0% found this document useful (0 votes)
17 views146 pages

Standard Theory Test Questions A41 A66 Tcm17 10107

The document outlines a technical test for various construction machinery, including loaders, crushers, and concrete pumps, detailing questions related to safety, operation, and regulations. It covers topics such as risk assessments, health and safety duties, environmental impact, and operational procedures. Each section includes specific questions that assess the knowledge required for safe and effective machinery operation in construction settings.

Uploaded by

john.woosey48
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views146 pages

Standard Theory Test Questions A41 A66 Tcm17 10107

The document outlines a technical test for various construction machinery, including loaders, crushers, and concrete pumps, detailing questions related to safety, operation, and regulations. It covers topics such as risk assessments, health and safety duties, environmental impact, and operational procedures. Each section includes specific questions that assess the knowledge required for safe and effective machinery operation in construction settings.

Uploaded by

john.woosey48
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 146

Technical Test – Questions

Contents

A41 Loader Compressor


A42 Crusher
A43 Screener
A44 Concrete Pump – Trailer Mounted
A45 Piling Rig – Driven below 15 tonnes
A46 Piling Rig – Driven above 15 tonnes
A47 Piling Rig – Bored below 15 tonnes
A48 Piling Rig – Bored above 15 tonnes
A49 Loader/Securer – Non-STGO
A50 Loader/Securer STGO
A56 Dump Truck – Articulated Chassis
A57 Dump Truck – Rigid Chassis
A58 Excavator 360° below 10 tonnes
A59 Excavator 360° above 10 tonnes
A60 Mobile Crane
A61 Appointed Person – Lifting Operations
A62 Crane/Lifting Operations Supervisor
A63 Pedestrian Operated Tower Crane
A65 Demolition Plant
A66 Compact Crane

CPCS Technical Test – Questions Contents


© Construction Industry Training Board 2008 11-07-2008
Loader Compressor A41
Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of The Health and Safety at Work Act must employees follow?

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations.

8. Plant operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A41 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Loader Compressor A41
Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a loader
compressor?

A
Roles and responsibilities continued

11. The operator has to fit and use a new bucket using a quick-hitch coupler that they are
unfamiliar with. What do Regulations (i.e. PUWER 98) and other guidance require the
operator to have?

12. What are the possible outcomes if being prosecuted (by judicial bodies) for not complying
with legislation and regulations?

13. How can a qualification or card benefit a plant operator?

14. Name THREE ways that a plant operator can contribute in ensuring repeat business with
the client or main contractor.

15. Where should the machine’s Operator’s Manual be kept and why?

A
Preparing for work

16. If the operator has to refill the fuel tank, state TWO precautions to ensure cleanliness of the
system.

17. What is the purpose of a roll or ROPS frame?

continued…

CPCS Technical Test – A41 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Loader Compressor A41
Technical Test – Theory

For questions 18 and 19 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

18. Using the Operator’s Manual, state the figure for the tyres’ operating pressure.

19. Using the Operator’s Manual, state the cold-starting procedure for the machine.

20. What is a possible consequence of using a tyre with a deep cut in the sidewall?

21. If checking the oil level using a dipstick, why must gloves be worn?
Preparing for work continued

22. How is a compressor output calculated?

23. What is the typical working pressure of an air operated breaker?

24. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

25. When air is compressed, what fluid is produced?

26. What is the purpose of the compressor’s pressure relieve valve?

27. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

CPCS Technical Test – A41 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Loader Compressor A41
Technical Test – Theory

28. An operator has to travel the machine on the public highway. List SIX requirements that
must be followed.

29. If the loader compressor is being travelled or working on the public highway, including
adjacent pavement and verges, The Road Traffic Act applies. a) What type of licence and
which classes should the operator hold and b) what is the minimum age allowed?

A
Travelling and manoeuvring

30. Name THREE conditions that mirrors must be in, on the machine.

31. Why must the seat belt be worn, even with the cab door closed?

32. What problems and hazards can soft ground cause to a loaded loader compressor?

33. Give FOUR reasons that may cause the loader compressor to tip over sideways.

34. Whenever possible, who should decide the positioning of a vehicle to be loaded?

A
Setting up for work

35. Explain ALL visual checks that must be carried out on all types of quick-hitch bucket
attaching systems before use.

CPCS Technical Test – A41 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Loader Compressor A41
Technical Test – Theory

36. On a semi-automatic quick-hitch bucket attaching system: a) what is the purpose of the
safety pin and b) what checks MUST be made to the pin before use?

37. Why should air hosing length be kept to a minimum?

38. Give THREE possible reasons why loader compressors should not stray off the designated
haul routes.

39. Describe ONE physical method of checking that the attachment is fully secured to the
coupler prior to work.

A
Setting up for work continued

40. a) What is meant by ‘white finger’ and b) name TWO methods of reducing the effect?

41. If setting up to work in a pedestrianised area, state THREE factors that need to be taken
into account?

42. If using a compressed air tool to break up a concrete type surface, list FIVE items of PPE
that must be worn.

43. What is regarded as the most productive position for a vehicle to be loaded to be in when
being loaded from a stockpile?

44. Before manually changing any bucket: a) where should the bucket be positioned (in relation
to the ground) before removing the final pin and b) why?

continued…

CPCS Technical Test – A41 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Loader Compressor A41
Technical Test – Theory

45. Give TWO reasons why the loader compressor operator should have an understanding of
Setting up for work

the type of material being loaded.


continued

46. The operator is asked to tip material into a trench. State FIVE different requirements that
must be considered or implemented before tipping commences.

47. Who should determine the maximum load that should be placed into the body of a vehicle
being loaded?

48. If a load has to be tipped on a slope, what may happen if the load is tipped downhill and
why?
Working tasks

49. When working in a confined area or space, name THREE hazards that can occur.

50. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when tipping loads and b) explain why a distance should
be kept.

51. State TWO requirements of using a stop block or earth bank (berm) at a trench discharging
point.

A
Completing work

52. Before leaving the cab for a rest break, after parking and switching off the machine, what
final action must be carried out?

CPCS Technical Test – A41 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Loader Compressor A41
Technical Test – Theory

53. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

54. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.

A
Shutdown

55. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, what
checks must be carried out before they leave the cab?

56. Why should a loader compressor be re-fuelled at the end of the day?

CPCS Technical Test – A41 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Crusher A42
Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of the Health and Safety at Work Act must employees follow?

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations.

8. Plant operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A42 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Crusher A42
Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a crusher?

11. The operator has to use a new type of crusher that they are unfamiliar with. What do
Regulations (i.e. PUWER 98) and other guidance require the operator to have?
Roles and responsibilities continued

12. What are the possible outcomes if being prosecuted (by judicial bodies) for not complying
with legislation and regulations?

13. Give TWO examples of where The Work at Height Regulations 1995 may apply to crusher
operations.

14. How can a qualification or card benefit a plant operator?

15. Name THREE ways that a plant operator can contribute in ensuring repeat business with
the client or main contractor.

16. Where should the crusher’s Operator’s Manual be kept and why?

A
Preparing for work

17. If the operator has to top-up the hydraulic oil, state TWO precautions to ensure cleanliness
of the system.

continued…

CPCS Technical Test – A42 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Crusher A42
Technical Test – Theory

For questions 18 and 19 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

18. Using the Operator’s Manual, state the procedure for adjusting conveyor belt tension.

19. Using the Operator’s Manual, state the cold-starting procedure for the machine.

20. If checking the oil level using a dipstick, why must gloves be worn?

21. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

A
Preparing for work continued

22. What is the purpose of the sizing bars on the crusher feed?

23. Name a) THREE differences between ‘cone’ and ‘jaw ‘type crushers and b) ONE suitable
application for each.

24. Name THREE requirements of the Noise at Work Act 1994 that apply to crusher
operations.

25. Name FIVE items of specific PPE applicable to crusher operations.

26. What are the THREE actions or stages that a crusher operator undertakes during pre-use
inspections?

continued…

CPCS Technical Test – A42 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Crusher A42
Technical Test – Theory

27. Name the FOUR key causes of accidents that occur during crushing operations.

28. When would a harness be used?

29. a) What is the purpose of a magnetic separator and b) where would it be located?

30. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.
Preparing for work continued

31. For mobile crushers, when MUST a banksman/signaller be used before moving a mobile
crusher?

32. What problems and hazards can soft ground cause when travelling a mobile unit across a
site?

33. a) What is the minimum distance allowed near open trenches when travelling with a mobile
crusher and b) explain why.

34. Give THREE reasons that may cause a mobile crusher to tip over sideways during travel.

35. Give TWO reasons why the operator should have an understanding of the type of material
being loaded for crushing.
Setting up for work

36. Explain SIX requirements to be taken into account when positioning a crusher prior to work.

continued…

CPCS Technical Test – A42 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Crusher A42
Technical Test – Theory

37. Describe ONE method of how to adjust a cone type crusher to produce the desired
aggregate size.

38. a) Which part of the crusher applies loading or pressure to the ground and b) name ONE
way that pressure can be reduced.

39. As far as is reasonably practical, where should crushing operations be kept clear of?
Setting up for work continued

40. What are the requirements for the ramps that are to be used by loading shovels loading the
crusher?

41. What are the requirements for the standing for loading excavators?

42. If setting up to work near a pedestrianised area, state THREE factors that need to be taken
into account.

43. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when setting up the machine and b) explain why a
distance should be kept.

44. If a trench has a depth of 2.0 metres: a) what is the minimum distance to maintain from the
edge of the trench when forming stockpiles and b) explain why.

45. What FOUR steps should initially be taken should a crusher be blocked before remedial
Working tasks

work starts?

46. Why should the engine speed be set to the manufacturer’s recommendations on magnet
equipped machines?

continued…

CPCS Technical Test – A42 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Crusher A42
Technical Test – Theory

47. Name FOUR possible causes for blockages in crushers.

48. Why is it recommended to leave a layer of material in the feed hopper during loading?

49. A previous, traditional method of clearing blockages was the use of a wedge or mouse.
Explain why this method must not be used.

50. If radios are to be used during the crushing operations, what FOUR actions and checks
must be made by the loading and crusher operators before use?

A
Working tasks continued

51. When using water suppression, where should the water be applied?

52. Apart from water, name THREE other methods that can be used to minimise dust.

53. Name TWO things that can cause ‘bridging’.

54. Name FIVE possible dangers to health if operating the crusher from the platform.

55. During an unblocking activity, even though the crusher may be switched off: a) what else
must be done and b) why?

56. When is it permitted to enter the crushing chamber area?

continued…

CPCS Technical Test – A42 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Crusher A42
Technical Test – Theory

57. What TWO problems can wet weather cause?

A
Working tasks continued

58. If a crusher has appeared to stall, what are the THREE initial steps to take before remedial
work starts?

59. What is the meaning of this hand signal (being demonstrated by the Tester)?

60. What checks should be made to stockpiled materials at the end of a working day?
Completing work

61. Before leaving the machine for a rest break, after switching off the machine, what final
action must be carried out?

62. If parking a mobile unit away from the working area, name THREE places where the
machine should NOT be parked.

63. The crusher operator has been asked to drive a mobile crusher onto a transporter/trailer.
a) Who is responsible for the loading operations and b) state FOUR actions to be
Shutdown

considered by the operator before loading commences.

64. Why should a crusher be re-fuelled at the end of the day?

CPCS Technical Test – A42 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Screener A43
Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of the Health and Safety at Work Act must employees follow?

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations.

8. Plant operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A43 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Screener A43
Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a screener?

11. The operator has to use a new type of screener that they are unfamiliar with. What do
Regulations (i.e. PUWER 98) and other guidance require the operator to have?
Roles and responsibilities continued

12. What are the possible outcomes if being prosecuted (by judicial bodies) for not complying
with legislation and regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to screener
operations.

14. How can a qualification or card benefit a plant operator?

15. Name THREE ways that a plant operator can contribute in ensuring repeat business with
the client or main contractor.

16. Where should the screener’s Operator’s Manual be kept and why?

A
Preparing for work

17. If the operator has to top-up the hydraulic oil, state TWO precautions to ensure cleanliness
of the system.

continued…

CPCS Technical Test – A43 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Screener A43
Technical Test – Theory

For questions 18 and 19 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

18. Using the Operator’s Manual, state the procedure for adjusting conveyor belt tension.

19. Using the Operator’s Manual, state the cold-starting procedure for the machine.

20. If checking the oil level using a dipstick, why must gloves be worn?

21. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

A
Preparing for work continued

22. What is the purpose of the sizing bars on the hopper feed?

23. How does a trommel type screener segregate material?

24. Name THREE requirements of the Noise at Work Act 1994 that apply to screener
operations.

25. Name FIVE items of specific PPE applicable to screener operations.

26. What are the THREE actions or stages that a screener operator undertakes during pre-use
inspections?

27. Name the FOUR key causes of accidents that could occur during screening operations.

CPCS Technical Test – A43 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Screener A43
Technical Test – Theory

28. When would a harness be used?

29. Name THREE types of conveyor that may be used on a screener.

30. a) Where is the spreader located and b) what is its purpose?

31. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.
Preparing for work continued

32. For mobile screeners, when MUST a banksman/signaller be used before moving a
screener?

33. What problems and hazards can soft ground cause when travelling a mobile unit across a
site?

34. a) What is the minimum distance allowed near open trenches when travelling with a mobile
screener and b) explain why.

35. Give THREE reasons that may cause a mobile screener to tip over sideways during travel.

36. Give TWO reasons why the operator should have an understanding of the type of material
being loaded for screening.
Setting up for work

37. Explain SIX requirements to be taken into account when positioning a screener prior to
work.

continued…

CPCS Technical Test – A43 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Screener A43
Technical Test – Theory

38. How should the screener be set up to meet the production output specification?

39. a) Which part of the screener applies loading or pressure to the ground and b) name ONE
ways that pressure can be reduced.

40. As far as is reasonably practical, where should screening operations be kept clear of?

A
Setting up for work continued

41. What are the requirements for the ramps that are to be used by loading shovels loading the
screener?

42. What are the requirements for the standing for loading excavators?

43. If setting up to work near a pedestrianised area, state THREE factors that need to be taken
into account

44. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when setting up the machine and b) explain why a
distance should be kept.

45. If a trench has a depth of 2.0 metres: a) what is the minimum distance to maintain from the
edge of the trench when forming stockpiles and b) explain why.

46. What FIVE steps should be initially taken should a screener be blocked before remedial
Working tasks

work starts?

47. Give THREE possible causes of screen box overload.

continued…

CPCS Technical Test – A43 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Screener A43
Technical Test – Theory

48. What is the effect on the screening operation if the screen box is raised?

49. a) What is meant by roll back and b) how can it be prevented?

50. If radios are to be used during the screening operations, what FOUR actions and checks
must be made by the loading and screener operators before use?

