0% found this document useful (0 votes)
41 views25 pages

She PZ El 05868 0 B

This document is a Work Inspection Request (WIR) for the installation of FCU control panels at the Third Saudi Expansion of the Holy Mosque project. It includes details about the materials used, inspection dates, and comments from the consultant regarding the responsibilities of the contractor. The document outlines the acceptance criteria for various stages of the Building Management System (BMS) installation and emphasizes that approval does not relieve the contractor of their obligations.

Uploaded by

Shoaib Saeed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views25 pages

She PZ El 05868 0 B

This document is a Work Inspection Request (WIR) for the installation of FCU control panels at the Third Saudi Expansion of the Holy Mosque project. It includes details about the materials used, inspection dates, and comments from the consultant regarding the responsibilities of the contractor. The document outlines the acceptance criteria for various stages of the Building Management System (BMS) installation and emphasizes that approval does not relieve the contractor of their obligations.

Uploaded by

Shoaib Saeed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 25

Contractor:

THIRD SAUDI EXPANSION OF THE HOLY MOSQUE & SURROUNDING AREAS

Dep. Name Dep. Name


Civil Arch.
E.E Geo.
Project Ref:1150 M.E Other Issue Date: 12-Apr-2023
WIR Reference No. Rev.
WORK INSPECTION REQUEST (WIR)
SHE-PZ-EL-05868 0
Project Name: Piazza
CIVIL ARCH. √ ELE. MECH. R&E GEO. OTHER

Zone: 7 From To

IR Type: BMS
33A, 33D, 43A, 43B,

Location
Area:

Level
43C & 44C
SBF N/A
Subcontractor MTTS Axes: PB4 - PB16/C63 - CL70

Request received by (Dar Al-Handasah) :- Date & Time of Requested Inspection

ali al saadi
Name: …………………...………….
Description of work
12-04-2023
Date: ………………….…………… Date: 15-Apr-2023
Reference Documents
Time: 7:03 AM

FCU CONTROL PANELS FULL INSTALLATION WITHOUT Design Dwg.: AS PER ATTACHED DRAWING LIST
TERMINATION.
(FCU/SHZ-BU-07-269, 292, 293, 294, 295, 296, 297, 298, 316 Shop Dwg.: AS PER ATTACHED DRAWING LIST
& 322).
QUANTITY: Rfi No.: N/A
PANELS: (10) PCS
3/4" LS0H LIQUID TIGHT FLEXIBLE CONDUIT: (40) MTR Checklist Ref No.: ICL-1150-EL-041-00
1" EMT CONDUIT: (100) MTR
Inspection and test plan : ITP-1150-EL-041-00

SHE-SD-BM-E03-00-0120-03
Other Doc.: SHE-HR-MIR-MTTS-EL-55-00

Construction Manager QC Manager: Project Manager:


Name: ENG.MOHAMED ILYAS ALI Name: Eng.AKRAM EZZ ELDEEN Name: Eng. MOHAMED FAWZY
Sign: Sign: ……………………………………………. Sign:

Contractor/ Subcontractor Consultant


Title Action
Name Signature Name Signature

A B C D
INSP. BANDR ALSHAREEF Date: / / 2023
SURV.
A B C D
Date: / / 2023
A B C D
C.E.
Date: / / 2023

FAZAL AHMAD A B C D
E.E.
MOHAMMED HANOUSH Sayed Meslhy Date: 20-04-2023 / / 2023

M.E. A B C D
Date: / / 2023
ARCH.
A B C D
Date: / / 2023
GEO.
A B C D
Date: / / 2023
R&E
A B C D
Date: / / 2023
A B C D
Other
Date: / / 2023

STATUS

A-Approved B-Approved as Noted C-Revise and Resubmit D-Rejected

Sayed Meslhy
Resident Eng. ……………………………………………………………………………………………. Date:- / /

……………………………………………………………………………………………. 20-04-2023
Received by Contractor :

Name: …………………………………………………………………………… Date: …………………………………. Sign: ……………………………………

1- Approval shall not relieve the Contractor of its obligations and liabilities under the Contract or constitute authorization of any change to Contract Documents, and therefore shall not imply any recognition whatsoever of additional time and/ or cost.

2- Distribution : Original to Contractor and Copy to Consultant.


Note:

3- IR shall be closed within 48 hours from the above mentioned Date of Inspection.

