Asme Viii - 2021
Asme Viii - 2021
1-2021
SECTION VIII
Rules for Construction of Pressure Vessels
ASME VIII (BOK) 2
The following categories describe the minimum necessary knowledge and skills:
II. WELDING PROCEDURE AND QUALIFICATION EVALUATION BASED ON ASME BOILER AND
PRESSURE VESSEL CODE, SECTION IX
The inspector should be familiar with and understand the general rules for welding in ASME Section VIII, Div. 1, Parts UW
and UCS such as:
The inspector should be familiar with and understand the general rules for NDE (UG, UW, Appendices 4, 6, 8, and 12)
Introduction 5
There are several “Fabrication” codes that provide the requirements for design,
material selection, fabrication, testing, identification and documentation for boilers
and pressure vessels.
The reference codes were issued to support the “book codes” “Fabrication codes”.
• These reference codes provide information that is common to all the construction
codes.
• Section II, Materials, which was issued in 1924 and now consists of four parts:
- Part A, Ferrous Materials
- Part B, Non-Ferrous Materials
- Part C, Welding Materials
- Part D, Material Properties
The following classes of vessels are not considered to be within the scope of the
division
API 510
U-2 General 9
Para. (a), The user or his designated agent shall establish the design requirements
which shall include as a minimum:
UG-4(a) is the general paragraph that says that material used for pressure parts must comply with a
specification given in Section II, Part D, and that are permitted in Subsection C.
USER'S RESPONSIBILITIES
• UG-4(f) states that the user or his designated agent assures that the material used is acceptable for the
intended services.
(1) does not apply to heat transfer plates of plate-type heat exchangers;
(2) does not apply to the inner pipe of double pipe heat exchangers nor to pipes and tubes that are enclosed
and protected from mechanical damage by a shell, casing, or ducting, where such pipes or tubes are NPS 6
(DN 150) and less.
(3) The minimum thickness of shells and heads of unfired steam boilers shall be1/4 in. (6 mm) exclusive of
any corrosion allowance;
(4) The minimum thickness of shells and heads used in compressed air service, steam service, and
water service, made from materials listed in Table UCS-23, shall be 3/32 in. (2.5 mm) exclusive of any
corrosion allowance.
(5) This minimum thickness does not apply to the tubes in air cooled and cooling tower heat exchangers.
UG Design 12
• It state that plate material shall be ordered not thinner than the design thickness.
• However, it is also acceptable that an under-tolerance of < smaller value of 0.01 in. (0.3 mm) or 6%
of the ordered thickness may be used at the full design pressure for the thickness ordered.
UG-22 Loadings
• Internal or external design pressure,
• Weight of vessel plus normal and test contents including static head,
• Weights of attachments,
• Internal attachments,
• Vessel support attachments,
• Cyclic and dynamic reactions due to pressure, thermal, or mechanical loads,
• Wind, snow, and seismic loads,
• Impact reactions such as those due to fluid shock, and
• Temperature gradients and differential thermal expansion.
UG Design 14
UG-116(a) requires that each pressure vessel are marked with the following:
• The official Code U Symbol
• Name of the Manufacturer of the pressure vessel preceded by the words "certified by";
• Maximum allowable working pressure at temperature;
• Minimum design metal temperature
• Manufacturer's serial number;
• Year built.
UG Design 15
• The letters PHT shall be applied under the Code Symbol when only part of the complete
vessel has been post-weld heat treated as provided in UW-10 (see UG-116(f)(2)).
UG Design 16
UG-119 Nameplates
specifies that nameplates are to be used on vessels, except when markings are directly
applied on the vessel wall according to UG-118.
Nameplates must be made from a metal suitable for the intended service with the markings
specified in UG-116.
Nameplates must also be located in an obvious location on the vessel to allow for easy
reading.
