 24 mm in diameter, with a free tread width of 20 cm. For
protection against slipping a lateral limit of min. 20 mm above top of step shall be provided. The
tread side of the step bolts shall be uniform for all towers. The fastening side may accommodate
different sizes, to take advantage of holes provided for structural bolts. Step bolts shall be rated
at least for a concentrated load of 1.5 kN, acting vertically at the most unfavourable position. If
applied in place of a structural bolt, it’s loading has to be considered, too.
Towers above 60 meters height shall be equipped from the appropriate level with inclined step
ladders, at the transversal tower faces or inside the tower shaft. Safe changeover routing from
step bolts to step ladders is to be provided. The ladders shall be fitted with safety cages and
provide passing platforms every 20 meters.
Tower members positioned above insulator strings/solar panels (if applicable) shall be fitted with
stainless steel needle strips, effectively preventing birds from sitting in these locations. The strips
shall extend sufficiently, horizontally beyond the protected location and be applied to all surfaces
a bird can sit on. Where needles are projecting from the crossarm contour towards live parts, the
tower clearance diagram shall consider the height of the needles.
Conductor and earth wire attachments shall be considered as part of the respective basic towers
and shall be supplied as integral parts of them.
All conductor suspension points shall provide 3 brackets for installation of suspension hinges
suitable for the attachment of double and single insulator strings associated with suspension
conductor support assemblies. Both, individual hinges and suspension point assemblies shall be
orientated in line direction, allowing the insulator strings to swing in crossarm direction.
Tension towers shall have brackets suitable for the attachment of tension hinges for double
insulator strings associated with dead-end conductor assemblies. These attachments shall be
provided in a way to maintain all distances between phases/OPGW/EW as on suspension towers
across the whole deflection range of the respective tower type.
The shieldwire shall be connected to the suspension tower peak by one hinge orientated in line
direction, allowing the suspension assembly to swing in crossarm direction. Connection to
tension towers shall be provided by tension assemblies, to be fixed to the tower peak.
For direct connection of overhead shield wire shunts to the towers, 2 sets of two holes, each,
shall be provided on every earth wire peak.
In the tower shaft, at top crossarm level, a steel grating work platform of min. 6 m² shall be
provided, suitable for installation of a battery/control unit enclosure with dimensions of min.
BxDxH of 130 cm x 130 cm x 100 cm, and a weight of min. 250 kg. Besides the box, the
platform shall be able to carry, simultaneously, the weight of 3 linesmen with tackle.
At the earthwire peak, two holes shall be provided, for vertical attachment of a warning light
assembly. In case of an earthwire crossarm, a pole shall be provided allowing installation of the
light above the system elevation.
Above facilities are considered integral tower part and shall be provided, regardless whether the
scope of work actually requires supply of warning lights or not.
Towers exceeding 45 m in height shall consider in the design the permanent and installation
loads of two intensity light systems installed a diagonally opposite tower legs, at half tower
height. These shall compromise for each system a photovoltaic module surface of min. 1.2m x
1.2m installed at a inclination of 450, a system enclosure of min. 100 kg with a platform of min
2m x 2m, and three linesmen with tackle.
For such lights, actual installation provision shall be procured only in case of actual requirement,
to be intimated by TRANSCO. These shall be designed in a way allowing installation on the step
bolt legs of the tower without need of drilling additional holes in the tower steel work.
2.1.11 Workmanship
All work shall be equal to the best modern practice in the manufacture and fabrication of
materials covered by this Specification.
The Bidder/Contractor shall be responsible for the correct fitting of all parts. He shall replace,
free of cost, any defective material discovered during erection, and pay all costs of field
corrections for such replacement.
All parts of the structure shall be neatly finished and free from kinks, twists or bends. The
fabrication shall be in strict accordance with the shop drawings prepared by the
Bidder/Contractor and approved by TRANSCO.
Structural material shall be straight and cleaned of all rust and dirt before laid out or worked in
any manner. Shearing and cutting shall be performed carefully. Manually guided cutting torches
shall not be used.
All bolt holes in steel members shall be punched, sub-punched, reamed or drilled before
galvanizing. Holes shall not be punched but only drilled, if the thickness of the metal exceeds the
diameter of the hole, in mild steel sections of > 19 mm thickness, high yield steel sections > 14
mm, and in all crossarm members exposed to permanent tension. All holes shall be cylindrical
and perpendicular to the member, clean cut with sharp tools and without torn or ragged edges.
All members shall be cut to jig and all holes shall be punched or drilled to jig. All parts shall be
carefully cut and holes accurately located so that when the members are in position the holes will
be truly opposite each other before being bolted up. Drifting of holes will not be allowed.
Danger plates shall feature red symbols on a white background. They shall comprise a skull with
crossed bones, as well as lightning arrows conforming to DIN 40006. The text “DANGER” shall
be boldly written in both, Arabic and English languages. The line voltage shall be shown, as
well.
Tower number plates shall show the tower number in black letters, on a white background. The
height of the letters shall not be less than 150 mm. letters in all ID plates should fit each plate
width identified, in bold fonts.
Circuit number plates shall show the circuit abbreviation and number in black letters, on a white
background. Termination gantries shall be equipped with circuit plates showing the circuit names
in full length.
Phase plates shall show the English letters “R”, “Y”, and “B”, in black color, on red, yellow &
blue backgrounds. The plate’s arrangement shall be in line with the phase’s configuration.
The tower number plate shall be installed on the tower base at height ≥2 m. The number plate
shall face the normal tower access. Fitting positions for all towers shall be submitted for
TRANSCO’s approval.
The circuit designation & the danger sign, as well as the phase identification plates shall be
installed under each circuit and shall be placed on the step bolt legs side (not on the leg itself),
directly above the anti climbing device. They shall be positioned to reflect the phase allocation
on the tower and to be easily identifiable from ground level.
Furthermore, on each tension and every tenth suspension tower an airborne observation number
plate shall be provided. The tower number shall be cut from the sheet metal, with a letter height
of min. 700 mm. The plate background shall be black. The plates shall be installed, either on the
top crossarm or on the earthwire peak, in a position that is easily recognizable from the air. It
shall be ensured that legibility of the cut-out number is not impaired by tower steelworks, placed
behind the plate. Orientation of all plates on the line shall be uniform, to TRANSCO’s approval.
All plates shall be of corrosion resistant aluminium with embossed letters and painted, with
thickness ≥3 mm.
On all plates, the colors shall be free from fading. Lettering and size of the plates shall be to
TRANSCO’s approval.
Tower members shall be assembled for shipment in bundles of the same size and weight
containing pieces of the same or similar identifications mark and length. All bolts, nuts, washers,
step bolts and minor fittings shall be shipped in wooden cases of suitable size and weight, with
pieces properly separated according to size and type.
To ensure uninterrupted erection, the Bidder/Contractor shall supply a five (5) percent excess of
bolts, nuts, washers, step bolts, and minor fittings.
It is the Bidder’s/Contractor’s responsibility to ensure that the packing and handling is made in
such a way that neither the steel nor the galvanizing shall be damaged in transit. Transporting
vehicles shall be clean and free from foreign material, which could in any way injure the steel or
zinc coating.
“maximum weight spans”. All Angle tower types have to be designed for “minimum weight
spans” equivalent to half of the maximum span given in schedule C2. At suspension position, the
minimum weight of conductor supported shall not be less than 25 % of the total weight of
conductor in the two adjacent spans.
Terminal towers shall be designed to face the direction of the incoming line, and shall withstand
the load of all conductors and earth wire.
2.1.18.1 Execution
Full scale tower load tests of assembled galvanized towers shall be carried out in accordance
with Standards IEC Publication No. 60652 (latest version).
The following requirements shall be fulfilled in the load tests of the tower:
i. The members in a test tower shall be of the same grade and quality of fabrication as those
to be supplied for the towers under these Tender Documents. The Bidder/Contractor shall
furnish certified test reports of the heats from which the material was rolled and a record
showing the heat from which each member was obtained. In order to differentiate the test
tower material from other tower material, the test tower material must be indented with a
different identification number.
ii. Test towers shall not be specially fitted other than with such fittings as are required on
similar towers to be erected in the field.
iii. Test towers shall be erected on a foundation structure, which shall be of adequate strength
and stiffness to safely withstand the tower reactions under test loading, without noticeable
distortion or displacement. The tower legs shall be connected to the anchorage in the same
manner as to the normal stub angle at site.
iv. While preparing for the tests, the Bidder/Contractor shall supply TRANSCO with a test
program, together with diagrams indicating the proposed methods of applying the various
loads and measurement of deflections. All instruments to be used in the tests such as
dynamometers, gauges and load cells shall be calibrated before the test.
v. The test loads shall be those obtained from the design loads multiplied by the specified
safety factor. Any combination of the test loads shall be applied to prove the capability of
the structure to withstand all required loading. The dead load of the tower will not be
factored.
vi. Each tower shall withstand the test loads for a duration as specified in IEC 60652, without
failure or permanent distortion of any member, fitting, bolt or part and without elongation
of bolt holes. The duration of test load shall start after the all indicators show that the loads
are not less than 100% of the test loads. There shall be no adjustment of loads during the
duration, as specified in IEC 60652. Should it become necessary to adjust the loading, the
duration, as specified in IEC 60652, shall restart after the adjustment is completed.
vii. All test loads shall be removed completely before the loads for the next test are applied.
Test loads corresponding to conductor and earthwire loading shall be applied to the
attachments provided for these loads while test loads equivalent to wind load on the tower
shall be applied in locations approved by TRANSCO. Friction losses in rigging shall be
taken into account in the application of the test loads.
viii. Any conspicuous yielding or any failure, under any of the test loading, shall be considered
as a defect, in which case the Bidder/Contractor shall modify the design and shall repeat
the test case in which a defect developed, at his own expense. Any delays in execution of
contract due to such failures or repetition of test, shall be the sole responsibility of the
Bidder/Contractor.
ix. One tower structure of each type (with maximum height extension) shall be tested. The
tower must be dismantled carefully after it has withstood all the test loads successfully.
The tested tower shall be transported to the project site for erection. The tower shall be
located in line route in such a way that it remains under-utilised compared to the design
loads. The location must be decided with TRANSCO’s approval.
x. TRANSCO reserves the right to modify the requirements for performing any or all tests
and the Bidder/Contractor will not be entitled to any compensation by reason of such
modification.
xi. Test samples for mechanical characteristics shall be cut from member of the prototype
tower and standard tensile tests shall be performed at Bidder’s(Contractor’s expense. The
results of the tests on these samples shall be considered satisfactory, if:
a. average yield value is equal or smaller than guaranteed minimum value time 1.25 for
steel members having a minimum guaranteed yield point lower or equal to 300 Mpa
b. average yield value of equal or smaller guaranteed minimum value times 1.17 for steel
members having a minimum guaranteed yield point greater than 300 Mpa
c. average ultimate strength value of equal or smaller than guaranteed minimum value
times 1.20.
The average are obtained from eight test specimens taken from different most heavily
loaded members of the tower for each grade of steel.
xii. The Bidder/Contractor shall submit full reports of all tower physical load tests including
clear photograph of the test set-ups and nature of all failures, certified calibration reports,
detailed diagrams showing the manner in which test loads were applied, deflection records,
mill certificate of tower material and material test report.
xiii. Each tower structure shall be assembled with all step bolts/ladders in place. TRANSCO’s
representative will test all climbing provisions for strict adherence to the specification and
suitability, by climbing every tower completely. Any modifications found advisable during
this test shall be incorporated into the tower design, without any extra cost.
Notwithstanding prior approval given for tower drawings, design and location of all
2.2.1 General
The Bidder/Contractor shall ascertain that all concrete foundations or rock anchor grouting are
cured and that all back-filled material is compacted to its approved level before placing or
erecting tower steel on the foundations. Concrete in tower foundations shall be allowed to set a
minimum of 7 days before erection of the tower and a minimum of 28 days before conductor and
earth wire installation on the tower.
The Bidder/Contractor shall erect the types of towers specified at the locations indicated on the
Contract Drawings.
Towers shall be assembled in accordance with the approved drawings and erected by a suitable
method, which will not overstrain structural members or their foundations, subject to
TRANSCO’s approval.
Larger damages to, or systematic defects of the galvanizing shall be repaired by hot-dip
galvanizing, only.
The attempt to repair shall not bind TRANSCO to accept the repaired part when this is re-offered
for inspection.
Acceptance by TRANSCO of any repaired galvanized steel does not absolve the
Bidder/Contractor from his responsibility of supplying galvanized steel to give satisfactory
service in the prevailing corrosive atmosphere. TRANSCO reserve the right to reject any
galvanized steel found rusty, damaged, bent or other-wise defective, before final acceptance.
The Bidder/Contractor shall note that galvanizing facilities are existing in the U.A.E. and may be
used for re-galvanizing of seriously damaged parts, on the advise of TRANSCO.
2.2.3 Erection
Prior to the commencement of any tower erection activity the Bidder/Contractor shall submit for
approval a Method Statement detailing the proposed erection methods and safety precautions to
be taken during the erection.
The Bidder/Contractor shall erect towers for the transmission line in accordance with the
erection diagrams, construction lists and other drawings and instructions.
The method of assembling and erecting a tower shall be such that during erection no member
shall be subjected to any stress in excess of that for which it was designed.
Misalignment or misfit of adjacent sections or members attributable to the adopted method of
erection shall be corrected by changing erection methods as necessary to eliminate trouble.
Straining of members shall not be permitted for bringing them into position. It may, however, be
necessary to match hole positions at joints and to facilitate this, tommy bars not more than
450mm long may be used.
For ease of checking bolts and nuts shall be generally fitted in such a way that the nuts are placed
outside for horizontal bolts and downside for vertical bolts.
Before starting erection of an upper section, the lower section shall be completely braced and all
bolts provided tightened adequately in accordance with approved drawings to prevent any
mishap during erection.
All plan diagonals relevant to a section of tower shall be placed in position before assembly of
upper section is taken up.
All members shall have their joints cleaned when bolted up.
If erected by assembling in sections, the initial tightening of bolts shall be adequate for dead
load, live load and direction stresses, but shall not be so strong as to prevent aligning and fitting
adjacent sections or members. The assembled sections shall be adequately supported during
erection.
All blank holes, if any left, after complete erection of the tower, are to be filled up by bolts and
nuts of the correct size.
During the erection, no tools shall be taken up to the towers, except structure wrenches and drift
pins. Only such wrenches will be allowed, which do neither deform nor injure the galvanized
coating of the bolts/nuts. Use of drift pins is limited to guiding the different tower members into
position, without enlarging holes or distorting tower members.
Each bolt shall be securely tightened with adequate but non-excessive torque. Proper tightness
shall be spot checked by the Bidder/Contractor, to TRANSCO’s satisfaction, with an accurately
calibrated torque wrench. The Bidder/Contractor shall indicate the torque that shall be applied
for each bolt size. All tower bolts shall be completely tightened, immediately after a tower is
erected. After erection, towers shall be left in workmanlike condition, complete and safe in every
respect.
In order to prevent pilfering, all bolts and nuts below a minimum height of 3 m above the
foundation cap shall be secured by suitable means, to be proposed by the Bidder/Contractor, for
TRANSCO’s approval.
During assembly punching, reaming or drilling for correction of mismatched holes shall not be
permitted without the authorisation of TRANSCO in writing.
If any shop errors are discovered in the steel, the Bidder/Contractor shall notify TRANSCO who
will decide on site whether the error shall be corrected on site or the members shall be replaced.
All exposed steel surfaces around the holes or on cuts on which corrective work is permitted
shall be given sufficient coats of an authorised zinc rich paint to provide sufficient protection to
the steel and shall be to the approval of TRANSCO.
Earth clamping bolts and tower sign plates shall be installed according to Article 2.1.9.
Towers must be completely erected with all members in place and bolts securely tightened
before any stringing of conductors or earth wires may be started. All towers shall be inspected by
TRANSCO accompanied by the Bidder/Contractor before the stringing operation. Prior to the
erection of towers or parts of towers, which had completely been assembled on ground, the
approval of TRANSCO is required.
In aviation-marking areas, immediately after erection above foundation level, the towers shall be
illuminated, either by the permanent lighting system or by a temporary lighting system, to be
approved by the Department of Civil Aviation.
3.1 Schedule A
LINE DATA (400 KV)
Item Description Details
1 Number of Circuits 2
2 Number of conductors per phase 4
3 Number of OPGW/earthwires 2
3.2 Schedule B1
TOWER TYPES (400/220/132 KV)
Item Tower Position where Used Angle of Deviation Type of
Types up to (Degrees) Insulator String
1 S Straight line 0..2 Suspension
2 AT Angle tension 0..30 Tension
3 BAT Big Angle tension 30..60 Tension
If the Bidder/Contractor deems a combination of different tower types into a single type (still
according to the specification requirements) as economical solution, he is invited to propose so.
Notes:
* DE tower and Gantries shall be designed to face the direction of the incoming line and shall
withstand the load of the conductors and OPGW/earthwire. Both shall be designed to accept at
least 45 degree in the slack span. The gantry width shall be provided as per actual requirements.
Erection Holes to be provided at crossarm tip of all towers. All BAT/DE towers shall have
provision for three earth wires to be connected to substation. All Gantries in substations shall
have provision (holes) on end columns for future extension.
The design of the towers shall cater for leg extensions from +6m to -6m in steps of 1m. The
estimated quantity of leg extensions as per the Bills of Quantities is the cumulated quantity for
all numbers of leg extensions per tower type.
If the Bidder/Contractor deems a combination of different tower types into a single type (still
according to the specification requirements) as economical solution, he is invited to propose so.
Notes:
* BAT Tower shall have same body with different cross-arms for the deviation ranges up to
60/90 degree. Extended or rectangular shape cross-arms may be provided.
** DE (terminal) tower shall face the direction of the incoming line and shall withstand the
load of the conductors and earthwire. The cross arm arrangement and cross arm lengths
shall be designed for down leads to the sealing ends and surge arresters installed on the
provided tower platforms.
The design of the towers shall cater for leg extensions from +6m to –6m in steps of 1m.
The estimated quantity of leg extensions as per the Bills of Quantities is the cumulated
quantity for all numbers of leg extensions per tower type.
3.3 Schedule B2
TOWER STEEL PARTICULARS
Item Description Minimum Values
1 Structural Steel (S275)
1.1 Tensile strength N/mm2 410
1.2 Yield point N/mm2 275
3.4 Schedule C1
FACTORS OF SAFETY
Item Description Minimum Factor of Safety
1 Conductors
1.1 Conductors at final maximum working tension
based on:
- ultimate strength 2.50
1.2 Conductors at still air everyday temperatures
final tension based on:
- ultimate strength 5.55
1.3 Dead end compression clamps and compression
splices based on:
- conductor ultimate strength 0.95
Schedule C1 (continued)
4 OPGW/Earthwires
4.1 OPGW/Earthwire at final maximum
working tension based on:
- ultimate strength 2.50
4.2 OPGW/Earthwire at still air everyday
temperature final tension based on:
- ultimate strength 5.55
Schedule C1 (continued)
3.5 Schedule C2
DESIGN SPANS (400 KV)
Abbr. Tower Type Basic- Wind Max. Weight- Min. Weight-
span Span Span Span
S Suspension 500 550 600 150
AT Angle tension 500 550 600 -
BAT Big angle tension 500 550 600 -
DE Dead-end tension 350 400 550 -
G Substation gantry 120 120 120 -
Schedule C2 (continued)
3.6 Schedule C3
DESIGN DATA
Item Description Data
1 Temperatures
1.1 Maximum temperature of °C 80
conductor
1.2 Everyday temperature of °C 35
conductor
1.3 Minimum temperature of °C 5
conductor
1.4 Maximum temperature of °C 60
OPGW
1.5 Everyday temperature of °C 35
OPGW
1.6 Minimum temperature of °C 5
OPGW
2. Wind Loads
Wind Pressure on Tower and its According to VDE 0210.
attachments shall be calculated for a wind The dynamic wind pressure
speed of 160Kmph combined with the in Table 5 is based on a
3.7 Schedule D
Electrical minimum clearances shall be according to International Standards and shall
correspond to those clearances specified in the Standard Technical Specification, Part: Electrical
Design Fundamentals (S-GEN-EDF).
The following are the minimum clearances between live conductors and other objects, to
correspond with the maximum conductor sag conditions.
MINIMUM CLEARANCES FOR 400 KV OHL
Item Description Minimum clearances
in meters
1. Normal ground for pedestrians only 9
2. Residential areas 9
4. Highways 12
8. Telecommunication lines 5
Schedule D (continued)
2. Residential areas 8
4. Highways 10
8. Telecommunication lines 5
Schedule D (continued)
The following are the minimum clearances between live conductors and other objects, to
correspond with the maximum conductor sag conditions.
4. Highways 10
Schedule D (continued)
For other objects not listed in the Schedule the requirements for minimum clearances shall
comply with DIN VDE 0210.
Minimum clearances to objects shall be kept after final settling of conductors, i.e. including 20
years creep.
Minimum clearances between live metal and earth steelwork shall be calculated in accordance
with DIN VDE 0210. These clearances shall be checked on the assumption that the conductor
may attain a position at any angle between 5° above and 20° below the horizontal for all types of
tower.
Conductor sag shall conform to EDS at 35°C ≤ 18% UTS.
Earth wire sag shall not be larger then the conductor sag under any circumstances.
3.8 Schedule E
Item Description
1 Ground rods
2 Ground strip
Welded connections
Schedules shall be submitted to TRANSCO for his approval and the same shall form part of the
final records.
