GS 2020 Amd No 2024 - 01 - 240730
GS 2020 Amd No 2024 - 01 - 240730
2020 Edition
VOLUME 1
SECTION 6 EARTHWORKS
APPENDIX 6.3
(a) Appendix 6.3.2 Replace “Method 10.1 or 10.2” with “Methods 10.1, 10.2, 10.5 or 10.6”
after “Test” in item (a).
(b) Appendix 6.3.3 Replace “10” with “13” after “The size of the sample shall be sufficient
to yield a minimum of” in the first paragraph of item (a).
Replace “four” with “five” after “by using a riffle box to obtain a
minimum of” in item (e).
Replace “Clause 10.1.5 or Test Method 10.2, Clause 10.2.5” with “Clause
10.1.5, Test Method 10.2, Clause 10.2.5, Test Method 10.5, Clause 10.5.5
or Test method 10.6 Clause 10.6.5” after “in accordance with Geospec 3,”
and “(wi)” with “(w)” after “The in-situ moisture content of the slice” in
the second bullet point of item (i).
Add “approximately” before “4% of the mass of the specimen” and “2%
of the mass of the specimen” in item (l).
(c) Appendix 6.3.4 Replace “value of the moisture correction curve passing through the peak
value of the plotted parabolic curve” with “moisture content adjustment
value” in the second bullet point of item (3).
(d) Appendix 6.3.5 Add the following item after item (f):
(g) The difference between optimum moisture content and the in-situ
moisture content to the nearest 0.1%, if determined.
APPENDIX 6.4
(e) Appendix 6.4.3 Add the following at the end of item (e):
APPENDIX 6.5
(g) Appendix 6.5.1 Delete “soil with particle size distribution within the range stated in Table
6.5.1 as a percentage of the mass of the dry soil” after “the moisture
content of” in the first paragraph.
Add “with convection heating” after “by infrared oven drying” in the
first paragraph.
(a) An infrared oven with convection heating and with a suitable power
control device and ventilation, capable of maintaining oven
temperature at 105 ± 5 °C and meeting the following performance
requirements: -
(i) the difference of mass of the test specimens(1) taken in 3 hours and
3½ hours after drying in the infrared oven shall be less than 0.1%
of the original wet mass of the test specimens;
Note: (1) Test specimens used for verifying the performance of the
infrared oven should have a minimum moisture content
of optimum moisture content plus 3%.
Replace “be at least 300g and in no case be greater than 350g.” with
“follow Clause 5.1.4 of Test Method 5.1 of Geospec 3.” after “a test
specimen shall” in item (b).
with
(k) Appendix 6.5.5 Replace “the nearest 0.1%.” with “two significant figures for values up to
10% or to the nearest whole number for values above 10%.” in item (b).
MATERIALS
(l) Clause 7.140 Replace the heading with “Repairs to galvanized coating”.
VOLUME 2
SECTION 17 PRESTRESSING
MATERIALS
(m) Clause 17.07 Add the following item after item (2):
(n) Clause 17.37 Replace “, and” with “and couplers for joints in prestressing tendons,” in
item (c).
(g) For external tendons, in case the vents cannot be placed because of
encroachment upon the diaphragm/deviator block, vents should be
installed on both sides of the diaphragm/deviator block. For
anchorage locations, vents should be provided at the other side of the
diaphragm.
(o) Clause 17.45 Replace the paragraph with the following paragraphs:
(1) Grouting of prestressing tendons shall be effective such that the duct
and anchorage are completely filled, and the prestressing tendon is
completely surrounded, with grout. Vacuum-assisted grouting shall be
adopted. For vacuum-assisted grouting, a negative pressure of no less than
0.75 bar shall be maintained within the tendon duct for at least one minute
before the injection of grout and throughout the whole grouting operation.
(4) The inspection of the quality of grout detailed in sub-clauses (2) and
(3) shall be conducted by an experienced person from an organization
independent of the main contractor and prestressing works contractor, and
shall possess at least three years of experience in the inspection of grouting
quality at ducts.
(p) Clause 17.46 Add “In case grouting cannot be carried out within 5 days after tensioning
of the prestressing tendons, temporary corrosion protection measures
should be implemented. The Contractor shall submit proposal of
corrosion protection measures to the Engineer for approval before
commencement of tendon prestressing works.” at the end of item (2).
(13) The Contractor shall employ on the Site in connection with execution
of grouting works for prestressing systems an experienced site personnel
who is required to supervise, witness and take record of the whole grouting
process of each tendon. The site personnel shall record the sequence of
work and check against the prescribed method statement. Any anomaly
shall be recorded and investigated. The record shall be countersigned by a
supervising engineer and submitted to the Engineer within 3 days of each
grouting operation.
(a) Name,