UG-120(a) requires the vessel Manufacturer to fill out a data report on Form U-
1 or Form U-1A. It must
also be signed by the Manufacturer and the Inspector for each pressure vessel
marked with the Code U
Symbol.
(a) Furnish a copy of the Manufacturer's Data Report to the user and, upon
request, to the Inspector;
(c) Keep a copy of the Manufacturer's Data Report on file in a safe repository
for at least 3 years.
UW-3 weld joint category 18
UW-3 weld joint category 19
The term “Category” as used herein defines the location of a joint in a vessel, but not the type of
joint.
Category A - Longitudinal and spiral welded joints within the main shell, communicating
chambers, transitions in diameter, or nozzles;
- Any welded joint within a sphere, within a formed or flat head, or within
the side plates of a flat-sided vessel;
- Circumferential welded joints connecting hemispherical heads to main
shells, to transitions in diameters, to nozzles, or to communicating chambers.
UW-3 weld joint category 20
The term “Category” as used herein defines the location of a joint in a vessel, but not the type of
joint.
The term “Category” as used herein defines the location of a joint in a vessel, but not the type of
joint.
Welded joints connecting flanges, tube sheets, or flat heads to main shell, to
Category C formed heads, to transitions in diameter, to nozzles, or to communicating
chambers any welded joint connecting one side plate to another side plate of
a flat-sided vessel.
UW-3 weld joint category 22
The term “Category” as used herein defines the location of a joint in a vessel, but not the type of
joint.
Lethal Service When the substance in the vessel is designated as lethal, all butt welds used to
manufacture the vessel shall be fully examined using radiographic techniques,
Some other important liquid or restricts weld types listed in table UW-12 that
gaseous lethal service restrictions are designated for lethal service as follows:
listed in UW2(a) are as follows: - Category A shall be Type No. (1)
- ERW pipe or tube is not permitted to - Categories B and C shall be Type No. (1) or
be used as a shell or nozzle. No. (2)
- When fabricated of carbon or low - Category D shall be full penetration welds
alloy steel, post-weld heat treated is extending through the entire thickness of the
required vessel wall or nozzle wall
ERW >> Electric Resistance Welded
Joint type (UW-12) 27
Joint Type
Type (6) Type (5) Type (4) Type (3) Type (2) Type (1)
Joint type (UW-12) & Service Restrictions (UW-2) 28
Type (1) Butt joints as attained by double welding or by other means which will obtain
the same quality of deposited weld metal on the inside and outside weld
surfaces to agree with the requirements of UW 35.
Welds using metal backing strips which remain in place are excluded.
Joint type (UW-12) & Service Restrictions (UW-2) 29
Type (2) Single welded butt joint with backing strip other than those included under (1)
Type (3) Butt joints welded from one side only without a permanent backing strip that
cannot be verified as having achieved full penetration and fusion
Joint type (UW-12) & Service Restrictions (UW-2) 30
Type (5) Single full fillet lap joints with plug welds
Type (6) Single full fillet lap joints without plug welds
RADIOGRAPHIC AND ULTRASONIC EXAMINATION UW-11 31
RT Radiography
UW-52 UW-51
RADIOGRAPHIC AND ULTRASONIC EXAMINATION UW-11 32
Full Radiography
(1) All butt welds in the shell and heads of vessels used to contain lethal substances
Full Radiography
(5) (desired by the designer to improve E) (3 items if applied >> full RT)
(a) Category A and B welds connecting the shell or heads of vessels shall be of Type No. (1) or
Type No. (2) of Table UW-12;
(b) Category B or C butt welds [but not including those in nozzles and communicating
chambers except as required in (4) above] which intersect the Category A butt welds in the
shell or heads of vessels or connect seamless vessel shell or heads shall, as a minimum, meet
the requirements for spot radiography in accordance with UW-52.
UW-3 weld joint category 35
Spot radiographs required by this paragraph shall not be used to satisfy the spot radiography
rules as applied to any other weld increment.
