Nit 800kwp Solar
Nit 800kwp Solar
C.P.W.D.
NIT for above work approved for Rs. 6,59,81,582/- (Rupees Six Crore Fifty Nine Lakh Eighty
One Thousand Five Hundred Eighty Two Only) and containing page 01 to 95 excluding cover
page.
BID DOCUMENT
PART-A
GOVERNMENT OF INDIA
CENTRAL PUBLIC WORKS
DEPARTMENT
स मेवजयते
The Executive Engineer cum Senior Manager (E), MNIT Electrical Project Division, CPWD, Jaipur
on behalf of the President of India invites online Percentage Rate E-Tender in two bid system from
CPWD Enlisted Contractor of appropriate class in Buildings & Roads (erstwhile
composite/Building/Infrastructure) category/ Specialized Agency/ Manufacturer/OEM for
the following work:
Name of Work: Supply, installation, testing and commissioning of 800 KWP Solar Photo Voltaic
Generation System at MNIT, Jaipur.
Estimated Cost: Rs. 6,59,81,582/-
Earnest Money: Rs. 13,19,632/-
Time Allowed: 04 Months
The tender forms and other details can be obtained from the website https://etender.cpwd.gov.in
or www.cpwd.gov.in
25.04.2025 at 03: 00 PM
25.04.2025 at 03: 30 PM
Rs. 6,59,81,582/-
Technical bid.
Rs. 13,19,632/-
MNIT, Jaipur.
04 Months
1
1. Eligibility Criteria:
1.2.1 The Specialized Agency, who fulfills the following requirements, shall be eligible to apply.
Joint Ventures are not accepted.
1.2.2 Should have satisfactorily completed the works as mentioned below during the last seven years
ending on last day of previous month of last date of submission of tenders.
Similar work shall mean works of “Supply, installation, testing and commissioning of Solar
Photo Voltaic Generation system.”
Note:- Costing for similar works shall be calculated for component of Solar Photo Voltaic
Generation System only.
The specialized firms shall satisfy the following eligibility criteria: Experience of having successfully
completed works during last seven years ending on last day of previous month of last date of
submission of tenders.
Three similar works each of value not less than 40% of the estimated cost put to tender (Rs.
2,63,92,632/-).
OR
Two similar works each of value not less than 60% of the estimated cost put to tender (Rs.
3,95,88,949/-).
OR
One similar work of value not less than 80% of the estimated cost put to tender (Rs.
5,27,85,265/-).
(a) Should have had Average Annual Financial Turnover of Rs. 1,97,94,474/-
on similar works during the last three years ending 31st March 2024(Scanned copy of
Certificate from CA with Unique Document Identification Number (UDIN) to be
uploaded).The value of annual turnover figures shall be brought to the current value by
enhancing the actual turnover figures at simple rate of 7% per annum..
1.2.4 Should have bidding capacity equal to or more than the estimated cost of the work put to tender.
The bidding capacity shall be worked out by the following formula:
Bidding Capacity = {[AxNx1.5]-B}
Where,
A = Maximum turnover in similar works executed in any one year during the last seven years taking
into account the completed as well as works in progress. The value of completed works shall be
brought to current costing level by enhancing at a simple rate of 7% per annum.
N = Number of years prescribed for completion of work for which bids have been invited.
B = Value of existing commitments of ongoing works during the period of execution of work for
which bids have been invited.
1.3.1 The Manufacturer/OEM shall submit its OEM certificate/ Proof of PV module capacity of
540Wp or above.
Additional Points:
1. The intending bidder must read the terms and conditions of CPWD-6 carefully. He should
only submit his bid if he consider himself eligible and he is in possession of all the documents
required.
2. The intending bidders are required to update their profile in CPWD e-tender portal and to
upload their bids well in advance of last date of submission of tender. Any issue related to
updating profile / uploading tender can be resolved through the concerned Executive
Engineer/ Assistant Engineer (Phone No. 0141-2945387 E-Mail ID [email protected]) or
ERP help line no. 18001803286 or e-mail Id [email protected]. The e-
tendering bidders are also advised not to wait to raise any issues till the last date of submission
of bid in their own interest.
3. Information and Instructions for bidders posted on website shall form part of bid document.
4. The bid document consisting of plans, specifications, the schedule of quantities of various
types of items to be executed and the set of terms and conditions of the contract to be
complied with and other necessary documents can be seen and downloaded from website
www.etender.cpwd.gov.in and www.eprocure.gov.in free of cost.
5. But the bid can only be submitted after depositing of original EMD either in the office of
Executive Engineer inviting bids or division office of any Executive Engineer, CPWD within
the period of bid submission, and uploading the mandatory scanned documents such as
Demand Draft or Pay order or Banker`s Cheque or Deposit at call Receipt or Fixed Deposit
Receipts and Bank Guarantee of any Scheduled Bank towards EMD in favour of Executive
Engineer as mentioned in NIT, receipt for deposition of original EMD to division office of
any Executive Engineer, (including NIT issuing EE) C.P.W.D and other documents NIT
issuing EE) as specified.
7. Stamp duty tax applicable as per Govt. of Rajasthan, Finance Department (Tax Division),
Jaipur under GCC Clause 34 & 38.
8. The intending bidder must have valid class-III digital signature to submit the bid.
9. On opening date, bidders can login and see the bid opening process. After opening of bids he
will receive the competitor bid sheets.
10. Bidder can upload documents in the form of JPG format and PDF format.
11. Bidder must ensure to quote rate of each item. The column meant for quoting rate in figures
appears in pink colour and the moment rate is entered, it turns sky blue. In addition to this,
while selecting any of the cells a warning appears that if any cell is left blank the same shall
be treated as “0”.
Therefore, if any cell is left blank and no rate is quoted by the bidder, rate of such item shall
be treated as “0” (ZERO).
12. Pre Bid conference shall be held with the intending bidder in the office of SE & PD,
MNITPC, CPWD, Jaipur - 302017 at 11.04.2025 at 11:00 AM to clear doubts of intending
bidders if any. Bidders should send all their queries by email on [email protected] latest by
11.04.2025 at 11:00 AM.
13. The tenderer should not have been blacklisted or penalized by any Central Government
/ State Government Offices/PSUs. A self-certificate / declaration in this effect is required
to be scanned and uploaded while participation in tendering process as per form G.
14. List of Documents to be scanned and uploaded within the period of bid submission:-
(i) Treasury Challan /Demand Draft / Pay order or Banker`s Cheque / Deposit at Call Receipt/
FDR/ Bank Guarantee of any scheduled Bank against EMD in the favour of Executive
Engineer, MNIT Project Division, CPWD, Jaipur and hard copy of the same EMD have to
be deposited physically in Division Office of any Executive Engineer, CPWD, inviting bids
or division office of Executive Engineer, CPWD within the period of Bid submission. The
same should also be Scanned and Uploaded by the intending bidders. (For CPWD enlisted
Contractor/Specialized Agency/Manufacturer/OEM)
(ii) Copy of receipt for deposition of original EMD issued from division office of any Executive
Engineer, CPWD (including NIT issuing EE), CPWD. (For CPWD enlisted Contractor/
Specialized Agency/Manufacturer/OEM)
(iii) Copy of enlistment order in appropriate class and category issued by CPWD. (For
CPWD enlisted Contractor)
Or
(iv) Net worth Certificate as per FORM “B” (For Specialized Agency)
Or
(v) Certificate of Financial Turnover from Charted Accountant (Form ‘A’) (For Specialized
Agency)
(vi) Details of Eligible Similar nature of works completed and ongoing during the last 7 years as
mentioned in Form ‘C’ & ‘C-1’ (For Specialized Agency)
(viii) Latest date Affidavit for “Proforma of Affidavit For Non - Black Listing” (Form G). (For
CPWD enlisted Contractor/ Specialized Agency/ Manufacturer/OEM)
(ix) Certificate of Registration for GST and acknowledgement of filled return. (For CPWD
enlisted Contractor/ Specialized Agency/ Manufacturer/OEM)
Or
an undertaking that:
"If work is awarded to me, I/we shall obtain GST registration certificate, as applicable,
within one month from the date of receipt of award letter or before release of any payment by
CPWD, whichever is earlier, failing which I/we shall be responsible for any delay in payments
which will be due towards me/us on account of the work executed and/or for any action taken
by CPWD or GST department in this regard".
