The document outlines the curriculum for a Diploma in Civil Engineering course titled 'Construction Management' at Government Polytechnic, Amravati. It includes details on teaching schemes, examination schemes, course rationale, outcomes, and a comprehensive list of theoretical and practical contents. The course aims to equip students with essential management skills for effectively overseeing civil engineering projects.

Uploaded by

Sagar Bethekar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views4 pages

CNM Cur

The document outlines the curriculum for a Diploma in Civil Engineering course titled 'Construction Management' at Government Polytechnic, Amravati. It includes details on teaching schemes, examination schemes, course rationale, outcomes, and a comprehensive list of theoretical and practical contents. The course aims to equip students with essential management skills for effectively overseeing civil engineering projects.

Uploaded by

Sagar Bethekar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

GOVERNMENT POLYTECHNIC, AMRAVATI

(AN AUTONOMOUS INSTITUTE OF GOVT. OF MAHARASHTRA)


CURRICULUM DEVELOPMENT CELL
----------------------------------------------------------------------------------------------------------------
PROGRAMME TITLE: DIPLOMA IN CIVIL ENGINEERING
COURSE CODE: CE4452
COURSE TITLE: CONSTRUCTION MANAGEMENT
TEACHING SCHEME:
TOTAL CONTACT
LEVEL OF PRERE- WEEKLY TOTAL TOTAL HOURS
COURSE QUISITE CONTACT HRS. CREDITS WEEKS
L T P L T P
IV B - 03 - 02 05 16 48 - 32

EXAMINATION SCHEME:
THEORY(Marks) PRACTICAL(Marks)
ESE ESE PA TOTAL ESE PA TOTAL
PAPER (Marks)
HRS.
3Hrs MAX. 70 30* 100 25 # 25^ 150
MIN. 28 --- 40 10 10
@: Internal Assessment #: External Assessment –skill test based
(*) Under the Theory PA, Out Of 30 Marks, 20 Marks is the Average of Two Tests and 10 Marks are for Micro project-
(^) Under practical PA Continuous Assessment of Practical Work is to be done by Course Teacher as per CDC norms.
For the courses having only practical examination, PA has two parts (i) Continuous Assessment of Practical
work - 60% and (ii) microproject-40%.

1. RATIONALE:
Civil engineering projects involve various resources like men, materials, machinery, time and money.
Therefore these projects need to be efficiently managed to utilize the resources to the optimum so that they are
completed at least cost and within stipulated time duration. Civil engineers at the site and office are responsible
to manage the projects efficiently. Therefore Civil engineering diploma holders working in the projects should
be conversant with the various aspects of managing the resources. This course is designed to develop
competencies in the diploma holders and enable them to manage the resources efficiently at construction
projects.

2. COURSE OUTCOMES (COs)

At the end of this course, student will be able to: -


1. Illustrate principles and functions of management at civil engineering work.
2. Plan construction activities with bar chart method
3. Schedule the project with network method.
4. Carry out inventory control with respect to store
5. Develop qualities of leader as a personnel manager
6. Apply safety measures at construction industry.

265
3. DETAILED CONTENTS: THEORY

Unit Unit Outcomes (UOs) Topic and Sub-topics C Hr Marks


(In cognitive domain) O
No
1. 1b. .Describe the role of 1.1 Role of construction industry 1 10 14
Management construction industry in in national development.
Principles and national development Different small scale
functions 1b. Difference between industries related to
management and construction, Special
administration characteristics of civil
1c . Apply principles of engineering work
management to 1.2 Concept of management and
construction work. construction management
1d.Carry out functions of Difference between
management at management and
construction work. administration,
1e.Compare various types of 1.3 Principle of management and
organization its application to construction
work.
1.4 Functions of management
and its application to
construction work
1.5 Definition and need of
organization—span of control,
,Types of organization— line,
line and staff, functional
organization. Organization
suitable for construction firm
2. 2d. Prepare WBS of 2.1 WBS-(Work Breakdown 2 05 08
Bar Chart construction project. Structure) –Concept, WBS of
Method of 2e. Enlist various activities Civil Engineering Project.
scheduling of the project 2.2 Listing Broad Activities for a
2f. Prepare the bar chart for work & allotting time to it
The project 2.3 Methods of scheduling
2d Show the progress of (planning) the project
project on bar chart 2.4 Bar chart-Development of bar
2e Illustrate merits & charts, Bar chart for
limitations of bar chart construction project with
examples
2.5 Merits and limitations of bar
chart