36
- This paragraph is only mandatory when it is desired by the designer to use the highest joint efficiency possible for
calculations of thickness required or pressure allowed.
- It is a choice the designer makes when there are no mandatory requirements based on service or material as found in UW-
11 (a) (1)*Lethal Service, (2)*Thickness exceeded
RADIOGRAPHIC AND ULTRASONIC EXAMINATION UW-11 37
Full Radiography
(6)
- All butt welds joined by electro-gas welding with any single pass greater than 11/2 in. (38
mm)
- All butt welds joined by electroslag welding.
(7) All Category A welds in a tube-sheet shall be of Type (1) of Table UW-12
RADIOGRAPHIC EXAMINATION OF WELDED JOINTS UW-51 38
Full Radiography
UW-51 (a) (4)
1/4 in. (6 mm) and greater in thickness may be examined using the ultrasonic (UT) method
Full Radiography
UW-51 (b)
- Defects shall be repaired as provided in UW-38, and the repaired area shall be reexamined.
- In lieu of reexamination by radiography, the repaired weld may be ultrasonically examined
in accordance with Mandatory Appendix 12 at the Manufacturer’s option.
- This ultrasonic examination shall be noted under Remarks on the Manufacturer’s Data
Report Form
RADIOGRAPHIC EXAMINATION OF WELDED JOINTS UW-51 40
Spot Radiography
Minimum Extent of Spot Radiographic Examination
(1) One spot shall be examined on each vessel for each 50 ft (15 m) increment of weld or
fraction thereof for which a joint efficiency from column (b) of Table UW-12 is selected.
- However, for identical vessels or parts, each with less than 50 ft (15 m) of weld for which a
joint efficiency from column (b) of Table UW-12 is selected, 50 ft (15 m) increments of weld
may be represented by one spot examination
50' 25' fraction
increment
The minimum length of spot
radiograph shall be 6 in. (150 mm).
SPOT EXAMINATION OF WELDED JOINTS UW-52 42
Spot Radiography
Minimum Extent of Spot Radiographic Examination
(2) For each increment of weld to be examined, a sufficient number of spot radiographs shall be taken
to examine the welding of each welder or welding operator.
Under conditions where two or more welders or welding operators make weld layers in a joint, or on
the two sides of a double‐welded butt joint, one spot may represent the work of all welders or welding
operators.
Welder A
Alone
SPOT EXAMINATION OF WELDED JOINTS UW-52 43
Spot Radiography
Minimum Extent of Spot Radiographic Examination
(3) Each spot examination shall be made as soon as practicable after completion of the increment of
weld to be examined. The location of the spot shall be chosen by the Inspector after completion of the
increment of welding to be examined, except that when the Inspector has been notified in advance and
cannot be present or otherwise make the selection, the Manufacturer may exercise his own judgment
in selecting the spots.
SPOT EXAMINATION OF WELDED JOINTS UW-52 44
Spot Radiography
UW-14(b)
Single openings meeting the requirements given in UG-36(c)(3) may be located in head-to-shell or
Category B or C butt welded joints, provided the weld meets the radiographic requirements in UW-51
for a length equal to three times the diameter of the opening with the center of the hole at mid-
length.
SPOT EXAMINATION OF WELDED JOINTS UW-52 46
Spot Radiography
UW-52 (d) Evaluation and Retests
When a spot, radiographed as required in (b)(1) or (b)(2) above has been examined and the radiograph
discloses welding which does not comply……..two additional spots shall be examined in the same weld
increment at locations away from the original spot..
SPOT EXAMINATION OF WELDED JOINTS UW-52 47
Spot Radiography
Evaluation and Retests
The locations shall be determined by the Inspector… if the two additional pass, repair the failed spot, if
either of the two additional spots fail ,the entire rejected weld shall be removed and the joint
rewelded or the entire increment completely radiographed and all defects corrected
Lethal E= 1.0
Cylindrical Shells
The minimum thickness or maximum allowable working pressure of cylindrical shells shall be
the greater thickness or lesser pressure as given by (1) or (2) below.