CORROSION PROTECTION
( SPECIFICATION )
CONTENTS
CORROSION PROTECTION
1 GENERAL
This specification generally covers surface protections against corrosion and defines the
minimum requirements for surface preparation/treatment, protective coatings and painting for
structural steel, iron works, metal and other non-metallic surfaces.
The following shall be applicable and shall be considered:
a) All metallic parts (except stainless steel parts) used inside closed rooms shall be painted or
galvanised.
b) All metallic parts used outdoor shall be galvanized and painted.
c) Zink and paints and related protection material shall be in accordance with the latest
international standards as a minimum requirement, and shall comply with the requirements of
proper health, safety, and environmental conditions.
d) Equipment to be used for performing the required galvanizing or painting, should be
equivalent to the equipment recommended by the paint manufacturer and should be suitable
to apply the coating as specified.
e) Painting materials shall be delivered to locations where painting is to be carried out, in
unopened original containers, which shall bear a legible product designation, batch number,
date of manufacture and expiry date. The date of manufacture must not be before the date of
paint system approval.
f) Only complete paint kits shall be mixed. No partial kits will be accepted. Surplus Paint in
Pots of expired mixed material must not be used after the expiry date of these materials.
g) The painting material shall be handled and stored in accordance with the paint
manufacturer’s latest published instructions and shall be protected against damage, moisture,
direct sunlight and temperatures.
h) Storage temperature of paint shall range between 5oC and 35oC.
i) Compressed air used for cleaning, surface preparation (abrasive blasting) and application
shall be free of oil and moisture.
j) Blasting material shall be clean and free from oil or contaminants. The particle size shall be
capable of achieving specified surface profile.
3 SAFETY PRECAUTIONS
All painting and corrosion protection works shall be performed under strict safety conditions,
primarily adequate ventilation and protection from open flames, spark and excessive heat.
The Bidder/Contractor shall take all necessary precautions to protect personnel and property
from hazards due to falls, injuries, toxic fumes, fires, explosions or other dangers.
All paint and thinners shall be stored in areas, which are well ventilated and protected. The
Bidder/Contractor shall consider air-conditioned storage facilities due to the limited store-ability
of the paints required.
Temporary constructions, ladders scaffolding, runways, etc. required for safe execution of the
painting work shall be rigidly built so as to safely support four times the weight of all materials,
apparatus, equipment and workers thereon.
Test Instruments
The surface preparations for steel iron works shall be compared with the relevant pictures of SIS
05 5900. The surface profile shall be measured by using a Profilometer, i.e. Tester Tape.
If required by TRANSCO/ENGINEER copper sulfate test shall be carried out to check for
residual mill scales.
The dry film thickness or galvanization thickness on steel shall be measured by means of a
magnetic or electrical thickness gauge such as "Microtester" or "Elcometer", and recorded in a
tabulated form, indicating each layer of coat and the total dry film thickness.
In case of fluid retaining structures, pinhole detection shall be carried out by means of low-
voltage, non-destructive flow detector, whereas, in the case of rubber lining or wrapping,
damages shall be checked by means of a spark tester.
During application of paint the wet film thickness shall be checked continuously by means of an
approved wet film thickness gauge. Also, the dew point has to be monitored continuously by
through an approved instrument and methods of measurements/ recording.
A pull-off adhesion test must be used in case of paint on concrete and steel surfaces.
An approved type of multi-cross cutter for adhesion tests depending on the thickness of the
coating is also required.
For the above mentioned tests which shall be performed in the presence of TRANSCO, all
respective instruments shall be provided by the Bidder/Contractor, and shall be kept in good
working condition and valid/certified calibration.
4 MATERIALS
The materials of successive coats shall be from the same manufacturer and subject to
TRANSCO’s approval before relevant orders are placed.
Materials shall be used from a manufacturer who has good experience with his products with
regard to corrosion protection in such special areas. Further reference for supply of samples is
made hereafter.
Materials, which are to be supplied and used for the surface protection work (e.g. paints, filling
cements, metallic coating etc.,) must comply with quality regulations and standards, as well as
with the following provisions and any special permit conditions and official regulations. Should
a certain material, stipulated in the Specification, not possible to get during the design/execution
of the paint system, it shall be possible subject to an approval by TRANSCO, to use an
alternative material that can be proven to be at least equal in quality and suitability.
The Bidder/Contractor shall obtain the paint manufacturer's specific recommendations,
directions and specific provisions for application. These recommendations and directions shall
be strictly adhered to. The use of any amount of thinners is restricted to the permission of
TRANSCO and paint manufacturer.
All paints shall be delivered in their original undamaged sealed containers and shall remain
unopened until required for use. Paint, which has gelled or otherwise deteriorated over the
storage period, shall not be used.
The quality of the paints should be such that they do not form solid sediment but, at most, a
slight skin in unopened original containers over a period of not less than six months calculated
from the manufactures delivery date. A paint which has formed a solid sediment or more than
just a slight skin in the unopened original containers by the time of use or which cannot be
processed satisfactorily shall not be used. A sediment shall be regarded as solid if it cannot be
dispelled again quickly and completely by stirring with an adequate electric driven mixer
(maximum speed 350 to 400 rpm).
Paint that does not have to be prepared by mixing several constituents should be delivered to the
site, just prior to use, in such a state of readiness that they need only be adjusted to brushing or
spraying consistency. This is to meet the relevant working conditions, such as temperature, by
adding the particular thinners as per the manufacturer instructions, which shall be subject to
TRANSCO approval.
In the case of paints, which are only prepared for use immediately before application by mixing
several constituents (e.g. multi-constituent types), the various constituents should be of such a
kind that mixing at site is restricted to the necessary extent.
Paints and filling cements selected for the protection of steel or aluminium alloys against
corrosion, for which no regulations, permit conditions or technical conditions of delivery exist,
may be used if proven suitable, by the Bidder/Contractor, for the necessary degree of protection
against corrosion, and after approval of TRANSCO.
square meter and corresponding average thickness of Zink coating shall not be less than 128 Micron
and the individual coating shall not be less than 125 Micron. For all fasteners the minimum Zinc coat
applied shall be 381 gram per square meter and corresponding average thickness of Zink coating
shall not be less than 54 Micron. The individual coating shall not be less than 43 Micron.
The Zinc coating shall confirm to ASTM A123/A 123M for all steel products and ASTM A 153/A
153M for all fasteners except the required Zinc coating thickness given in above clause for all steel
including bolts, nuts and washers.
Adhesion tests outlined in Article 7.4.2, ASTM A 123-84, shall be performed, at the discretion
of TRANSCO.
Where members are of such length that they cannot be dipped in one operation, great care shall
be exercised to prevent wrapping. All holes in material shall be free of excess spelter after
galvanizing. All material shall be safeguarded against embrittlement during galvanizing. The
Zinc coating shall be uniform in thickness and so applied that it will adhere to the surface of the
steel.
Major damage to galvanizing shall be cause for rejection. Material on which galvanizing has
been damaged shall be re-dipped unless the damage is minor and local then it can be repaired by,
simply, applying galvanizing repair paint or hot zinc spray to the satisfaction of TRANSCO.
For protection during transport and erection, all galvanized steel members shall be coated with a
suitable pre-primer with minimum thickness of 40 micron and matching the primer to be applied
after erection. The primer shall be subject to TRANSCO’s approval.
If not otherwise specified, galvanized steel surfaces shall be chromated with approximately 4-
micron thickness and shall be removed by suitable means prior to painting.
Single items such as cable trays, fences, etc. shall be galvanized, and PVC covered if so
approved by TRANSCO.
7 REPAIR PROCEDURES
Every coat of paint shall have a thickness as even as possible. It must not be, in any place, lower
than the specified minimum thickness. Too big thickness is not recommended, and adherence to
the manufacturers maximum coat thickness shall be observed.
All finishes shall be in clean, good and sound condition and kept clean and dry until the paint has
reached a hard setting. Completed surfaces, which do not meet the levels, as set forth in these
Specifications, shall be re-coated at the cost of the Bidder/Contractor.
To ensure the suitability of paints the Bidder/Contractor shall execute sample tests at site. Such
panels must be approved and shall be used as reference for quality control.
These tests shall be carried out at a very early stage of the contract period and no paint shall be
ordered beforehand. Final selection of the paint is subject to the approval of TRANSCO,
depending on the results of the above mentioned site tests.
9.1 Cleaning and Surface Preparation of Ferrous and Non Ferrous Surfaces
Surfaces shall be cleaned and prepared for painting in accordance with the following regulations
and specifications:
• Chemical cleaning and surface preparation/etching
• Mechanical hand cleaning according to SIS 05 5900
• Blast cleaning of steel surfaces with abrasive as approved by TRANSCO and according to
SIS 05 5900 SA2.5 or SA3 or equivalent.
Aluminum and other light metals shall have their surfaces cleaned and degreased by a detergent
such as trichloroethylene prior to painting. A one coat of a wash-primer shall be applied before
proceeding with the specified coating system. Wash-primer shall be applied in a very thin film (5
- 10 microns) direct on pre-treated surfaces.
9.4.1 General
This article covers, besides the painting of work fabricated at site, also repair painting of
damaged surfaces originally corrosion protected at the manufacturer's premises.
For general performance and application under local climate conditions, reference is made to
Standard Technical Specification, Part:
➢ S-TR-GEN-GDF - General Conditions
All surfaces shall be carefully dried and cleaned prior to painting; in particular, removal of all
foreign matters such as salt, grease, dust, sand, dirt, and rust (if applicable) is of utmost
importance. Sand blasting to SA2.5.
All steel surfaces of solid type transformer tanks, conservators, cable boxes, etc. shall be
sand-blasted in accordance with DIN 55928, Part 4 (equivalent to SIS 055900), and all surfaces of
radiators and corrugated tank walls shall be thoroughly cleaned of rust, scale, grease and dirt and
other foreign matter and all imperfections shall be removed by means of approved methods.
Then the following painting systems shall be applied complying with the requirements as specified
below.
If any hot-dip galvanised steel parts will be provided, e.g. for access ladders etc., the same
painting methods as above shall be applied. However, instead of a primer coat as specified above
one adhesive base coat shall be applied. In this case, the minimum thickness of galvanising shall
be 55 m. However, a two-component epoxy zinc-dust coat instead of hot dip galvanising is
preferred.
In case of any kind of aluminium and/or ordinary stainless steel (Cr-Ni alloyed only) the primer
coat as above may be omitted, and the minimum thickness of the “intermediate” coat and of the
top coat as specified above shall be at least 50 m each (total min.100 m).
The final coat of painting shall be non-porous and of homogeneous quality and shall be of a
uniform shade of colour code RAL 7032 (pebble-grey). For OLTC equipment and sub-supplier’s
accessories only, the colour code as per manufacturer’s standard may also be accepted, on condition
that a two-component epoxy based undercoat (minimum thickness 80 m) and a two-component
polyurethane based top coat (minimum thickness 80 m) will be applied. The total dry-film
thickness shall not be less than 160 m.
Mechanical damage of painting shall be repaired at site with the same original type of painting as
above.
9.5.2 Internal Surfaces of Transformer/Reactor Tank, Cover, Core Steel Plates, etc.)
Inside the transformer and rector vessel, sand-blasting shall be performed in accordance with
DIN 55928 Part 4 (equivalent to SIS 055900). After that, an oil and gas resistant insulating
coating shall be applied to all steel surfaces in contact with oil or gas (e.g. tank, cover, core steel
plates, etc.).
The minimum dry-film thickness shall be 35 m. The applicable colour code shall be RAL 9010
(white) or equivalent.
Inaccessible surface e.g. back to back members shall be painted prior to site erection.
In highly restricted areas, all towers and structures above specified height, application of the red
and white bands shall be in accordance with Annex 14, Aerodromes, Chapter 6, paragraph 6.2.5
of the International Standards and Recommended Practices issued by the International Civil
Aviation Organization, and shall be subject to TRANSCO's approval.
Galvanized structures, such as towers, supporting structures and gantries located 70 km away
from the coastal line need not to be painted unless else specified.
EARTHING / LIGHTNING
( SPECIFICATION )
EARTHING/GROUNDING SYSTEMS
CONTENTS
1 GENERAL ....................................................................................................................... 4
1.1 Drawings ........................................................................................................................... 4
1.2 Equipment Identification and Color Codes ....................................................................... 5
2 TECHNICAL DESCRIPTION ...................................................................................... 5
2.1 General .............................................................................................................................. 5
2.2 Earthing/Grounding System Planning and Design............................................................ 7
2.2.1 General .............................................................................................................................. 7
2.2.2 Design Requirements ........................................................................................................ 8
2.2.3 Applicable Apparent Soil Resistance Measurement Method ............................................ 9
2.2.4 Calculation of Step and Touch Voltages ......................................................................... 10
2.3 Potential Equalizing ........................................................................................................ 10
2.4 Equipment and Materials Requirements ......................................................................... 11
2.4.1 Mobile Earthing/Grounding Equipment.......................................................................... 11
2.4.2 Earthing/Grounding Terminal Lugs ................................................................................ 11
2.4.3 Earthing/Grounding Flexible Copper Braids................................................................... 11
2.4.4 Earthing/Grounding Cables............................................................................................. 11
2.4.5 Risers............................................................................................................................... 11
2.4.6 Grounding Rods .............................................................................................................. 11
2.4.7 Grounding Electrodes...................................................................................................... 11
2.4.8 Low Resistance Shield Conductors ................................................................................. 12
2.4.9 Ground Continuity Conductors ....................................................................................... 12
2.5 Earthing/Grounding Connections.................................................................................... 12
2.6 Earthing Conductor Connections .................................................................................... 13
2.6.1 General ............................................................................................................................ 13
2.6.2 Exothermic Welding Materials (if Exothermic Process is Required) ............................. 13
2.7 Deep Bore Grounding ..................................................................................................... 14
2.8 Earthing /Grounding Applications .................................................................................. 14
2.8.1 Overhead Tower .............................................................................................................. 14
2.8.2 Power Transformer and Reactor...................................................................................... 15
2.8.3 Power Cables................................................................................................................... 16
2.8.4 GIS .................................................................................................................................. 18
2.8.5 Fixed Earthing/Grounding Switches, etc......................................................................... 19
2.8.6 Lightning Arrestors ......................................................................................................... 19
2.8.7 Light Poles....................................................................................................................... 19
2.8.8 Panels, Cubicles .............................................................................................................. 19
2.8.9 DC Distribution Equipment............................................................................................. 19
2.8.10 AC Distribution Equipment............................................................................................. 19
2.8.11 Steel Structure ................................................................................................................. 19
2.8.12 Operating Areas............................................................................................................... 20
2.8.13 Operating Handles and Switch Shafts ............................................................................. 20
2.8.14 Fences and Service Areas outside of Fences ................................................................... 20
2.8.15 Others .............................................................................................................................. 20
3 TESTING AND INSPECTION.................................................................................... 20
3.1 General ............................................................................................................................ 20
EARTHING/GROUNDING SYSTEMS
1 GENERAL
1.1 Drawings
Typical Drawings for Earthing/Grounding System are provided in the Drawings Section as
follows:
Drawing No. Title
DWG TR EARTH 01 01 Earthing/Grounding System-1 (Sample 1)
DWG TR EARTH 01 02 Earthing/Grounding System-1 (Sample 2)
DWG TR EARTH 01 03 Detail of Earthing/Grounding System
DWG TR EARTH 01 04 Standard Copper Wire Junctions for Earthing/Grounding
Systems
DWG TR EARTH 01 05 Potential Equalising Grid in Concrete Floor
2 TECHNICAL DESCRIPTION
2.1 General
This specification covers the technical requirements for Earthing/Grounding Systems in
substations and/or switchyards, to protect people, equipment and to allow safe service and
maintenance of the electrical installations.
The Earthing/Grounding System, even when designed with a very low resistance, cannot be
considered as an equal-voltage surface. Substantial system voltage differences may occur and
may directly influence through a number of factors such as system resistance, system geometry
and distribution of ground currents, ground resistivity, and frequency of the transient.
The Earthing/Grounding System shall include earthing grid, raisers, grounding rods and all
required earthing/grounding connections.
The Bidder/Contractor shall design and install a high quality Earthing/Grounding System by
application of materials that meet the requirements of this specification.
The Bidder/Contractor shall bear full responsibility for the Earthing/Grounding System materials
by ensuring that the proposed Earthing/Grounding Systems are designed, manufactured and
installed in line with all internationally recognised codes and standards.
Earthing/Grounding Systems shall perform satisfactorily for the whole life time (50 years) of the
substation and/or switching yard without deterioration due to corrosion. It should continually
maintain a low resistance to the ground, satisfy thermal stability, and be capable of carrying
maximum anticipated full fault currents without deterioration.
The Earthing/Grounding System conductor size shall be designed to satisfy the flow of full fault
currents as specified in the Technical Data Sheets.
The Bidder/Contractor shall carry out ground resistivity and aggressiveness of soil measurements
of the whole Substation plot. If a plot will be filled with a soil layer > 1 m to rise the level, two
soil resistivity measurements – one before and one after the filling – shall be carried out. Based
on the results of these measurements and taking into account the system parameters, the
appropriate calculation and design shall then be worked out. The calculation shall indicate areas
where impermissible touch and step voltage exists. This shall include any place within the
substation premises and the area surrounding around the substation and/or switchyard
boundary/fence (approximately 3 m outside the boundary), where people/vehicles are likely to
pass by.
Prior to any Earthing/Grounding System calculation, the Bidder/Contractor shall agree with
TRANSCO what type of computer programme shall be applied for the Earthing/Grounding
System calculation.
If the finally agreed calculation programme is already available with TRANSCO it should be
updated (if it is not the latest version) otherwise the applied software shall be supplied to
TRANSCO and a software training shall be included in the Contract price.
The calculation results and the Earthing/Grounding System design shall be submitted for
TRANSCO approval.
The Earthing/Grounding System installation shall be closely co-ordinated with the relevant parts
of the civil works and have to be checked with the detailed civil engineering drawings related to
all structures, incl. foundations.
The design of Earthing/Grounding System, the methods of earthing/grounding, and the shielding
of control circuits shall not affect the control equipment.
Upon approving the calculation and respectively the Earthing/Grounding design the
Bidder/Contractor shall commence the implementation of the Earthing/Grounding System
accordingly.
The Bidder/Contractor shall carry out verification checks (by experienced personnel) during and
after installation to ensure that the applied Earthing/Grounding System is in accordance with the
design and that permissible step and touch voltage will/has not been exceeded.
All documents including limitations and justifications shall be forwarded to TRANSCO for
approval.
Earthing/grounding and shielding methods shall be as follows:
a) Number of earthing/grounding rods shall be defined according to earthing/grounding
calculation.
b) In electrical rooms like GIS, LVAC/DC rooms, basements, etc galvanised iron potential
equalising meshes as specified in the Technical Data Sheets shall be provided. It shall be
connected to the earthing grid via potential equalization bars at four locations. The
potential equalisation bars shall meet requirements as specified in the Technical Data
Sheets and shall be approved by TRANSCO. The potential equalisation bars shall be
protected by a stainless steel cover.
c) Steel fences within and around substation and/or switchyard areas shall be connected to the
Earthing/Grounding System at different intervals. Touch and step potentials on both sides
of the fences must be within the specified limits.
d) At least, one potential control ring as specified in the Technical Data Sheets shall be
installed around each building inside of the substation and/or switchyard.
e) An earthing mesh as specified in the Technical Data Sheets shall be installed underneath of
each power transformer.
f) When a Substation is located adjacent to either another substation or to a power station, the
existing Earthing/Grounding Systems and (the new one) of the subject project shall be
inter-connected as specified in the Technical Data Sheets.
g) Minimum one earthing/grounding rod shall be installed, one at each corner of a building
and of a substation and/or switchyard plot.
h) Secondary of current transformer shall be connected to ground at only one point.
Earthing/Grounding System shall compose of copper-claded steel electrodes, tinned stranded
copper conductors/copper tapes, PVC covered stranded copper conductors, etc.
2.2.1 General
The function of an Earthing/Grounding System for an electrical installation shall be threefold:
i. To maintain the potential of any part of the installation at a definite value with respect to
the ground.
ii. To allow current to flow in the event of a fault to ground, so that the protective equipment
will operate and the faulty circuit thus become isolated.
iii. To ensure that in the event of a fault, equipment normally ‘dead’ (un-energised) does not
attain a dangerous potential above or below ground.
Measurement of:
a) Soil resistivity
b) Aggressiveness of the soil (such as redex potential, moisture content, pH value, presence of
dissolved salts/organic acids, etc.)
for sizing of the Earthing/Grounding Grid shall be executed.
For the effect of corrosion, an allowance, which should not be less than 10% of the calculated
Earthing/Grounding grid size can be considered.
Calculations as above specified shall be made to establish an Earthing/Grounding System by
assuming ideal conditions. However, it is important to make allowances for possible variations.
Likewise, when measuring the ground resistance variations should be kept in mind considering
the accuracy of the measurement required.
It is normally the best policy to plan an Earthing/Grounding System with information gained
from a resistivity survey, plus using system design formula. The true soil resistance is likely to
be nearer the design value, if environmental and ground conditions changes have been taken into
account. The measured value tends to be lower than the true value with techniques used today.
The conductivity of the ground has a considerable influence on the effectiveness of an
Earthing/Grounding System. It shall be one of the factors governing a grounding electrode’s
resistance.
The resistivity of the soil shall be taken as:
ρ = Ω x m2 / m = Ω x m
which represents the resistance between opposite faces of a metre cube of ground.
Various conditions of the ground causes different resistivities and the differences found between
them are quite considerable, as the table above illustrates.
The amount of water held in the soil is governed by the weather conditions, time of the year,
nature of the soil, etc. To a certain degree the temperature of the soil has an effect upon
resistivity, lower temperatures causing higher resistivities, therefore, climatic changes have a
bearing on the planning of Earthing/Grounding Systems.