51. If fitted, when using water suppression, where should the water be applied?

A
Working tasks continued

52. Apart from water, name THREE other methods that can be used to minimise dust.

53. Why should discharge stockpiles not be allowed to reach conveyor height?

54. During an unblocking activity, even though the screener may be switched off: a) what else
must be done and b) why?

55. When is it permitted to enter the screening chamber area?

56. What TWO problems can wet weather cause?

57. What is the meaning of this hand signal (being demonstrated by the Tester)?

CPCS Technical Test – A43 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Screener A43
Technical Test – Theory

58. What checks should be made to stockpiled materials at the end of the working day?
Completing work

59. Before leaving the machine for a rest break, after switching off the machine, what final
action must be carried out?

60. If parking a mobile unit away from the working area, name THREE places where the
machine should NOT be parked.

61. The screener operator has been asked to drive a mobile screener onto a transporter/trailer.
a) Who is responsible for the loading operations and b) state FOUR actions to be
Shutdown

considered by the operator before loading commences.

62. Why should a screener be re-fuelled at the end of the day?

CPCS Technical Test – A43 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Concrete Pump A44
Trailer Mounted Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of The Health and Safety at Work Act must employees follow?

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

8. Concrete pump operators are generally regarded as ‘safety-critical’ workers. What does
this mean?

continued…

CPCS Technical Test – A44 Theory Q


© Construction Industry Training Board 2008 Page 1 of 6 11-07-2008
Concrete Pump A44
Trailer Mounted Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. If required, in what situation does a hard hat NOT need to be worn when operating a
concrete pump?
Roles and responsibilities continued

11. The operator has to use a new type of pump that they are unfamiliar with. What do Regulations
(i.e. PUWER 98) and other guidance require the operator to have?

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. How can a qualification or card benefit a concrete pump operator?

14. Name THREE ways that a concrete pump operator can contribute in ensuring repeat
business with the client or main contractor.
A

15. Where should the User’s Manual be kept and why?

16. What are the THREE actions or stages that a concrete pump operator undertakes during
pre-use inspections?
A
Preparing for work

For questions 17 and 18 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate
17. Using the Operator’s Manual, state the tyres’ operating pressure.

18. Using the Operator’s Manual, state the cold starting procedure for the pump.

19. If checking the oil level using a dipstick, why must gloves be worn?

continued…

CPCS Technical Test – A44 Theory Q


© Construction Industry Training Board 2008 Page 2 of 6 11-07-2008
Concrete Pump A44
Trailer Mounted Technical Test – Theory

20. Apart from the operator, who else may need to use the machine’s User’s Manual?

21. What is the purpose of stabilisers on the concrete pump?

22. What is the purpose of the blanking piece?

23. What are the main component parts of a concrete mix?

24. What is the difference between: a) a placement hose and b) a delivery hose?
Preparing for work continued

25. What piece of information would a client need from pump hirer/owner before a hire?

26. What is the function, if fitted, of the mixer paddles?

27. On a piston type pump, what is the purpose of the water bow?

28. Why must the thickness of steel pipelines be checked on a regular basis?

29. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

30. a) Which part of the concrete pump applies loading or pressure to the ground and b) how
can that pressure be reduced?
Setting up for work

31. If setting up to pump concrete in a pedestrianised area, state THREE factors that need to
be taken into account.

continued…

CPCS Technical Test – A44 Theory Q


© Construction Industry Training Board 2008 Page 3 of 6 11-07-2008
Concrete Pump A44
Trailer Mounted Technical Test – Theory

32. What is the purpose of pumping grout through the pipeline?

33. When setting up to work, what should be taken into account for the mixer vehicles?

34. If pipelines have to be connected to scaffolding, what TWO items must be ensured?

35. On what basis are pipelines and couplers selected?

A.

36. Name THREE possible underground hazards that may affect the stability of the trailer when
in operation.

37. If the pump has to be lifted into the required position, name SIX factors to be taken into
Setting up for work continued

account prior to the lift taking place.

38. What checks should be made to the couplers?

39. What checks should be made to the transmitter of a remote-controlled pump before work?

40. Before the start for work: a) how should signallers be identified and b) what should be
agreed between the pump operator and a signaller?

41. Before towing a trailer mounted pump into position, name SIX factors to be taken into
account.

continued…

CPCS Technical Test – A44 Theory Q


© Construction Industry Training Board 2008 Page 4 of 6 11-07-2008
Concrete Pump A44
Trailer Mounted Technical Test – Theory

42. What can occur if the placement hose is longer than specified?
Setting up for work continued

43. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden pylons when setting up the machine and b) explain why a
distance should be kept.

44. If radios are to be used during the lifting operations, what FIVE actions and checks must be
made by the concrete pump operator before use?

45. During the pumping operation, part of the task cannot be carried out as detailed in the
method statement. a) What initially must happen to the operation and b) who authorises
any changes?

46. Describe at least THREE causes of blockages that may occur within the pipeline.

A
Working tasks

47. During pumping, if the operator (using a remote control) needs to leave the pump, what
TWO things need to be ensured?

48. When working in a confined area or space, name THREE dangers that can be present.

49. a) What is considered as the danger zone around the placement hose and b) what is
regarded as the safe minimum?

50. If the words STOP NOW are given to the concrete pump operator by radio during the lift,
what action must the operator take?

continued…

CPCS Technical Test – A44 Theory Q


© Construction Industry Training Board 2008 Page 5 of 6 11-07-2008
Concrete Pump A44
Trailer Mounted Technical Test – Theory
Working tasks continued

51. If a blockage occurs, what actions must be taken by the operator?

52. What is the meaning of this hand signal (being demonstrated by the Tester)?

53. a) What additional items (over and above standard site wear) of PPE are required when
cleaning out concrete pumps and b) explain why?
Completing work

54. Before leaving the pump for a rest break, after switching off the pump, what final action
must be carried out?

55. Name THREE places where the trailer should NOT be parked after completion of the
pumping operation.

56. When is it acceptable to use compressed air to clean out pipelines?

A
Shutdown

57. Before cleaning a pipeline with compressed air, what must be removed from the line itself?

58. What is the maximum allowable air pressure to clean out the pipes?

59. Where must waste from the cleaning process be deposited?

CPCS Technical Test – A44 Theory Q


© Construction Industry Training Board 2008 Page 6 of 6 11-07-2008
Piling Rig A45
Driven below 15 tonnes Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of The Health and Safety at Work Act must employees follow?

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

8. Rig operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A45 Theory Q


© Construction Industry Training Board 2008 Page 1 of 6 11-07-2008
Piling Rig A45
Driven below 15 tonnes Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a piling rig?

11. The operator has to use a new model of rig that they are unfamiliar with. What do Regulations
Roles and responsibilities continued

(i.e. PUWER 98) and other guidance require the operator to have?

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to piling rig
operations.

14. How can a qualification or card benefit a rig operator?

15. Name THREE ways that a rig operator can contribute in ensuring repeat business with the
client or main contractor.

16. Where should the Operator’s Manual be kept and why?

A
Preparing for work

17. What is the purpose of a roll or ROPS frame?

18. What are the THREE actions or stages that a rig operator undertakes during pre-use
inspections?

continued…

CPCS Technical Test – A45 Theory Q


© Construction Industry Training Board 2008 Page 2 of 6 11-07-2008
Piling Rig A45
Driven below 15 tonnes Technical Test – Theory

For questions 19 and 20 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

19. Using the Operator’s Manual, state the figure for setting the track tension.

20. Using the Operator’s Manual, state the cold-starting procedure for the machine.

21. A piling rig has been delivered to site, assembled and configured for work. What must be
carried out before piling starts and by whom?

22. If checking the oil level using a dipstick, why must gloves be worn?

23. List FIVE checks that should be made to the tracks and running gear.
Preparing for work continued

24. Name THREE different types of driven hammers.

25. Where would you find the dolly on a percussive driven hammer?

26. Name THREE different types of driven pile.

27. What is the purpose of a cofferdam?

28. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

29. What is the purpose of counterweight(s) on the rig?

30. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

CPCS Technical Test – A45 Theory Q


© Construction Industry Training Board 2008 Page 3 of 6 11-07-2008
Piling Rig A45
Driven below 15 tonnes Technical Test – Theory

31. If both travel levers are pushed forwards when the track motors are in front of the cab, in
which direction would the machine move?

32. If the rig has to cross the public highway, the Road Traffic Act applies. a) What type of
licence and which classes should the operator hold and b) what is the minimum age
allowed?
Travelling and manoeuvring

33. a) What is the minimum distance allowed near open trenches when travelling the rig and b)
explain why.

34. When MUST a banksman or signaller be used before moving a rig?

35. Why must the seat belt be worn when travelling, even with the cab door closed?

36. a) Which part of the rig applies loading or pressure to the ground and b) name TWO ways
that pressure can be reduced.

37. What checks and procedures need to be made before a ‘permit to dig’ can be issued?

A
Setting up for work

38. Wind speeds can be variable throughout the working day. What action must be taken to
ensure safe working conditions are maintained?

39. When working in a confined area or space: a) what danger can be present with regards to
the counterweight of the machine, b) what is the recommended minimum distance and c)
what measures must be implemented if the gap is less?

CPCS Technical Test – A45 Theory Q


© Construction Industry Training Board 2008 Page 4 of 6 11-07-2008
Piling Rig A45
Driven below 15 tonnes Technical Test – Theory

40. If setting up to pile near a pedestrianised area, state THREE factors that need to be taken
Setting up for work continued

into account.

41. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on metal pylons when setting up the machine and b) explain why a distance
should be kept.

42. What is meant by ‘toeing in’ when referring to the piling activity?

43. What does ‘backdriving’ mean?

44. What is meant by the term ‘refusal’?

45. What is meant by ‘splicing’?

46. What is meant by the term ‘raking angle’?

A
Working tasks

47. What is a ‘driven cast in-situ’ pile?

48. Give THREE reasons that may cause the rig to overturn.

49. If radios are to be used during the piling operations, what FIVE actions and checks must be
made by the rig operator before use?

50. During the piling operation, part of the task cannot be carried out as detailed in the lift plan.
a) What initially must happen to the piling operation and b) who authorises any changes?

continued…

CPCS Technical Test – A45 Theory Q


© Construction Industry Training Board 2008 Page 5 of 6 11-07-2008
Piling Rig A45
Driven below 15 tonnes Technical Test – Theory

51. In driven piling, what is meant by the ‘drop height’?

52. How can the noise level of the hammering operation be reduced on: a) pre-cast types and
b) cast in-situ types?

53. Why are driven piles generally used on contaminated sites?


Working tasks continued

54. What is the function of the shoe as used in cast in-situ piling?

55. What are pre-cast piles most suitable for?

56. If the words STOP NOW are given to the rig operator by radio during the lift, what action
must the operator take?

57. a) What is meant by the lifting capacity of the rig and b) who determines it?

58. Before leaving the cab for a rest break, after parking and switching off the machine, what
Completing

final action must be carried out?


work

59. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

60. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.

A
Shutdown

61. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, what
checks must be carried out before they leave the cab?

62. Why should the rig be re-fuelled at the end of the day?

CPCS Technical Test – A45 Theory Q


© Construction Industry Training Board 2008 Page 6 of 6 11-07-2008
Piling Rig A46
Driven above 15 tonnes Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of The Health and Safety at Work Act must employees follow?

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

8. Rig operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A46 Theory Q


© Construction Industry Training Board 2008 Page 1 of 6 11-07-2008
Piling Rig A46
Driven above 15 tonnes Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a piling rig?

11. The operator has to use a new model of rig that they are unfamiliar with. What do Regulations
Roles and responsibilities continued

(i.e. PUWER 98) and other guidance require the operator to have?

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to piling rig
operations.

14. How can a qualification or card benefit a rig operator?

15. Name THREE ways that a rig operator can contribute in ensuring repeat business with the
client or main contractor.

16. Where should the Operator’s Manual be kept and why?

A
Preparing for work

17. What is the purpose of a roll or ROPS frame?

18. What are the THREE actions or stages that a rig operator undertakes during pre-use
inspections?

continued…

CPCS Technical Test – A46 Theory Q


© Construction Industry Training Board 2008 Page 2 of 6 11-07-2008
Piling Rig A46
Driven above 15 tonnes Technical Test – Theory

For questions 19 and 20 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

19. Using the Operator’s Manual, state the figure for setting the track tension.

20. Using the Operator’s Manual, state the cold-starting procedure for the machine.

21. A piling rig has been delivered to site, assembled and configured for work. What must be
carried out before piling starts and by whom?

22. If checking the oil level using a dipstick, why must gloves be worn?

23. List FIVE checks that should be made to the tracks and running gear.
Preparing for work continued

24. Name THREE different types of driven hammers.

25. Where would you find the dolly on a percussive driven hammer?

26. Name THREE different types of driven pile.

27. What is the purpose of a cofferdam?

28. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

29. What is the purpose of counterweight(s) on the rig?

30. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

CPCS Technical Test – A46 Theory Q


© Construction Industry Training Board 2008 Page 3 of 6 11-07-2008
Piling Rig A46
Driven above 15 tonnes Technical Test – Theory

31. If both travel levers are pushed forwards when the track motors are in front of the cab, in
which direction would the machine move?

32. If the rig has to cross the public highway, the Road Traffic Act applies. a) What type of
licence and which classes should the operator hold and b) what is the minimum age
allowed?

A
Travelling and manoeuvring

33. a) What is the minimum distance allowed near open trenches when travelling the rig and b)
explain why.

34. When MUST a banksman or signaller be used before moving a rig?

35. Why must the seat belt be worn when travelling, even with the cab door closed?

36. a) Which part of the rig applies loading or pressure to the ground and b) name TWO ways
that pressure can be reduced.

37. What checks and procedures need to be made before a ‘permit to dig’ can be issued?

A
Setting up for work

38. Wind speeds can be variable throughout the working day. What action must be taken to
ensure safe working conditions are maintained?

39. When working in a confined area or space: a) what danger can be present with regards to
the counterweight of the machine, b) what is the recommended minimum distance and c)
what measures must be implemented if the gap is less?

CPCS Technical Test – A46 Theory Q


© Construction Industry Training Board 2008 Page 4 of 6 11-07-2008
Piling Rig A46
Driven above 15 tonnes Technical Test – Theory

40. If setting up to pile near a pedestrianised area, state THREE factors that need to be taken
Setting up for work continued

into account.

41. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on metal pylons when setting up the machine and b) explain why a distance
should be kept.

42. What is meant by ‘toeing in’ when referring to the piling activity?

43. What does ‘backdriving’ mean?

44. What is meant by the term ‘refusal’?

45. What is meant by ‘splicing’?

46. What is meant by the term ‘raking angle’?

A
Working tasks

47. What is a ‘driven cast in-situ’ pile?

48. Give THREE reasons that may cause the rig to overturn.

49. If radios are to be used during the piling operations, what FIVE actions and checks must be
made by the rig operator before use?

