EEC 2nd Chapter Notes
EEC 2nd Chapter Notes
Explanation:
1) Electrical installation should be electrically and mechanically safe. All precautions
should be taken.
2) Life of installation should be long.
3) Appearance should be good and decorative.
4) It should be economical
5) Maintenance & repairing should be simple and less.
6) Future expansion can be easily done.
7) For the better requirement the selection of wires, wiring method and wiring
accessorieswith our economy is also very important
8) Precautions should be taken to prevent leakage of water into installation rooms.
9) Provide proper clearance for cable and Follow minimum wire bending.
1. Energy meter and switch board should install near to each other.
2. The place selected for energy meter should cover to provide protection against rain and
8. All incandescent lamps, unless otherwise required, are to be hung at a height of 2.5
meters above the floor level. And ceiling fans are to be hung 2.75 meters above the floor.
9. Each light sub-circuit is not to have more than a total ten points of lights, fans and socket-
outlets. The load on each sub-circuit is to be restricted to 800 watts.
10. Each power sub-circuit is not to have more than a total of 2 points. The load on each sub-
circuit is to be restricted to 3000 watts.
11. In 3- phase, 4 wire installation the load is to be distributed equally on all phases.
12. Switches and fuse should connect in live wire.
13. Location of the main switch board should such that it is easily accessible to any person
to quickly disconnect the supply in case of emergency.
14. 5 A switch and socket should be used for light load and 15 A switch and sockets used for
power load.
15. Light point should be located 0.5 m below ceiling.
16. Each sub-circuit is to be protected against excessive current (that may occur either due
to over load or due to failure of insulation) by fuse or automatic circuit breaker.
17. Earth Resistance: should be very low for domestic installation it should be equal to or
less than 5 ohms to 8 ohm
1) Cleat wiring
2) Batten wiring
1) Cleat wiring:
The cost of wiring is less. The PVC or VIR wires are carried through porcelain
cleats. This wiring is very simple and used for temporary application. The wires are
exposed to the sky, so there are chances of mechanical injury. This type ofwiring is rarely
used.
The cost of wiring is also less but more than cleat wiring. The PVC or VIR wires
are carried through batten. This wiring is very simple and now a day it is rarely used. More
number of wires can be carried through the batten. Wires are exposed to thesky, so there are
chances of mechanical injury. Fault finding is easy.
The cost of wiring is more. The PVC or VIR wires are carried through wooden
casing capping. This wiring is very simple but due to high cost and now a day it is rarely
used. More number of wires can be carried through the wooden casing capping. Wires are
The cost of wiring is slightly more. The PVC or VIR wires are carried through
PVC casing capping. This wiring is very simple so it is widely used. More number ofwires
can be carried through the different size of PVC casing capping. Wires are not exposed to
the sky, so there are less chances of mechanical injury. Future expansion is possible and
repairing and maintenance is easily possible.
Area of application-Offices and commercial places.
6) Concealed wiring:
The cost of wiring is very high. The PVC or VIR wires are carried through thechannels
made in ceilings and walls at the time of building construction. This wiring is slightly
difficult but appearance is very good, so it is widely used. More number of wires can be
carried through the different size of channels. Wires are not exposed to the sky, so there
are less chances of mechanical injury. Fault finding is difficult. Future expansion is not
possible and repairing and maintenance difficult.
Area of application- Office building.
12) MCB: Miniature circuit breaker operates automatically at the time of fault or over load.
And it is used for the protection of electrical installation. They are available from 0.5 A to 100
Amps. They can be single pole, Double pole or three poles.
13) Socket outlet of plug : To give the supply to the load by using supply pins and
also provided inelectrical installation for adopting or connecting home appliances.
14) ICDP: ICDP means Iron clad Double pole. Its function is for cut off operation of
single phase supply.
15)Conduit: To run the wires from switch board to appliances.
OR
State the sequence followed to prepare appropriate estimation for residential installation.
OR
Mention general rules used for wiring of residential installation.
1) Find out the total electrical load for the given residential installation.
2) Differentiate this total electrical load in lighting load and power load.
3) Make the no. of lighting sub circuit for lighting load.
7) Determine the size of wire required for every sub circuit by considering overload starting surge and
future expansion.
8) Draw the single line diagram.
9) Mark the batten on plan layout.
10)Find out the total length of batten or (conduit) required for every sub circuit and whole residential
installation.
11) Find out the total length and size of wire required for every sub circuit.
12) out the material required for whole residential installation.
13) Find out cost of material and labour in estimation chart.
14) Find out the total cost of estimation with profit margin and contingencies charges.
15) Find out per point charges.
16) Draw the circuit diagram.
1) Electrical cables: You will need electrical cables to carry the electrical current throughout the
house. The most common types used are non-metallic sheathed cable (NM), also known as Romex,
which consists of insulated wires bundled together.