The design of the earthing/grounding system shall be such that the maximum permissible step
and touch voltages are not exceeded, (refer to Guide IEEE Std. 80, latest Version).
For turnkey projects, if the actually measured resistance of the installed ground system is higher
than specified, the Bidder/Contractor shall install, at no extra cost, additional earthing/grounding
rods, mats, etc., until the field-measured resistance is equal to or less than the specified value.
The ground system shall be composed of a system of tinned copper conductors buried
approximately 60 cm. beneath the surface of the ground, excluding crushed rock surfacing. The
grid system shall cover the entire fenced substation area and shall extend one meter outside of
the substation fence.
In case of smaller plot areas or substations housed in buildings, the grounding mesh shall be
installed below the basement floor. At each corner a ground rod shall be provided.
Driven ground rods shall be installed at regular intervals and connected to the earthing/grounding
conductor at grid nodes. Four of the ground rods, at least, must be installed (one at each corner of
the ground grid). The Bidder/Contractor shall determine the spacing of ground grid conductors
and the total number and location of ground rods and their lengths (single or two or more
coupled sections).
The measuring technique to be followed for apparent soil resistance measurement shall be the
one developed Dr. F. Wenner of the US Bureau of Standards, which is described in a paper:
report No. 255 Bulletin of Bureau Standards, volume 12 No. 3, 11th October 1915, and titled ‘A
Method of Measuring Earth Resistivity’. The basis of this principle is given below:
The method is sometimes known as the ‘four electrodes method’ because four electrodes (spikes)
are inserted into the ground and connected to the terminals of the earth tester.
The four spikes are equally spaced in a straight line and driven into the ground such that the
depth of insertion is <1/3 of the distance “a” between the spikes.
The spikes are connected to the earth resistance tester by multi-core cables.
Current is passed through the ground via the two outer spikes, which are connected to the current
terminals of the tester. The voltage appearing between the inner spikes connected to the potential
terminals of the tester as a result of the current flowing is measured.
The formula for calculating the specific apparent soil resistance at a certain depth of b is:
4⋅π⋅a⋅RM
ρ :=
1 + ⎡⎢ ⎤−
(2⋅a) a
2 ⎥
⎣ ( a ) + ⎡⎣4⋅(b )⎤⎦ ⎦ ( a ) + (b )
2 2 2
2.4.5 Risers
Risers shall meet requirements as specified in the Technical Data Sheets.
network. The resistance of a grounding electrode is not constant but varies with the amount of
moisture in the ground. As weather conditions change throughout the year, grounding electrode
resistance will change. It is therefore required that the Bidder/Contractor shall carry out
verification checks on the resistance to ground of all grounding electrodes.
Overhead Ground Wire/Optical Ground Wire (OPGW)
For the technical details of the Overhead Ground Wires and OPGW reference shall be made to
Standard Technical Specification, Part:
¾ S-TR-OHL-OPGW - Optical Ground Wires
2.6.1 General
For copper bar to copper bar connections the following connection methods are applicable:
a) Brazing, using zinc-free brazing material with a melting point of at least 6000 C
b) Bolting (min. two 8 mm bolts each with two washers , one spring washers and a nut)
c) Exothermic welding (according to ANSI/UL 467)
d) Cold pressure welding
2.8.1.1 General
For Overhead Tower Earthing/Grounding Details, reference shall be made to Standard Technical
Specification, Part
¾ S-TR-OHL-T - HV/MV Towers of Lattice Steel Design
and Drawings:
Drawing No. Title
DWG TR EARTH 01 15 Details of Metallic Tower Earthing
All wires and strips shall be handled and installed in the best possible manner, free of kinks and
damage of any kind. Backfill for strip trenches shall be sieved material and thoroughly
compacted in layers.
After installation of the basic Earthing/Grounding System, the Bidder/Contractor shall measure
the earth resistance at each tower structure and submit the results to TRANSCO, for approval.
All supporting structures having a resistance to earth, exceeding 20 Ohms for towers and/or 10
Ohms for poles, shall be furnished with deep bore earthing/grounding at tower locations, as will
be defined by TRANSCO, also deep bore earthing/grounding and/or earth grading rings shall be
installed as far as needed. After application of additional grounding, the Bidder/Contractor shall
repeat the resistance measurement in all concerned locations. The stringing of the earth wire may
commence only after final approval of the resistance values by TRANSCO.
The transformer and shunt reactor tank shall be connected to the Earthing/Grounding System
following the same principles as for steel structures.
Directly grounded power transformer/reactor neutrals shall be connected by two copper
conductors (isolated from the transformer tank) to two separate grounding rods. The grounding
rods shall be connected to the Earthing/Grounding System.
The copper conductors shall be properly clamped to a supporting steel structure.
2.8.3.1 General
Fundamentally the screen of a power cable can be treated in the following way:
• Sheath bonded at one side only
• Sheath bonded at both sides
• Application of cross-bonding systems
The practical implications of the choice of a specific earthing system are manifold and must be
taken into account when a power cable system is designed. The following aspects are influenced
when the earthing concept of a power cable system:
• Current rating of a power cable circuit
• Overvoltage in the power cable screen
• Magnitude of the zero and positive sequence impedance
• Appearance of stray current in the earth
• Earthing impedance of (remote) substations.
• The earthing impedance of (remote) substations can be improved by the screen of the
cable.
• The zero-sequence impedance has normally lower value than with one side bonding and
can be calculated more accurately.
2.8.3.4 Cross-Bonding
In a cross-bonding system the whole cable circuit should be divided in three sections with the
same length. After every section the screen of the power cable is cross-bonded to a different
phase. This is preferable done in positions, where joints (with screen interruption) are placed.
Like this the connected screen will see the same amount of induced voltage from every phase,
hence the induced voltage is becoming zero. If the power cables are laid in plain, the cables itself
need to be transposed at every joint bay, as the screen impedance is different for the inner cable
and the outer cables. In order the sum of the induced voltage is really becoming zero, the
connected screen must run always on the same position of the power cable circuit.
A cross-bonding system can be considered as combining the advantages of single- and one side
bonding, which are the follows:
• In a cross-bonding system the power cable screen can be earthed on both sides without
having circulating currents and additional losses (as long as every section has the same
length).
• Earthing impedances and zero sequence impedances are improved due to both side
bonding.
However the disadvantage of the induced voltage appearing on every cross-bonding point –
similar to one side bonding – is still remaining. Hence the length of one section is limited.
2.8.3.5 Recommendations
Earthing concept in or near a substation, where an earthing grid is in the ground
• Single side bonding in order to reduce the losses in the power cable screen.
Earthing concept outside of a substation
• For short cable length, where less than three sections of power cables are needed, single-
side bonding together with an additional earth conductor to improve the zero-sequence
and the earthing impedance.
• For long power cable lengths, consisting at least of three cable sections, implementing a
cross-bonding system as it increases the ampacity and improves the zero-sequence
impedance.
• For power cable circuits, where the number of cable sections is unequal to three or
unequal to multiple of three, both above described methods can be adopted.
If for any reason both side bonding (without cross-bonding) is applicable, the spacing between
the power cables shall be minimised and trefoil formation shall be chosen in order to reduce the
losses in the screen and to maximise the ampacity of the power cable.
2.8.4 GIS
GIS Earthing/Grounding shall meet requirements as specified in IEEE Std 80-2000.
For high-frequency earthing, CIGRE (Group 23.10, Publ. Earthing of GIS – An application
Guide) shall be considered.
The GIS manufacturer shall evaluate:
a) Induced enclosure currents
b) Metal to metal touch voltage during internal and external GIS faults
c) Justify that specified touch voltage criteria are met and submission of special precautions for
TRANSCO’s approval.
Steel structures constructed as one unit (all parts are welded) can be utilised for
earthing/grounding of electrical parts installed on it, if the steel structures are earthed according
to DIN VDE 0141, i.e. as follows:
• For gantries, Earthing/Grounding System shall be connected at two points
• Sufficient conductive cross-sections of the gantry supporting structure
• Electrical conductive connections at the gantry structure shall be bolted or welded.
2.8.15 Others
Communication Circuits, Control Cable Sheaths, Rails, LV Neutral Wires, Portable Equipment
and Tools supplied from Substation, Piping, Auxiliary Buildings shall be connected to the
Earthing/Grounding System as specified in IEEE Std 80-2000.
TRANSCO reserves the right to perform checks during manufacturing process at any time or all
the times. It shall be at the discretion of TRANSCO to witness tests on 100%, or any percentage
quantity of each lot for routine tests, apart from the type tests, wherever called for.
Tests of Earthing/Grounding Systems shall comprise factory and site tests.
CIVIL WORKS
( SPECIFICATION )
CONTENTS
1 GENERAL ....................................................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 General .............................................................................................................................. 3
2.2 Concrete ............................................................................................................................ 3
2.3 Form-Work ........................................................................................................................ 5
2.3.1 General .............................................................................................................................. 5
2.3.2 Form-Work Classes ........................................................................................................... 5
2.3.3 Form-Work Removal ........................................................................................................ 6
2.4 Reinforcement ................................................................................................................... 6
2.4.1 Material ............................................................................................................................. 7
2.4.2 Fabrication ......................................................................................................................... 7
2.4.3 Site Installation and Handling ........................................................................................... 8
2.5 Cement .............................................................................................................................. 9
2.6 Aggregates ......................................................................................................................... 9
2.7 Admixtures ...................................................................................................................... 10
2.8 Tests and Properties......................................................................................................... 10
2.8.1 Testing ............................................................................................................................. 10
2.8.2 Concrete Quality Requirements ...................................................................................... 12
2.8.3 Particular Requirements .................................................................................................. 13
2.8.4 Construction and Expansion Joints ................................................................................. 13
2.8.5 Construction Joints .......................................................................................................... 13
2.8.6 Expansion Joints .............................................................................................................. 14
2.8.7 Joint Filler Board ............................................................................................................. 14
2.9 Special Requirements for Safety against Cracking ......................................................... 14
3 GENERAL FOR PRE-CAST CONCRETE CONSTRUCTION .............................. 14
1 GENERAL
This part of the Specification shall cover all items related to concrete and reinforced concrete
works for the Project. Works shall include all items required for the tendered Project, as well as
all auxiliary works as/and where required.
All works shall further be carried out in full compliance with all local rules and regulations and
the Specification shall further be read if applicable for the Project.
For applicable technical standards, tests, reference shall be made to:
S-TR-CIVIL-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
S-GEN-CDF - Civil Design Fundamentals
2 TECHNICAL DESCRIPTION
2.1 General
This article shall apply to all concrete and reinforced concrete works within this Project. All
works shall be designed and executed in accordance with the structural analysis and the approved
design. All work shall be performed according to the working drawings designed by the
Bidder/Contractor and approved by TRANSCO.
Concrete and reinforced concrete shall be placed either in-situ or by prefabricated units.
This Article also covers the reinforcement steel, as well as the form-work required for the
particular structural member.
2.2 Concrete
Before executing any load bearing structural members, the Bidder/Contractor shall furnish
TRANSCO with a concrete mix design and a detailed concreting programme, which shall be
subject for approval.
Only ready-mix concrete shall to be used and one trial mix has at least to be carried out
successfully for every mix. The batching plant has to be approved by TRANSCO. If a known
mix, which was successfully used before, is proposed, trial mixing can be waived The
composition of one batch concrete, its aggregates, the cement and water content and the
additives, if any, in kg or litre per m3 of compacted concrete shall be displayed legibly at the
batching plant.
Concrete shall be placed and compacted in its final position within 90 minutes of the water being
added to the mix. If the Bidder/Contractor proposes the use of pumps for the transporting and
placing of concrete, he shall submit a detailed method statement. Bidder/Contractor shall ensure
that pumping shocks shall not be transferred from the pipeline to the form-work, previously laid
concrete or the structure. The initial discharge of any pumped concrete shall be discarded
completely.
Concrete shall be placed and compacted/vibrated in horizontal layers of not more than 300 mm
thickness each. For large areas to be cast proven technique (e.g. staggered layers) may be
proposed for approval at Site. The rate of delivery of concrete during concreting operations shall
be such that the interval between batches shall be minimised to avoid cold joints, if cold joints
cannot be avoided, a stop-end vertical surface joint shall be provided.
For slabs thicker than 900 mm, thermocouples shall be provided to control and record the
temperature of the concrete during curing. Allowable differential temperature should not exceed
200C.
For concreting in hot weather, ACI Standard 305R "Hot Weather Concreting" and the "CIRIA
and Concrete Society’s “Guide to the construction of reinforced concrete in the Arabian
Peninsular”. and its recommendations shall be followed and various means may be employed to
lower the temperature of concrete such as:
Cooling coarse aggregate with water by sprinkling and shading
Using chilled water
Using crushed ice
Avoiding the use of the hot cement
Shading mixer drums, facilities and material by use of permanent wet burlap coverings
Adequately watering of sub-grade, form-work and reinforcement
Insulating water supply lines and tanks and/or painting exposed portions white
Working only at cooler daytime
Covering freshly poured concrete with polythene sheets
Intensive moist-curing with potable water of the concrete placed
Curing the concrete continuously with water at least for 7 days and as detailed in CIRIA
and Concrete Society’s –“Guide to the construction of reinforced concrete in the Arabian
Peninsular”. Attention to curing requirements is important at all times; it is especially in
hot, dry weather because of greater danger of cracking. The use of ice to lower the
temperature of fresh concrete must be carefully controlled. If flaked ice is used in the mix,
it must be of such a size that it will melt completely in the mix and that no ice remains
once the batching is complete. The temperature of fresh concrete must in no case exceed
+ 30°C. When discharged in the form-work, particular care shall be given for thick section
(>900mm) where insulation boards shall be used to reduce temperature gradient.
2.3 Form-Work
2.3.1 General
The stability of the form-work, false work and scaffolding shall be proven by static analysis.
Form-work and its supporting structures shall be constructed in accordance with the static
analysis and shall safely resist all occurring forces, including the effect of the concreting rate and
the method of compaction. For columns and walls, the strength of form-work shall be adjusted to
the rate of placing the concrete. Scaffolding along with Form-Work (shuttering) system shall be
supplied by specialized supplier. The work shall be executed by the certified scaffolders holding
valid specialized third party certification. The entire scaffolding system shall be inspected at site
prior to its usage (concreting, external scaffolding, etc.) by approved specialized third party
scaffolding supplier to ensure the compliance with latest safety & technical code of practice. All
timber for form-work shall have selected quality, brand new and shall have a flexural stress
"Sigma b" minimum 10 N/mm2. Formwork drawings/calculations shall be submitted for
information.
All form-work and moulds shall be of such tight construction that slurry cannot flow out at the
joints during pouring and compaction. If required, joints shall be sealed with foam rubber strips.
2.4 Reinforcement
For Reinforcement, reference shall be made to the below listed drawings, which are provided in
the Drawings Section.
Drawing No. Title
2.4.1 Material
Reinforcement is to be hot-rolled deformed high yield steel in accordance with DIN 488 DIN EN
ISO 15360 or BS 4449 – Grade 460, or higher. Before use, any matter liable to impair the bond
shall be removed from the steel, e.g., dirt, grease, organic matter, and rust. Particular care shall
be taken to ensure that the reinforcing bars are given the shape (including diameter of curvature),
length and position conforming to the reinforcement drawings.
Any reinforcement shall be so far cold deformable that it will stand the cold bending test, where
the space between the two limbs of the piece bent through 180° must be equal to twice the
diameter of the rod under test. No cracks shall occur on the tensioned side.
Reinforcing steels of group IIIa shall be weldable by the flash welding process to produce
welded joints, which pass the cold bending test.
Steel fabrics of group IVb shall be of steel whose elastic limit and tensile strength are guaranteed
by special cold working, however, steel fabrics shall not be welded or heat-treated in any other
way.
Fabric reinforcement shall be bent accurately to the required shapes before the fabric is laid in
position – all bending and cutting shall be done cold and no heating or welding is allowed. All
the fabric shall be lapped and tied together on both the longitudinal and transverse wires and all
lapping shall be sufficient for the steel to develop its full strength.
Pre-stressing reinforcement shall comply with BS 5896-1980 or DIN 10138 and DIN EN
ISO 15630.
2.4.2 Fabrication
All reinforcements shall be bent cold unless otherwise permitted by TRANSCO. Bar cutting and
bending equipment for coated reinforcement shall have padded supports and contact areas and
shall be fitted with nylon or plastic mandrels supplied by, or approved by, the coating factory
representative.
The top reinforcement shall be secured against being pushed down by using steel chairs/supports
positioned between top and bottom layers of reinforcement. Steel supports shall be made of new
steel of similar type and quality of the main reinforcement.
Reinforcement bars shall normally not be connected to the earthing system. Separate earthing
mesh shall be provided instead. Earthing to be routed through piles must be isolated from the pile
reinforcement. The reinforcement for piles shall be without fusion bonded epoxy coating.
To receive good bonding and to avoid corrosion, plastic spacers shall be fixed between form-
work and reinforcement minimum four per m2. The Bar Bending Schedule shall be submitted
along with detailed shop drawings for information.
2.5 Cement
The type of cement to be used shall depend on the constructional circumstances and on the
prevailing local conditions. Portland cement, Type I, may be used at places not exposed to
chemical aggressiveness, whereas Portland cement, Type V, shall in general be used for all
concrete work in foundations and plinths and in concrete structures covered by soil.
Moderate sulphate resistant cement as per ASTM C 150, type 2, may be used only after
TRANSCO's explicit written approval to replace the type V cement.
Cement shall be of recent manufacture and shall be used within a period of 3 months from
production.
Total cementitious contents in the mix shall be limited to avoid excessive risk of thermal and
shrinkage cracking. It shall always be in the range of 350 – 400 kg/m3 unless otherwise approved
by TRANSCO. The proportioning of mixes for durability will be primarily controlled through
the specified limits on free W/C ratio. The W/C ratio shall always lie in the range of 0.36-0.45.
Appropriate use shall be made of approved admixtures to simultaneously meet the requirements
for W/C ratio and workability.
Before supplying cement to Site or receiving ready-mixed concrete, the Bidder/Contractor shall
submit to TRANSCO, the manufacturer’s statement of Specification and test certificate together
with date of manufacture of any cement to be used. TRANSCO reserves the right to take samples
and order any additional / re-tests in accordance with BS EN 196-7 : 1992, BS EN 196-6, BS
4450 and ASTMC 186.
In mix designs with an emphasis on durability, ground granulated blast furnace slag as per BS
6699 or EN 197 or microsilica may be incorporated in the mix. Proportions of slag shall
normally not exceed 60 %, those of microsilica shall not exceed 8%, for items thicker than 1.2m,
these proportions shall not exceed 10%.
2.6 Aggregates
Aggregates shall be crushed rock type and conform to the relevant applicable standard BS
882:1992. The combined aggregate shall be as coarse-grained and dense-graded as possible and
shall be according to the guidelines of BS 882. The maximum particle size shall be so chosen as
to be compatible with mixing, handling, placing and workability of the concrete.
For underwater concrete, proof shall be given that the mix is adequately cohesive and maintains
this property during placing by using under-water admixtures.
Aggregates shall - for all groups except the dune sand - be a product of crushed rock, with the
source and type being subject to TRANSCO´s approval. Only for exceptional cases and upon
TRANSCO´s specific written approval, aggregates of other origin may be used for certain parts
of the work.
Size of aggregate used in concrete: maximum aggregate size shall be 20mm, except for thick
elements (>900mm) where particular heat of hydration control is required. There, aggregate of
28mm max size may be used. For the required concrete of Grade 40 (C28 = 40 N/mm2), at least
one particle size fraction shall be in the 0-4 mm range.
2.7 Admixtures
No admixtures shall be used without approval of TRANSCO and unless the suitability of
admixtures must be proven in trial mixes in presence of TRANSCO.
Admixture containing chlorides shall not be used under any circumstance.
Manufacturer’s recommendations and instructions concerning overdosing of additives shall be
strictly observed.
2.8.1 Testing
Throughout the construction period the quality of concrete mixed at and/or delivered to Site has
to be controlled. Tests shall be carried out in the presence of TRANSCO or under the supervision
of an approved office for testing of such kind of works. The following minimum numbers of
tests shall be carried out:
a) Aggregates
Sampling of Aggregate: Sampling and testing of Aggregate shall be carried out in accordance
with BS 812 and BS 882. However, the Client reserves the right to call for additional tests
whenever felt necessary.
b) Cement
b1) For site mixed concrete if applicable and or approved by TRANSCO
One setting test to vicat per car-load
One boiling test per car-load.
b2) For ready mixed concrete
Mill certificates of the cement used in the plant
Chemical composition in line with DIN 1164 or BS 12.
c) Water
One chemical water analysis every 3 months of construction. First analysis before start of
foundation works.
d) Admixtures and Additives
Three (3) samples of each kind of admixture and additive before start of casting of the first load
bearing structural member.
e) Concrete delivered to Site
One set of at least six (6) test cubes for every 100 m3 or every daily pour of concrete or as
directed by TRANSCO.
The compression strength tests shall be carried out after seven (7) days for the first two
cubes of each set, and after 28 days for the second two cubes of the set, and - if requested –
the last two cubes of each set may be tested in case of failure of a cube.
Slump tests are to be executed for every truck load supplied during concreting and as per
TRANSCO's instructions, provided concreting is proceeding.
Concrete temperature is to be recorded at the arrival of concrete at Site.