(x) Bidder’s Contact Address, Telephone & Email id in form of letter of transmittal /submission of
bid as per Annexure-1. (For CPWD enlisted Contractor/ Specialized Agency/
Manufacturer/OEM)
(xi) Bidding Capacity along with list of works in hand in form ‘C-3’. (For CPWD enlisted
Contractor/ Specialized Agency)
(xii) Details of structure & organization (Form ‘E’) (For specialized Agency)
(xiii) Undertaking on structural stability and soundness as per prescribed format in Form ‘F’. (For
CPWD enlisted Contractor/ Specialized Agency/ Manufacturer/OEM)
(xiv) Any other Documents, if have. (For CPWD enlisted Contractor/ Specialized Agency/
Manufacturer/OEM)
1 Name of work : Supply, installation, testing and commissioning of 800 KWP Solar
Photo Voltaic Generation System at MNIT, Jaipur.
2 NIT No : 10/2025/SEcumPD/MNITPC/Jaipur
2 Form of EMD :
3 Amount of Earnest :
Money Deposit
4 Date of submission of :
EMD
To
The Executive Engineer cum Senior Manager (Elect.)
MNITPED, CPWD, Jaipur.
Subject : Supply, installation, testing and commissioning of 800 KWP Solar Photo Voltaic
Generation System at MNIT, Jaipur.
Having examined details given in Tender Notice and bid document for the above work, I/we hereby
submit the bid with requisite information & documents.
1. I/We hereby certify that all the information and documents submitted with the bid are true and
correct.
2. I / We have furnished all information and details necessary for eligibility and have no further
pertinent information to supply.
3. I/We also authorize Executive Engineer cum Senior Manager (E), MNIT Project Electrical
Division, CPWD, Jaipur to approach individuals, CPWDs, firms and corporation to verify our
competence and general reputation.
4. Our Current Contact address, email and telephone number details are as under:
Name of Bidder/Authorized Person of Bidder:
10
FINANCIAL INFORMATION
I. Financial Analysis – Details to be furnished for the last five years duly certified by the
Chartered Accountant, as submitted by the applicant to the Income Tax Department.
Amount in Lacs
S. Description Financial Year
No.
2019-20 2020-21 2021-22 2022-23 2023-24
II. Financial arrangements proposed for carrying out the proposed work.
11
It is to certify that as per the audited balance sheet and profit & loss account during the financial year
......................, the Net Worth of M/s. ................................................................... (Name & Registered
Address of individual / firms / company), as on ............................. (the relevant date) is Rs.
................................. after considering all liabilities. It is further certified that the Net Worth of the
company has not eroded by more than 30% in the last three years ending on (the relevant date.
NOTE:
Net Worth Certificate should be on letter head of the Chartered Accountant, addressed to tendering
authority. i.e. Executive Engineer cum Senior Manager (E), MNITPED, CPWD, Jaipur
12
This is to certify that to the best of our knowledge and information that M/s./
Sh…………....................
................................................... having marginally noted address, …….as a Customer of our bank
are/ is respectable and can be treated as good for any engagement upto a limit of
Rs…………………. (Rupees… .......................................................................... )
This certificate is issued without any guarantee or responsibility on the bank or any of the
officers.
NOTE
1. Banker’s Certificates should be on letter head of the Bank, addressed to tendering authority.
2. In case of Partnership firm, certificate should include names of all partners as recorded with
the Bank.
13
2
Name of work / Project and Location
3
Owner or sponsoring organization
4
Cost of work in lacs of rupees
5
contract
6
Stipulated date of completion
LAST DATE OF SUBMISSION OF BIDS.
7
Actual Date of Completion
14
8
in progress with details *
9 Name and address / telephone
AE(C)/(E)
Number of officer to whom reference
may be made.
EEcumSM(C)/(E)
Private
DETAILS OF ELIGIBLE SIMILAR NATURE OF WORKS COMPLETED DURING THE
LAST SEVEN YEARS ENDING LAST DAY OF PREVIOUS MONTH TO THE MONTH OF
2
Name of work / Project and Location
3
Owner or sponsoring organization
4
Cost of work in lacs of rupees
5
contract
6
Stipulated date of completion
15
thereof
AE(C)/(E)
Number of officer to whom reference
may be made.
Whether the work was done on back
DETAILS OF ELIGIBLE SIMILAR NATURE OF ONGOING WORKS
10
EEcumSM(C)/(E)
Private
Certified that the above list of works is complete and no work has been left out and that the
Remarks if any
column 8 / 100
may be made.
contract
S. No.
work
1 2 3 4 5 6 7 8 9 10 11
Total (B) =
Maximum turnover in last seven years =
Updated value of turnover (A) =
No. of Years (N) =
Bidding Capacity =
I certify that all the awarded and ongoing works have been included in the above list.
16
Dated:
Owner/sponsoring organizations signature with date and seal (Project Manager/ Executive Engineer
or Equivalent)
17
Name of
Work:- Date of
Inspection:-
Date of submission of report:-
A. General Observation & Operational Aspects Yes/ No
1. Availability of approval from local bodies in case of Construction
of Private Buildings
2. Availability of approved Structural drawings
3. Observation on seepage/ leakage in the Building
4. Whether Line & level Maintained
5. In case of basement, observation on seepage, if any
6. Any Structural defects / distress observed. If yes give details
7. Whether safety measures adopted at site as per CPWD Safety Code and or
govt. guidelines are adequate or not
8. Whether the Welfare facilities provided to labour as per Clause 19 H of GCC
for CPWD Works/and or govt. guidelines are adequate or not
9. Whether AHU getting automatically switched off and fire damps closed in
case of fire signal?
10. Whether thimbles used for termination of wires in DBs, EBDs & Panels?
B. Quality of Work Marks Assessed
1. Quality of plaster/ finishing
2. Quality of R C C / C C Work
3. Quality of Flooring
4. Quality of Wood Work
5. Quality of Steel Work / Aluminium Work
6. Quality of Plumbing and Sanitary Installation
7. Quality of Workmanship
8. Quality of Waterproofing
9. If cladding done, observation on efficiency/ quality of cladding /
Brick work
10. Quality of internal electrification work
11. Quality of DBs, EBDs & Panels
12. Quality of E&M equipments, panels & feeder pillar
13. Quality of fire alarm system/ fire fighting system
15. Quality of Sub-station based on complete live diagram, capacitor panel, power
factor, insulating Mat, cleanliness, cable termination, earthing pits, earthing of
transformer / DG sets
16. Any Other aspect (To be elaborated )
18
Note:-
1. All the above parameters may be considered for assessing the overall quality of work executed
by the contractor. Each attribute shall be assessed on maximum marks of 10 under B above.
2. In case, any attribute is not applicable, the same may not be included in assessment and
mentioned are not applicable (N/A)
3. The works as assessed above shall be converted on a scale of 25/15 marks for
completed/ongoing works respectively.
19
5. Names and titles of Directors & Officers with designation to be concerned with this work.
6. Designation of individuals authorized to act for the organization
7. Has the bidder, or any constituent partner in case of partnership firm, limited company/Joint
Venture, ever been convicted by the court of Law? If so, give details
8. In which field of Civil Engineering construction the bidder has specialization and interest?
9. Any other information considered necessary but not included above.
Signature of Bidder(s)
20
Attributes Evaluation
(a) Financial strength (20 marks)
(i) Average annual turnover - 16 marks (i) 60% marks for minimum eligibility
(ii) Banker’s Certificate - 4 marks criteria
(ii) 100% marks for twice the minimum
eligibility criteria or more
In between (i) & (ii) – on pro-rata basis
(b) Experience in similar class of works - (20 (i) 60% marks for minimum eligibility
marks) criteria
(ii) 100% marks for twice the minimum
eligibility criteria or more
In between (i) & (ii) – on pro-rata basis
(c) Performance on works (20 marks)
(time over run)
Parameter Calculation For Score Maximum Marks
points
If TOR = 1.00 2.00 3.00 >3.50 20
(i) Without levy of compensation 20 15 10 10
(ii) With levy of compensation 20 5 0 -5
(iii) Levy of compensation not decided 20 10 0 0
TOR = AT/ST, where AT= Actual Time; ST= Stipulated Time in the Agreement plus (+)
justified period of Extension of Time
Note: Marks for value in between the stages indicated above is to be determined by straight line
variation basis.