50. During the piling operation, part of the task cannot be carried out as detailed in the lift plan.
a) What initially must happen to the piling operation and b) who authorises any changes?

continued…

CPCS Technical Test – A46 Theory Q


© Construction Industry Training Board 2008 Page 5 of 6 11-07-2008
Piling Rig A46
Driven above 15 tonnes Technical Test – Theory

51. In driven piling, what is meant by the ‘drop height’?


A
52. How can the noise level of the hammering operation be reduced on: a) pre-cast types and
b) cast in-situ types?
A
53. Why are driven piles generally used on contaminated sites?
Working tasks continued

A
54. What is the function of the shoe (end-cap) as used in cast in-situ piling?

A
55. What are pre-cast piles most suitable for?
A
56. If the words STOP NOW are given to the rig operator by radio during the lift, what action
must the operator take?
A
57. a) What is meant by the lifting capacity of the rig and b) who determines it?

58. Before leaving the cab for a rest break, after parking and switching off the machine, what
Completing

final action must be carried out?


work

59. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

60. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.

A
Shutdown

61. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, what
checks must be carried out before they leave the cab?

62. Why should the rig be re-fuelled at the end of the day?

CPCS Technical Test – A46 Theory Q


© Construction Industry Training Board 2008 Page 6 of 6 11-07-2008
Piling Rig A47
Bored below 15 tonnes Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of The Health and Safety at Work Act must employees follow?

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

8. Rig operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A47 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Piling Rig A47
Bored below 15 tonnes Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a piling rig?

11. The operator has to use a new model of rig that they are unfamiliar with. What do Regulations
Roles and responsibilities continued

(i.e. PUWER 98) and other guidance require the operator to have?

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to piling rig
operations.

14. How can a qualification or card benefit a rig operator?

15. Name THREE ways that a rig operator can contribute in ensuring repeat business with the
client or main contractor.

16. Where should the Operator’s Manual be kept and why?

17. List FIVE checks that should be made to the tracks and running gear.
Preparing for work

18. What is the purpose of a roll or ROPS frame?

19. What are the THREE actions or stages that a rig operator undertakes during pre-use
inspections?

continued…

CPCS Technical Test – A47 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Piling Rig A47
Bored below 15 tonnes Technical Test – Theory

For questions 20 and 21 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

20. Using the Operator’s Manual, state the figure for setting the track tension.

21. Using the Operator’s Manual, state the cold-starting procedure for the machine.

22. A piling rig has been delivered to site, assembled and configured for work. What must be
carried out before piling starts and by whom?

23. If checking the oil level using a dipstick, why must gloves be worn?

A
Preparing for work continued

24. When using a CFA type, what is the purpose of the leaders?

25. How is drive transmitted to the short auger?

26. Why is bored piling more suitable for use within urban areas?

27. What is the purpose of a cofferdam?

28. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

29. What is the purpose of counterweight(s) on the rig?

30. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

CPCS Technical Test – A47 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Piling Rig A47
Bored below 15 tonnes Technical Test – Theory

31. If both travel levers are pushed forwards when the track motors are in front of the cab, in
which direction would the machine move?

32. If the rig has to cross the public highway, the Road Traffic Act applies. a) What type of
licence and which classes should the operator hold and b) what is the minimum age
allowed?
Travelling and manoeuvring

33. a) What is the minimum distance allowed near open trenches when travelling the rig and b)
explain why.

34. When MUST a banksman or signaller be used before moving a rig?

35. Why must the seat belt be worn when travelling, even with the cab door closed?

36. a) Which part of the rig applies loading or pressure to the ground and b) name TWO ways
that pressure can be reduced.

37. What checks and procedures need to be made before a ‘permit to dig’ can be issued?

A
Setting up for work

38. Wind speeds can be variable throughout the working day. What action must be taken to
ensure safe working conditions are maintained?

39. When working in a confined area or space: a) what danger can be present with regards to
the counterweight of the machine, b) what is the recommended minimum distance and c)
what measures must be implemented if the gap is less?

continued…

CPCS Technical Test – A47 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Piling Rig A47
Bored below 15 tonnes Technical Test – Theory

40. If setting up to pile near a pedestrianised area, state THREE factors that need to be taken
Setting up for work continued

into account.

41. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on metal pylons when setting up the machine and b) explain why a distance
should be kept.

42. Name THREE different types of bored piling methods.

43. Give THREE reasons that may cause the rig to overturn.

44. If radios are to be used during the piling operations, what FIVE actions and checks must be
made by the rig operator before use?

45. During the piling operation, part of the task cannot be carried out as detailed in the method
statement. a) What initially must happen to the piling operation and b) who authorises any
Working tasks

changes?

46. What is the function of the shoe (end-cap) as used in CFA piling?

47. How is a rotary auger of a bored rig cleaned?

48. What size is the controlled or restricted zone around a CFA drilling operation?

49. What is the purpose of a double rotary head?

50. What is meant by a ‘contiguous pile line’?

continued…

CPCS Technical Test – A47 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Piling Rig A47
Bored below 15 tonnes Technical Test – Theory

51. Explain the purpose of the casings when piling.

52. What is the purpose of an oscillator?

53. When are the auger gates allowed to be opened in the middle of a CFA operation?

A
Working tasks continued

54. What is the purpose of a ‘Tremie’ pipe?

55. On CFA rigs, at what height should the auger be stopped when cleaning spoil from the
auger?

56. If the words STOP NOW are given to the rig operator by radio during the lift, what action
must the operator take?

57. a) What is meant by the lifting capacity of the rig and b) who determines it?

58. Before leaving the cab for a rest break, after parking and switching off the machine, what
Completing

final action must be carried out?


work

59. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

A
Shutdown

60. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.

CPCS Technical Test – A47 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Piling Rig A47
Bored below 15 tonnes Technical Test – Theory

61. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, what
checks must be carried out before they leave the cab?
Shutdown continued

62. Why should the rig be re-fuelled at the end of the day?

CPCS Technical Test – A47 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Piling Rig A48
Bored above 15 tonnes Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of The Health and Safety at Work Act must employees follow?

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

8. Rig operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A48 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Piling Rig A48
Bored above 15 tonnes Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a piling rig?

11. The operator has to use a new model of rig that they are unfamiliar with. What do Regulations
Roles and responsibilities continued

(i.e. PUWER 98) and other guidance require the operator to have?

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to piling rig
operations.

14. How can a qualification or card benefit a rig operator?

15. Name THREE ways that a rig operator can contribute in ensuring repeat business with the
client or main contractor.

16. Where should the Operator’s Manual be kept and why?

17. List FIVE checks that should be made to the tracks and running gear.
Preparing for work

18. What is the purpose of a roll or ROPS frame?

19. What are the THREE actions or stages that a rig operator undertakes during pre-use
inspections?

continued…

CPCS Technical Test – A48 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Piling Rig A48
Bored above 15 tonnes Technical Test – Theory

For questions 20 and 21 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

20. Using the Operator’s Manual, state the figure for setting the track tension.

21. Using the Operator’s Manual, state the cold-starting procedure for the machine.

22. A piling rig has been delivered to site, assembled and configured for work. What must be
carried out before piling starts and by whom?

23. If checking the oil level using a dipstick, why must gloves be worn?

A
Preparing for work continued

24. When using a CFA type, what is the purpose of the leaders?

25. How is drive transmitted to the short auger?

26. Why is bored piling more suitable for use within urban areas?

27. What is the purpose of a cofferdam?

28. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

29. What is the purpose of counterweight(s) on the rig?

30. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

CPCS Technical Test – A48 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Piling Rig A48
Bored above 15 tonnes Technical Test – Theory

31. If both travel levers are pushed forwards when the track motors are in front of the cab, in
which direction would the machine move?

32. If the rig has to cross the public highway, the Road Traffic Act applies. a) What type of
licence and which classes should the operator hold and b) what is the minimum age
allowed?
Travelling and manoeuvring

33. a) What is the minimum distance allowed near open trenches when travelling the rig and b)
explain why.

34. When MUST a banksman or signaller be used before moving a rig?

35. Why must the seat belt be worn when travelling, even with the cab door closed?

36. a) Which part of the rig applies loading or pressure to the ground and b) name TWO ways
that pressure can be reduced.

37. What checks and procedures need to be made before a ‘permit to dig’ can be issued?

A
Setting up for work

38. Wind speeds can be variable throughout the working day. What action must be taken to
ensure safe working conditions are maintained?

39. When working in a confined area or space: a) what danger can be present with regards to
the counterweight of the machine, b) what is the recommended minimum distance and c)
what measures must be implemented if the gap is less?

continued…

CPCS Technical Test – A48 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Piling Rig A48
Bored above 15 tonnes Technical Test – Theory

40. If setting up to pile near a pedestrianised area, state THREE factors that need to be taken
Setting up for work continued

into account.

41. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on metal pylons when setting up the machine and b) explain why a distance
should be kept.

42. Name THREE different types of bored piling methods.

43. Give THREE reasons that may cause the rig to overturn.

44. If radios are to be used during the piling operations, what FIVE actions and checks must be
made by the rig operator before use?

45. During the piling operation, part of the task cannot be carried out as detailed in the method
statement. a) What initially must happen to the piling operation and b) who authorises any
Working tasks

changes?

46. What is the function of the shoe (end-cap) as used in CFA piling?

47. How is a rotary auger of a bored rig cleaned?

48. What size is the controlled or restricted zone around a CFA drilling operation?

49. What is the purpose of a double rotary head?

50. What is meant by a ‘contiguous pile line’?

continued…

CPCS Technical Test – A48 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Piling Rig A48
Bored above 15 tonnes Technical Test – Theory

51. Explain the purpose of the casings when piling.

52. What is the purpose of an oscillator?

53. When are the auger gates allowed to be opened in the middle of a CFA operation?

A
Working tasks continued

54. What is the purpose of a ‘Tremie’ pipe?

55. On CFA rigs, at what height should the auger be stopped when cleaning spoil from the
auger?

56. If the words STOP NOW are given to the rig operator by radio during the lift, what action
must the operator take?

57. a) What is meant by the lifting capacity of the rig and b) who determines it?

58. Before leaving the cab for a rest break, after parking and switching off the machine, what
Completing

final action must be carried out?


work

59. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

A
Shutdown

60. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.

CPCS Technical Test – A48 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Piling Rig A48
Bored above 15 tonnes Technical Test – Theory

61. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, what
checks must be carried out before they leave the cab?

A
Shutdown continued

62. Why should the rig be re-fuelled at the end of the day?

CPCS Technical Test – A48 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of the Health and Safety at Work Act must employees follow?

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to vehicles and equipment?

6. a) What is the purpose of a Method Statement and b) what is required of the driver?

7. Name FOUR different types or levels of sanctions that can be applied to transport drivers
who do not comply with, or follow legislation and regulations.

8. Transport drivers are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 1 of 9 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

9. Name THREE ways in which transport drivers can minimise their impact upon the
environment whilst using the vehicle.

10. In what situation does a hard hat need to be worn when driving a transporter?

11. The transport driver has to drive a new type of plant that they are unfamiliar with. What do
Roles and responsibilities continued

Regulations (i.e. PUWER 98) and other guidance require the transport driver to have?

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to transporters.

14. How can a qualification or card benefit a transport driver?

15. Name THREE ways that a transport driver can contribute in ensuring repeat business with
the client or main contractor.

16. Where should the vehicle’s manual be kept and why?

A
Preparing for work

17. What is a possible consequence of using a tyre with a deep cut in the sidewall?

18. If the transport driver has to top-up the engine oil, state TWO precautions to ensure
cleanliness of the system.

continued…

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 2 of 9 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

For questions 19 and 20 the Operator’s Manual for one of the items of plant being used
for the test MUST be available for reference by the candidate

19. Using the machine’s Operator’s Manual, state the procedure for preparing and loading the
machine onto a transporter.

20. Using the machine’s Operator’s Manual, state how the machine must be secured for
transport.

A
Preparing for work continued

21. If checking the oil level using a dipstick, why must gloves be worn?

22. What is the difference between a low loader and a semi-trailer?

23. Name ONE example of ‘road friendly’ suspension.

24. On start up, the air pressure on the vehicle is low. What actions must the transport driver
carry out before work and during work?

25. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

26. Before setting off to retrieve a machine from site, in terms of arrival, what THREE things
should be checked before leaving?

A
Travelling and manoeuvring

27. What problems and hazards can soft ground cause to a loaded transporter?

28. a) What is the minimum distance allowed near open trenches when travelling with a
transporter and b) explain why.

continued…

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 3 of 9 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

29. When are the most likely times that loads may move during transit in the transporter?
Travelling and manoeuvring

A
continued

30. Give THREE possible reasons why transporters should not stray off the designated travel
routes.

31. If setting up to work in a pedestrianised area, state THREE factors that need to be taken
into account.

32. Name SIX safety considerations when selecting a site for loading or unloading plant.

33. Once the transporter is positioned, state SIX actions to be considered before loading
commences.
Setting up for work

34. Where and why would packing be used?

35. When is loading and unloading allowed on verges or footpaths?

36. Whenever possible, who should decide the positioning of the transporter for loading?

37. When working in a confined area or space, name THREE hazards that can occur.
Working
tasks

continued…

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 4 of 9 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

38. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when loading and b) explain why a distance should be
kept.

39. What is the maximum distance that the end marker board must be from the edge of a
projection?

40. What checks should be made to flat webbing slings before use?

41. Under what conditions can lashing chains be used for lifting operations?

42. a) What type of lashing should be used when securing a 360 excavator fitted with rubber
tracks and b) explain why.
Working tasks continued

43. Why should the centre of gravity of a load be in front of the rear axle of an articulated semi
trailer?

44. What effect does chocking timber (dunnage) have on carrying capacity?

45. If loading a smooth drum ride-on roller, how can friction between the drums and the
transporter ramps/bed be increased?

46. When a long load on a short rigid vehicle results in excessive overhang over the rear of the
vehicle, what are TWO possible dangers?

47. What is the definition of a ‘long load’?

48. What is the maximum width of a load before it becomes classed as a ‘wide load’?

A 2

continued…

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 5 of 9 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

49. State three instances when marker boards must be fitted.

50. Give FIVE instances where lights should be fitted to an overhanging load both widthways
and lengthways.

51. What THREE pieces of information are needed to calculate axle loadings?

52. How is the kerbside weight of a vehicle determined?

53. Before loading or unloading on the public highway, what specific measures must be
Working tasks continued

considered?

54. During the loading process, in terms of the load, what is the transporter driver responsible
for?

55. When loading, where is the optimum, or best position to place an item of plant?

56. What is the recommended maximum pull on a restraining or lashing chain?

57. In general: a) what is the maximum angle that lashings should be restricted to and b) why?

58. When securing machines having hydraulically operated booms (e.g. 360 excavators etc),
what should be ensured when restraining?

continued…

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 6 of 9 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

59. On articulated-steered plant, what should be engaged after loading?

60. If an item of plant is being loaded where it is known that the parking brake is not fully
effective, what action must be taken?

