0% found this document useful (0 votes)
11 views1 page

Const - C1B - 31st May 2012

Uploaded by

gihan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views1 page

Const - C1B - 31st May 2012

Uploaded by

gihan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

NORTHERN ROAD REHABILITATION PROJECT (NRRP)

REHABILITATION AND IMPROVEMENT OF 90 KM LENGTH OF A009 ROAD FROM 230KM POST TO JAFFNA
CONTRACT PACKAGE NO. RDA/NRRP/CGF/C1B
EMPLOYER : Road Development Authority (RDA)
ENGINEER : Central Engineering Consultancy Bureau (CECB)
CONTRACTOR : China National Aero Technology International Engineering Corporation (CATIC)
PROGRESS REVIEW AS AT 31 st May 2012

for completion / up
as at 31st May 2012

as at 31st May 2012


Expected progress
Scheduled Date of

Scheduled Date of

Physical Progress
Duration / (days)

No of days taken
Commencement

Lagging against

Leading against
Commencement
Actual Date of

Actual Date of
Completion

Completion

No of Days

No of Days
Scheduled

the Work

the Work

Remarks
Se. No.

to date

Programme

Programme
Activity

1 Section 1 (Ch.257+000 - 277+000) 02/05/2011 20/08/2013 670 71% 22/02/2011 - 72% 368 - 7
1.1 Site Clearing 21/05/2011 29/06/2012 336 96% 22/02/2011 14/05/2012 100% 353 - 40
1.1.1 Cleaning and grubbing 21/05/2011 14/05/2012 287 100% 22/02/2011 24/02/2012 100% 296 - 58
1.1.2 Removal of Structures and obstructions 01/07/2011 29/06/2012 292 92% 20/04/2011 14/05/2012 100% 321 - 40
1.2 Earth Works (Embankment Construction) 14/06/2011 01/10/2012 383 77% 22/02/2011 14/05/2012 100% 353 - 93
1.3 Culvert and Miscellaneous Construction 02/05/2011 28/02/2012 248 100% 24/03/2011 09/11/2011 100% 201 - 90
1.5 Drainage Construction 14/06/2011 31/12/2012 457 63% 24/08/2011 09/11/2011 100% 282 - 334
1.6 Road Pavement Construction 14/06/2011 26/01/2013 478 60% 21/04/2011 - 79% 326 - 91
1.6.1 Edge Widening and Sub base Filling 14/06/2011 22/11/2012 426 66% 21/04/2011 14/05/2012 100% 320 - 185
1.6.2 ABC Overlay 15/07/2011 06/12/2012 412 62% 26/06/2011 - 85% 272 - 95
1.6.3 Prime Coat 15/07/2011 24/12/2012 427 60% 07/07/2011 - 85% 263 - 107
1.6.4 Binder / Wearing Course 15/08/2011 16/01/2013 419 55% 18/07/2011 - 85% 255 - 126
1.6.5 Earth Shoulder Construction 01/07/2011 16/01/2013 419 58% 03/07/2011 - 40% 266 75.42 -
2 Section 2 (Ch.277+000 - 320+000) 23/02/2011 03/07/2013 681 68% 22/02/2011 - 75% 368 - 47.67
2.1 Site Clearing 02/05/2011 09/02/2012 233 100% 22/02/2011 - 71% 368 67.57 -
2.1.1 Cleaning and grubbing 02/05/2011 09/02/2012 233 100% 22/02/2011 20/03/2012 100% 316 - 33
2.1.2 Removal of Structures and obstructions 02/05/2011 09/02/2012 233 100% 20/04/2011 - 42% 329 135 -
2.2 Earth Works (Embankment Construction) 10/03/2011 09/11/2012 487 73% 22/02/2011 - 71% 370 9.74 -
2.3 Culvert and Miscellaneous Construction 02/05/2011 04/10/2012 421 80% 24/03/2011 - 90% 345 - 42.1

for completion / up
as at 31st May 2012

as at 31st May 2012


Expected progress
Scheduled Date of

Scheduled Date of

Physical Progress
Duration / (days)

No of days taken
Commencement

Lagging against

Leading against
Commencement
Actual Date of

Actual Date of
Completion

Completion

No of Days

No of Days
Scheduled

the Work

the Work

Remarks
Se. No.

to date

Programme

Programme
Activity

2.4 Bridge Construction 01/08/2011 12/12/2012 403 76% - 26/03/2012 100% - - -


2.5 Drainage Construction 02/06/2011 24/09/2012 387 77% - - 70% 294 27 -
2.6 Road Pavement Construction 14/06/2011 29/04/2013 544 54% 21/04/2011 - 49% 328 27 -
2.6.1 Edge Widening and Sub base Filling 14/06/2011 08/12/2012 447 63% 21/04/2011 - 71% 328 - 36
2.6.2 ABC Overlay 15/07/2011 22/01/2013 449 57% 26/06/2011 - 48% 274 40 -
2.6.3 Prime Coat 18/07/2011 26/02/2013 474 54% 07/07/2011 - 48% 265 28 -
2.6.4 Binder / Wearing Course 15/08/2011 02/04/2013 480 48% 18/07/2011 - 73% 257 - 120
2.6.5 Earth Shoulder Construction 01/07/2011 29/04/2013 530 51% 03/07/2011 - 4% 268 249 -
3 Section 3 (Ch.230+000 - 257+000) 22/02/2011 20/04/2013 623 64% - - 89% 370 - 156
3.1 Site Clearing 14/06/2011 15/10/2012 394 72% - 28/05/2012 100% - - 116
3.1.1 Cleaning and grubbing 14/06/2011 27/09/2012 380 74% - 28/05/2012 100% - - 102
3.1.2 Removal of Structures and obstructions 01/07/2011 15/10/2012 380 71% - 28/05/2012 100% - - 116
3.2 Earth Works (Embankment Construction) 27/06/2011 15/12/2012 435 59% - 28/05/2012 100% - - 167
3.3 Culvert and Miscellaneous Construction 02/06/2011 30/05/2012 291 100% - - 93% 294 20 -
3.4 Bridge Construction 23/02/2011 22/06/2012 385 98% - - 100% 369 - -
3.5 Drainage Construction 07/11/2011 03/08/2012 214 77% - - 75% 163 4 -
3.6 Road Pavement Construction 10/06/2011 13/03/2013 516 50% - - 66% 287 - 83
3.6.1 Edge Widening and Sub base Filling 10/06/2011 15/12/2012 448 64% - 28/05/2012 100% - - 167
3.6.2 ABC Overlay 18/07/2011 23/01/2013 448 57% - - 74% 257 - 76
3.6.3 Prime Coat 25/07/2011 08/02/2013 454 55% - - 74% 251 - 86
3.6.4 Binder / Wearing Course 08/09/2011 14/02/2013 454 50% - - 67% 187 - 77
3.6.5 Earth Shoulder Construction 21/05/2012 13/03/2013 241 4% - - 15% - - 27
Overall Physical Progress 22/02/2011 20/08/2013 721 32.10% 22/02/2011 - 61.19% 368 - 210