Bimonthly or for every 750 m3 of concrete cast, the Bidder/Contractor shall prepare the
following for durability testing, which - after approval of TRANSCO – may be carried out
through the concrete supplier:
- Rapid test for chlorides
- Rapid test for sulphates
- A Trial panel, from which at 28 days 3 Nos. Cores, 75mm diameter and 75 mm long,
shall be taken for water absorption testing (to BS 1881)
- 3 Nos. blocks, 200 x 200 x 120 mm thick, for water penetration testing (to DIN
1048)
- 4 Nos. cubes, 150 mm, for rapid chloride permeability testing (to AASHTO T-277)
curing of samples shall be as close to the current Site practice as possible.
f) Reinforcement
The Bidder/Contractor shall provide copies of the manufacturer’s test certificates with each
consignment of reinforcement brought to Site. In addition and before the execution of works, and
for every 100 T in each shipment, two (2) samples of each bar size shall be tested as follows:
Chemical composition to be tested to BS 4449
Mechanical properties test including tensile properties, elongation, bend test and re-bent
test
Cross sectional area and mass test
For detailed curves, diagrams and tables, reference is made to DIN 1045 or the relevant
BS, both latest editions.
In case of failure of tests, retesting for steel shall be carried out as BS4449.
Notes:
* Water retaining structures and Basements in areas with high water table
** Marine structures and structures in areas with highly aggressive soil conditions, classified
as class 4 & 5 as per the BRE Digest 363.
Pre-cast concrete units shall be cast in individual forms and may be cured in the pre-cast yard by
steam curing for at least four (4) days or continuous water curing for at least 7 days, followed by
application of an approved curing membrane or other approved methods.
For pre-cast concrete elements and units where the use of immersion type vibrators is not
applicable, the Bidder/Contractor shall consolidate such units on vibrating tables or by any other
method approved by TRANSCO.
Pre-cast concrete units shall not be branded or marked in any position, which can be seen, in the
finished work or against which any concrete is to be placed.
Pre-cast concrete units may be supplied by a Manufacturer or may be manufactured by the
Bidder/Contractor at a location as approved by TRANSCO.
During transportation and storage, pre-cast panels shall be supported as in their final positions.
Other methods of support will not be permitted. The pre-cast members shall be adequately
braced and supported during erection to ensure proper alignment and safety. Such bracing or
support shall be maintained until adequate permanent connections have been made.
The dimensions of the finished pre-cast units shall be within the following limits at the time of
placement in the structure:
Overall dimensions of member 3.0 mm
Cross-sectional dimensions:
Sections less than 75 mm 1.5 mm
Sections over 75 mm and less than 300 mm 3.0 mm
Sections over 300 mm 5.0 mm
Deviation from straight line in long sections less than 5 mm per 6 m
Deviation from camber 1.5 mm per 3 m of span
No pre-cast units shall be considered for diaphragm action horizontal pre-cast elements. Normal
weight concrete topping is to be used for such behaviour.
Bond/Anchorage test must be performed in the Factory on at least 2 samples of each thickness of
Hollow Core Slabs.
Full scale load tests shall be carried out on each panel of typical design in accordance with ACI
318M-08/318RM-08. The purpose of such load tests is to determine the behaviour of the slabs
under working conditions. Acceptance criteria shall be as follows:
Applied test load T shall be equal to 0.85 (1.4 D + 1.7 L). (D = dead load, L = live load under
consideration of reductions permitted in the general design). Loads shall be applied in at least
four (4) increments and the final load shall be kept for at least 24 hours.
The test load shall be removed immediately after reading of the initial deflection and the final
reading shall be taken 24 hours after removal of the test load.
If visual evidence of failure, e.g. cracking, spaling, excessive deflection, etc., appears, the tested
member shall be considered to have failed the test. If no visual indications of failure occur,
following shall be the limiting criteria to define acceptable behaviour:
Maximum deflection of beams, floor or roof shall be less than l2 / 20,000 h. (l = clear span
and h = thickness)
If the above is exceeded, the deflection recovery within 24 hours after removal of the test
load shall be at least 75% of the maximum deflection for non-pre-stressed concrete or 80%
for pre-stressed concrete
For cantilevers, l shall taken as twice the distance from cantilever support to end.
Deflection shall be adjusted for support movements.
Retesting:
If nonprestressed concrete fails to show the required 75% recovery of deflection, may be re-
tested not earlier than 72 hours after first test load removal. The re-tested portion of the structure
may be considered satisfactory if it shows no visible sign of failure, and the deflection recovery
caused by the second test load is at least 80% of the maximum deflection in the second test.
Pre-stressed concrete construction shall not be re-tested.
CIVIL WORKS
( SPECIFICATION )
SECURITY FENCING
CONTENTS
1 GENERAL ....................................................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 General Guideline.............................................................................................................. 3
2.2 Steel Fencing Posts............................................................................................................ 3
2.3 Wire-Mesh......................................................................................................................... 4
2.4 Barbed Wire ...................................................................................................................... 4
2.5 Gates.................................................................................................................................. 4
SECURITY FENCING
1 GENERAL
This part of the Specification shall cover all items related to security and other fence installation
works for the Project. Works shall include all items required for the tendered Project, as well as
all auxiliary works.
All works shall further be carried out in full compliance with all local rules and regulations and
the Specification shall further be read, if applicable for the Project.
For applicable technical standards, tests, reference shall be made to:
¾ S-TR-CIVIL-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
2 TECHNICAL DESCRIPTION
For Chain Link Fence Details, reference shall be made to the below listed drawings, which are
provided in the Civil Drawings Section.
Drawing No. Title
DWG TR CIV 13 01 Chain Link Fence Details
Before hot-dip galvanising of the posts, strong T-shaped flanges to receive fixing brackets shall
be welded.
Corner posts shall be equipped with corner turnbuckles for bracing wires and joint clamps for
horizontal bracing rails and reverse bracing. All components shall be plastic-coated to increase
the corrosion protection properties.
Application : Fences for gantry areas and outdoor capacitor banks.
Height of internal fence shall be 2.60m.
2.3 Wire-Mesh
Chain link wire-mesh shall be of minimum 4 mm diameter wires, opening size of not more than
50 x 50 mm. Mesh shall be hot-dip galvanised and provided with plastic coating, color to the
discretion of TRANSCO.
The wire mesh shall be new and unused, and in single length between the posts. The plastic
coating shall be thick and elastic, durable and should be able to withstand a temperature up to
+ 90°C.
Alternative fence systems utilising welded mesh may be proposed for approval.
2.5 Gates
For Main Gate Details, reference shall be made to the below listed drawings, which are provided
in the Civil Drawings Section.
Drawing No. Title
DWG TR CIV 13 02 01 Main Gate Details Sheet 1/4
DWG TR CIV 13 02 02 Main Gate Details Sheet 2/4
DWG TR CIV 13 02 03 Main Gate Details Sheet 3/4
DWG TR CIV 13 02 04 Main Gate Details Sheet 4/4
Entrance Gates (hinged) shall be provided as outlined under Section “Metal Works”.
Gates for areas fenced with chain link fence shall be made of frames from trapezoidal or triangle
hollow steel sections according to the fence design may be proposed. These gates shall be fitted
with adjustable hinges and bronze bushes with greasing points. The in-fill of such gates may be
of chain link wire mesh or welded mesh as used for the fence.
Gates shall be lockable and the drop-bolts of inactive leafs shall be locked in the closed position
by the active gate to prevent opening.
The corrosion protection shall be provided by hot dip galvanising and subsequent plastic coating
of the gates.
CIVIL WORKS
GENERAL REQUIREMENTS
(Applicable Technical Standards, Tests etc.)
CONTENTS
GENERAL REQUIREMENTS
(Applicable Technical Standards, Tests, etc.)
1 CIVIL WORKS
1.1 General
This part of the specification shall cover
¾ Design
¾ Construction
¾ Testing and
¾ Commissioning
¾ S-TR-CIVIL-MAS - Masonry
¾ S-TR-CIVIL-CONCRETE - Concrete and Reinforced Concrete
¾ S-TR-CIVIL-STEEL - Structural Steel Work
¾ S-TR-CIVIL-METAL - Metal Work
¾ S-TR-CIVIL-DRAIN - Drainage Work
¾ S-TR-CIVIL-SAN - Plumbing and Sanitary Installation
¾ S-TR-CIVIL-SURF - Surface Protection
¾ S-TR-CIVIL-ROAD - Roads and Pavements
¾ S-TR-CIVIL-FENCE - Security Fencing
¾ S-TR-CIVIL-FINISH - Finishing Schedule
¾ S-TR-CIVIL-LIGHT - Lighting and other Electrical Installations in Substations
¾ S-TR-CIVIL-CAB - Civil Works for Underground Cables
¾ S-TR-CIVIL-OHL - Civil Works for Overhead Transmission/ Distribution
Lines
• EARTHING / GROUNDING SYSTEMS
¾ S-TR-EARTH- - General Requirements (Applicable Technical Standards,
LIGHTNING-GEN Tests etc.)
¾ S-TR-EARTH-GROUND - Earthing / Grounding Systems
¾ S-TR-LIGHTNING - Lightning Protection System
• FIRE FIGHTING SYSTEMS
¾ S-TR-FIF - Fire Protection System
• ELECTROMECHANICAL SERVICES
¾ S-TR-ELMS-GEN - General Requirements (Applicable Technical Standards,
Tests etc.)
¾ S-TR-ELMS-LIFT - Lifts (Elevators)
¾ S-TR-ELMS-CRANE - Gantry Crane
¾ S-TR-ELMS- - Air Conditioning and Ventilation Systems
HVAC+VENT
Above specifications shall cover all civil works required to form a completely safe and reliably
designed system as tendered and in accordance with the technical description of the project.
For supply items standard designs and models from a manufacturing program of one supplier are
preferred, provided they meet the requirements of this Specification, and serve the intended
purpose.
If substantial improvements of any of the specified technical requirements, which are seen by the
Bidder/Contractor to provide technical or economical advantages to TRANSCO, are desired to
be presented in the Bid, the improvement may be proposed as an alternative in addition to the
specified design. However, it is not mandatory that the alternative design is to be accepted, but
shall be subject to the decision of TRANSCO upon evaluation of the same. The difference in
price shall be clearly stated in amount/percentage/unit.
It is not the intent to specify completely herein all the details of design and manufacturing of the
substation lighting system. It may be noted that norms specified are the bare minimum that is
required. The substation lighting system shall conform in all respects to high standards of
engineering design and workmanship and should be capable of performing continuous
commercial operation within the parameters guaranteed by the Bidder/Contractor in a manner
acceptable to TRANSCO, who will interpret the meanings of drawings and specifications and
shall have power to reject any material, which in his judgement is not in accordance with the
specifications and the guaranteed parameters.
All material and equipment to be used and/or supplied under these Specifications shall be new
and of the latest proven “state-of-the art” technology. Prototype equipment shall not be accepted.
3 APPLICABLE TESTS
Details of Tests are specified in Standard Technical Specification, Part:
APPROVAL OF DATA AND DRAWINGS
The following information and data must be submitted to TRANSCO for approval prior to
manufacturing of the equipment:
• Vendor(s) details / reference list
• Completely filled in data sheets
• Testing schedule
• Documentation formats and quantities.
documents must be submitted to TRANSCO:
• Bill of equipment showing complete re-ordering information for all replaceable parts
• Installation, operation and maintenance instructions including hardware / software.
CIVIL WORKS
( SPECIFICATION )
CONTENTS
1 GENERAL ....................................................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 Soil Investigation............................................................................................................... 3
2.1.1 Execution of Borings and In-Situ Tests (SPT) .................................................................. 4
2.1.2 Bore Logs .......................................................................................................................... 6
2.1.3 Laboratory Tests ................................................................................................................ 6
2.1.4 Reports .............................................................................................................................. 7
2.1.5 Change of Investigation Program ...................................................................................... 8
2.2 Foundations ....................................................................................................................... 8
2.2.1 General .............................................................................................................................. 8
2.2.2 Foundation Types .............................................................................................................. 9
2.2.3 Soil Characteristics .......................................................................................................... 10
2.2.4 Protection of Tower Foundations .................................................................................... 10
2.2.5 Caps ................................................................................................................................. 12
2.3 Gantries ........................................................................................................................... 13
2.4 Access.............................................................................................................................. 13
2.5 Design of Foundations..................................................................................................... 16
2.5.1 Pile Foundation................................................................................................................ 16
2.5.2 Pad and Chimney Foundation ......................................................................................... 17
2.5.3 Rock Anchor Foundation: ............................................................................................... 18
2.6 Erection of Foundations .................................................................................................. 19
2.6.1 General ............................................................................................................................ 19
2.6.2 Earth and Rockwork ........................................................................................................ 20
2.6.3 Concrete Work ................................................................................................................ 21
2.6.4 Bored Pile Foundations ................................................................................................... 28
2.6.5 Foundation Load Tests .................................................................................................... 29
2.6.6 Additional Civil Work ..................................................................................................... 32
2.6.7 Sign Boards for Road Crossings...................................................................................... 32
2.7 Factors of Safety.............................................................................................................. 33
1 GENERAL
This part of the Specification shall cover all items related to civil works within overhead and
overhead transmission line projects.
Works shall include, but not be limited to the following: geo-technical investigations, soil
resistivity measurements, selecting, design, setting out, installation and testing of all required
types of tower foundations for the different types tower types and location conditions. Provision
of tower platforms and/or stabilising of tower locations, access roads and provision of revetment
protection as/and where required.
For applicable technical standards, tests, reference shall be made to:
S-TR-CIVIL-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
2 TECHNICAL DESCRIPTION
If the initial groundwater level is recorded higher than 4 m below surface, weekly readings
of the groundwater table up to the casting of foundations to monitor fluctuations of
groundwater.
For pole lines of 33 kV and below, initially only dead-end towers, angle towers and tension
towers and at every third suspension tower location shall be investigated, provided that the
resulting spacing between boreholes does not exceed 200 m. At locations where boreholes are
not being carried out, results of adjacent boreholes may be interpolated. If severe variations of
the ground conditions between boreholes are recorded, additional interim locations shall be
investigated.
2.1.1.1 Borings
The methods of boring shall enable undisturbed sampling as well as rotary coring. The minimum
borehole diameter for undisturbed sampling shall be 100mm. The equipment shall allow the
execution of Standard Penetration Tests and undisturbed sampling, for instance by using piston
sampler.
For the drilling works in cohesive and/or hard soils, a double tube core barrel of at least 3"
(7.5 cm) inside diameter shall be used exclusively, provided that this kind of boring can be
continued to the final bottom of the borehole in question. A 95 % core recovery is required.
Beyond this, the Bidder/Contractor may choose for his own convenience the type of equipment
and accessories to be used at each individual borehole and depth, provided that in TRANSCO's
opinion, the equipment chosen is suitable for the drilling. The Bidder/Contractor may also
choose the initial and intermediate diameters of each borehole for his own convenience, provided
that he will secure the aforementioned minimum acceptable size of core.
Adequate casing has to be used to ensure the stability of the borehole. The Bidder/Contractor
will not be entitled to any compensation or additional payment for casing.
The method of drilling, casing and flushing shall be described in the offer. Bentonite shall be
added to the drilling fluid only after the explicit permission of TRANSCO.
It is to be emphasised that the Bidder/Contractor shall supply an equipment to take undisturbed
samples from cohesive and non-cohesive soils for laboratory tests, according to international
standards. The samples shall be treated in an adequate manner to avoid disturbances and drying
out.
All boreholes shall after completion of the investigation be refilled with sand and not left open.
2.1.1.2 Sampling
All soils sampled by SPT, undisturbed sampling or core barrel have to be properly stored. Non-
cohesive soils have to be kept in water-tight boxes or bags. Borehole number and depth of
sample shall be written on the cover of the bags and boxes, and the cores must be placed in the
order as taken. The corresponding depth of the material shall continuously be written on the
partition walls of the boxes. Undisturbed samples shall be of 100mm dia and 450mm length.
Samples shall be collected in such a manner that the structure of the soil and its moisture content
are not changed.
The borders between different strata, and the sections of core boxes shall be fixed with thin
boards, and marked with the depth. Core boxes shall be designed for approximately 7 metre of
continuous soil samples. Before shifting the soil samples to the laboratory, the boxes shall be
stored accessible at any time for TRANSCO.
Ground-water and disturbed soil samples taken for the chemical analysis shall be kept in
watertight, durable plastic jars.
Color print photographs shall be taken of all cores packed in the core boxes, suitably labelled.
Negatives and six sets of postcard size prints shall be provided.
In case cemented layers occur into which the cone cannot penetrate, the Bidder/Contractor shall
pre-bore through the hard soil before the cone test is continued. However, this procedure shall
only be performed after explicit instruction of TRANSCO at site.
The Bidder/Contractor shall deliver copies of the original sounding records as well as the
elaborated cone test diagrams to TRANSCO.
In areas where access roads are not available and which are not accessible for the Dutch Cone
Machine another type of cone penetration tests may be performed after TRANSCO’s approval.
The equipment shall be light, transportable with four-wheel drive vehicle or by hand. The cone
shall be driven by a hammer, in accordance with one of the International Standards.
2.1.4 Reports
Field reports have to be handed over to TRANSCO at site including bore-logs with all pertinent
data, SPT results, ground water levels, cone penetration diagrams, test pit logs, as well as
readings of groundwater levels within three days after completion of the corresponding work.
Weekly Progress Reports on approved forms shall be submitted to TRANSCO at site.
On completion of all field and laboratory work, the Bidder/Contractor shall submit to
TRANSCO a Geotechnical Investigation Report, containing the procedure used during the
investigation, field test results, laboratory observations and test results both in tabular and
graphical form. Practical and theoretical considerations for the interpretation of the test results,
supporting calculations for the conclusions drawn etc., shall be included. The report shall contain
theoretical as well as practical considerations for the design and construction of the different
types foundations and any proposals which the Bidder/Contractor may consider necessary to be
made with regard to the parameters and dimensions of the standard foundations, as well as clear
recommendations for the need for special designs.
The Bidder’s/Contractor’s qualified geotechnical engineer shall visit TRANSCO’s office for a
detailed discussion on the draft report. During the discussions TRANSCO and the
Bidder/Contractor shall decide on the amendments that need to be made in the draft report.
Thereafter, the Bidder/Contractor shall incorporate in the report the agreed modifications, and
after TRANSCO approves the report, the Bidder/Contractor shall submit six (6) copies of the
final report along with a reproducible set of all tables, graphs etc. At least two original copies
with colored photographs shall be submitted to TRANSCO.
The Bidder/Contractor shall prepare a schedule for construction purposes, which clearly
indicates the type of foundation to be installed at each site and records the soil investigation data
on which the choice has been made. The Schedule will be subject to the approval of TRANSCO
prior to commencement of foundation construction.
2.2 Foundations
2.2.1 General
a) Tower foundations shall normally be single leg foundations of reinforced concrete each
tower foundation selected has to be proposed and justified by the Bidder/Contractor and
shall be approved by TRANSCO.
b) The Bidder/Contractor shall stake out the tower locations and submit to TRANSCO the
foundation conditions including permissible bearing pressure assumed at each tower,
together with the type of foundation considered applicable. TRANSCO may require the
Bidder/Contractor to make additional soil investigations at tower sites to verify the
foundation conditions at no additional cost.
c) For his final foundation design the Bidder/Contractor has to perform the required soil
investigations and has to base his design calculations on the detailed information obtained.
The Bidder/Contractor is requested to quote firm unit rates for the different types of
foundations and towers as set out in the Bills of Quantities. These unit rates will be
considered as flat rates covering all foundation costs for any type of soil encountered along
the line and no adjustment of the rates will be permitted.
d) The number of towers set out in the Bills of Quantities against each type may change, as
well as the numbers of specific types of foundations. Their numbers will be adjusted and
remunerated according to the quoted unit rates. This will, however, not entitle the
Bidder/Contractor to a change of the quoted unit rates or to any other additional claim.
Table-1
SIEVE % PASSING
25.4 mm 100
19.05 mm 70 – 100
9.53 mm 50 – 80
No. 4 35 – 65
No. 10 25 – 50
No. 40 15 –30
No. 200 5 –15
Note: the maximum allowable L.L. and P.I are 35
and 10 respectively
CBR = above 20%
2.2.4.4 Slope Protection Works on Mountain Slope at Tower Location in Hilly Terrain
Area
a. Preliminary survey:
It is the responsibility of the Bidder to visit the site and acquire the required information
for the proposed work and obtain necessary approval from the concerned authorities.
Bidder to Conduct geological survey for surrounding of the Tower location & submit
report to O/E for approval stating stability of Rock layers. Also Bidder needs to conduct
Hydrological Survey in order to design proper drainage works around the Tower
Location.
This Provision addresses supply and application of rock anchors and bolts, steel wire
mesh and net, rockfall barriers around Tower legs and supply 50–200mm maximum
thickness ready-mix shotcrete using the highest quality materials, equipment and
workmanship.
Scope includes, Supply and installation of steel wire mesh fence over and side of the
mountain slope to hold the rocks. The loose rock pocket area needs to be strengthen by
Rock Anchors & bolts. This rock anchors and bolts consisting of grouted steel bars,
anchor plates, nuts and if applicable, bearing plates and washers. Use neat cement grout
for anchors and bolts. Galvanize bars, plates, nuts and washers shall be in accordance
with recommendation by Anchor Manufacturer. Provide support ropes to suspend wire
mesh or nets from rock anchors. At the bidders option and when noted in the plans,
suspend wire mesh or nets from grouted cable anchors instead of rock anchors and
connect cable anchors to support ropes with shackles.
The bidder has to submit the detailed layout with length and width of the area for the
approval prior to commencement of work. Drilling and fixing of anchor bolts not less
than 8mm dia on rocks to the depth of 85 to 100mm into the rocks. Supply wet mix
concrete as per approved concrete mix design. Bidder has to submit and obtain approval
for concrete mix design. Concrete mix design shall be as per TRANSO specification.