A
Working tasks continued

61. State: a) at what distance a rear overhang should be identified and b) how.

62. What checks should be made to cabbed machines after loading?

63. What is the meaning of this hand signal (being demonstrated by the Tester)?

64. After loading and securing plant for transit: a) when should the lashings or securing
equipment be re-checked and b) why?
Completing work

65. Before leaving the cab for a rest break, after parking and switching off the vehicle, what
final action must be carried out?

66. When parking the vehicle at the end of the shift, name THREE places where the
transporter should NOT be parked.

A
Shutdown

67. Many transporters have a turbo-charged engine. a) What is the normal procedure before
switching off the engine after working and b) what happens if the procedure is not followed?

68. What is meant by Maximum Authorised Mass?

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 7 of 9 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

69. What is the maximum gross train weight of vehicle movement allowed under the current
Construction and Use Regulations on: a) Road Friendly Suspension and b) non Road
Friendly Suspension?

70. a) How many mirrors are required on a rigid LGV transporter over 7.5 tonnes and b) where
should they be positioned?

71. State the maximum allowed speeds of a transporter loaded with a 13 tonne 360 degree
excavator which is travelling on: a) Motorway, b) Dual Carriageway (unrestricted) and c)
Single carriageway (unrestricted).

72. When a pick-up/transit type vehicle is over 3 tonnes in weight, what is required with regard
to testing requirements?

A
Shutdown continued

73. Where should the vehicle plating certificate be positioned on the vehicle?

74. If a vehicle is carrying an item of plant that gives a total height of over three metres, what
must be available to the driver en route?

75. Name FOUR items that must be displayed on a DoT approved plating certificate.

76. What does the (new) driver Certificate of Professional Competence (CPC) require a driver
to undertake every five years?

77. a) What type of licence and which class should a transport driver hold and b) what is the
minimum age allowed?

continued…

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 8 of 9 11-07-2008
Loader/Securer A49
Non-STGO Technical Test – Theory

78. Under the Road Traffic Act 1998, state ONE instance when an overloaded vehicle may
travel on the public highway
Shutdown continued

79. If towing a trailer, what class of licence is required?

CPCS Technical Test – A49 Theory Q


© Construction Industry Training Board 2008 Page 9 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of the Health and Safety at Work Act must employees follow?

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to vehicles and equipment?

6. a) What is the purpose of a Method Statement and b) what is required of the driver?

7. Name FOUR different types or levels of sanctions that can be applied to transport drivers
who do not comply with, or follow legislation and regulations.

8. Transport drivers are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 1 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

9. Name THREE ways in which transport drivers can minimise their impact upon the
environment whilst using the vehicle.

10. In what situation does a hard hat need to be worn when driving a transporter?

11. The transport driver has to drive a new type of plant that they are unfamiliar with. What do
Roles and responsibilities continued

Regulations (i.e. PUWER 98) and other guidance require the transport driver to have?

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to transporters.

14. How can a qualification or card benefit a transport driver?

15. Name THREE ways that a transport driver can contribute in ensuring repeat business with
the client or main contractor.

16. Where should the vehicle’s manual be kept and why?

A
Preparing for work

17. What is a possible consequence of using a tyre with a deep cut in the sidewall?

18. If the transport driver has to top-up the engine oil, state TWO precautions to ensure
cleanliness of the system.

continued…

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 2 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

For questions 19 and 20 the Operator’s Manual for one of the items of plant being used
for the test MUST be available for reference by the candidate

19. Using the machine’s Operator’s Manual, state the procedure for preparing and loading the
machine onto a transporter.

20. Using the machine’s Operator’s Manual, state how the machine must be secured for
transport.

A
Preparing for work continued

21. If checking the oil level using a dipstick, why must gloves be worn?

22. What is the difference between a low loader and a semi-trailer?

23. Name ONE example of ‘road friendly’ suspension.

24. On start up, the air pressure on the vehicle is low. What actions must the transport driver
carry out before work and during work?

25. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

26. Before setting off to retrieve a machine from site, in terms of arrival, what THREE things
should be checked before leaving?
Travelling and manoeuvring

27. What problems and hazards can soft ground cause to a loaded transporter?

28. a) What is the minimum distance allowed near open trenches when travelling with a
transporter and b) explain why.

continued…

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 3 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

29. When are the most likely times that loads may move during transit in the transporter?
Travelling and manoeuvring

30. Give THREE possible reasons why transporters should not stray off the designated travel
continued

routes.

31. If setting up to work in a pedestrianised area, state THREE factors that need to be taken
into account.

32. Name SIX safety considerations when selecting a site for loading or unloading plant.

33. Once the transporter is positioned, state SIX actions to be considered before loading
commences.
Setting up for work

34. Where and why would packing be used?

35. When is loading and unloading allowed on verges or footpaths?

36. Whenever possible, who should decide the positioning of the transporter for loading?

A
Working tasks

37. When working in a confined area or space, name THREE hazards that can occur.

continued…

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 4 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

38. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when loading and b) explain why a distance should be
kept.

39. What is the maximum distance that the end marker board must be from the edge of a
projection?

40. What checks should be made to flat webbing slings before use?

41. Under what conditions can lashing chains be used for lifting operations?

42. a) What type of lashing should be used when securing a 360 excavator fitted with rubber
tracks and b) explain why.
Working tasks continued

43. Why should the centre of gravity of a load be in front of the rear axle of an articulated semi
trailer?

44. What effect does chocking timber (dunnage) have on carrying capacity?

45. If loading a smooth drum ride-on roller, how can friction between the drums and the
transporter ramps/bed be increased?

46. When a long load on a short rigid vehicle results in excessive overhang over the rear of the
vehicle, what are TWO possible dangers?

47. What is the definition of a ‘long load’?

48. What is the maximum width of a load before it becomes classed as a ‘wide load’?

continued…

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 5 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

49. State three instances when marker boards must be fitted.

50. Give FIVE instances where lights should be fitted to an overhanging load both widthways
and lengthways.

51. What THREE pieces of information are needed to calculate axle loadings?

52. How is the kerbside weight of a vehicle determined?

53. Before loading or unloading on the public highway, what specific measures must be
Working tasks continued

considered?

54. During the loading process, in terms of the load, what is the transporter driver responsible
for?

55. When loading, where is the optimum, or best position to place an item of plant?

56. What is the recommended maximum pull on a restraining or lashing chain?

57. In general: a) what is the maximum angle that lashings should be restricted to and b) why?

58. When securing machines having hydraulically operated booms (e.g. 360 excavators etc),
what should be ensured when restraining?

continued…

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 6 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

59. On articulated-steered plant, what should be engaged after loading?

60. If an item of plant is being loaded where it is known that the parking brake is not fully
effective, what action must be taken?

61. State: a) at what distance a rear overhang should be identified and b) how.

62. What checks should be made to cabbed machines after loading?


Working tasks continued

63. Under Special Types General Order, give TWO instances when an attendant is required.

64. What is the minimum height of an amber flashing beacon?

65. When would outriggers on the trailer normally be used?

66. What is the meaning of this symbol (being demonstrated by the Tester)?

67. A 70 tonne tracked excavator is being transported. A spare bucket is part of the load. a) Is
this allowed and b) give a reason for your answer.

68. After loading and securing plant for transit: a) when should the lashings or securing
equipment be re-checked and b) why?
Completing work

69. Before leaving the cab for a rest break, after parking and switching off the vehicle, what
final action must be carried out?

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 7 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

70. When parking the vehicle at the end of the shift, name THREE places where the
transporter should NOT be parked.

71. Many transporters have a turbo-charged engine. a) What is the normal procedure before
switching off the engine after working and b) what happens if the procedure is not followed?

72. What is meant by Maximum Authorised Mass?

73. What is the maximum gross train weight of vehicle movement allowed under the current
Construction and Use Regulations on: a) Road Friendly Suspension and b) non Road
Friendly Suspension?

74. a) How many mirrors are required on a rigid LGV transporter over 7.5 tonnes and b) where
should they be positioned?

A
Shutdown

75. State the maximum allowed speeds of a fully loaded category 3 transporter which is
travelling on: a) Motorway, b) Dual Carriageway (unrestricted) and c) Single carriageway
(unrestricted).

76. In terms of gross vehicle weights, at which weight do the Police require written notification
of the movement?

77. Where should the vehicle plating certificate be positioned on the vehicle?

78. If a vehicle is carrying an item of plant that gives a total height of over three metres, what
must be available to the driver en route?

79. Name FOUR items that must be displayed on a DoT approved plating certificate.

continued…

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 8 of 9 11-07-2008
Loader/Securer A50
STGO Technical Test – Theory

80. What does the (new) driver Certificate of Professional Competence (CPC) require a driver
to undertake every five years?

81. a) What type of licence and which class should STGO transport drivers hold and b) what is
the minimum age allowed?

82. What is the maximum allowable total laden weight of a category 2 vehicle or combination?

A
Shutdown continued

83. Under the Road Traffic Act 1998, state ONE instance when an overloaded vehicle may
travel on the public highway

84. State the minimum time period when notification has to be given to the Highways and
Bridges Authorities if the total weight exceeds 80,000 kg.

85. What is the maximum permitted axle weight on a Low Loader?

86. How many days clear notice is required, if the width of the load to be moved exceeds 5
metres and is up to 6.1 metres wide?

CPCS Technical Test – A50 Theory Q


© Construction Industry Training Board 2008 Page 9 of 9 11-07-2008
Dump Truck A56
Articulated Chassis Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of the Health and Safety at Work Act must employees follow?

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied to plant operators
who do not comply with, or follow legislation and regulations.

8. Plant operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A56 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Dump Truck A56
Articulated Chassis Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a dump truck?

11. The operator has to use a new type of dump truck that they are unfamiliar with. What do
Regulations (i.e. PUWER 98) and other guidance require the operator to have?
Roles and responsibilities continued

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to dump trucks.

14. How can a qualification or card benefit a plant operator?

15. What is a dump truck operator’s main purpose or requirement?

16. Name THREE ways that a plant operator can contribute in ensuring repeat business with
the client or main contractor.

17. Where should the dump truck’s Operator’s Manual be kept and why?

A
Preparing for work

18. What is a possible consequence of using a tyre with a deep cut in the sidewall?

19. When would the body safety strut or support be used?

continued…

CPCS Technical Test – A56 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Dump Truck A56
Articulated Chassis Technical Test – Theory

20. If the operator has to top-up the hydraulic oil, state TWO precautions to ensure cleanliness
of the system.

For questions 21 and 22 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

21. Using the Operator’s Manual, state the figure for tyres’ operating pressure.

22. Using the Operator’s Manual, state the cold-starting procedure for the machine.

23. On articulated dump trucks, steering is achieved by actuating a hydraulic ram (or rams)
which is controlled by turning the steering wheel. a) How does the engine supply the oil flow
and b) what happens to the steering when the engine stops?
Preparing for work continued

24. If checking the oil level using a dipstick, why must gloves be worn?

25. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

26. What is the purpose of a ROPS cab?

27. A dump truck is classified by a manufacturer as a 30 tonne machine. What does this mean?

28. State the purpose of a heated body.

29. On start up, the air pressure on the machine is low. What actions must the operator carry
out before work and during work?

continued…

CPCS Technical Test – A56 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Dump Truck A56
Articulated Chassis Technical Test – Theory
work continued
30. During work, the engine starts to overheat. Explain the danger if someone tries to remove
Preparing for

the radiator or expansion tank cap.

31. The rear axle units on most dump trucks pivot on the chassis. Explain the reason for
pivoting axles.

32. a) State the purpose of a retarder and b) and the possible consequences of not using it
when required.

33. a) Name THREE purposes of the raised lugs on tyres and b) what can happen to a dump
truck if the lugs are severely worn?

A
Travelling and manoeuvring

34. What problems and hazards can soft ground cause to a loaded dump truck?

35. a) Give ONE advantage and b) TWO disadvantages of rear mounted cameras.

36. a) What is the minimum distance allowed near open trenches when travelling with a dump
truck and b) explain why.

37. If the machine is being travelled or working on the public highway, including adjacent
pavements and verges, the Road Traffic Act applies. a) What type of licence and which
class should the operator hold and b) what is the minimum age allowed?

38. When travelling on wet clay, what effect does this have on the dump truck?

continued…

CPCS Technical Test – A56 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Dump Truck A56
Articulated Chassis Technical Test – Theory

39. Why must the seat belt be worn at all times, even with the cab door closed?
Travelling and manoeuvring

A
continued

40. Give THREE possible reasons why dump trucks should not stray off the designated haul
routes.

41. If setting up to work in a pedestrianised area, state THREE factors that need to be taken
into account.

42. Whenever possible, who should decide the positioning of the dump truck for loading?

43. The operator is asked to tip material into a new trench. State FIVE different requirements
Setting up for work

that must be considered or implemented before tipping commences.

44. Give TWO reasons why the dump truck operator should have an understanding of the type
of spoil being transported.

45. When working in a confined area or space, what danger can be present with an articulated
dump truck with regards to steering?

A
Working tasks

46. Why should tail gates not be fitted when transporting bulky or rock type material?

47. When working in a confined area or space, name THREE hazards that can occur.

continued…

CPCS Technical Test – A56 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Dump Truck A56
Articulated Chassis Technical Test – Theory

48. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when tipping loads and b) explain why a distance should
be kept.

49. a) Why should the body of the dump truck be raised slowly/carefully especially with wet or
sticky material and b) what would be a consequence if this was not done?

50. Who should determine the maximum load that should be placed into the body of the dump
truck?

51. State TWO requirements of using a stop block or earth bank (berm) at a trench discharging
point.

A
Working tasks continued

52. When tipping a load, the centre of gravity of the machine changes. a) How does this affect
the dump truck and b) state TWO actions to avoid accidents?

53. If a load has to be tipped on a slope, what may happen if the load is tipped downhill and
why?

54. An operator has been asked to transport a load down a small section of the public highway,
for which the Road Traffic Act applies. What effect does this have on dump truck
operations?

55. What is regarded as the most productive position for the dump truck to be in when being
loaded by a wheeled loading shovel working from a stockpile?

56. What is the meaning of this hand signal (being demonstrated by the Tester)?

continued…

CPCS Technical Test – A56 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Dump Truck A56
Articulated Chassis Technical Test – Theory

57. Operators should lower the body fully before driving away. Give TWO possible
Working tasks

consequences if this is not carried out.


continued

A
Completing work

58. Before leaving the cab for a rest break, after parking and switching off the machine, what
final action must be carried out?

59. When parking the machine at the end of the shift, name THREE places where the dump
truck should NOT be parked.

60. Many dump trucks have a turbo-charged engine. a) What is the normal procedure before
switching off the engine after working and b) what happens if the procedure is not followed?

61. Why should a dump truck be re-fuelled at the end of the day?

A
Shutdown

62. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.

63. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, state
THREE actions that must be carried out before they leave the machine.