(d) Performance of works (Quality) as per Assessment In Form D-1. (40 marks)
Completed works Ongoing works (Total marks assessed)
(max. 25 marks) (max. 15 marks)
21
I/we undertake and confirm that any building / infrastructure constructed by our firm /partnership
firm/ company has not suffered any failure, making it unfit for intended use, either due to structural
design and defects or due to use of sub-standard materials or execution of sub-standard work, poor
workmanship or any other reason during the last 25 (twenty five) years.
I/we, further, undertake that if such information comes to the notice of CPWD, then Engineer-
in- Charge shall be free to terminate the bid/agreement and to forfeit the entire amount of earnest
money deposit, performance guarantee and security deposits.
I/we, also undertake that in addition to above, the Engineer-in-Charge shall be free to debar us
forever from tendering in CPWD.
The decision of Engineer-in-Charge or any higher authority shall be final and binding.
Note: Affidavit to be furnished on a ‘Non-judicial’ stamp paper of Rs. 200/-(scanned copy of the
notarized affidavit to be uploaded at the time of submission of bid).
22
I/we undertake and confirm that our firm/partnership firm has not been blacklisted by any
state/Central Departments/PSUs/Autonomous bodies during the last 7 years of its operations.
Further that, if such information comes to the notice of the department, then I/we shall be debarred
for bidding in CPWD in future forever. Also, if such information comes to the notice of department
on any day before date of start of work, the Engineer-in-charge shall be free to cancel the
agreement and to forfeit the entire amount of Earnest Money Deposit/Performance Guarantee
(Scanned copy of this notarized affidavit to be uploaded at the time of submission of bid)
23
The Executive Engineer cum Senior Manager (E), MNIT Electrical Project Division, CPWD, Jaipur
on behalf of the President of India invites online Percentage Rate E-Tenders in two bid system for
the following work: “Supply, installation, testing and commissioning of 800 KWP Solar Photo
Voltaic Generation System at MNIT, Jaipur.”
1. The enlistment of the Contractor should be valid on the last date of submission of tenders. In
case the last date of submission of tender is extended, the enlistment of Contractor should be
valid on the original date of submission of tenders. The work is estimated to cost Rs.
6,59,81,582/-. This estimate, however, is given merely as a rough guide.
2. The time allowed for carrying out the work will be 04 Months from the date of start as
defined in schedule ‘F’ or from the first date of handing over of the site, whichever is later, in
accordance with the phasing, if any, indicated in the bid documents.
4. The bid document consisting of plans, specifications, the schedule of quantities of various
types of items to be executed and the set of terms and conditions of the contract to be
complied with and other necessary documents except Standard General Conditions of
Contract Form can be seen from website www.etender.cpwd.gov.in free of cost.
5. After submission of the bid the Bidder can re-submit revised bid any number of times but
before last time and date of submission of bid as notified.
6. White submitting the revised bid, Bidder can revise the rate of one or more item(s) any
number of times (he need not re-enter rate of all the items) but before last time and date of
submission of bid as notified.
7. When bids are invited in two stage system and if it is desired to submit revised financial bid
then it shall be mandatory to submit revised financial bid. If not submitted then the bid
submitted earlier shall become invalid.
8. Earnest Money in the form of Treasury Challan or Demand Draft or Pay order or Banker`s
Cheque or Deposit at Call Receipt or Fixed Deposit Receipt (drawn in favour of Executive
Engineer, MNIT Project Division, CPWD, Jaipur shall be scanned and uploaded to the e-
tendering website within the period of bid submission. The Original EMD should be deposited
either in the office of Executive Engineer inviting bids or division office of any Executive
Engineer inviting bids or division office of any Executive Engineer, CPWD within the Period
of bid submission. The EMD receiving Executive Engineer (including NIT issuing EE/AE)
shall issue a receipt of deposition of earnest money deposit to the bidder in a prescribed
format (enclosed) uploaded by tender inviting Executive Engineer in the NIT.
24
9. A part of earnest money is acceptable in the form of bank guarantee also. In such case,
minimum 50% of earnest money or Rs. 20 lacs, whichever is less, shall have to be deposited
in shape prescribed above, and balance may be deposited in shape of Bank Guarantee of any
scheduled bank having validity for six months or more from the last date of receipt of bids
which is to be scanned and uploaded by the intending bidders.
Copy of documents as specified in the press notice shall be scanned and uploaded to the e-
tendering website within the period of bid submission. However, certified copy of all the
scanned and uploaded documents as specified in press notice shall have to be submitted by the
lowest bidder only within a week Physical EMD of the scanned copy of EMD uploaded shall
must have to be deposited in Division Office.
Online bids documents submitted by intending bidders shall be opened only of those bidders,
whose original EMD deposited with any division of CPWD and other Documents scanned and
uploaded are found in order.
The bid submitted shall become invalid and e-Tender processing fee shall not be refunded if:
(ii) The bidders do not upload all the documents (including GST registration) as stipulated
in the bid documents including declaration of EMD.
(iii) If any discrepancy is noticed between the documents as uploaded at the time of
submission of bid and hard copies as submitted physically by the lowest tenderer in the
office of tender opening authority.
The Bidder whose bid is accepted, will be required to furnish performance guarantee
of 5% (Five Percent) of the bidded amount within the period specified in Schedule F.
This guarantee shall be in the form of cash (in case guarantee amount is less than Rs.
10000/-) or Deposit at Call receipt of any scheduled bank / Banker’s cheque of any
scheduled bank/Demand Draft of any scheduled bank /Pay order of any Scheduled
Bank or Government Securities or Fixed Deposit Receipts or Guarantee Bonds of any
Scheduled Bank or the State Bank of India in accordance with the prescribed form. In
case the Bidder fails to deposit the said performance guarantee within the period as
indicated in Schedule ‘F’. including the extended period if any, the Earnest Money
deposited by the Bidder shall be forfeited automatically without any notice to the
Bidder. The earnest money deposited along with bid shall be returned after receiving
the aforesaid performance guarantee.
10. Intending bidders are advised to inspect and examine the site and its surroundings and satisfy
themselves before submitting their bids as to the nature of the ground and sub-soil (so far as is
25
11. The competent authority on behalf of the President of India does not bind itself to accept the
lowest or any other bid and reserves to itself the authority to reject any or all the bids received
without the assignment of any reason. All bids in which any of the prescribed condition is not
fulfilled or any condition including that of conditional rebate is put forth by the bidders shall
be summarily rejected.
12. Canvassing whether directly or indirectly, in connection with bidders is strictly prohibited and
the bids submitted by the Bidders who resort to canvassing will be liable to rejection.
13. The competent authority on behalf of President of India reserves to himself the right of
accepting the whole or any part of the bid and the bidders shall be bound to perform the same
at the rate quoted.
14. The Bidder shall not be permitted to bid for works in the CPWD Circle (Division in case of
Bidders of Horticulture/Nursery category) responsible for award and execution of contracts, in
which his near relative is posted a Divisional Accountant or as an officer in any capacity
between the grades of Superintending Engineer and Junior Engineer (both inclusive). He shall
also intimate the names of persons who are working with him in any capacity or are
subsequently employed by him and who are near relatives to any gazette officer in the Central
Public Works Department or in the Ministry of Urban Development. Any breach of this
condition by the Bidder would render him liable to be removed from the approved list of
Bidders of this Department.
26
17. Forfeiture of Earnest Money – (i) If any tenderer withdraws his tenders or makes any
modifications in the terms & condition of the tender which is not acceptable to the department
within 7 days after opening of tender (excluding date of opening of tender) then the
Government shall without prejudice to any other right or remedy, be at liberty to forfeit 50%
of the earnest money absolutely. (ii) After 7 days of opening of tender the Government shall
without prejudice to any other right or remedy, be at liberty to forfeit 100% of the earnest
money absolutely.
18. This notice inviting Tender shall form a part of the contract document. The successful
bidder/Bidder, on acceptance of his bid by the Accepting Authority shall within 15 days from
the stipulated date of start of the work, sign the contract consisting of:-
a) The Notice Inviting Bid, all the documents including additional conditions, specifications and
drawings, if any, forming part of the bid as uploaded at the time of invitation of bid and the
rates quoted online at the time of submission of bid and acceptance thereof together with any
correspondence leading thereto.