2) Circuit breakers: Circuit breakers protect the electrical circuits from overload or short circuits.
They come in various sizes and ratings to match the specific requirements of each circuit.
5) Conduit and fittings: Conduit is a protective tubing used to encase electrical wires in areas
where they may be exposed or subject to damage. Common types include PVC conduit and metal
conduit. Fittings are used to join and secure conduit sections together.
6) Wire connectors: Wire connectors are used to join or terminate wires. They provide a secure
and insulated connection and come in various types, such as wire nuts, crimp connectors, and
terminal blocks.
7) Electrical tape: Electrical tape is used to insulate and protect wire connections. It helps prevent
accidental contact with live wires and ensures electrical safety.
8) Wire staples and fasteners: These are used to secure electrical cables andconduit to walls,
ceilings, or other surfaces.
9) Wire strippers and cutters: These tools are necessary for removing insulationfrom wires and
cutting them to the desired length.
10) Screwdrivers, pliers, and wrenches: Basic hand tools are needed for various installation
tasks, such as tightening terminal screws, bending wires, and securing fittings.
Equipment’s Used in Residential Installation
Fan, Tube lights, Refrigerators, washing machine, Electric Heaters, etc
Each sub circuit should not have more than a total 10 points (including lights, fans and 5A
socket outlet)
Each sub-circuit should not exceed 800 watts.
2) Power Circuit:
ii) For power load there should be maximum 3000W for 2 to 3 points.
iii) Make the no. of power sub circuits for power load using following formula
OR
Total No.of power points
No. of power Sub circuits
2
Numerical
1320 20
= 𝑜𝑟 = 2 sub-circuits
𝑃𝑜w𝑒𝑟 𝑙𝑜𝑎𝑑 4000
No. of power sub-circuit = = = 1.33 2 sub-circuits
4. Size of distribution board
Since there are 2 lighting sub-circuits and 2 power sub-circuit, we require 4 way
distribution board. It includes main MCB with other 2 MCBs for lighting sub-circuits and
2 more MCBs for power sub-circuits.
1) Draw the wiring diagram for the residential load shown in Fig. No. 1
MB-Main Board PS-
Power Socket
Assume one socket on each switch board
Ans:
2)Calculate the length of phase wire & neutral wire for the residential
installation as shown inthe Fig. No. 1.
Ans:
Assumptions:
There will be two sub-circuits; One is lighting and other is for power socket.
Starting from Main Board (MB), the length of conduit required for lighting sub-
circuit is
Where, H represents horizontal run on wall or ceiling and V represents vertical run on
wall, may be up / down
= 19.75 m
Starting from Main Board (MB), the length of conduit required for power socket is given
by,
= 1(H)+2.5(H)+1(Vdown)
Remark: Initial Vertical up run of 0.75 m is already considered in lighting sub-circuit)
= 4.5 m
Total length of phase & neutral wire (1 mm2) for lighting sub-circuit:
Total length of phase & neutral wire (2.5 mm2) for power socket:
= 5.25 + 5.25 + 10% = 10.5 + 1.05 = 11.55 m 12 m
3)Estimate the quantity of material and cost of installation required for the PVC casing
capping wiring system used in house. The plan of which is shown in figure No. 1. Assumeheight
of roof 4m. One plug point is to be provided in each room and power socket in
Bathroom.(w.18)
Total load in Hall= tubes in Watt+ Fans in Watt +Lamps in WC & Bath+ Plug Socket+ Power
socket
i) Total load in Installation = 80 +120 + 80 + 200 +1000 = 1480 watt
1480
ii) Total load in Amps = = 6.43 or 7 Amp
230
So Use,
230V, 16A, ISI mark Main switch of any company and lighting load 480 watt & 6
points & one power in bath room
Therefore one lighting & Power sub circuit is required
Wiring Layout:
V H H V H H H H H
= 11.5 + 10 + 10%
= 24 3 + 20%
= 72 + 20%
= 72 + 14.4
= 86.4 87 Mtr
Schedule of Material:
1 ICDP 250V, 16A 01 250.00 250.00
2 20A MCB for Power load 01 175.00 175.00
3 6A MCB for lighting load 01 45.00 45.00
4 PVC conduit (3 Mtr pipe) 1.5mm 24 Mtr 15.00 360.00
thickness
5 1 Sqmm Copper Wire (90 mtr bundle) 01 mtr 650.00 650.00
6 2.5 Sqmm Copper Wire 20 Mtr 12.00 240.00
7 Copper Earthing Plate 01 490.00 490.00
8 Earthing Sundry lumsump 200.00 200.00
9 6A Switch 08 15.00 120.00
10 6A Three point socket 02 18.00 36.00
11 16 A Power socket 01 55.00 55.00
12 Ceiling rose 04 10.00 40.00
13 Angle holder 02 10.00 20.00
14 Junction Box 08 10.00 80.00
15 4 x 4 Switch board with cutting 03 20.00 60.00
16 25 x 8 screws 01 35.00 70.00
17 Raval plug 03 05.00 15.00
18 Labour Charges 08 110.00 880.00
Total Amount :- 3786.00
Commercial Installation
Q. Explain the design consideration and guidelines for the electrical installation in
commercial building.
