Risk Assessment For Excavation Slope
Risk Assessment For Excavation Slope
or activity:
Component or
Sloping of Excavation Rev. Sheet no. 1 of 9
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Sloping of Excavation Rev.
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
Workers,
• Method statement to be explained to all
Failure to communicate RAMS Foreman, employees and copy made available at the site.
necessary control measures - Engineers,
2 4 P AR • The risk assessment shall be communicated to 2 UL A
Injury to personnel and damage Supervisor,
to property Operators and all personnel involved in the job.
workers
• The engineer/supervisor should communicate
the work scope to be done. Outline the hazards
& control measures through comprehensive daily
TBTs.
• Pre-Task Activity Briefing Shall be conducted by
the site supervisor prior to start any activity.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
R = Rare – unlikely to occur risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
aspect of work:
Sloping of Excavation
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
R = Rare – unlikely to occur risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Sloping of Excavation Rev.
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
R = Rare – unlikely to occur risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Sloping of Excavation Rev.
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
R = Rare – unlikely to occur risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Sloping of Excavation Rev.
aspect of work:
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Name of project
Component or
Sloping of Excavation Rev.
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
• Do Not attempt to extinguish any fire if
you are not trained. Immediate leave
the area and ask for help of trained
personnel.
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
R = Rare – unlikely to occur risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Name of project
Component or
Sloping of Excavation Rev.
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
Health & safety severity: Likelihood: Assessed Severity Name & signature Date
R = Rare – unlikely to occur risk: 1 2 3 4 5
1 = Very Low – no injury, 2-man days LTI
Prep’d:
UL = Unlikely – unlikely but possible R N N A A A
2 =Low – minor ‘first aid’ injury, 2-4 days LTI
M = Possible – possible at some time UL N A A AR AR
3 =–Medium several causalities that might require hospitalization with long term effect Rev’d:
H =Likely – likely to occur several times P A A AR AR UA
5 to 15 man-days (LTI)
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible
Sloping of Excavation Rev.
aspect of work:
Initial assessment Residual risk
Serial Who or what may be
Nature and possible effects of a hazard Likelih Ass'ed Risk control measures Likelih Ass’ed Comments
no. affected? Severity
ood risk
Severity
ood risk
Likelihood
AC = Frequent – likely to occur many times L A AR AR UA UA
4 =High – •Would cause serious causalities result in long term physical impairment of personnel
•Incident resulting in complete stop of work for more than 2 weeks
5 =Very High – • Would cause serious causalities result in serious Injuries or loss of lives. AC A AR UA UA UA
Incident resulting in complete shutdown of operations
Acceptability of assessed risks: UA = Unacceptable (action essential) AR = Action required (if reasonably practicable) A = Acceptable (manage risk) N = Negligible