27
Copy to: -
1. SE cum PD, MNITPC, CPWD, Jaipur for information.
2. EE cum SM (C), MNITPD, CPWD, Jaipur for information.
3. Assistant Engineer (E)-II, MNITPED, CPWD, Jaipur..
4. Notice Board.
5. Cashier.
6. File No. Concern File
28
WHEREAS, Bidder.................. (Name of Bidder) (hereinafter called "the Bidder") has submitted his
tender dated ............. (date) for the construction of ................................................ (name of work)
(here in after called “the Tender")
KNOW ALL PEOPLE by these presents that we ......................................... (Name of bank) having
our registered office at ................................... (here in after called "the Bank") are bound unto
................................................... (Name and division of Executive Engineer) (here in after called "the
Engineer-in-Charge") in the sum of Rs. ......................... (Rs. in words .................................................)
for which payment well and truly to be made to the said Engineer-in-Charge the Bank binds itself, his
successors and assigns by these presents.
SEALED with the Common Seal of the said Bank this ................. day of ................. 20......
(1) If after tender opening the Bidder withdraws, his tender during the period of validity of tender
(including extended validity of tender) specified in the Form of Tender;
(2) If the Bidder having been notified of the acceptance of his tender by the Engineer-in-Charge:
(a) fails or refuses to execute the Form of Agreement in accordance with the Instructions
to Bidder, if required;
OR
(b) fails or refuses to furnish the Performance Guarantee, in accordance with the
provisions of tender document and Instructions to Bidder,
We undertake to pay to the Engineer-in-Charge up either to the above amount or part thereof
upon receipt of his first written demand, without the Engineer-in-Charge having to substantiates his
demand, provided that in his demand the Engineering-Charge will note that the amount claimed by
his is due to him owing to the occurrence of one or any of the above conditions, specifying the
occurred condition or conditions.
This Guarantee will remain in force up to and including the date* ............. after the deadline
for submission of tender as such deadline is stated in the Instructions to Bidder or as it may be
extended by the Engineer-in-Charge, notice of which extension(s) to the Bank is hereby waived. Any
demand in respect of this Guarantee should reach the Bank not later than the above date.
DATE .............
SIGNATURE OF THE BANK
WITNESS .................. SEAL
(SIGNATURE, NAME AND ADDRESS)
*Date to be worked out on the basis of validity period of 6 months from last date of receipt of
tender.
29
In consideration of the President of India (hereinafter called “The Government”) having offered to
accept the terms and conditions of the proposed agreement between…………………………….and
……………………… (hereinafter called “the said Bidder(s)”) for the
work…………………………………………………… (hereinafter called “the said agreement”)
having agreed to production of an irrevocable Bank Guarantee for Rs. …………. (Rupees
………………………………… only) as a security/guarantee from the Bidder(s) for compliance of
his obligations in accordance with the terms and conditions in the said agreement.
1. We, ………………………………. (hereinafter referred to as “the Bank”) hereby undertake to
pay to the Government an amount not exceeding Rs. ………………………..
(Rupees………………. Only) on demand by the Government.
2. We, ……………………………….(indicate the name of the Bank) do hereby undertake to pay
the amounts due and payable under this guarantee without any demure, merely on a demand
from the Government stating that the amount claimed as required to meet the recoveries due
or likely to be due from the said Bidder(s). Any such demand made on the bank shall be
conclusive as regards the amount due and payable by the bank under this Guarantee.
However, our liability under this guarantee shall be restricted to an amount not exceeding
Rs.………………….. (Rupees ………………………….only)
3. We, the said bank further undertake to pay the Government any money so demanded
notwithstanding any dispute or disputes raised by the Bidder(s) in any suit or proceeding
pending before any court or Tribunal relating thereto, our liability under this present being
absolute and unequivocal.
The payment so made by us under this bond shall be a valid discharge of our liability for
payment thereunder and the Bidder(s) shall have no claim against us for making such
payment.
4. We, ……………………………. (indicate the name of the Bank) further agree that the
guarantee herein contained shall remain in full force and effect during the period that would
be taken for the performance of the said agreement and that it shall continue to be enforceable
till all the dues of the Government under or by virtue of the said agreement have been fully
paid and its claims satisfied or discharged or till Engineering-Charge on behalf of the
Government certified that the terms and conditions of the said agreement have been fully and
properly carried out by the said Bidder(s) and accordingly discharges this guarantee.
5. We, ……………………………. (indicate the name of the Bank) further agree with the
Government that the Government shall have the fullest liberty without our consent and
without affecting in any manner our obligation hereunder to vary any of the terms and
conditions of the said agreement or to extend time of performance by the said Bidder(s) from
time to time or to postpone for any time or from time to time any of the powers exercisable by
the Government against the said Bidder(s) and to forbear or enforce any of the terms and
conditions relating to the said agreement and we shall not be relieved from our liability by
reason of any such variation, or extension being granted to the said Bidder(s) or for any
forbearance, act of omission on the part of the Government or any indulgence by the
Government to the said Bidder(s) or by any such matter or thing whatsoever which under the
law relating to sureties would, but for this provision, have effect of so relieving us.
30
31
I / We also indemnify the Government against any losses arising out of non-encashment of the
bank guarantee if any.
(Deponent)
Signature of Bidder
32
Tender for the work of: Supply, installation, testing and commissioning of 800 KWP Solar Photo
Voltaic Generation System at MNIT, Jaipur.
(ii) Technical bid will be opened in presence of tenderers who may be present at 03:30 PM on
25.04.2025 in the office of Executive Engineer cum Senior Manager (E), MNIT Project
Electrical Division, CPWD, Jaipur.
(iii) The Price Bid opening date and time shall be intimated later to qualified Bidders in
Technical bid.
TENDER
I/We have read and examined the notice inviting tender, schedule, A, B, C, D, E & F.
Specifications applicable, Drawings & Designs, General Rules and Directions, Conditions of
Contract, clauses of contract, Special conditions, Schedule of Rate & other documents and Rules
referred to in the conditions of contract and all other contents in the tender document for the work.
I/We hereby tender for the execution of the work specified for the President of India within
the time specified in Schedule “F”, viz., schedule of quantities and in accordance in all respects
with the specifications, designs, drawings and instructions in writing referred to in Rule-1 of
General Rules and Directions and in Clause 11 of the Conditions of contract and with such
materials as are provided for, by, and in respects in accordance with, such conditions so far as
applicable.
We agree to keep the tender open Seventy-Five (75) days from the date of opening of
technical bid in case tenders are invited on 2 bid / envelop system and not to make any
modifications in its terms and conditions.
A sum of Rs. 13,19,632/- is hereby forwarded in cash/receipt treasury challan/deposit at call
receipt of a scheduled bank/fixed deposit receipt of scheduled bank/demand draft of a scheduled
bank/bank guarantee issued by a scheduled bank as earnest money. If I/We, fail to furnish the
prescribed performance guarantee within prescribed period. I/We agree that the said President of
India or his successors in office shall without prejudice to any other right or remedy, be at liberty to
forfeit the said earnest money absolutely. Further, if I/We fail to commence work as specified, I/We
agree that President of India or the successors in office shall without prejudice to any other right or
33
Further, I/We agree that in case of forfeiture of Earnest Money or Performance Guarantee as
aforesaid, I/We shall be debarred for participation in the re-tendering process of the work.
I/We undertake and confirm that eligible similar work(s) has/have not been got executed
through another Bidder on back-to-back basis. Further that, if such a violation comes to the notice
of Department, then I/We shall be debarred for tendering in CPWD in future forever. Also, if such a
violation comes to the notice of Department before date of start of work, the Engineer-in-Charge
shall be free to forfeit the entire amount of Earnest Money Deposit/Performance Guarantee.
I/We hereby declare that I/We shall treat the tender documents drawings and other records
connected with the work as secret/confidential documents and shall not communicate
information/derived there from to any person other than a person to whom I/we am/are authorized
to communicate the same or use the information in any manner prejudicial to the safety of the State.
………………(yyy)
Dated : …………………(yyy) Signature of Bidder
Postal Address
Witness: ………………(yyy)
Address : …………..…(yyy)
Occupation : ………….(yyy)
34
35
SCHEDULE ‘A’
Schedule of quantities As per part –C of the NIT
SCHEDULE ‘B’
Schedule of materials to be issued to the Bidder
1 2 3 4 5
SCHEDULE ‘C’
SCHEDULE ‘E’
Reference to General Conditions of contract: As per CPWD Works Manual 2024 and its
SOP & General conditions of contract
Construction works 2023 amendments up to
date.
36
2(iv) Standard schedule of Rates DSR 2022 (E&M) DSR 2023 (Civil), DSR
2019 (Solar PV) & Market rates.