266
3 3d. Draw the network for 3.1 Elements of Network: 3 18 24
Network a given project Event, activity, dummy
Methods of 3e. Calculate event times activities, Precautions in
Scheduling in network drawing network,
3f. Calculate different 3.2 Event Times by Forward Pass
activity times in a & Backward Pass
network. Calculation
3d .Calculate different 3.3 CPM networks— activity
floats of various time estimate, start and finish
activities time of activity, project
3e. Mark the critical path duration, Floats—Types of
and find project Floats —Free, independent &
duration. total floats , critical activities
3f Calculate PERT times & critical path , combined
and project duration. tabular calculations,
3g Calculate cost slope of 3.4PERT—Three Time Estimates
various activities. ( Optimistic , Pessimistic &
3h.Carry out cost Most likely time )
optimization of small 3.5Comparison among BAR chart
project CPM and PERT.
3i. Carry out recourse 3.6 Project Cost- Direct cost,
leveling for labor Indirect cost, Total cost,
components in a small Optimum cost, Normal Time
project & Normal Cost ;Crash Time
& Crash Cost ,Cost slope .
3.7 Cost optimization-
crashing a simple network
consisting maximum 06
activities.
3.8 Necessity of Resource
allocation/leveling. Procedure
of resource leveling of labors,
Resource leveling of labor for
a simple project consisting
maximum six activities
4. 4a.Illustrate functions of 4.1 Necessity of material 4 05 08
Material material manager management ,Functions/duties
Management 4b.Carry out inventory of material manager.
control by ABC technique 4.2 Inventory and inventory
4c.Calculate EOQ control, ,A-B-C technique of
4d.Illustrate the process of inventory control,
indenting. 4.3 Inventory order cost and
inventory carrying cost,
Economic Order Quantity
(EOQ) – Analytical &
Graphical calculation of EOQ
4.4Maintenance of store—
Indenting , receipt & issue of
materials different types of
forms used

267
5 5a. Illustrate functions of 5.1 Personnel Management— 5 05 08
Human personnel manager Functions of Personnel
Resource 5b Compare theory X and Manager, Human Needs &
Management theory Y of Maslow’s Need Hierarchy
communication with examplesTypes of labor
5c Compare various types of –Skilled, semiskilled and
leadership unskilled labor.
5.2 Motivation – McGregor theory
X & theory Y, Importance &
Types of motivation-Intrinsic
and extrinsic
5.3 Leadership ,Qualities of a
Good Leader, Types/styles of
leadership—Autocratic,
Democratic & Free-rein,
6.Safety in 6a Apply safety measures in 6.1 Importance Safety in 6 05 08
Construction construction project Construction Industry
Industry 6b.Identify causes of 6.2 Causes of Accidents,
accidents in construction Remedial & Preventive
industry, remedial and Measures,
preventive measures 6.3Measurement of Accidents—
6c. Measure the accident Direct Cost, Indirect cost
cost. ,Injury Frequency Rate ,Injury
6d. Illustrate provisions in Severity rate
differ important labor 6.4 Introduction to important
laws laws related to construction
industry, Provisions in revised
factory Acts, minimum wages
acts, workmanship
compensation acts.

4. LIST OF PRACTICALS:

Sr PRACTICAL OUTCOMES (PrOs) CO


No. NO.
Prepare the organization chart of any one government/public sector organization
1 1
executing any major civil engineering projects in your area.
Prepare the organization chart of any one private organization executing any
2 1
major civil engineering projects in your area.
Check the breakdown structure of a typical construction project to justify its role
3 2
in managing the relevant activities.
4 Prepare the bar chart for given construction project. 2
5 Prepare the time schedule of different activities for practical no 4 2
Prepare a network for given construction project to identify the critical activity in
6 3
a project.(to develop the critical path)
7 Compute activity times, event times and floats for above network 3
8 Carry out cost optimization of the given project. 3
9 Carry out labor resource levelling for the given project 4
10 Carry out the ABC analysis of the given items in a store. 5