Scope also includes preparation of surface by applying necessary water (pre wetting
substrate) on the rock surface to ensure that all the pores and pits are adequately wet and
prevent suction and necessary formwork to withstand the load, while applying spray
concrete. Concrete mixing procedure and application of concrete over mountain rock
surface shall be approved by the Engineer/Transco. Concrete surface Finishing and
curing shall be as per Transco specification. Store materials on blocking at least 12"
above the ground and protect it at all times from damage; and when placing in the work
make sure it is free from dirt, dust, loose mill scale, loose rust, paint, oil or other foreign
materials. Load, transport, unload and store rock slope materials are kept clean and free
of damage. Bent, damaged or defective materials will be rejected.
Bidder/ Contractor to provide proper drainage around the Tower Leg platform in order to
avoid landing or failure due to scouring of rain runoff water. Rockfall barriers needs to be
provided around Predominant tower leg only in order to protect steel OHL Tower from
direct impact of sliding/ rolling off rocks/ boulders.
The successful bidder has to submit a detailed method statement prior to commencement of work
and get approval from the Engineer/ Transco.
2.2.5 Caps
In locations not liable to flooding of bearing surface water, all steelworks, whether part of the
tower or part of the stub-angle foundation shall be completely encased in concrete to ensure a
concrete cover of 100 mm for any part of the stub leg/tower steel in the ground. This shall apply
from a point 450 mm above ground down to the toe of the stub angle. Cleats fitted to the stub-
angles shall be considered.
All concrete foundations shall be at least 75 cm above the final ground of the tower location.
Free-standing length of pile foundations shall be limited to 2.0 m above Finished/ Natural
Ground Level. Foundations shall be of dense concrete, adequately sloped off around the steel leg
/ stub angle section and smoothly finished to ensure drainage of water away from the steel work.
No capping shall be commenced in any portion of the work until the designed portion has been
approved by TRANSCO.
Final (future) finished ground level/elevation at the tower location shall be obtained from the
concerned local authorities during route approval, i.e. to consider future filling and development
works. In areas adjacent to roads (within 200 meters centreline to centreline), the tower location
level shall not be lower than the road level.
All tower foundation concrete above ground is to be protected equivalent to the concrete below
ground.
2.3 Gantries
The gantry will be located at a distance of about 50 to 120 m from the terminal tower. As
protection against entrance of unauthorised persons, a fence of galvanised and plastic coated
steel mesh of an approved type and with a minimum height of the mesh of 3.0 m with galvanised
plastic coated steel posts and gates, shall be provided around the gantry. Unless a gantry is
located within a Sub or Power Station area, inclined holders with 4 strands of galvanised or
stainless steel barbed wire shall additionally be installed at the top of the perimeter fence. Proper
earthing of the fence shall be provided if required.
Foundation design, grounding and painting of the gantry, and for the design of its foundation the
same stipulations are valid as for towers and foundations.
An earthing grid up to outside of the fence has to be provided with stranded tinned copper
conductor of at least 95 mm² and conforming to the requirements of VDE 0141.
All areas of the gantry shall receive topping with gravel and shall be excavated to a depth of not
less than 150 mm referring to finished ground level. The bottom of the excavated area shall be
plain, topped and levelled with coarse gravel of 25-51 mm in size and of a thickness of not less
than 150 mm. Alternative solutions may be proposed by the Bidder/Contractor for TRANSCO’s
approval.
Fencing, earthing and gravelling of the gantry areas according to Gantry layout is deemed to be
included in the items “gantry” and “foundation for gantry” of the Price Tabulation Sheet.
2.4 Access
The Bidder/Contractor shall be responsible for the provision of access to the transmission line
routes and the tower locations as required for complete constructions works.
Access for later maintenance of the transmission line (if required) shall be instructed by
TRANSCO and paid according to the respective BOQ item in stages as mentioned In Table-2.
Such access may be used by the Bidder/Contractor for construction purposes by laying only
initial layers, later; shall be completed as per the specifications requirements and maintained up
to FAC. All access provisions shall be submitted for TRANSCO’s approval prior to construction.
Access provisions over and above access instructed by TRANSCO for future maintenance of the
transmission line shall be at the Bidder’s/Contractor's responsibility and at their own cost.
Maintenance roads along the line route instructed by TRANSCO shall be routed at a minimum
distance between the edge of the road and the longest crossarm plus 5m. The crossing of the line
centreline by such maintenance road shall if possible be avoided.
Maintenance roads shall have a clear width as specified in Table-2 at the top and with side slopes
at a gradient not steeper than 1:1. They shall be constructed from and approved gatch material
and compacted by roller to a minimum final thickness So, the final surface level above the
existing ground level shall be as in Table-2.
No separate payment shall be made to the Bidder/Contractor on account of slight changes on the
line routings such as they may be required in shifting the transmission line route due to the
requirements of local Authorities and TRANSCO. Further reference is made to the Special
Conditions. Notice has to be given that the line routes contained in this Tender Document are of
tentative and preliminary purpose.
Table-2
Road Thickness
Road Width
Type of Terrain (meters)
(meters)
Below Ground Above Ground Total
Plain terrain (with hard - - - -
surface and no moving sand)
Subkha area (swampy / water 4 0.3 0.7 1.0
logged areas / area which
may get water on surface
during rain or during high
tide
Sand dune area with less 4 0.2 0.3 0.5
moving sand
Sand dune area with high 7 0.2 0.3 0.5
and frequent moving sand
Hilly terrain road (benched 4 - - -
levelled, filled & compacted)
Dam Road (for back water / as per Scope of as per Scope of as per Scope of as per Scope of
water logged area) with slope work & Tender work & Tender work & Tender work & Tender
protection specific drawing specific drawing specific drawing specific
drawing
Material to be used for the construction of maintenance road shall fulfil the requirements listed in
article 2.2.4.3(material for fill and backfill).
For sand dune area, in order to avoid moving sand covering the road, access road route shall be
carefully selected and also where required during construction sand shall be cleared both side at
least 4 meters either side of the maintenance access road.
For foundations in hilly areas where rock/hard soil cutting, grading etc. is required (especially
when unequal leg extensions are necessary).
The foundation shall be designed for the respective forces of the tower type and extension
and the actual angle acting on the tower.
For Typical Section of Gatch Road details, reference shall be made to the below listed drawings,
which are provided in the Drawing Section:
Drawing No. Title
DWG TR CIV 11 04 Typical Section of Gatch Road
c) It shall be assumed that soil doesn’t offer any skin resistance up to a depth of 2m from the
Natural Ground Level.
d) For design purposes, it shall be assumed that Ground water Table is 2m above the
measured level. Accordingly, the unit weights of soil and concrete shall be adjusted in the
calculations.
e) Angle of Friction shall be assumed as follows:
SPT Values Friction Angle
Less than or equal to 10 0
More than 10 but less than 25 30
More than or equal to 25 but less than 35 32
More than or equal to 35 34
c) For design purposes, it shall be assumed that Ground water Table is 2m above the
measured level. Accordingly, the unit weights of soil and concrete shall be adjusted in the
calculations.
d) The depth of pad and chimney foundation shall be based on inverted cone-Frustum Angle
Method as described in the specification.
e) While deciding the depth of foundation, the ratio of ultimate uplift capacity against
ultimate uplift forces shall not be less than 1.2.
f) The nominal cover to reinforcement shall be 75mm.
The following foundation types shall be considered (but not limited to):
Pad and chimney with or without undercut (concrete block foundation);
Rock anchor foundations;
Pile foundations (single or group of piles per leg);
a) Hard rock of homogenous solid rock is encountered within one meter of ground surface;
b) Soft rock - homogeneous fractured limestone or weathered, stratified rock occurring for
complete depth of foundation (100% soft rock) or for 50% of the foundation depth (50%
soft rock);
c) Normal soil - soil reasonably compact or stiff;
d) Poor soil - silty sand, silty clay of weak strength with or without layers of gravel,
unconsolidated sands,;
e) Special soil conditions - like in wadis (watercourse beds) subject to occasional flooding,
subkha, sand dunes areas etc.
2.6.1 General
Tower foundation installation shall include tower site preparation, excavation, any measures
required to ensure slope stability or free drainage dewatering, foundation placement
measurements, assembly and placement of the approved foundation, foundation protection, as
well as backfill and clean-up.
The Bidder/Contractor shall employ templates for stub setting for each tower and gantries. In
general, all four stubs shall be set simultaneously using templates. However, in case of
undulating terrain or due any other specific problem, each stub may be set separately using
templates.
The Bidder/Contractor shall remove all vegetation and other debris from the tower site, which
will interfere with his operation. Vegetation and debris removed from the tower site shall be
disposed off outside the right of way as directed by TRANSCO and/or in accordance with local
regulations.
The ground levels existing before the installation of foundations have to be considered in
determining tower platform heights.
The Bidder/Contractor shall dispose of material and regulate the movement of equipment so that
grades shall not be exposed, and slopes necessary to develop required loading characteristics
shall be maintained, especially in side-hill locations.
The depth of pile foundations shall always be related to the lowest ground (not platform/fill
elevation in the area occupied by the foundation.
2.6.2.1 General
There will be no classification of excavated materials, and the term “Excavation” shall include
all materials to be excavated or to be removed within the Project, regardless of the type,
character, composition, or conditions of the material excavated and shall further include all
debris, junk, broken concrete, bricks, logs, stumps, roots, and all other material encountered
within the specified excavation limits.
The Bidder/Contractor is responsible for all necessary safety measures. He is liable for any
damage and accidents occurring while earth work is being carried out. Proper standing, including
any necessary re-arrangement protection of slopes or cribbing, preparation of design
calculations, etc. shall be deemed included in the prices.
In the event of soil slides occurring during earth and rock work, all damage will be to the
Bidder’s/Contractor’s debit. This also implies that no payment will be made for the additional
moving of soil resulting from such damage.
2.6.2.3 Backfilling
Refilling around the pile head pits shall be carried out only after all works within the excavations
have been inspected and approved by TRANSCO.
Unless otherwise directed all filling shall be approved selected material, and shall be deposited
and compacted using approved material in layers not exceeding 150 mm thick for hand
compaction and 250 mm for mechanical compaction, loose depth.
During the placing of backfill the hole shall be kept free from water. All temporary timbering
and all decomposable material shall be removed from the excavations prior to backfilling.
2.6.2.4 Settlement
The Bidder/Contractor shall be responsible for making good all settlements of filling due to any
cause whatever which may occur up to the end of the period of maintenance.
2.6.3.2 Aggregates
Aggregates shall be crushed rock type and conform to the relevant applicable standard BS
882:1992. The combined aggregate shall be as coarse-grained and dense-graded as possible and
shall be according to the guidelines of BS 882. The maximum particle size shall be so chosen as
to be compatible with mixing, handling, placing and workability of the concrete.
For underwater concrete, proof shall be given that the mix is adequately cohesive and maintains
this property during placing by using under-water admixtures.
Aggregates shall - for all groups except the dune sand - be a product of crushed rock, with the
source and type being subject to TRANSCO´s approval. Only for exceptional cases and upon
TRANSCO´s specific written approval, aggregates of other origin may be used for certain parts
of the work.
Size of aggregate used in concrete: maximum aggregate size shall be 20mm, except for thick
elements (>900mm) where particular heat of hydration control is required. There, aggregate of
28mm max size may be used. For the required concrete of Grade 40 (C28 = 40 N/mm2), at least
one particle size fraction shall be in the 0-4 mm range.
Aggregates shall be of limestone source and shall be subject to TRANSCO´s approval.
2.6.3.3 Cement
a) Type of Cement
The type of cement to be used shall depend on the constructional circumstances and on the
prevailing local conditions. Portland cement, Type I, may be used at places not exposed to
chemical aggressiveness, whereas Portland cement, Type V, shall in general be used for all
concrete work in foundations and plinths and in concrete structures covered by soil.
Moderate sulphate resistant cement as per ASTM C 150, type 2, may be used only after
TRANSCO's explicit written approval to replace the type V cement.
Cement shall be of recent manufacture and shall be used within a period of 3 months from
production.
Total cementitious contents in the mix shall be limited to avoid excessive risk of thermal and
shrinkage cracking. It shall always be in the range of 350 – 400 kg/m3, unless otherwise
approved by TRANSCO. The proportioning of mixes for durability will be primarily controlled
through the specified limits on free W/C ratio. The W/C ratio shall always lie in the range of
0.36-0.45. Appropriate use shall be made of approved admixtures to simultaneously meet the
requirements for W/C ratio and workability.
Before supplying cement to Site or receiving ready-mixed concrete, the Bidder/Contractor shall
submit to TRANSCO, the manufacturer’s statement of Specification and test certificate together
with date of manufacture of any cement to be used. TRANSCO reserves the right to take samples
and order any additional / re-tests in accordance with BS EN 196-7 : 1992, BS EN 196-6, BS
4450 and ASTMC 186.
In mix designs with an emphasis on durability, ground granulated blast furnace slag as per BS
6699 or EN 197 or microsilica may be incorporated in the mix. Proportions of slag shall
normally not exceed 60 %, those of microsilica shall not exceed 8%, for items thicker than 1.2m,
these proportions shall not exceed 10%.
The cement shall be selected according to the recommendations of BRE-Digest 363 of 1991 and
as summarised here:
SO4 IN SOIL OR FILL SO4 IN CEMENT TYPE
GROUNDWATER
Soil Class by 2:1 water/soil extract – g/l
g/l
1 and 2 ≤ 2.3 ≤ 1.4 OPC
3 2.3 ≤ 3.7 1.4 ≤ 3.0 SRC / MSRC
4 and 5 ≥ 3.7 ≥ 3.0 SRC
to enable all the necessary tests to be carried out before it is used, but should not be stored for
more than 6 weeks.
TRANSCO may reject any cement as a result of any tests thereof, notwithstanding the
manufacturer’s certificate. He may also reject cement, which has deteriorated owing to
inadequate protection or other causes or in any other case where the cement is not to his
satisfaction. The Bidder/Contractor must remove all rejected cement from the site without delay
and expenses for TRANSCO.
2.6.3.5 Reinforcement
a) Epoxy Coated Reinforcement
Reinforcement is to be hot-rolled deformed high yield steel in accordance with DIN 488,
DIN EN ISO 15630 or BS 4449 – Grade 460 or higher. Only epoxy coated reinforcement shall
be used for foundations of transmission line towers.
The reinforcement steel shall be protected against corrosion with a fusion-bonded epoxy coating.
The coating shall be applied in accordance with ASTM A775/775M-01, and shall be supplied
from an approved coating factory using approved epoxy resins.
All handling and bending procedures shall be to the coating factory’s recommendations and
instructions, and as agreed with TRANSCO. A coating factory representative shall ensure his
product is used fully in accordance with his recommendations.
The Bidder/Contractor shall furnish to TRANSCO a certificate of compliance for each shipment
of coated bars.
b) Repair of Damaged Epoxy Coating
When the epoxy coating is damaged, (cut ends, accidental damage etc.) the coating shall be
repaired with parching material conforming to ASTM A775/A775M-01 and shall be carried out
in accordance with the manufacturer’s recommendations.
The repair to the damaged area shall be carried out as soon as possible, and before oxidation of
the surface occurs. In no case shall the repair be delayed more than 8 hours. Any trace or rust or
oxidation must be removed by grinder or wire brush prior to touch-up.
c) Fabrication
All reinforcements shall be bent cold unless otherwise permitted by TRANSCO. Bar cutting
equipment shall have padded supports and contact areas. Bar bending equipment shall have
padded supports and contact areas and shall be fitted with nylon or plastic mandrels supplied by,
or approved by, the coating factory representative.
d) Site Installation and Handling
Reinforcement of all types shall be stored on Site in protected racks above ground in an
approved manner so as to avoid damage to the coating. Direct metal to coating contact should be
avoided wherever possible.
The number, size, form and disposition of bars shall be strictly in accordance with the drawings
and bending schedules or as directed by TRANSCO. Reinforcement shall be checked after being
fixed and no concrete shall be placed around the reinforcement until such checking has taken
place.
Equipment for handling epoxy coated bars shall have padded contact areas. Bundles shall be
lifted with a strong-back or have multiple supports to prevent bar-to-bar abrasion from sags in
the bundle. Bars or bundles shall not be dragged or dropped. Any coating damage due to
handling, shipment and placing shall be repaired as described above.
All tie-wires or other devices used to connect, support, secure or fasten epoxy coated
reinforcement shall be made of, or coated with, a dielectric material such as nylon, epoxy or
plastic. All bundles shall be identified at the factory with durable tags to allow checking of
coating quality control at site. Reinforcement shall not be straightened or re-bent in a manner,
which may cause injury to the material. Bars with shapes not shown on the drawings shall not be
used.
All reinforcing bars shall be bent in accordance with the relevant standard. In particular, no
reinforcement shall be heated. All reinforcement shall be rigidly fixed in position to the concrete
cover specified by an approved means.
Prior to concreting the Bidder/Contractor shall ensure that the reinforcement is cleaned of all
concrete from previous pours and any damage to the coating is repaired.
2.6.3.6 Concreting
Concreting for pile foundation shall be done through tremie-pipes or equivalent devices to
prevent segregation. Alternatively pumping methods may be proposed by the Bidder/Contractor.
For concreting in hot weather, ACI Standard 305R "Hot Weather Concreting" and the "CIRIA –
“Guide to the construction of reinforced concrete in the Arabian Peninsular”. and its
recommendations shall be followed and various means may be employed to lower the
temperature of concrete such as:
Cooling coarse aggregate with water by sprinkling and shading
Using chilled water
Using crushed ice
Avoiding the use of the hot cement
Shading mixer drums, facilities and material by use of permanent wet burlap coverings
Adequately watering of sub-grade, form-work and reinforcement
Insulating water supply lines and tanks and/or painting exposed portions white
Working only at cooler daytime
2.6.3.7 Testing
Throughout the construction period the quality of concrete mixed at and/or delivered to Site has
to be controlled. Tests shall be carried out in the presence of TRANSCO or under the supervision
of an approved office for testing of such kind of works. The following minimum numbers of
tests shall be carried out:
a) Water
One chemical water analysis every 3 months of construction. First analysis before start of
foundation works.
b) Cement
b1) For site mixed concrete if applicable and or approved by TRANSCO
One setting test to vicat per car-load
One boiling test per car-load.
b2) For ready mixed concrete
Mill certificates of the cement used in the plant
Chemical composition in line with DIN 1164 or BS 12.
c) Admixtures and Additives
Three (3) samples of each kind of admixture and additive before start of casting of the first load
bearing structural member.
d) Concrete delivered to Site
One set of at least six (6) test cubes for every 100 m3 or every daily pour of concrete or as
directed by TRANSCO. The compression strength tests shall be carried out after seven (7)
days for the first two cubes of each set, and after 28 days for the second two cubes of the
set, and - if requested – the last two cubes of each set may be tested in case of failure of a
cube.
Slump tests are to be executed for every truck load supplied during concreting and as per
TRANSCO's instructions, provided concreting is proceeding.
Concrete temperature is to be recorded at the arrival of concrete at Site.
Bimonthly or for every 750 m3 of concrete cast, the Bidder/Contractor shall prepare the
following for durability testing, which - after approval of TRANSCO – may be carried out
through the concrete supplier:
- Rapid test for chlorides
- Rapid test for sulphates
- A Trial panel, from which at 28 days 3 Nos. Cores, 75mm diameter and 75 mm long,
shall be taken for water absorption testing (to BS 1881).
- 3 Nos. blocks, 200 x 200 x 120 mm thick, for water penetration testing (to DIN
1048).
- 4 Nos. cubes, 150 mm, for rapid chloride permeability testing (to AASHTO T-277)
curing of samples shall be as close to the current Site practice as possible.
e) Reinforcement
The Bidder/Contractor shall provide copies of the manufacturer’s test certificates with each
consignment of reinforcement brought to Site. In addition and before the execution of works, and
for every 100 T in each shipment, two (2) samples of each bar size shall be tested as follows:
Chemical composition to be tested to BS 4449
Mechanical properties test including tensile properties, elongation, bend test and re-bent
test
Cross sectional area and mass test
For detailed curves, diagrams and tables, reference is made to DIN 1045 or the relevant
BS, both latest editions.
In case of failure of tests of reinforcement, retesting shall be carried out as BS4449.
For epoxy coated reinforcement, following additional tests shall be carried out in line with the
guidelines of A775/775M-01:
Coating thickness
Holidays on the coating
Adhesion of the coating.
Notes:
* Water retaining structures and Basements in areas with high water table
** Marine structures and structures in areas with highly aggressive soil conditions, classified
as class 4 & 5 as per the BRE Digest 363
Aggregates contamination limits shall be as follows:
Chlorides Sulphates Reference
Coarse Aggregates < 0.03% < 0.4% CIRIA
Fine Aggregates < 0.06% < 0.4% CIRIA
RC with SRC < 0.20% < 4.0% CIRIA
RC with OPC < 0.30% < 4.0% CIRIA
Not Reinforced Concrete < 0.60% < 4.0% CIRIA
shall submit for approval a Method Statement detailing the method to be used to ensure the
satisfactory placing, compaction, curing and protection of concrete.
The compaction is not to be confined to the upper surface of the layer deposited, but the whole
mass of concrete must be thoroughly punnedand/or vibrated. Concrete has to be brought up in
layers to become consolidated, with the mass assuming a jelly-like consistency and the water just
appearing on the surface. Reinforcement or form-work must not be moved by placing and
compacting the concrete.
Adequate curing and protection of the fresh concrete to TRANSCO’s satisfaction is mandatory.