4- IR must be submitted prior to inspection date and time by at least 24 hrs

Form No. QMPF-32-WIR-R05


Contractor:
THIRD SAUDI EXPANSION OF THE HOLY MOSQUE &
SURROUNDING AREAS

Project Ref:1150 Issue Date: 12-Apr-2023

CONSULTANT'S COMMENTS (CC)

Sub-Project Name: Piazza Date: 15-Apr-2023

Elements: BMS SYSTEM WIR No: SHE-PZ-EL-05868 REV. 0

MIR No: N/A

Comments:

Name of the
Sr No. Discipline Comments
Engineer
Sayed Meslhy LC & Control

1-Main contractor is fully responsible for saving installations & changing any damaged material
2- Contractor shall provide BMS T&C plan for review and approval

3- earthing , labeling , end cab for c-hcannels shall be checked with the next stage

4- Final approval is subject to system functionality

Approval shall not relieve the Contractor of its obligations and liabilities under the Contract or constitute authorization of any change to Contract Documents, and therefore
shall not imply any recognition whatsoever of additional time and/ or cost.
Form No. QMPF-45-CC-R01
Contractor:
THIRD SAUDI EXPANSION OF THE HOLY
MOSQUE & SURROUNDING AREAS
Project Ref:1150 Issue Date: 12-Apr-2023
LIST OF DRAWINGS (LOD)

WIR Reference SHE-PZ-EL-05868 REV. 0

DESIGN DRAWING
No. Drawing Reference Rev. No.
1 N/A
2
3
4
5
6
7
8
9
10
11
12
13
15
SHOP DRAWING
No. Drawing Reference Rev. No.
1 SHZ-SD-BM-E02-B2-033A-03 03
2 SHZ-SD-BM-E02-B2-033D-03 03
3 SHZ-SD-BM-E02-B2-043A-03 03
4 SHZ-SD-BM-E02-B2-043B-03 03
5 SHZ-SD-BM-E02-B2-043C-03 03
6 SHZ-SD-BM-E02-B2-044C-03 03
7
8
9
10
11
12
13
14
15
16
17
18
19
Consultant Engineer Q.C Engineer BANDR ALSHAREEF
Name: ……………………………………………………………. Name:
Sayed Meslhy
Sign. : ……………………………………………………………. Sign. : …………………………………………………………….
Approval shall not relieve the Contractor of its obligations and liabilities under the Contract or constitute authorization of any change to
Contract Documents, and therefore shall not imply any recognition whatsoever of additional time and/ or cost.
Form No. QMPF-04-LOD-R00
Consultant: Contractor:
THIRD SAUDI EXPANSION OF THE HOLY MOSQUE &
SURROUNDING AREAS

INSPECTION CHECK LIST BUILDING MANAGEMENT SYSTEM (BMS)

ICL-1150-EL-041-00 WIR Ref No.:SHE-PZ-EL-05868 Rev:0

SUB-PROJECT TITLE :- CUC PROJECT INSPECTION DATE & TIME:


SBG - QC Consultant
Item No ACCEPTANCE CRITERIA NA Comments
PASS FAIL PASS FAIL

A BMS SYSTEM

A1 Material approval as related MIR.


P
A2
All shop /coordination drawings and other related
documents for related area are approved. P
Check that all materials and accessories(type -size-rated -
A3 etc) in accordance to latest approved material submittal,
drawings / specification
P
A4
Check that all Materials are free of physical damages and
defects & missing parts P
A5 Check that WIR release according to approved ITP
P
A6
Check the installed quantities for related PO and related
tender BOQ items P
A7 Check that Coordination is done with other related services
P
B SECTION 1 - FIRST FIX WORKS

B1
Outlet boxes are installed at exact locations and levels as
per specification and approved shop dwg. P
B2
Conduits will be terminated with locknuts and bushings or
any approved fittings to boxes ,or boards . P
B3
Approved Pull boxes are provided for every two bend or
every straight runs exceeding 15 meters. P
Openings in Walls & floors for cable Tray crossing are
B4 sealed using fire proof sealant or other sealant as per
Approval/Dwg
P
B5
Conduits, trunks crossing expansion joint provided with
expansion coupler P
B6
Flexible conduit is used for final connection to field devices
. P
B7
Check that separate conduits for BMS are not shared with
other systems. P
B8
Check that Bending radius as per specs and manufacturer
recommendation. P
B9
Installed raceways have no more than 2 quarter bends , field
bends don't hinder cable pulling P

1/5

ICL-1150-EL-041-00
Consultant: Contractor:
THIRD SAUDI EXPANSION OF THE HOLY MOSQUE &
SURROUNDING AREAS

INSPECTION CHECK LIST BUILDING MANAGEMENT SYSTEM (BMS)

ICL-1150-EL-041-00 WIR Ref No.:SHE-PZ-EL-05868 Rev:0

SUB-PROJECT TITLE :- CUC PROJECT INSPECTION DATE & TIME:


SBG - QC Consultant
Item No ACCEPTANCE CRITERIA NA Comments
PASS FAIL PASS FAIL

Water proof material should be used between electrical and


B10 mechanical works in wet area ( near any mechanical work
which may leak , condensate , evaporate water or liquids)
P
B11 Check that Draw - wires are pulled in all conduits
P
B12
Check the color coding for conduits and cable tray every 3
meters. P
B13 Check that knock out boxes should be closed
P
B14
Check the cable tray and ladder are installed properly and
routing as per latest approved shop drawings. P
B15
Check for Vibration and seismic supports as per approved
submittal and shop drawings P
B16
Check that the approved proper supports for cable tray and
ladder are provided at distance <1.5 m . P
B17
Cable trays are accessible to , pulling of cables and
maintenance. P
B18
Check continuity and earthing of trunkes and cable tray /
ladder by means of earth strips . P
B19
Check that approved labels and identification are provided
and completed P
B20
Supports of cable trunks and trays are checked by civil
engineer . P
C SECTION 2 - SECOND FIX WORKS

C1
Check cables for twisting & damage in outer insulation
sheath. P
C2
Check the size, type, rating and color coding of cables
installation as per latest approved shop drawings / specs. P
Check the cables tags , identification as per project
C3 specification along the route and at every change in
direction and both ends, each side of duct etc.
P
C4 Check cables according to cable test plan
P
C5
Check the permissible length of control cable according to
material submittal approval P
C6
Check that all cables are secured At ends to avoid
excessive tension and protected from dust. P

2/5

ICL-1150-EL-041-00
Consultant: Contractor:
THIRD SAUDI EXPANSION OF THE HOLY MOSQUE &
SURROUNDING AREAS

INSPECTION CHECK LIST BUILDING MANAGEMENT SYSTEM (BMS)

ICL-1150-EL-041-00 WIR Ref No.:SHE-PZ-EL-05868 Rev:0

SUB-PROJECT TITLE :- CUC PROJECT INSPECTION DATE & TIME:


SBG - QC Consultant
Item No ACCEPTANCE CRITERIA NA Comments
PASS FAIL PASS FAIL

C7
Check that Filling ratio of pulling cables in raceways is
accepted P
C8
Check that the cables segregation and spacing are as per
specification and Manufacturer’s recommendations. P
C9
Check the sealing of Pipe/pvc duct /openings in route of
cable installed. P
Check that Protective sleeves are provided as per
C10 specification, and location such as road crossing, passing
from wall etc.
P
C11
Check glanding of cables installed secured and correctly
with accessories, no sharp bends. P
C12
Check termination, jointing as per procedure &
identification of joints, its boxes etc. P
C13 Check cable for its supports & clamping at termination end.
P
C14
Check the tightness of connection of terminals, screw and
supports .. etc. P
C15 LAN cable shall not share conduit with any other cable
P
C16
Check for adequate length of free conductors in boxes and
at both the ends of termination. P
C17 Check that Continuity Test is done and accepted.
P
C18
Check that Insulation Resistance/Capacitance Test for
max acceptable length is done and accepted. P
C19 Check for cable labeling at both ends,
P
C20 Check for cable ties
P
D SECTION 3 - THIRD FIX WORKS

Check that all devices are installed at exact locations and


D1 levels as per latest approved shop drawings and
manufacture instructions.
P
Check that main DCP, CCP and FCU Panel and equipment
D2 are installed at defined locations as per latest approved
shop drawings and manufacture instructions.
P
D3
Check the DCP, CCP and FCU panels shall have switch
with lockable handle or cover. P
D4
Check for exact routing and layout of all cable trays, cabling
and wire ways. P
3/5

ICL-1150-EL-041-00
Consultant: Contractor:
THIRD SAUDI EXPANSION OF THE HOLY MOSQUE &
SURROUNDING AREAS

INSPECTION CHECK LIST BUILDING MANAGEMENT SYSTEM (BMS)

ICL-1150-EL-041-00 WIR Ref No.:SHE-PZ-EL-05868 Rev:0

SUB-PROJECT TITLE :- CUC PROJECT INSPECTION DATE & TIME:


SBG - QC Consultant
Item No ACCEPTANCE CRITERIA NA Comments
PASS FAIL PASS FAIL

Check that Termination completed and Tighten outgoing


D5 connectors and terminals according to manufacturers
recommendation.
P
D6
Check that IP network connection for CCP Panel is done
as per manufacturers recommendation. P
D7
Check the interfaces and connections with all related
systems . P
D8
Check the identification for system equipment, electronic
component and devices . P
D9 Check the color coding of circuit wiring , installation
P
D10
Check the grounding of the system equipment, devices,
cable shield etc to eliminate. P
check that Programing And Adjusting are done as per
D11 project specification, approved material submittal &
approved shop drawing.
P
D12 Check calibration of the field device.
P
Check that the field device has the correct rangefor the
D13
application, that the range is correctly entered in the
controller and the display of values is correctly engineered
on the operator's terminal.
P