E = joint efficiency
P = internal design pressure (see UG-21)
R = inside radius of the shell course under consideration,
S = maximum allowable stress value (see UG-23 and
t = minimum required thickness of shell
Thickness of Shells Under Internal Pressure UG-27 52
Spherical Shells
When the thickness of the shell of a wholly spherical vessel does not exceed 0.356R, or P does
not exceed 0.665SE, the following formulas shall apply:
E = joint efficiency
P = internal design pressure (see UG-21)
R = inside radius of the shell course under consideration,
S = maximum allowable stress value (see UG-23 and
t = minimum required thickness of shell
Thickness of Shells Under Internal Pressure UG-27 53
Unreal point
Example
Givens: The same pressure, stress and, dimension values will be used for all heads. Let’s
determine which type of head will be the thickest required and which will be the thinnest
allowed.
P = 100 psi
S = 17500 PSI
E = 0.85 for spot RT of Hemi-head joint to shell
E = 1.0 for seamless heads ( Ellipsoidal and Torispherical )
L = 48" for the inside spherical radius for the hemi-head
L = 96" for the inside crown radius of the torispherical head
D = 96" inside diameter of the ellipsoidal
t = ? Required wall thickness, inches
Internal pressure on formed head UG-32 57
Example
Given the above data find the required thickness of a seamless ellipsoidal head
PD
t=
2SE - 0.2 P
100 x 96 9600
t= = .2744 "
(2 x 17,500 x 1.0) - (0.2 x 100) 34980
Internal pressure on formed head UG-32 58
Example
Using the same data, calculate the required thickness of a hemispherical head
PL
t=
2SE - 0.2P
100 x 48 4800
t= = = 0.1614 "
( 2 x 17,500 x 0.85) − (0.2 x 100) 29730
Internal pressure on formed head UG-32 59
Example
Determine the required t of this tori-spherical head
0.885PL
t=
SE - 0.1P
Remember
So we have from thickest to thinnest, all things equal:
There have been several exams where the question was asked, “ Which is required to be
thickest” or “ Which can be the thinnest” Remember this.
Hydrostatic test UG-99 61
- A hydrostatic test based on a calculated pressure may be used by agreement between the user and the
manufacturer .
The hydrostatic test pressure at the top of the vessel shall be the minimum of the test pressures calculated by
multiplying the basis for calculated test pressure
- If the vessel is subjected to visible permanent distortion, the Inspector shall reserve the right to reject the
vessel.
Hydrostatic test UG-99 62
(The visual inspection of joints and connections for leaks at the test pressure divided by 1.3
may be waived provided:-
Metal temperature.
- It is recommended that the metal temperature during hydrostatic test be maintained at least 30°F
above the minimum design metal temperature, but need not exceed 120°F, to minimize the risk of
brittle fracture.
- API 510 has a different rule for this, it recommends that the temperature be 10°F above for 2 in.
(≤50mm) thickness and under and 30°F above for over 2 in. (>50mm).
Hydrostatic test UG-99 64
Metal temperature
- If the test temperature exceeds 120°F (48°C), it is recommended that inspection of the vessel required
by UG-99(g) above be delayed until the temperature is reduced to 120°F (48°C) or less.
- Caution: A small liquid relief valve set to 1-1/3 (1.33) times the test pressure is recommended for the
pressure test system, in case a vessel, while under test, is likely to be warmed up materially with
personnel absent.
Hydrostatic test UG-99 65
Static Head
- The inspector must be able to compensate for the pressure resulting from static head.
