TR Manual - Color 001
TR Manual - Color 001
Transformer Manual
An ISO 9001:2000 Company
INSTRUCTIONS FOR
INSTALLATION, COMMISSIONING, OPERATION AND MAINTENANCE OF
TRANSFORMERS AND REACTORS
Transformer Manual
I N D E X
Sr. No. PARTICULARS PAGE NO.
1.0 LIST OF STANDARDS RELATED TO OUR PRODUCTS
1.1 LIST OF INDIAN STANDARDS REFERRED 1
1.2 LIST OF IEC STANDARDS REFERRED 2
2.0 TRANSPORTATION, DESPATCH AND STORAGE
2.1 TRANSPORTATION 3
2.2 RECEIPT OF TRANSFORMER AT SITE 3
2.3 STORAGE 5
3.0 INSTALLATION
3.1 LOCATION AND SITE PREPARATION 6
3.2 ASSEMBLING THE TRANSFORMER 6
3.3 GASKETS 7
3.4 BUSHINGS 7
3.5 TAP CHANGERS 11
3.6 COOLING OF TRANSFORMERS 14
3.7 RADIATORS 14
3.8 COOLING FANS 15
3.9 OIL PUMP 15
3.10 OIL FLOW INDICATOR 16
3.11 HEAT EXCHANGER 17
3.12 DIFFERENTIAL PRESSURE GAUGE 17
3.13 CONSERVATOR TANK 18
3.14 MAGNETIC OIL LEVEL GAUGE 18
3.15 COMMISSIONING OF AIR CELL 19
3.16 GAS AND OIL OPERATED (BUCHHOLZ) RELAYS 20
3.17 SILICA GEL BREATHER 22
3.18 PRESSURE RELIEF VALVE (PRV) 23
3.19 DOUBLE DIAPHRAGM EXPLOSION VENT 24
3.20 MARSHALLING BOX 25
3.21 OIL TEMPERATURE INDICATOR 25
3.22 WINDING TEMPERATURE INDICATOR 25
3.23 CURRENT TRANSFORMER 28
3.24 CONTROL CABLING 28
3.25 ASSEMBLY OF VALVES 28
3.26 ASSEMBLY OF PIPE WORK 28
3.27 OIL FILLING 28
3.28 EARTHING 31
3.29 COMPLETION OF ERECTION WORK 31
3.30 TOUCH-UP PAINTING 31
4.0 COMMISSIONING
4.1 GENERAL CHECK POINTS 32
4.2 DO’S & DON’TS FOR POWER TRANSFORMER 33
4.3 INSULATION RESISTANCE TEST (MEGGER) 34
4.4 VOLTAGE RATIO TEST 34
4.5 MAGNETIZATION CURRENT 35
4.6 VECTOR GROUP 35
4.7 MAGNETIC BALANCE 36
4.8 WINDING RESISTANCE 36
4.9 OLTC CONTINUITY CHECK 36
4.10 OIL CHARACTERISTICS 37
4.11 TESTING OF ON LOAD TAP CHANGER 37
4.12 OFF CIRCUIT TAP CHANGER 37
4.13 TEST ON CT 38
4.14 TESTING OF COOLING CIRCUIT 38
4.15 TERTIARY WINDING PROTECTION 38
4.16 PROTECTION AND ALARMS 38
4.17 DETAILS OF CIRCUIT BREAKER 39
4.18 ENERGIZING 39
4.19 RECORD AFTER CHARGING 39
5.0 MAINTENANCE AND OPERATION
5.1 GENERAL 40
5.2 ROUTINE MAINTENANCE INSPECTION OF OLTC 40
5.3 OIL FILTRATION AND MOISTURE REMOVAL 42
5.4 TEMPERATURE SUPERVISION 43
5.5 IR TEMPERATURE RELATION 43
5.6 SUPERVISION AND CONTROL OF OIL 44
5.7 TROUBLE SHOOTING 44
5.8 GAS ANALYSIS ON TRANSFORMER OIL 44
5.9 MAINTENANCE SCHEDULE 48
P R E F A C E
• TARIL Transformers are designed, manufactured and tested with care. With proper attention during
installation and use, the user should receive from it the maximum expected service.
• This maintenance procedure gives a good understanding about handling and maintenance of the
transformer.
• It is recommended to go through all information contained in this before installing, operating and
maintenance of the transformer.
• These instructions have been prepared to provide information on assembly, installation, commissioning
and regular maintenance of the transformers and shall form part of Instruction Manual.
• In operating the Transformer, care should be taken that loading limits as specified are strictly followed.
For instructions regarding, general information on accessories such as OLTC, WTI, OTI, Buchholz relay,
fan, pump, etc. may please be referred.
• In case there is doubt about any portion or wants more details .pleas contact us in the following
address.
• If any problem occurs during operation, inform T&R at following address by specifying the following.
A. SL. NO.
B. YEAR OF MANUFACTURE
C. VOLTAGE
D. PROBLEM FACED
1
1.2 LIST OF IEC STANDARDS REFERRED
SR NO IEC NO EDITION YEAR DESCRIPTION
1 60-1 SECOND 1989-11 HIGH-VOLTAGE TEST TECHNIQUES (GENERAL DEFINITIONS AND TEST REQUIREMENT)
2 60-2 SECOND 1994-11 HIGH VOLTAGE TEST TECHNIQUES (MEASURING SYSTEMS)
3 76-1 SECOND 1993-03 POWER TRANSFORMERS (GENERAL)
4 76-2 SECOND 1993-04 POWER TRANSFORMERS (TEMPERATURE RISE)
5 76-3 SECOND 2000-03 POWER TRANS. INSULATION LEVELS ,EXTERNAL CLEARANCE & DIELECTRIC TESTS
6 76-3-1 FIRST 1987 POWER TRANSFORMERS (INSULATION LEVELS AND DIELECTRIC TESTS EXTERNAL
CLEARANCES IN AIR)
7 60076-5 SECOND 2000-07 POWER TRANSFORMER – ABILITY TO WITHSTAND SHORT CIRCUIT
8 60076-5 THIRD 2006-02 POWER TRANSFORMER – ABILITY TO WITHSTAND SHORT CIRCUIT
9 60076-7 FIRST 2005-12 LOADING GUIDE FOR OIL-IMMERSED POWER TRANSFORMERS
10 60076-8 FIRST 1997-10 POWER TRANSFORMERS-APPLICATION GUIDE
11 60076-10 FIRST 2001-05 POWER TRANSFORMER-DETERMINATION OF SOUND LEVELS
12 60076-10-1 FIRST 2005-10 DETERMINATION OF SOUND LEVELS-APPLICATION GUIDE
13 60076-11 FIRST 2004-05 POWER TRANSFORMERS-DRY TYPE TRANSFORMERS
14 TS 60076-14 FIRST 2004-11 DESIGN & APPLICATION OF LIQUID-IMMERSED POWER TRANSFORMERS USING
HIGH-TEMPERATURE INSULATION MATERIAL
15 60137 FIFTH 2003-08 INSULATED BUSHING FOR ALTERNATING VOLTAGES ABOVE 1000V
16 289 SECOND 1988 BOBINES D’INDUCTANCE (REACTORS)
17 296 SECOND‘ 1982 SPECIFICATION FOR UNUSED MINERAL INSULATING OILS FOR TRANSFORMERS
18 317-0-2 2.1 2000-01 SPECIFICATION FOR PARTICULAR TYPES OF WINDING WIRES
19 396 SECOND 1991-02 TEST METHOD FOR INDUCTION CHANNEL FURNACES
20 554-1 FIRST 1977 SPECIFICATION FOR CELLULOSE PAPER FOR ELECTRICAL PURPOSES
21 554-3-3 FIRST 1980-01 SPEC.. FOR CELLULOSE PAPER FOR ELECTRICAL PURPOSES
22 641-1 FIRST 1979 SPEC. FOR PRESSBOARD & PRESS PAPER FOR ELECTRICAL PURPOSE
23 641-3-1 FIRST 1992-04 SPEC. FOR PRESSBOARD & PRESS PAPER FOR ELECTRICAL PURPOSE
24 60038 6.2 2002-07 IEC STANDARD VOLTAGES
25 60044-1 2000-07 CURRENT TRANSFORMER
26 60214-1 FIRST 2003-02 TAP CHANGERS-PERFORMANCE REQUIREMENTS & TEST METHODS
27 60214-2 FIRST 2004-10 TAP CHANGERS-APPLICATION GUIDE
28 60270 THIRD 2000-12 HIGH VOLTAGE TEST TECHNIQUES - PARTIAL DISCHARGE MEASUREMENT
29 60317-27 THIRD 1998-01 SPEC. FOR PARTICULAR TYPES OF WINDING WIRES
30 60404-8-7 SECOND 2008 MAGNETIC MATERIAL
31 60554-2 SECOND 2001-11 CELLULOSE PAPERS FOR ELECTRICAL PURPOSES
32 60599 SECOND 1999-03 MINERAL OIL IMPREGNATE ELECTRICAL EQUIPMENT IN SERVICE GUIDE TO
THE INTERPRETATION OF DISSOLVED AND REC GASES ANALYSIS
33 62271-209 FIRST 2007-08 HIGH VOLTAGE SWITCHGEAR AND CONTROL GEAR - CABLE CONNECTION FOR
GAS INSULATED METAL ENCLOSED SWITCHGEAR FOR RATED VOLTAGE ABOVE 52 KV
2
Transformer Manual
2.1 TRANSPORTATION
“Transformers,” depending upon the restriction imposed by transport weight and/or other considerations, have to be
transported either filled with oil or Nitrogen as per the description given below.