2(v) Department
Central Public Works Department
2(vi) Standard CPWD contract Form
GCC construction works 2023 &
CPWD form 7 as modified &
corrected upto date
Authority to Decide:
i. Authority to convey the decision of EE cum SM (E), MNITPED,
Shifting of milestone and extension of time CPWD, Jaipur
ii. Authority to decide reschedule of milestone and SE cum PD, MNITPC, CPWD,
And extension of time. Jaipur
iii. Shifting of date of start in case of delays in SE cum PD, MNITPC, CPWD,
handing over of site Jaipur
Clause 6 CMB/EMB
38
Clause N.A.
10CA Whether clause 10CA shall be Applicable.
Materials covered under this Nearest material for which All Base price of all material covered
clause India under Clause 10 CA
Wholesale Price Index is to be
followed
--------Nil------------ -----------------Nil-------------------- ----------------Nil-----------------
--------Nil------------ ---------------------Nil---------------- -----------------Nil-----------------
--------Nil------------ ------------------Nil------------------- -----------------Nil-----------------
Schedule of component of cement, steel, other materials, Labour etc. for price escalation:
Clause 18 List of mandatory machinery, tools & plants to be As required for timely execution
deployed by the Bidder at site. of work
(a) Conciliator for conciliation Special Director General- Region Chandigarh, CPWD,
of disputes or Successor thereof.
Assistant Engineers retired from Government services that are holding Diploma will be treated at par
with Graduate Engineers.
40
EE cum SM (E)
MNITPED, CPWD, Jaipur
41
PART-B
42
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
CPWD-6 CPWD
After the award of work, in case the CPWD contractor himself meets the required eligibility
criteria, he shall be allowed to execute the same after due verification etc., otherwise he shall either
associate specialized agency or manufacturer/ OEM as per eligibility criteria.
1. The main contractor shall submit the details of specialized agency to be associated in Annexure
– A within two weeks of awarded of work. Following documents for association shall be submitted to
the Executive Engineer cum Senior Manager (E), MNITPED, CPWD, Jaipur in charge for deciding
the eligibility
A. Willingness from eligible specialized agency to get associated with the applicant for execution
of the work as per the conditions set out in the MOU as per the proforma given in Annexure-B to be
signed between the CPWD contractor and the associated eligible specialized agency.
C. MOU signed on Rs. 100/- with eligible specialized agency meeting the eligibility criteria and
same as specified for specialized works. The MOU in the enclosed form as per Annexure-C shall be
signed by both the parties i.e. contractor as 1st party and associated agency as 2nd party.
“I/We undertake and confirm that eligible similar works(s) has/have not been executed through
another contractor on back-to-back basis. Further that, if such a violation comes to the notice of
Department, then I/we shall be debarred for associated agency in CPWD in future forever.”
43
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
2. In the event of the concerned associated agency not performing satisfactorily or failure of
associate to complete the work, the contractor on the written direction of the department, shall remove
the Associate deployed on the work and shall submit name of new associate who fulfill the conditions
mentioned in NIT to execute the leftover work without any loss of time or variation in cost to the
department in this regard. Contractor shall meet all the guarantee for the equipment already supplied
for which payment has been released by the Deptt. in part. If any equipment supplied for the work,
during the currency of the earlier Associate and paid partly by the Deptt., becomes redundant /not in a
position to be installed and commissioned and put to beneficial use due to change in agency for
execution of E&M work, the contractor shall be liable for replacement of the equipment(s) at no cost
to Department. No change of Associated Specialized Agency or Manufacturer/OEM will be allowed
without prior approval of the Engineer-in-charge.
44
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
ANNEXURE-A
We hereby propose the following electrical agencies as per details mentioned against each. Their
Willingness Certificates are also attached as per Annexure-B.
2.
3.
Contractor’s signature
45
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
ANNEXURE-B
WILLINGNESS CERTIFICATE
I will execute the work as per specifications and conditions for the agreement and as per
direction of the Engineer-in-Charge. Also I will engage full time technically qualified
supervisor/engineer for the work. I will attend inspection of officers of the department as and when
required.
Dated:
46
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
ANNEXURE-C
And
Whereas, This Memorandum of Understanding has been entered into to execute the above
work by the Main Contractor and Associate Contractor.
Whereas, both the parties have gone through and understood the various conditions and clauses
of the tender and willingly agree to abide by them.
This MOU shall be valid till the duration of completion of above work and shall be extended if
so required by the CPWD.
1 The associated agency shall completely execute, perform and do all the works mentioned and
described in the main agreement for its electrical components according to the specifications,
terms and conditions etc. of the main agreement.
2 The associated agency shall execute and complete the works in all respect up to full
satisfaction of the CPWD officers and attend to them during their inspection at site, meetings
etc., whenever required by the CPWD officers.
3 The cost of electrical works executed by the associated electrical contractor will include the
cost of all the materials, accessories, equipments, tools & plants, laborers technical persons
required etc. in all respect.
4 The associated agency is responsible for getting recorded measurements and preparation,
submissions & pursuance of payment of the bills of the work done for electrical portion of the
main agreement.
5 The rate will be as per the schedule enclosed.
6 The Quantity will be as per actual measurement as received from CPWD to main contractor
and the rate will be as per the mutually agreed.
47
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
7 The payment to associate contractor will be released after the payment to main contractor is
made by the CPWD.
8 The technical staff required for the associate discipline shall be of associate/main contractor.
9 The guarantee of the installation after the completion of the work shall be responsibility of the
associate contractor and main contractor both as required by the CPWD.
10 There is Service Tax (GST) liability; work being related to the construction of the Central
Govt. Deptt. However, if any liability of the Service Tax (GST) is imposed on the associated
electrical contractor then it will be paid by main contractor.
11 Either party shall not repudiate the contract in mid-way without the consent of each other.
Otherwise, it will be treated as breach of agreement for any reason whatsoever.
12 The main agency shall be solely responsible for deferment & rescheduling of each milestone
fixed as per contract documents and in such eventuality, the consequences arising out of the
same rests on main agency.
13 The main contractor only shall be responsible for getting extension of delay regularized and
liability what so ever flowing out shall lies with them. There shall be no direct or indirect
impact on associate contractor.
14 TDS shall be deducted by the main contractor as per Income Tax law from associated agency.
In case liability of tax other than Income Tax (Such as GST, or any other mechanism formed)
is levied on associated contractor then the main agency will reimburse it in full to associated
agency.
15 The associated contractor shall be bound to execute work up to a deviation limit prescribed in
schedule-Fin quantities of items of work at the agreement rate. Beyond deviation limit the
rates will be decided by main & Associated contractor on mutually agreed basis.
16 For the items such as extra items, substitute items and new items other than the items of main
agreement, if any incorporated in the work, then the main contractor shall pay the full amount
so approved to the associate contractor.
17 The validity of rates shall be ______ months after finalization & acceptance of MOU by the
competent authority.
18 In case main contractor delays the payment to associated contractor after the payment is
released by department to the main contractor then on receipt of delay in payment from
associate contractor the CPWD shall directly make the payment to associated contractor.
19 The main contractor shall at their cost provide necessary requisite arrangement for storage of
material.
20 Sand& cement used in the electrical work shall be provide by main contractor.
21 Security Deposit as deducted by the CPWD will be reimbursed by main contractor to associate
contractor. However associated contractor will deposit 2 ½ % of Agreement amount of Rs.
______________ in shape of FDR towards S/D to be retained by main contractor which will
refunded to electrical contractor after completion of electrical work.
22 The Income tax, Commercial tax and labour cess tax deducted by the CPWD from the bills of
electrical work shall be reimbursed by the main contractor in favour of the associated electrical
contractor accordingly.
Signature Signature
(Associated Contractor) (Major Contractor)
Address : _________________ Address : __________________
48
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
GENERAL TERMS AND CONDITIONS
Rates:
The work shall be treated as on works contract basis and the rates tendered shall be for complete items
of work inclusive of all taxes including GST, duties, and levies etc. and all charges for items
contingent to the work, such as packing, forwarding, insurance, freight and delivery at site for the
materials to be supplied by the contractor, watch and ward of all materials for the work at site etc.
Mobilization Advance:
No mobilization advance shall be paid for the work, unless otherwise stipulated in tender papers for
any individual works/ composite work.
Completeness of Tender:
All sundry fittings, assemblies, accessories, hardware items, foundation bolts, termination lugs for
electrical connections as required, and all other sundry items which are useful and necessary for proper
assembly and efficient working of the various components of the work shall be deemed to have been
included in the tender, whether such items are specifically mentioned in the tender documents or not.