CPCS Technical Test – A56 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Dump Truck A57
Rigid Chassis Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of the Health and Safety at Work Act must employees follow?

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied to plant operators
who do not comply with, or follow legislation and regulations.

8. Plant operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A57 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Dump Truck A57
Rigid Chassis Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a dump truck?

11. The operator has to use a new type of dump truck that they are unfamiliar with. What do
Regulations (i.e. PUWER 98) and other guidance require the operator to have?
Roles and responsibilities continued

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to dump trucks.

14. How can a qualification or card benefit a plant operator?

15. What is a dump truck operator’s main purpose or requirement?

16. Name THREE ways that a plant operator can contribute in ensuring repeat business with
the client or main contractor.

17. Where should the dump truck’s Operator’s Manual be kept and why?

A
Preparing for work

18. What is a possible consequence of using a tyre with a deep cut in the sidewall?

19. When would the body safety strut or support be used?

continued…

CPCS Technical Test – A57 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Dump Truck A57
Rigid Chassis Technical Test – Theory

20. If the operator has to top-up the hydraulic oil, state TWO precautions to ensure cleanliness
of the system.

For questions 21 and 22 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

21. Using the Operator’s Manual, state the figure for tyres’ operating pressure. For tracked
units, state checks needed to be made to the track belts.

22. Using the Operator’s Manual, state the cold-starting procedure for the machine.

23. If fitted, name the purpose of having independent front suspension.

24. If checking the oil level using a dipstick, why must gloves be worn?
Preparing for work continued

25. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

26. What is the purpose of a ROPS cab?

27. A dump truck is classified by a manufacturer as a 60 tonne machine. What does this mean?

28. Why do most dump trucks have a sloping body tail?

29. On start up, the air pressure on the machine is low. What actions must the operator carry
out before work and during work?

30. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

CPCS Technical Test – A57 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Dump Truck A57
Rigid Chassis Technical Test – Theory

31. a) State the purpose of a retarder and b) and the possible consequences of not using it
when required.

32. a) Name THREE purposes of the raised lugs on tyres and b) what can happen to a dump
truck if the lugs are severely worn?

33. What problems and hazards can soft ground cause to a loaded dump truck?

34. a) Give ONE advantage and b) TWO disadvantages of rear mounted cameras.

A
Travelling and manoeuvring

35. a) What is the minimum distance allowed near open trenches when travelling with a dump
truck and b) explain why.

36. If the machine is being travelled or working on the public highway, including adjacent
pavements and verges, the Road Traffic Act applies. a) What type of licence and which
class should the operator hold and b) what is the minimum age allowed?

37. When travelling on wet clay, what effect does this have on the dump truck?

38. Why must the seat belt be worn at all times, even with the cab door closed?

39. Name THREE conditions that the mirrors on the machine must be in.

40. Give THREE possible reasons why dump trucks should not stray off the designated haul
routes.

CPCS Technical Test – A57 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Dump Truck A57
Rigid Chassis Technical Test – Theory

41. If setting up to work in a pedestrianised area, state THREE factors that need to be taken
into account.

42. Whenever possible, who should decide the positioning of the dump truck for loading?

A
Setting up for work

43. The operator is asked to tip material into a new trench. State FIVE different requirements
that must be considered or implemented before tipping commences.

44. Give TWO reasons why the dump truck operator should have an understanding of the type
of spoil being transported.

45. Why should tail gates not be fitted when transporting bulky or rock type material?

46. When working in a confined area or space, name THREE hazards that can occur.

47. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when tipping loads and b) explain why a distance should
be kept.
Working tasks

48. a) Why should the body of the dump truck be raised slowly/carefully especially with wet or
sticky material and b) what would be a consequence if this was not done?

49. Who should determine the maximum load that should be placed into the body of the dump
truck?

continued…

CPCS Technical Test – A57 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Dump Truck A57
Rigid Chassis Technical Test – Theory

50. State TWO requirements of using a stop block or earth bank (berm) at a trench discharging
point.

51. When tipping a load, the centre of gravity of the machine changes. a) How does this affect
the dump truck and b) state TWO actions to avoid accidents?

52. If a load has to be tipped on a slope, what may happen if the load is tipped downhill and
why?

A
Working tasks continued

53. An operator has been asked to transport a load down a small section of the public highway,
for which the Road Traffic Act applies. What effect does this have on dump truck
operations?

54. What is regarded as the most productive position for the dump truck to be in when being
loaded by a wheeled loading shovel working from a stockpile?

55. What is the meaning of this hand signal (being demonstrated by the Tester)?

56. Operators should lower the body fully before driving away. Give TWO possible
consequences if this is not carried out.

57. Before leaving the cab for a rest break, after parking and switching off the machine, what
Completing work

final action must be carried out?

CPCS Technical Test – A57 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Dump Truck A57
Rigid Chassis Technical Test – Theory

58. Many dump trucks have a turbo-charged engine. a) What is the normal procedure before
switching of the engine after working and b) what happens if the procedure is not followed?

59. When parking the machine at the end of the shift, name THREE places where the dump
truck should NOT be parked.

60. Why should a dump truck be re-fuelled at the end of the day?
Shutdown

61. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.

62. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, state
THREE actions that must be carried out before they leave the machine.

CPCS Technical Test – A57 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Excavator 360 A58
Below 10 tonne Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of the Health and Safety at Work Act must employees follow?

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations.

8. Plant operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A58 Theory Q


© Construction Industry Training Board 2008 Page 1 of 8 11-07-2008
Excavator 360 A58
Below 10 tonne Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a 360 excavator?

A
Roles and responsibilities continued

11. The operator has to fit and use a new bucket using a quick-hitch coupler that they are
unfamiliar with. What do Regulations (i.e. PUWER 98) and other guidance require the
operator to have?

12. What are the possible outcomes if being prosecuted (by judicial bodies) for not complying
with legislation and regulations?

13. How can a qualification or card benefit a plant operator?

14. Name THREE ways that a plant operator can contribute in ensuring repeat business with
the client or main contractor.

15. Where should the excavator’s Operator’s Manual be kept and why?

A
Preparing for work

16. If the operator has to top-up the hydraulic oil, state TWO precautions to ensure cleanliness
of the system.

continued…

CPCS Technical Test – A58 Theory Q


© Construction Industry Training Board 2008 Page 2 of 8 11-07-2008
Excavator 360 A58
Below 10 tonne Technical Test – Theory

For questions 17 and 18 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

17. Using the Operator’s Manual, state the figure for setting track tension. For wheeled units,
state the tyres’ operating pressure.

18. Using the Operator’s Manual, state the cold-starting procedure for the machine.

19. State the purpose of the check valve(s) located on the boom cylinder rams.

A
Preparing for work continued

20. What is the purpose of a roll or ROPS frame?

21. If checking the oil level using a dipstick, why must gloves be worn?

22. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

23. What is the purpose of the counterweight of the machine?

24. What is meant by zero-tail swing excavators?

25. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

26. If both travel levers (or travel pedal for wheeled machines) are pushed forwards when the
Travelling and
manoeuvring

track motors (or driving wheels) are in front of the cab, in which direction would the
machine move?

continued…

CPCS Technical Test – A58 Theory Q


© Construction Industry Training Board 2008 Page 3 of 8 11-07-2008
Excavator 360 A58
Below 10 tonne Technical Test – Theory

27. If the machine is being travelled or working on the public highway, including adjacent
pavements and verges, the Road Traffic Act applies. a) What type of licence and which
classes should the operator hold and b) what is the minimum age allowed?

A
Travelling and manoeuvring continued

28. When MUST a banksman/signaller be used before moving an excavator?

29. Why must the seat belt be worn, even with the cab door closed?

30. Give FOUR reasons that may cause the machine to tip over – forwards and/or sideways.

31. What information does the ‘dig-envelope’ (also known as ‘working range’) chart give?
(Candidates may be shown a copy of a chart)

32. Explain ALL visual checks that must be carried out on all types of quick-hitch bucket
attaching systems before use.

A
Setting up for work

33. On a semi-automatic quick-hitch bucket attaching system: a) what is the purpose of the safety
pin and b) what checks MUST be made to the pin before use?

34. Cable avoidance tools (CATs) can detect a variety of buried services. What type of material
do they have limitations in locating?

continued…

CPCS Technical Test – A58 Theory Q


© Construction Industry Training Board 2008 Page 4 of 8 11-07-2008
Excavator 360 A58
Below 10 tonne Technical Test – Theory

35. Describe ONE physical method of checking that a bucket is fully secured to the quick-hitch
coupler prior to work.

36. Name TWO types of equipment used to ensure that excavation levels, measurements and
positions are to the required specification.

37. When working in a confined area or space: a) what danger can be present with regards to
the counterweight of the machine, b) what is the recommended minimum distance and c)
what measures must be implemented if the gap is less?

A
Setting up for work continued

38. If setting up to excavate in a confined area, name TWO things that should be taken into
account before starting.

39. What particular and specific hazards can affect the stability of the machine when working
on old industrial (Brownfield) sites?

40. If setting up to work in a pedestrianised area, state THREE factors that need to be taken
into account.

41. The operator is asked to excavate a new trench. State FIVE different requirements that must
be considered or implemented before work commences.

42. Before manually changing any bucket: a) where should the bucket be positioned (in relation
to the ground) before removing the final pin and b) why?

continued…

CPCS Technical Test – A58 Theory Q


© Construction Industry Training Board 2008 Page 5 of 8 11-07-2008
Excavator 360 A58
Below 10 tonne Technical Test – Theory

43. With regards to lifting accessories, irrespective of who supplied the accessories, what
THREE factors should be ensured before the accessories are used?
Setting up for work continued

44. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when setting up the machine and b) explain why a
distance should be kept.

45. If a trench has a depth of 2.0 metres: a) what is the minimum distance to maintain from the
edge of the trench when placing spoil and b) explain why.

46. Why should different soils be segregated during excavating?

47. Give THREE reasons why an oversize bucket should not be used when excavating
trenches to specification.

48. a) Why should the slewing direction be to the left wherever possible and b) explain why.

A
Working tasks

49. Why must excavator operators not begin to load vehicles until the forward tipping dumper
driver is clear of their machine?

50. What makes up the total (or gross) weight of a load that is to be lifted’?

51. Using the lifting capacity diagram (Annex A): a) what is the maximum lifting capacity at
4 metres radius over the sides of the track with the load at a height of 1.0 metre, b) what
effect does fitting a bucket have on the lifting capacity and c) what effect does the dozer
blade have on the lifting capacity?

52. What factors determine the shoring requirements of a trench?

continued…

CPCS Technical Test – A58 Theory Q


© Construction Industry Training Board 2008 Page 6 of 8 11-07-2008
Excavator 360 A58
Below 10 tonne Technical Test – Theory

53. Give TWO reasons why, wherever possible, operators should excavate ground in layers.

54. If a yellow coloured marker tape is unearthed during excavating, which two types of
services could this indicate?

55. What is the nearest distance allowed to gas pipes when excavating with the machine?

A
Working tasks continued

56. When slewing with a load, where should the operator be looking?

57. What is the meaning of this hand signal (being demonstrated by the Tester)?

58. Explain a possible danger if the excavator is lifting a load on sloping ground, even though
the load chart indicates that the machine can lift that load?

59. Before lowering a pipe into a deep trench, what trench-related checks must be made?

60. If the excavator is carrying out deep excavating work using the full working range, what
hazard may occur?

61. Describe TWO actions to be taken for an open trench at the end of a working day.
Completing work

62. Before leaving the cab for a rest break, after parking and switching off the machine, what
final action must be carried out?

63. When parking the machine at the end of the shift, name THREE places where the machine
Shutdown

should NOT be parked.

continued…

CPCS Technical Test – A58 Theory Q


© Construction Industry Training Board 2008 Page 7 of 8 11-07-2008
Excavator 360 A58
Below 10 tonne Technical Test – Theory

64. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.
Shutdown continued

65. Why should an excavator be re-fuelled at the end of the day?

CPCS Technical Test – A58 Theory Q


© Construction Industry Training Board 2008 Page 8 of 8 11-07-2008
Excavator 360 A59
Above 10 tonne Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of the Health and Safety at Work Act must employees follow?

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations.

8. Plant operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A59 Theory Q


© Construction Industry Training Board 2008 Page 1 of 8 11-07-2008
Excavator 360 A59
Above 10 tonne Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a 360 excavator?

11. The operator has to fit and use a new bucket using a quick-hitch coupler that they are
unfamiliar with. What do Regulations (i.e. PUWER 98) and other guidance require the
Roles and responsibilities continued

operator to have?

12. What are the possible outcomes if being prosecuted (by judicial bodies) for not complying
with legislation and regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to 360 excavator
operations.

14. How can a qualification or card benefit a plant operator?

15. Name THREE ways that a plant operator can contribute in ensuring repeat business with
the client or main contractor.

16. Where should the excavator’s Operator’s Manual be kept and why?

A
Preparing for work

17. If the operator has to top-up the hydraulic oil, state TWO precautions to ensure cleanliness
of the system.

continued…

CPCS Technical Test – A59 Theory Q & A


© Construction Industry Training Board 2008 Page 2 of 8 11-07-2008
Excavator 360 A59
Above 10 tonne Technical Test – Theory

For questions 18 and 19 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

18. Using the Operator’s Manual, state the figure for setting track tension. For wheeled units,
state the tyres’ operating pressure.

19. Using the Operator’s Manual, state the cold-starting procedure for the machine.

20. State the purpose of the check valve(s) located on the boom cylinder rams.
Preparing for work continued

21. What is the purpose of a roll or ROPS frame?

22. If checking the oil level using a dipstick, why must gloves be worn?

23. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

24. What is the purpose of the counterweight of the machine?

25. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

26. If both travel levers (or travel pedal for wheeled machines) are pushed forwards when the
Travelling and manoeuvring

track motors (or driving wheels) are in front of the cab, in which direction would the
machine move?

27. If the machine is being travelled or working on the public highway, including adjacent
pavements and verges, the Road Traffic Act applies. a) What type of licence and which
classes should the operator hold and b) what is the minimum age allowed?

continued…

CPCS Technical Test – A59 Theory Q & A


© Construction Industry Training Board 2008 Page 3 of 8 11-07-2008
Excavator 360 A59
Above 10 tonne Technical Test – Theory

28. When MUST a banksman/signaller be used before moving an excavator?


Travelling and manoeuvring continued

29. Why must the seat belt be worn, even with the cab door closed?

30. Give FOUR reasons that may cause the machine to tip over – forwards and/or sideways.

31. What information does the ‘dig-envelope’ (also known as ‘working range’) chart give?
(Candidates may be shown a copy of a chart)

32. Explain ALL visual checks that must be carried out on all types of quick-hitch bucket
attaching systems before use.

33. On a semi-automatic quick-hitch bucket attaching system: a) what is the purpose of the safety
pin and b) what checks MUST be made to the pin before use?
Setting up for work

34. Cable avoidance tools (CATs) can detect a variety of buried services. What type of material
do they have limitations in locating?