WITH OIL
The Transformer is filled with oil such that sufficient tank volume is left clear for expansion to limit the excess internal
air pressure to 0.35 kg/cm2. Fittings dismantled before transport is packed in packing cases in line with packing list.
All openings resulting from removal of fittings for shipment are sealed with suitable blanking plates during transport.
The balance oil quantity required for the complete filling of the transformer is supplied separately.
A transformer dispatched according to this method can be stored at site or elsewhere for one year provided, that all
insulating materials are covered with oil and silica gel breather is mounted and quality of oil is maintained as per IS: 1866.
INSTRUCTIONS FOR FILLING DRY PURE NITROGEN GAS WITH BACK UP CYLINDERS (AT WORKS)
1. Lower the oil level to the minimum necessary to dismantle the items (such as bushing and turrets) which must be
removed for shipping.
2. Pull 500mm. mercury vacuum after blanking off all openings.
3. Break the vacuum by admitting dry nitrogen through a convenient valve at the top of the tank and drain the oil
completely.
4. Continue to supply nitrogen until it maintains a steady pressure of 0.14 ± 0.02 kg/cm2 above the atmosphere.
5. Pressure of nitrogen gas shall be maintained at 0.14 ± 0.02 kg/cm2 at same reference temperature. Pressure
would be monitored by taking three readings within 24 hours to ensure that there is no leakage of gas
6. Shut off the gas supply valve and fit dry nitrogen back up cylinders through nitrogen regulator valve.
3
This section gives instructions how handling, lifting, storing and assembling should be carried out. For large Transformers
it is recommended that the work is done by TARIL or is under supervision by experts from TARIL.
INSPECTION
In connection with receiving and unloading at site, and at the final storing place before assembling, the transformers
shall be inspected carefully for external visible damages as dents, paint damages etc.
After the arrival of the material at receiving points, the customer should, in case of possible damage/loss of any
component, make the necessary claims with the contractor’s representatives under intimation to supplier so that such
claims can be registered with the transport agents. Before unloading, the condition of packing and of the visible parts
should be checked and possible traces of leaks verified (condenser bushings). If necessary, appropriate statements and
claims should be made.
Drums containing oil which have been dispatched separately should be examined carefully for leaks or any sign of
tampering. All drums are dispatched filled up to their capacity and any shortage should be reported. As a principle we
never supply partly filled drums.
In order to protect the active part against moisture, the transformer tank is filled with nitrogen during transport at an
over pressure of 0.2kg/cm2 approximately at room temperature.
Check immediately the gas pressure at the arrival. A positive pressure indicates that the tank and the transformer
components respectively are tight, and that the active part including the insulation materials is dry.
If there is no positive gas-pressure, transformer should be immediately filled with dry Nitrogen gas at pressure of 2 PSI
without loss of time.
DAMAGE/LOSS
Damage or loss of any component should be reported to Supplier immediately. Photographs or other useful evident
should be submitted wherever possible.
When the transformer is dispatched filled with oil, level in transformer main tank should be checked & if the level is
below the indicated level in main tank the same should be reported to the supplier immediately & also the same
should be mentioned in LR copy. When the transformer is dispatched filled with oil, a sample of oil should be taken
from bottom of the tank and tested to IS: 1866. If the dielectric strength is below 50KV, when tested on standard IS:
1866, the matter should be reported to supplier along with insulation resistance values of the various windings to
earth.
Drums containing transformer oil which have been dispatched separately should be examined carefully for leaks or
any signs of tempering. All drums are dispatched filled up to their capacity and any shortage should be reported to us
immediately.
UNLOADING
The transformer should be unloaded by means of crane or suitable device of sufficient capacity (Please refer rating
plate for weight detail).
For lifting purpose lifting lugs are provided on the top cover & on the sides of tank. Lifting lugs on the sided of tank are
lifting the complete transformer, whereas the lugs provided on the tank cover should be used only for lifting the cover.
Lifting lugs for transformer lifting are painted red. Check at lifting of complete transformer that the lifting wires/ropes
are not in contact with bushing or other components on the cover.
Four jacking pads are also provided for lifting the transformer with the help of jacks.
Bidirectional skids are also provided on the bottom of the transformer, in the form of channels having towing holes on
both the sided & also holes for foundation of transformer.
Transformer should be jacked up using the projections specially provided for that purpose. Jack should never be placed
under any valves.
To avoid undue mechanical stresses the transformers must be kept on reasonably level foundation.
ASSEMBLY OF WHEELS
Whenever wheels are supplied with transformer, movement of transformer at site is carried out by mounting these
wheels.
4
Transformer Manual
Mounting of wheels under transformer is to be done as per roller arrangement drawing. In power transformer wheels
are designed such a way that conservator side wheels are of slight higher in height fin the view of keeping transformer
shortly inclined to release trapped air from main tank and to avoid accumulating rain water on the tank top cover.
While fixing the rollers, the flange should come on the inner side of the rails.
Transformer placement can be with or without rollers as per applicable GA/foundation drawing. When the transformer
is in the final position, the wheels shall be locked to prevent accidental movement of the transformer.
2.3 STORAGE
1. After arrival at site, it is desirable to erect and commission the transformer with minimum delay. In case this is
not possible the transformer shall be erected at its permanent location with conservator and breather fitted and
dry oil filled to the correct level. Whether storage or in use, the dehydrating breather must be fitted on all the
transformers which are oil filled. The breather incorporates an oil sealing device which must be filled with oil, to
the level marked, to be effective. The condition of silica gel must be checked periodically, particularly during
monsoons.
2. Dismantled equipment and components are packed to be protected against normal handling and transport
stresses.
3. All other accessories should be stored in a covered dry place. It should be ensured that there is no damage to the
gasketted joints and that all the blanked joints are tight.
4. Goods stored outdoors must not be placed directly on the ground, and should be covered carefully with tarpaulin
or similar material.
5. The tap changer, if provided, should be operated at 6 monthly intervals. Two of three runs from one end of the
range to the other and back are sufficient.
6. Heaters on Marshalling kiosks, etc. should be kept energized. If for this purpose, power supply at the appropriate
voltage to suit the heater is not available, temporary heaters should then be installed to suit the site voltage. The
provision of heaters is important and failure to provide them may result in extensive damage to the contents of
the kiosk because of condensation.
7. If oil received in drums is not likely to be used immediately the drums should be stored in a covered space where
the temperature variation is minimum. If it is necessary to store the oil outside, adequate protection must be
provided at all times. Oil drums should be stored in horizontal (lying) position with both the bungs also in
horizontal position.
INDOOR STORAGE
The following items shall be stored indoor.
1) All the Bushings.
2) Insulating Materials & Paints.
3) M.Box R.T.C.C. & Motor Drive of OLTC.
4) Turrets with C.T. mounting.
5) Components like B. Relay, MOO, PRy, Pressure gauges & Flow Indicators, Breather.
6) Cooling fans & Pumps.
5
3 INSTALLATION
3.1 LOCATION AND SITE PREPARATION
1. Transformer should be placed on the foundation so that easy access is available all around and diagram plates,
thermometers, valves, oil gauges, etc. can be easily reached or read. Adequate electrical clearances are also to
be provided from various live points of the transformer to earthed parts.