OR
State the sequence followed to prepare the estimate for commercial electrical
installation.
Numerical:
Draw single line diagram showing the position of switches and fittings. Prepare the list of
material required for class room wiring.
Ans:
Assumptions:
1. Switch Board at the height of 1.5 m from ground level.
2. Conduit runs at the height of 3.5 m.
3. Main Board (MB) is at the height of 1.75 m
4. Tube T1 at the height of conduit run i.e. 3.5 m. Other all tubes at height of ceiling
5. Plug point present in each Switchboard
i) Total Load:
09 Fluorescent tubes each of 40 W =09x40= 360 W
1) Total Load
a) Lighting & Fan:
12 Fluorescent tubes each of 40 W =12x40= 840 W06
Fans each of 60 W = 06x40 = 240 W
08 No. of 5 Amp Sockets = 08 x 100 = 800WL & F Total=1880 W
b) Power Load:
02 No. of 15 Amp sockets = 02x1000=2000 W
Total =1880+2000= 3880 W
1) Sizes of wire
Sub circuit No. Wire
L & F sub circuit No. I, II,III 1/1.40mm, 1.5 mm2Aluminium conductor or
equivalent
Assumptions:
Wiring is casing capping type
Height of EM-MS-MDB from floor- 2m
Height of switch boards from floor-1.5 m
+(1x3)+(1x4)+(1x2.5)+(2x2.5)+(2x2)+(1x3)
= 58.5 m
(b) Neutral wire for Sub circuit No II
=1+1.5+4+4+1.5+1+8+2.5+(3x3) =32.5 m
Total for L & F circuit
Schedule of material:
Sr. Quantity
Description of the material Unit
No. required
1 ICDP, Main switch, 36A, 250V 1 No.
2 MDB, 4 way, 15 A per way, 250 V 1 No.
3 PVC casing capping 100 m
1/1.40mm, 1.5 mm2 Aluminium conductor or
4 325 m
equivalent
1/1.80mm, 2.5 mm2 Aluminum conductor or
5 33 m
equivalent
1/2.24mm, 4 mm2 Aluminum conductor or
6 1 m
equivalent
7 5A socket 8 No.
8 5 A switch 26 No.
9 15A socket 2 No.
Service connection:
Explanation:
Bare over head conductors are used for the service line when the consumer premises are
more than 45 meter away from the supplier’s distribution pole.
The GI wire is stretched between the pole and the GI pipe which is fixed near to the building.
With the help of GI wire ( 8 SWG) whether proof cable is laid byusing the ring (bobbin)
insulator.
For supporting the GI pipe stay wire and stay Bow is used.
The minimum height of the service wire from the ground level is according to
IE rule i. e 5.7 meter from the ground level for low voltage.
OR
1. 4 Sqmm x 2 core PVC insulated cable or insulated wire 70 mtr length : (Size of cable is
5. Stay wire 3 m
7. cement 01 Bag
8. sand 01 Bag
10. GI pipe 01 No
Explanation:
Generally for thickly populated cities or for factory premises underground service
connection is preferred.
Normallyundergroundcableislaid1meterbelowthegroundlevel.
For laying of cable, cable trench is used and with the help of bricks and sand cable is laid.
In underground service connection armoured or unarmoured cables are used according to
requirement.
Service cable is connected to the distribution line through a cable joint box, mounted on
the supplier’s distribution pole.
If the proper protection against mechanical damage is to be provided then it is run through GI pipe
or MS pipe
3. If cable is laid across the public road then Cement pipe, DWC pipe or GI pipe is
required for better protection of cable
4. Cable lug as per required size.
6. Feeder piller or cable box or bus bar and cable end box.
8. Cable bushing.
9. 8 SWG Wire
11. As such all service connection material like main switch, MCB, Energy meter, Neutral
link, IC cut out, earthing nut, screws, and wooden board. Etc
2. Appearance is good
5. More safety
1. Cost is more
Important Questions
6) For a residential building prepare the list of electrical wiring installation material
required along with electrical apparatus used in the residential building.6 marks
7) Explain the design consideration and guidelines for the electrical installation in commercial
building. 4marks
8) List any Four examples of Commercial Unit- 2 marks
9) Compare residential and commercial wiring. 2 or 4 marks
10) Explain overhead service connection with neat diagram.-4 marks
11) Explain underground service connection with neat diagram.-4 marks
12) Compare overhead and underground service connection on any eight points.-4 m
13) Numerical on to calculate total lighting sub circuit and power sub circuit -4 marks
14 Numerical on residential installation-6marks
15) Numerical on commercial installation -6 marks