49
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Electric Power Supply and Water Supply:
Power and water supply will be arranged by the contractor at the site for installation and testing
purposes. The contractor will take due care to ensure safety of electrical installation during execution
of work.
Payment Terms:
Payment shall be made as per the relevant clauses of form PWD 7/8 forming part of the tender
documents.
Care of buildings:
Care shall be taken by the contractor to avoid damage to the building during execution of his part of
the work. He shall be responsible for repairing all damages and restoring the same to their original
finish at his cost. He shall also remove, at his costs, all unwanted and waste materials arising out of
his work, from the site.
Addition to an installation:
Any addition, temporary or permanent, to the existing electrical installation shall not be made without
a properly worked out scheme/design by a qualified Electrical Engineer to ensure that such addition
does not lead to overloading, safety violation of the existing system.
Drawings:
After award of the work, the firm will be required to prepare &submit the drawings of Electrical
Installation in accordance to inventory of the proposed work in addition to layout plan, conduit routes,
cable routes etc. in both AutoCAD & PDF format for approval of Engineer-in-charge. The work shall
be carried out in accordance with the drawings and the tender documents and also in accordance with
modification thereto from time to time as approved by the Engineer-in-charge. All wiring diagrams
shall be deemed to be ‘Drawings’ within the meaning of the term as used in Clause 11 of the
conditions of contract (PWD 7). They shall indicate the main switchboard, the distribution boards
(with circuit numbers controlled by them), the runs of various mains and sub mains and the position of
50
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
all points with their controls. All circuits shall be indicated and numbered in the wiring diagram and
the points shall be given the same number as the circuit to which they are electrically connected.
Tolerances:
Tolerance of +- 5% is allowed in Schedule of Quantities
Quality of material:
All materials and equipment supplied by the contractor shall be new and must be in original seal-pack.
They shall be of such design, size and materials as to satisfactorily function under the rated conditions
of operation and to withstand the environmental conditions at site.
Adequate care to ensure that only tested and genuine materials of proper quality are used in work shall
be ensured by firm. The firm shall ensure that:
(i) Material will be ordered & delivered at site only with the prior approval of the department to
ensure timely delivery.
(ii) As and when the order is placed for the fittings/ fixtures, cables, switchgears, poles, rising
main, other main items etc., its copy shall be endorsed to the CPWD Engineer-in-charge.
(iii) The firm will be required to procure material like exhaust fans, MCB’s & DB’s, switches &
sockets, wires & cables, conduits and switchgears etc. directly from the manufacturer/ authorized
dealers to ensure genuineness & quality and as per the approved makes only. Proof in this regard shall
be submitted by the contractor if required by the department.
(iv) Inspection at factory or at go down of the manufacturer, as required, shall be arranged by the
firm for a mutually agreed date.
(v) Delivery of material shall be taken up only with the consent of department, after clearance of
the material.
(vi) Department shall reserve the right to waive inspection in lieu of suitable test certificate, at its
discretion.
Similarly, for fabricated equipment, the contractor will first submit dimensional detailed drawings for
approval before fabrication is taken up in the factory. Suitable stage inspection at factory also will be
made to ensure proper use of materials, workmanship and quality control.
Ratings of components:
All components in a wiring installation shall be of appropriate ratings of voltage, current and
frequency, as required at the respective sections of the electrical installations in which they are used.
All conductors, switches and accessories shall be of such size as to be capable of carrying the
maximum current, which will normally flow through them, without their respective ratings being
exceeded.
51
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Conformity to standards:
All components shall conform to relevant Indian Standard Specifications wherever existing. Materials
with ISI certification mark shall be preferred. Relevant Indian Standards including amendments or
revisions thereof up to the date of tender acceptance shall be applicable in the respective contracts for
respective items, firm to ensure its compliance.
Interchangeability:
Similar parts of all switches, lamp holders, distribution fuse boards, Switch gears, ceiling roses,
brackets, pendants, fans and all other fittings of the same type shall be interchangeable in each
installation.
Workmanship:
Good workmanship is an essential requirement to be complied with. The entire work of
manufacture/fabrication, assembly and installation shall conform to sound engineering practice.
Testing:
All testes prescribed in this General Specification, to be done before, during and after installation,
shall be carried out, and the test results shall be submitted to the Engineer-in-charge in prescribed
Performa, forming part of the Completion Certificate.
Commissioning on completion:
After the work is completed, it shall be ensured that the installation is tested and commissioned.
53
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
SCOPE OF WORK
The following are the tentative location and capacity of solar PV systems:
Bidders are requested to visit the site before quoting their rates and familiarize themselves with site
conditions. Scope of work is not limited to only listed structures/ buildings mentioned in above table
and successful bidder may explore other possibilities / buildings/ structures to install solar PV
system(s) in case 800 KWp is not achieved in these listed structures/ buildings
1. Design, planning, SITC (supply, installation, testing & commissioning), solar metering and
handing over to client department (MNIT Jaipur) of PV systems as per above table is the broad
scope of work.
2. Preliminary designs, PV schemes, drawings, structural detailing etc are given in the NIT for
reference. Contractor based on these preliminary details shall submit detailed designs, PV
schemes, electrical drawings, proof checked/ vetted structural drawings, PV module
specifications, etc (separately for each individual building/structure) to the department for
approval.
3. Contractor shall get the structural drawings proof checked/ vet from any of the IITs/ NITs/
Govt. engineering institute. Successful bidder may get preliminary Staad Pro software
structural analysis from the office of EE&SM(E), MNITPED, CPWD Jaipur for reference.
4. On successful commissioning of solar PV systems, contractor shall contact JVVNL for solar
metering. SITC of metering systems is in the scope of work. Any statutory payment to local
bodies (like JVVNL) shall be made/ reimbursed by department however liaison with local
bodies is in the scope of work.
5. Other than the above structures/ buildings, solar metering from JVNNL shall also be installed
and commissioned for 100 KWp rooftop solar PV system in Aravali hostel and for 10 KWp
rooftop solar PV system in Chandrashekhar hostel. In this regard nothing extra shall be
payable.
54
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
6. Any additional electrical panels and accessories required for solar metering from JVVNL shall
be inclusive in the rates of SOQ. Nothing extra shall be payable.
7. Roofs in Roof top installations shall be painted with solar reflective paints without any
additional cost.
8. Tree/ bush pruning &trimming if required shall be carried out without any additional cost.
9. Inverters shall be placed in outdoor (Minimum IP54 protection) CRCA enclosures without any
additional cost.
10. Structure i/c existing base structure shall be painted with desired colour shade as per direction
of engineer in charge without any additional cost.
11. Output from all inverters to outdoor panels to the termination panels shall be synchronized.
Any additional accessories/ equipment needed to achieve proper synchronization shall be
provided without any additional cost.
12. Contractor shall have full responsibility of structural stability and functionality of all the PV
systems.
13. All PV systems should be designed for a wind speed of 180 km per hour.
14. All PV systems should be connected on-grid.
15. All PV systems should be provided with surge & lighting protection. All necessary
arrangements including earthing shall be inclusive in rates (only PV modules, structure and
inverters) in schedule of quantities and nothing extra shall be payable. However, earthing of
outdoor panels and terminations panels is payable as per items in schedule of quantities.
16. All inverters/Power conditioning units shall have a warranty/guarantee of 10 years.
Bidders are requested quote accordingly. Security deposit @ 1% of tendered amount
shall be additionally deducted and shall be released after 10 years from date of
Completion of work.
17. Foundations as per final design shall be inclusive of rates in schedule of quantities. Nothing
extra shall be payable.
18. Security deposit @ 1% of tendered amount shall be additionally deducted against
performance of Solar PV system and shall be released after 25 years from date of
Completion of work.
55
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Isometric & Top View Drawings - As per part D of the NIT
56
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Isometric & Top View Drawings - As per part D of the NIT
57
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Isometric & Top View Drawings - As per part D of the NIT
58
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Google Earth Snap
59
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Structural Drawings - As per part D of the NIT
60
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Structural Drawings - As per part D of the NIT
61
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
TECHNICAL SPECIFICATION
A Grid Connected Solar Photo Voltaic (SPV) power generation system consists of SPV array, Module
Mounting Structure, Inverter/Power Conditioning Unit (PCU) consisting of Maximum Power Point
Tracker (MPPT), and Controls & Protections, interconnect cables and switches. PV Array is mounted
on a suitable structure. Grid connected SPV generation system is without battery and should be
designed with necessary features to supplement the grid power during day time. Components and parts
used in the SPV power systems including the PV modules, structures, cables, junction boxes, switches,
inverters/PCUs etc., should conform to the BIS or IEC or international specifications, wherever such
specifications are available and applicable. The inverters provide a wide maximum point power
tracking (MPPT) voltage range on EU efficiency of 97%.