35. Describe ONE physical method of checking that a bucket is fully secured to the quick-hitch
coupler prior to work.

36. Name TWO types of equipment used to ensure that excavation levels, measurements and
positions are to the required specification.

continued…

CPCS Technical Test – A59 Theory Q & A


© Construction Industry Training Board 2008 Page 4 of 8 11-07-2008
Excavator 360 A59
Above 10 tonne Technical Test – Theory

37. When working in a confined area or space: a) what danger can be present with regards to
the counterweight of the machine, b) what is the recommended minimum distance and c)
what measures must be implemented if the gap is less?

38. If setting up to excavate in a confined area, name TWO things should be taken into account
before starting.

39. What particular and specific hazards can affect the stability of the machine when working
on old industrial (Brownfield) sites?

40. If setting up to work in a pedestrianised area, state THREE factors that need to be taken
into account.
Setting up for work continued

41. The operator is asked to excavate a new trench. State FIVE different requirements that must
be considered or implemented before work commences.

42. Before manually changing any bucket: a) where should the bucket be positioned (in relation
to the ground) before removing the final pin and b) why?

43. With regards to lifting accessories, irrespective of who supplied the accessories, what
THREE factors should be ensured before the accessories are used?

44. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when setting up the machine and b) explain why a
distance should be kept.

continued…

CPCS Technical Test – A59 Theory Q & A


© Construction Industry Training Board 2008 Page 5 of 8 11-07-2008
Excavator 360 A59
Above 10 tonne Technical Test – Theory

45. If a trench has a depth of 2.0 metres: a) what is the minimum distance to maintain from the
edge of the trench when placing spoil and b) explain why.

46. Why should different soils be segregated during excavating?

47. Give THREE reasons why an oversize bucket should not be used when excavating
trenches to specification.

48. a) Why should the slewing direction be to the left wherever possible and b) explain why.

49. Why must excavator operators not begin to load vehicles until the forward tipping dumper
driver is clear of their machine?
Working tasks

50. What makes up the total (or gross) weight of a load that is to be lifted’?

51. Using the lifting capacity diagram (Annex A): a) if the machine is equipped with a 2.50
metre long dipper, what is the maximum lifting capacity in tonnes at 6 metres radius over
the sides of the track with the load at 3.0 metres height and b) if a longer dipper is fitted,
what effect does that have on the lifting capacity?

52. What factors determine the shoring requirements of a trench?

53. Give TWO reasons why, wherever possible, operators should excavate ground in layers.

54. If a yellow coloured marker tape is unearthed during excavating, which two types of
services could this indicate?

continued…

CPCS Technical Test – A59 Theory Q & A


© Construction Industry Training Board 2008 Page 6 of 8 11-07-2008
Excavator 360 A59
Above 10 tonne Technical Test – Theory

55. What is the nearest distance allowed to gas pipes when excavating with the machine?

56. When slewing with a load, where should the operator be looking?

57. What is the meaning of this hand signal (being demonstrated by the tester)?
Working tasks continued

58. Explain a possible danger if the excavator is lifting a load on sloping ground, even though
the load chart indicates that the machine can lift that load?

59. Before lowering into or moving a drag box into a trench, what trench-related checks must
be made?

60. If the excavator is carrying out deep excavating work using the full working range, what
hazard may occur?

61. Describe TWO actions to be taken for an open trench at the end of a working day.
Completing work

62. Before leaving the cab for a rest break, after parking and switching off the machine, what
final action must be carried out?

63. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

A
Shutdown

64. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.

CPCS Technical Test – A59 Theory Q & A


© Construction Industry Training Board 2008 Page 7 of 8 11-07-2008
Excavator 360 A59
Above 10 tonne Technical Test – Theory

65. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, what
checks must be carried out before they leave the cab?

A
Shutdown continued

66. Why should an excavator be re-fuelled at the end of the day?

CPCS Technical Test – A59 Theory Q & A


© Construction Industry Training Board 2008 Page 8 of 8 11-07-2008
Mobile Crane A60
Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

A
Roles and responsibilities

4. What THREE main duties of The Health and Safety at Work Act must employees follow?

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

8. Crane operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A60 Theory Q


© Construction Industry Training Board 2008 Page 1 of 8 11-07-2008
Mobile Crane A60
Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. State the functions or job role of the following personnel:


a) Appointed Person, b) Crane Supervisor, c) Slinger, d) Signaller

11. In what situation does a hard hat NOT need to be worn when operating a mobile crane?
Roles and responsibilities continued

12. The operator has to use a new model of mobile crane that they are unfamiliar with. What do
Regulations (i.e. LOLER 98) and other guidance require the operator to have?

13. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

14. Give TWO examples of where The Work at Height Regulations may apply to mobile crane
operations.

15. How can a qualification or card benefit a crane operator?

16. Name THREE ways that a crane operator can contribute in ensuring repeat business with
the client or main contractor.

continued…

CPCS Technical Test – A60 Theory Q


© Construction Industry Training Board 2008 Page 2 of 8 11-07-2008
Mobile Crane A60
Technical Test – Theory

17. Where should the Operator’s Manual be kept and why?

18. What is the difference between a contract lift and a ‘standard’ crane hire?

19. Crane operations fall within the scope of the Lifting Operations and Lifting Equipment
Regulations (LOLER) 1998. Name TWO requirements of the regulations with regards to
lifting.

20. a) What is meant by the lifting capacity of the crane and b) who determines it?

21. What is the purpose of a roll or ROPS frame?

A
Preparing for work

22. What are the THREE actions or stages that a crane operator undertakes during pre-use
inspections?

For questions 23 and 24 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

23. Using the Operator’s Manual, state the figure for the tyre pressures.

24. Using the Operator’s Manual, state the cold-starting procedure for the crane (can be the
drive engine or auxiliary engine).

25. What is the purpose of the hoisting limit switch (also known as the ‘chandelier’)?

26. What is meant by the footprint of the crane?

27. Which parts of the crane is the radius (for lifting) measured from?

continued…

CPCS Technical Test – A60 Theory Q


© Construction Industry Training Board 2008 Page 3 of 8 11-07-2008
Mobile Crane A60
Technical Test – Theory

28. If checking the oil level using a dipstick, why must gloves be worn?

29. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

30. What is the purpose of counterweight(s) on the crane?

A
Preparing for work continued

31. a) How does the number of lines or falls of rope affect the lifting capacity for the crane and
b) how is hoist speed affected when the number of lines (or falls of rope) is reduced?

32. When would a fly jib or lattice extension be fitted and used?

33. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

34. As a lifting machine, the crane must be thoroughly examined. a) What is the purpose of the
examination and b) who would carry out the examination?

35. If the crane has to travel on the public highway, the Road Traffic Act applies. a) What type
of licence and which classes should the operator hold and b) what is the minimum age
allowed?
Travelling and manoeuvring

36. a) What is the minimum distance allowed near open trenches when travelling the crane and
b) explain why.

37. When MUST a banksman or signaller be used before moving a crane?

continued…

CPCS Technical Test – A60 Theory Q


© Construction Industry Training Board 2008 Page 4 of 8 11-07-2008
Mobile Crane A60
Technical Test – Theory

38. Why must the seat belt be worn, even with the cab door closed?
Travelling and manoeuvring

A
continued

39. If asked to travel with a suspended load, name FIVE factors that must be taken into
account by the operator before moving

40. a) Which part of the crane applies loading or pressure to the ground and b) name TWO
ways that pressure can be reduced.

41. If a load of 40 tonnes is lifted on 4 falls or lines of rope, what is the tension in each fall or
line?

42. Wind speeds can be variable throughout the working day. What action must be taken to
ensure safe working conditions are maintained?

43. What is the main purpose of the Rated Capacity Indicator (RCI)?
Setting up for work

44. When working in a confined area or space: a) what danger can be present with regards to
the counterweight of the machine, b) what is the recommended minimum distance and c)
what measures must be implemented if the gap is less?

45. If setting up to lift loads in a pedestrianised area, state THREE factors that need to be
taken into account.

46. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on metal pylons when setting up the machine and b) explain why a distance
should be kept.

continued…

CPCS Technical Test – A60 Theory Q


© Construction Industry Training Board 2008 Page 5 of 8 11-07-2008
Mobile Crane A60
Technical Test – Theory
Setting up for work continued

47. On a busy construction site, how would the slinger/signaller be identified to the crane
operator?

48. a) Who only can authorise partial outrigger extensions and b) what is the effect on lifting
capacity by partially extending the outriggers?

49. The safe working load or working load limit (SWL/WLL) of a multi-leg chain sling only
applies in what TWO conditions or configuration?

50. The number of falls has been changed on the hook block. How has this action affected the
RCI?

51. Name TWO things that happen if the hoist rope is not vertical when lifting a load.

52. Give FOUR reasons that may cause the crane to overturn.
Working tasks

53. When slewing with a load, where should the operator be looking?

54. If radios are to be used during the lifting operations, what FIVE actions and checks must be
made by the crane operator before use?

55. What makes up the total (or gross) weight of a load that is to be lifted?

continued…

CPCS Technical Test – A60 Theory Q


© Construction Industry Training Board 2008 Page 6 of 8 11-07-2008
Mobile Crane A60
Technical Test – Theory

56. Using the lifting capacity diagram (Annex A): a) what is the maximum lifting capacity, b)
what boom extension is required for a load weighing 7.6 tonnes needed to be placed at
15 metres radius and c) what counterweight is required?

57. Name TWO ways that wet weather can affect lifting operations.

58. As the crane rotates through 360 degrees with a load, what happens to the loading on each
outrigger or wheel?

59. What effect can a swinging load have on a crane?

60. An operator has been asked to transport a load down a small section of the public highway,
for which The Road Traffic Act applies. What effect does this have on crane operations?
Working tasks continued

61. During the lifting operation, part of the task cannot be carried out as detailed in the lift plan.
a) What initially must happen to the lifting operation and b) who authorises any changes?

62. Name THREE ways in which wind speed can affect the lifting operation.

63. If a load is slewed rather quickly, what TWO initial effects does it have on the load whilst
slewing?

64. If the words STOP NOW are given to the crane operator by radio during the lift, what action
must the operator take?

65. Only two legs of an 8 tonne 4 legged chain sling are being used. What is the maximum load
that can be lifted?

continued…

CPCS Technical Test – A60 Theory Q


© Construction Industry Training Board 2008 Page 7 of 8 11-07-2008
Mobile Crane A60
Technical Test – Theory

66. If a heavy load is being slewed at high speed over at least 180 degrees, what TWO factors
must the operator and signaller take into account?

67. How does the deflection of the boom or jib affect lift?

A
Working tasks continued

68. What is the meaning of this hand signal (being demonstrated by the Tester)?

69. If the hook block inadvertently (accidentally) lands, what course of action should be taken?

70. Two cranes are working in the same vicinity that encroach the operating radius of each.
What actions would the lift plan or method statement normally specify?

71. Before leaving the cab for a rest break, after parking and switching off the machine, what
Completing

final action must be carried out?


work

72. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

A
Shutdown

73. Why should the crane be re-fuelled at the end of the day?

CPCS Technical Test – A60 Theory Q


© Construction Industry Training Board 2008 Page 8 of 8 11-07-2008
Appointed Person A61
Technical Test – Theory

Note: The candidate may refer to copies of the guidance notes of PUWER 1998,
LOLER 1998 and BS 7212 parts 1 to 3 during the theory test

1. Explain the difference between an employing and user organisation.

2. State why there must be a safe system of work.

3. Name TWO duties of the crane operator.

4. Name FOUR items that must be recorded when a thorough examination on a lifting
appliance has been carried out.
Legislative and regulative

5. What is the Factor of Safety when lifting personnel?

6. Who has overall control of the lifting operation?

7. When a crane company hires out a crane, name TWO main legal requirements the hire
company must meet regarding the crane and driver.

8. To whom should the appointed person give all details involving the lifting operation?

9. Who is responsible for providing the contractor with written details of the work to be done?

10. Name TWO possible penalties for not following legal requirements when using a crane.

A
continued…

CPCS Technical Test – A61 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Appointed Person A61
Technical Test – Theory

11. Which part of BS 7121 is specific to mobile cranes?

12. State which bodies have to be notified when planning a lift on or near by: a) Rivers,
b) Airfields, c) Highways, d) Railways, e) Live plant.

13. What is the definition of a competent person as stated by Codes of Practice?

A
Legislative and regulative continued

14. State ONE difference between a regulation and a Code of Practice.

15. What types of crane are not covered by BS 7121?

16. State the legislation and the regulation therein that refers to the stability of cranes.

17. What is the main aim of the HASWA 1974?

18. Name two possible penalties for not following legal requirements when using a crane.

19. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

20. What is the minimum recommended distance that is allowed between the counterweight(s)
Lifting equipment (cranes)

of the crane and another object/structure?

21. Explain the purpose of the over hoist limit switch.

continued…

CPCS Technical Test – A61 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Appointed Person A61
Technical Test – Theory

22. Name THREE factors that determine the safe working load of the crane.

23. What is a Load Radius Indicator?

24. Define the term ‘Radius’.

25. Describe how to calculate the area of support beneath a crane outrigger, which gives
maximum possible safeguards against ground subsidence.

A
Lifting equipment (cranes) continued

26. If a crane is out of level, what effect will it have on the radius?

27. To lift a load of 12 tonnes on a two point lift using single leg slings, what is the required
SWL (WLL) for each sling with an included angle of 87 degrees? Please explain your
calculation.

28. In what application have single leg slings been rated with their SWL (WLL)?

29. When and why are axle or suspension locks fitted to most mobile cranes?

30. What advantage is there by increasing the number of falls on a hook block?

31. What does the term ‘structural strength’ relate to with regard to the lifting capacity of the
crane?

continued…

CPCS Technical Test – A61 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Appointed Person A61
Technical Test – Theory

32. What is a Load Radius Indicator?

A
Lifting equipment (cranes) continued

33. What are the types of warning that an RCI will indicate, and at what point are they
activated?

34. a) Where must the load radius diagram on a tower crane be located and b) what
information must it contain?