2. ONAN type transformers depend entirely upon the surrounding air for carrying away the heat generated due to
losses. For indoor installation, therefore, the room must be well ventilated so that the heated air can escape
readily and be replaced by cool air. Air inlets and outlets should be of sufficient size and number to pass
adequate air to cool the transformer. The inlets should be as near the floor as possible and outlets as high as the
building will allow. Where necessary, exhaust fans can be installed for the purpose.
3. The transformers should always be separated from one another and from all walls and partitions to permit free
circulation of air.
Where walls are provided, it should be ensured that the transformer gets good ventilation as mentioned above
for indoor transformers. Provision should be made for the emergency drainage of the oil from the transformers
(e.g. in case of fire in neighboring apparatus or bushing or the transformer tank), by surrounding the transformer
plinth with sump filled with small pebbles.
6
Transformer Manual
16. Check that the bushing leads set without being too close to ground or other points of different potential.
17. Core-ground; this is checked with the megger after removing earth connection.
18. Before entering into a N2 filled transformer make sure that sufficient Oxygen is available inside.
3.3 GASKETS
The sealing system normally used against oil and gas in transformers and belonging components has rubber bonded
cork gaskets at joints.
Whenever the blanking plates are removed to fix detached parts such as bushing turrets, etc., a new gasket shall be
used while fixing the same. A set of new unused gaskets of correct size and thickness is supplied with every transformer
for this purpose.
Gaskets are best stored in such a way, that they must be protected from damp, oil and grease
To make a gasket joint, first clean the metal surfaces ensuring that they are free from oil, rust, scale etc.
Using one of the flanges as a template, punch the necessary bolt holes. Insert the bolts and tighten the bolts sequentially,
a little every time so that uniform pressure is exerted on the gasket until the gasket is compressed to about 2/3 of its
original thickness.
Joints should not be subjected to pressure until tightening is complete. If care is taken in making joints, and in handling
the gasket, it is possible to break and remake a joint several times, using the same gasket.
Bolts/studs should be tighten the lightly and diagonally in the sequence. Do not over tight, otherwise gasket will get
crushed.
3.4 BUSHINGS
After completing the internal connections, windings leads are brought out through suitable bushing.
Normally three types of bushings are used.
7
CONDENSER TYPE
Generally condenser type bushings are used for 72.5 KV and above. Design of this bushing is such that their mounting
is independent of oil level in conservator, whenever this bushing are mounted on bushing pockets or raised truncated
portions. Air vent pipes are provided for carrying away air or gases from these pockets to Bucholz relay during service.
The bushing should be examined for damage at oil end and as well as the porcelain before fixing which may have
occurred during transit.
The bushing shall be lifted by using the lifting eyes and soft ropes. Steel wire ropes or slings shall not be used.
The turrets are often individually adapted; check therefore that they are remounted in correct places, which appear
from the GA drawing and, part list.
8
Transformer Manual
9
Bushings should be cleaned by dry & non fluffy cloth.
Bushing insulator and metal parts are dispatched separately.
Refer to G.A. Drawing for the position of bushing on transformer.
Ensure that the oil level is below the tank cover. (Please check prismatic oil level gauge on main tank or Check it by
unscrewing air release plug provided on the tank cover. No oil should come out).
Remove blanking plates from tank cover. Check the gasket is OK. Replace it if required.
Put the lock washer over the connecting stud. Screw the connecting stud to the connecting plug.
NOTE: IN CASE LIGHTNING ARRESTERS ARE FIXED CLOSE TO TRANSFORMER ARCING HORNS ARE NOT REQUIRED.
ASSEMBLY OF PLAIN PORCELAIN & PLAIN OIL FILLED TYPE OF BUSHING USED FOR VOLTAGE
RATING UP TO 36KV.
1. Fix the stem on the top of the connecting stud and then lock them with lock nuts.
2. Insert the clamping ring over the bottom of the insulator before kept in the position. Place the insulator on the
cover property, insert threading stem assembly and insulating tube through it. Ensure that stem is properly
engaged inside the groove of the bushing.
3. Insert seal ring, cap and fix them in position by hexagonal nut.
4. Clamp the insulator by means of clamping ring, clamp, washer and hexagonal nut. See that the insulator is
tightened evenly and carefully at all places. Turn the cap so that mounting locations for spark gap horns which
are fitted later are in the position.
5. Fix the hexagonal nut, plain washer and spring washer.
Before mounting on transformer, clean the bushing thoroughly and check for any damage. The lower part and inside
of the centre pipe (in case of draw load/rod type bushing) should be further cleaned with transformer oil.
10
Transformer Manual
PRE-COMMISSIONING CHECKS
1. Check capacitance/tan delta of the bushing preferably at 600 V and less than 10 KV, between High voltage
terminal and test tap (after removing the cap) and compare with factory test results. Any abnormality should
immediately be reported to TARIL. After the test, put back the cap.
CAP SHOULD NOT BE LEFT OPEN UNDER ANY CIRCUMSTANCES.
2. Check oil level of the bushing. In vertical condition, oil level should be at the middle of the indicator/gauge.
3. Check that the HV terminal is firmly tightened with the gasket to avoid passage of moisture to transformer.
4. Ensure that the transformer is energized minimum 36 Hrs. after mounting the bushing.
11
switches for raising or lowering the taps and is provided with a remote tap changer control cubical (R.T.C.C). Automatic
voltages regulation can be provided as an optional fitting.
Where transformers have to operate in parallel, special circuits are employed such as Master - Follower and will be
given with each scheme by the supplier in agreement with user.
For constructional details, refer manuals of manufacturer.
It is advisable to fit the tap changer on the transformer even during storage & connect it to the conservator and
breather.
It should be ensured that the selector switch & diverter switch are filled with clean dry processed oil to keep selector
switch & diverter switch moisture & dust free.
A Protective oil operated relay is supplied and the dispatched loose. This relay is sensitive to both low oil level and oil
surge conditions. The relay must be fitted in a pipe connection from the tap changer conservator pad to the conservator
and its contacts must be connected to the inter tripping system so as to isolate both sides of the transformer. The pipe
work rising to the conservator should be arranged at an angle of 5° above the horizontal to ensure the effective
operation of the protective relay. The connection of the relay contacts in the trip circuit such that the transformer is
fully isolated will prevent damage to the tap changer the in case of low oil level.
Extensive damage will also be prevented in remote cases of incipient faults in the tap changer.
If the relay is painted at site care should be taken to see that the vent and drain holes in the terminal box are not
clogged. A separate indication to show operation of tap changer oil surge relay should be available to avoid unnecessary
inspection of tap changer in case only the transformer gas and oil surge relay operates.
OIL
The oil in the tap changer should conform to IS 335 and thus be thoroughly dried out by filtration. The electrical
withstand level of Oil should be minimum 50kV when tested as per IS 335 - and IS: 5792-1972. The oil should be free
from solid contaminations as well.
HEATER
Heater is provided in the drive mechanism in order to eliminate condensation troubles due to changes in ambient
temperature. The heater is controlled by an ON-OFF Switch and should be switched on when there is a possibility of
moisture condensation such as during monsoons.
12
Transformer Manual
COMMISSIONING CHECKS
1. The associated transformer should be de-energized, isolated and earthed during these checks to prevent any
unintended damage to life equipment. Switch off auxiliary supply to tap changer.
2. Inspect the outside of the tap changer and inside of the drive mechanism to ensure that nothing is damaged or
removed and that the mechanism chamber is clean. Touch up paint and lubricate if required.
3. Ensure that the tap changer is filled with oil to the level required in the conservator. Test oil.
4. Check that the breather charge is blue.
5. Check tripping operation of surge relay.
6. Operate the tap changer manually to extreme position, and check the operation of the limit switches and crank
handle interlock visually. Bring the tap changer manually to a position in the middle of the tapping range.
7. Switch on mechanism auxiliary supply.
8. Stall motor by holding coupling and ensure that the motor protection relay trips.
9. Check that the damper is locked.
10. Check that the mechanism travels in the correct direction when operated electrically.
11. Check that the friction device is pressing tightly on the coupling drum.
12. Check that during electrical operation the pointer is approximately in the middle of the white sector when the
motor comes to rest after tap change.
13. Check that the heaters are working.
14. Check counter operation.
15. Carry out approximately 100 electrical operations through the full range.
16. Check operation of all electrical control both local and remote as well as paralleling where provided.
17. Operate the tap changer one complete cycle with the transformer energized. It is not essential that the transformer
be loaded for this test. If the tap changer oil surge relay trips during this test do not operate tap changer further.
Isolate the whole equipment electrically and examine the tap changer completely, including the selector switch.
Rectify any faults found and recommission.