Unless otherwise approved, there shall be no joints in concrete foundations. Where the
construction of the foundation is such that joints are unavoidable, adequate bonding between the
old and new concrete shall be ensured by exposing the larger aggregate particles near the surface
by scaling hammer and leaving a clean surface free from loose particles. Immediately before
placing the new concrete, this cleaned surface shall be primed with a bonding agent to
TRANSCO’s approval.
Not less than 10 cm of blinding concrete shall be placed as a base for all concrete to be placed
below ground. The surface of the blinding and the vertical surfaces of all structures in contact
with the ground or filling shall have a dense, continuous and water-proof membrane of approved
thickness and material applied.
In the case of piles penetrating into caps or beams, etc., i.e. not for single pile foundations, water-
tight connections of pile shell and the protective membrane have to be guaranteed.
Parts of the line(s) pass through areas with extraordinarily aggressive soils. Special precautions
to protect the concrete shall be proposed by the Bidder/Contractor, and will be subject to the
approval of TRANSCO.
Subjected to TRANSCO approval; Bentonite SLURRY could be used instead of Temporary steel
casing to prevent erosion during the drilling due to difficulties to remove the temporary casing
after concreting.
0 15 min OFFLOADING
100 1 hr S≤0.25 mm
125 1 hr S≤0.25 mm
150 1 hr S≤0.25 mm
175 1 hr S≤0.25 mm
200 1 hr S≤0.25 mm
225 1 hr S≤0.25 mm
250 24 hrs S≤0.25 mm
200 15 min S≤0.25 mm
150 15 min OFFLOADING
100 15 min OFFLOADING
50 15 min OFFLOADING
0 1 hr OFFLOADING
On every increment, settlements shall be recorded after 30”, 2’, 4’, 8’, 15’, 30’, 1h. Movement of
the pile head shall be less than 0.25 mm within that hour , or until 2 hours have elapsed,
whichever occurs first, before the application of the new load increment.
For working piles, the load cycles will be terminated at a maximum of 150 %.
For arrangement of Pile Load Tests details, reference shall be made to the below listed drawings,
which are provided in the Drawings Section:
Drawing No. Title
DWG TR CIV 03 04 Arrangement of Pile Load Test
Complete records of level, load cell and dial gauge readings against date and time
throughout the test in a tabulation
Graphs of load and settlement/heave versus time
Graphs of settlement/heave versus load
Remarks concerning any unusual occurrences during the loading of the pile.
TRANSCO will decide on completion of tests and evaluations whether the test piles shall be left
in place or shall be extracted. No extra payment will be made for the extraction of test piles.
The design for the signboard has to be submitted for the approval of TRANSCO and other
authorities concerned.
CIVIL WORKS
( SPECIFICATION )
SITE INSTALLATION
CONTENTS
1 GENERAL ....................................................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 General .............................................................................................................................. 3
2.2 Installation ......................................................................................................................... 3
2.2.1 Removal ............................................................................................................................ 4
2.3 Material ............................................................................................................................. 4
2.4 Auxiliary Work.................................................................................................................. 4
2.5 Facilities at Site ................................................................................................................. 4
2.6 Regular Cleaning of the Construction Site ........................................................................ 6
2.7 Relocation / Protection of the Existing Services ............................................................... 6
2.8 Fencing and Signboard ...................................................................................................... 7
SITE INSTALLATION
1 GENERAL
This part of the Specification shall cover all items related to site installation works for the
Project. Works shall include all items required for the tendered Project, as well as all auxiliary
works.
All works shall further be carried out in full compliance with all local rules and regulations and
the Specification shall further be read, if applicable for the Project.
For applicable technical standards, tests, reference shall be made to:
S-TR-CIVIL-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
2 TECHNICAL DESCRIPTION
2.1 General
All relevant site installation required for performance of the entire project shall be provided by
the Bidder/Contractor, who shall prior to commencement of works issue a "Notice of Intent" in
line with the local regulations.
2.2 Installation
The site installation shall include supply, furnishing, transport, erection, maintenance and
supplementing, if required, and removal of all plant, machinery, vehicles, scaffolding, all
construction equipment, auxiliary equipment, materials, personnel and work instruments, all
temporary and permanent installations, (permanent in the sense that according to the contract,
they are to remain for the use of TRANSCO after completion of the work), workshops, office
buildings, laboratories, stores, housing canteen, first aid and all other facilities if so required for
or in connection with the construction of the work and for the fulfilment of the
Bidder’s/Contractor's obligations.
Also included in Site installation shall be such general and/or temporary work as access roads,
vehicle parking areas, storage areas, buildings, and structures, electrical supply, medical
facilities, construction of workers' and supervisors' housing and community facilities,
laboratories, and similar work unless included under other cost items, when such work is called
for by the Contract documents or are required for the safe and efficient execution of the work.
Access roads, car park area, storage area, power supply, water supply, first aid station, site
laboratory, housing accommodation for Bidder’s/Contractor's employees shall be part of the
scope of supply and as specified hereafter. Prior to commencement of any installation work a
drawing showing the proposed site installation shall be submitted to TRANSCO for approval.
2.2.1 Removal
As soon as the Work is completed and before the Bidder’s/Contractor's final liquidation, the
Bidder/Contractor shall remove from TRANSCO's property all temporary buildings, installations
and temporary facilities erected above ground. The Bidder/Contractor shall fill with earth all
basements and underground areas, leaving the terrain completely clean, free from temporary
under-ground installations and with a good appearance.
The Bidder/Contractor shall also treat the excavations executed for his own convenience, such as
temporary roads, in a way acceptable to TRANSCO.
If the Bidder/Contractor refuses to remove the temporary construction installations or if the
operation is not completed within 2 months from completion of the work, the materials and
installations may be removed by TRANSCO, and the costs shall be deducted from the
Bidder’s/Contractor's final payment.
2.3 Material
All equipment, machinery, materials and tools required for execution of the works shall be
workable and kept in good working conditions throughout the construction period, and shall be
listed in a schedule, which shall be subject to TRANSCO’s approval.
with all electrical wiring and light fittings, plumbing and sanitary systems to the approval of
TRANSCO.
The tentative layout of these offices can be seen from the below listed drawing, which is
provided in the Drawings Section.
Drawing No. Title
DWG TR CIV 01 02 Site Office Arrangement
The office blocks shall be located in the project area and as directed or approved by TRANSCO.
Each office block shall consist of a "two room office", each office room with a floor area of not
less than 20 m2. The floor area of the conference room shall be at least 20 m2. A toilet and
kitchen shall be attached to each office block as well.
Toilet and washroom facilities shall include western style WC's and washbasins with hot and
cold water, extraction fans and shall discharge into a septic tank unless connected to a public
sewer system.
The following equipment and furniture shall be supplied for each office block:
2 Station telephone/Mobile
2 PC’s with associated printers and Email.
4 Writing desks
4 Swivel arm chairs
6 Guest chairs
2 Drawing hanger stands
2 Bookshelves
2 Pin boards
2 Storage lockers
2 Split-type Air-Conditioners
1 Fire extinguisher
1 white writing board
Stationary as required.
Window curtains for all windows.
The following equipments shall be general for both office blocks:
1 Photo copier
1 Fax machine
1 Drawing tables
1 Hot plate
1 Refrigerator
1 Water cooler
1 Microwave
1 Firs aid kit
1 Stationary as required.
The conference room block shall be sized to accommodate at least 12 persons and equipped with a
1 Conference room table ( 1.5 * 3.5 M )
12 Chairs
1 White board
2 Pin boards
1 Side Board.
1 AC “split unit “of minimum 2 tons capacity.
Whenever required during the execution of the work, particular survey and testing equipment for
supervision of the work and testing of materials shall be made available by the Bidder/Contractor
for the sole use by TRANSCO's supervisory staff. Survey and testing equipment shall be kept in
good working order throughout the contract period and shall be replaced if reported damaged or
being inaccurate.
The types of instruments and equipment as will be required for the survey of the work and
testing of the materials will be intimated to the Bidder/Contractor prior to the start of the work,
e.g. at the first site co-ordination meeting.
For all site services specified, the investment cost for the full contract period shall be quoted in
the Bill of Quantities. Against issuance of the Final Acceptance Certificate, all provisions will be
returned to the Bidder/Contractor, unless specified to the contrary.
Any damage occurring to services located within the plot shall be the Bidder’s/Contractor’s full
responsibility. Compliance with the “Notice of Intent” requirement shall not relieve the
Bidder/Contractor from his responsibility.
For existing HV cables suitable culverts shall then be prepared in order to cover and protect all
these cables during the construction works.
Other services shall be treated according to the requirements of their respective Owner’s.
For the protection of underground services reference shall be made to the below listed drawing,
which is provided in the Drawings Section:
Drawing No. Title
DWG TR CIV 02 Protection of Underground Services
CIVIL WORKS
( SPECIFICATION )
SOIL INVESTIGATION
CONTENTS
1 GENERAL ....................................................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 Soil Investigation............................................................................................................... 3
2.1.1 Execution of Borings and In-Situ Tests (SPT) .................................................................. 4
2.1.2 Bore Logs .......................................................................................................................... 6
2.1.3 Laboratory Tests ................................................................................................................ 6
2.2 Geophysical Survey ....................................................................................................... ...8
2.3 Reports .............................................................................................................................. 9
SOIL INVESTIGATION
1 GENERAL
This part of the Specification shall cover all items related to soil investigation works for the
Project. Works shall include all items required for the tendered Project, as well as all auxiliary
works.
All works shall further be carried out in full compliance with all local rules and regulations and
the Specification shall further be read, if applicable for the Project. Subsurface exploration shall
be performed under the constant supervision of at least one qualified soil and foundation
Engineer or Engineering Geologist, who is fully cognizant of the Geological and Engineering
considerations involved.
For applicable technical standards, tests, reference shall be made to:
S-TR-CIVIL-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
2 TECHNICAL DESCRIPTION
2.1.1.1 Borings
The methods of boring shall enable undisturbed sampling as well as rotary coring. The minimum
borehole diameter for undisturbed sampling shall be 100mm. The equipment shall allow the
execution of Standard Penetration Tests and undisturbed sampling, for instance by using piston
sampler.
For the drilling works in cohesive and/or hard soils, a double tube core barrel of at least 3"
(7.5 cm) inside diameter shall be used exclusively, provided that this kind of boring can be
continued to the final bottom of the borehole in question. A 95% core recovery is required.
Beyond this, the Bidder/Contractor may choose for his own convenience the type of equipment
and accessories to be used at each individual borehole and depth, provided that in TRANSCO's
opinion, the equipment chosen is suitable for the drilling. The Bidder/Contractor may also
choose the initial and intermediate diameters of each borehole for his own convenience, provided
that he will secure the aforementioned minimum acceptable size of core.
Adequate casing has to be used to ensure the stability of the borehole. The Bidder/Contractor
will not be entitled to any compensation or additional payment for casing.
The method of drilling, casing and flushing shall be described in the offer. Bentonite shall be
added to the drilling fluid only after the explicit permission of TRANSCO.
It is to be emphasised that the Bidder/Contractor shall supply an equipment to take undisturbed
samples from cohesive and non-cohesive soils for laboratory tests, according to international
standards. The samples shall be treated in an adequate manner to avoid disturbances and drying
out.
All boreholes shall after completion of the investigation be refilled with sand and not left open.
2.1.1.2 Sampling
All soils sampled by SPT, undisturbed sampling or core barrel have to be properly stored. Non-
cohesive soils have to be kept in water-tight boxes or bags. Borehole number and depth of
sample shall be written on the cover of the bags and boxes, and the cores must be placed in the
order as taken. The corresponding depth of the material shall continuously be written on the
partition walls of the boxes. Undisturbed samples shall be of 100mm dia and 450mm length.
Samples shall be collected in such a manner that the structure of the soil and its moisture content
are not changed.
The borders between different strata and the sections of core boxes shall be fixed with thin
boards, and marked with the depth. Core boxes shall be designed for approximately 7 metre of
continuous soil samples. Before shifting the soil samples to the laboratory, the boxes shall be
stored accessible at any time for TRANSCO.
Ground-water and disturbed soil samples taken for the chemical analysis shall be kept in
watertight, durable plastic jars.
Color print photographs shall be taken of all cores packed in the core boxes, suitably labelled.
Negatives and six sets of postcard size prints shall be provided.
The equipment shall be light, transportable with four-wheel drive vehicle or by hand. The cone
shall be driven by a hammer, in accordance with one of the International Standards.
1. Procedure of the survey and method adopted with the relevant backup documents like
plan of the plot and brochure of the method used for the survey.
2. General Description of the geological strata underlying the site plot.
3. Detrminination of presence of cavities and the extent of these cavities both horizontally
and vertically and/or determination of the likelihood of these cavities forming in the
future if not already formed.
4. Detrminination of presence of fractured rocks or anomalies of the kind, the extent of
these anomalies both horizontally and vertically and the consequences of the presence of
these anomalies on the structural integrity of the geological strata.
5. Recommendations regarding remedies for the cavities and/or anomalies in the plot site to
restore the geotechnical structural integrity of the plot.
6. Recommendation of the allowable bearing capacities in the plot based on the findings of
the survey and after implementing the remedies.
7. The expected short and long term settlement under the recommended allowable bearing
capacities.
8. The report should recommend the feasible and safe type of foundation system to support
the substation facilities with acceptable limits of settlements as per the recognized
geotechnical standards.
2.3 Reports
Field reports have to be handed over to TRANSCO at site including bore-logs with all pertinent
data, SPT results, ground water levels, cone penetration diagrams, test pit logs, as well as
readings of groundwater levels within three days after completion of the corresponding work.
Weekly Progress Reports on approved forms shall be submitted to TRANSCO at site.
On completion of all field and laboratory work, the Bidder/Contractor shall submit to
TRANSCO a Geotechnical Investigation Report, containing the procedure used during the
investigation, field test results, laboratory observations and test results both in tabular and
graphical form. Practical and theoretical considerations for the interpretation of the test results,
supporting calculations for the conclusions drawn etc., shall be included. The report shall contain
theoretical as well as practical considerations for the design and construction of the different
type’s foundations and any proposals which the Bidder/Contractor may consider necessary to be
made with regard to the parameters and dimensions of the standard foundations, as well as clear
recommendations for the need for special designs. The report should also contain field Bore Log
sheets too.
The Bidder’s/Contractor’s qualified geotechnical engineer shall visit TRANSCO’s office for a
detailed discussion on the draft report. During the discussions TRANSCO and the
Bidder/Contractor shall decide on the amendments that need to be made in the draft report.
Thereafter, the Bidder/Contractor shall incorporate in the report the agreed modifications, and
after TRANSCO approves the report, the Bidder/Contractor shall submit six (6) copies of the
final report (hard and soft copies, signed and stamped) along with a reproducible set of all tables,
graphs etc. At least two original copies with colored photographs shall be submitted to
TRANSCO.
CIVIL WORKS
( SPECIFICATION )
SURFACE PROTECTION
CONTENTS
1 GENERAL ....................................................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 Concrete Flooring of Switchgear Rooms .......................................................................... 3
2.1.1 Surface Preparation ........................................................................................................... 3
2.1.2 Application of Primer........................................................................................................ 3
2.2 Floor Epoxy Coating of Normally Loaded Areas ............................................................. 4
2.2.1 Application of Primer........................................................................................................ 4
2.2.2 Application of Final Coats ................................................................................................ 4
2.3 Repair of Existing Concrete Floors ................................................................................... 4
2.4 Floor Hardeners................................................................................................................. 5
2.5 Dust Sealer ........................................................................................................................ 5
2.6 Concrete Walls, Plastered Walls and Ceilings .................................................................. 5
2.6.1 Preparation of New Surfaces ............................................................................................. 5
2.6.2 Preparation of Surfaces Previously Painted ...................................................................... 5
2.6.3 Coating Application and Systems ..................................................................................... 6
2.7 Painting of Woodwork ...................................................................................................... 7
2.7.1 Surface Preparation ........................................................................................................... 7
2.7.2 Painting of Wooden Surfaces ............................................................................................ 7
2.8 General for Painting and Coating ...................................................................................... 7
2.9 Ceramic Finishes ............................................................................................................... 7
2.9.1 Ceramic Floor Tiles........................................................................................................... 7
2.9.2 Ceramic Wall Tiles............................................................................................................ 8
2.9.3 Chemical Resistant Tiling ................................................................................................. 8
SURFACE PROTECTION
1 GENERAL
This part of the Specification shall cover all items related to surface protection in civil works for
floors, walls, etc. within the Project. Works shall include all items required for the tendered
Project, as well as all auxiliary works.
All works shall further be carried out in full compliance with all local rules and regulations and
the Specification shall further be read, if applicable for the Project.
For applicable technical standards, tests, reference shall be made to:
¾ S-TR-CIVIL-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
2 TECHNICAL DESCRIPTION
Maximum air and / or surface temperature for application should not exceed + 40oC, and the
relative humidity should in no case exceed 85%. Approx. 400 g/m2 pure material shall be
applied, depending on the absorptive capacity of the substrate.
If required, holes, broken-out parts, unevenness etc., shall be repaired with a solvent-free and
pigmented epoxy mortar. This mortar shall be mixed according to the film thickness required.
All steel surfaces, doors, supports, angles and other members shall be hot dip galvanized
and coated by an approved epoxy painting system. In case of UV exposure, top coats shall
be UV resistance.
CIVIL WORKS
( SPECIFICATION )
CONTENTS
1 GENERAL ....................................................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 Safety Precautions During Construction ........................................................................... 3
2.2 Material ............................................................................................................................. 3
2.3 Auxiliary Work.................................................................................................................. 4
2.4 Surveying Work ................................................................................................................ 4
2.4.1 General .............................................................................................................................. 4
2.4.2 Instruments ........................................................................................................................ 4
2.4.3 Auxiliary Work.................................................................................................................. 4
2.4.4 Site Survey ........................................................................................................................ 5
2.4.5 Setting Out of Works ......................................................................................................... 5
2.5 Dewatering During Construction ...................................................................................... 6
2.5.1 General .............................................................................................................................. 6
2.5.2 Execution ........................................................................................................................... 7
2.5.3 Method of Dewatering....................................................................................................... 7
2.5.4 Discharging of Water ........................................................................................................ 7
2.6 Earth and Rock Work ........................................................................................................ 7
2.6.1 General .............................................................................................................................. 7
2.6.2 Material ............................................................................................................................. 8
2.6.3 Execution ........................................................................................................................... 8
2.6.4 Auxiliary Work.................................................................................................................. 8
2.6.5 Tests and Properties........................................................................................................... 9
2.6.6 Open-Cut Excavation ...................................................................................................... 10
2.6.7 Stockpiles and Disposal................................................................................................... 10
2.6.8 Excavation and Manual Excavation ................................................................................ 11
2.6.9 Backfilling ....................................................................................................................... 11
2.6.10 Filling .............................................................................................................................. 11
2.6.11 Material for Structural Fill and Backfill .......................................................................... 12
2.6.12 Material for Non-Structural Fill and Backfill .................................................................. 12
2.6.13 Topping with Gravel “under foundation/ structural” ...................................................... 13
2.7 Piling Work ..................................................................................................................... 13
2.7.1 General ............................................................................................................................ 13
2.7.2 Materials .......................................................................................................................... 13
2.7.3 Reinforcement ................................................................................................................. 13
2.7.4 Execution of Work .......................................................................................................... 13
2.7.5 Basics for Test Piles ........................................................................................................ 15
2.7.6 Details for Pile Tests ....................................................................................................... 16
2.7.7 Driving of Piles (if applicable) ........................................................................................ 18
2.7.8 Foundation Work............................................................................................................. 21
2.7.9 Joints................................................................................................................................ 22
2.8 Cable and Pipe Trenches/Channels ................................................................................. 22
2.9 Grout under Base Plates .................................................................................................. 23
1 GENERAL
This part of the Specification shall cover all items related to civil construction works of the
Project, including survey works, dewatering, earth and rockwork, piling work, foundation works
and auxiliary works. Works shall include all items required for the tendered Project, as well as
all auxiliary works.
All works shall further be carried out in full compliance with all local rules and regulations and
the Specification shall be read, if applicable for the Project.
For applicable technical standards, tests, reference shall be made to:
S-TR-CIVIL-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
S-GEN-CDF - Civil Design Fundamentals
2 TECHNICAL DESCRIPTION
2.2 Material
All equipment, machinery, materials and tools required for execution of the works shall be
workable and kept in good working conditions throughout the construction period, and shall be
listed in a schedule, which shall be subject to TRANSCO’s approval.
For all materials to be used and to be installed, the Bidder/Contractor shall give special attention
to manufacturer's written instructions and follow them carefully.
2.4.1 General
Surveying works shall include the survey and setting out of survey points as particularly
described hereafter, as well as the determination of UTM Co-ordinates (Nahrawhan Datum) to
the satisfaction of Town Planning Department. The results of all surveying works carried out
shall be submitted to TRANSCO and shall be adjusted, if required.
2.4.2 Instruments
Only instruments, recently calibrated by the concerned gauging office, and acceptable to
TRANSCO, shall be used. The certificate of the gauging office, latest issue, shall be submitted
prior to the start of works and whenever required.
5- Average annual rainfall, Maximum annual rainfall, Maximum daily (24 h) rainfall &
Maximum hourly rainfall in the catchment area.
Hydrological investigation shall be executed with the following minimum requirements and
subject to the discretion of Transco/ Engineer:
a) Data gathered at site shall include
Manual stream flow measurements.
A site survey to obtain a channel cross-section, as well as channel
gradient, bed and bank material size characterizations.
Qualitative observations of channel debris potential.