SPV MODULE/ARRAY:
Solar Photo Voltaic Generating Sources: SPV generating sources constituted of following building
blocks:
SPV Module: SPV Module is the basic building block of the SPV power supply, which consists of
Solar cells (a Semiconductor Devices which when exposed to sunlight produces DC electricity)
connected in series. These modules are connected in series and parallel to get the desired power and
voltage. The Rated DC current of One module shall be 540Wp or higher.
SPV Panel: SPV Modules of same rating are connected in series to form a SPV panel to get the desired
voltage.
SPV Array: Panels are connected in parallel to get the desired power. This Whole combination is
called an array. The SPV array is so designed that it provides simultaneously meets the load demand.
Design Features: The mechanical design and construction of SPV modules, panels and mounting
structure shall be inherently robust and rigid under all conditions of operation, adjustment, storage and
transport.
Protective devices against surges at the PV module shall be provided. Low voltage drop bypass diodes
shall be provided. The module frame shall be made of corrosion resistant materials having anodized
aluminum or steel or as per manufacturer standard. The bidder shall carefully design & accommodate
requisite numbers of the modules to achieve the rated power.
Other general requirement for the PV modules and subsystems shall be the following:
The rated output power of any supplied module shall have tolerance of ± 3%.
The peak-power point voltage and the peak-power point current of any supplied module
and/or any module string (series connected modules) shall not vary by more than 2 (two)
per cent from the respective arithmetic means for all modules and/or for all module strings.
The module shall be provided with a junction box with weather proof lid of sealed type and
IP-65 rated.
62
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
Warranties: The PV Modules must be warranted for output wattage, which should not be less than
90% at the end of 10 years and not less than 80% at the end of 25 years.
SPV Modules to be supplied should have minimum declared output of 540Wp or higher. Number of
Modules to be supplied shall be worked out accordingly. Test reports of the modules should be
submitted.
Stabilized output of the Solar PV Array for the Power System should not be less than Calculated Kwp
under standard Test Condition. Modules for Power System shall be made of mono-crystalline Silicon
Solar cells. Peak power point voltage and the peak power point current of any supplied module and/or
any module string (series connected module) shall not be more than 3% from the respective arithmetic
means for all modules and/or for all module strings.
The module frame shall be made of aluminum or steel or corrosion resistant material, which shall be
electrically compatible with the structural material used for mounting the modules. Crystalline high-
power cells shall be used in the Solar Photovoltaic module. Solar Module shall be laminated using
laminating technology using established polymer (EVA) and Tedlar /Polyester laminate as per OEM
standards. The solar modules shall have suitable encapsulation and sealing arrangement to protect the
silicon cells from the environment. The arrangement and the material of encapsulation shall be
compatible with thermal expansion properties of the Silicon cells of the module framing arrangement.
The encapsulation arrangement shall ensure complete moisture proofing during the life of solar
modules.
Module rating is considered under standard test conditions, however Solar modules shall be designed
to operated and perform in relative humidity up to 100% with temperature between -10 Deg C and +85
Deg C and with stand guts up to 180Km/h. The Geological data of MNIT, Jaipur can be referred to
meet optimum generation. Sample modules and production processes employed in the manufacture of
the offered module shall be in accordance with the requirement of IEC 61730.
PV ARRAY CONFIGURATION
The Solar array shall be configured in multiple No. of sub- arrays, providing optimum DC power. The
PV modules should be mounted on aluminum structures GI/ MS powder coated of adequate strength
and appropriate design, which can withstand load of modules and high wind velocities up to 180 km
per hour. The array structure shall be so designed that it will occupy minimum space without
sacrificing the output from the SPV panels
63
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
MODULE MOUNTING STRUCTURE
The mounting structure would be designed to sustain wind loading of up to 180Kmph and shall be
protected by using Eco friendly anticorrosion on structure. The entire structure including array will be
earthed to an independent pit with redundant paths. The Hardware shall be made of SS material or as
per manufacturer standard. The structure should be designed to allow easy replacement of any module.
The structure should be designed for simple mechanical and electrical installation. It shall support SPV
module at a given orientation, absorb and transfer the mechanical loads to the roof/base structure
properly. The array structure shall be so designed that it will occupy minimum space without
sacrificing the output from SPV panels at the same time. Nut & bolts supporting structure including
module Mounting Structures shall have to be adequately protected with atmosphere and weather
prevailing in the area; Nut bolts should be especially in SS material or manufacturer recommended.
The PCU shall have protection features such as, over current, short circuit, over temperature to
name a few.
The PCU shall be of very high quality having high efficiency (>92%) and shall be capable of
running in isolated mode.
The PCU should be designed to be completely compatible with the SPV array voltage and grid
supply voltage.
The PCU should be designed for continuous, reliable power supply as per specifications.
The PCU shall have internal protection arrangement against any sustained fault.
It should have user friendly LCD display for programming and view online parameters such as
DC power input, DC input voltage, DC current, AC power output, AC voltage and AC current
and Power factor.
The PCU shall have arrangements for adjusting DC input current and should trip against
sustainable fault downstream and shall not start till the fault is rectified.
The Grid connect PCU shall be sourced from reputed firms, which will incorporate latest
Technological advances to provide highly reliable and efficient energy conversion from DC to AC.
The PCU incorporates a new system design which uses multiple power stacks which work in tandem.
The PCU should be Single/three phase static solid state type power conditioning units/string inverters
suitability connected & synchronized to give three phase supply output. Both AC & DC lines shall
have suitable fuses/MCBs and contactors to allow safe start up and shut down of the system.
Fuses/MCBs used in the DC circuit should be DC rated. The PCU shall have provision for input and
output isolation. Each solid-state electronic device shall have to be protected to ensure long life of the
inverter as well as smooth functioning of the inverter.
64
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
AC side:
DC Side:
65
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
guidelines for interconnecting solar power with Grid shall be followed. Certification of Islanding
protection in the inverter/PCU from the manufacturer of the equipment shall be mandatory. This shall
be arranged by the supplier from the manufacturer.
DATA MONITORING:
PCU to log the inverter performance data and transmit the same to the Data logger. Data logger shall
then gather information and monitor the performance of the inverter. It shall also support
measurements from external sensors. The data can be acquired remotely via modem.
The lightning conductor shall be earthed through flats and connected to the Earth mats as per
applicable Indian Standards with earth pits. Each Lightning Conductor shall be fitted with individual
earth pit as per required Standards including accessories, and providing masonry enclosure with cast
iron cover plate having locking arrangement, watering pipe using charcoal or coke and salt as per
required provisions of IS.
The bidder shall ensure adequate lightning protection to provide an acceptable degree of protection for
the array Yard/Shed. If necessary, more numbers of Lightning conductors may be provided.
EARTHING SYSTEM
Earthing Protection: Each array structure of the PV yard should be grounded/ earthed properly as per
IS: 3043-1987. In addition, the lighting arrester/masts should also be earthed inside the array field.
Earth Resistance shall be tested in presence of the representative of Department as and when required
after earthing by calibrated earth tester. PCU, ACDB, Electrical Panels and DCDB should also be
earthed properly. Earth resistance shall not be more than 01 ohms. It shall be ensured that all the
earthing points are bonded together to make them at the same potential.
GRID ISLANDING:
In the event of a power failure on the electric grid, it is required that any independent power-producing
inverters attached to the grid turn off in a short period of time. This prevents the DC-to-AC inverters
from continuing to feed power into small sections of the grid, known as “islands.”
Powered islands present a risk to workers who may expect the area to be unpowered, and they may
also damage grid-tied equipment. The PV systems should be equipped with islanding protection. In
addition to disconnection from the grid (due to islanding protection) disconnection due to under and
over voltage conditions shall also be provided. A manual disconnect pole isolation switch beside
automatic disconnection to grid would have to be provided at utility end to isolate the grid connection
by the utility personnel to carry out any maintenance. This switch shall be locked, if required, by the
utility personnel.