18. Record the counter reading at the end of commissioning checks.
13
PUTTING INTO OPERATION
Before connecting the motor drive to the mains, check whether voltage, current and power of the supply should
coincide with the required values. When checking the voltage for the motor circuit take care that the RYB phase
sequence is clockwise.
As the gearing and the ball bearings of the driving motor are sufficiently supplied with grease a regular maintenance
is not necessary. We recommend, however, Check that all wiping faces, gear teeth, cam faces etc. are lubricated with
special molybdenum disulphide lubricant. No oil should be used for lubrication. Ensure that drive mechanism chamber
is clean and free from dust.
TYPE OF COOLING
1. OIL NATURAL AIR NATURAL COOLED TRANSFORMER (ONAN)
2. OIL NATURAL AIR FORCED COOLED TRANSFORMER (ONAF)
3. OIL FORCED AIR FORCED COOLED TRANSFORMER (OFAF)
4. OIL FORCED WATER COOLED TRANSFORMER (OFW)
The cooling equipments & associated pipe work & fittings are to be thoroughly cleaned thoroughly before assembly.
Valves which are not dismantled like shut-off valves for radiators, coolers and possible headers shall be provided with
blanking plates during the transport.
Remove the blanking plates when the assembling of the coolers is to be started. Check first that the valves are closed.
The pressure gauge, differential pressure gauges, etc. should be fitted in position.
Check that each radiators and possible headers are assembled in the correct positions according to GA drawing.
The shut-off valves against the transformer tank shall be closed until the oil-filling is started.
The cooler and associated pipe work is then filled with clean dry oil keeping all the cooler circuit open. Air is released
from all the pipe work during filling.
3.7 RADIATORS
Transformer is provided with detachable pressed sheet radiators with isolating valve. Due to transport limitation and
considering possible transit damages, the radiator valve are closed at the time of dispatch and radiators are detached
and sent separately keeping the valve in position on tank flange. The valve blanking plate is to be removed only when
the radiator is ready for mounting on flanges. On removal of blanking plate, oil will seep out. After filling the oil in
radiators and venting air from them, radiator valves at top and bottom must be kept in OPEN position and sealed.
In large transformers the radiators are sometimes separately mounted. In such cases there will be a header each at top
& the bottom, which are supported on frames. Flanges are provided on these headers for fixing the radiators. Radiators
valves are fitted to the headers and dispatched. The end frames are to be erected first. The frames should be
positioned correctly with respect to the transformer. The distance between centre lines of transformer and cooler
should be strictly as per GA drawing otherwise the connecting pipe work will not match. After erecting the end frames
14
Transformer Manual
the top and bottom headers are mounted. The headers will have to be properly leveled so that the connecting pipe
work can be easily fixed. Radiators should be mounted in last.
If the conservator is to be provided on the cooler bank, the same may be mounted on it and all fittings for the same
attached.
The interconnecting pipe work may be done taking care to connect correct pieces at the correct location. Usually
expansion joints are provided in the pipeline connecting the transformer tank to cooler. Special care should be taken
to see that these are installed correctly.
MOUNTING OF RADIATORS
Ensure that the transformer and radiators are not damaged in transit.
Special care should be taken while removing radiators from crates subsequent handling operations and while mounting
on tank. Any damage while handling may result in cracks and oil may leak when fitted on tank and filled.
(1) Lift the radiator vertically. Bring the radiator nearer to the valve. Remove the blanking plates from valve. Slide
the radiator on the bolt from pipe flange the radiator valve and tighten using plain washer, spring washer and
nuts. Tighten nuts in sequence applying uniform pressure on the gasket to make a proper leak proof fitting.
Assembly all the radiators in the same manner.
(2) Clamping arrangement at outer ends of the radiators is to be fitted to minimize the vibrations of radiators.
Required number of bracing straps in standard lengths are sent separately with hole arrangement.
(3) Make arrangements to fill the transformer oil through the main conservator. It is recommended to use hot
filtered oil directly from the filter.
(4) Fill only one radiator at a time. Open the bottom valve. Slowly unscrew the air release plug on the top of the
radiators until the air starts escaping. The oil from the main tank will now flow in the radiator. Start putting fresh
oil in the conservator.
(5) After filling open valve at top.
(6) Fill the remaining radiators in the same manner.
15
3.10 OIL FLOW INDICATOR
FUNCTION
Flow indicators are mainly designed as a safety device looking to the need of an electrical signal on failure of forced
circulation of liquid in pipe line. They perform following functions:
1. Indicate the rate of full flow in proper direction in specified pipe.
2. Operate one or two mercury switches when rate of flow drops near to 70% of specified full flow.
These switches can be used to initiate precautionary systems of safety devices.
3. To introduce these Flow Indicators in a pipe line a “T-Mounting” is necessary.
CONSTRUCTION & WORKING
A suspended vane is used as sensor. Its surface is kept at right angle to direction of flow. When liquid starts flowing
through pipe, the vane gets deflected along with vane shaft. This deflection is used to indicate flow inside the pipe
and to operate mercury switches as follows:
A pair of permanent magnets is used as glandless coupling. The driving magnet is connected with vane; therefore it
rotates with vane and remains in liquid. The follower magnet, separated by a nonmagnetic wall, is kept outside in air
and acquires position corresponding to driving magnet. The follower magnet carries a pointer and a cam. The pointer
is set to read the specified rate of full flow and the cam is set to operate one or two mercury switches when flow drops
near to 70% of full flow. A return spring is used which acts in the opposite direction of flow. Hence any steady position
of pointer is the result of equilibrium of force due to impinging liquid on vane spring tension & weight of vane. The
pointer does not remain steady for unsteady flows. The size and shape of vane and tension on return spring is adjusted
to suit specified full flow. The vane occupies very small area out of full cross section of pipe at NO-FLOW position. At
full flow it becomes almost parallel to flow. Hence there is practically no head-loss across Flow Indicator. The flow
indicators are distinguished in two series 4021 & 4022. Basic difference between two series is that in Series 4021 only
one mercury switch is provided. Whereas in Series 4022 two mercury switches are provided. Proportionately, number
of terminals, size of switch-box and size of terminal box differ.
DIAL MARKING
Usually PUMP ON-PUMP OFF or FULL FLOW-NO FLOW type of limit markings are printed. Intermediate markings such
as ALARM, TRIP are also printed if required. Besides, specifications such as value of full flow, liquid, pipe size and
direction of flow are also printed. The background of dial is white. Direction indicating arrow is in red color and all
other markings in black color.
SWITCHES
One or two mercury switches are provided. Their contact position can be set on NO or NC at full flow. If required,
switch can be changed from NO to NC or vice versa at site.
16
Transformer Manual
In case of single switch, it is set to operate near 70% when flow is fallen. In case of two switches, both are mounted
on same plate. Hence both operate at same rate of flow. But in order to satisfy design requirements, one switch can
lie set to operate near 80% and the other near 70% or one near 70% and the other near 60%. It is not possible to set
a switch to operate at lower value than 60%. Even when both switches are set to operate at same rate of flow, some
switching differential is observed due to use of mercury as switching element. We can modify setting suitably if
switching requirements are clearly specified.
WIRING
Leads from mercury switch/switches are brought into a terminal box at the bottom of indicator. Terminals are accessible
for wiring after removing cover. A hole with conduit threads is provided for fixing cable gland to box. Terminals are
marked. Wiring should be done as per respective wiring diagrams.
NOTES:
1. Flow indicators are not interchangeable direction of flow or rate of flow.
2. Locking pin in the terminal box should be removed before taking into service.
17
3.13 CONSERVATOR TANK
The conservator, which may be with or without air cell is assembled either on the transformer, or on a separate frame.
Before the conservator is assembled it shall be checked that belonging equipment -e.g. Oil-level indicator -functions
satisfactorily. Before erection of conservator make sure that all gasketted joints are oil tight and pipe work is clean
and free of moisture.
The breather is connected to the oil conservator, and it is very important that joints and couplings in the pipe between
breather and conservator are air tight.
18
Transformer Manual
The float is hinged and swings up or down when oil level rise or falls. This rise or fall rotates the bevel gear and thus
the pinion of the gear assembly. The pinion in turn rotates the driving magnet inside the conservator. The follower
magnet positioned outside carries a pointer and a cam. The pointer reads oil level and the cam set to operate the
mercury switch at a predetermined low level. MGOs are with different specifications are not interchangeable.