Photographs of the site.
b) Annual and Seasonal Total Flow Volume
c) Peak Discharges
d) Drought Discharges
Based on the findings, the Contractor shall propose the design assumptions to Transco/
Engineer for approval.
2.5.1 General
Before the method of ground water lowering is selected, adequate knowledge of the ground and
water conditions has to be obtained from the results of a soil investigation and/or information,
which may be available from TRANSCO.
For the method and technique to be chosen by the Bidder/Contractor, the British Standard CP
2004 shall apply.
Where necessary, cofferdams, sheet piles, pump sumps, channels, troughs, inlet gutters, pipes
and any other required works to control and discharge water found in the work site to keep the
different work fronts free of any water during construction shall be part of the scope. The
dewatering system shall be designed and installed in such a way that alteration and extensions
can be made any time throughout the operating time, if necessary. Reserve unit shall be kept
ready for service when failure of any of the installed unit occurs. Hydraulic Calculation should
be submitted for approval.
The Bidder/Contractor has to consider the possibility of a temporary failure of the electric power
service and shall install emergency power units with sufficient capacity to feed the necessary
power to the installed unit at the moment of failure.
The Bidder/Contractor shall submit to TRANSCO, the detailed planning of the chosen
dewatering method and technique and the stand-by reserve units. The Bidder/Contractor has to
adjust the system if required by TRANSCO.
The Bidder/Contractor must ensure that drainage works will be eliminated without causing any
interference to his own work and that of other Bidder’s/Contractor’s operating elsewhere on the
construction site and to structures already erected or still in progress. Any damage occurring
during the above mentioned period shall then be made good by the Bidder/Contractor at his own
expense.
2.5.2 Execution
The Bidder/Contractor has to record all revealed data, which might occur during continuous
operation. The records have to be submitted to TRANSCO for information and checking by 9
a.m.
The Bidder/Contractor has to ensure the control of operation by manpower experienced in this
field round the clock, full operation of the dewatering systems during curing time of concrete
structures, removal of cofferdam, sheet piling, suction pipes, well points, channels, troughs, inlet
gutters, pipes, etc, after completion of dewatering.
In case of dewatering by means of the casing method the shells have to be extracted or filled up
with lean concrete.
Temporary buildings, structures and hard-standings and any other works required for installation
and operation of the dewatering systems, have to be removed after completion of the works.
2.6.1 General
This Article applies to all earth and rock-work required within the Project for establishing of the
buildings, structures and underground services.
Generally, all buildings and structures shall be founded on bearing strata and all excavation work
for foundations have to be carried out in accordance with the approved design and drawings.
2.6.2 Material
The characteristics of various types of ground and allowable bearing pressure are defined in
DIN, BS, or the equivalent EN (Euronorm). Values applicable during design shall be verified
through the Soil Investigation.
2.6.3 Execution
The Bidder/Contractor shall carry out all kind of earth and rock- works, either by manpower or
by use of fuel driven machinery and tools acceptable to TRANSCO for the following:
Clearing and grubbing
Excavation of top soil
Mining
Demolition of existing structures
Grading
Open cut excavation
Obstacles and archaeological findings
Replacement of material
Trench excavation for services
Backfilling
Safety precaution during earthwork.
If excavated material is rich in organic matter, it shall be stockpiled and after completion of all
civil and appertaining works, the green/agricultural area of the project area shall be reinstated by
placing the top soil layers as directed by TRANSCO. No additional payment shall be allowed for
such works.
Burning and blowing off of any material and use of explosives is generally not permitted except
where written order has been issued by TRANSCO and has been confirmed by the concerned
local authorities.
Reducing the under-ground water level, difficult work caused by water, etc
Removal of any groynes, buried pipes, wattle-work, fascines and the like that might
interfere with excavation profiles, irrespective of whether or not such structures are
specified in the Tender
Excavation /removal of concrete plates, beams, floors, boulders, rocks, large stones or
foundations
Eliminating unsuitable material from fills, and, if necessary, mixing of different soil
materials, spreading and compacting of filling materials in layers not exceeding 250 mm,
compaction tests every second layer all to maintain in the fills complying with the related
standard
Transport of excavated material to fill or deposit, placing and spreading in layers according
to conditions and drawings, and careful compaction
Grading of intermediate and top fill surfaces and slopes to fines and levels required
Sorting of excavated material which, if necessary, is to be used for special purposes
Providing, maintaining and later removal of driveways, maintaining existing ways and
roads; providing, placing, maintaining and later removing, conveying and dumping
equipment
Protection/support to existing adjacent building or structures during excavation or draw
down the under ground water table.
All tests have to be recorded in forms acceptable to TRANSCO. If not otherwise specified, the
minimum required degree of the compaction of the modified proctor density shall be:
Under blinding concrete for shallow foundations and slabs on grade 97%
Under pavements, under embankments. 95%
Roads. 98%
Under blinding concrete for pile caps and suspended grounds slabs 90%
equipment. All traffic towards or from the waste areas shall be continuously directed and
changed for the total covering of the surface of such areas in order to take advantage of the
weight of vehicles for compaction.
The Bidder/Contractor shall not have the right either to additional payment or to claim due to
work required for stockpiling materials or to take to waste areas.
The cost of the transportation of materials from the excavations to their final destination
including any necessary temporary stockpiling and the additional loading and transporting
operations shall be included in the total bid.
2.6.9 Backfilling
For backfilling of structures and areas, only selected imported material or approved well graded
granular material from the open-cut excavation shall be used. Use of any kind of waste or
building material or rock pieces for this scope shall not be permitted.
Dumped soil material touching the faces of the structures shall be of soft material. The material
shall be placed in horizontal layers of not more than 25 cm in compacted thickness. The fill
moisture content shall be adjusted to achieve a maximum of compaction.
The material shall be compacted by vibrator plates and/or mechanical tampers. The minimum
required degree of compaction shall be as defined before under Tests and Properties above.
2.6.10 Filling
Filling shall be approved well graded and selected material from excavations of predominantly
granular materials and free from slurry, mud, organic and other unsuitable matter, capable of
compaction by ordinary means.
Filling shall be placed in 25 cm layers and compacted at optimum moisture content by
mechanical means, where possible. Alternatively, where allowed by TRANSCO, fill shall be
placed in layers and saturated with sufficient water or otherwise compacted to produce maximum
compaction.
Filling around pipes and cables shall be of fine material to cover the pipe or cable by at least
15cm before the normal in-filling is placed.
All filled areas shall be left neat, smooth and well compacted, the top surface consisting of the
normal site surface soil, unless otherwise directed.
The Bidder/Contractor shall be responsible for the reinstatement of any surfaces of structures,
which may move or otherwise be affected by settlement of backfill.
SIEVE % PASSING
25.4 mm 100
19.05 mm 70 – 100
9.53 mm 50 – 80
No. 4 35 – 65
No. 10 25 – 50
No. 40 15 –30
No. 200 5 –15
Note: the maximum allowable L.L. and P.I are 35
and 10 respectively
2.7.1 General
This Article applies to the foundation design/static analysis in view of necessary piling works.
Piling works shall be based on the findings of the soil investigations and/or information given in
writing by TRANSCO. Piles shall be designed for the required design loading (uplift,
compression and horizontal loads) in line with the approved foundation design.
Earthwork as well as all concrete and reinforced concrete work shall be as specified under the
relevant items. All site installations, auxiliary works, materials, services, safety measures, and -
as requested by TRANSCO - all tests and samples required for the completion of the piling
works are to be included.
The static analysis/pile design shall normally be in accordance with DIN EN 1536, DIN 1045,
1054, 1055, 4014 and 4026, or BS-8004, BS-8110 and other applicable DIN or British Standard.
2.7.2 Materials
All materials to be used for the piling works shall meet the requirements as specified below.
Cement to be used for concrete piles shall be selected according to the recommendations of the
soil investigations report. Sulphate resistant Type Cement (SRC), or under certain conditions,
‘Moderately Sulphate Resistant Cement’ (MSRC-type II to ASTM-C150) based on the
recommendations of the Geotechnical Engineer and approved by TRANSCO, shall be used. All
cements are to be in accordance with either DIN 1164, DIN EN 196, BS or the American
Standards ACI, ASTM C150.
2.7.3 Reinforcement
Epoxy coated steel is not required, deformed high tensile steel shall be applied.
drilling, the reinforcement has to be placed, ensuring a minimum concrete cover of 75 mm, and
the pile has to be cast.
Spacers to be used shall be of the concrete type only. Other materials shall only be used upon
explicit approval of TRANSCO.
Daily records of each pile shall be produced by the Bidder/Contractor. The records shall give
detailed information on the type, diameter, length, location, penetration into bearing strata, piling
platform level related to zero level, date driven, date of casting, volume of concrete consumed,
depth from piling plat form level to toe, cut off level, top concrete level, length of temporary
casing, length of permanent casing and details of any obstructions encountered. Records shall be
submitted in duplicate to TRANSCO every following working day by 09 00 HRS.
Each cast-in-situ pile shall be filled with quality concrete up to at least 60 cm above the cut-off
level of the pile to allow for complete removal of slush and other foreign matters etc. from the
main pile and thus obtain sound and uniform concrete. Pouring concrete into the pile shall be
carried out using the tremie pipe method as well as the concrete pump. Pouring concrete into pile
shall only be stopped once complete removal of slush and other foreign matter has been ensured,
or as directed by TRANSCO.
The heads of concrete piles shall be incorporated with in-situ concrete pile caps, etc., and the
concrete in the head of the pile shall be carefully broken away from the reinforcement which
shall then be cleaned and straighten as shown on the Drawings or as directed. The pile shall be
cut off at the specified level and the concrete surface must be horizontal, plane and free from all
loose aggregate.
The top portion of the pile reinforcement shall be protected with PVC pipes, polythene sheet
wrapping or equivalent means to prevent damages to the reinforcement when trimming the pile
heads.
The Bidder/Contractor shall carry out successful foundation load tests in order to prove the
suitability of the pile foundation selected. The results of the tests shall be submitted in a format
for approval by TRANSCO.
2.7.6.1 Loading
The Bidder/Contractor shall execute the test piles using the same equipment, which he intends to
use for execution of all the piles. The test piles should be of the same length and same type as the
piles proposed for the project. Loads shall be applied in the direction of the resultant force acting
on the pile.
The loading tests of piles shall be in accordance with the procedure outlined in DIN 1054,
DIN 4014 and DIN 4026 as well as ISSMFE recommendation on "Axial pile loading tests", Part
1, static loading.
Type tests (preliminary pile tests) are to be loaded to either 250% of the anticipated design load,
or to the ultimate bearing load. At least two load cycles have to be made during type testing, the
first reaching from 0% to 100% and the second - after off-loading - to 250% of the design load.
Load steps shall normally not exceed 25% of the design load.
For routine tests (working pile tests) a loading to 150% of the design load is required. At least
two load cycles have to be carried out, the first reaching from 0% to 100%, and the second - after
off-loading to 150% of the design load. Load steps shall be worked out in line with the latest
edition of the “Building Regulations and Guidelines” of Abu Dhabi Municipality, whereby
following load steps/cycles shall normally be applied:
Vertical movements have to be measured by means of at least four dial gauges; horizontal
movements have to be measured by two dial gauges only, with a precision of 1/100 mm. On
every increment, settlements shall be recorded after 30”, 2’, 4’, 8’, 15’, 30’, 1h. Movement of the
pile head shall be less than 0.25 mm within that hour, or until 2 hours have elapsed, whichever
occurs first, before the application of the new load increment.
Complete records of level, load cell and dial gauge readings against date and time
throughout the test, preferably in a tabulation
Graphs of load and settlement/heave versus time
Graphs of settlement/heave versus load
Remarks concerning any unusual occurrences during the loading of the pile
Test reports on integrity testing of piles shall include clear sample diagrams of acceptable
signals for comparison purpose, as well as sample graphs indicating defects or doubts on
the integrity of the pile.
2.7.6.3 Evaluation/Conclusion
A safe design pile capacity shall be the least value determined in accordance with the
Municipality Regulations and this specification.
Proposal for the minimum penetrated depth of the piles through the ground
Complete information about the driving and the hammers to be used.
Piles shall not be driven until the excavation has been completed to the grade required for
footings or pile caps. Piles shall be driven in the exact locations shown on the drawings to be
submitted by the Bidder/Contractor and approved by TRANSCO or as may be directed by
TRANSCO.
The Bidder/Contractor shall be responsible for the accuracy of location of each pile and the
grade of the off-cut. Driving shall be done with fixed leads, which will hold the pile firmly in
position and in axial alignment with the hammer. Driving tolerances shall not be more than one
per cent out of plump and not more than 5 cm out of place. Driving of each pile shall be
continuous without intermission until the pile has been driven to refusal or to total penetration
for the last ten blows not exceeding the design penetration unless otherwise approved by
TRANSCO. Any piles that are split, warped, buckled, damaged or imperfect in any way shall be
removed and discarded. If any driven pile shall have been raised by the subsequent driving of
any adjacent pile or by any cause, the raised pile shall be re-driven to its original penetration and
resistance. The refusal shall be with HILEY formula or any other dynamic formula subject to the
approval of TRANSCO.
Debris from pile cut-offs and damaged piles shall not be buried in required fill under slabs at
grade or in required embankments, but shall be disposed by the Bidder/Contractor off the Site of
the work.
A record of the driving of all piles shall be kept by the Bidder/Contractor, and a signed copy
submitted to TRANSCO daily. The records shall show the pile type, length, location, penetration
for driving stages and the results of any tests.
After driving, the concrete heads of the piles are to be stripped off, to the elevation required, the
binders removed, and the main reinforcement bent to form an anchorage into the concrete of the
pile cap. Care must be taken in breaking out concrete that no damage is done to the lower section
of the piles.
2.7.7.2.4 Set
Set limits shall be defined based on the working load, factor of safety soil condition and driving
equipment. During measurement of the “set”, exposed parts of the casing shall not be damaged
or deformed and the dolly, helmet, etc., shall be in good condition. Set, i.e. the achieved
penetration during driving and the temporary compression after completion of driving shall be
measured and recorded for each pile. The set shall be recorded either as the number of blows
resulting in a penetration of 25 mm or the penetration in millimetres achieved by imposing 10
blows.
2.7.7.2.6 Reinforcement
Once the casing has been driven to the design depth, the reinforcement cage shall be installed.
Reinforcement details shall be as for bored cast in situ piles.
2.7.7.2.7 Concreting
Concreting shall be facilitated by pump, flexible hose, tremie-pipe or by bucket, as per the
approved method statement. Concrete quality and consistency shall be provided in line with
guidelines for cast in situ piles.
* Minimum value to be considered for routine testing only, for further testing, BS 4449 is to be
observed
Foundations shall be externally protected as indicated in the substructure water proofing system
of the technical specification.
2.7.9 Joints
All joints in concrete below ground shall be sealed by means of water bars.
Details of all waterbars, joint fillers, sealants and cover shall be fully described on all relevant
drawings and shall be approved by TRANSCO prior to materials being ordered.
Further reference is made to the below listed sample drawing, which is provided in the Drawings
Section.
Drawing No. Title
DWG TR CIV 03 03 Details of Expansion Joints
Cable and pipe channels at surface elevations shall be covered by prefabricated concrete covers,
designed for a traffic load SLW 60 according to DIN 1072. The length of each plate shall
normally not exceed 2.0 m. Provisions shall be made for lifting the cover plate by crane.
The edges of the recesses in walls and the edges of plates, pit recesses, lids, slabs, trenches,
trench covers, etc., shall have edge-protection of rolled steel sections, minimum size
45/45/4 mm. The steel sections shall be hot dip galvanised and –if required – in addition suitably
corrosion protected and finished as specified. The surface of the plates shall be plain trowelled to
receive dust proof hardener to be applied during concreting.
Concrete trenches, base and walls shall be protected externally as detailed for sub structural
concrete, and shall also be protected and sealed internally by the application of approved
pigmented sealant. Pre-cast concrete trench covers shall be protected on all sides by application
of two coats of approved clear sealer or approved dust proof hardener. Any cable and pipe
trenches/ channels deeper than 1.0 m shall be provided with permanent access ladder or rungs.
Compressive strength shall be in accordance with BS 1881, Part116 and BS 6319, Part 3
(epoxies), the cubes size shall be 100 mm, and the flexural strength shall be tested in accordance
with BS 4551.
Surfaces of the concrete base, which shall receive grouts shall be cleared of all defective
concrete, latency, oil, grease, other chemicals and dirt, and shall be roughened by chipping,
hammering or other techniques. The surfaces of all equipment bases or base-plates to be in
contact with the grout shall also be thoroughly cleaned of harmful matter, i.e. oil, grease, rust,
etc.
Before grouting, concrete surfaces shall be thoroughly wetted, if possible saturated with water.
When a dry grout is used, surfaces shall be pre-treated with cement slurry.
All shuttering, if any, shall be of adequate strength and securely fixed to withstand the pressure
of the grout and shall be sufficiently tight to prevent leakage.
Care shall be taken to ensure that the grout completely fills all voids to be grouted and is
thoroughly compacted and free of air pockets. Any areas or pockets, which are not to receive
grout, shall be properly sealed with an approved material.
The Bidder/Contractor shall take care that after the completion of grouting operations, all surplus
grout has to be removed and after a period of not more than 10 hours, the work shall neatly be
pointed and trowel led off and left in a workmanlike condition. Exposed edges of the grout shall
be adequately protected against damage and the effects of the environment during the airing
period
The Bidder/Contractor hereby states that in accordance with the design conditions
set forth in the present documents, the estimated net weight of the steel towers
will be as follows :
1.00 220 KV
1.01.2 S-6m kg
1.01.3 S+6m kg
1.01.5 AT - 6 m kg
1.01.6 AT + 6 m kg
1.01.8 BAT - 6 m kg
1.01.9 BAT +6 m kg
1.01.11 BAT90/ DE - 6 m kg
1.01.12 BAT90/DE + 6 m kg
___________________________________________________________________________________________________________________
D-OHL-T-220 (Rev.0-2009) Page 3 of 3
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-OHL-T-400 (Rev.0-2009) Page 1 of 3
OVERHEAD TRANSMISSION LINES
HV Towers of Lattice Steel Design (400 kV)
Table of Content
Page
1.00 400 KV 3
_____________________________________________________________________________________________________________
D-OHL-T-400 (Rev.0-2009) Page 2 of 3
OVERHEAD TRANSMISSION LINES
HV Towers of Lattice Steel Design (400 kV)
The Bidder/Contractor hereby states that in accordance with the design conditions
set forth in the present documents, the estimated net weight of the steel towers
will be as follows :
1.00 400 KV
1.01.2 S-6m kg
1.01.3 S+6m kg
1.01.5 AT - 6 m kg
1.01.6 AT + 6 m kg
1.01.8 BAT - 6 m kg
1.01.9 BAT +6 m kg
1.01.12 BAT90/DE + 6 m kg
yes
yes
___________________________________________________________________________________________________________________
D-OHL-T-400 (Rev.0-2009) Page 3 of 3
Standard Technical Specifications for Electrical Works
Conductors
(400 kV, ACSR/AW)
CARDINAL
________________________________________________________________________________________
D-OHL-CON-T-400 ACSR-AW Cardinal (Rev 0-2015) Page 1 of 4
OVERHEAD TRANSMISSION LINES
Conductors (400 kV, ACSR/AW)CARDINAL
Table of Content
Page
_____________________________________________________________________________________________________________
D-OHL-CON-T-400 ACSR-AW Cardinal (Rev 0-2015) Page 2 of 4
OVERHEAD TRANSMISSION LINES
Conductors (400 kV, ACSR/AW)CARDINAL
1.01 Manufacturer
1.02 Applicable standards IEC
VDE
DIN
ASTM
1.19.2 width cm
___________________________________________________________________________________________________________________
D-OHL-CON-T-400 ACSR-AW Cardinal (Rev 0-2015) Page 3 of 4
OVERHEAD TRANSMISSION LINES
Conductors (400 kV, ACSR/AW)CARDINAL
___________________________________________________________________________________________________________________
D-OHL-CON-T-400 ACSR-AW Cardinal (Rev 0-2015) Page 4 of 4
Standard Technical Specifications for Electrical Works
Conductors
(400 kV, ACSS/AW)
DOVE (14 EHSA)
________________________________________________________________________________________
D-OHL-CON-T-400 ACSS-AW Dove (Rev 0-2023) Page 1 of 4
OVERHEAD TRANSMISSION LINES
ACSS/AW Dove (14 EHSA)( 400 kV)
Table of Content
Page
_____________________________________________________________________________________________________________
D-OHL-CON-T-400 ACSS-AW Dove (Rev 0-2023) Page 2 of 4
OVERHEAD TRANSMISSION LINES
ACSS/AW Dove (14 EHSA)( 400 kV)
1.01 Manufacturer
1.02 Applicable standards IEC
EN
VDE
DIN
ASTM
1.19.2 width cm
___________________________________________________________________________________________________________________
D-OHL-CON-T-400 ACSS-AW Dove (Rev 0-2023) Page 3 of 4
OVERHEAD TRANSMISSION LINES
ACSS/AW Dove (14 EHSA)( 400 kV)
___________________________________________________________________________________________________________________
D-OHL-CON-T-400 ACSS-AW Dove (Rev 0-2023) Page 4 of 4
OVERHEAD TRANSMISSION LINES
ACSS/AW Dove (14 EHSA)( 400 kV)
___________________________________________________________________________________________________________________
D-OHL-CON-T-400 ACSS-AW Dove (Rev 0-2023) Page 5 of 4
Standard Technical Specifications for Electrical Works
Conductors
(400, 220 & 132 kV ACSR) Dove
________________________________________________________________________________________
D-OHL-CON-T-400-220-132-ACSR Dove (Rev.0-2015) Page 1 of 4
OVERHEAD TRANSMISSION LINES
Conductors (400, 220 & 132 kV ACSR) Dove
Table of Content
Page
_____________________________________________________________________________________________________________
D-OHL-CON-T-400-220-132-ACSR Dove (Rev.0-2015) Page 2 of 4
OVERHEAD TRANSMISSION LINES
Conductors (400, 220 & 132 kV ACSR) Dove
1.01 Manufacturer
1.02 Applicable standards IEC
VDE
DIN
ASTM
1.19.2 width cm
___________________________________________________________________________________________________________________
D-OHL-CON-T-400-220-132-ACSR Dove (Rev.0-2015) Page 3 of 4
OVERHEAD TRANSMISSION LINES
Conductors (400, 220 & 132 kV ACSR) Dove
___________________________________________________________________________________________________________________
D-OHL-CON-T-400-220-132-ACSR Dove (Rev.0-2015) Page 4 of 4
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-OHL-INS-220-COMP - Dove Conductor (Rev.0-2009) -40mm per kV Page 1 of 5
OVERHEAD TRANSMISSION LINES
Insulators (220 kV Composite)
Table of Content
Page
_____________________________________________________________________________________________________________
D-OHL-INS-220-COMP - Dove Conductor (Rev.0-2009) -40mm per kV Page 2 of 5
OVERHEAD TRANSMISSION LINES
Insulators (220 kV Composite)
1.03 Manufacturer
1.03.1 name
1.03.2 country of manufacturing
1.04 Applicable standards IEC
VDE
DIN
1.11 Sheds
1.11.1 material
1.11.2 number No.
