Practice Questions
Practice Questions
The Mukuru Co produces three products, A, B and C, all made from the
same material. Until now, it has used traditional absorption costing to
allocate overheads to its products. The company is now considering an
activity-based costing system in the hope that it will improve profitability.
Information for the three products for the last year is as follows:
A B C
Production and sales volumes (units) 15,000 12,000 18,00
0
Selling price per unit $7.50 $12 $13
Raw material usage (kg) per unit 2 3 4
Direct labour hours per unit 0·1 0·15 0·2
Machine hours per unit 0·5 0·7 0·9
Number of production runs per annum 16 12 8
Number of purchase orders per annum 24 28 42
Number of deliveries to retailers per 48 30 62
annum
The price for raw materials remained constant throughout the year at
$1·20 per kg. Similarly, the direct labour cost for the whole workforce was
$14·80 per hour. The annual overhead costs were as follows:
$
Machine set up costs 26,550
Machine running costs 66,400
Procurement costs 48,000
Delivery costs 54,320
YOU ARE REQUIRED TO:
(a)Calculate the full cost per unit for products A, B and C under traditional
absorption costing, using direct labour hours as the basis for
apportionment. (7 marks)
(b)Calculate the full cost per unit of each product using activity-based costing.
(12 marks)
Using your calculation from (a) and (b) above, explain how activity-based
costing may help The Mukuru Co improve the profitability of each product. (6
marks
QUESTION
Direct labour is paid at $14 per labour hour. The company calculates
selling price by applying a mark-up on cost of 25%.
Details of the three models of products and relevant actual information for
the last period are also provided as follows.
(a) Calculate the unit production cost of each of the three products using
(i) The traditional absorption costing, and
(ii)The activity based costing approach respectively. (20 marks)
Comment on the calculations in part (a) above and explain why the activity
based costing approach is superior to traditional absorption costing.
QUESTION
Duff Co manufactures three products, X, Y and Z. Demand for products X
and Y is relatively elastic whilst demand for product Z is relatively
inelastic. Each product uses the same materials and the same type of
direct labour but in different quantities. For many years, the company has
been using full absorption costing and absorbing overheads on the basis
of direct labour hours. Selling prices are then determined using cost plus
pricing. This is common within this industry, with most competitors
applying a standard mark-up.
Budgeted production and sales volumes for X, Y and Z for the next year
are 20,000 units, 16,000 units and 22,000 units respectively.
The budgeted direct costs of the three products are shown below:
Product X Y Z
$ per unit $ per unit $ per unit
Direct materials 25 28 22
Direct labour ($12 per hour) 30 36 24
In the next year, Duff Co also expects to incur indirect production costs of
$1,377,400, which are analysed as follows:
Cost pools $ Cost drivers
Machine set up costs 280,000 Number of batches
Material ordering costs 316,000 Number of purchase
orders
Machine running costs 420,000 Number of machine
hours
General facility costs 361,400 Number of machine
hours
1,377,400
The following additional data relate to each product:
Product X Y Z
Batch size (units) 500 800 400
No of purchase orders per 4 5 4
batch
Machine hours per unit 1·5 1·25 1·4
Duff Co wants to boost sales revenue in order to increase profits but its
capacity to do this is limited because of its use of cost plus pricing and the
application of the standard mark-up. The finance director has suggested
using activity based costing (ABC) instead of full absorption costing, since
this will alter the cost of the products and may therefore enable a different
price to be charged.
THROUGHPUT ACCOUNTING
QUESTION 9
Due to poor productivity levels, late orders and declining profits over
recent years, the finance director has suggested the introduction of
throughput accounting within the organisation, together with a ‘Just in
Time’ system of production. Material costs and selling prices for each type
of panel are shown below.
Total factory costs, which include the cost of labour and all factory
overheads, are $12 million each year at the plant.
Out of the 13 hours available for production each day, workers take a one
hour lunch break. For the remaining 12 hours, Machine C is utilized 85% of
the time and Machines M and A are utilized 90% of the time. The
unproductive time arises either as a result
of routine maintenance or because of staff absenteeism, as each machine
needs to be manned by skilled workers in order for the machine to run.
The skilled workers are currently only trained to work on one type of
machine each. Maintenance work is carried out by external contractors
who provide a round the clock service (that is, they are available 24 hours
a day, seven days a week), should it be required.