1. Before assembly, ensure that there is no leakage in the air cell. Keep the air cell fixed inside the conservator.
Inflate air cell by dry air or Nitrogen to a pressure of 0.08 kg/sqcm max. through the opening for breather
connection. There should be one valve and a pressure gauge fitted in between this valve and air cell close the
valve after required pressure is achieved. Keep in this condition for 24Hrs ensure no leakage in air cell with the
help of pressure gauge.
2. Assemble the air cell conservator on the transformer.
3. Connect the conservator to transformer tank through Bucholz relay pipe line.
4. Close the valve between Bucholz relay & conservator.
5. Fill the oil in the transformer up to upper tank flange level under vacuum.
6. Keep the air cell inflated to a pressure of 0.08 kg/sqcm by Nitrogen / dry air through the opening for breather.
7. Open the valve between Bucholz relay & conservator.
8. Start further filling through the transformer lower filter valve slowly. Continue filling till the oil appears through
‘C1’. Close vent holes ‘C1’ and when oil appears through vent holes ‘C2’ close it. During oil filling, the pressure
gauge should be kept 0.08 kg/sqcm.
19
9. Start further filling through the transformer lower filter valve slowly. Continue filling till the oil appears through
‘C1’. Close vent holes ‘C1’ and when oil appears through vent holes ‘C2’ close it. During oil filling, the pressure
gauge should be kept 0.08 kg/sqcm.
10. Now remove the pressure supply connection of conservator & fix the breather with its pipeline. Keep further
filling of oil and stop at the value selected for the filling temperature.
11. Before applying pressure or vacuum close the valve between Bucholz relay & conservator perfectly.
12. While air cell in service never open the vent holes ‘C1’ & ‘C2’ to check oil level. This will cause sudden fall in oil
level. If oil level is to be checked first inflate the separator to 0.08kg/sqcm pressure and then open the vent holes.
CONTENTS
Protective devices In the ideal case must be sensitive to all faults, simple in operation, robust for service and economically
feasible. The relay operates on the fact that almost every type of electric fault in oil filed transformer gives rise to gas.
This gas is collected in the body of the relay and is used in some way or other to cause the alarm or the tripping circuit
to operate. The Relay is capable of indicate incipient fault thereby preventing further spreading of the fault and
extensive damage and thus saving expensive and protracted repairs.
Double element relays are being used in detecting minor or major faults in transformer. The alarm element will
operate, after a specified volume of gas has collected to give an alarm indication. Examples of incipient faults are.
1. Broken - down core bolt insulation,
2. Shorted laminations
3. Bad contacts
4. Overheating of part of windings.
The alarm element will also operate in the event of oil leakage and if air gets into the oil system.
The trip element will be operated by an oil surge in the event of more serious faults such as
1. Earth faults
2. Winding short circuits
3. Puncture of bushings
4. Short circuit between phases
The trip element will also be operated if a rapid loss of oil occurs. Single element relays can be used to detect either
incipient or major faults in oil filled potential transformers, reactors, capacitors etc. A special single element relay is
available for the protection of on load tap-change equipment.
CONSTRUCTION
The Buchholz relay essentially consists of enclosure i.e. an oil tight container and an inserted assembly comprising of
two floated elements fitted with switches. The enclosure is provided with inlet and outlet for the liquid. To allow
connection of pipes, the enclosure openings can be designed with pipe thread or flange. The front inspection glass is
provided with a graduation to allow reading the accumulated volume of gas and observe color of gas for fault analysis.
For checking the function of the inserted assembly a Test Key is provided. There is also a visual indication on the scale
20
Transformer Manual
of service and Test/Locking position, in the form of movement of red indicator on the reading scale. This allows the
testing of the alarm and Trip circuits before installation and even when the transformer is in service.
Just above the inspection glass an arrow shows the specified direction of flow of the insulation liquid to the conservator.
Enclosure and its inserted Assembly cover are made out of Cast iron/weather resistant light alloy.
FUNCTIONAL TEST
1. Testing the relay function with the Test Key.
A test system is provided in the Buchholz relay that allows the functional test of the upper and lower switching
system. To test the relay function loosen the nut on the Test Key and rotate the key with a screwdriver in the
Anticlockwise direction the SLOT on the Test Key points towards the T/L position Both the alarm (upper switching
system) and Trip (lower switching system) will show continuity.
On bringing the SLOT on the Test Key to S (Service) position by rotating the key clockwise the Alarm and Trip
circuits will not show continuity. The circuits will be actuated to ‘ON’ position only when there will be a fault in
the transformer. Repeat the functional test each time a relay is started or maintenance completed.
2. Testing the relay function with draining the oil. Close the valves both the side of the relay. Put continuity tester
across the alarm & trip contacts of the relay terminal box. Open the air vent lug on the top of the relay. Drain the
oil from relay from drain plug at the bottom of the relay. As oil start draining alarm & trip contact will close.
INSTALLATION
Mount the Buchholz relay as close as possible to the tank in the pipeline between transformer and conservator.
Keep pipe bends as wide as possible. Avoid close bends.
Make sure pipe ascends to the conservator at angle between one degree to nine degrees.
Make pipe bends as wide as possible between transformer and conservator.
See that the relay enclosure is not subjected to stress. If necessary, use expansion compensators.
Ensure that the slot on the Test Key remains in the T/L (Test/Locking) position during storage or loose transportation of
the relay.
Ensure that the slot on the Test key remains in the ‘S (Service) position and the Test Key Bolt is tightened just before
commissioning of the relay.
MAINTENANCE
No servicing is needed during operation. On routine inspections of the protection equipment test the function of the
Buchholz relay as described earlier and check the alarm and trip devices connected to them.
BASIC CHARACTERISTICS
The Gas and Oil relay provides protection against a number of internal faults but it is also able to indicate in several
cases the tyke of fault. This is possible because the gas collected in relay can, from its color, odor and composition,
indicate where the fault may be and what its nature is. By examining the gases collected it is possible to identify the
nature of the fault.
DIAGNOSIS
I. If the gas is colorless and odorless or with only a faint odor of oil, the gas is air trapped in the oil or the insulation.
2. If the gas is Greyish White with sharp and penetrating odor and be non-inflammable it is due to overheated or
faulty insulation.
3. If the gas is Yellowish in color and inflammable it may be due to surface leakage on material like wood.
4. If the gas is dark Grey and inflammable it may be due to a flashover in oil or due to excessive overheating of the
oil caused by a fault in the winding or the core.
On the operation of the alarm if investigation of the collected gas does not indicate a serious fault it is possible
to leave the transformer In service till it Is convenient to carry out a thorough inspection. This occurrence is
possible on a newly commissioned transformer due to air trapped in the oil, or the
insulation. On repeated and frequent alarm signals the transformer should be taken out of service for thorough
check up.
21
FUNCTION
The function of a double element relay will be described here. During normal operation of a transformer the Buchholz
relay is completely oil filled.
In the event some fault in the interior of the transformer tank gas bubbles are produced and accumulate in the
Buchholz relay on the way to the conservator. In consequence, the oil level in the relay enclosure drops which in turn
lowers the upper bucket.
This causes the mercury switch/Reed switch to operate an alarm signal.
The lower bucket does not change its position, because when the gas reaches the upper inside wall of the pipe it can
escape into the conservator. Hence, minor fault in the transformer tank will not trigger the lower switching assembly
and will not trip the transformer.
In case the liquid continues to drop due to loss of oil, the lower bucket also goes down in consequence lower switching
system operates if the level of oil goes below the bottom level of the pipe connected the relay.
Alternately in the event the liquid flow exceeds a specific value the lower bucket is forced down, thus triggering the
lower switching system to operate.
As the liquid flow rate decreases or the level of the liquid raises the bucket returns to its original position.
The single element relay has only one operating element and it responds to either gas collection or oil surges. The
single element OIL SURGE RELAY has been specifically designed for use with on load tap change equipment and it
will bypass normal amounts of gas which are generated by tap change operations and will only responds to oil surges
and loss of oil.
OPERATING CHARACTERISTICS
Normally Relays of the double element type are made in three sizes GOR1, GOR2 & GOR3 according to the diameter
25, 50 and 80 mm respectively of the bore of the oil pipe connecting the transformer to the conservator tank.
All relays are normally open types.
When transformers are required for use in areas subject to earthquakes or for traction application, we can supply
special relays which use magnetically operated Reed Switches instead of mercury switches.
OPERATION
Dry silica gel crystals which are dark blue
in color have a very good capacity to
absorb moisture. When the air from
outside is breathed in the conservator,
it passes through the crystals and the
moisture in the air is absorbed. Thus the
air that reaches the conservator is dry.