1.11.3 diameter mm
1.11.4 spacing mm
1.11.5 inclination
1.11.5.1 upside °C
1.11.5.2 downside °C
___________________________________________________________________________________________________________________
D-OHL-INS-220-COMP - Dove Conductor (Rev.0-2009) -40mm per kV Page 3 of 5
OVERHEAD TRANSMISSION LINES
Insulators (220 kV Composite)
1.12 Caps
1.12.1 material forged steel
1.14 Mass kg
___________________________________________________________________________________________________________________
D-OHL-INS-220-COMP - Dove Conductor (Rev.0-2009) -40mm per kV Page 4 of 5
OVERHEAD TRANSMISSION LINES
Insulators (220 kV Composite)
2.01.5 Vee-string
2.01.5.1 number of insulators 2
___________________________________________________________________________________________________________________
D-OHL-INS-220-COMP - Dove Conductor (Rev.0-2009) -40mm per kV Page 5 of 5
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -40mm per kV Page 1 of 5
OVERHEAD TRANSMISSION LINES
Insulators 400 kV Composite)
Table of Content
Page
_____________________________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -40mm per kV Page 2 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)
1.03 Manufacturer
1.03.1 name
1.03.2 country of manufacturing
1.04 Applicable standards IEC
VDE
DIN
1.11 Sheds
1.11.1 material
1.11.2 number No.
1.11.3 diameter mm
1.11.4 spacing mm
1.11.5 inclination
1.11.5.1 upside °C
1.11.5.2 downside °C
___________________________________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -40mm per kV Page 3 of 5
1.12 Caps
1.12.1 material forged steel
1.14 Mass kg
2.01.5 Vee-string
TENDERER`s STAMP SIGNATURE
___________________________________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -40mm per kV Page 4 of 5
2.01.5.1 number of insulators 2
___________________________________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -40mm per kV Page 5 of 5
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -45mm per kV Page 1 of 5
OVERHEAD TRANSMISSION LINES
Insulators 400 kV Composite)
Table of Content
Page
_____________________________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -45mm per kV Page 2 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)
1.03 Manufacturer
1.03.1 name
1.03.2 country of manufacturing
1.04 Applicable standards IEC
VDE
DIN
1.11 Sheds
1.11.1 material
1.11.2 number No.
1.11.3 diameter mm
1.11.4 spacing mm
1.11.5 inclination
1.11.5.1 upside °C
1.11.5.2 downside °C
___________________________________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -45mm per kV Page 3 of 5
1.12 Caps
1.12.1 material forged steel
1.14 Mass kg
2.01.5 Vee-string
___________________________________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -45mm per kV Page 4 of 5
2.01.5.1 number of insulators 2
___________________________________________________________________________________________________________________
D-OHL-INS-400-COMP - Dove Conductor (Rev.0-2023) -45mm per kV Page 5 of 5
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-OHL-INS-400-Post -COMP - Dove Conductor (Rev.0-2023)-45mm per kV Page 1 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)
Table of Content
Page
_____________________________________________________________________________________________________________
D-OHL-INS-400-Post -COMP - Dove Conductor (Rev.0-2023)-45mm per kV Page 2 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)
1.03 Manufacturer
1.03.1 name
1.03.2 country of manufacturing
1.04 Applicable standards IEC
VDE
DIN
1.09
1.11 Sheds
1.11.1 material
1.11.2 number No.
1.11.3 diameter mm
1.11.4 spacing mm
1.11.5 inclination
1.11.5.1 upside °C
1.11.5.2 downside °C
___________________________________________________________________________________________________________________
D-OHL-INS-400-Post -COMP - Dove Conductor (Rev.0-2023)-45mm per kV Page 3 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)
1.12 Caps
1.12.1 material forged steel
1.14 Mass kg
___________________________________________________________________________________________________________________
D-OHL-INS-400-Post -COMP - Dove Conductor (Rev.0-2023)-45mm per kV Page 4 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)
2.01.5 Vee-string
2.01.5.1 number of insulators 2
___________________________________________________________________________________________________________________
D-OHL-INS-400-Post -COMP - Dove Conductor (Rev.0-2023)-45mm per kV Page 5 of 5
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-SUSP for all (Rev.1-2023) - 45mm per kV Page 1 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)SUSPENSION INSULATORS
Table of Content
Page
_____________________________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-SUSP for all (Rev.1-2023) - 45mm per kV Page 2 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)SUSPENSION INSULATORS
1.03 Manufacturer
1.03.1 name
1.03.2 country of manufacturing
1.04 Applicable standards IEC
VDE
DIN
1.11 Sheds
1.11.1 material
1.11.2 number No.
1.11.3 diameter mm
1.11.4 spacing mm
1.11.5 inclination
1.11.5.1 upside °C
1.11.5.2 downside °C
___________________________________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-SUSP for all (Rev.1-2023) - 45mm per kV Page 3 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)SUSPENSION INSULATORS
1.12 Caps
1.12.1 material forged steel
1.14 Mass kg
2.01.3 Vee-string
2.01.3.1 number of insulators 2
___________________________________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-SUSP for all (Rev.1-2023) - 45mm per kV Page 4 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)SUSPENSION INSULATORS
___________________________________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-SUSP for all (Rev.1-2023) - 45mm per kV Page 5 of 5
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-TENS-380KN -Cardinal (Rev.1-2023) - 45mm per kV Page 1 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)TENSION INSULATORS
Table of Content
Page
_____________________________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-TENS-380KN -Cardinal (Rev.1-2023) - 45mm per kV Page 2 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)TENSION INSULATORS
1.03 Manufacturer
1.03.1 name
1.03.2 country of manufacturing
1.04 Applicable standards IEC
VDE
DIN
1.11 Sheds
1.11.1 material
1.11.2 number No.
1.11.3 diameter mm
1.11.4 spacing mm
1.11.5 inclination
1.11.5.1 upside °C
1.11.5.2 downside °C
___________________________________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-TENS-380KN -Cardinal (Rev.1-2023) - 45mm per kV Page 3 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)TENSION INSULATORS
1.12 Caps
1.12.1 material forged steel
1.14 Mass kg
___________________________________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-TENS-380KN -Cardinal (Rev.1-2023) - 45mm per kV Page 4 of 5
OVERHEAD TRANSMISSION LINES
Insulators (400 kV Composite)TENSION INSULATORS
___________________________________________________________________________________________________________________
D-TR-OHL-INS-400-COMP-TENS-380KN -Cardinal (Rev.1-2023) - 45mm per kV Page 5 of 5
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-TR-OHL-OPGW (Rev.0-2017) Page 1 of 9
OVERHEAD TRANSMISSION LINES
Optical Ground Wires (OPGW)
Table of Content
Page
_____________________________________________________________________________________________________________
D-TR-OHL-OPGW (Rev.0-2017) Page 2 of 9
OVERHEAD TRANSMISSION LINES
Optical Ground Wires (OPGW)
1.01 Manufacturer
1.01.1 name
1.01.2 country of manufacturer
1.01.3 Factory address
1.02 Appointed Local Agent
1.02.1 name
1.02.2 address
1.02.3 Certificate of agency attached Yes
___________________________________________________________________________________________________________________
D-TR-OHL-OPGW (Rev.0-2017) 3
OVERHEAD TRANSMISSION LINES
Optical Ground Wires (OPGW)
2.01 Manufacture
2.02 Reel material
2.02.1 wooden yes/no
2.03.2 width cm
2.03.3 weight kg
3.01 Hollow stainless steel extruded/welded and aluminium extrued tube ST & AE
3.01.6 number of buffers inside the hollow tube: (IF APPLICABLE) No.
3.01.7 the ST & AE tube is filled with water blocking and yes/no
___________________________________________________________________________________________________________________
D-TR-OHL-OPGW (Rev.0-2017) 4
OVERHEAD TRANSMISSION LINES
Optical Ground Wires (OPGW)
4.01 Manufacturer
4.02 Applicable standards all relevant ITU-T,
IEC, IEEE standards
4.03 Buffer tube is made of polybuthylen yes/no yes
therephthalate (IF APPLICABLE)
4.04 Buffer tubes are in hollow stainless steel / aluminium
extruded tube (IF APPLICABLE)
4.05 Minimum thickness of buffer tube wall (IF APPLICABLE) mm 0.25
4.07 Buffer tubes are filled with water blocking jelly (IF APPLICABLE) yes
4.08 Gel dripping temperature higher than 85 120 degC or more yes
___________________________________________________________________________________________________________________
D-TR-OHL-OPGW (Rev.0-2017) 5
OVERHEAD TRANSMISSION LINES
Optical Ground Wires (OPGW)
4.21.1 1310 nm
4.21.2 1550 nm
4.22 Attenuation at 1310 nm
4.22.1 on reel at factory or dB/km max. 0.35
at site before installation
4.22.2 after installation, including splicing dB/km max. 0.40
5.01 Splices
5.02 Manufacturer
5.03 Applicable standards
5.04 Maximum average splice loss of any
any individual splice (mean value of the splice
loss measured from both sides) at
5.04.1 1310 nm dB 0.05
___________________________________________________________________________________________________________________
D-TR-OHL-OPGW (Rev.0-2017) 6
OVERHEAD TRANSMISSION LINES
Optical Ground Wires (OPGW)
6.01 Manufacturer
6.02 Material cast aluminium
or stainless steel
min. grade ANSI317
6.07 Dimensions
6.07.1 height mm
6.07.2 width mm
6.07.3 depth mm
7.01 Manufacturer
7.02 Material cast aluminium
or stainless steel
min. grade ANSI317
7.07 Dimensions
7.07.1 height mm
7.07.2 width mm
7.07.3 depth mm
___________________________________________________________________________________________________________________
D-TR-OHL-OPGW (Rev.0-2017) 7
OVERHEAD TRANSMISSION LINES
Optical Ground Wires (OPGW)
8.01 Manufacturer
8.02 Material cast aluminium
or stainless steel
min. grade ANSI 316
8.03 Protection degree IP65W
8.04 OPGW - OPGW - OPGW 3 Way splicing yes
8.05 No. of splices (minimum) (As applicable) 60 / 120
8.06 Cable entry from bottom yes
8.07 Dimensions
8.07.1 height mm
8.07.2 width mm
8.07.3 depth mm
___________________________________________________________________________________________________________________
D-TR-OHL-OPGW (Rev.0-2017) 8
Standard Technical Specifications for Electrical Works
________________________________________________________________________________________
D-TR-OHL-POL (Rev.0-2014) Page 1 of 5
OVERHEAD TRANSMISSION LINES
Photovoltaic Obstruction Light Equipment
Table of Content
Page
_____________________________________________________________________________________________________________
D-TR-OHL-POL (Rev.0-2014) Page 2 of 5
OVERHEAD TRANSMISSION LINES
Photovoltaic Obstruction Light Equipment
A. Low Intensity
3.05 length mm
3.06 width mm
3.07 depth mm
3.08 weight kg
3.09 no. of modules per system
3.10 Life time hrs
3.11 Manufacturer Name / Country of Origin
4.00 Batteries
4.01 type sealed
maintenance-free
___________________________________________________________________________________________________________________
D-TR-OHL-POL (Rev.0-2014) Page 3 of 5
OVERHEAD TRANSMISSION LINES
Photovoltaic Obstruction Light Equipment
4.04 length mm
4.05 width mm
4.06 depth mm
4.07 weight kg
4.08 no. of batteries per system
B Medium Intensity
3.05 length mm
3.06 width mm
___________________________________________________________________________________________________________________
D-TR-OHL-POL (Rev.0-2014) Page 4 of 5
OVERHEAD TRANSMISSION LINES
Photovoltaic Obstruction Light Equipment
3.07 depth mm
3.08 weight kg
3.09 no. of modules per system
3.10 Life time hrs
3.11 Manufacturer Name / Country of Origin
4.00 Batteries
4.01 type sealed
maintenance-free
___________________________________________________________________________________________________________________
D-TR-OHL-POL (Rev.0-2014) Page 5 of 5
STANDARD TECHNICAL SPECIFICATIONS FOR ELECTRIC WORKS
COMMUNICATION SYSTEMS
Communication Systems
1.1 Checking of the cabinet interior shall be made to verify clearances between live
electrical parts, isolation of phase and neutral buses from cabinet, tightness of all
mechanical connections and space for future extensions.
2. Site Tests
OHTL
OHTL
During the erection the following tests shall be carried out by the Bidder/Contractor in the presence of
TRANSCO.
Item Description
1. Tower footing resistance
Support footing resistance
The resistance to earth of the complete foundation of individual structures
shall be measured in an approved manner before the earth conductors are
erected. The placing of the test electrodes shall normally be along the center
line of the route in such direction as to ensure the lowest resistance to earth
is recorded, and a note shall be made of the direction in the test log. The
schedule used for recording earth resistance test shall contain in addition to
the measured ohmic values, details of the surface soils and general ground
conditions at the time of test.
Additional tower footing tests
If, in the opinion of TRANSCO, it is necessary to reduce the tower footing
resistance by approved means, the Bidder/Contractor shall make further tests
after the additional measures have been carried out and before the earthwires
are erected. Any further re-testing shall be carried out as necessary without
extra charge.
2. Measurement of galvanising and paint thickness
The Bidder/Contractor shall have available on site for TRANSCO’s use an
instrument suitable for the accurate checking of painted coats and galvanising
thickness. The gauge shall be available from the time of arrival of the first
consignment of steel work until the issue of the final acceptance certificate. The
cost of the gauge and other operating expenses are deemed to be included in
the contract price and the gauge will remain the property of the
Bidder/Contractor.
3. Measurement of resistance of clamps and joints
4. Sagging reports, sagging control measurements
5. Clearance measurements at qualified crossing spans or other spans defined by
TRANSCO to ground and/or obstacles
Tests on Commissioning
OHTL
ACCESSORIES
OHTL Accessories
A. Busbar Conductors
2. Site Tests
2.4 Measurement of noise levels. The following noise levels shall not be exceeded at
the substation fence and / or 25 meters from the busbar, whichever is closer.
Measurement shall be made at 2 points on each side of the substation.
For 500 kV:
2.5 Measurement of electric field. Measurement shall be made at two points in each bay
and at the two points around the substation fence. The following values should not
be exceeded:
It is not permitted to use only one insulator string to separate two systems. Two insulator strings
have to be applied and the fittings between the two insulators strings have to be earthed.
1.1 Checking of level and alignment of installed station insulators and accessories
1.3 Checking of proper grounding of steel structure support for station post insulators
COMMISSIONING CHECKLIST
CONTRACT
PROJECT TITLE CONTRACTOR CONSULTANT
NO.
NXXXX
This document is the property of TRANSCO and shall not be used by or given to any outside party without prior authorization.
Page 2 of 2
Table of Contents
Preface..................................................................................................................................................................................... I
Record of Checklists ............................................................................................................................................................ II
Chapter A: Commissioning Checklist (Electrical) ............................................................................................................. 1
Section 1:Switchgear........................................................................................................................................................... 2
Section 2:Power Transformers .......................................................................................................................................... 10
Section 3:Protection System ............................................................................................................................................. 21
Section 3.1: Transformer Protection System ................................................................................................................ 22
Section 3.2: Cable Protection System ........................................................................................................................... 25
Section 3.3: OHL Protection System ............................................................................................................................ 28
Section 3.4: Busbar Protection System ......................................................................................................................... 31
Section 3.5: Bus-coupler Protection System ................................................................................................................. 35
Section 3.6: Bus-section Protection System ................................................................................................................. 38
Section 3.7: Circuit Breaker Failure Protection System ............................................................................................... 41
Section 4:SCMS ................................................................................................................................................................ 43
Section 5:FMS................................................................................................................................................................... 48
Section 6:Telecommunication System .............................................................................................................................. 52
Section 7:FOC System ...................................................................................................................................................... 54
Section 8:AC Distribution System .................................................................................................................................... 56
Section 8.1: LVAC.......................................................................................................................................................... 3
Section 8.2: Auxiliary Transformer ................................................................................................................................ 3
Section 8.3: Small Lighting System................................................................................................................................ 3
Section 9: DC Distribution System ................................................................................................................................... 61
Section 9.1: 110V Battery System .................................................................................................................................. 3
Section 9.2: 48V Battery System .................................................................................................................................... 3
Section 10:UPS System .................................................................................................................................................... 64
Section 11:Power Cable .................................................................................................................................................... 66
Section 12:Overhead Line (OHL) ..................................................................................................................................... 69
Section 13:Remote Ends Works........................................................................................................................................ 73
Section 14:SO Integration ................................................................................................................................................. 78
Section 15:Earthing System .............................................................................................................................................. 81
Section 16:Metering System (EWEC) .............................................................................................................................. 83
Section 17:Shunt Reactor .................................................................................................................................................. 86
TRANSCO Power Engineering Department has developed The Commissioning Checklist for different
equipments. This Commissioning Checklist is developed to fulfill regulatory requirements. Moreover, the aim
of this checklist is to standardize TRANSCO procedures and to make sure that proper commissioning is
conducted under the highest levels of quality, reliability and durability for all equipments in various projects
under TRANSCO execution.
All Consultants and Contractors are required to use The Commissioning Checklist in all projects. No
“Clearance To Energize” will be signed and accepted without submitting proper Commissioning Checklist. The
Commissioning Checklist should fulfill the following:
Any Consultant/Contractor can obtain softcopy by contacting the following TRANSCO Engineers:
➢ Sherif Allam [email protected] 02/4164428
➢ Sami F. Salahat [email protected] 02/4164429
➢ Abdulrhman Ahli [email protected] 02/4164446
Section 1
GENERAL
"Consultant Logo" "Contractor Logo"
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Description Date
Engineer Engineer Name Signature
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Description Date
Engineer Engineer Name Signature
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Description Date
Engineer Engineer Name Signature
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Description Date
Engineer Engineer Name Signature
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Description Date
Engineer Engineer Name Signature
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Description Date
Engineer Engineer Name Signature
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Description Date
Engineer Engineer Name Signature
Section 2
INTERFACE AND
CONNECTION
DOCUMENTATION
"Consultant Logo" "Contractor Logo"
COMMISSIONING CHECKLIST
Commissioning Checklist- Chapter D, Section 2- I&C Docs_Rev 1.1 Date of Issue: 21/01/2022, SAS Page 2 of 3
"Consultant Logo" "Contractor Logo"
COMMISSIONING CHECKLIST
Commissioning Checklist- Chapter D, Section 2- I&C Docs_Rev 1.1 Date of Issue: 21/01/2022, SAS Page 3 of 3
POWER ENGINEERING DEPARTMENT (PED)
CHAPTER D
COMMISSIONING CHECKLIST
(GENERAL)
A ELECTRICAL
1 Switchgear
2 Power Transformer
3 Protection System
Power Transformer Protection System
Power Cable Protection System
OHL Protection System
Busbar Protection System
Bus Coupler Protection System
Bus-Section Protection System
Circuit Breaker Failure Protection System
4 Substation Control and Monitoring System (SCMS)
5 Fault Monitoring System (FMS)
6 Telecommunication System
7 Fiber Optic Cable (FOC)
8 AC Supply System
LVAC
Auxiliary Transformer
Small Lighting
9 DC Supply System
110V DC Battery System
48V DC Battery System
10 Un-Interrupted Power Supply (UPS)
11 XLPE Power Cable
12 Overhead Lines (OHL)
13 Remote Ends Works
14 SO (EWEC) Integration
15 Earthing System
16 Metering System (EWEC)
17 Shunt Reactor
B MECHANICAL
1 Fire Fighting System
2 Heating, Ventilation, Air Conditioner (HVAC)
3 Crane
C CIVIL
1 Building Services
D General
1 General requirements
2 Connection and Interface documentation
Section 12
OVERHEAD LINES (OHL)
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Test Description Date
Engineer Engineer Name Signature
COMMISSIONING CHECKLIST
"Contractor" "Consultant" TRANSCO Engineer Remarks
No. Test Description Date
Engineer Engineer Name Signature
CHAPTER A
COMMISSIONING CHECKLIST
(ELECTRICAL)