This document provides design details for a syphon aqueduct, including: 1) Design data such as discharge rate, canal dimensions, and Manning's coefficient. 2) Calculations for the drainage waterway including perimeter, number of piers, and syphon barrel dimensions. 3) Dimensions for the flumed canal waterway including width ratios and transition lengths. 4) Design of the canal bed level to maintain a flow depth of 2 meters, including cross-section dimensions and velocities. 5) Design of the transition including length calculations based on bed width.

Uploaded by

ale hopeju2009
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
401 views4 pages

CD Work

This document provides design details for a syphon aqueduct, including: 1) Design data such as discharge rate, canal dimensions, and Manning's coefficient. 2) Calculations for the drainage waterway including perimeter, number of piers, and syphon barrel dimensions. 3) Dimensions for the flumed canal waterway including width ratios and transition lengths. 4) Design of the canal bed level to maintain a flow depth of 2 meters, including cross-section dimensions and velocities. 5) Design of the transition including length calculations based on bed width.

Uploaded by

ale hopeju2009
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Design of a Syphon Aqueduct i) Design Data Data Canal Stream Unit

Discharge 30 Bed Level 200 Canal FSL 202 bed width 25 canal side slopes(m) (m:1 V) 1.5 stream high flood level general terrain level = 200.00m AOD Manning coefficinet,n 0.014 ii)Drainage Waterway Perimeter, P=4.75Q1/2 Assuming; spam width of each Piers thickness Therfeore provide; 12*1.5+13*7=106m No of piers= No of span= Assume velocity through syphone barrel barrel height=

3 500 m /s 198 m asl m asl

200.5 m asl

106 m 7m 1.2 m 12 13 2 m/s 2.75 m

iii) Canal Waterway

The canal shall be flumed Adopt flume ratio Flumed canal width= Canal width*Flum ratio= Splay in contraction; 2:1 Transition length in contraction=2*(25-12.5) Splay in expansion; 3:1 Transition length in expantion=3*(25-12.5) Length of trough from abutment to abutment=

0.5 12.5 2 12.5 3 18.75 106

iv) Design of Canal bed level to keep flow depth of 2m(given) Section

4--4 Width (m) Area of Flow (m2) Velocity (m/s) Losses(m) Water surface level Velocity head TEL Flow depth (m) Bed level 25 56 0.535714 0.018 202 0.015 202.015 2 200

3--3 12.5 25 1.2 0.017 201.959 0.073 202.032 2 199.959

2--2

1--1 12.5 25 25 56 1.2 0.535714 0.012 202.047 0.015 202.061 2 200.047 Vf= Lf= n= A= P= R= HL=

201.976 0.073 202.049 2 199.976

v) Design of Transition the distance x from the tration for a bed width Bx of the transition is ; (UPIRI,1940) where L= length of transition

Bx (m) x(m) for contraction x(m) for expansion

12.5 15 17.5 20 22.5 0 4.626721 7.663401 9.78221 11.3295 0 6.940081 11.4951 14.67331 16.99425

25 12.5 18.75

Vi) Water Surface Profile in Transition

1.2 106 0.014 25 16.5 1.515152 0.017192