Dust particles are partly trapped in the
oil seal and partly trapped by the crystals
of the silica gel. Silica gel crystals change
their color from dark blue to pink
depending upon absorption of certain
quantity of moisture.
Silica gel crystals can be reactivated a numbers of times and therefore, they can be used over a long period. They
should be observed for the color of the silica gel on weekly basis. Change oil in oil seal once the color changes from
light yellow to dark brown.
22
Transformer Manual
impurities and/or Humidity which changes dielectric strength of transformer oil. Hence, it is necessary that, the air
entering into the transformer is free from moisture & foreign impurities.
INSTALLATION
The Breather is connected to transformer by either threaded or flanged joint (after removing the Seal) as per details
mentioned below. Before putting the Breather Into service, remove the Oil Cup and fill it up with fresh transformer oil
up to the line marked on Cup. Remove the seals on the air holes of the Cup and fit the Cup to the Breather The
Breather is how ready for installation.
MAINTENANCE
As the color of the Silica Gel changes to pinkish whit after use, it needs recharging.
Take out the Silica Gel and heat it, until color of Gel changes to deep blue. The Gel content or the size of the Breather
is determined by the Volume contents of the air passing through the Breather, the Oil Transformer and the atmospheric
conditions of installation. Hence, the Transformer Manufacturer or the ultimate user should decide the size of Breather
would shut the transformer.
APPLICATION
This PRV is designed to be used on power Transformer. When pressure in the tank rise above, predetermined safe limit
this valve operates and allows the pressure to drop by instantaneously opening a port of about 150 mm diameter &
give valve & operation by raising a flag and also operates a switch. This switch has 1 NO and 1 NC contacts (As per
requirement). Hence switch can be effectively used in control circuit.
SPECIFICATIONS
Normally PRVs are used of two sizes T-3 & T-6 each are having variety of three pressure ratings of 0.42 kg/sqcm (6 PSI),
0.49 kg/sqcm (7 PSI) and 0.56 kg/sqcm (8 PSI).
23
exposes the transformer pressure to a greater of side gasket, resulting sudden increase of force. The disk lifts
instantaneously and vents gases, vapor and liquid till the pressure falls to allowable value.
The PRVs are recommended to be used on power transformers. They are much more effective, durable and suitable
for repeated operations than the conventionally used explosion vent.
MOUNTING
The PRV should be preferably mounted in the horizontal position, top side up. However, it can be mounted on its side,
in vertical plane also.
INSTALLATION
This PRV has ‘an integral flange with four/six holes for mounting. Check that no parts are damaged in transit. Clean
surface of mounting pad on tank and place the flange with gasket. Each valve should be cleaned form inside (tank
side). All particles should be removed from tank side. All the bolts should be tightened evenly so that equal pressure
is exerted on gasket aid base. Ensure that the gasket is placed in the groove provided in the flange. Check the
operation of switch by manually lifting the operation rod. After checking, the switch should be manually reset by
placing the roller type knob back to its original position.
MAINTENANCE
The PRV has a rugged construction and does not require any maintenance. The operating pressure is factory preset
and cannot be changed at site. The operation of switch may be periodically tested by manually lifting the operating
rod and should be reset before putting the instrument in service.
CONSTRUCTION
Explosion vent consists of a bent pipe with aluminum diaphragms at both ends. A protective wire mesh is fitted on the
opening of the transformer to prevent the piece of ruptured diaphragm from entering the tank.
Near the lower end of the vent, there is small oil level indicator. When lower diaphragm ruptures, transformer oil rises
in the vent pipe and is visible through the indicator indicating the failure of the lower diaphragm. In case the pressure
developed is not reduced to safe value after the bursting of lower diaphragm, upper diaphragm also gives way
throwing the gas and oil outside and thus protecting the transformer tank from mechanical damage.
Sometimes conservator and explosion vent are connected with an equalizer pipe with or without a valve. The pipe
equalizes the pressure between conservator and explosion vent.
24
Transformer Manual
It should be fitted after vacuum application. Care being taken to ensure that the top diaphragm with its gaskets
makes an air tight joint.
CONSTRUCTION
Hinged lockable front door is provided with a glass window from which the temperature readings on the indicators can
be observed. The capillary from each indicator take off from the indicators, come out from the side of the marshalling
box. The entire kiosk has a rain shed provided on top to prevent ingress of water due to heavy rains falling directly over
the marshalling kiosk.
OPERATION
The liquid inside the bulb in contact with the hot oil in the thermometer pocket expands and the pressure of the vapor
in side the system increases. This increase in pressure results in movement of the bellow. A link and lever mechanism
amplified this movement to the disc carrying pointer and switches which indicates the temperature on the dial of the
thermometer.
OPERATION
The indicator is similar to OTI. The winding temperature indicator is calibrated to indicates the hottest spot of the
winding.
The switches are adjusted to make contact at desired temperature depending upon the site conditions, i.e., ambient
temperature, loading conditions, etc.
The capillary tube is protected adequately to withstand all normal handling. It should not, however, be bent sharply or
repeatedly and should be supported by clips to prevent sagging.
The thermometer pocket should be filled with transformer oil.
For OFAF & OFW cooling OTI & WTI are provided with four contacts, used for Alarm, Trip, Fan Starting & Pump
Starting.
The instrument indicates the temperature rise of the transformer winding over, the top oil temperature for any
specified load current.
The maximum Input current to the heater coil temperature not exceed 2.0 Amps. The maximum permissible secondary
current from the Current Transformer at rated load is 2.0 Amps.
25
OPERATING MECHANISM
The system is self contained and does not depend on any outside power source for its operation. It consists of a liquid
filled bellows capillary tube of required length and sensing element or bulb. This system is thermally balanced by a
compensating bellow and a second capillary which terminates at the head of the bulb. The two bellows are linked
together via a lever In such a manner that temperature changes on the capillary line and head are automatically
compensated for. Temperature changes on the bulb motivates the operating bellows only which is linked to the single
rotating switch platform and indicating pointer.
The power available from this type of system is adequate to operate up to four switches and a potentiometer without
any visible pointer detect. This robustness also ensures that the instrument does not suffer from normal shock conditions
such as may be experienced in handling and transport.
DIAL
A 4 1/2 long segment dial is provided with bold graduations. The standard range is 0-150°C with 5 per graduation.
MAXIMUM POINTER
A maximum indicating pointer red in color is fitted to the instrument window aid operated by a peg driven by the
indicating pointer. It can be reset with a standard screwdriver blade, after removing the knurled weatherproof knob.
As switch testing knob is fitted on the bottom of the lid to check the switch without removing the lid.
Instrument should be mounted only in vertical position: Inclined mounting will upset zero setting of the mercury
switches.
The transport lock should be removed after opening the cover before putting the instrument to use. The capillary line
can be supplied up to 15 meters in length. It is protected by flexible stainless steel armor. Ordinary care should be
taken while running the capillary and sharp bends should be avoided, particularly where it joins the instruments case
and the bulb. The capillary should he supported by suitable clips at 12to 18 Inches and necessary length left so that the
bulb may be freely installed and removed.
26
Transformer Manual
27
3.23 CURRENT TRANSFORMER
Current transformer for winding temperature indicator is provided on winding of the transformer at either the terminals
or on the bus bar of terminal gear. The secondary winding of the current transformers are connected to a terminal box.
Current transformer terminals from terminal box are wired to winding temperature indicator mounted in marshalling box.
The connections between terminals are made by links which can also be arranged to short circuit and earth the
current transformer when disconnected. For detail of CTs refer Rating and Diagram plate drawing.
Current transformers are used in transformer for measuring and also for protection purpose. CTs are provided as per
customer’s requirement and specification. All current transformer secondary terminals should be short circuited or
loaded before commissioning the transformer. This will prevent excessive voltage developing across CT terminals
which can damage the CT and be hazard if touched. CTs should not be dismantled & if required extra care should be
taken in handling it.
28
Transformer Manual
OIL SAMPLING
Oil takes up moisture readily and its condition should always be checked before use. Oil of a muddy color is certain to
be wet. Water and water-saturated oil are both heavier that dry oil and sink to the bottom of any container. Samples
shall, therefore, be taken from bottom.
While taking sample from Transformer Tank care should be taken that dirt from the draw-off valve or plug should be
removed. To ensure that the valve is clean, some quantity of oil should be allowed to flow into a separate container
before collecting sample for sampling. Sample should be collected either in glass bottle or in stainless steel bottle.