66
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
PAINTING & FINISH
All metal surfaces shall be thoroughly cleaned of rust, scale, oil, grease, dirt etc. Fabricated structures
shall be pickled and then rinsed to remove any trace of acid. The under surface shall be made free
from all imperfections before undertaking the finishing coat.
67
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
LIST OF PREFERRED MAKES
68
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
14 NETWORK SWITCH NETGEAR/ CISCO/ ARISTA/ COMMSCOPE/
COMSCORE/ DIGILINK/ HP ENTERPRISES
15 POWER CONDITIONING ABB/ LEGRAND/ HITACHI/ UTL/SIEMENS/
UNIT/INVERTER SCHNEIDER/DELTA/ MITSUBISHI OEM/ OEM
RECOMMENDED
16 SOLAR METER JVVNL RECOMMENDED
17 SOLAR PV MODULE PREVAILING MNRE ALMM LIST
18 UPVC/ CPVC PIPES SUPREME/ASTRAL/FINOLAX/ASHIRWAD/PRINCE
Note - Any other make other than mentioned above conforming BOQ description, item
specificatilons, NIT terms & conditions and public procurement policy of India are also
acceptable.
69
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
(Schedule of Quantities)
PART-C
70
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
SCHEDULE OF QUANTITIES
S.No. Description Unit Qty Rate Amount
1 Designing, Planning, Supply, Installation, Testing,
Commissioning, net metering and handing over to
client department of ongrid Solar Photovoltaic Power
Systems conforming to MNRE specifications as
amended, consisting of Mono Crystaline silicon solar
cells, net metering facility from JVVNL, necessary
protections, earthing, mounted on structure as per scope
of work and terms and conditions of the NIT with
following components complete as required:-
a) Solar Photovoltaic Module of capacity 540 Wp or
above, manufactured in India, conforming to IS
14286/IEC 61215, IS/IEC 61730-Part-1, IS/IEC 61730-
Part-2. Solar Photovoltaic Module conversion
efficiency shall not be less than 20%. PV modules used
in solar power systems must be warranted for their
output peak watt capacity, which should not be less
than 90% at the end of 10 years and 80% at the end of
25 years.
b) Power Conditioning Unit (PCU) of 350-800 V DC
Input voltage range and 400 V AC, three phase, 4 wire,
50Hz +/- 2.5 Hz, output voltage suitable to generate AC
Power with efficiency not less than 97%, total harmonic
distortion less than 3% and suitable for ambient
temperature from 0 to 50 degree C. The PCU shall
adjust the voltage and frequency level to suit the Grid
Voltage Frequency.
c) Data Monitoring System complete with accessories.
d) Fixing of Array junction box & Main junction box
with minimum IP 65 protection and termination
arrangement for incoming and outgoing cable along
with glands, lugs and other accessories etc. as required.
e) Lightning and surge voltage protection.
f) Connections & Interconnections by supplying &
fixing required size copper conductor and control
cables between solar modules, PCU unit along with
supplying & fixing of necessary channel/conduit lugs
and other accessories etc. as required.
g) Outdoor type minimum IP 65 enclosure (floor
mounted) for housing PCU units and accessories of
suitable size made up of CRCA sheet as per scope of
work.
h) Supporting structure as per tender documents.
i) Foundations as per design. KWp 800 75743.00 60594400.00
75
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
PERFORMA FOR QUOTING THE RATES
Name of work : Supply, installation, testing and commissioning of 800 KWP Solar Photo Voltaic
Generation System at MNIT, Jaipur.
Estimated cost put to Tender:
Name of Bidder:
76
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
(Preliminary Drawings)
PART-D
77
Correction. Nil Deletion.. Nil Insertion.. Nil Overwriting..Nil AE(C)/(E) EEcumSM(C)/(E)
24293
4544
5539
64816 25341
4560
5035
2307
63775
1144
PV MODULES
35873
4544
5047
36917
35873
4544
5048
36916
PV MODULES
11555 16187
45662
5101
4544
4544
5140
5079
4544
12083 16142
43979
5761
44590
43618
5748
5761
44590
8224618
PV MODULES
2307
1144
5747
40821
39618
7204
5821
7165
7166
PV MODULES
10226
9302
7425
5821
26429
26429
25626
25626
7134
5821 5821
12182
12201
11634
11634
2307
5821 5821
1144 7165
5585 12879 10068 11856 9263 14981 8732
6343
17345
1144
2307
PV MODULES
8081 5765
4552
4500
4500
9078
17345
13354
23135
1895
4500
40505
26609 38189
4500
15585
11337
5765
4500
4607
4500
4500
8901
8685
5765
5765
4607
4552
4500
4500
31241
13273
12384
31241 33557
4500
PV MODULES
2307
1144
6948
5757
87261
M2
PURLIN (M3)
TYP.WELD 8MM
M2 8mm THK.
PLATE
8mm THK. PLATE M1
DETAIL-1
M3 M2
M1
TYP.WELD 8MM
M1
DETAIL-2
BASE PLATE
BP1
BP1
S/NO. MEMBERS
M3 RHS 60x40x3.6 mm
SPACING
3000 TO 4000 MAX
PURLIN
MAY VARIES M3
M2 M2 M2
SAG ROD 12 MM
STRUCTURE CONSULTANTS:-
ER .SHERRY RAKHRA
CHARTERED STRUCTURE ENGG.
M.E (STRUCTURES ) hons.
M.I.S.E, M.I.E, M.I.O.V, M.I.C.I
RAKHRA ASSOCIATES
#2500, SECTOR-40-C, chandigarh
@ - [email protected]
099-8880-9055 (M)
099-8820-9055 (M)
M6 - RHS 122x61x5.4 mm
M7 - RHS 96x48x4.8 mm
SECTION AT A-A
M3
PURLIN
M7
B B
M3
M4 M4
STRUCTURE CONSULTANTS:-
ER .SHERRY RAKHRA
CHARTERED STRUCTURE ENGG.
M.E (STRUCTURES ) hons.
M.I.S.E, M.I.E, M.I.O.V, M.I.C.I
RAKHRA ASSOCIATES
#2500, SECTOR-40-C, chandigarh
@ - [email protected]
A A 099-8880-9055 (M)
099-8820-9055 (M)
M3
PLAN OF VLTC PARKING AREA
SPACING
3000 TO 4000 MAX
MAY VARIES
PURLIN
M4
M3 M3 M3
SAG ROD 12 MM
STRUCTURE CONSULTANTS:-
ER .SHERRY RAKHRA
CHARTERED STRUCTURE ENGG.
M.E (STRUCTURES ) hons.
M.I.S.E, M.I.E, M.I.O.V, M.I.C.I
RAKHRA ASSOCIATES
#2500, SECTOR-40-C, chandigarh
@ - [email protected]
099-8880-9055 (M)
099-8820-9055 (M)
M5
M1 TYP.WELD 8MM
R4000
M1 M2
DETAIL-2
M2
S/NO. OLD MEMBERS NEW MEMBERS
PURLIN
M4
A A STRUCTURE CONSULTANTS:-
ER .SHERRY RAKHRA
CHARTERED STRUCTURE ENGG.
M.E (STRUCTURES ) hons.
M.I.S.E, M.I.E, M.I.O.V, M.I.C.I
RAKHRA ASSOCIATES
#2500, SECTOR-40-C, chandigarh
@ - [email protected]
M1 099-8880-9055 (M)
099-8820-9055 (M)
M3 M3 DETAIL-1
M3
M2
M4 M1
TYP.WELD 8MM
EXISTING MEMBER
AS/ ARCHITECT DESIGN
DETAIL-2
ADDITION OF COLUMN
AS PER EXISTING EXISTING COLUMN
ARCHITECT DESIGN AS/ ARCHITECT DESIGN
BASE PLATE
STRUCTURE CONSULTANTS:-
20mm THK. BASE PLATE ER .SHERRY RAKHRA
CHARTERED STRUCTURE ENGG.
S/NO. MEMBERS M.E (STRUCTURES ) hons.
M.I.S.E, M.I.E, M.I.O.V, M.I.C.I
RAKHRA ASSOCIATES
VERTICAL 12 No. #2500, SECTOR-40-C, chandigarh
@ - [email protected]
16Ø STIRUPS M1 RHS 122x61x5.4 mm 099-8880-9055 (M)
099-8820-9055 (M)
8Ø@150C/C
12Ø@150C/C M2 RHS 122x61x5.4 mm
BOTH WAYS
M3 RHS 122x61x5.4 mm