D14
Check that BMS panels shall be positioned to allow doors
to be fully opened for easy access to wiring and component P
D15
Check that all control and monitoring cables shall not share
any cable carrying voltages in excess of 48V P
D16
Check That Field Device Installed as per approved Shop
Drawing. P
D17
Check That Equipment and field device properly Installed
and accessible for operation and Maintanence . P
D18
Check That VAV cable Termination done as per approved
shop drawings. P
Check That Damper Aqtuator Termination as per
D19 coordinated with fire alarm control modules as per
approved detail.
P

4/5

ICL-1150-EL-041-00
Consultant: Contractor:
THIRD SAUDI EXPANSION OF THE HOLY MOSQUE &
SURROUNDING AREAS

INSPECTION CHECK LIST BUILDING MANAGEMENT SYSTEM (BMS)

ICL-1150-EL-041-00 WIR Ref No.:SHE-PZ-EL-05868 Rev:0

SUB-PROJECT TITLE :- CUC PROJECT INSPECTION DATE & TIME:


SBG - QC Consultant
Item No ACCEPTANCE CRITERIA NA Comments
PASS FAIL PASS FAIL

D20
Check all input & output point according to the I/O LIST
APPROVAL P
D21
Check That Air Flow Station Installation And cable
Termination done as per approve shop drawings. P
D22
Chek That Valve Actuator Termination done as per approve
shop drawings. P
D23 Functional operation tests are done and accepted .
P
check that Testing and commissioning as per approved
D24
testing and commissioning plan for all of the system
components as well interfacing with the other related
systems are done and accepted .
P

Site Engineer : QC Engineer : Consultant Engineer :

Name :M.Hannoush Name : bandr elsharif Name :


Sayed Meslhy
Signature : Signature : Signature :

Date :12-04-2023 Date :12-04-2023 Date :


20-04-2023

Engineer's representative Approval

Approved Approved as noted Revise and Resubmit Rejected

Comments :

Sayed Meslhy 20-04-2023


Name : Signature : Date :

5/5

ICL-1150-EL-041-00
Refer to comments on DWG# SHZ-SD-BM-E02-B2-032B-03

BMS code "B"


Ahmed A.Raheem
30/6/2020

Low Current: Code "B"


Refer to the comments in dwg. no. "SHZ-SD-BM-
E02-B2-032A-03"

Elect. (B)
refer to all comments on DWG# SHZ-SD-BM-E02-B2-032B-03

A.A 30/6/2020
Elect. (B)
refer to all comments on DWG# SHZ-SD-BM-E02-B2-032B-03

Refer to comments on DWG# SHZ-SD-BM-E02-B2-032B-03

BMS code "B"


Ahmed A.Raheem
30/6/2020

Low Current: Code "B"


Refer to the comments in dwg. no. "SHZ-SD-BM-
E02-B2-032A-03"

Check FCU serving


space and its related
Thermostat.

A.A 30/6/2020
Refer to comments on drawing no.
SHZ-SD-BM-E02-B2-040A-03.

BMS Code "B"


30/6/2020

T.A 30/6/2020

Elect. (B)
refer to all comments on the DWG# SHZ-SD-BM-E02-B2-023B-03
Low Current: Code "B"
Refer to the comments on dwg no. SHZ-SD-BM-E02-B2-040A-03
FCU thermostats
are missing.

Low Current: Code "B"


Refer to the comments on dwg no. SHZ-SD-BM-E02-B2-040A-03

Refer to comments on drawing no.


SHZ-SD-BM-E02-B2-040A-03.

BMS Code "B"


30/6/2020

T.A 30/6/2020
Elect.(B)
refer to all comments on DWG# SHZ-SD-BM-E02-B2-023B-03
Missing
FCUs

Elect. (B)
refer to all comments on DWG# SHZ-SD-BM-E02-B2-032B-03

Refer to comments on drawing no.


SHZ-SD-BM-E02-B2-040A-03.

BMS Code "B"


30/6/2020

Low Current: Code "B"


Refer to the comments on dwg no. SHZ-SD-BM-E02-B2-040A-03

T.A 30/6/2020
Pump control panel
shall be connected
to BMS.

T.A 30/6/2020

Low Current: Code "B"


Refer to the comments on dwg no. SHZ-SD-BM-E02-B2-040A-03

Elect. (B)
refer to all comments on DWG# SHZ-SD-BM-E02-B2-032B-03

Refer to comments on drawing no.


SHZ-SD-BM-E02-B2-040A-03.

BMS Code "B"


30/6/2020

You might also like