For taking sample from oil drum, the drum should first be allowed to stand with the bung vertically upwards for at least
29
24 hours. The area around the bung should be cleaned. A clean tube long enough to reach to within 10 mm of the
drum should be inserted, keeping the uppermost end of the tube sealed with the thumb whilst doing so. Remove the
thumb, thereby allowing oil to enter the bottom of the tube.
The sample should have following information
1. Date of sampling.
2. MVA & Voltage Class of Transformer.
3. WO & Sr. No. of Transformer
4. Whether the sample from Main Tanker or OLTC.
5. Sample Taken from Top or Bottom.
6. Before filtration or After filtration
7. Before charging or After Charging.
OIL FILLING
Before filling oil in the tank, it should be tested to meet the requirements as per IS:1866. In case oil does not meet the
requirement, it should be processed and shall only be used when meets the requirements.
For transformers dispatched gas filled, remove N2 gas from the tank by means of a vacuum pump and take full
vacuum and check & rectify if any leakage is there & keep the transformer under vacuum for 12:00 HRS. The filling
of oil inside the tank should be done under vacuum & fill the transformer main tank up to top cover. Do not open any
blank flange for erection without filling oil up to top cover. Transformer of high voltage rating (66KV and above) have
their tanks designed to withstand full vacuum. Below 66KV class transformer, full or partial vacuum should not be
applied without consulting manufacturer.
When filling a transformer with oil it is preferable that the oil be pumped into the bottom of the tank through filtration
machine.
It should also be ensured that the tap changer board, relief vent diaphragm, conservator, etc. are not subjected to full
vacuum as these may not designed for the same.
In case the transformer is provided with OLTC of in-tank type, while evacuating the main transformer tank, the
diverter switch compartment must also be evacuated simultaneously so that no undue pressure is allowed on the Tap
Changer Chamber. While releasing vacuum, the Tap Changer vacuum should also be released simultaneously. For
this, one equalizer pipe should be connected between main tank and tap changer.
30
Transformer Manual
3.28 EARTHING
Tank should be permanently and effectively earthed by means of connection to the earthing terminals provided for the
purpose at the bottom of the tank.
A good low-resistance earth is essential for adequate protection. The earthing connection should be of sufficient cross-
section to carry the LV line current for 30 seconds. Other accessories such as fan motors, oil pump motors, winding
neutrals etc. should also be earthed.
Earthing terminals are provided on tank for earthing of tank mentioned in General Arrangement Drawing. Ensure that
paint on the earthing terminal is removed before connecting the earthing strips.
Earth resistance should be measured and it should be within acceptable limit.
31
4 COMMISSIONING
After completion of proper erection, transformer is to be kept ready for commissioning. Before putting transformer in
service, following check points and Testing should be done to ensure the healthiness of the transformer.
Following details should be collected from name plate of transformer for reference before testing.
32
Transformer Manual
33
7. Check the oil for acidity and sludge as per IS: 1866.
8. If inspection covers are opened or any gasket joint is to be tightened, then tighten the bolts evenly to avoid
uneven pressure.
9. Check & clean the relay and alarm contacts. Check also their operation and accuracy and if required, change
the setting.
10. Check the protection circuit periodically.
11. Check the pointer of all gauges for their free movement.
12. Clean the oil conservator thoroughly before erecting.
13. Check the bucholz relay.
14. Inspect the painting and if necessary retouching should be done.
15. Check the OTI & WTI pockets and replenish the oil, if required.
16. Examine and replace the burnt or worn out contacts.
17. Check all bearings and operating mechanism and lubricate them as per schedule.
18. Open the equalizing valve between tank and OLTC, wherever provided at the time of filling the oil in the tank.
19. Connect gas cylinder with automatic regulator if transformer is to be stored for long in order to maintain positive
pressure.
20. Fill the oil in the transformer at the earliest opportunity at site and follow storage instructions.
21. Check the door seals of marshalling Box.
22. Equalize the diverter compartment of the OLTC by connecting equalizing pipe between flange joints provided on
the tap changer head.
23. Follow the oil filling instruction for topping up of oil for transformer with air cell type of oil, preservation system.
Make
Temp
34
Transformer Manual
For LV winding of more then 1.1 KV class, Apply 3 phase, 3 wire 415 volt from LV side & keep HV and neutral isolated.
Measure the excitation current in all 3 LV.
Note: Magnetising current on LV side is applicable for power transformer only. This shall be not applicable for furnace
duty, rectifier duty and distribution transformer.
35
4.7 MAGNETIC BALANCE
Purpose of this test is to check healthiness windings, core assembly condition and flux distribution in the transformer.
Single phase supply (preferable 230 volts AC) is applied to each winding and the induced voltages are measured
across other two phases. When the supply is fed to outer phase of a transformer, the voltage induced in the center
phase shall be 50 to 90% of the applied voltage. However, when the center phase is excited then the voltage induced
in the outer phases shall be 30 to 70% of the applied voltage.
Apply 230 volt AC on primary/Secondary winding and measure the voltage.
Note: Magnetic balance on LV side is applicable for power transformer only. This shall be not applicable for furnace
duty, rectifier duty transformer.
36
Transformer Manual
37
4.13 TEST ON CT
1. Ratio
2. Polarity
3. Magnetising current
4. IR value
NOTE: FOR OFW COOLING & UNIT COOLERS PUMP WILL BE ON WHEN TRANSFORMER IN OPERATION.
38
Transformer Manual
Sl. No. Relays on HV & LV Current setting Time setting Make / Type
1 Differential relay
2 Over current relay
3 Earth fault relay
4 Over fluxing relay
5 R.E.F relay
6 Over voltage relay
7 Under voltage relay
Make : Type :
Make : Type :
4.18 ENERGISING
When all checks and tests are found satisfactory, Air should be vented from all air release plug/screws provided on the
transformer, radiators, bushings, buchholz relay, oil surge relay. After completely venting the air out, the transformer
should be energised and maintained on no load for 24 hours. The initial Magnetising
current at the time of switching will be very high. This depends on the particular movement in the cycle. Humming
sound and chattering of arcing horn should also be monitored after charging of few minutes.
After 24 hours no load operation, the transformer should be de-energised and air venting should be carried out again
to release all the trapped air. After this venting operation, the transformer should be re-energised and maintained on
no load for 6 hours. After this period of 6 hours the transformer can be put on load gradually.
U Phase : Amp
V Phase : Amp
W Phase : Amp
O.T.I : ºC
W.T.I : ºC
Ambient : ºC
39
5 MAINTENANCE AND OPERATION
5.1 GENERAL MAINTENANCE
In order to avoid faults and disturbance, it is important that a careful and regular supervision and control of the
transformer and its components is planned and carried out. A regular system of inspection and preventive maintenance
will give long life and trouble free service. The causes of breakdown of transformer are generally classified as:
1. Overload 4. Poor workmanship
2. Incorrect installations 5. Accident
3. Faulty design 6. Surges on transformer
DIRT/DUST:
The external transformer surface shall be inspected regularly and when required cleaned from dust, inserts, leaves and
other airborne dirt. Dust collection on bushing, in control cubicle should be inspected.
POSSIBLE LEAKAGE:
After energizing of the transformer, a certain setting may appear in sealing joints. This should therefore be retightened
according to schedule.
SUCTION PIPE
As the Diverter Oil Vessel has only very small oil volume, no provision for circulation is made as standard.
However a Suction pipe may be provided optionally to remove oil from the bottom of the Oil Vessel.
In case where such a Suction Pope is provided it is absolutely imperative 1: that while filling the Diverter Oil Vessel, the
vent of the suction Pipe should be opened.
Schedule of Routine Inspection Operating Current Number of Tap changes Time between Routine Inspection.
Up to l5OA 100000
Over l50A 70000
Up to 400 A 50000
Up to 500 A 50000 or 3 years which ever is earlier
Upto400A 100000
Upto500A 100000
Upto 800 A 70000
U5to120OA 85000 above.
Figures given above are applicable to units at the star point. For three phase delta Tap changers and for Line End units
take Number of operations at 60% of
40
Transformer Manual
INSULATING OIL
The switch tank is fitted with drain valve and filtration may be carried out via this valve and the tank top cover.
The oil should be filtered after every 30,000 operation.
At intervals preferably during filtration the diverter switch unit should be washed down with clean’ oil and all traces of
carbon removed.
The electrical withstand strength of oil must not be less that 30 KV at any time. Oil from selector switch should be
tested every six months.