- All static head will be based upon a specific gravity of 1.0.
a) know the difference between vessel MAWP and vessel part MAWP (UG-98);
b) calculate total pressure (MAWP + static head) on any vessel part;
Hydrostatic test UG-99 66
Stest temperature
Ptest = 1.3 ( MAWP)
Sdesign temperature
UG-98(a) The maximum allowable working pressure for a vessel is the maximum pressure
permissible at the top of the vessel in its normal operating position at the designated
coincident temperature specified for that pressure.
Min. MAWP Calculated
Hydrostatic test UG-99 68
What would be the pressure at the bottom if an pressure of 235 psi were applied ?
235 235
psi psi
The hydrostatic head of water is equal to 0.433 psi per vertical foot
above the point where the pressure will measured. For example,
the hydrostatic head of water at a point in a vessel with 10 feet of
water above it is calculated by multiplying 10 x 0.433 psi.
Hemispherical Head
For this example, we will use a hemispherical head that has an inside diameter of 48 inches
which means it has a radius of 24 inches. The radius is the depth of the hemispherical head
Hydrostatic test UG-99 71
- Wherever possible, pneumatic test should be avoided because the expansive nature of a
gas could maintain stress on a leak and cause it to grow, thus creating the potential for an
explosive failure during the test.
- Specifically, UG-100(a) only gives two possible reasons for performing a pneumatic test in
lieu of hydrostatic testing for vessels:
* UG-100(a)(1) that are so designed and/or supported that they cannot safely be filled with
water;
* UG-100(a)(2) not readily dried, that are to be used in services where traces of the testing
liquid cannot be tolerated and the parts of which have, where possible, been previously tested
by hydrostatic pressure to the pressure required in UG-99.
Pneumatic test UG-100 74
Ug-102 (c)
- All gages shall be calibrated against a
standard deadweight tester or a calibrated
master gage.
- The vessel portion outside of the furnace must be shielded prevent any harmful temperature
gradient.
UCS-56 Requirements for Post-weld Heat Treatment 81
UCS-56 (a)
UCS-56 (d)
- The temperature of the furnace shall not exceed 800°F (427°C) at the time the vessel or part
is placed in it.
- Above 800°F (427°C), the rate of heating shall be not more than 400°F/hr (222°C/ hr) divided
by the maximum metal thickness of the shell or head plate in inches, but in no case more than
400°F/hr (222°C/hr).
Max. heating
- The rates of heating and rate = 400 F / t
cooling need not be less
than 100°F/hr (56°C).
Min. heating
T = 0.5 inch rate = 100/hr F
Max. = 400 / 0.5 = 800
>> 400 F
UCS-56 Requirements for Post-weld Heat Treatment 87
During the holding period, there shall not be a greater difference than 150°F (83°C) between
the highest and lowest temperature throughout the portion of the vessel being heated,
except where the range is further limited in Table UCS‐56.
UCS-56 (d)(5)
Above 800°F (425°C), cooling shall be done in a closed furnace or cooling chamber at a rate
not greater than 500°F/hr (280°C/hr) divided by the maximum metal thickness of the shell or
head plate in inches, but in no case more than 500°F/hr (280°C/hr).
- From 800°F (425°C) the vessel may be cooled in still air.
- The rates of heating and cooling need not be less than 100°F/hr (56°C). However, in all cases
consideration of closed chambers and complex structures may indicate reduced rates of
heating and cooling to avoid structural damage due to excessive thermal gradients.
UCS-56 Requirements for Post-weld Heat Treatment 90
The rates of heating and cooling need not be less than 100°F/hr (56°C).
UCS-56 Requirements for Post-weld Heat Treatment 91
UCS-56 Requirements for Post-weld Heat Treatment 92
Alternative Post-weld Heat Treatment Requirements For Carbon and Low Alloy Steels (Table
UCS-S6.1)
Table UCS-56.1 presents alternative lower temperatures with corresponding longer times at
temperature (see Table UCS-56.1 Note (1)).
