Const - C1B - 31st May 2012
Const - C1B - 31st May 2012
REHABILITATION AND IMPROVEMENT OF 90 KM LENGTH OF A009 ROAD FROM 230KM POST TO JAFFNA
CONTRACT PACKAGE NO. RDA/NRRP/CGF/C1B
EMPLOYER : Road Development Authority (RDA)
ENGINEER : Central Engineering Consultancy Bureau (CECB)
CONTRACTOR : China National Aero Technology International Engineering Corporation (CATIC)
PROGRESS REVIEW AS AT 31 st May 2012
for completion / up
as at 31st May 2012
Scheduled Date of
Physical Progress
Duration / (days)
No of days taken
Commencement
Lagging against
Leading against
Commencement
Actual Date of
Actual Date of
Completion
Completion
No of Days
No of Days
Scheduled
the Work
the Work
Remarks
Se. No.
to date
Programme
Programme
Activity
1 Section 1 (Ch.257+000 - 277+000) 02/05/2011 20/08/2013 670 71% 22/02/2011 - 72% 368 - 7
1.1 Site Clearing 21/05/2011 29/06/2012 336 96% 22/02/2011 14/05/2012 100% 353 - 40
1.1.1 Cleaning and grubbing 21/05/2011 14/05/2012 287 100% 22/02/2011 24/02/2012 100% 296 - 58
1.1.2 Removal of Structures and obstructions 01/07/2011 29/06/2012 292 92% 20/04/2011 14/05/2012 100% 321 - 40
1.2 Earth Works (Embankment Construction) 14/06/2011 01/10/2012 383 77% 22/02/2011 14/05/2012 100% 353 - 93
1.3 Culvert and Miscellaneous Construction 02/05/2011 28/02/2012 248 100% 24/03/2011 09/11/2011 100% 201 - 90
1.5 Drainage Construction 14/06/2011 31/12/2012 457 63% 24/08/2011 09/11/2011 100% 282 - 334
1.6 Road Pavement Construction 14/06/2011 26/01/2013 478 60% 21/04/2011 - 79% 326 - 91
1.6.1 Edge Widening and Sub base Filling 14/06/2011 22/11/2012 426 66% 21/04/2011 14/05/2012 100% 320 - 185
1.6.2 ABC Overlay 15/07/2011 06/12/2012 412 62% 26/06/2011 - 85% 272 - 95
1.6.3 Prime Coat 15/07/2011 24/12/2012 427 60% 07/07/2011 - 85% 263 - 107
1.6.4 Binder / Wearing Course 15/08/2011 16/01/2013 419 55% 18/07/2011 - 85% 255 - 126
1.6.5 Earth Shoulder Construction 01/07/2011 16/01/2013 419 58% 03/07/2011 - 40% 266 75.42 -
2 Section 2 (Ch.277+000 - 320+000) 23/02/2011 03/07/2013 681 68% 22/02/2011 - 75% 368 - 47.67
2.1 Site Clearing 02/05/2011 09/02/2012 233 100% 22/02/2011 - 71% 368 67.57 -
2.1.1 Cleaning and grubbing 02/05/2011 09/02/2012 233 100% 22/02/2011 20/03/2012 100% 316 - 33
2.1.2 Removal of Structures and obstructions 02/05/2011 09/02/2012 233 100% 20/04/2011 - 42% 329 135 -
2.2 Earth Works (Embankment Construction) 10/03/2011 09/11/2012 487 73% 22/02/2011 - 71% 370 9.74 -
2.3 Culvert and Miscellaneous Construction 02/05/2011 04/10/2012 421 80% 24/03/2011 - 90% 345 - 42.1
for completion / up
as at 31st May 2012
Scheduled Date of
Physical Progress
Duration / (days)
No of days taken
Commencement
Lagging against
Leading against
Commencement
Actual Date of
Actual Date of
Completion
Completion
No of Days
No of Days
Scheduled
the Work
the Work
Remarks
Se. No.
to date
Programme
Programme
Activity