SERVICING SCHEDULE
1. De-energize, isolate and earth the transformer. Drain Oil from tap changer.
2. Inspect the selector switch through the top inspection cover.
3. Check condition of fixed and moving contacts. The tips of these will appear to be slightly roughened due to
arcing. This is normal. If however, the contacts are found to be worn out replace with new contacts.
4. Check Pat in the rest position the resistor the fixed contacts.
5. Check and ensure that all nuts, screws and other fasteners are secured properly and all connections are in good
condition.
6. Be careful not to alter the vernier setting and clarifiers of the coupling between the drive mechanism and the
selector switch but the tightness of the nuts should be checked.
7. Check visual and by continuity test that the transition resistors are in good condition.
8. Wash down the switch with dry hot transformer oil. Do not use cotton waste. A piece of cloth should be used to
clean bottom of tank. Ensure that no foreign particles should be left inside the switch.
9. Refill with clean dry hot oil. The oil must have an electrical withstand value of not less than 50KV.
10. Examine silica-gel breather, and reactivate or replace as necessary.
11. Clean drive mechanism chamber and tighten fasteners.
12. Ensure that all gaskets on drive mechanism door are in place and in good condition and the window glass is
intact. Replace as found necessary.
13. Lubricate all surfaces such as gear teeth, wiping surfaces etc. with special lubricant as required.
14. If any scratches are found on painted surfaces, touch up with paint.
15. Clean air filters.
16. Check electrical operation.
17. Check functioning of limit switches, crank handle interlock, motor protection relay and heaters.
18. Ensure damper is locked in minimum position.
19. Operate the switch by hand one cycle, and electrical through two cycles to check all functions. The switch should
show snappy action all the time.
41
20. Check operation of oil surge relay trip.
21. PLEASE DO NOT:
1. Work with naked lights.
2. Allow moisture to get into selector tank while servicing.
3; Allow other solid contamination of oil.
4. Alter disposition of connections to terminal board in any manner.
5. Stress terminal board stems while trying to tighten connection.
6. Leave any foreign matter in the selector switch tank.
42
Transformer Manual
2. Thermometer for measuring of Top-oil temperature: The thermometer consists of a cylindrical sensing body with
a flange, a capillary tube, and a thermometer housing with dial and contact device. The measuring system is
filled with liquid, which changes its volume at the temperature variations, and affects spring bellows. The movements
of the bellows are transferred to the pointer and signal contacts of mercury switches. The contact can be set
independently of each other.
3. Winding Temperature Indicator: The thermometer system consist of a sensitive body with assembling details, a
capillary tube and a thermometer housing, which consist a scale with an indicating pointer and a maximum
temperature pointer, heating and adjusting resistor, as well as contact-device for four micro switches.
4. Remote control of winding temperature: For remote control of winding temperature a resistance temperature
device has been used with a heating element built in to the same housing. The heating element is fed by the
second current of a current transformer.
For setting of the heating element there is a parallel connected adjustment resistor installed in the control cabinet.
5. Radiators: The external cooling surface shall be inspected regularly and when required cleaned from dust, insects,
leaves or other airborne dirt. This is especially important in case of fan cooling. The cleaning is suitable carried out
by means of water flushing at high pressure. Normally, no measures are necessary for keeping the internal
cooling surfaces clean as long as oil is in good condition. If, however, sludge formation has set in, the sludge may
deposit on horizontal surfaces in radiators. In such a case, the radiator should be flushed internally with clean oil.
If the sludge does not loosen, we can firstly flush with petrol etc. and then with oil.
6. Bushings: Bushings porcelains shall be cleaned from dust and dirt regularly. In areas where the air contains
impurities as salt, cement dust, smoke or chemical substances, shorter intervals are required.
7. Connection: In order to avoid prohibited temperature rises in the electrical connections of the transformers, all
screw joints should be checked and retightened according to schedule.
8. Accessories: Separate leaflet should be followed for various fittings for, fans, pumps, Flow indicators, pressure
gauge, Oil gauge, pressure reducing valve, OLTC, Off circuit tap changer, Coolers etc.
Suppose IR value of 70º C is 300 M ohms and we want to convert at 40º C, the factor K will give you difference in
temperature i.e. (70º C - 40º C) = 30º C.
K for 30º C temperature difference = 4.2
so the value at 40º C = 4.2 * 300 = 1260 M ohms.
Value thus converted fairly tally with actual value cooling of transformer.
Schedule:-
The oil should be maintained as per the guidelines of IS: 1866. Periodicity of test and permissible limits for important
parameters of oil - electrical strength, water contents, receptivity, tan-delta, neutralization value, sediment and perceptible
sludge, flash point and interfacial tension are given in Annexure. Health of transformer can be effectively monitored by
Dissolved Gas Analysis (DGA Test). This technique helps in detection of incipient fault in transformer.
43
5.7 TROUBLE SHOOTING
General measures for trouble shooting are described in this section.
1. Following information to be informed to T & R in case of trouble in transformer.
(1) Specification of transformers (Capacity, Sr. No.)
(2) Load current (A) and operating Voltage
(3) Operating tap position
(4) Condition at the time of trouble.
2. Transformer trouble and checks items, Troubles, their possible causes and item to be checked are given in Table.
3. Table for Detective devices and their functions.
4. Table for Check items and judging.
5. Detection method of oil or gas leaks.
SAMPLING
Metal cylinders as in figure are to be used collect
oil samples from transformers. Proper sampling
procedure is required to get representative
sample from transformers. Take sample from a
position where oil is in circulation. Sampling valve
if provided at middle is best to get a
representative sample. Stagnant oil from the
sampling valve of the transformer may be
removed before sampling. To achieve this,
remove 2 to 3 liters of oil to waste container before
connecting metal cylinder to sampling valve.
Attach bottom valve of container to the sampling
valve of the transformer through clear PVC
tubing. PVC tube connected to top valve may
run to a waste oil container. Sampling may be
done in following sequence.
1. Open Sampling valve of transformer (C)
2. Open bottom valve of metal cylinder (A)
3. Open top valve of metal cylinder (B)
44
Transformer Manual
Allow 200ml of oil to flow through cylinder to waste container. While filling the cylinder sides may be tapped with a
hard object to dislodge air bubbles trapped inside.
After Sampling valves may be shut in the reverse order.
1. Close top cylinder valve (B)
2. Close bottom cylinder valve (A)
3. Close transformer sampling valve (C)
After the filling shake the cylinder and feel for any signs of incomplete filling. If not completely filled, redo filling.
Close transformer valve. Remove PVC tubing. Apply sealing to the valves opening. Send sample to lab after proper
identification.
ANALYSING RESULTS
No immediate action is required if values of the gases are with in the values given table no.1 except for new
transformers and for transformers with earlier test data are available. For new transformers and transformers with
earlier data are available, rate of rise shall be limited to values given in table 2
Table -1
Maximum Values in ppm
Type of transformer H2 CO CO2 CH4 C2H6 C2H4 C2H2
Power transformer Without
communicating OLTC 150 900 15000 110 90 280 50
Power transformer With
communicating OLTC 150 850 12000 130 70 250 270
Furnace transformers 200 800 6000 150 150 200 *
Distribution transformers 100 200 5000 50 50 50 5
Table - 2
Maximum rise
Gas H2 CO CO2 CH4 C2H6 C2H4 C2H2
milli liters per day <5 <50 <200 <2 <2 <2 < 0.1
Equation to calculate rate of rise of gas
(y1-y2) q
rate =
(d2-d1)
Where
y1 is the value of reference analysis
y2 is the value of last analysis
d1 date of reference sample y1
d2 date of last sample y2
q Quantity of oil in the transformer
ANALYSING
If gas contents are more than table 1 or table 2 depending on the case, analyse as given below.
Divide quantity of H2, CH4, C2H6, C2H4 and C2H2 by maximum value of gas out of these gases. Mark position of
these gases in X axis and ratio of particular gas with highest quantity in y axis, plot a graph. Compare this pattern with
typical patterns given below:
45
46
Transformer Manual
TEMPERATURE OF FAULT
Temperature of fault may be calculated by using following formula
Temperature in ºC = 322log (C2H4/C2H6) +525
47
5.9 MAINTENANCE SCHEDULE:
The maintenance schedule given below is a good indication required to be given to the transformer under average
condition.
48
Transformer Manual
49
Transformer Manual
Survey No. 344 to 350, Sarkhej Bavla Highway, N.H. 8-A, Village: Changodar,
Ta. Sanand, Dist. Ahmedabad - 382210. Gijarat, INDIA
Phone: +91-2717-661661 Fax: +91-2717-661716 Email: [email protected]
www.transformerindia.com