Post-weld heat treatment temperatures of 150°F or 200°F lower than permitted in Tables
UCS-56 are only permitted for P-No. 1 Gr. Nos. 1 and 2 materials (see Table UCS-56.1 Note
(2)).
UCS-56 Requirements for Post-weld Heat Treatment 93
Design Temperature UG-20 94
Impact testing per UG-84 is not mandatory for pressure vessel materials that satisfy all of the following:
1. Material is limited to P-No.1 Gr. No.1 or 2 and the thicknesses don't exceed the following:
(a) 1/2 in. (13 mm) for materials listed in Curve A of Fig. UCS-66;
(b) 1 in (25 mm) for materials from Curve B, C or D of Fig. UCS-66;
2. The completed vessel shall be hydrostatically tested per UG-99(b) or (c) or 27-4.
3. Design temperature is no warmer than 650°F (345°C) or colder than -20°F (−29°C).
4. The thermal or mechanical shock loadings are not controlling design. (See UG-22.)
1. Material is limited to P-
No.1 Gr. No.1 or 2 and the
thicknesses don't exceed the
following:
(a) 1/2 in. for materials listed
in Curve A of Fig. UCS-66;
(b) 1 in for materials from
Curve B, C or D of Fig. UCS-66;
When coincident
ratio are defined :-
Charpy Impact Tests UG-84 98
UG-84(a) General.
Charpy impact tests in accordance with the provisions of this paragraph shall be made on weldments
and all materials for shells, heads, nozzles, for which impact tests are required by the rules in
Subsection C.
UG-84(b)(1) Impact test procedures and apparatus shall conform to the applicable paragraphs of SA-
370.
SA-370 is a document that describes in great detail the actual procedure for breaking specimens.
- The standard (10 mm ×10 mm) specimens, when obtainable, shall be used for nominal thicknesses
of 0.438 in. (11.13 mm) or greater, except as otherwise permitted…
- Subsize (10 mm × 6.7 mm) specimens may be used in lieu of full-size specimens for materials that
normally have absorbed energy in excess of 75 ft‐lbf (100 J) minimum for each specimen and the
lateral expansion in mils (mm) shall be reported
Charpy Impact Tests UG-84 100
When the average value of the three specimens ≥ the minimum value permitted for a single specimen
(2/3 specified average) and.
- the value for more than one specimen is below the required average value, or
- when the value for one specimen is below the minimum value permitted for a single specimen,.
a retest of three additional specimens shall be made.
The value for each of these retest specimens shall ≥ the required average value.
Charpy Impact Tests UG-84 105
A high energy
value for a notch
toughness test
indicates The
material is ductile
A low energy
value for a notch
toughness test
indicates The
material is brittle
Charpy Impact Tests UG-84 106
Step 1. Determine appropriate Curve for the material, including the Notes in Fig. UCS-66.
Step 2. Determine the governing thickness (tg) from UCS-66(a)(1) through (a)(5).
The governing thickness to be used in Fig. UCS-66 is determined from paragraph UCS-66(a)(1) through
(a)(5) based upon if the component under consideration is a welded part, casting, flat non-welded part, or
a dished non-welded part.
Step 3. Using the Curve and tg, determine the MDMT from Tabular Values in Fig. UCS-66.
LOW TEMPERATURE OPERATION 109
Step 5. UCS-68(b)(2) For MDMT colder than −55°F (−48°C), impact testing is required for all materials
except as allowed in (3) below and in UCS-68(c).
UW-33 Welding Alignment Tolerance 110
UW‐33(a) Alignment of sections at edges to be butt welded shall be such that the maximum
offset is not greater than the applicable amount for the welded joint category (see UW‐3)
under consideration, as listed in Table UW‐33. The section thickness t is the nominal
thickness of the thinner section at the joint.
Thank You For Your Attention
Inspection Academy is Global Learning Community That Can Provide eLearning courses combined with
online testing tools will help you train your personnel anytime and anywhere while providing real-time
measurable results.