35. How does the deflection of the boom on a mobile crane or jib affect lift?

36. State the maximum recommended angle for single leg slings when used as a pair.

37. List FOUR items to be found on a chain sling inspection certificate.

38. Name a design of accessory hook that is exempt from being fitted with a safety catch.

39. What is the maximum angle a bow shackle used as a pair on a crane hook can be used at?

A
Lifting accessories

40. How long is a thorough examination for a lifting accessory valid for?

41. How is the SWL/WLL/rated capacity for multi-legs slings determined?

42. Give TWO methods of obtaining the centre of gravity on an unbalanced load.

43. If a load of 20 tonnes is lifted on 4 falls of rope, what is the tension in each fall?

44. Name three markings found on multiple leg slings.

continued…

CPCS Technical Test – A61 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Appointed Person A61
Technical Test – Theory

45. State the sling angle if the distance between the lifting points is one and a half times the leg
Lifting accessories

length.
continued

46. What is the Factor of Safety for chains?

47. If radios are to be used during the lifting operations, what FIVE actions and checks must be
made before use?

A
Communication

48. Using simple graphics draw the recommended hand signals for: a) emergency stop and b)
hoist up.

49. Why is it recommended to complete a report after the completion of the lifting operation?

50. State the safe procedure to be followed before lifting or lowering a load down a shaft or
excavation.

51. State SIX environmental factors that can affect an external lifting operation.

52. Why must a crane driver never try and ‘drag’ a load?
Planning

53. List TWO methods of obtaining the accurate weight of a load.

54. Identify FOUR requirements for ensuring the stability of mobile cranes on site.

continued…

CPCS Technical Test – A61 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Appointed Person A61
Technical Test – Theory

55. Give THREE examples of how excessive rain can affect an external lifting operation when
using a mobile crane.

56. A replacement crane driver has been supplied to continue the lift. What must they be made
aware of before further lifting can take place?

57. During dismantling operations, what is the recommended percentage of de-rating if lifting a
load from height where the weight has been estimated?

58. Give one reason why it is not advised to lift a single load using the fly hook block and main
hook block.

59. Name the section in BS 7121 where advice is given if carrying out’ free-on-wheels’ duties.

A
Planning continued

60. Explain the additional requirements of a standard lift over a basic lift.

61. With a bearing load of 14,000 kg and an outrigger base of 1m square, what would be the
resultant ground pressure in kg?

62. Define the term ‘outreach’.

63. During dismantling operations, what is the recommended percentage of de-rating if lifting a
load from height where the load has been estimated?

64. Where a scale drawing is being used, if the scale used is 1:200, what is the 1 cm
equivalent to?

65. If planning to lift loads in or near a pedestrianised area, what main factor needs to be taken
into account?

continued…

CPCS Technical Test – A61 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Appointed Person A61
Technical Test – Theory

66. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on metal pylons and b) explain why a distance should be kept.

A
Planning continued

67. Two cranes are working in the same vicinity that encroach the operating radius of each.
What actions should the lift plan or method statement normally specify?

CPCS Technical Test – A61 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Crane/Lifting Operations Supervisor A62
Technical Test – Theory

Note: The candidate may refer to copies of the guidance notes of PUWER 1998,
LOLER 1998 and BS 7212 parts 1 to 3 during the theory test

1. Explain the difference between an employing and user organisation.

2. State why there must be a safe system of work.

3. Name TWO duties of the crane operator.

4. Name FOUR items that must be recorded when a thorough examination on a lifting
Legislative and regulative

appliance has been carried out.

5. What is the Factor of Safety when lifting personnel?

6. Who has overall control of the lifting operation?

7. When a crane company hires out a crane, name TWO main legal requirements the hire
company must meet regarding the crane and driver.

8. To whom should the appointed person give all details involving the lifting operation?

9. Who is responsible for providing the contractor with written details of the work to be done?

continued…

CPCS Technical Test – A62 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Crane/Lifting Operations Supervisor A62
Technical Test – Theory

10. Name TWO possible penalties for not following legal requirements when using a crane.

11. Which part of BS 7121 is specific to mobile cranes?

12. What is the definition of, or how can a hazard be described?

13. What is the purpose of a risk assessment?

14. List SIX typical subject areas that should be covered in a site induction.

A
Legislative and regulative continued

15. What THREE main duties of The Health and Safety at Work Act must employees follow?

16. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

17. a) What is the purpose of a Method Statement and b) what is required of the operator?

18. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

19. The operator has to use a new model of crane that they are unfamiliar with. What do
Regulations (i.e. LOLER 98) and other guidance require the operator to have?

continued…

CPCS Technical Test – A62 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Crane/Lifting Operations Supervisor A62
Technical Test – Theory

20. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?
Legislative and regulative continued

21. What do The Work at Height Regulations require of crane supervisors?

22. How can a qualification or card benefit a crane supervisor?

23. What is the difference between a contract lift and a ‘standard’ crane hire?

24. What effect does boom and chassis deflection have on the radius of a crane?

25. What is the minimum recommended distance that is allowed between the counterweight(s)
of the crane and another object/structure?

26. What advantage is there by increasing the number of falls on a hook block?

27. Explain the purpose of the over hoist limit switch.

A
Lifting equipment (cranes)

28. Name THREE factors that determine the safe working load of the crane.

29. Why is it important to ensure the wheels are clear of the ground when outriggers are
employed?

30. What is a Load Radius Indicator?

31. Define the term ‘Radius’.

continued…

CPCS Technical Test – A62 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Crane/Lifting Operations Supervisor A62
Technical Test – Theory

32. Describe how to calculate the area of support beneath a crane outrigger, which gives
maximum possible safeguards against ground subsidence.

33. If a crane is out of level, what effect will it have on the radius?

34. What are the types of warning that an RCI will indicate?

35. To lift a load of 12 tonnes on a two point lift using single leg slings, what is the required
SWL (WLL) for each sling with an included angle of 87 degrees? Please explain your
calculation.

A
Lifting equipment (cranes) continued

36. In what application have single leg slings been rated with their SWL (WLL)?

37. When and why are axle or suspension locks fitted to most mobile cranes?

38. According to BS 7121 part 1: a) what is the minimum number of allowable turns on the
hoist drum and b) who decides the actual minimum for a given model of crane?

39. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using a crane.

40. Name THREE ways that a crane supervisor can contribute in ensuring repeat business with
the client or main contractor.

41. Where should the crane’s Operator’s Manual be kept and why?

continued…

CPCS Technical Test – A62 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Crane/Lifting Operations Supervisor A62
Technical Test – Theory

42. a) What is meant by the lifting capacity of the crane and b) who determines it?

43. What are the THREE actions or stages that a crane operator undertakes during pre-use
inspections?

A
Lifting equipment (cranes) continued

44. a) On a tower crane, where must the load radius diagram be located and b) what
information must it contain?

45. A tower crane has been delivered to site, assembled and configured for lifting. What must
be carried out before lifting starts and by whom?

46. Name FIVE requirements that must be followed if accessing the end of the jib for
maintenance purposes.

47. How does the deflection of the boom on a mobile crane or jib affect lift?

48. State the maximum recommended angle for single leg slings when used as a pair.

49. List FOUR items to be found on a chain sling inspection certificate.

A
Lifting accessories

50. Name a design of accessory hook that is exempt from being fitted with a safety catch.

51. What is the maximum angle a bow shackle used as a pair on a crane hook can be used at?

52. How long is a thorough examination for a lifting accessory valid for?

continued…

CPCS Technical Test – A62 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Crane/Lifting Operations Supervisor A62
Technical Test – Theory

53. How is the SWL/WLL/rated capacity for multi-legs slings determined?


Lifting accessories
continued

54. Give TWO methods of obtaining the centre of gravity on an unbalanced load.

55. If radios are to be used during the lifting operations, what FIVE actions and checks must be
made before use?
Communication

56. What is the meaning of this hand signal (being demonstrated by the Tester)?

57. State the safe procedure to be followed before lifting or lowering a load down a shaft or
excavation.

58. State SIX environmental factors that can affect an external lifting operation.

59. Why must a crane driver never try and ‘drag’ a load?

60. List TWO methods of obtaining the accurate weight of a load.


Supervising

61. Identify FOUR requirements for ensuring the stability of mobile cranes on site.

62. Give THREE examples of how excessive rain can affect an external lifting operation when
using a mobile crane.

63. A replacement crane driver has been supplied to continue the lift. What must they be made
aware of before further lifting can take place?

continued…

CPCS Technical Test – A62 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Crane/Lifting Operations Supervisor A62
Technical Test – Theory

64. If setting up to lift loads near a pedestrianised area, what main factor needs to be taken into
account?

65. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on metal pylons and b) explain why a distance should be kept.

66. If a heavy load is being slewed at high speed over at least 180 degrees, what TWO factors
must the operator and signaller take into account?
Supervising continued

67. Two cranes are working in the same vicinity that encroach the operating radius of each.
What actions would the lift plan or method statement normally specify?

68. At the end of the shift: a) in what position should luffing jibs on a tower crane be left in and
b) why?

69. During the lifting operation, part of the task cannot be carried out as detailed in the lift plan.
a) What initially must happen to the lifting operation and b) who authorises any changes?

CPCS Technical Test – A62 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Pedestrian Operated Tower Crane A63
Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

4. What THREE main duties of The Health and Safety at Work Act must employees follow?
Roles and responsibilities

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

8. Crane operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A63 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Pedestrian Operated Tower Crane A63
Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. State the functions or job role of the following personnel:


a) Appointed Person, b) Crane Supervisor, c) Slinger, d) Signaller

A
Roles and responsibilities continued

11. The operator has to use a new model of POTC that they are unfamiliar with. What do
Regulations (i.e. LOLER 98) and other guidance require the operator to have?

12. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

13. What do The Work at Height Regulations require of crane operations.

14. How can a qualification or card benefit a crane operator?

15. Name THREE ways that a crane operator can contribute in ensuring repeat business with
the client or main contractor.

16. Where should the Operator’s Manual be kept and why?

A
Preparing for work

17. What is the difference between a contract lift and a ‘standard’ crane hire?

18. a) Where must the load radius diagram be located and b) what information must it contain?

continued…

CPCS Technical Test – A63 Theory Q


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Pedestrian Operated Tower Crane A63
Technical Test – Theory

19. a) What is meant by the lifting capacity of the crane and b) who determines it?

20. What are the THREE actions or stages that a crane operator undertakes during pre-use
inspections?

For questions 21 and 22 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

21. Using the Operator’s Manual or other, state the procedure for changing the number of falls
on the hook block.

22. Using the Operator’s Manual or other, state the maximum wind speed the crane may be
operated in.
Preparing for work continued

23. What prevents the hook block from contacting the jib pulley?

24. A POTC has been delivered to site, assembled and configured for lifting. What must be
carried out before lifting starts and by whom?

25. Which parts of the crane is the radius (for lifting) measured from?

26. Name TWO advantages of using a POTC over other forms of lifting equipment.

27. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

28. What is the purpose of counterweight(s) on the crane?

continued…

CPCS Technical Test – A63 Theory Q


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Pedestrian Operated Tower Crane A63
Technical Test – Theory

29. a) How does the number of lines or falls of rope affect the lifting capacity for the crane and
b) how is hoist speed affected when the number of lines (or falls of rope) is reduced?

A
Preparing for work continued

30. a) What checks should be made to the ground conditions and b) when should the checks
be made?

31. What is the purpose of the flags situated on the jib?

32. What checks should be made to the transmitter of a remote-controlled POTC before work?

33. On inclined jib types, what must be undertaken after the jib is inclined?

34. If assisting in erecting a POTC, why is it important that the manufacturer’s procedures are
followed precisely?

35. If a load of 8 tonnes is lifted on 2 falls or lines of rope, what is the tension in each fall or
line?

36. If the legs of a chain sling are more than 90 degrees apart from each other, what happens
Setting up for work

to the SWL?

37. What information is needed when estimating the weight of a load?

38. Wind speeds can be variable throughout the working day. What action must be taken to
ensure safe working conditions are maintained?

39. What is the main purpose of the Rated Capacity Indicator (RCI)?

40. What do the words SWL, as stamped on lifting accessories, signify?

continued…

CPCS Technical Test – A63 Theory Q


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Pedestrian Operated Tower Crane A63
Technical Test – Theory

41. If setting up to lift loads in a pedestrianised area, what main factor needs to be taken into
account?

42. a) What is the recommended minimum distance to be kept away from overhead power
Setting up for work continued

lines mounted on wooden poles when setting up the crane and b) explain why a distance
should be kept.

43. What is meant by centre of gravity, or how is the Centre of Gravity determined, on a load to
be lifted?

44. On a busy construction site, if required, how would the slinger/signaller be identified to the
crane operator?

45. The number of falls has been changed on the hook block. How has this action affected the
RCI?

46. The safe working load or working load limit (SWL/WLL) of a multi-leg chain sling only
applies in what TWO conditions or configuration?

47. Name TWO things that happen if the hoist rope is not vertical when lifting a load.

48. Apart from lifting using the hook, what other type of work can POTCs undertake?
Working tasks

49. What is jib deflection and when does it occur?

50. If radios are to be used during the lifting operations, what FIVE actions and checks must be
made by the crane operator before use?

51. What would happen if the operator faces the crane whilst using remote control?

continued…

CPCS Technical Test – A63 Theory Q


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Pedestrian Operated Tower Crane A63
Technical Test – Theory

52. Name TWO ways that wet weather can affect lifting operations.

53. What makes up the total (or gross) weight of a load that is to be lifted?

54. a) When is a trial lift carried out and b) name THREE checks to be made.

55. Using the lifting capacity diagram (supplied – Annex A), with a jib length of 33 metres:
a) what is the maximum possible lifting capacity in tonnes, b) what is the lifting capacity at
20.0 metres radius using 4 falls of rope and c) what is the difference in maximum lifting
capacity between a 2-falls hook block and a 4-falls hook block in 2-falls mode?

56. What effect can a swinging load have on a crane?


Working tasks continued

57. During the lifting operation, part of the task cannot be carried out as detailed in the lift plan.
a) What initially must happen to the lifting operation and b) who authorises any changes?

58. What problems can be created when operating the crane in high-speed drive?

59. Name THREE ways in which wind speed can affect the lifting operation.

60. If a load is slewed rather quickly, what TWO initial effects does it have on the load whilst
slewing?

61. When slewing with a load, where should the operator be looking?

62. If the words STOP NOW are given to the crane operator by radio during the lift, what action
must the operator take?

continued…

CPCS Technical Test – A63 Theory Q


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Pedestrian Operated Tower Crane A63
Technical Test – Theory

63. Only two legs of an 8 tonne 4 legged chain sling are being used. What is the maximum load
that can be lifted?

64. If a heavy load is being slewed at high speed over at least 180 degrees, what TWO factors
must the operator (and signaller) take into account?

65. If the hook block inadvertently (accidentally) lands, what course of action should be taken?

A
Working tasks continue

66. Two cranes are working in the same vicinity that encroach the operating radius of each.
What actions would the lift plan or method statement normally specify?

67. What is the meaning of this hand signal (being demonstrated by the Tester)?

68. During a rest break, or leaving the crane for a short period, what action should be taken for
the control box?

69. When would a load require netting?

70. At the end of the shift: a) in what position should jibs and trolleys be left in and b) why?

A
Shutdown

71. At the end of the shift: a) what THREE security measures should be applied and b) why?

CPCS Technical Test – A63 Theory Q


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Demolition Plant A65
Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

4. What THREE main duties of the Health and Safety at Work Act must employees follow?
Roles and responsibilities

5. What does the Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations.

8. Plant operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A65 Theory Q


© Construction Industry Training Board 2008 Page 1 of 7 11-07-2008
Demolition Plant A65
Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. In what situation does a hard hat NOT need to be worn when operating a demolition
machine?