(a) Calculate the throughput accounting ratio for large panels and for
small panels and explain what they indicate to S Co about
production of large and small panels. (12 marks)
(b) Assume that your calculations in part (a) have shown that large
panels have a higher throughput accounting ratio than small panels.
(c) Suggest and discuss THREE ways in which S Co could try to increase
its production capacity and hence increase throughput in the next
year without making any additional investment in machinery. (6
marks)
[Total: 25 Marks]
QUESTION
A Co makes two products, B1 and B2. Its machines can only work on one
product at a time. The two products are worked on in two departments by
differing grades of labour. The labour requirements for the two products
are as follows:
Minutes per unit of
product B1
B2
Department 1 12 16
Department 2 20 15
There is currently a shortage of labour and the maximum times available
each day in Departments 1 and 2 are 480 minutes and 840 minutes,
respectively.
The current selling prices and costs for the two products are shown below:
B1 B2
$ per unit $ per
unit
Selling price 50·00 65·00
Direct materials 10·00 15·00
Direct labour 10·40 6·20
Variable overheads 6·40 9·20
Fixed overheads 12·80 18·40
Profit per unit 10·40 16·20
QUESTION
Product X Y Z
($) ($) ($)
Selling price per unit 20 15 10
Direct materials 8 5 4
Direct labour 5 3 2
Overheads 2 1 1
Required:
(a) Calculate throughput accounting ratio and rank the products. (18 marks)
(b) Calculate the revised production schedule and the maximum profit that
the company is likely to get given that there is a bottleneck. (7
marks)
(TOTAL MARKS: 25)
Wargrin designs, develops and sells many PC games. Games have a short
lifecycle lasting around three years only. Performance of the games is
measured by reference to the profits made in each of the expected three
years of popularity. Wargrin accepts a net profit of 35% of turnover as
reasonable. A rate of contribution (sales price less variable cost) of 75% is
also considered acceptable.
Wargrin has a large centralized development department which carries
out all the design work before it passes the completed game to the sales
and distribution department to market and distribute the product.
Wargrin has developed a brand new game called Stealth and this has the
following budgeted performance figures.
The selling price of Stealth will be a constant $30 per game. Analysis of
the costs show that at a volume of 10,000 units a total cost of $130,000 is
expected. However at a volume of 14,000 units a total cost of $150,000 is
expected. If volumes exceed 15,000 units the fixed costs will increase by
50%.
Stealth's budgeted volumes are as follows:
Year 1 Year 2 Year 3
Sales volume 8,000 units 16,000 units 4,000 units
In addition, marketing costs for Stealth will be $60,000 in year one and
$40,000 in year two. Design and development costs are all incurred
before the game is launched and has cost $300,000 for Stealth. These
costs are written off to the income statement as incurred (i.e. before year
1 above).
YOU ARE REQUIRED TO:
(a) Explain the principles behind lifecycle costing and briefly state why
Wargrin in particular should consider these lifecycle principles. (5 marks)
(b)Produce the budgeted results for the game 'Stealth' and briefly assess
the game's expected performance, taking into account the whole lifecycle
of the game. (10 marks)
(c) Explain why environmental management accounting has become so
common these days and how is this related to life cycle costing. (6 marks)
(d) Discuss the extent to which a meaningful standard cost can be set for
games produced by Wargrin. You should consider each of the cost
classifications mentioned above. (4 marks)
(Total 25 marks)
QUESTION 23
Fit Co specialises in the manufacture of a small range of hi-tech products
for the fitness market. They are currently considering the development of
a new type of fitness monitor, which would be the first of its kind in the
market. It would take one year to develop, with sales then commencing at
the beginning of the second year. The product is expected to have a life
cycle of two years, before it is replaced with a technologically superior
product. The following cost estimates have been made.
QUESTION
3. The company does not have any black cotton fabric in stock.
However, it could buy some from an existing supplier for
$2.60 per metre but must purchase a minimum of 2,500
metres. At present the company has no use for any unused black
cotton fabric.
QUESTION 9
(17 marks)
b) Explain the relevant costing principles used in part (a) and
explain the implications of the minimum price that has been
calculated in relation to the final price agreed with Push Co.
(8 marks)
(Total 25 marks)
QUESTION