11. The operator has to fit and use a new attachment using a quick-hitch coupler that they are
unfamiliar with. What do Regulations (i.e. PUWER 98) and other guidance require the
Roles and responsibilities continued

operator to have?

12. What are the possible outcomes if being prosecuted (by judicial bodies) for not complying
with legislation and regulations?

13. Give TWO examples of where The Work at Height Regulations may apply to demolition
machine operations.

14. How can a qualification or card benefit a plant operator?

15. Name THREE ways that a plant operator can contribute in ensuring repeat business with
the client or main contractor.

16. Where should the machine’s Operator’s Manual be kept and why?

A
Preparing for work

17. If the operator has to top-up the hydraulic oil, state TWO precautions to ensure cleanliness
of the system.

continued…

CPCS Technical Test – A65 Theory Q & A


© Construction Industry Training Board 2008 Page 2 of 7 11-07-2008
Demolition Plant A65
Technical Test – Theory

For questions 18 and 19 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

18. Using the Operator’s Manual, state the figure for setting track tension.

19. Using the Operator’s Manual, state the cold-starting procedure for the machine.

A
20. State the purpose of the check valve(s) located on the boom cylinder rams.
A

21. What is the purpose of a roll or ROPS frame?

22. If checking the oil level using a dipstick, why must gloves be worn?
Preparing for work continued

23. Name FOUR hydraulically operated attachments that may be used on Demolition.

24. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

25. What is the purpose of the counterweight of the machine?

26. On many demolition machines, the slew is restricted. a) What is the normal position for
working and b) why is the slew restricted?

27. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.

28. If both travel levers (or travel pedal for wheeled machines) are pushed forwards when the
track motors (or driving wheels) are in front of the cab, in which direction would the
machine move?

continued…

CPCS Technical Test – A65 Theory Q & A


© Construction Industry Training Board 2008 Page 3 of 7 11-07-2008
Demolition Plant A65
Technical Test – Theory

29. If the machine is crossing the public highway, the Road Traffic Act applies. a) What type of
licence and which classes should the operator hold and b) what is the minimum age
allowed?
A
Preparing for work continued

30. When MUST a banksman/signaller be used before moving the machine?

31. Why must the seat belt be worn, even with the cab door closed?
A

32. Give FOUR reasons that may cause the machine to tip over – forwards and/or sideways.
A

33. There are five areas within a demolition site. Name THREE of those areas.

34. Explain ALL visual checks that must be carried out on all types of quick-hitch attachment
connecting systems before use.

35. When using a high reach machine, describe FOUR considerations that must be taken into
account when setting up for work.
Setting up for work

36. On high reach machines, what should be considered when positioning the machine for
work?

37. On a semi-automatic quick-hitch attaching system: a) what is the purpose of the safety pin
and b) what checks MUST be made to the pin before use?

38. Cable avoidance tools (CATs) can detect a variety of buried services. What type of material
do they have limitations in locating?

continued…

CPCS Technical Test – A65 Theory Q & A


© Construction Industry Training Board 2008 Page 4 of 7 11-07-2008
Demolition Plant A65
Technical Test – Theory

39. Describe ONE physical method of checking that an attachment is fully secured to the quick-
hitch coupler prior to work.

40. When working in a confined area or space: a) what danger can be present with regards to
the counterweight of the machine, b) what is the recommended minimum distance and c)
what measures must be implemented if the gap is less?

41. If setting up to demolish in a confined area, name TWO things that should be taken into
account before starting.

42. What particular and specific hazards can affect the stability of the machine when working
on old industrial (Brownfield) sites?

A
Setting up for work continued

43. If setting up to work close to a pedestrianised area, state THREE factors that need to be
taken into account.

44. The operator is asked to demolish a new structure. State FIVE different requirements that
must be considered or implemented before work commences.

45. Before manually changing any attachment: a) where should the attachment be positioned
(in relation to the ground) before removing the final pin and b) why?

46. Before starting work on a new structure, how should the operator familiarise themselves
with the work zone?

47. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when setting up the machine and b) explain why a
distance should be kept.

continued…

CPCS Technical Test – A65 Theory Q & A


© Construction Industry Training Board 2008 Page 5 of 7 11-07-2008
Demolition Plant A65
Technical Test – Theory

48. If a trench has a depth of 2.0 metres: a) what is the minimum distance to maintain from the
edge of the trench when working and b) explain why.

49. Why should different materials be segregated during demolishing?

50. a) Why should the slewing direction be to the left wherever possible and b) explain why.

51. What are the requirements for creating a raised working platform?

52. If loading a vehicle with material, in what circumstances can the truck/wagon driver remain
in the cab?

A
Working tasks

53. a) Give ONE advantage and b) TWO disadvantages of using cameras to monitor the work.

54. If the structure being demolished has a basement, name two precautions to be taken to
ensure the integrity of the floor slab.

55. Explain the difference between pre-tensioned and post-tensioned members.

56. Name FOUR load bearing structural elements.

57. The operator must be aware at all times of the operation of the attachment, and of the
progress of the demolition. Give THREE examples on how they would achieve this.

58. Why should the jaws of a shear be kept downwards if working at height?

continued…

CPCS Technical Test – A65 Theory Q & A


© Construction Industry Training Board 2008 Page 6 of 7 11-07-2008
Demolition Plant A65
Technical Test – Theory

59. Why should linkage pins be checked on a regular basis?


Working tasks continued

60. Explain a possible danger if the machine is demolishing on sloping ground.

61. What actions should be taken to a partially demolished structure at the end of a working
day?

A
Completing work

62. Before leaving the cab for a rest break, after parking and switching off the machine, what
final action must be carried out?

63. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

64. Many demolition machines have a turbo-charged engine. a) What is the normal procedure
before switching off the engine after working and b) what happens if the procedure is not
followed?

65. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
operator before loading commences.
Shutdown

66. If the operator has loaded the machine onto a transporter/trailer on behalf of a driver, what
checks must be carried out before they leave the cab?

67. Why should a machine be re-fuelled at the end of the day?

CPCS Technical Test – A65 Theory Q & A


© Construction Industry Training Board 2008 Page 7 of 7 11-07-2008
Compact Crane A66
Technical Test – Theory

1. What is the definition of, or how can a hazard be described?

2. What is the purpose of a risk assessment?

3. List SIX typical subject areas that should be covered in a site induction.

4. What THREE main duties of The Health and Safety at Work Act must employees follow?
Roles and responsibilities

5. What does The Health and Safety at Work Act require employers to do with regards
specifically to plant?

6. a) What is the purpose of a Method Statement and b) what is required of the operator?

7. Name FOUR different types or levels of sanctions that can be applied (by employers and
judicial bodies) to plant operators who do not comply with, or follow legislation and
regulations?

8. Crane operators are generally regarded as ‘safety-critical’ workers. What does this mean?

continued…

CPCS Technical Test – A66 Theory Q


© Construction Industry Training Board 2008 Page 1 of 8 11-07-2008
Compact Crane A66
Technical Test – Theory

9. Name THREE ways in which an operator can minimise their impact upon the environment
whilst using the machine.

10. State the functions or job role of the following personnel:


a) Appointed Person, b) Crane Supervisor, c) Slinger, d) Signaller

A
Roles and responsibilities continued

11. In what situation does a hard hat NOT need to be worn when operating a compact crane?

12. The operator has to use a new model of compact crane that they are unfamiliar with. What
do Regulations (i.e. LOLER 98) and other guidance require the operator to have?

13. What are the possible outcomes if being prosecuted for not complying with legislation and
regulations?

14. How can a qualification or card benefit a crane operator?

15. Name THREE ways that a crane operator can contribute in ensuring repeat business with
the client or main contractor.

16. Where should the Operator’s Manual be kept and why?

17. What is the difference between a contract lift and a ‘standard’ crane hire?
Preparing for work

18. a) What is meant by the lifting capacity of the crane and b) who determines it?

19. What is the purpose of a roll or ROPS frame?

CPCS Technical Test – A66 Theory Q


© Construction Industry Training Board 2008 Page 2 of 8 11-07-2008
Compact Crane A66
Technical Test – Theory

20. What are the THREE actions or stages that a crane operator undertakes during pre-use
inspections?

For questions 21 and 22 the Operator’s Manual for the machine being used for the test
MUST be available for reference by the candidate

21. Using the Operator’s Manual, state the figure for the tyre pressures or checks to be made
to the track belts.

22. Using the Operator’s Manual, state the cold-starting procedure for the crane.

23. What prevents the hook block from contacting the jib pulley?

A
Preparing for work continued

24. What is meant by the footprint of the crane?

25. Which parts of the crane is the radius (for lifting) measured from?

26. If checking the oil level using a dipstick, why must gloves be worn?

27. Apart from the operator, who else may need to use the machine’s Operator’s Manual?

28. What is the purpose of counterweight(s) on the crane?

29. a) How does the number of lines or falls of rope affect the lifting capacity for the crane and
b) how is hoist speed affected when the number of lines (or falls of rope) is reduced?

30. When would a fly jib or extension be fitted and used?

continued…

CPCS Technical Test – A66 Theory Q


© Construction Industry Training Board 2008 Page 3 of 8 11-07-2008
Compact Crane A66
Technical Test – Theory

31. During work, the engine starts to overheat. Explain the danger if someone tries to remove
the radiator or expansion tank cap.
Preparing for work

A
continued

32. What checks should be made to the transmitter of a remote-controlled crane before work?

33. a) What is the minimum distance allowed near open trenches when travelling the crane and
b) explain why.

A
Travelling and manoeuvring

34. When MUST a banksman or signaller be used before moving a crane?

35. Why must the seat belt be worn, even with a ROPS frame or cab?

36. If asked to travel with a suspended load, name FIVE factors that must be taken into
account by the operator before moving

37. a) Which part of the crane applies loading or pressure to the ground and b) name TWO
ways that pressure can be reduced.

38. If assisting in fitting a fly jib/extension to the crane, why is it important that the
Setting up for work

manufacturers’ procedures are followed precisely?

39. If a load of 5 tonnes is lifted on 2 falls or lines of rope, what is the tension in each fall or
line?

40. Wind speeds can be variable throughout the working day. What action must be taken to
ensure safe working conditions are maintained?

continued…

CPCS Technical Test – A66 Theory Q


© Construction Industry Training Board 2008 Page 4 of 8 11-07-2008
Compact Crane A66
Technical Test – Theory

41. What is the main purpose of the Rated Capacity Indicator (RCI) or Load Moment Indicator
(LMI)?

42. When working in a confined area or space: a) what danger can be present with regards to
the counterweight (or rear) of the machine, b) what is the recommended minimum distance
and c) what measures must be implemented if the gap is less?

43. What do the letters SWL signify, as stamped on lifting accessories?

44. If setting up to lift loads in a pedestrianised area, state THREE factors that need to be
taken into account.
Setting up for work continued

45. a) If fitted, who only can authorise partial outrigger extensions and b) what is the effect on
lifting capacity if partially extending the outriggers?

46. a) What is the recommended minimum distance to be kept away from overhead power
lines mounted on wooden poles when setting up the machine and b) explain why a
distance should be kept.

47. On a busy construction site, how would the slinger/signaller be identified to the crane
operator?

48. The safe working load (SWL) of a multi-leg chain slings only applies in what TWO
conditions or configurations?

49. What information is needed when estimating the weight of a load?

CPCS Technical Test – A66 Theory Q


© Construction Industry Training Board 2008 Page 5 of 8 11-07-2008
Compact Crane A66
Technical Test – Theory

50. On hoist rope cranes, the number of falls has been changed on the hook block. How has
this action affected the RCI/LMI?

51. On mobile units, state the possible effect of lifting downhill on a slope.

52. Give FOUR reasons that may cause the crane to overturn.

53. If radios are to be used during the lifting operations, what FIVE actions and checks must be
made by the crane operator before use?

54. What makes up the total (or gross) weight of a load that is to be lifted?
Working tasks

55. Using either chart A, B or C on the lifting capacity diagrams (supplied – Annex A, B or C):
For chart A – a) what is the maximum lifting capacity, b) what is the maximum lift capacity at
10 metres radius and c) if a load of 1800 kg needs to be lifted to a height of 12 metres, what
is the maximum available radius?
For chart B – a) what is the maximum working height (to the nearest 0.2 metre), b) what is
the maximum outreach (to nearest 0.2 metre) and c) on the first stage boom extension, what
is the difference in kg when lowering from full raise to horizontal?
For chart C – a) what is the maximum working height (to the nearest 0.2 metre), b) at what
radius and height can a load of 0.3 tonnes be placed and c) what is the lift capacity at
maximum reach?

56. a) When is a trial lift carried out and b) name THREE checks to be made.

57. If the hook block inadvertently (accidentally) lands, what course of action should be taken?

continued…

CPCS Technical Test – A66 Theory Q


© Construction Industry Training Board 2008 Page 6 of 8 11-07-2008
Compact Crane A66
Technical Test – Theory

58. When working in a confined area or space, name THREE dangers that can be present.

59. During the lifting operation, part of the task cannot be carried out as detailed in the lift plan.
a) What initially must happen to the lifting operation and b) who authorises any changes?

60. Name THREE ways in which wind speed can affect the lifting operation.

61. If a load is slewed (or turned) rather quickly, what TWO initial effects does it have on the
load whilst slewing?

A
Working tasks continued

62. If the words STOP NOW are given to the crane operator by radio during the lift, what action
must the operator take?

63. Name TWO things that happen if the hoist rope (or lifting accessories) is (are) not vertical
when lifting a load.

64. On hoist rope units, if a heavy load is being slewed at high speed over at least 180
degrees, what TWO factors must the operator (and signaller) take into account?

65. As a slewing crane rotates through 360 degrees with a load, what happens to the loading
on each outrigger?

66. What effect can a swinging load have on a crane?

67. Only one leg of a 4 tonne 2 legged chain sling is being used. What is the maximum load
that can be lifted?

continued…

CPCS Technical Test – A66 Theory Q


© Construction Industry Training Board 2008 Page 7 of 8 11-07-2008
Compact Crane A66
Technical Test – Theory

68. What is the meaning of this hand signal (being demonstrated by the Tester)?
Working tasks continued

69. Two cranes are working in the same vicinity that encroach the operating radius of each.
What actions would the lift plan or method statement normally specify?

A
Completing work

70. Before leaving for a rest break, after parking and switching off the machine, what final
action must be carried out?

71. When parking the machine at the end of the shift, name THREE places where the machine
should NOT be parked.

72. The operator has been asked to drive the machine onto a transporter/trailer. a) Who is
responsible for the loading operations and b) state FOUR actions to be considered by the
Shutdown

operator before loading commences.

73. If applicable, why should the crane be re-fuelled at the end of the day?

CPCS Technical Test – A66 Theory Q


© Construction Industry Training Board 2008 Page 8 of 8 11-07-2008

You might also like